project management snspa

download project management snspa

of 31

Transcript of project management snspa

  • 8/13/2019 project management snspa

    1/31

    1

    Project Management course notes 1st semester

    Simona Bonghez, Ph.DLoredana Radu, Ph.D, MBA

  • 8/13/2019 project management snspa

    2/31

    2

    Project?

    A project is a temporary endeavor undertaken to create a unique product,service, or result

    (PMBOK Guide 4th Edition, p. 5)

    A temporary organisation for the performance of a relatively unique, short tomedium term, strategically important process of medium or large scope(Happy Projects!, Gareis, R., Manz, Vienna 2006)

    PM M

    Project A

    PM

    Project B

  • 8/13/2019 project management snspa

    3/31

    Project characteristics

    Temporary Definite beginning and definite end (... does not necessarily mean short in duration)

    Unique Product, Service, or Result ( although repetitive elements maybe present in some project deliverables)

    A product can be either an end item in itself or a component item A capability to perform a service, such as business functions supporting

    production or distribution A result such as outcomes or documents (e.g. research project develops

    knowledge)

    Progressive Elaboration Means developing in steps, and continuing by increments

  • 8/13/2019 project management snspa

    4/31

    4

    Project: A Social System

    Project boundaries, project contextRelative project autonomy, self-organising

    PROJECT

    CONTEXT

  • 8/13/2019 project management snspa

    5/31

    What is Project Management?

    The application of knowledge, skills, tools, and techniques toproject activities in order to meet project requirements

    (PMBOK Guide 4th Edition, p. 6)

    Project Management is accomplished through the appropriate

    application and integration of the42 logically grouped projectmanagement processes comprising the 5 process groups . These 5process groups are:

    Initiating Planning

    Executing Monitoring &Controlling Closing

    (PMBOK Guide 5th Edition, p. 6)

  • 8/13/2019 project management snspa

    6/31

    Knowledge Area

    Process Group

    Initiating Planning Executing Monitoring & Controlling Closing

    Integration 4.1 DevelopProjectCharter

    4.2 Develop ProjectManagement Plan

    4.3 Direct and Manage ProjectWork

    4.4 Monitor and Control ProjectWork4.5 Perform Integrated ChangeControl

    4.6 Close Project orPhase

    Scope 5.1 Plan Scope Management5.2 Collect Requirements

    5.3 Define Scope5.4 Create WBS

    5.5 Validate Scope5.6 Control Scope

    Time 6.1 Plan Schedule Management6.2 Define Activities6.3 Sequence Activities6.4 Estimate Activity Resources6.5 Estimate Activity Duration6.6 Develop Schedule

    6.7 Control Schedule

    Cost 7.1 Plan Cost Management7.2 Estimate Costs7.3 Determine Budget

    7.4 Control Costs

    Quality 8.1 Plan Quality Management 8.2 Perform Quality Assurance 8.3 Control Quality

    HR 9.1 Plan Human ResourceManagement

    9.2 Acquire Project Team9.3 Develop Project Team9.4 Manage Project Team

    Communications 10.1 Plan CommunicationsManagement

    10.2 Manage Communications 10.3 Control Communications

    Risk 11.1 Plan Risk Management11.2 Identify Risks11.3 Perform Qualitative RiskAnalysis11.4 Perform Quantitative RiskAnalysis11.5 Plan Risk Responses

    11.6 Control Risks

    Procurement 12.1 Plan ProcurementManagement

    12.2 Conduct Procurements 12.3 Control Procurements 12.4 CloseProcurements

    Stakeholder 13.1 IdentifyStakeholders

    13.2 Plan StakeholderManagement

    13.3 Manage StakeholderEngagement

    13.4 Control StakeholderEngagement

  • 8/13/2019 project management snspa

    7/31

    Typical Cost and Staffing levels across theproject life cycle

    Startingthe

    project

    C o s

    t a n

    d S t a f f i n g

    l e v e

    l Organizingandpreparing

    Carrying out the work Closingthe

    project

    Time

    ProjectCharter

    ProjectManagement Plan

    AcceptedDeliverables

    ArchivedProject

    Documents

    ProjectManagement

    Outputs

    (PMBOK Guide 4th Edition, p.16)

  • 8/13/2019 project management snspa

    8/31

    8

    Objects of consideration ofproject management

    Objectives, deliverables, schedule, resources,budget, income, riskOrganisation, culture, personnel,infrastructureContext: Pre-, post project-phase,stakeholders, other projects, companystrategies, business case

    Scope

    Schedule Budget

  • 8/13/2019 project management snspa

    9/31

    9

    Project management and content activities What is wrong inthe schedule below?

    months 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    Project managementDetailed planningImplementationTest and trainingInitial operationPilot operation

    Follow-up

    Work package

    P - Start P - -CloseDown

  • 8/13/2019 project management snspa

    10/31

    10

    Map of Processes: IT Company

    A n g e b o

    t s -

    l e g u n

    g

    Markt - forschung

    BusinessDevelop-

    ment

    A u

    f t r a g s -

    A b w

    i c k l u n g

    A P r e -

    S a

    l e s

    Clients

    PartnerDevelop

    ment

    A u

    f t r a g s -

    A b w

    i c l u n g

    B P r o p o s a

    l

    P r e p e

    r a t i o n

    S e r v i c e

    C o n t r a c

    t i n g

    PR Werbung

    S e r v i c e

    C o n t r a c

    t t o

    R e

    f e r n c e

    Werbung

    L e a

    d t o

    O p p o

    r t u n

    i t y

    charter ofa Project

    ProjectPortfolio-

    Management

    Primaryprocesses

    Secondaryprocesses

    Tertiaryprocesses

    StrategicPlanning

    Campaignto Lead

    C o n

    t a c

    t

    t o L e a

    d

    PRProductDevelopment

    ServiceDevelop-

    ment

    Forecasting

  • 8/13/2019 project management snspa

    11/31

    11

    Adequate organisations for different processes

    Processcharacteristic Attribute

    Frequency often once once

    Scope small-medium medium-large large

    Importance low medium-high high

    Duration short short-medium medium-long

    Resources few some many

    Costs low-medium medium-high high

    Number oforganizations

    few several-many many

    Type of organization Permanent

    organization ProjectProgramme

    Managementapproaches

    Processmanagement

    Projectmanagement

    Programmemanagement

  • 8/13/2019 project management snspa

    12/31

    12

    Example: Project definition of an Austrian Bank

    Criterion Small Project Project Programme

    StrategicImportance

    Small Medium to high High

    Duration at least 2 months at least 4 months at least 21months

    Organisationsinvolved

    at least 3organisations(inclusive externalpartners)

    at least 5organisations(inclusive externalpartners)

    at least 7organisations(inclusive externalpartners)

    Resources at least 100person-days at least 200person-days at least 500 person-days

    Costs at least 0,1 Mio at least 1,0 Mio at least 10 Mio

  • 8/13/2019 project management snspa

    13/31

    13

    Checklist for the Application of Methods inthe Planning process group (example)

    Application of Methods in the PlanningProcess Group

    Small Project Project

    Planning Methods

    Project objectives plan must must

    Objects of consideration plan mustProject work breakdown structure must must

    Project work package specification

    Project bar chart must must

    Project finance plan

    Project cost plan must must

    Business case analysis must

  • 8/13/2019 project management snspa

    14/31

    14

    Multi-Methods Approach

    The use of a multi-method approach relates to the project complexity.

    Different project management methods have be used depending on theproject complexity.

    For different planning methods different levels of detail are necessary.

    Planning results can be standardised for repetitive projects.

    By relating methods to each other the project management quality isassured.

  • 8/13/2019 project management snspa

    15/31

    15

    Programme: Definition

    A temporary organisation for the fulfilment of a unique process, which is ofhigh strategic importance and time-limited.Programmes consist of projects and work packages which are closely coupledby programme structures.

  • 8/13/2019 project management snspa

    16/31

    Programme Name Programme Objective Company Railway stations initiative Revitalising of 40

    austrian railway stations sterreichischeBundesbahnen

    LKS 2000 Reorganisation of theLandeskliniken Salzburg

    Landeskli niken Salzburg

    Statoil SAP Implementation of SAP atStatoil

    Statoil

    programm I austria The austrian Project Managment - Initiative

    PMG und PROJEKTMANAGEMENT AUSTRIA

    STAR 2000 Migration of SW - Systemsof Lufthansa and AUA

    Austrian Airlines

    eBanking & eBrokerage Establisment of eBanking and eBrokerage - Companies

    ABN AMRO

    Symphonie Merger of the banksBawag and PSK

    Bawag/PSK

    Programme: Examples

    16

  • 8/13/2019 project management snspa

    17/31

    17

    Different Types of Projects

    Criterion Project type Relation to processes primary, secondary, tertiary processesIndustry construction, engineering, IT

    pharmaceutical, NPO, etc.Location national, internationalContent customer relations, products and markets,

    infrastructure, personnel, organisation

    Investment phase study, conception, realisation, re-launch ormaintenance

    Degree of repetition unique, repetitiveCustomer internal customer, external customerDuration short-, medium-, long term

  • 8/13/2019 project management snspa

    18/31

    18

    Projects in the Investment Life Cycle

  • 8/13/2019 project management snspa

    19/31

    Case study

  • 8/13/2019 project management snspa

    20/31

    20

    Project assignment/charter (project initiationdocument)

  • 8/13/2019 project management snspa

    21/31

    Objects of consideration

    RealizationeApplication

    21

  • 8/13/2019 project management snspa

    22/31

    Documentde iniiereproiect /

    ProjectCharter

    Titlu proiectOrganizare evenimentStrike Force Competition

    Initiator proiectAsociatia Speciala deAirsoft

    Data demarare 01.03.2012 Data incheiere 08.06.2012

    Manager proiect Secretar Executiv ASAProprietarproiect

    Presedinte ASA

    Obiective generale proiect Non-obiective proiect

    Organizarea unei competitii de airsoft cuatragerea publicului minim 3 echipe, maxim 6 echipe (5 membri) maxim 100 spectatori data desfasurare: 2 iunie 2012 autofinatata

    Instruirea participantilor la competitia deairsoft

    Formarea echipelor participante de catreorganizatori

    Furnizarea de echipamente de protectie pedurata competitiei

    Obiective de business

    Promovarea imaginii Asociatiei Speciale de Airsoft Promovarea airsoft-ului in Romania

    Buget estimat 45.000 euro + 130 zile om Venituri 0

    Roluri in echipa de proiect Stakeholderi

    Responsabil contracte Responsabil infrastructura competitie Responsabil program artistic si infrastructura

    aferenta Responsabil zone acces public Responsabil relatii publice si legatura cu

    agentia de organizare Responsabil desfasurare eveniment

    Asociatia Speciala de Airsoft Cluburi sportive Participanti competitie Spectatori competitie Parteneri eveniment Sponsori eveniment Directia Generala de Politie a Municipiului

    Bucuresti (SAEST)Ipoteze Constrangeri

    Ipoteze: Terenul va fi pus la dispozitie de MAI. Echipele inscrise detin autorizatiile si

    permisele necesare. Participantii indeplinesc conditiile de

    rezistenta fizica necesare acestui tip decompetitie.

    Autorizatii si premise impuse de legislatie. Limitare numar participanti la suprafata

    disponibila Autofinantare

    Semnatura proprietar proiect Semnatura manager proiect

  • 8/13/2019 project management snspa

    23/31

  • 8/13/2019 project management snspa

    24/31

  • 8/13/2019 project management snspa

    25/31

    Work Breakdown Structure

    25

  • 8/13/2019 project management snspa

    26/31

    26

    Work Package Specifications

  • 8/13/2019 project management snspa

    27/31

    What is the WBS?

    Students favorite tool

    WBS is a tools that is used to:

    Define the projects scope of work Provide the PM team with a framework on which tobase project status and progress reports

    Facilitate communication between the PM and the

    project stakeholders As a key input to other PM processes and deliverables.

  • 8/13/2019 project management snspa

    28/31

    The 100% rule

    WBS includes 100% of the work defined by the project scope and capturesall deliverables in terms of work to be completed, including projectmanagement.

  • 8/13/2019 project management snspa

    29/31

    Project deliverable

    Any unique and verifiable product, result, or capability to perform a servicethat must be produced to complete a process, phase or project.

  • 8/13/2019 project management snspa

    30/31

    A poorly constructed WBS

    Incomplete project definitions leading to ongoing project extensionsUnclear work assignments, goals, objectives, or deliverablesScope creep, frequently changing scopeBudget overrunMissed deadlinesUnusable new product

  • 8/13/2019 project management snspa

    31/31

    WBS creation methods

    Top-downBottom-upStandardsSpecial templates