Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3...

57
Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03 Date : 2014-8-21

Transcript of Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3...

Page 1: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

Project:Renovation Works at Ricci Hall at 93 Pok Fu Lam Road

CSub-basement Level

VIEW 5

VIEW 3

VIEW 4

VIEW 2

VIEW 1

VIEW 6

PROGRESS PHOTO REPORT - 03Date : 2014-8-21

Page 2: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 1

2014-7-6

Descriptions

- Paint to wall was completed

2014-8-14

Page 3: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 2

Descriptions

- Paint to wall was completed

- A/C equipment has installed on site

2014-8-142014-7-6

Page 4: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 3

Descriptions

- Paint to wall was completed

2014-8-142014-7-6

Page 5: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 4

Descriptions

- Paint to wall was completed

2014-8-142014-7-6

Page 6: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 5

Descriptions

- Site condition

2014-8-142014-7-6

Page 7: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 6

Descriptions

- All the existing finish will be demolish

2014-8-142014-7-6

Page 8: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

Project:Renovation Works at Ricci Hall at 93 Pok Fu Lam Road

CGround Floor

VIEW 1

VIEW 2VIEW 5

VIEW 3

VIEW 6

VIEW 4

VIEW 7

VIEW 8

PROGRESS PHOTO REPORT - 03Date : 2014-8-21

Page 9: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 1

Descriptions

- Paint to wall was completed

2014-8-142014-7-6

Page 10: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 2

Descriptions

- Paint to wall was completed

- The door frame has installed

2014-8-142014-7-6

Page 11: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 3

Descriptions

- Paint to wall was completed

- Furniture arrived on site

2014-8-142014-7-6

Page 12: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 4

Descriptions

- Plastering works in progress

- The door frame has installed

2014-8-142014-7-6

Page 13: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 5

Descriptions

- Paint to wall was completed

2014-8-142014-7-6

Page 14: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 6

Descriptions

- Paint to wall was completed

2014-8-142014-7-6

Page 15: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 7

Descriptions

- Site condition

2014-8-142014-7-6

Page 16: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 8

Descriptions

- All the existing finish will be demolish

2014-8-142014-7-6

Page 17: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

Project:Renovation Works at Ricci Hall at 93 Pok Fu Lam Road

CFirst Floor

BGround Floor

AGround Floor

VIEW 3

VIEW 4

VIEW 2VIEW 1

VIEW 9VIEW 10 VIEW 13

VIEW 14

VIEW 12VIEW 11

VIEW 5

VIEW 6VIEW 7

VIEW 8VIEW 4

VIEW 2

VIEW 1

VIEW 3

VIEW 5

VIEW 6

VIEW 7

VIEW 8

VIEW 9

VIEW 10

VIEW 1

VIEW 2

VIEW 5

VIEW 6

VIEW 3

VIEW 4

VIEW 7

VIEW 8

PROGRESS PHOTO REPORT - 03Date : 2014-8-21

Page 18: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 1

Descriptions

- Paint to wall was completed

- Furniture arrived on site

AGround Floor

2014-8-142014-7-6

Page 19: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 2

Descriptions

- Paint to wall was completed

- Furniture arrived on site

AGround Floor

2014-8-142014-7-6

Page 20: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 3

Descriptions

- Plastering works in progress

- Furniture has installed

AGround Floor

2014-8-142014-7-6

Page 21: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 4

Descriptions

- Paint to wall was completed

AGround Floor

2014-8-142014-7-6

Page 22: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 5

Descriptions

- Plastering works in progress

- Furniture has installed

AGround Floor

2014-8-142014-7-6

Page 23: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 6

Descriptions

- Site condition

AGround Floor

2014-8-142014-7-6

Page 24: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 7

Descriptions

- Plastering works in progress

- Furniture has installed

AGround Floor

2014-8-142014-7-6

Page 25: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 8

Descriptions

- Plastering works in progress

- Furniture arrived on site

AGround Floor

2014-8-142014-7-6

Page 26: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 9

Descriptions

- Plastering works in progress

- Furniture has installed

AGround Floor

2014-8-142014-7-6

Page 27: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 10

Descriptions

- Site condition

AGround Floor

2014-8-142014-7-6

Page 28: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 1

Descriptions

- Plastering works in progress

- Furniture has installed

BGround Floor

2014-8-142014-7-6

Page 29: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 2

Descriptions

- Site condition

BGround Floor

2014-8-142014-7-6

Page 30: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 3

Descriptions

- Plastering works in progress

- Furniture has installed

BGround Floor

2014-8-142014-7-6

Page 31: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 4

Descriptions

- Paint to wall was completed

BGround Floor

2014-8-142014-7-6

Page 32: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 5

Descriptions

- Plastering works in progress

- Furniture has installed

BGround Floor

2014-8-142014-7-6

Page 33: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 6

Descriptions

- Site condition

BGround Floor

2014-8-142014-7-6

Page 34: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 7

Descriptions

- Plastering works in progress

- Furniture has installed

BGround Floor

2014-8-142014-7-6

Page 35: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 8

Descriptions

- Furniture arrived on site

BGround Floor

2014-8-142014-7-6

Page 36: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 9

Descriptions

- Paint to wall was completed

- The door frame has installed

BGround Floor

2014-8-142014-7-6

Page 37: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 10

Descriptions

- Paint to wall was completed

- The door frame has installed

BGround Floor

2014-8-142014-7-6

Page 38: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 11

Descriptions

- All the existing finish will be demolish

BGround Floor

2014-8-142014-7-6

Page 39: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 12

Descriptions

- All the existing finish will be demolish

- Site material arrived on site

BGround Floor

2014-8-142014-7-6

Page 40: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 13

Descriptions

- Paint to wall was completed

BGround Floor

2014-8-142014-7-6

Page 41: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 14

Descriptions

- Paint to wall was completed

BGround Floor

2014-8-142014-7-6

Page 42: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 1

Descriptions

- Plastering works in progress

CGround Floor

2014-8-142014-7-6

Page 43: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 2

Descriptions

- Furniture arrived on site

CGround Floor

2014-8-142014-7-6

Page 44: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 3

Descriptions

- Plastering works in progress

- Furniture arrived on site

CGround Floor

2014-8-142014-7-6

Page 45: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 4

Descriptions

- Furniture arrived on site

CGround Floor

2014-8-142014-7-6

Page 46: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 5

Descriptions

- Furniture arrived on site

CGround Floor

2014-8-142014-7-6

Page 47: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 6

Descriptions

- Plastering works in progress

CGround Floor

2014-8--142014-7-6

Page 48: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 7

Descriptions

- Paint to wall was completed

CGround Floor

2014-8-142014-7-6

Page 49: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 8

Descriptions

- Paint to wall was completed

CGround Floor

2014-8-142014-7-6

Page 50: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

Project:Renovation Works at Ricci Hall at 93 Pok Fu Lam Road

BFirst Floor

EFirst Floor

EFirst Floor

VIEW 2

VIEW 3

VIEW 1

VIEW 2

VIEW 1VIEW 1

VIEW 2

PROGRESS PHOTO REPORT - 03Date : 2014-8-21

Page 51: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 1

Descriptions

- Plastering works in progress

BFirst Floor

2014-8-142014-7-6

Page 52: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 2

Descriptions

- Plastering works in progress

BFirst Floor

2014-8-142014-7-6

Page 53: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 4

Descriptions

- Tile works was completed

BFirst Floor

2014-8-142014-7-6

Page 54: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 1

Descriptions

- Tile works was completed

EFirst Floor

Female Toilet & Disable toilet

2014-8-142014-7-6

Page 55: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 2

Descriptions

- Tile works was completed

EFirst Floor

Female Toilet & Disable toilet

2014-8-142014-7-6

Page 56: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 1

Descriptions

- Plastering works in progress

- The door frame has installed

EFirst Floor

Male Toilet

2014-8-142014-7-6

Page 57: Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.

VIEW 2

Descriptions

- Plastering works in progress

- The door frame has installed

EFirst Floor

Male Toilet

2014-8-142014-7-6