Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter...

34
Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1 Project: El Chaguite Water System

Transcript of Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter...

Page 1: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Project Location: El Chaguite, Yoro District, Honduras

Northeastern University’s Student Chapter

1Project: El Chaguite Water System

Page 2: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Project: El Chaguite Water System 2

Page 3: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Project: El Chaguite Water System 3

Page 4: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Project: El Chaguite Water System 4

Page 5: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Guides

Project: El Chaguite Water System 5

Page 6: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

El Tecuan

Project: El Chaguite Water System 6

Page 7: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Los Planes

Project: El Chaguite Water System 7

Page 8: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Project Schedule

Project: El Chaguite Water System 8

Dates of Travel Purpose Description

December 2007 Los Planes Implementation & El Chaguite Assessment

Complete Transmission Main in Los Planes, Visit El Chaguite

April – May 2008 El Chaguite Assess. Water Quality, Hydraulic Investigations, Existing System Inspections, Topographic Survey, Health Survey

December 14- December 29, 2008

El Chaguite Phase 1 Implementation

Construct Transmission Main/ Begin Distribution System

April – May 2010(proposed)

El Chaguite Phase 2 Implementation

Storage Tank/ Finish Distribution System

Page 9: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

El Chaguite Existing System

9Project: El Chaguite Water System

Page 10: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Existing Conditions

Project: El Chaguite Water System 10

• Sufficient, clean water source• Limited service• Unusable distribution system• Damaged main line• Diverse topography• Hurricane damage• Fire damage

Page 11: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

11Project: El Chaguite Water System

Page 12: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Current and Future Conditions

Project: El Chaguite Water System 12

Chaguite now: Chaguite in 25 years:

60 homes 87 homes

333 people 483 people

68 students 99 students

Conditions now: Conditions in 25 years

Total Average Available Flow (GPD)

22,349Total Average Available Flow (GPD)

22,349

Total Average Demand for People (GPD)

8,797Total Average Demand for People (GPD)

12,755

Total Average Demand for Irrigation (GPD)

3,000Total Average Demand for Irrigation (GPD)

4,350

Total Demand (GPD) 11,797 Total Demand (GPD) 17,105

Page 13: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Design Details

• Feasibility

• Transmission Main

• Distribution Network

• Float Valve Tank

• Sustainability

Project: El Chaguite Water System 13

Page 14: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

El ChaguitePopulation: 333 people

Project: El Chaguite Water System 14

Page 15: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Overall Feasibility

Project: El Chaguite Water System 15

• Water Source : 15.52 gpm (22,348 gallons/day)

• 25 year projected demand: 12,755 gpd

+4,350 gpd (Irrigation use)

17,105 gpd• Diurnal Demand Cycle

• Conclusion: Feasible with water storage tank

Page 16: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Design Process

Project: El Chaguite Water System 16

• Excel water flow model• WaterGEMS flow model• Multi-phase implementation

• Phase 1 (COMPLETE)– Construct Transmission Main– Instruct villagers on

construction of distribution system

– Build break pressure tank (float-valve tank)

• Phase 2– Water storage tank– Inspect village-constructed

distribution system

Page 17: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Transmission Main

Project: El Chaguite Water System 17

SourceProposed Tank Site

Existing Tank Site

Page 18: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Transmission Main

Project: El Chaguite Water System 18

Page 19: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Float Valve Tank

Project: El Chaguite Water System 19

Page 20: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Alternatives Considered

Project: El Chaguite Water System 20

North Water Storage Tank East Water Storage Tank

Page 21: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Distribution System Model

Project: El Chaguite Water System 21

Page 22: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

El Chaguite

Project: El Chaguite Water System 22

Page 23: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Transmission Main

Project: El Chaguite Water System 23

Page 24: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Trench Detail

Project: El Chaguite Water System 24

Page 25: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Trench Examples

Project: El Chaguite Water System 25

Page 26: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Tank Design

Page 27: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Trip Schedule

Project: El Chaguite Water System 27

Jun-11Fly to San Pedro SulaGet Supplies Order MaterialsVisit Rigo

Jun-12Buy GroceriesOrder Rest of SuppliesResearch Pumps for Carrizalito Project

Jun-13Drive To RosarioMeet with Village and Present DesignLay out Tank Site

Jun-14Dig Tank SiteTransport Bricks, Cement, Rebar, etc.

Jun-15 Train Villagers our process for concreteJun-16 Layout casting of FoundationJun-17 Cast Foundation

Jun-18Inspect Distribution System - Day 1Install Services - Day 1

Jun-19Start Walls of TankInspect Distribution System - Day 2Install Services - Day 2

Jun-20Visit Los PlanesVisit El Tecuan

Jun-21Survey CarrizalitoTake a trip to Yoro

Jun-22Cut GI pipe for tankVisit El Rosario School

Jun-23 Visit El Chaguite SchoolJun-24 Final Meeting With El ChaguiteJun-25 Drive to San Pedro SulaJun-26 Fly back to Boston

Page 28: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Budget

Project: El Chaguite Water System 28

El Chaguite Phase 2 Estimated Budget

Travel

Airfare $ 4,800

Exit Fees $ 210

Truck Rental $ 1,300

Gas $ 120

GroundHotel $ 300

Food $ 600

Labor

Guides $ 240

Laundress $ 100

Cooks $ 240

Materials

PVC Fittings/Valves $ 180

GI Pipes & Fittings $ 281

Tools $ 164

Tank Materials $ 1,365

Contingency $ 928

Total $ 10,827

Page 29: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Building Materials

Project: El Chaguite Water System 29

Page 30: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Sustainability• Extra materials supplied for maintenance and replacement.

• Locals will be educated on water conservation and proper system maintenance.

• Water Board willcollect usage tax to fund future repairs.

• Simple design and construction

Project: El Chaguite Water System 30

Page 31: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Community Ownership & Education

Project: El Chaguite Water System 31

• What kind of help will the community be providing?– Labor (digging trench, laying pipe, mixing cement, transporting

materials).– We will coordinate a schedule of construction with El Chaguite’s

Water Board.

• Who will own the project once it’s completed? – El Chaguite will own the water system upon completion of the

project. The El Chaguite Water Board will manage the communally used infrastructure.

Page 32: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Community Ownership & Education

Project: El Chaguite Water System 32

• Who will be overseeing maintenance once the team leaves and how will repairs be paid for?– El Chaguite’s Water Board will be overseeing the maintenance

of the system. We will leave extra materials with the villagers to take care of any immediate necessary repairs. Hopefully, with improved health, the villagers will be able to establish community funds and pay for repairs further in the future.

• What education will be provided to the community?– The community will be educated on the maintenance of the

system, and we also plan to provide information about health and sanitation. In order for this to be a successful effort we will be working with the community Water Board and local organizations to ensure that the people understand the situation and are well informed about health and sanitation issues.

Page 33: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Project Lead Sign-Off

Project: El Chaguite Water System 33

• I, Daniel P. Saulnier, P.E., as the Professional Mentor of this project, have reviewed the technical and logistical contents of this project, and approve of the proposed design. I will also comply with TAC recommended changes and make suggested changes before traveling on the implementation trip.

• Daniel P. Saulnier October 8, 2008 [signed]

Page 34: Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.

Questions?

Project: El Chaguite Water System 34

Thank you for your attention. This slide

concludes our formal presentation.