Jody
Tassno
Mengapa Proyek Gagal? Kurang jelasnya apa yang diinginkan
Problems avoided, covered up, or minimized
Inadequate planning (the devil is in the details)
Ineffective process to deal with changes or problems Lack of willingness or discipline to monitor progress
Unresolved conflicts
Lack of committed, dedicated resources
Lack of understanding of project management
2
-
8/10/2019 Project Scope - Project Management
3/23
-
8/10/2019 Project Scope - Project Management
4/23
Jody
Tassno
Proj Charter: daftar peserta
4
Isabelle de Zegher [email protected] +41 61 3242592
Charlie Mead [email protected]
Georges De Moor [email protected]
Eric Morincomme [email protected] +32 3 444 7512
Christel Daniel [email protected] +33 660 484133
Philippe Lambin [email protected] Zahlmann [email protected] +49 9131 84 7944
Ulrike Schwarz-Boeger [email protected] +49 89 4140 2409
Piere-Yves Lastic [email protected] +33 145 362591
Suzanne Markel-Fox [email protected] +1 610 787 3862
Sarah Payne [email protected] +44 7896 568458
Isabelle de Zegher [email protected] +41 79 8241110
Johan van der Lei [email protected] +31 10 408 7050Marc Peeters [email protected] +41 79 788 65 92
Rob Thwaites [email protected] +44 208 966 4816
Michael Thick [email protected]
-
8/10/2019 Project Scope - Project Management
5/23
Jody
Tassno
Statement Of Work (SOW)
Uraian resmi tertulis berisi
permintaan minimum yang
harus dilakukan kontraktor.
5
-
8/10/2019 Project Scope - Project Management
6/23
Jody
Tassno
Isian SOW1. Establish a preliminary scope statement ( i.e., the purpose or
objective of your procurement)
2. List the tasks to be performed ( i.e., All performancerequirements you intend the contractor to satisfy, allrequirements that the contractor must comply with during
contract performance )3. Group similar and related tasks.
4. Organize the tasks in logical sequence
5. Identify the input ( Required resources to perform the tasks)
6. Identify the output ( Required results or deliverables )
7. Identify the timeline or frequency of the deliverables (output)8. Develop the parameters for acceptable quality and performance
9. Determine how you will monitor the deliverables
6
-
8/10/2019 Project Scope - Project Management
7/23
Jody
Tassno
Project Scope Management
Scopeadalah seluruh pekerjaanyang diperlukan untuk
mendapatkan hasil proyek serta proses yang digunakannya
Deliverableadalah produk/jasa/sistem yang dihasilkan dalam
bagian proyek, seperti hardware atau software, dokumen
perencanaan, risalah rapat
Project scope management termasuk proses2 dalam
menentukan dan mengendalikan apa yang termasuk dan tidak-
termasuk dalam proyek.
7
-
8/10/2019 Project Scope - Project Management
8/23
Jody
Tassno
Proses Pengelolaan Scope Proyek Scope planning:menetapkan bagaimana scope akan ditentukan,
diperiksa, dan dikendalikan
Scope definition: meninjau pernyataan proyek dan pernyataan scope
awal dan menambahkan informasi yang dibutuhkan agar dapat
disepakati
Membuat WBS: memilah-milah proyek menjadi bagian yang lebih kecil
dalam bentuk yang manageable
Scope verification: penerimaan formal terhadap scope proyek
Scope control: mengendalikan perubahan dalam scope proyek.
8
-
8/10/2019 Project Scope - Project Management
9/23
Jody
TassnoScope Planning and the
Scope Management Plan
Scope management plan adalah suatu dokumen yang
didalamnya termasuk bagaimana team menyiapkan
project scope statement, membuat WBS, memeriksahasil proyek, dan mengendalikan perubahan dalam
scope
Asupannya mencakupproject charter,preliminary scope
statement, danproject management plan.
9
-
8/10/2019 Project Scope - Project Management
10/23
Jody
Tassno
Project Scope Statement
Scope statement awal, project charter,
organizational process, dan approved change
requestssebagai bahan utama membuat
project scope statement
Dengan berjalannya waktu scope proyek akan
semakin jelas dan spesifik.
10
-
8/10/2019 Project Scope - Project Management
11/23
Jody
Tassno
Work Breakdown Structure
WBS adalah pengelompokan pekerjaan berdasarkan
produk(deliverable) yang mendefinisikan scope proyek.
WBS merupakan dokumen dasar yang merupakan landasan bagi
perencanaan jadwal, biaya, sumberdaya dan perubahan.
Penguraian(decomposition) adalah memilah hasil proyek menjadi
bagian lebih kecil.
Paket kerja adalah tugas terbawah dalam tingkatan WBS.
11
-
8/10/2019 Project Scope - Project Management
12/23
Jody
Tassno
Penguraian WBS
12
Mission
Project Goal
Statement
Objective
Major Step
Activity
Task Task Task Task Task Task Task TaskTask Task
Objective
Major Step
Objective
Major Step
Activity Activity Activity Activity
Level 1
Level 2
Level 3
-
8/10/2019 Project Scope - Project Management
13/23
Jody
Tassno
WBS Proyek Intranet
13
-
8/10/2019 Project Scope - Project Management
14/23
Jody
Tassno
WBS Intranet Tabular
14
1.0 Concept
1.1 Evaluate current systems
1.2 Define Requirements
1.2.1 Define user requirements
1.2.2 Define content requirements
1.2.3 Define system requirements
1.2.4 Define server owner requirements
1.3 Define specific functionality
1.4 Define risks and risk management approach
1.5 Develop project plan
1.6 Brief Web development team2.0 Web Site Design
3.0 Web Site Development
4.0 Roll Out
5.0 Support
-
8/10/2019 Project Scope - Project Management
15/23
Jody
Tassno
Membuat WBS Dengan petunjuk: ada organisasi yang memiliki, seperti DOD
Cara analogi: dari proyek yang sejenis, sesuaikan dengan proyek
kita
Cara top-down: mulai dengan bagian yang terbesar dan uraikan ke
bawah
Cara bottom-up : mulai dengan kegiatan khusus, naikan ke atas
(role-up)
Caramind mapping suatu teknik seperti pencabangan dari suatu
gagasan inti.
15
-
8/10/2019 Project Scope - Project Management
16/23
Jody
Tassno
Kamus WBS dan Dasar Cakupan
Beberapa kegiatan WBS agak kurang jelas sehingga perlu
diterangkan sehingga dapat diperkirakan waktu dan biaya
untuk mengerjakannya
KamusWBS adalah dokumen yang menjelaskan secara rinci
tentang setiap bagian WBS
Pernyataanproject scopedengan WBS dan kamus WBS-nya
membentuk scope baseline, yang digunakan untuk
mengukur kinerja pencapaian proyek.
16
-
8/10/2019 Project Scope - Project Management
17/23
Jody
Tassno
Paket Kerja Bagian terbawah WBS yang disepakati sebagai alat pengelolaan,
dengan maksud
Pendelegasian tanggungjawab dan wewenang
Pertanggungjawaban pekerjaan
Merupakan building blockbagi Project Baseline Plan
Memberikan dasar umum untuk
Memprakirakan Scope, Waktu, Sumberdaya, dan Resiko
Memperbandingkan antara rencana dengan aktual.
17
-
8/10/2019 Project Scope - Project Management
18/23
Jody
Tassno
Tabel Penanggungjawab
18
Project Name Date
Task Smith Johnson Tully Hughs Person n Hours
1.1 6 R 1 1 2 2 12
1.2 3 3 R 2 3 3 14
1.3 1 2 3 6 6 R 181.4 2 1 2 R 2 4 11
1.5 4 1 1 3 R 5 14
1.6 3 2 2 R 2 2 11
1.7 2 1 2 5 R 3 13
m-th task
Total hours 21 11 13 23 25 93
R - Resposible engineer, in-charge
-
8/10/2019 Project Scope - Project Management
19/23
Jody
Tassno
Memadukan WBS
19
-
8/10/2019 Project Scope - Project Management
20/23
Jody
Tassno
Scope Verification
Tidak mudah membuat scope statementdan WBS untuk
proyek
Demikian juga untuk memeriksa dan mengujinya, terutamaagar tidak banyak perubahan
Scope verification harus dapat diterima oleh pemangku-
kepentingan
Penerimaan biasanya dengan pemeriksaan oleh
pelanggan.
20
-
8/10/2019 Project Scope - Project Management
21/23
Jody
Tassno
Scope Control
Scope controlmencakup pengendalian perubahan2nya
Sasaran scope control untuk:
Mengetahui penyebab2 perubahan
Menjamin bahwa perubahan bagian pengendalian perubahan yang
terpadu
Mengelola perubahan pada saat terjadinya
Varianceadalah perbedaan antara kinerja yang direncanakan
dengan realisasinya.
21
-
8/10/2019 Project Scope - Project Management
22/23
Jody
TassnoMengurangi Permasalahan
dalam Scope
1. Realistik
2. Libatkan pengguna
3. Gunakan perangkat dan piranti
4. Ikuti proses manajemen proyek.
22
-