PROJECT STATUS DECEMBER 2019
![Page 2: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/2.jpg)
![Page 3: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/3.jpg)
Villa 1 and 2-Internal flooring work in progress
Villa 36-Plastering in progress, Villa 37-
Finishing work in progress
![Page 4: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/4.jpg)
Villa 39-Finishing work in progress
Villa 38-Internal flooring work in progress
![Page 5: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/5.jpg)
Villa 40-External primer completed, Villa 41-External Plastering
completed
Villa 42-Painting work in progress
![Page 6: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/6.jpg)
Villa 43-First floor slab work completed
Villa 44-First floor column work in progress
![Page 7: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/7.jpg)
Villa 45-Finishing work in progress
Villa 46-Block work completed
![Page 8: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/8.jpg)
Villa 48-External plastering completed
Villa 50-Block work in progress
![Page 9: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/9.jpg)
Villa 51-External landscape work in progress
Villa 52-Flooring in progress,53-Finishing in progress,54-Flooring in
progress,55-Primer completed
![Page 10: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/10.jpg)
Villa 56-Funder max cladding work in progress,
Villa 57-Flooring work in progress
Villa 58-External Primer work completed, Villa 59-Flooring work in progress
![Page 11: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/11.jpg)
Villa 60-External primer completed, Villa 61-
External primer completed
Villa 77-First floor roof slab & Bock work in
progress
![Page 12: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/12.jpg)
Villa 78-Flooring in progress, Villa 79-Primer
work in progress
Villa 80-Plastering completed, Villa 82-
Plastering in progress
![Page 13: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/13.jpg)
Villa 82-Primer work completed
Villa 83-Block work in progress
![Page 14: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/14.jpg)
Villa 84-External plastering completed
Villa 86-Block work in progress
![Page 15: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/15.jpg)
Villa 87-External plastering completed
Villa 88-Finishing work in progress
![Page 16: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/16.jpg)
Villa 89-Flooring work in progress
Villa 90-Finishing work in progress
![Page 17: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/17.jpg)
Villa 91-Internal plastering work completed
Villa 92-External primer completed
![Page 18: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/18.jpg)
Villa 93-Internal flooring work in progress
Villa 94-Internal flooring work in progress
![Page 19: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/19.jpg)
Villa 95-Internal flooring work in progress
Villa 96-Block work in progress
![Page 20: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/20.jpg)
Villa 98-External plastering completed
Villa 99-Primer work completed, Villa 100-
Flooring work in progress
![Page 21: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/21.jpg)
Villa 101-Block work in progress
Villa 102-First floor roof slab completed
![Page 22: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/22.jpg)
Villa 103-First floor roof slab in progress
Villa 106-Internal flooring in progress
![Page 23: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/23.jpg)
Villa 107-Block work completed
Villa 108-External plastering completed
![Page 24: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/24.jpg)
Villa 109-Primer work completed, Villa 110-Flooring in progress
Villa 111-First floor column work in progress
![Page 25: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/25.jpg)
Villa 115-Block work completed
Villa 116-External plastering completed
![Page 26: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/26.jpg)
Villa 117-External plastering work
completed
Villa 118-Flooring work in progress
![Page 27: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/27.jpg)
Villa 119
Villa 120-Block work completed
![Page 28: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/28.jpg)
Villa 122-Block work in progress
Villa 124-External primer work completed,
Villa 125-Block work completed
![Page 29: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/29.jpg)
Villa 127-Bedroom sloped roof work in
progress
Villa 128-First floor slab work completed
![Page 30: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/30.jpg)
Villa 129-Block work completed
Villa 130-Block work in progress
![Page 31: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/31.jpg)
Villa 139-Primer work completed
Villa 140 and 141-Flooring work in progress
![Page 32: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/32.jpg)
Villa 142-First floor sloped roof slab in progress, Villa 143-SHR slab in progress
Villa 144-External plastering completed, Villa
145-Block work in progress
![Page 33: PROJECT STATUS DECEMBER 2019 - puravankara.com · External Plastering completed. Villa 42-Painting work in progress. Villa 43-First floor slab work completed. Villa 44-First floor](https://reader034.fdocuments.net/reader034/viewer/2022051809/60129314320ae55ec949a106/html5/thumbnails/33.jpg)