AND FIRST COURSE SHELL ON CONDENSATE TANK, SHARJAH, UAE Project Description: PROJECT: REPAIR AND REFURBISHMENT OF TANK BASE T C M Corrotech Construction Chemicals, P. O. Box 8344, Dubai, U.A.E.; Tel: +971 4 8112100; Fax: +971 4 8112101; www.mctuae.com page 1 of 1 / 27-CCCrefPUA-6 ISO 9000:2001 certified company The condensate tank base had lost its integrity, corrosion has damaged the floor due to water forming under the condensate, and being in direct contact with the steel, once the epoxy paint lining was damaged. Application took place in the following steps: 1. Corroded steel tank base and 1st course shell were grit blasted to SA 2.5 cleanliness and to a minimum 75 μm profile. 2. Corroprime EP SF was spray applied to the blasted area. 3. Corrocoat PUA SG was applied to 2.5 mm thickness with Graco XP-2 high pressure spray units. 4. All inlet high abrasion areas were sprayed to 5mm thickness to provide extra protection. Failure to attend to the corrosion problem would have caused the tank to condemn. To offer as a solution a similar rigid epoxy as previously applied, meant this would crack due to movement of the tank base causing premature failure again. Corrocoat PUA was specified as a long term protection system with flexibility. The complete process of surface-preparation and application of base coat was successfully completed in 10 days despite extreme HS regulations and conditions of spraying internally. Client Location Coating Contractor Consultant Project Product Area Date of application : BP / Petrofac : Dubai, U.A.E : Anticor LLC, Dubai : AMCE Inspection Group : Condensate Tank, Sharjah : Corroprime EPSF, Corrocoat PUA SG : Tank base and first course shell diameter 21m : September 2011 Project Information

Transcript of PROJECT: REPAIR AND REFURBISHMENT OF TANK BASE … · AND FIRST COURSE SHELL ON CONDENSATE TANK,...

Page 1: PROJECT: REPAIR AND REFURBISHMENT OF TANK BASE … · AND FIRST COURSE SHELL ON CONDENSATE TANK, SHARJAH, UAE Project Description: PROJECT: REPAIR AND REFURBISHMENT OF TANK BASE C

AND FIRST COURSE SHELL ON CONDENSATE TANK, SHARJAH, UAE

Project Description:

PROJECT: REPAIR AND REFURBISHMENT OF TANK BASE

TCM

Corrotech Construction Chemicals, P. O. Box 8344, Dubai, U.A.E.; Tel: +971 4 8112100; Fax: +971 4 8112101; www.mctuae.com

page 1 of 1 / 27-CCCrefPUA-6

ISO 9000:2001 certified company

The condensate tank base had lost its integrity, corrosion has damaged the floor due to water forming under the condensate, and being in direct contact with the steel, once the epoxy paint lining was damaged.

Application took place in the following steps:1. Corroded steel tank base and 1st course shell were grit blasted to SA 2.5 cleanliness and to a minimum 75 μm profile.

2. Corroprime EP SF was spray applied to the blasted area.

3. Corrocoat PUA SG was applied to 2.5 mm thickness with Graco XP-2 high pressure spray units.

4. All inlet high abrasion areas were sprayed to 5mm thickness to provide extra protection.

Failure to attend to the corrosion problem would have caused the tank to condemn. To offer as a solution a similar rigid epoxy as previously applied, meant this would crack due to movement of the tank base causing premature failure again. Corrocoat PUA was specified as a long term protection system with flexibility.

The complete process of surface-preparation and application of base coat was successfully completed in 10 days despite extreme HS regulations and conditions of spraying internally.

Client

Location

Coating Contractor

Consultant

Project

Product

Area

Date of application

: BP / Petrofac

: Dubai, U.A.E

: Anticor LLC, Dubai

: AMCE Inspection Group

: Condensate Tank, Sharjah

: Corroprime EPSF, Corrocoat PUA SG

: Tank base and first course shell diameter 21m

: September 2011