project management snspa
-
Upload
camelia-cami -
Category
Documents
-
view
230 -
download
0
Transcript of project management snspa
-
8/13/2019 project management snspa
1/31
1
Project Management course notes 1st semester
Simona Bonghez, Ph.DLoredana Radu, Ph.D, MBA
-
8/13/2019 project management snspa
2/31
2
Project?
A project is a temporary endeavor undertaken to create a unique product,service, or result
(PMBOK Guide 4th Edition, p. 5)
A temporary organisation for the performance of a relatively unique, short tomedium term, strategically important process of medium or large scope(Happy Projects!, Gareis, R., Manz, Vienna 2006)
PM M
Project A
PM
Project B
-
8/13/2019 project management snspa
3/31
Project characteristics
Temporary Definite beginning and definite end (... does not necessarily mean short in duration)
Unique Product, Service, or Result ( although repetitive elements maybe present in some project deliverables)
A product can be either an end item in itself or a component item A capability to perform a service, such as business functions supporting
production or distribution A result such as outcomes or documents (e.g. research project develops
knowledge)
Progressive Elaboration Means developing in steps, and continuing by increments
-
8/13/2019 project management snspa
4/31
4
Project: A Social System
Project boundaries, project contextRelative project autonomy, self-organising
PROJECT
CONTEXT
-
8/13/2019 project management snspa
5/31
What is Project Management?
The application of knowledge, skills, tools, and techniques toproject activities in order to meet project requirements
(PMBOK Guide 4th Edition, p. 6)
Project Management is accomplished through the appropriate
application and integration of the42 logically grouped projectmanagement processes comprising the 5 process groups . These 5process groups are:
Initiating Planning
Executing Monitoring &Controlling Closing
(PMBOK Guide 5th Edition, p. 6)
-
8/13/2019 project management snspa
6/31
Knowledge Area
Process Group
Initiating Planning Executing Monitoring & Controlling Closing
Integration 4.1 DevelopProjectCharter
4.2 Develop ProjectManagement Plan
4.3 Direct and Manage ProjectWork
4.4 Monitor and Control ProjectWork4.5 Perform Integrated ChangeControl
4.6 Close Project orPhase
Scope 5.1 Plan Scope Management5.2 Collect Requirements
5.3 Define Scope5.4 Create WBS
5.5 Validate Scope5.6 Control Scope
Time 6.1 Plan Schedule Management6.2 Define Activities6.3 Sequence Activities6.4 Estimate Activity Resources6.5 Estimate Activity Duration6.6 Develop Schedule
6.7 Control Schedule
Cost 7.1 Plan Cost Management7.2 Estimate Costs7.3 Determine Budget
7.4 Control Costs
Quality 8.1 Plan Quality Management 8.2 Perform Quality Assurance 8.3 Control Quality
HR 9.1 Plan Human ResourceManagement
9.2 Acquire Project Team9.3 Develop Project Team9.4 Manage Project Team
Communications 10.1 Plan CommunicationsManagement
10.2 Manage Communications 10.3 Control Communications
Risk 11.1 Plan Risk Management11.2 Identify Risks11.3 Perform Qualitative RiskAnalysis11.4 Perform Quantitative RiskAnalysis11.5 Plan Risk Responses
11.6 Control Risks
Procurement 12.1 Plan ProcurementManagement
12.2 Conduct Procurements 12.3 Control Procurements 12.4 CloseProcurements
Stakeholder 13.1 IdentifyStakeholders
13.2 Plan StakeholderManagement
13.3 Manage StakeholderEngagement
13.4 Control StakeholderEngagement
-
8/13/2019 project management snspa
7/31
Typical Cost and Staffing levels across theproject life cycle
Startingthe
project
C o s
t a n
d S t a f f i n g
l e v e
l Organizingandpreparing
Carrying out the work Closingthe
project
Time
ProjectCharter
ProjectManagement Plan
AcceptedDeliverables
ArchivedProject
Documents
ProjectManagement
Outputs
(PMBOK Guide 4th Edition, p.16)
-
8/13/2019 project management snspa
8/31
8
Objects of consideration ofproject management
Objectives, deliverables, schedule, resources,budget, income, riskOrganisation, culture, personnel,infrastructureContext: Pre-, post project-phase,stakeholders, other projects, companystrategies, business case
Scope
Schedule Budget
-
8/13/2019 project management snspa
9/31
9
Project management and content activities What is wrong inthe schedule below?
months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Project managementDetailed planningImplementationTest and trainingInitial operationPilot operation
Follow-up
Work package
P - Start P - -CloseDown
-
8/13/2019 project management snspa
10/31
10
Map of Processes: IT Company
A n g e b o
t s -
l e g u n
g
Markt - forschung
BusinessDevelop-
ment
A u
f t r a g s -
A b w
i c k l u n g
A P r e -
S a
l e s
Clients
PartnerDevelop
ment
A u
f t r a g s -
A b w
i c l u n g
B P r o p o s a
l
P r e p e
r a t i o n
S e r v i c e
C o n t r a c
t i n g
PR Werbung
S e r v i c e
C o n t r a c
t t o
R e
f e r n c e
Werbung
L e a
d t o
O p p o
r t u n
i t y
charter ofa Project
ProjectPortfolio-
Management
Primaryprocesses
Secondaryprocesses
Tertiaryprocesses
StrategicPlanning
Campaignto Lead
C o n
t a c
t
t o L e a
d
PRProductDevelopment
ServiceDevelop-
ment
Forecasting
-
8/13/2019 project management snspa
11/31
11
Adequate organisations for different processes
Processcharacteristic Attribute
Frequency often once once
Scope small-medium medium-large large
Importance low medium-high high
Duration short short-medium medium-long
Resources few some many
Costs low-medium medium-high high
Number oforganizations
few several-many many
Type of organization Permanent
organization ProjectProgramme
Managementapproaches
Processmanagement
Projectmanagement
Programmemanagement
-
8/13/2019 project management snspa
12/31
12
Example: Project definition of an Austrian Bank
Criterion Small Project Project Programme
StrategicImportance
Small Medium to high High
Duration at least 2 months at least 4 months at least 21months
Organisationsinvolved
at least 3organisations(inclusive externalpartners)
at least 5organisations(inclusive externalpartners)
at least 7organisations(inclusive externalpartners)
Resources at least 100person-days at least 200person-days at least 500 person-days
Costs at least 0,1 Mio at least 1,0 Mio at least 10 Mio
-
8/13/2019 project management snspa
13/31
13
Checklist for the Application of Methods inthe Planning process group (example)
Application of Methods in the PlanningProcess Group
Small Project Project
Planning Methods
Project objectives plan must must
Objects of consideration plan mustProject work breakdown structure must must
Project work package specification
Project bar chart must must
Project finance plan
Project cost plan must must
Business case analysis must
-
8/13/2019 project management snspa
14/31
14
Multi-Methods Approach
The use of a multi-method approach relates to the project complexity.
Different project management methods have be used depending on theproject complexity.
For different planning methods different levels of detail are necessary.
Planning results can be standardised for repetitive projects.
By relating methods to each other the project management quality isassured.
-
8/13/2019 project management snspa
15/31
15
Programme: Definition
A temporary organisation for the fulfilment of a unique process, which is ofhigh strategic importance and time-limited.Programmes consist of projects and work packages which are closely coupledby programme structures.
-
8/13/2019 project management snspa
16/31
Programme Name Programme Objective Company Railway stations initiative Revitalising of 40
austrian railway stations sterreichischeBundesbahnen
LKS 2000 Reorganisation of theLandeskliniken Salzburg
Landeskli niken Salzburg
Statoil SAP Implementation of SAP atStatoil
Statoil
programm I austria The austrian Project Managment - Initiative
PMG und PROJEKTMANAGEMENT AUSTRIA
STAR 2000 Migration of SW - Systemsof Lufthansa and AUA
Austrian Airlines
eBanking & eBrokerage Establisment of eBanking and eBrokerage - Companies
ABN AMRO
Symphonie Merger of the banksBawag and PSK
Bawag/PSK
Programme: Examples
16
-
8/13/2019 project management snspa
17/31
17
Different Types of Projects
Criterion Project type Relation to processes primary, secondary, tertiary processesIndustry construction, engineering, IT
pharmaceutical, NPO, etc.Location national, internationalContent customer relations, products and markets,
infrastructure, personnel, organisation
Investment phase study, conception, realisation, re-launch ormaintenance
Degree of repetition unique, repetitiveCustomer internal customer, external customerDuration short-, medium-, long term
-
8/13/2019 project management snspa
18/31
18
Projects in the Investment Life Cycle
-
8/13/2019 project management snspa
19/31
Case study
-
8/13/2019 project management snspa
20/31
20
Project assignment/charter (project initiationdocument)
-
8/13/2019 project management snspa
21/31
Objects of consideration
RealizationeApplication
21
-
8/13/2019 project management snspa
22/31
Documentde iniiereproiect /
ProjectCharter
Titlu proiectOrganizare evenimentStrike Force Competition
Initiator proiectAsociatia Speciala deAirsoft
Data demarare 01.03.2012 Data incheiere 08.06.2012
Manager proiect Secretar Executiv ASAProprietarproiect
Presedinte ASA
Obiective generale proiect Non-obiective proiect
Organizarea unei competitii de airsoft cuatragerea publicului minim 3 echipe, maxim 6 echipe (5 membri) maxim 100 spectatori data desfasurare: 2 iunie 2012 autofinatata
Instruirea participantilor la competitia deairsoft
Formarea echipelor participante de catreorganizatori
Furnizarea de echipamente de protectie pedurata competitiei
Obiective de business
Promovarea imaginii Asociatiei Speciale de Airsoft Promovarea airsoft-ului in Romania
Buget estimat 45.000 euro + 130 zile om Venituri 0
Roluri in echipa de proiect Stakeholderi
Responsabil contracte Responsabil infrastructura competitie Responsabil program artistic si infrastructura
aferenta Responsabil zone acces public Responsabil relatii publice si legatura cu
agentia de organizare Responsabil desfasurare eveniment
Asociatia Speciala de Airsoft Cluburi sportive Participanti competitie Spectatori competitie Parteneri eveniment Sponsori eveniment Directia Generala de Politie a Municipiului
Bucuresti (SAEST)Ipoteze Constrangeri
Ipoteze: Terenul va fi pus la dispozitie de MAI. Echipele inscrise detin autorizatiile si
permisele necesare. Participantii indeplinesc conditiile de
rezistenta fizica necesare acestui tip decompetitie.
Autorizatii si premise impuse de legislatie. Limitare numar participanti la suprafata
disponibila Autofinantare
Semnatura proprietar proiect Semnatura manager proiect
-
8/13/2019 project management snspa
23/31
-
8/13/2019 project management snspa
24/31
-
8/13/2019 project management snspa
25/31
Work Breakdown Structure
25
-
8/13/2019 project management snspa
26/31
26
Work Package Specifications
-
8/13/2019 project management snspa
27/31
What is the WBS?
Students favorite tool
WBS is a tools that is used to:
Define the projects scope of work Provide the PM team with a framework on which tobase project status and progress reports
Facilitate communication between the PM and the
project stakeholders As a key input to other PM processes and deliverables.
-
8/13/2019 project management snspa
28/31
The 100% rule
WBS includes 100% of the work defined by the project scope and capturesall deliverables in terms of work to be completed, including projectmanagement.
-
8/13/2019 project management snspa
29/31
Project deliverable
Any unique and verifiable product, result, or capability to perform a servicethat must be produced to complete a process, phase or project.
-
8/13/2019 project management snspa
30/31
A poorly constructed WBS
Incomplete project definitions leading to ongoing project extensionsUnclear work assignments, goals, objectives, or deliverablesScope creep, frequently changing scopeBudget overrunMissed deadlinesUnusable new product
-
8/13/2019 project management snspa
31/31
WBS creation methods
Top-downBottom-upStandardsSpecial templates