Phase Column Descriptions:• Scoping/Estimating - Project manager has been assigned and development of a cost estimate for the project is underway.• Awaiting Funding - Cost estimate has been provided to the customer. Funding has not been received.• Procurement - Funding is in place. Contracting process is underway.• Design - Contract for design services has been awarded. Design is in progress.• Construction - Contract for construction services has been awarded. Construction is underway.• On Hold• Complete - Work has been completed and accepted by the customer.• Closeout - Financial closeout is underway.
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5573 882000 180180 - 923590
4762 COLLEGE ACRES DRIVE (COLLEGE ACRES HOUSE) - REPAIR CONCRETE DRIVEWAY
5/31/17 $3K SPR RECEIVED 4/19/17. FUNDING ESTABLISHED 4/19/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BOYD, E. 5573 FAC ADMIN CLOSEOUT
5555 882000 319290 - 945860
625 MACMILLAN AVENUE - 84 LUMBER SITE PRE-DESIGN
6/15/17 $2.6K SPR RECEIVED 3/27/17. FUNDING RECEIVED 3/27/17. RENDERINGS ARE COMPLETE, MAKING SOME REVISIONS BASED ON COMMENTS FROM CHANCELLOR.
JAMISON, G. 5555 FAC ADMIN CLOSEOUT
5574 882000 218024 - 945968
625 MACMILLAN AVENUE - INSTALL UTILITY SERVICES AT 84 LUMBER SITE
12/31/17 $290K SPR RECEIEVD 4/24/17. FUNDING SET-UP 4/24/17. INITIAL FUNDING SETUP FOR $10,000 FOR FY17. REMAINING BALANCE OF $290,000 RECEIVED.
JAMISON, G. 5574 ACSVCS CONSTRUCTION
5397 882000 281815 - 945860
720 ST. JAMES - CLINICAL RENOVATION OF BUILDING - DESIGN ONLY
6/15/17 $35K SPR RECEIVED 9/7/16. FUNDING ESTABLISHED 1/27/17. DESIGN AWARDED AND IN PROGRESS. FINALIZING FLOOR PLAN AND IT NEEDS. FLOOR PLAN FINALIZED. DESIGNER IS MOVING FORWARD WITH FULL DESIGN. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5397 FAC ADMIN CLOSEOUT
Project Report
2
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5693 882000 180187, 180540, 218026 - 945850
720 ST. JAMES - PSYCHOLOGY CLINIC RENOVATION - CONSTRUCTION PHASE
5/31/18 $454.8K SPR RECEIVED 9/20/17. FUNDING REQUESTED 9/20/17. FUNDING RECEIVED 10/2/17 FROM TWO DIFFERENT FUNDS. STEEL ERECTED MID-FEBRUARY 2018. FUNDING INCREASED 2/14/18 FROM 180187. GLASS ENTRY BEING INSTALLED WEEK OF APRIL 9.
SOUTHERLAND, E.
5693 PROJ MGMT CONSTRUCTION
5695 882000 125615 - 945866
803 S. COLLEGE ROAD - FASCIA/SIGN UPDATES
4/30/18 $15.8K SPR RECEIVED 9/20/17. FUNDING REQUESTED 2/27/18. FUNDING RECEIVED 3/7/18.
SINGLEY, D. 5695 PROJ MGMT PROCUREMENT
5694 882000 125981 - 945850
803 S. COLLEGE ROAD - INSTALL NEW EMERGENCY EXIT DOOR AND NEW FRONT DOOR
1/15/18 $25K SPR RECEIVED 9/20/17. FUNDING REQUESTED 10/20/17. FUNDING RECEIVED 11/1/17. FUNDING UPGRADE RECEIVED 2/28/18.
SINGLEY, D. 5694 PROJ MGMT CONSTRUCTION
5800 882000 152030 - 945866
803 S. COLLEGE ROAD - INSTALL SECURITY CAMERA
6/15/18 $3K SPR RECEIVED 2/21/18. FUNDING REQUESTED 2/28/18. FUNDING RECEIVED 3/21/18.
SINGLEY, D. 5800 PROJ MGMT PROCUREMENT
5356 882000 575680 - 945850
803 S. COLLEGE ROAD - RENOVATIONS FOR COLLABORATIVE WORK SPACE IN SUITE B
4/30/16 $285K SPR RECEIVED 7/28/16. FUNDING REQUESTED 8/1/16. FUNDING RECEIVED 8/12/16. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5356 FAC ADMIN CLOSEOUT
5581 882000 218023 - 945810
ADMINISTRATIVE ANNEX - CONSTRUCTION OF NEW BUILDING
8/15/18 $5.3M PROJECT SET UP IN AIM 5/9/17. SPR RECEIVED 5/24/17. RUNNING AS A QUASI-ENDOWMENT NON-CODE/ITEM SPECIAL PROJECT. NEW FUND HAS BEEN ENTERED,. SCO SUBMISSION PLANNED FOR MID-JANUARY.
JAMISON, G. 5581 ACSVCS DESIGN
CI12-13 443816 443816 - 923510
ALDERMAN HALL - COLUMNS REPAIR (2007 R&R)
8/31/17 $1.8K $1.8K ADDITIONAL R&R PROJECT SET UP TO HANDLE SPECIAL REPAIR NEED 8/3/17. FUNDING SET UP IN AIM 8/3/17. WORK IS COMPLETE.
MCCARLEY, T. 5637 PROJ MGMT COMPLETE
Project Report
3
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5577 882000 180187 - 945864
ALDERMAN HALL - INSTALL ADDITIONAL FA HORNS AND STROBE LIGHTS
5/31/17 $25K SPR RECEIVED 4/26/17. FUNDING REQUESTED 4/26/17. FUNDING RECEIVED 4/28/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5577 FAC ADMIN CLOSEOUT
5468 882000 180180 - 945863
ALDERMAN HALL - INSTALL AIR HANDLING UNITS
6/15/17 $275K SPR RECEIVED 1/26/17. FUNDING ESTABLISHED 1/27/17. BIDS ARE DUE 3/16/17. AWARDED TO SOUTHERN PIPING. EQUIPMENT HAS BEEN ORDERED. INSTALLATION TO START ON 5/8/17. WILL COMPLETE THE THIRD UNIT DURING THE FIRST WEEK OF JUNE. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
WILLIAMS, R. 5468 FAC ADMIN CLOSEOUT
5596 882000 180187 - 923590
ALDERMAN HALL - INSTALL GOLF CART PAD BEHIND BUILDING
6/15/17 $15K SPR RECEIVED 6/6/17. FUNDING REQUESTED 6/7/17. FUNDING RECEIVED 6/7/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5596 FAC ADMIN CLOSEOUT
5488 882000 177700 - 945866
ALDERMAN HALL - INSTALL LED LIGHTS AND HANG TV IN ROOM 104B
5/31/17 $12K SPR RECEIVED 2/6/17. FUNDING REQUESTED 2/14/17. FUNDING RECEIVED 2/20/17. FUNDING UPGRADE RECEIVED 3/27/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5488 FAC ADMIN CLOSEOUT
5578 882000 180540 - 945863
ALDERMAN HALL - INSTALL NEW HVAC IN ROOMS 201-207
5/31/18 $275K SPR RECEIVED 4/26/17. FUNDING REQUESTED 10/17/17. FUNDING RECEIVED 10/18/17. LOW BID AWARDED TO HARRELSON MECHANICAL. INSTALLATION GOING WELL, APPROX. 80% COMPLETE; STARTUP OF NEW SYSTEM AND DEMO OF OLD.
WILLIAMS, R. 5578 PROJ MGMT CONSTRUCTION
5475 882000 180187 - 923510
ALDERMAN HALL - REFURBISH STAIRWELLS
6/15/17 $150K SPR RECEIVED 1/26/17. FUNDING ESTABLISHED 1/27/17. IN PROGRESS. TESTING FOR MOLD. PRE-BID WAS 4/4/17. WORK BEGINS 5/8/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5475 FAC ADMIN CLOSEOUT
5489 882000 177700 - 945866
ALDERMAN HALL - REMOVE DOOR IN ROOM 204
5/31/17 $1.5K SPR RECEIVED 2/6/17. FUNDING REQUESTED 2/14/17. FUNDING RECEIVED 2/20/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5489 FAC ADMIN CLOSEOUT
Project Report
4
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5491 466280 466280 - 945810
ALLIED HEALTH BUILDING 6/30/20 $65.4M $66M CAPITAL PROJECT ESTABLISHED 2/7/17. AP, SD COMPLETE. BLDG DD SUBMITTED TO SCO. EARLY SITE PKG APPROVED TO BID. DESIGNER - EYP; CMR - WM JORDAN; CX- RMF.
SEIFERT, L. 5491 ACSVCS DESIGN
ALMKUIST-NIXON - REPAIR WHIRLPOOL IN ROOM 108
T.B.D. T.B.D. SPR RECEIVED 2/21/18. MET WITH SPONSOR AND VENDOR ON 3/22/18.
SOUTHERLAND, E.
5797 PROJ MGMT SCOPE & ESTIMATING
5362 882000 319080 - 923510
ALMKUIST-NIXON - REPLACE FLOORING IN ROOM 105
9/29/17 $18K SPR RECEIVED 8/10/16. FUNDING REQUESTED 10/18/16. FUNDING RECEIVED 11/8/16. WORK SCHEDULED FOR WEEK OF 5/15/17. FUNDING UPGRADE RECEIVED 07/17/2017. MATERIAL ARRIVED DAMAGED. WORK WILL BE RESCHEDULED FOR SEPTEMBER. FUNDING UPGRADE RECEIVED 9/18/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5362 FAC ADMIN CLOSEOUT
AQUACULTURE RESEARCH LAB - SURVEY UTILITIES IN PARKING AREA
T.B.D. $2.4K SPR RECEIVED 3/24/15. MEETING WITH SPONSOR4/13/15. FUNDING REQUESTED 4/29/15
MCCARLEY, T. 5017 SPONSOR AWAITING FUNDING
5477 422000 422000 - 945810
BASEBALL HITTING FACILITY CONSTRUCTION
6/30/18 $2.1M $2.4M PROJECT SET UP ON 1/30/17. INITIAL $900K FUNDING SET UP. AWAITING FURTHER FUNDING. RECEIVED COMMENTS ON CD'S FROM SCO. GROUNDBREAKING IN MAY. RESPONDING TO SCO REVIEW DATED 3/30/17.
COLEMAN, I. 5477 ACSVCS CONSTRUCTION
Project Report
5
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
4959 882000 319098 - 945966
BASEBALL INDOOR PRACTICE FACILITY - DESIGN ONLY
6/15/16 $150K SPR RECEIVED 12/15/14. DESIGNER INTERVIEWS CONDUCTED 1/15/15. DESIGNER HAS BEEN SELECTED. DESIGN IS UNDERWAY. AWAITING DESIGNER PROPOSAL. FUNDING REQUESTED 12/8/15. FUNDING RECEIVED 12/16/15. IN CD PHASE. MEETING WITH COACHES TO FINALIZE DESIGN SCHEDULED FOR FEBRUARY 21, 2017. CD'S TO BE SUBMITTED TO SCO ON 3/10/17. HAVE REQUESTED FEE PROPOSAL FOR BID/CA. RESPONDING TO SCO REVIEW DATED 3/30/17. GC CONTRACT TO SCO FOR APPROVAL.
COLEMAN, I. 4959 ACSVCS DESIGN
5742 882000 121981 - 945861
BEAR HALL - INSTALL DRYWALL IN FIRST FLOOR CORRIDORS
6/15/18 $118.8K SPR RECEIVED 11/2/17. FUNDING REQUESTED 12/11/17. FUNDING RECEIVED 12/15/17.
BLUME, J. 5742 PROJ MGMT CONSTRUCTION
5469 882000 180180 - 945863
BEAR HALL - INSTALL HVAC SYSTEM
6/15/17 $260K SPR RECEIVED 1/26/17. FUNDING ESTABLISHED 1/27/17. $22K FOR CW LINES DESIGN; PROPOSALS IN HAND FROM BRADY. EQUIPMENT ORDERED. FUNDING UPGRADE 4/6/17. INSTALLATION TO START 5/8/17. COMPLETING THE THIRD UNIT THE FIRST WEEK OF JUNE. CLOSEOUT IS UNDERWAY.
WILLIAMS, R. 5469 FAC ADMIN CLOSEOUT
5763 882000 121981 - 945850
BEAR HALL - INSTALL STAIRWELL AND ADDITIONAL ELECTRICAL IN ROOM 106
6/15/18 $8.2K SPR RECEIVED 12/18/17. DESIGN FUNDING REQUESTED 1/24/18. DESIGN FUNDING RECEIVED 1/30/18.
BLUME, J. 5763 PROJ MGMT DESIGN
BEAR HALL - PAINT EXTERIOR WINDOWS
T.B.D. $12K SPR RECEIVED 4/11/18. FUNDING REQUESTED 4/17/18.
GUINN, T. 5852 SPONSOR AWAITING FUNDING
Project Report
6
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5419 882000 121981 - 945850
BEAR HALL - RENOVATE COMPUTER LAB 202
6/15/17 $29.4K SPR RECEIVED 10/19/16. FUNDING REQUESTED 11/10/16. FUNDING RECEIVED 3/3/17. EXPECT TO COMPLETE. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5419 FAC ADMIN CLOSEOUT
5639 882000 121981 - 945850
BEAR HALL - RENOVATE OFFICE AREAS IN SUITE 146
10/31/17 $22K SPR RECEIVED 8/7/17. FUNDING REQUESTED 9/6/17. FUNDING ESTABLISHED 9/7/17. WORK IS COMPLETE, CLOSEOUT IS UNDERWAY.
MULLINS, K. 5639 FAC ADMIN CLOSEOUT
5700 882000 121981 - 945850
BEAR HALL - RENOVATE ROOM 164
3/30/18 $47K SPR RECEIVED 9/25/17. FUNDING REQUESTED 10/12/17. FUNDING RECEIVED 10/16/17. FUNDING UPGRADE RECEIVED 2/8/18.
BLUME, J. 5700 PROJ MGMT COMPLETE
5741 882000 121981 - 945850
BEAR HALL - RENOVATE ROOM 165
6/15/18 $35K SPR RECEIVED 11/2/17. FUNDING REQUESTED 2/9/18. FUNDING RECEIVED 2/9/18.
BLUME, J. 5741 PROJ MGMT PROCUREMENT
5498 882000 152470 - 945850
BEAR HALL - RENOVATE ROOM 170 INTO DEAN'S SUITE
6/15/17 $60K SPR RECEIVED 2/13/17. AWAITING ESTIMATE FROM DESIGNER. EXPECT TO COMPLETE IF SCO GRANTS REVIEW EXEMPTION. BIDS ARE DUE 4/12/17. FUNDING REQUESTED 4/21/17. FUNDING RECEIVED 4/21/17. WORK TO START 5/8/17. WORK TO BE COMPLETE BY 6/15. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
WILLIAMS, R. 5498 FAC ADMIN CLOSEOUT
BEAR HALL - REPLACE CEILING AND PAINT IN ROOM 102
T.B.D. T.B.D. SPR RECEIVED 4/11/18. MULLINS, K. 5849 PROJ MGMT SCOPE & ESTIMATING
BEAR HALL - REPLACE DOORS ON FIRST FLOOR
T.B.D. T.B.D. SPR RECEIVED 4/11/18. HEINS, R. 5846 PROJ MGMT SCOPE & ESTIMATING
Project Report
7
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5724 882000 180540 - 945864
BEAR HALL - REPLACE WIRELESS EXTERNAL READERS
12/31/17 $6.5K SPR RECEIVED 10/13/17. FUNDING REQUESTED FROM ANNUAL ALLOCATIONS VIA BUDGET OFFICE 10/13/17. FUNDING RECEIVED 10/13/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5724 FAC ADMIN CLOSEOUT
5547 882000 318500 - 945850
BELK HALL - RENOVATION OF BATHROOMS
7/31/18 $300K SPR RECEIVED 3/22/17. FUNDING REQUESTED 3/22/17. FUNDING RECEIVED 3/22/17. FUNDING REDUCED 3/27/17. BID OPENING 4/25/17. NOTICE TO PROCEED AND PRECONSTRUCTION CONFERENCE HELD 5/8/17. PROJECT SUBSTANTIALLY COMPLETE. WORKING ON PUNCHLIST ITEMS. RECEIVED CLOSEOUT DOCUMENTS. WORK IS COMPLETE.
JORDAN, W. 5547 ACSVCS COMPLETE
5717 882000 180187 - 923590
BLUE LINE STREAM - DESIGN FOR EROSION REPAIR
6/15/18 $50K SPR RECEIVED 10/12/17. FUNDING RECEIVED 10/17/17.
BLUME, J. 5717 PROJ MGMT DESIGN
5782 882000 319080 - 945966
BOSEMAN FIELD - INSTALL 6' FENCE
2/28/18 $2.6K SPR RECEIVED 2/5/18. FUNDING REQUESTED 2/5/18. FUNDING RECEIVED 2/7/18. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
MULLINS, K. 5782 FAC ADMIN CLOSEOUT
BOSEMAN FIELD - INSTALL NEW PADDED OF WALL
T.B.D. $41.1K SPR RECEIVED 2/21/17. CUSTOMER HAS PRICE ON PADDING AND INSTALLATION. PM IS SECURING PRICE ON ENGINEERING FOR TOTAL ESTIMATE. FUNDING REQUESTED 5/17/17.
WILLIAMS, R. 5507 SPONSOR AWAITING FUNDING
5783 882000 319080 - 945940
BOSEMAN FIELD - INSTALL SIDEWALK EXTENSION
3/15/18 $2.5K SPR RECEIVED 2/5/18. FUNDING REQUESTED 2/5/18. FUNDING RECEIVED 2/7/18. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
MULLINS, K. 5783 FAC ADMIN CLOSEOUT
5539 882000 180180 - 945860
BOSEMAN FIELD - PRESSBOX REPLACEMENT
6/15/17 $5.5K SPR RECEIVED 3/15/17. FUNDING ESTABLISHED 3/16/17. AWARD MADE TO ESTIMATING COMPANY. DRAWINGS SUBMITTED TO SCO ON 3/29/17. CLOSEOUT IS UNDERWAY.
PATRICK, R. 5539 FAC ADMIN CLOSEOUT
Project Report
8
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
BOSEMAN FIELD: ESTIMATE FOR LOCKER ROOM BUILDING
T.B.D. $288K SPR RECEIVED 8/5/15. FUNDING REQUESTED10/08/15.
MCCARLEY, T. 5087 SPONSOR AWAITING FUNDING
5713 882000 319080 - 945966
BROOKS FIELD - INSTALL BATTER'S EYE EQUIPMENT
2/15/18 $96K SPR RECEIVED 10/4/17. FUNDING REQUESTED 12/21/17. FUNDING RECEIVED 1/2/18. FUNDING UPGRADE RECEIVED 1/12/18. PO AWARDED, DELIVERY EXPECTED 2/22/18. INSTALLATION IS GOING SLOW. CONTRACTOR HAVING PROBLEMS WITH SOIL AT SITE. MATERIALS ON SITE; WORK TO START APRIL 10.
WILLIAMS, R. 5713 PROJ MGMT DESIGN
BROOKS FIELD - INSTALL CONCRETE PAD AT TICKET BOOTH
T.B.D. $2.6K SPR RECEIVED 3/23/18. FUNDING REQUESTED 3/26/18.
MULLINS, K. 5828 SPONSOR AWAITING FUNDING
5508 882000 319080 - 945961
BROOKS FIELD - NEW ENTRY ENHANCEMENTS
12/31/17 $40K SPR RECEIVED 2/21/17. EXPECTING ESTIMATE WEEK OF JULY 3. FUNDING REQUESTED 7/31/17. SCOPE MEETING SCHEDULED FOR WEEK OF SEPTEMBER 11. REVISED ESTIMATE SENT TO ATHLETICS 9/13/17. FUNDING RECEIVED 9/20/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
MULLINS, K. 5508 FAC ADMIN CLOSEOUT
5618 882000 318300 - 945850
BUILDING 4D - MODIFICATIONS TO CONCESSIONS SPACE
9/30/17 $13.8K SPR RECEIVED 7/10/17. FUNDING REQUESTED 8/4/17. FUNDING RECEIVED 8/25/17.
SINGLEY, D. 5618 PROJ MGMT CONSTRUCTION
BUILDING 7C - ADD BIKE RACK AND EMERGENCY CALL BOX
T.B.D. T.B.D. SPR RECEIVED 7/10/17. SINGLEY, D. 5623 PROJ MGMT SCOPE & ESTIMATING
5624 882000 371020 - 945940
BUILDING 7C - ADD CURBING AND SIDEWALKS
8/15/17 $36K SPR RECEIVED 7/10/17. FUNDING REQUESTED 7/11/17. FUNDING RECEIVED 7/12/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
COLEMAN, I. 5624 FAC ADMIN CLOSEOUT
Project Report
9
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5622 882000 371020 - 945966
BUILDING 7C - ADD SIDE DRIVES AND EMERGENCY VEHICLE PAD
8/15/17 $36K SPR RECEIVED 7/10/17. FUNDING REQUESTED 7/11/17. FUNDING RECEIVED 7/12/17. WORK IS COMPLETE.
COLEMAN, I. 5622 FAC ADMIN CLOSEOUT
BUILDING 7C - INSTALL OPERABLE GLASS WINDOWS/DOORS
T.B.D. T.B.D. SPR RECEIVED 4/4/18. SINGLEY, D. 5840 PROJ MGMT SCOPE & ESTIMATING
5515 882000 371020 - 945865
BUILDING 7C - INSTALL SPEAKER/INTERCOM SYSTEM
5/31/17 $34K SPR RECEIVED 3/6/17. FUNDING REQUESTED 4/3/17. FUNDING RECEIVED 4/6/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
COLEMAN, I. 5515 FAC ADMIN CLOSEOUT
BURNEY CENTER - AV UPGRADE IN BALLROOMS
T.B.D. T.B.D. SPR RECEIVED 2/21/18. GUINN, T. 5795 PROJ MGMT SCOPE & ESTIMATING
416290 416290 - 945864
BURNEY CEP - CONTROLS UPGRADE
T.B.D. $97.8K SPR GENERATED 4/10/14. R&R FUNDING ESTABLISHED 4/9/14.
MCCARLEY, T. 4820 PROJ MGMT SCOPE & ESTIMATING
5537 882000 180730 - 923590
BURNEY FOUNTAIN - REFURBISH FOUNTAIN AND LIGHTING
8/31/17 $23K SPR RECEIVED 3/9/17. FUNDING REQUESTED 6/19/17. FUNDING RECEIVED 7/5/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5537 FAC ADMIN CLOSEOUT
Project Report
10
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
SP14-014 883106 218019 - 945940
CAHILL DRIVE - INSTALL CURB & GUTTER
9/30/15 $350K PROJECT HAS BEEN APPROVED BY THE BUILDINGS AND GROUNDS COMMITTEE AND THE DESIGN REVIEW COMMITTEE. FUNDING REQUEST FORWARDED TO PROJECT SPONSOR ON 4/24/13. FUNDING RECEIVED 7/30/13. PERMIT RECONCILIATION IS COMPLETE. CAHILL DRIVE WORK IS COMPLETE. SCOPE OF PROJECT EXPANDED TO INCLUDE LIGHTING IMPROVEMENTS ALONG WALTON DRIVE. BID OPENING CONDUCTED ON 2/26/15. PO FOR THE ADDITIONAL WORK HAS BEEN AWARDED. LIGHTING WORK IS 60% COMPLETE.
MCCARLEY, T. 4617 PROJ MGMT CONSTRUCTION
5732 882000 125981 - 945860
CAMERON HALL - ADDITIONAL PRE-DESIGN FOR BUILDING EXPANSION
1/15/18 $30K SPR RECEIVED 10/23/17. FUNDING REQUESTED 10/23/17. FUNDING RECEIVED 10/31/17. DESIGN CONTRACT AWARDED. CONCEPT DESIGN IS UNDERWAY.
PATRICK, R. 5732 ACSVCS DESIGN
5672 882000 271609 - 945865
CAMERON HALL - AV UPGRADE IN ROOM 105
3/3/18 $10.6K SPR RECEIVED 9/12/17. FUNDING REQUESTED 10/11/17. FUNDING RECEIVED 11/30/17. PUNCHLIST ITEMS IN PROGRESS.
SOUTHERLAND, E.
5672 PROJ MGMT COMPLETE
5497 882000 180180 - 945868
CAMERON HALL - EXTEND CW HW LINES FROM DOBO TO CAMERON CHILLER
6/15/17 $38K SPR RECEIVED 2/9/17. FUNDING ESTABLISHED 2/9/17. DESIGN IN PROGRESS. $33K FOR DESIGN. PREBID SCHEDULED 4/11/17. BIDS HAVE BEEN OPENED. REVIEWING BIDS. FUNDING DECREASED 5/25/17. FUNDING DECREASED 6/2/17. FUNDING DECREASED 6/7/17. CLOSEOUT IS UNDERWAY.
MCCARLEY, T. 5497 FAC ADMIN CLOSEOUT
5691 419250 419250 - 923510
CAMERON HALL - HVAC & ELEC INFRASTRUCTURE (2015 R&R)
6/1/18 $232K SPR RECEIVED 9/19/17. FUNDING SET UP 9/20/17.
MCCARLEY, T. 5691 PROJ MGMT PROCUREMENT
Project Report
11
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
CAMERON HALL - HVAC IMPROVEMENTS ROOM 105 - DESIGN ONLY
T.B.D. T.B.D. SPR RECEIVED 4/11/18. SOUTHERLAND, E.
5845 PROJ MGMT SCOPE & ESTIMATING
CAMERON HALL - INSTALL CURTAIN, SCREEN MOTOR, ACOUSTIC PANELS IN ROOM 105
T.B.D. T.B.D. SPR RECEIVED 3/14/18. MET WITH SPONSOR AND VENDOR ON 4/4/18.
SOUTHERLAND, E.
5813 PROJ MGMT SCOPE & ESTIMATING
CAMERON HALL - INSTALL ELECTRICAL OUTLETS IN ROOM 133
T.B.D. $8.5K SPR RECEIVED 4/12/17. FUNDING REQUESTED 4/11/18.
GUINN, T. 5570 SPONSOR AWAITING FUNDING
5527 882000 271200 - 945850
CAMERON HALL - INSTALL NEW POWER AND DATA IN ROOM 240R
6/15/17 $36.8K SPR RECEIVED 3/6/17. FUNDING REQUESTED 3/16/17. FUNDING RECEIVED 3/21/17. FUNDING UPGRADE RECEIVED 4/10/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5527 FAC ADMIN CLOSEOUT
5632 882000 125981 - 923510
CAMERON HALL - INSTALL NEW TILE IN ENTRY ROOMS AT 105
8/15/17 $900 SPR RECEIVED 7/31/17. FUNDING REQUESTED 7/31/17. FUNDING RECEIVED 8/2/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5632 FAC ADMIN CLOSEOUT
CAMERON HALL - INSTALL ONE HOUR RATED WALL IN ROOM 100
T.B.D. $51.6K SPR RECEIVED 3/2/16. FUNDING REQUESTED 4/8/16.
MCCARLEY, T. 5244 SPONSOR AWAITING FUNDING
CAMERON HALL - REMOVE CABINETS IN ROOM 100-F
T.B.D. T.B.D. SPR RECEIVED 4/4/18. HEINS, R. 5841 PROJ MGMT SCOPE & ESTIMATING
5633 882000 125981 - 923510
CAMERON HALL - REMOVE CARPET AND INSTALL TILE IN ROOM 105
8/15/17 $1K SPR RECEIVED 7/31/17. FUNDING REQUESTED 7/31/17. FUNDING RECEIVED 8/2/17. WORK COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5633 FAC ADMIN CLOSEOUT
Project Report
12
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5394 882000 125981 - 945850
CAMERON HALL - RENOVATE ROOM 105
6/15/17 $145K SPR RECEIVED 9/9/16. FUNDING REQUESTED 10/25/16. DESIGN FUNDING RECEIVED 10/28/16. FUNDING UPGRADE RECEIVED 12/16/16. PHASE I (PROJECTION BOOTH DEMO) HAS BEEN COMPLETED. FUNDING UPGRADE RECEIVED 2/17/17. ADDITIONAL FUNDING UPGRADE RECEIVED 3/8/17. REDUCED SCOPE; EXPECT TO COMPLETE. FUNDING REDUCED BY $100,000 4/18/17. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5394 FAC ADMIN CLOSEOUT
5770 882000 125981 - 945850
CAMERON HALL - RENOVATE ROOM 105B INTO TWO OFFICES
6/15/18 $21.9K SPR RECEIVED 1/22/18. AWAITING SPACE COMMITTEE APPROVAL. MET WITH SPONSOR 2/9/18. PRE-BID SET FOR 3/12/18. FUNDING REQUESTED 3/26/18. FUNDING RECEIVED 4/11/18.
SOUTHERLAND, E.
5770 PROJ MGMT PROCUREMENT
5328 420202 420202 - 923510
CAMERON HALL - REPLACE ALL EXTERIOR WINDOWS (R&R)
8/1/18 $195K $195K SPR RECEIVED 6/30/16. FUNDING REQUESTED 9/23/16. R&R FUNDING ESTABLISHED 1/30/17. FUNDING UPGRADE REQUESTED 3/3/17.
BLUME, J. 5328 PROJ MGMT CONSTRUCTION
CAMERON HALL - REPLACE TRANSFORMER T23
T.B.D. $37.5K SPR RECEIVED 3/8/17. FUNDING REQUESTED 4/6/17.
GUINN, T. 5535 SPONSOR AWAITING FUNDING
5606 882000 125615 - 945850
CAMERON HALL - REPLACE WALLS WITH GLASS IN ROOMS 121 AND 136
2/15/18 $40K SPR RECEIVED 6/28/17. FUNDING REQUESTED 11/21/17. FUNDING RECEIVED 2/6/18. FUNDING UPGRADE RECEIVED 3/7/18. FUNDING UPGRADE RECEIVED 3/9/18. FUNDING LIQUIDATED ($35K) ON 4/2/18.
SOUTHERLAND, E.
5606 PROJ MGMT CONSTRUCTION
5580 882000 172325 - 945866
CAMERON HALL - REPLACEMENT OF MAG STRIPE READER
6/15/17 $18.3K SPR RECEIVED, FUNDING REQUESTED, FUNDING RECEIVED 5/8/17. CLOSEOUT IS UNDERWAY.
MCCARLEY, T. 5580 FAC ADMIN CLOSEOUT
Project Report
13
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5812 882000 180187 - 923510
CAMERON HALL - WINDOW REPLACEMENT, PHASE 2
6/15/18 $36K SPR RECEIVED 3/13/18. FUNDING RECEIVED 3/13/18.
BLUME, J. 5812 PROJ MGMT CONSTRUCTION
5594 882000 217770 - 923590
CAMPUS COMMONS - INSTALL 2016-2017 PAVER
6/30/17 $1.7K SPR RECEIVED 5/30/17. FUNDING REQUESTED 5/31/17. FUNDING RECEIVED 5/31/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5594 FAC ADMIN CLOSEOUT
5584 882000 180180 - 945966
CAMPUS COMMONS - INSTALL REPLACEMENT STONE
6/15/17 $2K SPR RECEIVED 5/18/17. FUNDING REQUESTED 5/18/17. FUNDING RECEIVED 5/18/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5584 FAC ADMIN CLOSEOUT
CAMPUS COMMONS - REPAIR EROSION ALONG POND BANK
T.B.D. $2K SPR RECEIVED 3/2/16. FUNDING REQUESTED 4/8/16.
MCCARLEY, T. 5245 SPONSOR AWAITING FUNDING
5480 420203 420203 - 945964
CAMPUS WIDE - ELECTRICAL WEST SUB #5 TO SWITCH 11 FEEDER PHASE I
12/31/17 $450K $450K SPR RECEIVED 1/31/17. FUNDING ESTABLISHED 1/31/17.
MULLINS, K. 5480 PROJ MGMT COMPLETE
CAMPUS WIDE - FIRE ALARM DIALER REPLACEMENTS
T.B.D. $350K SPR RECEIVED 2/15/16. JORDAN, W. 5227 ACSVCS SCOPE & ESTIMATING
5204 882000 180180 - 945871
CAMPUS WIDE - LANDSCAPING IMPROVEMENTS
3/31/16 $150K SPR RECEIVED 1/21/16. FUNDING REQUESTED 1/22/16. FUNDED IN PART ON 1/29/16. WORK IS IN PROGRESS. FUNDING UPGRADE RECEIVED 2/22/16 FOR FULL AMOUNT. WORK IN PROGRESS. FUNDING UPGRADE RECEIVED ON 4/5/16. CLOSEOUT IS UNDERWAY.
MCCARLEY, T. 5204 FAC ADMIN CLOSEOUT
5492 423000 423000 - 945950
CAMPUS WIDE - PARKING REPAIRS AND IMPROVEMENTS (1A & 1B)
6/30/18 $1.8M $1.8M PROJECT ESTABLISHED 2/7/17. CAPITAL FUNDING RECEIVED 2/21/17. DESIGN CONTRACT FINALIZED 4/4/17. PARKING LOT CONSTRUCTION TO BE COMPLETE IN LATE FEB.
JAMISON, G. 5492 ACSVCS CONSTRUCTION
Project Report
14
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5215 418210 418210 - 945966
CAMPUS WIDE - PERFORMANCE CONTRACT #2 - CONSTRUCTION PHASE
7/1/17 $6.4M $6.8M SPR RECEIVED 2/2/16. FUNDING IS IN PLACE FOLLOWING CONTRACT EXECUTION IN DECEMBER. CONSTRUCTION IS UNDERWAY.
SHARPE, S. 5215 ACSVCS CONSTRUCTION
5532 882000 180180 - 945866
CAMPUS WIDE - PERFORMANCE CONTRACT 2 - 2017 SUPPORT
6/15/17 $250K SPR RECEIVED 3/6/17. REQUESTED FUNDING 3/6/17. FUNDING ESTABLISHED AT $100,000 ON 3/27/17. FUNDING INCREASED TO $250,000 ON 5/25/17. CLOSEOUT IS UNDERWAY.
SHARPE, S. 5532 FAC ADMIN CLOSEOUT
5758 882000 180187 - 923590
CAMPUS WIDE - RESTRIPE ROADWAYS
6/15/18 $35K SPR RECEIVED 12/13/17. FUNDING RECEIVED 12/13/17 FROM FY18 AA.
BLUME, J. 5758 PROJ MGMT CONSTRUCTION
5435 882000 180187 - 945940
CAMPUS WIDE - SIDEWALK REPAIR
6/15/17 $40K SPR RECEIVED 11/22/16. FUNDING REQUESTED 11/22/16. FUNDING RECEIVED 12/1/16. WORK IS UNDERWAY. FUNDING INCREASED TO $40,000 ON 1/19/17. IN PROGRESS IDENTIFYING REPAIRS; WILL COMPLETE BY 6/15. CLOSEOUT IS UNDERWAY.
COLEMAN, I. 5435 FAC ADMIN CLOSEOUT
5452 882000 180180 - 945860
CAMPUS-WIDE - CAMPUS FACILITIES MASTER PLAN UPDATE 2016
5/30/17 $386K SPR RECEIVED 12/19/16. FUNDING RECEIVED 12/19/16. ONGOING. TO BE COMPLETED OCTOBER 2017. CAMPUS-WIDE SURVEY TO BE SENT OUT IN MID-MARCH. EXPECT TO COMPLETE THIS FUNDING 90% BY YEAR-END.
PATRICK, R. 5452 ACSVCS DESIGN
5685 882000 180186 - 945866
CAMPUS-WIDE - FY17-18 1292 ENERGY SAVING PROJECT
6/15/18 $151K SPR RECEIVED 9/15/17. FUNDING RECEIVED 9/19/17.
SHARPE, S. 5685 ACSVCS CONSTRUCTION
5473 882000 180187 - 923590
CAMPUS-WIDE - REFURBISH DENR PONDS TO PERMIT STANDARDS
6/15/17 $50K SPR RECEIVED 1/26/17. FUNDING ESTABLISHED 1/27/17. MACK, RACHEL, AND MARK ARE SCOPING WORK; EXPECT TO COMPLETE. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
COLEMAN, I. 5473 FAC ADMIN CLOSEOUT
Project Report
15
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5719 882000 180187 - 923590
CAMPUS-WIDE - RENOVATE RETENTION PONDS FOR PERMIT COMPLIANCE
6/1/18 $100K SPR RECEIVED 10/12/17. FUNDING RECEIVED 10/18/17.
MULLINS, K. 5719 PROJ MGMT CONSTRUCTION
CAMPUS-WIDE - REPLACE PLACARDS AT SINGLE-STALL RESTROOMS
T.B.D. $8.3K SPR RECEIVED 5/18/17. FUNDING REQUESTED 12/11/17.
BLUME, J. 5583 SPONSOR AWAITING FUNDING
5731 882000 180187 - 923590
CAMPUS-WIDE - ROAD AND SIDEWALK IMPROVEMENTS
5/31/18 $74.7K SPR RECEIVED 10/17/17. FUNDING RECEIVED 10/17/17. FUNDING REDUCED TO $109,800 ON 10/23/17. REDUCED FUNDING 12/13/17 BY $35,000 TO FUND ADDITIONAL ROADWAY PROJECT (PM5758). REDUCED $63 TO FUND FUNDING UPGRADE ON PM5630.
BLUME, J. 5731 PROJ MGMT CONSTRUCTION
5470 882000 180180 - 945869
CAMPUS-WIDE - TRAFFIC STUDY 6/15/17 $200K SPR RECEIVED 1/26/17. FUNDING ESTABLISHED 1/27/17. FUNDING FOR TRAFFIC STUDY.
PATRICK, R. 5470 ACSVCS DESIGN
R&R 413320 413320 - 945863
CENTRAL ENERGY PLANT - UPGRADE CONTROLS
6/30/15 $164.5K SPR GENERATED 12/20/13. R&R FUNDING ESTABLISHED 12/20/13.
MCCARLEY, T. 4741 PROJ MGMT PROCUREMENT
R&R 416260 416260 - 945868
CEP TO DOBO HALL - INFRASTRUCTURE
1/15/18 $100K SPR GENERATED 4/10/14. R&R FUNDING ESTABLISHED 4/9/14.
MCCARLEY, T. 4817 PROJ MGMT PROCUREMENT
5368 882000 180180 - 945964
CHANCELLOR'S WALK - INSTALL LIGHTS ON THE SIDES OF CHANCELLOR'S WALK
6/15/17 $37K SPR RECEIVED 8/15/16. FUNDING ESTABLISHED 1/27/17. LIGHTS SHIPPING 3/28. INSTALLATION BEING BID; EXPECT TO COMPLETE 6/15. FUNDING DECREASE TO $37K 4/19/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5368 FAC ADMIN CLOSEOUT
Project Report
16
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5170 882000 904668 - 945863
CIE - EVALUATION AND UPGRADES TO HVAC SYSTEM
3/31/17 $10K SPR RECEIVED 11/9/15. FUNDING REQUESTED 12/23/15. FUNDING RECEIVED 12/21/16. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5170 FAC ADMIN CLOSEOUT
5777 882000 172800 - 945861
CIE - INSTALL TWO GLASS DOORS OUTSIDE OF ROOM 1127
4/30/18 $11.2K SPR RECEIVED 2/2/18. FUNDING REQUESTED 2/19/18. FUNDING RECEIVED 3/7/18.
SINGLEY, D. 5777 PROJ MGMT PROCUREMENT
5320 882000 152451 - 945860
CIS - RENOVATE SUITE 1004 5/31/17 $26K SPR RECEIVED 6/27/16. DESIGN FUNDING REQUESTED 7/28/16. FUNDING RECEIVED 8/8/16. FUNDING UPGRADE RECEIVED 12/8/16. FUNDING UPGRADE RECEIVED 2/2/17. WILL COMPLETE 4/7/17.
BLUME, J. 5320 FAC ADMIN CLOSEOUT
5155 882000 180187 - 923510
CIS - REPAIR PORTICO DOOR LEAKS
6/15/18 $60.2K SPR RECEIVED 10/28/15. FUNDING RECEIVED 10/17/17. FUNDING REDUCED 3/13/18.
BLUME, J. 5155 PROJ MGMT CONSTRUCTION
CIS BUILDING - HVAC AND ELECTRICAL UPGRADES IN ROOM 2035A
T.B.D. $34K SPR RECEIVED 12/21/17. FUNDING REQUESTED 1/31/18.
SINGLEY, D. 5765 SPONSOR AWAITING FUNDING
5726 882000 180540 - 945864
CIS BUILDING - INSTALL DOOR MONITORING FOR EXTERNAL DOORS
12/31/17 $3.6K SPR RECEIVED 10/13/17. FUNDING REQUESTED FROM ANNUAL ALLOCATIONS VIA BUDGET OFFICE 10/13/17. FUNDING RECEIVED 10/13/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
MULLINS, K. 5726 FAC ADMIN CLOSEOUT
CIS BUILDING - INSTALL LENEL CARD READER IN ROOM 1025
T.B.D. T.B.D. SPR RECEIVED 3/19/18. HEINS, R. 5825 PROJ MGMT SCOPE & ESTIMATING
CIS BUILDING - INSTALL OUTLETS AND DATA IN ROOM 2010
T.B.D. T.B.D. SPR RECEIVED 8/11/17. SINGLEY, D. 5645 PROJ MGMT SCOPE & ESTIMATING
Project Report
17
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
CIS BUILDING - RENOVATE ROOM 1023 INTO TWO OFFICES
T.B.D. T.B.D. SPR RECEIVED 2/2/18. GUINN, T. 5776 PROJ MGMT SCOPE & ESTIMATING
5579 882000 172375 - 945866
CMGMG - MAIN BUILDING: REPLACEMENT OF MAG STRIPE READER
6/15/17 $5.9K SPR RECEIVED, FUNDING REQUESTED, AND FUNDING RECEIVED 5/8/17. CLOSEOUT IS UNDERWAY.
MCCARLEY, T. 5579 FAC ADMIN CLOSEOUT
5738 CMS - DREDGE IN AND AROUND FLOATING DOCKS
T.B.D. T.B.D. SPR RECEIVED 10/30/17. ON HOLD UNTIL FY19.
SOUTHERLAND, E.
5738 PROJ MGMT ON HOLD
CMS - INSTALL AWNING OVER ENTRANCE TO BOAT SHOP
T.B.D. $25.5K SPR RECEIVED 10/30/17. FUNDING REQUESTED 12/6/17.
SOUTHERLAND, E.
5736 SPONSOR AWAITING FUNDING
CMS - INSTALL PROPERTY LINE FENCE
T.B.D. $48.4K SPR RECEIVED 4/20/16. FUNDING REQUESTED 6/28/16.
SOUTHERLAND, E.
5289 SPONSOR AWAITING FUNDING
CI10-05 443751 443751 - 945868
CMS - MARBIONC 12/31/15 T.B.D. NOTICE TO PROCEED ISSUED 10/5/11. WORK IS COMPLETE.
SEIFERT, L. 3915 FAC ADMIN CLOSEOUT
5377 882000 180187 - 923510
CMS - REPAIR/REPLACE EXTERIOR DOOR #3
12/31/17 $24K SPR RECEIVED 8/31/16. AWAITING QUOTES FROM CONTRACTORS. FUNDING REQUESTED 11/17/16. RECONSTRUCTING FILE, REQUESTING NEW QUOTES; AWAITING FINAL QUOTE FROM VENDOR. FUNDING RECEIVED 11/1/17. WORK COMPLETE; PUNCHLIST ITEMS REMAINING.
WILLIAMS, R. 5377 PROJ MGMT COMPLETE
Project Report
18
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5737 419210 419210 - 923510
CMS - REPLACE CONTROLLER FOR GREENHOUSE LIGHT
1/31/18 $10.4K SPR RECEIVED 10/30/17. FUNDING REQUESTED 11/13/17. FUNDING RECEIVED FROM R&R 11/21/17. CONTROLLER EXPECTED 2/19/18. EQUIPMENT IS IN OUR WAREHOUSE. ENGINEERED CONTROL SOLUTIONS TO INSTALL 3/14/18. FUNDING UPGRADE RECEIVED 3/22/18. CONTROLLER WORK TO START APRIL 4.
WILLIAMS, R. 5737 PROJ MGMT CONSTRUCTION
CMS MAIN - INSTALL MODULAR STORAGE UNIT
T.B.D. T.B.D. SPR RECEIVED 3/14/18. MULLINS, K. 5817 PROJ MGMT SCOPE & ESTIMATING
CMS MAIN - REPAIR WINDOWS IN ROOM 1101
T.B.D. $2K SPR RECEIVED 3/14/18. FUNDING REQUESTED 4/5/18.
MULLINS, K. 5818 SPONSOR AWAITING FUNDING
CMS MAIN BUILDING - RE-GASKET CHILLER
T.B.D. T.B.D. SPR RECEIVED 5/30/17. PATRICK, A. 5593 PLANTADMIN SCOPE & ESTIMATING
5728 419210 419210 - 923510
CMS MAIN BUILDING - REGASKET CHILLER #2
3/31/18 $175K SPR RECEIVED 10/16/17. FUNDING REQUESTED 10/17/17. FUNDING SET UP USING R&R FUNDING 11/1/17. AWAITING DELIVERY OF CHILLER MOTOR. WORK TO FINISH MID-APRIL. RE-GASKETING WORK STARTED, NEW MOTOR EXPECTED 3/12/18. AWAITING FINAL INVOICE.
WILLIAMS, R. 5728 PROJ MGMT COMPLETE
5666 882000 121040, 180730 - 945863
CMS MAIN BUILDING - REPLACE FUME HOOD IN ROOM 2309
6/15/18 $63.8K SPR RECEIVED 9/8/17. FUNDING REQUESTED 10/17/17. FUNDING RECEIVED 2/5/18. DESIGN AWARDED. PLANS TO BE READY WEEK OF APRIL 2.
WILLIAMS, R. 5666 PROJ MGMT DESIGN
5614 882000 319156 - 945866
CMS MARBIONC - INSTALL CHEMICAL RESISTANT SINK IN ROOM 1015
10/31/17 $2.2K SPR RECEIVED 6/28/17. FUNDING REQUESTED 9/14/17. FUNDING RECEIVED 9/26/17. PO HAS BEEN ISSUED. WORK COMPLETE; AWAITING INVOICE. CLOSEOUT IS UNDERWAY.
WILLIAMS, R. 5614 FAC ADMIN CLOSEOUT
Project Report
19
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
CMS MARBIONC - INSTALL NITROGEN GENERATION SYSTEM
T.B.D. $112K SPR RECEIVED 3/23/18. FUNDING REQUESTED 4/5/18.
SINGLEY, D. 5826 SPONSOR AWAITING FUNDING
CMS MARBIONC - VENTILIATION AND LAB ACH OPTIMIZATION
T.B.D. T.B.D. SPR RECEIVED 7/23/15. WILLIAMS, R. 5078 PROJ MGMT SCOPE & ESTIMATING
CMS WRIGHTSVILLE BEACH - MOVE POWER POLE AT PUMP STATION
T.B.D. T.B.D. SPR RECEIVED 6/29/17. SINGLEY, D. 5617 PROJ MGMT SCOPE & ESTIMATING
5716 882000 180187 - 923510
CMS WRIGHTSVILLE BEACH MODULAR - PROVIDE RATED ENCLOSURE AROUND RISER ROOM (FY18)
4/30/18 $40K SPR RECEIVED 10/12/17. FUNDING RECEIVED 10/17/17. PLANS HAVE BEEN SUBMITTED TO SCO FOR REVIEW.
SOUTHERLAND, E.
5716 PROJ MGMT CONSTRUCTION
5474 882000 180187 - 945866
CMS-WB MODULAR - PROVIDE RATED ENCLOSURE AT RISER ROOM AND PROTECT UNDER STRUCTURE
6/15/17 $26K SPR RECEIVED 1/26/17. FUNDING ESTABLISHED 1/27/17. GATHERING ESTIMATES; EXPECT TO COMPLETE. LOW BID RECEIVED AND PO ISSUED. FUNDING REDUCED 6/9/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5474 FAC ADMIN CLOSEOUT
5403 882000 121981 - 945810
CMSMG - CONSTRUCT NEW WET LAB
6/15/17 $433K SPR RECEIVED 9/15/16. FUNDING REQUESTED 9/26/16. FUNDING RECEIVED 11/2/16. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5403 FAC ADMIN CLOSEOUT
SP14-028 883120 214802, 573750 - 945966
CMSMG - EXPAND FLOATING DOCKS
2/28/15 $333K SPR RECEIVED 9/30/13. FUNDING REQUESTED 9/30/13. FUNDING RECEIVED 10/17/13. BID OPENING CONDUCTED ON 4/29/14. WORK IS UNDERWAY. FUNDING UPGRADE RECEIVED 8/22/14. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
MCCARLEY, T. 4693 FAC ADMIN CLOSEOUT
Project Report
20
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5565 882000 281781 - 945968
CMSMG - INSTALL 8" RPX BACKFLOW ON MAIN LINE
6/5/17 $60K SPR RECEIVED 4/12/17. FUNDING REQUESTED 4/12/17. FUNDING RECEIVED 4/12/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5565 FAC ADMIN CLOSEOUT
5631 419210 419210 - 923510
CMSMG - MAIN BUILDING - REPAIR STRUCTURAL CEILING SUPPORTS IN ROOM 2203
9/30/17 $9K SPR RECEIVED 7/27/17. FUNDING REQUESTED 8/3/17. FUNDING RECEIVED 8/24/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5631 FAC ADMIN CLOSEOUT
5605 882000 180187 - 923590
CMSMG - REMOVE BROKEN PILINGS AT PIER
12/31/17 $12K SPR RECEIVED 6/28/17. SURVEY WILL BE HANDLED IN PM5635, R&R PROJECT. THIS PROJECT IS FOR ANY STRUCTURAL REPAIRS, FUNDED BY AA. FUNDING RECEIVED 10/17/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5605 FAC ADMIN CLOSEOUT
5564 882000 281781 - 923510
CMSMG - REPLACE DOMESTIC WATER BOOSTER PUMP
6/5/17 $60K SPR RECEIVED 4/12/17. FUNDING REQUESTED 4/12/17. FUNDING RECEIVED 4/12/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5564 FAC ADMIN CLOSEOUT
5635 441551 441551 - 923590
CMSMG - STRUCTURAL REPAIR (2009 R&R)
12/31/17 $3K PROJECT ESTABLISHED IN AIM USING 2009 R&R FUNDS 8/1/17.
SOUTHERLAND, E.
5635 PROJ MGMT CONSTRUCTION
CMSMG MAIN BUILDING - INSTALL SUPPORT DEVICE FOR TOWER
T.B.D. T.B.D. SPR RECEIVED 8/22/17. SINGLEY, D. 5656 PROJ MGMT SCOPE & ESTIMATING
5655 882000 148600, 180730 - 923510
CMSMG MAIN BUILDING - REPAIR CRACKS IN FLOOR IN ROOM 2201
11/30/17 $3.5K SPR RECEIVED 8/22/17. FUNDING REQUESTED 9/20/17. FUNDING RECEIVED 10/18/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5655 FAC ADMIN CLOSEOUT
COLLEGE ROAD ENTRANCES - CONCEPTUAL LANDSCAPING DESIGN FOR ENTRANCE WING WALLS
T.B.D. $11K SPR RECEIVED 4/13/16. FUNDING REQUESTED 4/29/16.
SOUTHERLAND, E.
5286 SPONSOR AWAITING FUNDING
Project Report
21
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5465 882000 180180 - 945966
COLLEGE ROAD ENTRANCES - REPLACE MARQUEE
5/31/17 $130K SPR RECEIVED 1/26/17. FUNDING ESTABLISHED 1/27/17. PROPOSALS REQUESTED. DAKTRONICS HAS AWARD TO UPGRADE MARQUEE ($118,872); EXPECT TO COMPLETE. FUNDING REDUCED 5/8/17. CLOSEOUT IS UNDERWAY. WORK IS COMPLETE.
MCCARLEY, T. 5465 FAC ADMIN CLOSEOUT
5270 882000 180180 - 945966
COLLEGE ROAD SEAHAWK COUNTRY SIGN - PULL POWER AND INSTALL PHOTO CELLS AND NEW LIGHTS
6/15/17 $20K SPR RECEIVED 4/1/16. FUNDING REQUESTED 4/28/16. FUNDING RECEIVED 5/8/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5270 FAC ADMIN CLOSEOUT
5753 882000 318500 - 923510
CORNERSTONE HALL - REPAIR/REPLACE SHOWER PANS
7/1/18 $20.2K SPR RECEIVED 11/21/17. FUNDING REQUESTED 3/13/18. FUNDING RECEIVED 3/15/18.
HEINS, R. 5753 PROJ MGMT PROCUREMENT
5241 882000 180310 - 923590
CROSS CITY TRAIL - TEXTURE WALKING SURFACE AND CUT DOWN RAILINGS
5/15/16 $1K SPR RECEIVED 3/2/16. FUNDING REQUESTED 3/8/16. FUNDING RECEIVED 4/11/16. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
PICKARD, S. 5241 FAC ADMIN CLOSEOUT
5786 882000 121160 - 945860
CULTURAL ARTS BUILDING - ELECTRICAL UPGRADES IN BECKWITH RECITAL HALL
6/15/18 $5.4K SPR RECEIVED 2/5/18. DESIGN FUNDING REQUESTED 2/22/18. FUNDING RECEIVED 2/23/18.
GUINN, T. 5786 PROJ MGMT PROCUREMENT
5653 882000 215207 - 945864
CULTURAL ARTS BUILDING - INSTALL ADDITIONAL POWER FOR HOIST MOTORS
10/31/17 $7.7K SPR RECEIVED 8/22/17. FUNDING REQUESTED 9/25/17. FUNDING RECEIVED 9/29/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5653 FAC ADMIN CLOSEOUT
5755 882000 180730 - 945866
CULTURAL ARTS BUILDING - INSTALL DOOR AT OUTDOOR CERAMICS AREA
3/31/18 $4.3K SPR RECEIVED 12/6/17. FUNDING REQUESTED 1/23/18. MET WITH SPONSOR 2/1/18. FUNDING RECEIVED 2/15/18. FUNDING UPGRADE RECEIVED 2/16/18.
SOUTHERLAND, E.
5755 PROJ MGMT CONSTRUCTION
CULTURAL ARTS BUILDING - INSTALL EXTERIOR SIGNAGE
T.B.D. T.B.D. SPR RECEIVED 3/23/18. BLUME, J. 5829 PROJ MGMT SCOPE & ESTIMATING
Project Report
22
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5699 882000 121981 - 945866
CULTURAL ARTS BUILDING - INSTALL ROOF OVER WELDING YARD
6/15/18 $150K SPR RECEIVED 9/25/17. FUNDING REQUESTED 1/19/18. FUNDING RECEIVED 2/9/18.
BLUME, J. 5699 PROJ MGMT DESIGN
5533 882000 215207 - 945866
CULTURAL ARTS BUILDING - INSTALL WASHER/DRYER HOOKUPS IN ROOM 1101 AND 1103
6/30/17 $8K SPR RECEIVED 3/6/17. FUNDING REQUESTED 4/4/17. FUNDING RECEIVED 4/6/17. FUNDING UPGRADE 6/5/17. CLOSEOUT IS UNDERWAY.
BLUME, J. 5533 FAC ADMIN CLOSEOUT
R&R 416250 416250 - 945868
CULTURAL ARTS BUILDING - REPLACE CHILLER COMPRESSOR
6/30/15 $55K SPR GENERATED 4/10/13. R&R FUNDING ESTABLISHED 4/9/14. REPAIR OF COMPRESSOR MOTOR IS COMPLETE. ADDITIONAL WORK BEING CONSIDERED.
MCCARLEY, T. 4816 PROJ MGMT CONSTRUCTION
CULTURAL ARTS BUILDING - REPLACE GRIPS AND WIRING IN SCENE SHOP
T.B.D. $7.8K SPR RECEIVED 10/12/17. FUNDING REQUESTED 1/16/18.
SINGLEY, D. 5714 SPONSOR AWAITING FUNDING
5725 882000 180540 - 945864
CULTURAL ARTS BUILDING - REPLACE WIRELESS EXTERNAL READERS
12/31/17 $45K SPR RECEIVED 10/13/17. FUNDING REQUESTED FROM ANNUAL ALLOCATIONS VIA BUDGET OFFICE 10/13/17. FUNDING RECEIVED 10/13/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
MULLINS, K. 5725 FAC ADMIN CLOSEOUT
5771 882000 152421 - 945860
D.C. VIRGO - DESIGN AND BUILDING ASSESSMENT
8/1/18 $120K SPR RECEIVED 1/24/18. FUNDING REQUESTED 1/24/18. FUNDING RECEIVED 1/29/18. FUNDING UPGRADE RECEIVED 3/6/18.
COLEMAN, I. 5771 ACSVCS DESIGN
5665 882000 121120 - 945864
DELOACH HALL - RE-WIRE ELECTRICAL IN ROOMS 202 AND 202A
2/28/18 $8.9K SPR RECEIVED 9/8/17. FUNDING REQUESTED 10/2/17. FUNDING RECEIVED 1/19/18. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5665 FAC ADMIN CLOSEOUT
5399 882000 121250 - 945864
DELOACH HALL - REMOVE NON-WORKING HOOD AND ELECTRICAL UPGRADES IN ROOM 215
3/31/17 $8.4K SPR RECEIVED 9/15/16. FUNDING REQUESTED 1/3/17. FUNDING RECEIVED 2/8/17. ADDITIONAL SCOPE; EXPECT TO COMPLETE 6/15. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5399 FAC ADMIN CLOSEOUT
Project Report
23
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5729 882000 180540 - 945850
DELOACH HALL - RENOVATE CLASSROOMS 114 AND 212
6/1/18 $300K SPR RECEIVED 10/17/17. FUNDING RECEIVED 10/18/17.
SOUTHERLAND, E.
5729 PROJ MGMT CONSTRUCTION
5187 882000 121981 - 945850
DELOACH HALL - RENOVATE ROOMS 210 AND 211
4/15/16 $47.3K SPR RECEIVED 12/8/15. FUNDING REQUESTED 1/21/16. FUNDING RECEIVED 2/12/16. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
PICKARD, S. 5187 FAC ADMIN CLOSEOUT
5301 882000 175000 - 945866
DELOACH HALL AND CMS TRITIUM FACILITY - INSTALL WIRELESS LENEL READERS
5/1/17 $1.3K SPR RECEIVED 5/19/16. EQUIPMENT ON HAND IN SECURE ACCESS OFFICE. ESTIMATING REQUIREMENTS FOR INSTALLATION. FUNDING FOR INSTALLATION RECEIVED 3/7/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5301 FAC ADMIN CLOSEOUT
5460 882000 318400 - 945850
DEPAOLO HALL - DIVIDE ROOM 2032 INTO TWO OFFICES
6/15/17 $15K SPR RECEIVED 1/13/17. FUNDING REQUESTED 2/2/17. FUNDING RECEIVED 2/21/17. FUNDING UPGRADE RECEIVED 5/5/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5460 FAC ADMIN CLOSEOUT
5481 882000 152440 - 945861
DEPAOLO HALL - SOUNDPROOFING IN PROCTORING ROOMS IN SUITE 1033
6/15/17 $1.5K SPR RECEIVED 1/31/17. FUNDING REQUESTED 3/30/17. FUNDING RECEIVED 3/31/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5481 FAC ADMIN CLOSEOUT
5588 DESIGN AND CONSTRUCTION GUIDELINES REVIEW AND REVISION
9/15/17 $0 PROJECT SET UP 5/25/17. WORK IS UNDERWAY. ELECTRICAL/MECHANICAL SECTIONS REVIEWED. PREPARING LIST OF PREFERRED ALTERNATES FOR REVIEW.
JAMISON, G. 5588 ACSVCS DESIGN
DOBO HALL - COMMISSIONING AND EVALUATION OF HVAC
T.B.D. T.B.D. SPR RECEIVED 7/24/17. PATRICK, A. 5627 PLANTADMIN SCOPE & ESTIMATING
5587 882000 138050 - 945850
DOBO HALL - DEMOLISH EXISTING FURNITURE IN ROOM 134
6/15/17 $30K SPR RECEIVED 5/25/17. FUNDING REQUESTED 5/30/17. FUNDING RECEIVED 5/30/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5587 FAC ADMIN CLOSEOUT
Project Report
24
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5768 882000 180540 - 945863
DOBO HALL - HVAC REPAIRS 6/15/18 $280K SPR RECEIVED 1/2/18. FUNDING RECEIVED 2/21/18.
PATRICK, A. 5768 PLANTADMIN CONSTRUCTION
5831 882000 121981 - 945864
DOBO HALL - INSTALL ELECTRICAL OUTLETS/GAS PLUGS IN ROOMS 117B/119
6/15/18 $2.8K SPR RECEIVED 3/23/18. FUNDING REQUESTED 4/9/18. FUNDING RECEIVED 4/11/18.
SINGLEY, D. 5831 PROJ MGMT PROCUREMENT
5701 882000 121981 - 945864
DOBO HALL - INSTALL ELECTRICAL POWER IN ROOMS 103 AND 134
5/31/17 $11.3K SPR RECEIVED 9/25/17. FUNDING REQUESTED 11/14/17. FUNDING RECEIVED 1/19/18. WORK IS COMPLETE, CLOSEOUT IS UNDERWAY.
GUINN, T. 5701 FAC ADMIN CLOSEOUT
5466 882000 180180 - 945864
DOBO HALL - INSTALL EMERGENCY GENERATOR
6/15/17 $8K SPR RECEIVED 1/26/17. FUNDING RECEIVED 1/27/17. REDUCED BUDGET TO $50,000 ON 2/9/17. REDUCED FUNDING TO $10,000 ON 3/10/17. OTHER FUNDS DIVERTED TO DOBO CAMERON CW HW LINES. FUNDING REDUCED 6/8/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5466 FAC ADMIN CLOSEOUT
5641 882000 271514 - 945864
DOBO HALL - INSTALL OUTLETS IN ROOM 121F
5/31/18 $4.9K SPR RECEIVED 8/11/17. FUNDING REQUESTED 3/12/18. FUNDING RECEIVED 4/11/18.
BLUME, J. 5641 PROJ MGMT PROCUREMENT
DOBO HALL - INSTALL SNORKEL HOODS
T.B.D. $17K SPR RECEIVED 4/30/14. FUNDING REQUESTED 7/29/14. SPONSORE INQUIED SEPTEMBER 2015. PROJECT MAY BE FUNDED IN THE NEAR FUTURE.
MCCARLEY, T. 4842 SPONSOR AWAITING FUNDING
5450 419200 419200 - 923510
DOBO HALL - LAB EXHAUST HVAC ROOF REF (2015 R&R)
12/31/17 $607K $607K SPR RECEIVED 12/19/16. FUNDING REQUESTED 12/19/16. FUNDING RECEIVED FROM R&R FUNDS 12/20/16. FUNDING INCREASED 1/6/17. PROJECT TO HANDLE ALL R&R WORK FROM FUND 419200. BUDGET UPDATED TO REFLECT.
PATRICK, A. 5450 PLANTADMIN CONSTRUCTION
Project Report
25
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
R&R 413230 413230 - 945863
DOBO HALL - REFRIGERANT MONITORING
6/30/15 $210K SPR GENERATED 12/20/13. R&R FUNDING ESTABLISHED 12/20/13.
MCCARLEY, T. 4739 PROJ MGMT CONSTRUCTION
R&R 416230 416230 - 945868
DOBO HALL - REFRIGERANT MONITORING
6/30/15 $60K SPR GENERATED 4/10/14. R&R FUNDING ESTABLISHED 4/9/14.
MCCARLEY, T. 4814 PROJ MGMT CONSTRUCTION
5346 882000 121981 - 945850
DOBO HALL - RENOVATE ENVIRONMENTAL CHAMBERS IN ROOMS 212/240/250A
5/30/17 $499.9K SPR RECEIVED 7/18/16. FUNDING REQUESTED 11/22/16. FUNDING RECEIVED 11/22/16. BID OPENING SCHEDULED FOR 1/10/17. BIDS OPENED AND PREPARING REQUISITION DOCUMENTS. WORK IS UNDERWAY; DEMO TO BE COMPLETED 3/10/17. EXPECT TO COMPLETE 6/15; POSSIBLE SURPLUS FUNDING. DEMO IS COMPLETE. ALL EQUIPMENT IN PLACE. REFRIGERATION WORK TO START WEEK OF 5/8/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
WILLIAMS, R. 5346 FAC ADMIN CLOSEOUT
5342 882000 121981 - 945850
DOBO HALL - RENOVATIONS TO SUITE 117 AND 119
6/15/17 $247.7K SPR RECEIVED 7/18/16. DESIGN HAS BEEN COMPLETED UNDER ANOTHER PROJECT. CONSTRUCTION SCOPING/PLANNING UNDERWAY. FUNDING REQUESTED 4/5/17. FUNDING RECEIVED 4/25/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5342 FAC ADMIN CLOSEOUT
R&R 416270 416270 - 945868
DOBO HALL - REPLACE BOLIER T.B.D. $250K SPR GENERATED 4/10/14. R&R FUNDING ESTABLISHED 4/9/14. DESIGN FEE PROPOSAL HAS BEEN REQUESTED.
MCCARLEY, T. 4818 PROJ MGMT PROCUREMENT
5612 882000 121050 - 923510
DOBO HALL - REPLACE SEATING IN ROOM 103
8/15/17 $22K SPR RECEIVED 6/28/17. FUNDING REQUESTED 7/10/17. FUNDING RECEIVED 7/10/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5612 FAC ADMIN CLOSEOUT
Project Report
26
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
DOBO HALL - STAND-ALONE COMPRESSED AIR/NITROGEN SYSTEM
T.B.D. T.B.D. SPR RECEIVED 12/8/17. SINGLEY, D. 5757 PROJ MGMT SCOPE & ESTIMATING
5733 882000 319246 - 945950
EAST PARKING DECK - HOUSING PARKING DECK STUDY AND EAST DECK EVALUATION
2/1/18 $35K SPR RECEIVED 10/23/17. FUNDING REQUESTED 10/23/17. FUNDING RECEIVED 10/23/17. FINAL REPORT PLANNED LATE JANUARY.
JAMISON, G. 5733 ACSVCS DESIGN
5531 882000 152420 - 945850
EDUCATION BUILDING - CONVERT ROOM 350 INTO TWO OFFICES
6/15/17 $11.6K SPR RECEIVED 3/6/17. FUNDING REQUESTED 4/6/17. FUNDING RECEIVED 4/12/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5531 FAC ADMIN CLOSEOUT
EDUCATION BUILDING - INSTALL NEW HVAC SYSTEM IN ROOMS 264 AND 329A
T.B.D. T.B.D. SPR RECEIVED 2/21/18. AWAITING PRICE FROM CONTRACTOR.
WILLIAMS, R. 5793 PROJ MGMT SCOPE & ESTIMATING
5546 882000 123981 - 923510
EDUCATION BUILDING - INSTALL TILE AT BACKSPLASH IN ROOM 134
6/15/17 $900 SPR RECEIVED 3/20/17. FUNDING REQUESTED 3/27/17. FUNDING RECEIVED 5/5/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5546 FAC ADMIN CLOSEOUT
5751 882000 152420 - 945850
EDUCATION BUILDING - RENOVATE ROOM 313 INTO OFFICE
1/15/18 $6.7K SPR RECEIVED 11/13/17. FUNDING REQUESTED 11/29/17. FUNDING RECEIVED 12/7/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
MULLINS, K. 5751 FAC ADMIN CLOSEOUT
5723 882000 180540 - 945864
EDUCATION BUILDING - REPLACE WIRELESS EXTERNAL READERS
12/31/17 $30K SPR RECEIVED 10/13/17. FUNDING REQUESTED FROM ANNUAL ALLOCATIONS VIA BUDGET OFFICE 10/13/17. FUNDING RECEIVED 10/13/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
MULLINS, K. 5723 FAC ADMIN CLOSEOUT
5772 882000 152420 - 945850
EDUCATION BUILDING - REVIEW SPACE OPTIONS FOR RENOVATION IN ROOM 106
6/15/18 $25K SPR RECEIVED 1/25/18. MET WITH SPONSOR. FUNDING REQUESTED 2/15/18. FUNDING RECEIVED 2/21/18. FUNDING REDUCED 4/9/18.
SOUTHERLAND, E.
5772 PROJ MGMT CONSTRUCTION
Project Report
27
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5494 882000 141021 - 945850
EDUCATION BUILDING - TECHNOLOGY UPGRADES IN ROOM 235
8/15/17 $15K SPR RECEIVED 2/7/17. FUNDING REQUESTED 7/12/17. FUNDING RECEIVED 7/17/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5494 FAC ADMIN CLOSEOUT
FACILITIES BUILDING - INSTALL CONTRACTOR KEYTRAC SYSTEM
T.B.D. T.B.D. SPR RECEIVED 4/11/18. HEINS, R. 5856 PROJ MGMT SCOPE & ESTIMATING
FACILITIES BUILDING - RECONFIGURE SPACE IN ROOM 173
T.B.D. $12K SPR RECEIVED 7/7/16. FUNDING REQUESTED 7/28/16.
SOUTHERLAND, E.
5335 SPONSOR AWAITING FUNDING
5553 882000 180184, 180720 - 923510
FACILITIES BUILDING - REPLACE CUBICLES WITH GYPSUM WALLS
6/15/17 $79.6K SPR RECEIVED 3/27/17. FUNDING REQUESTED 3/27/17. FUNDING RECEIVED 3/28/17. PREPARING PLANS FOR SCO SUBMITTAL. FUNDING UPGRADE RECEIVED 7/31/17. WORK 98% COMPLETE. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
MCCARLEY, T. 5553 FAC ADMIN CLOSEOUT
5722 882000 180540 - 945864
FACILITIES BUILDING - REPLACE WIRELESS READERS
1/15/18 $5.5K SPR RECEIVED 10/13/17. FUNDING REQUESTED FROM ANNUAL ALLOCATIONS VIA BUDGET OFFICE 11/14/17.
MULLINS, K. 5722 PROJ MGMT PROCUREMENT
5563 882000 319080 - 945866
FISHER FIELDHOUSE - INSTALL DEHUMIDIFIER IN ROOM 103
5/31/17 $1.5K SPR RECEIVED 4/5/17. FUNDING REQUESTED 4/5/17. FUNDING RECEIVED 4/21/17. DEHUMIDIFIERS HAVE BEEN DELIVERED; INSTALL TO OCCUR 5/8/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
WILLIAMS, R. 5563 FAC ADMIN CLOSEOUT
5715 882000 644550 - 945864
FISHER STUDENT CENTER - INSTALL ADA PUSH BUTTON AT CLOCK TOWER LOUNGE
4/30/18 $8.9K SPR RECEIVED 10/12/17. FUNDING REQUESTED 1/9/18. FUNDING RECEIVED 2/21/18. WORK SCHEDULED TO BEGIN 4/16/18.
SOUTHERLAND, E.
5715 PROJ MGMT CONSTRUCTION
Project Report
28
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5703 882000 180310 - 945866
FISHER STUDENT CENTER - INSTALL WEATHERSTEM STATION
6/15/18 $5K SPR RECEIVED 9/27/17. REQUESTED FUNDING 10/19/17. FUNDING RECEIVED 2/19/18. TEMPORARILY ON HOLD TO DETERMINE NEW BUILDING LOCATION.
SINGLEY, D. 5703 PROJ MGMT PROCUREMENT
FISHER STUDENT CENTER - MINOR RENOVATIONS AT BOOKSTORE (B&N PROJECT)
3/15/18 $0 SPR RECEIVED 1/29/18. PROJECT FUNDED INDEPENDENTLY BY BARNES AND NOBLE WITH PROJECT MANAGEMENT OVERSIGHT ONLY.
SINGLEY, D. 5774 PROJ MGMT SCOPE & ESTIMATING
5146 882000 318300, 319163 - 945863
FISHER STUDENT CENTER - RECOMMISSIONING UPGRADES
6/15/18 $255K SPR RECEIVED 10/13/15. AWAITING DECISIONS ON RECOMMENDATIONS FOR PROJECT. FUNDING RECEIVED 10/31/16. SECURING QUOTES FROM CONTRACTORS. PO'S HAVE BEEN ISSUED. CONTRACTOR IS ON SITE AND HAS BEGUN WORK. INSULATION REMOVAL ON THE OA DUCT FOR AHU-4 SCHEDULED FOR 7/10 TO GET MEASUREMENTS FOR NEW OA DAMPER, AFS, AND TRANSITIONS. UV LIGHTS FOR AHU COILS HAVE BEEN ORDERED. CABLES HAVE BEEN PULLED AND NEW BOXES MOUNTED FOR CONTROLLERS, NEW T-STATS BEING MOUNTED. WEEKLY COORDINATION MEETING ESTABLISHED WITH ALL AFFECTED ENTITIES AND WITH PM GROUP AS THEY HAVE FLOOR WORK BEING DONE IN THE AREA AS WELL.
PATRICK, A. 5146 PLANTADMIN CONSTRUCTION
5640 882000 319163 - 923510
FISHER STUDENT CENTER - REPAIR ROOF OVER LUMINA THEATER
8/30/17 $10.1K SPR RECEIVED 8/10/17. FUNDING REQUESTED 8/10/17. FUNDING RECEIVED 8/14/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5640 FAC ADMIN CLOSEOUT
5794 882000 644550 - 945866
FISHER STUDENT CENTER - REPLACE FIRE RATED DOORS IN ROOM 1006
4/30/18 $12K SPR RECEIVED 2/21/18. FUNDING REQUESTED 2/26/18. FUNDING RECEIVED 3/7/18.
GUINN, T. 5794 PROJ MGMT PROCUREMENT
Project Report
29
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5092 882000 319163 - 923510
FISHER STUDENT CENTER - REPLACE FIRST FLOOR FLOORING
8/1/17 $440.3K SPR RECEIVED 8/18/15. MET WITH SPONSOR 3/3/16. FUNDING REQUESTED 4/8/16. WORK DEFERRED UNTIL SUMMER 2017. SPONSOR PLANS TO MOVE FORWARD. SCHEDULING DESIGN MEETING. PREPARING BID DOCUMENTS. PRE-BID HELD 12/8/16. BID OPENING 1/4/17. FUNDING RECEIVED 1/12/17. FINAL PUNCHLIST ITEMS IN PROGRESS. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5092 FAC ADMIN CLOSEOUT
FISHER STUDENT CENTER - SEAL AND REPAINT COLONNADE
T.B.D. $20.6K SPR RECEIVED 6/30/16. FUNDING REQUESTED 7/29/16. ADDITIONAL SCOPING AND ESTIMATING NEEDED DUE TO DESIGN CHANGE. FUNDING REQUEST UPDATED 10/21/16. ADDITIONAL SCOPING/ESTIMATING UNDERWAY. TESTING TREATING FOR RUST.
SOUTHERLAND, E.
5324 PROJ MGMT SCOPE & ESTIMATING
5811 882000 644550 - 945866
FISHER STUDENT CENTER - WATERPROOF ROOF OVER CAIC OFFICE
4/30/18 $10.4K SPR RECEIVED 3/6/18. FUNDING REQUESTED 3/6/18. FUNDING RECEIVED 3/7/18.
BLUME, J. 5811 PROJ MGMT CONSTRUCTION
5541 882000 162510 - 945866
FISHER UNIVERSITY UNION - DOOR RENOVATIONS IN SUITE 2013
6/15/17 $9.4K SPR RECEIVED 3/16/17. FUNDING REQUESTED 4/4/17. FUNDING RECEIVED 4/26/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5541 FAC ADMIN CLOSEOUT
FISHER UNIVERSITY UNION - ENERGY CONSERVATION MEASURES IMPLEMENTATION
T.B.D. $120K SPR RECEIVED 11/17/15. FUNDING REQUESTED 11/18/15.
MCCARLEY, T. 5175 SPONSOR AWAITING FUNDING
5708 882000 644550 - 945864
FISHER UNIVERSITY UNION - INSTALL ELECTRICAL OUTLETS FOR CHARGING STATIONS
1/15/18 $2.3K SPR RECEIVED 9/27/17. FUNDING REQUESTED 11/14/17. FUNDING RECEIVED 11/30/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5708 FAC ADMIN CLOSEOUT
Project Report
30
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5707 882000 319157 - 945864
FISHER UNIVERSITY UNION - INSTALL ELECTRICAL OUTLETS FOR MONITORS
1/15/18 $3.8K SPR RECEIVED 9/27/17. FUNDING REQUESTED 11/14/17. FUNDING RECEIVED 12/4/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5707 FAC ADMIN CLOSEOUT
5529 882000 161340 - 945865
FISHER UNIVERSITY UNION - INSTALL ELECTRICAL, VOICE, AND DATA DROPS
6/15/17 $4K SPR RECEIVED 3/6/17. FUNDING REQUESTED 4/4/17. FUNDING RECEIVED 5/5/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5529 FAC ADMIN CLOSEOUT
FISHER UNIVERSITY UNION - INSTALL HVAC SYSTEM AT CHICK-FIL-A
T.B.D. T.B.D. SPR RECEIVED 9/12/17. AWAITING A DESIGN PROPOSAL.
WILLIAMS, R. 5670 PROJ MGMT SCOPE & ESTIMATING
5669 882000 644560 - 945966
FISHER UNIVERSITY UNION - INSTALL NEW CONCRETE BIKE PAD
11/30/17 $3K SPR RECEIVED 9/12/17. FUNDING REQUESTED 9/18/17. FUNDING RECEIVED 10/19/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5669 FAC ADMIN CLOSEOUT
5568 882000 174200 - 945866
FISHER UNIVERSITY UNION - INSTALL SECURITY CAMERAS IN ROOM 1005
6/15/17 $4K SPR RECEIVED 4/12/17. FUNDING REQUESTED 4/20/17. FUNDING RECEIVED 5/8/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5568 FAC ADMIN CLOSEOUT
5597 882000 180730 - 923510
FISHER UNIVERSITY UNION - PAINT FASCIA/TRIM FACING COURTYARD
8/15/17 $10K SPR RECEIVED 6/6/17. FUNDING REQUESTED 6/28/17. FUNDING RECEIVED 7/5/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5597 FAC ADMIN CLOSEOUT
5630 882000 180187 - 923590
FISHER UNIVERSITY UNION - PREVENT EROSION AT SOUTHWEST CORNER OF BUILDING
2/28/18 $15.3K SPR RECEIVED 7/24/17. FUNDING REQUESTED 8/11/17. FUNDING RECEIVED 10/3/17. FUNDING UPGRADE 1/2/18 TO COVER LOCATE CHARGE. FUNDING UPGRADE 2/22/18.
BLUME, J. 5630 FAC ADMIN CLOSEOUT
5303 882000 374001 - 945850
FISHER UNIVERSITY UNION - REDESIGN SPACE IN ROOM 1049
8/15/17 $100K SPR RECEIVED 5/19/16. DESIGN FUNDING REQUESTED 9/28/16. FUNDING RECEIVED 10/21/16. PRE-BID HELD 3/27/17. AWARDED PO, WORK TO BEGIN 5/8/17. FINAL PUNCHLIST ITEMS IN PROGRESS. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5303 FAC ADMIN CLOSEOUT
Project Report
31
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5217 882000 318300 - 945860
FISHER UNIVERSITY UNION - RENOVATE SEATING AREA
8/15/17 $5K SPR RECEIVED 2/4/16. PROJECT TITLE AND SCOPE CHANGED 5/24/16. FUNDING REQUESTED 6/2/16. FUNDING RECEIVED 6/8/16. WORK SCHEDULED TO BEGIN 6/27. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5217 FAC ADMIN CLOSEOUT
5634 882000 318300 - 923510
FISHER UNIVERSITY UNION - REPLACE CARPET WITH TILE AT HAWK'S NEST
8/15/17 $30K SPR RECEIVED 7/31/17. FUNDING REQUESTED 7/31/17. FUNDING RECEIVED 8/1/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5634 FAC ADMIN CLOSEOUT
5668 882000 318300 - 945866
FISHER UNIVERSITY UNION - REPLACE WALL AND CEILING COVERING WITH NEW FRP
1/10/18 $27.5K SPR RECEIVED 9/12/17. FUNDING REQUESTED 11/27/17. FUNDING RECEIVED 12/7/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5668 FAC ADMIN CLOSEOUT
5501 882000 180180 - 945860
FRIDAY ANNEX II (PROPOSED) - PRE-DESIGN
6/15/17 $25K SPR RECEIVED AND FUNDING ESTABLISHED 2/15/17. BECKER MORGAN TO DO PRE-DESIGN. RENDERINGS TO BE READY FOR APRIL BOT MEETING. WORKING; EXPECT TO SPEND. BECKER MORGAN IS WORKING ON RENDERINGS. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
HOLSINGER, D. 5501 FAC ADMIN CLOSEOUT
5688 419220 419220 - 923510
FRIDAY HALL - BOILER SEWER MAIN REPL (2015 R&R)
6/1/18 $205K SPR RECEIVED 9/19/17. FUNDING SET UP 9/20/17.
MCCARLEY, T. 5688 PROJ MGMT PROCUREMENT
5769 882000 173160 - 945866
FRIDAY HALL - INTEGRATE ADA PUSH BUTTON WITH LENEL READER
3/15/18 $960 SPR RECEIVED 1/17/18. FUNDING REQUESTED 1/22/18. FUNDING RECEIVED 2/7/18. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5769 FAC ADMIN CLOSEOUT
FRIDAY HALL - REPLACE WIRELESS DOOR MONITORS
T.B.D. T.B.D. SPR RECEIVED 4/11/18. SOUTHERLAND, E.
5853 PROJ MGMT SCOPE & ESTIMATING
Project Report
32
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5702 882000 318500 - 945860
GALLOWAY HALL - HOUSING STUDY AND PRESENTATIONS
12/1/17 $65K SPR RECEIVED 9/26/17. FUNDING REQUESTED 9/26/17. FUNDING RECEIVED 9/28/17. FINAL STUDY REPORT IN REVIEW.
JAMISON, G. 5702 ACSVCS DESIGN
5679 882000 318500 - 945850
GALLOWAY HALL - INSTALL EPOXY IN SHOWER PANS AND WALLS
6/15/18 $38.2K SPR RECEIVED 9/12/17. FUNDING REQUESTED 11/15/17. FUNDING RECEIVED 11/30/17. FUNDING UPGRADE RECEIVED 12/5/17.
HEINS, R. 5679 PROJ MGMT PROCUREMENT
5650 882000 318500 - 945876
GALLOWAY HALL - REPAIR OR REPLACE ROOF LEADERS
7/31/18 $80.9K SPR RECEIVED 8/22/17. REQUESTED FUNDING 10/30/17. FUNDING RECEIVED 4/11/18.
BLUME, J. 5650 PROJ MGMT PROCUREMENT
5567 882000 318500 - 945940
GRAHAM HALL - ADD SIDEWALK AND FILL IN AREAS
6/15/18 $72K SPR RECEIVED 4/12/17. FUNDING REQUESTED 5/10/17. FUNDING RECEIVED 5/11/17.
BLUME, J. 5567 PROJ MGMT CONSTRUCTION
5548 882000 318500 - 945850
GRAHAM HALL - RENOVATION OF BATHROOMS
7/31/18 $300K SPR RECEIVED 3/22/17. FUNDING REQUESTED 3/22/17. FUNDING RECEIVED 3/22/17. FUNDING REDUCED 3/27/17. BID OPENING 4/25/17. NOTICE TO PROCEED AND PRECONSTRUCTION CONFERENCE HELD 5/8/17. PROJECT SUBSTANTIALLY COMPLETE. WORKING ON PUNCHLIST ITEMS. RECEIVED CLOSEOUT DOCUMENTS. WORK IS COMPLETE.
JORDAN, W. 5548 ACSVCS COMPLETE
5651 882000 318500 - 923510
GRAHAM HALL - REPLACE FOUR OUTSIDE WINDOWS
12/31/17 $9.3K SPR RECEIVED 8/22/17. FUNDING REQUESTED 9/13/17. FUNDING RECEIVED 9/22/17. FUNDING UPGRADE RECEIVED 12/6/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5651 FAC ADMIN CLOSEOUT
GRAHAM/HEWLETT CONNECTOR - RE-COVER FRONT DESK AND INSTALL NEW TOP
T.B.D. $5.6K SPR RECEIVED 10/8/15. FUNDING REQUESTED 10/22/15. POSSIBLY DELAYED UNTIL NEXT SPRING.
WILLIAMS, R. 5140 SPONSOR AWAITING FUNDING
Project Report
33
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
GRAHAM/HEWLETT HALLS - REPLACE FIRE DETECTOR DEVICES
T.B.D. T.B.D. SPR RECEIVED 10/23/15. MET WITH FIRE ALARM TECHNICIAN ON 12/22/15. PREPARING SUBMITTAL FOR SCO APPROVAL.
MCCARLEY, T. 5151 PROJ MGMT SCOPE & ESTIMATING
5684 882000 180540 - 945964
GREENE TRACK - LIGHTING IMPROVEMENTS
5/31/18 $200K SPR RECEIVED 9/15/17. FUNDING REQUESTED 10/18/17. FUNDING RECEIVED 10/18/17.
HOLSINGER, D. 5684 ACSVCS DESIGN
5696 438000 438000 - 945966
GREENE TRACK - TRACK RENOVATIONS AND IMPROVEMENTS
8/1/18 $784.4K $1.3M NEW PROJECT SET UP 9/25/17 TO USE CAPITAL FUNDING SOURCE. BEGINNING STAGES OF PRE-DESIGN AND DESIGN SELECTION. CAPITAL FUNDING SETUP WITH CASH ON HAND OF $784,418. WORK IS COMPLETE.
HOLSINGER, D. 5696 ACSVCS CONSTRUCTION
5602 882000 319089 - 945966
GREENE TRACK - TRACK RENOVATIONS AND IMPROVEMENTS INVESTIGATION
3/1/18 $60K SPR RECEIVED 6/16/17. INITIAL $60,000 FUNDED 6/19/17. PROJECT KICKOFF 7/5/17. LIQUIDATED BALANCE OF SPECIAL PROJECT 1/6/18 SO FUNDING CAN BE USED IN NEW CAPITAL PROJECT.
HOLSINGER, D. 5602 FAC ADMIN CLOSEOUT
GREENE TRACK: ESTIMATE FOR PORTAL/GATEWAY BUILDING
T.B.D. $1.1M SPR RECEIVED 8/5/15. FUNDING REQUESTED 10/08/15.
MCCARLEY, T. 5086 SPONSOR AWAITING FUNDING
GROUNDS - CONSTRUCT NEW SURFACE PARKING LOT
T.B.D. T.B.D. SPR RECEIVED 10/8/15. WILL BE COMBINED INTO CAPITAL PROJECT.
MCCARLEY, T. 5141 PROJ MGMT SCOPE & ESTIMATING
5601 882000 318500 - 945980
GROUNDS - FIELD INVESTIGATIONS FOR NEW HOUSING BUILDINGS
8/31/17 $60K SPR RECEIVED 6/14/17. FUNDING REQUESTED 6/14/17. FIELD INVESTIGATIONS COMPLETED IN SEPTEMBER 2017. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
JAMISON, G. 5601 FAC ADMIN CLOSEOUT
5278 882000 121100 - 945864
GROUNDS - INSTALL DIRECT POWER SUPPLY TO RAIN COLLECTION SITE
6/15/17 $22.6K SPR RECEIVED 4/7/16. FUNDING REQUESTED 4/20/16. FUNDING RECEIVED 5/26/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5278 FAC ADMIN CLOSEOUT
Project Report
34
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
GROUNDS - INSTALL NEW VERIZON FIBER CABLE FEED AT MONOPOLE
T.B.D. T.B.D. SPR RECEIVED 12/19/17. KIGHT, R. 5764 PROJ MGMT SCOPE & ESTIMATING
5654 882000 217334 - 932990
GROUNDS - INSTALL STANCHIONS FOR BANNERS
10/31/17 $25K SPR RECEIVED 8/22/17. FUNDING REQUESTED 9/18/17. FUNDING RECEIVED 9/18/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
KIGHT, R. 5654 FAC ADMIN CLOSEOUT
GROUNDS - MAIN CAMPUS: REPLACE CALLBOX POLES
T.B.D. $8.5K SPR RECEIVED 3/14/18. FUNDING REQUESTED 4/6/18.
BLUME, J. 5820 SPONSOR AWAITING FUNDING
5647 GROUNDS - MONOPOLE - AT&T EQUIPMENT UPGRADES (2017)
11/30/17 $0 SPR RECEIVED 8/15/17. PROJECT TO BE FUNDED BY AT&T. REQUIRES SCO OVERSIGHT SO PM NUMBER ASSIGNED.
MCCARLEY, T. 5647 PROJ MGMT CONSTRUCTION
CI13-007 443783 443783 - 945860
GROUNDS - OUTDOOR ENHANCEMENT MASTER PLAN
12/31/17 $8.1M $8.1M DESIGN CONTRACT HAS BEEN AWARDED. WORK IS COMPLETE ON BASEBALL PRACTICE FIELD. BUILDING 4D AWARDED TO BARBOZA 8/4/15. 4D WORK WAS COMPLETED 3/14/16.. LIGHTING CONSTRUCTION COMPLETE. 7C CONTRACT AWARDED 12/21/15 AND BUILDING IS UNDER CONSTRUCTION. FIELDS AWARDED TO SPORTS CONSTRUCTION MANAGEMENT AND UNDER CONSTRUCTION.FIELDS ARE ON TRACK TO FINISH IN JUNE 2017. MACK IS PRICING OUT NEW FENCING, WILL BE DONE AS SEPARATE SPECIAL PROJECT. BOB MYERS WILL BE PM FOR BUILDING 7D. SCO PLAN REVIEW FOR 7D UNDERWAY.
COLEMAN, I. 4743 ACSVCS CONSTRUCTION
5603 GROUNDS - RE-FEED SUBSTATION ON LIONFISH DRIVE (DUKE ENERGY PROJECT)
8/1/17 $0 SPR RECEIVED 6/20/17. PROJECT PAID FOR BY DUKE ENERGY. OVERSEEN BY STEVE PICKARD.
MCCARLEY, T. 5603 PROJ MGMT CONSTRUCTION
Project Report
35
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5620 882000 319240 - 945950
GROUNDS - REPAIR POTHOLES THROUGHOUT CAMPUS
10/15/17 $16.5K SPR RECEIVED 7/10/17. FUNDING REQUESTED 7/24/17. FUNDING RECEIVED 8/14/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5620 FAC ADMIN CLOSEOUT
5502 424000 424000 - 945966
GROUNDS - SRC WALTON DR FAC IMPROV (OUTDOOR ENHANCEMENT PLAN PHASE II)
6/30/18 $2.3M $3.6M PROJECT ESTABLISHED 2/16/17. AWAITING CAPITAL FUNDING SETUP. CAPITAL FUNDING RECEIVED 2/21/17. BUDGET INCREASED BY $1,003,662.60 FROM UNEXPENDED BOND PROCEEDS ON 11/20/17.
COLEMAN, I. 5502 ACSVCS CONSTRUCTION
4919 882000 212139 - 945966
GROUNDS - SUNDIAL INSTALLATION
4/30/15 $11K SPR RECEIVED 10/24/14. FUNDING REQUESTED 12/9/14. FUNDING RECEIVED 12/18/14. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 4919 FAC ADMIN CLOSEOUT
HAMILTON DRIVE - ADVANCE PLANNING FOR INTERSECTION IMPROVEMENTS AT RIEGEL ROAD
T.B.D. T.B.D. SPR RECEIVED 3/5/18. JAMISON, G. 5809 ACSVCS SCOPE & ESTIMATING
HANOVER HALL - DESIGN ELEVATOR REPAIR/REPLACEMENT
T.B.D. $30K SPR RECEIVED 3/26/18. FUNDING REQUESTED 4/10/18.
SINGLEY, D. 5838 SPONSOR AWAITING FUNDING
HANOVER HALL - INSTALL NEW HVAC IN MEN'S BASKETBALL LOCKER ROOM
T.B.D. T.B.D. SPR RECEIVED 9/8/17. AWAITING A DESIGN PROPOSAL.
WILLIAMS, R. 5660 PROJ MGMT SCOPE & ESTIMATING
5798 882000 152030 - 945866
HANOVER HALL - INSTALL RETRACTABLE GYM DIVIDER
6/15/18 $20K SPR RECEIVED 2/21/18. FUNDING REQUESTED 2/28/18. FUNDING RECEIVED 3/21/18.
SINGLEY, D. 5798 PROJ MGMT PROCUREMENT
HANOVER HALL - REPAIR DOORS T.B.D. T.B.D. SPR RECEIVED 3/26/18. SINGLEY, D. 5834 PROJ MGMT SCOPE & ESTIMATING
Project Report
36
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5589 882000 180187 - 923510
HANOVER HALL - REPAIR WALL TILE IN CORRIDOR 4
6/15/17 $6K SPR RECEIVED 5/26/17. FUNDING REQUESTED 5/31/17. FUNDING RECEIVED 5/31/17. CLOSEOUT IS UNDERWAY.
MCCARLEY, T. 5589 FAC ADMIN CLOSEOUT
HANOVER HALL - RESTROOM UPGRADES
T.B.D. $35K SPR RECEIVED 3/26/18. REQUESTING FUNDING 4/10/18.
SINGLEY, D. 5836 SPONSOR AWAITING FUNDING
5549 882000 318500 - 945850
HEWLETT HALL - RENOVATION OF BATHROOMS
7/31/18 $300K SPR RECEIVED 3/22/17. FUNDING REQUESTED 3/22/17. FUNDING RECEIVED 3/22/17. FUNDING REDUCED 3/27/17. BID OPENING 4/25/17. NOTICE TO PROCEED AND PRECONSTRUCTION CONFERENCE HELD 5/8/17. PROJECT SUBSTANTIALLY COMPLETE. WORKING ON PUNCHLIST ITEMS. RECEIVED CLOSEOUT DOCUMENTS. WORK IS COMPLETE.
JORDAN, W. 5549 ACSVCS COMPLETE
HOGGARD HALL - INSTALL CARD SWIPE ACCESS IN SERVER WING
T.B.D. $3.1K SPR RECEIVED 2/26/18. FUNDING REQUESTED 4/3/18.
SINGLEY, D. 5807 SPONSOR AWAITING FUNDING
5626 882000 271603 - 945865
HOGGARD HALL - INSTALL FIBER OPTIC STRAND FROM HOGGARD TO CIS
8/31/17 $21.2K SPR RECEIVED 7/24/17. FUNDING REQUESTED 7/24/17. FUNDING RECEIVED 8/2/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5626 FAC ADMIN CLOSEOUT
HOGGARD HALL - RENOVATIONS TO ROOM 279
T.B.D. $14K SPR RECEIVED 2/7/18. FUNDING REQUESTED 3/22/18.
SINGLEY, D. 5788 SPONSOR AWAITING FUNDING
5727 882000 180540 - 945864
HOGGARD HALL - REPLACE WIRELESS EXTERNAL READERS
12/31/17 $9K SPR RECEIVED 10/13/17. FUNDING REQUESTED FROM ANNUAL ALLOCATIONS VIA BUDGET OFFICE 10/13/17. FUNDING RECEIVED 10/13/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
MULLINS, K. 5727 FAC ADMIN CLOSEOUT
Project Report
37
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
HOGGARD HALL -INSTALL DOORS AT TOP OF STAIRS
T.B.D. T.B.D. SPR RECEIVED 2/7/18. SINGLEY, D. 5787 PROJ MGMT SCOPE & ESTIMATING
5132 882000 318500 - 945866
HONORS HOUSE- REPLACE BATHROOM PARTITIONS
7/31/17 $24K SPR RECEIVED 10/8/15. FUNDING REQUESTED 10/22/15. FUNDING RECEIVED 12/15/16. WORK SCHEDULED 7/17/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5132 FAC ADMIN CLOSEOUT
5652 882000 318500 - 945876
HOUSING AND RESIDENCE LIFE OFFICE - REPLACE ROOF
6/15/18 $33.6K SPR RECEIVED 8/22/17. FUNDING REQUESTED 10/2/17. FUNDING RECEIVED 12/4/17.
BLUME, J. 5652 PROJ MGMT PROCUREMENT
5115 882000 318500 - 945850
HOUSING MULTIPLE BUILDINGS - HOUSING R&R PHASE I, FY16
8/12/17 $486.4K SPR RECEIVED 9/18/15. SCOPE MEETINGS ARE CONTINUING, FIRST COST ESTIMATE IS $7.5M. CM@R PRE-BID SCHEDULED FOR 11/10/15. DESIGN FUNDING IDENTIFIED 12/8/15. CM@R RECOMMENDATION WILL BE PRESENTED TO BOT IN MID-JANUARY. BALFOUR BEATTY SELECTED AS CM@R. FUNDING INCREASED 6/15/16. VANITY REPLACEMENTS IN PROGRESS DURING SUMMER 2016 BREAK. FUNDING UPGRADED 7/15/16 AND 8/15/16. PROJECT NEARING CLOSEOUT. AWAITING ARCHITECT'S PAPERWORK. PREPARING FOR CLOSEOUT.
JORDAN, W. 5115 ACSVCS CONSTRUCTION
5093 882000 318300 - 945866
HUB BUILDING - INFRASTRUCTURE - PHASE I
6/30/17 $406.3K SPR RECEIVED 8/19/15. CONSTRUCTION COMPLETE. ACCEPTED 6/9/17. PUNCHLIST COMPLETION IS IN PROGRESS. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SEIFERT, L. 5093 FAC ADMIN CLOSEOUT
HURST DRIVE - ADVANCE PLANNING FOR ROAD EXTENSION TO RIEGEL ROAD
T.B.D. T.B.D. SPR RECEIVED 3/5/18. JAMISON, G. 5810 ACSVCS SCOPE & ESTIMATING
Project Report
38
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5615 429000 429000 - 945950
HURST PARKING LOT - CONSTRUCTION
6/30/18 $4.5M $4.5M AUTHORIZATION RECEIVED JUNE 2017. SET UP IN AIM 6/29/17. FUNDING SET UP IN AIM/BANNER 8/21/17. TREE CLEARING COMPLETE IN FEB 2018, PARKING LOTS COMPLETION PLANNED AUGUST 2018. IN CONSTRUCTION AND DESIGN PHASES. ADDITIONAL FUNDING RECEIVED 2/12/18, UPDATED BUDGET.
JAMISON, G. 5615 ACSVCS CONSTRUCTION
5808 882000 319098 - 945810
INDOOR HITTING FACILITY - ADDITIONAL CONSTRUCTION CHANGE ORDERS
5/31/18 $25K SPR RECEIVED 2/26/18. FUNDING REQUESTED 3/15/18. FUNDING RECEIVED 3/15/18.
COLEMAN, I. 5808 ACSVCS PROCUREMENT
INDOOR HITTING FACILITY - COVER AND PAINT INTERIOR WALLS
T.B.D. T.B.D. SPR RECEIVED 4/11/18. SINGLEY, D. 5857 PROJ MGMT SCOPE & ESTIMATING
5129 882000 318500 - 945866
INNOVATION HOUSE - REPLACE BATHROOM PARTITIONS
7/31/17 $24K SPR RECEIVED 10/8/15. FUNDING REQUESTED 10/22/15. FUNDING RECEIVED 12/15/16. WORK SCHEDULED 7/17/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5129 FAC ADMIN CLOSEOUT
5517 882000 371020 - 945966
INTRAMURAL FIELDS - INSTALL PERIMETER FENCING
8/31/17 $300K SPR RECEIVED 3/6/17. FUNDING REQUESTED 7/11/17. FUNDING RECEIVED 7/12/17.
COLEMAN, I. 5517 ACSVCS CONSTRUCTION
INTRAMURAL FIELDS - INSTALL TWO PADS FOR GOAL STORAGE
T.B.D. $11.3K SPR RECEIVED 12/15/17. FUNDING REQUESTED 2/27/18.
SINGLEY, D. 5761 SPONSOR AWAITING FUNDING
5760 882000 319242 - 945966
ISAAC BEAR EARLY COLLEGE - RELOCATE SHUTTLE SHELTER AND INSTALL CONCRETE PAD
1/31/18 $14K SPR RECEIVED 12/14/17. SINGLEY, D. 5760 PROJ MGMT CONSTRUCTION
Project Report
39
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5658 882000 218024 - 945866
ISAAC BEAR EARLY COLLEGE HIGH SCHOOL - RELOCATE CANOPY AND ADD PARKING SPACES
12/20/17 $50K SPR RECEIVED 8/30/17. FUNDING REQUESTED 8/30/17. FUNDING RECEIVED 9/5/17. WORK 95% COMPLETE.
HOLSINGER, D. 5658 ACSVCS CONSTRUCTION
5784 882000 180187 - 945869
JAMES HALL - INSTALL CARD READER AT ELEVATOR
5/15/18 $4K SPR RECEIVED 2/5/18. FUNDING REQUESTED 3/22/18. FUNDING RECEIVED 6/15/18.
MULLINS, K. 5784 PROJ MGMT PROCUREMENT
5739 882000 275100 - 945863
JAMES HALL - INSTALL EXHAUST FAN IN BREAK ROOM 138
12/22/17 $4.2K SPR RECEIVED 10/30/17. FUNDING REQUESTED 11/22/17. FUNDING RECEIVED 11/30/17. WORK TO COMPLETE FIRST WEEK OF JANUARY. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
WILLIAMS, R. 5739 FAC ADMIN CLOSEOUT
5609 882000 161330 - 945950
JAMES HALL - INSTALL GOLF CART PAD BEHIND BUILDING
10/31/17 $6.5K SPR RECEIVED 6/28/17. FUNDING REQUESTED 7/13/17. FUNDING RECEIVED 7/24/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5609 FAC ADMIN CLOSEOUT
5745 882000 161500 - 945850
JAMES HALL - REDESIGN SUITE 121
6/15/18 $21K SPR RECEIVED 11/2/17. FUNDING REQUESTED 1/22/18. FUNDING RECEIVED 3/26/18.
BLUME, J. 5745 PROJ MGMT PROCUREMENT
5610 882000 161330 - 945850
JAMES HALL - RENOVATE ROOMS 127 AND 128
2/28/18 $30.5K SPR RECEIVED 6/28/17. FUNDING REQUESTED 7/14/17. REVISED FUNDING REQUEST SENT 11/9/17. FUNDING RECEIVED 11/21/17. FUNDING UPGRADE RECEIVED 1/3/18. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5610 FAC ADMIN CLOSEOUT
5789 882000 161330 - 945850
JAMES HALL - RENOVATIONS TO ROOM 142 AND 148
5/1/18 $14K SPR RECEIVED 2/7/18. FUNDING REQUESTED 2/19/18. FUNDING RECEIVED 2/21/18.
BLUME, J. 5789 PROJ MGMT CONSTRUCTION
5692 419260 419260 - 923510
JAMES HALL - ROOF LEADER REPAIRS (2015 R&R)
6/1/18 $50.2K SPR RECEIVED 9/19/17. FUNDING SET UP 9/20/17.
MCCARLEY, T. 5692 PROJ MGMT PROCUREMENT
Project Report
40
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5461 882000 161330 - 945865
JAMES HALL - UPDATE AV EQUIPMENT IN ROOM 102
6/15/17 $26K SPR RECEIVED 1/13/17. FUNDING REQUESTED 2/21/17. FUNDING RECEIVED 2/27/17. BIDDING BY PURCHASING UNDERWAY. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5461 FAC ADMIN CLOSEOUT
KENAN AUDITORIUM - DESIGN FIRE BARRIER IN ROOMS 1114/2118
T.B.D. $30K SPR RECEIVED 4/4/18. FUNDING REQUESTED 4/5/18.
MULLINS, K. 5844 SPONSOR AWAITING FUNDING
5431 882000 121750 - 945866
KENAN AUDITORIUM - INSTALL ORCHESTRA PIT COVER
5/15/17 $23K SPR RECEIVED 11/3/16. FUNDING REQUESTED 11/4/16. FUNDING RECEIVED 11/18/16. WORK SCHEDULED WEEK OF 4/10/17. EXPECT TO COMPLETE. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5431 FAC ADMIN CLOSEOUT
KENAN AUDITORIUM - REPAIR ENTRY STEPS
T.B.D. T.B.D. SPR RECEIVED 2/2/18. AWAITING QUOTE FROM CONTRACTOR.
WILLIAMS, R. 5781 PROJ MGMT SCOPE & ESTIMATING
5554 882000 218027 - 945860
KENAN HALL - FILM STUDIES PRE-DESIGN
6/15/18 $92K SPR RECEIVED 3/27/17. FUNDING RECEIVED 3/27/17. MEETING WITH FILM STUDIES 4/5/17. BECKER MORGAN CONTINUED PRE-DESIGN AND COST ESTIMATE. ADDITIONAL DESIGN TO INCLUDE KENAN AUDITORIUM EXPANSION. LIQUIDATED BALANCE FROM 319290. AWAITING NEW FUNDING SOURCE.
HOLSINGER, D. 5554 ACSVCS DESIGN
KENAN HALL - INSTALL CANOPIES IN COURTYARD
T.B.D. T.B.D. SPR RECEIVED 4/11/18. MULLINS, K. 5850 PROJ MGMT SCOPE & ESTIMATING
KENAN HALL - REPAIR DOWNSPOUT AND COLUMN
T.B.D. T.B.D. SPR RECEIVED 4/11/18. MULLINS, K. 5848 PROJ MGMT SCOPE & ESTIMATING
Project Report
41
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5540 882000 180180 - 923510
KENAN HOUSE - ANNUAL MAINTENANCE
6/15/17 $45K SPR RECEIVED 3/16/17. FUNDING ESTABLISHED 3/16/17. TREE TRIMMING APRIL 10-14. FUNDING UPGRADE 4/19/17. FUNDING UPGRADE 5/17/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5540 FAC ADMIN CLOSEOUT
5194 882000 218003 - 945871
KENAN HOUSE - COURTYARD REFURBISHMENT
11/15/16 $29K SPR RECEIVED 12/23/15. FUNDING RECEIVED 10/6/16.
SINGLEY, D. 5194 PROJ MGMT CONSTRUCTION
4914 882000 680100 - 945850
KENAN HOUSE - REPAIRS & IMPROVEMENTS
6/30/15 $15K SPR GENERATED 10/17/14. FUNDING RECEIVED 10/21/14.WORK IS UNDERWAY. WORK IS COMPLETE.
MCCARLEY, T. 4914 PROJ MGMT COMPLETE
KENAN HOUSE - REPLACE HEATING HOT WATER BOILER
T.B.D. T.B.D. SPR RECEIVED 9/15/15. PHYSICAL PLANT HAS COMPLETED SOME INITIAL WORK PRIOR TO PROJECT FUNDING. CURRENTLY EXAMINING POSSIBLE CHANGES IN VENTING FIRST.
WILLIAMS, R. 5108 PROJ MGMT SCOPE & ESTIMATING
5193 882000 218003 - 945966
KENAN HOUSE - SECURITY FENCE MODIFICATIONS
11/15/16 $10K SPR RECEIVED 12/23/15. FUNDING RECEIVED 10/6/16.
SINGLEY, D. 5193 PROJ MGMT CONSTRUCTION
SP13-107 883066 680100 - 945850
KENAN HOUSE - SOLARIUM REFURBISHMENT STUDY
8/1/14 $125K SPR RECEIVED 1/11/13. FUNDING RECEIVED 4/26/13. PREBID CONDUCTED 11/19/13. PREWORK CONFERENCE CONDUCTED 1/7/14. WORK IS UNDERWAY. ADDITIONAL FUNDING RECEIVED 7/14/14. SCOPE OF WORK HAS BEEN INCREASED. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 4523 FAC ADMIN CLOSEOUT
5744 882000 121981 - 923510
KING HALL - CLEAN AND REPAIR EXTERIOR
3/31/18 $24.6K SPR RECEIVED 11/2/17. FUNDING REQUESTED 1/22/18. FUNDING RECEIVED 2/6/18. FUNDING UPGRADE RECEIVED 3/13/18.
GUINN, T. 5744 PROJ MGMT PROCUREMENT
Project Report
42
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5690 419240 419240 - 923510
KING HALL - HVAC AHU REPL (2015 R&R)
6/1/18 $265K SPR RECEIVED 9/19/17. FUNDING SET UP 9/20/17.
MCCARLEY, T. 5690 PROJ MGMT PROCUREMENT
KING HALL - MODIFICATIONS TO ROOMS 105, 106, 106A, 106H
T.B.D. $10.7K PROJECT REACTIVATED 12/14/16. DESIGN FUNDING REQUESTED 1/12/17.
WILLIAMS, R. 4822 SPONSOR AWAITING FUNDING
5806 882000 121981 - 945850
KING HALL - RENOVATIONS TO ROOMS 104B&C, 105
6/15/18 $20K SPR RECEIVED 2/21/18. MET WITH SPONSOR 3/1/18. FUNDING REQUESTED 4/5/18. DARKROOM WORK CANNOT BE COMPLETED THIS FISCAL YEAR. FUNDING RECEIVED 4/6/18.
SOUTHERLAND, E.
5806 PROJ MGMT PROCUREMENT
5110 420205 420205 - 945863
KING HALL - REPLACE ALL AIR HANDLERS
8/31/17 $290K $290K SPR RECEIVED 9/15/15. R&R FUNDING ESTABLISHED 1/30/17.
WILLIAMS, R. 5110 PROJ MGMT CONSTRUCTION
KRESEGE GREENHOUSE - PAINT ROOF
T.B.D. T.B.D. SPR RECEIVED 3/23/18. HEINS, R. 5832 PROJ MGMT SCOPE & ESTIMATING
5748 882000 180730 - 945864
KRESEGE GREENHOUSE - SERVICE OR REPLACE ELECTRIC MOTOR
4/15/18 $11.6K SPR RECEIVED 11/13/17. FUNDING REQUESTED 2/14/18. FUNDING RECEIVED 2/15/18.
GUINN, T. 5748 PROJ MGMT PROCUREMENT
LANDSCAPING NURSERY - INSTALL CONCRETE BARRIERS FOR LOOSE MATERIAL STORAGE
T.B.D. $4.2K SPR RECEIVED 3/28/16. FUNDING REQUESTED 4/27/16.
MCCARLEY, T. 5264 SPONSOR AWAITING FUNDING
LEUTZE HALL - INVESTIGATE AND REPAIR COOLING TOWER #2
T.B.D. T.B.D. SPR RECEIVED 8/10/16. AWAITING PLANS FROM DESIGN ENGINEER. PREPARING ESTIMATE. WORK TO BE PERFORMED IN R&R PROJECT PM4738.
WILLIAMS, R. 5366 PROJ MGMT SCOPE & ESTIMATING
Project Report
43
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
LEUTZE HALL - PAINT FIRST FLOOR FOYER AND STAIRWELL
T.B.D. T.B.D. SPR RECEIVED 4/11/18. MULLINS, K. 5847 PROJ MGMT SCOPE & ESTIMATING
5582 882000 121155 - 945850
LEUTZE HALL - RELOCATE DOOR IN SUITE 222
6/15/17 $4K SPR RECEIVED 5/17/17. FUNDING REQUESTED 5/19/17. FUNDING RECEIVED 5/26/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5582 FAC ADMIN CLOSEOUT
5331 882000 121600 - 923510
LEUTZE HALL - REMOVE WALLPAPER AND PAINT ROOM 268
5/31/17 $1.2K SPR RECEIVED 6/30/16. FUNDING REQUESTED 7/14/16. FUNDING RECEIVED 4/19/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5331 FAC ADMIN CLOSEOUT
LEUTZE HALL - RENOVATE ROOM 125 (FLOOR, FURNITURE)
T.B.D. T.B.D. SPR RECEIVED 4/11/18. MULLINS, K. 5851 PROJ MGMT SCOPE & ESTIMATING
LOT A - REPAIR CRACKED STORMWATER LINE
T.B.D. $34.6K SPR RECEIVED 2/21/17. FUNDING REQUESTED 2/22/17. REVISED FUNDING REQUEST SENT 4/4/17.
BLUME, J. 5512 SPONSOR AWAITING FUNDING
LOT EE - FEASIBILITY STUDY FOR CONNECTING LOT EE TO SUITE SERVICES LOOP
T.B.D. T.B.D. SPR RECEIVED 10/28/16. MORGAN, M. 5430 FACILITIES SCOPE & ESTIMATING
5762 882000 319248 - 945960
LOT EE- LOT EXPANSION PRE-DESIGN
5/31/18 $35K SPR RECEIVED 12/18/17. FUNDING REQUESTED 1/12/18. FUNDING RECEIVED 1/22/18.
JAMISON, G. 5762 ACSVCS DESIGN
5619 882000 319240 - 945950
LOT O - REPAIR/REPLACE CURBING
10/15/17 $10.4K SPR RECEIVED 7/10/17. FUNDING REQUESTED 7/24/17. FUNDING RECEIVED 8/14/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
BLUME, J. 5619 FAC ADMIN CLOSEOUT
Project Report
44
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5790 882000 319240 - 945950
LOT P - REPAIR ASPHALT 3/31/18 $9.6K SPR RECEIVED 2/12/18. FUNDING REQUESTED 2/19/18. FUNDING RECEIVED 2/28/18.
BLUME, J. 5790 PROJ MGMT COMPLETE
5735 882000 319248 - 945966
LOTS 1A/1B: ELECTRICAL AND STORMWATER MANAGEMENT UPGRADES
2/1/18 $250K SPR RECEIVED 10/27/17. FUNDING REQUESTED 10/27/17. FUNDING RECEIVED 10/27/17. ELECTRICAL UPGRADES AWARDED DECEMBER 2017.
JAMISON, G. 5735 ACSVCS CONSTRUCTION
5680 882000 271609 - 945865
MCNEILL HALL - AV RENOVATIONS IN ROOM 1005
2/28/18 $14K SPR RECEIVED 9/12/17. FUNDING REQUESTED 10/11/17. FUNDING RECEIVED 11/30/17. MET WITH SPONSOR 1/11/18.
SOUTHERLAND, E.
5680 PROJ MGMT CONSTRUCTION
5801 882000 152030 - 945866
MCNEILL HALL - INSTALL WIRELESS CARD READERS
6/15/18 $10K SPR RECEIVED 2/21/18. FUNDING REQUESTED 2/28/18. FUNDING RECEIVED 3/14/18.
SINGLEY, D. 5801 PROJ MGMT PROCUREMENT
5799 882000 152030 - 945866
MCNEILL HALL - REPAIR AND UPGRADE FOLDING WALL IN ROOM 1051
6/15/18 $20K SPR RECEIVED 2/21/18. FUNDING REQUESTED 2/28/18. FUNDING RECEIVED 3/21/18.
SINGLEY, D. 5799 PROJ MGMT PROCUREMENT
5616 882000 1AP100 - 945850
MCNEILL HALL - REPAIRS AND IMPROVEMENTS
6/15/18 $60K SPR RECEIVED 6/29/17. FUNDING REQUESTED 6/30/17. FUNDING RECEIVED 7/12/17. FUNDING UPGRADE RECEIVED 10/30/17.
BLUME, J. 5616 PROJ MGMT CONSTRUCTION
5804 882000 152030 - 945866
MCNEILL HALL - ROOM RESERVATION MONITORS PHASE 1
6/15/18 $20K SPR RECEIVED 2/21/18. FUNDING REQUESTED 2/28/18. FUNDING RECEIVED 3/21/18.
SINGLEY, D. 5804 PROJ MGMT PROCUREMENT
5805 882000 152030 - 945866
MCNEILL HALL - ROOM RESERVATION MONITORS PHASE 2
6/15/18 $20K SPR RECEIVED 2/21/18. FUNDING REQUESTED 2/28/18. FUNDING RECEIVED 3/21/18.
SINGLEY, D. 5805 PROJ MGMT PROCUREMENT
Project Report
45
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5803 882000 152030 - 945864
MCNEILL HALL - UPGRADES IN ROOM 1052
6/15/18 $15K SPR RECEIVED 2/21/18. FUNDING REQUESTED 2/28/18. FUNDING RECEIVED 3/21/18.
SINGLEY, D. 5803 PROJ MGMT PROCUREMENT
5648 882000 218024 - 945810
MODULAR BUILDING - INSTALL BUILDING AND PROVIDE BUILDING SERVICES
11/30/17 $150K SPR RECEIVED 8/16/17. FUNDING REQUESTED 8/16/17. FUNDING RECEIVED 8/16/17.
SINGLEY, D. 5648 PROJ MGMT CONSTRUCTION
5467 882000 180180 - 945863
MORTON HALL - INSTALL AIR HANDLING UNIT
6/15/17 $47K SPR RECEIVED 1/26/17. FUNDING ESTABLISHED 1/27/17. FUNDING DECREASE 3/16/17. FUNDING DECREASE 3/27/17. FUNDING DECREASE 4/6/17. FUNDING DECREASE 5/17/17. FUNDING DECREASE 5/18/17. CLOSEOUT IS UNDERWAY.
WILLIAMS, R. 5467 FAC ADMIN CLOSEOUT
5756 882000 121981 - 923510
MORTON HALL - REPLACE CARPET AND VCT THROUGHOUT BUILDING
2/15/18 $100.8K SPR RECEIVED 12/8/17. FUNDING REQUESTED 12/13/17. FUNDING RECEIVED 12/14/17. WORK IS UNDERWAY. 75% COMPLETE.
WILLIAMS, R. 5756 PROJ MGMT CONSTRUCTION
5697 882000 121981 - 945866
MORTON HALL - REPLACE CEILING GRID AND VCT TILES THROUGHOUT
5/31/18 $162K SPR RECEIVED 9/25/17. BIDS DUE FOR PRICING PURPOSES 2/21/18. FUNDING REQUESTED 2/16/18. FUNDING RECEIVED 2/20/18. PO ISSUED TO AG CONSTRUCTION; WORK STARTED 3/5/18. 40% COMPLETE.
WILLIAMS, R. 5697 PROJ MGMT CONSTRUCTION
5743 882000 121981 - 945861
MORTON HALL - REPLACE EXTERIOR WINDOWS
6/15/18 $195K SPR RECEIVED 11/2/17. FUNDING REQUESTED 12/7/17. FUNDING RECEIVED 12/12/17.
BLUME, J. 5743 PROJ MGMT CONSTRUCTION
5705 882000 173160 - 945866
MORTON HALL - REPLACE FIRE DOOR HARDWARE
6/15/18 $12.5K SPR RECEIVED 9/27/17. FUNDING REQUESTED 12/20/17. FUNDING RECEIVED 2/7/18.
BLUME, J. 5705 PROJ MGMT PROCUREMENT
Project Report
46
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5698 882000 121981 - 923510
MORTON HALL - REPLACE TORN STAIRWELL THREADS
4/15/18 $24K SPR RECEIVED 9/25/17. FUNDING REQUESTED 10/27/17. FUNDING RECEIVED 11/2/17. WORK IS COMPLETE.
SOUTHERLAND, E.
5698 PROJ MGMT COMPLETE
R&R 413220 413220 - 945863
MORTON HALL - UPGRADE CHILLER CONTROLS
6/30/15 $80K SPR GENERATED 12/20/13. R&R FUNDING ESTABLISHED 12/20/13.
MCCARLEY, T. 4738 PROJ MGMT PROCUREMENT
5822 882000 180187 - 923590
MOTOR POOL - REPAIR METAL BRACING AT GAS PUMPS
6/15/18 $12K SPR RECEIVED 3/14/18. FUNDING REQUESTED 3/26/18. FUNDING RECEIVED 4/3/18.
HEINS, R. 5822 PROJ MGMT PROCUREMENT
5317 882000 319080 - 945866
MULTIPLE BUILDINGS (ATHLETICS) - INSTALL NEW LENEL KEYPADS
12/31/18 $16.5K SPR RECEIVED 5/31/16. FUNDING REQUESTED 7/20/17. FUNDING RECEIVED 8/9/17. FUNDING UPGRADE RECEIVED 9/14/17.
SOUTHERLAND, E.
5317 PROJ MGMT CONSTRUCTION
5518 882000 318500 - 923510
MULTIPLE BUILDINGS (HOUSING) - 2017 SUMMER PAINTING CONTRACT 1
7/31/17 $31.4K SPR RECEIVED 3/6/17. FUNDING REQUESTED 3/10/17. FUNDING RECEIVED 3/17/17. PRE-BID HELD 4/6/17. FUNDING UPGRADE RECEIVED 5/9/17. AWARDED PO. WORK IS COMPLETE.
SOUTHERLAND, E.
5518 FAC ADMIN CLOSEOUT
5519 882000 318500 - 923510
MULTIPLE BUILDINGS (HOUSING) - 2017 SUMMER PAINTING CONTRACT 2
7/31/17 $12.4K SPR RECEIVED 3/6/17. FUNDING REQUESTED 3/10/17. FUNDING RECEIVED 3/17/17. PRE-BID HELD 4/6/17. FUNDING UPGRADE RECEIVED 5/9/17. AWARDED PO. FUNDING REDUCED 6/19/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5519 FAC ADMIN CLOSEOUT
5520 882000 318515 - 923510
MULTIPLE BUILDINGS (HOUSING) - 2017 SUMMER PAINTING CONTRACT 3
7/31/17 $27.2K SPR RECEIVED 3/6/17. FUNDING REQUESTED 3/10/17. FUNDING RECEIVED 3/17/17. PRE-BID HELD 4/6/17. AWARDED PO. FUNDING UPGRADE RECEIVED 8/24/17. WORK COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5520 FAC ADMIN CLOSEOUT
Project Report
47
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5521 882000 318505 - 923510
MULTIPLE BUILDINGS (HOUSING) - 2017 SUMMER PAINTING CONTRACT 4
7/31/17 $25K SPR RECEIVED 3/6/17. FUNDING REQUESTED 3/10/17. FUNDING RECEIVED 3/17/17. PRE-BID HELD 4/6/17. AWARDED PO. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5521 FAC ADMIN CLOSEOUT
5522 882000 318510 - 923510
MULTIPLE BUILDINGS (HOUSING) - 2017 SUMMER PAINTING CONTRACT 5
7/31/17 $40.3K SPR RECEIVED 3/6/17. FUNDING REQUESTED 3/10/17. FUNDING RECEIVED 3/17/17. PRE-BID HELD 4/6/17. AWARDED PO. FUNDING UPGRADE 6/19/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5522 FAC ADMIN CLOSEOUT
MULTIPLE BUILDINGS (HOUSING) - HVAC RECOMMISSIONING
T.B.D. T.B.D. SPR RECEIVED 3/6/17. WILLIAMS, R. 5525 PROJ MGMT SCOPE & ESTIMATING
MULTIPLE BUILDINGS (HOUSING) - JET ALL SHOWER AND SINK DRAINS TO CLEAR PIPING
T.B.D. T.B.D. SPR RECEIVED 1/2/18. HEINS, R. 5767 PROJ MGMT SCOPE & ESTIMATING
5638 882000 318500 - 921990
MULTIPLE BUILDINGS (HOUSING) - PRE-DESIGN FOR NEW HOUSING BUILDINGS
11/1/17 $299K SPR RECEIVED 7/27/17. FUNDING REQUESTED 7/27/17. FUNDING RECEIVED 8/8/17. PRE-DESIGN FINAL DELIVERABLE DUE IN LATE JANUARY, PROCEEDING WITH P3 PROCUREMENT.
JAMISON, G. 5638 ACSVCS DESIGN
5451 882000 180186 - 945866
MULTIPLE BUILDINGS - 1292 ENERGY CONSERVATION
6/15/17 $120.9K SPR RECEIVED 12/19/16. FUNDING REQUESTED 12/19/16. FUNDING RECEIVED 12/20/16. $28K EXPENDED; STEVE ORDERING LIGHTS. CLOSEOUT IS UNDERWAY.
SHARPE, S. 5451 FAC ADMIN CLOSEOUT
5759 430200 430200 - 923510
MULTIPLE BUILDINGS - 2017-2018 R&R REPAIRS (ELECTRICAL, PLUMBING, HVAC - DOBO HALL)
12/31/18 $1.9M $1.9M PROJECT ESTABLISHED IN AIM 12/14/17 AFTER AUTHORIZATION. CAPITAL R&R FUNDING RECEIVED 1/3/18. FUNDING SET UP.
HOLSINGER, D. 5759 ACSVCS DESIGN
5538 882000 319290 - 921990
MULTIPLE BUILDINGS - ACS STAFF AUGMENTATION
1/31/18 $443.2K SPR RECEIVED 3/13/17. FUNDING RECEIVED AND UPGRADED 3/15/17. FUNDING UPGRADE RECEIVED 9/11/17 FOR $227,040 BRINGING BALANCE TO $443,240.
PATRICK, R. 5538 ACSVCS PROCUREMENT
Project Report
48
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5595 427000 427000 - 945864
MULTIPLE BUILDINGS - CAMPUS FIRE ALARM SYSTEM UPGRADE
12/31/17 $400K $400K CAPITAL PROJECT SET UP 5/31/17 FOLLOWING BOG AUTHORIZATION OF $400,000. FUNDING SET UP 6/28/17. MEETING WITH DESIGNER 8/4/17.
JORDAN, W. 5595 ACSVCS PROCUREMENT
5718 882000 180187 - 923510
MULTIPLE BUILDINGS - CARPET REPLACEMENT FOR SAFETY (FY18)
6/1/18 $50K SPR RECEIVED 10/12/17. FUNDING RECEIVED 10/18/17.
GUINN, T. 5718 PROJ MGMT CONSTRUCTION
5490 882000 1AP100 - 945850
MULTIPLE BUILDINGS - CHHS SPACE MANAGEMENT PROJECT FY2017
6/15/17 $300K SPR RECEIVED 2/6/17. FUNDING REQUESTED 2/13/17. FUNDING RECEIVED 2/22/17. DESIGNER (RIGHT ANGLE) HAS RED FLAG. SPONSOR KNOWS COMPLETION IS QUESTIONABLE. FUNDING REDUCED 5/23/17. CLOSEOUT IS UNDERWAY.
BLUME, J. 5490 FAC ADMIN CLOSEOUT
5516 882000 371020 - 945861
MULTIPLE BUILDINGS - DESIGN AND INSTALL SHELVING IN BUILDINGS 7C AND 7D
8/15/17 $24.9K SPR RECEIVED 3/6/17. FUNDING REQUESTED 7/11/17. FUNDING RECEIVED 7/12/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
COLEMAN, I. 5516 FAC ADMIN CLOSEOUT
MULTIPLE BUILDINGS - DESIGN ELECTRICAL UPGRADE FOR MAIN SWITCH GEAR AT BELK/GRAHAM/HEWLETT
T.B.D. T.B.D. SPR RECEIVED 5/4/16. DESIGN BEING ACCOMPLISHED THROUGH UPCOMING CAPITAL PROJECT.
MCCARLEY, T. 5293 PROJ MGMT SCOPE & ESTIMATING
5440 420010 420010 - 945850
MULTIPLE BUILDINGS - HOUSING R&R PHASE I (BATHROOMS AND MECHANICAL)
6/30/17 $9M $5M PROJECT SET UP 11/29/16. CAPITAL FUNDING ESTABLISHED 11/29/16. DESIGN MEETING AT SCO ON 12/9/16. ALSO AWAITING CONTRACT SCO DECISION RE DESIGNER AND CM@R.
JORDAN, W. 5440 ACSVCS DESIGN
5599 882000 318500 - 945850
MULTIPLE BUILDINGS - MAINTENANCE MATERIALS AT BELK, GRAHAM, HEWLETT
8/1/17 $283K SPR RECEIVED 6/13/17. FUNDING RECEIVED 6/13/17. WORK IS COMPLETE.
JORDAN, W. 5599 ACSVCS COMPLETE
5586 882000 1AP100 - 945850
MULTIPLE BUILDINGS - OFFICE AND CLASSROOM IMPROVEMENTS (CHHS)
6/15/17 $100K SPR RECEIVED 5/23/17. FUNDING REQUESTED 5/23/17. FUNDING RECEIVED 5/24/17. CLOSEOUT IS UNDERWAY.
BLUME, J. 5586 FAC ADMIN CLOSEOUT
Project Report
49
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5683 882000 180540 - 923510
MULTIPLE BUILDINGS - PREPARATIONS FOR 2018 BOG MEETING
3/15/18 $100K SPR RECEIVED 6/15/17. FUNDING REQUESTED 10/17/17. FUNDING RECEIVED 10/18/17.
MULLINS, K. 5683 PROJ MGMT CONSTRUCTION
5476 882000 180187 - 923510
MULTIPLE BUILDINGS - REPAIR/REPLACE HANDRAILS FOR ADA COMPLIANCE
6/15/17 $80K SPR RECEIVED 1/26/17. FUNDING ESTABLISHED 1/27/17. FUNDING UPGRADED TO $100,000 ON 2/24/17. EXPECT TO COMPLETE NATATORIUM. FUNDING REDUCED 6/9/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5476 FAC ADMIN CLOSEOUT
5472 882000 180187 - 923510
MULTIPLE BUILDINGS - REPLACE WORN CARPET
6/15/17 $30K SPR RECEIVED 1/26/17. FUNDING ESTABLISHED 1/27/17. TOMMY IS WORKING ON AWARD; GATHERING PROPOSALS. FUNDING REDUCED 6/9/17. CLOSEOUT IS UNDERWAY.
GUINN, T. 5472 FAC ADMIN CLOSEOUT
5661 882000 180730 - 923510
MULTIPLE BUILDINGS - SEAL MECHANICAL ROOM FLOORS
10/31/17 $5.6K SPR RECEIVED 9/8/17. FUNDING REQUESTED 9/26/17. FUNDING RECEIVED 9/26/17. PO ISSUED. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
WILLIAMS, R. 5661 FAC ADMIN CLOSEOUT
5682 882000 180540 - 945866
MULTIPLE BUILDINGS - UPGRADE LOCKSETS
6/15/18 $300K SPR RECEIVED 9/15/17. FUNDING REQUESTED 10/18/17. FUNDING RECEIVED 10/18/17.
SINGLEY, D. 5682 PROJ MGMT CONSTRUCTION
5600 882000 318500 - 945850
MULTIPLE BUILDINGS - VALVE STRAIGHTENING AT BELK, GRAHAM, HEWLETT
8/1/17 $50.6K SPR RECEIVED 6/13/17. FUNDING RECEIVED 6/13/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
PATRICK, R. 5600 FAC ADMIN CLOSEOUT
5720 882000 180187 - 923510
NATATORIUM - CONSTRUCTION OF NEW EGRESS FOR CODE COMPLIANCE
6/15/18 $184K SPR RECEIVED 10/12/17. FUNDING RECEIVED 10/17/17. FUNDING REDUCED 4/3/18.
BLUME, J. 5720 PROJ MGMT DESIGN
5608 882000 180187 - 923510
NATATORIUM - INSTALL HANDRAILS AT SOUTH ENTRANCE
11/30/17 $1.8K SPR RECEIVED 6/28/17. FUNDING REQUESTED 6/29/17. FUNDING RECEIVED FROM ANNUAL ALLOCATION 10/18/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5608 FAC ADMIN CLOSEOUT
Project Report
50
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5711 882000 319080 - 945860
NATATORIUM - INSTALL SCOREBOARD BEAMS
11/30/17 $15.4K SPR RECEIVED 10/4/17. FUNDING REQUESTED 10/12/17. FUNDING RECEIVED 10/19/17. FUNDING UPGRADE RECEIVED 11/21/17. NEW BUDGET IS $15,410. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
MULLINS, K. 5711 FAC ADMIN CLOSEOUT
NATATORIUM - INVESTIGATE FOUNDATION FOR SETTLING
T.B.D. T.B.D. SPR RECEIVED 3/2/16. THIS WORK WILL BE ACCOMPLISHED IN A COMPREHENSIVE STUDY.
MCCARLEY, T. 5242 PROJ MGMT SCOPE & ESTIMATING
5572 882000 218021 - 945863
NATATORIUM - REPLACE FABRIC SOCK SYSTEM AT POOL
7/31/17 $300K SPR RECEIVED 4/18/17. FUNDING RECEIVED 4/18/17. BIDS RECEIVED 4/28/17. FUNDING UPGRADED 5/9/17. RETURN DUCT INSTALLATION IS UNDERWAY. SOCK DUCT TO SHIP LAST WEEK OF JULY. JOB IS 99% COMPLETE. DESIGN ENGINEER TO INSPECT WEEK OF SEPTEMBER 11. PO ISSUED FOR ADDITIONAL WORK. CLOSEOUT IS UNDERWAY.
WILLIAMS, R. 5572 FAC ADMIN CLOSEOUT
5112 882000 218021 - 945863
NATATORIUM - REPLACE HVAC DEKTRON UNIT
7/31/17 $200K SPR RECEIVED 9/15/15. FUNDING REQUESTED 2/7/17. FUNDING RECEIVED 2/17/17. DESIGN IN PROGRESS. DESIGN 95% COMPLETE. FUNDING REDUCED TO $290,000 ON 4/18/17. DESIGN AT 90% COMPLETE. FUNDING REDUCED TO $200,000 5/9/17. BIDS RECEIVED. NEED FUNDING UPGRADE TO COMPLETE PROJECT. UNIT ORDERED/DELIVERY MARCH 15, WORK COMPLETED APPROX. APRIL 15. 85% COMPLETE, AWAITING STARTUP.
WILLIAMS, R. 5112 PROJ MGMT CONSTRUCTION
5552 882000 121550 - 945864
NATATORIUM - REPLACEMENT OF PUMP IN ROOM 151
5/31/17 $12K SPR RECEIVED 3/24/17. FUNDING REQUESTED 4/13/17. FUNDING RECEIVED 4/18/17.
SINGLEY, D. 5552 FAC ADMIN CLOSEOUT
Project Report
51
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5709 882000 172972 - 923590
OFF-CAMPUS (MULTIPLE LOCATIONS) - COMPLETE COLLEGE ROAD SIGN AND BUILD CMSMG SIGN
10/31/17 $570 SPR RECEIVED 9/27/17. FUNDING REQUESTED 10/3/17. FUNDING RECEIVED 10/3/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5709 FAC ADMIN CLOSEOUT
5730 882000 180187 - 923590
OFF-CAMPUS - BUILD CMS SIGN (AND COMPLETE SEAHAWK COUNTRY SIGN)
12/31/17 $25K SPR RECEIVED 10/17/17. FUNDING RECEIVED 10/17/17.
SINGLEY, D. 5730 PROJ MGMT PROCUREMENT
5785 882000 152360 - 945860
OLLI (620 S. COLLEGE ROAD) - EXPANSION PRE-DESIGN
3/31/18 $22K SPR RECEIVED 2/5/18. FUNDING REQUESTED 2/5/18. FUNDING RECEIVED 2/5/18.
JORDAN, W. 5785 ACSVCS DESIGN
OSPREY HALL - INSTALL EXTERIOR SIGNAGE
T.B.D. T.B.D. SPR RECEIVED 3/23/18. BLUME, J. 5830 PROJ MGMT SCOPE & ESTIMATING
OSPREY HALL - INSTALL WIRELESS CARD READERS IN ROOMS 1007I AND 2007
T.B.D. T.B.D. SPR RECEIVED 3/14/18. MULLINS, K. 5819 PROJ MGMT SCOPE & ESTIMATING
5097 443811 443811 - 923510
PADRICK HOUSE - REPAIRS AND IMPROVEMENTS
9/30/15 $10.1K SPR RECEIVED 8/26/15. FUNDING ESTABLISHED 8/26/15. WORK IS UNDERWAY. WORK IS COMPLETE. WAITING FOR FINANCIAL CLOSEOUT. CLOSEOUT IS UNDERWAY.
BOYD, E. 5097 FAC ADMIN CLOSEOUT
PADRICK HOUSE - REPLACE FLOORING
T.B.D. $5.2K SPR RECEIVED 3/17/17. FUNDING REQUESTED 3/17/17.
BOYD, E. 5543 SPONSOR AWAITING FUNDING
5823 882000 319246 - 923590
PARKING DECK - PRESSURE WASH EXTERIOR
3/31/18 $12K SPR RECEIVED 3/14/18. FUNDING REQUESTED 3/15/18. FUNDING RECEIVED 3/16/18. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
MULLINS, K. 5823 FAC ADMIN CLOSEOUT
Project Report
52
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5754 882000 319246 - 945966
PARKING DECK - REMOVE BIKE RACKS AND INSTALL FENCE
1/30/18 $7K SPR RECEIVED 12/5/17. FUNDING REQUESTED 12/13/17. FUNDING RECEIVED 12/19/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5754 FAC ADMIN CLOSEOUT
5773 882000 319246 - 945950
PARKING DECK - REPAIRS AND MAINTENANCE PROJECT
8/31/18 $175K SPR RECEIVED 1/29/18. FUNDING REQUESTED 1/30/18. FUNDING RECEIVED 2/7/18.
JAMISON, G. 5773 ACSVCS PROCUREMENT
5598 882000 180180 - 945930
PARKING LOTS 1A AND 1B: TREE CLEARING AND GRUBBING
6/30/17 $32K SPR RECEIEVD 6/7/17. FUNDING REQUESTED 6/7/17. FUNDING RECEIVED 6/7/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
JAMISON, G. 5598 FAC ADMIN CLOSEOUT
PHYSICAL PLANT CRAFT SHOPS - CONVERT CARD READERS TO WIRED
T.B.D. T.B.D. SPR RECEIVED 4/11/18. SOUTHERLAND, E.
5854 PROJ MGMT SCOPE & ESTIMATING
5558 882000 319290 - 923590
PLYLER DRIVE- REPLACE DAMAGED LIGHT POLE
5/31/17 $8.3K SPR RECEIVED 3/28/17. FUNDING REQUESTED 4/4/17. FUNDING RECEIVED 4/5/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5558 FAC ADMIN CLOSEOUT
PPH LAB - AQUARIUM PROJECT IN ROOM 106
T.B.D. T.B.D. SPR RECEIVED 3/14/18. SINGLEY, D. 5816 PROJ MGMT SCOPE & ESTIMATING
5438 882000 319230 - 945850
PRINTING SERVICE - REMODEL ALL RESTROOMS
5/15/18 $12.5K SPR RECEIVED 11/22/16. FUNDING REQUESTED 3/16/17. CORRECTED FUNDING REQUEST SENT 10/16/17. FUNDING RECEIVED 11/21/17. SEEKING SPACE MANAGEMENT APPROVAL.
SOUTHERLAND, E.
5438 PROJ MGMT PROCUREMENT
5437 882000 318100 - 945850
PRINTING SERVICES - REPLACE FLOORING THROUGHOUT BUILDING
3/31/17 $10K SPR RECEIVED 11/22/16. FUNDING REQUESTED 2/2/17. FUNDING RECEIVED 2/22/17.
SOUTHERLAND, E.
5437 PROJ MGMT CONSTRUCTION
Project Report
53
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5621 882000 318100 - 945850
PRINTING SERVICES BUILDING - CONSTRUCT WALL IN ROOM 106
10/15/17 $5.5K SPR RECEIVED 7/10/17. FUNDING REQUESTED 8/8/17. FUNDING RECEIVED 8/14/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5621 FAC ADMIN CLOSEOUT
5493 882000 319290 - 923510
PURCHASING SERVICES BUILDING - REPLACE ROOF ON ORIGINAL BUILDING
4/30/17 $31K SPR RECEIVED 2/7/17. FUNDING REQUESTED 2/13/17. FUNDING RECEIVED 2/27/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5493 FAC ADMIN CLOSEOUT
5636 882000 151100 - 945866
RANDALL LIBRARY - ADD CEMENT AND BENCH AT BOOK DROP
11/25/17 $5.8K SPR RECEIVED 8/2/17. FUNDING REQUESTED 8/22/17. FUNDING RECEIVED 9/20/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
MULLINS, K. 5636 FAC ADMIN CLOSEOUT
5550 882000 151100 - 945860
RANDALL LIBRARY - DESIGN AND CONSTRUCTION OF DIGITAL CREATION SPACE
6/15/17 $16.6K SPR RECEIVED 3/22/17. DESIGNER PROPOSALS RECEIVED 4/6/17. FUNDING REQUESTED 4/19/17. FUNDING RECEIVED 4/21/17. DESIGN UNDERWAY 5/1/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
HOLSINGER, D. 5550 FAC ADMIN CLOSEOUT
RANDALL LIBRARY - DESIGN FOR ROOM 2042, SPECIAL COLLECTIONS
T.B.D. T.B.D. SPR RECEIVED 2/20/18. WAITING FOR PROPOSAL FROM VENDOR.
HOLSINGER, D. 5791 ACSVCS SCOPE & ESTIMATING
5628 882000 151100 - 945866
RANDALL LIBRARY - INSTALL LENEL KEYPAD SYSTEM IN ROOM 1029
11/30/17 $1K SPR RECEIVED 7/24/17. FUNDING REQUESTED 8/3/17. FUNDING RECEIVED 10/18/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5628 FAC ADMIN CLOSEOUT
5395 882000 151100 - 945850
RANDALL LIBRARY - INSTALL NEW FRONT DOORS
6/15/17 $30.6K SPR RECEIVED 9/12/16. MET WITH REQUESTOR. PREPARING ESTIMATE. FUNDING REQUESTED 1/26/17. FUNDING RECEIVED 2/7/17. SCOPING. DOOR CONTRACT AWARDED. EXPECT TO COMPLETE. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
MCCARLEY, T. 5395 FAC ADMIN CLOSEOUT
Project Report
54
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5629 882000 151100 - 945850
RANDALL LIBRARY - INSTALLATION AND RENOVATION OF DIGITAL MAKER SPACE - RM 1023
1/31/18 $239.9K SPR RECEIVED 7/24/17. FUNDING REQUESTED 8/30/17. FUNDING RECEIVED 9/12/17. FUNDING UPGRADE RECEIVED 1/11/18.
HOLSINGER, D. 5629 ACSVCS COMPLETE
5544 426000 426000 - 945850
RANDALL LIBRARY - LIFE SAFETY, ADA, AND RESTROOM IMPROVEMENTS
7/31/18 $1.5M $1.5M PROJECT ESTABLISHED AND AUTHORITY RECEIVED 3/20/17. DESIGNER INTERVIEWS ON 4/11/17. DESIGNER ASSIGNED 4/28/17. DESIGN REVISIONS AND SCHEDULE IN PROGRESS. PRE-CONSTRUCTION UNDERWAY.
HOLSINGER, D. 5544 ACSVCS CONSTRUCTION
RANDALL LIBRARY - REMODEL TAC
T.B.D. $36.7K SPR RECEIVED 3/3/15. MET WITH SPONSOR 3/19/15. FUNDING REQUESTED 4/29/15. REVISED FUNDING REQUEST SUBMITTED 2/16/16.
MCCARLEY, T. 5000 SPONSOR AWAITING FUNDING
5775 882000 151100 - 945850
RANDALL LIBRARY - RENOVATION OF SECOND FLOOR RESTROOMS
6/15/18 $140K SPR RECEIVED 2/1/18. FUNDING REQUESTED 2/2/18. FUNDING RECEIVED 2/6/18. ASI ISSUED. AWAITING FUND TRANSFER.
HOLSINGER, D. 5775 ACSVCS PROCUREMENT
5551 882000 151100 - 945860
RANDALL LIBRARY - RENOVATIONS TO SUITE 1023
5/31/17 $5K SPR RECEIVED 3/22/17. DESIGN FUNDING REQUESTED 4/17/17. FUNDING RECEIVED 4/18/17. DESIGN IN FINAL REVIEW. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
HOLSINGER, D. 5551 FAC ADMIN CLOSEOUT
5721 882000 180187 - 923510
RANDALL LIBRARY - REPLACE ADA RAILS ON RAMP
12/31/17 $5.8K SPR RECEIVED 10/12/17. FUNDING RECEIVED 10/18/17. FUNDING UPGRADE RECEIVED 10/23/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5721 FAC ADMIN CLOSEOUT
5585 RANDALL LIBRARY - STRUCTURAL ENGINEERING REVIEW OF SECOND FLOOR
T.B.D. $35K SPR RECEIVED 5/22/17. FUNDING REQUESTED 5/25/17. ON HOLD PER SPONSOR.
HOLSINGER, D. 5585 ACSVCS ON HOLD
5750 882000 371020 - 945865
RECREATION OPS NORTH - INSTALL AV AND DATA
3/31/18 $1.4K SPR RECEIVED 11/13/17. FUNDING REQUESTED 2/1/18. FUNDING RECEIVED 2/21/18.
GUINN, T. 5750 PROJ MGMT PROCUREMENT
Project Report
55
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5505 882000 137301 - 945850
RESIDENTIAL PROGRAMS SUPPORT FACILITY - RENOVATE ROOM 003G INTO THREE OFFICES
6/15/17 $59K SPR RECEIVED 2/16/17. FUNDING REQUESTED 3/1/17. FUNDING RECEIVED 3/7/17. BID OPENING SCHEDULED FOR 3/13. EXPECT TO COMPLETE. AWARDED CONTRACT. WORK BEGINS 5/8/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5505 FAC ADMIN CLOSEOUT
5464 882000 318500 - 945863
RESIDENTIAL SUPPORT FACILITY (GRAHAM/HEWLETT CONNECTOR) - REPLACE 20 TON A/C UNIT
3/15/17 $96K SPR RECEIVED 1/23/17. FUNDING REQUESTED 1/24/17. FUNDING RECEIVED 1/26/17. EQUIPMENT ON ORDER, 6 WEEK DELIVERY LEAD TIME. TWO DAMPERS ORDER TO BE INSTALLED WEEK OF 6/12/17 TO COMPLETE PROJECT. WORK IS COMPLETE.
JORDAN, W. 5464 ACSVCS COMPLETE
REYNOLDS DRIVE - INSTALL BIKE LANES
T.B.D. T.B.D. SPR RECEIVED 4/4/18. BLUME, J. 5842 PROJ MGMT SCOPE & ESTIMATING
5514 882000 180180 - 945866
RIEGEL ROAD - UTILITIES 6/15/17 $300K SPR RECEIVED 2/23/17. FUNDING ESTABLISHED 2/23/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
COLEMAN, I. 5514 FAC ADMIN CLOSEOUT
CI13-006 416290 416290 - 945867
S&BS RENOVATIONS 8/15/15 $11.2M DESIGN FIRM HAS BEEN SELECTED. DESIGN IS UNDERWAY. CMR HAS BEEN SELECTED. WORK IS UNDERWAY. DESIGNER PRE-FINAL INSPECTION 6/4/15. SCO FINAL APPROVAL OBTAINED 8/3/15.
SEIFERT, L. 4716 FAC ADMIN CLOSEOUT
5561 882000 319248 - 945950
SAWTOOTH DRIVE - ADD ADDITIONAL PARKING AND RESURFACE LOT CC
3/2/18 $70K SPR RECEIVED 3/31/17. FUNDING REQUESTED 6/16/17. FUNDING RECEIVED 11/03/17.
SINGLEY, D. 5561 PROJ MGMT DESIGN
5676 882000 318500 - 945850
SCHWARTZ HALL - INSTALL EPOXY IN SHOWER PANS
6/1/18 $47.4K SPR RECEIVED 9/12/17. FUNDING REQUESTED 11/15/17. FUNDING RECEIVED 11/30/17. FUNDING UPGRADE RECEIVED 12/5/17.
HEINS, R. 5676 PROJ MGMT PROCUREMENT
Project Report
56
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5734 882000 318500 - 945830
SCHWARTZ HALL - INSTALL LANDSCAPING AND IRRIGATION AT BIKE RACK AREA
6/15/18 $24K SPR RECEIVED 10/26/17. FUNDING REQUESTED 1/22/18. FUNDING RECEIVED 1/23/18.
BLUME, J. 5734 PROJ MGMT CONSTRUCTION
5821 882000 318500 - 945866
SCHWARTZ HALL - INSTALL SECURITY CAMERA IN ROOM 100
4/30/18 $660 SPR RECEIVED 3/14/18. FUNDING REQUESTED 3/15/18. FUNDING RECEIVED 3/20/18.
MULLINS, K. 5821 PROJ MGMT PROCUREMENT
5675 882000 318500 - 945850
SCHWARTZ HALL - REPLACE COUNTER TOPS
6/1/18 $43.2K SPR RECEIVED 9/12/17. FUNDING REQUESTED 11/15/17. FUNDING RECEIVED 11/30/17. FUNDING UPGRADE RECEIVED 12/5/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
HEINS, R. 5675 FAC ADMIN CLOSEOUT
SCHWARTZ HALL - REPLACE SHOWER VALVES
T.B.D. $88K SPR RECEIVED 9/12/17. FUNDING REQUESTED 11/15/17.
HEINS, R. 5674 SPONSOR AWAITING FUNDING
5576 882000 318515 - 945864
SEAHAWK CROSSING - REPLACE POWER METERS AT BUILDINGS 1 & 4
7/31/17 $6.8K SPR RECEIVED 4/26/17. FUNDING REQUESTED 5/24/17. FUNDING RECEIVED 6/6/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5576 FAC ADMIN CLOSEOUT
5487 882000 180410 - 945966
SEAHAWK CROSSING BUILDING 3 - MOVE CALLBOX 109 AND CREATE ACCESSIBLE PATH
5/15/17 $1.8K SPR RECEIVED 2/6/17. FUNDING REQUESTED 2/22/17. REVISED FUNDING REQUEST SENT 3/20/17. FUNDING ESTABLISHED 4/4/14. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5487 FAC ADMIN CLOSEOUT
5483 882000 318515 - 923510
SEAHAWK CROSSING BUILDING 4 - ROLLOVER CONTRACT (2017)
8/10/17 $50K SPR RECEIVED 1/31/17. FUNDING REQUESTED 3/10/17. FUNDING RECEIVED 3/17/17. PRE-BID HELD 4/6/17. PROJECT CANCELLED 4/25/17. MADE INACTIVE AND LIQUIDATED FUNDS BACK TO SPONSOR. PROJECT REACTIVATED AND ENCUMBERED AT $50,000 AT REQUEST ON SPONSOR 4/26/17. PREBID FOR CROSSING 4 HELD 5/1/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5483 FAC ADMIN CLOSEOUT
Project Report
57
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
SEAHAWK CROSSING GROUNDS - ADD SWINGS AND GROUND COVER IN COURTYARD
T.B.D. T.B.D. SPR RECEIVED 3/14/18. HEINS, R. 5815 PROJ MGMT SCOPE & ESTIMATING
5536 882000 318510 - 945860
SEAHAWK LANDING - REPLACE HVAC UNITS (DESIGN ONLY)
1/15/18 $28.6K SPR RECEIVED 3/9/17. ESTIMATE RECEIVED; LIKELY TO TURN INTO CAPITAL PROJECT AND WILL NEED AUTHORIZATION. FUNDING FOR DESIGN ONLY RECEIVED 11/3/17.
WILLIAMS, R. 5536 PROJ MGMT PROCUREMENT
SEAHAWK LANDING GROUNDS - ADD PAVILION IN COURTYARD
T.B.D. T.B.D. SPR RECEIVED 3/14/18. HEINS, R. 5814 PROJ MGMT SCOPE & ESTIMATING
5523 882000 318505 - 945860
SEAHAWK VILLAGE - DESIGN FOR HVAC REPLACEMENT
1/15/18 $27K SPR RECEIVED 3/6/17. ESTIMATE RECEIVED; LIKELY TO TURN INTO CAPITAL PROJECT AND WILL NEED AUTHORIZATION. FUNDING FOR DESIGN ONLY RECEIVED 11/3/17. ENGINEERING COMPLETE. EXPECTING QUOTE WEEK OF 2/6/18. HOPE TO AWARD WEEK OF 3/5/18. DESIGN COMPLETE, CONSTRUCTION PO ISSUED.
WILLIAMS, R. 5523 PROJ MGMT COMPLETE
5252 882000 318505 - 923510
SEAHAWK VILLAGE - INSTALL NEW DHW HEATERS IN EACH APARTMENT
8/15/16 $65K SPR RECEIVED 3/23/16. FUNDING RECEIVED 4/4/16. WORK AWARDED AND IN PROGRESS. WORK IS COMPLETE.
MCCARLEY, T. 5252 PROJ MGMT COMPLETE
5824 882000 318505 - 945863
SEAHAWK VILLAGE - REPLACEMENT OF HVAC UNITS IN BUILDINGS 4-6, CLUBHOUSE
7/31/18 $300K SPR RECEIVED 3/15/18. FUNDING REQUESTED 3/15/18. FUNDING RECEIVED 3/15/18. CONSTRUCTION PO ISSUED FOR SUMMER WORK. WORK TO BEGIN 5/6/18.
WILLIAMS, R. 5824 PROJ MGMT PROCUREMENT
5752 882000 318505 - 945866
SEAHAWK VILLAGE BUILDINGS 1-6 - MOVE ADA DOOR OPENERS TO BACK DOORS
6/15/18 $6.5K SPR RECEIVED 11/21/17. FUNDING REQUESTED 12/15/17. FUNDING RECEIVED 12/18/17.
BLUME, J. 5752 PROJ MGMT CONSTRUCTION
Project Report
58
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5441 882000 318300 - 945860
SHOPS AT THE CROSSING - STRUCTURAL ENGINEERING REVIEW AND RENOVATIONS
6/30/18 $8.1K SPR RECEIVED 11/30/2016. FUNDING REQUESTED 1/19/17. FUNDING RECEIVED 2/1/17.
BLUME, J. 5441 PROJ MGMT DESIGN
5350 882000 319080 - 945940
SOCCER FIELD - CURB CUT AT HAMILTON DRIVE
12/30/16 $15.6K SPR RECEIVED 7/21/16. FUNDING REQUESTED 9/13/16. FUNDING RECEIVED 10/5/16. WORK SCHEDULED FOR DECEMBER 12. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5350 FAC ADMIN CLOSEOUT
5314 882000 319080 - 945940
SOCCER FIELD - EXTEND SIDEWALK
9/15/17 $21.4K SPR RECEIVED 5/31/16. FUNDING REQUESTED 8/26/16. REVISED ESTIMATE SENT 7/27/17. FUNDING RECEIVED 8/14/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5314 FAC ADMIN CLOSEOUT
SOCCER FIELD - INSTALL 25' FLAG POLE
T.B.D. $7.3K SPR RECEIVED 8/15/16. FUNDING REQUESTED 9/1/16.
SOUTHERLAND, E.
5367 SPONSOR AWAITING FUNDING
SOCCER FIELD - INSTALL NEW SCOREBOARD
T.B.D. T.B.D. SPR RECEIVED 6/27/16. MEETING WITH ATHLETICS AND DAKTRONICS ON 4/6/17. COMPLETING ESTIMATE IN NEAR FUTURE; ROUGH ESTIMATE IS $210,000.
SOUTHERLAND, E.
5322 PROJ MGMT SCOPE & ESTIMATING
SOCCER FIELD - INSTALL STORAGE CONTAINER
T.B.D. $7.9K SPR RECEIVED 3/23/18. FUNDING REQUESTED 3/26/18.
MULLINS, K. 5827 SPONSOR AWAITING FUNDING
5766 882000 371020 - 945866
STUDENT REC CENTER - INSTALL BALLET BARRE IN ROOMS 129, 226/228
2/28/18 $6.2K SPR RECEIVED 1/2/18. FUNDING REQUESTED 1/10/18. FUNDING RECEIVED 1/22/18. MET WITH SPONSOR 1/23/18.
SOUTHERLAND, E.
5766 PROJ MGMT CONSTRUCTION
5667 882000 371020 - 945940
STUDENT REC CENTER - INSTALL CAULKING AT SIDEWALKS, JOINTS, OUTDOOR POOL
12/31/17 $8.5K SPR RECEIVED 9/12/17. FUNDING REQUESTED 9/14/17. FUNDING RECEIVED 9/26/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5667 FAC ADMIN CLOSEOUT
Project Report
59
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5644 882000 371020 - 945866
STUDENT REC CENTER - INSTALL EARTH NETWORKS EQUIPMENT
11/15/17 $28.8K SPR RECEIVED 8/11/17. FUNDING REQUESTED 9/19/17. FUNDING RECEIVED 10/4/17.
SINGLEY, D. 5644 PROJ MGMT CONSTRUCTION
STUDENT REC CENTER - INSTALL HEAT IN ROOM 136
T.B.D. T.B.D. SPR RECEIVED 2/21/18. GUINN, T. 5796 PROJ MGMT SCOPE & ESTIMATING
5590 882000 371020 - 945940
STUDENT REC CENTER - INSTALL NEW DRAINAGE SYSTEM FOR WALKWAY
8/1/17 $7.5K SPR RECEIVED 5/26/17. FUNDING REQUESTED 6/15/17. FUNDING RECEIVED 6/21/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
MCCARLEY, T. 5590 FAC ADMIN CLOSEOUT
5591 882000 371020 - 945966
STUDENT REC CENTER - NEW CARGO NET AT CHALLENGE COURSE
8/15/17 $8.5K SPR RECEIVED 5/26/17. FUNDING REQUESTED 5/26/17. FUNDING RECEIVED 6/8/17. WORK COMPLETE. CLOSEOUT IS UNDERWAY.
MCCARLEY, T. 5591 FAC ADMIN CLOSEOUT
STUDENT REC CENTER - REPAIR DITCH BEHIND BUILDING
T.B.D. T.B.D. SPR RECEIVED 10/8/15. MCADAMS WORKING ON REPAIR.
MCCARLEY, T. 5126 PROJ MGMT SCOPE & ESTIMATING
5749 882000 371020 - 923510
STUDENT REC CENTER - REPAIR POOL LIGHTING
12/31/17 $6.5K SPR RECEIVED 11/13/17. FUNDING REQUESTED 11/14/17. FUNDING RECEIVED 11/30/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5749 FAC ADMIN CLOSEOUT
5445 882000 371020 - 945864
STUDENT REC CENTER - RETRO-FIT POOL LIGHTING TO LED
6/1/18 $88K SPR RECEIVED 12/7/16. FUNDING REQUESTED 3/15/18. FUNDING RECEIVED 3/20/18.
GUINN, T. 5445 PROJ MGMT PROCUREMENT
STUDENT REC CENTER - SEAL MECHANICAL ROOM FLOORS, RMS 202, 203
T.B.D. T.B.D. SPR RECEIVED 4/4/18. WILLIAMS, R. 5843 PROJ MGMT SCOPE & ESTIMATING
Project Report
60
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5643 882000 371020 - 945864
STUDENT REC CENTER - UPDATE POOL LIGHTING TO LED
8/31/17 $13.1K SPR RECEIVED 8/11/17. FUNDING REQUESTED 8/14/17. FUNDING RECEIVED 8/14/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5643 FAC ADMIN CLOSEOUT
5657 882000 318500 - 945863
SUITE SERVICE BUILDING - REPLACE 5 TON RTU UNIT ON ROOF
10/31/17 $10.4K SPR RECEIVED 8/22/17. FUNDING RECEIVED 9/12/17. INSTALLATION BEGIN 9/29/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
WILLIAMS, R. 5657 FAC ADMIN CLOSEOUT
5423 882000 212167 - 945861
TEACHING LAB - BUILD SHELVES IN ROOM 2008
6/15/18 $5K SPR RECEIVED 9/29/16. FUNDING REQUESTED 11/9/16. REVISED ESTIMATE SEND 4/17/17. FUNDING RECEIVED 3/7/18.
SOUTHERLAND, E.
5423 PROJ MGMT PROCUREMENT
446904 446904 - 945861
TEACHING LAB - STORMWATER 9/30/14 $55.3K FUNDING REQUESTED 12/14/11. FUNDING RECEIVED 2/24/12. ANALYSIS UNDERWAY. WORK IS COMPLETE. CLOSEOUT IN PROGRESS.
MORGAN, M. 4336 FACILITIES OPEN
TELECOM BUILDING - ESTIMATE FIRE ALARM SYSTEM IN ROOM 108
T.B.D. T.B.D. SPR RECEIVED 9/19/16. RECEIVED ESTIMATES FROM CONTRACTOR 10/27/16. PREPARING ESTIMATE LETTER AND SPR.
MCCARLEY, T. 5407 PROJ MGMT SCOPE & ESTIMATING
5562 882000 319080 - 945966
TENNIS COMPLEX - ADD FLAG POLES AT TENNIS AND TRACK COMPLEXES
8/31/17 $4.9K SPR RECEIVED 3/31/17. FUNDING REQUESTED 4/20/17. FUNDING RECEIVED 7/17/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5562 FAC ADMIN CLOSEOUT
5607 882000 319080 - 923590
TENNIS COURTS - RESURFACE TENNIS COURTS
10/31/17 $66K SPR RECEIVED 6/28/17. FUNDING REQUESTED 8/16/17. FUNDING RECEIVED 8/23/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5607 FAC ADMIN CLOSEOUT
5687 417210 417210 - 923510
TRASK COLISEUM - CODE DEFICIENCY (2014 R&R)
6/1/18 $476K SPR RECEIVED 9/19/17. FUNDING SET UP 9/20/17.
MCCARLEY, T. 5687 PROJ MGMT PROCUREMENT
Project Report
61
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
TRASK COLISEUM - DESIGN NEW ELEVATOR IMPLEMENTATION
T.B.D. T.B.D. SPR RECEIVED 3/26/18. SINGLEY, D. 5835 PROJ MGMT SCOPE & ESTIMATING
TRASK COLISEUM - DESIGN STUDENT BLEACHER REPLACEMENT
T.B.D. T.B.D. SPR RECEIVED 3/26/18. SINGLEY, D. 5839 PROJ MGMT SCOPE & ESTIMATING
5478 420201 420201 - 945864
TRASK COLISEUM - EMERGENCY LIGHTING UPGRADES FOR CODE COMPLIANCE (R&R)
6/15/18 $145K $145K SPR RECEIVED 1/31/17. R&R FUNDING ESTABLISHED 1/31/17.
BLUME, J. 5478 PROJ MGMT CONSTRUCTION
5689 419230 419230 - 923510
TRASK COLISEUM - LIFE SAFETY IMPROVEMENTS (2015 R&R)
6/1/18 $400K SPR RECEIVED 9/19/17. FUNDING SET UP 9/20/17.
MCCARLEY, T. 5689 PROJ MGMT CONSTRUCTION
TRASK COLISEUM - LOADING DOCK REPAIR
T.B.D. $9K SPR RECEIVED 3/26/18. FUNDING REQUESTED 4/3/18.
SINGLEY, D. 5837 SPONSOR AWAITING FUNDING
5710 882000 180187 - 923510
TRASK COLISEUM - MODIFICATIONS TO BLEACHERS
12/31/17 $10K SPR RECEIVED 10/3/17. FUNDING ESTABLISHED 10/3/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SINGLEY, D. 5710 FAC ADMIN CLOSEOUT
TRASK COLISEUM - PROVIDE ADDITIONAL STORAGE
T.B.D. T.B.D. SPR RECEIVED 2/12/15. SCOPING IN PROGRESS.
MCCARLEY, T. 4978 PROJ MGMT SCOPE & ESTIMATING
TRASK COLISEUM - REPAIR HANDRAILS IN ARENA
T.B.D. T.B.D. SPR RECEIVED 3/26/18. SINGLEY, D. 5833 PROJ MGMT SCOPE & ESTIMATING
Project Report
62
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
TRASK COLISEUM - REPLACE PARTITIONS AND CEILING TILES IN ROOM 134
T.B.D. $9K SPR RECEIVED 9/13/16. FUNDING REQUESTED 10/11/16.
WILLIAMS, R. 5391 SPONSOR AWAITING FUNDING
TRASK COLISEUM - REPLACE WIRELESS DOOR MONITORS AT HALLWAY DOORS
T.B.D. T.B.D. SPR RECEIVED 4/11/18. SOUTHERLAND, E.
5855 PROJ MGMT SCOPE & ESTIMATING
R&R 414210 414210 - 945860
TRASK COLISEUM - UPGRADE FIRE ALARM SYSTEM (DESIGN) (R&R FUNDS)
6/30/15 $282.7K SPR RECEIVED 4/5/13. ESTIMATE AND FUNDING REQUEST FORWARDED TO PROJECT SPONSOR ON 4/5/13. R&R FUNDING RECEIVED. ANALYSIS AND DESIGN IS UNDERWAY.
MCCARLEY, T. 4595 PROJ MGMT DESIGN
5802 882000 152030 - 945866
TRASK COLISEUM / HANOVER HALL - INSTALL WIRELESS CARD READERS
6/15/18 $15K SPR RECEIVED 2/21/18. FUNDING REQUESTED 2/28/18. FUNDING RECEIVED 3/14/18.
SINGLEY, D. 5802 PROJ MGMT PROCUREMENT
TRASK COMPLEX - REPLACE DOMESTIC HOT WATER TANK IN POOL ROOM 151
T.B.D. T.B.D. SPR RECEIVED 9/6/17. MCCARLEY, T. 5659 PROJ MGMT SCOPE & ESTIMATING
5557 425000 425000 - 945864
UNIVERSITY POLICE - INSTALL GENERATOR
6/15/17 $265K $265K SPR RECEIVED 3/28/17. FUNDING REQUESTED 3/28/17. FUNDING RECEIVED 3/28/17. DESIGN AWARDED.
SINGLEY, D. 5557 PROJ MGMT DESIGN
5513 425000 425000 - 945850
UNIVERSITY POLICE - UPD RENOVATION AND EXPANSION
6/30/18 $484.7K $484.7K CAPITAL PROJECT SET UP 2/22/17. CAPITAL FUNDING SETUP COMPLETED 2/24/17. RACHEL TO HAVE BECKER MORGAN DO RENDERINGS FOR APRIL BOT MEETING. BUDGET REDUCED TO COVER GENERATOR COSTS IN PM5557.
SINGLEY, D. 5513 PROJ MGMT CONSTRUCTION
5678 882000 318500 - 945850
UNIVERSITY SUITES - INSTALL EPOXY IN SHOWER PANS
6/15/18 $31.2K SPR RECEIVED 9/12/17. FUNDING REQUESTED 11/15/17. FUNDING RECEIVED 11/30/17. FUNDING UPGRADE RECEIVED 12/5/17.
HEINS, R. 5678 PROJ MGMT PROCUREMENT
Project Report
63
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5524 882000 318500 - 945850
UNIVERSITY SUITES - RENOVATIONS TO SUITES
7/31/17 $20K SPR RECEIVED 3/6/17. PRE-BID HELD 4/6/17. FUNDING REQUESTED 4/6/17. FUNDING RECEIVED 4/6/17. AWARDED PO. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5524 FAC ADMIN CLOSEOUT
5677 UNIVERSITY SUITES - REPLACE SINK VANITIES
T.B.D. $134K SPR RECEIVED 9/12/17. FUNDING REQUESTED 11/15/17. ON HOLD UNTIL SUMMER 2019.
HEINS, R. 5677 PROJ MGMT ON HOLD
5207 WAGONER HALL - ATTACH NEW GAS HOSES TO GRILL
T.B.D. $0 SPR RECEIVED 1/28/16. WORK IN PROGRESS. DESIGNER IS INVOLVED TO MAKE FA INTEGRATE WITH BUILDING AUTOMATION. WORK IN PROGRESS VIA OTHER CONTRACTS THROUGH ARAMARK. WORK COMPLETE.
MCCARLEY, T. 5207 PROJ MGMT COMPLETE
5575 882000 318300 - 945865
WAGONER HALL - INSTALL AV EQUIPMENT AT MADELINE SUITE
8/1/17 $103K SPR RECEIVED 4/25/17. FUNDING REQUESTED 4/26/17. FUNDING RECEIVED 5/5/17. PO AWARDED 5/5/17. WORK IS COMPLETE. PREPARING TO CLOSE. CLOSEOUT IS UNDERWAY.
MCCARLEY, T. 5575 FAC ADMIN CLOSEOUT
5712 882000 318300 - 945864
WAGONER HALL - INSTALL ELECTRICAL OUTLET AT LOADING DOCK
1/31/18 $4.9K SPR RECEIVED 10/4/17. FUNDING REQUESTED 11/22/17. FUNDING REQUESTED 12/7/17. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
GUINN, T. 5712 FAC ADMIN CLOSEOUT
4956 882000 318300 - 945850
WAGONER HALL - RENOVATIONS TO MADELINE SUITE
8/30/16 $311.4K SPR RECEIVED 12/5/14. AUTHORITY REQUESTED FROM GA. FUNDING REQUESTED FOR MECHANICAL DESIGN ON 4/12/16. FUNDING RECEIVED 7/19/16. CONSTRUCTION IN PROGRESS. FUNDING UPGRADE RECEIVED 3/29/17. 65% COMPLETE. EXPECT COMPLETION IN MAY 2017. CONSTRUCTION AT 80% COMPLETE. WORK IS COMPLETE. PREPARING TO CLOSE. CLOSEOUT IS UNDERWAY.
MCCARLEY, T. 4956 FAC ADMIN CLOSEOUT
Project Report
64
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5604 882000 318300 - 945860
WAGONER HALL - REPLACE CAST IRON PIPING IN CRAWL SPACE
5/31/18 $189.9K SPR RECEIVED 6/28/17. FUNDING REQUESTED 10/4/17. FUNDING RECEIVED 10/5/17. ENGINEERED DRAWINGS STARTED. BIDS EXPECTED 2/21/18. FUNDING UPGRADE FOR CONSTRUCTION RECEIVED 3/1/18. PO ISSUED 3/5/18. WORK WILL START 4/19/18.
WILLIAMS, R. 5604 PROJ MGMT CONSTRUCTION
WALTON DRIVE - FEASIBILITY STUDY
T.B.D. T.B.D. SPR GENERATED 11/25/14. DESIGNER GENERATING CONCEPT DESIGNS.
MORGAN, M. 4947 ACSVCS SCOPE & ESTIMATING
SP15-004 883237 319248 - 945966
WALTON DRIVE - INSTALL TRAFFIC SIGNAL AT CHANCELLORS WALK CROSSING
9/19/14 $25K SPR GENERATED 6/16/14. FUNDING REQUESTED 6/16/14. FUNDING RECEIVED 7/2/14. PRELIMINARY DESIGN IS UNDER REVIEW. COORDINATION MEETING CONDUCTED ON 8/19/14. PROJECT PRESENTED TO DESIGN REVIEW COMMITTEE 10/7/14. DESIGN REVISIONS HAVE BEEN COMPLETED. FUNDING FOR CONSTRUCTION HAS BEEN REQUESTED. LIGHTING PACKAGE PAID FOR OUT OF PM 4617, CAHILL CURB AND GUTTER. LIGHTING PHASE IN PROGRESS. LIGHTING PHASE I IS COMPLETE. DESIGN BEING FINALIZED.
MCCARLEY, T. 4872 PROJ MGMT COMPLETE
Project Report
65
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
5111 420206 420206 - 945863
WAREHOUSE - REPLACE ALL HVAC PACKAGE UNITS
7/31/17 $60.7K SPR RECEIVED 9/15/15. AWAITING INITIAL ESTIMATE FROM CONTRACTOR. WORKING ON PROPOSAL IN ORDER TO PUT OUT PROJECT FOR BID. FUNDING REQUESTED 4/7/16. OUT FOR PRICING WITH CHANGED DESIGN AND SCOPE. NEW FUNDING REQUEST SENT 9/21/16. ONE UNIT IN FACILITIES STORES WAS FUNDED THROUGH EMERGENCY PO (180730). PM WILL OVERSEE. THAT PART OF THE WORK IS COMPLETE. R&R FUNDING RECEIVED FOR OTHER TWO UNITS (420206) ON 1/30/17 (THE NEW BUDGET FOR THAT IS $60,683). PO HAS BEEN ISSUED. WORK IS COMPLETE. AWAITING INVOICE PAYMENT IN JULY.
WILLIAMS, R. 5111 PROJ MGMT COMPLETE
WAREHOUSE - UPGRADE FIRE SUPPRESSION AND ALARM SYSTEM
T.B.D. T.B.D. SPR RECEIVED 9/19/17. SINGLEY, D. 5686 PROJ MGMT SCOPE & ESTIMATING
5479 420204 420204 - 945866
WARWICK CENTER - ADA IMPROVEMENTS (R&R)
6/15/18 $45K SPR RECEIVED 1/31/17. R&R FUNDING ESTABLISHED 1/31/17.
BLUME, J. 5479 PROJ MGMT CONSTRUCTION
5779 882000 318100 - 945966
WARWICK CENTER - CONSTRUCT DUMPSTER ENCLOSURE
5/31/18 $54K SPR RECEIVED 2/2/18. MET WITH SPONSOR 1/6/18. FUNDING REQUESTED 2/13/18. FUNDING RECEIVED 2/19/18. BRICK WORK UNDERWAY.
SOUTHERLAND, E.
5779 PROJ MGMT CONSTRUCTION
5305 882000 180180, 319163 - 945850
WARWICK CENTER - EXPAND SPACE FOR LOUNGE IN ROOM 152
10/30/16 $95.3K SPR RECEIVED 5/19/16. FUNDING FOR DESIGN ONLY REQUESTED 6/24/16. FUNDING RECEIVED FOR DESIGN 7/12/16. DESIGN IN PROGRESS. SCO APPROVAL RECEIVED. PREPARING TO BID. CONSTRUCTION FUNDING ENCUMBERED FROM 180180 5/5/17. CONSTRUCTION PO ISSUED 5/5/17. EXPECT TO COMPLETE 6/15/17. CLOSEOUT IS UNDERWAY.
MCCARLEY, T. 5305 FAC ADMIN CLOSEOUT
Project Report
66
SP/CI PROJ
FUND NO SOURCE FUND
TITLE ESTM'D CPLTN
PROJ BDGT
AUTH. STATUS PROJ MGR PM NO ACTION OFFICE
PHASE
WARWICK CENTER - REVERSE DOOR IN ROOM 102D
T.B.D. T.B.D. SPR RECEIVED 9/15/16. MCCARLEY, T. 5406 PROJ MGMT SCOPE & ESTIMATING
5409 WATER TOWER - UPDATE AT&T EQUIPMENT
12/31/16 $0 SPR RECEIVED 9/19/16. WORK TO BE PAID BY AT&T. NO COST TO UNIVERSITY.
MCCARLEY, T. 5409 PROJ MGMT CONSTRUCTION
WESTSIDE CEP - INSTALL WATER AND ELECTRICAL TAPS
T.B.D. T.B.D. SPR RECEIVED 7/13/17. SINGLEY, D. 5625 PROJ MGMT SCOPE & ESTIMATING
5285 882000 171415 - 945866
WISE HOUSE - PAINT HOUSE EXTERIOR
6/15/17 $100K SPR RECEIVED 4/13/16. FUNDING REQUESTED 8/3/16. REVISED FUNDING REQUEST FOR DESIGN ONLY SENT 4/10/17. FUNDING RECEIVED 5/23/17 IN THE AMOUNT OF $100,000. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY.
SOUTHERLAND, E.
5285 FAC ADMIN CLOSEOUT
5740 882000 218002 - 923510
WISE HOUSE - REPAIR COLUMNS AND PAINT EXTERIOR
4/1/18 $95K SPR RECEIVED 11/2/17. FUNDING REQUESTED 11/28/17. FUNDING RECEIVED 12/1/17. STRUCTURAL STEEL IN PLACE.
SOUTHERLAND, E.
5740 PROJ MGMT CONSTRUCTION