Project risk management - PMI Central Italy Chapter P. Iva ... · PDF...

18
1 Page 1 Copyright © 2004-8 David Hillson/Risk Doctor Limited © 2004-8 David Hillson/Risk Doctor Limited, Slide 1 Project risk management: Best practice & future developments Presented by Dr David Hillson FAPM FIRM PMP Director Risk Doctor & Partners [email protected] www.risk-doctor.com © 2004-8 David Hillson/Risk Doctor Limited, Slide 2 What is “best practice”? Routine activities that lead to excellence Not “what everyone does”… … but “what everyone should do Accepted by leading professionals Implemented by leading practitioners Widely accessible Scaleable, easily tailored or modified

Transcript of Project risk management - PMI Central Italy Chapter P. Iva ... · PDF...

1

Page 1Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 1

Project risk management:Best practice &

future developments

Presented byDr David Hillson FAPM FIRM PMP

Director Risk Doctor & [email protected] www.risk-doctor.com

© 2004-8 David Hillson/Risk Doctor Limited, Slide 2

What is “ best practice ”?

� “ Routine activities that lead to excellence ”

� Not “ what everyone does ”…… but “ what everyone should do ”

� Accepted by leading professionals

� Implemented by leading practitioners

� Widely accessible

� Scaleable, easily tailored or modified

2

Page 2Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 3

Uncertainty is everywhere …

… but

© 2004-8 David Hillson/Risk Doctor Limited, Slide 4

�Risk = Uncertainty

True or False ?

Risk = Uncertainty that matters(i.e. can affect objectives )

Risk and uncertainty

3

Page 3Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 5

Two dimensions of risk

Risk has two dimensions :1. uncertainty2. effect on objectives

“impact”

“probability”

Risk connects uncertainty with objectives

© 2004-8 David Hillson/Risk Doctor Limited, Slide 6

Traps and cheese

� What kind of impact “ matters ”?

� Could be either positive or negative

� Uncertainty that helps as well as uncertainty that harms

� Both need managing proactively

4

Page 4Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 7

“An uncertain event or condition that, if it occurs, has a e ffect on

a project objective ”(PMI® PMBoK Ch 11)

Risk includes both opportunities & threats

positive or negative

What is a risk?

Risk connects uncertainty with objectives

© 2004-8 David Hillson/Risk Doctor Limited, Slide 8

Best-practice concepts

1. Risk is “ uncertainty that matters ”

2. Risk is defined against objectives

3. Risk includes both opportunity & threat

5

Page 5Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 9

Implementation & review

Initiation/Establish context

Riskidentification

Qualitative riskassessment

Quantitative riskanalysis

Risk response development

Generic risk management process

© 2004-8 David Hillson/Risk Doctor Limited, Slide 10

Risk process initiation

“ Set the scope, objectives and context for the risk management process ” (PRAM Guide)

“ The process of deciding how to approach & plan risk management activities for a project ” (PMBoK)

�Ensure level, type & visibility of process match:� riskiness of project� importance of project to organisation

�Output : Risk Management Plan

6

Page 6Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 11

Risk process initiation best practice

1. Essential to define scope & objectives first

2. Risk process is scaleable

© 2004-8 David Hillson/Risk Doctor Limited, Slide 12

?____

?____

?____

TRIALS & ACCEPTANCE

SUBCONTRACT SOFTWARE

DEVELOPMENT

IN HOUSE SOFTWARE

DEVELOPMENT

PREPARE DETAILED

DESIGN SPECIFICATION

Risk identification

� Aim to expose “all” knowable risks

� Common risk id techniques :� brainstorming/workshops

� prompt lists/check lists

� assumptions analysis

� interviews/questionnaires

� other techniques� document review

� Delphi groups

� diagramming techniques

7

Page 7Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 13

Separate risks from non-risks

� A risk is not an issue� Risk = uncertain future event that matters� Issue = certain present event that matters

� A risk is not a cause or an effect� Cause = current fact or condition,

may give rise to risk� Effect = dependent result of a risk

if it happens

CAUSE

EFFECT

RISK

Need clear unambiguous risk descriptions

© 2004-8 David Hillson/Risk Doctor Limited, Slide 14

Risk metalanguage

� A structured description of a risk which separates cause , risk and effect

“As a result of <1. existing condition >,<2. uncertain event > may occur,which would lead to <3. effect on objectives >”

� Key words :1. is, do, has, has not … [present condition]2. may, might, possibly … [uncertain future]3. would, could … [conditional future]

8

Page 8Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 15

Risk identification best practice

1. Use multiple identification techniques

2. Separate risks from non-risks

3. Use risk metalanguage for clear descriptions

© 2004-8 David Hillson/Risk Doctor Limited, Slide 16

Risk assessment/analysis

� Qualitative assessment

� What is the risk?

� Why might it occur?

� How likely is it? ( Probability )

� How bad/good might it be? ( Impacts )

� Does it matter?

� What can we do?

� When should we act?

� Who is responsible?

� Record/analyse in Risk Register

� Quantitative analysis

� modelling uncertainty

� simulate combined effect of risks

� predicting outcomes

� range, min/max, expected

� testing scenarios

� setting confidence limits

� identifying criticalities

� determining options

� Model in software

9

Page 9Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 17

Qualitative techniques

2. Risk categorisation (RBS)� common sources� “hot-spots” of exposure

IMPACT

VHI

HI

MED

LO

VLO

VLO LO MED HI VHI

PR

OB

AB

ILIT

Y

ReliabilitySafetyPerformance

TechnicalRisk

ProjectRisk

ManagementRisk

CommercialRisk

Contractual OrganisationalResources Information Communication

1. Probability/Impact Matrix� define terms HI/MED/LO� prioritise risks R/Y/G

© 2004-8 David Hillson/Risk Doctor Limited, Slide 18

VHI

HI

MED

LO

VLO

POSITIVE IMPACT(Opportunities)

VHI HI MED LO VLO

PR

OB

AB

ILITY

NEGATIVE IMPACT(Threats)

VHI

HI

MED

LO

VLO

VLO LO MED HI VHI

PR

OB

AB

ILIT

Y

The “mirror” double P-I Matrix

THEATTENTION

ARROW

Use two matrixes : rotate opportunity half

10

Page 10Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 19

Qualitative risk assessmentbest practice

1. Define terms for probability & impacts

2. Use double P-I Matrix for threats and opportunities

3. Group risks using RBS

© 2004-8 David Hillson/Risk Doctor Limited, Slide 20

Quantitative techniques

� Sensitivity analysis

� Decision trees

�Statistical simulation (Monte Carlo)

DECISION: Accept 6month Purchase Agreement?

EXPECTED COST (M£): 11.256

EVENT: Price increase £1050/tonProbability: 0.500Cost (M£): 12.600EXPECTED COST (M£): 12.600

EVENT: No change in priceProbability: 0.250Cost (M£): 12.000

EXPECTED COST (M£): 12.000

EVENT: Price falls to £850/tonProbability: 0.250Cost (M£): 10.200EXPECTED COST (M£): 10.200

ALTERNATIVE : Accept £938/tonCost (M£): 11.256EXPECTED COST (M£): 11.256

ALTERNATIVE : Decline the offerCost (M£): 0EXPECTED COST (M£): 11.850

0

10

20

30

40

50

60

0

10

20

30

40

50

60

70

80

90

100

Cum

ulat

ive

prob

abili

ty c

urve

(%

)

Ear

ly F

inis

h F

requ

ency

his

togr

am

Based on 1000 trialsMean = 29 JuneStandard deviation = 25 daysEach bar represents 3 days

6 Sept26 July14 June3 May

An Oil Field DevelopmentEarly Finish Histogram for Activity G44 (1st Oil)

11

Page 11Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 21

Quantitative risk analysisbest practice

1. Only use when appropriate (large, complex or important projects)

2. Use with care (GIGO)

© 2004-8 David Hillson/Risk Doctor Limited, Slide 22

Risk response development

� Using risk information to make decisions

� Based on :� type & nature of risk� manageability� impact severity� resource availability� cost-effectiveness

� Identify :� best owner for response� appropriate response� effective management action

12

Page 12Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 23

Avoid

Reduce

Transfer

Accept

THREAT GENERIC STRATEGY OPPORTUNITYELIMINATE UNCERTAINTY

CHANGE SIZE

INVOLVE OTHERS

TAKE THE RISK

Exploit

Enhance

Share

Accept

Strategy before Tactics ���� Focus

Risk response strategies

© 2004-8 David Hillson/Risk Doctor Limited, Slide 24

Response developmentbest practice

1. Adopt strategic approach to create focus

2. Give equal attention to both opportunities and threats

13

Page 13Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 25

Implementation & Review

� Many risk processes have nothing between Response Development and Review

� Where do we implement agreed actions?� Pass into routine project activity� Monitored via regular project process

Danger point !!!

© 2004-8 David Hillson/Risk Doctor Limited, Slide 26

Implementation & Review

� Turn responses into actions

� Ensure ownership� Risk Owner & Action Owners

� Take proactive action

� Evaluate resulting position� Risk reviews

14

Page 14Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 27

Implementation & Reviewbest practice

1. Do it ! (remember the frogs)

2. Check for change3. Do it again

© 2004-8 David Hillson/Risk Doctor Limited, Slide 28

Best practice summary

� What everyone should do, not what everyone does!

� Where are you?

� Where do you want to be? IT WAS AT THAT MOMENT THAT

LENNY KNEW HE WAS DIFFERENTFROM THE OTHER LEMMINGS

15

Page 15Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 29

The way ahead?

© 2004-8 David Hillson/Risk Doctor Limited, Slide 30

Vision for the future

� Risk management is not static

� still developing and moving forward

� Three areas for development

� integration

� increased depth & breadth

� behavioural aspects

16

Page 16Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 31

Integration

� Integral to management of projects� culture� process� tools

� Integral to corporate culture� Enterprise risk management

� across the business, top to bottom

� Total Risk Management (TRM) :� a way of thinking� attitudes lead to actions

© 2004-8 David Hillson/Risk Doctor Limited, Slide 32

Increased depth & breadth

� Depth of risk analysis� better tools & techniques

� user-friendly� functionality� integration

� use of AI, IKBS, expert systems� knowledge management� learning from experience

� draw on other disciplines� value management� system dynamics� safety and hazard analysis� scenario planning

17

Page 17Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 33

Increased depth & breadth

� Breadth of application� not just threats to project time & cost

� risk as opportunity� other objectives : performance, quality …� soft objectives : environment, HF, reputation …

� programme/portfolio risk assessment� inter-project issues

� business risk assessment� business drivers, investment appraisal� corporate governance, holistic risk

© 2004-8 David Hillson/Risk Doctor Limited, Slide 34

Behavioural aspects

� Risk is not managed by robots� Human psychology is major influence� Risk attitudes affect risk process

� Awareness ���� understanding ���� change

� Aim for “risk maturity”� Appropriate choice of attitude & approach to

meet specific needs of situation

18

Page 18Copyright © 2004-8 David Hillson/Risk Doctor Limited

© 2004-8 David Hillson/Risk Doctor Limited, Slide 35

Where are we going?

� Project risk management has a future� not just a passing fad

� Develop or die� pioneers or settlers

� Do it - because it works!

j d i !!j d i !!j d i !!j d i !!

© 2004-8 David Hillson/Risk Doctor Limited, Slide 36

More information from David Hillson

[email protected] www.risk-doctor.com