Start Here Welcome to Project KickStart 6 Introduction 7 Welcome to Project KickStart 7 Use Project KickStart to 8 Use the Planning Wizard 9 Navigating Project KickStart 10 Whats New in Project KickStart Pro 5 11 Whats New in Project KickStart Pro 5 (Pro Users) 12 Compatibility with earlier versions 13 Activating Trial Version 14 Licenses and Support 16 End User License Agreement 16 Customer Support 20 Reporting Technical Issues 21 Register Project KickStart 22Planning Projects 23 Name Your Project 23 Phases - Step 1 of 2 24 Phases - Step 2 of 2 25 Goals - Step 1 of 3 26 Goals - Step 2 of 2 27 Goals - Step 3 of 3 28 Similar Projects - Step 1 of 2 29 Similar Projects - Step 2 of 2 30 People - Step 1 of 3 31 People - Step 2 of 3 32 People - Step 3 of 3 33 Obstacles - Step 1 of 3 34 Obstacles - Step 2 of 3 35 Obstacles - Step 3 of 3 36Assigning People 37 Assign Tasks to People 37 Remove People from a Task 38 Add a New Person or Resource 39 Edit or Substitute People 40Organizing the Project Plan 41 About Organizing Tasks 41 Change the Appearance of the Task List 43 Show or Hide Tasks in the Task List 44 Move Tasks within the Task List 45 Outdent and Indent Tasks 46 Add a Task or Subtask 47 Edit Tasks 48 Add Task Notes and Attachments 49 Add or Change Task Assignments 51 Add or Change Task Details 52 Check Spelling 53Scheduling Tasks in the Gantt Chart 54 Scheduling Overview 55 About Scheduling Tasks 55

4

copy Experience In Software Inc 1995 - 2006

About the Gantt Chart 57 Autolink tasks (Pro Users) 58 About Linking Tasks (Pro Users) 59 Change the Display of the Schedule 61 Use the Gantt Chart Toolbar 63 Use the Gantt Chart Toolbar (Pro Users) 65 Understand Task Data View 66 Additional Features in Task Data View (Pro Users) 68 Understand Chart View 69 Additional Tools in Chart View (Pro Users) 71 Change Task Dates 73 Phase Dates Cannot Be Edited 75 Quick Tour of Working with Linked Tasks (Pro Users) 76 Link and Unlink Tasks (Pro Users) 78 Create a Milestone 79 Change Task Details 80 Change Details for Linked Tasks (Pro Users) 81 Reorganize Tasks in Task Data View 83 Change the Timescale of the Schedule 84 Specify Working Days 85 Change the Color of Taskbars 86 Make Tasks Overlap (Pro Users) 87 Manage Changes in Your Schedule (Pro Users) 88Managing Libraries 89 Use a Library 89 Manage a Library 90 Manage the People Library 91 Import ACT Contacts and Users to the People Library 92 Import Outlook Contacts to the People Library 94 Import Outlook Contacts via CSV to the People Library (Pro Users) 96Printing Reports 97 Printing Dashboards 98 Print Reports 98 Print Dashboard Reports 99 Page Setup 100 Save As 101 Printing Task Reports 102 Print Task Reports 102 Print Preview 105 Printer Setup 106 Page Setup 107 Email Task Reports 108 Save As HTML 109 Save As RTF 110 Printing Gantt Chart Reports 111 Print a Gantt Chart 111 Print Preview a Gantt Chart 115 Page Setup 116 Printing to an Adobe PDF file 117 Save Gantt Chart Images 118Export Project Data 119 Export to ACT 120 Export to ACT 7 and Later 120

5

copy Experience In Software Inc 1995 - 2006

Export to ACT 6 122 Export to Microsoft Outlook 123 Export to Microsoft Word 125 Export to Word Processors (Other than Word) 127 Export to Microsoft Excel 128 Export to Microsoft PowerPoint 130 Export to Microsoft Project 132 Export to SureTrak Project Manager 133 Export to FastTrack Schedule 134 Export to Milestones Professional 135 Export to Mindjet MindManager 136 Export to WBS Chart Pro 137 Export MPX Files 138Reference 139 Menus 140 File Menu 140 Edit Menu 141 View Menu 142 Tools Menu 143 Options 144 Data Menu 145 Timescale Menu 146 Help Menu 147 Shortcuts 148 Share Project KickStart data 150 Open a Project 151 Dedication 152 Credits and Trademarks 153 Uninstalling the software 154 Using Past Projects 155

6

copy Experience In Software Inc 1995 - 2006

Start Here Welcome to Project KickStart

7

copy Experience In Software Inc 1995 - 2006

Introduction

Welcome to Project KickStart

Whether yoursquore a novice or seasoned pro yoursquoll be amazed at how quickly you can create a thoughtfulcomprehensive task list and project schedule Using Project KickStart you can go from raw idea to aproject task list in 30 minutes You do not need any special project management training to use ProjectKickStart

The first thing youll want to do is

Open a project Click to open one of our sample projects

Start a new project Click to begin planning your own project

Open your last project If youve already created a project click this option to open your most recentproject

After that let Project KickStart show you the way Itrsquos easy to navigate Project KickStart with its intuitivegraphical interface--it feels like a coach is guiding you through each step

Next StepsProject KickStart guides you through the process of planning and scheduling your project On the top ofeach Project KickStart window are instructions explaining what to do Read the instructions enter your dataand then click the Next button in the lower-right corner of the window Additional help is always availablefrom the onscreen Advisor and Project KickStart Help

Sample ProjectsThe sample projects are completed projects that let you get a feel for Project KickStart If you find onesimilar to the project you want to create open it save it with a new name and then customize it to meetyour needs

-o-

8

copy Experience In Software Inc 1995 - 2006

Use Project KickStart to

Project KickStart is organized into three sections planning scheduling and exporting to other programs

Plan The Project KickStart graphical interface acts as a Planning Wizard guiding you through eightsteps for planning your project Some planning steps involve brainstorming to identify tasks that youmight otherwise overlook

Schedule The Project KickStart Gantt chart makes scheduling tasks fast and easy You can printtaskbars in color and save Gantt charts reports as images so you can email them to colleagues orinclude them in a report

Export Communicate your projects in a variety of ways by exporting project data to other applicationsincluding Microsoft Outlook With one mouse click you can include Project KickStart plans in aMicrosoft Word document Excel spreadsheet PowerPoint slide presentation and more

People are using Project KickStart to

Create process templates project reports to-do lists and more

Communicate project details to others through reports email and Gantt chart schedules

Ensure project buy-in by including the needs of team members in your plan

Consider project goals and obstacles in the planning process and prevent surprises later

-o-

9

copy Experience In Software Inc 1995 - 2006

Use the Planning Wizard

Project KickStart uses a Planning Wizard that guides you through eight steps for planning your project Tostep through the wizard click each icon on the Steps bar (on the left side of the Project KickStart window) inorder On each window t ips and advice are always available by clicking the Advisor button You click theNext button to continue

Name Each project has a name To start planning your project give it ashort descriptive name

Phases Consider how your project will break down into major activitiesor phases Start by listing your phases and then list the tasks thatbelong in each phase

Goals Goals are what you hope to accomplish in your project Enter orselect the goals for your project Then you can list any new tasks toachieve each goal

Similar Projects often have tasks in common In this step you canborrow tasks from past projects to help you plan this project Then youcan add any new tasks from a similar project to the phases of yourcurrent project

People List the people groups or things that might provide resourcesfor your project including yourself Then identify any new tasks thesepeople might do or suggest for your project

Obstacles Each project has obstacles you can overcome if youanticipate them List the obstacles you will face in your project and thenidentify any new tasks needed to avoid the obstacles

Assign Assign tasks to people and other resources

Tasks Change the order of your tasks add and delete tasks andcreate subtasks You can also edit tasks change assignments and addnotes

Schedule Schedule the tasks in your project To make schedulingeasier new projects open with a starter schedule beginning todaywhich you can customize to fit your project

-o-

10

copy Experience In Software Inc 1995 - 2006

Navigating Project KickStart

When you use the Planning Wizard you work with a step window similar to the following illustration

Steps bar Click a step button to perform a step in the Planning Wizard The selected button shows yourcurrent step

Name of your project Shows the name entered in the Name step

Menu bar Select options from the menu bar to work with your projects

Toolbar Click buttons to perform common tasks such as saving your project

Step instructions Indicate how to perform the current step

Library button Click to open a library for the current step For example click the Goals Library button toopen a library listing typical project goals

Back and Next buttons Click a button to return to the previous step or continue to the next step in thePlanning Wizard

Advisor button Click to see instructions tips and notes for completing the current step

-o-

11

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5

The following table outlines whatrsquos new in Project KickStart Pro 5

If you own a previous version of Project KickStart yoursquoll notice the new Pro version has a new look and feelAs you begin to check it out yoursquoll soon discover Project KickStart Version 5 is a lot more powerful thanprevious versions and comes with some great new features

FEATURE DESCRIPTION IMPROVED

NEW

Dashboard Reporting

Quickly assess what is due TodayNext Week or Next Month

X

Import Contacts Import from a comma separatedvalue (CSV) file

X

Templates Use as is or customize X

Gantt Chart Greater stability and functionality X

User Interface Contemporary look and colorscheme

X

Preferences Customize look and feel andprogram defaults

X

Productivity Pack Project template Word docs fornewbies

X

Exports Improved Outlook MindManager and ACTimproved data exchange

X

-o-

12

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5 (Pro Users)

This feature is available only in Project KickStart Professional

The following table outlines whatrsquos new in Project KickStart Pro 5

FEATURE DESCRIPTION IMPROVED NEW

Gantt Chart Task dependencies in Gantt chart X

Link tasks Show task dependencies X

Unlink tasks Remove task dependencies X

Add predecessors Add task predecessors X

Add successors Add task successors X

Project Coordination Link to GoToMeeting for onlinemeetings on projects

X

Project KickStart Pro now includes dependencies on the Gantt chart This sophisticated scheduling andproject management tool is new to Project KickStart Pro and is designed to make complex projectscheduling easy and straightforward

Use dependencies to handle scheduling demands delays and surprises without modifying every task inyour project Dependencies let you make adjustments as events change giving you a more robust scheduleand the opportunity to conduct what-if analysis

Suppose you are managing a landscaping project involving subcontractors and dozens of tasks One ofyour first tasks is to pave a path with flagstones but the shipment of flagstones is two days late Usingdependencies you can delay the path-paving task in a couple of clicks and Project KickStart Proautomatically updates the schedule for the remaining tasks

Although dependencies meet your advanced scheduling needs the Project KickStart Pro approach todependencies keeps them as simple as possible If you want to link a couple of tasks which are dependenton one another you can simply highlight the tasks and click the link icon

If you select the option of Autolinking tasks then when you display the Gantt chart the first time all tasksare pre-linked allowing you to adjust durations schedules of individual tasks and time between taskswhich is called Lead Time in Project KickStart Pro

Unlike other project management programs such as Microsoft Project Project KickStart Pro does notburden you with complicated error messages and various types of dependencies It provides only one typeof dependency finish-to-start which is the most common type This means you can fine-tune your scheduleas soon as you open the Gantt chartmdashwithout having to learn technical terms or advanced projectmanagement techniques

The Project Coordination functionality that we are providing is through GoToMeeting and is a chargedservice

Note

These features are in addition to those listed on the Whatrsquos New in Project KickStart 5 page

-o-

13

copy Experience In Software Inc 1995 - 2006

Compatibility with earlier versions

Project KickStart 5 can open and save projects in Project KickStart 4 prx file format (Same as ProjectKickStart 5)

Project KickStart 5 can open and convert projects saved in Project KickStart 3 prj file format You need tohave a licensed copy of Project KickStart 3 on your system to make the conversion

To open a prj project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click prj file type3 Navigate to the folder that contains the prj file Generally prj files are stored in cprogram filesProject

KickStart 34 Double-click the name of the file

Tips

The tasks in the converted Project KickStart 5 file will have the same start and finish dates and samedurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way (ie as working days) To have weekends as non working days click the Change WorkingSchedule button on the Gantt chart toolbar and mark weekends as non working

Note

Project KickStart 5 does not open and convert prj files from Project KickStart 1 or 2

-o-

14

copy Experience In Software Inc 1995 - 2006

Activating trial version

You may have obtained a FREE 20-day trial version of Project KickStart 5 from our website or from areseller

To convert your Trial Version to a Full Version youll need to purchase a License Key and to activate thesoftware

To activate Project KickStart 5 trial1 Start the Project KickStart trial

2 If you have not purchased your License Key yet click the Buy button to purchase online3 If you have purchased a License Key click the Activate button and copy and paste the License Key

that you received when you purchased Project KickStart as well as your name and email

15

copy Experience In Software Inc 1995 - 2006

4 You must be connected to the Internet and you must tell your Firewall to allow communication forPKS5Kickstartexe

Tip

Your License Key allows 2 activations per user One is for your primary computer and one is for asecond computer you use such as your laptop or home computer

-o-

16

copy Experience In Software Inc 1995 - 2006

Licenses and Support

End User License Agreement

EXPERIENCE IN SOFTWARE INC END USER LICENSE AGREEMENT AND WARRANTYDISCLAIMER

PROJECT KICKSTARTtrade STANDARD 5 AND PRO 5 EDITIONS

NOTICE This is a legally binding contract between you the end user and EXPERIENCE IN SOFTWAREINC

EXPERIENCE IN SOFTWARE INC (EIS or LICENSOR) LICENSES THE ENCLOSED SOFTWARETO YOU (USER or LICENSEE) ONLY UPON THE CONDITION THAT YOU ACCEPT ALL OF THETERMS CONTAINED IN THIS LICENSE AGREEMENT PLEASE READ THE TERMS CAREFULLY BYOPENING THIS PACKAGE BREAKING THE SEAL CLICKING ON THE ldquoAGREErdquo OR ldquoYESrdquo BUTTONOR OTHERWISE INDICATING ASSENT ELECTRONICALLY OR LOADING THE SOFTWARE YOUAGREE TO THE TERMS AND CONDITIONS OF THIS AGREEMENT IF YOU DO NOT AGREE TOTHESE TERMS AND CONDITIONS CLICK ON THE ldquoI DO NOT AGREErdquo ldquoNOrdquo BUTTON OR MAKE NOFURTHER USE OF THE SOFTWARE IF YOU DO NOT AGREE TO THESE TERMS THEN EIS ISUN-WILLING TO LICENSE THE SOFTWARE TO YOU IN WHICH EVENT YOU SHOULD RETURN THEFULL PURCHASED PRODUCT WITH PROOF OF PURCHASE TO LICENSOR OR THE DEALER FROMWHOM IT WAS ACQUIRED WITHIN 15 DAYS OF PURCHASE AND YOUR MONEY WILL BEREFUNDED

LICENSE AND WARRANTY

The software that accompanies this license (Software) is the property of EIS and is protected by copyrightand other intellectual property law Although EIS at all times owns the Software you will have certain rightsto use the Software after your acceptance of this license Except as may be modified by an addendumwhich may accompany or be added to this license your rights and obligations with respect to the use of thisSoftware are as follows

You may

(i) install and use one copy of the specified edition of Software and documentation on a single computerand only by one user (ldquoPrimary Userrdquo) If you have purchased multiple licenses for the Software asindicated as Quantity or Number of Licenses on the Invoice or electronic confirmation issued by EIS orits Resellers then at any time you may have as many copies of the Software in use as you have licenses The Software is ldquoin userdquo on a computer when it is loaded into the temporary memory (ie RAM) or installedinto the permanent memory (eg hard disk CD-ROM or other storage device) of that computer

(ii) install and use a second copy of the Software on a second computer for the limited and exclusive use ofthe Primary User

(iii) use the Software on a network provided that Licensee has a licensed copy of the Software for eachnamed user that can access the Software over that network

(iv) make one copy of the Software for archival purposes or copy the Software onto the hard disk of yourcomputer and retain the original for archival purposes

(v) after written notice to EIS transfer the Software on a permanent basis to another person or entityprovided that you retain no copies of the Software and the transferee agrees to the terms of this agreement

You may not

(i) rent lease copy distribute license or otherwise transfer the Software or its documentation to any otherparty Licensee may make a reasonable number of back-up copies for archival purposes only TheSoftware contains copyrighted material trade secrets and other proprietary material If Licensee has theright to duplicate the Software for multiple Users then Licensee must reproduce on all such copies of theSoftware the copyright notices and any other proprietary legends that were on the original copy of theSoftware or

(ii) decompile reverse engineer disassemble translate make any attempt to discover the source code ofthe Software or otherwise reduce the Software to a human perceivable form or modify network or create

17

copy Experience In Software Inc 1995 - 2006

derivative works based upon the Software or the documentation in whole or in part nor permit any otherparty to do so

Notwithstanding anything herein if the Software is lawfully acquired outside of the United States within ajurisdiction which is a member of the European Union subject to the EEC Council Directive 91250EEC ofMay 14 1991 Licensee agrees that within that jurisdiction it shall not and shall not allow any party onLicensees behalf to attempt to reverse engineer or decompile the Software into another computerlanguage except as expressly and specifically provided in the EEC Council Directive 91250EEC of May14 1991 Any and all information obtained during such lawful reverse engineering andor decompilingactivities including but not limited to the organization logic algorithms and processes of the Softwareshall be deemed to be the confidential and proprietary information of EIS

Licensee shall not make copies of the copyrighted Software documentation without the prior writtenpermission of EIS provided that for electronic transactions Licensee may make one (1) hard copy of suchdocumentation for each User

Intellectual Property and Duplication of Software

The Software contains copyrighted material trade secrets and other proprietary material If Licensee hasthe right to duplicate the Software for multiple Users then Licensee must reproduce on all such copies ofthe Software the copyright notices and any other proprietary legends that were on the original copy of theSoftware

Upgrades

To use a Product identified as an upgrade you must first be licensed for the product identified by EIS aseligible for the upgrade After upgrading you may no longer transfer the product that formed the basis foryour upgrade eligibility to another person or entity

Technical Support

Licensee must register the Software in order to be eligible for free technical support (including installationand registration of the product) during the first 90 days after purchase

Thirty Day Money Back Guarantee

If you are the original Licensee of this copy of the Software and are dissatisfied with it for any reason youmay return the complete product together with your receipt to EIS or an authorized dealer postageprepaid for a full refund at any time during the thirty-day period following the delivery to you of thePurchased Software

Export Law Assurances

You are responsible for complying with all trade regulations and laws both foreign and domestic Youacknowledge that none of the Software or underlying information or technology may be downloaded orotherwise exported or re-exported (i) into Afghanistan (Taliban-controlled areas) Cuba Iran Iraq LibyaNorth Korea Serbia (except Kosovo) Sudan and Syria or any other country subject to a US embargo or(ii) to anyone on the US Treasury Departments list of Specially Designated Nationals or the USCommerce Departments Denied Parties List or Entity List By using the Software you are agreeing to theforegoing and are representing and warranting that (i) no US federal agency has suspended revoked ordenied you export privileges (ii) you are not located in or under the control of a national or resident of anysuch country or on any such list and (iii) you will not export or re-export the Software to any prohibitedcounty or to any prohibited person entity or end-user as specified by US export controls as defined byEAR 15 CFR Parts 730-774 and BXA (httpwwwbxadocgov)

Data Collection and Privacy Policy

You acknowledge and agree that EIS may collect and retain information about you such as your nameaddress and e-mail address You also understand that EIS may employ other companies to performfunctions on our behalf such as fulfilling orders delivering packages sending postal mail and e-mailproviding marketing assistance and processing credit card payments These companies may have accessto personal information needed to perform their functions and may not use such information for otherpurposes By assenting to this agreement you agree that you have read and understand our Privacy PolicyFor more detailed information httpwwwprojectkickstartcomhtmlprivacy_statementhtm

Termination

This License is effective until terminated Licensee may terminate this License at any time by destroying allcopies of the Software and its documentation This License will terminate immediately without notice from

18

copy Experience In Software Inc 1995 - 2006

EIS if Licensee fails to comply with any provision of this License Upon termination Licensee must destroyall copies of the Software and its documentation and cease and desist from any further use of the Software

Limited Warranty

EIS warrants that the media on which the Software is distributed will be free from defects and that theSoftware shall perform substantially as described in its documentation for a period of sixty (60) days frompurchase Your sole remedy in the event of a breach of this warranty will be that EIS will replace anydefective media returned to EIS within the warranty period EIS does not warrant that the Software willmeet your requirements or that operation of the Software will be uninterrupted or that the Software will beerror-free

THE ABOVE WARRANTY IS EXCLUSIVE AND IN LIEU OF ALL OTHER WARRANTIES WHETHEREXPRESS OR IMPLIED INCLUDING THE IMPLIED WARRANTIES OF MERCHANTABILITY FITNESSFOR A PARTICULAR PURPOSE AND NONINFRINGEMENT OF INTELLECTUAL PROPERTY RIGHTSTHIS WARRANTY GIVES YOU SPECIFIC LEGAL RIGHTS YOU MAY HAVE OTHER RIGHTS WHICHVARY FROM STATE TO STATE AND COUNTRY TO COUNTRY

Disclaimer of Damages

REGARDLESS OF WHETHER ANY REMEDY SET FORTH HEREIN FAILS OF ITS ESSENTIALPURPOSE IN NO EVENT WILL EIS OR ITS RESELLERS BE LIABLE TO YOU FOR ANY SPECIALCONSEQUENTIAL INDIRECT OR SIMILAR DAMAGES INCLUDING BUT NOT LIMITED TO ANY LOSTPROFITS OR LOST DATA ARISING OUT OF THE USE OR INABILITY TO USE THE SOFTWARE EVENIF EIS HAS BEEN ADVISED OF THE POSSIBILTIY OF SUCH DAMAGES SOME STATES DO NOTALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FOR INCIDENTAL OR CONSEQUENTIALDAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAY NOT APPLY TO YOU IN NO CASESHALL EISS ITrsquoS RESELLERrsquoS LIABILITY EXCEED THE PURCHASE PRICE FOR THE SOFTWARE

SOME STATES AND COUNTRIES INCLUDING MEMBER COUNTRIES OF THE EUROPEANECONOMIC AREA DO NOT ALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FORINCIDENTAL OR CONSEQUENTIAL DAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAYNOT APPLY TO YOU

The disclaimers and limitations set forth above will apply regardless of whether you accept the Software

US Government Restricted Rights

DISTRIBUTION TO THE US GOVERNMENT This Software is commercial software developedexclusively at private expense This Software and the documentation are provided with RESTRICTEDRIGHTS applicable to private and public licenses alike Use duplication or disclosure by civilian agenciesof the US Government shall be in accordance with the Commercial Computer Software-Restricted Rightsclause at FAR 52227-19 Use duplication or disclosure by Department of Defense agencies is subjectsolely to the terms of this software licensing agreement pursuant to DFARS 2277202Contractormanufacturer of the Software is EXPERIENCE IN SOFTWARE INC 2029 Durant AveBerkeley CA 94704 USA

General

This Agreement shall be governed by the laws of the State of California without giving effect to principles ofconflict of laws You hereby consent to the exclusive jurisdiction and venue of the state courts sitting in SanFrancisco County California or the federal courts in the Northern District of California to resolve anydisputes arising under this Agreement This Agreement contains the complete understanding between theparties with respect to the subject matter hereof and supersedes all prior or contemporaneous Agreementsor understandings whether oral or written You agree that any varying or additional terms contained in anypurchase order or other written notification or document issued by you in relation to the Software licensedhereunder shall be of no effect No provision hereof shall be deemed waived or modified except in writing No EIS dealer agent or employee is authorized to make any amendment to this Agreement

The intellectual property protections the disclaimers of warranties and the limitation of damages shallsurvive termination The failure or delay of EIS to exercise any of its rights under this Agreement or uponany breach of this Agreement shall not be deemed a waiver of those rights or of the breach If any provisionof this Agreement is held invalid the remainder of this Agreement will remain in full force and effect

Should you have any questions concerning this Agreement or if you desire to contact EIS for any reasonplease write to EXPERIENCE IN SOFTWARE INC 2029 Durant Ave Berkeley CA 94704 USA

-o-

19

copy Experience In Software Inc 1995 - 2006

20

copy Experience In Software Inc 1995 - 2006

Customer Support

When you need help in solving a problem with the software Experience In Software is available to assistyou First check this help file for information on the part of the program you are having a problem withAlso take a look at the Web site for late-breaking technical support information wwwprojectkickstartcomsupporttechnical_supportcfm If you are a regustered user you can obtain support in the following ways

Web httpwwwprojectkickstartcomsupportemail_supportcfm E-mail supportprojectkickstartcom

Hours 900 am to 500 pm Pacific time Monday - Friday

To make the support process more efficient have the following information ready for the support staff

Provide your name phone number and email address

Describe the problem including any error messages

If reporting a potential bug describe what you did immediately before seeing the bug

Provide the Project KickStart version number and Build Date (Click Help on the menu bar and thenclick About Project KickStart)

Identify the version of Windows (Windows Vista etc) you are using

Notes

Our policy is to respond to support email within two business days If you have not received aresponse please double check that spam filters are blocking our messages to you If you maintain anincoming whitelist please allow all messages from the projectkickstartcom domain

Support is available in English only If you purchased a translated version please contact your localreseller for help in other languages

See Also

Reporting Technical Issues

-o-

21

copy Experience In Software Inc 1995 - 2006

Reporting Technical Issues

If Project KickStart 5 detects an error it will write a log of technical issues and then create a temporarymenu to the right of the Help menu which says Send Log to Technical Support You should immediatelyclick the menu and then click Yes to send the error log to us

Please fill in your email address so that we can get back to you with any questions about what caused theerror

Tip

If you have an Internet Security Program such as Norton Internet Security please allowPKS5Kickstartexe to communicate with the Internet to report the error

-o-

22

copy Experience In Software Inc 1995 - 2006

Register Project KickStart

To print this page click the Print button on the Help window toolbar

Register Project KickStart 5 for technical support upgrade information and software discounts You canregister by completing printing and then sending or faxing this form to Experience In Software You canalso register online at httpwwwprojectkickstartcomsupportregiscfm

Name _______________________________________________________

Title _______________________________________________________

Company _______________________________________________________

Address _______________________________________________________

CityStateZip ______________________________________________________

Country _______________________________________________________

Day Phone _______________________________________________________

Fax _______________________________________________________

E-mail _______________________________________________________

Purchased from __ Experience In Software __ Other ____________________

Number of people in company _ 1 to 25 _ 26 to 100 _ 101 to 1000 _ Over 1000

Which industry do you work in ______________________________________

Interested in a project management workshop for your company __ Yes __ No

Comments _______________________________________________________

_________________________________________________________________

_________________________________________________________________

Experience In Software 2029 Durant Ave Berkeley CA 94704

Send or FAX to (510) 644-3823

-o-

23

copy Experience In Software Inc 1995 - 2006

Planning Projects

Name Your Project

Before you start thinking about the tasks in your project yoursquoll want to give your project an appropriate titleIf you open an existing project you might want to edit or change the name of your project

To name your project1 In the Type a name for your project text box enter a name2 Click the Next button

Tips

You can enter up to 58 characters and more than one

Use short descriptive project names such as ldquoCompany Web Siterdquo

Avoid vague project names such as ldquoDatabase Projectrdquo or ldquoCDP-7rdquo especially if you plan to circulatereports to others

Enter your project title using uppercase letters if you want the title to stand out in reports

One way to reuse your projects is to open an existing project and then change its name in this stepAfter saving the project with a different name you can modify details to customize the project

See Also

Use the Planning Wizard

-o-

24

copy Experience In Software Inc 1995 - 2006

Phases - Step 1 of 2

After naming your project the next step in the Planning Wizard is to identify the major activities in yourproject Using phases helps organize tasks so that an obviously early task such as ldquoOrganize materialsrdquoappears before a later task such as ldquoReview final draftrdquo

To enter phases1 Type each phase one per line

OrClick the Phases Library button The Phases Library contains typical phases that many organizationsuse in the early middle and late stages of their projects Drag an entry from the Phases Library to thelist and then click the OK button to close the Phases Library

2 To insert a phase in the middle of the phases list click where you want to insert a new blank line andthen press the Insert keyTo edit the phase text double-click the phase

Tips

Start each phase name with an action verb as in ldquoBuild systemrdquo or ldquoWrite reportrdquo

Use actions that have clearly defined beginnings middles and ends For example you can scheduletasks like ldquoTest prototyperdquo more easily than tasks like ldquoPurchase high-quality partsrdquo

Note

Youll have the opportunity to edit phases later in the Tasks step For now continue planning thephases in your project

See Also

Use the Planning Wizard

Use a Library

Move Tasks within the Task List

-o-

25

copy Experience In Software Inc 1995 - 2006

Phases - Step 2 of 2

For each phase list all of the tasks that could be performed during that phase You can refine and organizethe tasks later in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each phase1 Type the tasks associated with the phase displayed in the Tasks for phase text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next phase in your project click the Next button If you prefer to work out oforder click the Tasks for phase list arrow and then click the phase you want

3 When you are finished entering tasks for the last phase in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

26

copy Experience In Software Inc 1995 - 2006

Goals - Step 1 of 3

Enter the goals for your project the objectives you hope to accomplish Then you can brainstorm anyadditional tasks that will help you meet these goals

To enter goals1 Type each goal one per line

OrThe Goals Library contains typical sample goals that you can customize Drag an entry from the GoalsLibrary to the list and then click the OK button to close the Goals Library

2 To insert a goal in the middle of the goals list click where you want to insert a new blank line and thenpress the Insert keyTo edit the goal text double-click the goal

3 Click the Next button

Tips

List goals that apply to the entire project such as Develop a high-quality system A goal such as Getthe contract signed applies only to an early phase

Write goals as actions you can measure For example Complete the project for $75000 or less ismore concrete and specific than Complete the project within budget Numbers make goal statementsreal

If youre not sure how to measure a goal use a range as in About 15 - 25 people will use the results ofthe project

See Also

Use the Planning Wizard

Use a Library

-o-

27

copy Experience In Software Inc 1995 - 2006

Goals - Step 2 of 3

For each goal list any new tasks needed to accomplish that goal You can refine and organize the taskslater in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each goal1 Type the tasks for accomplishing the goal displayed in the For the goal text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next goal in your project click the Next button If you prefer to work out of orderclick the For the goal list arrow and then click the goal you want

3 When you are finished entering tasks for the last goal in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

28

copy Experience In Software Inc 1995 - 2006

Goals - Step 3 of 3

After you identify new tasks for your project assign each new task to an appropriate phase

To assign new tasks to phases1 Click a task in the New tasks to achieve goals list (on the left)2 Click one or more phases in the Assign them to Phases list (on the right) to which the task belongs A

checkmark appears next to tasks youve assigned

If a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Note

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

29

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 1 of 2

Projects often have tasks in common The Similar Projects step makes it easy for you to borrow tasks fromother projects and add them to your current project

By default this step shows the Project KickStart (PRX) projects stored in the same folder as the currentproject including sample projects and those you already created

To select similar projects1 Review the projects in the list To sort the project names alphabetically click the Project Name header

Click the Project Name header again to sort the names in reverse order2 Click one or more projects in the list that contain tasks you want to use in the current project A

checkmark appears next to the projects you selected3 To list projects stored in a different folder on your system click the Browse button and then navigate to

the folder you want4 Click the Next button

If no projects seem related to your current project skip this step for now

Tips

The Similar Projects step becomes more helpful the more you use Project KickStart Every time yousave a project it becomes available for future use

Many projects share the same phases and tasks such as those for setting up a contract or purchasingequipment You can use Project KickStart to create these mini-projects or templates and then importtheir tasks into a new project during the Similar Projects step

-o-

30

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 2 of 2

After you select one or more projects containing tasks you might want to use assign those borrowed tasksto a phase in this project

To assign borrowed tasks to phases1 Click a task in the list on the left If a task includes subtasks click the plus icon to expand the list Click

the minus icon if you want to hide the subtasks To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more phases in the Assign tasks to phase(s) of your project list (on the right) to whichthe task belongs A checkmark appears next to tasks youve assigned

3 To assign one or more tasks to a new phase select the tasks click ltNew Phasegt in the Assign tasksto Phases of your project list and then type a name for the new phase

4 To select tasks from another project you selected as similar click the Tasks from Similar Projects listarrow click the project you want and then assign the tasks to phases

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also Edit Tasks

-o-

31

copy Experience In Software Inc 1995 - 2006

People - Step 1 of 3

Enter the names or descriptions of the people involved in your project Include key decision makers suchas executives or customers who must approve or consult with you about the project These are yourprojects resources In the next People step youll identify new tasks associated with these resources

To enter people1 Type each name or description one per line

OrIf you have stored information about people and other resources in the People Library click the PeopleLibrary button drag an entry from the library to the list and then click the OK button to close thePeople Library

2 To edit the people text double-click the name or description3 Click the Next button

Tips

Be consistent with the resource names in your projects For instance avoid using Richard in oneproject and Dick in another project when referring to the same person

Include names for people teams (such as Quality control team) departments (such as Manufacturing)companies (such as Acme Widgets Corp) or even equipment (such as wheat thrasher)

Note

Add people and other resource information to the People Library so that you can quickly drag resourcesfrom the library to any project You can even import people from your Outlook and ACT address books

See Also

Manage the People Library

Import ACT Contacts and Users to the People Library

-o-

32

copy Experience In Software Inc 1995 - 2006

People - Step 2 of 3

Now that you have defined the people needed to complete your project list any new tasks that eachresource might suggest or require

To enter new tasks for each person1 Type the new tasks associated with the person displayed in the Tasks For text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next person in your project click the Next button If you prefer to work out oforder click the Tasks For list arrow and then click the person you want

3 When you are finished entering new tasks for the last person in your project click the Next button tocontinue in the Planning Wizard

Tips

This step provides a good opportunity to get input from your resources directly and make sure theproject plan reflects the views of everyone on the team

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo Write the tasks roughly in the order that you will complete them You can reorganize the tasks later in

the Tasks step

Note

You assign people to tasks in the Assign Tasks and Schedule steps

See Also

Use a Library

Move Tasks within the Task List

Assign Tasks to People

-o-

33

copy Experience In Software Inc 1995 - 2006

People - Step 3 of 3

After you identify new tasks associated with the people in your project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by people list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

34

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 1 of 3

Every project has obstacles and risks that can affect its success List the major obstacles you face incompleting your project Then you can brainstorm any additional tasks that can help you overcome orminimize these problems

To enter obstacles1 Type each obstacle one per line

OrThe Obstacles Library contains typical sample obstacles that you can customize Drag an entry fromthe Obstacles Library to the list and then click the OK button to close the Obstacles Library

2 To insert an obstacle in the middle of the obstacles list click where you want to insert a new blank lineand then press the Insert key

3 To edit the obstacle text double-click the obstacle4 Click the Next button

Tips

Be creative when thinking of obstacles Highly imaginative obstacles can suggest realistic tasks Forexample Project manager kidnapped by aliens can lead to Project manager out of town forconference In Obstacles step 2 of 3 you can add the realistic activities as tasks You can delete theunrealistic obstacles later by returning to Obstacles step 1 of 3

Avoid listing too many obstacles even if they are realistic Hard core pessimists find it hard to getanything done

Edit and update the Obstacles Library so that you can quickly drag obstacles from the library to anyproject in your organization

See Also

Use a Library

-o-

35

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 2 of 3

After identifying the obstacles to completing your project determine how you can avoid these stumblingblocks List any new tasks you need to overcome or avoid each obstacle In this way you are developing acontingency plan for your project

To enter new tasks for each obstacle1 Type the new tasks associated with the obstacle displayed in the Obstacle text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next obstacle in your project click the Next button If you prefer to work outof order click the Obstacle list arrow and then click the obstacle you want

3 When you are finished entering new tasks for the last obstacle in your project click the Next button tocontinue in the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

You can reorganize the tasks and add notes later in the Tasks step

See Also

Use a Library

Move Tasks within the Task List

Add Task Notes and Attachments

-o-

36

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 3 of 3

After you identify new tasks for overcoming the obstacles to completing project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by obstacles list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

3 Click the Next button

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

37

copy Experience In Software Inc 1995 - 2006

Assigning People

Assign Tasks to People

After youve identified people working on your project you can assign tasks to each person or otherresource

To assign tasks to people1 Click a phase or task in the For each phase or tasks list (on the left)

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more people in the Assign some people list (on the right) who will perform the task Acheckmark appears next to tasks youve assigned

3 To assign a selected task to all of the people in your project click the All button4 To assign one or more tasks to a new person select the tasks click ltNew Persongt in the Assign

some people list and then type a name for the new person

To unassign a task

To unassign a task click the task and then click the highlighted person from which you want to removethe task You can assign that task to a different person if necessary You can also click the All buttonto remove a task from all of its assignments at the same time

Tip

Some users like to skip to the Tasks step before performing the Assign step That way they can edittheir list of tasks before assigning people and resources This helps them focus the project and givesthem a clearer idea of what must be done before committing resources

Notes

You can also assign tasks to people in the Tasks step and the Schedule step

You can assign tasks to non-personnel resources such as equipment (a CAD system or back hoe)facilities (a classroom or hotel) services (lab work or insurance) or materials (lumber or officesupplies) just as you assign tasks to people Click ltNew Persongt to add a new resource to the list

See Also

Remove People from a Task

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

38

copy Experience In Software Inc 1995 - 2006

Remove People from a Task

After assigning tasks you might need to remove people from a task or unassign them

To remove people from a task (unassigning)1 Click a phase or task in the For each phase or tasks list (on the left)

The people assigned to that phase or task are highlighted in the Assign some people list (on theright)

2 Click a highlighted person to remove or unassign that person from the taskWhen the person is no longer highlighted they are not assigned to the selected task

See Also

Assign Tasks to People

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

39

copy Experience In Software Inc 1995 - 2006

Add a New Person or Resource

If you realize that you want to assign some tasks to a person not included in the Assign some people listyou can add that person and assign tasks in the same step You can also add non-personnel resourcessuch as such as equipment (a CAD system or back hoe) facilities (a classroom or hotel) services (lab workor insurance) or materials (lumber or office supplies)

To add a new person or resource1 Select one or more phases or tasks in the For each phase or tasks list (on the left) 2 Click ltNew Persongt in the Assign some people list and then type a name for the new person or

resourceThis adds the new person or resource to the list and assigns the selected tasks to them

See Also

Assign Tasks to People

Remove People from a Task

Edit or Substitute People

Add or Change Task Assignments

-o-

40

copy Experience In Software Inc 1995 - 2006

Edit or Substitute People

If the people or resources in your project change you can replace them or edit their names anddescriptions

To edit or substitute people1 Click the People icon

You return to People step 1 of 32 In the list of people defined for the project double-click the person you want to edit or replace or click

the name and press F23 Edit the name or description of the person

When you return to the Assign step the name of the person appears as you changed it

See Also

Assign Tasks to People

Remove People from a Task

Add a New Person or Resource

Add or Change Task Assignments

-o-

41

copy Experience In Software Inc 1995 - 2006

Organizing the Project Plan

About Organizing Tasks

In the Tasks step you work with an outline of your project plan Here you can easily edit and reorganizetasks spell check and even add notes and attachmentsClick the following illustration to see tips for using this window

Edit the Task List to Consolidate and delete tasks Add subtasks Add or change task assignments Add follow-up notes to tasks Add or change attachments Review the order of the tasks in each phase and move tasks up or down so that they progress

sequentially Review task descriptions to make sure they are clear and that all the team members will understand

them Convert vague tasks such as reminders and open issues to task notes

Notes

Some users like to revise their Task List before they assign resources You can go to the Task List atany time while you are using Project KickStart

Each project created with Project KickStart can contain up to 1000 tasks

See Also

Change the Appearance of the Task List

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

Add Task Notes and Attachments

Add or Change Task Assignments

Add or Change Task Details

-o-

42

copy Experience In Software Inc 1995 - 2006

43

copy Experience In Software Inc 1995 - 2006

Change the Appearance of the Task List

You can change the appearance of the Task List so you can work with it more effectively

To add a column

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task ListBy default the Task List shows the Task Name Assignments and Notes columns You can also showCost and Done columns

To hide a column

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

To move a column

Drag a column heading to a new position in the Task List

To change the column width

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Show or Hide Tasks in the Task List

-o-

44

copy Experience In Software Inc 1995 - 2006

Show or Hide Tasks in the Task List

To hide tasks or subtasks

To hide the subtasks for a task click the minus icon next to the task

To hide all the tasks in the Task List and show only phases click all the minus icons next to thephases

To show tasks or subtasks

To show the subtasks for a task click the plus icon next to the task

To show the tasks for a phase click the plus icon next to the phase

See Also

Change the Appearance of the Task List

-o-

45

copy Experience In Software Inc 1995 - 2006

Move Tasks within the Task List

In the Tasks step you can reorganize the tasks in your project so that they better represent the work youand your team plan to do In particular you should review the order of the tasks in each phase and move tasks up and down so thattasks follow in a sequential order Use the Up and Down Arrow buttons to move the tasks

To reorder tasks1 Click a task or phase to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youmove must be next to each other

2 Click the Up Arrow button to move a task up one rowOrClick the Down Arrow button to move a task down one row

Note

When you move a bolded phase you move the phase and all of its tasks at the same time

See Also

Outdent and Indent Tasks

-o-

46

copy Experience In Software Inc 1995 - 2006

Outdent and Indent Tasks

Subtasks are smaller parts of tasks Use subtasks when you need to break tasks down into moremanageable parts In the Task List you can turn a task into a subtask by indenting it You can also add anew subtask to the Task ListIf your Task List contains subtasks you can turn a subtask into a task by outdenting itUse the Outdent and Indent buttons to promote (outdent) and demote (indent) tasks

To promote and demote tasks1 Click a phase task or subtask to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youpromote or demote must be next to each other

2 Click the Outdent button to promote the selected tasksOrClick the Indent button to demote the selected tasksYou can also right-click an item in the Task List and then click Outdent or Indent on the shortcut menu

Tips

When you promote (outdent) a task it becomes a phase and its subtasks become tasks When youpromote a subtask it becomes a task

When you demote (indent) a phase it becomes a task and its tasks become subtasks When youdemote a task it becomes a subtask

Notes

You can have up to 10 levels of subtasks in your project

Use Task Notes instead of subtasks for task comments or additions that are not actually work items

See Also

Move Tasks with the Task List

Add a Task or Subtask

-o-

47

copy Experience In Software Inc 1995 - 2006

Add a Task or Subtask

If you realize you want to add another task to the Task List use the Add Task button A subtask is a smaller part of a task Use subtasks when you need to break tasks down into moremanageable partsTo add a subtask use the Add Subtask button

To add a task1 Click a task and then click the Add Task button right-click a task and then click Add Task on the

shortcut menu or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskProject KickStart numbers the new task in the proper sequence

To add a subtask1 Click a task and then click the Add Subtask button right-click a task and then click Add Task on the

shortcut menu or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtask3 Project KickStart numbers the new subtask in the proper sequenceNote

To add a new phase click a phase and then click the Add Task button

See Also

Outdent and Indent Tasks

-o-

48

copy Experience In Software Inc 1995 - 2006

Edit Tasks

Edit tasks in the Task List to fine tune your project You can edit the names of the phases tasks andsubtasks delete tasks and cut copy and paste task information

To edit task names1 Click the phase task or subtask you want to edit and then press the F2 key2 Type to edit the text3 To undo an edit click the Undo button

To delete a task

Click the task you want to delete and then press the Delete key or click the Delete button Or

Right-click a task and then click Delete Row on the shortcut menu

To cut copy and paste tasks1 Select the tasks you want to cut or copy Use Shift-click or Ctrl-click to select more than one task

2 Click the Cut button (Ctrl-X) or click the Copy button (Ctrl-C )

3 Click where you want to insert the tasks and then click the Paste button (Ctrl-V)

Tip

If your project includes some of the same tasks repeated in different phases save time by copying rowsof tasks and pasting them to another phase

Notes

You can also edit task names using the Task Information dialog box To open this dialog boxdouble-click a task or click a task and then click the Edit Task Information button

If you delete a phase you also delete its tasks and subtasks If you delete a task you also delete itssubtasks Project KickStart warns you before deleting tasks or subtasks and gives you a chance tocancel the deletion

See Also

Add Task Notes and Attachments

Add or Change Task Assignments

-o-

49

copy Experience In Software Inc 1995 - 2006

Add Task Notes and Attachments

You might find that some of your tasks are actually more notes than tasks For example Remember tocheck Daves specifications might work better as a note than a task especially if it could take several daysto catch up with Dave but only a few minutes to review his specs By using notes you clarify your projectand increase your chances for success An attachment is a document graphic or any other type of file related to a task For example to a tasksuch as Review proposal you can attach the proposal document Or you can attach a hyperlink to a pageon a web site

To add a note or attachment to a task1 Double-click the Notes column next to the task The Task Information dialog box opens to the Notes

and Attachments tab2 In the Enter a Note box type in or edit the task note (Press Enter to insert line break)3 To attach a file click the Add Files button In the Select File to Attach dialog box navigate to the file

you want and then click the Open button The filename appears in the Add Attachments box with apaperclip icon

4 To insert a hyperlink click the Add URL button In the Insert Hyperlink dialog box type in the URL youwould like to link to The URL appears in the Add Attachments box with a paperclip icon

5 Click the OK button

To open or remove an attachment1 Open the Notes and Attachments tab in the Task Information dialog box2 To open an attachment double-click the filename in the Add Attachments box3 To delete an attachment click the attachment in the Add Attachments box and then click the Remove

button

To change a task into a task note1 Copy (Ctrl-C) the text of the task you want to change into a note2 Double-click the task to which you want to add the note3 In the Task Information dialog box click the Notes and Attachments tab and add paste the text in the

Enter a Note box Close the Task Information dialog box4 In the Task Name column delete the original task that how appears as a note for a different task

Tips

Use notes to keep track of the operational details of a project the little nagging details that are criticalto success

Although the Task List provides plenty of room for notes it is best to keep your notes concise

Some tasks might benefit from instructional notes those that explain what to do in a task or how tosuccessfully complete a task

You can also include a hyperlink in a note by typing httpxxx (where xxx is an e-mail or Web address)In Outlook Word Excel or your browser the hyperlink will be active You can click the link to godirectly to that site or to send an e-mail to that address

Note

You can also open the Notes and Attachments tab in the Task Information dialog box by clicking atask and then clicking the Edit Notes and Attachments button or by double-clicking a task to openthe Task Information dialog box and then clicking the Notes and Attachments tab

See Also

Edit Tasks

Add or Change Task Assignments

Change Task Details in the Gantt chart

50

copy Experience In Software Inc 1995 - 2006

-o-

51

copy Experience In Software Inc 1995 - 2006

Add or Change Task Assignments

The Assignments column in the Task List shows the people and other resources assigned to each task

To add or change a task assignment1 Double-click the Assignments column next to the task The Task Information dialog box opens to the

Assignments tabThe Assignments tab lists all of the people and resources in your project If this task is already assignedto people they are highlighted on the Assignments tab

2 To assign this task to another person or resource click the resource name in the Assignments list3 To remove (unassign) this task from a person or resource click a highlighted name in the Assignments

list4 To add a person and assign the task at the same time click ltNew Persongt in the Assignments list

and then enter the name of the new person5 Click the OK button

Note You can also open the Task Information dialog box by clicking a task and then clicking the Edit Task

Information button to or by double-clicking a task

-o-

52

copy Experience In Software Inc 1995 - 2006

Add or Change Task Details

Besides task names notes and assignments you can include cost and done details about tasks In theSchedule step you can also include start and finish dates and durations

To add task details

1 Click a task and then click the Edit Task Information button or double-click the task you wantThe Task Information dialog box opens

2 Enter Cost or Done informationCost Enter the cost associated with this task For example you could enter $150 as the cost for a tasknamed Purchase photo CD Done Click the list arrow to select 0 25 50 75 or 100 or enter the percentage you want such as33

3 Click the OK button

To show or hide task details

Right-click a column heading to open a shortcut menu and then click Cost or Done In the shortcutmenu a checkmark appears next to columns that are displayed in the Task List

To edit task details

Open the Task Information dialog box (click a task and then click the Edit Task Information button or double-click the task you want)

Or

Double-click the Cost or the Done entry to update these details directly in the Task List

Notes

The Cost amount appears with the currency symbol set for your system (in the Regional and LanguageOptions dialog box of the Windows Control Panel)

Project KickStart calculates the running totals for the tasks within a phase and displays this total in theCost column for the phase When you create and print Task reports the total costs for the entire projectappear at the end of the Cost column

See Also

Edit Tasks

Print Task Reports

-o-

53

copy Experience In Software Inc 1995 - 2006

Check Spelling

Spell check your tasks and notes before you print reports or export to other software

To check the spelling of tasks and notes

Click the Check Spelling button on the Project KickStart toolbarOr

Click Tools on the menu bar and then click Spelling

Notes

Spell checking updates entries on the Task List and the Gantt chart (the Schedule step) It can alsocheck the spelling of intermediate entries such as goals and tasks to accomplish goals if you spellcheck during those steps

Spell checking does not check the names of people on the People List or the contents of the PeopleLibrary

-o-

54

copy Experience In Software Inc 1995 - 2006

Scheduling Tasks in the Gantt Chart

55

copy Experience In Software Inc 1995 - 2006

Scheduling Overview

About Scheduling Tasks

In the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the other

You work with the Gantt chart using the familiar Task Data view in the left pane or the graphical Chart viewin the right pane To adjust the schedule to fit your project set the project start date in the toolbar moveand resize the taskbars in the Chart view or change the start and finish dates or durations of individualtasks in the Task Data view

Click the following illustration to see general tips for using the Gantt chart See About the Gantt Chart formore details

In the Schedule step you can

Change a start date for the project Set start and finish dates or durations for tasks Change the timescale of the schedule Change the working schedule to specify which days are nonworking days such as weekends and

holidays Fine-tune the organization of the phases tasks and subtasks Color-code tasks to identify assignments critical deadlines or other information at a glance Insert milestones to indicate events that mark a moment in time such as the approval of a design Review and edit task details including task name assignments notes and attachments Hide or show task data columns in the left pane Export project data to other software applications

Tip

56

copy Experience In Software Inc 1995 - 2006

To save time you can reuse projects such as one for a trade show and create an updated scheduleby changing the project start date in the Schedule step

See Also

About the Gantt Chart

Understand Task Data View

Understand Chart View

-o-

57

copy Experience In Software Inc 1995 - 2006

About the Gantt Chart

The Gantt chart provides two views of your project schedule The Task Data view in the left pane lists thesame task information as in the Tasks step but now includes durations and start and finish dates TheChart view in the right pane displays taskbars and symbols to represent the same information You canchange the schedule information by working directly in the Task Data view and Chart view or by using theGantt Chart toolbarClick the following illustration to see general tips for using this window

-o-

58

copy Experience In Software Inc 1995 - 2006

Autolink tasks (Pro Users)

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatProject KickStart Pro does not assume that you want to link all of the tasks in a serial manner (one after theother) when you get to the Gantt chart Indeed many users want that behavior and many do notTo accomodate both types of users you can set whether you want the program to Autolink tasks In theTools menu select Autolink tasks Thereafter in all your projects when you get to the Gantt chart for thefirst time the tasks will be linked in a serial mannor

-o-

59

copy Experience In Software Inc 1995 - 2006

About Linking Tasks

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatWhen you link tasks the Gantt chart shows additional information about the tasks Click the followingillustration to see general tips for using linked tasks

Task Data view Chart view Description

Predecessor tasksA predecessor task is onethat you must completebefore you can start thenext task For exampleTask 2 - Prepare soil isthe predecessor to Task3 - Plant shrubs becauseyou need to prepare thesoil before you can plantthe shrubs

Successor tasksWhen you finish onelinked task you can moveonto the next onemdashthesuccessor task Forexample the successorfor Task 2 ndash Prepare soilis Task 3 ndash Plant shrubsand the successor forTask 3 is Task 4 ndash MulchLink linesThe first task isscheduled for one dayand the second one forthe next day In additionthe link line and arrowshow that the first taskmust end before thesecond one can start

These linked tasks arescheduled for the sametime

60

copy Experience In Software Inc 1995 - 2006

These tasks which aredependent on earliertasks and the last twotasks are also scheduledfor the same time

See Also

About the Gantt Chart

Autolink tasks

Make tasks overlap

-o-

-o-

61

copy Experience In Software Inc 1995 - 2006

Change the Display of the Schedule

You can change the onscreen appearance of the schedule so you can work with it more effectively Thefollowing illustration shows the Schedule window with the Steps bar closed and only the task number taskname and duration displayed in the Task Data view This provides more room to display the Gantt chart

To show or hide the Step bar or Project KickStart toolbar

Click View on the menu bar and then click Steps Bar to show or hide the vertical Steps bar on the leftof the Project KickStart window

Click View on the menu bar and then click Tool Bar to show or hide the Project KickStart toolbarwhich appears just below the menu bar In the View menu a checkmark appears next to the items displayed in the Project KickStart window

To display more or less of the Task Data view or Chart view

Drag the splitter bar between the Task Data view and the Chart view

To change the timescale in the chart

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years

To add a column to the Task Data view

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task Data viewBy default the Task Data view shows the Info Task Name Days Start and Finish columns Youcan also show Done Cost and Assignments columns

To hide a column in the Task Data view

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

62

copy Experience In Software Inc 1995 - 2006

To change the column width in the Task Data view

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Understand Task Data View

Understand Chart View

-o-

63

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

-o-

64

copy Experience In Software Inc 1995 - 2006

65

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Some features in this topic are available only in Project KickStart Professional

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view In Project KickStart Professional you also use the Gantt chart toolbar to linkand unlink tasks

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysLink Tasks (Pro Users)Link the selected tasksUnlink Tasks (Pro Users)Unlink the selected tasksChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

See Also

Use the Gantt Chart Toolbar

-o-

66

copy Experience In Software Inc 1995 - 2006

Understand Task Data View

The following illustration shows all the columns of information you can display in Task Data view

The Task data columns are the same as in the Tasks step but also include date information

Row number

Info Shows an icon if a note attachment or both are associated with the task Double-click anicon to view or edit the associated information

Task Name Name of the phases tasks and subtasks Double-click a task name to edit it directly

Days The amount of time it takes to complete the task If you change the number of days for a taskProject KickStart changes the Finish date accordingly

Start Date this task starts Double-click a Start date and then click the list arrow to open a calendar andselect a different date This also changes the Finish date

Finish Date this task ends Double-click a Finish date and then click the list arrow to open a calendar andselect a different date This changes the task duration shown in the Days column

Done Percentage of the phase task or subtask completed Show progress for any task by entering apercent of up to 100

$ Cost Cost for each task summed in the appropriate phase row Reports include total costs for theproject when you select the Cost column in the Create and Print Task Reports dialog box or the Createand Print Gantt Chart Report dialog box The Cost appears with the currency symbol set for your system(in the Regional and Language Options dialog box of the Windows Control Panel)

Assignments People and other resources assigned to the task Double-click an assignment to open theTask Information dialog box to the Assignments tab where you can add and change assignments

Tip

A task with a duration of zero (0) days is a milestone See Create a Milestone for more information

Notes

By default Task Data view displays all the columns the Info Task Name Days Start and Finish Done Cost and Assignments columns Some of these columns might be hidden by the Gantt chartview To hide columns right-click a column heading to open a shortcut menu and then click the columnyou want to hide In the shortcut menu no checkmark appears next to columns that are hidden

To change the width of a column drag a splitter bar in the column heading row or double-click a splitterbar to have the column accommodate its longest entry

As in the Tasks step expand phases and tasks by clicking the plus icon and collapse phases andtasks by clicking the minus icon

See Also

67

copy Experience In Software Inc 1995 - 2006

Understand Chart View

Change Task Dates

-o-

68

copy Experience In Software Inc 1995 - 2006

Additional Features in Task Data View

These features are available only in Project KickStart Professional

In Project KickStart Pro you can view two columns of information in addition to the nine columns availablein the Project KickStart Standard These two additional columns are labeled Pred (for Predecessor) andSucc (for Successor) The following illustration shows a typical Task Data view with these additionalcolumns

Besides the nine columns of information shown in Task Data view in Project KickStart Standard you canalso show the following information in the Professional version

Pred Indicates which task is the predecessor to the current task Double-click a task number in the Predcolumn to change it

Succ Indicates which task is the successor to the current task Double-click a task number in the Succcolumn to change it

Notes

When you link tasks Project KickStart assigns predecessors and successors according to their order inthe Task Data view

When you move a linked task in the Task Data view the predecessor and successor do not changeFor example in the above illustration if you move Task 3 ndash Plan design so it becomes Task 2 itspredecessor remains Land survey and its successor remains Engineering You can change these bydouble-clicking the task number in the Pred or Succ column and then entering a new number

See Also

Understand Task Data View

-o-

69

copy Experience In Software Inc 1995 - 2006

Understand Chart View

The following illustration shows a daily schedule in Chart view Point to the illustration to display text thatdefines the chart elements

Summary bar Summarizes the tasks below it and extends from the earliest start date(where the first triangle in the summary bar appears) to the latest finish date (where the last triangleappears) If a phase has tasks the summary bar appears in the phase row to summarize the tasks If atask has subtasks the summary bar appears in the task row to summarize the subtasks

To reschedule a phase and all of its tasks (or a task and all of its subtasks) click the summary bar and dragit to the left or right until it spans your desired set of dates This changes the earliest start date and latestfinish date in that phase and keeps the same duration And all the tasks move with the change of thephase

Taskbar Shows the length and scheduled dates for a task To change the duration of a taskresize the taskbar click the taskbar and then drag its left edge to schedule a different start date or drag itsright edge to schedule a different finish date

To reschedule a task without changing the duration drag the taskbar to a different date in the chart

Taskbar with percent done If you enter a Done amount in the Task Data view a progress barin the taskbar indicates the amount of the task completed

Red vertical line Indicates todays date

Milestone Indicates a task with a zero duration Milestones mark an event that must be reflected inyour project plan such as the approval of a design or an assembly line startup You can drag the left edgeof a milestone icon to stretch it into a taskbar The milestone becomes a task with a start and finish date

Notes

Because a summary bar summarizes the tasks below it you cannot resize a summary bar

To scroll the schedule use the vertical and horizontal scroll bars or the green drag bar at the top of theChart view

The shaded days in the Chart view indicate nonworking days To set which days are working andnonworking see Specify Working Days

70

copy Experience In Software Inc 1995 - 2006

-o-

71

copy Experience In Software Inc 1995 - 2006

Additional Tools in Chart View

These features are available only in Project KickStart Professional

If you use Project KickStart Pro the Chart view displays lines and arrows to show linked tasks The linklines and arrows show the relationships dependencies between one linked task and another

Besides the summary bar taskbar and other information provided in Project KickStart Standard Chart viewin the Professional version also provides the following information

The first task is scheduled for one day and the second one for the next day In addition the link line andarrow show that the first task must end before the second one can start

These linked tasks are scheduled for the same time However the first task must end before the secondone can start

The first two tasks are scheduled for the same time and must be completed before the third task can start

These linked tasks are scheduled for the same time However the second task must end before the firstone can start

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

Understand Chart View

-o-

72

copy Experience In Software Inc 1995 - 2006

73

copy Experience In Software Inc 1995 - 2006

Change Task Dates

You can revise a project schedule by changing task dates in the Task Data view or the Chart view You canalso reschedule an entire project by changing the projects start date

To change the project start date1 Click the Project Start list arrow to open a calendar

The calendar highlights the selected date and outlines todays date2 Find the date you want using the left and right scroll arrows to view a different month and then click the

date

To change task dates in Task Data view1 Double-click the Start or Finish date for a task

2 Then edit the date (you can edit the day month or year) OrClick the list arrow to open a calendarThe calendar highlights the selected date and outlines todays date

3 Find the date you want using the left and right scroll arrows to view a different month and then click thedateProject KickStart changes the Start and Finish dates according to your selection updates the durationof the task in the Days column and adjusts the taskbar in the Chart view

To change task dates by changing the duration in Task Data view

Double-click the Days column for a task and then enter the number of days it will take to complete thetaskProject KickStart changes the Finish date of the task and adjusts the taskbar in the Chart view

To change task dates in Chart view

Resize a taskbar click the taskbar and then drag its left edge to schedule a different start date or dragits right edge to schedule a different finish dateProject KickStart updates the summary bar in Chart view and the task dates and duration in the TaskData view

To reschedule a task without changing the duration drag the taskbar to a different date You can alsodrag a summary bar to reschedule a phase and all of its tasks (or a task and all of its subtasks) so itspans a different set of datesProject KickStart updates the task dates and duration as necessary in the Task Data view

To change task dates in the Task Information dialog box1 Open the Task Information dialog box (Right-click a task and then click Task Information or click a

task and then click the Edit Task Information button )2 Click the General tab3 In the Dates section change the following information as necessary

Start Click the Start list arrow to open a calendar and then click the appropriate start dateFinish Click the Finish list arrow to open a calendar and then click the appropriate finish dateDays Enter a number or click the spin arrows to set the task durationMilestone Select the Milestone check box if you want this task to be a milestone (A milestone is atask with a zero duration and marks an event such as the approval of a design)

Notes

You cannot delete the Start or Finish date of a task If you want to specify that a task has no durationconvert it to a milestone

When working with a calendar to schedule a start or finish date click the Today date text (where date

74

copy Experience In Software Inc 1995 - 2006

is todays date) to select todays date

See Also

Understand Task Data View

Understand Chart View

Create a Milestone

-o-

75

copy Experience In Software Inc 1995 - 2006

Phase Dates Cannot Be Edited

You cannot change the bold phase dates in the Task Data view of the Gantt chart They are a summary ofthe task dates for a particular phase and are view only You can revise phase dates by changing task dateswithin the phase

To change phase dates in Chart view

You cannot directly resize a summary bar You can extend or move the blue task barswithin a phase on the chart and Project KickStart updates the summary bar

To reschedule a phase on the chart drag the summary bar to a new date and all of its tasks (or a taskand all of its subtasks) will move with it

-o-

76

copy Experience In Software Inc 1995 - 2006

Quick Tour of Working with Linked Tasks

This feature is available only in Project KickStart ProfessionalIn the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the otherIn addition Project KickStart Pro links the tasks for you so when you open the Gantt chart you see a linkedwaterfall similar to the one shown below Besides providing a schedule that starts in a cascade with eachtask lasting one day each task is linked to the next task

You work with the Gantt chart either using the Task Data view in the left pane or the graphical Chart view inthe right pane To adjust the schedule to fit your project set the project start date in the toolbar move andresize the taskbars in the Chart view or change the start and finish dates or durations of individual tasks inthe Task Data view See About Scheduling Tasks for detailsNext fine-tune the dependencies in your project by you can linking and unlinking tasks changing theirpredecessors and successors and setting lead times For example if one task is not dependent onanother you can unlink the tasks If another task canrsquot start until two other tasks are finished you can add apredecessor to that task in which case the two tasks will be linked

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

To fine-tune the linked tasks To change the scheduled start and end dates of linked tasks move and resize taskbars in the Chart

view or change the number of days or the Start date in the Task Data view To display predecessor and successor information in the Task Data view right-click any column

heading and then click Pred or Succ To change the predecessor for a task double-click the number in the Pred column for the task and

then enter the number of a different task To change the successor for a task double-click the number in the Succ column for the task and then

77

copy Experience In Software Inc 1995 - 2006

enter the number of a different task To add another predecessor or successor to a task click in the appropriate column for the task and

then enter the number of another task To change the details of a linked task open its Task Information dialog box To do so right-click the

task and then click Task Information on the shortcut menu or click a task and then click the Edit TaskInformation button See Change Details for Linked Tasks

In the Task Information dialog you can also specify the predecessor(s) of a task and lead time(s) of thetasks

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

About Scheduling Tasks

About Linking Tasks (Pro Users)

Use the Gantt Chart Toolbar (Pro Users)

Manage Changes in Your Schedule (Pro Users)

-o-

-o-

78

copy Experience In Software Inc 1995 - 2006

Link and Unlink Tasks

These features are available only in Project KickStart Professional

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

See Also

About Linking Tasks

Quick Tour of Working with Linked Tasks

-o-

79

copy Experience In Software Inc 1995 - 2006

Create a Milestone

A milestone Indicates a task with a zero duration Milestones mark an event that must be reflected in yourproject plan such as the approval of a design or an assembly line startup

To create a milestone in the Task Data view

Double-click the Days number for a task and then enter 0 (zero)Or

Open the Task Information dialog box click the General tab and then click to insert a checkmark inthe Milestone check box

In the Chart view Project KickStart changes the taskbar to a milestone icon To create a milestone in Chart view

Click a taskbar and then drag to shrink the taskbar to a milestone icon In the Task Data view Project KickStart changes the Days for this task to 0 (zero)

Notes

To change a milestone into a task you change its duration or start and finish dates See Change TaskDates for instructions

To move a milestone in Chart view click the milestone icon on the upper left corner of the milestoneicon With the left mouse down move the icon to another date and release the mouse

To move a milestone in the Task Data view change the start date or the finish date and the milestonewill move

-o-

80

copy Experience In Software Inc 1995 - 2006

Change Task Details

You can use the Task Information dialog box to change the following task details in Task Data view

Task properties including the task name cost for completing the task and the percent completed

Dates including the start and finish dates duration and whether to convert the task to a milestone

Assignments

Notes and attachmentsYou can also edit the task name days dates costs and Done directly by clicking items in the task datacolumns

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button 2 Click the appropriate tab and then change the task details

General tab Change the task name and enter or change the cost associated with the task To changethe amount of the task completed click the Done list arrow and then select a value or type a value inthe Done text box Enter or change date information as described in Change Task Dates Assignments tab People assigned to this task are highlighted in the list To assign this task to anotherperson or resource click the name in the Assignments list To remove (unassign) this task from aperson or resource click a highlighted name in the Assignments list See Add or Change TaskAssignments for more detailsNotes and Attachments tab Type or edit a task note (Press Enter for a line break) To add anattachment click the Add button In the Select File to Attach dialog box navigate to the file you wantand then click the Open button The filename appears with a paper clip icon See Add Task Notes andAttachments for more details

To change task details directly in Task Data view

To modify the task name press F2 or double-click a task and then edit or replace the text

To change date information see Change Task Dates

To change the amount of the task completed double-click in the Done column and then enter a newvalue

To change the cost associated with the task double-click in the Cost column and then enter a newvalue

Notes

When you enter costs for tasks the total appears in the phase row for those tasks Reports include thetotal costs of all tasks in the project when you select the Cost column in the Create and Print TaskReports dialog box or the Create and Print Gantt Chart Report dialog box

You cannot change the cost of a phase because it represents the total costs for the tasks in that phaseInstead change the costs associated with the tasks in the phase

When you enter a Done for a task the corresponding taskbar in the Chart view includes a blackprogress bar

-o-

81

copy Experience In Software Inc 1995 - 2006

Change Details for Linked Tasks

This feature is available only in Project KickStart ProfessionalIf you are using Project KickStart Pro you can use the Task Information dialog box to change the followingtask details

Predecessor for a linked task

Lead time for a linked task

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button

2 Click the Predecessors tab and then change the task details about predecessors and lead timePredecessors tab The Task Properties section shows the name of the selected task which you canchange The Predecessor (Finish-to-Start) section shows the tasks that are predecessors to theselected task A predecessor task must be finished before you start the current task You can change the ID name or lead time of the predecessor task Also you can also add additionalother predecessorsThe lead time is the amount of time you need to wait after finishing the predecessor task before so youcan start the current task Lead time can be positive or negative

Note

In some programs the is time shift is called ldquolag timerdquo But we think that the term ldquolead timerdquo is moreaccurate and descriptive since itrsquos the amount of time you want to allow before you start a task

See Also

Change Task Details

82

copy Experience In Software Inc 1995 - 2006

-o-

-o-

83

copy Experience In Software Inc 1995 - 2006

Reorganize Tasks in Task Data View

Although your project should be fairly well organized by the time you start the Schedule step you canfine-tune the organization in the Task Data view using the same techniques you use in the Tasks stepTo reorder tasks

Right-click a task and then click Move Task Up or Move Task Down on the shortcut menu Or

Click a task or phase to select it and then click the Up Arrow button or the Down Arrow button on theGantt chart toolbar

To promote and demote tasks

Right-click a task and then click Outdent or Indent on the shortcut menu Or

Click a phase task or subtask to select it and then click the Outdent button or the Indent button onthe Gantt chart toolbar

To add a task1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Task button on the Gantt chart toolbar or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskTo add a subtask1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Subtask button on the Gantt chart toolbar or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtaskTo delete a task

Right-click a task and then click Delete Row on the shortcut menuOr

Click the task you want to delete and then click the Delete button

To delete a row click the Task row number and press the Delete button

See Also

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

-o-

84

copy Experience In Software Inc 1995 - 2006

Change the Timescale of the Schedule

You can display the Gantt chart schedule in the Chart view using days weeks months quarters or yearsas the timescale Changing from days to weeks for example displays a longer period of time but lessdetail

Days timescale Weeks timescale

To change the timescale in the Chart view

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years Youcan also change the timescale by clicking Timescale on the menu bar and then clicking the option youwant

Notes

When you print a Gantt chart your current timescale is used by default However you can change it inthe Print Options dialog For example even though you were viewing your Gantt chart by weeks youcan choose to print the Gantt chart by months

If your mouse comes with a wheel you can adjust Project KickStarts timescale by rolling the wheelforward or backward The Timescale list box must be selected first

-o-

85

copy Experience In Software Inc 1995 - 2006

Specify Working Days

You can select which days are working days and which days are nonworking days for scheduling purposesBy default Monday - Friday are working days and Saturday and Sunday are nonworking days You can addto and change these settings to specify holidays for example

To set working and nonworking days

1 Click the Change Working Schedule button on the Gantt chart toolbar The Change Working Schedule for this Project dialog box opens Nonworking days are shaded in grayWorking days are unshaded

2 To change a single date (from working to nonworking or from nonworking to working) click the date3 To change one day of the week for the entire project such as all Fridays double-click any Friday4 To display schedules for other months click the left and right arrows5 Click OK

Note

Project KickStart maintains separate calendars for each project

If you typically work weekends create a simple template with weekends displayed as Working daysSave as your starter template Use the starter template when you start a new project and then save theproject with a different name Weekends will be displayed as Working days in your projects

-o-

86

copy Experience In Software Inc 1995 - 2006

Change the Color of Taskbars

You can change the color of the taskbars in the Chart view to call attention to particular tasks For exampleyou can change the colors of all tasks in a particular phase resource or deadline to make them stand outin a report

To change the color of a taskbar1 Right-click a taskbar and then click Color on the shortcut menu or click a taskbar and then click the

Color button on the Gantt chart toolbar The Color dialog box opens

2 Click the color you want to assign to the taskbarTips

Avoid changing the taskbar color to black because it obscures the Done progress bar (The Doneprogress bar is a black bar displayed within a taskbar)

Also avoid changing the taskbar color to white because it will not appear in the white rows of the Chartview

-o-

87

copy Experience In Software Inc 1995 - 2006

Make Tasks Overlap

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro the schedule starts in a cascade with each task lasting one day and each tasklinked to the following taskHowever it is very unlikely that your entire schedule matches such a cascade so you can adjust theschedule Start by estimating the duration of tasksmdashthe number of days that each task will take Generallyit is best to estimate how many days will elapse before the task is done You might also want some tasks to occur at the same time To do so you can overlap the tasks To make tasks overlap like this

You can do this in three ways Set the same predecessor for both tasks

Or Set the second task as the successor of the first task and then then move the second task into a

position when it starts on the same day as the first taskOr

Set the second task as the successor of the first task and then assign a lead time of ndash3 days (the number of days scheduled for the task)

To make tasks overlap like this

Set the second task as the predecessor of the first task and then assign a lead time of ndash2 days(one less than the number of days scheduled for the task)

-o-

88

copy Experience In Software Inc 1995 - 2006

Manage Changes in Your Schedule

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro when you schedule with dependencies you can adapt to changes on the fly andcreate what-if scenarios to forecast how one change affects the overall project schedule A commonscenario is dealing with delays You can reschedule an entire project or only selected tasks When you doProject KickStart Pro updates the schedule for you

To delay an entire project Click in the Project Start text box and then edit the date to match your new start date (You can edit

the day month or year)Or

1 Click the Project Start list arrow to display the calendar The calendar highlights the selected date andoutlines todays date

2 Find the date you want using the left and right scroll arrows to view a different month and then click thedate Project KickStart changes the Start and Finish dates for all tasks according to your selection

To delay a task In Task Data view double-click the Days column for the task and then edit the number of days it will

take to complete the taskProject KickStart changes the Finish date of the task adjusts the taskbar in the Chart view andchanges the Start and Finish dates for all tasks linked to this taskOr

In Chart view resize a taskbar by clicking the taskbar and then dragging its left edge to schedule adifferent start date or dragging its right edge to schedule a different finish date Project KickStart updates the summary bar in Chart view the task dates and duration in the Task Dataview and reschedules all tasks linked to this task

To reschedule a task without changing the duration in Chart view drag the taskbar to a different date Project KickStart updates the task dates and duration as necessary in the Task Data view andreschedules all tasks linked to this task

Note

Project KickStart Pro does not include a critical path

-o-

89

copy Experience In Software Inc 1995 - 2006

Managing Libraries

Use a Library

Project KickStart has five libraries that contain lists of useful phases tasks goals people and obstaclesAll libraries expect the People Library contain sample entries that you can use in your projects Yougenerally build your own People Library from the resources that are available to you

To use a library1 In the Phases Tasks Goals People or Obstacles step of the Planning Wizard click the Library button

to open the appropriate library2 Select one or more items in a library and then drag them to your list3 Close the Library window

Tips

Feel free to add (or delete) items to the libraries to make them richer and more pertinent to yourprojects

Keeping libraries small makes them easier to use

Widen the library window to see the full text of long entries

Note

After adding a library entry to a list you can double-click the entry to edit it

See Also

Manage a Library

-o-

90

copy Experience In Software Inc 1995 - 2006

Manage a Library

Customize the libraries by adding and changing entries and reorganizing them so you can use the librariesefficiently The Phases Tasks Goals People and Obstacles Libraries include a single column ofinformation while the People Library provides additional columns (See Manage the People Library)

To edit a library1 Open the library by clicking the appropriate Library button2 To edit an entry double-click it

3 To add an entry to the library press Insert or click the Add a row button You can also select oneor more items in the list and then drag them to the library

4 To delete an entry select the entry and then press Delete or click the Delete a row button 5 To move an item up or down select the item and then click the Up Arrow or the Down Arrow button

6 Click the OK button to save your changes and close the Library windowTips

Widen the Library window to add a long entry

Libraries can serve as ldquoKnowledge Librariesrdquo By including typical company-specific terms in yourLibraries you create a quick reference for yourself and colleagues now and in the future To do so adda new line in the Library enter the name of your company (or department) as a heading in capitalletters and then list your personal terms under the heading

If you use Project KickStart on more than one computer such as at home and work you can transportchanges you make in your Libraries from one computer to another The data in all the Libraries isstored in one file pks5libxdat so you can copy that file on one computer and paste it into the ProjectKickStart 5 folder on the other computer

Keeping Libraries small makes them easier to use Project KickStarts Libraries are fairly rich out of thebox If some of the terms don rsquot apply to your type projects delete them

See Also

Manage the People Library

-o-

91

copy Experience In Software Inc 1995 - 2006

Manage the People Library

The People Library is like the other libraries but with a few important extra features

You can store contact data such as Company Email Phone and Job Title

You can import names from ACT or from Outlook if you use either of those programsTo use the People Library1 In the People step of the Planning Wizard click the People Library button2 Select one or more names in the People Library and then drag them to your list (This adds only the

names of people not their contact data) If the People Library contains company names but not contactnames you can drag the company name to your list

3 Close the Library windowTo organize the People Library

To show or hide a column right-click a column heading to open a shortcut menu and then click acolumn name In the shortcut menu a checkmark appears next to columns that are displayed in thePeople Library

To sort the people in the People Library click a column heading For example click the Name columnheading to sort the people alphabetically by name To reverse the sort click the column heading again

To move a person up or down select the person and then click the Up Arrow or the Down Arrowbutton

Click the OK button to save your changes and close the People LibraryTo edit the People Library

To edit a persons name and contact data double-click the entry

To add a person to the People Library click the first blank row press Insert or click the Add a rowbutton Then type to enter the persons name and contact information You can also select one ormore items in the list and then drag them to the People Library

To delete an entry select the entry and then press Delete or click the Delete a row button

Click the OK button to save your changes and close the People LibraryTips

Use the People Library to store names for people teams (such as Quality control team) departments(such as Manufacturing) companies (such as Acme Widgets Corp) or even equipment (such as wheatthrasher)

Widen the People Library window to add a long entry

Resize the columns by dragging or double-clicking a splitter barNotes

After adding a person or resource to your list you can double-click the name to edit it

You can import contact information stored in an Outlook or ACT (version 6 7 or later) address book toyour People Library

See Also

Import ACT Contacts and Users to the People Library

Import Outlook Contacts to the People Library

-o-

92

copy Experience In Software Inc 1995 - 2006

Import ACT Contacts and Users to the People Library

If you use ACT 7 or later (200520062007) or if you use ACT 6 you can import contacts and users to thePeople Library This speeds up your work by letting you use ACT information in your Project KickStartplans If you export a plan to ACT 7 or later it recognizes the people and other resources you entered inProject KickStart

To import ACT contacts and users1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click ACT 7 or later or ACT 6 Click the Import button3 Click the Select ACT Database button and select the ACT 7 or later database (pad) containing the

people information you want to import The ACT 7 and later databases are usually stored in MyDocumentsACTACT for Win 7Databases (If you use ACT 6 your data is stored in a dbf database) If you select a multi-user ACT database you must enter your user name and password for the ACTdatabase

4 In the Import to People Library dialog box the names of Contacts and Users are listed on the left Clickthe Users tab select one or more users and then click Add to move the user names to the Import listClick the Contacts tab to select contact names the same way Click the Add All button to select allusers or contacts for import Note You can sort the contacts alphabetically by name or by company name by clicking theappropriate column heading

5 Click the Import button to add the names and related information from the selected ACT database tothe People Library

Notes

Importing contacts and users to the People Library does not remove them from the ACT database

If you try to import the same ACT contact or user twice it appears only once in the People Library

-o-

93

copy Experience In Software Inc 1995 - 2006

94

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts to the People Library

If you use Microsoft Outlook to maintain your contacts you can import selected contacts to the PeopleLibrary ThisThis speeds up your work by letting you use Outlook information in your Project KickStartplans If you export a plan to Outlook it recognizes the people and other resources you entered in ProjectKickStart

To import Outlook contacts1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click Outlook Click the Import buttonA dialog box opens informing you that Project KickStart is trying to access your Outlook data

3 Allow access for 1 minute and then click the Yes button4 If Outlook asks you to choose your profile please do so5 The Import to People Library dialog box opens listing Outlook Contacts on the left Select one or more

contacts and then click Add to move the contact names to the Import list Click the Add All button toselect all contacts for import

6 Click the Import button to add the contact names to the People Library

Notes

Importing contacts and users to the People Library does not remove them from Outlook If you try to import the same Outlook contact twice it appears only once in the People Library

95

copy Experience In Software Inc 1995 - 2006

You can import Contacts from the Outlook Business Contact Manager

See Also

Import Outlook Contacts via CSV to the People Library (Pro Users)

-o-

96

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts via CSV to the People Library (ProUsers)

This feature is available only in Project KickStart Professional

If you use Microsoft Outlook to maintain your contacts and many of the people on your project are not inyour personal contacts folder in Outlook you can use our new utility to import these Outlook contacts viaCSV to the People Library

To export Outlook contacts to a CSV file1 In Outlook - Click File Import and Export Export to A File and click Next2 Select Comma Separated Values (Windows) and click Next3 Select the Contacts folder to export and click Next4 Save Exported File As with the default being your My Documents folder5 Click Next

To import Outlook contacts to the People Library

1 Be sure that you exit Project KickStart before running the Import Utility

2 Run ImportCSVToPKSexe which is located in the Project KickStart application folder

3 Browse or type the Contacts CSV file (the path is My DocumentsProject KickStart Projects folder bydefault)

4 Browse or type the pks5libxdat file (default is the Project KickStart application folder)

5 Click on Import

Note

Importing contacts and users to the People Library does not remove them from Outlook

-o-

97

copy Experience In Software Inc 1995 - 2006

Printing Reports

98

copy Experience In Software Inc 1995 - 2006

Printing Dashboards

Print Reports

You can print reports from anywhere in Project KickStart through a new Reports Step

You will see Reports divided into three areas

Dashboard

Task Reports

Gantt Chart Reports

-o-

99

copy Experience In Software Inc 1995 - 2006

Print Dashboard Reports

You can print dashboard reports from anywhere in Project KickStart though it makes the most sense toprint them after you have developed your tasks and arranged them in a sensible order

To print a dashboard report

1 Click File on the menu bar and then click Print Reports and then click Dashboard Reports or clickthe Print Reports button

2 In the left column select one of these dashboard reports Whats Due Today Whats Due NextWeek Whats Due Next Month

3 Change the page setup as necessary or Save As a file (See Page Setup and Save As)

4 Click the Print button

Tip

You can see the number of tasks in each dashboard report from the dashboard menu

-o-

100

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Dashboard Reports

Printer Setup

-o-

101

copy Experience In Software Inc 1995 - 2006

Save as HTML or RTF

You can dashboard reports to a Hypertext Markup Language (HTML) format for viewing with an Internetbrowser such as Microsoft Internet Explorer or Mozilla FireFox or to an RTF format for viewing in MicrosoftWord

To save a dashboard report as an HTML file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save button

To save a report as an RTF file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

102

copy Experience In Software Inc 1995 - 2006

Printing Task Reports

Print Task Reports

You can print task reports from anywhere in Project KickStart though it makes the most sense to print themafter you have developed your tasks and arranged them in a sensible orderBefore you print task reports you might want to widen the Task Name column in the Task List to make sureyou print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a task report

1 Click File on the menu bar and then click Print Task Reports In the Tasks step you can click thePrint Reports button instead

The Create and Print Task Reports dialog box opens

2 Click the list arrow and then click Task Report Individual Assignments or Phases Goals People ampObstacles

3 Select the information you want to include in the report as described below

4 Preview the report and change the page setup as necessary (See Print Preview and Page Setup)

5 Click the Print button

Task Report

The Task report covers the entire project and includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

103

copy Experience In Software Inc 1995 - 2006

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to display in the report

By default the report prints all tasks Click the Incomplete Tasks or Completed Tasks option button tofocus on one type of task

4 Click the Preview button (See Print Preview for details)

Individual Assignments

The Individual Assignments report covers the entire project and lists the tasks assigned to each resourceThe report includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to include in the report

Click the All Tasks Incomplete Tasks or Completed Tasks option button

4 Choose which people to include The report lists tasks assigned to the people you select

Click to insert or remove a checkmark from the box for each person

5 Click the Preview button (See Print Preview for details)

Phases Goals People amp Obstacles

This report includes the phases goals people and obstacles in your project You can include some or all ofthese items in the report

104

copy Experience In Software Inc 1995 - 2006

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Click the Preview button (See Print Preview for details)

Tip

If you have many long notes for the tasks of your project it may be hard to read them if you select everycolumn in the Task Reports You should consider selecting a report with only columns for Tasks andNotes

See Also

Print Gantt Chart Reports

-o-

105

copy Experience In Software Inc 1995 - 2006

Print Preview

Before printing a report preview its pages so you know how the report will look when printed

To preview a task report1 Click the Preview button on the Create and Print Task Reports dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from 79 to 100 or from 100 to 79Zoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25

viewPrint the report

You can also click the Page Setup button to change margins and other settings or click the Closebutton to close the Print Preview window

2 If the report appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintTask Reports dialog box

Note

Print Preview is for viewing only--you cannot edit the contents of a report

See Also

Print Task Reports

Printer Setup

Page Setup

-o-

106

copy Experience In Software Inc 1995 - 2006

Printer Setup

Before you print a report you can change the following printer settings

Printer name (and other properties) Paper size Number of copies

To change the printer setup1 Click the Printer button on the Project KickStart toolbar or the Print Preview toolbar2 In the Print dialog box change the printer settings

See Also

Print Task Reports

Print Preview

Page Setup

-o-

107

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Task Reports

Print Preview

Printer Setup

-o-

108

copy Experience In Software Inc 1995 - 2006

Email Task Reports

After creating and previewing a task report you can distribute it to others via email

To email a task report1 In the Create and Print Task Reports dialog box select a report and then click the Email Report

button Project KickStart creates the report opens a new message in your email software and attaches thereport as an HTML file to the message

2 Insert one or more email addresses include the message text and then send the message the way youusually do

Tip

To send a task report to each person in your project with the appropriate assignments select theIndividual assignments report select one person to receive the report and then click the Email Reportbutton Enter the email address of the recipient and send the message Do this for each person in yourproject

-o-

109

copy Experience In Software Inc 1995 - 2006

Save as HTML

You can export tasks assignments days and notes to a Hypertext Markup Language (HTML) format forviewing with an Internet browser such as Microsoft Internet Explorer or Mozilla FireFox

To save a report as an HTML file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

110

copy Experience In Software Inc 1995 - 2006

Save as RTF

You can export tasks assignments durations and notes to a Rich Text Format (RTF) for editing inMicrosoft Word

To save a report as an RTF file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can open an RTF file in a word processor such as Microsoft Word

To send an RTF document to each person in your project with the appropriate assignments select theIndividual Assignments report select one person to receive the report and then save the report asRTF Do this for each person in your project

See Also

Save as HTML

-o-

111

copy Experience In Software Inc 1995 - 2006

Printing Gantt Chart Reports

Print a Gantt Chart

Once you create your schedule you can print a Gantt chart from anywhere in Project KickStart

Before you print a Gantt chart you might want to widen the Task Name column in the Task pane to makesure you print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a Gantt chart1 Click File on the menu bar and then click Reports and then select Gantt Chart Reports In the

Schedule step you can click the Print Reports button insteadThe Create and Print Gantt Chart Report dialog box opens

2 Click the Format list arrow and then click Wall chart Fit to smallest size or Repeat tasks on everypage (for handouts)

3 Select the information you want to include in the report as described below4 Preview the report and change the page setup as necessary (See Print Preview a Gantt Chart and

Page Setup)5 Click the Print button

Wall Chart The wall chart prints the Gantt chart information spread across many pages which you can tape together tocreate a wall chart On the left side of the report the wall chart includes the task data columns you selectThe right side of the report includes the graphical view shown in the Gantt chart pane on the right

1 Select the task data columns you want to display for the task information on the left side of the wallchartClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the wall chart

112

copy Experience In Software Inc 1995 - 2006

By default the wall chart prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the wall chartBy default the wall chart prints the timescale you were using in the Gantt chart Click the SetTimescale list arrow to change the timescale to Weeks Months Quarters or Years

4 Select the orientation for the wall chartClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Fit to Smallest Size When you select the Fit to smallest size format Project KickStart reduces the size of the entire Gantt chartincluding the information in the Task pane on the left and the graphical view shown in the Gantt chart paneon the right so it fits as well as possible in the smallest number of pages

1 Select the data columns you want to display for the task information on the left side of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 The timescale for the Gantt chart view on the right side of the report is determined by the length of yourproject and may not be changed

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 The number of pages of the report is shown here (The Fit to smallest scale report will print up to 78rows of tasks per page)

6 Click the Preview button (See Print Preview a Gantt Chart for details)

Standard (for Handouts) This report lists the data columns you specify on the left side of the first page and can repeat the tasknumber task name or assignments on every interior page of the report which is especially useful for

113

copy Experience In Software Inc 1995 - 2006

handouts

1 Select the data columns you want to print on the left side of the first page and the data columns youwant to print on every page of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the reportBy default the report prints a daily view of the tasks Click the Set Timescale list arrow to change thetimescale to Weeks Months Quarters or Years

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Tips

Print Preview shows how many pages the Gantt chart will take to print If there are too many pagesconsider changing the timescale or the date range You can also choose to show fewer columns of taskdata

If possible use paper that is larger than 85 x 11 inches You can select the paper size in Print Previewusing the Page Setup dialog box

If you change the timescale from Days to Weeks or Months this can make tasks with short durations (1to 5 days) difficult to see

If you have trouble printing the Gantt chart report try changing the dpi from 600 to 300 (draft mode) Ifyou continue to have problems contact your printer manufacturer and see if it supports PCL (PrinterCommand Language) technology which is included in most printers today

If you have trouble printing the Gantt chart report on a PDF printer you can try to scale the printing tographics setting to 50

114

copy Experience In Software Inc 1995 - 2006

See Also

Save Gantt Chart Images

Print Task Reports

Printer Setup

Page Setup

-o-

115

copy Experience In Software Inc 1995 - 2006

Print Preview a Gantt Chart

Before printing a Gantt chart preview its pages so you know how the report will look when printed

To preview a Gantt chart1 Click the Preview button on the Create and Print Gantt Chart Report dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from the current zoom percentage to 100 or from 100 to the current zoom percentageZoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25 viewChange printer settings and then print the reportYou can also click the Page Setup button to set margins select paper size and enter headers andfooters or click the Close button to close the Print Preview window

2 If the Gantt chart appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintGantt Chart Report dialog box

Notes

Print Preview is for viewing only--you cannot edit the contents of a report

If you want to print a wider task column return to the Gantt chart widen the Tasks Name column andthen print

To change print settings such as the printer selection and number of copies click the Print button to open the Print dialog box You can save the Gantt chart in a PDF file by clicking the Print button andthen clicking the PDF printer selection (such as Adobe PDF or PDF-XChange ) You can then distributethe Gantt chart electronically as a PDF file

See Also

Print a Gantt Chart

Page Setup

-o-

116

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a Gantt chart you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print a Gantt Chart

Print Preview a Gantt Chart

-o-

117

copy Experience In Software Inc 1995 - 2006

Printing to an Adobe PDF file

To print a Gantt chart to an Adobe PDF file you may have to make some adjustments to your settings

To preview a Gantt chart1 Select Adobe PDF as the name of the printer2 Click Properties button3 Click the PaperQuality tab4 Click Advanced button5 In the Graphic Section lower the setting on Print Quality6 Also in the Graphic Section change the Scaling from 100 to 50

-o-

118

copy Experience In Software Inc 1995 - 2006

Save Gantt Chart Images

You can save a Gantt chart as a series of graphic files in the Meta File (emf) format which you can theninsert in a file such as a Microsoft Word document or PowerPoint presentation The number of graphic filescreated depends on the report type and options you choose in the Create and Print Gantt Chart Reportdialog box By default Project KickStart saves the files in a folder named for your project

To save Gantt chart images1 In the Create and Print Gantt Chart Report dialog box click the Save Image button

The Save Image dialog box opens2 Change the location where you want to save the image files or change the part of the file name that

includes the project name and report type if necessary3 Click the Save buttonNotes

Project KickStart saves the image files in the PKSGanttImagesproject name folder stored in the MyDocumentsProject KickStart Projects folder (where project name is the name of your project)

Each graphic file name includes the name of the project report type date you created the report andnumber in the series of images as in CreateaWinningPresentation_Wall chart_09112008_1emf toCreateaWinningPresentation_Wall chart_09112008_20emf

To email the Gantt chart images attach the images in the PKSGanttImagesproject name folder storedin the My DocumentsProject KickStart Projects folder (where project name is the name of your project)If the image files are large zip or compress the files first

If you have installed PDF as a printer selection you can print the Gantt chart to a PDF file and thenattach the PDF file to an e-mail message PDF files are often easier to read than image files See thenotes in Print Preview a Gantt Chart for instructions on printing to a PDF file

-o-

119

copy Experience In Software Inc 1995 - 2006

Export Project Data

120

copy Experience In Software Inc 1995 - 2006

Export to ACT

Export to ACT 7 or Later

If you use ACT 7 or later (20052006200720082009) you can export your plan from Project KickStart toan ACT database with just one click After you export your plan you see your tasks in the ACT Groupview grouped under the name of your project

To export to ACT 7 or later

1 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 7 and later andthen click the Go button You can also click File on the menu bar point to Export to and then clickACT 7 and later

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (pad file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opens

Each time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks

4 Click Start (This works best if ACT is already open )

5 If you are exporting to a multi-user ACT database enter your ACT User Name and Password

To view each project separately in ACT Group Details

1 In ACT click the Group List icon

2 Double-click the Project Name in the Group Name column The Group Detail appears for the projectyou selected

3 Click the Contacts tab to see Contacts and click the Activities tab to see tasks for that project

4 You should press Ctrl-F5 to refresh the view Also you might have to adjust the Filter in ACT so thatDates to show is set to All Dates

Task names are listed in the Regarding column Assignments are listed in the Scheduled With columnPhases are shown in red and tasks and subtasks are shown in blue

To view tasks from multiple projects sorted by date in Task List or Calendar

In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn Project names are in the Associate With column You might have to adjust the Filter in ACT sothat Dates to show is set to All Dates

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar Tasks are set as timeless (Duration of 0 minutes) so the transferred tasks dont fill up thecalendar

121

copy Experience In Software Inc 1995 - 2006

Tips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

The ACT 7 and later export is smart enough to update your existing tasks from the same project If youexport the same Project KickStart project two or more times ACT recognizes the project and asks ifyou want to update the project information in ACT You do not lose your task history or notes in ACT

Tasks that are unassigned in Project KickStart are listed as Scheduled With Unassigned PKS

You can filter by Selected Users in the Task List and in Groups

See Also

Import ACT Contacts and Users to the People Library

-o-

122

copy Experience In Software Inc 1995 - 2006

Export to ACT 6

If you use ACT 6 ACT 2000 or ACT 5 you can transfer a Project KickStart plan into an ACT databasewith just one click After you export your plan you see your tasks in the ACT Group view grouped underthe name of your project

To export to ACT 61 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 6 and then click

the Go button You can also click File on the menu bar point to Export to and then click ACT 6

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (dbf file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opensEach time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks4 Click Start (This works best if ACT is already open )5 If you are exporting to a multi-user ACT database enter your ACT user name and passwordTo view each project separately in ACT1 In ACT click the Groups icon 2 Click the Project Name listed under All Groups on the left3 On the lower-right part of the window click the Activities tab to see tasks for that project

Task names are listed in the Regarding column Assignments are listed in the Scheduled With column 4 You might have to adjust the Filter in ACT so that Dates to show is set to All Dates Also you might

have to press Ctrl-F5 to refresh the view5 To view task details click the button next to the task column on the leftTo view tasks from multiple projects sorted by date1 In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn You might have to adjust the Filter in ACT so that Dates to show is set to All Dates

2 If the Group column is not showing add it by clicking ViewAdd Columns and then double-clickingGroupThe tasks are identified by group (project name)

3 To view task details click the button next to the task column on the leftTips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar as well as in the Task List

You can filter by Selected Users in the Task List and in Groups

After exporting your tasks to ACT you can import them to your Palm Pilot using the ACT Link

See Also

Import ACT Contacts and Users to the People Library

-o-

123

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Outlook

If you use Microsoft Outlook you can export your plan from Project KickStart to Outlook in a click of abutton After you export your plan you see your tasks in the Outlook Tasks view grouped under a categorynamed for your project In Outlook you can track your tasks and email tasks to team members

To export to Microsoft Outlook1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Outlook and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Outlook The Export to Outlook dialog box opens

2 Click an option button to export All tasks Uncompleted tasks or Completed tasks3 If you want to display the tasks you export on your Outlook Calendar click the check box4 Click the Start button A dialog box opens informing you that Project KickStart is trying to access your

Outlook data

5 Allow access for 1 minute and then click the Yes buttonTo view your tasks in Microsoft Outlook1 Click the Outlook Tasks button2 Depending on the version of Outlook you are using set to view the tasks by category In Outlook 2003

click the By Category option button in the Current View list You can also click View on the menu barpoint to Arrange By and then click CategoriesYour project is listed by its project name in the Categories list

3 Click an expand icon to see the complete list of tasks and subtasks

124

copy Experience In Software Inc 1995 - 2006

4 To view task details double-click the task nameTips

The export to Outlook works best if Outlook is already open

In Outlook you can set priorities set reminders and schedule by the hour

If you export to your Outlook Calendar a reminder appears on the due date of each task

After you export tasks to Outlook you can synchronize with your Palm Pilot Windows CE device orother handheld computer

Note

You can export only to Microsoft Office Outlook not Outlook Express

See Also

Import Outlook Contacts to the People Library

-o-

125

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Word

If you use Microsoft Word you can export your plan from Project KickStart to Word in a click of a buttonYour project appears in a Word table in a doc file You can cut and paste change column widths deletecolumns and print from Word

To export to Microsoft Word

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Word andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Word

Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in a Word document in a doc format

2 When youre finished use Save As to save the Word file with a new name such as ltnamegtdoc Forconvenience you can save the file using the same name as your Project KickStart project name

Benefits of using Project KickStart and Word

Communicate projects flexibly After exporting to Word you can communicate your project details ina variety of text formats You can also enhance your document by adding color logos clip art orhyperlinks

Distribute plans to others You can send doc files to other Microsoft Word users via email andrequest comments using Words Send To and Comments features

Tip

Include your strategic plan in documents letters and web pages in a doc or html file

Note

The image of the Gantt chart does not import into Word automatically You can manually import theGantt chart image into a Word document In Word select Insert on the menu bar point to Pictureclick From File and then browse to the folder containing the Gantt chart images you saved By defaultthis is cMy DocumentsProject KickStart ProjectsPKSGanttImages in a folder named for your project

See Also

Export to Word Processors (Other than Word)

Save Gantt Chart Images

126

copy Experience In Software Inc 1995 - 2006

-o-

127

copy Experience In Software Inc 1995 - 2006

Export to Word Processors (Other than Word)

If you are using a word processor other than Microsoft Word you can export your Project KickStart taskreport by first saving it as an HTML or RTF file

To export to word processors other than Microsoft Word

1 Save a Project KickStart task report using HTML or RTF format using the Save As button in the Createand Print Task Reports dialog box

2 Open the file with your word processor

3 Save the file using the Save As command using a different name

See Also

Print Task Reports

Save as HTML

Save as RTF

-o-

128

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Excel

If you use Microsoft Excel you can export your plan from Project KickStart to Excel in a click of a buttonYour project appears in an Excel worksheet in a xls file You can add task details perform calculationsand share your project data with other Excel users

To export to Microsoft Excel1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Excel and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Excel Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in an Excel worksheet in an xls format

2 When youre done select FileSave As to save the Excel file under a new name For convenience youmight want to save it under the same name as your Project KickStart project name

To manually import Gantt chart images into Microsoft Excel1 In Excel click Sheet2 and select ToolsOptions on the menu bar and unclick the box for Gridlines2 Then select Insert on the menu bar point to Picture click From File and then browse to the folder

containing the Gantt chart images you saved By default this is cMy DocumentsProject KickStartProjectsPKSGanttImages in a folder named for your project

3 Select one Gantt chart image at a time to bring it in 4 You can manipulate the size of the image in Excel

Benefits of using Project KickStart and ExcelProject KickStart is very good at scoping out a schedule but there are a few reasons why you might want touse both programs

Data sharing A Project KickStart user might want to share the information with other Excel users whodont have Project KickStart They could change enhance or redistribute their portions of the schedule

129

copy Experience In Software Inc 1995 - 2006

Add more task details Excel users can add new columns of task data that cant be added in ProjectKickStart

Sort task lists For example you could show your projects tasks sorted by each resources namethen see each resources tasks sorted by the tasks start date

Filter tasks Excel can show tasks that meet certain criteria For instance show tasks with the wordtesting in the task name

See Also

Save Gantt Chart Images

-o-

130

copy Experience In Software Inc 1995 - 2006

Export to Microsoft PowerPoint

If you use Microsoft PowerPoint you can export your plan from Project KickStart to PowerPoint in a click ofa button Your project appears as a formatted PowerPoint presentation in a ppt file

To export to Microsoft PowerPoint

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft PowerPointand then click the Go button You can also click File on the menu bar point to Export to and thenclick Microsoft PointPoint

The Export to PowerPoint dialog box opens where you can choose a PowerPoint design template ifyou like

2 Click the Start button

Your tasks days start and finish dates and costs appear in a PowerPoint presentation with an imageof the Gantt chart in one or more slides at the end of your slide show

Once you have created a PowerPoint presentation you can enhance your slides in several ways

Delete slides that are not appropriate for your presentation

131

copy Experience In Software Inc 1995 - 2006

Rearrange the order of the slides

Add colors for emphasis

Add graphics such as company logo clip art and colors

Shorten any long task titles

Benefits of using Project KickStart and PowerPoint

Save time You can dramatically save time in creating a PowerPoint presentation on your project

Present projects to others Present project details in webinars presentations and corporatemeetings Create template presentations or how tos for implementing an installation productintroduction or corporate policy for example

Communicate plans Email project plans in ppt format to colleagues and presentors

Tips

If you use a PowerPoint design template choose one that has a white or light background for maximumlegibility of the Gantt chart in the presentation

The Gantt chart image in the PowerPoint presentation is generated ldquoon the flyrdquo Change the Timescalesettings of the Gantt chart considering how it will be reflected in the number of images of the Ganttchart For example the Day view results in more Gantt chart images than the Months view

-o-

132

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Project

If you use Microsoft Project 98 2000 2002 or 2003 you can export your plan from Project KickStart toProject in a click of a button

To export to Microsoft Project

In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Project andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Project Your tasks assignments days start and finish dates costs done and notes (excluding attachments) appearin a Microsoft Project file

Benefits of using Project KickStart and Microsoft Project

Share data with others Send a project to a colleague or client that expects to see your schedule in anMicrosoft Project format

Schedule tasks with more flexibility Schedule tasks in different durations particularly in less than aday

Track resources Track resource usage and resource leveling and to have greater flexibility in sortingfiltering and reporting project information

Notes

Project KickStart tasks transfer to Microsoft Project as tasks with a Constraint type of Start No EarlierThan This keeps the dates the same as in the Project KickStart schedule

The settings in Project KickStart Working Days Calendar also transfer to Microsoft Project

Exporting to Microsoft Project allows you to take advantage of the advanced tracking and schedulingfeatures that large projects often require

You can also save your Project KickStart projects as an mpx file which you can open in MicrosoftProject and send to other Microsoft Project users Click File on the Project KickStart menu bar clickSave As and then choose mpx as the file type After you save the file click File on the MicrosoftProject menu bar click Open and open your mpx file

-o-

133

copy Experience In Software Inc 1995 - 2006

Export to SureTrak Project Manager

If you use SureTrak Project Manager you can export your plan from Project KickStart to SureTrak ProjectManager

To export to SureTrak Project Manager

1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file

2 In SureTrak click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

SureTrak

You will see your tasks and assignments (but not the notes) appear in a SureTrak file The file is shownin outline view

Benefits of using Project KickStart and SureTrak

Add new information to tasks such as how they are linked

Track progress particularly for comparing plans verses actual results

Have greater flexibility in sorting filtering and reporting project information

Notes

Task notes are not included in the transfer

A version of Project KickStart called the Project KickStart Wizard is included in SureTrak 2 andSureTrak 3 You can use it within SureTrak

See Also

Export MPX Files

-o-

134

copy Experience In Software Inc 1995 - 2006

Export to FastTrack Schedule

If you use FastTrack Schedule you can save your Project KickStart project as an mpx file and import it intoFastTrack ScheduleTo export to FastTrack Schedule1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file2 In FastTrack Schedule click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

FastTrack ScheduleBenefits of using Project KickStart and FastTrack Schedule

Add more task details FastTrack Schedule provides the features and tools needed in many largeprojects

Multiproject reporting Consolidate multiple projects into a master project file

See Also

Export MPX Files

-o-

135

copy Experience In Software Inc 1995 - 2006

Export to Milestones Professional

If you use Milestone Professional you can export your plan from Project KickStart to MilestonesProfessional in a click of a button

To export to Milestone Professional

In the Schedule step click the Export to list arrow below the Gantt chart click MilestonesProfessional and then click the Go button You can also click File on the menu bar point to Export to and then click Milestones Professional

Your tasks assignments start and finish dates and notes (excluding attachments) appear in aMilestones file

Tips

After you export your tasks to Milestones Professional you can create taskbars add titles and performother tasks to produce a presentation-quality schedule You can also use Milestones to track your tasksby showing task durations and percent completions Make scheduling changes by dragging the taskdates

If you have an earlier version of Milestones (eg version 45 or 5) you can save Project KickStart dataas an mpx file and then open the mpx file in Milestones

-o-

136

copy Experience In Software Inc 1995 - 2006

Export to Mindjet MindManager

If you use Mindjet MindManager 7 or later you can export your project plan from Project KickStart in a clickof a button Or you can develop a rough plan in MindManager and export your mind map to ProjectKickStart for enhanced planning It works both ways

To export from Project KickStart to MindManager

In the Schedule step click the Export to list arrow below the Gantt chart click MindManager and thenclick the Go button You can also click File on the menu bar point to Export to and then clickMindManager

Your tasks assignments start and finish dates durations costs Done and notes (excludingattachments) appear in a MindManager file

To export from MindManager to Project KickStart

In MindManager click File on the menu bar point to Send To and then click Project KickStart Thenclick the OK button to start the export

You can also click the Project KickStart icon at the bottom of the MindManager window

Benefits of using Project KickStart and MindManager together

Visualize your plan in two ways Brainstorm plan and communicate your project details in both agraphical and linear style

Develop a graphical plan and then fine-tune the details MindManager uses mindmappingtechniques to develop a high-level plan in a graphical format Export to Project KickStart to enhanceyour plan details by focusing on your projects goals obstacles and resource needs You can alsocreate a Gantt chart schedule

Communicate concepts Project KickStart users can display their plans in a highly graphicalmindmapping format in MindManager The maps make it easier to communicate complex processesand visually identify important tasks issues and relationships

Tip

If you dont already use MindManager you can purchase it in our Thinking Tools Store

-o-

137

copy Experience In Software Inc 1995 - 2006

Export to WBS Chart Pro

If you use WBS Chart Pro you can export your plan from Project KickStart to WBS Chart Pro in a click of abutton

To export to WBS Chart Pro

In the Schedule step click the Export to list arrow below the Gantt chart click WBS Chart Pro andthen click the Go button You can also click File on the menu bar point to Export to and then clickWBS Chart ProYour project is displayed under the project name Each phase in the project is shown in a box with ashadow Each lower level task in a phase is displayed under their respective phase box groupedtogether with the other tasks in that phase

Benefits of using Project KickStart and WBS Chart

Visualize tasks Work with tasks in a tree-style chart called a Work Breakdown Structure (WBS)chart

Communicate your project plan with others WBS Chart uses the outline you create in ProjectKickStart to create a top-down picture of your plan This picture is similar to an Organization chart Butinstead of displaying the structure of your company a WBS chart displays the structure of your projectplan

Notes

WBS Chart refers to the phases in the project as Summary Tasks and the detail for each phase asTasks

The export only works if WBS Chart is not currently running You must close WBS Chart before you cancreate another chart

See Also

Export MPX Files

-o-

138

copy Experience In Software Inc 1995 - 2006

Export MPX Files

The MPX file format is an ASCII format created by Microsoft Project or another program and is used tosend data to and from project management software programs

The following programs can create and open MPX files

FastTrack Schedule

Microsoft Project (95 or 98)

Project KickStart 5

Project KickStart 32

RiskyProject

SureTrak Project Manager

WBS Chart

In these programs you save a project as an MPX file using the Save As command on the File menu Youcan then open an MPX file by using the Open command on the File menu and then specifying the file typeas mpx

For example if you want to move a project from Project KickStart 5 to Project KickStart 32 you can savethe project as an mpx file and then open it in Project KickStart 32

In Microsoft Visio you can create a Visio project time line from Project KickStart To do so you first mustsave your file in Project KickStart as an MPX file Then

1 Start Visio

2 Click File on the menu bar point to New click Business Diagram and then click Project TimelinesWizard

3 Click Next

4 On the second window click Import MPX File to import the Project KickStart mpx file

5 Enter the file location and name or click Browse to locate the file

6 Follow the instructions in the Visio Project Timelines Wizard windows

Tip

If you have difficulty importing the mpx file remove any commas from task names

-o-

139

copy Experience In Software Inc 1995 - 2006

Reference

140

copy Experience In Software Inc 1995 - 2006

Menus

File Menu

Command Keyboard Shortcut Description

New Project Ctrl+N Creates and names a new project fileOpen Project Ctrl+O Opens a previously saved Project KickStart 4 or 5 file

(prx) Project KickStart 3 file (prj) or mpx fileClose Ctrl+W Closes an open Project KickStart fileSave Ctrl+S Saves a project file (prx) in which you made changes Save As Saves a project file with a different file name or different

file format such as MPXPrint Task Reports

Ctrl+T Generates and prints a report letting you preview thecontents

Print Gantt ChartReports

Ctrl+G In the Gantt chart (Schedule step) generates andprints the Gantt chart in the current timescale

Export To Sends the project to another program such asMicrosoft Outlook or ACT 7

Recent file list Lists the last three files opened in Project KickStartExit

Alt+F4 Exits the program

-o-

141

copy Experience In Software Inc 1995 - 2006

Edit Menu

Command Keyboard Shortcut Description

UndoRedo Ctrl+Z Undoes or repeats the last operationCut

Ctrl+X Deletes the currently selected information placing it on theclipboard so you can paste it elsewhere

Copy

Ctrl+C Places a copy of selected information on the Clipboard so youcan paste it elsewhere

Paste

Ctrl+V Places information from the Clipboard to the currently selectedlocation

Select all Ctrl+A Selects all the content in the windowAdd a line Adds a new row where you can enter text

-o-

142

copy Experience In Software Inc 1995 - 2006

View Menu

Command Description

Tool Bar Shows or hides the toolbar (a checkmark indicates thetoolbar is displayed)

Steps Bar Shows or hides the Steps bar (a checkmark indicates the Steps bar is displayed)

Name Go to the Name your project stepPhases Go to Phases stepGoals Go to Goals stepSimilar Projects Go to Similar projects stepPeople Go to People stepObstacles Go to Obstacles stepAssign Go to Assign tasks to people stepTasks Go to Tasks stepSchedule Go to Schedule step

-o-

143

copy Experience In Software Inc 1995 - 2006

Tools Menu

Command Keyboard Shortcut Description

Spelling

F7 Checks spelling of project dataexcept for names of people

Collaboration To access or find out aboutGoToMeeting

Options Select options for running thesoftware

-o-

144

copy Experience In Software Inc 1995 - 2006

Options

-o-

145

copy Experience In Software Inc 1995 - 2006

Data Menu

The Data menu is available in the Tasks and Schedule steps for manipulating tasks and creating ascheduleCommand Description

Move Up Moves the selected task item upMove Down Moves the selected task item downOutdent Moves the selected task item to the leftIndent Moves the selected task item to the rightInsert Task Insert task in row aboveInsert SubTask Insert subtask below current rowDelete Task Delete current taskEdit Task Properties Brings you to an edit screen where you can edit task

name change assignments and edit task notesEdit Notes Brings you to an edit screen for editing task notesColor Taskbars Change the color of selected tasks (in Schedule)Change Working Days Select which days are working and which are

nonworking (in Schedule)Link Tasks Link tasks in Gantt chart (Pro Users)Unlink Tasks Unlink tasks in Gantt chart (Pro Users)

-o-

146

copy Experience In Software Inc 1995 - 2006

Timescale Menu

The Timescale menu is available in the Schedule step so you can change the display of the Gantt chartschedule

Command Description

Days Displays a daily schedule in theGantt chart

Weeks Displays a weekly schedule inthe Gantt chart

Months Displays a monthly schedule inthe Gantt chart

Quarters Displays a quarterly schedule inthe Gantt chart

Years Displays a yearly schedule inthe Gantt chart

-o-

147

copy Experience In Software Inc 1995 - 2006

Help Menu

Command Description

Project KickStart Help Help for Project KickStart including a Table ofContents and index of terms

Online Tutorials View several Getting Started Tutorials to getyou started with Project KickStart whether youare a new or experienced user

Keyboard Shortcuts Shortcuts for programTechnical Support How to obtain Technical Support for Project

KickStart via web form and email[Send Log to Technical Support] If the program detects an error it writes a log

of technical issues Click Send Log toTechnical Support to send the error log to us

ProjectKickStartcom Visit the Project KickStart Web siteGet Latest Version See what the latest published version is and

download it if you need itAbout Project KickStart Shows Project KickStart version number build

date copyright and system information

-o-

148

copy Experience In Software Inc 1995 - 2006

Shortcuts

Use the following keyboard shortcuts to move quickly around in Project KickStart

Navigation

Move forward to the next window Alt+NMove back to the previous window Alt+BSteps

Go to Name step Alt+MGo to Phases step Alt+SGo to Goals step Alt+GGo to Similar step Alt+RGo to People step Alt+PGo to Obstacles step Alt+OGo to Assign step Alt+IGo to Tasks step Alt+KGo to Library (Phases Tasks GoalsPeople Obstacles)

Alt+L

Menus

File menu Alt+FEdit menu Alt+EView menu Alt+VShow menu (Tasks step) Alt+WOutline menu (Tasks step) Alt+UTimescale (Schedule step) Alt+CHelp menu Alt+H F1Other

Edit tasks assignments amp notes (Tasks step)F3Save Ctrl+SPrint Task Report Ctrl+PPrint Gantt Chart (Schedule step) Ctrl+GCut Ctrl+XCopy Ctrl+CPaste Ctrl+VInsert Row InsertDelete Row DeleteInsert Line Break (in Notes in Task List andSchdule steps)

Enter

Spell Check

Ignore Alt+IIgnore All Alt+GChange Alt+CChange All Alt+HHelp

149

copy Experience In Software Inc 1995 - 2006

Contents in Help Alt+CIndex Alt+IBack in Help Alt+BClose Help Alt+LHelp about the current step Alt+H

-o-

150

copy Experience In Software Inc 1995 - 2006

Share Project KickStart Data

Project KickStart makes it easy to share data with other people involved with a project You can share yourProject KickStart data in the following ways

Send a printed report Make a PowerPoint presentation Send a file (prx html rtf mpx) Post an HTML file to a Web site and access it with your web browser Export to other programs such as Microsoft Word or Excel and send data in a format the recipient can

access (such as doc xls or mpx)

Note

You can also collaborate with a colleague by conducting an online meeting using GoToMeeting (Prousers)

-o-

151

copy Experience In Software Inc 1995 - 2006

Open a Project

After you create a project and save it in a prx prj or mpx file using Project KickStart or other softwareyou can open the project in Project KickStartTo open a project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click a file type (prxprj or mpx)

3 Navigate to the folder that contains the file4 Double-click the name of the file

Opening a Project KickStart 3 prj file converts it to a prx file

Generally prj files are stored in cprogram filesProject KickStart 3

The tasks in the converted Project KickStart 5 file will have the same start and finish dates anddurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way To have weekends as non working days open the working days calendar and markweekends as non working

Opening a mpx file converts it to a prx file

The tasks in each project have the same start and finish dates and durations

-o-

152

copy Experience In Software Inc 1995 - 2006

Dedication

I dedicate this software program to my new colleague

Kevin Ahlvin

Roy A Nierenberg President

-o-

153

copy Experience In Software Inc 1995 - 2006

Credits and Trademarks

Credits

Missak Koumoudjian Program Architect and Chief Programmer

Kevin Ahlvin Interface DesignAnn Kawamoto Quality AssuranceAlexander Setzepfandt Quality AssuranceJackie LeungJeffrey Chow

Programming Interns

Kevin Ahlvin Product Supervisor and CoordinatorJoseph Fusco Project Management Consultant and content

providerLisa RuffoloJoseph Fusco

Help System

Roy A Nierenberg President

Trademark

Project KickStart and Project KickStart Wizard are trademarks of Experience In Software Inc in the UnitedStates andor in other countries All rights reserved All other trademarks mentioned herein are the propertyof their respective owners

-o-

154

copy Experience In Software Inc 1995 - 2006

Uninstalling

You can uninstall Project KickStart 5 through the Control Panel AddRemove Programs Select ProjectKickStart 5 This starts the InstallShield Maintenance Program You should then remove all of theprogram files that were installed It will not erase your Project KickStart prx data files

If that does not work you can delete the Project KickStart files manually

Note

If you purchased Project KickStart and you want to return it for a refund follow the instructions forDe-activating the software at httpwwwprojectkickstartcomcontactreturnscfm

-o-

155

copy Experience In Software Inc 1995 - 2006

Using Past Projects

You can use past projects in two ways

If you have projects that are similar you can use a past project as a template for a new project In theWelcome window select Open a Project Open that project and Save As under a different name Nowyou can open up the renamed project and modify it for the current project

You can draw from several projects in the Similar Projects step First select projects that are similarand click Next Then select tasks from those projects and decide where they would fit into your currentproject

See Also

Opening a project Compatibility with earlier versions

-o-

156

copy Experience In Software Inc 1995 - 2006

Index

- - Change Working Schedule 85

- -prj file format 13

- A -About Linking Tasks (Pro Users) 59About Scheduling Tasks 55About the Gantt Chart 57ACT 120 92 122ACT 6 92 122ACT 7 or later 92 120Activate 14Activating Trial Version 14Add a New Person or Resource 39add a subtask 83add a task 83Add a Task or Subtask 47Add or Change Task Assignments 51Add or Change Task Details 52Add Subtask 63Add Task 63Add URL 49Additional Features in Task Data View (Pro Users) 68Additional Tools in Chart View (Pro Users) 71Adobe PDF 117Assignments tab 80Attachments 49Autolink tasks (Pro Users) 58

- B -Back 10borrow tasks 29

- C -Change Details for Linked Tasks (Pro Users) 81Change Project Start 63Change Task Dates 73Change Task Details 80Change the Appearance of the Task List 43Change the Display of the Schedule 61Change Timescale 63Change Working Schedule 63Chart view 57

157

copy Experience In Software Inc 1995 - 2006

Cloning projects 155Color 63 86Compatibility 13Compatibility with earlier versions 13convert projects 13Coordination 12Create and Print Task Reports 102Credits 153Credits and Trademarks 153critical path 88CSV 96Customer support 20Customer Support 20Customizing Project KickStart

- D -Dashboard 99Data Menu 145Dedication 152Delete 63delete a task 83demote 46dependencies 12 76

- E -Edit Menu 141Edit Notes and Attachments 63Edit or Substitute People 40Edit Task Information 63Email Task Reports 108End User License Agreement 16error 21Error Messages 21export from MindManager 136Export MPX Files 138Export to ACT 6 122Export to ACT 7 and Later 120Export to FastTrack Schedule 134Export to Microsoft Excel 128Export to Microsoft Outlook 123Export to Microsoft PowerPoint 130Export to Microsoft Project 132Export to Microsoft Word 125Export to Milestones Professional 135Export to Mindjet MindManager 136Export to SureTrak Project Manager 133Export to WBS Chart Pro 137

- F -FastTrack Schedule 134File Menu 140Fit to page 111Fit to Smallest Size 111

158

copy Experience In Software Inc 1995 - 2006

- G -Gantt chart 55 57General tab 80Goal 26Goal statements 26Goals 26Goals - Step 1 of 3 26Goals - Step 2 of 3 27Goals - Step 3 of 3 28goals library 26 89Goalsadd 26Goalsdelete 26Goalsedit 26Goalstasks for 27GoToMeeting 150 12

- H -Handouts 111Help Menu 147hyperlink 49

- I -Import ACT 92import contacts and users 92import Outlook contacts 94Import Outlook Contacts via CSV to the People Library (Pro Users) 96ImportCSVToPKSexe 96Indent 46Individual Assignments 102Introduction 7Introduction 7

- K -Knowledge Libraries 90

- L -lag time 81lead time 59 81library 89License Key 14link 59Link lines 59Link tasks 12 65linked tasks 59

- M -major activities 24Make Tasks Overlap (Pro Users) 87Manage a Library 90

159

copy Experience In Software Inc 1995 - 2006

Menu 140Microsoft Excel 128Microsoft Outlook 123Microsoft PowerPoint 130Microsoft Project 132Microsoft Project (95 or 98) 138Microsoft Visio 138Microsoft Word 125Milestone 69 79Milestones Professional 135Mindjet MindManager 136MindManager 136

- N -Name 23Name Your Project 23Navigating Project KickStart 10Next 10Notes and Attachments tab 80

- O -Objectives 26Obstacles 34Obstacles - Step 3 of 3 36Obstacles Library 89Open a Project 151Options 144Outdent 46Outdent and Indent arrows 63Outlook Calendar 123Overview

- P -Page Setup 107 116 100PDF 117people 31People - Step 3 of 3 28People Library 91phase 24phase dates 75Phase Dates Cannot Be Edited 75phases 24Phases - Step 1 of 2 24Phases - Step 2 of 2 25Phases Library 89Phases Goals People amp Obstacles 102PowerPoint presentation 130Pred 68Predecessor 68Predecessor tasks 59predecessors 76Print a Gantt Chart 111Print Dashboard Reports 99Print Preview 105Print Preview a Gantt Chart 115Print Reports 98Print Task Reports 102

160

copy Experience In Software Inc 1995 - 2006

Printer Setup 106Printing to an Adobe PDF file 117prj 13Pro 145Pro Edition 145Product support 20Project 23Project KickStart 3 prj file 151Project KickStart for Windows 7project name 23project start date 73project template 155project title 23promote 46promote and demote tasks 83

- Q -Quick Tour of Working with Linked Tasks (Pro Users) 76

- R -Red vertical line 69Redo 11Register Project KickStart 22Registering Project KickStart 22remove people 38Remove People from a Task 38reorder tasks 83Reorganize Tasks in Task Data View 83Repeat tasks on every page (for handouts) 111Reporting Technical Issues 21resource 31resources 31restore 34return 154risks 34RiskyProject 138

- S -Save As 101Save as HTML 109Save as RTF 110Save Gantt Chart Images 118Schedule 55Send Error Report 21similar projects 29spelling 53starter schedule 55Steps 7subtask 47Subtasks 46Succ 68Successor 68Successor tasks 59successors 76Summary bar 69Support 20SureTrak Project Manager 133

161

copy Experience In Software Inc 1995 - 2006

- T -Task Data view 57task dates 73Task Report 102Taskbar 69Taskbar with percent done 69Tasks 25Tasks in Phases 25Tasks Library 89team 31Technical support 20timescale 84Timescale Menu 146Tools Menu 143Trademark 153trademarks 153Trial 14

- U -unassigning 38Understand Chart View 69Understand Task Data View 66Undo 11UndoRedo Buttons 11uninstallUninstalling 154Unlink tasks 12 65Up and Down arrows 63Use Project KickStart to 8Use the Gantt Chart Toolbar 63Use the Planning Wizard 9Uses 8Using Past Projects 29 155

- V -Version View Menu 142Visio 138

- W -Wall chart 111WBS Chart Pro 137Welcome to Project KickStart 7Whats Due Next Month 99Whats Due Next Week 99Whats Due Today 99Whats New in Project KickStart Pro 5 11Windows Vista 20

162

copy Experience In Software Inc 1995 - 2006

copy Experience In Software 2008w w w projectkickstartcom

  • Table of Contents
  • Start Here Welcome to Project KickStart
    • Introduction
      • Welcome to Project KickStart
      • Use Project KickStart to
      • Use the Planning Wizard
      • Navigating Project KickStart
      • Whats New in Project KickStart Pro 5
      • Whats New in Project KickStart Pro 5 (Pro Users)
      • Compatibility with earlier versions
      • Activating Trial Version
        • Licenses and Support
          • End User License Agreement
          • Customer Support
          • Reporting Technical Issues
          • Register Project KickStart
              • Planning Projects
                • Name Your Project
                • Phases - Step 1 of 2
                • Phases - Step 2 of 2
                • Goals - Step 1 of 3
                • Goals - Step 2 of 2
                • Goals - Step 3 of 3
                • Similar Projects - Step 1 of 2
                • Similar Projects - Step 2 of 2
                • People - Step 1 of 3
                • People - Step 2 of 3
                • People - Step 3 of 3
                • Obstacles - Step 1 of 3
                • Obstacles - Step 2 of 3
                • Obstacles - Step 3 of 3
                  • Assigning People
                    • Assign Tasks to People
                    • Remove People from a Task
                    • Add a New Person or Resource
                    • Edit or Substitute People
                      • Organizing the Project Plan
                        • About Organizing Tasks
                        • Change the Appearance of the Task List
                        • Show or Hide Tasks in the Task List
                        • Move Tasks within the Task List
                        • Outdent and Indent Tasks
                        • Add a Task or Subtask
                        • Edit Tasks
                        • Add Task Notes and Attachments
                        • Add or Change Task Assignments
                        • Add or Change Task Details
                        • Check Spelling
                          • Scheduling Tasks in the Gantt Chart
                            • Scheduling Overview
                              • About Scheduling Tasks
                              • About the Gantt Chart
                              • Autolink tasks (Pro Users)
                              • About Linking Tasks (Pro Users)
                              • Change the Display of the Schedule
                              • Use the Gantt Chart Toolbar
                              • Use the Gantt Chart Toolbar (Pro Users)
                              • Understand Task Data View
                              • Additional Features in Task Data View (Pro Users)
                              • Understand Chart View
                              • Additional Tools in Chart View (Pro Users)
                                • Change Task Dates
                                • Phase Dates Cannot Be Edited
                                • Quick Tour of Working with Linked Tasks (Pro Users)
                                • Link and Unlink Tasks (Pro Users)
                                • Create a Milestone
                                • Change Task Details
                                • Change Details for Linked Tasks (Pro Users)
                                • Reorganize Tasks in Task Data View
                                • Change the Timescale of the Schedule
                                • Specify Working Days
                                • Change the Color of Taskbars
                                • Make Tasks Overlap (Pro Users)
                                • Manage Changes in Your Schedule (Pro Users)
                                  • Managing Libraries
                                    • Use a Library
                                    • Manage a Library
                                    • Manage the People Library
                                    • Import ACT Contacts and Users to the People Library
                                    • Import Outlook Contacts to the People Library
                                    • Import Outlook Contacts via CSV to the People Library (Pro Users)
                                      • Printing Reports
                                        • Printing Dashboards
                                          • Print Reports
                                          • Print Dashboard Reports
                                          • Page Setup
                                          • Save As
                                            • Printing Task Reports
                                              • Print Task Reports
                                              • Print Preview
                                              • Printer Setup
                                              • Page Setup
                                              • Email Task Reports
                                              • Save As HTML
                                              • Save As RTF
                                                • Printing Gantt Chart Reports
                                                  • Print a Gantt Chart
                                                  • Print Preview a Gantt Chart
                                                  • Page Setup
                                                  • Printing to an Adobe PDF file
                                                  • Save Gantt Chart Images
                                                      • Export Project Data
                                                        • Export to ACT
                                                          • Export to ACT 7 and Later
                                                          • Export to ACT 6
                                                            • Export to Microsoft Outlook
                                                            • Export to Microsoft Word
                                                            • Export to Word Processors (Other than Word)
                                                            • Export to Microsoft Excel
                                                            • Export to Microsoft PowerPoint
                                                            • Export to Microsoft Project
                                                            • Export to SureTrak Project Manager
                                                            • Export to FastTrack Schedule
                                                            • Export to Milestones Professional
                                                            • Export to Mindjet MindManager
                                                            • Export to WBS Chart Pro
                                                            • Export MPX Files
                                                              • Reference
                                                                • Menus
                                                                  • File Menu
                                                                  • Edit Menu
                                                                  • View Menu
                                                                  • Tools Menu
                                                                  • Options
                                                                  • Data Menu
                                                                  • Timescale Menu
                                                                  • Help Menu
                                                                    • Shortcuts
                                                                    • Share Project KickStart data
                                                                    • Open a Project
                                                                    • Dedication
                                                                    • Credits and Trademarks
                                                                    • Uninstalling the software
                                                                    • Using Past Projects
Page 2: Project KickStart Help File in PDF format

2

copy Experience In Software Inc 1995 - 2006

3

copy Experience In Software Inc 1995 - 2006

Table of Contents

Start Here Welcome to Project KickStart 6 Introduction 7 Welcome to Project KickStart 7 Use Project KickStart to 8 Use the Planning Wizard 9 Navigating Project KickStart 10 Whats New in Project KickStart Pro 5 11 Whats New in Project KickStart Pro 5 (Pro Users) 12 Compatibility with earlier versions 13 Activating Trial Version 14 Licenses and Support 16 End User License Agreement 16 Customer Support 20 Reporting Technical Issues 21 Register Project KickStart 22Planning Projects 23 Name Your Project 23 Phases - Step 1 of 2 24 Phases - Step 2 of 2 25 Goals - Step 1 of 3 26 Goals - Step 2 of 2 27 Goals - Step 3 of 3 28 Similar Projects - Step 1 of 2 29 Similar Projects - Step 2 of 2 30 People - Step 1 of 3 31 People - Step 2 of 3 32 People - Step 3 of 3 33 Obstacles - Step 1 of 3 34 Obstacles - Step 2 of 3 35 Obstacles - Step 3 of 3 36Assigning People 37 Assign Tasks to People 37 Remove People from a Task 38 Add a New Person or Resource 39 Edit or Substitute People 40Organizing the Project Plan 41 About Organizing Tasks 41 Change the Appearance of the Task List 43 Show or Hide Tasks in the Task List 44 Move Tasks within the Task List 45 Outdent and Indent Tasks 46 Add a Task or Subtask 47 Edit Tasks 48 Add Task Notes and Attachments 49 Add or Change Task Assignments 51 Add or Change Task Details 52 Check Spelling 53Scheduling Tasks in the Gantt Chart 54 Scheduling Overview 55 About Scheduling Tasks 55

4

copy Experience In Software Inc 1995 - 2006

About the Gantt Chart 57 Autolink tasks (Pro Users) 58 About Linking Tasks (Pro Users) 59 Change the Display of the Schedule 61 Use the Gantt Chart Toolbar 63 Use the Gantt Chart Toolbar (Pro Users) 65 Understand Task Data View 66 Additional Features in Task Data View (Pro Users) 68 Understand Chart View 69 Additional Tools in Chart View (Pro Users) 71 Change Task Dates 73 Phase Dates Cannot Be Edited 75 Quick Tour of Working with Linked Tasks (Pro Users) 76 Link and Unlink Tasks (Pro Users) 78 Create a Milestone 79 Change Task Details 80 Change Details for Linked Tasks (Pro Users) 81 Reorganize Tasks in Task Data View 83 Change the Timescale of the Schedule 84 Specify Working Days 85 Change the Color of Taskbars 86 Make Tasks Overlap (Pro Users) 87 Manage Changes in Your Schedule (Pro Users) 88Managing Libraries 89 Use a Library 89 Manage a Library 90 Manage the People Library 91 Import ACT Contacts and Users to the People Library 92 Import Outlook Contacts to the People Library 94 Import Outlook Contacts via CSV to the People Library (Pro Users) 96Printing Reports 97 Printing Dashboards 98 Print Reports 98 Print Dashboard Reports 99 Page Setup 100 Save As 101 Printing Task Reports 102 Print Task Reports 102 Print Preview 105 Printer Setup 106 Page Setup 107 Email Task Reports 108 Save As HTML 109 Save As RTF 110 Printing Gantt Chart Reports 111 Print a Gantt Chart 111 Print Preview a Gantt Chart 115 Page Setup 116 Printing to an Adobe PDF file 117 Save Gantt Chart Images 118Export Project Data 119 Export to ACT 120 Export to ACT 7 and Later 120

5

copy Experience In Software Inc 1995 - 2006

Export to ACT 6 122 Export to Microsoft Outlook 123 Export to Microsoft Word 125 Export to Word Processors (Other than Word) 127 Export to Microsoft Excel 128 Export to Microsoft PowerPoint 130 Export to Microsoft Project 132 Export to SureTrak Project Manager 133 Export to FastTrack Schedule 134 Export to Milestones Professional 135 Export to Mindjet MindManager 136 Export to WBS Chart Pro 137 Export MPX Files 138Reference 139 Menus 140 File Menu 140 Edit Menu 141 View Menu 142 Tools Menu 143 Options 144 Data Menu 145 Timescale Menu 146 Help Menu 147 Shortcuts 148 Share Project KickStart data 150 Open a Project 151 Dedication 152 Credits and Trademarks 153 Uninstalling the software 154 Using Past Projects 155

6

copy Experience In Software Inc 1995 - 2006

Start Here Welcome to Project KickStart

7

copy Experience In Software Inc 1995 - 2006

Introduction

Welcome to Project KickStart

Whether yoursquore a novice or seasoned pro yoursquoll be amazed at how quickly you can create a thoughtfulcomprehensive task list and project schedule Using Project KickStart you can go from raw idea to aproject task list in 30 minutes You do not need any special project management training to use ProjectKickStart

The first thing youll want to do is

Open a project Click to open one of our sample projects

Start a new project Click to begin planning your own project

Open your last project If youve already created a project click this option to open your most recentproject

After that let Project KickStart show you the way Itrsquos easy to navigate Project KickStart with its intuitivegraphical interface--it feels like a coach is guiding you through each step

Next StepsProject KickStart guides you through the process of planning and scheduling your project On the top ofeach Project KickStart window are instructions explaining what to do Read the instructions enter your dataand then click the Next button in the lower-right corner of the window Additional help is always availablefrom the onscreen Advisor and Project KickStart Help

Sample ProjectsThe sample projects are completed projects that let you get a feel for Project KickStart If you find onesimilar to the project you want to create open it save it with a new name and then customize it to meetyour needs

-o-

8

copy Experience In Software Inc 1995 - 2006

Use Project KickStart to

Project KickStart is organized into three sections planning scheduling and exporting to other programs

Plan The Project KickStart graphical interface acts as a Planning Wizard guiding you through eightsteps for planning your project Some planning steps involve brainstorming to identify tasks that youmight otherwise overlook

Schedule The Project KickStart Gantt chart makes scheduling tasks fast and easy You can printtaskbars in color and save Gantt charts reports as images so you can email them to colleagues orinclude them in a report

Export Communicate your projects in a variety of ways by exporting project data to other applicationsincluding Microsoft Outlook With one mouse click you can include Project KickStart plans in aMicrosoft Word document Excel spreadsheet PowerPoint slide presentation and more

People are using Project KickStart to

Create process templates project reports to-do lists and more

Communicate project details to others through reports email and Gantt chart schedules

Ensure project buy-in by including the needs of team members in your plan

Consider project goals and obstacles in the planning process and prevent surprises later

-o-

9

copy Experience In Software Inc 1995 - 2006

Use the Planning Wizard

Project KickStart uses a Planning Wizard that guides you through eight steps for planning your project Tostep through the wizard click each icon on the Steps bar (on the left side of the Project KickStart window) inorder On each window t ips and advice are always available by clicking the Advisor button You click theNext button to continue

Name Each project has a name To start planning your project give it ashort descriptive name

Phases Consider how your project will break down into major activitiesor phases Start by listing your phases and then list the tasks thatbelong in each phase

Goals Goals are what you hope to accomplish in your project Enter orselect the goals for your project Then you can list any new tasks toachieve each goal

Similar Projects often have tasks in common In this step you canborrow tasks from past projects to help you plan this project Then youcan add any new tasks from a similar project to the phases of yourcurrent project

People List the people groups or things that might provide resourcesfor your project including yourself Then identify any new tasks thesepeople might do or suggest for your project

Obstacles Each project has obstacles you can overcome if youanticipate them List the obstacles you will face in your project and thenidentify any new tasks needed to avoid the obstacles

Assign Assign tasks to people and other resources

Tasks Change the order of your tasks add and delete tasks andcreate subtasks You can also edit tasks change assignments and addnotes

Schedule Schedule the tasks in your project To make schedulingeasier new projects open with a starter schedule beginning todaywhich you can customize to fit your project

-o-

10

copy Experience In Software Inc 1995 - 2006

Navigating Project KickStart

When you use the Planning Wizard you work with a step window similar to the following illustration

Steps bar Click a step button to perform a step in the Planning Wizard The selected button shows yourcurrent step

Name of your project Shows the name entered in the Name step

Menu bar Select options from the menu bar to work with your projects

Toolbar Click buttons to perform common tasks such as saving your project

Step instructions Indicate how to perform the current step

Library button Click to open a library for the current step For example click the Goals Library button toopen a library listing typical project goals

Back and Next buttons Click a button to return to the previous step or continue to the next step in thePlanning Wizard

Advisor button Click to see instructions tips and notes for completing the current step

-o-

11

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5

The following table outlines whatrsquos new in Project KickStart Pro 5

If you own a previous version of Project KickStart yoursquoll notice the new Pro version has a new look and feelAs you begin to check it out yoursquoll soon discover Project KickStart Version 5 is a lot more powerful thanprevious versions and comes with some great new features

FEATURE DESCRIPTION IMPROVED

NEW

Dashboard Reporting

Quickly assess what is due TodayNext Week or Next Month

X

Import Contacts Import from a comma separatedvalue (CSV) file

X

Templates Use as is or customize X

Gantt Chart Greater stability and functionality X

User Interface Contemporary look and colorscheme

X

Preferences Customize look and feel andprogram defaults

X

Productivity Pack Project template Word docs fornewbies

X

Exports Improved Outlook MindManager and ACTimproved data exchange

X

-o-

12

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5 (Pro Users)

This feature is available only in Project KickStart Professional

The following table outlines whatrsquos new in Project KickStart Pro 5

FEATURE DESCRIPTION IMPROVED NEW

Gantt Chart Task dependencies in Gantt chart X

Link tasks Show task dependencies X

Unlink tasks Remove task dependencies X

Add predecessors Add task predecessors X

Add successors Add task successors X

Project Coordination Link to GoToMeeting for onlinemeetings on projects

X

Project KickStart Pro now includes dependencies on the Gantt chart This sophisticated scheduling andproject management tool is new to Project KickStart Pro and is designed to make complex projectscheduling easy and straightforward

Use dependencies to handle scheduling demands delays and surprises without modifying every task inyour project Dependencies let you make adjustments as events change giving you a more robust scheduleand the opportunity to conduct what-if analysis

Suppose you are managing a landscaping project involving subcontractors and dozens of tasks One ofyour first tasks is to pave a path with flagstones but the shipment of flagstones is two days late Usingdependencies you can delay the path-paving task in a couple of clicks and Project KickStart Proautomatically updates the schedule for the remaining tasks

Although dependencies meet your advanced scheduling needs the Project KickStart Pro approach todependencies keeps them as simple as possible If you want to link a couple of tasks which are dependenton one another you can simply highlight the tasks and click the link icon

If you select the option of Autolinking tasks then when you display the Gantt chart the first time all tasksare pre-linked allowing you to adjust durations schedules of individual tasks and time between taskswhich is called Lead Time in Project KickStart Pro

Unlike other project management programs such as Microsoft Project Project KickStart Pro does notburden you with complicated error messages and various types of dependencies It provides only one typeof dependency finish-to-start which is the most common type This means you can fine-tune your scheduleas soon as you open the Gantt chartmdashwithout having to learn technical terms or advanced projectmanagement techniques

The Project Coordination functionality that we are providing is through GoToMeeting and is a chargedservice

Note

These features are in addition to those listed on the Whatrsquos New in Project KickStart 5 page

-o-

13

copy Experience In Software Inc 1995 - 2006

Compatibility with earlier versions

Project KickStart 5 can open and save projects in Project KickStart 4 prx file format (Same as ProjectKickStart 5)

Project KickStart 5 can open and convert projects saved in Project KickStart 3 prj file format You need tohave a licensed copy of Project KickStart 3 on your system to make the conversion

To open a prj project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click prj file type3 Navigate to the folder that contains the prj file Generally prj files are stored in cprogram filesProject

KickStart 34 Double-click the name of the file

Tips

The tasks in the converted Project KickStart 5 file will have the same start and finish dates and samedurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way (ie as working days) To have weekends as non working days click the Change WorkingSchedule button on the Gantt chart toolbar and mark weekends as non working

Note

Project KickStart 5 does not open and convert prj files from Project KickStart 1 or 2

-o-

14

copy Experience In Software Inc 1995 - 2006

Activating trial version

You may have obtained a FREE 20-day trial version of Project KickStart 5 from our website or from areseller

To convert your Trial Version to a Full Version youll need to purchase a License Key and to activate thesoftware

To activate Project KickStart 5 trial1 Start the Project KickStart trial

2 If you have not purchased your License Key yet click the Buy button to purchase online3 If you have purchased a License Key click the Activate button and copy and paste the License Key

that you received when you purchased Project KickStart as well as your name and email

15

copy Experience In Software Inc 1995 - 2006

4 You must be connected to the Internet and you must tell your Firewall to allow communication forPKS5Kickstartexe

Tip

Your License Key allows 2 activations per user One is for your primary computer and one is for asecond computer you use such as your laptop or home computer

-o-

16

copy Experience In Software Inc 1995 - 2006

Licenses and Support

End User License Agreement

EXPERIENCE IN SOFTWARE INC END USER LICENSE AGREEMENT AND WARRANTYDISCLAIMER

PROJECT KICKSTARTtrade STANDARD 5 AND PRO 5 EDITIONS

NOTICE This is a legally binding contract between you the end user and EXPERIENCE IN SOFTWAREINC

EXPERIENCE IN SOFTWARE INC (EIS or LICENSOR) LICENSES THE ENCLOSED SOFTWARETO YOU (USER or LICENSEE) ONLY UPON THE CONDITION THAT YOU ACCEPT ALL OF THETERMS CONTAINED IN THIS LICENSE AGREEMENT PLEASE READ THE TERMS CAREFULLY BYOPENING THIS PACKAGE BREAKING THE SEAL CLICKING ON THE ldquoAGREErdquo OR ldquoYESrdquo BUTTONOR OTHERWISE INDICATING ASSENT ELECTRONICALLY OR LOADING THE SOFTWARE YOUAGREE TO THE TERMS AND CONDITIONS OF THIS AGREEMENT IF YOU DO NOT AGREE TOTHESE TERMS AND CONDITIONS CLICK ON THE ldquoI DO NOT AGREErdquo ldquoNOrdquo BUTTON OR MAKE NOFURTHER USE OF THE SOFTWARE IF YOU DO NOT AGREE TO THESE TERMS THEN EIS ISUN-WILLING TO LICENSE THE SOFTWARE TO YOU IN WHICH EVENT YOU SHOULD RETURN THEFULL PURCHASED PRODUCT WITH PROOF OF PURCHASE TO LICENSOR OR THE DEALER FROMWHOM IT WAS ACQUIRED WITHIN 15 DAYS OF PURCHASE AND YOUR MONEY WILL BEREFUNDED

LICENSE AND WARRANTY

The software that accompanies this license (Software) is the property of EIS and is protected by copyrightand other intellectual property law Although EIS at all times owns the Software you will have certain rightsto use the Software after your acceptance of this license Except as may be modified by an addendumwhich may accompany or be added to this license your rights and obligations with respect to the use of thisSoftware are as follows

You may

(i) install and use one copy of the specified edition of Software and documentation on a single computerand only by one user (ldquoPrimary Userrdquo) If you have purchased multiple licenses for the Software asindicated as Quantity or Number of Licenses on the Invoice or electronic confirmation issued by EIS orits Resellers then at any time you may have as many copies of the Software in use as you have licenses The Software is ldquoin userdquo on a computer when it is loaded into the temporary memory (ie RAM) or installedinto the permanent memory (eg hard disk CD-ROM or other storage device) of that computer

(ii) install and use a second copy of the Software on a second computer for the limited and exclusive use ofthe Primary User

(iii) use the Software on a network provided that Licensee has a licensed copy of the Software for eachnamed user that can access the Software over that network

(iv) make one copy of the Software for archival purposes or copy the Software onto the hard disk of yourcomputer and retain the original for archival purposes

(v) after written notice to EIS transfer the Software on a permanent basis to another person or entityprovided that you retain no copies of the Software and the transferee agrees to the terms of this agreement

You may not

(i) rent lease copy distribute license or otherwise transfer the Software or its documentation to any otherparty Licensee may make a reasonable number of back-up copies for archival purposes only TheSoftware contains copyrighted material trade secrets and other proprietary material If Licensee has theright to duplicate the Software for multiple Users then Licensee must reproduce on all such copies of theSoftware the copyright notices and any other proprietary legends that were on the original copy of theSoftware or

(ii) decompile reverse engineer disassemble translate make any attempt to discover the source code ofthe Software or otherwise reduce the Software to a human perceivable form or modify network or create

17

copy Experience In Software Inc 1995 - 2006

derivative works based upon the Software or the documentation in whole or in part nor permit any otherparty to do so

Notwithstanding anything herein if the Software is lawfully acquired outside of the United States within ajurisdiction which is a member of the European Union subject to the EEC Council Directive 91250EEC ofMay 14 1991 Licensee agrees that within that jurisdiction it shall not and shall not allow any party onLicensees behalf to attempt to reverse engineer or decompile the Software into another computerlanguage except as expressly and specifically provided in the EEC Council Directive 91250EEC of May14 1991 Any and all information obtained during such lawful reverse engineering andor decompilingactivities including but not limited to the organization logic algorithms and processes of the Softwareshall be deemed to be the confidential and proprietary information of EIS

Licensee shall not make copies of the copyrighted Software documentation without the prior writtenpermission of EIS provided that for electronic transactions Licensee may make one (1) hard copy of suchdocumentation for each User

Intellectual Property and Duplication of Software

The Software contains copyrighted material trade secrets and other proprietary material If Licensee hasthe right to duplicate the Software for multiple Users then Licensee must reproduce on all such copies ofthe Software the copyright notices and any other proprietary legends that were on the original copy of theSoftware

Upgrades

To use a Product identified as an upgrade you must first be licensed for the product identified by EIS aseligible for the upgrade After upgrading you may no longer transfer the product that formed the basis foryour upgrade eligibility to another person or entity

Technical Support

Licensee must register the Software in order to be eligible for free technical support (including installationand registration of the product) during the first 90 days after purchase

Thirty Day Money Back Guarantee

If you are the original Licensee of this copy of the Software and are dissatisfied with it for any reason youmay return the complete product together with your receipt to EIS or an authorized dealer postageprepaid for a full refund at any time during the thirty-day period following the delivery to you of thePurchased Software

Export Law Assurances

You are responsible for complying with all trade regulations and laws both foreign and domestic Youacknowledge that none of the Software or underlying information or technology may be downloaded orotherwise exported or re-exported (i) into Afghanistan (Taliban-controlled areas) Cuba Iran Iraq LibyaNorth Korea Serbia (except Kosovo) Sudan and Syria or any other country subject to a US embargo or(ii) to anyone on the US Treasury Departments list of Specially Designated Nationals or the USCommerce Departments Denied Parties List or Entity List By using the Software you are agreeing to theforegoing and are representing and warranting that (i) no US federal agency has suspended revoked ordenied you export privileges (ii) you are not located in or under the control of a national or resident of anysuch country or on any such list and (iii) you will not export or re-export the Software to any prohibitedcounty or to any prohibited person entity or end-user as specified by US export controls as defined byEAR 15 CFR Parts 730-774 and BXA (httpwwwbxadocgov)

Data Collection and Privacy Policy

You acknowledge and agree that EIS may collect and retain information about you such as your nameaddress and e-mail address You also understand that EIS may employ other companies to performfunctions on our behalf such as fulfilling orders delivering packages sending postal mail and e-mailproviding marketing assistance and processing credit card payments These companies may have accessto personal information needed to perform their functions and may not use such information for otherpurposes By assenting to this agreement you agree that you have read and understand our Privacy PolicyFor more detailed information httpwwwprojectkickstartcomhtmlprivacy_statementhtm

Termination

This License is effective until terminated Licensee may terminate this License at any time by destroying allcopies of the Software and its documentation This License will terminate immediately without notice from

18

copy Experience In Software Inc 1995 - 2006

EIS if Licensee fails to comply with any provision of this License Upon termination Licensee must destroyall copies of the Software and its documentation and cease and desist from any further use of the Software

Limited Warranty

EIS warrants that the media on which the Software is distributed will be free from defects and that theSoftware shall perform substantially as described in its documentation for a period of sixty (60) days frompurchase Your sole remedy in the event of a breach of this warranty will be that EIS will replace anydefective media returned to EIS within the warranty period EIS does not warrant that the Software willmeet your requirements or that operation of the Software will be uninterrupted or that the Software will beerror-free

THE ABOVE WARRANTY IS EXCLUSIVE AND IN LIEU OF ALL OTHER WARRANTIES WHETHEREXPRESS OR IMPLIED INCLUDING THE IMPLIED WARRANTIES OF MERCHANTABILITY FITNESSFOR A PARTICULAR PURPOSE AND NONINFRINGEMENT OF INTELLECTUAL PROPERTY RIGHTSTHIS WARRANTY GIVES YOU SPECIFIC LEGAL RIGHTS YOU MAY HAVE OTHER RIGHTS WHICHVARY FROM STATE TO STATE AND COUNTRY TO COUNTRY

Disclaimer of Damages

REGARDLESS OF WHETHER ANY REMEDY SET FORTH HEREIN FAILS OF ITS ESSENTIALPURPOSE IN NO EVENT WILL EIS OR ITS RESELLERS BE LIABLE TO YOU FOR ANY SPECIALCONSEQUENTIAL INDIRECT OR SIMILAR DAMAGES INCLUDING BUT NOT LIMITED TO ANY LOSTPROFITS OR LOST DATA ARISING OUT OF THE USE OR INABILITY TO USE THE SOFTWARE EVENIF EIS HAS BEEN ADVISED OF THE POSSIBILTIY OF SUCH DAMAGES SOME STATES DO NOTALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FOR INCIDENTAL OR CONSEQUENTIALDAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAY NOT APPLY TO YOU IN NO CASESHALL EISS ITrsquoS RESELLERrsquoS LIABILITY EXCEED THE PURCHASE PRICE FOR THE SOFTWARE

SOME STATES AND COUNTRIES INCLUDING MEMBER COUNTRIES OF THE EUROPEANECONOMIC AREA DO NOT ALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FORINCIDENTAL OR CONSEQUENTIAL DAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAYNOT APPLY TO YOU

The disclaimers and limitations set forth above will apply regardless of whether you accept the Software

US Government Restricted Rights

DISTRIBUTION TO THE US GOVERNMENT This Software is commercial software developedexclusively at private expense This Software and the documentation are provided with RESTRICTEDRIGHTS applicable to private and public licenses alike Use duplication or disclosure by civilian agenciesof the US Government shall be in accordance with the Commercial Computer Software-Restricted Rightsclause at FAR 52227-19 Use duplication or disclosure by Department of Defense agencies is subjectsolely to the terms of this software licensing agreement pursuant to DFARS 2277202Contractormanufacturer of the Software is EXPERIENCE IN SOFTWARE INC 2029 Durant AveBerkeley CA 94704 USA

General

This Agreement shall be governed by the laws of the State of California without giving effect to principles ofconflict of laws You hereby consent to the exclusive jurisdiction and venue of the state courts sitting in SanFrancisco County California or the federal courts in the Northern District of California to resolve anydisputes arising under this Agreement This Agreement contains the complete understanding between theparties with respect to the subject matter hereof and supersedes all prior or contemporaneous Agreementsor understandings whether oral or written You agree that any varying or additional terms contained in anypurchase order or other written notification or document issued by you in relation to the Software licensedhereunder shall be of no effect No provision hereof shall be deemed waived or modified except in writing No EIS dealer agent or employee is authorized to make any amendment to this Agreement

The intellectual property protections the disclaimers of warranties and the limitation of damages shallsurvive termination The failure or delay of EIS to exercise any of its rights under this Agreement or uponany breach of this Agreement shall not be deemed a waiver of those rights or of the breach If any provisionof this Agreement is held invalid the remainder of this Agreement will remain in full force and effect

Should you have any questions concerning this Agreement or if you desire to contact EIS for any reasonplease write to EXPERIENCE IN SOFTWARE INC 2029 Durant Ave Berkeley CA 94704 USA

-o-

19

copy Experience In Software Inc 1995 - 2006

20

copy Experience In Software Inc 1995 - 2006

Customer Support

When you need help in solving a problem with the software Experience In Software is available to assistyou First check this help file for information on the part of the program you are having a problem withAlso take a look at the Web site for late-breaking technical support information wwwprojectkickstartcomsupporttechnical_supportcfm If you are a regustered user you can obtain support in the following ways

Web httpwwwprojectkickstartcomsupportemail_supportcfm E-mail supportprojectkickstartcom

Hours 900 am to 500 pm Pacific time Monday - Friday

To make the support process more efficient have the following information ready for the support staff

Provide your name phone number and email address

Describe the problem including any error messages

If reporting a potential bug describe what you did immediately before seeing the bug

Provide the Project KickStart version number and Build Date (Click Help on the menu bar and thenclick About Project KickStart)

Identify the version of Windows (Windows Vista etc) you are using

Notes

Our policy is to respond to support email within two business days If you have not received aresponse please double check that spam filters are blocking our messages to you If you maintain anincoming whitelist please allow all messages from the projectkickstartcom domain

Support is available in English only If you purchased a translated version please contact your localreseller for help in other languages

See Also

Reporting Technical Issues

-o-

21

copy Experience In Software Inc 1995 - 2006

Reporting Technical Issues

If Project KickStart 5 detects an error it will write a log of technical issues and then create a temporarymenu to the right of the Help menu which says Send Log to Technical Support You should immediatelyclick the menu and then click Yes to send the error log to us

Please fill in your email address so that we can get back to you with any questions about what caused theerror

Tip

If you have an Internet Security Program such as Norton Internet Security please allowPKS5Kickstartexe to communicate with the Internet to report the error

-o-

22

copy Experience In Software Inc 1995 - 2006

Register Project KickStart

To print this page click the Print button on the Help window toolbar

Register Project KickStart 5 for technical support upgrade information and software discounts You canregister by completing printing and then sending or faxing this form to Experience In Software You canalso register online at httpwwwprojectkickstartcomsupportregiscfm

Name _______________________________________________________

Title _______________________________________________________

Company _______________________________________________________

Address _______________________________________________________

CityStateZip ______________________________________________________

Country _______________________________________________________

Day Phone _______________________________________________________

Fax _______________________________________________________

E-mail _______________________________________________________

Purchased from __ Experience In Software __ Other ____________________

Number of people in company _ 1 to 25 _ 26 to 100 _ 101 to 1000 _ Over 1000

Which industry do you work in ______________________________________

Interested in a project management workshop for your company __ Yes __ No

Comments _______________________________________________________

_________________________________________________________________

_________________________________________________________________

Experience In Software 2029 Durant Ave Berkeley CA 94704

Send or FAX to (510) 644-3823

-o-

23

copy Experience In Software Inc 1995 - 2006

Planning Projects

Name Your Project

Before you start thinking about the tasks in your project yoursquoll want to give your project an appropriate titleIf you open an existing project you might want to edit or change the name of your project

To name your project1 In the Type a name for your project text box enter a name2 Click the Next button

Tips

You can enter up to 58 characters and more than one

Use short descriptive project names such as ldquoCompany Web Siterdquo

Avoid vague project names such as ldquoDatabase Projectrdquo or ldquoCDP-7rdquo especially if you plan to circulatereports to others

Enter your project title using uppercase letters if you want the title to stand out in reports

One way to reuse your projects is to open an existing project and then change its name in this stepAfter saving the project with a different name you can modify details to customize the project

See Also

Use the Planning Wizard

-o-

24

copy Experience In Software Inc 1995 - 2006

Phases - Step 1 of 2

After naming your project the next step in the Planning Wizard is to identify the major activities in yourproject Using phases helps organize tasks so that an obviously early task such as ldquoOrganize materialsrdquoappears before a later task such as ldquoReview final draftrdquo

To enter phases1 Type each phase one per line

OrClick the Phases Library button The Phases Library contains typical phases that many organizationsuse in the early middle and late stages of their projects Drag an entry from the Phases Library to thelist and then click the OK button to close the Phases Library

2 To insert a phase in the middle of the phases list click where you want to insert a new blank line andthen press the Insert keyTo edit the phase text double-click the phase

Tips

Start each phase name with an action verb as in ldquoBuild systemrdquo or ldquoWrite reportrdquo

Use actions that have clearly defined beginnings middles and ends For example you can scheduletasks like ldquoTest prototyperdquo more easily than tasks like ldquoPurchase high-quality partsrdquo

Note

Youll have the opportunity to edit phases later in the Tasks step For now continue planning thephases in your project

See Also

Use the Planning Wizard

Use a Library

Move Tasks within the Task List

-o-

25

copy Experience In Software Inc 1995 - 2006

Phases - Step 2 of 2

For each phase list all of the tasks that could be performed during that phase You can refine and organizethe tasks later in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each phase1 Type the tasks associated with the phase displayed in the Tasks for phase text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next phase in your project click the Next button If you prefer to work out oforder click the Tasks for phase list arrow and then click the phase you want

3 When you are finished entering tasks for the last phase in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

26

copy Experience In Software Inc 1995 - 2006

Goals - Step 1 of 3

Enter the goals for your project the objectives you hope to accomplish Then you can brainstorm anyadditional tasks that will help you meet these goals

To enter goals1 Type each goal one per line

OrThe Goals Library contains typical sample goals that you can customize Drag an entry from the GoalsLibrary to the list and then click the OK button to close the Goals Library

2 To insert a goal in the middle of the goals list click where you want to insert a new blank line and thenpress the Insert keyTo edit the goal text double-click the goal

3 Click the Next button

Tips

List goals that apply to the entire project such as Develop a high-quality system A goal such as Getthe contract signed applies only to an early phase

Write goals as actions you can measure For example Complete the project for $75000 or less ismore concrete and specific than Complete the project within budget Numbers make goal statementsreal

If youre not sure how to measure a goal use a range as in About 15 - 25 people will use the results ofthe project

See Also

Use the Planning Wizard

Use a Library

-o-

27

copy Experience In Software Inc 1995 - 2006

Goals - Step 2 of 3

For each goal list any new tasks needed to accomplish that goal You can refine and organize the taskslater in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each goal1 Type the tasks for accomplishing the goal displayed in the For the goal text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next goal in your project click the Next button If you prefer to work out of orderclick the For the goal list arrow and then click the goal you want

3 When you are finished entering tasks for the last goal in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

28

copy Experience In Software Inc 1995 - 2006

Goals - Step 3 of 3

After you identify new tasks for your project assign each new task to an appropriate phase

To assign new tasks to phases1 Click a task in the New tasks to achieve goals list (on the left)2 Click one or more phases in the Assign them to Phases list (on the right) to which the task belongs A

checkmark appears next to tasks youve assigned

If a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Note

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

29

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 1 of 2

Projects often have tasks in common The Similar Projects step makes it easy for you to borrow tasks fromother projects and add them to your current project

By default this step shows the Project KickStart (PRX) projects stored in the same folder as the currentproject including sample projects and those you already created

To select similar projects1 Review the projects in the list To sort the project names alphabetically click the Project Name header

Click the Project Name header again to sort the names in reverse order2 Click one or more projects in the list that contain tasks you want to use in the current project A

checkmark appears next to the projects you selected3 To list projects stored in a different folder on your system click the Browse button and then navigate to

the folder you want4 Click the Next button

If no projects seem related to your current project skip this step for now

Tips

The Similar Projects step becomes more helpful the more you use Project KickStart Every time yousave a project it becomes available for future use

Many projects share the same phases and tasks such as those for setting up a contract or purchasingequipment You can use Project KickStart to create these mini-projects or templates and then importtheir tasks into a new project during the Similar Projects step

-o-

30

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 2 of 2

After you select one or more projects containing tasks you might want to use assign those borrowed tasksto a phase in this project

To assign borrowed tasks to phases1 Click a task in the list on the left If a task includes subtasks click the plus icon to expand the list Click

the minus icon if you want to hide the subtasks To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more phases in the Assign tasks to phase(s) of your project list (on the right) to whichthe task belongs A checkmark appears next to tasks youve assigned

3 To assign one or more tasks to a new phase select the tasks click ltNew Phasegt in the Assign tasksto Phases of your project list and then type a name for the new phase

4 To select tasks from another project you selected as similar click the Tasks from Similar Projects listarrow click the project you want and then assign the tasks to phases

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also Edit Tasks

-o-

31

copy Experience In Software Inc 1995 - 2006

People - Step 1 of 3

Enter the names or descriptions of the people involved in your project Include key decision makers suchas executives or customers who must approve or consult with you about the project These are yourprojects resources In the next People step youll identify new tasks associated with these resources

To enter people1 Type each name or description one per line

OrIf you have stored information about people and other resources in the People Library click the PeopleLibrary button drag an entry from the library to the list and then click the OK button to close thePeople Library

2 To edit the people text double-click the name or description3 Click the Next button

Tips

Be consistent with the resource names in your projects For instance avoid using Richard in oneproject and Dick in another project when referring to the same person

Include names for people teams (such as Quality control team) departments (such as Manufacturing)companies (such as Acme Widgets Corp) or even equipment (such as wheat thrasher)

Note

Add people and other resource information to the People Library so that you can quickly drag resourcesfrom the library to any project You can even import people from your Outlook and ACT address books

See Also

Manage the People Library

Import ACT Contacts and Users to the People Library

-o-

32

copy Experience In Software Inc 1995 - 2006

People - Step 2 of 3

Now that you have defined the people needed to complete your project list any new tasks that eachresource might suggest or require

To enter new tasks for each person1 Type the new tasks associated with the person displayed in the Tasks For text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next person in your project click the Next button If you prefer to work out oforder click the Tasks For list arrow and then click the person you want

3 When you are finished entering new tasks for the last person in your project click the Next button tocontinue in the Planning Wizard

Tips

This step provides a good opportunity to get input from your resources directly and make sure theproject plan reflects the views of everyone on the team

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo Write the tasks roughly in the order that you will complete them You can reorganize the tasks later in

the Tasks step

Note

You assign people to tasks in the Assign Tasks and Schedule steps

See Also

Use a Library

Move Tasks within the Task List

Assign Tasks to People

-o-

33

copy Experience In Software Inc 1995 - 2006

People - Step 3 of 3

After you identify new tasks associated with the people in your project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by people list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

34

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 1 of 3

Every project has obstacles and risks that can affect its success List the major obstacles you face incompleting your project Then you can brainstorm any additional tasks that can help you overcome orminimize these problems

To enter obstacles1 Type each obstacle one per line

OrThe Obstacles Library contains typical sample obstacles that you can customize Drag an entry fromthe Obstacles Library to the list and then click the OK button to close the Obstacles Library

2 To insert an obstacle in the middle of the obstacles list click where you want to insert a new blank lineand then press the Insert key

3 To edit the obstacle text double-click the obstacle4 Click the Next button

Tips

Be creative when thinking of obstacles Highly imaginative obstacles can suggest realistic tasks Forexample Project manager kidnapped by aliens can lead to Project manager out of town forconference In Obstacles step 2 of 3 you can add the realistic activities as tasks You can delete theunrealistic obstacles later by returning to Obstacles step 1 of 3

Avoid listing too many obstacles even if they are realistic Hard core pessimists find it hard to getanything done

Edit and update the Obstacles Library so that you can quickly drag obstacles from the library to anyproject in your organization

See Also

Use a Library

-o-

35

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 2 of 3

After identifying the obstacles to completing your project determine how you can avoid these stumblingblocks List any new tasks you need to overcome or avoid each obstacle In this way you are developing acontingency plan for your project

To enter new tasks for each obstacle1 Type the new tasks associated with the obstacle displayed in the Obstacle text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next obstacle in your project click the Next button If you prefer to work outof order click the Obstacle list arrow and then click the obstacle you want

3 When you are finished entering new tasks for the last obstacle in your project click the Next button tocontinue in the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

You can reorganize the tasks and add notes later in the Tasks step

See Also

Use a Library

Move Tasks within the Task List

Add Task Notes and Attachments

-o-

36

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 3 of 3

After you identify new tasks for overcoming the obstacles to completing project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by obstacles list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

3 Click the Next button

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

37

copy Experience In Software Inc 1995 - 2006

Assigning People

Assign Tasks to People

After youve identified people working on your project you can assign tasks to each person or otherresource

To assign tasks to people1 Click a phase or task in the For each phase or tasks list (on the left)

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more people in the Assign some people list (on the right) who will perform the task Acheckmark appears next to tasks youve assigned

3 To assign a selected task to all of the people in your project click the All button4 To assign one or more tasks to a new person select the tasks click ltNew Persongt in the Assign

some people list and then type a name for the new person

To unassign a task

To unassign a task click the task and then click the highlighted person from which you want to removethe task You can assign that task to a different person if necessary You can also click the All buttonto remove a task from all of its assignments at the same time

Tip

Some users like to skip to the Tasks step before performing the Assign step That way they can edittheir list of tasks before assigning people and resources This helps them focus the project and givesthem a clearer idea of what must be done before committing resources

Notes

You can also assign tasks to people in the Tasks step and the Schedule step

You can assign tasks to non-personnel resources such as equipment (a CAD system or back hoe)facilities (a classroom or hotel) services (lab work or insurance) or materials (lumber or officesupplies) just as you assign tasks to people Click ltNew Persongt to add a new resource to the list

See Also

Remove People from a Task

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

38

copy Experience In Software Inc 1995 - 2006

Remove People from a Task

After assigning tasks you might need to remove people from a task or unassign them

To remove people from a task (unassigning)1 Click a phase or task in the For each phase or tasks list (on the left)

The people assigned to that phase or task are highlighted in the Assign some people list (on theright)

2 Click a highlighted person to remove or unassign that person from the taskWhen the person is no longer highlighted they are not assigned to the selected task

See Also

Assign Tasks to People

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

39

copy Experience In Software Inc 1995 - 2006

Add a New Person or Resource

If you realize that you want to assign some tasks to a person not included in the Assign some people listyou can add that person and assign tasks in the same step You can also add non-personnel resourcessuch as such as equipment (a CAD system or back hoe) facilities (a classroom or hotel) services (lab workor insurance) or materials (lumber or office supplies)

To add a new person or resource1 Select one or more phases or tasks in the For each phase or tasks list (on the left) 2 Click ltNew Persongt in the Assign some people list and then type a name for the new person or

resourceThis adds the new person or resource to the list and assigns the selected tasks to them

See Also

Assign Tasks to People

Remove People from a Task

Edit or Substitute People

Add or Change Task Assignments

-o-

40

copy Experience In Software Inc 1995 - 2006

Edit or Substitute People

If the people or resources in your project change you can replace them or edit their names anddescriptions

To edit or substitute people1 Click the People icon

You return to People step 1 of 32 In the list of people defined for the project double-click the person you want to edit or replace or click

the name and press F23 Edit the name or description of the person

When you return to the Assign step the name of the person appears as you changed it

See Also

Assign Tasks to People

Remove People from a Task

Add a New Person or Resource

Add or Change Task Assignments

-o-

41

copy Experience In Software Inc 1995 - 2006

Organizing the Project Plan

About Organizing Tasks

In the Tasks step you work with an outline of your project plan Here you can easily edit and reorganizetasks spell check and even add notes and attachmentsClick the following illustration to see tips for using this window

Edit the Task List to Consolidate and delete tasks Add subtasks Add or change task assignments Add follow-up notes to tasks Add or change attachments Review the order of the tasks in each phase and move tasks up or down so that they progress

sequentially Review task descriptions to make sure they are clear and that all the team members will understand

them Convert vague tasks such as reminders and open issues to task notes

Notes

Some users like to revise their Task List before they assign resources You can go to the Task List atany time while you are using Project KickStart

Each project created with Project KickStart can contain up to 1000 tasks

See Also

Change the Appearance of the Task List

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

Add Task Notes and Attachments

Add or Change Task Assignments

Add or Change Task Details

-o-

42

copy Experience In Software Inc 1995 - 2006

43

copy Experience In Software Inc 1995 - 2006

Change the Appearance of the Task List

You can change the appearance of the Task List so you can work with it more effectively

To add a column

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task ListBy default the Task List shows the Task Name Assignments and Notes columns You can also showCost and Done columns

To hide a column

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

To move a column

Drag a column heading to a new position in the Task List

To change the column width

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Show or Hide Tasks in the Task List

-o-

44

copy Experience In Software Inc 1995 - 2006

Show or Hide Tasks in the Task List

To hide tasks or subtasks

To hide the subtasks for a task click the minus icon next to the task

To hide all the tasks in the Task List and show only phases click all the minus icons next to thephases

To show tasks or subtasks

To show the subtasks for a task click the plus icon next to the task

To show the tasks for a phase click the plus icon next to the phase

See Also

Change the Appearance of the Task List

-o-

45

copy Experience In Software Inc 1995 - 2006

Move Tasks within the Task List

In the Tasks step you can reorganize the tasks in your project so that they better represent the work youand your team plan to do In particular you should review the order of the tasks in each phase and move tasks up and down so thattasks follow in a sequential order Use the Up and Down Arrow buttons to move the tasks

To reorder tasks1 Click a task or phase to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youmove must be next to each other

2 Click the Up Arrow button to move a task up one rowOrClick the Down Arrow button to move a task down one row

Note

When you move a bolded phase you move the phase and all of its tasks at the same time

See Also

Outdent and Indent Tasks

-o-

46

copy Experience In Software Inc 1995 - 2006

Outdent and Indent Tasks

Subtasks are smaller parts of tasks Use subtasks when you need to break tasks down into moremanageable parts In the Task List you can turn a task into a subtask by indenting it You can also add anew subtask to the Task ListIf your Task List contains subtasks you can turn a subtask into a task by outdenting itUse the Outdent and Indent buttons to promote (outdent) and demote (indent) tasks

To promote and demote tasks1 Click a phase task or subtask to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youpromote or demote must be next to each other

2 Click the Outdent button to promote the selected tasksOrClick the Indent button to demote the selected tasksYou can also right-click an item in the Task List and then click Outdent or Indent on the shortcut menu

Tips

When you promote (outdent) a task it becomes a phase and its subtasks become tasks When youpromote a subtask it becomes a task

When you demote (indent) a phase it becomes a task and its tasks become subtasks When youdemote a task it becomes a subtask

Notes

You can have up to 10 levels of subtasks in your project

Use Task Notes instead of subtasks for task comments or additions that are not actually work items

See Also

Move Tasks with the Task List

Add a Task or Subtask

-o-

47

copy Experience In Software Inc 1995 - 2006

Add a Task or Subtask

If you realize you want to add another task to the Task List use the Add Task button A subtask is a smaller part of a task Use subtasks when you need to break tasks down into moremanageable partsTo add a subtask use the Add Subtask button

To add a task1 Click a task and then click the Add Task button right-click a task and then click Add Task on the

shortcut menu or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskProject KickStart numbers the new task in the proper sequence

To add a subtask1 Click a task and then click the Add Subtask button right-click a task and then click Add Task on the

shortcut menu or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtask3 Project KickStart numbers the new subtask in the proper sequenceNote

To add a new phase click a phase and then click the Add Task button

See Also

Outdent and Indent Tasks

-o-

48

copy Experience In Software Inc 1995 - 2006

Edit Tasks

Edit tasks in the Task List to fine tune your project You can edit the names of the phases tasks andsubtasks delete tasks and cut copy and paste task information

To edit task names1 Click the phase task or subtask you want to edit and then press the F2 key2 Type to edit the text3 To undo an edit click the Undo button

To delete a task

Click the task you want to delete and then press the Delete key or click the Delete button Or

Right-click a task and then click Delete Row on the shortcut menu

To cut copy and paste tasks1 Select the tasks you want to cut or copy Use Shift-click or Ctrl-click to select more than one task

2 Click the Cut button (Ctrl-X) or click the Copy button (Ctrl-C )

3 Click where you want to insert the tasks and then click the Paste button (Ctrl-V)

Tip

If your project includes some of the same tasks repeated in different phases save time by copying rowsof tasks and pasting them to another phase

Notes

You can also edit task names using the Task Information dialog box To open this dialog boxdouble-click a task or click a task and then click the Edit Task Information button

If you delete a phase you also delete its tasks and subtasks If you delete a task you also delete itssubtasks Project KickStart warns you before deleting tasks or subtasks and gives you a chance tocancel the deletion

See Also

Add Task Notes and Attachments

Add or Change Task Assignments

-o-

49

copy Experience In Software Inc 1995 - 2006

Add Task Notes and Attachments

You might find that some of your tasks are actually more notes than tasks For example Remember tocheck Daves specifications might work better as a note than a task especially if it could take several daysto catch up with Dave but only a few minutes to review his specs By using notes you clarify your projectand increase your chances for success An attachment is a document graphic or any other type of file related to a task For example to a tasksuch as Review proposal you can attach the proposal document Or you can attach a hyperlink to a pageon a web site

To add a note or attachment to a task1 Double-click the Notes column next to the task The Task Information dialog box opens to the Notes

and Attachments tab2 In the Enter a Note box type in or edit the task note (Press Enter to insert line break)3 To attach a file click the Add Files button In the Select File to Attach dialog box navigate to the file

you want and then click the Open button The filename appears in the Add Attachments box with apaperclip icon

4 To insert a hyperlink click the Add URL button In the Insert Hyperlink dialog box type in the URL youwould like to link to The URL appears in the Add Attachments box with a paperclip icon

5 Click the OK button

To open or remove an attachment1 Open the Notes and Attachments tab in the Task Information dialog box2 To open an attachment double-click the filename in the Add Attachments box3 To delete an attachment click the attachment in the Add Attachments box and then click the Remove

button

To change a task into a task note1 Copy (Ctrl-C) the text of the task you want to change into a note2 Double-click the task to which you want to add the note3 In the Task Information dialog box click the Notes and Attachments tab and add paste the text in the

Enter a Note box Close the Task Information dialog box4 In the Task Name column delete the original task that how appears as a note for a different task

Tips

Use notes to keep track of the operational details of a project the little nagging details that are criticalto success

Although the Task List provides plenty of room for notes it is best to keep your notes concise

Some tasks might benefit from instructional notes those that explain what to do in a task or how tosuccessfully complete a task

You can also include a hyperlink in a note by typing httpxxx (where xxx is an e-mail or Web address)In Outlook Word Excel or your browser the hyperlink will be active You can click the link to godirectly to that site or to send an e-mail to that address

Note

You can also open the Notes and Attachments tab in the Task Information dialog box by clicking atask and then clicking the Edit Notes and Attachments button or by double-clicking a task to openthe Task Information dialog box and then clicking the Notes and Attachments tab

See Also

Edit Tasks

Add or Change Task Assignments

Change Task Details in the Gantt chart

50

copy Experience In Software Inc 1995 - 2006

-o-

51

copy Experience In Software Inc 1995 - 2006

Add or Change Task Assignments

The Assignments column in the Task List shows the people and other resources assigned to each task

To add or change a task assignment1 Double-click the Assignments column next to the task The Task Information dialog box opens to the

Assignments tabThe Assignments tab lists all of the people and resources in your project If this task is already assignedto people they are highlighted on the Assignments tab

2 To assign this task to another person or resource click the resource name in the Assignments list3 To remove (unassign) this task from a person or resource click a highlighted name in the Assignments

list4 To add a person and assign the task at the same time click ltNew Persongt in the Assignments list

and then enter the name of the new person5 Click the OK button

Note You can also open the Task Information dialog box by clicking a task and then clicking the Edit Task

Information button to or by double-clicking a task

-o-

52

copy Experience In Software Inc 1995 - 2006

Add or Change Task Details

Besides task names notes and assignments you can include cost and done details about tasks In theSchedule step you can also include start and finish dates and durations

To add task details

1 Click a task and then click the Edit Task Information button or double-click the task you wantThe Task Information dialog box opens

2 Enter Cost or Done informationCost Enter the cost associated with this task For example you could enter $150 as the cost for a tasknamed Purchase photo CD Done Click the list arrow to select 0 25 50 75 or 100 or enter the percentage you want such as33

3 Click the OK button

To show or hide task details

Right-click a column heading to open a shortcut menu and then click Cost or Done In the shortcutmenu a checkmark appears next to columns that are displayed in the Task List

To edit task details

Open the Task Information dialog box (click a task and then click the Edit Task Information button or double-click the task you want)

Or

Double-click the Cost or the Done entry to update these details directly in the Task List

Notes

The Cost amount appears with the currency symbol set for your system (in the Regional and LanguageOptions dialog box of the Windows Control Panel)

Project KickStart calculates the running totals for the tasks within a phase and displays this total in theCost column for the phase When you create and print Task reports the total costs for the entire projectappear at the end of the Cost column

See Also

Edit Tasks

Print Task Reports

-o-

53

copy Experience In Software Inc 1995 - 2006

Check Spelling

Spell check your tasks and notes before you print reports or export to other software

To check the spelling of tasks and notes

Click the Check Spelling button on the Project KickStart toolbarOr

Click Tools on the menu bar and then click Spelling

Notes

Spell checking updates entries on the Task List and the Gantt chart (the Schedule step) It can alsocheck the spelling of intermediate entries such as goals and tasks to accomplish goals if you spellcheck during those steps

Spell checking does not check the names of people on the People List or the contents of the PeopleLibrary

-o-

54

copy Experience In Software Inc 1995 - 2006

Scheduling Tasks in the Gantt Chart

55

copy Experience In Software Inc 1995 - 2006

Scheduling Overview

About Scheduling Tasks

In the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the other

You work with the Gantt chart using the familiar Task Data view in the left pane or the graphical Chart viewin the right pane To adjust the schedule to fit your project set the project start date in the toolbar moveand resize the taskbars in the Chart view or change the start and finish dates or durations of individualtasks in the Task Data view

Click the following illustration to see general tips for using the Gantt chart See About the Gantt Chart formore details

In the Schedule step you can

Change a start date for the project Set start and finish dates or durations for tasks Change the timescale of the schedule Change the working schedule to specify which days are nonworking days such as weekends and

holidays Fine-tune the organization of the phases tasks and subtasks Color-code tasks to identify assignments critical deadlines or other information at a glance Insert milestones to indicate events that mark a moment in time such as the approval of a design Review and edit task details including task name assignments notes and attachments Hide or show task data columns in the left pane Export project data to other software applications

Tip

56

copy Experience In Software Inc 1995 - 2006

To save time you can reuse projects such as one for a trade show and create an updated scheduleby changing the project start date in the Schedule step

See Also

About the Gantt Chart

Understand Task Data View

Understand Chart View

-o-

57

copy Experience In Software Inc 1995 - 2006

About the Gantt Chart

The Gantt chart provides two views of your project schedule The Task Data view in the left pane lists thesame task information as in the Tasks step but now includes durations and start and finish dates TheChart view in the right pane displays taskbars and symbols to represent the same information You canchange the schedule information by working directly in the Task Data view and Chart view or by using theGantt Chart toolbarClick the following illustration to see general tips for using this window

-o-

58

copy Experience In Software Inc 1995 - 2006

Autolink tasks (Pro Users)

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatProject KickStart Pro does not assume that you want to link all of the tasks in a serial manner (one after theother) when you get to the Gantt chart Indeed many users want that behavior and many do notTo accomodate both types of users you can set whether you want the program to Autolink tasks In theTools menu select Autolink tasks Thereafter in all your projects when you get to the Gantt chart for thefirst time the tasks will be linked in a serial mannor

-o-

59

copy Experience In Software Inc 1995 - 2006

About Linking Tasks

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatWhen you link tasks the Gantt chart shows additional information about the tasks Click the followingillustration to see general tips for using linked tasks

Task Data view Chart view Description

Predecessor tasksA predecessor task is onethat you must completebefore you can start thenext task For exampleTask 2 - Prepare soil isthe predecessor to Task3 - Plant shrubs becauseyou need to prepare thesoil before you can plantthe shrubs

Successor tasksWhen you finish onelinked task you can moveonto the next onemdashthesuccessor task Forexample the successorfor Task 2 ndash Prepare soilis Task 3 ndash Plant shrubsand the successor forTask 3 is Task 4 ndash MulchLink linesThe first task isscheduled for one dayand the second one forthe next day In additionthe link line and arrowshow that the first taskmust end before thesecond one can start

These linked tasks arescheduled for the sametime

60

copy Experience In Software Inc 1995 - 2006

These tasks which aredependent on earliertasks and the last twotasks are also scheduledfor the same time

See Also

About the Gantt Chart

Autolink tasks

Make tasks overlap

-o-

-o-

61

copy Experience In Software Inc 1995 - 2006

Change the Display of the Schedule

You can change the onscreen appearance of the schedule so you can work with it more effectively Thefollowing illustration shows the Schedule window with the Steps bar closed and only the task number taskname and duration displayed in the Task Data view This provides more room to display the Gantt chart

To show or hide the Step bar or Project KickStart toolbar

Click View on the menu bar and then click Steps Bar to show or hide the vertical Steps bar on the leftof the Project KickStart window

Click View on the menu bar and then click Tool Bar to show or hide the Project KickStart toolbarwhich appears just below the menu bar In the View menu a checkmark appears next to the items displayed in the Project KickStart window

To display more or less of the Task Data view or Chart view

Drag the splitter bar between the Task Data view and the Chart view

To change the timescale in the chart

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years

To add a column to the Task Data view

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task Data viewBy default the Task Data view shows the Info Task Name Days Start and Finish columns Youcan also show Done Cost and Assignments columns

To hide a column in the Task Data view

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

62

copy Experience In Software Inc 1995 - 2006

To change the column width in the Task Data view

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Understand Task Data View

Understand Chart View

-o-

63

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

-o-

64

copy Experience In Software Inc 1995 - 2006

65

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Some features in this topic are available only in Project KickStart Professional

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view In Project KickStart Professional you also use the Gantt chart toolbar to linkand unlink tasks

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysLink Tasks (Pro Users)Link the selected tasksUnlink Tasks (Pro Users)Unlink the selected tasksChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

See Also

Use the Gantt Chart Toolbar

-o-

66

copy Experience In Software Inc 1995 - 2006

Understand Task Data View

The following illustration shows all the columns of information you can display in Task Data view

The Task data columns are the same as in the Tasks step but also include date information

Row number

Info Shows an icon if a note attachment or both are associated with the task Double-click anicon to view or edit the associated information

Task Name Name of the phases tasks and subtasks Double-click a task name to edit it directly

Days The amount of time it takes to complete the task If you change the number of days for a taskProject KickStart changes the Finish date accordingly

Start Date this task starts Double-click a Start date and then click the list arrow to open a calendar andselect a different date This also changes the Finish date

Finish Date this task ends Double-click a Finish date and then click the list arrow to open a calendar andselect a different date This changes the task duration shown in the Days column

Done Percentage of the phase task or subtask completed Show progress for any task by entering apercent of up to 100

$ Cost Cost for each task summed in the appropriate phase row Reports include total costs for theproject when you select the Cost column in the Create and Print Task Reports dialog box or the Createand Print Gantt Chart Report dialog box The Cost appears with the currency symbol set for your system(in the Regional and Language Options dialog box of the Windows Control Panel)

Assignments People and other resources assigned to the task Double-click an assignment to open theTask Information dialog box to the Assignments tab where you can add and change assignments

Tip

A task with a duration of zero (0) days is a milestone See Create a Milestone for more information

Notes

By default Task Data view displays all the columns the Info Task Name Days Start and Finish Done Cost and Assignments columns Some of these columns might be hidden by the Gantt chartview To hide columns right-click a column heading to open a shortcut menu and then click the columnyou want to hide In the shortcut menu no checkmark appears next to columns that are hidden

To change the width of a column drag a splitter bar in the column heading row or double-click a splitterbar to have the column accommodate its longest entry

As in the Tasks step expand phases and tasks by clicking the plus icon and collapse phases andtasks by clicking the minus icon

See Also

67

copy Experience In Software Inc 1995 - 2006

Understand Chart View

Change Task Dates

-o-

68

copy Experience In Software Inc 1995 - 2006

Additional Features in Task Data View

These features are available only in Project KickStart Professional

In Project KickStart Pro you can view two columns of information in addition to the nine columns availablein the Project KickStart Standard These two additional columns are labeled Pred (for Predecessor) andSucc (for Successor) The following illustration shows a typical Task Data view with these additionalcolumns

Besides the nine columns of information shown in Task Data view in Project KickStart Standard you canalso show the following information in the Professional version

Pred Indicates which task is the predecessor to the current task Double-click a task number in the Predcolumn to change it

Succ Indicates which task is the successor to the current task Double-click a task number in the Succcolumn to change it

Notes

When you link tasks Project KickStart assigns predecessors and successors according to their order inthe Task Data view

When you move a linked task in the Task Data view the predecessor and successor do not changeFor example in the above illustration if you move Task 3 ndash Plan design so it becomes Task 2 itspredecessor remains Land survey and its successor remains Engineering You can change these bydouble-clicking the task number in the Pred or Succ column and then entering a new number

See Also

Understand Task Data View

-o-

69

copy Experience In Software Inc 1995 - 2006

Understand Chart View

The following illustration shows a daily schedule in Chart view Point to the illustration to display text thatdefines the chart elements

Summary bar Summarizes the tasks below it and extends from the earliest start date(where the first triangle in the summary bar appears) to the latest finish date (where the last triangleappears) If a phase has tasks the summary bar appears in the phase row to summarize the tasks If atask has subtasks the summary bar appears in the task row to summarize the subtasks

To reschedule a phase and all of its tasks (or a task and all of its subtasks) click the summary bar and dragit to the left or right until it spans your desired set of dates This changes the earliest start date and latestfinish date in that phase and keeps the same duration And all the tasks move with the change of thephase

Taskbar Shows the length and scheduled dates for a task To change the duration of a taskresize the taskbar click the taskbar and then drag its left edge to schedule a different start date or drag itsright edge to schedule a different finish date

To reschedule a task without changing the duration drag the taskbar to a different date in the chart

Taskbar with percent done If you enter a Done amount in the Task Data view a progress barin the taskbar indicates the amount of the task completed

Red vertical line Indicates todays date

Milestone Indicates a task with a zero duration Milestones mark an event that must be reflected inyour project plan such as the approval of a design or an assembly line startup You can drag the left edgeof a milestone icon to stretch it into a taskbar The milestone becomes a task with a start and finish date

Notes

Because a summary bar summarizes the tasks below it you cannot resize a summary bar

To scroll the schedule use the vertical and horizontal scroll bars or the green drag bar at the top of theChart view

The shaded days in the Chart view indicate nonworking days To set which days are working andnonworking see Specify Working Days

70

copy Experience In Software Inc 1995 - 2006

-o-

71

copy Experience In Software Inc 1995 - 2006

Additional Tools in Chart View

These features are available only in Project KickStart Professional

If you use Project KickStart Pro the Chart view displays lines and arrows to show linked tasks The linklines and arrows show the relationships dependencies between one linked task and another

Besides the summary bar taskbar and other information provided in Project KickStart Standard Chart viewin the Professional version also provides the following information

The first task is scheduled for one day and the second one for the next day In addition the link line andarrow show that the first task must end before the second one can start

These linked tasks are scheduled for the same time However the first task must end before the secondone can start

The first two tasks are scheduled for the same time and must be completed before the third task can start

These linked tasks are scheduled for the same time However the second task must end before the firstone can start

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

Understand Chart View

-o-

72

copy Experience In Software Inc 1995 - 2006

73

copy Experience In Software Inc 1995 - 2006

Change Task Dates

You can revise a project schedule by changing task dates in the Task Data view or the Chart view You canalso reschedule an entire project by changing the projects start date

To change the project start date1 Click the Project Start list arrow to open a calendar

The calendar highlights the selected date and outlines todays date2 Find the date you want using the left and right scroll arrows to view a different month and then click the

date

To change task dates in Task Data view1 Double-click the Start or Finish date for a task

2 Then edit the date (you can edit the day month or year) OrClick the list arrow to open a calendarThe calendar highlights the selected date and outlines todays date

3 Find the date you want using the left and right scroll arrows to view a different month and then click thedateProject KickStart changes the Start and Finish dates according to your selection updates the durationof the task in the Days column and adjusts the taskbar in the Chart view

To change task dates by changing the duration in Task Data view

Double-click the Days column for a task and then enter the number of days it will take to complete thetaskProject KickStart changes the Finish date of the task and adjusts the taskbar in the Chart view

To change task dates in Chart view

Resize a taskbar click the taskbar and then drag its left edge to schedule a different start date or dragits right edge to schedule a different finish dateProject KickStart updates the summary bar in Chart view and the task dates and duration in the TaskData view

To reschedule a task without changing the duration drag the taskbar to a different date You can alsodrag a summary bar to reschedule a phase and all of its tasks (or a task and all of its subtasks) so itspans a different set of datesProject KickStart updates the task dates and duration as necessary in the Task Data view

To change task dates in the Task Information dialog box1 Open the Task Information dialog box (Right-click a task and then click Task Information or click a

task and then click the Edit Task Information button )2 Click the General tab3 In the Dates section change the following information as necessary

Start Click the Start list arrow to open a calendar and then click the appropriate start dateFinish Click the Finish list arrow to open a calendar and then click the appropriate finish dateDays Enter a number or click the spin arrows to set the task durationMilestone Select the Milestone check box if you want this task to be a milestone (A milestone is atask with a zero duration and marks an event such as the approval of a design)

Notes

You cannot delete the Start or Finish date of a task If you want to specify that a task has no durationconvert it to a milestone

When working with a calendar to schedule a start or finish date click the Today date text (where date

74

copy Experience In Software Inc 1995 - 2006

is todays date) to select todays date

See Also

Understand Task Data View

Understand Chart View

Create a Milestone

-o-

75

copy Experience In Software Inc 1995 - 2006

Phase Dates Cannot Be Edited

You cannot change the bold phase dates in the Task Data view of the Gantt chart They are a summary ofthe task dates for a particular phase and are view only You can revise phase dates by changing task dateswithin the phase

To change phase dates in Chart view

You cannot directly resize a summary bar You can extend or move the blue task barswithin a phase on the chart and Project KickStart updates the summary bar

To reschedule a phase on the chart drag the summary bar to a new date and all of its tasks (or a taskand all of its subtasks) will move with it

-o-

76

copy Experience In Software Inc 1995 - 2006

Quick Tour of Working with Linked Tasks

This feature is available only in Project KickStart ProfessionalIn the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the otherIn addition Project KickStart Pro links the tasks for you so when you open the Gantt chart you see a linkedwaterfall similar to the one shown below Besides providing a schedule that starts in a cascade with eachtask lasting one day each task is linked to the next task

You work with the Gantt chart either using the Task Data view in the left pane or the graphical Chart view inthe right pane To adjust the schedule to fit your project set the project start date in the toolbar move andresize the taskbars in the Chart view or change the start and finish dates or durations of individual tasks inthe Task Data view See About Scheduling Tasks for detailsNext fine-tune the dependencies in your project by you can linking and unlinking tasks changing theirpredecessors and successors and setting lead times For example if one task is not dependent onanother you can unlink the tasks If another task canrsquot start until two other tasks are finished you can add apredecessor to that task in which case the two tasks will be linked

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

To fine-tune the linked tasks To change the scheduled start and end dates of linked tasks move and resize taskbars in the Chart

view or change the number of days or the Start date in the Task Data view To display predecessor and successor information in the Task Data view right-click any column

heading and then click Pred or Succ To change the predecessor for a task double-click the number in the Pred column for the task and

then enter the number of a different task To change the successor for a task double-click the number in the Succ column for the task and then

77

copy Experience In Software Inc 1995 - 2006

enter the number of a different task To add another predecessor or successor to a task click in the appropriate column for the task and

then enter the number of another task To change the details of a linked task open its Task Information dialog box To do so right-click the

task and then click Task Information on the shortcut menu or click a task and then click the Edit TaskInformation button See Change Details for Linked Tasks

In the Task Information dialog you can also specify the predecessor(s) of a task and lead time(s) of thetasks

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

About Scheduling Tasks

About Linking Tasks (Pro Users)

Use the Gantt Chart Toolbar (Pro Users)

Manage Changes in Your Schedule (Pro Users)

-o-

-o-

78

copy Experience In Software Inc 1995 - 2006

Link and Unlink Tasks

These features are available only in Project KickStart Professional

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

See Also

About Linking Tasks

Quick Tour of Working with Linked Tasks

-o-

79

copy Experience In Software Inc 1995 - 2006

Create a Milestone

A milestone Indicates a task with a zero duration Milestones mark an event that must be reflected in yourproject plan such as the approval of a design or an assembly line startup

To create a milestone in the Task Data view

Double-click the Days number for a task and then enter 0 (zero)Or

Open the Task Information dialog box click the General tab and then click to insert a checkmark inthe Milestone check box

In the Chart view Project KickStart changes the taskbar to a milestone icon To create a milestone in Chart view

Click a taskbar and then drag to shrink the taskbar to a milestone icon In the Task Data view Project KickStart changes the Days for this task to 0 (zero)

Notes

To change a milestone into a task you change its duration or start and finish dates See Change TaskDates for instructions

To move a milestone in Chart view click the milestone icon on the upper left corner of the milestoneicon With the left mouse down move the icon to another date and release the mouse

To move a milestone in the Task Data view change the start date or the finish date and the milestonewill move

-o-

80

copy Experience In Software Inc 1995 - 2006

Change Task Details

You can use the Task Information dialog box to change the following task details in Task Data view

Task properties including the task name cost for completing the task and the percent completed

Dates including the start and finish dates duration and whether to convert the task to a milestone

Assignments

Notes and attachmentsYou can also edit the task name days dates costs and Done directly by clicking items in the task datacolumns

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button 2 Click the appropriate tab and then change the task details

General tab Change the task name and enter or change the cost associated with the task To changethe amount of the task completed click the Done list arrow and then select a value or type a value inthe Done text box Enter or change date information as described in Change Task Dates Assignments tab People assigned to this task are highlighted in the list To assign this task to anotherperson or resource click the name in the Assignments list To remove (unassign) this task from aperson or resource click a highlighted name in the Assignments list See Add or Change TaskAssignments for more detailsNotes and Attachments tab Type or edit a task note (Press Enter for a line break) To add anattachment click the Add button In the Select File to Attach dialog box navigate to the file you wantand then click the Open button The filename appears with a paper clip icon See Add Task Notes andAttachments for more details

To change task details directly in Task Data view

To modify the task name press F2 or double-click a task and then edit or replace the text

To change date information see Change Task Dates

To change the amount of the task completed double-click in the Done column and then enter a newvalue

To change the cost associated with the task double-click in the Cost column and then enter a newvalue

Notes

When you enter costs for tasks the total appears in the phase row for those tasks Reports include thetotal costs of all tasks in the project when you select the Cost column in the Create and Print TaskReports dialog box or the Create and Print Gantt Chart Report dialog box

You cannot change the cost of a phase because it represents the total costs for the tasks in that phaseInstead change the costs associated with the tasks in the phase

When you enter a Done for a task the corresponding taskbar in the Chart view includes a blackprogress bar

-o-

81

copy Experience In Software Inc 1995 - 2006

Change Details for Linked Tasks

This feature is available only in Project KickStart ProfessionalIf you are using Project KickStart Pro you can use the Task Information dialog box to change the followingtask details

Predecessor for a linked task

Lead time for a linked task

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button

2 Click the Predecessors tab and then change the task details about predecessors and lead timePredecessors tab The Task Properties section shows the name of the selected task which you canchange The Predecessor (Finish-to-Start) section shows the tasks that are predecessors to theselected task A predecessor task must be finished before you start the current task You can change the ID name or lead time of the predecessor task Also you can also add additionalother predecessorsThe lead time is the amount of time you need to wait after finishing the predecessor task before so youcan start the current task Lead time can be positive or negative

Note

In some programs the is time shift is called ldquolag timerdquo But we think that the term ldquolead timerdquo is moreaccurate and descriptive since itrsquos the amount of time you want to allow before you start a task

See Also

Change Task Details

82

copy Experience In Software Inc 1995 - 2006

-o-

-o-

83

copy Experience In Software Inc 1995 - 2006

Reorganize Tasks in Task Data View

Although your project should be fairly well organized by the time you start the Schedule step you canfine-tune the organization in the Task Data view using the same techniques you use in the Tasks stepTo reorder tasks

Right-click a task and then click Move Task Up or Move Task Down on the shortcut menu Or

Click a task or phase to select it and then click the Up Arrow button or the Down Arrow button on theGantt chart toolbar

To promote and demote tasks

Right-click a task and then click Outdent or Indent on the shortcut menu Or

Click a phase task or subtask to select it and then click the Outdent button or the Indent button onthe Gantt chart toolbar

To add a task1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Task button on the Gantt chart toolbar or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskTo add a subtask1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Subtask button on the Gantt chart toolbar or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtaskTo delete a task

Right-click a task and then click Delete Row on the shortcut menuOr

Click the task you want to delete and then click the Delete button

To delete a row click the Task row number and press the Delete button

See Also

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

-o-

84

copy Experience In Software Inc 1995 - 2006

Change the Timescale of the Schedule

You can display the Gantt chart schedule in the Chart view using days weeks months quarters or yearsas the timescale Changing from days to weeks for example displays a longer period of time but lessdetail

Days timescale Weeks timescale

To change the timescale in the Chart view

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years Youcan also change the timescale by clicking Timescale on the menu bar and then clicking the option youwant

Notes

When you print a Gantt chart your current timescale is used by default However you can change it inthe Print Options dialog For example even though you were viewing your Gantt chart by weeks youcan choose to print the Gantt chart by months

If your mouse comes with a wheel you can adjust Project KickStarts timescale by rolling the wheelforward or backward The Timescale list box must be selected first

-o-

85

copy Experience In Software Inc 1995 - 2006

Specify Working Days

You can select which days are working days and which days are nonworking days for scheduling purposesBy default Monday - Friday are working days and Saturday and Sunday are nonworking days You can addto and change these settings to specify holidays for example

To set working and nonworking days

1 Click the Change Working Schedule button on the Gantt chart toolbar The Change Working Schedule for this Project dialog box opens Nonworking days are shaded in grayWorking days are unshaded

2 To change a single date (from working to nonworking or from nonworking to working) click the date3 To change one day of the week for the entire project such as all Fridays double-click any Friday4 To display schedules for other months click the left and right arrows5 Click OK

Note

Project KickStart maintains separate calendars for each project

If you typically work weekends create a simple template with weekends displayed as Working daysSave as your starter template Use the starter template when you start a new project and then save theproject with a different name Weekends will be displayed as Working days in your projects

-o-

86

copy Experience In Software Inc 1995 - 2006

Change the Color of Taskbars

You can change the color of the taskbars in the Chart view to call attention to particular tasks For exampleyou can change the colors of all tasks in a particular phase resource or deadline to make them stand outin a report

To change the color of a taskbar1 Right-click a taskbar and then click Color on the shortcut menu or click a taskbar and then click the

Color button on the Gantt chart toolbar The Color dialog box opens

2 Click the color you want to assign to the taskbarTips

Avoid changing the taskbar color to black because it obscures the Done progress bar (The Doneprogress bar is a black bar displayed within a taskbar)

Also avoid changing the taskbar color to white because it will not appear in the white rows of the Chartview

-o-

87

copy Experience In Software Inc 1995 - 2006

Make Tasks Overlap

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro the schedule starts in a cascade with each task lasting one day and each tasklinked to the following taskHowever it is very unlikely that your entire schedule matches such a cascade so you can adjust theschedule Start by estimating the duration of tasksmdashthe number of days that each task will take Generallyit is best to estimate how many days will elapse before the task is done You might also want some tasks to occur at the same time To do so you can overlap the tasks To make tasks overlap like this

You can do this in three ways Set the same predecessor for both tasks

Or Set the second task as the successor of the first task and then then move the second task into a

position when it starts on the same day as the first taskOr

Set the second task as the successor of the first task and then assign a lead time of ndash3 days (the number of days scheduled for the task)

To make tasks overlap like this

Set the second task as the predecessor of the first task and then assign a lead time of ndash2 days(one less than the number of days scheduled for the task)

-o-

88

copy Experience In Software Inc 1995 - 2006

Manage Changes in Your Schedule

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro when you schedule with dependencies you can adapt to changes on the fly andcreate what-if scenarios to forecast how one change affects the overall project schedule A commonscenario is dealing with delays You can reschedule an entire project or only selected tasks When you doProject KickStart Pro updates the schedule for you

To delay an entire project Click in the Project Start text box and then edit the date to match your new start date (You can edit

the day month or year)Or

1 Click the Project Start list arrow to display the calendar The calendar highlights the selected date andoutlines todays date

2 Find the date you want using the left and right scroll arrows to view a different month and then click thedate Project KickStart changes the Start and Finish dates for all tasks according to your selection

To delay a task In Task Data view double-click the Days column for the task and then edit the number of days it will

take to complete the taskProject KickStart changes the Finish date of the task adjusts the taskbar in the Chart view andchanges the Start and Finish dates for all tasks linked to this taskOr

In Chart view resize a taskbar by clicking the taskbar and then dragging its left edge to schedule adifferent start date or dragging its right edge to schedule a different finish date Project KickStart updates the summary bar in Chart view the task dates and duration in the Task Dataview and reschedules all tasks linked to this task

To reschedule a task without changing the duration in Chart view drag the taskbar to a different date Project KickStart updates the task dates and duration as necessary in the Task Data view andreschedules all tasks linked to this task

Note

Project KickStart Pro does not include a critical path

-o-

89

copy Experience In Software Inc 1995 - 2006

Managing Libraries

Use a Library

Project KickStart has five libraries that contain lists of useful phases tasks goals people and obstaclesAll libraries expect the People Library contain sample entries that you can use in your projects Yougenerally build your own People Library from the resources that are available to you

To use a library1 In the Phases Tasks Goals People or Obstacles step of the Planning Wizard click the Library button

to open the appropriate library2 Select one or more items in a library and then drag them to your list3 Close the Library window

Tips

Feel free to add (or delete) items to the libraries to make them richer and more pertinent to yourprojects

Keeping libraries small makes them easier to use

Widen the library window to see the full text of long entries

Note

After adding a library entry to a list you can double-click the entry to edit it

See Also

Manage a Library

-o-

90

copy Experience In Software Inc 1995 - 2006

Manage a Library

Customize the libraries by adding and changing entries and reorganizing them so you can use the librariesefficiently The Phases Tasks Goals People and Obstacles Libraries include a single column ofinformation while the People Library provides additional columns (See Manage the People Library)

To edit a library1 Open the library by clicking the appropriate Library button2 To edit an entry double-click it

3 To add an entry to the library press Insert or click the Add a row button You can also select oneor more items in the list and then drag them to the library

4 To delete an entry select the entry and then press Delete or click the Delete a row button 5 To move an item up or down select the item and then click the Up Arrow or the Down Arrow button

6 Click the OK button to save your changes and close the Library windowTips

Widen the Library window to add a long entry

Libraries can serve as ldquoKnowledge Librariesrdquo By including typical company-specific terms in yourLibraries you create a quick reference for yourself and colleagues now and in the future To do so adda new line in the Library enter the name of your company (or department) as a heading in capitalletters and then list your personal terms under the heading

If you use Project KickStart on more than one computer such as at home and work you can transportchanges you make in your Libraries from one computer to another The data in all the Libraries isstored in one file pks5libxdat so you can copy that file on one computer and paste it into the ProjectKickStart 5 folder on the other computer

Keeping Libraries small makes them easier to use Project KickStarts Libraries are fairly rich out of thebox If some of the terms don rsquot apply to your type projects delete them

See Also

Manage the People Library

-o-

91

copy Experience In Software Inc 1995 - 2006

Manage the People Library

The People Library is like the other libraries but with a few important extra features

You can store contact data such as Company Email Phone and Job Title

You can import names from ACT or from Outlook if you use either of those programsTo use the People Library1 In the People step of the Planning Wizard click the People Library button2 Select one or more names in the People Library and then drag them to your list (This adds only the

names of people not their contact data) If the People Library contains company names but not contactnames you can drag the company name to your list

3 Close the Library windowTo organize the People Library

To show or hide a column right-click a column heading to open a shortcut menu and then click acolumn name In the shortcut menu a checkmark appears next to columns that are displayed in thePeople Library

To sort the people in the People Library click a column heading For example click the Name columnheading to sort the people alphabetically by name To reverse the sort click the column heading again

To move a person up or down select the person and then click the Up Arrow or the Down Arrowbutton

Click the OK button to save your changes and close the People LibraryTo edit the People Library

To edit a persons name and contact data double-click the entry

To add a person to the People Library click the first blank row press Insert or click the Add a rowbutton Then type to enter the persons name and contact information You can also select one ormore items in the list and then drag them to the People Library

To delete an entry select the entry and then press Delete or click the Delete a row button

Click the OK button to save your changes and close the People LibraryTips

Use the People Library to store names for people teams (such as Quality control team) departments(such as Manufacturing) companies (such as Acme Widgets Corp) or even equipment (such as wheatthrasher)

Widen the People Library window to add a long entry

Resize the columns by dragging or double-clicking a splitter barNotes

After adding a person or resource to your list you can double-click the name to edit it

You can import contact information stored in an Outlook or ACT (version 6 7 or later) address book toyour People Library

See Also

Import ACT Contacts and Users to the People Library

Import Outlook Contacts to the People Library

-o-

92

copy Experience In Software Inc 1995 - 2006

Import ACT Contacts and Users to the People Library

If you use ACT 7 or later (200520062007) or if you use ACT 6 you can import contacts and users to thePeople Library This speeds up your work by letting you use ACT information in your Project KickStartplans If you export a plan to ACT 7 or later it recognizes the people and other resources you entered inProject KickStart

To import ACT contacts and users1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click ACT 7 or later or ACT 6 Click the Import button3 Click the Select ACT Database button and select the ACT 7 or later database (pad) containing the

people information you want to import The ACT 7 and later databases are usually stored in MyDocumentsACTACT for Win 7Databases (If you use ACT 6 your data is stored in a dbf database) If you select a multi-user ACT database you must enter your user name and password for the ACTdatabase

4 In the Import to People Library dialog box the names of Contacts and Users are listed on the left Clickthe Users tab select one or more users and then click Add to move the user names to the Import listClick the Contacts tab to select contact names the same way Click the Add All button to select allusers or contacts for import Note You can sort the contacts alphabetically by name or by company name by clicking theappropriate column heading

5 Click the Import button to add the names and related information from the selected ACT database tothe People Library

Notes

Importing contacts and users to the People Library does not remove them from the ACT database

If you try to import the same ACT contact or user twice it appears only once in the People Library

-o-

93

copy Experience In Software Inc 1995 - 2006

94

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts to the People Library

If you use Microsoft Outlook to maintain your contacts you can import selected contacts to the PeopleLibrary ThisThis speeds up your work by letting you use Outlook information in your Project KickStartplans If you export a plan to Outlook it recognizes the people and other resources you entered in ProjectKickStart

To import Outlook contacts1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click Outlook Click the Import buttonA dialog box opens informing you that Project KickStart is trying to access your Outlook data

3 Allow access for 1 minute and then click the Yes button4 If Outlook asks you to choose your profile please do so5 The Import to People Library dialog box opens listing Outlook Contacts on the left Select one or more

contacts and then click Add to move the contact names to the Import list Click the Add All button toselect all contacts for import

6 Click the Import button to add the contact names to the People Library

Notes

Importing contacts and users to the People Library does not remove them from Outlook If you try to import the same Outlook contact twice it appears only once in the People Library

95

copy Experience In Software Inc 1995 - 2006

You can import Contacts from the Outlook Business Contact Manager

See Also

Import Outlook Contacts via CSV to the People Library (Pro Users)

-o-

96

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts via CSV to the People Library (ProUsers)

This feature is available only in Project KickStart Professional

If you use Microsoft Outlook to maintain your contacts and many of the people on your project are not inyour personal contacts folder in Outlook you can use our new utility to import these Outlook contacts viaCSV to the People Library

To export Outlook contacts to a CSV file1 In Outlook - Click File Import and Export Export to A File and click Next2 Select Comma Separated Values (Windows) and click Next3 Select the Contacts folder to export and click Next4 Save Exported File As with the default being your My Documents folder5 Click Next

To import Outlook contacts to the People Library

1 Be sure that you exit Project KickStart before running the Import Utility

2 Run ImportCSVToPKSexe which is located in the Project KickStart application folder

3 Browse or type the Contacts CSV file (the path is My DocumentsProject KickStart Projects folder bydefault)

4 Browse or type the pks5libxdat file (default is the Project KickStart application folder)

5 Click on Import

Note

Importing contacts and users to the People Library does not remove them from Outlook

-o-

97

copy Experience In Software Inc 1995 - 2006

Printing Reports

98

copy Experience In Software Inc 1995 - 2006

Printing Dashboards

Print Reports

You can print reports from anywhere in Project KickStart through a new Reports Step

You will see Reports divided into three areas

Dashboard

Task Reports

Gantt Chart Reports

-o-

99

copy Experience In Software Inc 1995 - 2006

Print Dashboard Reports

You can print dashboard reports from anywhere in Project KickStart though it makes the most sense toprint them after you have developed your tasks and arranged them in a sensible order

To print a dashboard report

1 Click File on the menu bar and then click Print Reports and then click Dashboard Reports or clickthe Print Reports button

2 In the left column select one of these dashboard reports Whats Due Today Whats Due NextWeek Whats Due Next Month

3 Change the page setup as necessary or Save As a file (See Page Setup and Save As)

4 Click the Print button

Tip

You can see the number of tasks in each dashboard report from the dashboard menu

-o-

100

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Dashboard Reports

Printer Setup

-o-

101

copy Experience In Software Inc 1995 - 2006

Save as HTML or RTF

You can dashboard reports to a Hypertext Markup Language (HTML) format for viewing with an Internetbrowser such as Microsoft Internet Explorer or Mozilla FireFox or to an RTF format for viewing in MicrosoftWord

To save a dashboard report as an HTML file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save button

To save a report as an RTF file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

102

copy Experience In Software Inc 1995 - 2006

Printing Task Reports

Print Task Reports

You can print task reports from anywhere in Project KickStart though it makes the most sense to print themafter you have developed your tasks and arranged them in a sensible orderBefore you print task reports you might want to widen the Task Name column in the Task List to make sureyou print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a task report

1 Click File on the menu bar and then click Print Task Reports In the Tasks step you can click thePrint Reports button instead

The Create and Print Task Reports dialog box opens

2 Click the list arrow and then click Task Report Individual Assignments or Phases Goals People ampObstacles

3 Select the information you want to include in the report as described below

4 Preview the report and change the page setup as necessary (See Print Preview and Page Setup)

5 Click the Print button

Task Report

The Task report covers the entire project and includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

103

copy Experience In Software Inc 1995 - 2006

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to display in the report

By default the report prints all tasks Click the Incomplete Tasks or Completed Tasks option button tofocus on one type of task

4 Click the Preview button (See Print Preview for details)

Individual Assignments

The Individual Assignments report covers the entire project and lists the tasks assigned to each resourceThe report includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to include in the report

Click the All Tasks Incomplete Tasks or Completed Tasks option button

4 Choose which people to include The report lists tasks assigned to the people you select

Click to insert or remove a checkmark from the box for each person

5 Click the Preview button (See Print Preview for details)

Phases Goals People amp Obstacles

This report includes the phases goals people and obstacles in your project You can include some or all ofthese items in the report

104

copy Experience In Software Inc 1995 - 2006

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Click the Preview button (See Print Preview for details)

Tip

If you have many long notes for the tasks of your project it may be hard to read them if you select everycolumn in the Task Reports You should consider selecting a report with only columns for Tasks andNotes

See Also

Print Gantt Chart Reports

-o-

105

copy Experience In Software Inc 1995 - 2006

Print Preview

Before printing a report preview its pages so you know how the report will look when printed

To preview a task report1 Click the Preview button on the Create and Print Task Reports dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from 79 to 100 or from 100 to 79Zoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25

viewPrint the report

You can also click the Page Setup button to change margins and other settings or click the Closebutton to close the Print Preview window

2 If the report appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintTask Reports dialog box

Note

Print Preview is for viewing only--you cannot edit the contents of a report

See Also

Print Task Reports

Printer Setup

Page Setup

-o-

106

copy Experience In Software Inc 1995 - 2006

Printer Setup

Before you print a report you can change the following printer settings

Printer name (and other properties) Paper size Number of copies

To change the printer setup1 Click the Printer button on the Project KickStart toolbar or the Print Preview toolbar2 In the Print dialog box change the printer settings

See Also

Print Task Reports

Print Preview

Page Setup

-o-

107

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Task Reports

Print Preview

Printer Setup

-o-

108

copy Experience In Software Inc 1995 - 2006

Email Task Reports

After creating and previewing a task report you can distribute it to others via email

To email a task report1 In the Create and Print Task Reports dialog box select a report and then click the Email Report

button Project KickStart creates the report opens a new message in your email software and attaches thereport as an HTML file to the message

2 Insert one or more email addresses include the message text and then send the message the way youusually do

Tip

To send a task report to each person in your project with the appropriate assignments select theIndividual assignments report select one person to receive the report and then click the Email Reportbutton Enter the email address of the recipient and send the message Do this for each person in yourproject

-o-

109

copy Experience In Software Inc 1995 - 2006

Save as HTML

You can export tasks assignments days and notes to a Hypertext Markup Language (HTML) format forviewing with an Internet browser such as Microsoft Internet Explorer or Mozilla FireFox

To save a report as an HTML file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

110

copy Experience In Software Inc 1995 - 2006

Save as RTF

You can export tasks assignments durations and notes to a Rich Text Format (RTF) for editing inMicrosoft Word

To save a report as an RTF file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can open an RTF file in a word processor such as Microsoft Word

To send an RTF document to each person in your project with the appropriate assignments select theIndividual Assignments report select one person to receive the report and then save the report asRTF Do this for each person in your project

See Also

Save as HTML

-o-

111

copy Experience In Software Inc 1995 - 2006

Printing Gantt Chart Reports

Print a Gantt Chart

Once you create your schedule you can print a Gantt chart from anywhere in Project KickStart

Before you print a Gantt chart you might want to widen the Task Name column in the Task pane to makesure you print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a Gantt chart1 Click File on the menu bar and then click Reports and then select Gantt Chart Reports In the

Schedule step you can click the Print Reports button insteadThe Create and Print Gantt Chart Report dialog box opens

2 Click the Format list arrow and then click Wall chart Fit to smallest size or Repeat tasks on everypage (for handouts)

3 Select the information you want to include in the report as described below4 Preview the report and change the page setup as necessary (See Print Preview a Gantt Chart and

Page Setup)5 Click the Print button

Wall Chart The wall chart prints the Gantt chart information spread across many pages which you can tape together tocreate a wall chart On the left side of the report the wall chart includes the task data columns you selectThe right side of the report includes the graphical view shown in the Gantt chart pane on the right

1 Select the task data columns you want to display for the task information on the left side of the wallchartClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the wall chart

112

copy Experience In Software Inc 1995 - 2006

By default the wall chart prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the wall chartBy default the wall chart prints the timescale you were using in the Gantt chart Click the SetTimescale list arrow to change the timescale to Weeks Months Quarters or Years

4 Select the orientation for the wall chartClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Fit to Smallest Size When you select the Fit to smallest size format Project KickStart reduces the size of the entire Gantt chartincluding the information in the Task pane on the left and the graphical view shown in the Gantt chart paneon the right so it fits as well as possible in the smallest number of pages

1 Select the data columns you want to display for the task information on the left side of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 The timescale for the Gantt chart view on the right side of the report is determined by the length of yourproject and may not be changed

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 The number of pages of the report is shown here (The Fit to smallest scale report will print up to 78rows of tasks per page)

6 Click the Preview button (See Print Preview a Gantt Chart for details)

Standard (for Handouts) This report lists the data columns you specify on the left side of the first page and can repeat the tasknumber task name or assignments on every interior page of the report which is especially useful for

113

copy Experience In Software Inc 1995 - 2006

handouts

1 Select the data columns you want to print on the left side of the first page and the data columns youwant to print on every page of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the reportBy default the report prints a daily view of the tasks Click the Set Timescale list arrow to change thetimescale to Weeks Months Quarters or Years

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Tips

Print Preview shows how many pages the Gantt chart will take to print If there are too many pagesconsider changing the timescale or the date range You can also choose to show fewer columns of taskdata

If possible use paper that is larger than 85 x 11 inches You can select the paper size in Print Previewusing the Page Setup dialog box

If you change the timescale from Days to Weeks or Months this can make tasks with short durations (1to 5 days) difficult to see

If you have trouble printing the Gantt chart report try changing the dpi from 600 to 300 (draft mode) Ifyou continue to have problems contact your printer manufacturer and see if it supports PCL (PrinterCommand Language) technology which is included in most printers today

If you have trouble printing the Gantt chart report on a PDF printer you can try to scale the printing tographics setting to 50

114

copy Experience In Software Inc 1995 - 2006

See Also

Save Gantt Chart Images

Print Task Reports

Printer Setup

Page Setup

-o-

115

copy Experience In Software Inc 1995 - 2006

Print Preview a Gantt Chart

Before printing a Gantt chart preview its pages so you know how the report will look when printed

To preview a Gantt chart1 Click the Preview button on the Create and Print Gantt Chart Report dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from the current zoom percentage to 100 or from 100 to the current zoom percentageZoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25 viewChange printer settings and then print the reportYou can also click the Page Setup button to set margins select paper size and enter headers andfooters or click the Close button to close the Print Preview window

2 If the Gantt chart appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintGantt Chart Report dialog box

Notes

Print Preview is for viewing only--you cannot edit the contents of a report

If you want to print a wider task column return to the Gantt chart widen the Tasks Name column andthen print

To change print settings such as the printer selection and number of copies click the Print button to open the Print dialog box You can save the Gantt chart in a PDF file by clicking the Print button andthen clicking the PDF printer selection (such as Adobe PDF or PDF-XChange ) You can then distributethe Gantt chart electronically as a PDF file

See Also

Print a Gantt Chart

Page Setup

-o-

116

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a Gantt chart you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print a Gantt Chart

Print Preview a Gantt Chart

-o-

117

copy Experience In Software Inc 1995 - 2006

Printing to an Adobe PDF file

To print a Gantt chart to an Adobe PDF file you may have to make some adjustments to your settings

To preview a Gantt chart1 Select Adobe PDF as the name of the printer2 Click Properties button3 Click the PaperQuality tab4 Click Advanced button5 In the Graphic Section lower the setting on Print Quality6 Also in the Graphic Section change the Scaling from 100 to 50

-o-

118

copy Experience In Software Inc 1995 - 2006

Save Gantt Chart Images

You can save a Gantt chart as a series of graphic files in the Meta File (emf) format which you can theninsert in a file such as a Microsoft Word document or PowerPoint presentation The number of graphic filescreated depends on the report type and options you choose in the Create and Print Gantt Chart Reportdialog box By default Project KickStart saves the files in a folder named for your project

To save Gantt chart images1 In the Create and Print Gantt Chart Report dialog box click the Save Image button

The Save Image dialog box opens2 Change the location where you want to save the image files or change the part of the file name that

includes the project name and report type if necessary3 Click the Save buttonNotes

Project KickStart saves the image files in the PKSGanttImagesproject name folder stored in the MyDocumentsProject KickStart Projects folder (where project name is the name of your project)

Each graphic file name includes the name of the project report type date you created the report andnumber in the series of images as in CreateaWinningPresentation_Wall chart_09112008_1emf toCreateaWinningPresentation_Wall chart_09112008_20emf

To email the Gantt chart images attach the images in the PKSGanttImagesproject name folder storedin the My DocumentsProject KickStart Projects folder (where project name is the name of your project)If the image files are large zip or compress the files first

If you have installed PDF as a printer selection you can print the Gantt chart to a PDF file and thenattach the PDF file to an e-mail message PDF files are often easier to read than image files See thenotes in Print Preview a Gantt Chart for instructions on printing to a PDF file

-o-

119

copy Experience In Software Inc 1995 - 2006

Export Project Data

120

copy Experience In Software Inc 1995 - 2006

Export to ACT

Export to ACT 7 or Later

If you use ACT 7 or later (20052006200720082009) you can export your plan from Project KickStart toan ACT database with just one click After you export your plan you see your tasks in the ACT Groupview grouped under the name of your project

To export to ACT 7 or later

1 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 7 and later andthen click the Go button You can also click File on the menu bar point to Export to and then clickACT 7 and later

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (pad file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opens

Each time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks

4 Click Start (This works best if ACT is already open )

5 If you are exporting to a multi-user ACT database enter your ACT User Name and Password

To view each project separately in ACT Group Details

1 In ACT click the Group List icon

2 Double-click the Project Name in the Group Name column The Group Detail appears for the projectyou selected

3 Click the Contacts tab to see Contacts and click the Activities tab to see tasks for that project

4 You should press Ctrl-F5 to refresh the view Also you might have to adjust the Filter in ACT so thatDates to show is set to All Dates

Task names are listed in the Regarding column Assignments are listed in the Scheduled With columnPhases are shown in red and tasks and subtasks are shown in blue

To view tasks from multiple projects sorted by date in Task List or Calendar

In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn Project names are in the Associate With column You might have to adjust the Filter in ACT sothat Dates to show is set to All Dates

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar Tasks are set as timeless (Duration of 0 minutes) so the transferred tasks dont fill up thecalendar

121

copy Experience In Software Inc 1995 - 2006

Tips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

The ACT 7 and later export is smart enough to update your existing tasks from the same project If youexport the same Project KickStart project two or more times ACT recognizes the project and asks ifyou want to update the project information in ACT You do not lose your task history or notes in ACT

Tasks that are unassigned in Project KickStart are listed as Scheduled With Unassigned PKS

You can filter by Selected Users in the Task List and in Groups

See Also

Import ACT Contacts and Users to the People Library

-o-

122

copy Experience In Software Inc 1995 - 2006

Export to ACT 6

If you use ACT 6 ACT 2000 or ACT 5 you can transfer a Project KickStart plan into an ACT databasewith just one click After you export your plan you see your tasks in the ACT Group view grouped underthe name of your project

To export to ACT 61 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 6 and then click

the Go button You can also click File on the menu bar point to Export to and then click ACT 6

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (dbf file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opensEach time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks4 Click Start (This works best if ACT is already open )5 If you are exporting to a multi-user ACT database enter your ACT user name and passwordTo view each project separately in ACT1 In ACT click the Groups icon 2 Click the Project Name listed under All Groups on the left3 On the lower-right part of the window click the Activities tab to see tasks for that project

Task names are listed in the Regarding column Assignments are listed in the Scheduled With column 4 You might have to adjust the Filter in ACT so that Dates to show is set to All Dates Also you might

have to press Ctrl-F5 to refresh the view5 To view task details click the button next to the task column on the leftTo view tasks from multiple projects sorted by date1 In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn You might have to adjust the Filter in ACT so that Dates to show is set to All Dates

2 If the Group column is not showing add it by clicking ViewAdd Columns and then double-clickingGroupThe tasks are identified by group (project name)

3 To view task details click the button next to the task column on the leftTips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar as well as in the Task List

You can filter by Selected Users in the Task List and in Groups

After exporting your tasks to ACT you can import them to your Palm Pilot using the ACT Link

See Also

Import ACT Contacts and Users to the People Library

-o-

123

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Outlook

If you use Microsoft Outlook you can export your plan from Project KickStart to Outlook in a click of abutton After you export your plan you see your tasks in the Outlook Tasks view grouped under a categorynamed for your project In Outlook you can track your tasks and email tasks to team members

To export to Microsoft Outlook1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Outlook and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Outlook The Export to Outlook dialog box opens

2 Click an option button to export All tasks Uncompleted tasks or Completed tasks3 If you want to display the tasks you export on your Outlook Calendar click the check box4 Click the Start button A dialog box opens informing you that Project KickStart is trying to access your

Outlook data

5 Allow access for 1 minute and then click the Yes buttonTo view your tasks in Microsoft Outlook1 Click the Outlook Tasks button2 Depending on the version of Outlook you are using set to view the tasks by category In Outlook 2003

click the By Category option button in the Current View list You can also click View on the menu barpoint to Arrange By and then click CategoriesYour project is listed by its project name in the Categories list

3 Click an expand icon to see the complete list of tasks and subtasks

124

copy Experience In Software Inc 1995 - 2006

4 To view task details double-click the task nameTips

The export to Outlook works best if Outlook is already open

In Outlook you can set priorities set reminders and schedule by the hour

If you export to your Outlook Calendar a reminder appears on the due date of each task

After you export tasks to Outlook you can synchronize with your Palm Pilot Windows CE device orother handheld computer

Note

You can export only to Microsoft Office Outlook not Outlook Express

See Also

Import Outlook Contacts to the People Library

-o-

125

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Word

If you use Microsoft Word you can export your plan from Project KickStart to Word in a click of a buttonYour project appears in a Word table in a doc file You can cut and paste change column widths deletecolumns and print from Word

To export to Microsoft Word

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Word andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Word

Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in a Word document in a doc format

2 When youre finished use Save As to save the Word file with a new name such as ltnamegtdoc Forconvenience you can save the file using the same name as your Project KickStart project name

Benefits of using Project KickStart and Word

Communicate projects flexibly After exporting to Word you can communicate your project details ina variety of text formats You can also enhance your document by adding color logos clip art orhyperlinks

Distribute plans to others You can send doc files to other Microsoft Word users via email andrequest comments using Words Send To and Comments features

Tip

Include your strategic plan in documents letters and web pages in a doc or html file

Note

The image of the Gantt chart does not import into Word automatically You can manually import theGantt chart image into a Word document In Word select Insert on the menu bar point to Pictureclick From File and then browse to the folder containing the Gantt chart images you saved By defaultthis is cMy DocumentsProject KickStart ProjectsPKSGanttImages in a folder named for your project

See Also

Export to Word Processors (Other than Word)

Save Gantt Chart Images

126

copy Experience In Software Inc 1995 - 2006

-o-

127

copy Experience In Software Inc 1995 - 2006

Export to Word Processors (Other than Word)

If you are using a word processor other than Microsoft Word you can export your Project KickStart taskreport by first saving it as an HTML or RTF file

To export to word processors other than Microsoft Word

1 Save a Project KickStart task report using HTML or RTF format using the Save As button in the Createand Print Task Reports dialog box

2 Open the file with your word processor

3 Save the file using the Save As command using a different name

See Also

Print Task Reports

Save as HTML

Save as RTF

-o-

128

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Excel

If you use Microsoft Excel you can export your plan from Project KickStart to Excel in a click of a buttonYour project appears in an Excel worksheet in a xls file You can add task details perform calculationsand share your project data with other Excel users

To export to Microsoft Excel1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Excel and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Excel Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in an Excel worksheet in an xls format

2 When youre done select FileSave As to save the Excel file under a new name For convenience youmight want to save it under the same name as your Project KickStart project name

To manually import Gantt chart images into Microsoft Excel1 In Excel click Sheet2 and select ToolsOptions on the menu bar and unclick the box for Gridlines2 Then select Insert on the menu bar point to Picture click From File and then browse to the folder

containing the Gantt chart images you saved By default this is cMy DocumentsProject KickStartProjectsPKSGanttImages in a folder named for your project

3 Select one Gantt chart image at a time to bring it in 4 You can manipulate the size of the image in Excel

Benefits of using Project KickStart and ExcelProject KickStart is very good at scoping out a schedule but there are a few reasons why you might want touse both programs

Data sharing A Project KickStart user might want to share the information with other Excel users whodont have Project KickStart They could change enhance or redistribute their portions of the schedule

129

copy Experience In Software Inc 1995 - 2006

Add more task details Excel users can add new columns of task data that cant be added in ProjectKickStart

Sort task lists For example you could show your projects tasks sorted by each resources namethen see each resources tasks sorted by the tasks start date

Filter tasks Excel can show tasks that meet certain criteria For instance show tasks with the wordtesting in the task name

See Also

Save Gantt Chart Images

-o-

130

copy Experience In Software Inc 1995 - 2006

Export to Microsoft PowerPoint

If you use Microsoft PowerPoint you can export your plan from Project KickStart to PowerPoint in a click ofa button Your project appears as a formatted PowerPoint presentation in a ppt file

To export to Microsoft PowerPoint

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft PowerPointand then click the Go button You can also click File on the menu bar point to Export to and thenclick Microsoft PointPoint

The Export to PowerPoint dialog box opens where you can choose a PowerPoint design template ifyou like

2 Click the Start button

Your tasks days start and finish dates and costs appear in a PowerPoint presentation with an imageof the Gantt chart in one or more slides at the end of your slide show

Once you have created a PowerPoint presentation you can enhance your slides in several ways

Delete slides that are not appropriate for your presentation

131

copy Experience In Software Inc 1995 - 2006

Rearrange the order of the slides

Add colors for emphasis

Add graphics such as company logo clip art and colors

Shorten any long task titles

Benefits of using Project KickStart and PowerPoint

Save time You can dramatically save time in creating a PowerPoint presentation on your project

Present projects to others Present project details in webinars presentations and corporatemeetings Create template presentations or how tos for implementing an installation productintroduction or corporate policy for example

Communicate plans Email project plans in ppt format to colleagues and presentors

Tips

If you use a PowerPoint design template choose one that has a white or light background for maximumlegibility of the Gantt chart in the presentation

The Gantt chart image in the PowerPoint presentation is generated ldquoon the flyrdquo Change the Timescalesettings of the Gantt chart considering how it will be reflected in the number of images of the Ganttchart For example the Day view results in more Gantt chart images than the Months view

-o-

132

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Project

If you use Microsoft Project 98 2000 2002 or 2003 you can export your plan from Project KickStart toProject in a click of a button

To export to Microsoft Project

In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Project andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Project Your tasks assignments days start and finish dates costs done and notes (excluding attachments) appearin a Microsoft Project file

Benefits of using Project KickStart and Microsoft Project

Share data with others Send a project to a colleague or client that expects to see your schedule in anMicrosoft Project format

Schedule tasks with more flexibility Schedule tasks in different durations particularly in less than aday

Track resources Track resource usage and resource leveling and to have greater flexibility in sortingfiltering and reporting project information

Notes

Project KickStart tasks transfer to Microsoft Project as tasks with a Constraint type of Start No EarlierThan This keeps the dates the same as in the Project KickStart schedule

The settings in Project KickStart Working Days Calendar also transfer to Microsoft Project

Exporting to Microsoft Project allows you to take advantage of the advanced tracking and schedulingfeatures that large projects often require

You can also save your Project KickStart projects as an mpx file which you can open in MicrosoftProject and send to other Microsoft Project users Click File on the Project KickStart menu bar clickSave As and then choose mpx as the file type After you save the file click File on the MicrosoftProject menu bar click Open and open your mpx file

-o-

133

copy Experience In Software Inc 1995 - 2006

Export to SureTrak Project Manager

If you use SureTrak Project Manager you can export your plan from Project KickStart to SureTrak ProjectManager

To export to SureTrak Project Manager

1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file

2 In SureTrak click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

SureTrak

You will see your tasks and assignments (but not the notes) appear in a SureTrak file The file is shownin outline view

Benefits of using Project KickStart and SureTrak

Add new information to tasks such as how they are linked

Track progress particularly for comparing plans verses actual results

Have greater flexibility in sorting filtering and reporting project information

Notes

Task notes are not included in the transfer

A version of Project KickStart called the Project KickStart Wizard is included in SureTrak 2 andSureTrak 3 You can use it within SureTrak

See Also

Export MPX Files

-o-

134

copy Experience In Software Inc 1995 - 2006

Export to FastTrack Schedule

If you use FastTrack Schedule you can save your Project KickStart project as an mpx file and import it intoFastTrack ScheduleTo export to FastTrack Schedule1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file2 In FastTrack Schedule click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

FastTrack ScheduleBenefits of using Project KickStart and FastTrack Schedule

Add more task details FastTrack Schedule provides the features and tools needed in many largeprojects

Multiproject reporting Consolidate multiple projects into a master project file

See Also

Export MPX Files

-o-

135

copy Experience In Software Inc 1995 - 2006

Export to Milestones Professional

If you use Milestone Professional you can export your plan from Project KickStart to MilestonesProfessional in a click of a button

To export to Milestone Professional

In the Schedule step click the Export to list arrow below the Gantt chart click MilestonesProfessional and then click the Go button You can also click File on the menu bar point to Export to and then click Milestones Professional

Your tasks assignments start and finish dates and notes (excluding attachments) appear in aMilestones file

Tips

After you export your tasks to Milestones Professional you can create taskbars add titles and performother tasks to produce a presentation-quality schedule You can also use Milestones to track your tasksby showing task durations and percent completions Make scheduling changes by dragging the taskdates

If you have an earlier version of Milestones (eg version 45 or 5) you can save Project KickStart dataas an mpx file and then open the mpx file in Milestones

-o-

136

copy Experience In Software Inc 1995 - 2006

Export to Mindjet MindManager

If you use Mindjet MindManager 7 or later you can export your project plan from Project KickStart in a clickof a button Or you can develop a rough plan in MindManager and export your mind map to ProjectKickStart for enhanced planning It works both ways

To export from Project KickStart to MindManager

In the Schedule step click the Export to list arrow below the Gantt chart click MindManager and thenclick the Go button You can also click File on the menu bar point to Export to and then clickMindManager

Your tasks assignments start and finish dates durations costs Done and notes (excludingattachments) appear in a MindManager file

To export from MindManager to Project KickStart

In MindManager click File on the menu bar point to Send To and then click Project KickStart Thenclick the OK button to start the export

You can also click the Project KickStart icon at the bottom of the MindManager window

Benefits of using Project KickStart and MindManager together

Visualize your plan in two ways Brainstorm plan and communicate your project details in both agraphical and linear style

Develop a graphical plan and then fine-tune the details MindManager uses mindmappingtechniques to develop a high-level plan in a graphical format Export to Project KickStart to enhanceyour plan details by focusing on your projects goals obstacles and resource needs You can alsocreate a Gantt chart schedule

Communicate concepts Project KickStart users can display their plans in a highly graphicalmindmapping format in MindManager The maps make it easier to communicate complex processesand visually identify important tasks issues and relationships

Tip

If you dont already use MindManager you can purchase it in our Thinking Tools Store

-o-

137

copy Experience In Software Inc 1995 - 2006

Export to WBS Chart Pro

If you use WBS Chart Pro you can export your plan from Project KickStart to WBS Chart Pro in a click of abutton

To export to WBS Chart Pro

In the Schedule step click the Export to list arrow below the Gantt chart click WBS Chart Pro andthen click the Go button You can also click File on the menu bar point to Export to and then clickWBS Chart ProYour project is displayed under the project name Each phase in the project is shown in a box with ashadow Each lower level task in a phase is displayed under their respective phase box groupedtogether with the other tasks in that phase

Benefits of using Project KickStart and WBS Chart

Visualize tasks Work with tasks in a tree-style chart called a Work Breakdown Structure (WBS)chart

Communicate your project plan with others WBS Chart uses the outline you create in ProjectKickStart to create a top-down picture of your plan This picture is similar to an Organization chart Butinstead of displaying the structure of your company a WBS chart displays the structure of your projectplan

Notes

WBS Chart refers to the phases in the project as Summary Tasks and the detail for each phase asTasks

The export only works if WBS Chart is not currently running You must close WBS Chart before you cancreate another chart

See Also

Export MPX Files

-o-

138

copy Experience In Software Inc 1995 - 2006

Export MPX Files

The MPX file format is an ASCII format created by Microsoft Project or another program and is used tosend data to and from project management software programs

The following programs can create and open MPX files

FastTrack Schedule

Microsoft Project (95 or 98)

Project KickStart 5

Project KickStart 32

RiskyProject

SureTrak Project Manager

WBS Chart

In these programs you save a project as an MPX file using the Save As command on the File menu Youcan then open an MPX file by using the Open command on the File menu and then specifying the file typeas mpx

For example if you want to move a project from Project KickStart 5 to Project KickStart 32 you can savethe project as an mpx file and then open it in Project KickStart 32

In Microsoft Visio you can create a Visio project time line from Project KickStart To do so you first mustsave your file in Project KickStart as an MPX file Then

1 Start Visio

2 Click File on the menu bar point to New click Business Diagram and then click Project TimelinesWizard

3 Click Next

4 On the second window click Import MPX File to import the Project KickStart mpx file

5 Enter the file location and name or click Browse to locate the file

6 Follow the instructions in the Visio Project Timelines Wizard windows

Tip

If you have difficulty importing the mpx file remove any commas from task names

-o-

139

copy Experience In Software Inc 1995 - 2006

Reference

140

copy Experience In Software Inc 1995 - 2006

Menus

File Menu

Command Keyboard Shortcut Description

New Project Ctrl+N Creates and names a new project fileOpen Project Ctrl+O Opens a previously saved Project KickStart 4 or 5 file

(prx) Project KickStart 3 file (prj) or mpx fileClose Ctrl+W Closes an open Project KickStart fileSave Ctrl+S Saves a project file (prx) in which you made changes Save As Saves a project file with a different file name or different

file format such as MPXPrint Task Reports

Ctrl+T Generates and prints a report letting you preview thecontents

Print Gantt ChartReports

Ctrl+G In the Gantt chart (Schedule step) generates andprints the Gantt chart in the current timescale

Export To Sends the project to another program such asMicrosoft Outlook or ACT 7

Recent file list Lists the last three files opened in Project KickStartExit

Alt+F4 Exits the program

-o-

141

copy Experience In Software Inc 1995 - 2006

Edit Menu

Command Keyboard Shortcut Description

UndoRedo Ctrl+Z Undoes or repeats the last operationCut

Ctrl+X Deletes the currently selected information placing it on theclipboard so you can paste it elsewhere

Copy

Ctrl+C Places a copy of selected information on the Clipboard so youcan paste it elsewhere

Paste

Ctrl+V Places information from the Clipboard to the currently selectedlocation

Select all Ctrl+A Selects all the content in the windowAdd a line Adds a new row where you can enter text

-o-

142

copy Experience In Software Inc 1995 - 2006

View Menu

Command Description

Tool Bar Shows or hides the toolbar (a checkmark indicates thetoolbar is displayed)

Steps Bar Shows or hides the Steps bar (a checkmark indicates the Steps bar is displayed)

Name Go to the Name your project stepPhases Go to Phases stepGoals Go to Goals stepSimilar Projects Go to Similar projects stepPeople Go to People stepObstacles Go to Obstacles stepAssign Go to Assign tasks to people stepTasks Go to Tasks stepSchedule Go to Schedule step

-o-

143

copy Experience In Software Inc 1995 - 2006

Tools Menu

Command Keyboard Shortcut Description

Spelling

F7 Checks spelling of project dataexcept for names of people

Collaboration To access or find out aboutGoToMeeting

Options Select options for running thesoftware

-o-

144

copy Experience In Software Inc 1995 - 2006

Options

-o-

145

copy Experience In Software Inc 1995 - 2006

Data Menu

The Data menu is available in the Tasks and Schedule steps for manipulating tasks and creating ascheduleCommand Description

Move Up Moves the selected task item upMove Down Moves the selected task item downOutdent Moves the selected task item to the leftIndent Moves the selected task item to the rightInsert Task Insert task in row aboveInsert SubTask Insert subtask below current rowDelete Task Delete current taskEdit Task Properties Brings you to an edit screen where you can edit task

name change assignments and edit task notesEdit Notes Brings you to an edit screen for editing task notesColor Taskbars Change the color of selected tasks (in Schedule)Change Working Days Select which days are working and which are

nonworking (in Schedule)Link Tasks Link tasks in Gantt chart (Pro Users)Unlink Tasks Unlink tasks in Gantt chart (Pro Users)

-o-

146

copy Experience In Software Inc 1995 - 2006

Timescale Menu

The Timescale menu is available in the Schedule step so you can change the display of the Gantt chartschedule

Command Description

Days Displays a daily schedule in theGantt chart

Weeks Displays a weekly schedule inthe Gantt chart

Months Displays a monthly schedule inthe Gantt chart

Quarters Displays a quarterly schedule inthe Gantt chart

Years Displays a yearly schedule inthe Gantt chart

-o-

147

copy Experience In Software Inc 1995 - 2006

Help Menu

Command Description

Project KickStart Help Help for Project KickStart including a Table ofContents and index of terms

Online Tutorials View several Getting Started Tutorials to getyou started with Project KickStart whether youare a new or experienced user

Keyboard Shortcuts Shortcuts for programTechnical Support How to obtain Technical Support for Project

KickStart via web form and email[Send Log to Technical Support] If the program detects an error it writes a log

of technical issues Click Send Log toTechnical Support to send the error log to us

ProjectKickStartcom Visit the Project KickStart Web siteGet Latest Version See what the latest published version is and

download it if you need itAbout Project KickStart Shows Project KickStart version number build

date copyright and system information

-o-

148

copy Experience In Software Inc 1995 - 2006

Shortcuts

Use the following keyboard shortcuts to move quickly around in Project KickStart

Navigation

Move forward to the next window Alt+NMove back to the previous window Alt+BSteps

Go to Name step Alt+MGo to Phases step Alt+SGo to Goals step Alt+GGo to Similar step Alt+RGo to People step Alt+PGo to Obstacles step Alt+OGo to Assign step Alt+IGo to Tasks step Alt+KGo to Library (Phases Tasks GoalsPeople Obstacles)

Alt+L

Menus

File menu Alt+FEdit menu Alt+EView menu Alt+VShow menu (Tasks step) Alt+WOutline menu (Tasks step) Alt+UTimescale (Schedule step) Alt+CHelp menu Alt+H F1Other

Edit tasks assignments amp notes (Tasks step)F3Save Ctrl+SPrint Task Report Ctrl+PPrint Gantt Chart (Schedule step) Ctrl+GCut Ctrl+XCopy Ctrl+CPaste Ctrl+VInsert Row InsertDelete Row DeleteInsert Line Break (in Notes in Task List andSchdule steps)

Enter

Spell Check

Ignore Alt+IIgnore All Alt+GChange Alt+CChange All Alt+HHelp

149

copy Experience In Software Inc 1995 - 2006

Contents in Help Alt+CIndex Alt+IBack in Help Alt+BClose Help Alt+LHelp about the current step Alt+H

-o-

150

copy Experience In Software Inc 1995 - 2006

Share Project KickStart Data

Project KickStart makes it easy to share data with other people involved with a project You can share yourProject KickStart data in the following ways

Send a printed report Make a PowerPoint presentation Send a file (prx html rtf mpx) Post an HTML file to a Web site and access it with your web browser Export to other programs such as Microsoft Word or Excel and send data in a format the recipient can

access (such as doc xls or mpx)

Note

You can also collaborate with a colleague by conducting an online meeting using GoToMeeting (Prousers)

-o-

151

copy Experience In Software Inc 1995 - 2006

Open a Project

After you create a project and save it in a prx prj or mpx file using Project KickStart or other softwareyou can open the project in Project KickStartTo open a project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click a file type (prxprj or mpx)

3 Navigate to the folder that contains the file4 Double-click the name of the file

Opening a Project KickStart 3 prj file converts it to a prx file

Generally prj files are stored in cprogram filesProject KickStart 3

The tasks in the converted Project KickStart 5 file will have the same start and finish dates anddurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way To have weekends as non working days open the working days calendar and markweekends as non working

Opening a mpx file converts it to a prx file

The tasks in each project have the same start and finish dates and durations

-o-

152

copy Experience In Software Inc 1995 - 2006

Dedication

I dedicate this software program to my new colleague

Kevin Ahlvin

Roy A Nierenberg President

-o-

153

copy Experience In Software Inc 1995 - 2006

Credits and Trademarks

Credits

Missak Koumoudjian Program Architect and Chief Programmer

Kevin Ahlvin Interface DesignAnn Kawamoto Quality AssuranceAlexander Setzepfandt Quality AssuranceJackie LeungJeffrey Chow

Programming Interns

Kevin Ahlvin Product Supervisor and CoordinatorJoseph Fusco Project Management Consultant and content

providerLisa RuffoloJoseph Fusco

Help System

Roy A Nierenberg President

Trademark

Project KickStart and Project KickStart Wizard are trademarks of Experience In Software Inc in the UnitedStates andor in other countries All rights reserved All other trademarks mentioned herein are the propertyof their respective owners

-o-

154

copy Experience In Software Inc 1995 - 2006

Uninstalling

You can uninstall Project KickStart 5 through the Control Panel AddRemove Programs Select ProjectKickStart 5 This starts the InstallShield Maintenance Program You should then remove all of theprogram files that were installed It will not erase your Project KickStart prx data files

If that does not work you can delete the Project KickStart files manually

Note

If you purchased Project KickStart and you want to return it for a refund follow the instructions forDe-activating the software at httpwwwprojectkickstartcomcontactreturnscfm

-o-

155

copy Experience In Software Inc 1995 - 2006

Using Past Projects

You can use past projects in two ways

If you have projects that are similar you can use a past project as a template for a new project In theWelcome window select Open a Project Open that project and Save As under a different name Nowyou can open up the renamed project and modify it for the current project

You can draw from several projects in the Similar Projects step First select projects that are similarand click Next Then select tasks from those projects and decide where they would fit into your currentproject

See Also

Opening a project Compatibility with earlier versions

-o-

156

copy Experience In Software Inc 1995 - 2006

Index

- - Change Working Schedule 85

- -prj file format 13

- A -About Linking Tasks (Pro Users) 59About Scheduling Tasks 55About the Gantt Chart 57ACT 120 92 122ACT 6 92 122ACT 7 or later 92 120Activate 14Activating Trial Version 14Add a New Person or Resource 39add a subtask 83add a task 83Add a Task or Subtask 47Add or Change Task Assignments 51Add or Change Task Details 52Add Subtask 63Add Task 63Add URL 49Additional Features in Task Data View (Pro Users) 68Additional Tools in Chart View (Pro Users) 71Adobe PDF 117Assignments tab 80Attachments 49Autolink tasks (Pro Users) 58

- B -Back 10borrow tasks 29

- C -Change Details for Linked Tasks (Pro Users) 81Change Project Start 63Change Task Dates 73Change Task Details 80Change the Appearance of the Task List 43Change the Display of the Schedule 61Change Timescale 63Change Working Schedule 63Chart view 57

157

copy Experience In Software Inc 1995 - 2006

Cloning projects 155Color 63 86Compatibility 13Compatibility with earlier versions 13convert projects 13Coordination 12Create and Print Task Reports 102Credits 153Credits and Trademarks 153critical path 88CSV 96Customer support 20Customer Support 20Customizing Project KickStart

- D -Dashboard 99Data Menu 145Dedication 152Delete 63delete a task 83demote 46dependencies 12 76

- E -Edit Menu 141Edit Notes and Attachments 63Edit or Substitute People 40Edit Task Information 63Email Task Reports 108End User License Agreement 16error 21Error Messages 21export from MindManager 136Export MPX Files 138Export to ACT 6 122Export to ACT 7 and Later 120Export to FastTrack Schedule 134Export to Microsoft Excel 128Export to Microsoft Outlook 123Export to Microsoft PowerPoint 130Export to Microsoft Project 132Export to Microsoft Word 125Export to Milestones Professional 135Export to Mindjet MindManager 136Export to SureTrak Project Manager 133Export to WBS Chart Pro 137

- F -FastTrack Schedule 134File Menu 140Fit to page 111Fit to Smallest Size 111

158

copy Experience In Software Inc 1995 - 2006

- G -Gantt chart 55 57General tab 80Goal 26Goal statements 26Goals 26Goals - Step 1 of 3 26Goals - Step 2 of 3 27Goals - Step 3 of 3 28goals library 26 89Goalsadd 26Goalsdelete 26Goalsedit 26Goalstasks for 27GoToMeeting 150 12

- H -Handouts 111Help Menu 147hyperlink 49

- I -Import ACT 92import contacts and users 92import Outlook contacts 94Import Outlook Contacts via CSV to the People Library (Pro Users) 96ImportCSVToPKSexe 96Indent 46Individual Assignments 102Introduction 7Introduction 7

- K -Knowledge Libraries 90

- L -lag time 81lead time 59 81library 89License Key 14link 59Link lines 59Link tasks 12 65linked tasks 59

- M -major activities 24Make Tasks Overlap (Pro Users) 87Manage a Library 90

159

copy Experience In Software Inc 1995 - 2006

Menu 140Microsoft Excel 128Microsoft Outlook 123Microsoft PowerPoint 130Microsoft Project 132Microsoft Project (95 or 98) 138Microsoft Visio 138Microsoft Word 125Milestone 69 79Milestones Professional 135Mindjet MindManager 136MindManager 136

- N -Name 23Name Your Project 23Navigating Project KickStart 10Next 10Notes and Attachments tab 80

- O -Objectives 26Obstacles 34Obstacles - Step 3 of 3 36Obstacles Library 89Open a Project 151Options 144Outdent 46Outdent and Indent arrows 63Outlook Calendar 123Overview

- P -Page Setup 107 116 100PDF 117people 31People - Step 3 of 3 28People Library 91phase 24phase dates 75Phase Dates Cannot Be Edited 75phases 24Phases - Step 1 of 2 24Phases - Step 2 of 2 25Phases Library 89Phases Goals People amp Obstacles 102PowerPoint presentation 130Pred 68Predecessor 68Predecessor tasks 59predecessors 76Print a Gantt Chart 111Print Dashboard Reports 99Print Preview 105Print Preview a Gantt Chart 115Print Reports 98Print Task Reports 102

160

copy Experience In Software Inc 1995 - 2006

Printer Setup 106Printing to an Adobe PDF file 117prj 13Pro 145Pro Edition 145Product support 20Project 23Project KickStart 3 prj file 151Project KickStart for Windows 7project name 23project start date 73project template 155project title 23promote 46promote and demote tasks 83

- Q -Quick Tour of Working with Linked Tasks (Pro Users) 76

- R -Red vertical line 69Redo 11Register Project KickStart 22Registering Project KickStart 22remove people 38Remove People from a Task 38reorder tasks 83Reorganize Tasks in Task Data View 83Repeat tasks on every page (for handouts) 111Reporting Technical Issues 21resource 31resources 31restore 34return 154risks 34RiskyProject 138

- S -Save As 101Save as HTML 109Save as RTF 110Save Gantt Chart Images 118Schedule 55Send Error Report 21similar projects 29spelling 53starter schedule 55Steps 7subtask 47Subtasks 46Succ 68Successor 68Successor tasks 59successors 76Summary bar 69Support 20SureTrak Project Manager 133

161

copy Experience In Software Inc 1995 - 2006

- T -Task Data view 57task dates 73Task Report 102Taskbar 69Taskbar with percent done 69Tasks 25Tasks in Phases 25Tasks Library 89team 31Technical support 20timescale 84Timescale Menu 146Tools Menu 143Trademark 153trademarks 153Trial 14

- U -unassigning 38Understand Chart View 69Understand Task Data View 66Undo 11UndoRedo Buttons 11uninstallUninstalling 154Unlink tasks 12 65Up and Down arrows 63Use Project KickStart to 8Use the Gantt Chart Toolbar 63Use the Planning Wizard 9Uses 8Using Past Projects 29 155

- V -Version View Menu 142Visio 138

- W -Wall chart 111WBS Chart Pro 137Welcome to Project KickStart 7Whats Due Next Month 99Whats Due Next Week 99Whats Due Today 99Whats New in Project KickStart Pro 5 11Windows Vista 20

162

copy Experience In Software Inc 1995 - 2006

copy Experience In Software 2008w w w projectkickstartcom

  • Table of Contents
  • Start Here Welcome to Project KickStart
    • Introduction
      • Welcome to Project KickStart
      • Use Project KickStart to
      • Use the Planning Wizard
      • Navigating Project KickStart
      • Whats New in Project KickStart Pro 5
      • Whats New in Project KickStart Pro 5 (Pro Users)
      • Compatibility with earlier versions
      • Activating Trial Version
        • Licenses and Support
          • End User License Agreement
          • Customer Support
          • Reporting Technical Issues
          • Register Project KickStart
              • Planning Projects
                • Name Your Project
                • Phases - Step 1 of 2
                • Phases - Step 2 of 2
                • Goals - Step 1 of 3
                • Goals - Step 2 of 2
                • Goals - Step 3 of 3
                • Similar Projects - Step 1 of 2
                • Similar Projects - Step 2 of 2
                • People - Step 1 of 3
                • People - Step 2 of 3
                • People - Step 3 of 3
                • Obstacles - Step 1 of 3
                • Obstacles - Step 2 of 3
                • Obstacles - Step 3 of 3
                  • Assigning People
                    • Assign Tasks to People
                    • Remove People from a Task
                    • Add a New Person or Resource
                    • Edit or Substitute People
                      • Organizing the Project Plan
                        • About Organizing Tasks
                        • Change the Appearance of the Task List
                        • Show or Hide Tasks in the Task List
                        • Move Tasks within the Task List
                        • Outdent and Indent Tasks
                        • Add a Task or Subtask
                        • Edit Tasks
                        • Add Task Notes and Attachments
                        • Add or Change Task Assignments
                        • Add or Change Task Details
                        • Check Spelling
                          • Scheduling Tasks in the Gantt Chart
                            • Scheduling Overview
                              • About Scheduling Tasks
                              • About the Gantt Chart
                              • Autolink tasks (Pro Users)
                              • About Linking Tasks (Pro Users)
                              • Change the Display of the Schedule
                              • Use the Gantt Chart Toolbar
                              • Use the Gantt Chart Toolbar (Pro Users)
                              • Understand Task Data View
                              • Additional Features in Task Data View (Pro Users)
                              • Understand Chart View
                              • Additional Tools in Chart View (Pro Users)
                                • Change Task Dates
                                • Phase Dates Cannot Be Edited
                                • Quick Tour of Working with Linked Tasks (Pro Users)
                                • Link and Unlink Tasks (Pro Users)
                                • Create a Milestone
                                • Change Task Details
                                • Change Details for Linked Tasks (Pro Users)
                                • Reorganize Tasks in Task Data View
                                • Change the Timescale of the Schedule
                                • Specify Working Days
                                • Change the Color of Taskbars
                                • Make Tasks Overlap (Pro Users)
                                • Manage Changes in Your Schedule (Pro Users)
                                  • Managing Libraries
                                    • Use a Library
                                    • Manage a Library
                                    • Manage the People Library
                                    • Import ACT Contacts and Users to the People Library
                                    • Import Outlook Contacts to the People Library
                                    • Import Outlook Contacts via CSV to the People Library (Pro Users)
                                      • Printing Reports
                                        • Printing Dashboards
                                          • Print Reports
                                          • Print Dashboard Reports
                                          • Page Setup
                                          • Save As
                                            • Printing Task Reports
                                              • Print Task Reports
                                              • Print Preview
                                              • Printer Setup
                                              • Page Setup
                                              • Email Task Reports
                                              • Save As HTML
                                              • Save As RTF
                                                • Printing Gantt Chart Reports
                                                  • Print a Gantt Chart
                                                  • Print Preview a Gantt Chart
                                                  • Page Setup
                                                  • Printing to an Adobe PDF file
                                                  • Save Gantt Chart Images
                                                      • Export Project Data
                                                        • Export to ACT
                                                          • Export to ACT 7 and Later
                                                          • Export to ACT 6
                                                            • Export to Microsoft Outlook
                                                            • Export to Microsoft Word
                                                            • Export to Word Processors (Other than Word)
                                                            • Export to Microsoft Excel
                                                            • Export to Microsoft PowerPoint
                                                            • Export to Microsoft Project
                                                            • Export to SureTrak Project Manager
                                                            • Export to FastTrack Schedule
                                                            • Export to Milestones Professional
                                                            • Export to Mindjet MindManager
                                                            • Export to WBS Chart Pro
                                                            • Export MPX Files
                                                              • Reference
                                                                • Menus
                                                                  • File Menu
                                                                  • Edit Menu
                                                                  • View Menu
                                                                  • Tools Menu
                                                                  • Options
                                                                  • Data Menu
                                                                  • Timescale Menu
                                                                  • Help Menu
                                                                    • Shortcuts
                                                                    • Share Project KickStart data
                                                                    • Open a Project
                                                                    • Dedication
                                                                    • Credits and Trademarks
                                                                    • Uninstalling the software
                                                                    • Using Past Projects
Page 3: Project KickStart Help File in PDF format

3

copy Experience In Software Inc 1995 - 2006

Table of Contents

Start Here Welcome to Project KickStart 6 Introduction 7 Welcome to Project KickStart 7 Use Project KickStart to 8 Use the Planning Wizard 9 Navigating Project KickStart 10 Whats New in Project KickStart Pro 5 11 Whats New in Project KickStart Pro 5 (Pro Users) 12 Compatibility with earlier versions 13 Activating Trial Version 14 Licenses and Support 16 End User License Agreement 16 Customer Support 20 Reporting Technical Issues 21 Register Project KickStart 22Planning Projects 23 Name Your Project 23 Phases - Step 1 of 2 24 Phases - Step 2 of 2 25 Goals - Step 1 of 3 26 Goals - Step 2 of 2 27 Goals - Step 3 of 3 28 Similar Projects - Step 1 of 2 29 Similar Projects - Step 2 of 2 30 People - Step 1 of 3 31 People - Step 2 of 3 32 People - Step 3 of 3 33 Obstacles - Step 1 of 3 34 Obstacles - Step 2 of 3 35 Obstacles - Step 3 of 3 36Assigning People 37 Assign Tasks to People 37 Remove People from a Task 38 Add a New Person or Resource 39 Edit or Substitute People 40Organizing the Project Plan 41 About Organizing Tasks 41 Change the Appearance of the Task List 43 Show or Hide Tasks in the Task List 44 Move Tasks within the Task List 45 Outdent and Indent Tasks 46 Add a Task or Subtask 47 Edit Tasks 48 Add Task Notes and Attachments 49 Add or Change Task Assignments 51 Add or Change Task Details 52 Check Spelling 53Scheduling Tasks in the Gantt Chart 54 Scheduling Overview 55 About Scheduling Tasks 55

4

copy Experience In Software Inc 1995 - 2006

About the Gantt Chart 57 Autolink tasks (Pro Users) 58 About Linking Tasks (Pro Users) 59 Change the Display of the Schedule 61 Use the Gantt Chart Toolbar 63 Use the Gantt Chart Toolbar (Pro Users) 65 Understand Task Data View 66 Additional Features in Task Data View (Pro Users) 68 Understand Chart View 69 Additional Tools in Chart View (Pro Users) 71 Change Task Dates 73 Phase Dates Cannot Be Edited 75 Quick Tour of Working with Linked Tasks (Pro Users) 76 Link and Unlink Tasks (Pro Users) 78 Create a Milestone 79 Change Task Details 80 Change Details for Linked Tasks (Pro Users) 81 Reorganize Tasks in Task Data View 83 Change the Timescale of the Schedule 84 Specify Working Days 85 Change the Color of Taskbars 86 Make Tasks Overlap (Pro Users) 87 Manage Changes in Your Schedule (Pro Users) 88Managing Libraries 89 Use a Library 89 Manage a Library 90 Manage the People Library 91 Import ACT Contacts and Users to the People Library 92 Import Outlook Contacts to the People Library 94 Import Outlook Contacts via CSV to the People Library (Pro Users) 96Printing Reports 97 Printing Dashboards 98 Print Reports 98 Print Dashboard Reports 99 Page Setup 100 Save As 101 Printing Task Reports 102 Print Task Reports 102 Print Preview 105 Printer Setup 106 Page Setup 107 Email Task Reports 108 Save As HTML 109 Save As RTF 110 Printing Gantt Chart Reports 111 Print a Gantt Chart 111 Print Preview a Gantt Chart 115 Page Setup 116 Printing to an Adobe PDF file 117 Save Gantt Chart Images 118Export Project Data 119 Export to ACT 120 Export to ACT 7 and Later 120

5

copy Experience In Software Inc 1995 - 2006

Export to ACT 6 122 Export to Microsoft Outlook 123 Export to Microsoft Word 125 Export to Word Processors (Other than Word) 127 Export to Microsoft Excel 128 Export to Microsoft PowerPoint 130 Export to Microsoft Project 132 Export to SureTrak Project Manager 133 Export to FastTrack Schedule 134 Export to Milestones Professional 135 Export to Mindjet MindManager 136 Export to WBS Chart Pro 137 Export MPX Files 138Reference 139 Menus 140 File Menu 140 Edit Menu 141 View Menu 142 Tools Menu 143 Options 144 Data Menu 145 Timescale Menu 146 Help Menu 147 Shortcuts 148 Share Project KickStart data 150 Open a Project 151 Dedication 152 Credits and Trademarks 153 Uninstalling the software 154 Using Past Projects 155

6

copy Experience In Software Inc 1995 - 2006

Start Here Welcome to Project KickStart

7

copy Experience In Software Inc 1995 - 2006

Introduction

Welcome to Project KickStart

Whether yoursquore a novice or seasoned pro yoursquoll be amazed at how quickly you can create a thoughtfulcomprehensive task list and project schedule Using Project KickStart you can go from raw idea to aproject task list in 30 minutes You do not need any special project management training to use ProjectKickStart

The first thing youll want to do is

Open a project Click to open one of our sample projects

Start a new project Click to begin planning your own project

Open your last project If youve already created a project click this option to open your most recentproject

After that let Project KickStart show you the way Itrsquos easy to navigate Project KickStart with its intuitivegraphical interface--it feels like a coach is guiding you through each step

Next StepsProject KickStart guides you through the process of planning and scheduling your project On the top ofeach Project KickStart window are instructions explaining what to do Read the instructions enter your dataand then click the Next button in the lower-right corner of the window Additional help is always availablefrom the onscreen Advisor and Project KickStart Help

Sample ProjectsThe sample projects are completed projects that let you get a feel for Project KickStart If you find onesimilar to the project you want to create open it save it with a new name and then customize it to meetyour needs

-o-

8

copy Experience In Software Inc 1995 - 2006

Use Project KickStart to

Project KickStart is organized into three sections planning scheduling and exporting to other programs

Plan The Project KickStart graphical interface acts as a Planning Wizard guiding you through eightsteps for planning your project Some planning steps involve brainstorming to identify tasks that youmight otherwise overlook

Schedule The Project KickStart Gantt chart makes scheduling tasks fast and easy You can printtaskbars in color and save Gantt charts reports as images so you can email them to colleagues orinclude them in a report

Export Communicate your projects in a variety of ways by exporting project data to other applicationsincluding Microsoft Outlook With one mouse click you can include Project KickStart plans in aMicrosoft Word document Excel spreadsheet PowerPoint slide presentation and more

People are using Project KickStart to

Create process templates project reports to-do lists and more

Communicate project details to others through reports email and Gantt chart schedules

Ensure project buy-in by including the needs of team members in your plan

Consider project goals and obstacles in the planning process and prevent surprises later

-o-

9

copy Experience In Software Inc 1995 - 2006

Use the Planning Wizard

Project KickStart uses a Planning Wizard that guides you through eight steps for planning your project Tostep through the wizard click each icon on the Steps bar (on the left side of the Project KickStart window) inorder On each window t ips and advice are always available by clicking the Advisor button You click theNext button to continue

Name Each project has a name To start planning your project give it ashort descriptive name

Phases Consider how your project will break down into major activitiesor phases Start by listing your phases and then list the tasks thatbelong in each phase

Goals Goals are what you hope to accomplish in your project Enter orselect the goals for your project Then you can list any new tasks toachieve each goal

Similar Projects often have tasks in common In this step you canborrow tasks from past projects to help you plan this project Then youcan add any new tasks from a similar project to the phases of yourcurrent project

People List the people groups or things that might provide resourcesfor your project including yourself Then identify any new tasks thesepeople might do or suggest for your project

Obstacles Each project has obstacles you can overcome if youanticipate them List the obstacles you will face in your project and thenidentify any new tasks needed to avoid the obstacles

Assign Assign tasks to people and other resources

Tasks Change the order of your tasks add and delete tasks andcreate subtasks You can also edit tasks change assignments and addnotes

Schedule Schedule the tasks in your project To make schedulingeasier new projects open with a starter schedule beginning todaywhich you can customize to fit your project

-o-

10

copy Experience In Software Inc 1995 - 2006

Navigating Project KickStart

When you use the Planning Wizard you work with a step window similar to the following illustration

Steps bar Click a step button to perform a step in the Planning Wizard The selected button shows yourcurrent step

Name of your project Shows the name entered in the Name step

Menu bar Select options from the menu bar to work with your projects

Toolbar Click buttons to perform common tasks such as saving your project

Step instructions Indicate how to perform the current step

Library button Click to open a library for the current step For example click the Goals Library button toopen a library listing typical project goals

Back and Next buttons Click a button to return to the previous step or continue to the next step in thePlanning Wizard

Advisor button Click to see instructions tips and notes for completing the current step

-o-

11

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5

The following table outlines whatrsquos new in Project KickStart Pro 5

If you own a previous version of Project KickStart yoursquoll notice the new Pro version has a new look and feelAs you begin to check it out yoursquoll soon discover Project KickStart Version 5 is a lot more powerful thanprevious versions and comes with some great new features

FEATURE DESCRIPTION IMPROVED

NEW

Dashboard Reporting

Quickly assess what is due TodayNext Week or Next Month

X

Import Contacts Import from a comma separatedvalue (CSV) file

X

Templates Use as is or customize X

Gantt Chart Greater stability and functionality X

User Interface Contemporary look and colorscheme

X

Preferences Customize look and feel andprogram defaults

X

Productivity Pack Project template Word docs fornewbies

X

Exports Improved Outlook MindManager and ACTimproved data exchange

X

-o-

12

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5 (Pro Users)

This feature is available only in Project KickStart Professional

The following table outlines whatrsquos new in Project KickStart Pro 5

FEATURE DESCRIPTION IMPROVED NEW

Gantt Chart Task dependencies in Gantt chart X

Link tasks Show task dependencies X

Unlink tasks Remove task dependencies X

Add predecessors Add task predecessors X

Add successors Add task successors X

Project Coordination Link to GoToMeeting for onlinemeetings on projects

X

Project KickStart Pro now includes dependencies on the Gantt chart This sophisticated scheduling andproject management tool is new to Project KickStart Pro and is designed to make complex projectscheduling easy and straightforward

Use dependencies to handle scheduling demands delays and surprises without modifying every task inyour project Dependencies let you make adjustments as events change giving you a more robust scheduleand the opportunity to conduct what-if analysis

Suppose you are managing a landscaping project involving subcontractors and dozens of tasks One ofyour first tasks is to pave a path with flagstones but the shipment of flagstones is two days late Usingdependencies you can delay the path-paving task in a couple of clicks and Project KickStart Proautomatically updates the schedule for the remaining tasks

Although dependencies meet your advanced scheduling needs the Project KickStart Pro approach todependencies keeps them as simple as possible If you want to link a couple of tasks which are dependenton one another you can simply highlight the tasks and click the link icon

If you select the option of Autolinking tasks then when you display the Gantt chart the first time all tasksare pre-linked allowing you to adjust durations schedules of individual tasks and time between taskswhich is called Lead Time in Project KickStart Pro

Unlike other project management programs such as Microsoft Project Project KickStart Pro does notburden you with complicated error messages and various types of dependencies It provides only one typeof dependency finish-to-start which is the most common type This means you can fine-tune your scheduleas soon as you open the Gantt chartmdashwithout having to learn technical terms or advanced projectmanagement techniques

The Project Coordination functionality that we are providing is through GoToMeeting and is a chargedservice

Note

These features are in addition to those listed on the Whatrsquos New in Project KickStart 5 page

-o-

13

copy Experience In Software Inc 1995 - 2006

Compatibility with earlier versions

Project KickStart 5 can open and save projects in Project KickStart 4 prx file format (Same as ProjectKickStart 5)

Project KickStart 5 can open and convert projects saved in Project KickStart 3 prj file format You need tohave a licensed copy of Project KickStart 3 on your system to make the conversion

To open a prj project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click prj file type3 Navigate to the folder that contains the prj file Generally prj files are stored in cprogram filesProject

KickStart 34 Double-click the name of the file

Tips

The tasks in the converted Project KickStart 5 file will have the same start and finish dates and samedurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way (ie as working days) To have weekends as non working days click the Change WorkingSchedule button on the Gantt chart toolbar and mark weekends as non working

Note

Project KickStart 5 does not open and convert prj files from Project KickStart 1 or 2

-o-

14

copy Experience In Software Inc 1995 - 2006

Activating trial version

You may have obtained a FREE 20-day trial version of Project KickStart 5 from our website or from areseller

To convert your Trial Version to a Full Version youll need to purchase a License Key and to activate thesoftware

To activate Project KickStart 5 trial1 Start the Project KickStart trial

2 If you have not purchased your License Key yet click the Buy button to purchase online3 If you have purchased a License Key click the Activate button and copy and paste the License Key

that you received when you purchased Project KickStart as well as your name and email

15

copy Experience In Software Inc 1995 - 2006

4 You must be connected to the Internet and you must tell your Firewall to allow communication forPKS5Kickstartexe

Tip

Your License Key allows 2 activations per user One is for your primary computer and one is for asecond computer you use such as your laptop or home computer

-o-

16

copy Experience In Software Inc 1995 - 2006

Licenses and Support

End User License Agreement

EXPERIENCE IN SOFTWARE INC END USER LICENSE AGREEMENT AND WARRANTYDISCLAIMER

PROJECT KICKSTARTtrade STANDARD 5 AND PRO 5 EDITIONS

NOTICE This is a legally binding contract between you the end user and EXPERIENCE IN SOFTWAREINC

EXPERIENCE IN SOFTWARE INC (EIS or LICENSOR) LICENSES THE ENCLOSED SOFTWARETO YOU (USER or LICENSEE) ONLY UPON THE CONDITION THAT YOU ACCEPT ALL OF THETERMS CONTAINED IN THIS LICENSE AGREEMENT PLEASE READ THE TERMS CAREFULLY BYOPENING THIS PACKAGE BREAKING THE SEAL CLICKING ON THE ldquoAGREErdquo OR ldquoYESrdquo BUTTONOR OTHERWISE INDICATING ASSENT ELECTRONICALLY OR LOADING THE SOFTWARE YOUAGREE TO THE TERMS AND CONDITIONS OF THIS AGREEMENT IF YOU DO NOT AGREE TOTHESE TERMS AND CONDITIONS CLICK ON THE ldquoI DO NOT AGREErdquo ldquoNOrdquo BUTTON OR MAKE NOFURTHER USE OF THE SOFTWARE IF YOU DO NOT AGREE TO THESE TERMS THEN EIS ISUN-WILLING TO LICENSE THE SOFTWARE TO YOU IN WHICH EVENT YOU SHOULD RETURN THEFULL PURCHASED PRODUCT WITH PROOF OF PURCHASE TO LICENSOR OR THE DEALER FROMWHOM IT WAS ACQUIRED WITHIN 15 DAYS OF PURCHASE AND YOUR MONEY WILL BEREFUNDED

LICENSE AND WARRANTY

The software that accompanies this license (Software) is the property of EIS and is protected by copyrightand other intellectual property law Although EIS at all times owns the Software you will have certain rightsto use the Software after your acceptance of this license Except as may be modified by an addendumwhich may accompany or be added to this license your rights and obligations with respect to the use of thisSoftware are as follows

You may

(i) install and use one copy of the specified edition of Software and documentation on a single computerand only by one user (ldquoPrimary Userrdquo) If you have purchased multiple licenses for the Software asindicated as Quantity or Number of Licenses on the Invoice or electronic confirmation issued by EIS orits Resellers then at any time you may have as many copies of the Software in use as you have licenses The Software is ldquoin userdquo on a computer when it is loaded into the temporary memory (ie RAM) or installedinto the permanent memory (eg hard disk CD-ROM or other storage device) of that computer

(ii) install and use a second copy of the Software on a second computer for the limited and exclusive use ofthe Primary User

(iii) use the Software on a network provided that Licensee has a licensed copy of the Software for eachnamed user that can access the Software over that network

(iv) make one copy of the Software for archival purposes or copy the Software onto the hard disk of yourcomputer and retain the original for archival purposes

(v) after written notice to EIS transfer the Software on a permanent basis to another person or entityprovided that you retain no copies of the Software and the transferee agrees to the terms of this agreement

You may not

(i) rent lease copy distribute license or otherwise transfer the Software or its documentation to any otherparty Licensee may make a reasonable number of back-up copies for archival purposes only TheSoftware contains copyrighted material trade secrets and other proprietary material If Licensee has theright to duplicate the Software for multiple Users then Licensee must reproduce on all such copies of theSoftware the copyright notices and any other proprietary legends that were on the original copy of theSoftware or

(ii) decompile reverse engineer disassemble translate make any attempt to discover the source code ofthe Software or otherwise reduce the Software to a human perceivable form or modify network or create

17

copy Experience In Software Inc 1995 - 2006

derivative works based upon the Software or the documentation in whole or in part nor permit any otherparty to do so

Notwithstanding anything herein if the Software is lawfully acquired outside of the United States within ajurisdiction which is a member of the European Union subject to the EEC Council Directive 91250EEC ofMay 14 1991 Licensee agrees that within that jurisdiction it shall not and shall not allow any party onLicensees behalf to attempt to reverse engineer or decompile the Software into another computerlanguage except as expressly and specifically provided in the EEC Council Directive 91250EEC of May14 1991 Any and all information obtained during such lawful reverse engineering andor decompilingactivities including but not limited to the organization logic algorithms and processes of the Softwareshall be deemed to be the confidential and proprietary information of EIS

Licensee shall not make copies of the copyrighted Software documentation without the prior writtenpermission of EIS provided that for electronic transactions Licensee may make one (1) hard copy of suchdocumentation for each User

Intellectual Property and Duplication of Software

The Software contains copyrighted material trade secrets and other proprietary material If Licensee hasthe right to duplicate the Software for multiple Users then Licensee must reproduce on all such copies ofthe Software the copyright notices and any other proprietary legends that were on the original copy of theSoftware

Upgrades

To use a Product identified as an upgrade you must first be licensed for the product identified by EIS aseligible for the upgrade After upgrading you may no longer transfer the product that formed the basis foryour upgrade eligibility to another person or entity

Technical Support

Licensee must register the Software in order to be eligible for free technical support (including installationand registration of the product) during the first 90 days after purchase

Thirty Day Money Back Guarantee

If you are the original Licensee of this copy of the Software and are dissatisfied with it for any reason youmay return the complete product together with your receipt to EIS or an authorized dealer postageprepaid for a full refund at any time during the thirty-day period following the delivery to you of thePurchased Software

Export Law Assurances

You are responsible for complying with all trade regulations and laws both foreign and domestic Youacknowledge that none of the Software or underlying information or technology may be downloaded orotherwise exported or re-exported (i) into Afghanistan (Taliban-controlled areas) Cuba Iran Iraq LibyaNorth Korea Serbia (except Kosovo) Sudan and Syria or any other country subject to a US embargo or(ii) to anyone on the US Treasury Departments list of Specially Designated Nationals or the USCommerce Departments Denied Parties List or Entity List By using the Software you are agreeing to theforegoing and are representing and warranting that (i) no US federal agency has suspended revoked ordenied you export privileges (ii) you are not located in or under the control of a national or resident of anysuch country or on any such list and (iii) you will not export or re-export the Software to any prohibitedcounty or to any prohibited person entity or end-user as specified by US export controls as defined byEAR 15 CFR Parts 730-774 and BXA (httpwwwbxadocgov)

Data Collection and Privacy Policy

You acknowledge and agree that EIS may collect and retain information about you such as your nameaddress and e-mail address You also understand that EIS may employ other companies to performfunctions on our behalf such as fulfilling orders delivering packages sending postal mail and e-mailproviding marketing assistance and processing credit card payments These companies may have accessto personal information needed to perform their functions and may not use such information for otherpurposes By assenting to this agreement you agree that you have read and understand our Privacy PolicyFor more detailed information httpwwwprojectkickstartcomhtmlprivacy_statementhtm

Termination

This License is effective until terminated Licensee may terminate this License at any time by destroying allcopies of the Software and its documentation This License will terminate immediately without notice from

18

copy Experience In Software Inc 1995 - 2006

EIS if Licensee fails to comply with any provision of this License Upon termination Licensee must destroyall copies of the Software and its documentation and cease and desist from any further use of the Software

Limited Warranty

EIS warrants that the media on which the Software is distributed will be free from defects and that theSoftware shall perform substantially as described in its documentation for a period of sixty (60) days frompurchase Your sole remedy in the event of a breach of this warranty will be that EIS will replace anydefective media returned to EIS within the warranty period EIS does not warrant that the Software willmeet your requirements or that operation of the Software will be uninterrupted or that the Software will beerror-free

THE ABOVE WARRANTY IS EXCLUSIVE AND IN LIEU OF ALL OTHER WARRANTIES WHETHEREXPRESS OR IMPLIED INCLUDING THE IMPLIED WARRANTIES OF MERCHANTABILITY FITNESSFOR A PARTICULAR PURPOSE AND NONINFRINGEMENT OF INTELLECTUAL PROPERTY RIGHTSTHIS WARRANTY GIVES YOU SPECIFIC LEGAL RIGHTS YOU MAY HAVE OTHER RIGHTS WHICHVARY FROM STATE TO STATE AND COUNTRY TO COUNTRY

Disclaimer of Damages

REGARDLESS OF WHETHER ANY REMEDY SET FORTH HEREIN FAILS OF ITS ESSENTIALPURPOSE IN NO EVENT WILL EIS OR ITS RESELLERS BE LIABLE TO YOU FOR ANY SPECIALCONSEQUENTIAL INDIRECT OR SIMILAR DAMAGES INCLUDING BUT NOT LIMITED TO ANY LOSTPROFITS OR LOST DATA ARISING OUT OF THE USE OR INABILITY TO USE THE SOFTWARE EVENIF EIS HAS BEEN ADVISED OF THE POSSIBILTIY OF SUCH DAMAGES SOME STATES DO NOTALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FOR INCIDENTAL OR CONSEQUENTIALDAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAY NOT APPLY TO YOU IN NO CASESHALL EISS ITrsquoS RESELLERrsquoS LIABILITY EXCEED THE PURCHASE PRICE FOR THE SOFTWARE

SOME STATES AND COUNTRIES INCLUDING MEMBER COUNTRIES OF THE EUROPEANECONOMIC AREA DO NOT ALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FORINCIDENTAL OR CONSEQUENTIAL DAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAYNOT APPLY TO YOU

The disclaimers and limitations set forth above will apply regardless of whether you accept the Software

US Government Restricted Rights

DISTRIBUTION TO THE US GOVERNMENT This Software is commercial software developedexclusively at private expense This Software and the documentation are provided with RESTRICTEDRIGHTS applicable to private and public licenses alike Use duplication or disclosure by civilian agenciesof the US Government shall be in accordance with the Commercial Computer Software-Restricted Rightsclause at FAR 52227-19 Use duplication or disclosure by Department of Defense agencies is subjectsolely to the terms of this software licensing agreement pursuant to DFARS 2277202Contractormanufacturer of the Software is EXPERIENCE IN SOFTWARE INC 2029 Durant AveBerkeley CA 94704 USA

General

This Agreement shall be governed by the laws of the State of California without giving effect to principles ofconflict of laws You hereby consent to the exclusive jurisdiction and venue of the state courts sitting in SanFrancisco County California or the federal courts in the Northern District of California to resolve anydisputes arising under this Agreement This Agreement contains the complete understanding between theparties with respect to the subject matter hereof and supersedes all prior or contemporaneous Agreementsor understandings whether oral or written You agree that any varying or additional terms contained in anypurchase order or other written notification or document issued by you in relation to the Software licensedhereunder shall be of no effect No provision hereof shall be deemed waived or modified except in writing No EIS dealer agent or employee is authorized to make any amendment to this Agreement

The intellectual property protections the disclaimers of warranties and the limitation of damages shallsurvive termination The failure or delay of EIS to exercise any of its rights under this Agreement or uponany breach of this Agreement shall not be deemed a waiver of those rights or of the breach If any provisionof this Agreement is held invalid the remainder of this Agreement will remain in full force and effect

Should you have any questions concerning this Agreement or if you desire to contact EIS for any reasonplease write to EXPERIENCE IN SOFTWARE INC 2029 Durant Ave Berkeley CA 94704 USA

-o-

19

copy Experience In Software Inc 1995 - 2006

20

copy Experience In Software Inc 1995 - 2006

Customer Support

When you need help in solving a problem with the software Experience In Software is available to assistyou First check this help file for information on the part of the program you are having a problem withAlso take a look at the Web site for late-breaking technical support information wwwprojectkickstartcomsupporttechnical_supportcfm If you are a regustered user you can obtain support in the following ways

Web httpwwwprojectkickstartcomsupportemail_supportcfm E-mail supportprojectkickstartcom

Hours 900 am to 500 pm Pacific time Monday - Friday

To make the support process more efficient have the following information ready for the support staff

Provide your name phone number and email address

Describe the problem including any error messages

If reporting a potential bug describe what you did immediately before seeing the bug

Provide the Project KickStart version number and Build Date (Click Help on the menu bar and thenclick About Project KickStart)

Identify the version of Windows (Windows Vista etc) you are using

Notes

Our policy is to respond to support email within two business days If you have not received aresponse please double check that spam filters are blocking our messages to you If you maintain anincoming whitelist please allow all messages from the projectkickstartcom domain

Support is available in English only If you purchased a translated version please contact your localreseller for help in other languages

See Also

Reporting Technical Issues

-o-

21

copy Experience In Software Inc 1995 - 2006

Reporting Technical Issues

If Project KickStart 5 detects an error it will write a log of technical issues and then create a temporarymenu to the right of the Help menu which says Send Log to Technical Support You should immediatelyclick the menu and then click Yes to send the error log to us

Please fill in your email address so that we can get back to you with any questions about what caused theerror

Tip

If you have an Internet Security Program such as Norton Internet Security please allowPKS5Kickstartexe to communicate with the Internet to report the error

-o-

22

copy Experience In Software Inc 1995 - 2006

Register Project KickStart

To print this page click the Print button on the Help window toolbar

Register Project KickStart 5 for technical support upgrade information and software discounts You canregister by completing printing and then sending or faxing this form to Experience In Software You canalso register online at httpwwwprojectkickstartcomsupportregiscfm

Name _______________________________________________________

Title _______________________________________________________

Company _______________________________________________________

Address _______________________________________________________

CityStateZip ______________________________________________________

Country _______________________________________________________

Day Phone _______________________________________________________

Fax _______________________________________________________

E-mail _______________________________________________________

Purchased from __ Experience In Software __ Other ____________________

Number of people in company _ 1 to 25 _ 26 to 100 _ 101 to 1000 _ Over 1000

Which industry do you work in ______________________________________

Interested in a project management workshop for your company __ Yes __ No

Comments _______________________________________________________

_________________________________________________________________

_________________________________________________________________

Experience In Software 2029 Durant Ave Berkeley CA 94704

Send or FAX to (510) 644-3823

-o-

23

copy Experience In Software Inc 1995 - 2006

Planning Projects

Name Your Project

Before you start thinking about the tasks in your project yoursquoll want to give your project an appropriate titleIf you open an existing project you might want to edit or change the name of your project

To name your project1 In the Type a name for your project text box enter a name2 Click the Next button

Tips

You can enter up to 58 characters and more than one

Use short descriptive project names such as ldquoCompany Web Siterdquo

Avoid vague project names such as ldquoDatabase Projectrdquo or ldquoCDP-7rdquo especially if you plan to circulatereports to others

Enter your project title using uppercase letters if you want the title to stand out in reports

One way to reuse your projects is to open an existing project and then change its name in this stepAfter saving the project with a different name you can modify details to customize the project

See Also

Use the Planning Wizard

-o-

24

copy Experience In Software Inc 1995 - 2006

Phases - Step 1 of 2

After naming your project the next step in the Planning Wizard is to identify the major activities in yourproject Using phases helps organize tasks so that an obviously early task such as ldquoOrganize materialsrdquoappears before a later task such as ldquoReview final draftrdquo

To enter phases1 Type each phase one per line

OrClick the Phases Library button The Phases Library contains typical phases that many organizationsuse in the early middle and late stages of their projects Drag an entry from the Phases Library to thelist and then click the OK button to close the Phases Library

2 To insert a phase in the middle of the phases list click where you want to insert a new blank line andthen press the Insert keyTo edit the phase text double-click the phase

Tips

Start each phase name with an action verb as in ldquoBuild systemrdquo or ldquoWrite reportrdquo

Use actions that have clearly defined beginnings middles and ends For example you can scheduletasks like ldquoTest prototyperdquo more easily than tasks like ldquoPurchase high-quality partsrdquo

Note

Youll have the opportunity to edit phases later in the Tasks step For now continue planning thephases in your project

See Also

Use the Planning Wizard

Use a Library

Move Tasks within the Task List

-o-

25

copy Experience In Software Inc 1995 - 2006

Phases - Step 2 of 2

For each phase list all of the tasks that could be performed during that phase You can refine and organizethe tasks later in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each phase1 Type the tasks associated with the phase displayed in the Tasks for phase text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next phase in your project click the Next button If you prefer to work out oforder click the Tasks for phase list arrow and then click the phase you want

3 When you are finished entering tasks for the last phase in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

26

copy Experience In Software Inc 1995 - 2006

Goals - Step 1 of 3

Enter the goals for your project the objectives you hope to accomplish Then you can brainstorm anyadditional tasks that will help you meet these goals

To enter goals1 Type each goal one per line

OrThe Goals Library contains typical sample goals that you can customize Drag an entry from the GoalsLibrary to the list and then click the OK button to close the Goals Library

2 To insert a goal in the middle of the goals list click where you want to insert a new blank line and thenpress the Insert keyTo edit the goal text double-click the goal

3 Click the Next button

Tips

List goals that apply to the entire project such as Develop a high-quality system A goal such as Getthe contract signed applies only to an early phase

Write goals as actions you can measure For example Complete the project for $75000 or less ismore concrete and specific than Complete the project within budget Numbers make goal statementsreal

If youre not sure how to measure a goal use a range as in About 15 - 25 people will use the results ofthe project

See Also

Use the Planning Wizard

Use a Library

-o-

27

copy Experience In Software Inc 1995 - 2006

Goals - Step 2 of 3

For each goal list any new tasks needed to accomplish that goal You can refine and organize the taskslater in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each goal1 Type the tasks for accomplishing the goal displayed in the For the goal text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next goal in your project click the Next button If you prefer to work out of orderclick the For the goal list arrow and then click the goal you want

3 When you are finished entering tasks for the last goal in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

28

copy Experience In Software Inc 1995 - 2006

Goals - Step 3 of 3

After you identify new tasks for your project assign each new task to an appropriate phase

To assign new tasks to phases1 Click a task in the New tasks to achieve goals list (on the left)2 Click one or more phases in the Assign them to Phases list (on the right) to which the task belongs A

checkmark appears next to tasks youve assigned

If a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Note

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

29

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 1 of 2

Projects often have tasks in common The Similar Projects step makes it easy for you to borrow tasks fromother projects and add them to your current project

By default this step shows the Project KickStart (PRX) projects stored in the same folder as the currentproject including sample projects and those you already created

To select similar projects1 Review the projects in the list To sort the project names alphabetically click the Project Name header

Click the Project Name header again to sort the names in reverse order2 Click one or more projects in the list that contain tasks you want to use in the current project A

checkmark appears next to the projects you selected3 To list projects stored in a different folder on your system click the Browse button and then navigate to

the folder you want4 Click the Next button

If no projects seem related to your current project skip this step for now

Tips

The Similar Projects step becomes more helpful the more you use Project KickStart Every time yousave a project it becomes available for future use

Many projects share the same phases and tasks such as those for setting up a contract or purchasingequipment You can use Project KickStart to create these mini-projects or templates and then importtheir tasks into a new project during the Similar Projects step

-o-

30

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 2 of 2

After you select one or more projects containing tasks you might want to use assign those borrowed tasksto a phase in this project

To assign borrowed tasks to phases1 Click a task in the list on the left If a task includes subtasks click the plus icon to expand the list Click

the minus icon if you want to hide the subtasks To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more phases in the Assign tasks to phase(s) of your project list (on the right) to whichthe task belongs A checkmark appears next to tasks youve assigned

3 To assign one or more tasks to a new phase select the tasks click ltNew Phasegt in the Assign tasksto Phases of your project list and then type a name for the new phase

4 To select tasks from another project you selected as similar click the Tasks from Similar Projects listarrow click the project you want and then assign the tasks to phases

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also Edit Tasks

-o-

31

copy Experience In Software Inc 1995 - 2006

People - Step 1 of 3

Enter the names or descriptions of the people involved in your project Include key decision makers suchas executives or customers who must approve or consult with you about the project These are yourprojects resources In the next People step youll identify new tasks associated with these resources

To enter people1 Type each name or description one per line

OrIf you have stored information about people and other resources in the People Library click the PeopleLibrary button drag an entry from the library to the list and then click the OK button to close thePeople Library

2 To edit the people text double-click the name or description3 Click the Next button

Tips

Be consistent with the resource names in your projects For instance avoid using Richard in oneproject and Dick in another project when referring to the same person

Include names for people teams (such as Quality control team) departments (such as Manufacturing)companies (such as Acme Widgets Corp) or even equipment (such as wheat thrasher)

Note

Add people and other resource information to the People Library so that you can quickly drag resourcesfrom the library to any project You can even import people from your Outlook and ACT address books

See Also

Manage the People Library

Import ACT Contacts and Users to the People Library

-o-

32

copy Experience In Software Inc 1995 - 2006

People - Step 2 of 3

Now that you have defined the people needed to complete your project list any new tasks that eachresource might suggest or require

To enter new tasks for each person1 Type the new tasks associated with the person displayed in the Tasks For text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next person in your project click the Next button If you prefer to work out oforder click the Tasks For list arrow and then click the person you want

3 When you are finished entering new tasks for the last person in your project click the Next button tocontinue in the Planning Wizard

Tips

This step provides a good opportunity to get input from your resources directly and make sure theproject plan reflects the views of everyone on the team

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo Write the tasks roughly in the order that you will complete them You can reorganize the tasks later in

the Tasks step

Note

You assign people to tasks in the Assign Tasks and Schedule steps

See Also

Use a Library

Move Tasks within the Task List

Assign Tasks to People

-o-

33

copy Experience In Software Inc 1995 - 2006

People - Step 3 of 3

After you identify new tasks associated with the people in your project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by people list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

34

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 1 of 3

Every project has obstacles and risks that can affect its success List the major obstacles you face incompleting your project Then you can brainstorm any additional tasks that can help you overcome orminimize these problems

To enter obstacles1 Type each obstacle one per line

OrThe Obstacles Library contains typical sample obstacles that you can customize Drag an entry fromthe Obstacles Library to the list and then click the OK button to close the Obstacles Library

2 To insert an obstacle in the middle of the obstacles list click where you want to insert a new blank lineand then press the Insert key

3 To edit the obstacle text double-click the obstacle4 Click the Next button

Tips

Be creative when thinking of obstacles Highly imaginative obstacles can suggest realistic tasks Forexample Project manager kidnapped by aliens can lead to Project manager out of town forconference In Obstacles step 2 of 3 you can add the realistic activities as tasks You can delete theunrealistic obstacles later by returning to Obstacles step 1 of 3

Avoid listing too many obstacles even if they are realistic Hard core pessimists find it hard to getanything done

Edit and update the Obstacles Library so that you can quickly drag obstacles from the library to anyproject in your organization

See Also

Use a Library

-o-

35

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 2 of 3

After identifying the obstacles to completing your project determine how you can avoid these stumblingblocks List any new tasks you need to overcome or avoid each obstacle In this way you are developing acontingency plan for your project

To enter new tasks for each obstacle1 Type the new tasks associated with the obstacle displayed in the Obstacle text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next obstacle in your project click the Next button If you prefer to work outof order click the Obstacle list arrow and then click the obstacle you want

3 When you are finished entering new tasks for the last obstacle in your project click the Next button tocontinue in the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

You can reorganize the tasks and add notes later in the Tasks step

See Also

Use a Library

Move Tasks within the Task List

Add Task Notes and Attachments

-o-

36

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 3 of 3

After you identify new tasks for overcoming the obstacles to completing project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by obstacles list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

3 Click the Next button

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

37

copy Experience In Software Inc 1995 - 2006

Assigning People

Assign Tasks to People

After youve identified people working on your project you can assign tasks to each person or otherresource

To assign tasks to people1 Click a phase or task in the For each phase or tasks list (on the left)

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more people in the Assign some people list (on the right) who will perform the task Acheckmark appears next to tasks youve assigned

3 To assign a selected task to all of the people in your project click the All button4 To assign one or more tasks to a new person select the tasks click ltNew Persongt in the Assign

some people list and then type a name for the new person

To unassign a task

To unassign a task click the task and then click the highlighted person from which you want to removethe task You can assign that task to a different person if necessary You can also click the All buttonto remove a task from all of its assignments at the same time

Tip

Some users like to skip to the Tasks step before performing the Assign step That way they can edittheir list of tasks before assigning people and resources This helps them focus the project and givesthem a clearer idea of what must be done before committing resources

Notes

You can also assign tasks to people in the Tasks step and the Schedule step

You can assign tasks to non-personnel resources such as equipment (a CAD system or back hoe)facilities (a classroom or hotel) services (lab work or insurance) or materials (lumber or officesupplies) just as you assign tasks to people Click ltNew Persongt to add a new resource to the list

See Also

Remove People from a Task

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

38

copy Experience In Software Inc 1995 - 2006

Remove People from a Task

After assigning tasks you might need to remove people from a task or unassign them

To remove people from a task (unassigning)1 Click a phase or task in the For each phase or tasks list (on the left)

The people assigned to that phase or task are highlighted in the Assign some people list (on theright)

2 Click a highlighted person to remove or unassign that person from the taskWhen the person is no longer highlighted they are not assigned to the selected task

See Also

Assign Tasks to People

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

39

copy Experience In Software Inc 1995 - 2006

Add a New Person or Resource

If you realize that you want to assign some tasks to a person not included in the Assign some people listyou can add that person and assign tasks in the same step You can also add non-personnel resourcessuch as such as equipment (a CAD system or back hoe) facilities (a classroom or hotel) services (lab workor insurance) or materials (lumber or office supplies)

To add a new person or resource1 Select one or more phases or tasks in the For each phase or tasks list (on the left) 2 Click ltNew Persongt in the Assign some people list and then type a name for the new person or

resourceThis adds the new person or resource to the list and assigns the selected tasks to them

See Also

Assign Tasks to People

Remove People from a Task

Edit or Substitute People

Add or Change Task Assignments

-o-

40

copy Experience In Software Inc 1995 - 2006

Edit or Substitute People

If the people or resources in your project change you can replace them or edit their names anddescriptions

To edit or substitute people1 Click the People icon

You return to People step 1 of 32 In the list of people defined for the project double-click the person you want to edit or replace or click

the name and press F23 Edit the name or description of the person

When you return to the Assign step the name of the person appears as you changed it

See Also

Assign Tasks to People

Remove People from a Task

Add a New Person or Resource

Add or Change Task Assignments

-o-

41

copy Experience In Software Inc 1995 - 2006

Organizing the Project Plan

About Organizing Tasks

In the Tasks step you work with an outline of your project plan Here you can easily edit and reorganizetasks spell check and even add notes and attachmentsClick the following illustration to see tips for using this window

Edit the Task List to Consolidate and delete tasks Add subtasks Add or change task assignments Add follow-up notes to tasks Add or change attachments Review the order of the tasks in each phase and move tasks up or down so that they progress

sequentially Review task descriptions to make sure they are clear and that all the team members will understand

them Convert vague tasks such as reminders and open issues to task notes

Notes

Some users like to revise their Task List before they assign resources You can go to the Task List atany time while you are using Project KickStart

Each project created with Project KickStart can contain up to 1000 tasks

See Also

Change the Appearance of the Task List

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

Add Task Notes and Attachments

Add or Change Task Assignments

Add or Change Task Details

-o-

42

copy Experience In Software Inc 1995 - 2006

43

copy Experience In Software Inc 1995 - 2006

Change the Appearance of the Task List

You can change the appearance of the Task List so you can work with it more effectively

To add a column

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task ListBy default the Task List shows the Task Name Assignments and Notes columns You can also showCost and Done columns

To hide a column

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

To move a column

Drag a column heading to a new position in the Task List

To change the column width

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Show or Hide Tasks in the Task List

-o-

44

copy Experience In Software Inc 1995 - 2006

Show or Hide Tasks in the Task List

To hide tasks or subtasks

To hide the subtasks for a task click the minus icon next to the task

To hide all the tasks in the Task List and show only phases click all the minus icons next to thephases

To show tasks or subtasks

To show the subtasks for a task click the plus icon next to the task

To show the tasks for a phase click the plus icon next to the phase

See Also

Change the Appearance of the Task List

-o-

45

copy Experience In Software Inc 1995 - 2006

Move Tasks within the Task List

In the Tasks step you can reorganize the tasks in your project so that they better represent the work youand your team plan to do In particular you should review the order of the tasks in each phase and move tasks up and down so thattasks follow in a sequential order Use the Up and Down Arrow buttons to move the tasks

To reorder tasks1 Click a task or phase to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youmove must be next to each other

2 Click the Up Arrow button to move a task up one rowOrClick the Down Arrow button to move a task down one row

Note

When you move a bolded phase you move the phase and all of its tasks at the same time

See Also

Outdent and Indent Tasks

-o-

46

copy Experience In Software Inc 1995 - 2006

Outdent and Indent Tasks

Subtasks are smaller parts of tasks Use subtasks when you need to break tasks down into moremanageable parts In the Task List you can turn a task into a subtask by indenting it You can also add anew subtask to the Task ListIf your Task List contains subtasks you can turn a subtask into a task by outdenting itUse the Outdent and Indent buttons to promote (outdent) and demote (indent) tasks

To promote and demote tasks1 Click a phase task or subtask to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youpromote or demote must be next to each other

2 Click the Outdent button to promote the selected tasksOrClick the Indent button to demote the selected tasksYou can also right-click an item in the Task List and then click Outdent or Indent on the shortcut menu

Tips

When you promote (outdent) a task it becomes a phase and its subtasks become tasks When youpromote a subtask it becomes a task

When you demote (indent) a phase it becomes a task and its tasks become subtasks When youdemote a task it becomes a subtask

Notes

You can have up to 10 levels of subtasks in your project

Use Task Notes instead of subtasks for task comments or additions that are not actually work items

See Also

Move Tasks with the Task List

Add a Task or Subtask

-o-

47

copy Experience In Software Inc 1995 - 2006

Add a Task or Subtask

If you realize you want to add another task to the Task List use the Add Task button A subtask is a smaller part of a task Use subtasks when you need to break tasks down into moremanageable partsTo add a subtask use the Add Subtask button

To add a task1 Click a task and then click the Add Task button right-click a task and then click Add Task on the

shortcut menu or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskProject KickStart numbers the new task in the proper sequence

To add a subtask1 Click a task and then click the Add Subtask button right-click a task and then click Add Task on the

shortcut menu or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtask3 Project KickStart numbers the new subtask in the proper sequenceNote

To add a new phase click a phase and then click the Add Task button

See Also

Outdent and Indent Tasks

-o-

48

copy Experience In Software Inc 1995 - 2006

Edit Tasks

Edit tasks in the Task List to fine tune your project You can edit the names of the phases tasks andsubtasks delete tasks and cut copy and paste task information

To edit task names1 Click the phase task or subtask you want to edit and then press the F2 key2 Type to edit the text3 To undo an edit click the Undo button

To delete a task

Click the task you want to delete and then press the Delete key or click the Delete button Or

Right-click a task and then click Delete Row on the shortcut menu

To cut copy and paste tasks1 Select the tasks you want to cut or copy Use Shift-click or Ctrl-click to select more than one task

2 Click the Cut button (Ctrl-X) or click the Copy button (Ctrl-C )

3 Click where you want to insert the tasks and then click the Paste button (Ctrl-V)

Tip

If your project includes some of the same tasks repeated in different phases save time by copying rowsof tasks and pasting them to another phase

Notes

You can also edit task names using the Task Information dialog box To open this dialog boxdouble-click a task or click a task and then click the Edit Task Information button

If you delete a phase you also delete its tasks and subtasks If you delete a task you also delete itssubtasks Project KickStart warns you before deleting tasks or subtasks and gives you a chance tocancel the deletion

See Also

Add Task Notes and Attachments

Add or Change Task Assignments

-o-

49

copy Experience In Software Inc 1995 - 2006

Add Task Notes and Attachments

You might find that some of your tasks are actually more notes than tasks For example Remember tocheck Daves specifications might work better as a note than a task especially if it could take several daysto catch up with Dave but only a few minutes to review his specs By using notes you clarify your projectand increase your chances for success An attachment is a document graphic or any other type of file related to a task For example to a tasksuch as Review proposal you can attach the proposal document Or you can attach a hyperlink to a pageon a web site

To add a note or attachment to a task1 Double-click the Notes column next to the task The Task Information dialog box opens to the Notes

and Attachments tab2 In the Enter a Note box type in or edit the task note (Press Enter to insert line break)3 To attach a file click the Add Files button In the Select File to Attach dialog box navigate to the file

you want and then click the Open button The filename appears in the Add Attachments box with apaperclip icon

4 To insert a hyperlink click the Add URL button In the Insert Hyperlink dialog box type in the URL youwould like to link to The URL appears in the Add Attachments box with a paperclip icon

5 Click the OK button

To open or remove an attachment1 Open the Notes and Attachments tab in the Task Information dialog box2 To open an attachment double-click the filename in the Add Attachments box3 To delete an attachment click the attachment in the Add Attachments box and then click the Remove

button

To change a task into a task note1 Copy (Ctrl-C) the text of the task you want to change into a note2 Double-click the task to which you want to add the note3 In the Task Information dialog box click the Notes and Attachments tab and add paste the text in the

Enter a Note box Close the Task Information dialog box4 In the Task Name column delete the original task that how appears as a note for a different task

Tips

Use notes to keep track of the operational details of a project the little nagging details that are criticalto success

Although the Task List provides plenty of room for notes it is best to keep your notes concise

Some tasks might benefit from instructional notes those that explain what to do in a task or how tosuccessfully complete a task

You can also include a hyperlink in a note by typing httpxxx (where xxx is an e-mail or Web address)In Outlook Word Excel or your browser the hyperlink will be active You can click the link to godirectly to that site or to send an e-mail to that address

Note

You can also open the Notes and Attachments tab in the Task Information dialog box by clicking atask and then clicking the Edit Notes and Attachments button or by double-clicking a task to openthe Task Information dialog box and then clicking the Notes and Attachments tab

See Also

Edit Tasks

Add or Change Task Assignments

Change Task Details in the Gantt chart

50

copy Experience In Software Inc 1995 - 2006

-o-

51

copy Experience In Software Inc 1995 - 2006

Add or Change Task Assignments

The Assignments column in the Task List shows the people and other resources assigned to each task

To add or change a task assignment1 Double-click the Assignments column next to the task The Task Information dialog box opens to the

Assignments tabThe Assignments tab lists all of the people and resources in your project If this task is already assignedto people they are highlighted on the Assignments tab

2 To assign this task to another person or resource click the resource name in the Assignments list3 To remove (unassign) this task from a person or resource click a highlighted name in the Assignments

list4 To add a person and assign the task at the same time click ltNew Persongt in the Assignments list

and then enter the name of the new person5 Click the OK button

Note You can also open the Task Information dialog box by clicking a task and then clicking the Edit Task

Information button to or by double-clicking a task

-o-

52

copy Experience In Software Inc 1995 - 2006

Add or Change Task Details

Besides task names notes and assignments you can include cost and done details about tasks In theSchedule step you can also include start and finish dates and durations

To add task details

1 Click a task and then click the Edit Task Information button or double-click the task you wantThe Task Information dialog box opens

2 Enter Cost or Done informationCost Enter the cost associated with this task For example you could enter $150 as the cost for a tasknamed Purchase photo CD Done Click the list arrow to select 0 25 50 75 or 100 or enter the percentage you want such as33

3 Click the OK button

To show or hide task details

Right-click a column heading to open a shortcut menu and then click Cost or Done In the shortcutmenu a checkmark appears next to columns that are displayed in the Task List

To edit task details

Open the Task Information dialog box (click a task and then click the Edit Task Information button or double-click the task you want)

Or

Double-click the Cost or the Done entry to update these details directly in the Task List

Notes

The Cost amount appears with the currency symbol set for your system (in the Regional and LanguageOptions dialog box of the Windows Control Panel)

Project KickStart calculates the running totals for the tasks within a phase and displays this total in theCost column for the phase When you create and print Task reports the total costs for the entire projectappear at the end of the Cost column

See Also

Edit Tasks

Print Task Reports

-o-

53

copy Experience In Software Inc 1995 - 2006

Check Spelling

Spell check your tasks and notes before you print reports or export to other software

To check the spelling of tasks and notes

Click the Check Spelling button on the Project KickStart toolbarOr

Click Tools on the menu bar and then click Spelling

Notes

Spell checking updates entries on the Task List and the Gantt chart (the Schedule step) It can alsocheck the spelling of intermediate entries such as goals and tasks to accomplish goals if you spellcheck during those steps

Spell checking does not check the names of people on the People List or the contents of the PeopleLibrary

-o-

54

copy Experience In Software Inc 1995 - 2006

Scheduling Tasks in the Gantt Chart

55

copy Experience In Software Inc 1995 - 2006

Scheduling Overview

About Scheduling Tasks

In the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the other

You work with the Gantt chart using the familiar Task Data view in the left pane or the graphical Chart viewin the right pane To adjust the schedule to fit your project set the project start date in the toolbar moveand resize the taskbars in the Chart view or change the start and finish dates or durations of individualtasks in the Task Data view

Click the following illustration to see general tips for using the Gantt chart See About the Gantt Chart formore details

In the Schedule step you can

Change a start date for the project Set start and finish dates or durations for tasks Change the timescale of the schedule Change the working schedule to specify which days are nonworking days such as weekends and

holidays Fine-tune the organization of the phases tasks and subtasks Color-code tasks to identify assignments critical deadlines or other information at a glance Insert milestones to indicate events that mark a moment in time such as the approval of a design Review and edit task details including task name assignments notes and attachments Hide or show task data columns in the left pane Export project data to other software applications

Tip

56

copy Experience In Software Inc 1995 - 2006

To save time you can reuse projects such as one for a trade show and create an updated scheduleby changing the project start date in the Schedule step

See Also

About the Gantt Chart

Understand Task Data View

Understand Chart View

-o-

57

copy Experience In Software Inc 1995 - 2006

About the Gantt Chart

The Gantt chart provides two views of your project schedule The Task Data view in the left pane lists thesame task information as in the Tasks step but now includes durations and start and finish dates TheChart view in the right pane displays taskbars and symbols to represent the same information You canchange the schedule information by working directly in the Task Data view and Chart view or by using theGantt Chart toolbarClick the following illustration to see general tips for using this window

-o-

58

copy Experience In Software Inc 1995 - 2006

Autolink tasks (Pro Users)

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatProject KickStart Pro does not assume that you want to link all of the tasks in a serial manner (one after theother) when you get to the Gantt chart Indeed many users want that behavior and many do notTo accomodate both types of users you can set whether you want the program to Autolink tasks In theTools menu select Autolink tasks Thereafter in all your projects when you get to the Gantt chart for thefirst time the tasks will be linked in a serial mannor

-o-

59

copy Experience In Software Inc 1995 - 2006

About Linking Tasks

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatWhen you link tasks the Gantt chart shows additional information about the tasks Click the followingillustration to see general tips for using linked tasks

Task Data view Chart view Description

Predecessor tasksA predecessor task is onethat you must completebefore you can start thenext task For exampleTask 2 - Prepare soil isthe predecessor to Task3 - Plant shrubs becauseyou need to prepare thesoil before you can plantthe shrubs

Successor tasksWhen you finish onelinked task you can moveonto the next onemdashthesuccessor task Forexample the successorfor Task 2 ndash Prepare soilis Task 3 ndash Plant shrubsand the successor forTask 3 is Task 4 ndash MulchLink linesThe first task isscheduled for one dayand the second one forthe next day In additionthe link line and arrowshow that the first taskmust end before thesecond one can start

These linked tasks arescheduled for the sametime

60

copy Experience In Software Inc 1995 - 2006

These tasks which aredependent on earliertasks and the last twotasks are also scheduledfor the same time

See Also

About the Gantt Chart

Autolink tasks

Make tasks overlap

-o-

-o-

61

copy Experience In Software Inc 1995 - 2006

Change the Display of the Schedule

You can change the onscreen appearance of the schedule so you can work with it more effectively Thefollowing illustration shows the Schedule window with the Steps bar closed and only the task number taskname and duration displayed in the Task Data view This provides more room to display the Gantt chart

To show or hide the Step bar or Project KickStart toolbar

Click View on the menu bar and then click Steps Bar to show or hide the vertical Steps bar on the leftof the Project KickStart window

Click View on the menu bar and then click Tool Bar to show or hide the Project KickStart toolbarwhich appears just below the menu bar In the View menu a checkmark appears next to the items displayed in the Project KickStart window

To display more or less of the Task Data view or Chart view

Drag the splitter bar between the Task Data view and the Chart view

To change the timescale in the chart

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years

To add a column to the Task Data view

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task Data viewBy default the Task Data view shows the Info Task Name Days Start and Finish columns Youcan also show Done Cost and Assignments columns

To hide a column in the Task Data view

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

62

copy Experience In Software Inc 1995 - 2006

To change the column width in the Task Data view

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Understand Task Data View

Understand Chart View

-o-

63

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

-o-

64

copy Experience In Software Inc 1995 - 2006

65

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Some features in this topic are available only in Project KickStart Professional

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view In Project KickStart Professional you also use the Gantt chart toolbar to linkand unlink tasks

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysLink Tasks (Pro Users)Link the selected tasksUnlink Tasks (Pro Users)Unlink the selected tasksChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

See Also

Use the Gantt Chart Toolbar

-o-

66

copy Experience In Software Inc 1995 - 2006

Understand Task Data View

The following illustration shows all the columns of information you can display in Task Data view

The Task data columns are the same as in the Tasks step but also include date information

Row number

Info Shows an icon if a note attachment or both are associated with the task Double-click anicon to view or edit the associated information

Task Name Name of the phases tasks and subtasks Double-click a task name to edit it directly

Days The amount of time it takes to complete the task If you change the number of days for a taskProject KickStart changes the Finish date accordingly

Start Date this task starts Double-click a Start date and then click the list arrow to open a calendar andselect a different date This also changes the Finish date

Finish Date this task ends Double-click a Finish date and then click the list arrow to open a calendar andselect a different date This changes the task duration shown in the Days column

Done Percentage of the phase task or subtask completed Show progress for any task by entering apercent of up to 100

$ Cost Cost for each task summed in the appropriate phase row Reports include total costs for theproject when you select the Cost column in the Create and Print Task Reports dialog box or the Createand Print Gantt Chart Report dialog box The Cost appears with the currency symbol set for your system(in the Regional and Language Options dialog box of the Windows Control Panel)

Assignments People and other resources assigned to the task Double-click an assignment to open theTask Information dialog box to the Assignments tab where you can add and change assignments

Tip

A task with a duration of zero (0) days is a milestone See Create a Milestone for more information

Notes

By default Task Data view displays all the columns the Info Task Name Days Start and Finish Done Cost and Assignments columns Some of these columns might be hidden by the Gantt chartview To hide columns right-click a column heading to open a shortcut menu and then click the columnyou want to hide In the shortcut menu no checkmark appears next to columns that are hidden

To change the width of a column drag a splitter bar in the column heading row or double-click a splitterbar to have the column accommodate its longest entry

As in the Tasks step expand phases and tasks by clicking the plus icon and collapse phases andtasks by clicking the minus icon

See Also

67

copy Experience In Software Inc 1995 - 2006

Understand Chart View

Change Task Dates

-o-

68

copy Experience In Software Inc 1995 - 2006

Additional Features in Task Data View

These features are available only in Project KickStart Professional

In Project KickStart Pro you can view two columns of information in addition to the nine columns availablein the Project KickStart Standard These two additional columns are labeled Pred (for Predecessor) andSucc (for Successor) The following illustration shows a typical Task Data view with these additionalcolumns

Besides the nine columns of information shown in Task Data view in Project KickStart Standard you canalso show the following information in the Professional version

Pred Indicates which task is the predecessor to the current task Double-click a task number in the Predcolumn to change it

Succ Indicates which task is the successor to the current task Double-click a task number in the Succcolumn to change it

Notes

When you link tasks Project KickStart assigns predecessors and successors according to their order inthe Task Data view

When you move a linked task in the Task Data view the predecessor and successor do not changeFor example in the above illustration if you move Task 3 ndash Plan design so it becomes Task 2 itspredecessor remains Land survey and its successor remains Engineering You can change these bydouble-clicking the task number in the Pred or Succ column and then entering a new number

See Also

Understand Task Data View

-o-

69

copy Experience In Software Inc 1995 - 2006

Understand Chart View

The following illustration shows a daily schedule in Chart view Point to the illustration to display text thatdefines the chart elements

Summary bar Summarizes the tasks below it and extends from the earliest start date(where the first triangle in the summary bar appears) to the latest finish date (where the last triangleappears) If a phase has tasks the summary bar appears in the phase row to summarize the tasks If atask has subtasks the summary bar appears in the task row to summarize the subtasks

To reschedule a phase and all of its tasks (or a task and all of its subtasks) click the summary bar and dragit to the left or right until it spans your desired set of dates This changes the earliest start date and latestfinish date in that phase and keeps the same duration And all the tasks move with the change of thephase

Taskbar Shows the length and scheduled dates for a task To change the duration of a taskresize the taskbar click the taskbar and then drag its left edge to schedule a different start date or drag itsright edge to schedule a different finish date

To reschedule a task without changing the duration drag the taskbar to a different date in the chart

Taskbar with percent done If you enter a Done amount in the Task Data view a progress barin the taskbar indicates the amount of the task completed

Red vertical line Indicates todays date

Milestone Indicates a task with a zero duration Milestones mark an event that must be reflected inyour project plan such as the approval of a design or an assembly line startup You can drag the left edgeof a milestone icon to stretch it into a taskbar The milestone becomes a task with a start and finish date

Notes

Because a summary bar summarizes the tasks below it you cannot resize a summary bar

To scroll the schedule use the vertical and horizontal scroll bars or the green drag bar at the top of theChart view

The shaded days in the Chart view indicate nonworking days To set which days are working andnonworking see Specify Working Days

70

copy Experience In Software Inc 1995 - 2006

-o-

71

copy Experience In Software Inc 1995 - 2006

Additional Tools in Chart View

These features are available only in Project KickStart Professional

If you use Project KickStart Pro the Chart view displays lines and arrows to show linked tasks The linklines and arrows show the relationships dependencies between one linked task and another

Besides the summary bar taskbar and other information provided in Project KickStart Standard Chart viewin the Professional version also provides the following information

The first task is scheduled for one day and the second one for the next day In addition the link line andarrow show that the first task must end before the second one can start

These linked tasks are scheduled for the same time However the first task must end before the secondone can start

The first two tasks are scheduled for the same time and must be completed before the third task can start

These linked tasks are scheduled for the same time However the second task must end before the firstone can start

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

Understand Chart View

-o-

72

copy Experience In Software Inc 1995 - 2006

73

copy Experience In Software Inc 1995 - 2006

Change Task Dates

You can revise a project schedule by changing task dates in the Task Data view or the Chart view You canalso reschedule an entire project by changing the projects start date

To change the project start date1 Click the Project Start list arrow to open a calendar

The calendar highlights the selected date and outlines todays date2 Find the date you want using the left and right scroll arrows to view a different month and then click the

date

To change task dates in Task Data view1 Double-click the Start or Finish date for a task

2 Then edit the date (you can edit the day month or year) OrClick the list arrow to open a calendarThe calendar highlights the selected date and outlines todays date

3 Find the date you want using the left and right scroll arrows to view a different month and then click thedateProject KickStart changes the Start and Finish dates according to your selection updates the durationof the task in the Days column and adjusts the taskbar in the Chart view

To change task dates by changing the duration in Task Data view

Double-click the Days column for a task and then enter the number of days it will take to complete thetaskProject KickStart changes the Finish date of the task and adjusts the taskbar in the Chart view

To change task dates in Chart view

Resize a taskbar click the taskbar and then drag its left edge to schedule a different start date or dragits right edge to schedule a different finish dateProject KickStart updates the summary bar in Chart view and the task dates and duration in the TaskData view

To reschedule a task without changing the duration drag the taskbar to a different date You can alsodrag a summary bar to reschedule a phase and all of its tasks (or a task and all of its subtasks) so itspans a different set of datesProject KickStart updates the task dates and duration as necessary in the Task Data view

To change task dates in the Task Information dialog box1 Open the Task Information dialog box (Right-click a task and then click Task Information or click a

task and then click the Edit Task Information button )2 Click the General tab3 In the Dates section change the following information as necessary

Start Click the Start list arrow to open a calendar and then click the appropriate start dateFinish Click the Finish list arrow to open a calendar and then click the appropriate finish dateDays Enter a number or click the spin arrows to set the task durationMilestone Select the Milestone check box if you want this task to be a milestone (A milestone is atask with a zero duration and marks an event such as the approval of a design)

Notes

You cannot delete the Start or Finish date of a task If you want to specify that a task has no durationconvert it to a milestone

When working with a calendar to schedule a start or finish date click the Today date text (where date

74

copy Experience In Software Inc 1995 - 2006

is todays date) to select todays date

See Also

Understand Task Data View

Understand Chart View

Create a Milestone

-o-

75

copy Experience In Software Inc 1995 - 2006

Phase Dates Cannot Be Edited

You cannot change the bold phase dates in the Task Data view of the Gantt chart They are a summary ofthe task dates for a particular phase and are view only You can revise phase dates by changing task dateswithin the phase

To change phase dates in Chart view

You cannot directly resize a summary bar You can extend or move the blue task barswithin a phase on the chart and Project KickStart updates the summary bar

To reschedule a phase on the chart drag the summary bar to a new date and all of its tasks (or a taskand all of its subtasks) will move with it

-o-

76

copy Experience In Software Inc 1995 - 2006

Quick Tour of Working with Linked Tasks

This feature is available only in Project KickStart ProfessionalIn the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the otherIn addition Project KickStart Pro links the tasks for you so when you open the Gantt chart you see a linkedwaterfall similar to the one shown below Besides providing a schedule that starts in a cascade with eachtask lasting one day each task is linked to the next task

You work with the Gantt chart either using the Task Data view in the left pane or the graphical Chart view inthe right pane To adjust the schedule to fit your project set the project start date in the toolbar move andresize the taskbars in the Chart view or change the start and finish dates or durations of individual tasks inthe Task Data view See About Scheduling Tasks for detailsNext fine-tune the dependencies in your project by you can linking and unlinking tasks changing theirpredecessors and successors and setting lead times For example if one task is not dependent onanother you can unlink the tasks If another task canrsquot start until two other tasks are finished you can add apredecessor to that task in which case the two tasks will be linked

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

To fine-tune the linked tasks To change the scheduled start and end dates of linked tasks move and resize taskbars in the Chart

view or change the number of days or the Start date in the Task Data view To display predecessor and successor information in the Task Data view right-click any column

heading and then click Pred or Succ To change the predecessor for a task double-click the number in the Pred column for the task and

then enter the number of a different task To change the successor for a task double-click the number in the Succ column for the task and then

77

copy Experience In Software Inc 1995 - 2006

enter the number of a different task To add another predecessor or successor to a task click in the appropriate column for the task and

then enter the number of another task To change the details of a linked task open its Task Information dialog box To do so right-click the

task and then click Task Information on the shortcut menu or click a task and then click the Edit TaskInformation button See Change Details for Linked Tasks

In the Task Information dialog you can also specify the predecessor(s) of a task and lead time(s) of thetasks

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

About Scheduling Tasks

About Linking Tasks (Pro Users)

Use the Gantt Chart Toolbar (Pro Users)

Manage Changes in Your Schedule (Pro Users)

-o-

-o-

78

copy Experience In Software Inc 1995 - 2006

Link and Unlink Tasks

These features are available only in Project KickStart Professional

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

See Also

About Linking Tasks

Quick Tour of Working with Linked Tasks

-o-

79

copy Experience In Software Inc 1995 - 2006

Create a Milestone

A milestone Indicates a task with a zero duration Milestones mark an event that must be reflected in yourproject plan such as the approval of a design or an assembly line startup

To create a milestone in the Task Data view

Double-click the Days number for a task and then enter 0 (zero)Or

Open the Task Information dialog box click the General tab and then click to insert a checkmark inthe Milestone check box

In the Chart view Project KickStart changes the taskbar to a milestone icon To create a milestone in Chart view

Click a taskbar and then drag to shrink the taskbar to a milestone icon In the Task Data view Project KickStart changes the Days for this task to 0 (zero)

Notes

To change a milestone into a task you change its duration or start and finish dates See Change TaskDates for instructions

To move a milestone in Chart view click the milestone icon on the upper left corner of the milestoneicon With the left mouse down move the icon to another date and release the mouse

To move a milestone in the Task Data view change the start date or the finish date and the milestonewill move

-o-

80

copy Experience In Software Inc 1995 - 2006

Change Task Details

You can use the Task Information dialog box to change the following task details in Task Data view

Task properties including the task name cost for completing the task and the percent completed

Dates including the start and finish dates duration and whether to convert the task to a milestone

Assignments

Notes and attachmentsYou can also edit the task name days dates costs and Done directly by clicking items in the task datacolumns

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button 2 Click the appropriate tab and then change the task details

General tab Change the task name and enter or change the cost associated with the task To changethe amount of the task completed click the Done list arrow and then select a value or type a value inthe Done text box Enter or change date information as described in Change Task Dates Assignments tab People assigned to this task are highlighted in the list To assign this task to anotherperson or resource click the name in the Assignments list To remove (unassign) this task from aperson or resource click a highlighted name in the Assignments list See Add or Change TaskAssignments for more detailsNotes and Attachments tab Type or edit a task note (Press Enter for a line break) To add anattachment click the Add button In the Select File to Attach dialog box navigate to the file you wantand then click the Open button The filename appears with a paper clip icon See Add Task Notes andAttachments for more details

To change task details directly in Task Data view

To modify the task name press F2 or double-click a task and then edit or replace the text

To change date information see Change Task Dates

To change the amount of the task completed double-click in the Done column and then enter a newvalue

To change the cost associated with the task double-click in the Cost column and then enter a newvalue

Notes

When you enter costs for tasks the total appears in the phase row for those tasks Reports include thetotal costs of all tasks in the project when you select the Cost column in the Create and Print TaskReports dialog box or the Create and Print Gantt Chart Report dialog box

You cannot change the cost of a phase because it represents the total costs for the tasks in that phaseInstead change the costs associated with the tasks in the phase

When you enter a Done for a task the corresponding taskbar in the Chart view includes a blackprogress bar

-o-

81

copy Experience In Software Inc 1995 - 2006

Change Details for Linked Tasks

This feature is available only in Project KickStart ProfessionalIf you are using Project KickStart Pro you can use the Task Information dialog box to change the followingtask details

Predecessor for a linked task

Lead time for a linked task

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button

2 Click the Predecessors tab and then change the task details about predecessors and lead timePredecessors tab The Task Properties section shows the name of the selected task which you canchange The Predecessor (Finish-to-Start) section shows the tasks that are predecessors to theselected task A predecessor task must be finished before you start the current task You can change the ID name or lead time of the predecessor task Also you can also add additionalother predecessorsThe lead time is the amount of time you need to wait after finishing the predecessor task before so youcan start the current task Lead time can be positive or negative

Note

In some programs the is time shift is called ldquolag timerdquo But we think that the term ldquolead timerdquo is moreaccurate and descriptive since itrsquos the amount of time you want to allow before you start a task

See Also

Change Task Details

82

copy Experience In Software Inc 1995 - 2006

-o-

-o-

83

copy Experience In Software Inc 1995 - 2006

Reorganize Tasks in Task Data View

Although your project should be fairly well organized by the time you start the Schedule step you canfine-tune the organization in the Task Data view using the same techniques you use in the Tasks stepTo reorder tasks

Right-click a task and then click Move Task Up or Move Task Down on the shortcut menu Or

Click a task or phase to select it and then click the Up Arrow button or the Down Arrow button on theGantt chart toolbar

To promote and demote tasks

Right-click a task and then click Outdent or Indent on the shortcut menu Or

Click a phase task or subtask to select it and then click the Outdent button or the Indent button onthe Gantt chart toolbar

To add a task1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Task button on the Gantt chart toolbar or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskTo add a subtask1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Subtask button on the Gantt chart toolbar or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtaskTo delete a task

Right-click a task and then click Delete Row on the shortcut menuOr

Click the task you want to delete and then click the Delete button

To delete a row click the Task row number and press the Delete button

See Also

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

-o-

84

copy Experience In Software Inc 1995 - 2006

Change the Timescale of the Schedule

You can display the Gantt chart schedule in the Chart view using days weeks months quarters or yearsas the timescale Changing from days to weeks for example displays a longer period of time but lessdetail

Days timescale Weeks timescale

To change the timescale in the Chart view

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years Youcan also change the timescale by clicking Timescale on the menu bar and then clicking the option youwant

Notes

When you print a Gantt chart your current timescale is used by default However you can change it inthe Print Options dialog For example even though you were viewing your Gantt chart by weeks youcan choose to print the Gantt chart by months

If your mouse comes with a wheel you can adjust Project KickStarts timescale by rolling the wheelforward or backward The Timescale list box must be selected first

-o-

85

copy Experience In Software Inc 1995 - 2006

Specify Working Days

You can select which days are working days and which days are nonworking days for scheduling purposesBy default Monday - Friday are working days and Saturday and Sunday are nonworking days You can addto and change these settings to specify holidays for example

To set working and nonworking days

1 Click the Change Working Schedule button on the Gantt chart toolbar The Change Working Schedule for this Project dialog box opens Nonworking days are shaded in grayWorking days are unshaded

2 To change a single date (from working to nonworking or from nonworking to working) click the date3 To change one day of the week for the entire project such as all Fridays double-click any Friday4 To display schedules for other months click the left and right arrows5 Click OK

Note

Project KickStart maintains separate calendars for each project

If you typically work weekends create a simple template with weekends displayed as Working daysSave as your starter template Use the starter template when you start a new project and then save theproject with a different name Weekends will be displayed as Working days in your projects

-o-

86

copy Experience In Software Inc 1995 - 2006

Change the Color of Taskbars

You can change the color of the taskbars in the Chart view to call attention to particular tasks For exampleyou can change the colors of all tasks in a particular phase resource or deadline to make them stand outin a report

To change the color of a taskbar1 Right-click a taskbar and then click Color on the shortcut menu or click a taskbar and then click the

Color button on the Gantt chart toolbar The Color dialog box opens

2 Click the color you want to assign to the taskbarTips

Avoid changing the taskbar color to black because it obscures the Done progress bar (The Doneprogress bar is a black bar displayed within a taskbar)

Also avoid changing the taskbar color to white because it will not appear in the white rows of the Chartview

-o-

87

copy Experience In Software Inc 1995 - 2006

Make Tasks Overlap

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro the schedule starts in a cascade with each task lasting one day and each tasklinked to the following taskHowever it is very unlikely that your entire schedule matches such a cascade so you can adjust theschedule Start by estimating the duration of tasksmdashthe number of days that each task will take Generallyit is best to estimate how many days will elapse before the task is done You might also want some tasks to occur at the same time To do so you can overlap the tasks To make tasks overlap like this

You can do this in three ways Set the same predecessor for both tasks

Or Set the second task as the successor of the first task and then then move the second task into a

position when it starts on the same day as the first taskOr

Set the second task as the successor of the first task and then assign a lead time of ndash3 days (the number of days scheduled for the task)

To make tasks overlap like this

Set the second task as the predecessor of the first task and then assign a lead time of ndash2 days(one less than the number of days scheduled for the task)

-o-

88

copy Experience In Software Inc 1995 - 2006

Manage Changes in Your Schedule

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro when you schedule with dependencies you can adapt to changes on the fly andcreate what-if scenarios to forecast how one change affects the overall project schedule A commonscenario is dealing with delays You can reschedule an entire project or only selected tasks When you doProject KickStart Pro updates the schedule for you

To delay an entire project Click in the Project Start text box and then edit the date to match your new start date (You can edit

the day month or year)Or

1 Click the Project Start list arrow to display the calendar The calendar highlights the selected date andoutlines todays date

2 Find the date you want using the left and right scroll arrows to view a different month and then click thedate Project KickStart changes the Start and Finish dates for all tasks according to your selection

To delay a task In Task Data view double-click the Days column for the task and then edit the number of days it will

take to complete the taskProject KickStart changes the Finish date of the task adjusts the taskbar in the Chart view andchanges the Start and Finish dates for all tasks linked to this taskOr

In Chart view resize a taskbar by clicking the taskbar and then dragging its left edge to schedule adifferent start date or dragging its right edge to schedule a different finish date Project KickStart updates the summary bar in Chart view the task dates and duration in the Task Dataview and reschedules all tasks linked to this task

To reschedule a task without changing the duration in Chart view drag the taskbar to a different date Project KickStart updates the task dates and duration as necessary in the Task Data view andreschedules all tasks linked to this task

Note

Project KickStart Pro does not include a critical path

-o-

89

copy Experience In Software Inc 1995 - 2006

Managing Libraries

Use a Library

Project KickStart has five libraries that contain lists of useful phases tasks goals people and obstaclesAll libraries expect the People Library contain sample entries that you can use in your projects Yougenerally build your own People Library from the resources that are available to you

To use a library1 In the Phases Tasks Goals People or Obstacles step of the Planning Wizard click the Library button

to open the appropriate library2 Select one or more items in a library and then drag them to your list3 Close the Library window

Tips

Feel free to add (or delete) items to the libraries to make them richer and more pertinent to yourprojects

Keeping libraries small makes them easier to use

Widen the library window to see the full text of long entries

Note

After adding a library entry to a list you can double-click the entry to edit it

See Also

Manage a Library

-o-

90

copy Experience In Software Inc 1995 - 2006

Manage a Library

Customize the libraries by adding and changing entries and reorganizing them so you can use the librariesefficiently The Phases Tasks Goals People and Obstacles Libraries include a single column ofinformation while the People Library provides additional columns (See Manage the People Library)

To edit a library1 Open the library by clicking the appropriate Library button2 To edit an entry double-click it

3 To add an entry to the library press Insert or click the Add a row button You can also select oneor more items in the list and then drag them to the library

4 To delete an entry select the entry and then press Delete or click the Delete a row button 5 To move an item up or down select the item and then click the Up Arrow or the Down Arrow button

6 Click the OK button to save your changes and close the Library windowTips

Widen the Library window to add a long entry

Libraries can serve as ldquoKnowledge Librariesrdquo By including typical company-specific terms in yourLibraries you create a quick reference for yourself and colleagues now and in the future To do so adda new line in the Library enter the name of your company (or department) as a heading in capitalletters and then list your personal terms under the heading

If you use Project KickStart on more than one computer such as at home and work you can transportchanges you make in your Libraries from one computer to another The data in all the Libraries isstored in one file pks5libxdat so you can copy that file on one computer and paste it into the ProjectKickStart 5 folder on the other computer

Keeping Libraries small makes them easier to use Project KickStarts Libraries are fairly rich out of thebox If some of the terms don rsquot apply to your type projects delete them

See Also

Manage the People Library

-o-

91

copy Experience In Software Inc 1995 - 2006

Manage the People Library

The People Library is like the other libraries but with a few important extra features

You can store contact data such as Company Email Phone and Job Title

You can import names from ACT or from Outlook if you use either of those programsTo use the People Library1 In the People step of the Planning Wizard click the People Library button2 Select one or more names in the People Library and then drag them to your list (This adds only the

names of people not their contact data) If the People Library contains company names but not contactnames you can drag the company name to your list

3 Close the Library windowTo organize the People Library

To show or hide a column right-click a column heading to open a shortcut menu and then click acolumn name In the shortcut menu a checkmark appears next to columns that are displayed in thePeople Library

To sort the people in the People Library click a column heading For example click the Name columnheading to sort the people alphabetically by name To reverse the sort click the column heading again

To move a person up or down select the person and then click the Up Arrow or the Down Arrowbutton

Click the OK button to save your changes and close the People LibraryTo edit the People Library

To edit a persons name and contact data double-click the entry

To add a person to the People Library click the first blank row press Insert or click the Add a rowbutton Then type to enter the persons name and contact information You can also select one ormore items in the list and then drag them to the People Library

To delete an entry select the entry and then press Delete or click the Delete a row button

Click the OK button to save your changes and close the People LibraryTips

Use the People Library to store names for people teams (such as Quality control team) departments(such as Manufacturing) companies (such as Acme Widgets Corp) or even equipment (such as wheatthrasher)

Widen the People Library window to add a long entry

Resize the columns by dragging or double-clicking a splitter barNotes

After adding a person or resource to your list you can double-click the name to edit it

You can import contact information stored in an Outlook or ACT (version 6 7 or later) address book toyour People Library

See Also

Import ACT Contacts and Users to the People Library

Import Outlook Contacts to the People Library

-o-

92

copy Experience In Software Inc 1995 - 2006

Import ACT Contacts and Users to the People Library

If you use ACT 7 or later (200520062007) or if you use ACT 6 you can import contacts and users to thePeople Library This speeds up your work by letting you use ACT information in your Project KickStartplans If you export a plan to ACT 7 or later it recognizes the people and other resources you entered inProject KickStart

To import ACT contacts and users1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click ACT 7 or later or ACT 6 Click the Import button3 Click the Select ACT Database button and select the ACT 7 or later database (pad) containing the

people information you want to import The ACT 7 and later databases are usually stored in MyDocumentsACTACT for Win 7Databases (If you use ACT 6 your data is stored in a dbf database) If you select a multi-user ACT database you must enter your user name and password for the ACTdatabase

4 In the Import to People Library dialog box the names of Contacts and Users are listed on the left Clickthe Users tab select one or more users and then click Add to move the user names to the Import listClick the Contacts tab to select contact names the same way Click the Add All button to select allusers or contacts for import Note You can sort the contacts alphabetically by name or by company name by clicking theappropriate column heading

5 Click the Import button to add the names and related information from the selected ACT database tothe People Library

Notes

Importing contacts and users to the People Library does not remove them from the ACT database

If you try to import the same ACT contact or user twice it appears only once in the People Library

-o-

93

copy Experience In Software Inc 1995 - 2006

94

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts to the People Library

If you use Microsoft Outlook to maintain your contacts you can import selected contacts to the PeopleLibrary ThisThis speeds up your work by letting you use Outlook information in your Project KickStartplans If you export a plan to Outlook it recognizes the people and other resources you entered in ProjectKickStart

To import Outlook contacts1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click Outlook Click the Import buttonA dialog box opens informing you that Project KickStart is trying to access your Outlook data

3 Allow access for 1 minute and then click the Yes button4 If Outlook asks you to choose your profile please do so5 The Import to People Library dialog box opens listing Outlook Contacts on the left Select one or more

contacts and then click Add to move the contact names to the Import list Click the Add All button toselect all contacts for import

6 Click the Import button to add the contact names to the People Library

Notes

Importing contacts and users to the People Library does not remove them from Outlook If you try to import the same Outlook contact twice it appears only once in the People Library

95

copy Experience In Software Inc 1995 - 2006

You can import Contacts from the Outlook Business Contact Manager

See Also

Import Outlook Contacts via CSV to the People Library (Pro Users)

-o-

96

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts via CSV to the People Library (ProUsers)

This feature is available only in Project KickStart Professional

If you use Microsoft Outlook to maintain your contacts and many of the people on your project are not inyour personal contacts folder in Outlook you can use our new utility to import these Outlook contacts viaCSV to the People Library

To export Outlook contacts to a CSV file1 In Outlook - Click File Import and Export Export to A File and click Next2 Select Comma Separated Values (Windows) and click Next3 Select the Contacts folder to export and click Next4 Save Exported File As with the default being your My Documents folder5 Click Next

To import Outlook contacts to the People Library

1 Be sure that you exit Project KickStart before running the Import Utility

2 Run ImportCSVToPKSexe which is located in the Project KickStart application folder

3 Browse or type the Contacts CSV file (the path is My DocumentsProject KickStart Projects folder bydefault)

4 Browse or type the pks5libxdat file (default is the Project KickStart application folder)

5 Click on Import

Note

Importing contacts and users to the People Library does not remove them from Outlook

-o-

97

copy Experience In Software Inc 1995 - 2006

Printing Reports

98

copy Experience In Software Inc 1995 - 2006

Printing Dashboards

Print Reports

You can print reports from anywhere in Project KickStart through a new Reports Step

You will see Reports divided into three areas

Dashboard

Task Reports

Gantt Chart Reports

-o-

99

copy Experience In Software Inc 1995 - 2006

Print Dashboard Reports

You can print dashboard reports from anywhere in Project KickStart though it makes the most sense toprint them after you have developed your tasks and arranged them in a sensible order

To print a dashboard report

1 Click File on the menu bar and then click Print Reports and then click Dashboard Reports or clickthe Print Reports button

2 In the left column select one of these dashboard reports Whats Due Today Whats Due NextWeek Whats Due Next Month

3 Change the page setup as necessary or Save As a file (See Page Setup and Save As)

4 Click the Print button

Tip

You can see the number of tasks in each dashboard report from the dashboard menu

-o-

100

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Dashboard Reports

Printer Setup

-o-

101

copy Experience In Software Inc 1995 - 2006

Save as HTML or RTF

You can dashboard reports to a Hypertext Markup Language (HTML) format for viewing with an Internetbrowser such as Microsoft Internet Explorer or Mozilla FireFox or to an RTF format for viewing in MicrosoftWord

To save a dashboard report as an HTML file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save button

To save a report as an RTF file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

102

copy Experience In Software Inc 1995 - 2006

Printing Task Reports

Print Task Reports

You can print task reports from anywhere in Project KickStart though it makes the most sense to print themafter you have developed your tasks and arranged them in a sensible orderBefore you print task reports you might want to widen the Task Name column in the Task List to make sureyou print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a task report

1 Click File on the menu bar and then click Print Task Reports In the Tasks step you can click thePrint Reports button instead

The Create and Print Task Reports dialog box opens

2 Click the list arrow and then click Task Report Individual Assignments or Phases Goals People ampObstacles

3 Select the information you want to include in the report as described below

4 Preview the report and change the page setup as necessary (See Print Preview and Page Setup)

5 Click the Print button

Task Report

The Task report covers the entire project and includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

103

copy Experience In Software Inc 1995 - 2006

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to display in the report

By default the report prints all tasks Click the Incomplete Tasks or Completed Tasks option button tofocus on one type of task

4 Click the Preview button (See Print Preview for details)

Individual Assignments

The Individual Assignments report covers the entire project and lists the tasks assigned to each resourceThe report includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to include in the report

Click the All Tasks Incomplete Tasks or Completed Tasks option button

4 Choose which people to include The report lists tasks assigned to the people you select

Click to insert or remove a checkmark from the box for each person

5 Click the Preview button (See Print Preview for details)

Phases Goals People amp Obstacles

This report includes the phases goals people and obstacles in your project You can include some or all ofthese items in the report

104

copy Experience In Software Inc 1995 - 2006

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Click the Preview button (See Print Preview for details)

Tip

If you have many long notes for the tasks of your project it may be hard to read them if you select everycolumn in the Task Reports You should consider selecting a report with only columns for Tasks andNotes

See Also

Print Gantt Chart Reports

-o-

105

copy Experience In Software Inc 1995 - 2006

Print Preview

Before printing a report preview its pages so you know how the report will look when printed

To preview a task report1 Click the Preview button on the Create and Print Task Reports dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from 79 to 100 or from 100 to 79Zoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25

viewPrint the report

You can also click the Page Setup button to change margins and other settings or click the Closebutton to close the Print Preview window

2 If the report appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintTask Reports dialog box

Note

Print Preview is for viewing only--you cannot edit the contents of a report

See Also

Print Task Reports

Printer Setup

Page Setup

-o-

106

copy Experience In Software Inc 1995 - 2006

Printer Setup

Before you print a report you can change the following printer settings

Printer name (and other properties) Paper size Number of copies

To change the printer setup1 Click the Printer button on the Project KickStart toolbar or the Print Preview toolbar2 In the Print dialog box change the printer settings

See Also

Print Task Reports

Print Preview

Page Setup

-o-

107

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Task Reports

Print Preview

Printer Setup

-o-

108

copy Experience In Software Inc 1995 - 2006

Email Task Reports

After creating and previewing a task report you can distribute it to others via email

To email a task report1 In the Create and Print Task Reports dialog box select a report and then click the Email Report

button Project KickStart creates the report opens a new message in your email software and attaches thereport as an HTML file to the message

2 Insert one or more email addresses include the message text and then send the message the way youusually do

Tip

To send a task report to each person in your project with the appropriate assignments select theIndividual assignments report select one person to receive the report and then click the Email Reportbutton Enter the email address of the recipient and send the message Do this for each person in yourproject

-o-

109

copy Experience In Software Inc 1995 - 2006

Save as HTML

You can export tasks assignments days and notes to a Hypertext Markup Language (HTML) format forviewing with an Internet browser such as Microsoft Internet Explorer or Mozilla FireFox

To save a report as an HTML file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

110

copy Experience In Software Inc 1995 - 2006

Save as RTF

You can export tasks assignments durations and notes to a Rich Text Format (RTF) for editing inMicrosoft Word

To save a report as an RTF file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can open an RTF file in a word processor such as Microsoft Word

To send an RTF document to each person in your project with the appropriate assignments select theIndividual Assignments report select one person to receive the report and then save the report asRTF Do this for each person in your project

See Also

Save as HTML

-o-

111

copy Experience In Software Inc 1995 - 2006

Printing Gantt Chart Reports

Print a Gantt Chart

Once you create your schedule you can print a Gantt chart from anywhere in Project KickStart

Before you print a Gantt chart you might want to widen the Task Name column in the Task pane to makesure you print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a Gantt chart1 Click File on the menu bar and then click Reports and then select Gantt Chart Reports In the

Schedule step you can click the Print Reports button insteadThe Create and Print Gantt Chart Report dialog box opens

2 Click the Format list arrow and then click Wall chart Fit to smallest size or Repeat tasks on everypage (for handouts)

3 Select the information you want to include in the report as described below4 Preview the report and change the page setup as necessary (See Print Preview a Gantt Chart and

Page Setup)5 Click the Print button

Wall Chart The wall chart prints the Gantt chart information spread across many pages which you can tape together tocreate a wall chart On the left side of the report the wall chart includes the task data columns you selectThe right side of the report includes the graphical view shown in the Gantt chart pane on the right

1 Select the task data columns you want to display for the task information on the left side of the wallchartClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the wall chart

112

copy Experience In Software Inc 1995 - 2006

By default the wall chart prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the wall chartBy default the wall chart prints the timescale you were using in the Gantt chart Click the SetTimescale list arrow to change the timescale to Weeks Months Quarters or Years

4 Select the orientation for the wall chartClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Fit to Smallest Size When you select the Fit to smallest size format Project KickStart reduces the size of the entire Gantt chartincluding the information in the Task pane on the left and the graphical view shown in the Gantt chart paneon the right so it fits as well as possible in the smallest number of pages

1 Select the data columns you want to display for the task information on the left side of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 The timescale for the Gantt chart view on the right side of the report is determined by the length of yourproject and may not be changed

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 The number of pages of the report is shown here (The Fit to smallest scale report will print up to 78rows of tasks per page)

6 Click the Preview button (See Print Preview a Gantt Chart for details)

Standard (for Handouts) This report lists the data columns you specify on the left side of the first page and can repeat the tasknumber task name or assignments on every interior page of the report which is especially useful for

113

copy Experience In Software Inc 1995 - 2006

handouts

1 Select the data columns you want to print on the left side of the first page and the data columns youwant to print on every page of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the reportBy default the report prints a daily view of the tasks Click the Set Timescale list arrow to change thetimescale to Weeks Months Quarters or Years

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Tips

Print Preview shows how many pages the Gantt chart will take to print If there are too many pagesconsider changing the timescale or the date range You can also choose to show fewer columns of taskdata

If possible use paper that is larger than 85 x 11 inches You can select the paper size in Print Previewusing the Page Setup dialog box

If you change the timescale from Days to Weeks or Months this can make tasks with short durations (1to 5 days) difficult to see

If you have trouble printing the Gantt chart report try changing the dpi from 600 to 300 (draft mode) Ifyou continue to have problems contact your printer manufacturer and see if it supports PCL (PrinterCommand Language) technology which is included in most printers today

If you have trouble printing the Gantt chart report on a PDF printer you can try to scale the printing tographics setting to 50

114

copy Experience In Software Inc 1995 - 2006

See Also

Save Gantt Chart Images

Print Task Reports

Printer Setup

Page Setup

-o-

115

copy Experience In Software Inc 1995 - 2006

Print Preview a Gantt Chart

Before printing a Gantt chart preview its pages so you know how the report will look when printed

To preview a Gantt chart1 Click the Preview button on the Create and Print Gantt Chart Report dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from the current zoom percentage to 100 or from 100 to the current zoom percentageZoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25 viewChange printer settings and then print the reportYou can also click the Page Setup button to set margins select paper size and enter headers andfooters or click the Close button to close the Print Preview window

2 If the Gantt chart appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintGantt Chart Report dialog box

Notes

Print Preview is for viewing only--you cannot edit the contents of a report

If you want to print a wider task column return to the Gantt chart widen the Tasks Name column andthen print

To change print settings such as the printer selection and number of copies click the Print button to open the Print dialog box You can save the Gantt chart in a PDF file by clicking the Print button andthen clicking the PDF printer selection (such as Adobe PDF or PDF-XChange ) You can then distributethe Gantt chart electronically as a PDF file

See Also

Print a Gantt Chart

Page Setup

-o-

116

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a Gantt chart you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print a Gantt Chart

Print Preview a Gantt Chart

-o-

117

copy Experience In Software Inc 1995 - 2006

Printing to an Adobe PDF file

To print a Gantt chart to an Adobe PDF file you may have to make some adjustments to your settings

To preview a Gantt chart1 Select Adobe PDF as the name of the printer2 Click Properties button3 Click the PaperQuality tab4 Click Advanced button5 In the Graphic Section lower the setting on Print Quality6 Also in the Graphic Section change the Scaling from 100 to 50

-o-

118

copy Experience In Software Inc 1995 - 2006

Save Gantt Chart Images

You can save a Gantt chart as a series of graphic files in the Meta File (emf) format which you can theninsert in a file such as a Microsoft Word document or PowerPoint presentation The number of graphic filescreated depends on the report type and options you choose in the Create and Print Gantt Chart Reportdialog box By default Project KickStart saves the files in a folder named for your project

To save Gantt chart images1 In the Create and Print Gantt Chart Report dialog box click the Save Image button

The Save Image dialog box opens2 Change the location where you want to save the image files or change the part of the file name that

includes the project name and report type if necessary3 Click the Save buttonNotes

Project KickStart saves the image files in the PKSGanttImagesproject name folder stored in the MyDocumentsProject KickStart Projects folder (where project name is the name of your project)

Each graphic file name includes the name of the project report type date you created the report andnumber in the series of images as in CreateaWinningPresentation_Wall chart_09112008_1emf toCreateaWinningPresentation_Wall chart_09112008_20emf

To email the Gantt chart images attach the images in the PKSGanttImagesproject name folder storedin the My DocumentsProject KickStart Projects folder (where project name is the name of your project)If the image files are large zip or compress the files first

If you have installed PDF as a printer selection you can print the Gantt chart to a PDF file and thenattach the PDF file to an e-mail message PDF files are often easier to read than image files See thenotes in Print Preview a Gantt Chart for instructions on printing to a PDF file

-o-

119

copy Experience In Software Inc 1995 - 2006

Export Project Data

120

copy Experience In Software Inc 1995 - 2006

Export to ACT

Export to ACT 7 or Later

If you use ACT 7 or later (20052006200720082009) you can export your plan from Project KickStart toan ACT database with just one click After you export your plan you see your tasks in the ACT Groupview grouped under the name of your project

To export to ACT 7 or later

1 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 7 and later andthen click the Go button You can also click File on the menu bar point to Export to and then clickACT 7 and later

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (pad file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opens

Each time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks

4 Click Start (This works best if ACT is already open )

5 If you are exporting to a multi-user ACT database enter your ACT User Name and Password

To view each project separately in ACT Group Details

1 In ACT click the Group List icon

2 Double-click the Project Name in the Group Name column The Group Detail appears for the projectyou selected

3 Click the Contacts tab to see Contacts and click the Activities tab to see tasks for that project

4 You should press Ctrl-F5 to refresh the view Also you might have to adjust the Filter in ACT so thatDates to show is set to All Dates

Task names are listed in the Regarding column Assignments are listed in the Scheduled With columnPhases are shown in red and tasks and subtasks are shown in blue

To view tasks from multiple projects sorted by date in Task List or Calendar

In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn Project names are in the Associate With column You might have to adjust the Filter in ACT sothat Dates to show is set to All Dates

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar Tasks are set as timeless (Duration of 0 minutes) so the transferred tasks dont fill up thecalendar

121

copy Experience In Software Inc 1995 - 2006

Tips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

The ACT 7 and later export is smart enough to update your existing tasks from the same project If youexport the same Project KickStart project two or more times ACT recognizes the project and asks ifyou want to update the project information in ACT You do not lose your task history or notes in ACT

Tasks that are unassigned in Project KickStart are listed as Scheduled With Unassigned PKS

You can filter by Selected Users in the Task List and in Groups

See Also

Import ACT Contacts and Users to the People Library

-o-

122

copy Experience In Software Inc 1995 - 2006

Export to ACT 6

If you use ACT 6 ACT 2000 or ACT 5 you can transfer a Project KickStart plan into an ACT databasewith just one click After you export your plan you see your tasks in the ACT Group view grouped underthe name of your project

To export to ACT 61 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 6 and then click

the Go button You can also click File on the menu bar point to Export to and then click ACT 6

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (dbf file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opensEach time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks4 Click Start (This works best if ACT is already open )5 If you are exporting to a multi-user ACT database enter your ACT user name and passwordTo view each project separately in ACT1 In ACT click the Groups icon 2 Click the Project Name listed under All Groups on the left3 On the lower-right part of the window click the Activities tab to see tasks for that project

Task names are listed in the Regarding column Assignments are listed in the Scheduled With column 4 You might have to adjust the Filter in ACT so that Dates to show is set to All Dates Also you might

have to press Ctrl-F5 to refresh the view5 To view task details click the button next to the task column on the leftTo view tasks from multiple projects sorted by date1 In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn You might have to adjust the Filter in ACT so that Dates to show is set to All Dates

2 If the Group column is not showing add it by clicking ViewAdd Columns and then double-clickingGroupThe tasks are identified by group (project name)

3 To view task details click the button next to the task column on the leftTips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar as well as in the Task List

You can filter by Selected Users in the Task List and in Groups

After exporting your tasks to ACT you can import them to your Palm Pilot using the ACT Link

See Also

Import ACT Contacts and Users to the People Library

-o-

123

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Outlook

If you use Microsoft Outlook you can export your plan from Project KickStart to Outlook in a click of abutton After you export your plan you see your tasks in the Outlook Tasks view grouped under a categorynamed for your project In Outlook you can track your tasks and email tasks to team members

To export to Microsoft Outlook1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Outlook and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Outlook The Export to Outlook dialog box opens

2 Click an option button to export All tasks Uncompleted tasks or Completed tasks3 If you want to display the tasks you export on your Outlook Calendar click the check box4 Click the Start button A dialog box opens informing you that Project KickStart is trying to access your

Outlook data

5 Allow access for 1 minute and then click the Yes buttonTo view your tasks in Microsoft Outlook1 Click the Outlook Tasks button2 Depending on the version of Outlook you are using set to view the tasks by category In Outlook 2003

click the By Category option button in the Current View list You can also click View on the menu barpoint to Arrange By and then click CategoriesYour project is listed by its project name in the Categories list

3 Click an expand icon to see the complete list of tasks and subtasks

124

copy Experience In Software Inc 1995 - 2006

4 To view task details double-click the task nameTips

The export to Outlook works best if Outlook is already open

In Outlook you can set priorities set reminders and schedule by the hour

If you export to your Outlook Calendar a reminder appears on the due date of each task

After you export tasks to Outlook you can synchronize with your Palm Pilot Windows CE device orother handheld computer

Note

You can export only to Microsoft Office Outlook not Outlook Express

See Also

Import Outlook Contacts to the People Library

-o-

125

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Word

If you use Microsoft Word you can export your plan from Project KickStart to Word in a click of a buttonYour project appears in a Word table in a doc file You can cut and paste change column widths deletecolumns and print from Word

To export to Microsoft Word

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Word andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Word

Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in a Word document in a doc format

2 When youre finished use Save As to save the Word file with a new name such as ltnamegtdoc Forconvenience you can save the file using the same name as your Project KickStart project name

Benefits of using Project KickStart and Word

Communicate projects flexibly After exporting to Word you can communicate your project details ina variety of text formats You can also enhance your document by adding color logos clip art orhyperlinks

Distribute plans to others You can send doc files to other Microsoft Word users via email andrequest comments using Words Send To and Comments features

Tip

Include your strategic plan in documents letters and web pages in a doc or html file

Note

The image of the Gantt chart does not import into Word automatically You can manually import theGantt chart image into a Word document In Word select Insert on the menu bar point to Pictureclick From File and then browse to the folder containing the Gantt chart images you saved By defaultthis is cMy DocumentsProject KickStart ProjectsPKSGanttImages in a folder named for your project

See Also

Export to Word Processors (Other than Word)

Save Gantt Chart Images

126

copy Experience In Software Inc 1995 - 2006

-o-

127

copy Experience In Software Inc 1995 - 2006

Export to Word Processors (Other than Word)

If you are using a word processor other than Microsoft Word you can export your Project KickStart taskreport by first saving it as an HTML or RTF file

To export to word processors other than Microsoft Word

1 Save a Project KickStart task report using HTML or RTF format using the Save As button in the Createand Print Task Reports dialog box

2 Open the file with your word processor

3 Save the file using the Save As command using a different name

See Also

Print Task Reports

Save as HTML

Save as RTF

-o-

128

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Excel

If you use Microsoft Excel you can export your plan from Project KickStart to Excel in a click of a buttonYour project appears in an Excel worksheet in a xls file You can add task details perform calculationsand share your project data with other Excel users

To export to Microsoft Excel1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Excel and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Excel Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in an Excel worksheet in an xls format

2 When youre done select FileSave As to save the Excel file under a new name For convenience youmight want to save it under the same name as your Project KickStart project name

To manually import Gantt chart images into Microsoft Excel1 In Excel click Sheet2 and select ToolsOptions on the menu bar and unclick the box for Gridlines2 Then select Insert on the menu bar point to Picture click From File and then browse to the folder

containing the Gantt chart images you saved By default this is cMy DocumentsProject KickStartProjectsPKSGanttImages in a folder named for your project

3 Select one Gantt chart image at a time to bring it in 4 You can manipulate the size of the image in Excel

Benefits of using Project KickStart and ExcelProject KickStart is very good at scoping out a schedule but there are a few reasons why you might want touse both programs

Data sharing A Project KickStart user might want to share the information with other Excel users whodont have Project KickStart They could change enhance or redistribute their portions of the schedule

129

copy Experience In Software Inc 1995 - 2006

Add more task details Excel users can add new columns of task data that cant be added in ProjectKickStart

Sort task lists For example you could show your projects tasks sorted by each resources namethen see each resources tasks sorted by the tasks start date

Filter tasks Excel can show tasks that meet certain criteria For instance show tasks with the wordtesting in the task name

See Also

Save Gantt Chart Images

-o-

130

copy Experience In Software Inc 1995 - 2006

Export to Microsoft PowerPoint

If you use Microsoft PowerPoint you can export your plan from Project KickStart to PowerPoint in a click ofa button Your project appears as a formatted PowerPoint presentation in a ppt file

To export to Microsoft PowerPoint

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft PowerPointand then click the Go button You can also click File on the menu bar point to Export to and thenclick Microsoft PointPoint

The Export to PowerPoint dialog box opens where you can choose a PowerPoint design template ifyou like

2 Click the Start button

Your tasks days start and finish dates and costs appear in a PowerPoint presentation with an imageof the Gantt chart in one or more slides at the end of your slide show

Once you have created a PowerPoint presentation you can enhance your slides in several ways

Delete slides that are not appropriate for your presentation

131

copy Experience In Software Inc 1995 - 2006

Rearrange the order of the slides

Add colors for emphasis

Add graphics such as company logo clip art and colors

Shorten any long task titles

Benefits of using Project KickStart and PowerPoint

Save time You can dramatically save time in creating a PowerPoint presentation on your project

Present projects to others Present project details in webinars presentations and corporatemeetings Create template presentations or how tos for implementing an installation productintroduction or corporate policy for example

Communicate plans Email project plans in ppt format to colleagues and presentors

Tips

If you use a PowerPoint design template choose one that has a white or light background for maximumlegibility of the Gantt chart in the presentation

The Gantt chart image in the PowerPoint presentation is generated ldquoon the flyrdquo Change the Timescalesettings of the Gantt chart considering how it will be reflected in the number of images of the Ganttchart For example the Day view results in more Gantt chart images than the Months view

-o-

132

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Project

If you use Microsoft Project 98 2000 2002 or 2003 you can export your plan from Project KickStart toProject in a click of a button

To export to Microsoft Project

In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Project andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Project Your tasks assignments days start and finish dates costs done and notes (excluding attachments) appearin a Microsoft Project file

Benefits of using Project KickStart and Microsoft Project

Share data with others Send a project to a colleague or client that expects to see your schedule in anMicrosoft Project format

Schedule tasks with more flexibility Schedule tasks in different durations particularly in less than aday

Track resources Track resource usage and resource leveling and to have greater flexibility in sortingfiltering and reporting project information

Notes

Project KickStart tasks transfer to Microsoft Project as tasks with a Constraint type of Start No EarlierThan This keeps the dates the same as in the Project KickStart schedule

The settings in Project KickStart Working Days Calendar also transfer to Microsoft Project

Exporting to Microsoft Project allows you to take advantage of the advanced tracking and schedulingfeatures that large projects often require

You can also save your Project KickStart projects as an mpx file which you can open in MicrosoftProject and send to other Microsoft Project users Click File on the Project KickStart menu bar clickSave As and then choose mpx as the file type After you save the file click File on the MicrosoftProject menu bar click Open and open your mpx file

-o-

133

copy Experience In Software Inc 1995 - 2006

Export to SureTrak Project Manager

If you use SureTrak Project Manager you can export your plan from Project KickStart to SureTrak ProjectManager

To export to SureTrak Project Manager

1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file

2 In SureTrak click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

SureTrak

You will see your tasks and assignments (but not the notes) appear in a SureTrak file The file is shownin outline view

Benefits of using Project KickStart and SureTrak

Add new information to tasks such as how they are linked

Track progress particularly for comparing plans verses actual results

Have greater flexibility in sorting filtering and reporting project information

Notes

Task notes are not included in the transfer

A version of Project KickStart called the Project KickStart Wizard is included in SureTrak 2 andSureTrak 3 You can use it within SureTrak

See Also

Export MPX Files

-o-

134

copy Experience In Software Inc 1995 - 2006

Export to FastTrack Schedule

If you use FastTrack Schedule you can save your Project KickStart project as an mpx file and import it intoFastTrack ScheduleTo export to FastTrack Schedule1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file2 In FastTrack Schedule click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

FastTrack ScheduleBenefits of using Project KickStart and FastTrack Schedule

Add more task details FastTrack Schedule provides the features and tools needed in many largeprojects

Multiproject reporting Consolidate multiple projects into a master project file

See Also

Export MPX Files

-o-

135

copy Experience In Software Inc 1995 - 2006

Export to Milestones Professional

If you use Milestone Professional you can export your plan from Project KickStart to MilestonesProfessional in a click of a button

To export to Milestone Professional

In the Schedule step click the Export to list arrow below the Gantt chart click MilestonesProfessional and then click the Go button You can also click File on the menu bar point to Export to and then click Milestones Professional

Your tasks assignments start and finish dates and notes (excluding attachments) appear in aMilestones file

Tips

After you export your tasks to Milestones Professional you can create taskbars add titles and performother tasks to produce a presentation-quality schedule You can also use Milestones to track your tasksby showing task durations and percent completions Make scheduling changes by dragging the taskdates

If you have an earlier version of Milestones (eg version 45 or 5) you can save Project KickStart dataas an mpx file and then open the mpx file in Milestones

-o-

136

copy Experience In Software Inc 1995 - 2006

Export to Mindjet MindManager

If you use Mindjet MindManager 7 or later you can export your project plan from Project KickStart in a clickof a button Or you can develop a rough plan in MindManager and export your mind map to ProjectKickStart for enhanced planning It works both ways

To export from Project KickStart to MindManager

In the Schedule step click the Export to list arrow below the Gantt chart click MindManager and thenclick the Go button You can also click File on the menu bar point to Export to and then clickMindManager

Your tasks assignments start and finish dates durations costs Done and notes (excludingattachments) appear in a MindManager file

To export from MindManager to Project KickStart

In MindManager click File on the menu bar point to Send To and then click Project KickStart Thenclick the OK button to start the export

You can also click the Project KickStart icon at the bottom of the MindManager window

Benefits of using Project KickStart and MindManager together

Visualize your plan in two ways Brainstorm plan and communicate your project details in both agraphical and linear style

Develop a graphical plan and then fine-tune the details MindManager uses mindmappingtechniques to develop a high-level plan in a graphical format Export to Project KickStart to enhanceyour plan details by focusing on your projects goals obstacles and resource needs You can alsocreate a Gantt chart schedule

Communicate concepts Project KickStart users can display their plans in a highly graphicalmindmapping format in MindManager The maps make it easier to communicate complex processesand visually identify important tasks issues and relationships

Tip

If you dont already use MindManager you can purchase it in our Thinking Tools Store

-o-

137

copy Experience In Software Inc 1995 - 2006

Export to WBS Chart Pro

If you use WBS Chart Pro you can export your plan from Project KickStart to WBS Chart Pro in a click of abutton

To export to WBS Chart Pro

In the Schedule step click the Export to list arrow below the Gantt chart click WBS Chart Pro andthen click the Go button You can also click File on the menu bar point to Export to and then clickWBS Chart ProYour project is displayed under the project name Each phase in the project is shown in a box with ashadow Each lower level task in a phase is displayed under their respective phase box groupedtogether with the other tasks in that phase

Benefits of using Project KickStart and WBS Chart

Visualize tasks Work with tasks in a tree-style chart called a Work Breakdown Structure (WBS)chart

Communicate your project plan with others WBS Chart uses the outline you create in ProjectKickStart to create a top-down picture of your plan This picture is similar to an Organization chart Butinstead of displaying the structure of your company a WBS chart displays the structure of your projectplan

Notes

WBS Chart refers to the phases in the project as Summary Tasks and the detail for each phase asTasks

The export only works if WBS Chart is not currently running You must close WBS Chart before you cancreate another chart

See Also

Export MPX Files

-o-

138

copy Experience In Software Inc 1995 - 2006

Export MPX Files

The MPX file format is an ASCII format created by Microsoft Project or another program and is used tosend data to and from project management software programs

The following programs can create and open MPX files

FastTrack Schedule

Microsoft Project (95 or 98)

Project KickStart 5

Project KickStart 32

RiskyProject

SureTrak Project Manager

WBS Chart

In these programs you save a project as an MPX file using the Save As command on the File menu Youcan then open an MPX file by using the Open command on the File menu and then specifying the file typeas mpx

For example if you want to move a project from Project KickStart 5 to Project KickStart 32 you can savethe project as an mpx file and then open it in Project KickStart 32

In Microsoft Visio you can create a Visio project time line from Project KickStart To do so you first mustsave your file in Project KickStart as an MPX file Then

1 Start Visio

2 Click File on the menu bar point to New click Business Diagram and then click Project TimelinesWizard

3 Click Next

4 On the second window click Import MPX File to import the Project KickStart mpx file

5 Enter the file location and name or click Browse to locate the file

6 Follow the instructions in the Visio Project Timelines Wizard windows

Tip

If you have difficulty importing the mpx file remove any commas from task names

-o-

139

copy Experience In Software Inc 1995 - 2006

Reference

140

copy Experience In Software Inc 1995 - 2006

Menus

File Menu

Command Keyboard Shortcut Description

New Project Ctrl+N Creates and names a new project fileOpen Project Ctrl+O Opens a previously saved Project KickStart 4 or 5 file

(prx) Project KickStart 3 file (prj) or mpx fileClose Ctrl+W Closes an open Project KickStart fileSave Ctrl+S Saves a project file (prx) in which you made changes Save As Saves a project file with a different file name or different

file format such as MPXPrint Task Reports

Ctrl+T Generates and prints a report letting you preview thecontents

Print Gantt ChartReports

Ctrl+G In the Gantt chart (Schedule step) generates andprints the Gantt chart in the current timescale

Export To Sends the project to another program such asMicrosoft Outlook or ACT 7

Recent file list Lists the last three files opened in Project KickStartExit

Alt+F4 Exits the program

-o-

141

copy Experience In Software Inc 1995 - 2006

Edit Menu

Command Keyboard Shortcut Description

UndoRedo Ctrl+Z Undoes or repeats the last operationCut

Ctrl+X Deletes the currently selected information placing it on theclipboard so you can paste it elsewhere

Copy

Ctrl+C Places a copy of selected information on the Clipboard so youcan paste it elsewhere

Paste

Ctrl+V Places information from the Clipboard to the currently selectedlocation

Select all Ctrl+A Selects all the content in the windowAdd a line Adds a new row where you can enter text

-o-

142

copy Experience In Software Inc 1995 - 2006

View Menu

Command Description

Tool Bar Shows or hides the toolbar (a checkmark indicates thetoolbar is displayed)

Steps Bar Shows or hides the Steps bar (a checkmark indicates the Steps bar is displayed)

Name Go to the Name your project stepPhases Go to Phases stepGoals Go to Goals stepSimilar Projects Go to Similar projects stepPeople Go to People stepObstacles Go to Obstacles stepAssign Go to Assign tasks to people stepTasks Go to Tasks stepSchedule Go to Schedule step

-o-

143

copy Experience In Software Inc 1995 - 2006

Tools Menu

Command Keyboard Shortcut Description

Spelling

F7 Checks spelling of project dataexcept for names of people

Collaboration To access or find out aboutGoToMeeting

Options Select options for running thesoftware

-o-

144

copy Experience In Software Inc 1995 - 2006

Options

-o-

145

copy Experience In Software Inc 1995 - 2006

Data Menu

The Data menu is available in the Tasks and Schedule steps for manipulating tasks and creating ascheduleCommand Description

Move Up Moves the selected task item upMove Down Moves the selected task item downOutdent Moves the selected task item to the leftIndent Moves the selected task item to the rightInsert Task Insert task in row aboveInsert SubTask Insert subtask below current rowDelete Task Delete current taskEdit Task Properties Brings you to an edit screen where you can edit task

name change assignments and edit task notesEdit Notes Brings you to an edit screen for editing task notesColor Taskbars Change the color of selected tasks (in Schedule)Change Working Days Select which days are working and which are

nonworking (in Schedule)Link Tasks Link tasks in Gantt chart (Pro Users)Unlink Tasks Unlink tasks in Gantt chart (Pro Users)

-o-

146

copy Experience In Software Inc 1995 - 2006

Timescale Menu

The Timescale menu is available in the Schedule step so you can change the display of the Gantt chartschedule

Command Description

Days Displays a daily schedule in theGantt chart

Weeks Displays a weekly schedule inthe Gantt chart

Months Displays a monthly schedule inthe Gantt chart

Quarters Displays a quarterly schedule inthe Gantt chart

Years Displays a yearly schedule inthe Gantt chart

-o-

147

copy Experience In Software Inc 1995 - 2006

Help Menu

Command Description

Project KickStart Help Help for Project KickStart including a Table ofContents and index of terms

Online Tutorials View several Getting Started Tutorials to getyou started with Project KickStart whether youare a new or experienced user

Keyboard Shortcuts Shortcuts for programTechnical Support How to obtain Technical Support for Project

KickStart via web form and email[Send Log to Technical Support] If the program detects an error it writes a log

of technical issues Click Send Log toTechnical Support to send the error log to us

ProjectKickStartcom Visit the Project KickStart Web siteGet Latest Version See what the latest published version is and

download it if you need itAbout Project KickStart Shows Project KickStart version number build

date copyright and system information

-o-

148

copy Experience In Software Inc 1995 - 2006

Shortcuts

Use the following keyboard shortcuts to move quickly around in Project KickStart

Navigation

Move forward to the next window Alt+NMove back to the previous window Alt+BSteps

Go to Name step Alt+MGo to Phases step Alt+SGo to Goals step Alt+GGo to Similar step Alt+RGo to People step Alt+PGo to Obstacles step Alt+OGo to Assign step Alt+IGo to Tasks step Alt+KGo to Library (Phases Tasks GoalsPeople Obstacles)

Alt+L

Menus

File menu Alt+FEdit menu Alt+EView menu Alt+VShow menu (Tasks step) Alt+WOutline menu (Tasks step) Alt+UTimescale (Schedule step) Alt+CHelp menu Alt+H F1Other

Edit tasks assignments amp notes (Tasks step)F3Save Ctrl+SPrint Task Report Ctrl+PPrint Gantt Chart (Schedule step) Ctrl+GCut Ctrl+XCopy Ctrl+CPaste Ctrl+VInsert Row InsertDelete Row DeleteInsert Line Break (in Notes in Task List andSchdule steps)

Enter

Spell Check

Ignore Alt+IIgnore All Alt+GChange Alt+CChange All Alt+HHelp

149

copy Experience In Software Inc 1995 - 2006

Contents in Help Alt+CIndex Alt+IBack in Help Alt+BClose Help Alt+LHelp about the current step Alt+H

-o-

150

copy Experience In Software Inc 1995 - 2006

Share Project KickStart Data

Project KickStart makes it easy to share data with other people involved with a project You can share yourProject KickStart data in the following ways

Send a printed report Make a PowerPoint presentation Send a file (prx html rtf mpx) Post an HTML file to a Web site and access it with your web browser Export to other programs such as Microsoft Word or Excel and send data in a format the recipient can

access (such as doc xls or mpx)

Note

You can also collaborate with a colleague by conducting an online meeting using GoToMeeting (Prousers)

-o-

151

copy Experience In Software Inc 1995 - 2006

Open a Project

After you create a project and save it in a prx prj or mpx file using Project KickStart or other softwareyou can open the project in Project KickStartTo open a project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click a file type (prxprj or mpx)

3 Navigate to the folder that contains the file4 Double-click the name of the file

Opening a Project KickStart 3 prj file converts it to a prx file

Generally prj files are stored in cprogram filesProject KickStart 3

The tasks in the converted Project KickStart 5 file will have the same start and finish dates anddurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way To have weekends as non working days open the working days calendar and markweekends as non working

Opening a mpx file converts it to a prx file

The tasks in each project have the same start and finish dates and durations

-o-

152

copy Experience In Software Inc 1995 - 2006

Dedication

I dedicate this software program to my new colleague

Kevin Ahlvin

Roy A Nierenberg President

-o-

153

copy Experience In Software Inc 1995 - 2006

Credits and Trademarks

Credits

Missak Koumoudjian Program Architect and Chief Programmer

Kevin Ahlvin Interface DesignAnn Kawamoto Quality AssuranceAlexander Setzepfandt Quality AssuranceJackie LeungJeffrey Chow

Programming Interns

Kevin Ahlvin Product Supervisor and CoordinatorJoseph Fusco Project Management Consultant and content

providerLisa RuffoloJoseph Fusco

Help System

Roy A Nierenberg President

Trademark

Project KickStart and Project KickStart Wizard are trademarks of Experience In Software Inc in the UnitedStates andor in other countries All rights reserved All other trademarks mentioned herein are the propertyof their respective owners

-o-

154

copy Experience In Software Inc 1995 - 2006

Uninstalling

You can uninstall Project KickStart 5 through the Control Panel AddRemove Programs Select ProjectKickStart 5 This starts the InstallShield Maintenance Program You should then remove all of theprogram files that were installed It will not erase your Project KickStart prx data files

If that does not work you can delete the Project KickStart files manually

Note

If you purchased Project KickStart and you want to return it for a refund follow the instructions forDe-activating the software at httpwwwprojectkickstartcomcontactreturnscfm

-o-

155

copy Experience In Software Inc 1995 - 2006

Using Past Projects

You can use past projects in two ways

If you have projects that are similar you can use a past project as a template for a new project In theWelcome window select Open a Project Open that project and Save As under a different name Nowyou can open up the renamed project and modify it for the current project

You can draw from several projects in the Similar Projects step First select projects that are similarand click Next Then select tasks from those projects and decide where they would fit into your currentproject

See Also

Opening a project Compatibility with earlier versions

-o-

156

copy Experience In Software Inc 1995 - 2006

Index

- - Change Working Schedule 85

- -prj file format 13

- A -About Linking Tasks (Pro Users) 59About Scheduling Tasks 55About the Gantt Chart 57ACT 120 92 122ACT 6 92 122ACT 7 or later 92 120Activate 14Activating Trial Version 14Add a New Person or Resource 39add a subtask 83add a task 83Add a Task or Subtask 47Add or Change Task Assignments 51Add or Change Task Details 52Add Subtask 63Add Task 63Add URL 49Additional Features in Task Data View (Pro Users) 68Additional Tools in Chart View (Pro Users) 71Adobe PDF 117Assignments tab 80Attachments 49Autolink tasks (Pro Users) 58

- B -Back 10borrow tasks 29

- C -Change Details for Linked Tasks (Pro Users) 81Change Project Start 63Change Task Dates 73Change Task Details 80Change the Appearance of the Task List 43Change the Display of the Schedule 61Change Timescale 63Change Working Schedule 63Chart view 57

157

copy Experience In Software Inc 1995 - 2006

Cloning projects 155Color 63 86Compatibility 13Compatibility with earlier versions 13convert projects 13Coordination 12Create and Print Task Reports 102Credits 153Credits and Trademarks 153critical path 88CSV 96Customer support 20Customer Support 20Customizing Project KickStart

- D -Dashboard 99Data Menu 145Dedication 152Delete 63delete a task 83demote 46dependencies 12 76

- E -Edit Menu 141Edit Notes and Attachments 63Edit or Substitute People 40Edit Task Information 63Email Task Reports 108End User License Agreement 16error 21Error Messages 21export from MindManager 136Export MPX Files 138Export to ACT 6 122Export to ACT 7 and Later 120Export to FastTrack Schedule 134Export to Microsoft Excel 128Export to Microsoft Outlook 123Export to Microsoft PowerPoint 130Export to Microsoft Project 132Export to Microsoft Word 125Export to Milestones Professional 135Export to Mindjet MindManager 136Export to SureTrak Project Manager 133Export to WBS Chart Pro 137

- F -FastTrack Schedule 134File Menu 140Fit to page 111Fit to Smallest Size 111

158

copy Experience In Software Inc 1995 - 2006

- G -Gantt chart 55 57General tab 80Goal 26Goal statements 26Goals 26Goals - Step 1 of 3 26Goals - Step 2 of 3 27Goals - Step 3 of 3 28goals library 26 89Goalsadd 26Goalsdelete 26Goalsedit 26Goalstasks for 27GoToMeeting 150 12

- H -Handouts 111Help Menu 147hyperlink 49

- I -Import ACT 92import contacts and users 92import Outlook contacts 94Import Outlook Contacts via CSV to the People Library (Pro Users) 96ImportCSVToPKSexe 96Indent 46Individual Assignments 102Introduction 7Introduction 7

- K -Knowledge Libraries 90

- L -lag time 81lead time 59 81library 89License Key 14link 59Link lines 59Link tasks 12 65linked tasks 59

- M -major activities 24Make Tasks Overlap (Pro Users) 87Manage a Library 90

159

copy Experience In Software Inc 1995 - 2006

Menu 140Microsoft Excel 128Microsoft Outlook 123Microsoft PowerPoint 130Microsoft Project 132Microsoft Project (95 or 98) 138Microsoft Visio 138Microsoft Word 125Milestone 69 79Milestones Professional 135Mindjet MindManager 136MindManager 136

- N -Name 23Name Your Project 23Navigating Project KickStart 10Next 10Notes and Attachments tab 80

- O -Objectives 26Obstacles 34Obstacles - Step 3 of 3 36Obstacles Library 89Open a Project 151Options 144Outdent 46Outdent and Indent arrows 63Outlook Calendar 123Overview

- P -Page Setup 107 116 100PDF 117people 31People - Step 3 of 3 28People Library 91phase 24phase dates 75Phase Dates Cannot Be Edited 75phases 24Phases - Step 1 of 2 24Phases - Step 2 of 2 25Phases Library 89Phases Goals People amp Obstacles 102PowerPoint presentation 130Pred 68Predecessor 68Predecessor tasks 59predecessors 76Print a Gantt Chart 111Print Dashboard Reports 99Print Preview 105Print Preview a Gantt Chart 115Print Reports 98Print Task Reports 102

160

copy Experience In Software Inc 1995 - 2006

Printer Setup 106Printing to an Adobe PDF file 117prj 13Pro 145Pro Edition 145Product support 20Project 23Project KickStart 3 prj file 151Project KickStart for Windows 7project name 23project start date 73project template 155project title 23promote 46promote and demote tasks 83

- Q -Quick Tour of Working with Linked Tasks (Pro Users) 76

- R -Red vertical line 69Redo 11Register Project KickStart 22Registering Project KickStart 22remove people 38Remove People from a Task 38reorder tasks 83Reorganize Tasks in Task Data View 83Repeat tasks on every page (for handouts) 111Reporting Technical Issues 21resource 31resources 31restore 34return 154risks 34RiskyProject 138

- S -Save As 101Save as HTML 109Save as RTF 110Save Gantt Chart Images 118Schedule 55Send Error Report 21similar projects 29spelling 53starter schedule 55Steps 7subtask 47Subtasks 46Succ 68Successor 68Successor tasks 59successors 76Summary bar 69Support 20SureTrak Project Manager 133

161

copy Experience In Software Inc 1995 - 2006

- T -Task Data view 57task dates 73Task Report 102Taskbar 69Taskbar with percent done 69Tasks 25Tasks in Phases 25Tasks Library 89team 31Technical support 20timescale 84Timescale Menu 146Tools Menu 143Trademark 153trademarks 153Trial 14

- U -unassigning 38Understand Chart View 69Understand Task Data View 66Undo 11UndoRedo Buttons 11uninstallUninstalling 154Unlink tasks 12 65Up and Down arrows 63Use Project KickStart to 8Use the Gantt Chart Toolbar 63Use the Planning Wizard 9Uses 8Using Past Projects 29 155

- V -Version View Menu 142Visio 138

- W -Wall chart 111WBS Chart Pro 137Welcome to Project KickStart 7Whats Due Next Month 99Whats Due Next Week 99Whats Due Today 99Whats New in Project KickStart Pro 5 11Windows Vista 20

162

copy Experience In Software Inc 1995 - 2006

copy Experience In Software 2008w w w projectkickstartcom

  • Table of Contents
  • Start Here Welcome to Project KickStart
    • Introduction
      • Welcome to Project KickStart
      • Use Project KickStart to
      • Use the Planning Wizard
      • Navigating Project KickStart
      • Whats New in Project KickStart Pro 5
      • Whats New in Project KickStart Pro 5 (Pro Users)
      • Compatibility with earlier versions
      • Activating Trial Version
        • Licenses and Support
          • End User License Agreement
          • Customer Support
          • Reporting Technical Issues
          • Register Project KickStart
              • Planning Projects
                • Name Your Project
                • Phases - Step 1 of 2
                • Phases - Step 2 of 2
                • Goals - Step 1 of 3
                • Goals - Step 2 of 2
                • Goals - Step 3 of 3
                • Similar Projects - Step 1 of 2
                • Similar Projects - Step 2 of 2
                • People - Step 1 of 3
                • People - Step 2 of 3
                • People - Step 3 of 3
                • Obstacles - Step 1 of 3
                • Obstacles - Step 2 of 3
                • Obstacles - Step 3 of 3
                  • Assigning People
                    • Assign Tasks to People
                    • Remove People from a Task
                    • Add a New Person or Resource
                    • Edit or Substitute People
                      • Organizing the Project Plan
                        • About Organizing Tasks
                        • Change the Appearance of the Task List
                        • Show or Hide Tasks in the Task List
                        • Move Tasks within the Task List
                        • Outdent and Indent Tasks
                        • Add a Task or Subtask
                        • Edit Tasks
                        • Add Task Notes and Attachments
                        • Add or Change Task Assignments
                        • Add or Change Task Details
                        • Check Spelling
                          • Scheduling Tasks in the Gantt Chart
                            • Scheduling Overview
                              • About Scheduling Tasks
                              • About the Gantt Chart
                              • Autolink tasks (Pro Users)
                              • About Linking Tasks (Pro Users)
                              • Change the Display of the Schedule
                              • Use the Gantt Chart Toolbar
                              • Use the Gantt Chart Toolbar (Pro Users)
                              • Understand Task Data View
                              • Additional Features in Task Data View (Pro Users)
                              • Understand Chart View
                              • Additional Tools in Chart View (Pro Users)
                                • Change Task Dates
                                • Phase Dates Cannot Be Edited
                                • Quick Tour of Working with Linked Tasks (Pro Users)
                                • Link and Unlink Tasks (Pro Users)
                                • Create a Milestone
                                • Change Task Details
                                • Change Details for Linked Tasks (Pro Users)
                                • Reorganize Tasks in Task Data View
                                • Change the Timescale of the Schedule
                                • Specify Working Days
                                • Change the Color of Taskbars
                                • Make Tasks Overlap (Pro Users)
                                • Manage Changes in Your Schedule (Pro Users)
                                  • Managing Libraries
                                    • Use a Library
                                    • Manage a Library
                                    • Manage the People Library
                                    • Import ACT Contacts and Users to the People Library
                                    • Import Outlook Contacts to the People Library
                                    • Import Outlook Contacts via CSV to the People Library (Pro Users)
                                      • Printing Reports
                                        • Printing Dashboards
                                          • Print Reports
                                          • Print Dashboard Reports
                                          • Page Setup
                                          • Save As
                                            • Printing Task Reports
                                              • Print Task Reports
                                              • Print Preview
                                              • Printer Setup
                                              • Page Setup
                                              • Email Task Reports
                                              • Save As HTML
                                              • Save As RTF
                                                • Printing Gantt Chart Reports
                                                  • Print a Gantt Chart
                                                  • Print Preview a Gantt Chart
                                                  • Page Setup
                                                  • Printing to an Adobe PDF file
                                                  • Save Gantt Chart Images
                                                      • Export Project Data
                                                        • Export to ACT
                                                          • Export to ACT 7 and Later
                                                          • Export to ACT 6
                                                            • Export to Microsoft Outlook
                                                            • Export to Microsoft Word
                                                            • Export to Word Processors (Other than Word)
                                                            • Export to Microsoft Excel
                                                            • Export to Microsoft PowerPoint
                                                            • Export to Microsoft Project
                                                            • Export to SureTrak Project Manager
                                                            • Export to FastTrack Schedule
                                                            • Export to Milestones Professional
                                                            • Export to Mindjet MindManager
                                                            • Export to WBS Chart Pro
                                                            • Export MPX Files
                                                              • Reference
                                                                • Menus
                                                                  • File Menu
                                                                  • Edit Menu
                                                                  • View Menu
                                                                  • Tools Menu
                                                                  • Options
                                                                  • Data Menu
                                                                  • Timescale Menu
                                                                  • Help Menu
                                                                    • Shortcuts
                                                                    • Share Project KickStart data
                                                                    • Open a Project
                                                                    • Dedication
                                                                    • Credits and Trademarks
                                                                    • Uninstalling the software
                                                                    • Using Past Projects
Page 4: Project KickStart Help File in PDF format

4

copy Experience In Software Inc 1995 - 2006

About the Gantt Chart 57 Autolink tasks (Pro Users) 58 About Linking Tasks (Pro Users) 59 Change the Display of the Schedule 61 Use the Gantt Chart Toolbar 63 Use the Gantt Chart Toolbar (Pro Users) 65 Understand Task Data View 66 Additional Features in Task Data View (Pro Users) 68 Understand Chart View 69 Additional Tools in Chart View (Pro Users) 71 Change Task Dates 73 Phase Dates Cannot Be Edited 75 Quick Tour of Working with Linked Tasks (Pro Users) 76 Link and Unlink Tasks (Pro Users) 78 Create a Milestone 79 Change Task Details 80 Change Details for Linked Tasks (Pro Users) 81 Reorganize Tasks in Task Data View 83 Change the Timescale of the Schedule 84 Specify Working Days 85 Change the Color of Taskbars 86 Make Tasks Overlap (Pro Users) 87 Manage Changes in Your Schedule (Pro Users) 88Managing Libraries 89 Use a Library 89 Manage a Library 90 Manage the People Library 91 Import ACT Contacts and Users to the People Library 92 Import Outlook Contacts to the People Library 94 Import Outlook Contacts via CSV to the People Library (Pro Users) 96Printing Reports 97 Printing Dashboards 98 Print Reports 98 Print Dashboard Reports 99 Page Setup 100 Save As 101 Printing Task Reports 102 Print Task Reports 102 Print Preview 105 Printer Setup 106 Page Setup 107 Email Task Reports 108 Save As HTML 109 Save As RTF 110 Printing Gantt Chart Reports 111 Print a Gantt Chart 111 Print Preview a Gantt Chart 115 Page Setup 116 Printing to an Adobe PDF file 117 Save Gantt Chart Images 118Export Project Data 119 Export to ACT 120 Export to ACT 7 and Later 120

5

copy Experience In Software Inc 1995 - 2006

Export to ACT 6 122 Export to Microsoft Outlook 123 Export to Microsoft Word 125 Export to Word Processors (Other than Word) 127 Export to Microsoft Excel 128 Export to Microsoft PowerPoint 130 Export to Microsoft Project 132 Export to SureTrak Project Manager 133 Export to FastTrack Schedule 134 Export to Milestones Professional 135 Export to Mindjet MindManager 136 Export to WBS Chart Pro 137 Export MPX Files 138Reference 139 Menus 140 File Menu 140 Edit Menu 141 View Menu 142 Tools Menu 143 Options 144 Data Menu 145 Timescale Menu 146 Help Menu 147 Shortcuts 148 Share Project KickStart data 150 Open a Project 151 Dedication 152 Credits and Trademarks 153 Uninstalling the software 154 Using Past Projects 155

6

copy Experience In Software Inc 1995 - 2006

Start Here Welcome to Project KickStart

7

copy Experience In Software Inc 1995 - 2006

Introduction

Welcome to Project KickStart

Whether yoursquore a novice or seasoned pro yoursquoll be amazed at how quickly you can create a thoughtfulcomprehensive task list and project schedule Using Project KickStart you can go from raw idea to aproject task list in 30 minutes You do not need any special project management training to use ProjectKickStart

The first thing youll want to do is

Open a project Click to open one of our sample projects

Start a new project Click to begin planning your own project

Open your last project If youve already created a project click this option to open your most recentproject

After that let Project KickStart show you the way Itrsquos easy to navigate Project KickStart with its intuitivegraphical interface--it feels like a coach is guiding you through each step

Next StepsProject KickStart guides you through the process of planning and scheduling your project On the top ofeach Project KickStart window are instructions explaining what to do Read the instructions enter your dataand then click the Next button in the lower-right corner of the window Additional help is always availablefrom the onscreen Advisor and Project KickStart Help

Sample ProjectsThe sample projects are completed projects that let you get a feel for Project KickStart If you find onesimilar to the project you want to create open it save it with a new name and then customize it to meetyour needs

-o-

8

copy Experience In Software Inc 1995 - 2006

Use Project KickStart to

Project KickStart is organized into three sections planning scheduling and exporting to other programs

Plan The Project KickStart graphical interface acts as a Planning Wizard guiding you through eightsteps for planning your project Some planning steps involve brainstorming to identify tasks that youmight otherwise overlook

Schedule The Project KickStart Gantt chart makes scheduling tasks fast and easy You can printtaskbars in color and save Gantt charts reports as images so you can email them to colleagues orinclude them in a report

Export Communicate your projects in a variety of ways by exporting project data to other applicationsincluding Microsoft Outlook With one mouse click you can include Project KickStart plans in aMicrosoft Word document Excel spreadsheet PowerPoint slide presentation and more

People are using Project KickStart to

Create process templates project reports to-do lists and more

Communicate project details to others through reports email and Gantt chart schedules

Ensure project buy-in by including the needs of team members in your plan

Consider project goals and obstacles in the planning process and prevent surprises later

-o-

9

copy Experience In Software Inc 1995 - 2006

Use the Planning Wizard

Project KickStart uses a Planning Wizard that guides you through eight steps for planning your project Tostep through the wizard click each icon on the Steps bar (on the left side of the Project KickStart window) inorder On each window t ips and advice are always available by clicking the Advisor button You click theNext button to continue

Name Each project has a name To start planning your project give it ashort descriptive name

Phases Consider how your project will break down into major activitiesor phases Start by listing your phases and then list the tasks thatbelong in each phase

Goals Goals are what you hope to accomplish in your project Enter orselect the goals for your project Then you can list any new tasks toachieve each goal

Similar Projects often have tasks in common In this step you canborrow tasks from past projects to help you plan this project Then youcan add any new tasks from a similar project to the phases of yourcurrent project

People List the people groups or things that might provide resourcesfor your project including yourself Then identify any new tasks thesepeople might do or suggest for your project

Obstacles Each project has obstacles you can overcome if youanticipate them List the obstacles you will face in your project and thenidentify any new tasks needed to avoid the obstacles

Assign Assign tasks to people and other resources

Tasks Change the order of your tasks add and delete tasks andcreate subtasks You can also edit tasks change assignments and addnotes

Schedule Schedule the tasks in your project To make schedulingeasier new projects open with a starter schedule beginning todaywhich you can customize to fit your project

-o-

10

copy Experience In Software Inc 1995 - 2006

Navigating Project KickStart

When you use the Planning Wizard you work with a step window similar to the following illustration

Steps bar Click a step button to perform a step in the Planning Wizard The selected button shows yourcurrent step

Name of your project Shows the name entered in the Name step

Menu bar Select options from the menu bar to work with your projects

Toolbar Click buttons to perform common tasks such as saving your project

Step instructions Indicate how to perform the current step

Library button Click to open a library for the current step For example click the Goals Library button toopen a library listing typical project goals

Back and Next buttons Click a button to return to the previous step or continue to the next step in thePlanning Wizard

Advisor button Click to see instructions tips and notes for completing the current step

-o-

11

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5

The following table outlines whatrsquos new in Project KickStart Pro 5

If you own a previous version of Project KickStart yoursquoll notice the new Pro version has a new look and feelAs you begin to check it out yoursquoll soon discover Project KickStart Version 5 is a lot more powerful thanprevious versions and comes with some great new features

FEATURE DESCRIPTION IMPROVED

NEW

Dashboard Reporting

Quickly assess what is due TodayNext Week or Next Month

X

Import Contacts Import from a comma separatedvalue (CSV) file

X

Templates Use as is or customize X

Gantt Chart Greater stability and functionality X

User Interface Contemporary look and colorscheme

X

Preferences Customize look and feel andprogram defaults

X

Productivity Pack Project template Word docs fornewbies

X

Exports Improved Outlook MindManager and ACTimproved data exchange

X

-o-

12

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5 (Pro Users)

This feature is available only in Project KickStart Professional

The following table outlines whatrsquos new in Project KickStart Pro 5

FEATURE DESCRIPTION IMPROVED NEW

Gantt Chart Task dependencies in Gantt chart X

Link tasks Show task dependencies X

Unlink tasks Remove task dependencies X

Add predecessors Add task predecessors X

Add successors Add task successors X

Project Coordination Link to GoToMeeting for onlinemeetings on projects

X

Project KickStart Pro now includes dependencies on the Gantt chart This sophisticated scheduling andproject management tool is new to Project KickStart Pro and is designed to make complex projectscheduling easy and straightforward

Use dependencies to handle scheduling demands delays and surprises without modifying every task inyour project Dependencies let you make adjustments as events change giving you a more robust scheduleand the opportunity to conduct what-if analysis

Suppose you are managing a landscaping project involving subcontractors and dozens of tasks One ofyour first tasks is to pave a path with flagstones but the shipment of flagstones is two days late Usingdependencies you can delay the path-paving task in a couple of clicks and Project KickStart Proautomatically updates the schedule for the remaining tasks

Although dependencies meet your advanced scheduling needs the Project KickStart Pro approach todependencies keeps them as simple as possible If you want to link a couple of tasks which are dependenton one another you can simply highlight the tasks and click the link icon

If you select the option of Autolinking tasks then when you display the Gantt chart the first time all tasksare pre-linked allowing you to adjust durations schedules of individual tasks and time between taskswhich is called Lead Time in Project KickStart Pro

Unlike other project management programs such as Microsoft Project Project KickStart Pro does notburden you with complicated error messages and various types of dependencies It provides only one typeof dependency finish-to-start which is the most common type This means you can fine-tune your scheduleas soon as you open the Gantt chartmdashwithout having to learn technical terms or advanced projectmanagement techniques

The Project Coordination functionality that we are providing is through GoToMeeting and is a chargedservice

Note

These features are in addition to those listed on the Whatrsquos New in Project KickStart 5 page

-o-

13

copy Experience In Software Inc 1995 - 2006

Compatibility with earlier versions

Project KickStart 5 can open and save projects in Project KickStart 4 prx file format (Same as ProjectKickStart 5)

Project KickStart 5 can open and convert projects saved in Project KickStart 3 prj file format You need tohave a licensed copy of Project KickStart 3 on your system to make the conversion

To open a prj project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click prj file type3 Navigate to the folder that contains the prj file Generally prj files are stored in cprogram filesProject

KickStart 34 Double-click the name of the file

Tips

The tasks in the converted Project KickStart 5 file will have the same start and finish dates and samedurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way (ie as working days) To have weekends as non working days click the Change WorkingSchedule button on the Gantt chart toolbar and mark weekends as non working

Note

Project KickStart 5 does not open and convert prj files from Project KickStart 1 or 2

-o-

14

copy Experience In Software Inc 1995 - 2006

Activating trial version

You may have obtained a FREE 20-day trial version of Project KickStart 5 from our website or from areseller

To convert your Trial Version to a Full Version youll need to purchase a License Key and to activate thesoftware

To activate Project KickStart 5 trial1 Start the Project KickStart trial

2 If you have not purchased your License Key yet click the Buy button to purchase online3 If you have purchased a License Key click the Activate button and copy and paste the License Key

that you received when you purchased Project KickStart as well as your name and email

15

copy Experience In Software Inc 1995 - 2006

4 You must be connected to the Internet and you must tell your Firewall to allow communication forPKS5Kickstartexe

Tip

Your License Key allows 2 activations per user One is for your primary computer and one is for asecond computer you use such as your laptop or home computer

-o-

16

copy Experience In Software Inc 1995 - 2006

Licenses and Support

End User License Agreement

EXPERIENCE IN SOFTWARE INC END USER LICENSE AGREEMENT AND WARRANTYDISCLAIMER

PROJECT KICKSTARTtrade STANDARD 5 AND PRO 5 EDITIONS

NOTICE This is a legally binding contract between you the end user and EXPERIENCE IN SOFTWAREINC

EXPERIENCE IN SOFTWARE INC (EIS or LICENSOR) LICENSES THE ENCLOSED SOFTWARETO YOU (USER or LICENSEE) ONLY UPON THE CONDITION THAT YOU ACCEPT ALL OF THETERMS CONTAINED IN THIS LICENSE AGREEMENT PLEASE READ THE TERMS CAREFULLY BYOPENING THIS PACKAGE BREAKING THE SEAL CLICKING ON THE ldquoAGREErdquo OR ldquoYESrdquo BUTTONOR OTHERWISE INDICATING ASSENT ELECTRONICALLY OR LOADING THE SOFTWARE YOUAGREE TO THE TERMS AND CONDITIONS OF THIS AGREEMENT IF YOU DO NOT AGREE TOTHESE TERMS AND CONDITIONS CLICK ON THE ldquoI DO NOT AGREErdquo ldquoNOrdquo BUTTON OR MAKE NOFURTHER USE OF THE SOFTWARE IF YOU DO NOT AGREE TO THESE TERMS THEN EIS ISUN-WILLING TO LICENSE THE SOFTWARE TO YOU IN WHICH EVENT YOU SHOULD RETURN THEFULL PURCHASED PRODUCT WITH PROOF OF PURCHASE TO LICENSOR OR THE DEALER FROMWHOM IT WAS ACQUIRED WITHIN 15 DAYS OF PURCHASE AND YOUR MONEY WILL BEREFUNDED

LICENSE AND WARRANTY

The software that accompanies this license (Software) is the property of EIS and is protected by copyrightand other intellectual property law Although EIS at all times owns the Software you will have certain rightsto use the Software after your acceptance of this license Except as may be modified by an addendumwhich may accompany or be added to this license your rights and obligations with respect to the use of thisSoftware are as follows

You may

(i) install and use one copy of the specified edition of Software and documentation on a single computerand only by one user (ldquoPrimary Userrdquo) If you have purchased multiple licenses for the Software asindicated as Quantity or Number of Licenses on the Invoice or electronic confirmation issued by EIS orits Resellers then at any time you may have as many copies of the Software in use as you have licenses The Software is ldquoin userdquo on a computer when it is loaded into the temporary memory (ie RAM) or installedinto the permanent memory (eg hard disk CD-ROM or other storage device) of that computer

(ii) install and use a second copy of the Software on a second computer for the limited and exclusive use ofthe Primary User

(iii) use the Software on a network provided that Licensee has a licensed copy of the Software for eachnamed user that can access the Software over that network

(iv) make one copy of the Software for archival purposes or copy the Software onto the hard disk of yourcomputer and retain the original for archival purposes

(v) after written notice to EIS transfer the Software on a permanent basis to another person or entityprovided that you retain no copies of the Software and the transferee agrees to the terms of this agreement

You may not

(i) rent lease copy distribute license or otherwise transfer the Software or its documentation to any otherparty Licensee may make a reasonable number of back-up copies for archival purposes only TheSoftware contains copyrighted material trade secrets and other proprietary material If Licensee has theright to duplicate the Software for multiple Users then Licensee must reproduce on all such copies of theSoftware the copyright notices and any other proprietary legends that were on the original copy of theSoftware or

(ii) decompile reverse engineer disassemble translate make any attempt to discover the source code ofthe Software or otherwise reduce the Software to a human perceivable form or modify network or create

17

copy Experience In Software Inc 1995 - 2006

derivative works based upon the Software or the documentation in whole or in part nor permit any otherparty to do so

Notwithstanding anything herein if the Software is lawfully acquired outside of the United States within ajurisdiction which is a member of the European Union subject to the EEC Council Directive 91250EEC ofMay 14 1991 Licensee agrees that within that jurisdiction it shall not and shall not allow any party onLicensees behalf to attempt to reverse engineer or decompile the Software into another computerlanguage except as expressly and specifically provided in the EEC Council Directive 91250EEC of May14 1991 Any and all information obtained during such lawful reverse engineering andor decompilingactivities including but not limited to the organization logic algorithms and processes of the Softwareshall be deemed to be the confidential and proprietary information of EIS

Licensee shall not make copies of the copyrighted Software documentation without the prior writtenpermission of EIS provided that for electronic transactions Licensee may make one (1) hard copy of suchdocumentation for each User

Intellectual Property and Duplication of Software

The Software contains copyrighted material trade secrets and other proprietary material If Licensee hasthe right to duplicate the Software for multiple Users then Licensee must reproduce on all such copies ofthe Software the copyright notices and any other proprietary legends that were on the original copy of theSoftware

Upgrades

To use a Product identified as an upgrade you must first be licensed for the product identified by EIS aseligible for the upgrade After upgrading you may no longer transfer the product that formed the basis foryour upgrade eligibility to another person or entity

Technical Support

Licensee must register the Software in order to be eligible for free technical support (including installationand registration of the product) during the first 90 days after purchase

Thirty Day Money Back Guarantee

If you are the original Licensee of this copy of the Software and are dissatisfied with it for any reason youmay return the complete product together with your receipt to EIS or an authorized dealer postageprepaid for a full refund at any time during the thirty-day period following the delivery to you of thePurchased Software

Export Law Assurances

You are responsible for complying with all trade regulations and laws both foreign and domestic Youacknowledge that none of the Software or underlying information or technology may be downloaded orotherwise exported or re-exported (i) into Afghanistan (Taliban-controlled areas) Cuba Iran Iraq LibyaNorth Korea Serbia (except Kosovo) Sudan and Syria or any other country subject to a US embargo or(ii) to anyone on the US Treasury Departments list of Specially Designated Nationals or the USCommerce Departments Denied Parties List or Entity List By using the Software you are agreeing to theforegoing and are representing and warranting that (i) no US federal agency has suspended revoked ordenied you export privileges (ii) you are not located in or under the control of a national or resident of anysuch country or on any such list and (iii) you will not export or re-export the Software to any prohibitedcounty or to any prohibited person entity or end-user as specified by US export controls as defined byEAR 15 CFR Parts 730-774 and BXA (httpwwwbxadocgov)

Data Collection and Privacy Policy

You acknowledge and agree that EIS may collect and retain information about you such as your nameaddress and e-mail address You also understand that EIS may employ other companies to performfunctions on our behalf such as fulfilling orders delivering packages sending postal mail and e-mailproviding marketing assistance and processing credit card payments These companies may have accessto personal information needed to perform their functions and may not use such information for otherpurposes By assenting to this agreement you agree that you have read and understand our Privacy PolicyFor more detailed information httpwwwprojectkickstartcomhtmlprivacy_statementhtm

Termination

This License is effective until terminated Licensee may terminate this License at any time by destroying allcopies of the Software and its documentation This License will terminate immediately without notice from

18

copy Experience In Software Inc 1995 - 2006

EIS if Licensee fails to comply with any provision of this License Upon termination Licensee must destroyall copies of the Software and its documentation and cease and desist from any further use of the Software

Limited Warranty

EIS warrants that the media on which the Software is distributed will be free from defects and that theSoftware shall perform substantially as described in its documentation for a period of sixty (60) days frompurchase Your sole remedy in the event of a breach of this warranty will be that EIS will replace anydefective media returned to EIS within the warranty period EIS does not warrant that the Software willmeet your requirements or that operation of the Software will be uninterrupted or that the Software will beerror-free

THE ABOVE WARRANTY IS EXCLUSIVE AND IN LIEU OF ALL OTHER WARRANTIES WHETHEREXPRESS OR IMPLIED INCLUDING THE IMPLIED WARRANTIES OF MERCHANTABILITY FITNESSFOR A PARTICULAR PURPOSE AND NONINFRINGEMENT OF INTELLECTUAL PROPERTY RIGHTSTHIS WARRANTY GIVES YOU SPECIFIC LEGAL RIGHTS YOU MAY HAVE OTHER RIGHTS WHICHVARY FROM STATE TO STATE AND COUNTRY TO COUNTRY

Disclaimer of Damages

REGARDLESS OF WHETHER ANY REMEDY SET FORTH HEREIN FAILS OF ITS ESSENTIALPURPOSE IN NO EVENT WILL EIS OR ITS RESELLERS BE LIABLE TO YOU FOR ANY SPECIALCONSEQUENTIAL INDIRECT OR SIMILAR DAMAGES INCLUDING BUT NOT LIMITED TO ANY LOSTPROFITS OR LOST DATA ARISING OUT OF THE USE OR INABILITY TO USE THE SOFTWARE EVENIF EIS HAS BEEN ADVISED OF THE POSSIBILTIY OF SUCH DAMAGES SOME STATES DO NOTALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FOR INCIDENTAL OR CONSEQUENTIALDAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAY NOT APPLY TO YOU IN NO CASESHALL EISS ITrsquoS RESELLERrsquoS LIABILITY EXCEED THE PURCHASE PRICE FOR THE SOFTWARE

SOME STATES AND COUNTRIES INCLUDING MEMBER COUNTRIES OF THE EUROPEANECONOMIC AREA DO NOT ALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FORINCIDENTAL OR CONSEQUENTIAL DAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAYNOT APPLY TO YOU

The disclaimers and limitations set forth above will apply regardless of whether you accept the Software

US Government Restricted Rights

DISTRIBUTION TO THE US GOVERNMENT This Software is commercial software developedexclusively at private expense This Software and the documentation are provided with RESTRICTEDRIGHTS applicable to private and public licenses alike Use duplication or disclosure by civilian agenciesof the US Government shall be in accordance with the Commercial Computer Software-Restricted Rightsclause at FAR 52227-19 Use duplication or disclosure by Department of Defense agencies is subjectsolely to the terms of this software licensing agreement pursuant to DFARS 2277202Contractormanufacturer of the Software is EXPERIENCE IN SOFTWARE INC 2029 Durant AveBerkeley CA 94704 USA

General

This Agreement shall be governed by the laws of the State of California without giving effect to principles ofconflict of laws You hereby consent to the exclusive jurisdiction and venue of the state courts sitting in SanFrancisco County California or the federal courts in the Northern District of California to resolve anydisputes arising under this Agreement This Agreement contains the complete understanding between theparties with respect to the subject matter hereof and supersedes all prior or contemporaneous Agreementsor understandings whether oral or written You agree that any varying or additional terms contained in anypurchase order or other written notification or document issued by you in relation to the Software licensedhereunder shall be of no effect No provision hereof shall be deemed waived or modified except in writing No EIS dealer agent or employee is authorized to make any amendment to this Agreement

The intellectual property protections the disclaimers of warranties and the limitation of damages shallsurvive termination The failure or delay of EIS to exercise any of its rights under this Agreement or uponany breach of this Agreement shall not be deemed a waiver of those rights or of the breach If any provisionof this Agreement is held invalid the remainder of this Agreement will remain in full force and effect

Should you have any questions concerning this Agreement or if you desire to contact EIS for any reasonplease write to EXPERIENCE IN SOFTWARE INC 2029 Durant Ave Berkeley CA 94704 USA

-o-

19

copy Experience In Software Inc 1995 - 2006

20

copy Experience In Software Inc 1995 - 2006

Customer Support

When you need help in solving a problem with the software Experience In Software is available to assistyou First check this help file for information on the part of the program you are having a problem withAlso take a look at the Web site for late-breaking technical support information wwwprojectkickstartcomsupporttechnical_supportcfm If you are a regustered user you can obtain support in the following ways

Web httpwwwprojectkickstartcomsupportemail_supportcfm E-mail supportprojectkickstartcom

Hours 900 am to 500 pm Pacific time Monday - Friday

To make the support process more efficient have the following information ready for the support staff

Provide your name phone number and email address

Describe the problem including any error messages

If reporting a potential bug describe what you did immediately before seeing the bug

Provide the Project KickStart version number and Build Date (Click Help on the menu bar and thenclick About Project KickStart)

Identify the version of Windows (Windows Vista etc) you are using

Notes

Our policy is to respond to support email within two business days If you have not received aresponse please double check that spam filters are blocking our messages to you If you maintain anincoming whitelist please allow all messages from the projectkickstartcom domain

Support is available in English only If you purchased a translated version please contact your localreseller for help in other languages

See Also

Reporting Technical Issues

-o-

21

copy Experience In Software Inc 1995 - 2006

Reporting Technical Issues

If Project KickStart 5 detects an error it will write a log of technical issues and then create a temporarymenu to the right of the Help menu which says Send Log to Technical Support You should immediatelyclick the menu and then click Yes to send the error log to us

Please fill in your email address so that we can get back to you with any questions about what caused theerror

Tip

If you have an Internet Security Program such as Norton Internet Security please allowPKS5Kickstartexe to communicate with the Internet to report the error

-o-

22

copy Experience In Software Inc 1995 - 2006

Register Project KickStart

To print this page click the Print button on the Help window toolbar

Register Project KickStart 5 for technical support upgrade information and software discounts You canregister by completing printing and then sending or faxing this form to Experience In Software You canalso register online at httpwwwprojectkickstartcomsupportregiscfm

Name _______________________________________________________

Title _______________________________________________________

Company _______________________________________________________

Address _______________________________________________________

CityStateZip ______________________________________________________

Country _______________________________________________________

Day Phone _______________________________________________________

Fax _______________________________________________________

E-mail _______________________________________________________

Purchased from __ Experience In Software __ Other ____________________

Number of people in company _ 1 to 25 _ 26 to 100 _ 101 to 1000 _ Over 1000

Which industry do you work in ______________________________________

Interested in a project management workshop for your company __ Yes __ No

Comments _______________________________________________________

_________________________________________________________________

_________________________________________________________________

Experience In Software 2029 Durant Ave Berkeley CA 94704

Send or FAX to (510) 644-3823

-o-

23

copy Experience In Software Inc 1995 - 2006

Planning Projects

Name Your Project

Before you start thinking about the tasks in your project yoursquoll want to give your project an appropriate titleIf you open an existing project you might want to edit or change the name of your project

To name your project1 In the Type a name for your project text box enter a name2 Click the Next button

Tips

You can enter up to 58 characters and more than one

Use short descriptive project names such as ldquoCompany Web Siterdquo

Avoid vague project names such as ldquoDatabase Projectrdquo or ldquoCDP-7rdquo especially if you plan to circulatereports to others

Enter your project title using uppercase letters if you want the title to stand out in reports

One way to reuse your projects is to open an existing project and then change its name in this stepAfter saving the project with a different name you can modify details to customize the project

See Also

Use the Planning Wizard

-o-

24

copy Experience In Software Inc 1995 - 2006

Phases - Step 1 of 2

After naming your project the next step in the Planning Wizard is to identify the major activities in yourproject Using phases helps organize tasks so that an obviously early task such as ldquoOrganize materialsrdquoappears before a later task such as ldquoReview final draftrdquo

To enter phases1 Type each phase one per line

OrClick the Phases Library button The Phases Library contains typical phases that many organizationsuse in the early middle and late stages of their projects Drag an entry from the Phases Library to thelist and then click the OK button to close the Phases Library

2 To insert a phase in the middle of the phases list click where you want to insert a new blank line andthen press the Insert keyTo edit the phase text double-click the phase

Tips

Start each phase name with an action verb as in ldquoBuild systemrdquo or ldquoWrite reportrdquo

Use actions that have clearly defined beginnings middles and ends For example you can scheduletasks like ldquoTest prototyperdquo more easily than tasks like ldquoPurchase high-quality partsrdquo

Note

Youll have the opportunity to edit phases later in the Tasks step For now continue planning thephases in your project

See Also

Use the Planning Wizard

Use a Library

Move Tasks within the Task List

-o-

25

copy Experience In Software Inc 1995 - 2006

Phases - Step 2 of 2

For each phase list all of the tasks that could be performed during that phase You can refine and organizethe tasks later in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each phase1 Type the tasks associated with the phase displayed in the Tasks for phase text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next phase in your project click the Next button If you prefer to work out oforder click the Tasks for phase list arrow and then click the phase you want

3 When you are finished entering tasks for the last phase in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

26

copy Experience In Software Inc 1995 - 2006

Goals - Step 1 of 3

Enter the goals for your project the objectives you hope to accomplish Then you can brainstorm anyadditional tasks that will help you meet these goals

To enter goals1 Type each goal one per line

OrThe Goals Library contains typical sample goals that you can customize Drag an entry from the GoalsLibrary to the list and then click the OK button to close the Goals Library

2 To insert a goal in the middle of the goals list click where you want to insert a new blank line and thenpress the Insert keyTo edit the goal text double-click the goal

3 Click the Next button

Tips

List goals that apply to the entire project such as Develop a high-quality system A goal such as Getthe contract signed applies only to an early phase

Write goals as actions you can measure For example Complete the project for $75000 or less ismore concrete and specific than Complete the project within budget Numbers make goal statementsreal

If youre not sure how to measure a goal use a range as in About 15 - 25 people will use the results ofthe project

See Also

Use the Planning Wizard

Use a Library

-o-

27

copy Experience In Software Inc 1995 - 2006

Goals - Step 2 of 3

For each goal list any new tasks needed to accomplish that goal You can refine and organize the taskslater in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each goal1 Type the tasks for accomplishing the goal displayed in the For the goal text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next goal in your project click the Next button If you prefer to work out of orderclick the For the goal list arrow and then click the goal you want

3 When you are finished entering tasks for the last goal in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

28

copy Experience In Software Inc 1995 - 2006

Goals - Step 3 of 3

After you identify new tasks for your project assign each new task to an appropriate phase

To assign new tasks to phases1 Click a task in the New tasks to achieve goals list (on the left)2 Click one or more phases in the Assign them to Phases list (on the right) to which the task belongs A

checkmark appears next to tasks youve assigned

If a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Note

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

29

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 1 of 2

Projects often have tasks in common The Similar Projects step makes it easy for you to borrow tasks fromother projects and add them to your current project

By default this step shows the Project KickStart (PRX) projects stored in the same folder as the currentproject including sample projects and those you already created

To select similar projects1 Review the projects in the list To sort the project names alphabetically click the Project Name header

Click the Project Name header again to sort the names in reverse order2 Click one or more projects in the list that contain tasks you want to use in the current project A

checkmark appears next to the projects you selected3 To list projects stored in a different folder on your system click the Browse button and then navigate to

the folder you want4 Click the Next button

If no projects seem related to your current project skip this step for now

Tips

The Similar Projects step becomes more helpful the more you use Project KickStart Every time yousave a project it becomes available for future use

Many projects share the same phases and tasks such as those for setting up a contract or purchasingequipment You can use Project KickStart to create these mini-projects or templates and then importtheir tasks into a new project during the Similar Projects step

-o-

30

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 2 of 2

After you select one or more projects containing tasks you might want to use assign those borrowed tasksto a phase in this project

To assign borrowed tasks to phases1 Click a task in the list on the left If a task includes subtasks click the plus icon to expand the list Click

the minus icon if you want to hide the subtasks To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more phases in the Assign tasks to phase(s) of your project list (on the right) to whichthe task belongs A checkmark appears next to tasks youve assigned

3 To assign one or more tasks to a new phase select the tasks click ltNew Phasegt in the Assign tasksto Phases of your project list and then type a name for the new phase

4 To select tasks from another project you selected as similar click the Tasks from Similar Projects listarrow click the project you want and then assign the tasks to phases

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also Edit Tasks

-o-

31

copy Experience In Software Inc 1995 - 2006

People - Step 1 of 3

Enter the names or descriptions of the people involved in your project Include key decision makers suchas executives or customers who must approve or consult with you about the project These are yourprojects resources In the next People step youll identify new tasks associated with these resources

To enter people1 Type each name or description one per line

OrIf you have stored information about people and other resources in the People Library click the PeopleLibrary button drag an entry from the library to the list and then click the OK button to close thePeople Library

2 To edit the people text double-click the name or description3 Click the Next button

Tips

Be consistent with the resource names in your projects For instance avoid using Richard in oneproject and Dick in another project when referring to the same person

Include names for people teams (such as Quality control team) departments (such as Manufacturing)companies (such as Acme Widgets Corp) or even equipment (such as wheat thrasher)

Note

Add people and other resource information to the People Library so that you can quickly drag resourcesfrom the library to any project You can even import people from your Outlook and ACT address books

See Also

Manage the People Library

Import ACT Contacts and Users to the People Library

-o-

32

copy Experience In Software Inc 1995 - 2006

People - Step 2 of 3

Now that you have defined the people needed to complete your project list any new tasks that eachresource might suggest or require

To enter new tasks for each person1 Type the new tasks associated with the person displayed in the Tasks For text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next person in your project click the Next button If you prefer to work out oforder click the Tasks For list arrow and then click the person you want

3 When you are finished entering new tasks for the last person in your project click the Next button tocontinue in the Planning Wizard

Tips

This step provides a good opportunity to get input from your resources directly and make sure theproject plan reflects the views of everyone on the team

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo Write the tasks roughly in the order that you will complete them You can reorganize the tasks later in

the Tasks step

Note

You assign people to tasks in the Assign Tasks and Schedule steps

See Also

Use a Library

Move Tasks within the Task List

Assign Tasks to People

-o-

33

copy Experience In Software Inc 1995 - 2006

People - Step 3 of 3

After you identify new tasks associated with the people in your project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by people list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

34

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 1 of 3

Every project has obstacles and risks that can affect its success List the major obstacles you face incompleting your project Then you can brainstorm any additional tasks that can help you overcome orminimize these problems

To enter obstacles1 Type each obstacle one per line

OrThe Obstacles Library contains typical sample obstacles that you can customize Drag an entry fromthe Obstacles Library to the list and then click the OK button to close the Obstacles Library

2 To insert an obstacle in the middle of the obstacles list click where you want to insert a new blank lineand then press the Insert key

3 To edit the obstacle text double-click the obstacle4 Click the Next button

Tips

Be creative when thinking of obstacles Highly imaginative obstacles can suggest realistic tasks Forexample Project manager kidnapped by aliens can lead to Project manager out of town forconference In Obstacles step 2 of 3 you can add the realistic activities as tasks You can delete theunrealistic obstacles later by returning to Obstacles step 1 of 3

Avoid listing too many obstacles even if they are realistic Hard core pessimists find it hard to getanything done

Edit and update the Obstacles Library so that you can quickly drag obstacles from the library to anyproject in your organization

See Also

Use a Library

-o-

35

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 2 of 3

After identifying the obstacles to completing your project determine how you can avoid these stumblingblocks List any new tasks you need to overcome or avoid each obstacle In this way you are developing acontingency plan for your project

To enter new tasks for each obstacle1 Type the new tasks associated with the obstacle displayed in the Obstacle text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next obstacle in your project click the Next button If you prefer to work outof order click the Obstacle list arrow and then click the obstacle you want

3 When you are finished entering new tasks for the last obstacle in your project click the Next button tocontinue in the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

You can reorganize the tasks and add notes later in the Tasks step

See Also

Use a Library

Move Tasks within the Task List

Add Task Notes and Attachments

-o-

36

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 3 of 3

After you identify new tasks for overcoming the obstacles to completing project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by obstacles list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

3 Click the Next button

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

37

copy Experience In Software Inc 1995 - 2006

Assigning People

Assign Tasks to People

After youve identified people working on your project you can assign tasks to each person or otherresource

To assign tasks to people1 Click a phase or task in the For each phase or tasks list (on the left)

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more people in the Assign some people list (on the right) who will perform the task Acheckmark appears next to tasks youve assigned

3 To assign a selected task to all of the people in your project click the All button4 To assign one or more tasks to a new person select the tasks click ltNew Persongt in the Assign

some people list and then type a name for the new person

To unassign a task

To unassign a task click the task and then click the highlighted person from which you want to removethe task You can assign that task to a different person if necessary You can also click the All buttonto remove a task from all of its assignments at the same time

Tip

Some users like to skip to the Tasks step before performing the Assign step That way they can edittheir list of tasks before assigning people and resources This helps them focus the project and givesthem a clearer idea of what must be done before committing resources

Notes

You can also assign tasks to people in the Tasks step and the Schedule step

You can assign tasks to non-personnel resources such as equipment (a CAD system or back hoe)facilities (a classroom or hotel) services (lab work or insurance) or materials (lumber or officesupplies) just as you assign tasks to people Click ltNew Persongt to add a new resource to the list

See Also

Remove People from a Task

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

38

copy Experience In Software Inc 1995 - 2006

Remove People from a Task

After assigning tasks you might need to remove people from a task or unassign them

To remove people from a task (unassigning)1 Click a phase or task in the For each phase or tasks list (on the left)

The people assigned to that phase or task are highlighted in the Assign some people list (on theright)

2 Click a highlighted person to remove or unassign that person from the taskWhen the person is no longer highlighted they are not assigned to the selected task

See Also

Assign Tasks to People

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

39

copy Experience In Software Inc 1995 - 2006

Add a New Person or Resource

If you realize that you want to assign some tasks to a person not included in the Assign some people listyou can add that person and assign tasks in the same step You can also add non-personnel resourcessuch as such as equipment (a CAD system or back hoe) facilities (a classroom or hotel) services (lab workor insurance) or materials (lumber or office supplies)

To add a new person or resource1 Select one or more phases or tasks in the For each phase or tasks list (on the left) 2 Click ltNew Persongt in the Assign some people list and then type a name for the new person or

resourceThis adds the new person or resource to the list and assigns the selected tasks to them

See Also

Assign Tasks to People

Remove People from a Task

Edit or Substitute People

Add or Change Task Assignments

-o-

40

copy Experience In Software Inc 1995 - 2006

Edit or Substitute People

If the people or resources in your project change you can replace them or edit their names anddescriptions

To edit or substitute people1 Click the People icon

You return to People step 1 of 32 In the list of people defined for the project double-click the person you want to edit or replace or click

the name and press F23 Edit the name or description of the person

When you return to the Assign step the name of the person appears as you changed it

See Also

Assign Tasks to People

Remove People from a Task

Add a New Person or Resource

Add or Change Task Assignments

-o-

41

copy Experience In Software Inc 1995 - 2006

Organizing the Project Plan

About Organizing Tasks

In the Tasks step you work with an outline of your project plan Here you can easily edit and reorganizetasks spell check and even add notes and attachmentsClick the following illustration to see tips for using this window

Edit the Task List to Consolidate and delete tasks Add subtasks Add or change task assignments Add follow-up notes to tasks Add or change attachments Review the order of the tasks in each phase and move tasks up or down so that they progress

sequentially Review task descriptions to make sure they are clear and that all the team members will understand

them Convert vague tasks such as reminders and open issues to task notes

Notes

Some users like to revise their Task List before they assign resources You can go to the Task List atany time while you are using Project KickStart

Each project created with Project KickStart can contain up to 1000 tasks

See Also

Change the Appearance of the Task List

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

Add Task Notes and Attachments

Add or Change Task Assignments

Add or Change Task Details

-o-

42

copy Experience In Software Inc 1995 - 2006

43

copy Experience In Software Inc 1995 - 2006

Change the Appearance of the Task List

You can change the appearance of the Task List so you can work with it more effectively

To add a column

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task ListBy default the Task List shows the Task Name Assignments and Notes columns You can also showCost and Done columns

To hide a column

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

To move a column

Drag a column heading to a new position in the Task List

To change the column width

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Show or Hide Tasks in the Task List

-o-

44

copy Experience In Software Inc 1995 - 2006

Show or Hide Tasks in the Task List

To hide tasks or subtasks

To hide the subtasks for a task click the minus icon next to the task

To hide all the tasks in the Task List and show only phases click all the minus icons next to thephases

To show tasks or subtasks

To show the subtasks for a task click the plus icon next to the task

To show the tasks for a phase click the plus icon next to the phase

See Also

Change the Appearance of the Task List

-o-

45

copy Experience In Software Inc 1995 - 2006

Move Tasks within the Task List

In the Tasks step you can reorganize the tasks in your project so that they better represent the work youand your team plan to do In particular you should review the order of the tasks in each phase and move tasks up and down so thattasks follow in a sequential order Use the Up and Down Arrow buttons to move the tasks

To reorder tasks1 Click a task or phase to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youmove must be next to each other

2 Click the Up Arrow button to move a task up one rowOrClick the Down Arrow button to move a task down one row

Note

When you move a bolded phase you move the phase and all of its tasks at the same time

See Also

Outdent and Indent Tasks

-o-

46

copy Experience In Software Inc 1995 - 2006

Outdent and Indent Tasks

Subtasks are smaller parts of tasks Use subtasks when you need to break tasks down into moremanageable parts In the Task List you can turn a task into a subtask by indenting it You can also add anew subtask to the Task ListIf your Task List contains subtasks you can turn a subtask into a task by outdenting itUse the Outdent and Indent buttons to promote (outdent) and demote (indent) tasks

To promote and demote tasks1 Click a phase task or subtask to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youpromote or demote must be next to each other

2 Click the Outdent button to promote the selected tasksOrClick the Indent button to demote the selected tasksYou can also right-click an item in the Task List and then click Outdent or Indent on the shortcut menu

Tips

When you promote (outdent) a task it becomes a phase and its subtasks become tasks When youpromote a subtask it becomes a task

When you demote (indent) a phase it becomes a task and its tasks become subtasks When youdemote a task it becomes a subtask

Notes

You can have up to 10 levels of subtasks in your project

Use Task Notes instead of subtasks for task comments or additions that are not actually work items

See Also

Move Tasks with the Task List

Add a Task or Subtask

-o-

47

copy Experience In Software Inc 1995 - 2006

Add a Task or Subtask

If you realize you want to add another task to the Task List use the Add Task button A subtask is a smaller part of a task Use subtasks when you need to break tasks down into moremanageable partsTo add a subtask use the Add Subtask button

To add a task1 Click a task and then click the Add Task button right-click a task and then click Add Task on the

shortcut menu or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskProject KickStart numbers the new task in the proper sequence

To add a subtask1 Click a task and then click the Add Subtask button right-click a task and then click Add Task on the

shortcut menu or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtask3 Project KickStart numbers the new subtask in the proper sequenceNote

To add a new phase click a phase and then click the Add Task button

See Also

Outdent and Indent Tasks

-o-

48

copy Experience In Software Inc 1995 - 2006

Edit Tasks

Edit tasks in the Task List to fine tune your project You can edit the names of the phases tasks andsubtasks delete tasks and cut copy and paste task information

To edit task names1 Click the phase task or subtask you want to edit and then press the F2 key2 Type to edit the text3 To undo an edit click the Undo button

To delete a task

Click the task you want to delete and then press the Delete key or click the Delete button Or

Right-click a task and then click Delete Row on the shortcut menu

To cut copy and paste tasks1 Select the tasks you want to cut or copy Use Shift-click or Ctrl-click to select more than one task

2 Click the Cut button (Ctrl-X) or click the Copy button (Ctrl-C )

3 Click where you want to insert the tasks and then click the Paste button (Ctrl-V)

Tip

If your project includes some of the same tasks repeated in different phases save time by copying rowsof tasks and pasting them to another phase

Notes

You can also edit task names using the Task Information dialog box To open this dialog boxdouble-click a task or click a task and then click the Edit Task Information button

If you delete a phase you also delete its tasks and subtasks If you delete a task you also delete itssubtasks Project KickStart warns you before deleting tasks or subtasks and gives you a chance tocancel the deletion

See Also

Add Task Notes and Attachments

Add or Change Task Assignments

-o-

49

copy Experience In Software Inc 1995 - 2006

Add Task Notes and Attachments

You might find that some of your tasks are actually more notes than tasks For example Remember tocheck Daves specifications might work better as a note than a task especially if it could take several daysto catch up with Dave but only a few minutes to review his specs By using notes you clarify your projectand increase your chances for success An attachment is a document graphic or any other type of file related to a task For example to a tasksuch as Review proposal you can attach the proposal document Or you can attach a hyperlink to a pageon a web site

To add a note or attachment to a task1 Double-click the Notes column next to the task The Task Information dialog box opens to the Notes

and Attachments tab2 In the Enter a Note box type in or edit the task note (Press Enter to insert line break)3 To attach a file click the Add Files button In the Select File to Attach dialog box navigate to the file

you want and then click the Open button The filename appears in the Add Attachments box with apaperclip icon

4 To insert a hyperlink click the Add URL button In the Insert Hyperlink dialog box type in the URL youwould like to link to The URL appears in the Add Attachments box with a paperclip icon

5 Click the OK button

To open or remove an attachment1 Open the Notes and Attachments tab in the Task Information dialog box2 To open an attachment double-click the filename in the Add Attachments box3 To delete an attachment click the attachment in the Add Attachments box and then click the Remove

button

To change a task into a task note1 Copy (Ctrl-C) the text of the task you want to change into a note2 Double-click the task to which you want to add the note3 In the Task Information dialog box click the Notes and Attachments tab and add paste the text in the

Enter a Note box Close the Task Information dialog box4 In the Task Name column delete the original task that how appears as a note for a different task

Tips

Use notes to keep track of the operational details of a project the little nagging details that are criticalto success

Although the Task List provides plenty of room for notes it is best to keep your notes concise

Some tasks might benefit from instructional notes those that explain what to do in a task or how tosuccessfully complete a task

You can also include a hyperlink in a note by typing httpxxx (where xxx is an e-mail or Web address)In Outlook Word Excel or your browser the hyperlink will be active You can click the link to godirectly to that site or to send an e-mail to that address

Note

You can also open the Notes and Attachments tab in the Task Information dialog box by clicking atask and then clicking the Edit Notes and Attachments button or by double-clicking a task to openthe Task Information dialog box and then clicking the Notes and Attachments tab

See Also

Edit Tasks

Add or Change Task Assignments

Change Task Details in the Gantt chart

50

copy Experience In Software Inc 1995 - 2006

-o-

51

copy Experience In Software Inc 1995 - 2006

Add or Change Task Assignments

The Assignments column in the Task List shows the people and other resources assigned to each task

To add or change a task assignment1 Double-click the Assignments column next to the task The Task Information dialog box opens to the

Assignments tabThe Assignments tab lists all of the people and resources in your project If this task is already assignedto people they are highlighted on the Assignments tab

2 To assign this task to another person or resource click the resource name in the Assignments list3 To remove (unassign) this task from a person or resource click a highlighted name in the Assignments

list4 To add a person and assign the task at the same time click ltNew Persongt in the Assignments list

and then enter the name of the new person5 Click the OK button

Note You can also open the Task Information dialog box by clicking a task and then clicking the Edit Task

Information button to or by double-clicking a task

-o-

52

copy Experience In Software Inc 1995 - 2006

Add or Change Task Details

Besides task names notes and assignments you can include cost and done details about tasks In theSchedule step you can also include start and finish dates and durations

To add task details

1 Click a task and then click the Edit Task Information button or double-click the task you wantThe Task Information dialog box opens

2 Enter Cost or Done informationCost Enter the cost associated with this task For example you could enter $150 as the cost for a tasknamed Purchase photo CD Done Click the list arrow to select 0 25 50 75 or 100 or enter the percentage you want such as33

3 Click the OK button

To show or hide task details

Right-click a column heading to open a shortcut menu and then click Cost or Done In the shortcutmenu a checkmark appears next to columns that are displayed in the Task List

To edit task details

Open the Task Information dialog box (click a task and then click the Edit Task Information button or double-click the task you want)

Or

Double-click the Cost or the Done entry to update these details directly in the Task List

Notes

The Cost amount appears with the currency symbol set for your system (in the Regional and LanguageOptions dialog box of the Windows Control Panel)

Project KickStart calculates the running totals for the tasks within a phase and displays this total in theCost column for the phase When you create and print Task reports the total costs for the entire projectappear at the end of the Cost column

See Also

Edit Tasks

Print Task Reports

-o-

53

copy Experience In Software Inc 1995 - 2006

Check Spelling

Spell check your tasks and notes before you print reports or export to other software

To check the spelling of tasks and notes

Click the Check Spelling button on the Project KickStart toolbarOr

Click Tools on the menu bar and then click Spelling

Notes

Spell checking updates entries on the Task List and the Gantt chart (the Schedule step) It can alsocheck the spelling of intermediate entries such as goals and tasks to accomplish goals if you spellcheck during those steps

Spell checking does not check the names of people on the People List or the contents of the PeopleLibrary

-o-

54

copy Experience In Software Inc 1995 - 2006

Scheduling Tasks in the Gantt Chart

55

copy Experience In Software Inc 1995 - 2006

Scheduling Overview

About Scheduling Tasks

In the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the other

You work with the Gantt chart using the familiar Task Data view in the left pane or the graphical Chart viewin the right pane To adjust the schedule to fit your project set the project start date in the toolbar moveand resize the taskbars in the Chart view or change the start and finish dates or durations of individualtasks in the Task Data view

Click the following illustration to see general tips for using the Gantt chart See About the Gantt Chart formore details

In the Schedule step you can

Change a start date for the project Set start and finish dates or durations for tasks Change the timescale of the schedule Change the working schedule to specify which days are nonworking days such as weekends and

holidays Fine-tune the organization of the phases tasks and subtasks Color-code tasks to identify assignments critical deadlines or other information at a glance Insert milestones to indicate events that mark a moment in time such as the approval of a design Review and edit task details including task name assignments notes and attachments Hide or show task data columns in the left pane Export project data to other software applications

Tip

56

copy Experience In Software Inc 1995 - 2006

To save time you can reuse projects such as one for a trade show and create an updated scheduleby changing the project start date in the Schedule step

See Also

About the Gantt Chart

Understand Task Data View

Understand Chart View

-o-

57

copy Experience In Software Inc 1995 - 2006

About the Gantt Chart

The Gantt chart provides two views of your project schedule The Task Data view in the left pane lists thesame task information as in the Tasks step but now includes durations and start and finish dates TheChart view in the right pane displays taskbars and symbols to represent the same information You canchange the schedule information by working directly in the Task Data view and Chart view or by using theGantt Chart toolbarClick the following illustration to see general tips for using this window

-o-

58

copy Experience In Software Inc 1995 - 2006

Autolink tasks (Pro Users)

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatProject KickStart Pro does not assume that you want to link all of the tasks in a serial manner (one after theother) when you get to the Gantt chart Indeed many users want that behavior and many do notTo accomodate both types of users you can set whether you want the program to Autolink tasks In theTools menu select Autolink tasks Thereafter in all your projects when you get to the Gantt chart for thefirst time the tasks will be linked in a serial mannor

-o-

59

copy Experience In Software Inc 1995 - 2006

About Linking Tasks

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatWhen you link tasks the Gantt chart shows additional information about the tasks Click the followingillustration to see general tips for using linked tasks

Task Data view Chart view Description

Predecessor tasksA predecessor task is onethat you must completebefore you can start thenext task For exampleTask 2 - Prepare soil isthe predecessor to Task3 - Plant shrubs becauseyou need to prepare thesoil before you can plantthe shrubs

Successor tasksWhen you finish onelinked task you can moveonto the next onemdashthesuccessor task Forexample the successorfor Task 2 ndash Prepare soilis Task 3 ndash Plant shrubsand the successor forTask 3 is Task 4 ndash MulchLink linesThe first task isscheduled for one dayand the second one forthe next day In additionthe link line and arrowshow that the first taskmust end before thesecond one can start

These linked tasks arescheduled for the sametime

60

copy Experience In Software Inc 1995 - 2006

These tasks which aredependent on earliertasks and the last twotasks are also scheduledfor the same time

See Also

About the Gantt Chart

Autolink tasks

Make tasks overlap

-o-

-o-

61

copy Experience In Software Inc 1995 - 2006

Change the Display of the Schedule

You can change the onscreen appearance of the schedule so you can work with it more effectively Thefollowing illustration shows the Schedule window with the Steps bar closed and only the task number taskname and duration displayed in the Task Data view This provides more room to display the Gantt chart

To show or hide the Step bar or Project KickStart toolbar

Click View on the menu bar and then click Steps Bar to show or hide the vertical Steps bar on the leftof the Project KickStart window

Click View on the menu bar and then click Tool Bar to show or hide the Project KickStart toolbarwhich appears just below the menu bar In the View menu a checkmark appears next to the items displayed in the Project KickStart window

To display more or less of the Task Data view or Chart view

Drag the splitter bar between the Task Data view and the Chart view

To change the timescale in the chart

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years

To add a column to the Task Data view

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task Data viewBy default the Task Data view shows the Info Task Name Days Start and Finish columns Youcan also show Done Cost and Assignments columns

To hide a column in the Task Data view

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

62

copy Experience In Software Inc 1995 - 2006

To change the column width in the Task Data view

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Understand Task Data View

Understand Chart View

-o-

63

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

-o-

64

copy Experience In Software Inc 1995 - 2006

65

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Some features in this topic are available only in Project KickStart Professional

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view In Project KickStart Professional you also use the Gantt chart toolbar to linkand unlink tasks

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysLink Tasks (Pro Users)Link the selected tasksUnlink Tasks (Pro Users)Unlink the selected tasksChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

See Also

Use the Gantt Chart Toolbar

-o-

66

copy Experience In Software Inc 1995 - 2006

Understand Task Data View

The following illustration shows all the columns of information you can display in Task Data view

The Task data columns are the same as in the Tasks step but also include date information

Row number

Info Shows an icon if a note attachment or both are associated with the task Double-click anicon to view or edit the associated information

Task Name Name of the phases tasks and subtasks Double-click a task name to edit it directly

Days The amount of time it takes to complete the task If you change the number of days for a taskProject KickStart changes the Finish date accordingly

Start Date this task starts Double-click a Start date and then click the list arrow to open a calendar andselect a different date This also changes the Finish date

Finish Date this task ends Double-click a Finish date and then click the list arrow to open a calendar andselect a different date This changes the task duration shown in the Days column

Done Percentage of the phase task or subtask completed Show progress for any task by entering apercent of up to 100

$ Cost Cost for each task summed in the appropriate phase row Reports include total costs for theproject when you select the Cost column in the Create and Print Task Reports dialog box or the Createand Print Gantt Chart Report dialog box The Cost appears with the currency symbol set for your system(in the Regional and Language Options dialog box of the Windows Control Panel)

Assignments People and other resources assigned to the task Double-click an assignment to open theTask Information dialog box to the Assignments tab where you can add and change assignments

Tip

A task with a duration of zero (0) days is a milestone See Create a Milestone for more information

Notes

By default Task Data view displays all the columns the Info Task Name Days Start and Finish Done Cost and Assignments columns Some of these columns might be hidden by the Gantt chartview To hide columns right-click a column heading to open a shortcut menu and then click the columnyou want to hide In the shortcut menu no checkmark appears next to columns that are hidden

To change the width of a column drag a splitter bar in the column heading row or double-click a splitterbar to have the column accommodate its longest entry

As in the Tasks step expand phases and tasks by clicking the plus icon and collapse phases andtasks by clicking the minus icon

See Also

67

copy Experience In Software Inc 1995 - 2006

Understand Chart View

Change Task Dates

-o-

68

copy Experience In Software Inc 1995 - 2006

Additional Features in Task Data View

These features are available only in Project KickStart Professional

In Project KickStart Pro you can view two columns of information in addition to the nine columns availablein the Project KickStart Standard These two additional columns are labeled Pred (for Predecessor) andSucc (for Successor) The following illustration shows a typical Task Data view with these additionalcolumns

Besides the nine columns of information shown in Task Data view in Project KickStart Standard you canalso show the following information in the Professional version

Pred Indicates which task is the predecessor to the current task Double-click a task number in the Predcolumn to change it

Succ Indicates which task is the successor to the current task Double-click a task number in the Succcolumn to change it

Notes

When you link tasks Project KickStart assigns predecessors and successors according to their order inthe Task Data view

When you move a linked task in the Task Data view the predecessor and successor do not changeFor example in the above illustration if you move Task 3 ndash Plan design so it becomes Task 2 itspredecessor remains Land survey and its successor remains Engineering You can change these bydouble-clicking the task number in the Pred or Succ column and then entering a new number

See Also

Understand Task Data View

-o-

69

copy Experience In Software Inc 1995 - 2006

Understand Chart View

The following illustration shows a daily schedule in Chart view Point to the illustration to display text thatdefines the chart elements

Summary bar Summarizes the tasks below it and extends from the earliest start date(where the first triangle in the summary bar appears) to the latest finish date (where the last triangleappears) If a phase has tasks the summary bar appears in the phase row to summarize the tasks If atask has subtasks the summary bar appears in the task row to summarize the subtasks

To reschedule a phase and all of its tasks (or a task and all of its subtasks) click the summary bar and dragit to the left or right until it spans your desired set of dates This changes the earliest start date and latestfinish date in that phase and keeps the same duration And all the tasks move with the change of thephase

Taskbar Shows the length and scheduled dates for a task To change the duration of a taskresize the taskbar click the taskbar and then drag its left edge to schedule a different start date or drag itsright edge to schedule a different finish date

To reschedule a task without changing the duration drag the taskbar to a different date in the chart

Taskbar with percent done If you enter a Done amount in the Task Data view a progress barin the taskbar indicates the amount of the task completed

Red vertical line Indicates todays date

Milestone Indicates a task with a zero duration Milestones mark an event that must be reflected inyour project plan such as the approval of a design or an assembly line startup You can drag the left edgeof a milestone icon to stretch it into a taskbar The milestone becomes a task with a start and finish date

Notes

Because a summary bar summarizes the tasks below it you cannot resize a summary bar

To scroll the schedule use the vertical and horizontal scroll bars or the green drag bar at the top of theChart view

The shaded days in the Chart view indicate nonworking days To set which days are working andnonworking see Specify Working Days

70

copy Experience In Software Inc 1995 - 2006

-o-

71

copy Experience In Software Inc 1995 - 2006

Additional Tools in Chart View

These features are available only in Project KickStart Professional

If you use Project KickStart Pro the Chart view displays lines and arrows to show linked tasks The linklines and arrows show the relationships dependencies between one linked task and another

Besides the summary bar taskbar and other information provided in Project KickStart Standard Chart viewin the Professional version also provides the following information

The first task is scheduled for one day and the second one for the next day In addition the link line andarrow show that the first task must end before the second one can start

These linked tasks are scheduled for the same time However the first task must end before the secondone can start

The first two tasks are scheduled for the same time and must be completed before the third task can start

These linked tasks are scheduled for the same time However the second task must end before the firstone can start

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

Understand Chart View

-o-

72

copy Experience In Software Inc 1995 - 2006

73

copy Experience In Software Inc 1995 - 2006

Change Task Dates

You can revise a project schedule by changing task dates in the Task Data view or the Chart view You canalso reschedule an entire project by changing the projects start date

To change the project start date1 Click the Project Start list arrow to open a calendar

The calendar highlights the selected date and outlines todays date2 Find the date you want using the left and right scroll arrows to view a different month and then click the

date

To change task dates in Task Data view1 Double-click the Start or Finish date for a task

2 Then edit the date (you can edit the day month or year) OrClick the list arrow to open a calendarThe calendar highlights the selected date and outlines todays date

3 Find the date you want using the left and right scroll arrows to view a different month and then click thedateProject KickStart changes the Start and Finish dates according to your selection updates the durationof the task in the Days column and adjusts the taskbar in the Chart view

To change task dates by changing the duration in Task Data view

Double-click the Days column for a task and then enter the number of days it will take to complete thetaskProject KickStart changes the Finish date of the task and adjusts the taskbar in the Chart view

To change task dates in Chart view

Resize a taskbar click the taskbar and then drag its left edge to schedule a different start date or dragits right edge to schedule a different finish dateProject KickStart updates the summary bar in Chart view and the task dates and duration in the TaskData view

To reschedule a task without changing the duration drag the taskbar to a different date You can alsodrag a summary bar to reschedule a phase and all of its tasks (or a task and all of its subtasks) so itspans a different set of datesProject KickStart updates the task dates and duration as necessary in the Task Data view

To change task dates in the Task Information dialog box1 Open the Task Information dialog box (Right-click a task and then click Task Information or click a

task and then click the Edit Task Information button )2 Click the General tab3 In the Dates section change the following information as necessary

Start Click the Start list arrow to open a calendar and then click the appropriate start dateFinish Click the Finish list arrow to open a calendar and then click the appropriate finish dateDays Enter a number or click the spin arrows to set the task durationMilestone Select the Milestone check box if you want this task to be a milestone (A milestone is atask with a zero duration and marks an event such as the approval of a design)

Notes

You cannot delete the Start or Finish date of a task If you want to specify that a task has no durationconvert it to a milestone

When working with a calendar to schedule a start or finish date click the Today date text (where date

74

copy Experience In Software Inc 1995 - 2006

is todays date) to select todays date

See Also

Understand Task Data View

Understand Chart View

Create a Milestone

-o-

75

copy Experience In Software Inc 1995 - 2006

Phase Dates Cannot Be Edited

You cannot change the bold phase dates in the Task Data view of the Gantt chart They are a summary ofthe task dates for a particular phase and are view only You can revise phase dates by changing task dateswithin the phase

To change phase dates in Chart view

You cannot directly resize a summary bar You can extend or move the blue task barswithin a phase on the chart and Project KickStart updates the summary bar

To reschedule a phase on the chart drag the summary bar to a new date and all of its tasks (or a taskand all of its subtasks) will move with it

-o-

76

copy Experience In Software Inc 1995 - 2006

Quick Tour of Working with Linked Tasks

This feature is available only in Project KickStart ProfessionalIn the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the otherIn addition Project KickStart Pro links the tasks for you so when you open the Gantt chart you see a linkedwaterfall similar to the one shown below Besides providing a schedule that starts in a cascade with eachtask lasting one day each task is linked to the next task

You work with the Gantt chart either using the Task Data view in the left pane or the graphical Chart view inthe right pane To adjust the schedule to fit your project set the project start date in the toolbar move andresize the taskbars in the Chart view or change the start and finish dates or durations of individual tasks inthe Task Data view See About Scheduling Tasks for detailsNext fine-tune the dependencies in your project by you can linking and unlinking tasks changing theirpredecessors and successors and setting lead times For example if one task is not dependent onanother you can unlink the tasks If another task canrsquot start until two other tasks are finished you can add apredecessor to that task in which case the two tasks will be linked

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

To fine-tune the linked tasks To change the scheduled start and end dates of linked tasks move and resize taskbars in the Chart

view or change the number of days or the Start date in the Task Data view To display predecessor and successor information in the Task Data view right-click any column

heading and then click Pred or Succ To change the predecessor for a task double-click the number in the Pred column for the task and

then enter the number of a different task To change the successor for a task double-click the number in the Succ column for the task and then

77

copy Experience In Software Inc 1995 - 2006

enter the number of a different task To add another predecessor or successor to a task click in the appropriate column for the task and

then enter the number of another task To change the details of a linked task open its Task Information dialog box To do so right-click the

task and then click Task Information on the shortcut menu or click a task and then click the Edit TaskInformation button See Change Details for Linked Tasks

In the Task Information dialog you can also specify the predecessor(s) of a task and lead time(s) of thetasks

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

About Scheduling Tasks

About Linking Tasks (Pro Users)

Use the Gantt Chart Toolbar (Pro Users)

Manage Changes in Your Schedule (Pro Users)

-o-

-o-

78

copy Experience In Software Inc 1995 - 2006

Link and Unlink Tasks

These features are available only in Project KickStart Professional

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

See Also

About Linking Tasks

Quick Tour of Working with Linked Tasks

-o-

79

copy Experience In Software Inc 1995 - 2006

Create a Milestone

A milestone Indicates a task with a zero duration Milestones mark an event that must be reflected in yourproject plan such as the approval of a design or an assembly line startup

To create a milestone in the Task Data view

Double-click the Days number for a task and then enter 0 (zero)Or

Open the Task Information dialog box click the General tab and then click to insert a checkmark inthe Milestone check box

In the Chart view Project KickStart changes the taskbar to a milestone icon To create a milestone in Chart view

Click a taskbar and then drag to shrink the taskbar to a milestone icon In the Task Data view Project KickStart changes the Days for this task to 0 (zero)

Notes

To change a milestone into a task you change its duration or start and finish dates See Change TaskDates for instructions

To move a milestone in Chart view click the milestone icon on the upper left corner of the milestoneicon With the left mouse down move the icon to another date and release the mouse

To move a milestone in the Task Data view change the start date or the finish date and the milestonewill move

-o-

80

copy Experience In Software Inc 1995 - 2006

Change Task Details

You can use the Task Information dialog box to change the following task details in Task Data view

Task properties including the task name cost for completing the task and the percent completed

Dates including the start and finish dates duration and whether to convert the task to a milestone

Assignments

Notes and attachmentsYou can also edit the task name days dates costs and Done directly by clicking items in the task datacolumns

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button 2 Click the appropriate tab and then change the task details

General tab Change the task name and enter or change the cost associated with the task To changethe amount of the task completed click the Done list arrow and then select a value or type a value inthe Done text box Enter or change date information as described in Change Task Dates Assignments tab People assigned to this task are highlighted in the list To assign this task to anotherperson or resource click the name in the Assignments list To remove (unassign) this task from aperson or resource click a highlighted name in the Assignments list See Add or Change TaskAssignments for more detailsNotes and Attachments tab Type or edit a task note (Press Enter for a line break) To add anattachment click the Add button In the Select File to Attach dialog box navigate to the file you wantand then click the Open button The filename appears with a paper clip icon See Add Task Notes andAttachments for more details

To change task details directly in Task Data view

To modify the task name press F2 or double-click a task and then edit or replace the text

To change date information see Change Task Dates

To change the amount of the task completed double-click in the Done column and then enter a newvalue

To change the cost associated with the task double-click in the Cost column and then enter a newvalue

Notes

When you enter costs for tasks the total appears in the phase row for those tasks Reports include thetotal costs of all tasks in the project when you select the Cost column in the Create and Print TaskReports dialog box or the Create and Print Gantt Chart Report dialog box

You cannot change the cost of a phase because it represents the total costs for the tasks in that phaseInstead change the costs associated with the tasks in the phase

When you enter a Done for a task the corresponding taskbar in the Chart view includes a blackprogress bar

-o-

81

copy Experience In Software Inc 1995 - 2006

Change Details for Linked Tasks

This feature is available only in Project KickStart ProfessionalIf you are using Project KickStart Pro you can use the Task Information dialog box to change the followingtask details

Predecessor for a linked task

Lead time for a linked task

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button

2 Click the Predecessors tab and then change the task details about predecessors and lead timePredecessors tab The Task Properties section shows the name of the selected task which you canchange The Predecessor (Finish-to-Start) section shows the tasks that are predecessors to theselected task A predecessor task must be finished before you start the current task You can change the ID name or lead time of the predecessor task Also you can also add additionalother predecessorsThe lead time is the amount of time you need to wait after finishing the predecessor task before so youcan start the current task Lead time can be positive or negative

Note

In some programs the is time shift is called ldquolag timerdquo But we think that the term ldquolead timerdquo is moreaccurate and descriptive since itrsquos the amount of time you want to allow before you start a task

See Also

Change Task Details

82

copy Experience In Software Inc 1995 - 2006

-o-

-o-

83

copy Experience In Software Inc 1995 - 2006

Reorganize Tasks in Task Data View

Although your project should be fairly well organized by the time you start the Schedule step you canfine-tune the organization in the Task Data view using the same techniques you use in the Tasks stepTo reorder tasks

Right-click a task and then click Move Task Up or Move Task Down on the shortcut menu Or

Click a task or phase to select it and then click the Up Arrow button or the Down Arrow button on theGantt chart toolbar

To promote and demote tasks

Right-click a task and then click Outdent or Indent on the shortcut menu Or

Click a phase task or subtask to select it and then click the Outdent button or the Indent button onthe Gantt chart toolbar

To add a task1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Task button on the Gantt chart toolbar or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskTo add a subtask1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Subtask button on the Gantt chart toolbar or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtaskTo delete a task

Right-click a task and then click Delete Row on the shortcut menuOr

Click the task you want to delete and then click the Delete button

To delete a row click the Task row number and press the Delete button

See Also

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

-o-

84

copy Experience In Software Inc 1995 - 2006

Change the Timescale of the Schedule

You can display the Gantt chart schedule in the Chart view using days weeks months quarters or yearsas the timescale Changing from days to weeks for example displays a longer period of time but lessdetail

Days timescale Weeks timescale

To change the timescale in the Chart view

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years Youcan also change the timescale by clicking Timescale on the menu bar and then clicking the option youwant

Notes

When you print a Gantt chart your current timescale is used by default However you can change it inthe Print Options dialog For example even though you were viewing your Gantt chart by weeks youcan choose to print the Gantt chart by months

If your mouse comes with a wheel you can adjust Project KickStarts timescale by rolling the wheelforward or backward The Timescale list box must be selected first

-o-

85

copy Experience In Software Inc 1995 - 2006

Specify Working Days

You can select which days are working days and which days are nonworking days for scheduling purposesBy default Monday - Friday are working days and Saturday and Sunday are nonworking days You can addto and change these settings to specify holidays for example

To set working and nonworking days

1 Click the Change Working Schedule button on the Gantt chart toolbar The Change Working Schedule for this Project dialog box opens Nonworking days are shaded in grayWorking days are unshaded

2 To change a single date (from working to nonworking or from nonworking to working) click the date3 To change one day of the week for the entire project such as all Fridays double-click any Friday4 To display schedules for other months click the left and right arrows5 Click OK

Note

Project KickStart maintains separate calendars for each project

If you typically work weekends create a simple template with weekends displayed as Working daysSave as your starter template Use the starter template when you start a new project and then save theproject with a different name Weekends will be displayed as Working days in your projects

-o-

86

copy Experience In Software Inc 1995 - 2006

Change the Color of Taskbars

You can change the color of the taskbars in the Chart view to call attention to particular tasks For exampleyou can change the colors of all tasks in a particular phase resource or deadline to make them stand outin a report

To change the color of a taskbar1 Right-click a taskbar and then click Color on the shortcut menu or click a taskbar and then click the

Color button on the Gantt chart toolbar The Color dialog box opens

2 Click the color you want to assign to the taskbarTips

Avoid changing the taskbar color to black because it obscures the Done progress bar (The Doneprogress bar is a black bar displayed within a taskbar)

Also avoid changing the taskbar color to white because it will not appear in the white rows of the Chartview

-o-

87

copy Experience In Software Inc 1995 - 2006

Make Tasks Overlap

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro the schedule starts in a cascade with each task lasting one day and each tasklinked to the following taskHowever it is very unlikely that your entire schedule matches such a cascade so you can adjust theschedule Start by estimating the duration of tasksmdashthe number of days that each task will take Generallyit is best to estimate how many days will elapse before the task is done You might also want some tasks to occur at the same time To do so you can overlap the tasks To make tasks overlap like this

You can do this in three ways Set the same predecessor for both tasks

Or Set the second task as the successor of the first task and then then move the second task into a

position when it starts on the same day as the first taskOr

Set the second task as the successor of the first task and then assign a lead time of ndash3 days (the number of days scheduled for the task)

To make tasks overlap like this

Set the second task as the predecessor of the first task and then assign a lead time of ndash2 days(one less than the number of days scheduled for the task)

-o-

88

copy Experience In Software Inc 1995 - 2006

Manage Changes in Your Schedule

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro when you schedule with dependencies you can adapt to changes on the fly andcreate what-if scenarios to forecast how one change affects the overall project schedule A commonscenario is dealing with delays You can reschedule an entire project or only selected tasks When you doProject KickStart Pro updates the schedule for you

To delay an entire project Click in the Project Start text box and then edit the date to match your new start date (You can edit

the day month or year)Or

1 Click the Project Start list arrow to display the calendar The calendar highlights the selected date andoutlines todays date

2 Find the date you want using the left and right scroll arrows to view a different month and then click thedate Project KickStart changes the Start and Finish dates for all tasks according to your selection

To delay a task In Task Data view double-click the Days column for the task and then edit the number of days it will

take to complete the taskProject KickStart changes the Finish date of the task adjusts the taskbar in the Chart view andchanges the Start and Finish dates for all tasks linked to this taskOr

In Chart view resize a taskbar by clicking the taskbar and then dragging its left edge to schedule adifferent start date or dragging its right edge to schedule a different finish date Project KickStart updates the summary bar in Chart view the task dates and duration in the Task Dataview and reschedules all tasks linked to this task

To reschedule a task without changing the duration in Chart view drag the taskbar to a different date Project KickStart updates the task dates and duration as necessary in the Task Data view andreschedules all tasks linked to this task

Note

Project KickStart Pro does not include a critical path

-o-

89

copy Experience In Software Inc 1995 - 2006

Managing Libraries

Use a Library

Project KickStart has five libraries that contain lists of useful phases tasks goals people and obstaclesAll libraries expect the People Library contain sample entries that you can use in your projects Yougenerally build your own People Library from the resources that are available to you

To use a library1 In the Phases Tasks Goals People or Obstacles step of the Planning Wizard click the Library button

to open the appropriate library2 Select one or more items in a library and then drag them to your list3 Close the Library window

Tips

Feel free to add (or delete) items to the libraries to make them richer and more pertinent to yourprojects

Keeping libraries small makes them easier to use

Widen the library window to see the full text of long entries

Note

After adding a library entry to a list you can double-click the entry to edit it

See Also

Manage a Library

-o-

90

copy Experience In Software Inc 1995 - 2006

Manage a Library

Customize the libraries by adding and changing entries and reorganizing them so you can use the librariesefficiently The Phases Tasks Goals People and Obstacles Libraries include a single column ofinformation while the People Library provides additional columns (See Manage the People Library)

To edit a library1 Open the library by clicking the appropriate Library button2 To edit an entry double-click it

3 To add an entry to the library press Insert or click the Add a row button You can also select oneor more items in the list and then drag them to the library

4 To delete an entry select the entry and then press Delete or click the Delete a row button 5 To move an item up or down select the item and then click the Up Arrow or the Down Arrow button

6 Click the OK button to save your changes and close the Library windowTips

Widen the Library window to add a long entry

Libraries can serve as ldquoKnowledge Librariesrdquo By including typical company-specific terms in yourLibraries you create a quick reference for yourself and colleagues now and in the future To do so adda new line in the Library enter the name of your company (or department) as a heading in capitalletters and then list your personal terms under the heading

If you use Project KickStart on more than one computer such as at home and work you can transportchanges you make in your Libraries from one computer to another The data in all the Libraries isstored in one file pks5libxdat so you can copy that file on one computer and paste it into the ProjectKickStart 5 folder on the other computer

Keeping Libraries small makes them easier to use Project KickStarts Libraries are fairly rich out of thebox If some of the terms don rsquot apply to your type projects delete them

See Also

Manage the People Library

-o-

91

copy Experience In Software Inc 1995 - 2006

Manage the People Library

The People Library is like the other libraries but with a few important extra features

You can store contact data such as Company Email Phone and Job Title

You can import names from ACT or from Outlook if you use either of those programsTo use the People Library1 In the People step of the Planning Wizard click the People Library button2 Select one or more names in the People Library and then drag them to your list (This adds only the

names of people not their contact data) If the People Library contains company names but not contactnames you can drag the company name to your list

3 Close the Library windowTo organize the People Library

To show or hide a column right-click a column heading to open a shortcut menu and then click acolumn name In the shortcut menu a checkmark appears next to columns that are displayed in thePeople Library

To sort the people in the People Library click a column heading For example click the Name columnheading to sort the people alphabetically by name To reverse the sort click the column heading again

To move a person up or down select the person and then click the Up Arrow or the Down Arrowbutton

Click the OK button to save your changes and close the People LibraryTo edit the People Library

To edit a persons name and contact data double-click the entry

To add a person to the People Library click the first blank row press Insert or click the Add a rowbutton Then type to enter the persons name and contact information You can also select one ormore items in the list and then drag them to the People Library

To delete an entry select the entry and then press Delete or click the Delete a row button

Click the OK button to save your changes and close the People LibraryTips

Use the People Library to store names for people teams (such as Quality control team) departments(such as Manufacturing) companies (such as Acme Widgets Corp) or even equipment (such as wheatthrasher)

Widen the People Library window to add a long entry

Resize the columns by dragging or double-clicking a splitter barNotes

After adding a person or resource to your list you can double-click the name to edit it

You can import contact information stored in an Outlook or ACT (version 6 7 or later) address book toyour People Library

See Also

Import ACT Contacts and Users to the People Library

Import Outlook Contacts to the People Library

-o-

92

copy Experience In Software Inc 1995 - 2006

Import ACT Contacts and Users to the People Library

If you use ACT 7 or later (200520062007) or if you use ACT 6 you can import contacts and users to thePeople Library This speeds up your work by letting you use ACT information in your Project KickStartplans If you export a plan to ACT 7 or later it recognizes the people and other resources you entered inProject KickStart

To import ACT contacts and users1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click ACT 7 or later or ACT 6 Click the Import button3 Click the Select ACT Database button and select the ACT 7 or later database (pad) containing the

people information you want to import The ACT 7 and later databases are usually stored in MyDocumentsACTACT for Win 7Databases (If you use ACT 6 your data is stored in a dbf database) If you select a multi-user ACT database you must enter your user name and password for the ACTdatabase

4 In the Import to People Library dialog box the names of Contacts and Users are listed on the left Clickthe Users tab select one or more users and then click Add to move the user names to the Import listClick the Contacts tab to select contact names the same way Click the Add All button to select allusers or contacts for import Note You can sort the contacts alphabetically by name or by company name by clicking theappropriate column heading

5 Click the Import button to add the names and related information from the selected ACT database tothe People Library

Notes

Importing contacts and users to the People Library does not remove them from the ACT database

If you try to import the same ACT contact or user twice it appears only once in the People Library

-o-

93

copy Experience In Software Inc 1995 - 2006

94

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts to the People Library

If you use Microsoft Outlook to maintain your contacts you can import selected contacts to the PeopleLibrary ThisThis speeds up your work by letting you use Outlook information in your Project KickStartplans If you export a plan to Outlook it recognizes the people and other resources you entered in ProjectKickStart

To import Outlook contacts1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click Outlook Click the Import buttonA dialog box opens informing you that Project KickStart is trying to access your Outlook data

3 Allow access for 1 minute and then click the Yes button4 If Outlook asks you to choose your profile please do so5 The Import to People Library dialog box opens listing Outlook Contacts on the left Select one or more

contacts and then click Add to move the contact names to the Import list Click the Add All button toselect all contacts for import

6 Click the Import button to add the contact names to the People Library

Notes

Importing contacts and users to the People Library does not remove them from Outlook If you try to import the same Outlook contact twice it appears only once in the People Library

95

copy Experience In Software Inc 1995 - 2006

You can import Contacts from the Outlook Business Contact Manager

See Also

Import Outlook Contacts via CSV to the People Library (Pro Users)

-o-

96

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts via CSV to the People Library (ProUsers)

This feature is available only in Project KickStart Professional

If you use Microsoft Outlook to maintain your contacts and many of the people on your project are not inyour personal contacts folder in Outlook you can use our new utility to import these Outlook contacts viaCSV to the People Library

To export Outlook contacts to a CSV file1 In Outlook - Click File Import and Export Export to A File and click Next2 Select Comma Separated Values (Windows) and click Next3 Select the Contacts folder to export and click Next4 Save Exported File As with the default being your My Documents folder5 Click Next

To import Outlook contacts to the People Library

1 Be sure that you exit Project KickStart before running the Import Utility

2 Run ImportCSVToPKSexe which is located in the Project KickStart application folder

3 Browse or type the Contacts CSV file (the path is My DocumentsProject KickStart Projects folder bydefault)

4 Browse or type the pks5libxdat file (default is the Project KickStart application folder)

5 Click on Import

Note

Importing contacts and users to the People Library does not remove them from Outlook

-o-

97

copy Experience In Software Inc 1995 - 2006

Printing Reports

98

copy Experience In Software Inc 1995 - 2006

Printing Dashboards

Print Reports

You can print reports from anywhere in Project KickStart through a new Reports Step

You will see Reports divided into three areas

Dashboard

Task Reports

Gantt Chart Reports

-o-

99

copy Experience In Software Inc 1995 - 2006

Print Dashboard Reports

You can print dashboard reports from anywhere in Project KickStart though it makes the most sense toprint them after you have developed your tasks and arranged them in a sensible order

To print a dashboard report

1 Click File on the menu bar and then click Print Reports and then click Dashboard Reports or clickthe Print Reports button

2 In the left column select one of these dashboard reports Whats Due Today Whats Due NextWeek Whats Due Next Month

3 Change the page setup as necessary or Save As a file (See Page Setup and Save As)

4 Click the Print button

Tip

You can see the number of tasks in each dashboard report from the dashboard menu

-o-

100

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Dashboard Reports

Printer Setup

-o-

101

copy Experience In Software Inc 1995 - 2006

Save as HTML or RTF

You can dashboard reports to a Hypertext Markup Language (HTML) format for viewing with an Internetbrowser such as Microsoft Internet Explorer or Mozilla FireFox or to an RTF format for viewing in MicrosoftWord

To save a dashboard report as an HTML file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save button

To save a report as an RTF file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

102

copy Experience In Software Inc 1995 - 2006

Printing Task Reports

Print Task Reports

You can print task reports from anywhere in Project KickStart though it makes the most sense to print themafter you have developed your tasks and arranged them in a sensible orderBefore you print task reports you might want to widen the Task Name column in the Task List to make sureyou print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a task report

1 Click File on the menu bar and then click Print Task Reports In the Tasks step you can click thePrint Reports button instead

The Create and Print Task Reports dialog box opens

2 Click the list arrow and then click Task Report Individual Assignments or Phases Goals People ampObstacles

3 Select the information you want to include in the report as described below

4 Preview the report and change the page setup as necessary (See Print Preview and Page Setup)

5 Click the Print button

Task Report

The Task report covers the entire project and includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

103

copy Experience In Software Inc 1995 - 2006

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to display in the report

By default the report prints all tasks Click the Incomplete Tasks or Completed Tasks option button tofocus on one type of task

4 Click the Preview button (See Print Preview for details)

Individual Assignments

The Individual Assignments report covers the entire project and lists the tasks assigned to each resourceThe report includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to include in the report

Click the All Tasks Incomplete Tasks or Completed Tasks option button

4 Choose which people to include The report lists tasks assigned to the people you select

Click to insert or remove a checkmark from the box for each person

5 Click the Preview button (See Print Preview for details)

Phases Goals People amp Obstacles

This report includes the phases goals people and obstacles in your project You can include some or all ofthese items in the report

104

copy Experience In Software Inc 1995 - 2006

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Click the Preview button (See Print Preview for details)

Tip

If you have many long notes for the tasks of your project it may be hard to read them if you select everycolumn in the Task Reports You should consider selecting a report with only columns for Tasks andNotes

See Also

Print Gantt Chart Reports

-o-

105

copy Experience In Software Inc 1995 - 2006

Print Preview

Before printing a report preview its pages so you know how the report will look when printed

To preview a task report1 Click the Preview button on the Create and Print Task Reports dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from 79 to 100 or from 100 to 79Zoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25

viewPrint the report

You can also click the Page Setup button to change margins and other settings or click the Closebutton to close the Print Preview window

2 If the report appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintTask Reports dialog box

Note

Print Preview is for viewing only--you cannot edit the contents of a report

See Also

Print Task Reports

Printer Setup

Page Setup

-o-

106

copy Experience In Software Inc 1995 - 2006

Printer Setup

Before you print a report you can change the following printer settings

Printer name (and other properties) Paper size Number of copies

To change the printer setup1 Click the Printer button on the Project KickStart toolbar or the Print Preview toolbar2 In the Print dialog box change the printer settings

See Also

Print Task Reports

Print Preview

Page Setup

-o-

107

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Task Reports

Print Preview

Printer Setup

-o-

108

copy Experience In Software Inc 1995 - 2006

Email Task Reports

After creating and previewing a task report you can distribute it to others via email

To email a task report1 In the Create and Print Task Reports dialog box select a report and then click the Email Report

button Project KickStart creates the report opens a new message in your email software and attaches thereport as an HTML file to the message

2 Insert one or more email addresses include the message text and then send the message the way youusually do

Tip

To send a task report to each person in your project with the appropriate assignments select theIndividual assignments report select one person to receive the report and then click the Email Reportbutton Enter the email address of the recipient and send the message Do this for each person in yourproject

-o-

109

copy Experience In Software Inc 1995 - 2006

Save as HTML

You can export tasks assignments days and notes to a Hypertext Markup Language (HTML) format forviewing with an Internet browser such as Microsoft Internet Explorer or Mozilla FireFox

To save a report as an HTML file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

110

copy Experience In Software Inc 1995 - 2006

Save as RTF

You can export tasks assignments durations and notes to a Rich Text Format (RTF) for editing inMicrosoft Word

To save a report as an RTF file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can open an RTF file in a word processor such as Microsoft Word

To send an RTF document to each person in your project with the appropriate assignments select theIndividual Assignments report select one person to receive the report and then save the report asRTF Do this for each person in your project

See Also

Save as HTML

-o-

111

copy Experience In Software Inc 1995 - 2006

Printing Gantt Chart Reports

Print a Gantt Chart

Once you create your schedule you can print a Gantt chart from anywhere in Project KickStart

Before you print a Gantt chart you might want to widen the Task Name column in the Task pane to makesure you print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a Gantt chart1 Click File on the menu bar and then click Reports and then select Gantt Chart Reports In the

Schedule step you can click the Print Reports button insteadThe Create and Print Gantt Chart Report dialog box opens

2 Click the Format list arrow and then click Wall chart Fit to smallest size or Repeat tasks on everypage (for handouts)

3 Select the information you want to include in the report as described below4 Preview the report and change the page setup as necessary (See Print Preview a Gantt Chart and

Page Setup)5 Click the Print button

Wall Chart The wall chart prints the Gantt chart information spread across many pages which you can tape together tocreate a wall chart On the left side of the report the wall chart includes the task data columns you selectThe right side of the report includes the graphical view shown in the Gantt chart pane on the right

1 Select the task data columns you want to display for the task information on the left side of the wallchartClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the wall chart

112

copy Experience In Software Inc 1995 - 2006

By default the wall chart prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the wall chartBy default the wall chart prints the timescale you were using in the Gantt chart Click the SetTimescale list arrow to change the timescale to Weeks Months Quarters or Years

4 Select the orientation for the wall chartClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Fit to Smallest Size When you select the Fit to smallest size format Project KickStart reduces the size of the entire Gantt chartincluding the information in the Task pane on the left and the graphical view shown in the Gantt chart paneon the right so it fits as well as possible in the smallest number of pages

1 Select the data columns you want to display for the task information on the left side of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 The timescale for the Gantt chart view on the right side of the report is determined by the length of yourproject and may not be changed

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 The number of pages of the report is shown here (The Fit to smallest scale report will print up to 78rows of tasks per page)

6 Click the Preview button (See Print Preview a Gantt Chart for details)

Standard (for Handouts) This report lists the data columns you specify on the left side of the first page and can repeat the tasknumber task name or assignments on every interior page of the report which is especially useful for

113

copy Experience In Software Inc 1995 - 2006

handouts

1 Select the data columns you want to print on the left side of the first page and the data columns youwant to print on every page of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the reportBy default the report prints a daily view of the tasks Click the Set Timescale list arrow to change thetimescale to Weeks Months Quarters or Years

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Tips

Print Preview shows how many pages the Gantt chart will take to print If there are too many pagesconsider changing the timescale or the date range You can also choose to show fewer columns of taskdata

If possible use paper that is larger than 85 x 11 inches You can select the paper size in Print Previewusing the Page Setup dialog box

If you change the timescale from Days to Weeks or Months this can make tasks with short durations (1to 5 days) difficult to see

If you have trouble printing the Gantt chart report try changing the dpi from 600 to 300 (draft mode) Ifyou continue to have problems contact your printer manufacturer and see if it supports PCL (PrinterCommand Language) technology which is included in most printers today

If you have trouble printing the Gantt chart report on a PDF printer you can try to scale the printing tographics setting to 50

114

copy Experience In Software Inc 1995 - 2006

See Also

Save Gantt Chart Images

Print Task Reports

Printer Setup

Page Setup

-o-

115

copy Experience In Software Inc 1995 - 2006

Print Preview a Gantt Chart

Before printing a Gantt chart preview its pages so you know how the report will look when printed

To preview a Gantt chart1 Click the Preview button on the Create and Print Gantt Chart Report dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from the current zoom percentage to 100 or from 100 to the current zoom percentageZoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25 viewChange printer settings and then print the reportYou can also click the Page Setup button to set margins select paper size and enter headers andfooters or click the Close button to close the Print Preview window

2 If the Gantt chart appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintGantt Chart Report dialog box

Notes

Print Preview is for viewing only--you cannot edit the contents of a report

If you want to print a wider task column return to the Gantt chart widen the Tasks Name column andthen print

To change print settings such as the printer selection and number of copies click the Print button to open the Print dialog box You can save the Gantt chart in a PDF file by clicking the Print button andthen clicking the PDF printer selection (such as Adobe PDF or PDF-XChange ) You can then distributethe Gantt chart electronically as a PDF file

See Also

Print a Gantt Chart

Page Setup

-o-

116

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a Gantt chart you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print a Gantt Chart

Print Preview a Gantt Chart

-o-

117

copy Experience In Software Inc 1995 - 2006

Printing to an Adobe PDF file

To print a Gantt chart to an Adobe PDF file you may have to make some adjustments to your settings

To preview a Gantt chart1 Select Adobe PDF as the name of the printer2 Click Properties button3 Click the PaperQuality tab4 Click Advanced button5 In the Graphic Section lower the setting on Print Quality6 Also in the Graphic Section change the Scaling from 100 to 50

-o-

118

copy Experience In Software Inc 1995 - 2006

Save Gantt Chart Images

You can save a Gantt chart as a series of graphic files in the Meta File (emf) format which you can theninsert in a file such as a Microsoft Word document or PowerPoint presentation The number of graphic filescreated depends on the report type and options you choose in the Create and Print Gantt Chart Reportdialog box By default Project KickStart saves the files in a folder named for your project

To save Gantt chart images1 In the Create and Print Gantt Chart Report dialog box click the Save Image button

The Save Image dialog box opens2 Change the location where you want to save the image files or change the part of the file name that

includes the project name and report type if necessary3 Click the Save buttonNotes

Project KickStart saves the image files in the PKSGanttImagesproject name folder stored in the MyDocumentsProject KickStart Projects folder (where project name is the name of your project)

Each graphic file name includes the name of the project report type date you created the report andnumber in the series of images as in CreateaWinningPresentation_Wall chart_09112008_1emf toCreateaWinningPresentation_Wall chart_09112008_20emf

To email the Gantt chart images attach the images in the PKSGanttImagesproject name folder storedin the My DocumentsProject KickStart Projects folder (where project name is the name of your project)If the image files are large zip or compress the files first

If you have installed PDF as a printer selection you can print the Gantt chart to a PDF file and thenattach the PDF file to an e-mail message PDF files are often easier to read than image files See thenotes in Print Preview a Gantt Chart for instructions on printing to a PDF file

-o-

119

copy Experience In Software Inc 1995 - 2006

Export Project Data

120

copy Experience In Software Inc 1995 - 2006

Export to ACT

Export to ACT 7 or Later

If you use ACT 7 or later (20052006200720082009) you can export your plan from Project KickStart toan ACT database with just one click After you export your plan you see your tasks in the ACT Groupview grouped under the name of your project

To export to ACT 7 or later

1 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 7 and later andthen click the Go button You can also click File on the menu bar point to Export to and then clickACT 7 and later

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (pad file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opens

Each time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks

4 Click Start (This works best if ACT is already open )

5 If you are exporting to a multi-user ACT database enter your ACT User Name and Password

To view each project separately in ACT Group Details

1 In ACT click the Group List icon

2 Double-click the Project Name in the Group Name column The Group Detail appears for the projectyou selected

3 Click the Contacts tab to see Contacts and click the Activities tab to see tasks for that project

4 You should press Ctrl-F5 to refresh the view Also you might have to adjust the Filter in ACT so thatDates to show is set to All Dates

Task names are listed in the Regarding column Assignments are listed in the Scheduled With columnPhases are shown in red and tasks and subtasks are shown in blue

To view tasks from multiple projects sorted by date in Task List or Calendar

In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn Project names are in the Associate With column You might have to adjust the Filter in ACT sothat Dates to show is set to All Dates

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar Tasks are set as timeless (Duration of 0 minutes) so the transferred tasks dont fill up thecalendar

121

copy Experience In Software Inc 1995 - 2006

Tips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

The ACT 7 and later export is smart enough to update your existing tasks from the same project If youexport the same Project KickStart project two or more times ACT recognizes the project and asks ifyou want to update the project information in ACT You do not lose your task history or notes in ACT

Tasks that are unassigned in Project KickStart are listed as Scheduled With Unassigned PKS

You can filter by Selected Users in the Task List and in Groups

See Also

Import ACT Contacts and Users to the People Library

-o-

122

copy Experience In Software Inc 1995 - 2006

Export to ACT 6

If you use ACT 6 ACT 2000 or ACT 5 you can transfer a Project KickStart plan into an ACT databasewith just one click After you export your plan you see your tasks in the ACT Group view grouped underthe name of your project

To export to ACT 61 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 6 and then click

the Go button You can also click File on the menu bar point to Export to and then click ACT 6

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (dbf file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opensEach time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks4 Click Start (This works best if ACT is already open )5 If you are exporting to a multi-user ACT database enter your ACT user name and passwordTo view each project separately in ACT1 In ACT click the Groups icon 2 Click the Project Name listed under All Groups on the left3 On the lower-right part of the window click the Activities tab to see tasks for that project

Task names are listed in the Regarding column Assignments are listed in the Scheduled With column 4 You might have to adjust the Filter in ACT so that Dates to show is set to All Dates Also you might

have to press Ctrl-F5 to refresh the view5 To view task details click the button next to the task column on the leftTo view tasks from multiple projects sorted by date1 In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn You might have to adjust the Filter in ACT so that Dates to show is set to All Dates

2 If the Group column is not showing add it by clicking ViewAdd Columns and then double-clickingGroupThe tasks are identified by group (project name)

3 To view task details click the button next to the task column on the leftTips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar as well as in the Task List

You can filter by Selected Users in the Task List and in Groups

After exporting your tasks to ACT you can import them to your Palm Pilot using the ACT Link

See Also

Import ACT Contacts and Users to the People Library

-o-

123

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Outlook

If you use Microsoft Outlook you can export your plan from Project KickStart to Outlook in a click of abutton After you export your plan you see your tasks in the Outlook Tasks view grouped under a categorynamed for your project In Outlook you can track your tasks and email tasks to team members

To export to Microsoft Outlook1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Outlook and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Outlook The Export to Outlook dialog box opens

2 Click an option button to export All tasks Uncompleted tasks or Completed tasks3 If you want to display the tasks you export on your Outlook Calendar click the check box4 Click the Start button A dialog box opens informing you that Project KickStart is trying to access your

Outlook data

5 Allow access for 1 minute and then click the Yes buttonTo view your tasks in Microsoft Outlook1 Click the Outlook Tasks button2 Depending on the version of Outlook you are using set to view the tasks by category In Outlook 2003

click the By Category option button in the Current View list You can also click View on the menu barpoint to Arrange By and then click CategoriesYour project is listed by its project name in the Categories list

3 Click an expand icon to see the complete list of tasks and subtasks

124

copy Experience In Software Inc 1995 - 2006

4 To view task details double-click the task nameTips

The export to Outlook works best if Outlook is already open

In Outlook you can set priorities set reminders and schedule by the hour

If you export to your Outlook Calendar a reminder appears on the due date of each task

After you export tasks to Outlook you can synchronize with your Palm Pilot Windows CE device orother handheld computer

Note

You can export only to Microsoft Office Outlook not Outlook Express

See Also

Import Outlook Contacts to the People Library

-o-

125

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Word

If you use Microsoft Word you can export your plan from Project KickStart to Word in a click of a buttonYour project appears in a Word table in a doc file You can cut and paste change column widths deletecolumns and print from Word

To export to Microsoft Word

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Word andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Word

Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in a Word document in a doc format

2 When youre finished use Save As to save the Word file with a new name such as ltnamegtdoc Forconvenience you can save the file using the same name as your Project KickStart project name

Benefits of using Project KickStart and Word

Communicate projects flexibly After exporting to Word you can communicate your project details ina variety of text formats You can also enhance your document by adding color logos clip art orhyperlinks

Distribute plans to others You can send doc files to other Microsoft Word users via email andrequest comments using Words Send To and Comments features

Tip

Include your strategic plan in documents letters and web pages in a doc or html file

Note

The image of the Gantt chart does not import into Word automatically You can manually import theGantt chart image into a Word document In Word select Insert on the menu bar point to Pictureclick From File and then browse to the folder containing the Gantt chart images you saved By defaultthis is cMy DocumentsProject KickStart ProjectsPKSGanttImages in a folder named for your project

See Also

Export to Word Processors (Other than Word)

Save Gantt Chart Images

126

copy Experience In Software Inc 1995 - 2006

-o-

127

copy Experience In Software Inc 1995 - 2006

Export to Word Processors (Other than Word)

If you are using a word processor other than Microsoft Word you can export your Project KickStart taskreport by first saving it as an HTML or RTF file

To export to word processors other than Microsoft Word

1 Save a Project KickStart task report using HTML or RTF format using the Save As button in the Createand Print Task Reports dialog box

2 Open the file with your word processor

3 Save the file using the Save As command using a different name

See Also

Print Task Reports

Save as HTML

Save as RTF

-o-

128

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Excel

If you use Microsoft Excel you can export your plan from Project KickStart to Excel in a click of a buttonYour project appears in an Excel worksheet in a xls file You can add task details perform calculationsand share your project data with other Excel users

To export to Microsoft Excel1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Excel and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Excel Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in an Excel worksheet in an xls format

2 When youre done select FileSave As to save the Excel file under a new name For convenience youmight want to save it under the same name as your Project KickStart project name

To manually import Gantt chart images into Microsoft Excel1 In Excel click Sheet2 and select ToolsOptions on the menu bar and unclick the box for Gridlines2 Then select Insert on the menu bar point to Picture click From File and then browse to the folder

containing the Gantt chart images you saved By default this is cMy DocumentsProject KickStartProjectsPKSGanttImages in a folder named for your project

3 Select one Gantt chart image at a time to bring it in 4 You can manipulate the size of the image in Excel

Benefits of using Project KickStart and ExcelProject KickStart is very good at scoping out a schedule but there are a few reasons why you might want touse both programs

Data sharing A Project KickStart user might want to share the information with other Excel users whodont have Project KickStart They could change enhance or redistribute their portions of the schedule

129

copy Experience In Software Inc 1995 - 2006

Add more task details Excel users can add new columns of task data that cant be added in ProjectKickStart

Sort task lists For example you could show your projects tasks sorted by each resources namethen see each resources tasks sorted by the tasks start date

Filter tasks Excel can show tasks that meet certain criteria For instance show tasks with the wordtesting in the task name

See Also

Save Gantt Chart Images

-o-

130

copy Experience In Software Inc 1995 - 2006

Export to Microsoft PowerPoint

If you use Microsoft PowerPoint you can export your plan from Project KickStart to PowerPoint in a click ofa button Your project appears as a formatted PowerPoint presentation in a ppt file

To export to Microsoft PowerPoint

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft PowerPointand then click the Go button You can also click File on the menu bar point to Export to and thenclick Microsoft PointPoint

The Export to PowerPoint dialog box opens where you can choose a PowerPoint design template ifyou like

2 Click the Start button

Your tasks days start and finish dates and costs appear in a PowerPoint presentation with an imageof the Gantt chart in one or more slides at the end of your slide show

Once you have created a PowerPoint presentation you can enhance your slides in several ways

Delete slides that are not appropriate for your presentation

131

copy Experience In Software Inc 1995 - 2006

Rearrange the order of the slides

Add colors for emphasis

Add graphics such as company logo clip art and colors

Shorten any long task titles

Benefits of using Project KickStart and PowerPoint

Save time You can dramatically save time in creating a PowerPoint presentation on your project

Present projects to others Present project details in webinars presentations and corporatemeetings Create template presentations or how tos for implementing an installation productintroduction or corporate policy for example

Communicate plans Email project plans in ppt format to colleagues and presentors

Tips

If you use a PowerPoint design template choose one that has a white or light background for maximumlegibility of the Gantt chart in the presentation

The Gantt chart image in the PowerPoint presentation is generated ldquoon the flyrdquo Change the Timescalesettings of the Gantt chart considering how it will be reflected in the number of images of the Ganttchart For example the Day view results in more Gantt chart images than the Months view

-o-

132

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Project

If you use Microsoft Project 98 2000 2002 or 2003 you can export your plan from Project KickStart toProject in a click of a button

To export to Microsoft Project

In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Project andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Project Your tasks assignments days start and finish dates costs done and notes (excluding attachments) appearin a Microsoft Project file

Benefits of using Project KickStart and Microsoft Project

Share data with others Send a project to a colleague or client that expects to see your schedule in anMicrosoft Project format

Schedule tasks with more flexibility Schedule tasks in different durations particularly in less than aday

Track resources Track resource usage and resource leveling and to have greater flexibility in sortingfiltering and reporting project information

Notes

Project KickStart tasks transfer to Microsoft Project as tasks with a Constraint type of Start No EarlierThan This keeps the dates the same as in the Project KickStart schedule

The settings in Project KickStart Working Days Calendar also transfer to Microsoft Project

Exporting to Microsoft Project allows you to take advantage of the advanced tracking and schedulingfeatures that large projects often require

You can also save your Project KickStart projects as an mpx file which you can open in MicrosoftProject and send to other Microsoft Project users Click File on the Project KickStart menu bar clickSave As and then choose mpx as the file type After you save the file click File on the MicrosoftProject menu bar click Open and open your mpx file

-o-

133

copy Experience In Software Inc 1995 - 2006

Export to SureTrak Project Manager

If you use SureTrak Project Manager you can export your plan from Project KickStart to SureTrak ProjectManager

To export to SureTrak Project Manager

1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file

2 In SureTrak click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

SureTrak

You will see your tasks and assignments (but not the notes) appear in a SureTrak file The file is shownin outline view

Benefits of using Project KickStart and SureTrak

Add new information to tasks such as how they are linked

Track progress particularly for comparing plans verses actual results

Have greater flexibility in sorting filtering and reporting project information

Notes

Task notes are not included in the transfer

A version of Project KickStart called the Project KickStart Wizard is included in SureTrak 2 andSureTrak 3 You can use it within SureTrak

See Also

Export MPX Files

-o-

134

copy Experience In Software Inc 1995 - 2006

Export to FastTrack Schedule

If you use FastTrack Schedule you can save your Project KickStart project as an mpx file and import it intoFastTrack ScheduleTo export to FastTrack Schedule1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file2 In FastTrack Schedule click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

FastTrack ScheduleBenefits of using Project KickStart and FastTrack Schedule

Add more task details FastTrack Schedule provides the features and tools needed in many largeprojects

Multiproject reporting Consolidate multiple projects into a master project file

See Also

Export MPX Files

-o-

135

copy Experience In Software Inc 1995 - 2006

Export to Milestones Professional

If you use Milestone Professional you can export your plan from Project KickStart to MilestonesProfessional in a click of a button

To export to Milestone Professional

In the Schedule step click the Export to list arrow below the Gantt chart click MilestonesProfessional and then click the Go button You can also click File on the menu bar point to Export to and then click Milestones Professional

Your tasks assignments start and finish dates and notes (excluding attachments) appear in aMilestones file

Tips

After you export your tasks to Milestones Professional you can create taskbars add titles and performother tasks to produce a presentation-quality schedule You can also use Milestones to track your tasksby showing task durations and percent completions Make scheduling changes by dragging the taskdates

If you have an earlier version of Milestones (eg version 45 or 5) you can save Project KickStart dataas an mpx file and then open the mpx file in Milestones

-o-

136

copy Experience In Software Inc 1995 - 2006

Export to Mindjet MindManager

If you use Mindjet MindManager 7 or later you can export your project plan from Project KickStart in a clickof a button Or you can develop a rough plan in MindManager and export your mind map to ProjectKickStart for enhanced planning It works both ways

To export from Project KickStart to MindManager

In the Schedule step click the Export to list arrow below the Gantt chart click MindManager and thenclick the Go button You can also click File on the menu bar point to Export to and then clickMindManager

Your tasks assignments start and finish dates durations costs Done and notes (excludingattachments) appear in a MindManager file

To export from MindManager to Project KickStart

In MindManager click File on the menu bar point to Send To and then click Project KickStart Thenclick the OK button to start the export

You can also click the Project KickStart icon at the bottom of the MindManager window

Benefits of using Project KickStart and MindManager together

Visualize your plan in two ways Brainstorm plan and communicate your project details in both agraphical and linear style

Develop a graphical plan and then fine-tune the details MindManager uses mindmappingtechniques to develop a high-level plan in a graphical format Export to Project KickStart to enhanceyour plan details by focusing on your projects goals obstacles and resource needs You can alsocreate a Gantt chart schedule

Communicate concepts Project KickStart users can display their plans in a highly graphicalmindmapping format in MindManager The maps make it easier to communicate complex processesand visually identify important tasks issues and relationships

Tip

If you dont already use MindManager you can purchase it in our Thinking Tools Store

-o-

137

copy Experience In Software Inc 1995 - 2006

Export to WBS Chart Pro

If you use WBS Chart Pro you can export your plan from Project KickStart to WBS Chart Pro in a click of abutton

To export to WBS Chart Pro

In the Schedule step click the Export to list arrow below the Gantt chart click WBS Chart Pro andthen click the Go button You can also click File on the menu bar point to Export to and then clickWBS Chart ProYour project is displayed under the project name Each phase in the project is shown in a box with ashadow Each lower level task in a phase is displayed under their respective phase box groupedtogether with the other tasks in that phase

Benefits of using Project KickStart and WBS Chart

Visualize tasks Work with tasks in a tree-style chart called a Work Breakdown Structure (WBS)chart

Communicate your project plan with others WBS Chart uses the outline you create in ProjectKickStart to create a top-down picture of your plan This picture is similar to an Organization chart Butinstead of displaying the structure of your company a WBS chart displays the structure of your projectplan

Notes

WBS Chart refers to the phases in the project as Summary Tasks and the detail for each phase asTasks

The export only works if WBS Chart is not currently running You must close WBS Chart before you cancreate another chart

See Also

Export MPX Files

-o-

138

copy Experience In Software Inc 1995 - 2006

Export MPX Files

The MPX file format is an ASCII format created by Microsoft Project or another program and is used tosend data to and from project management software programs

The following programs can create and open MPX files

FastTrack Schedule

Microsoft Project (95 or 98)

Project KickStart 5

Project KickStart 32

RiskyProject

SureTrak Project Manager

WBS Chart

In these programs you save a project as an MPX file using the Save As command on the File menu Youcan then open an MPX file by using the Open command on the File menu and then specifying the file typeas mpx

For example if you want to move a project from Project KickStart 5 to Project KickStart 32 you can savethe project as an mpx file and then open it in Project KickStart 32

In Microsoft Visio you can create a Visio project time line from Project KickStart To do so you first mustsave your file in Project KickStart as an MPX file Then

1 Start Visio

2 Click File on the menu bar point to New click Business Diagram and then click Project TimelinesWizard

3 Click Next

4 On the second window click Import MPX File to import the Project KickStart mpx file

5 Enter the file location and name or click Browse to locate the file

6 Follow the instructions in the Visio Project Timelines Wizard windows

Tip

If you have difficulty importing the mpx file remove any commas from task names

-o-

139

copy Experience In Software Inc 1995 - 2006

Reference

140

copy Experience In Software Inc 1995 - 2006

Menus

File Menu

Command Keyboard Shortcut Description

New Project Ctrl+N Creates and names a new project fileOpen Project Ctrl+O Opens a previously saved Project KickStart 4 or 5 file

(prx) Project KickStart 3 file (prj) or mpx fileClose Ctrl+W Closes an open Project KickStart fileSave Ctrl+S Saves a project file (prx) in which you made changes Save As Saves a project file with a different file name or different

file format such as MPXPrint Task Reports

Ctrl+T Generates and prints a report letting you preview thecontents

Print Gantt ChartReports

Ctrl+G In the Gantt chart (Schedule step) generates andprints the Gantt chart in the current timescale

Export To Sends the project to another program such asMicrosoft Outlook or ACT 7

Recent file list Lists the last three files opened in Project KickStartExit

Alt+F4 Exits the program

-o-

141

copy Experience In Software Inc 1995 - 2006

Edit Menu

Command Keyboard Shortcut Description

UndoRedo Ctrl+Z Undoes or repeats the last operationCut

Ctrl+X Deletes the currently selected information placing it on theclipboard so you can paste it elsewhere

Copy

Ctrl+C Places a copy of selected information on the Clipboard so youcan paste it elsewhere

Paste

Ctrl+V Places information from the Clipboard to the currently selectedlocation

Select all Ctrl+A Selects all the content in the windowAdd a line Adds a new row where you can enter text

-o-

142

copy Experience In Software Inc 1995 - 2006

View Menu

Command Description

Tool Bar Shows or hides the toolbar (a checkmark indicates thetoolbar is displayed)

Steps Bar Shows or hides the Steps bar (a checkmark indicates the Steps bar is displayed)

Name Go to the Name your project stepPhases Go to Phases stepGoals Go to Goals stepSimilar Projects Go to Similar projects stepPeople Go to People stepObstacles Go to Obstacles stepAssign Go to Assign tasks to people stepTasks Go to Tasks stepSchedule Go to Schedule step

-o-

143

copy Experience In Software Inc 1995 - 2006

Tools Menu

Command Keyboard Shortcut Description

Spelling

F7 Checks spelling of project dataexcept for names of people

Collaboration To access or find out aboutGoToMeeting

Options Select options for running thesoftware

-o-

144

copy Experience In Software Inc 1995 - 2006

Options

-o-

145

copy Experience In Software Inc 1995 - 2006

Data Menu

The Data menu is available in the Tasks and Schedule steps for manipulating tasks and creating ascheduleCommand Description

Move Up Moves the selected task item upMove Down Moves the selected task item downOutdent Moves the selected task item to the leftIndent Moves the selected task item to the rightInsert Task Insert task in row aboveInsert SubTask Insert subtask below current rowDelete Task Delete current taskEdit Task Properties Brings you to an edit screen where you can edit task

name change assignments and edit task notesEdit Notes Brings you to an edit screen for editing task notesColor Taskbars Change the color of selected tasks (in Schedule)Change Working Days Select which days are working and which are

nonworking (in Schedule)Link Tasks Link tasks in Gantt chart (Pro Users)Unlink Tasks Unlink tasks in Gantt chart (Pro Users)

-o-

146

copy Experience In Software Inc 1995 - 2006

Timescale Menu

The Timescale menu is available in the Schedule step so you can change the display of the Gantt chartschedule

Command Description

Days Displays a daily schedule in theGantt chart

Weeks Displays a weekly schedule inthe Gantt chart

Months Displays a monthly schedule inthe Gantt chart

Quarters Displays a quarterly schedule inthe Gantt chart

Years Displays a yearly schedule inthe Gantt chart

-o-

147

copy Experience In Software Inc 1995 - 2006

Help Menu

Command Description

Project KickStart Help Help for Project KickStart including a Table ofContents and index of terms

Online Tutorials View several Getting Started Tutorials to getyou started with Project KickStart whether youare a new or experienced user

Keyboard Shortcuts Shortcuts for programTechnical Support How to obtain Technical Support for Project

KickStart via web form and email[Send Log to Technical Support] If the program detects an error it writes a log

of technical issues Click Send Log toTechnical Support to send the error log to us

ProjectKickStartcom Visit the Project KickStart Web siteGet Latest Version See what the latest published version is and

download it if you need itAbout Project KickStart Shows Project KickStart version number build

date copyright and system information

-o-

148

copy Experience In Software Inc 1995 - 2006

Shortcuts

Use the following keyboard shortcuts to move quickly around in Project KickStart

Navigation

Move forward to the next window Alt+NMove back to the previous window Alt+BSteps

Go to Name step Alt+MGo to Phases step Alt+SGo to Goals step Alt+GGo to Similar step Alt+RGo to People step Alt+PGo to Obstacles step Alt+OGo to Assign step Alt+IGo to Tasks step Alt+KGo to Library (Phases Tasks GoalsPeople Obstacles)

Alt+L

Menus

File menu Alt+FEdit menu Alt+EView menu Alt+VShow menu (Tasks step) Alt+WOutline menu (Tasks step) Alt+UTimescale (Schedule step) Alt+CHelp menu Alt+H F1Other

Edit tasks assignments amp notes (Tasks step)F3Save Ctrl+SPrint Task Report Ctrl+PPrint Gantt Chart (Schedule step) Ctrl+GCut Ctrl+XCopy Ctrl+CPaste Ctrl+VInsert Row InsertDelete Row DeleteInsert Line Break (in Notes in Task List andSchdule steps)

Enter

Spell Check

Ignore Alt+IIgnore All Alt+GChange Alt+CChange All Alt+HHelp

149

copy Experience In Software Inc 1995 - 2006

Contents in Help Alt+CIndex Alt+IBack in Help Alt+BClose Help Alt+LHelp about the current step Alt+H

-o-

150

copy Experience In Software Inc 1995 - 2006

Share Project KickStart Data

Project KickStart makes it easy to share data with other people involved with a project You can share yourProject KickStart data in the following ways

Send a printed report Make a PowerPoint presentation Send a file (prx html rtf mpx) Post an HTML file to a Web site and access it with your web browser Export to other programs such as Microsoft Word or Excel and send data in a format the recipient can

access (such as doc xls or mpx)

Note

You can also collaborate with a colleague by conducting an online meeting using GoToMeeting (Prousers)

-o-

151

copy Experience In Software Inc 1995 - 2006

Open a Project

After you create a project and save it in a prx prj or mpx file using Project KickStart or other softwareyou can open the project in Project KickStartTo open a project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click a file type (prxprj or mpx)

3 Navigate to the folder that contains the file4 Double-click the name of the file

Opening a Project KickStart 3 prj file converts it to a prx file

Generally prj files are stored in cprogram filesProject KickStart 3

The tasks in the converted Project KickStart 5 file will have the same start and finish dates anddurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way To have weekends as non working days open the working days calendar and markweekends as non working

Opening a mpx file converts it to a prx file

The tasks in each project have the same start and finish dates and durations

-o-

152

copy Experience In Software Inc 1995 - 2006

Dedication

I dedicate this software program to my new colleague

Kevin Ahlvin

Roy A Nierenberg President

-o-

153

copy Experience In Software Inc 1995 - 2006

Credits and Trademarks

Credits

Missak Koumoudjian Program Architect and Chief Programmer

Kevin Ahlvin Interface DesignAnn Kawamoto Quality AssuranceAlexander Setzepfandt Quality AssuranceJackie LeungJeffrey Chow

Programming Interns

Kevin Ahlvin Product Supervisor and CoordinatorJoseph Fusco Project Management Consultant and content

providerLisa RuffoloJoseph Fusco

Help System

Roy A Nierenberg President

Trademark

Project KickStart and Project KickStart Wizard are trademarks of Experience In Software Inc in the UnitedStates andor in other countries All rights reserved All other trademarks mentioned herein are the propertyof their respective owners

-o-

154

copy Experience In Software Inc 1995 - 2006

Uninstalling

You can uninstall Project KickStart 5 through the Control Panel AddRemove Programs Select ProjectKickStart 5 This starts the InstallShield Maintenance Program You should then remove all of theprogram files that were installed It will not erase your Project KickStart prx data files

If that does not work you can delete the Project KickStart files manually

Note

If you purchased Project KickStart and you want to return it for a refund follow the instructions forDe-activating the software at httpwwwprojectkickstartcomcontactreturnscfm

-o-

155

copy Experience In Software Inc 1995 - 2006

Using Past Projects

You can use past projects in two ways

If you have projects that are similar you can use a past project as a template for a new project In theWelcome window select Open a Project Open that project and Save As under a different name Nowyou can open up the renamed project and modify it for the current project

You can draw from several projects in the Similar Projects step First select projects that are similarand click Next Then select tasks from those projects and decide where they would fit into your currentproject

See Also

Opening a project Compatibility with earlier versions

-o-

156

copy Experience In Software Inc 1995 - 2006

Index

- - Change Working Schedule 85

- -prj file format 13

- A -About Linking Tasks (Pro Users) 59About Scheduling Tasks 55About the Gantt Chart 57ACT 120 92 122ACT 6 92 122ACT 7 or later 92 120Activate 14Activating Trial Version 14Add a New Person or Resource 39add a subtask 83add a task 83Add a Task or Subtask 47Add or Change Task Assignments 51Add or Change Task Details 52Add Subtask 63Add Task 63Add URL 49Additional Features in Task Data View (Pro Users) 68Additional Tools in Chart View (Pro Users) 71Adobe PDF 117Assignments tab 80Attachments 49Autolink tasks (Pro Users) 58

- B -Back 10borrow tasks 29

- C -Change Details for Linked Tasks (Pro Users) 81Change Project Start 63Change Task Dates 73Change Task Details 80Change the Appearance of the Task List 43Change the Display of the Schedule 61Change Timescale 63Change Working Schedule 63Chart view 57

157

copy Experience In Software Inc 1995 - 2006

Cloning projects 155Color 63 86Compatibility 13Compatibility with earlier versions 13convert projects 13Coordination 12Create and Print Task Reports 102Credits 153Credits and Trademarks 153critical path 88CSV 96Customer support 20Customer Support 20Customizing Project KickStart

- D -Dashboard 99Data Menu 145Dedication 152Delete 63delete a task 83demote 46dependencies 12 76

- E -Edit Menu 141Edit Notes and Attachments 63Edit or Substitute People 40Edit Task Information 63Email Task Reports 108End User License Agreement 16error 21Error Messages 21export from MindManager 136Export MPX Files 138Export to ACT 6 122Export to ACT 7 and Later 120Export to FastTrack Schedule 134Export to Microsoft Excel 128Export to Microsoft Outlook 123Export to Microsoft PowerPoint 130Export to Microsoft Project 132Export to Microsoft Word 125Export to Milestones Professional 135Export to Mindjet MindManager 136Export to SureTrak Project Manager 133Export to WBS Chart Pro 137

- F -FastTrack Schedule 134File Menu 140Fit to page 111Fit to Smallest Size 111

158

copy Experience In Software Inc 1995 - 2006

- G -Gantt chart 55 57General tab 80Goal 26Goal statements 26Goals 26Goals - Step 1 of 3 26Goals - Step 2 of 3 27Goals - Step 3 of 3 28goals library 26 89Goalsadd 26Goalsdelete 26Goalsedit 26Goalstasks for 27GoToMeeting 150 12

- H -Handouts 111Help Menu 147hyperlink 49

- I -Import ACT 92import contacts and users 92import Outlook contacts 94Import Outlook Contacts via CSV to the People Library (Pro Users) 96ImportCSVToPKSexe 96Indent 46Individual Assignments 102Introduction 7Introduction 7

- K -Knowledge Libraries 90

- L -lag time 81lead time 59 81library 89License Key 14link 59Link lines 59Link tasks 12 65linked tasks 59

- M -major activities 24Make Tasks Overlap (Pro Users) 87Manage a Library 90

159

copy Experience In Software Inc 1995 - 2006

Menu 140Microsoft Excel 128Microsoft Outlook 123Microsoft PowerPoint 130Microsoft Project 132Microsoft Project (95 or 98) 138Microsoft Visio 138Microsoft Word 125Milestone 69 79Milestones Professional 135Mindjet MindManager 136MindManager 136

- N -Name 23Name Your Project 23Navigating Project KickStart 10Next 10Notes and Attachments tab 80

- O -Objectives 26Obstacles 34Obstacles - Step 3 of 3 36Obstacles Library 89Open a Project 151Options 144Outdent 46Outdent and Indent arrows 63Outlook Calendar 123Overview

- P -Page Setup 107 116 100PDF 117people 31People - Step 3 of 3 28People Library 91phase 24phase dates 75Phase Dates Cannot Be Edited 75phases 24Phases - Step 1 of 2 24Phases - Step 2 of 2 25Phases Library 89Phases Goals People amp Obstacles 102PowerPoint presentation 130Pred 68Predecessor 68Predecessor tasks 59predecessors 76Print a Gantt Chart 111Print Dashboard Reports 99Print Preview 105Print Preview a Gantt Chart 115Print Reports 98Print Task Reports 102

160

copy Experience In Software Inc 1995 - 2006

Printer Setup 106Printing to an Adobe PDF file 117prj 13Pro 145Pro Edition 145Product support 20Project 23Project KickStart 3 prj file 151Project KickStart for Windows 7project name 23project start date 73project template 155project title 23promote 46promote and demote tasks 83

- Q -Quick Tour of Working with Linked Tasks (Pro Users) 76

- R -Red vertical line 69Redo 11Register Project KickStart 22Registering Project KickStart 22remove people 38Remove People from a Task 38reorder tasks 83Reorganize Tasks in Task Data View 83Repeat tasks on every page (for handouts) 111Reporting Technical Issues 21resource 31resources 31restore 34return 154risks 34RiskyProject 138

- S -Save As 101Save as HTML 109Save as RTF 110Save Gantt Chart Images 118Schedule 55Send Error Report 21similar projects 29spelling 53starter schedule 55Steps 7subtask 47Subtasks 46Succ 68Successor 68Successor tasks 59successors 76Summary bar 69Support 20SureTrak Project Manager 133

161

copy Experience In Software Inc 1995 - 2006

- T -Task Data view 57task dates 73Task Report 102Taskbar 69Taskbar with percent done 69Tasks 25Tasks in Phases 25Tasks Library 89team 31Technical support 20timescale 84Timescale Menu 146Tools Menu 143Trademark 153trademarks 153Trial 14

- U -unassigning 38Understand Chart View 69Understand Task Data View 66Undo 11UndoRedo Buttons 11uninstallUninstalling 154Unlink tasks 12 65Up and Down arrows 63Use Project KickStart to 8Use the Gantt Chart Toolbar 63Use the Planning Wizard 9Uses 8Using Past Projects 29 155

- V -Version View Menu 142Visio 138

- W -Wall chart 111WBS Chart Pro 137Welcome to Project KickStart 7Whats Due Next Month 99Whats Due Next Week 99Whats Due Today 99Whats New in Project KickStart Pro 5 11Windows Vista 20

162

copy Experience In Software Inc 1995 - 2006

copy Experience In Software 2008w w w projectkickstartcom

  • Table of Contents
  • Start Here Welcome to Project KickStart
    • Introduction
      • Welcome to Project KickStart
      • Use Project KickStart to
      • Use the Planning Wizard
      • Navigating Project KickStart
      • Whats New in Project KickStart Pro 5
      • Whats New in Project KickStart Pro 5 (Pro Users)
      • Compatibility with earlier versions
      • Activating Trial Version
        • Licenses and Support
          • End User License Agreement
          • Customer Support
          • Reporting Technical Issues
          • Register Project KickStart
              • Planning Projects
                • Name Your Project
                • Phases - Step 1 of 2
                • Phases - Step 2 of 2
                • Goals - Step 1 of 3
                • Goals - Step 2 of 2
                • Goals - Step 3 of 3
                • Similar Projects - Step 1 of 2
                • Similar Projects - Step 2 of 2
                • People - Step 1 of 3
                • People - Step 2 of 3
                • People - Step 3 of 3
                • Obstacles - Step 1 of 3
                • Obstacles - Step 2 of 3
                • Obstacles - Step 3 of 3
                  • Assigning People
                    • Assign Tasks to People
                    • Remove People from a Task
                    • Add a New Person or Resource
                    • Edit or Substitute People
                      • Organizing the Project Plan
                        • About Organizing Tasks
                        • Change the Appearance of the Task List
                        • Show or Hide Tasks in the Task List
                        • Move Tasks within the Task List
                        • Outdent and Indent Tasks
                        • Add a Task or Subtask
                        • Edit Tasks
                        • Add Task Notes and Attachments
                        • Add or Change Task Assignments
                        • Add or Change Task Details
                        • Check Spelling
                          • Scheduling Tasks in the Gantt Chart
                            • Scheduling Overview
                              • About Scheduling Tasks
                              • About the Gantt Chart
                              • Autolink tasks (Pro Users)
                              • About Linking Tasks (Pro Users)
                              • Change the Display of the Schedule
                              • Use the Gantt Chart Toolbar
                              • Use the Gantt Chart Toolbar (Pro Users)
                              • Understand Task Data View
                              • Additional Features in Task Data View (Pro Users)
                              • Understand Chart View
                              • Additional Tools in Chart View (Pro Users)
                                • Change Task Dates
                                • Phase Dates Cannot Be Edited
                                • Quick Tour of Working with Linked Tasks (Pro Users)
                                • Link and Unlink Tasks (Pro Users)
                                • Create a Milestone
                                • Change Task Details
                                • Change Details for Linked Tasks (Pro Users)
                                • Reorganize Tasks in Task Data View
                                • Change the Timescale of the Schedule
                                • Specify Working Days
                                • Change the Color of Taskbars
                                • Make Tasks Overlap (Pro Users)
                                • Manage Changes in Your Schedule (Pro Users)
                                  • Managing Libraries
                                    • Use a Library
                                    • Manage a Library
                                    • Manage the People Library
                                    • Import ACT Contacts and Users to the People Library
                                    • Import Outlook Contacts to the People Library
                                    • Import Outlook Contacts via CSV to the People Library (Pro Users)
                                      • Printing Reports
                                        • Printing Dashboards
                                          • Print Reports
                                          • Print Dashboard Reports
                                          • Page Setup
                                          • Save As
                                            • Printing Task Reports
                                              • Print Task Reports
                                              • Print Preview
                                              • Printer Setup
                                              • Page Setup
                                              • Email Task Reports
                                              • Save As HTML
                                              • Save As RTF
                                                • Printing Gantt Chart Reports
                                                  • Print a Gantt Chart
                                                  • Print Preview a Gantt Chart
                                                  • Page Setup
                                                  • Printing to an Adobe PDF file
                                                  • Save Gantt Chart Images
                                                      • Export Project Data
                                                        • Export to ACT
                                                          • Export to ACT 7 and Later
                                                          • Export to ACT 6
                                                            • Export to Microsoft Outlook
                                                            • Export to Microsoft Word
                                                            • Export to Word Processors (Other than Word)
                                                            • Export to Microsoft Excel
                                                            • Export to Microsoft PowerPoint
                                                            • Export to Microsoft Project
                                                            • Export to SureTrak Project Manager
                                                            • Export to FastTrack Schedule
                                                            • Export to Milestones Professional
                                                            • Export to Mindjet MindManager
                                                            • Export to WBS Chart Pro
                                                            • Export MPX Files
                                                              • Reference
                                                                • Menus
                                                                  • File Menu
                                                                  • Edit Menu
                                                                  • View Menu
                                                                  • Tools Menu
                                                                  • Options
                                                                  • Data Menu
                                                                  • Timescale Menu
                                                                  • Help Menu
                                                                    • Shortcuts
                                                                    • Share Project KickStart data
                                                                    • Open a Project
                                                                    • Dedication
                                                                    • Credits and Trademarks
                                                                    • Uninstalling the software
                                                                    • Using Past Projects
Page 5: Project KickStart Help File in PDF format

5

copy Experience In Software Inc 1995 - 2006

Export to ACT 6 122 Export to Microsoft Outlook 123 Export to Microsoft Word 125 Export to Word Processors (Other than Word) 127 Export to Microsoft Excel 128 Export to Microsoft PowerPoint 130 Export to Microsoft Project 132 Export to SureTrak Project Manager 133 Export to FastTrack Schedule 134 Export to Milestones Professional 135 Export to Mindjet MindManager 136 Export to WBS Chart Pro 137 Export MPX Files 138Reference 139 Menus 140 File Menu 140 Edit Menu 141 View Menu 142 Tools Menu 143 Options 144 Data Menu 145 Timescale Menu 146 Help Menu 147 Shortcuts 148 Share Project KickStart data 150 Open a Project 151 Dedication 152 Credits and Trademarks 153 Uninstalling the software 154 Using Past Projects 155

6

copy Experience In Software Inc 1995 - 2006

Start Here Welcome to Project KickStart

7

copy Experience In Software Inc 1995 - 2006

Introduction

Welcome to Project KickStart

Whether yoursquore a novice or seasoned pro yoursquoll be amazed at how quickly you can create a thoughtfulcomprehensive task list and project schedule Using Project KickStart you can go from raw idea to aproject task list in 30 minutes You do not need any special project management training to use ProjectKickStart

The first thing youll want to do is

Open a project Click to open one of our sample projects

Start a new project Click to begin planning your own project

Open your last project If youve already created a project click this option to open your most recentproject

After that let Project KickStart show you the way Itrsquos easy to navigate Project KickStart with its intuitivegraphical interface--it feels like a coach is guiding you through each step

Next StepsProject KickStart guides you through the process of planning and scheduling your project On the top ofeach Project KickStart window are instructions explaining what to do Read the instructions enter your dataand then click the Next button in the lower-right corner of the window Additional help is always availablefrom the onscreen Advisor and Project KickStart Help

Sample ProjectsThe sample projects are completed projects that let you get a feel for Project KickStart If you find onesimilar to the project you want to create open it save it with a new name and then customize it to meetyour needs

-o-

8

copy Experience In Software Inc 1995 - 2006

Use Project KickStart to

Project KickStart is organized into three sections planning scheduling and exporting to other programs

Plan The Project KickStart graphical interface acts as a Planning Wizard guiding you through eightsteps for planning your project Some planning steps involve brainstorming to identify tasks that youmight otherwise overlook

Schedule The Project KickStart Gantt chart makes scheduling tasks fast and easy You can printtaskbars in color and save Gantt charts reports as images so you can email them to colleagues orinclude them in a report

Export Communicate your projects in a variety of ways by exporting project data to other applicationsincluding Microsoft Outlook With one mouse click you can include Project KickStart plans in aMicrosoft Word document Excel spreadsheet PowerPoint slide presentation and more

People are using Project KickStart to

Create process templates project reports to-do lists and more

Communicate project details to others through reports email and Gantt chart schedules

Ensure project buy-in by including the needs of team members in your plan

Consider project goals and obstacles in the planning process and prevent surprises later

-o-

9

copy Experience In Software Inc 1995 - 2006

Use the Planning Wizard

Project KickStart uses a Planning Wizard that guides you through eight steps for planning your project Tostep through the wizard click each icon on the Steps bar (on the left side of the Project KickStart window) inorder On each window t ips and advice are always available by clicking the Advisor button You click theNext button to continue

Name Each project has a name To start planning your project give it ashort descriptive name

Phases Consider how your project will break down into major activitiesor phases Start by listing your phases and then list the tasks thatbelong in each phase

Goals Goals are what you hope to accomplish in your project Enter orselect the goals for your project Then you can list any new tasks toachieve each goal

Similar Projects often have tasks in common In this step you canborrow tasks from past projects to help you plan this project Then youcan add any new tasks from a similar project to the phases of yourcurrent project

People List the people groups or things that might provide resourcesfor your project including yourself Then identify any new tasks thesepeople might do or suggest for your project

Obstacles Each project has obstacles you can overcome if youanticipate them List the obstacles you will face in your project and thenidentify any new tasks needed to avoid the obstacles

Assign Assign tasks to people and other resources

Tasks Change the order of your tasks add and delete tasks andcreate subtasks You can also edit tasks change assignments and addnotes

Schedule Schedule the tasks in your project To make schedulingeasier new projects open with a starter schedule beginning todaywhich you can customize to fit your project

-o-

10

copy Experience In Software Inc 1995 - 2006

Navigating Project KickStart

When you use the Planning Wizard you work with a step window similar to the following illustration

Steps bar Click a step button to perform a step in the Planning Wizard The selected button shows yourcurrent step

Name of your project Shows the name entered in the Name step

Menu bar Select options from the menu bar to work with your projects

Toolbar Click buttons to perform common tasks such as saving your project

Step instructions Indicate how to perform the current step

Library button Click to open a library for the current step For example click the Goals Library button toopen a library listing typical project goals

Back and Next buttons Click a button to return to the previous step or continue to the next step in thePlanning Wizard

Advisor button Click to see instructions tips and notes for completing the current step

-o-

11

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5

The following table outlines whatrsquos new in Project KickStart Pro 5

If you own a previous version of Project KickStart yoursquoll notice the new Pro version has a new look and feelAs you begin to check it out yoursquoll soon discover Project KickStart Version 5 is a lot more powerful thanprevious versions and comes with some great new features

FEATURE DESCRIPTION IMPROVED

NEW

Dashboard Reporting

Quickly assess what is due TodayNext Week or Next Month

X

Import Contacts Import from a comma separatedvalue (CSV) file

X

Templates Use as is or customize X

Gantt Chart Greater stability and functionality X

User Interface Contemporary look and colorscheme

X

Preferences Customize look and feel andprogram defaults

X

Productivity Pack Project template Word docs fornewbies

X

Exports Improved Outlook MindManager and ACTimproved data exchange

X

-o-

12

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5 (Pro Users)

This feature is available only in Project KickStart Professional

The following table outlines whatrsquos new in Project KickStart Pro 5

FEATURE DESCRIPTION IMPROVED NEW

Gantt Chart Task dependencies in Gantt chart X

Link tasks Show task dependencies X

Unlink tasks Remove task dependencies X

Add predecessors Add task predecessors X

Add successors Add task successors X

Project Coordination Link to GoToMeeting for onlinemeetings on projects

X

Project KickStart Pro now includes dependencies on the Gantt chart This sophisticated scheduling andproject management tool is new to Project KickStart Pro and is designed to make complex projectscheduling easy and straightforward

Use dependencies to handle scheduling demands delays and surprises without modifying every task inyour project Dependencies let you make adjustments as events change giving you a more robust scheduleand the opportunity to conduct what-if analysis

Suppose you are managing a landscaping project involving subcontractors and dozens of tasks One ofyour first tasks is to pave a path with flagstones but the shipment of flagstones is two days late Usingdependencies you can delay the path-paving task in a couple of clicks and Project KickStart Proautomatically updates the schedule for the remaining tasks

Although dependencies meet your advanced scheduling needs the Project KickStart Pro approach todependencies keeps them as simple as possible If you want to link a couple of tasks which are dependenton one another you can simply highlight the tasks and click the link icon

If you select the option of Autolinking tasks then when you display the Gantt chart the first time all tasksare pre-linked allowing you to adjust durations schedules of individual tasks and time between taskswhich is called Lead Time in Project KickStart Pro

Unlike other project management programs such as Microsoft Project Project KickStart Pro does notburden you with complicated error messages and various types of dependencies It provides only one typeof dependency finish-to-start which is the most common type This means you can fine-tune your scheduleas soon as you open the Gantt chartmdashwithout having to learn technical terms or advanced projectmanagement techniques

The Project Coordination functionality that we are providing is through GoToMeeting and is a chargedservice

Note

These features are in addition to those listed on the Whatrsquos New in Project KickStart 5 page

-o-

13

copy Experience In Software Inc 1995 - 2006

Compatibility with earlier versions

Project KickStart 5 can open and save projects in Project KickStart 4 prx file format (Same as ProjectKickStart 5)

Project KickStart 5 can open and convert projects saved in Project KickStart 3 prj file format You need tohave a licensed copy of Project KickStart 3 on your system to make the conversion

To open a prj project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click prj file type3 Navigate to the folder that contains the prj file Generally prj files are stored in cprogram filesProject

KickStart 34 Double-click the name of the file

Tips

The tasks in the converted Project KickStart 5 file will have the same start and finish dates and samedurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way (ie as working days) To have weekends as non working days click the Change WorkingSchedule button on the Gantt chart toolbar and mark weekends as non working

Note

Project KickStart 5 does not open and convert prj files from Project KickStart 1 or 2

-o-

14

copy Experience In Software Inc 1995 - 2006

Activating trial version

You may have obtained a FREE 20-day trial version of Project KickStart 5 from our website or from areseller

To convert your Trial Version to a Full Version youll need to purchase a License Key and to activate thesoftware

To activate Project KickStart 5 trial1 Start the Project KickStart trial

2 If you have not purchased your License Key yet click the Buy button to purchase online3 If you have purchased a License Key click the Activate button and copy and paste the License Key

that you received when you purchased Project KickStart as well as your name and email

15

copy Experience In Software Inc 1995 - 2006

4 You must be connected to the Internet and you must tell your Firewall to allow communication forPKS5Kickstartexe

Tip

Your License Key allows 2 activations per user One is for your primary computer and one is for asecond computer you use such as your laptop or home computer

-o-

16

copy Experience In Software Inc 1995 - 2006

Licenses and Support

End User License Agreement

EXPERIENCE IN SOFTWARE INC END USER LICENSE AGREEMENT AND WARRANTYDISCLAIMER

PROJECT KICKSTARTtrade STANDARD 5 AND PRO 5 EDITIONS

NOTICE This is a legally binding contract between you the end user and EXPERIENCE IN SOFTWAREINC

EXPERIENCE IN SOFTWARE INC (EIS or LICENSOR) LICENSES THE ENCLOSED SOFTWARETO YOU (USER or LICENSEE) ONLY UPON THE CONDITION THAT YOU ACCEPT ALL OF THETERMS CONTAINED IN THIS LICENSE AGREEMENT PLEASE READ THE TERMS CAREFULLY BYOPENING THIS PACKAGE BREAKING THE SEAL CLICKING ON THE ldquoAGREErdquo OR ldquoYESrdquo BUTTONOR OTHERWISE INDICATING ASSENT ELECTRONICALLY OR LOADING THE SOFTWARE YOUAGREE TO THE TERMS AND CONDITIONS OF THIS AGREEMENT IF YOU DO NOT AGREE TOTHESE TERMS AND CONDITIONS CLICK ON THE ldquoI DO NOT AGREErdquo ldquoNOrdquo BUTTON OR MAKE NOFURTHER USE OF THE SOFTWARE IF YOU DO NOT AGREE TO THESE TERMS THEN EIS ISUN-WILLING TO LICENSE THE SOFTWARE TO YOU IN WHICH EVENT YOU SHOULD RETURN THEFULL PURCHASED PRODUCT WITH PROOF OF PURCHASE TO LICENSOR OR THE DEALER FROMWHOM IT WAS ACQUIRED WITHIN 15 DAYS OF PURCHASE AND YOUR MONEY WILL BEREFUNDED

LICENSE AND WARRANTY

The software that accompanies this license (Software) is the property of EIS and is protected by copyrightand other intellectual property law Although EIS at all times owns the Software you will have certain rightsto use the Software after your acceptance of this license Except as may be modified by an addendumwhich may accompany or be added to this license your rights and obligations with respect to the use of thisSoftware are as follows

You may

(i) install and use one copy of the specified edition of Software and documentation on a single computerand only by one user (ldquoPrimary Userrdquo) If you have purchased multiple licenses for the Software asindicated as Quantity or Number of Licenses on the Invoice or electronic confirmation issued by EIS orits Resellers then at any time you may have as many copies of the Software in use as you have licenses The Software is ldquoin userdquo on a computer when it is loaded into the temporary memory (ie RAM) or installedinto the permanent memory (eg hard disk CD-ROM or other storage device) of that computer

(ii) install and use a second copy of the Software on a second computer for the limited and exclusive use ofthe Primary User

(iii) use the Software on a network provided that Licensee has a licensed copy of the Software for eachnamed user that can access the Software over that network

(iv) make one copy of the Software for archival purposes or copy the Software onto the hard disk of yourcomputer and retain the original for archival purposes

(v) after written notice to EIS transfer the Software on a permanent basis to another person or entityprovided that you retain no copies of the Software and the transferee agrees to the terms of this agreement

You may not

(i) rent lease copy distribute license or otherwise transfer the Software or its documentation to any otherparty Licensee may make a reasonable number of back-up copies for archival purposes only TheSoftware contains copyrighted material trade secrets and other proprietary material If Licensee has theright to duplicate the Software for multiple Users then Licensee must reproduce on all such copies of theSoftware the copyright notices and any other proprietary legends that were on the original copy of theSoftware or

(ii) decompile reverse engineer disassemble translate make any attempt to discover the source code ofthe Software or otherwise reduce the Software to a human perceivable form or modify network or create

17

copy Experience In Software Inc 1995 - 2006

derivative works based upon the Software or the documentation in whole or in part nor permit any otherparty to do so

Notwithstanding anything herein if the Software is lawfully acquired outside of the United States within ajurisdiction which is a member of the European Union subject to the EEC Council Directive 91250EEC ofMay 14 1991 Licensee agrees that within that jurisdiction it shall not and shall not allow any party onLicensees behalf to attempt to reverse engineer or decompile the Software into another computerlanguage except as expressly and specifically provided in the EEC Council Directive 91250EEC of May14 1991 Any and all information obtained during such lawful reverse engineering andor decompilingactivities including but not limited to the organization logic algorithms and processes of the Softwareshall be deemed to be the confidential and proprietary information of EIS

Licensee shall not make copies of the copyrighted Software documentation without the prior writtenpermission of EIS provided that for electronic transactions Licensee may make one (1) hard copy of suchdocumentation for each User

Intellectual Property and Duplication of Software

The Software contains copyrighted material trade secrets and other proprietary material If Licensee hasthe right to duplicate the Software for multiple Users then Licensee must reproduce on all such copies ofthe Software the copyright notices and any other proprietary legends that were on the original copy of theSoftware

Upgrades

To use a Product identified as an upgrade you must first be licensed for the product identified by EIS aseligible for the upgrade After upgrading you may no longer transfer the product that formed the basis foryour upgrade eligibility to another person or entity

Technical Support

Licensee must register the Software in order to be eligible for free technical support (including installationand registration of the product) during the first 90 days after purchase

Thirty Day Money Back Guarantee

If you are the original Licensee of this copy of the Software and are dissatisfied with it for any reason youmay return the complete product together with your receipt to EIS or an authorized dealer postageprepaid for a full refund at any time during the thirty-day period following the delivery to you of thePurchased Software

Export Law Assurances

You are responsible for complying with all trade regulations and laws both foreign and domestic Youacknowledge that none of the Software or underlying information or technology may be downloaded orotherwise exported or re-exported (i) into Afghanistan (Taliban-controlled areas) Cuba Iran Iraq LibyaNorth Korea Serbia (except Kosovo) Sudan and Syria or any other country subject to a US embargo or(ii) to anyone on the US Treasury Departments list of Specially Designated Nationals or the USCommerce Departments Denied Parties List or Entity List By using the Software you are agreeing to theforegoing and are representing and warranting that (i) no US federal agency has suspended revoked ordenied you export privileges (ii) you are not located in or under the control of a national or resident of anysuch country or on any such list and (iii) you will not export or re-export the Software to any prohibitedcounty or to any prohibited person entity or end-user as specified by US export controls as defined byEAR 15 CFR Parts 730-774 and BXA (httpwwwbxadocgov)

Data Collection and Privacy Policy

You acknowledge and agree that EIS may collect and retain information about you such as your nameaddress and e-mail address You also understand that EIS may employ other companies to performfunctions on our behalf such as fulfilling orders delivering packages sending postal mail and e-mailproviding marketing assistance and processing credit card payments These companies may have accessto personal information needed to perform their functions and may not use such information for otherpurposes By assenting to this agreement you agree that you have read and understand our Privacy PolicyFor more detailed information httpwwwprojectkickstartcomhtmlprivacy_statementhtm

Termination

This License is effective until terminated Licensee may terminate this License at any time by destroying allcopies of the Software and its documentation This License will terminate immediately without notice from

18

copy Experience In Software Inc 1995 - 2006

EIS if Licensee fails to comply with any provision of this License Upon termination Licensee must destroyall copies of the Software and its documentation and cease and desist from any further use of the Software

Limited Warranty

EIS warrants that the media on which the Software is distributed will be free from defects and that theSoftware shall perform substantially as described in its documentation for a period of sixty (60) days frompurchase Your sole remedy in the event of a breach of this warranty will be that EIS will replace anydefective media returned to EIS within the warranty period EIS does not warrant that the Software willmeet your requirements or that operation of the Software will be uninterrupted or that the Software will beerror-free

THE ABOVE WARRANTY IS EXCLUSIVE AND IN LIEU OF ALL OTHER WARRANTIES WHETHEREXPRESS OR IMPLIED INCLUDING THE IMPLIED WARRANTIES OF MERCHANTABILITY FITNESSFOR A PARTICULAR PURPOSE AND NONINFRINGEMENT OF INTELLECTUAL PROPERTY RIGHTSTHIS WARRANTY GIVES YOU SPECIFIC LEGAL RIGHTS YOU MAY HAVE OTHER RIGHTS WHICHVARY FROM STATE TO STATE AND COUNTRY TO COUNTRY

Disclaimer of Damages

REGARDLESS OF WHETHER ANY REMEDY SET FORTH HEREIN FAILS OF ITS ESSENTIALPURPOSE IN NO EVENT WILL EIS OR ITS RESELLERS BE LIABLE TO YOU FOR ANY SPECIALCONSEQUENTIAL INDIRECT OR SIMILAR DAMAGES INCLUDING BUT NOT LIMITED TO ANY LOSTPROFITS OR LOST DATA ARISING OUT OF THE USE OR INABILITY TO USE THE SOFTWARE EVENIF EIS HAS BEEN ADVISED OF THE POSSIBILTIY OF SUCH DAMAGES SOME STATES DO NOTALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FOR INCIDENTAL OR CONSEQUENTIALDAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAY NOT APPLY TO YOU IN NO CASESHALL EISS ITrsquoS RESELLERrsquoS LIABILITY EXCEED THE PURCHASE PRICE FOR THE SOFTWARE

SOME STATES AND COUNTRIES INCLUDING MEMBER COUNTRIES OF THE EUROPEANECONOMIC AREA DO NOT ALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FORINCIDENTAL OR CONSEQUENTIAL DAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAYNOT APPLY TO YOU

The disclaimers and limitations set forth above will apply regardless of whether you accept the Software

US Government Restricted Rights

DISTRIBUTION TO THE US GOVERNMENT This Software is commercial software developedexclusively at private expense This Software and the documentation are provided with RESTRICTEDRIGHTS applicable to private and public licenses alike Use duplication or disclosure by civilian agenciesof the US Government shall be in accordance with the Commercial Computer Software-Restricted Rightsclause at FAR 52227-19 Use duplication or disclosure by Department of Defense agencies is subjectsolely to the terms of this software licensing agreement pursuant to DFARS 2277202Contractormanufacturer of the Software is EXPERIENCE IN SOFTWARE INC 2029 Durant AveBerkeley CA 94704 USA

General

This Agreement shall be governed by the laws of the State of California without giving effect to principles ofconflict of laws You hereby consent to the exclusive jurisdiction and venue of the state courts sitting in SanFrancisco County California or the federal courts in the Northern District of California to resolve anydisputes arising under this Agreement This Agreement contains the complete understanding between theparties with respect to the subject matter hereof and supersedes all prior or contemporaneous Agreementsor understandings whether oral or written You agree that any varying or additional terms contained in anypurchase order or other written notification or document issued by you in relation to the Software licensedhereunder shall be of no effect No provision hereof shall be deemed waived or modified except in writing No EIS dealer agent or employee is authorized to make any amendment to this Agreement

The intellectual property protections the disclaimers of warranties and the limitation of damages shallsurvive termination The failure or delay of EIS to exercise any of its rights under this Agreement or uponany breach of this Agreement shall not be deemed a waiver of those rights or of the breach If any provisionof this Agreement is held invalid the remainder of this Agreement will remain in full force and effect

Should you have any questions concerning this Agreement or if you desire to contact EIS for any reasonplease write to EXPERIENCE IN SOFTWARE INC 2029 Durant Ave Berkeley CA 94704 USA

-o-

19

copy Experience In Software Inc 1995 - 2006

20

copy Experience In Software Inc 1995 - 2006

Customer Support

When you need help in solving a problem with the software Experience In Software is available to assistyou First check this help file for information on the part of the program you are having a problem withAlso take a look at the Web site for late-breaking technical support information wwwprojectkickstartcomsupporttechnical_supportcfm If you are a regustered user you can obtain support in the following ways

Web httpwwwprojectkickstartcomsupportemail_supportcfm E-mail supportprojectkickstartcom

Hours 900 am to 500 pm Pacific time Monday - Friday

To make the support process more efficient have the following information ready for the support staff

Provide your name phone number and email address

Describe the problem including any error messages

If reporting a potential bug describe what you did immediately before seeing the bug

Provide the Project KickStart version number and Build Date (Click Help on the menu bar and thenclick About Project KickStart)

Identify the version of Windows (Windows Vista etc) you are using

Notes

Our policy is to respond to support email within two business days If you have not received aresponse please double check that spam filters are blocking our messages to you If you maintain anincoming whitelist please allow all messages from the projectkickstartcom domain

Support is available in English only If you purchased a translated version please contact your localreseller for help in other languages

See Also

Reporting Technical Issues

-o-

21

copy Experience In Software Inc 1995 - 2006

Reporting Technical Issues

If Project KickStart 5 detects an error it will write a log of technical issues and then create a temporarymenu to the right of the Help menu which says Send Log to Technical Support You should immediatelyclick the menu and then click Yes to send the error log to us

Please fill in your email address so that we can get back to you with any questions about what caused theerror

Tip

If you have an Internet Security Program such as Norton Internet Security please allowPKS5Kickstartexe to communicate with the Internet to report the error

-o-

22

copy Experience In Software Inc 1995 - 2006

Register Project KickStart

To print this page click the Print button on the Help window toolbar

Register Project KickStart 5 for technical support upgrade information and software discounts You canregister by completing printing and then sending or faxing this form to Experience In Software You canalso register online at httpwwwprojectkickstartcomsupportregiscfm

Name _______________________________________________________

Title _______________________________________________________

Company _______________________________________________________

Address _______________________________________________________

CityStateZip ______________________________________________________

Country _______________________________________________________

Day Phone _______________________________________________________

Fax _______________________________________________________

E-mail _______________________________________________________

Purchased from __ Experience In Software __ Other ____________________

Number of people in company _ 1 to 25 _ 26 to 100 _ 101 to 1000 _ Over 1000

Which industry do you work in ______________________________________

Interested in a project management workshop for your company __ Yes __ No

Comments _______________________________________________________

_________________________________________________________________

_________________________________________________________________

Experience In Software 2029 Durant Ave Berkeley CA 94704

Send or FAX to (510) 644-3823

-o-

23

copy Experience In Software Inc 1995 - 2006

Planning Projects

Name Your Project

Before you start thinking about the tasks in your project yoursquoll want to give your project an appropriate titleIf you open an existing project you might want to edit or change the name of your project

To name your project1 In the Type a name for your project text box enter a name2 Click the Next button

Tips

You can enter up to 58 characters and more than one

Use short descriptive project names such as ldquoCompany Web Siterdquo

Avoid vague project names such as ldquoDatabase Projectrdquo or ldquoCDP-7rdquo especially if you plan to circulatereports to others

Enter your project title using uppercase letters if you want the title to stand out in reports

One way to reuse your projects is to open an existing project and then change its name in this stepAfter saving the project with a different name you can modify details to customize the project

See Also

Use the Planning Wizard

-o-

24

copy Experience In Software Inc 1995 - 2006

Phases - Step 1 of 2

After naming your project the next step in the Planning Wizard is to identify the major activities in yourproject Using phases helps organize tasks so that an obviously early task such as ldquoOrganize materialsrdquoappears before a later task such as ldquoReview final draftrdquo

To enter phases1 Type each phase one per line

OrClick the Phases Library button The Phases Library contains typical phases that many organizationsuse in the early middle and late stages of their projects Drag an entry from the Phases Library to thelist and then click the OK button to close the Phases Library

2 To insert a phase in the middle of the phases list click where you want to insert a new blank line andthen press the Insert keyTo edit the phase text double-click the phase

Tips

Start each phase name with an action verb as in ldquoBuild systemrdquo or ldquoWrite reportrdquo

Use actions that have clearly defined beginnings middles and ends For example you can scheduletasks like ldquoTest prototyperdquo more easily than tasks like ldquoPurchase high-quality partsrdquo

Note

Youll have the opportunity to edit phases later in the Tasks step For now continue planning thephases in your project

See Also

Use the Planning Wizard

Use a Library

Move Tasks within the Task List

-o-

25

copy Experience In Software Inc 1995 - 2006

Phases - Step 2 of 2

For each phase list all of the tasks that could be performed during that phase You can refine and organizethe tasks later in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each phase1 Type the tasks associated with the phase displayed in the Tasks for phase text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next phase in your project click the Next button If you prefer to work out oforder click the Tasks for phase list arrow and then click the phase you want

3 When you are finished entering tasks for the last phase in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

26

copy Experience In Software Inc 1995 - 2006

Goals - Step 1 of 3

Enter the goals for your project the objectives you hope to accomplish Then you can brainstorm anyadditional tasks that will help you meet these goals

To enter goals1 Type each goal one per line

OrThe Goals Library contains typical sample goals that you can customize Drag an entry from the GoalsLibrary to the list and then click the OK button to close the Goals Library

2 To insert a goal in the middle of the goals list click where you want to insert a new blank line and thenpress the Insert keyTo edit the goal text double-click the goal

3 Click the Next button

Tips

List goals that apply to the entire project such as Develop a high-quality system A goal such as Getthe contract signed applies only to an early phase

Write goals as actions you can measure For example Complete the project for $75000 or less ismore concrete and specific than Complete the project within budget Numbers make goal statementsreal

If youre not sure how to measure a goal use a range as in About 15 - 25 people will use the results ofthe project

See Also

Use the Planning Wizard

Use a Library

-o-

27

copy Experience In Software Inc 1995 - 2006

Goals - Step 2 of 3

For each goal list any new tasks needed to accomplish that goal You can refine and organize the taskslater in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each goal1 Type the tasks for accomplishing the goal displayed in the For the goal text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next goal in your project click the Next button If you prefer to work out of orderclick the For the goal list arrow and then click the goal you want

3 When you are finished entering tasks for the last goal in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

28

copy Experience In Software Inc 1995 - 2006

Goals - Step 3 of 3

After you identify new tasks for your project assign each new task to an appropriate phase

To assign new tasks to phases1 Click a task in the New tasks to achieve goals list (on the left)2 Click one or more phases in the Assign them to Phases list (on the right) to which the task belongs A

checkmark appears next to tasks youve assigned

If a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Note

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

29

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 1 of 2

Projects often have tasks in common The Similar Projects step makes it easy for you to borrow tasks fromother projects and add them to your current project

By default this step shows the Project KickStart (PRX) projects stored in the same folder as the currentproject including sample projects and those you already created

To select similar projects1 Review the projects in the list To sort the project names alphabetically click the Project Name header

Click the Project Name header again to sort the names in reverse order2 Click one or more projects in the list that contain tasks you want to use in the current project A

checkmark appears next to the projects you selected3 To list projects stored in a different folder on your system click the Browse button and then navigate to

the folder you want4 Click the Next button

If no projects seem related to your current project skip this step for now

Tips

The Similar Projects step becomes more helpful the more you use Project KickStart Every time yousave a project it becomes available for future use

Many projects share the same phases and tasks such as those for setting up a contract or purchasingequipment You can use Project KickStart to create these mini-projects or templates and then importtheir tasks into a new project during the Similar Projects step

-o-

30

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 2 of 2

After you select one or more projects containing tasks you might want to use assign those borrowed tasksto a phase in this project

To assign borrowed tasks to phases1 Click a task in the list on the left If a task includes subtasks click the plus icon to expand the list Click

the minus icon if you want to hide the subtasks To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more phases in the Assign tasks to phase(s) of your project list (on the right) to whichthe task belongs A checkmark appears next to tasks youve assigned

3 To assign one or more tasks to a new phase select the tasks click ltNew Phasegt in the Assign tasksto Phases of your project list and then type a name for the new phase

4 To select tasks from another project you selected as similar click the Tasks from Similar Projects listarrow click the project you want and then assign the tasks to phases

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also Edit Tasks

-o-

31

copy Experience In Software Inc 1995 - 2006

People - Step 1 of 3

Enter the names or descriptions of the people involved in your project Include key decision makers suchas executives or customers who must approve or consult with you about the project These are yourprojects resources In the next People step youll identify new tasks associated with these resources

To enter people1 Type each name or description one per line

OrIf you have stored information about people and other resources in the People Library click the PeopleLibrary button drag an entry from the library to the list and then click the OK button to close thePeople Library

2 To edit the people text double-click the name or description3 Click the Next button

Tips

Be consistent with the resource names in your projects For instance avoid using Richard in oneproject and Dick in another project when referring to the same person

Include names for people teams (such as Quality control team) departments (such as Manufacturing)companies (such as Acme Widgets Corp) or even equipment (such as wheat thrasher)

Note

Add people and other resource information to the People Library so that you can quickly drag resourcesfrom the library to any project You can even import people from your Outlook and ACT address books

See Also

Manage the People Library

Import ACT Contacts and Users to the People Library

-o-

32

copy Experience In Software Inc 1995 - 2006

People - Step 2 of 3

Now that you have defined the people needed to complete your project list any new tasks that eachresource might suggest or require

To enter new tasks for each person1 Type the new tasks associated with the person displayed in the Tasks For text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next person in your project click the Next button If you prefer to work out oforder click the Tasks For list arrow and then click the person you want

3 When you are finished entering new tasks for the last person in your project click the Next button tocontinue in the Planning Wizard

Tips

This step provides a good opportunity to get input from your resources directly and make sure theproject plan reflects the views of everyone on the team

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo Write the tasks roughly in the order that you will complete them You can reorganize the tasks later in

the Tasks step

Note

You assign people to tasks in the Assign Tasks and Schedule steps

See Also

Use a Library

Move Tasks within the Task List

Assign Tasks to People

-o-

33

copy Experience In Software Inc 1995 - 2006

People - Step 3 of 3

After you identify new tasks associated with the people in your project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by people list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

34

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 1 of 3

Every project has obstacles and risks that can affect its success List the major obstacles you face incompleting your project Then you can brainstorm any additional tasks that can help you overcome orminimize these problems

To enter obstacles1 Type each obstacle one per line

OrThe Obstacles Library contains typical sample obstacles that you can customize Drag an entry fromthe Obstacles Library to the list and then click the OK button to close the Obstacles Library

2 To insert an obstacle in the middle of the obstacles list click where you want to insert a new blank lineand then press the Insert key

3 To edit the obstacle text double-click the obstacle4 Click the Next button

Tips

Be creative when thinking of obstacles Highly imaginative obstacles can suggest realistic tasks Forexample Project manager kidnapped by aliens can lead to Project manager out of town forconference In Obstacles step 2 of 3 you can add the realistic activities as tasks You can delete theunrealistic obstacles later by returning to Obstacles step 1 of 3

Avoid listing too many obstacles even if they are realistic Hard core pessimists find it hard to getanything done

Edit and update the Obstacles Library so that you can quickly drag obstacles from the library to anyproject in your organization

See Also

Use a Library

-o-

35

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 2 of 3

After identifying the obstacles to completing your project determine how you can avoid these stumblingblocks List any new tasks you need to overcome or avoid each obstacle In this way you are developing acontingency plan for your project

To enter new tasks for each obstacle1 Type the new tasks associated with the obstacle displayed in the Obstacle text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next obstacle in your project click the Next button If you prefer to work outof order click the Obstacle list arrow and then click the obstacle you want

3 When you are finished entering new tasks for the last obstacle in your project click the Next button tocontinue in the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

You can reorganize the tasks and add notes later in the Tasks step

See Also

Use a Library

Move Tasks within the Task List

Add Task Notes and Attachments

-o-

36

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 3 of 3

After you identify new tasks for overcoming the obstacles to completing project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by obstacles list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

3 Click the Next button

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

37

copy Experience In Software Inc 1995 - 2006

Assigning People

Assign Tasks to People

After youve identified people working on your project you can assign tasks to each person or otherresource

To assign tasks to people1 Click a phase or task in the For each phase or tasks list (on the left)

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more people in the Assign some people list (on the right) who will perform the task Acheckmark appears next to tasks youve assigned

3 To assign a selected task to all of the people in your project click the All button4 To assign one or more tasks to a new person select the tasks click ltNew Persongt in the Assign

some people list and then type a name for the new person

To unassign a task

To unassign a task click the task and then click the highlighted person from which you want to removethe task You can assign that task to a different person if necessary You can also click the All buttonto remove a task from all of its assignments at the same time

Tip

Some users like to skip to the Tasks step before performing the Assign step That way they can edittheir list of tasks before assigning people and resources This helps them focus the project and givesthem a clearer idea of what must be done before committing resources

Notes

You can also assign tasks to people in the Tasks step and the Schedule step

You can assign tasks to non-personnel resources such as equipment (a CAD system or back hoe)facilities (a classroom or hotel) services (lab work or insurance) or materials (lumber or officesupplies) just as you assign tasks to people Click ltNew Persongt to add a new resource to the list

See Also

Remove People from a Task

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

38

copy Experience In Software Inc 1995 - 2006

Remove People from a Task

After assigning tasks you might need to remove people from a task or unassign them

To remove people from a task (unassigning)1 Click a phase or task in the For each phase or tasks list (on the left)

The people assigned to that phase or task are highlighted in the Assign some people list (on theright)

2 Click a highlighted person to remove or unassign that person from the taskWhen the person is no longer highlighted they are not assigned to the selected task

See Also

Assign Tasks to People

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

39

copy Experience In Software Inc 1995 - 2006

Add a New Person or Resource

If you realize that you want to assign some tasks to a person not included in the Assign some people listyou can add that person and assign tasks in the same step You can also add non-personnel resourcessuch as such as equipment (a CAD system or back hoe) facilities (a classroom or hotel) services (lab workor insurance) or materials (lumber or office supplies)

To add a new person or resource1 Select one or more phases or tasks in the For each phase or tasks list (on the left) 2 Click ltNew Persongt in the Assign some people list and then type a name for the new person or

resourceThis adds the new person or resource to the list and assigns the selected tasks to them

See Also

Assign Tasks to People

Remove People from a Task

Edit or Substitute People

Add or Change Task Assignments

-o-

40

copy Experience In Software Inc 1995 - 2006

Edit or Substitute People

If the people or resources in your project change you can replace them or edit their names anddescriptions

To edit or substitute people1 Click the People icon

You return to People step 1 of 32 In the list of people defined for the project double-click the person you want to edit or replace or click

the name and press F23 Edit the name or description of the person

When you return to the Assign step the name of the person appears as you changed it

See Also

Assign Tasks to People

Remove People from a Task

Add a New Person or Resource

Add or Change Task Assignments

-o-

41

copy Experience In Software Inc 1995 - 2006

Organizing the Project Plan

About Organizing Tasks

In the Tasks step you work with an outline of your project plan Here you can easily edit and reorganizetasks spell check and even add notes and attachmentsClick the following illustration to see tips for using this window

Edit the Task List to Consolidate and delete tasks Add subtasks Add or change task assignments Add follow-up notes to tasks Add or change attachments Review the order of the tasks in each phase and move tasks up or down so that they progress

sequentially Review task descriptions to make sure they are clear and that all the team members will understand

them Convert vague tasks such as reminders and open issues to task notes

Notes

Some users like to revise their Task List before they assign resources You can go to the Task List atany time while you are using Project KickStart

Each project created with Project KickStart can contain up to 1000 tasks

See Also

Change the Appearance of the Task List

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

Add Task Notes and Attachments

Add or Change Task Assignments

Add or Change Task Details

-o-

42

copy Experience In Software Inc 1995 - 2006

43

copy Experience In Software Inc 1995 - 2006

Change the Appearance of the Task List

You can change the appearance of the Task List so you can work with it more effectively

To add a column

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task ListBy default the Task List shows the Task Name Assignments and Notes columns You can also showCost and Done columns

To hide a column

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

To move a column

Drag a column heading to a new position in the Task List

To change the column width

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Show or Hide Tasks in the Task List

-o-

44

copy Experience In Software Inc 1995 - 2006

Show or Hide Tasks in the Task List

To hide tasks or subtasks

To hide the subtasks for a task click the minus icon next to the task

To hide all the tasks in the Task List and show only phases click all the minus icons next to thephases

To show tasks or subtasks

To show the subtasks for a task click the plus icon next to the task

To show the tasks for a phase click the plus icon next to the phase

See Also

Change the Appearance of the Task List

-o-

45

copy Experience In Software Inc 1995 - 2006

Move Tasks within the Task List

In the Tasks step you can reorganize the tasks in your project so that they better represent the work youand your team plan to do In particular you should review the order of the tasks in each phase and move tasks up and down so thattasks follow in a sequential order Use the Up and Down Arrow buttons to move the tasks

To reorder tasks1 Click a task or phase to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youmove must be next to each other

2 Click the Up Arrow button to move a task up one rowOrClick the Down Arrow button to move a task down one row

Note

When you move a bolded phase you move the phase and all of its tasks at the same time

See Also

Outdent and Indent Tasks

-o-

46

copy Experience In Software Inc 1995 - 2006

Outdent and Indent Tasks

Subtasks are smaller parts of tasks Use subtasks when you need to break tasks down into moremanageable parts In the Task List you can turn a task into a subtask by indenting it You can also add anew subtask to the Task ListIf your Task List contains subtasks you can turn a subtask into a task by outdenting itUse the Outdent and Indent buttons to promote (outdent) and demote (indent) tasks

To promote and demote tasks1 Click a phase task or subtask to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youpromote or demote must be next to each other

2 Click the Outdent button to promote the selected tasksOrClick the Indent button to demote the selected tasksYou can also right-click an item in the Task List and then click Outdent or Indent on the shortcut menu

Tips

When you promote (outdent) a task it becomes a phase and its subtasks become tasks When youpromote a subtask it becomes a task

When you demote (indent) a phase it becomes a task and its tasks become subtasks When youdemote a task it becomes a subtask

Notes

You can have up to 10 levels of subtasks in your project

Use Task Notes instead of subtasks for task comments or additions that are not actually work items

See Also

Move Tasks with the Task List

Add a Task or Subtask

-o-

47

copy Experience In Software Inc 1995 - 2006

Add a Task or Subtask

If you realize you want to add another task to the Task List use the Add Task button A subtask is a smaller part of a task Use subtasks when you need to break tasks down into moremanageable partsTo add a subtask use the Add Subtask button

To add a task1 Click a task and then click the Add Task button right-click a task and then click Add Task on the

shortcut menu or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskProject KickStart numbers the new task in the proper sequence

To add a subtask1 Click a task and then click the Add Subtask button right-click a task and then click Add Task on the

shortcut menu or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtask3 Project KickStart numbers the new subtask in the proper sequenceNote

To add a new phase click a phase and then click the Add Task button

See Also

Outdent and Indent Tasks

-o-

48

copy Experience In Software Inc 1995 - 2006

Edit Tasks

Edit tasks in the Task List to fine tune your project You can edit the names of the phases tasks andsubtasks delete tasks and cut copy and paste task information

To edit task names1 Click the phase task or subtask you want to edit and then press the F2 key2 Type to edit the text3 To undo an edit click the Undo button

To delete a task

Click the task you want to delete and then press the Delete key or click the Delete button Or

Right-click a task and then click Delete Row on the shortcut menu

To cut copy and paste tasks1 Select the tasks you want to cut or copy Use Shift-click or Ctrl-click to select more than one task

2 Click the Cut button (Ctrl-X) or click the Copy button (Ctrl-C )

3 Click where you want to insert the tasks and then click the Paste button (Ctrl-V)

Tip

If your project includes some of the same tasks repeated in different phases save time by copying rowsof tasks and pasting them to another phase

Notes

You can also edit task names using the Task Information dialog box To open this dialog boxdouble-click a task or click a task and then click the Edit Task Information button

If you delete a phase you also delete its tasks and subtasks If you delete a task you also delete itssubtasks Project KickStart warns you before deleting tasks or subtasks and gives you a chance tocancel the deletion

See Also

Add Task Notes and Attachments

Add or Change Task Assignments

-o-

49

copy Experience In Software Inc 1995 - 2006

Add Task Notes and Attachments

You might find that some of your tasks are actually more notes than tasks For example Remember tocheck Daves specifications might work better as a note than a task especially if it could take several daysto catch up with Dave but only a few minutes to review his specs By using notes you clarify your projectand increase your chances for success An attachment is a document graphic or any other type of file related to a task For example to a tasksuch as Review proposal you can attach the proposal document Or you can attach a hyperlink to a pageon a web site

To add a note or attachment to a task1 Double-click the Notes column next to the task The Task Information dialog box opens to the Notes

and Attachments tab2 In the Enter a Note box type in or edit the task note (Press Enter to insert line break)3 To attach a file click the Add Files button In the Select File to Attach dialog box navigate to the file

you want and then click the Open button The filename appears in the Add Attachments box with apaperclip icon

4 To insert a hyperlink click the Add URL button In the Insert Hyperlink dialog box type in the URL youwould like to link to The URL appears in the Add Attachments box with a paperclip icon

5 Click the OK button

To open or remove an attachment1 Open the Notes and Attachments tab in the Task Information dialog box2 To open an attachment double-click the filename in the Add Attachments box3 To delete an attachment click the attachment in the Add Attachments box and then click the Remove

button

To change a task into a task note1 Copy (Ctrl-C) the text of the task you want to change into a note2 Double-click the task to which you want to add the note3 In the Task Information dialog box click the Notes and Attachments tab and add paste the text in the

Enter a Note box Close the Task Information dialog box4 In the Task Name column delete the original task that how appears as a note for a different task

Tips

Use notes to keep track of the operational details of a project the little nagging details that are criticalto success

Although the Task List provides plenty of room for notes it is best to keep your notes concise

Some tasks might benefit from instructional notes those that explain what to do in a task or how tosuccessfully complete a task

You can also include a hyperlink in a note by typing httpxxx (where xxx is an e-mail or Web address)In Outlook Word Excel or your browser the hyperlink will be active You can click the link to godirectly to that site or to send an e-mail to that address

Note

You can also open the Notes and Attachments tab in the Task Information dialog box by clicking atask and then clicking the Edit Notes and Attachments button or by double-clicking a task to openthe Task Information dialog box and then clicking the Notes and Attachments tab

See Also

Edit Tasks

Add or Change Task Assignments

Change Task Details in the Gantt chart

50

copy Experience In Software Inc 1995 - 2006

-o-

51

copy Experience In Software Inc 1995 - 2006

Add or Change Task Assignments

The Assignments column in the Task List shows the people and other resources assigned to each task

To add or change a task assignment1 Double-click the Assignments column next to the task The Task Information dialog box opens to the

Assignments tabThe Assignments tab lists all of the people and resources in your project If this task is already assignedto people they are highlighted on the Assignments tab

2 To assign this task to another person or resource click the resource name in the Assignments list3 To remove (unassign) this task from a person or resource click a highlighted name in the Assignments

list4 To add a person and assign the task at the same time click ltNew Persongt in the Assignments list

and then enter the name of the new person5 Click the OK button

Note You can also open the Task Information dialog box by clicking a task and then clicking the Edit Task

Information button to or by double-clicking a task

-o-

52

copy Experience In Software Inc 1995 - 2006

Add or Change Task Details

Besides task names notes and assignments you can include cost and done details about tasks In theSchedule step you can also include start and finish dates and durations

To add task details

1 Click a task and then click the Edit Task Information button or double-click the task you wantThe Task Information dialog box opens

2 Enter Cost or Done informationCost Enter the cost associated with this task For example you could enter $150 as the cost for a tasknamed Purchase photo CD Done Click the list arrow to select 0 25 50 75 or 100 or enter the percentage you want such as33

3 Click the OK button

To show or hide task details

Right-click a column heading to open a shortcut menu and then click Cost or Done In the shortcutmenu a checkmark appears next to columns that are displayed in the Task List

To edit task details

Open the Task Information dialog box (click a task and then click the Edit Task Information button or double-click the task you want)

Or

Double-click the Cost or the Done entry to update these details directly in the Task List

Notes

The Cost amount appears with the currency symbol set for your system (in the Regional and LanguageOptions dialog box of the Windows Control Panel)

Project KickStart calculates the running totals for the tasks within a phase and displays this total in theCost column for the phase When you create and print Task reports the total costs for the entire projectappear at the end of the Cost column

See Also

Edit Tasks

Print Task Reports

-o-

53

copy Experience In Software Inc 1995 - 2006

Check Spelling

Spell check your tasks and notes before you print reports or export to other software

To check the spelling of tasks and notes

Click the Check Spelling button on the Project KickStart toolbarOr

Click Tools on the menu bar and then click Spelling

Notes

Spell checking updates entries on the Task List and the Gantt chart (the Schedule step) It can alsocheck the spelling of intermediate entries such as goals and tasks to accomplish goals if you spellcheck during those steps

Spell checking does not check the names of people on the People List or the contents of the PeopleLibrary

-o-

54

copy Experience In Software Inc 1995 - 2006

Scheduling Tasks in the Gantt Chart

55

copy Experience In Software Inc 1995 - 2006

Scheduling Overview

About Scheduling Tasks

In the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the other

You work with the Gantt chart using the familiar Task Data view in the left pane or the graphical Chart viewin the right pane To adjust the schedule to fit your project set the project start date in the toolbar moveand resize the taskbars in the Chart view or change the start and finish dates or durations of individualtasks in the Task Data view

Click the following illustration to see general tips for using the Gantt chart See About the Gantt Chart formore details

In the Schedule step you can

Change a start date for the project Set start and finish dates or durations for tasks Change the timescale of the schedule Change the working schedule to specify which days are nonworking days such as weekends and

holidays Fine-tune the organization of the phases tasks and subtasks Color-code tasks to identify assignments critical deadlines or other information at a glance Insert milestones to indicate events that mark a moment in time such as the approval of a design Review and edit task details including task name assignments notes and attachments Hide or show task data columns in the left pane Export project data to other software applications

Tip

56

copy Experience In Software Inc 1995 - 2006

To save time you can reuse projects such as one for a trade show and create an updated scheduleby changing the project start date in the Schedule step

See Also

About the Gantt Chart

Understand Task Data View

Understand Chart View

-o-

57

copy Experience In Software Inc 1995 - 2006

About the Gantt Chart

The Gantt chart provides two views of your project schedule The Task Data view in the left pane lists thesame task information as in the Tasks step but now includes durations and start and finish dates TheChart view in the right pane displays taskbars and symbols to represent the same information You canchange the schedule information by working directly in the Task Data view and Chart view or by using theGantt Chart toolbarClick the following illustration to see general tips for using this window

-o-

58

copy Experience In Software Inc 1995 - 2006

Autolink tasks (Pro Users)

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatProject KickStart Pro does not assume that you want to link all of the tasks in a serial manner (one after theother) when you get to the Gantt chart Indeed many users want that behavior and many do notTo accomodate both types of users you can set whether you want the program to Autolink tasks In theTools menu select Autolink tasks Thereafter in all your projects when you get to the Gantt chart for thefirst time the tasks will be linked in a serial mannor

-o-

59

copy Experience In Software Inc 1995 - 2006

About Linking Tasks

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatWhen you link tasks the Gantt chart shows additional information about the tasks Click the followingillustration to see general tips for using linked tasks

Task Data view Chart view Description

Predecessor tasksA predecessor task is onethat you must completebefore you can start thenext task For exampleTask 2 - Prepare soil isthe predecessor to Task3 - Plant shrubs becauseyou need to prepare thesoil before you can plantthe shrubs

Successor tasksWhen you finish onelinked task you can moveonto the next onemdashthesuccessor task Forexample the successorfor Task 2 ndash Prepare soilis Task 3 ndash Plant shrubsand the successor forTask 3 is Task 4 ndash MulchLink linesThe first task isscheduled for one dayand the second one forthe next day In additionthe link line and arrowshow that the first taskmust end before thesecond one can start

These linked tasks arescheduled for the sametime

60

copy Experience In Software Inc 1995 - 2006

These tasks which aredependent on earliertasks and the last twotasks are also scheduledfor the same time

See Also

About the Gantt Chart

Autolink tasks

Make tasks overlap

-o-

-o-

61

copy Experience In Software Inc 1995 - 2006

Change the Display of the Schedule

You can change the onscreen appearance of the schedule so you can work with it more effectively Thefollowing illustration shows the Schedule window with the Steps bar closed and only the task number taskname and duration displayed in the Task Data view This provides more room to display the Gantt chart

To show or hide the Step bar or Project KickStart toolbar

Click View on the menu bar and then click Steps Bar to show or hide the vertical Steps bar on the leftof the Project KickStart window

Click View on the menu bar and then click Tool Bar to show or hide the Project KickStart toolbarwhich appears just below the menu bar In the View menu a checkmark appears next to the items displayed in the Project KickStart window

To display more or less of the Task Data view or Chart view

Drag the splitter bar between the Task Data view and the Chart view

To change the timescale in the chart

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years

To add a column to the Task Data view

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task Data viewBy default the Task Data view shows the Info Task Name Days Start and Finish columns Youcan also show Done Cost and Assignments columns

To hide a column in the Task Data view

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

62

copy Experience In Software Inc 1995 - 2006

To change the column width in the Task Data view

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Understand Task Data View

Understand Chart View

-o-

63

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

-o-

64

copy Experience In Software Inc 1995 - 2006

65

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Some features in this topic are available only in Project KickStart Professional

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view In Project KickStart Professional you also use the Gantt chart toolbar to linkand unlink tasks

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysLink Tasks (Pro Users)Link the selected tasksUnlink Tasks (Pro Users)Unlink the selected tasksChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

See Also

Use the Gantt Chart Toolbar

-o-

66

copy Experience In Software Inc 1995 - 2006

Understand Task Data View

The following illustration shows all the columns of information you can display in Task Data view

The Task data columns are the same as in the Tasks step but also include date information

Row number

Info Shows an icon if a note attachment or both are associated with the task Double-click anicon to view or edit the associated information

Task Name Name of the phases tasks and subtasks Double-click a task name to edit it directly

Days The amount of time it takes to complete the task If you change the number of days for a taskProject KickStart changes the Finish date accordingly

Start Date this task starts Double-click a Start date and then click the list arrow to open a calendar andselect a different date This also changes the Finish date

Finish Date this task ends Double-click a Finish date and then click the list arrow to open a calendar andselect a different date This changes the task duration shown in the Days column

Done Percentage of the phase task or subtask completed Show progress for any task by entering apercent of up to 100

$ Cost Cost for each task summed in the appropriate phase row Reports include total costs for theproject when you select the Cost column in the Create and Print Task Reports dialog box or the Createand Print Gantt Chart Report dialog box The Cost appears with the currency symbol set for your system(in the Regional and Language Options dialog box of the Windows Control Panel)

Assignments People and other resources assigned to the task Double-click an assignment to open theTask Information dialog box to the Assignments tab where you can add and change assignments

Tip

A task with a duration of zero (0) days is a milestone See Create a Milestone for more information

Notes

By default Task Data view displays all the columns the Info Task Name Days Start and Finish Done Cost and Assignments columns Some of these columns might be hidden by the Gantt chartview To hide columns right-click a column heading to open a shortcut menu and then click the columnyou want to hide In the shortcut menu no checkmark appears next to columns that are hidden

To change the width of a column drag a splitter bar in the column heading row or double-click a splitterbar to have the column accommodate its longest entry

As in the Tasks step expand phases and tasks by clicking the plus icon and collapse phases andtasks by clicking the minus icon

See Also

67

copy Experience In Software Inc 1995 - 2006

Understand Chart View

Change Task Dates

-o-

68

copy Experience In Software Inc 1995 - 2006

Additional Features in Task Data View

These features are available only in Project KickStart Professional

In Project KickStart Pro you can view two columns of information in addition to the nine columns availablein the Project KickStart Standard These two additional columns are labeled Pred (for Predecessor) andSucc (for Successor) The following illustration shows a typical Task Data view with these additionalcolumns

Besides the nine columns of information shown in Task Data view in Project KickStart Standard you canalso show the following information in the Professional version

Pred Indicates which task is the predecessor to the current task Double-click a task number in the Predcolumn to change it

Succ Indicates which task is the successor to the current task Double-click a task number in the Succcolumn to change it

Notes

When you link tasks Project KickStart assigns predecessors and successors according to their order inthe Task Data view

When you move a linked task in the Task Data view the predecessor and successor do not changeFor example in the above illustration if you move Task 3 ndash Plan design so it becomes Task 2 itspredecessor remains Land survey and its successor remains Engineering You can change these bydouble-clicking the task number in the Pred or Succ column and then entering a new number

See Also

Understand Task Data View

-o-

69

copy Experience In Software Inc 1995 - 2006

Understand Chart View

The following illustration shows a daily schedule in Chart view Point to the illustration to display text thatdefines the chart elements

Summary bar Summarizes the tasks below it and extends from the earliest start date(where the first triangle in the summary bar appears) to the latest finish date (where the last triangleappears) If a phase has tasks the summary bar appears in the phase row to summarize the tasks If atask has subtasks the summary bar appears in the task row to summarize the subtasks

To reschedule a phase and all of its tasks (or a task and all of its subtasks) click the summary bar and dragit to the left or right until it spans your desired set of dates This changes the earliest start date and latestfinish date in that phase and keeps the same duration And all the tasks move with the change of thephase

Taskbar Shows the length and scheduled dates for a task To change the duration of a taskresize the taskbar click the taskbar and then drag its left edge to schedule a different start date or drag itsright edge to schedule a different finish date

To reschedule a task without changing the duration drag the taskbar to a different date in the chart

Taskbar with percent done If you enter a Done amount in the Task Data view a progress barin the taskbar indicates the amount of the task completed

Red vertical line Indicates todays date

Milestone Indicates a task with a zero duration Milestones mark an event that must be reflected inyour project plan such as the approval of a design or an assembly line startup You can drag the left edgeof a milestone icon to stretch it into a taskbar The milestone becomes a task with a start and finish date

Notes

Because a summary bar summarizes the tasks below it you cannot resize a summary bar

To scroll the schedule use the vertical and horizontal scroll bars or the green drag bar at the top of theChart view

The shaded days in the Chart view indicate nonworking days To set which days are working andnonworking see Specify Working Days

70

copy Experience In Software Inc 1995 - 2006

-o-

71

copy Experience In Software Inc 1995 - 2006

Additional Tools in Chart View

These features are available only in Project KickStart Professional

If you use Project KickStart Pro the Chart view displays lines and arrows to show linked tasks The linklines and arrows show the relationships dependencies between one linked task and another

Besides the summary bar taskbar and other information provided in Project KickStart Standard Chart viewin the Professional version also provides the following information

The first task is scheduled for one day and the second one for the next day In addition the link line andarrow show that the first task must end before the second one can start

These linked tasks are scheduled for the same time However the first task must end before the secondone can start

The first two tasks are scheduled for the same time and must be completed before the third task can start

These linked tasks are scheduled for the same time However the second task must end before the firstone can start

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

Understand Chart View

-o-

72

copy Experience In Software Inc 1995 - 2006

73

copy Experience In Software Inc 1995 - 2006

Change Task Dates

You can revise a project schedule by changing task dates in the Task Data view or the Chart view You canalso reschedule an entire project by changing the projects start date

To change the project start date1 Click the Project Start list arrow to open a calendar

The calendar highlights the selected date and outlines todays date2 Find the date you want using the left and right scroll arrows to view a different month and then click the

date

To change task dates in Task Data view1 Double-click the Start or Finish date for a task

2 Then edit the date (you can edit the day month or year) OrClick the list arrow to open a calendarThe calendar highlights the selected date and outlines todays date

3 Find the date you want using the left and right scroll arrows to view a different month and then click thedateProject KickStart changes the Start and Finish dates according to your selection updates the durationof the task in the Days column and adjusts the taskbar in the Chart view

To change task dates by changing the duration in Task Data view

Double-click the Days column for a task and then enter the number of days it will take to complete thetaskProject KickStart changes the Finish date of the task and adjusts the taskbar in the Chart view

To change task dates in Chart view

Resize a taskbar click the taskbar and then drag its left edge to schedule a different start date or dragits right edge to schedule a different finish dateProject KickStart updates the summary bar in Chart view and the task dates and duration in the TaskData view

To reschedule a task without changing the duration drag the taskbar to a different date You can alsodrag a summary bar to reschedule a phase and all of its tasks (or a task and all of its subtasks) so itspans a different set of datesProject KickStart updates the task dates and duration as necessary in the Task Data view

To change task dates in the Task Information dialog box1 Open the Task Information dialog box (Right-click a task and then click Task Information or click a

task and then click the Edit Task Information button )2 Click the General tab3 In the Dates section change the following information as necessary

Start Click the Start list arrow to open a calendar and then click the appropriate start dateFinish Click the Finish list arrow to open a calendar and then click the appropriate finish dateDays Enter a number or click the spin arrows to set the task durationMilestone Select the Milestone check box if you want this task to be a milestone (A milestone is atask with a zero duration and marks an event such as the approval of a design)

Notes

You cannot delete the Start or Finish date of a task If you want to specify that a task has no durationconvert it to a milestone

When working with a calendar to schedule a start or finish date click the Today date text (where date

74

copy Experience In Software Inc 1995 - 2006

is todays date) to select todays date

See Also

Understand Task Data View

Understand Chart View

Create a Milestone

-o-

75

copy Experience In Software Inc 1995 - 2006

Phase Dates Cannot Be Edited

You cannot change the bold phase dates in the Task Data view of the Gantt chart They are a summary ofthe task dates for a particular phase and are view only You can revise phase dates by changing task dateswithin the phase

To change phase dates in Chart view

You cannot directly resize a summary bar You can extend or move the blue task barswithin a phase on the chart and Project KickStart updates the summary bar

To reschedule a phase on the chart drag the summary bar to a new date and all of its tasks (or a taskand all of its subtasks) will move with it

-o-

76

copy Experience In Software Inc 1995 - 2006

Quick Tour of Working with Linked Tasks

This feature is available only in Project KickStart ProfessionalIn the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the otherIn addition Project KickStart Pro links the tasks for you so when you open the Gantt chart you see a linkedwaterfall similar to the one shown below Besides providing a schedule that starts in a cascade with eachtask lasting one day each task is linked to the next task

You work with the Gantt chart either using the Task Data view in the left pane or the graphical Chart view inthe right pane To adjust the schedule to fit your project set the project start date in the toolbar move andresize the taskbars in the Chart view or change the start and finish dates or durations of individual tasks inthe Task Data view See About Scheduling Tasks for detailsNext fine-tune the dependencies in your project by you can linking and unlinking tasks changing theirpredecessors and successors and setting lead times For example if one task is not dependent onanother you can unlink the tasks If another task canrsquot start until two other tasks are finished you can add apredecessor to that task in which case the two tasks will be linked

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

To fine-tune the linked tasks To change the scheduled start and end dates of linked tasks move and resize taskbars in the Chart

view or change the number of days or the Start date in the Task Data view To display predecessor and successor information in the Task Data view right-click any column

heading and then click Pred or Succ To change the predecessor for a task double-click the number in the Pred column for the task and

then enter the number of a different task To change the successor for a task double-click the number in the Succ column for the task and then

77

copy Experience In Software Inc 1995 - 2006

enter the number of a different task To add another predecessor or successor to a task click in the appropriate column for the task and

then enter the number of another task To change the details of a linked task open its Task Information dialog box To do so right-click the

task and then click Task Information on the shortcut menu or click a task and then click the Edit TaskInformation button See Change Details for Linked Tasks

In the Task Information dialog you can also specify the predecessor(s) of a task and lead time(s) of thetasks

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

About Scheduling Tasks

About Linking Tasks (Pro Users)

Use the Gantt Chart Toolbar (Pro Users)

Manage Changes in Your Schedule (Pro Users)

-o-

-o-

78

copy Experience In Software Inc 1995 - 2006

Link and Unlink Tasks

These features are available only in Project KickStart Professional

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

See Also

About Linking Tasks

Quick Tour of Working with Linked Tasks

-o-

79

copy Experience In Software Inc 1995 - 2006

Create a Milestone

A milestone Indicates a task with a zero duration Milestones mark an event that must be reflected in yourproject plan such as the approval of a design or an assembly line startup

To create a milestone in the Task Data view

Double-click the Days number for a task and then enter 0 (zero)Or

Open the Task Information dialog box click the General tab and then click to insert a checkmark inthe Milestone check box

In the Chart view Project KickStart changes the taskbar to a milestone icon To create a milestone in Chart view

Click a taskbar and then drag to shrink the taskbar to a milestone icon In the Task Data view Project KickStart changes the Days for this task to 0 (zero)

Notes

To change a milestone into a task you change its duration or start and finish dates See Change TaskDates for instructions

To move a milestone in Chart view click the milestone icon on the upper left corner of the milestoneicon With the left mouse down move the icon to another date and release the mouse

To move a milestone in the Task Data view change the start date or the finish date and the milestonewill move

-o-

80

copy Experience In Software Inc 1995 - 2006

Change Task Details

You can use the Task Information dialog box to change the following task details in Task Data view

Task properties including the task name cost for completing the task and the percent completed

Dates including the start and finish dates duration and whether to convert the task to a milestone

Assignments

Notes and attachmentsYou can also edit the task name days dates costs and Done directly by clicking items in the task datacolumns

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button 2 Click the appropriate tab and then change the task details

General tab Change the task name and enter or change the cost associated with the task To changethe amount of the task completed click the Done list arrow and then select a value or type a value inthe Done text box Enter or change date information as described in Change Task Dates Assignments tab People assigned to this task are highlighted in the list To assign this task to anotherperson or resource click the name in the Assignments list To remove (unassign) this task from aperson or resource click a highlighted name in the Assignments list See Add or Change TaskAssignments for more detailsNotes and Attachments tab Type or edit a task note (Press Enter for a line break) To add anattachment click the Add button In the Select File to Attach dialog box navigate to the file you wantand then click the Open button The filename appears with a paper clip icon See Add Task Notes andAttachments for more details

To change task details directly in Task Data view

To modify the task name press F2 or double-click a task and then edit or replace the text

To change date information see Change Task Dates

To change the amount of the task completed double-click in the Done column and then enter a newvalue

To change the cost associated with the task double-click in the Cost column and then enter a newvalue

Notes

When you enter costs for tasks the total appears in the phase row for those tasks Reports include thetotal costs of all tasks in the project when you select the Cost column in the Create and Print TaskReports dialog box or the Create and Print Gantt Chart Report dialog box

You cannot change the cost of a phase because it represents the total costs for the tasks in that phaseInstead change the costs associated with the tasks in the phase

When you enter a Done for a task the corresponding taskbar in the Chart view includes a blackprogress bar

-o-

81

copy Experience In Software Inc 1995 - 2006

Change Details for Linked Tasks

This feature is available only in Project KickStart ProfessionalIf you are using Project KickStart Pro you can use the Task Information dialog box to change the followingtask details

Predecessor for a linked task

Lead time for a linked task

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button

2 Click the Predecessors tab and then change the task details about predecessors and lead timePredecessors tab The Task Properties section shows the name of the selected task which you canchange The Predecessor (Finish-to-Start) section shows the tasks that are predecessors to theselected task A predecessor task must be finished before you start the current task You can change the ID name or lead time of the predecessor task Also you can also add additionalother predecessorsThe lead time is the amount of time you need to wait after finishing the predecessor task before so youcan start the current task Lead time can be positive or negative

Note

In some programs the is time shift is called ldquolag timerdquo But we think that the term ldquolead timerdquo is moreaccurate and descriptive since itrsquos the amount of time you want to allow before you start a task

See Also

Change Task Details

82

copy Experience In Software Inc 1995 - 2006

-o-

-o-

83

copy Experience In Software Inc 1995 - 2006

Reorganize Tasks in Task Data View

Although your project should be fairly well organized by the time you start the Schedule step you canfine-tune the organization in the Task Data view using the same techniques you use in the Tasks stepTo reorder tasks

Right-click a task and then click Move Task Up or Move Task Down on the shortcut menu Or

Click a task or phase to select it and then click the Up Arrow button or the Down Arrow button on theGantt chart toolbar

To promote and demote tasks

Right-click a task and then click Outdent or Indent on the shortcut menu Or

Click a phase task or subtask to select it and then click the Outdent button or the Indent button onthe Gantt chart toolbar

To add a task1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Task button on the Gantt chart toolbar or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskTo add a subtask1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Subtask button on the Gantt chart toolbar or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtaskTo delete a task

Right-click a task and then click Delete Row on the shortcut menuOr

Click the task you want to delete and then click the Delete button

To delete a row click the Task row number and press the Delete button

See Also

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

-o-

84

copy Experience In Software Inc 1995 - 2006

Change the Timescale of the Schedule

You can display the Gantt chart schedule in the Chart view using days weeks months quarters or yearsas the timescale Changing from days to weeks for example displays a longer period of time but lessdetail

Days timescale Weeks timescale

To change the timescale in the Chart view

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years Youcan also change the timescale by clicking Timescale on the menu bar and then clicking the option youwant

Notes

When you print a Gantt chart your current timescale is used by default However you can change it inthe Print Options dialog For example even though you were viewing your Gantt chart by weeks youcan choose to print the Gantt chart by months

If your mouse comes with a wheel you can adjust Project KickStarts timescale by rolling the wheelforward or backward The Timescale list box must be selected first

-o-

85

copy Experience In Software Inc 1995 - 2006

Specify Working Days

You can select which days are working days and which days are nonworking days for scheduling purposesBy default Monday - Friday are working days and Saturday and Sunday are nonworking days You can addto and change these settings to specify holidays for example

To set working and nonworking days

1 Click the Change Working Schedule button on the Gantt chart toolbar The Change Working Schedule for this Project dialog box opens Nonworking days are shaded in grayWorking days are unshaded

2 To change a single date (from working to nonworking or from nonworking to working) click the date3 To change one day of the week for the entire project such as all Fridays double-click any Friday4 To display schedules for other months click the left and right arrows5 Click OK

Note

Project KickStart maintains separate calendars for each project

If you typically work weekends create a simple template with weekends displayed as Working daysSave as your starter template Use the starter template when you start a new project and then save theproject with a different name Weekends will be displayed as Working days in your projects

-o-

86

copy Experience In Software Inc 1995 - 2006

Change the Color of Taskbars

You can change the color of the taskbars in the Chart view to call attention to particular tasks For exampleyou can change the colors of all tasks in a particular phase resource or deadline to make them stand outin a report

To change the color of a taskbar1 Right-click a taskbar and then click Color on the shortcut menu or click a taskbar and then click the

Color button on the Gantt chart toolbar The Color dialog box opens

2 Click the color you want to assign to the taskbarTips

Avoid changing the taskbar color to black because it obscures the Done progress bar (The Doneprogress bar is a black bar displayed within a taskbar)

Also avoid changing the taskbar color to white because it will not appear in the white rows of the Chartview

-o-

87

copy Experience In Software Inc 1995 - 2006

Make Tasks Overlap

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro the schedule starts in a cascade with each task lasting one day and each tasklinked to the following taskHowever it is very unlikely that your entire schedule matches such a cascade so you can adjust theschedule Start by estimating the duration of tasksmdashthe number of days that each task will take Generallyit is best to estimate how many days will elapse before the task is done You might also want some tasks to occur at the same time To do so you can overlap the tasks To make tasks overlap like this

You can do this in three ways Set the same predecessor for both tasks

Or Set the second task as the successor of the first task and then then move the second task into a

position when it starts on the same day as the first taskOr

Set the second task as the successor of the first task and then assign a lead time of ndash3 days (the number of days scheduled for the task)

To make tasks overlap like this

Set the second task as the predecessor of the first task and then assign a lead time of ndash2 days(one less than the number of days scheduled for the task)

-o-

88

copy Experience In Software Inc 1995 - 2006

Manage Changes in Your Schedule

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro when you schedule with dependencies you can adapt to changes on the fly andcreate what-if scenarios to forecast how one change affects the overall project schedule A commonscenario is dealing with delays You can reschedule an entire project or only selected tasks When you doProject KickStart Pro updates the schedule for you

To delay an entire project Click in the Project Start text box and then edit the date to match your new start date (You can edit

the day month or year)Or

1 Click the Project Start list arrow to display the calendar The calendar highlights the selected date andoutlines todays date

2 Find the date you want using the left and right scroll arrows to view a different month and then click thedate Project KickStart changes the Start and Finish dates for all tasks according to your selection

To delay a task In Task Data view double-click the Days column for the task and then edit the number of days it will

take to complete the taskProject KickStart changes the Finish date of the task adjusts the taskbar in the Chart view andchanges the Start and Finish dates for all tasks linked to this taskOr

In Chart view resize a taskbar by clicking the taskbar and then dragging its left edge to schedule adifferent start date or dragging its right edge to schedule a different finish date Project KickStart updates the summary bar in Chart view the task dates and duration in the Task Dataview and reschedules all tasks linked to this task

To reschedule a task without changing the duration in Chart view drag the taskbar to a different date Project KickStart updates the task dates and duration as necessary in the Task Data view andreschedules all tasks linked to this task

Note

Project KickStart Pro does not include a critical path

-o-

89

copy Experience In Software Inc 1995 - 2006

Managing Libraries

Use a Library

Project KickStart has five libraries that contain lists of useful phases tasks goals people and obstaclesAll libraries expect the People Library contain sample entries that you can use in your projects Yougenerally build your own People Library from the resources that are available to you

To use a library1 In the Phases Tasks Goals People or Obstacles step of the Planning Wizard click the Library button

to open the appropriate library2 Select one or more items in a library and then drag them to your list3 Close the Library window

Tips

Feel free to add (or delete) items to the libraries to make them richer and more pertinent to yourprojects

Keeping libraries small makes them easier to use

Widen the library window to see the full text of long entries

Note

After adding a library entry to a list you can double-click the entry to edit it

See Also

Manage a Library

-o-

90

copy Experience In Software Inc 1995 - 2006

Manage a Library

Customize the libraries by adding and changing entries and reorganizing them so you can use the librariesefficiently The Phases Tasks Goals People and Obstacles Libraries include a single column ofinformation while the People Library provides additional columns (See Manage the People Library)

To edit a library1 Open the library by clicking the appropriate Library button2 To edit an entry double-click it

3 To add an entry to the library press Insert or click the Add a row button You can also select oneor more items in the list and then drag them to the library

4 To delete an entry select the entry and then press Delete or click the Delete a row button 5 To move an item up or down select the item and then click the Up Arrow or the Down Arrow button

6 Click the OK button to save your changes and close the Library windowTips

Widen the Library window to add a long entry

Libraries can serve as ldquoKnowledge Librariesrdquo By including typical company-specific terms in yourLibraries you create a quick reference for yourself and colleagues now and in the future To do so adda new line in the Library enter the name of your company (or department) as a heading in capitalletters and then list your personal terms under the heading

If you use Project KickStart on more than one computer such as at home and work you can transportchanges you make in your Libraries from one computer to another The data in all the Libraries isstored in one file pks5libxdat so you can copy that file on one computer and paste it into the ProjectKickStart 5 folder on the other computer

Keeping Libraries small makes them easier to use Project KickStarts Libraries are fairly rich out of thebox If some of the terms don rsquot apply to your type projects delete them

See Also

Manage the People Library

-o-

91

copy Experience In Software Inc 1995 - 2006

Manage the People Library

The People Library is like the other libraries but with a few important extra features

You can store contact data such as Company Email Phone and Job Title

You can import names from ACT or from Outlook if you use either of those programsTo use the People Library1 In the People step of the Planning Wizard click the People Library button2 Select one or more names in the People Library and then drag them to your list (This adds only the

names of people not their contact data) If the People Library contains company names but not contactnames you can drag the company name to your list

3 Close the Library windowTo organize the People Library

To show or hide a column right-click a column heading to open a shortcut menu and then click acolumn name In the shortcut menu a checkmark appears next to columns that are displayed in thePeople Library

To sort the people in the People Library click a column heading For example click the Name columnheading to sort the people alphabetically by name To reverse the sort click the column heading again

To move a person up or down select the person and then click the Up Arrow or the Down Arrowbutton

Click the OK button to save your changes and close the People LibraryTo edit the People Library

To edit a persons name and contact data double-click the entry

To add a person to the People Library click the first blank row press Insert or click the Add a rowbutton Then type to enter the persons name and contact information You can also select one ormore items in the list and then drag them to the People Library

To delete an entry select the entry and then press Delete or click the Delete a row button

Click the OK button to save your changes and close the People LibraryTips

Use the People Library to store names for people teams (such as Quality control team) departments(such as Manufacturing) companies (such as Acme Widgets Corp) or even equipment (such as wheatthrasher)

Widen the People Library window to add a long entry

Resize the columns by dragging or double-clicking a splitter barNotes

After adding a person or resource to your list you can double-click the name to edit it

You can import contact information stored in an Outlook or ACT (version 6 7 or later) address book toyour People Library

See Also

Import ACT Contacts and Users to the People Library

Import Outlook Contacts to the People Library

-o-

92

copy Experience In Software Inc 1995 - 2006

Import ACT Contacts and Users to the People Library

If you use ACT 7 or later (200520062007) or if you use ACT 6 you can import contacts and users to thePeople Library This speeds up your work by letting you use ACT information in your Project KickStartplans If you export a plan to ACT 7 or later it recognizes the people and other resources you entered inProject KickStart

To import ACT contacts and users1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click ACT 7 or later or ACT 6 Click the Import button3 Click the Select ACT Database button and select the ACT 7 or later database (pad) containing the

people information you want to import The ACT 7 and later databases are usually stored in MyDocumentsACTACT for Win 7Databases (If you use ACT 6 your data is stored in a dbf database) If you select a multi-user ACT database you must enter your user name and password for the ACTdatabase

4 In the Import to People Library dialog box the names of Contacts and Users are listed on the left Clickthe Users tab select one or more users and then click Add to move the user names to the Import listClick the Contacts tab to select contact names the same way Click the Add All button to select allusers or contacts for import Note You can sort the contacts alphabetically by name or by company name by clicking theappropriate column heading

5 Click the Import button to add the names and related information from the selected ACT database tothe People Library

Notes

Importing contacts and users to the People Library does not remove them from the ACT database

If you try to import the same ACT contact or user twice it appears only once in the People Library

-o-

93

copy Experience In Software Inc 1995 - 2006

94

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts to the People Library

If you use Microsoft Outlook to maintain your contacts you can import selected contacts to the PeopleLibrary ThisThis speeds up your work by letting you use Outlook information in your Project KickStartplans If you export a plan to Outlook it recognizes the people and other resources you entered in ProjectKickStart

To import Outlook contacts1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click Outlook Click the Import buttonA dialog box opens informing you that Project KickStart is trying to access your Outlook data

3 Allow access for 1 minute and then click the Yes button4 If Outlook asks you to choose your profile please do so5 The Import to People Library dialog box opens listing Outlook Contacts on the left Select one or more

contacts and then click Add to move the contact names to the Import list Click the Add All button toselect all contacts for import

6 Click the Import button to add the contact names to the People Library

Notes

Importing contacts and users to the People Library does not remove them from Outlook If you try to import the same Outlook contact twice it appears only once in the People Library

95

copy Experience In Software Inc 1995 - 2006

You can import Contacts from the Outlook Business Contact Manager

See Also

Import Outlook Contacts via CSV to the People Library (Pro Users)

-o-

96

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts via CSV to the People Library (ProUsers)

This feature is available only in Project KickStart Professional

If you use Microsoft Outlook to maintain your contacts and many of the people on your project are not inyour personal contacts folder in Outlook you can use our new utility to import these Outlook contacts viaCSV to the People Library

To export Outlook contacts to a CSV file1 In Outlook - Click File Import and Export Export to A File and click Next2 Select Comma Separated Values (Windows) and click Next3 Select the Contacts folder to export and click Next4 Save Exported File As with the default being your My Documents folder5 Click Next

To import Outlook contacts to the People Library

1 Be sure that you exit Project KickStart before running the Import Utility

2 Run ImportCSVToPKSexe which is located in the Project KickStart application folder

3 Browse or type the Contacts CSV file (the path is My DocumentsProject KickStart Projects folder bydefault)

4 Browse or type the pks5libxdat file (default is the Project KickStart application folder)

5 Click on Import

Note

Importing contacts and users to the People Library does not remove them from Outlook

-o-

97

copy Experience In Software Inc 1995 - 2006

Printing Reports

98

copy Experience In Software Inc 1995 - 2006

Printing Dashboards

Print Reports

You can print reports from anywhere in Project KickStart through a new Reports Step

You will see Reports divided into three areas

Dashboard

Task Reports

Gantt Chart Reports

-o-

99

copy Experience In Software Inc 1995 - 2006

Print Dashboard Reports

You can print dashboard reports from anywhere in Project KickStart though it makes the most sense toprint them after you have developed your tasks and arranged them in a sensible order

To print a dashboard report

1 Click File on the menu bar and then click Print Reports and then click Dashboard Reports or clickthe Print Reports button

2 In the left column select one of these dashboard reports Whats Due Today Whats Due NextWeek Whats Due Next Month

3 Change the page setup as necessary or Save As a file (See Page Setup and Save As)

4 Click the Print button

Tip

You can see the number of tasks in each dashboard report from the dashboard menu

-o-

100

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Dashboard Reports

Printer Setup

-o-

101

copy Experience In Software Inc 1995 - 2006

Save as HTML or RTF

You can dashboard reports to a Hypertext Markup Language (HTML) format for viewing with an Internetbrowser such as Microsoft Internet Explorer or Mozilla FireFox or to an RTF format for viewing in MicrosoftWord

To save a dashboard report as an HTML file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save button

To save a report as an RTF file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

102

copy Experience In Software Inc 1995 - 2006

Printing Task Reports

Print Task Reports

You can print task reports from anywhere in Project KickStart though it makes the most sense to print themafter you have developed your tasks and arranged them in a sensible orderBefore you print task reports you might want to widen the Task Name column in the Task List to make sureyou print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a task report

1 Click File on the menu bar and then click Print Task Reports In the Tasks step you can click thePrint Reports button instead

The Create and Print Task Reports dialog box opens

2 Click the list arrow and then click Task Report Individual Assignments or Phases Goals People ampObstacles

3 Select the information you want to include in the report as described below

4 Preview the report and change the page setup as necessary (See Print Preview and Page Setup)

5 Click the Print button

Task Report

The Task report covers the entire project and includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

103

copy Experience In Software Inc 1995 - 2006

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to display in the report

By default the report prints all tasks Click the Incomplete Tasks or Completed Tasks option button tofocus on one type of task

4 Click the Preview button (See Print Preview for details)

Individual Assignments

The Individual Assignments report covers the entire project and lists the tasks assigned to each resourceThe report includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to include in the report

Click the All Tasks Incomplete Tasks or Completed Tasks option button

4 Choose which people to include The report lists tasks assigned to the people you select

Click to insert or remove a checkmark from the box for each person

5 Click the Preview button (See Print Preview for details)

Phases Goals People amp Obstacles

This report includes the phases goals people and obstacles in your project You can include some or all ofthese items in the report

104

copy Experience In Software Inc 1995 - 2006

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Click the Preview button (See Print Preview for details)

Tip

If you have many long notes for the tasks of your project it may be hard to read them if you select everycolumn in the Task Reports You should consider selecting a report with only columns for Tasks andNotes

See Also

Print Gantt Chart Reports

-o-

105

copy Experience In Software Inc 1995 - 2006

Print Preview

Before printing a report preview its pages so you know how the report will look when printed

To preview a task report1 Click the Preview button on the Create and Print Task Reports dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from 79 to 100 or from 100 to 79Zoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25

viewPrint the report

You can also click the Page Setup button to change margins and other settings or click the Closebutton to close the Print Preview window

2 If the report appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintTask Reports dialog box

Note

Print Preview is for viewing only--you cannot edit the contents of a report

See Also

Print Task Reports

Printer Setup

Page Setup

-o-

106

copy Experience In Software Inc 1995 - 2006

Printer Setup

Before you print a report you can change the following printer settings

Printer name (and other properties) Paper size Number of copies

To change the printer setup1 Click the Printer button on the Project KickStart toolbar or the Print Preview toolbar2 In the Print dialog box change the printer settings

See Also

Print Task Reports

Print Preview

Page Setup

-o-

107

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Task Reports

Print Preview

Printer Setup

-o-

108

copy Experience In Software Inc 1995 - 2006

Email Task Reports

After creating and previewing a task report you can distribute it to others via email

To email a task report1 In the Create and Print Task Reports dialog box select a report and then click the Email Report

button Project KickStart creates the report opens a new message in your email software and attaches thereport as an HTML file to the message

2 Insert one or more email addresses include the message text and then send the message the way youusually do

Tip

To send a task report to each person in your project with the appropriate assignments select theIndividual assignments report select one person to receive the report and then click the Email Reportbutton Enter the email address of the recipient and send the message Do this for each person in yourproject

-o-

109

copy Experience In Software Inc 1995 - 2006

Save as HTML

You can export tasks assignments days and notes to a Hypertext Markup Language (HTML) format forviewing with an Internet browser such as Microsoft Internet Explorer or Mozilla FireFox

To save a report as an HTML file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

110

copy Experience In Software Inc 1995 - 2006

Save as RTF

You can export tasks assignments durations and notes to a Rich Text Format (RTF) for editing inMicrosoft Word

To save a report as an RTF file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can open an RTF file in a word processor such as Microsoft Word

To send an RTF document to each person in your project with the appropriate assignments select theIndividual Assignments report select one person to receive the report and then save the report asRTF Do this for each person in your project

See Also

Save as HTML

-o-

111

copy Experience In Software Inc 1995 - 2006

Printing Gantt Chart Reports

Print a Gantt Chart

Once you create your schedule you can print a Gantt chart from anywhere in Project KickStart

Before you print a Gantt chart you might want to widen the Task Name column in the Task pane to makesure you print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a Gantt chart1 Click File on the menu bar and then click Reports and then select Gantt Chart Reports In the

Schedule step you can click the Print Reports button insteadThe Create and Print Gantt Chart Report dialog box opens

2 Click the Format list arrow and then click Wall chart Fit to smallest size or Repeat tasks on everypage (for handouts)

3 Select the information you want to include in the report as described below4 Preview the report and change the page setup as necessary (See Print Preview a Gantt Chart and

Page Setup)5 Click the Print button

Wall Chart The wall chart prints the Gantt chart information spread across many pages which you can tape together tocreate a wall chart On the left side of the report the wall chart includes the task data columns you selectThe right side of the report includes the graphical view shown in the Gantt chart pane on the right

1 Select the task data columns you want to display for the task information on the left side of the wallchartClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the wall chart

112

copy Experience In Software Inc 1995 - 2006

By default the wall chart prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the wall chartBy default the wall chart prints the timescale you were using in the Gantt chart Click the SetTimescale list arrow to change the timescale to Weeks Months Quarters or Years

4 Select the orientation for the wall chartClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Fit to Smallest Size When you select the Fit to smallest size format Project KickStart reduces the size of the entire Gantt chartincluding the information in the Task pane on the left and the graphical view shown in the Gantt chart paneon the right so it fits as well as possible in the smallest number of pages

1 Select the data columns you want to display for the task information on the left side of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 The timescale for the Gantt chart view on the right side of the report is determined by the length of yourproject and may not be changed

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 The number of pages of the report is shown here (The Fit to smallest scale report will print up to 78rows of tasks per page)

6 Click the Preview button (See Print Preview a Gantt Chart for details)

Standard (for Handouts) This report lists the data columns you specify on the left side of the first page and can repeat the tasknumber task name or assignments on every interior page of the report which is especially useful for

113

copy Experience In Software Inc 1995 - 2006

handouts

1 Select the data columns you want to print on the left side of the first page and the data columns youwant to print on every page of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the reportBy default the report prints a daily view of the tasks Click the Set Timescale list arrow to change thetimescale to Weeks Months Quarters or Years

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Tips

Print Preview shows how many pages the Gantt chart will take to print If there are too many pagesconsider changing the timescale or the date range You can also choose to show fewer columns of taskdata

If possible use paper that is larger than 85 x 11 inches You can select the paper size in Print Previewusing the Page Setup dialog box

If you change the timescale from Days to Weeks or Months this can make tasks with short durations (1to 5 days) difficult to see

If you have trouble printing the Gantt chart report try changing the dpi from 600 to 300 (draft mode) Ifyou continue to have problems contact your printer manufacturer and see if it supports PCL (PrinterCommand Language) technology which is included in most printers today

If you have trouble printing the Gantt chart report on a PDF printer you can try to scale the printing tographics setting to 50

114

copy Experience In Software Inc 1995 - 2006

See Also

Save Gantt Chart Images

Print Task Reports

Printer Setup

Page Setup

-o-

115

copy Experience In Software Inc 1995 - 2006

Print Preview a Gantt Chart

Before printing a Gantt chart preview its pages so you know how the report will look when printed

To preview a Gantt chart1 Click the Preview button on the Create and Print Gantt Chart Report dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from the current zoom percentage to 100 or from 100 to the current zoom percentageZoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25 viewChange printer settings and then print the reportYou can also click the Page Setup button to set margins select paper size and enter headers andfooters or click the Close button to close the Print Preview window

2 If the Gantt chart appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintGantt Chart Report dialog box

Notes

Print Preview is for viewing only--you cannot edit the contents of a report

If you want to print a wider task column return to the Gantt chart widen the Tasks Name column andthen print

To change print settings such as the printer selection and number of copies click the Print button to open the Print dialog box You can save the Gantt chart in a PDF file by clicking the Print button andthen clicking the PDF printer selection (such as Adobe PDF or PDF-XChange ) You can then distributethe Gantt chart electronically as a PDF file

See Also

Print a Gantt Chart

Page Setup

-o-

116

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a Gantt chart you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print a Gantt Chart

Print Preview a Gantt Chart

-o-

117

copy Experience In Software Inc 1995 - 2006

Printing to an Adobe PDF file

To print a Gantt chart to an Adobe PDF file you may have to make some adjustments to your settings

To preview a Gantt chart1 Select Adobe PDF as the name of the printer2 Click Properties button3 Click the PaperQuality tab4 Click Advanced button5 In the Graphic Section lower the setting on Print Quality6 Also in the Graphic Section change the Scaling from 100 to 50

-o-

118

copy Experience In Software Inc 1995 - 2006

Save Gantt Chart Images

You can save a Gantt chart as a series of graphic files in the Meta File (emf) format which you can theninsert in a file such as a Microsoft Word document or PowerPoint presentation The number of graphic filescreated depends on the report type and options you choose in the Create and Print Gantt Chart Reportdialog box By default Project KickStart saves the files in a folder named for your project

To save Gantt chart images1 In the Create and Print Gantt Chart Report dialog box click the Save Image button

The Save Image dialog box opens2 Change the location where you want to save the image files or change the part of the file name that

includes the project name and report type if necessary3 Click the Save buttonNotes

Project KickStart saves the image files in the PKSGanttImagesproject name folder stored in the MyDocumentsProject KickStart Projects folder (where project name is the name of your project)

Each graphic file name includes the name of the project report type date you created the report andnumber in the series of images as in CreateaWinningPresentation_Wall chart_09112008_1emf toCreateaWinningPresentation_Wall chart_09112008_20emf

To email the Gantt chart images attach the images in the PKSGanttImagesproject name folder storedin the My DocumentsProject KickStart Projects folder (where project name is the name of your project)If the image files are large zip or compress the files first

If you have installed PDF as a printer selection you can print the Gantt chart to a PDF file and thenattach the PDF file to an e-mail message PDF files are often easier to read than image files See thenotes in Print Preview a Gantt Chart for instructions on printing to a PDF file

-o-

119

copy Experience In Software Inc 1995 - 2006

Export Project Data

120

copy Experience In Software Inc 1995 - 2006

Export to ACT

Export to ACT 7 or Later

If you use ACT 7 or later (20052006200720082009) you can export your plan from Project KickStart toan ACT database with just one click After you export your plan you see your tasks in the ACT Groupview grouped under the name of your project

To export to ACT 7 or later

1 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 7 and later andthen click the Go button You can also click File on the menu bar point to Export to and then clickACT 7 and later

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (pad file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opens

Each time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks

4 Click Start (This works best if ACT is already open )

5 If you are exporting to a multi-user ACT database enter your ACT User Name and Password

To view each project separately in ACT Group Details

1 In ACT click the Group List icon

2 Double-click the Project Name in the Group Name column The Group Detail appears for the projectyou selected

3 Click the Contacts tab to see Contacts and click the Activities tab to see tasks for that project

4 You should press Ctrl-F5 to refresh the view Also you might have to adjust the Filter in ACT so thatDates to show is set to All Dates

Task names are listed in the Regarding column Assignments are listed in the Scheduled With columnPhases are shown in red and tasks and subtasks are shown in blue

To view tasks from multiple projects sorted by date in Task List or Calendar

In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn Project names are in the Associate With column You might have to adjust the Filter in ACT sothat Dates to show is set to All Dates

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar Tasks are set as timeless (Duration of 0 minutes) so the transferred tasks dont fill up thecalendar

121

copy Experience In Software Inc 1995 - 2006

Tips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

The ACT 7 and later export is smart enough to update your existing tasks from the same project If youexport the same Project KickStart project two or more times ACT recognizes the project and asks ifyou want to update the project information in ACT You do not lose your task history or notes in ACT

Tasks that are unassigned in Project KickStart are listed as Scheduled With Unassigned PKS

You can filter by Selected Users in the Task List and in Groups

See Also

Import ACT Contacts and Users to the People Library

-o-

122

copy Experience In Software Inc 1995 - 2006

Export to ACT 6

If you use ACT 6 ACT 2000 or ACT 5 you can transfer a Project KickStart plan into an ACT databasewith just one click After you export your plan you see your tasks in the ACT Group view grouped underthe name of your project

To export to ACT 61 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 6 and then click

the Go button You can also click File on the menu bar point to Export to and then click ACT 6

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (dbf file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opensEach time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks4 Click Start (This works best if ACT is already open )5 If you are exporting to a multi-user ACT database enter your ACT user name and passwordTo view each project separately in ACT1 In ACT click the Groups icon 2 Click the Project Name listed under All Groups on the left3 On the lower-right part of the window click the Activities tab to see tasks for that project

Task names are listed in the Regarding column Assignments are listed in the Scheduled With column 4 You might have to adjust the Filter in ACT so that Dates to show is set to All Dates Also you might

have to press Ctrl-F5 to refresh the view5 To view task details click the button next to the task column on the leftTo view tasks from multiple projects sorted by date1 In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn You might have to adjust the Filter in ACT so that Dates to show is set to All Dates

2 If the Group column is not showing add it by clicking ViewAdd Columns and then double-clickingGroupThe tasks are identified by group (project name)

3 To view task details click the button next to the task column on the leftTips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar as well as in the Task List

You can filter by Selected Users in the Task List and in Groups

After exporting your tasks to ACT you can import them to your Palm Pilot using the ACT Link

See Also

Import ACT Contacts and Users to the People Library

-o-

123

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Outlook

If you use Microsoft Outlook you can export your plan from Project KickStart to Outlook in a click of abutton After you export your plan you see your tasks in the Outlook Tasks view grouped under a categorynamed for your project In Outlook you can track your tasks and email tasks to team members

To export to Microsoft Outlook1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Outlook and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Outlook The Export to Outlook dialog box opens

2 Click an option button to export All tasks Uncompleted tasks or Completed tasks3 If you want to display the tasks you export on your Outlook Calendar click the check box4 Click the Start button A dialog box opens informing you that Project KickStart is trying to access your

Outlook data

5 Allow access for 1 minute and then click the Yes buttonTo view your tasks in Microsoft Outlook1 Click the Outlook Tasks button2 Depending on the version of Outlook you are using set to view the tasks by category In Outlook 2003

click the By Category option button in the Current View list You can also click View on the menu barpoint to Arrange By and then click CategoriesYour project is listed by its project name in the Categories list

3 Click an expand icon to see the complete list of tasks and subtasks

124

copy Experience In Software Inc 1995 - 2006

4 To view task details double-click the task nameTips

The export to Outlook works best if Outlook is already open

In Outlook you can set priorities set reminders and schedule by the hour

If you export to your Outlook Calendar a reminder appears on the due date of each task

After you export tasks to Outlook you can synchronize with your Palm Pilot Windows CE device orother handheld computer

Note

You can export only to Microsoft Office Outlook not Outlook Express

See Also

Import Outlook Contacts to the People Library

-o-

125

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Word

If you use Microsoft Word you can export your plan from Project KickStart to Word in a click of a buttonYour project appears in a Word table in a doc file You can cut and paste change column widths deletecolumns and print from Word

To export to Microsoft Word

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Word andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Word

Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in a Word document in a doc format

2 When youre finished use Save As to save the Word file with a new name such as ltnamegtdoc Forconvenience you can save the file using the same name as your Project KickStart project name

Benefits of using Project KickStart and Word

Communicate projects flexibly After exporting to Word you can communicate your project details ina variety of text formats You can also enhance your document by adding color logos clip art orhyperlinks

Distribute plans to others You can send doc files to other Microsoft Word users via email andrequest comments using Words Send To and Comments features

Tip

Include your strategic plan in documents letters and web pages in a doc or html file

Note

The image of the Gantt chart does not import into Word automatically You can manually import theGantt chart image into a Word document In Word select Insert on the menu bar point to Pictureclick From File and then browse to the folder containing the Gantt chart images you saved By defaultthis is cMy DocumentsProject KickStart ProjectsPKSGanttImages in a folder named for your project

See Also

Export to Word Processors (Other than Word)

Save Gantt Chart Images

126

copy Experience In Software Inc 1995 - 2006

-o-

127

copy Experience In Software Inc 1995 - 2006

Export to Word Processors (Other than Word)

If you are using a word processor other than Microsoft Word you can export your Project KickStart taskreport by first saving it as an HTML or RTF file

To export to word processors other than Microsoft Word

1 Save a Project KickStart task report using HTML or RTF format using the Save As button in the Createand Print Task Reports dialog box

2 Open the file with your word processor

3 Save the file using the Save As command using a different name

See Also

Print Task Reports

Save as HTML

Save as RTF

-o-

128

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Excel

If you use Microsoft Excel you can export your plan from Project KickStart to Excel in a click of a buttonYour project appears in an Excel worksheet in a xls file You can add task details perform calculationsand share your project data with other Excel users

To export to Microsoft Excel1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Excel and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Excel Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in an Excel worksheet in an xls format

2 When youre done select FileSave As to save the Excel file under a new name For convenience youmight want to save it under the same name as your Project KickStart project name

To manually import Gantt chart images into Microsoft Excel1 In Excel click Sheet2 and select ToolsOptions on the menu bar and unclick the box for Gridlines2 Then select Insert on the menu bar point to Picture click From File and then browse to the folder

containing the Gantt chart images you saved By default this is cMy DocumentsProject KickStartProjectsPKSGanttImages in a folder named for your project

3 Select one Gantt chart image at a time to bring it in 4 You can manipulate the size of the image in Excel

Benefits of using Project KickStart and ExcelProject KickStart is very good at scoping out a schedule but there are a few reasons why you might want touse both programs

Data sharing A Project KickStart user might want to share the information with other Excel users whodont have Project KickStart They could change enhance or redistribute their portions of the schedule

129

copy Experience In Software Inc 1995 - 2006

Add more task details Excel users can add new columns of task data that cant be added in ProjectKickStart

Sort task lists For example you could show your projects tasks sorted by each resources namethen see each resources tasks sorted by the tasks start date

Filter tasks Excel can show tasks that meet certain criteria For instance show tasks with the wordtesting in the task name

See Also

Save Gantt Chart Images

-o-

130

copy Experience In Software Inc 1995 - 2006

Export to Microsoft PowerPoint

If you use Microsoft PowerPoint you can export your plan from Project KickStart to PowerPoint in a click ofa button Your project appears as a formatted PowerPoint presentation in a ppt file

To export to Microsoft PowerPoint

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft PowerPointand then click the Go button You can also click File on the menu bar point to Export to and thenclick Microsoft PointPoint

The Export to PowerPoint dialog box opens where you can choose a PowerPoint design template ifyou like

2 Click the Start button

Your tasks days start and finish dates and costs appear in a PowerPoint presentation with an imageof the Gantt chart in one or more slides at the end of your slide show

Once you have created a PowerPoint presentation you can enhance your slides in several ways

Delete slides that are not appropriate for your presentation

131

copy Experience In Software Inc 1995 - 2006

Rearrange the order of the slides

Add colors for emphasis

Add graphics such as company logo clip art and colors

Shorten any long task titles

Benefits of using Project KickStart and PowerPoint

Save time You can dramatically save time in creating a PowerPoint presentation on your project

Present projects to others Present project details in webinars presentations and corporatemeetings Create template presentations or how tos for implementing an installation productintroduction or corporate policy for example

Communicate plans Email project plans in ppt format to colleagues and presentors

Tips

If you use a PowerPoint design template choose one that has a white or light background for maximumlegibility of the Gantt chart in the presentation

The Gantt chart image in the PowerPoint presentation is generated ldquoon the flyrdquo Change the Timescalesettings of the Gantt chart considering how it will be reflected in the number of images of the Ganttchart For example the Day view results in more Gantt chart images than the Months view

-o-

132

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Project

If you use Microsoft Project 98 2000 2002 or 2003 you can export your plan from Project KickStart toProject in a click of a button

To export to Microsoft Project

In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Project andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Project Your tasks assignments days start and finish dates costs done and notes (excluding attachments) appearin a Microsoft Project file

Benefits of using Project KickStart and Microsoft Project

Share data with others Send a project to a colleague or client that expects to see your schedule in anMicrosoft Project format

Schedule tasks with more flexibility Schedule tasks in different durations particularly in less than aday

Track resources Track resource usage and resource leveling and to have greater flexibility in sortingfiltering and reporting project information

Notes

Project KickStart tasks transfer to Microsoft Project as tasks with a Constraint type of Start No EarlierThan This keeps the dates the same as in the Project KickStart schedule

The settings in Project KickStart Working Days Calendar also transfer to Microsoft Project

Exporting to Microsoft Project allows you to take advantage of the advanced tracking and schedulingfeatures that large projects often require

You can also save your Project KickStart projects as an mpx file which you can open in MicrosoftProject and send to other Microsoft Project users Click File on the Project KickStart menu bar clickSave As and then choose mpx as the file type After you save the file click File on the MicrosoftProject menu bar click Open and open your mpx file

-o-

133

copy Experience In Software Inc 1995 - 2006

Export to SureTrak Project Manager

If you use SureTrak Project Manager you can export your plan from Project KickStart to SureTrak ProjectManager

To export to SureTrak Project Manager

1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file

2 In SureTrak click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

SureTrak

You will see your tasks and assignments (but not the notes) appear in a SureTrak file The file is shownin outline view

Benefits of using Project KickStart and SureTrak

Add new information to tasks such as how they are linked

Track progress particularly for comparing plans verses actual results

Have greater flexibility in sorting filtering and reporting project information

Notes

Task notes are not included in the transfer

A version of Project KickStart called the Project KickStart Wizard is included in SureTrak 2 andSureTrak 3 You can use it within SureTrak

See Also

Export MPX Files

-o-

134

copy Experience In Software Inc 1995 - 2006

Export to FastTrack Schedule

If you use FastTrack Schedule you can save your Project KickStart project as an mpx file and import it intoFastTrack ScheduleTo export to FastTrack Schedule1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file2 In FastTrack Schedule click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

FastTrack ScheduleBenefits of using Project KickStart and FastTrack Schedule

Add more task details FastTrack Schedule provides the features and tools needed in many largeprojects

Multiproject reporting Consolidate multiple projects into a master project file

See Also

Export MPX Files

-o-

135

copy Experience In Software Inc 1995 - 2006

Export to Milestones Professional

If you use Milestone Professional you can export your plan from Project KickStart to MilestonesProfessional in a click of a button

To export to Milestone Professional

In the Schedule step click the Export to list arrow below the Gantt chart click MilestonesProfessional and then click the Go button You can also click File on the menu bar point to Export to and then click Milestones Professional

Your tasks assignments start and finish dates and notes (excluding attachments) appear in aMilestones file

Tips

After you export your tasks to Milestones Professional you can create taskbars add titles and performother tasks to produce a presentation-quality schedule You can also use Milestones to track your tasksby showing task durations and percent completions Make scheduling changes by dragging the taskdates

If you have an earlier version of Milestones (eg version 45 or 5) you can save Project KickStart dataas an mpx file and then open the mpx file in Milestones

-o-

136

copy Experience In Software Inc 1995 - 2006

Export to Mindjet MindManager

If you use Mindjet MindManager 7 or later you can export your project plan from Project KickStart in a clickof a button Or you can develop a rough plan in MindManager and export your mind map to ProjectKickStart for enhanced planning It works both ways

To export from Project KickStart to MindManager

In the Schedule step click the Export to list arrow below the Gantt chart click MindManager and thenclick the Go button You can also click File on the menu bar point to Export to and then clickMindManager

Your tasks assignments start and finish dates durations costs Done and notes (excludingattachments) appear in a MindManager file

To export from MindManager to Project KickStart

In MindManager click File on the menu bar point to Send To and then click Project KickStart Thenclick the OK button to start the export

You can also click the Project KickStart icon at the bottom of the MindManager window

Benefits of using Project KickStart and MindManager together

Visualize your plan in two ways Brainstorm plan and communicate your project details in both agraphical and linear style

Develop a graphical plan and then fine-tune the details MindManager uses mindmappingtechniques to develop a high-level plan in a graphical format Export to Project KickStart to enhanceyour plan details by focusing on your projects goals obstacles and resource needs You can alsocreate a Gantt chart schedule

Communicate concepts Project KickStart users can display their plans in a highly graphicalmindmapping format in MindManager The maps make it easier to communicate complex processesand visually identify important tasks issues and relationships

Tip

If you dont already use MindManager you can purchase it in our Thinking Tools Store

-o-

137

copy Experience In Software Inc 1995 - 2006

Export to WBS Chart Pro

If you use WBS Chart Pro you can export your plan from Project KickStart to WBS Chart Pro in a click of abutton

To export to WBS Chart Pro

In the Schedule step click the Export to list arrow below the Gantt chart click WBS Chart Pro andthen click the Go button You can also click File on the menu bar point to Export to and then clickWBS Chart ProYour project is displayed under the project name Each phase in the project is shown in a box with ashadow Each lower level task in a phase is displayed under their respective phase box groupedtogether with the other tasks in that phase

Benefits of using Project KickStart and WBS Chart

Visualize tasks Work with tasks in a tree-style chart called a Work Breakdown Structure (WBS)chart

Communicate your project plan with others WBS Chart uses the outline you create in ProjectKickStart to create a top-down picture of your plan This picture is similar to an Organization chart Butinstead of displaying the structure of your company a WBS chart displays the structure of your projectplan

Notes

WBS Chart refers to the phases in the project as Summary Tasks and the detail for each phase asTasks

The export only works if WBS Chart is not currently running You must close WBS Chart before you cancreate another chart

See Also

Export MPX Files

-o-

138

copy Experience In Software Inc 1995 - 2006

Export MPX Files

The MPX file format is an ASCII format created by Microsoft Project or another program and is used tosend data to and from project management software programs

The following programs can create and open MPX files

FastTrack Schedule

Microsoft Project (95 or 98)

Project KickStart 5

Project KickStart 32

RiskyProject

SureTrak Project Manager

WBS Chart

In these programs you save a project as an MPX file using the Save As command on the File menu Youcan then open an MPX file by using the Open command on the File menu and then specifying the file typeas mpx

For example if you want to move a project from Project KickStart 5 to Project KickStart 32 you can savethe project as an mpx file and then open it in Project KickStart 32

In Microsoft Visio you can create a Visio project time line from Project KickStart To do so you first mustsave your file in Project KickStart as an MPX file Then

1 Start Visio

2 Click File on the menu bar point to New click Business Diagram and then click Project TimelinesWizard

3 Click Next

4 On the second window click Import MPX File to import the Project KickStart mpx file

5 Enter the file location and name or click Browse to locate the file

6 Follow the instructions in the Visio Project Timelines Wizard windows

Tip

If you have difficulty importing the mpx file remove any commas from task names

-o-

139

copy Experience In Software Inc 1995 - 2006

Reference

140

copy Experience In Software Inc 1995 - 2006

Menus

File Menu

Command Keyboard Shortcut Description

New Project Ctrl+N Creates and names a new project fileOpen Project Ctrl+O Opens a previously saved Project KickStart 4 or 5 file

(prx) Project KickStart 3 file (prj) or mpx fileClose Ctrl+W Closes an open Project KickStart fileSave Ctrl+S Saves a project file (prx) in which you made changes Save As Saves a project file with a different file name or different

file format such as MPXPrint Task Reports

Ctrl+T Generates and prints a report letting you preview thecontents

Print Gantt ChartReports

Ctrl+G In the Gantt chart (Schedule step) generates andprints the Gantt chart in the current timescale

Export To Sends the project to another program such asMicrosoft Outlook or ACT 7

Recent file list Lists the last three files opened in Project KickStartExit

Alt+F4 Exits the program

-o-

141

copy Experience In Software Inc 1995 - 2006

Edit Menu

Command Keyboard Shortcut Description

UndoRedo Ctrl+Z Undoes or repeats the last operationCut

Ctrl+X Deletes the currently selected information placing it on theclipboard so you can paste it elsewhere

Copy

Ctrl+C Places a copy of selected information on the Clipboard so youcan paste it elsewhere

Paste

Ctrl+V Places information from the Clipboard to the currently selectedlocation

Select all Ctrl+A Selects all the content in the windowAdd a line Adds a new row where you can enter text

-o-

142

copy Experience In Software Inc 1995 - 2006

View Menu

Command Description

Tool Bar Shows or hides the toolbar (a checkmark indicates thetoolbar is displayed)

Steps Bar Shows or hides the Steps bar (a checkmark indicates the Steps bar is displayed)

Name Go to the Name your project stepPhases Go to Phases stepGoals Go to Goals stepSimilar Projects Go to Similar projects stepPeople Go to People stepObstacles Go to Obstacles stepAssign Go to Assign tasks to people stepTasks Go to Tasks stepSchedule Go to Schedule step

-o-

143

copy Experience In Software Inc 1995 - 2006

Tools Menu

Command Keyboard Shortcut Description

Spelling

F7 Checks spelling of project dataexcept for names of people

Collaboration To access or find out aboutGoToMeeting

Options Select options for running thesoftware

-o-

144

copy Experience In Software Inc 1995 - 2006

Options

-o-

145

copy Experience In Software Inc 1995 - 2006

Data Menu

The Data menu is available in the Tasks and Schedule steps for manipulating tasks and creating ascheduleCommand Description

Move Up Moves the selected task item upMove Down Moves the selected task item downOutdent Moves the selected task item to the leftIndent Moves the selected task item to the rightInsert Task Insert task in row aboveInsert SubTask Insert subtask below current rowDelete Task Delete current taskEdit Task Properties Brings you to an edit screen where you can edit task

name change assignments and edit task notesEdit Notes Brings you to an edit screen for editing task notesColor Taskbars Change the color of selected tasks (in Schedule)Change Working Days Select which days are working and which are

nonworking (in Schedule)Link Tasks Link tasks in Gantt chart (Pro Users)Unlink Tasks Unlink tasks in Gantt chart (Pro Users)

-o-

146

copy Experience In Software Inc 1995 - 2006

Timescale Menu

The Timescale menu is available in the Schedule step so you can change the display of the Gantt chartschedule

Command Description

Days Displays a daily schedule in theGantt chart

Weeks Displays a weekly schedule inthe Gantt chart

Months Displays a monthly schedule inthe Gantt chart

Quarters Displays a quarterly schedule inthe Gantt chart

Years Displays a yearly schedule inthe Gantt chart

-o-

147

copy Experience In Software Inc 1995 - 2006

Help Menu

Command Description

Project KickStart Help Help for Project KickStart including a Table ofContents and index of terms

Online Tutorials View several Getting Started Tutorials to getyou started with Project KickStart whether youare a new or experienced user

Keyboard Shortcuts Shortcuts for programTechnical Support How to obtain Technical Support for Project

KickStart via web form and email[Send Log to Technical Support] If the program detects an error it writes a log

of technical issues Click Send Log toTechnical Support to send the error log to us

ProjectKickStartcom Visit the Project KickStart Web siteGet Latest Version See what the latest published version is and

download it if you need itAbout Project KickStart Shows Project KickStart version number build

date copyright and system information

-o-

148

copy Experience In Software Inc 1995 - 2006

Shortcuts

Use the following keyboard shortcuts to move quickly around in Project KickStart

Navigation

Move forward to the next window Alt+NMove back to the previous window Alt+BSteps

Go to Name step Alt+MGo to Phases step Alt+SGo to Goals step Alt+GGo to Similar step Alt+RGo to People step Alt+PGo to Obstacles step Alt+OGo to Assign step Alt+IGo to Tasks step Alt+KGo to Library (Phases Tasks GoalsPeople Obstacles)

Alt+L

Menus

File menu Alt+FEdit menu Alt+EView menu Alt+VShow menu (Tasks step) Alt+WOutline menu (Tasks step) Alt+UTimescale (Schedule step) Alt+CHelp menu Alt+H F1Other

Edit tasks assignments amp notes (Tasks step)F3Save Ctrl+SPrint Task Report Ctrl+PPrint Gantt Chart (Schedule step) Ctrl+GCut Ctrl+XCopy Ctrl+CPaste Ctrl+VInsert Row InsertDelete Row DeleteInsert Line Break (in Notes in Task List andSchdule steps)

Enter

Spell Check

Ignore Alt+IIgnore All Alt+GChange Alt+CChange All Alt+HHelp

149

copy Experience In Software Inc 1995 - 2006

Contents in Help Alt+CIndex Alt+IBack in Help Alt+BClose Help Alt+LHelp about the current step Alt+H

-o-

150

copy Experience In Software Inc 1995 - 2006

Share Project KickStart Data

Project KickStart makes it easy to share data with other people involved with a project You can share yourProject KickStart data in the following ways

Send a printed report Make a PowerPoint presentation Send a file (prx html rtf mpx) Post an HTML file to a Web site and access it with your web browser Export to other programs such as Microsoft Word or Excel and send data in a format the recipient can

access (such as doc xls or mpx)

Note

You can also collaborate with a colleague by conducting an online meeting using GoToMeeting (Prousers)

-o-

151

copy Experience In Software Inc 1995 - 2006

Open a Project

After you create a project and save it in a prx prj or mpx file using Project KickStart or other softwareyou can open the project in Project KickStartTo open a project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click a file type (prxprj or mpx)

3 Navigate to the folder that contains the file4 Double-click the name of the file

Opening a Project KickStart 3 prj file converts it to a prx file

Generally prj files are stored in cprogram filesProject KickStart 3

The tasks in the converted Project KickStart 5 file will have the same start and finish dates anddurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way To have weekends as non working days open the working days calendar and markweekends as non working

Opening a mpx file converts it to a prx file

The tasks in each project have the same start and finish dates and durations

-o-

152

copy Experience In Software Inc 1995 - 2006

Dedication

I dedicate this software program to my new colleague

Kevin Ahlvin

Roy A Nierenberg President

-o-

153

copy Experience In Software Inc 1995 - 2006

Credits and Trademarks

Credits

Missak Koumoudjian Program Architect and Chief Programmer

Kevin Ahlvin Interface DesignAnn Kawamoto Quality AssuranceAlexander Setzepfandt Quality AssuranceJackie LeungJeffrey Chow

Programming Interns

Kevin Ahlvin Product Supervisor and CoordinatorJoseph Fusco Project Management Consultant and content

providerLisa RuffoloJoseph Fusco

Help System

Roy A Nierenberg President

Trademark

Project KickStart and Project KickStart Wizard are trademarks of Experience In Software Inc in the UnitedStates andor in other countries All rights reserved All other trademarks mentioned herein are the propertyof their respective owners

-o-

154

copy Experience In Software Inc 1995 - 2006

Uninstalling

You can uninstall Project KickStart 5 through the Control Panel AddRemove Programs Select ProjectKickStart 5 This starts the InstallShield Maintenance Program You should then remove all of theprogram files that were installed It will not erase your Project KickStart prx data files

If that does not work you can delete the Project KickStart files manually

Note

If you purchased Project KickStart and you want to return it for a refund follow the instructions forDe-activating the software at httpwwwprojectkickstartcomcontactreturnscfm

-o-

155

copy Experience In Software Inc 1995 - 2006

Using Past Projects

You can use past projects in two ways

If you have projects that are similar you can use a past project as a template for a new project In theWelcome window select Open a Project Open that project and Save As under a different name Nowyou can open up the renamed project and modify it for the current project

You can draw from several projects in the Similar Projects step First select projects that are similarand click Next Then select tasks from those projects and decide where they would fit into your currentproject

See Also

Opening a project Compatibility with earlier versions

-o-

156

copy Experience In Software Inc 1995 - 2006

Index

- - Change Working Schedule 85

- -prj file format 13

- A -About Linking Tasks (Pro Users) 59About Scheduling Tasks 55About the Gantt Chart 57ACT 120 92 122ACT 6 92 122ACT 7 or later 92 120Activate 14Activating Trial Version 14Add a New Person or Resource 39add a subtask 83add a task 83Add a Task or Subtask 47Add or Change Task Assignments 51Add or Change Task Details 52Add Subtask 63Add Task 63Add URL 49Additional Features in Task Data View (Pro Users) 68Additional Tools in Chart View (Pro Users) 71Adobe PDF 117Assignments tab 80Attachments 49Autolink tasks (Pro Users) 58

- B -Back 10borrow tasks 29

- C -Change Details for Linked Tasks (Pro Users) 81Change Project Start 63Change Task Dates 73Change Task Details 80Change the Appearance of the Task List 43Change the Display of the Schedule 61Change Timescale 63Change Working Schedule 63Chart view 57

157

copy Experience In Software Inc 1995 - 2006

Cloning projects 155Color 63 86Compatibility 13Compatibility with earlier versions 13convert projects 13Coordination 12Create and Print Task Reports 102Credits 153Credits and Trademarks 153critical path 88CSV 96Customer support 20Customer Support 20Customizing Project KickStart

- D -Dashboard 99Data Menu 145Dedication 152Delete 63delete a task 83demote 46dependencies 12 76

- E -Edit Menu 141Edit Notes and Attachments 63Edit or Substitute People 40Edit Task Information 63Email Task Reports 108End User License Agreement 16error 21Error Messages 21export from MindManager 136Export MPX Files 138Export to ACT 6 122Export to ACT 7 and Later 120Export to FastTrack Schedule 134Export to Microsoft Excel 128Export to Microsoft Outlook 123Export to Microsoft PowerPoint 130Export to Microsoft Project 132Export to Microsoft Word 125Export to Milestones Professional 135Export to Mindjet MindManager 136Export to SureTrak Project Manager 133Export to WBS Chart Pro 137

- F -FastTrack Schedule 134File Menu 140Fit to page 111Fit to Smallest Size 111

158

copy Experience In Software Inc 1995 - 2006

- G -Gantt chart 55 57General tab 80Goal 26Goal statements 26Goals 26Goals - Step 1 of 3 26Goals - Step 2 of 3 27Goals - Step 3 of 3 28goals library 26 89Goalsadd 26Goalsdelete 26Goalsedit 26Goalstasks for 27GoToMeeting 150 12

- H -Handouts 111Help Menu 147hyperlink 49

- I -Import ACT 92import contacts and users 92import Outlook contacts 94Import Outlook Contacts via CSV to the People Library (Pro Users) 96ImportCSVToPKSexe 96Indent 46Individual Assignments 102Introduction 7Introduction 7

- K -Knowledge Libraries 90

- L -lag time 81lead time 59 81library 89License Key 14link 59Link lines 59Link tasks 12 65linked tasks 59

- M -major activities 24Make Tasks Overlap (Pro Users) 87Manage a Library 90

159

copy Experience In Software Inc 1995 - 2006

Menu 140Microsoft Excel 128Microsoft Outlook 123Microsoft PowerPoint 130Microsoft Project 132Microsoft Project (95 or 98) 138Microsoft Visio 138Microsoft Word 125Milestone 69 79Milestones Professional 135Mindjet MindManager 136MindManager 136

- N -Name 23Name Your Project 23Navigating Project KickStart 10Next 10Notes and Attachments tab 80

- O -Objectives 26Obstacles 34Obstacles - Step 3 of 3 36Obstacles Library 89Open a Project 151Options 144Outdent 46Outdent and Indent arrows 63Outlook Calendar 123Overview

- P -Page Setup 107 116 100PDF 117people 31People - Step 3 of 3 28People Library 91phase 24phase dates 75Phase Dates Cannot Be Edited 75phases 24Phases - Step 1 of 2 24Phases - Step 2 of 2 25Phases Library 89Phases Goals People amp Obstacles 102PowerPoint presentation 130Pred 68Predecessor 68Predecessor tasks 59predecessors 76Print a Gantt Chart 111Print Dashboard Reports 99Print Preview 105Print Preview a Gantt Chart 115Print Reports 98Print Task Reports 102

160

copy Experience In Software Inc 1995 - 2006

Printer Setup 106Printing to an Adobe PDF file 117prj 13Pro 145Pro Edition 145Product support 20Project 23Project KickStart 3 prj file 151Project KickStart for Windows 7project name 23project start date 73project template 155project title 23promote 46promote and demote tasks 83

- Q -Quick Tour of Working with Linked Tasks (Pro Users) 76

- R -Red vertical line 69Redo 11Register Project KickStart 22Registering Project KickStart 22remove people 38Remove People from a Task 38reorder tasks 83Reorganize Tasks in Task Data View 83Repeat tasks on every page (for handouts) 111Reporting Technical Issues 21resource 31resources 31restore 34return 154risks 34RiskyProject 138

- S -Save As 101Save as HTML 109Save as RTF 110Save Gantt Chart Images 118Schedule 55Send Error Report 21similar projects 29spelling 53starter schedule 55Steps 7subtask 47Subtasks 46Succ 68Successor 68Successor tasks 59successors 76Summary bar 69Support 20SureTrak Project Manager 133

161

copy Experience In Software Inc 1995 - 2006

- T -Task Data view 57task dates 73Task Report 102Taskbar 69Taskbar with percent done 69Tasks 25Tasks in Phases 25Tasks Library 89team 31Technical support 20timescale 84Timescale Menu 146Tools Menu 143Trademark 153trademarks 153Trial 14

- U -unassigning 38Understand Chart View 69Understand Task Data View 66Undo 11UndoRedo Buttons 11uninstallUninstalling 154Unlink tasks 12 65Up and Down arrows 63Use Project KickStart to 8Use the Gantt Chart Toolbar 63Use the Planning Wizard 9Uses 8Using Past Projects 29 155

- V -Version View Menu 142Visio 138

- W -Wall chart 111WBS Chart Pro 137Welcome to Project KickStart 7Whats Due Next Month 99Whats Due Next Week 99Whats Due Today 99Whats New in Project KickStart Pro 5 11Windows Vista 20

162

copy Experience In Software Inc 1995 - 2006

copy Experience In Software 2008w w w projectkickstartcom

  • Table of Contents
  • Start Here Welcome to Project KickStart
    • Introduction
      • Welcome to Project KickStart
      • Use Project KickStart to
      • Use the Planning Wizard
      • Navigating Project KickStart
      • Whats New in Project KickStart Pro 5
      • Whats New in Project KickStart Pro 5 (Pro Users)
      • Compatibility with earlier versions
      • Activating Trial Version
        • Licenses and Support
          • End User License Agreement
          • Customer Support
          • Reporting Technical Issues
          • Register Project KickStart
              • Planning Projects
                • Name Your Project
                • Phases - Step 1 of 2
                • Phases - Step 2 of 2
                • Goals - Step 1 of 3
                • Goals - Step 2 of 2
                • Goals - Step 3 of 3
                • Similar Projects - Step 1 of 2
                • Similar Projects - Step 2 of 2
                • People - Step 1 of 3
                • People - Step 2 of 3
                • People - Step 3 of 3
                • Obstacles - Step 1 of 3
                • Obstacles - Step 2 of 3
                • Obstacles - Step 3 of 3
                  • Assigning People
                    • Assign Tasks to People
                    • Remove People from a Task
                    • Add a New Person or Resource
                    • Edit or Substitute People
                      • Organizing the Project Plan
                        • About Organizing Tasks
                        • Change the Appearance of the Task List
                        • Show or Hide Tasks in the Task List
                        • Move Tasks within the Task List
                        • Outdent and Indent Tasks
                        • Add a Task or Subtask
                        • Edit Tasks
                        • Add Task Notes and Attachments
                        • Add or Change Task Assignments
                        • Add or Change Task Details
                        • Check Spelling
                          • Scheduling Tasks in the Gantt Chart
                            • Scheduling Overview
                              • About Scheduling Tasks
                              • About the Gantt Chart
                              • Autolink tasks (Pro Users)
                              • About Linking Tasks (Pro Users)
                              • Change the Display of the Schedule
                              • Use the Gantt Chart Toolbar
                              • Use the Gantt Chart Toolbar (Pro Users)
                              • Understand Task Data View
                              • Additional Features in Task Data View (Pro Users)
                              • Understand Chart View
                              • Additional Tools in Chart View (Pro Users)
                                • Change Task Dates
                                • Phase Dates Cannot Be Edited
                                • Quick Tour of Working with Linked Tasks (Pro Users)
                                • Link and Unlink Tasks (Pro Users)
                                • Create a Milestone
                                • Change Task Details
                                • Change Details for Linked Tasks (Pro Users)
                                • Reorganize Tasks in Task Data View
                                • Change the Timescale of the Schedule
                                • Specify Working Days
                                • Change the Color of Taskbars
                                • Make Tasks Overlap (Pro Users)
                                • Manage Changes in Your Schedule (Pro Users)
                                  • Managing Libraries
                                    • Use a Library
                                    • Manage a Library
                                    • Manage the People Library
                                    • Import ACT Contacts and Users to the People Library
                                    • Import Outlook Contacts to the People Library
                                    • Import Outlook Contacts via CSV to the People Library (Pro Users)
                                      • Printing Reports
                                        • Printing Dashboards
                                          • Print Reports
                                          • Print Dashboard Reports
                                          • Page Setup
                                          • Save As
                                            • Printing Task Reports
                                              • Print Task Reports
                                              • Print Preview
                                              • Printer Setup
                                              • Page Setup
                                              • Email Task Reports
                                              • Save As HTML
                                              • Save As RTF
                                                • Printing Gantt Chart Reports
                                                  • Print a Gantt Chart
                                                  • Print Preview a Gantt Chart
                                                  • Page Setup
                                                  • Printing to an Adobe PDF file
                                                  • Save Gantt Chart Images
                                                      • Export Project Data
                                                        • Export to ACT
                                                          • Export to ACT 7 and Later
                                                          • Export to ACT 6
                                                            • Export to Microsoft Outlook
                                                            • Export to Microsoft Word
                                                            • Export to Word Processors (Other than Word)
                                                            • Export to Microsoft Excel
                                                            • Export to Microsoft PowerPoint
                                                            • Export to Microsoft Project
                                                            • Export to SureTrak Project Manager
                                                            • Export to FastTrack Schedule
                                                            • Export to Milestones Professional
                                                            • Export to Mindjet MindManager
                                                            • Export to WBS Chart Pro
                                                            • Export MPX Files
                                                              • Reference
                                                                • Menus
                                                                  • File Menu
                                                                  • Edit Menu
                                                                  • View Menu
                                                                  • Tools Menu
                                                                  • Options
                                                                  • Data Menu
                                                                  • Timescale Menu
                                                                  • Help Menu
                                                                    • Shortcuts
                                                                    • Share Project KickStart data
                                                                    • Open a Project
                                                                    • Dedication
                                                                    • Credits and Trademarks
                                                                    • Uninstalling the software
                                                                    • Using Past Projects
Page 6: Project KickStart Help File in PDF format

6

copy Experience In Software Inc 1995 - 2006

Start Here Welcome to Project KickStart

7

copy Experience In Software Inc 1995 - 2006

Introduction

Welcome to Project KickStart

Whether yoursquore a novice or seasoned pro yoursquoll be amazed at how quickly you can create a thoughtfulcomprehensive task list and project schedule Using Project KickStart you can go from raw idea to aproject task list in 30 minutes You do not need any special project management training to use ProjectKickStart

The first thing youll want to do is

Open a project Click to open one of our sample projects

Start a new project Click to begin planning your own project

Open your last project If youve already created a project click this option to open your most recentproject

After that let Project KickStart show you the way Itrsquos easy to navigate Project KickStart with its intuitivegraphical interface--it feels like a coach is guiding you through each step

Next StepsProject KickStart guides you through the process of planning and scheduling your project On the top ofeach Project KickStart window are instructions explaining what to do Read the instructions enter your dataand then click the Next button in the lower-right corner of the window Additional help is always availablefrom the onscreen Advisor and Project KickStart Help

Sample ProjectsThe sample projects are completed projects that let you get a feel for Project KickStart If you find onesimilar to the project you want to create open it save it with a new name and then customize it to meetyour needs

-o-

8

copy Experience In Software Inc 1995 - 2006

Use Project KickStart to

Project KickStart is organized into three sections planning scheduling and exporting to other programs

Plan The Project KickStart graphical interface acts as a Planning Wizard guiding you through eightsteps for planning your project Some planning steps involve brainstorming to identify tasks that youmight otherwise overlook

Schedule The Project KickStart Gantt chart makes scheduling tasks fast and easy You can printtaskbars in color and save Gantt charts reports as images so you can email them to colleagues orinclude them in a report

Export Communicate your projects in a variety of ways by exporting project data to other applicationsincluding Microsoft Outlook With one mouse click you can include Project KickStart plans in aMicrosoft Word document Excel spreadsheet PowerPoint slide presentation and more

People are using Project KickStart to

Create process templates project reports to-do lists and more

Communicate project details to others through reports email and Gantt chart schedules

Ensure project buy-in by including the needs of team members in your plan

Consider project goals and obstacles in the planning process and prevent surprises later

-o-

9

copy Experience In Software Inc 1995 - 2006

Use the Planning Wizard

Project KickStart uses a Planning Wizard that guides you through eight steps for planning your project Tostep through the wizard click each icon on the Steps bar (on the left side of the Project KickStart window) inorder On each window t ips and advice are always available by clicking the Advisor button You click theNext button to continue

Name Each project has a name To start planning your project give it ashort descriptive name

Phases Consider how your project will break down into major activitiesor phases Start by listing your phases and then list the tasks thatbelong in each phase

Goals Goals are what you hope to accomplish in your project Enter orselect the goals for your project Then you can list any new tasks toachieve each goal

Similar Projects often have tasks in common In this step you canborrow tasks from past projects to help you plan this project Then youcan add any new tasks from a similar project to the phases of yourcurrent project

People List the people groups or things that might provide resourcesfor your project including yourself Then identify any new tasks thesepeople might do or suggest for your project

Obstacles Each project has obstacles you can overcome if youanticipate them List the obstacles you will face in your project and thenidentify any new tasks needed to avoid the obstacles

Assign Assign tasks to people and other resources

Tasks Change the order of your tasks add and delete tasks andcreate subtasks You can also edit tasks change assignments and addnotes

Schedule Schedule the tasks in your project To make schedulingeasier new projects open with a starter schedule beginning todaywhich you can customize to fit your project

-o-

10

copy Experience In Software Inc 1995 - 2006

Navigating Project KickStart

When you use the Planning Wizard you work with a step window similar to the following illustration

Steps bar Click a step button to perform a step in the Planning Wizard The selected button shows yourcurrent step

Name of your project Shows the name entered in the Name step

Menu bar Select options from the menu bar to work with your projects

Toolbar Click buttons to perform common tasks such as saving your project

Step instructions Indicate how to perform the current step

Library button Click to open a library for the current step For example click the Goals Library button toopen a library listing typical project goals

Back and Next buttons Click a button to return to the previous step or continue to the next step in thePlanning Wizard

Advisor button Click to see instructions tips and notes for completing the current step

-o-

11

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5

The following table outlines whatrsquos new in Project KickStart Pro 5

If you own a previous version of Project KickStart yoursquoll notice the new Pro version has a new look and feelAs you begin to check it out yoursquoll soon discover Project KickStart Version 5 is a lot more powerful thanprevious versions and comes with some great new features

FEATURE DESCRIPTION IMPROVED

NEW

Dashboard Reporting

Quickly assess what is due TodayNext Week or Next Month

X

Import Contacts Import from a comma separatedvalue (CSV) file

X

Templates Use as is or customize X

Gantt Chart Greater stability and functionality X

User Interface Contemporary look and colorscheme

X

Preferences Customize look and feel andprogram defaults

X

Productivity Pack Project template Word docs fornewbies

X

Exports Improved Outlook MindManager and ACTimproved data exchange

X

-o-

12

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5 (Pro Users)

This feature is available only in Project KickStart Professional

The following table outlines whatrsquos new in Project KickStart Pro 5

FEATURE DESCRIPTION IMPROVED NEW

Gantt Chart Task dependencies in Gantt chart X

Link tasks Show task dependencies X

Unlink tasks Remove task dependencies X

Add predecessors Add task predecessors X

Add successors Add task successors X

Project Coordination Link to GoToMeeting for onlinemeetings on projects

X

Project KickStart Pro now includes dependencies on the Gantt chart This sophisticated scheduling andproject management tool is new to Project KickStart Pro and is designed to make complex projectscheduling easy and straightforward

Use dependencies to handle scheduling demands delays and surprises without modifying every task inyour project Dependencies let you make adjustments as events change giving you a more robust scheduleand the opportunity to conduct what-if analysis

Suppose you are managing a landscaping project involving subcontractors and dozens of tasks One ofyour first tasks is to pave a path with flagstones but the shipment of flagstones is two days late Usingdependencies you can delay the path-paving task in a couple of clicks and Project KickStart Proautomatically updates the schedule for the remaining tasks

Although dependencies meet your advanced scheduling needs the Project KickStart Pro approach todependencies keeps them as simple as possible If you want to link a couple of tasks which are dependenton one another you can simply highlight the tasks and click the link icon

If you select the option of Autolinking tasks then when you display the Gantt chart the first time all tasksare pre-linked allowing you to adjust durations schedules of individual tasks and time between taskswhich is called Lead Time in Project KickStart Pro

Unlike other project management programs such as Microsoft Project Project KickStart Pro does notburden you with complicated error messages and various types of dependencies It provides only one typeof dependency finish-to-start which is the most common type This means you can fine-tune your scheduleas soon as you open the Gantt chartmdashwithout having to learn technical terms or advanced projectmanagement techniques

The Project Coordination functionality that we are providing is through GoToMeeting and is a chargedservice

Note

These features are in addition to those listed on the Whatrsquos New in Project KickStart 5 page

-o-

13

copy Experience In Software Inc 1995 - 2006

Compatibility with earlier versions

Project KickStart 5 can open and save projects in Project KickStart 4 prx file format (Same as ProjectKickStart 5)

Project KickStart 5 can open and convert projects saved in Project KickStart 3 prj file format You need tohave a licensed copy of Project KickStart 3 on your system to make the conversion

To open a prj project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click prj file type3 Navigate to the folder that contains the prj file Generally prj files are stored in cprogram filesProject

KickStart 34 Double-click the name of the file

Tips

The tasks in the converted Project KickStart 5 file will have the same start and finish dates and samedurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way (ie as working days) To have weekends as non working days click the Change WorkingSchedule button on the Gantt chart toolbar and mark weekends as non working

Note

Project KickStart 5 does not open and convert prj files from Project KickStart 1 or 2

-o-

14

copy Experience In Software Inc 1995 - 2006

Activating trial version

You may have obtained a FREE 20-day trial version of Project KickStart 5 from our website or from areseller

To convert your Trial Version to a Full Version youll need to purchase a License Key and to activate thesoftware

To activate Project KickStart 5 trial1 Start the Project KickStart trial

2 If you have not purchased your License Key yet click the Buy button to purchase online3 If you have purchased a License Key click the Activate button and copy and paste the License Key

that you received when you purchased Project KickStart as well as your name and email

15

copy Experience In Software Inc 1995 - 2006

4 You must be connected to the Internet and you must tell your Firewall to allow communication forPKS5Kickstartexe

Tip

Your License Key allows 2 activations per user One is for your primary computer and one is for asecond computer you use such as your laptop or home computer

-o-

16

copy Experience In Software Inc 1995 - 2006

Licenses and Support

End User License Agreement

EXPERIENCE IN SOFTWARE INC END USER LICENSE AGREEMENT AND WARRANTYDISCLAIMER

PROJECT KICKSTARTtrade STANDARD 5 AND PRO 5 EDITIONS

NOTICE This is a legally binding contract between you the end user and EXPERIENCE IN SOFTWAREINC

EXPERIENCE IN SOFTWARE INC (EIS or LICENSOR) LICENSES THE ENCLOSED SOFTWARETO YOU (USER or LICENSEE) ONLY UPON THE CONDITION THAT YOU ACCEPT ALL OF THETERMS CONTAINED IN THIS LICENSE AGREEMENT PLEASE READ THE TERMS CAREFULLY BYOPENING THIS PACKAGE BREAKING THE SEAL CLICKING ON THE ldquoAGREErdquo OR ldquoYESrdquo BUTTONOR OTHERWISE INDICATING ASSENT ELECTRONICALLY OR LOADING THE SOFTWARE YOUAGREE TO THE TERMS AND CONDITIONS OF THIS AGREEMENT IF YOU DO NOT AGREE TOTHESE TERMS AND CONDITIONS CLICK ON THE ldquoI DO NOT AGREErdquo ldquoNOrdquo BUTTON OR MAKE NOFURTHER USE OF THE SOFTWARE IF YOU DO NOT AGREE TO THESE TERMS THEN EIS ISUN-WILLING TO LICENSE THE SOFTWARE TO YOU IN WHICH EVENT YOU SHOULD RETURN THEFULL PURCHASED PRODUCT WITH PROOF OF PURCHASE TO LICENSOR OR THE DEALER FROMWHOM IT WAS ACQUIRED WITHIN 15 DAYS OF PURCHASE AND YOUR MONEY WILL BEREFUNDED

LICENSE AND WARRANTY

The software that accompanies this license (Software) is the property of EIS and is protected by copyrightand other intellectual property law Although EIS at all times owns the Software you will have certain rightsto use the Software after your acceptance of this license Except as may be modified by an addendumwhich may accompany or be added to this license your rights and obligations with respect to the use of thisSoftware are as follows

You may

(i) install and use one copy of the specified edition of Software and documentation on a single computerand only by one user (ldquoPrimary Userrdquo) If you have purchased multiple licenses for the Software asindicated as Quantity or Number of Licenses on the Invoice or electronic confirmation issued by EIS orits Resellers then at any time you may have as many copies of the Software in use as you have licenses The Software is ldquoin userdquo on a computer when it is loaded into the temporary memory (ie RAM) or installedinto the permanent memory (eg hard disk CD-ROM or other storage device) of that computer

(ii) install and use a second copy of the Software on a second computer for the limited and exclusive use ofthe Primary User

(iii) use the Software on a network provided that Licensee has a licensed copy of the Software for eachnamed user that can access the Software over that network

(iv) make one copy of the Software for archival purposes or copy the Software onto the hard disk of yourcomputer and retain the original for archival purposes

(v) after written notice to EIS transfer the Software on a permanent basis to another person or entityprovided that you retain no copies of the Software and the transferee agrees to the terms of this agreement

You may not

(i) rent lease copy distribute license or otherwise transfer the Software or its documentation to any otherparty Licensee may make a reasonable number of back-up copies for archival purposes only TheSoftware contains copyrighted material trade secrets and other proprietary material If Licensee has theright to duplicate the Software for multiple Users then Licensee must reproduce on all such copies of theSoftware the copyright notices and any other proprietary legends that were on the original copy of theSoftware or

(ii) decompile reverse engineer disassemble translate make any attempt to discover the source code ofthe Software or otherwise reduce the Software to a human perceivable form or modify network or create

17

copy Experience In Software Inc 1995 - 2006

derivative works based upon the Software or the documentation in whole or in part nor permit any otherparty to do so

Notwithstanding anything herein if the Software is lawfully acquired outside of the United States within ajurisdiction which is a member of the European Union subject to the EEC Council Directive 91250EEC ofMay 14 1991 Licensee agrees that within that jurisdiction it shall not and shall not allow any party onLicensees behalf to attempt to reverse engineer or decompile the Software into another computerlanguage except as expressly and specifically provided in the EEC Council Directive 91250EEC of May14 1991 Any and all information obtained during such lawful reverse engineering andor decompilingactivities including but not limited to the organization logic algorithms and processes of the Softwareshall be deemed to be the confidential and proprietary information of EIS

Licensee shall not make copies of the copyrighted Software documentation without the prior writtenpermission of EIS provided that for electronic transactions Licensee may make one (1) hard copy of suchdocumentation for each User

Intellectual Property and Duplication of Software

The Software contains copyrighted material trade secrets and other proprietary material If Licensee hasthe right to duplicate the Software for multiple Users then Licensee must reproduce on all such copies ofthe Software the copyright notices and any other proprietary legends that were on the original copy of theSoftware

Upgrades

To use a Product identified as an upgrade you must first be licensed for the product identified by EIS aseligible for the upgrade After upgrading you may no longer transfer the product that formed the basis foryour upgrade eligibility to another person or entity

Technical Support

Licensee must register the Software in order to be eligible for free technical support (including installationand registration of the product) during the first 90 days after purchase

Thirty Day Money Back Guarantee

If you are the original Licensee of this copy of the Software and are dissatisfied with it for any reason youmay return the complete product together with your receipt to EIS or an authorized dealer postageprepaid for a full refund at any time during the thirty-day period following the delivery to you of thePurchased Software

Export Law Assurances

You are responsible for complying with all trade regulations and laws both foreign and domestic Youacknowledge that none of the Software or underlying information or technology may be downloaded orotherwise exported or re-exported (i) into Afghanistan (Taliban-controlled areas) Cuba Iran Iraq LibyaNorth Korea Serbia (except Kosovo) Sudan and Syria or any other country subject to a US embargo or(ii) to anyone on the US Treasury Departments list of Specially Designated Nationals or the USCommerce Departments Denied Parties List or Entity List By using the Software you are agreeing to theforegoing and are representing and warranting that (i) no US federal agency has suspended revoked ordenied you export privileges (ii) you are not located in or under the control of a national or resident of anysuch country or on any such list and (iii) you will not export or re-export the Software to any prohibitedcounty or to any prohibited person entity or end-user as specified by US export controls as defined byEAR 15 CFR Parts 730-774 and BXA (httpwwwbxadocgov)

Data Collection and Privacy Policy

You acknowledge and agree that EIS may collect and retain information about you such as your nameaddress and e-mail address You also understand that EIS may employ other companies to performfunctions on our behalf such as fulfilling orders delivering packages sending postal mail and e-mailproviding marketing assistance and processing credit card payments These companies may have accessto personal information needed to perform their functions and may not use such information for otherpurposes By assenting to this agreement you agree that you have read and understand our Privacy PolicyFor more detailed information httpwwwprojectkickstartcomhtmlprivacy_statementhtm

Termination

This License is effective until terminated Licensee may terminate this License at any time by destroying allcopies of the Software and its documentation This License will terminate immediately without notice from

18

copy Experience In Software Inc 1995 - 2006

EIS if Licensee fails to comply with any provision of this License Upon termination Licensee must destroyall copies of the Software and its documentation and cease and desist from any further use of the Software

Limited Warranty

EIS warrants that the media on which the Software is distributed will be free from defects and that theSoftware shall perform substantially as described in its documentation for a period of sixty (60) days frompurchase Your sole remedy in the event of a breach of this warranty will be that EIS will replace anydefective media returned to EIS within the warranty period EIS does not warrant that the Software willmeet your requirements or that operation of the Software will be uninterrupted or that the Software will beerror-free

THE ABOVE WARRANTY IS EXCLUSIVE AND IN LIEU OF ALL OTHER WARRANTIES WHETHEREXPRESS OR IMPLIED INCLUDING THE IMPLIED WARRANTIES OF MERCHANTABILITY FITNESSFOR A PARTICULAR PURPOSE AND NONINFRINGEMENT OF INTELLECTUAL PROPERTY RIGHTSTHIS WARRANTY GIVES YOU SPECIFIC LEGAL RIGHTS YOU MAY HAVE OTHER RIGHTS WHICHVARY FROM STATE TO STATE AND COUNTRY TO COUNTRY

Disclaimer of Damages

REGARDLESS OF WHETHER ANY REMEDY SET FORTH HEREIN FAILS OF ITS ESSENTIALPURPOSE IN NO EVENT WILL EIS OR ITS RESELLERS BE LIABLE TO YOU FOR ANY SPECIALCONSEQUENTIAL INDIRECT OR SIMILAR DAMAGES INCLUDING BUT NOT LIMITED TO ANY LOSTPROFITS OR LOST DATA ARISING OUT OF THE USE OR INABILITY TO USE THE SOFTWARE EVENIF EIS HAS BEEN ADVISED OF THE POSSIBILTIY OF SUCH DAMAGES SOME STATES DO NOTALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FOR INCIDENTAL OR CONSEQUENTIALDAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAY NOT APPLY TO YOU IN NO CASESHALL EISS ITrsquoS RESELLERrsquoS LIABILITY EXCEED THE PURCHASE PRICE FOR THE SOFTWARE

SOME STATES AND COUNTRIES INCLUDING MEMBER COUNTRIES OF THE EUROPEANECONOMIC AREA DO NOT ALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FORINCIDENTAL OR CONSEQUENTIAL DAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAYNOT APPLY TO YOU

The disclaimers and limitations set forth above will apply regardless of whether you accept the Software

US Government Restricted Rights

DISTRIBUTION TO THE US GOVERNMENT This Software is commercial software developedexclusively at private expense This Software and the documentation are provided with RESTRICTEDRIGHTS applicable to private and public licenses alike Use duplication or disclosure by civilian agenciesof the US Government shall be in accordance with the Commercial Computer Software-Restricted Rightsclause at FAR 52227-19 Use duplication or disclosure by Department of Defense agencies is subjectsolely to the terms of this software licensing agreement pursuant to DFARS 2277202Contractormanufacturer of the Software is EXPERIENCE IN SOFTWARE INC 2029 Durant AveBerkeley CA 94704 USA

General

This Agreement shall be governed by the laws of the State of California without giving effect to principles ofconflict of laws You hereby consent to the exclusive jurisdiction and venue of the state courts sitting in SanFrancisco County California or the federal courts in the Northern District of California to resolve anydisputes arising under this Agreement This Agreement contains the complete understanding between theparties with respect to the subject matter hereof and supersedes all prior or contemporaneous Agreementsor understandings whether oral or written You agree that any varying or additional terms contained in anypurchase order or other written notification or document issued by you in relation to the Software licensedhereunder shall be of no effect No provision hereof shall be deemed waived or modified except in writing No EIS dealer agent or employee is authorized to make any amendment to this Agreement

The intellectual property protections the disclaimers of warranties and the limitation of damages shallsurvive termination The failure or delay of EIS to exercise any of its rights under this Agreement or uponany breach of this Agreement shall not be deemed a waiver of those rights or of the breach If any provisionof this Agreement is held invalid the remainder of this Agreement will remain in full force and effect

Should you have any questions concerning this Agreement or if you desire to contact EIS for any reasonplease write to EXPERIENCE IN SOFTWARE INC 2029 Durant Ave Berkeley CA 94704 USA

-o-

19

copy Experience In Software Inc 1995 - 2006

20

copy Experience In Software Inc 1995 - 2006

Customer Support

When you need help in solving a problem with the software Experience In Software is available to assistyou First check this help file for information on the part of the program you are having a problem withAlso take a look at the Web site for late-breaking technical support information wwwprojectkickstartcomsupporttechnical_supportcfm If you are a regustered user you can obtain support in the following ways

Web httpwwwprojectkickstartcomsupportemail_supportcfm E-mail supportprojectkickstartcom

Hours 900 am to 500 pm Pacific time Monday - Friday

To make the support process more efficient have the following information ready for the support staff

Provide your name phone number and email address

Describe the problem including any error messages

If reporting a potential bug describe what you did immediately before seeing the bug

Provide the Project KickStart version number and Build Date (Click Help on the menu bar and thenclick About Project KickStart)

Identify the version of Windows (Windows Vista etc) you are using

Notes

Our policy is to respond to support email within two business days If you have not received aresponse please double check that spam filters are blocking our messages to you If you maintain anincoming whitelist please allow all messages from the projectkickstartcom domain

Support is available in English only If you purchased a translated version please contact your localreseller for help in other languages

See Also

Reporting Technical Issues

-o-

21

copy Experience In Software Inc 1995 - 2006

Reporting Technical Issues

If Project KickStart 5 detects an error it will write a log of technical issues and then create a temporarymenu to the right of the Help menu which says Send Log to Technical Support You should immediatelyclick the menu and then click Yes to send the error log to us

Please fill in your email address so that we can get back to you with any questions about what caused theerror

Tip

If you have an Internet Security Program such as Norton Internet Security please allowPKS5Kickstartexe to communicate with the Internet to report the error

-o-

22

copy Experience In Software Inc 1995 - 2006

Register Project KickStart

To print this page click the Print button on the Help window toolbar

Register Project KickStart 5 for technical support upgrade information and software discounts You canregister by completing printing and then sending or faxing this form to Experience In Software You canalso register online at httpwwwprojectkickstartcomsupportregiscfm

Name _______________________________________________________

Title _______________________________________________________

Company _______________________________________________________

Address _______________________________________________________

CityStateZip ______________________________________________________

Country _______________________________________________________

Day Phone _______________________________________________________

Fax _______________________________________________________

E-mail _______________________________________________________

Purchased from __ Experience In Software __ Other ____________________

Number of people in company _ 1 to 25 _ 26 to 100 _ 101 to 1000 _ Over 1000

Which industry do you work in ______________________________________

Interested in a project management workshop for your company __ Yes __ No

Comments _______________________________________________________

_________________________________________________________________

_________________________________________________________________

Experience In Software 2029 Durant Ave Berkeley CA 94704

Send or FAX to (510) 644-3823

-o-

23

copy Experience In Software Inc 1995 - 2006

Planning Projects

Name Your Project

Before you start thinking about the tasks in your project yoursquoll want to give your project an appropriate titleIf you open an existing project you might want to edit or change the name of your project

To name your project1 In the Type a name for your project text box enter a name2 Click the Next button

Tips

You can enter up to 58 characters and more than one

Use short descriptive project names such as ldquoCompany Web Siterdquo

Avoid vague project names such as ldquoDatabase Projectrdquo or ldquoCDP-7rdquo especially if you plan to circulatereports to others

Enter your project title using uppercase letters if you want the title to stand out in reports

One way to reuse your projects is to open an existing project and then change its name in this stepAfter saving the project with a different name you can modify details to customize the project

See Also

Use the Planning Wizard

-o-

24

copy Experience In Software Inc 1995 - 2006

Phases - Step 1 of 2

After naming your project the next step in the Planning Wizard is to identify the major activities in yourproject Using phases helps organize tasks so that an obviously early task such as ldquoOrganize materialsrdquoappears before a later task such as ldquoReview final draftrdquo

To enter phases1 Type each phase one per line

OrClick the Phases Library button The Phases Library contains typical phases that many organizationsuse in the early middle and late stages of their projects Drag an entry from the Phases Library to thelist and then click the OK button to close the Phases Library

2 To insert a phase in the middle of the phases list click where you want to insert a new blank line andthen press the Insert keyTo edit the phase text double-click the phase

Tips

Start each phase name with an action verb as in ldquoBuild systemrdquo or ldquoWrite reportrdquo

Use actions that have clearly defined beginnings middles and ends For example you can scheduletasks like ldquoTest prototyperdquo more easily than tasks like ldquoPurchase high-quality partsrdquo

Note

Youll have the opportunity to edit phases later in the Tasks step For now continue planning thephases in your project

See Also

Use the Planning Wizard

Use a Library

Move Tasks within the Task List

-o-

25

copy Experience In Software Inc 1995 - 2006

Phases - Step 2 of 2

For each phase list all of the tasks that could be performed during that phase You can refine and organizethe tasks later in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each phase1 Type the tasks associated with the phase displayed in the Tasks for phase text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next phase in your project click the Next button If you prefer to work out oforder click the Tasks for phase list arrow and then click the phase you want

3 When you are finished entering tasks for the last phase in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

26

copy Experience In Software Inc 1995 - 2006

Goals - Step 1 of 3

Enter the goals for your project the objectives you hope to accomplish Then you can brainstorm anyadditional tasks that will help you meet these goals

To enter goals1 Type each goal one per line

OrThe Goals Library contains typical sample goals that you can customize Drag an entry from the GoalsLibrary to the list and then click the OK button to close the Goals Library

2 To insert a goal in the middle of the goals list click where you want to insert a new blank line and thenpress the Insert keyTo edit the goal text double-click the goal

3 Click the Next button

Tips

List goals that apply to the entire project such as Develop a high-quality system A goal such as Getthe contract signed applies only to an early phase

Write goals as actions you can measure For example Complete the project for $75000 or less ismore concrete and specific than Complete the project within budget Numbers make goal statementsreal

If youre not sure how to measure a goal use a range as in About 15 - 25 people will use the results ofthe project

See Also

Use the Planning Wizard

Use a Library

-o-

27

copy Experience In Software Inc 1995 - 2006

Goals - Step 2 of 3

For each goal list any new tasks needed to accomplish that goal You can refine and organize the taskslater in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each goal1 Type the tasks for accomplishing the goal displayed in the For the goal text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next goal in your project click the Next button If you prefer to work out of orderclick the For the goal list arrow and then click the goal you want

3 When you are finished entering tasks for the last goal in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

28

copy Experience In Software Inc 1995 - 2006

Goals - Step 3 of 3

After you identify new tasks for your project assign each new task to an appropriate phase

To assign new tasks to phases1 Click a task in the New tasks to achieve goals list (on the left)2 Click one or more phases in the Assign them to Phases list (on the right) to which the task belongs A

checkmark appears next to tasks youve assigned

If a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Note

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

29

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 1 of 2

Projects often have tasks in common The Similar Projects step makes it easy for you to borrow tasks fromother projects and add them to your current project

By default this step shows the Project KickStart (PRX) projects stored in the same folder as the currentproject including sample projects and those you already created

To select similar projects1 Review the projects in the list To sort the project names alphabetically click the Project Name header

Click the Project Name header again to sort the names in reverse order2 Click one or more projects in the list that contain tasks you want to use in the current project A

checkmark appears next to the projects you selected3 To list projects stored in a different folder on your system click the Browse button and then navigate to

the folder you want4 Click the Next button

If no projects seem related to your current project skip this step for now

Tips

The Similar Projects step becomes more helpful the more you use Project KickStart Every time yousave a project it becomes available for future use

Many projects share the same phases and tasks such as those for setting up a contract or purchasingequipment You can use Project KickStart to create these mini-projects or templates and then importtheir tasks into a new project during the Similar Projects step

-o-

30

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 2 of 2

After you select one or more projects containing tasks you might want to use assign those borrowed tasksto a phase in this project

To assign borrowed tasks to phases1 Click a task in the list on the left If a task includes subtasks click the plus icon to expand the list Click

the minus icon if you want to hide the subtasks To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more phases in the Assign tasks to phase(s) of your project list (on the right) to whichthe task belongs A checkmark appears next to tasks youve assigned

3 To assign one or more tasks to a new phase select the tasks click ltNew Phasegt in the Assign tasksto Phases of your project list and then type a name for the new phase

4 To select tasks from another project you selected as similar click the Tasks from Similar Projects listarrow click the project you want and then assign the tasks to phases

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also Edit Tasks

-o-

31

copy Experience In Software Inc 1995 - 2006

People - Step 1 of 3

Enter the names or descriptions of the people involved in your project Include key decision makers suchas executives or customers who must approve or consult with you about the project These are yourprojects resources In the next People step youll identify new tasks associated with these resources

To enter people1 Type each name or description one per line

OrIf you have stored information about people and other resources in the People Library click the PeopleLibrary button drag an entry from the library to the list and then click the OK button to close thePeople Library

2 To edit the people text double-click the name or description3 Click the Next button

Tips

Be consistent with the resource names in your projects For instance avoid using Richard in oneproject and Dick in another project when referring to the same person

Include names for people teams (such as Quality control team) departments (such as Manufacturing)companies (such as Acme Widgets Corp) or even equipment (such as wheat thrasher)

Note

Add people and other resource information to the People Library so that you can quickly drag resourcesfrom the library to any project You can even import people from your Outlook and ACT address books

See Also

Manage the People Library

Import ACT Contacts and Users to the People Library

-o-

32

copy Experience In Software Inc 1995 - 2006

People - Step 2 of 3

Now that you have defined the people needed to complete your project list any new tasks that eachresource might suggest or require

To enter new tasks for each person1 Type the new tasks associated with the person displayed in the Tasks For text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next person in your project click the Next button If you prefer to work out oforder click the Tasks For list arrow and then click the person you want

3 When you are finished entering new tasks for the last person in your project click the Next button tocontinue in the Planning Wizard

Tips

This step provides a good opportunity to get input from your resources directly and make sure theproject plan reflects the views of everyone on the team

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo Write the tasks roughly in the order that you will complete them You can reorganize the tasks later in

the Tasks step

Note

You assign people to tasks in the Assign Tasks and Schedule steps

See Also

Use a Library

Move Tasks within the Task List

Assign Tasks to People

-o-

33

copy Experience In Software Inc 1995 - 2006

People - Step 3 of 3

After you identify new tasks associated with the people in your project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by people list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

34

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 1 of 3

Every project has obstacles and risks that can affect its success List the major obstacles you face incompleting your project Then you can brainstorm any additional tasks that can help you overcome orminimize these problems

To enter obstacles1 Type each obstacle one per line

OrThe Obstacles Library contains typical sample obstacles that you can customize Drag an entry fromthe Obstacles Library to the list and then click the OK button to close the Obstacles Library

2 To insert an obstacle in the middle of the obstacles list click where you want to insert a new blank lineand then press the Insert key

3 To edit the obstacle text double-click the obstacle4 Click the Next button

Tips

Be creative when thinking of obstacles Highly imaginative obstacles can suggest realistic tasks Forexample Project manager kidnapped by aliens can lead to Project manager out of town forconference In Obstacles step 2 of 3 you can add the realistic activities as tasks You can delete theunrealistic obstacles later by returning to Obstacles step 1 of 3

Avoid listing too many obstacles even if they are realistic Hard core pessimists find it hard to getanything done

Edit and update the Obstacles Library so that you can quickly drag obstacles from the library to anyproject in your organization

See Also

Use a Library

-o-

35

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 2 of 3

After identifying the obstacles to completing your project determine how you can avoid these stumblingblocks List any new tasks you need to overcome or avoid each obstacle In this way you are developing acontingency plan for your project

To enter new tasks for each obstacle1 Type the new tasks associated with the obstacle displayed in the Obstacle text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next obstacle in your project click the Next button If you prefer to work outof order click the Obstacle list arrow and then click the obstacle you want

3 When you are finished entering new tasks for the last obstacle in your project click the Next button tocontinue in the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

You can reorganize the tasks and add notes later in the Tasks step

See Also

Use a Library

Move Tasks within the Task List

Add Task Notes and Attachments

-o-

36

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 3 of 3

After you identify new tasks for overcoming the obstacles to completing project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by obstacles list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

3 Click the Next button

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

37

copy Experience In Software Inc 1995 - 2006

Assigning People

Assign Tasks to People

After youve identified people working on your project you can assign tasks to each person or otherresource

To assign tasks to people1 Click a phase or task in the For each phase or tasks list (on the left)

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more people in the Assign some people list (on the right) who will perform the task Acheckmark appears next to tasks youve assigned

3 To assign a selected task to all of the people in your project click the All button4 To assign one or more tasks to a new person select the tasks click ltNew Persongt in the Assign

some people list and then type a name for the new person

To unassign a task

To unassign a task click the task and then click the highlighted person from which you want to removethe task You can assign that task to a different person if necessary You can also click the All buttonto remove a task from all of its assignments at the same time

Tip

Some users like to skip to the Tasks step before performing the Assign step That way they can edittheir list of tasks before assigning people and resources This helps them focus the project and givesthem a clearer idea of what must be done before committing resources

Notes

You can also assign tasks to people in the Tasks step and the Schedule step

You can assign tasks to non-personnel resources such as equipment (a CAD system or back hoe)facilities (a classroom or hotel) services (lab work or insurance) or materials (lumber or officesupplies) just as you assign tasks to people Click ltNew Persongt to add a new resource to the list

See Also

Remove People from a Task

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

38

copy Experience In Software Inc 1995 - 2006

Remove People from a Task

After assigning tasks you might need to remove people from a task or unassign them

To remove people from a task (unassigning)1 Click a phase or task in the For each phase or tasks list (on the left)

The people assigned to that phase or task are highlighted in the Assign some people list (on theright)

2 Click a highlighted person to remove or unassign that person from the taskWhen the person is no longer highlighted they are not assigned to the selected task

See Also

Assign Tasks to People

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

39

copy Experience In Software Inc 1995 - 2006

Add a New Person or Resource

If you realize that you want to assign some tasks to a person not included in the Assign some people listyou can add that person and assign tasks in the same step You can also add non-personnel resourcessuch as such as equipment (a CAD system or back hoe) facilities (a classroom or hotel) services (lab workor insurance) or materials (lumber or office supplies)

To add a new person or resource1 Select one or more phases or tasks in the For each phase or tasks list (on the left) 2 Click ltNew Persongt in the Assign some people list and then type a name for the new person or

resourceThis adds the new person or resource to the list and assigns the selected tasks to them

See Also

Assign Tasks to People

Remove People from a Task

Edit or Substitute People

Add or Change Task Assignments

-o-

40

copy Experience In Software Inc 1995 - 2006

Edit or Substitute People

If the people or resources in your project change you can replace them or edit their names anddescriptions

To edit or substitute people1 Click the People icon

You return to People step 1 of 32 In the list of people defined for the project double-click the person you want to edit or replace or click

the name and press F23 Edit the name or description of the person

When you return to the Assign step the name of the person appears as you changed it

See Also

Assign Tasks to People

Remove People from a Task

Add a New Person or Resource

Add or Change Task Assignments

-o-

41

copy Experience In Software Inc 1995 - 2006

Organizing the Project Plan

About Organizing Tasks

In the Tasks step you work with an outline of your project plan Here you can easily edit and reorganizetasks spell check and even add notes and attachmentsClick the following illustration to see tips for using this window

Edit the Task List to Consolidate and delete tasks Add subtasks Add or change task assignments Add follow-up notes to tasks Add or change attachments Review the order of the tasks in each phase and move tasks up or down so that they progress

sequentially Review task descriptions to make sure they are clear and that all the team members will understand

them Convert vague tasks such as reminders and open issues to task notes

Notes

Some users like to revise their Task List before they assign resources You can go to the Task List atany time while you are using Project KickStart

Each project created with Project KickStart can contain up to 1000 tasks

See Also

Change the Appearance of the Task List

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

Add Task Notes and Attachments

Add or Change Task Assignments

Add or Change Task Details

-o-

42

copy Experience In Software Inc 1995 - 2006

43

copy Experience In Software Inc 1995 - 2006

Change the Appearance of the Task List

You can change the appearance of the Task List so you can work with it more effectively

To add a column

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task ListBy default the Task List shows the Task Name Assignments and Notes columns You can also showCost and Done columns

To hide a column

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

To move a column

Drag a column heading to a new position in the Task List

To change the column width

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Show or Hide Tasks in the Task List

-o-

44

copy Experience In Software Inc 1995 - 2006

Show or Hide Tasks in the Task List

To hide tasks or subtasks

To hide the subtasks for a task click the minus icon next to the task

To hide all the tasks in the Task List and show only phases click all the minus icons next to thephases

To show tasks or subtasks

To show the subtasks for a task click the plus icon next to the task

To show the tasks for a phase click the plus icon next to the phase

See Also

Change the Appearance of the Task List

-o-

45

copy Experience In Software Inc 1995 - 2006

Move Tasks within the Task List

In the Tasks step you can reorganize the tasks in your project so that they better represent the work youand your team plan to do In particular you should review the order of the tasks in each phase and move tasks up and down so thattasks follow in a sequential order Use the Up and Down Arrow buttons to move the tasks

To reorder tasks1 Click a task or phase to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youmove must be next to each other

2 Click the Up Arrow button to move a task up one rowOrClick the Down Arrow button to move a task down one row

Note

When you move a bolded phase you move the phase and all of its tasks at the same time

See Also

Outdent and Indent Tasks

-o-

46

copy Experience In Software Inc 1995 - 2006

Outdent and Indent Tasks

Subtasks are smaller parts of tasks Use subtasks when you need to break tasks down into moremanageable parts In the Task List you can turn a task into a subtask by indenting it You can also add anew subtask to the Task ListIf your Task List contains subtasks you can turn a subtask into a task by outdenting itUse the Outdent and Indent buttons to promote (outdent) and demote (indent) tasks

To promote and demote tasks1 Click a phase task or subtask to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youpromote or demote must be next to each other

2 Click the Outdent button to promote the selected tasksOrClick the Indent button to demote the selected tasksYou can also right-click an item in the Task List and then click Outdent or Indent on the shortcut menu

Tips

When you promote (outdent) a task it becomes a phase and its subtasks become tasks When youpromote a subtask it becomes a task

When you demote (indent) a phase it becomes a task and its tasks become subtasks When youdemote a task it becomes a subtask

Notes

You can have up to 10 levels of subtasks in your project

Use Task Notes instead of subtasks for task comments or additions that are not actually work items

See Also

Move Tasks with the Task List

Add a Task or Subtask

-o-

47

copy Experience In Software Inc 1995 - 2006

Add a Task or Subtask

If you realize you want to add another task to the Task List use the Add Task button A subtask is a smaller part of a task Use subtasks when you need to break tasks down into moremanageable partsTo add a subtask use the Add Subtask button

To add a task1 Click a task and then click the Add Task button right-click a task and then click Add Task on the

shortcut menu or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskProject KickStart numbers the new task in the proper sequence

To add a subtask1 Click a task and then click the Add Subtask button right-click a task and then click Add Task on the

shortcut menu or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtask3 Project KickStart numbers the new subtask in the proper sequenceNote

To add a new phase click a phase and then click the Add Task button

See Also

Outdent and Indent Tasks

-o-

48

copy Experience In Software Inc 1995 - 2006

Edit Tasks

Edit tasks in the Task List to fine tune your project You can edit the names of the phases tasks andsubtasks delete tasks and cut copy and paste task information

To edit task names1 Click the phase task or subtask you want to edit and then press the F2 key2 Type to edit the text3 To undo an edit click the Undo button

To delete a task

Click the task you want to delete and then press the Delete key or click the Delete button Or

Right-click a task and then click Delete Row on the shortcut menu

To cut copy and paste tasks1 Select the tasks you want to cut or copy Use Shift-click or Ctrl-click to select more than one task

2 Click the Cut button (Ctrl-X) or click the Copy button (Ctrl-C )

3 Click where you want to insert the tasks and then click the Paste button (Ctrl-V)

Tip

If your project includes some of the same tasks repeated in different phases save time by copying rowsof tasks and pasting them to another phase

Notes

You can also edit task names using the Task Information dialog box To open this dialog boxdouble-click a task or click a task and then click the Edit Task Information button

If you delete a phase you also delete its tasks and subtasks If you delete a task you also delete itssubtasks Project KickStart warns you before deleting tasks or subtasks and gives you a chance tocancel the deletion

See Also

Add Task Notes and Attachments

Add or Change Task Assignments

-o-

49

copy Experience In Software Inc 1995 - 2006

Add Task Notes and Attachments

You might find that some of your tasks are actually more notes than tasks For example Remember tocheck Daves specifications might work better as a note than a task especially if it could take several daysto catch up with Dave but only a few minutes to review his specs By using notes you clarify your projectand increase your chances for success An attachment is a document graphic or any other type of file related to a task For example to a tasksuch as Review proposal you can attach the proposal document Or you can attach a hyperlink to a pageon a web site

To add a note or attachment to a task1 Double-click the Notes column next to the task The Task Information dialog box opens to the Notes

and Attachments tab2 In the Enter a Note box type in or edit the task note (Press Enter to insert line break)3 To attach a file click the Add Files button In the Select File to Attach dialog box navigate to the file

you want and then click the Open button The filename appears in the Add Attachments box with apaperclip icon

4 To insert a hyperlink click the Add URL button In the Insert Hyperlink dialog box type in the URL youwould like to link to The URL appears in the Add Attachments box with a paperclip icon

5 Click the OK button

To open or remove an attachment1 Open the Notes and Attachments tab in the Task Information dialog box2 To open an attachment double-click the filename in the Add Attachments box3 To delete an attachment click the attachment in the Add Attachments box and then click the Remove

button

To change a task into a task note1 Copy (Ctrl-C) the text of the task you want to change into a note2 Double-click the task to which you want to add the note3 In the Task Information dialog box click the Notes and Attachments tab and add paste the text in the

Enter a Note box Close the Task Information dialog box4 In the Task Name column delete the original task that how appears as a note for a different task

Tips

Use notes to keep track of the operational details of a project the little nagging details that are criticalto success

Although the Task List provides plenty of room for notes it is best to keep your notes concise

Some tasks might benefit from instructional notes those that explain what to do in a task or how tosuccessfully complete a task

You can also include a hyperlink in a note by typing httpxxx (where xxx is an e-mail or Web address)In Outlook Word Excel or your browser the hyperlink will be active You can click the link to godirectly to that site or to send an e-mail to that address

Note

You can also open the Notes and Attachments tab in the Task Information dialog box by clicking atask and then clicking the Edit Notes and Attachments button or by double-clicking a task to openthe Task Information dialog box and then clicking the Notes and Attachments tab

See Also

Edit Tasks

Add or Change Task Assignments

Change Task Details in the Gantt chart

50

copy Experience In Software Inc 1995 - 2006

-o-

51

copy Experience In Software Inc 1995 - 2006

Add or Change Task Assignments

The Assignments column in the Task List shows the people and other resources assigned to each task

To add or change a task assignment1 Double-click the Assignments column next to the task The Task Information dialog box opens to the

Assignments tabThe Assignments tab lists all of the people and resources in your project If this task is already assignedto people they are highlighted on the Assignments tab

2 To assign this task to another person or resource click the resource name in the Assignments list3 To remove (unassign) this task from a person or resource click a highlighted name in the Assignments

list4 To add a person and assign the task at the same time click ltNew Persongt in the Assignments list

and then enter the name of the new person5 Click the OK button

Note You can also open the Task Information dialog box by clicking a task and then clicking the Edit Task

Information button to or by double-clicking a task

-o-

52

copy Experience In Software Inc 1995 - 2006

Add or Change Task Details

Besides task names notes and assignments you can include cost and done details about tasks In theSchedule step you can also include start and finish dates and durations

To add task details

1 Click a task and then click the Edit Task Information button or double-click the task you wantThe Task Information dialog box opens

2 Enter Cost or Done informationCost Enter the cost associated with this task For example you could enter $150 as the cost for a tasknamed Purchase photo CD Done Click the list arrow to select 0 25 50 75 or 100 or enter the percentage you want such as33

3 Click the OK button

To show or hide task details

Right-click a column heading to open a shortcut menu and then click Cost or Done In the shortcutmenu a checkmark appears next to columns that are displayed in the Task List

To edit task details

Open the Task Information dialog box (click a task and then click the Edit Task Information button or double-click the task you want)

Or

Double-click the Cost or the Done entry to update these details directly in the Task List

Notes

The Cost amount appears with the currency symbol set for your system (in the Regional and LanguageOptions dialog box of the Windows Control Panel)

Project KickStart calculates the running totals for the tasks within a phase and displays this total in theCost column for the phase When you create and print Task reports the total costs for the entire projectappear at the end of the Cost column

See Also

Edit Tasks

Print Task Reports

-o-

53

copy Experience In Software Inc 1995 - 2006

Check Spelling

Spell check your tasks and notes before you print reports or export to other software

To check the spelling of tasks and notes

Click the Check Spelling button on the Project KickStart toolbarOr

Click Tools on the menu bar and then click Spelling

Notes

Spell checking updates entries on the Task List and the Gantt chart (the Schedule step) It can alsocheck the spelling of intermediate entries such as goals and tasks to accomplish goals if you spellcheck during those steps

Spell checking does not check the names of people on the People List or the contents of the PeopleLibrary

-o-

54

copy Experience In Software Inc 1995 - 2006

Scheduling Tasks in the Gantt Chart

55

copy Experience In Software Inc 1995 - 2006

Scheduling Overview

About Scheduling Tasks

In the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the other

You work with the Gantt chart using the familiar Task Data view in the left pane or the graphical Chart viewin the right pane To adjust the schedule to fit your project set the project start date in the toolbar moveand resize the taskbars in the Chart view or change the start and finish dates or durations of individualtasks in the Task Data view

Click the following illustration to see general tips for using the Gantt chart See About the Gantt Chart formore details

In the Schedule step you can

Change a start date for the project Set start and finish dates or durations for tasks Change the timescale of the schedule Change the working schedule to specify which days are nonworking days such as weekends and

holidays Fine-tune the organization of the phases tasks and subtasks Color-code tasks to identify assignments critical deadlines or other information at a glance Insert milestones to indicate events that mark a moment in time such as the approval of a design Review and edit task details including task name assignments notes and attachments Hide or show task data columns in the left pane Export project data to other software applications

Tip

56

copy Experience In Software Inc 1995 - 2006

To save time you can reuse projects such as one for a trade show and create an updated scheduleby changing the project start date in the Schedule step

See Also

About the Gantt Chart

Understand Task Data View

Understand Chart View

-o-

57

copy Experience In Software Inc 1995 - 2006

About the Gantt Chart

The Gantt chart provides two views of your project schedule The Task Data view in the left pane lists thesame task information as in the Tasks step but now includes durations and start and finish dates TheChart view in the right pane displays taskbars and symbols to represent the same information You canchange the schedule information by working directly in the Task Data view and Chart view or by using theGantt Chart toolbarClick the following illustration to see general tips for using this window

-o-

58

copy Experience In Software Inc 1995 - 2006

Autolink tasks (Pro Users)

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatProject KickStart Pro does not assume that you want to link all of the tasks in a serial manner (one after theother) when you get to the Gantt chart Indeed many users want that behavior and many do notTo accomodate both types of users you can set whether you want the program to Autolink tasks In theTools menu select Autolink tasks Thereafter in all your projects when you get to the Gantt chart for thefirst time the tasks will be linked in a serial mannor

-o-

59

copy Experience In Software Inc 1995 - 2006

About Linking Tasks

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatWhen you link tasks the Gantt chart shows additional information about the tasks Click the followingillustration to see general tips for using linked tasks

Task Data view Chart view Description

Predecessor tasksA predecessor task is onethat you must completebefore you can start thenext task For exampleTask 2 - Prepare soil isthe predecessor to Task3 - Plant shrubs becauseyou need to prepare thesoil before you can plantthe shrubs

Successor tasksWhen you finish onelinked task you can moveonto the next onemdashthesuccessor task Forexample the successorfor Task 2 ndash Prepare soilis Task 3 ndash Plant shrubsand the successor forTask 3 is Task 4 ndash MulchLink linesThe first task isscheduled for one dayand the second one forthe next day In additionthe link line and arrowshow that the first taskmust end before thesecond one can start

These linked tasks arescheduled for the sametime

60

copy Experience In Software Inc 1995 - 2006

These tasks which aredependent on earliertasks and the last twotasks are also scheduledfor the same time

See Also

About the Gantt Chart

Autolink tasks

Make tasks overlap

-o-

-o-

61

copy Experience In Software Inc 1995 - 2006

Change the Display of the Schedule

You can change the onscreen appearance of the schedule so you can work with it more effectively Thefollowing illustration shows the Schedule window with the Steps bar closed and only the task number taskname and duration displayed in the Task Data view This provides more room to display the Gantt chart

To show or hide the Step bar or Project KickStart toolbar

Click View on the menu bar and then click Steps Bar to show or hide the vertical Steps bar on the leftof the Project KickStart window

Click View on the menu bar and then click Tool Bar to show or hide the Project KickStart toolbarwhich appears just below the menu bar In the View menu a checkmark appears next to the items displayed in the Project KickStart window

To display more or less of the Task Data view or Chart view

Drag the splitter bar between the Task Data view and the Chart view

To change the timescale in the chart

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years

To add a column to the Task Data view

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task Data viewBy default the Task Data view shows the Info Task Name Days Start and Finish columns Youcan also show Done Cost and Assignments columns

To hide a column in the Task Data view

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

62

copy Experience In Software Inc 1995 - 2006

To change the column width in the Task Data view

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Understand Task Data View

Understand Chart View

-o-

63

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

-o-

64

copy Experience In Software Inc 1995 - 2006

65

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Some features in this topic are available only in Project KickStart Professional

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view In Project KickStart Professional you also use the Gantt chart toolbar to linkand unlink tasks

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysLink Tasks (Pro Users)Link the selected tasksUnlink Tasks (Pro Users)Unlink the selected tasksChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

See Also

Use the Gantt Chart Toolbar

-o-

66

copy Experience In Software Inc 1995 - 2006

Understand Task Data View

The following illustration shows all the columns of information you can display in Task Data view

The Task data columns are the same as in the Tasks step but also include date information

Row number

Info Shows an icon if a note attachment or both are associated with the task Double-click anicon to view or edit the associated information

Task Name Name of the phases tasks and subtasks Double-click a task name to edit it directly

Days The amount of time it takes to complete the task If you change the number of days for a taskProject KickStart changes the Finish date accordingly

Start Date this task starts Double-click a Start date and then click the list arrow to open a calendar andselect a different date This also changes the Finish date

Finish Date this task ends Double-click a Finish date and then click the list arrow to open a calendar andselect a different date This changes the task duration shown in the Days column

Done Percentage of the phase task or subtask completed Show progress for any task by entering apercent of up to 100

$ Cost Cost for each task summed in the appropriate phase row Reports include total costs for theproject when you select the Cost column in the Create and Print Task Reports dialog box or the Createand Print Gantt Chart Report dialog box The Cost appears with the currency symbol set for your system(in the Regional and Language Options dialog box of the Windows Control Panel)

Assignments People and other resources assigned to the task Double-click an assignment to open theTask Information dialog box to the Assignments tab where you can add and change assignments

Tip

A task with a duration of zero (0) days is a milestone See Create a Milestone for more information

Notes

By default Task Data view displays all the columns the Info Task Name Days Start and Finish Done Cost and Assignments columns Some of these columns might be hidden by the Gantt chartview To hide columns right-click a column heading to open a shortcut menu and then click the columnyou want to hide In the shortcut menu no checkmark appears next to columns that are hidden

To change the width of a column drag a splitter bar in the column heading row or double-click a splitterbar to have the column accommodate its longest entry

As in the Tasks step expand phases and tasks by clicking the plus icon and collapse phases andtasks by clicking the minus icon

See Also

67

copy Experience In Software Inc 1995 - 2006

Understand Chart View

Change Task Dates

-o-

68

copy Experience In Software Inc 1995 - 2006

Additional Features in Task Data View

These features are available only in Project KickStart Professional

In Project KickStart Pro you can view two columns of information in addition to the nine columns availablein the Project KickStart Standard These two additional columns are labeled Pred (for Predecessor) andSucc (for Successor) The following illustration shows a typical Task Data view with these additionalcolumns

Besides the nine columns of information shown in Task Data view in Project KickStart Standard you canalso show the following information in the Professional version

Pred Indicates which task is the predecessor to the current task Double-click a task number in the Predcolumn to change it

Succ Indicates which task is the successor to the current task Double-click a task number in the Succcolumn to change it

Notes

When you link tasks Project KickStart assigns predecessors and successors according to their order inthe Task Data view

When you move a linked task in the Task Data view the predecessor and successor do not changeFor example in the above illustration if you move Task 3 ndash Plan design so it becomes Task 2 itspredecessor remains Land survey and its successor remains Engineering You can change these bydouble-clicking the task number in the Pred or Succ column and then entering a new number

See Also

Understand Task Data View

-o-

69

copy Experience In Software Inc 1995 - 2006

Understand Chart View

The following illustration shows a daily schedule in Chart view Point to the illustration to display text thatdefines the chart elements

Summary bar Summarizes the tasks below it and extends from the earliest start date(where the first triangle in the summary bar appears) to the latest finish date (where the last triangleappears) If a phase has tasks the summary bar appears in the phase row to summarize the tasks If atask has subtasks the summary bar appears in the task row to summarize the subtasks

To reschedule a phase and all of its tasks (or a task and all of its subtasks) click the summary bar and dragit to the left or right until it spans your desired set of dates This changes the earliest start date and latestfinish date in that phase and keeps the same duration And all the tasks move with the change of thephase

Taskbar Shows the length and scheduled dates for a task To change the duration of a taskresize the taskbar click the taskbar and then drag its left edge to schedule a different start date or drag itsright edge to schedule a different finish date

To reschedule a task without changing the duration drag the taskbar to a different date in the chart

Taskbar with percent done If you enter a Done amount in the Task Data view a progress barin the taskbar indicates the amount of the task completed

Red vertical line Indicates todays date

Milestone Indicates a task with a zero duration Milestones mark an event that must be reflected inyour project plan such as the approval of a design or an assembly line startup You can drag the left edgeof a milestone icon to stretch it into a taskbar The milestone becomes a task with a start and finish date

Notes

Because a summary bar summarizes the tasks below it you cannot resize a summary bar

To scroll the schedule use the vertical and horizontal scroll bars or the green drag bar at the top of theChart view

The shaded days in the Chart view indicate nonworking days To set which days are working andnonworking see Specify Working Days

70

copy Experience In Software Inc 1995 - 2006

-o-

71

copy Experience In Software Inc 1995 - 2006

Additional Tools in Chart View

These features are available only in Project KickStart Professional

If you use Project KickStart Pro the Chart view displays lines and arrows to show linked tasks The linklines and arrows show the relationships dependencies between one linked task and another

Besides the summary bar taskbar and other information provided in Project KickStart Standard Chart viewin the Professional version also provides the following information

The first task is scheduled for one day and the second one for the next day In addition the link line andarrow show that the first task must end before the second one can start

These linked tasks are scheduled for the same time However the first task must end before the secondone can start

The first two tasks are scheduled for the same time and must be completed before the third task can start

These linked tasks are scheduled for the same time However the second task must end before the firstone can start

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

Understand Chart View

-o-

72

copy Experience In Software Inc 1995 - 2006

73

copy Experience In Software Inc 1995 - 2006

Change Task Dates

You can revise a project schedule by changing task dates in the Task Data view or the Chart view You canalso reschedule an entire project by changing the projects start date

To change the project start date1 Click the Project Start list arrow to open a calendar

The calendar highlights the selected date and outlines todays date2 Find the date you want using the left and right scroll arrows to view a different month and then click the

date

To change task dates in Task Data view1 Double-click the Start or Finish date for a task

2 Then edit the date (you can edit the day month or year) OrClick the list arrow to open a calendarThe calendar highlights the selected date and outlines todays date

3 Find the date you want using the left and right scroll arrows to view a different month and then click thedateProject KickStart changes the Start and Finish dates according to your selection updates the durationof the task in the Days column and adjusts the taskbar in the Chart view

To change task dates by changing the duration in Task Data view

Double-click the Days column for a task and then enter the number of days it will take to complete thetaskProject KickStart changes the Finish date of the task and adjusts the taskbar in the Chart view

To change task dates in Chart view

Resize a taskbar click the taskbar and then drag its left edge to schedule a different start date or dragits right edge to schedule a different finish dateProject KickStart updates the summary bar in Chart view and the task dates and duration in the TaskData view

To reschedule a task without changing the duration drag the taskbar to a different date You can alsodrag a summary bar to reschedule a phase and all of its tasks (or a task and all of its subtasks) so itspans a different set of datesProject KickStart updates the task dates and duration as necessary in the Task Data view

To change task dates in the Task Information dialog box1 Open the Task Information dialog box (Right-click a task and then click Task Information or click a

task and then click the Edit Task Information button )2 Click the General tab3 In the Dates section change the following information as necessary

Start Click the Start list arrow to open a calendar and then click the appropriate start dateFinish Click the Finish list arrow to open a calendar and then click the appropriate finish dateDays Enter a number or click the spin arrows to set the task durationMilestone Select the Milestone check box if you want this task to be a milestone (A milestone is atask with a zero duration and marks an event such as the approval of a design)

Notes

You cannot delete the Start or Finish date of a task If you want to specify that a task has no durationconvert it to a milestone

When working with a calendar to schedule a start or finish date click the Today date text (where date

74

copy Experience In Software Inc 1995 - 2006

is todays date) to select todays date

See Also

Understand Task Data View

Understand Chart View

Create a Milestone

-o-

75

copy Experience In Software Inc 1995 - 2006

Phase Dates Cannot Be Edited

You cannot change the bold phase dates in the Task Data view of the Gantt chart They are a summary ofthe task dates for a particular phase and are view only You can revise phase dates by changing task dateswithin the phase

To change phase dates in Chart view

You cannot directly resize a summary bar You can extend or move the blue task barswithin a phase on the chart and Project KickStart updates the summary bar

To reschedule a phase on the chart drag the summary bar to a new date and all of its tasks (or a taskand all of its subtasks) will move with it

-o-

76

copy Experience In Software Inc 1995 - 2006

Quick Tour of Working with Linked Tasks

This feature is available only in Project KickStart ProfessionalIn the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the otherIn addition Project KickStart Pro links the tasks for you so when you open the Gantt chart you see a linkedwaterfall similar to the one shown below Besides providing a schedule that starts in a cascade with eachtask lasting one day each task is linked to the next task

You work with the Gantt chart either using the Task Data view in the left pane or the graphical Chart view inthe right pane To adjust the schedule to fit your project set the project start date in the toolbar move andresize the taskbars in the Chart view or change the start and finish dates or durations of individual tasks inthe Task Data view See About Scheduling Tasks for detailsNext fine-tune the dependencies in your project by you can linking and unlinking tasks changing theirpredecessors and successors and setting lead times For example if one task is not dependent onanother you can unlink the tasks If another task canrsquot start until two other tasks are finished you can add apredecessor to that task in which case the two tasks will be linked

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

To fine-tune the linked tasks To change the scheduled start and end dates of linked tasks move and resize taskbars in the Chart

view or change the number of days or the Start date in the Task Data view To display predecessor and successor information in the Task Data view right-click any column

heading and then click Pred or Succ To change the predecessor for a task double-click the number in the Pred column for the task and

then enter the number of a different task To change the successor for a task double-click the number in the Succ column for the task and then

77

copy Experience In Software Inc 1995 - 2006

enter the number of a different task To add another predecessor or successor to a task click in the appropriate column for the task and

then enter the number of another task To change the details of a linked task open its Task Information dialog box To do so right-click the

task and then click Task Information on the shortcut menu or click a task and then click the Edit TaskInformation button See Change Details for Linked Tasks

In the Task Information dialog you can also specify the predecessor(s) of a task and lead time(s) of thetasks

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

About Scheduling Tasks

About Linking Tasks (Pro Users)

Use the Gantt Chart Toolbar (Pro Users)

Manage Changes in Your Schedule (Pro Users)

-o-

-o-

78

copy Experience In Software Inc 1995 - 2006

Link and Unlink Tasks

These features are available only in Project KickStart Professional

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

See Also

About Linking Tasks

Quick Tour of Working with Linked Tasks

-o-

79

copy Experience In Software Inc 1995 - 2006

Create a Milestone

A milestone Indicates a task with a zero duration Milestones mark an event that must be reflected in yourproject plan such as the approval of a design or an assembly line startup

To create a milestone in the Task Data view

Double-click the Days number for a task and then enter 0 (zero)Or

Open the Task Information dialog box click the General tab and then click to insert a checkmark inthe Milestone check box

In the Chart view Project KickStart changes the taskbar to a milestone icon To create a milestone in Chart view

Click a taskbar and then drag to shrink the taskbar to a milestone icon In the Task Data view Project KickStart changes the Days for this task to 0 (zero)

Notes

To change a milestone into a task you change its duration or start and finish dates See Change TaskDates for instructions

To move a milestone in Chart view click the milestone icon on the upper left corner of the milestoneicon With the left mouse down move the icon to another date and release the mouse

To move a milestone in the Task Data view change the start date or the finish date and the milestonewill move

-o-

80

copy Experience In Software Inc 1995 - 2006

Change Task Details

You can use the Task Information dialog box to change the following task details in Task Data view

Task properties including the task name cost for completing the task and the percent completed

Dates including the start and finish dates duration and whether to convert the task to a milestone

Assignments

Notes and attachmentsYou can also edit the task name days dates costs and Done directly by clicking items in the task datacolumns

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button 2 Click the appropriate tab and then change the task details

General tab Change the task name and enter or change the cost associated with the task To changethe amount of the task completed click the Done list arrow and then select a value or type a value inthe Done text box Enter or change date information as described in Change Task Dates Assignments tab People assigned to this task are highlighted in the list To assign this task to anotherperson or resource click the name in the Assignments list To remove (unassign) this task from aperson or resource click a highlighted name in the Assignments list See Add or Change TaskAssignments for more detailsNotes and Attachments tab Type or edit a task note (Press Enter for a line break) To add anattachment click the Add button In the Select File to Attach dialog box navigate to the file you wantand then click the Open button The filename appears with a paper clip icon See Add Task Notes andAttachments for more details

To change task details directly in Task Data view

To modify the task name press F2 or double-click a task and then edit or replace the text

To change date information see Change Task Dates

To change the amount of the task completed double-click in the Done column and then enter a newvalue

To change the cost associated with the task double-click in the Cost column and then enter a newvalue

Notes

When you enter costs for tasks the total appears in the phase row for those tasks Reports include thetotal costs of all tasks in the project when you select the Cost column in the Create and Print TaskReports dialog box or the Create and Print Gantt Chart Report dialog box

You cannot change the cost of a phase because it represents the total costs for the tasks in that phaseInstead change the costs associated with the tasks in the phase

When you enter a Done for a task the corresponding taskbar in the Chart view includes a blackprogress bar

-o-

81

copy Experience In Software Inc 1995 - 2006

Change Details for Linked Tasks

This feature is available only in Project KickStart ProfessionalIf you are using Project KickStart Pro you can use the Task Information dialog box to change the followingtask details

Predecessor for a linked task

Lead time for a linked task

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button

2 Click the Predecessors tab and then change the task details about predecessors and lead timePredecessors tab The Task Properties section shows the name of the selected task which you canchange The Predecessor (Finish-to-Start) section shows the tasks that are predecessors to theselected task A predecessor task must be finished before you start the current task You can change the ID name or lead time of the predecessor task Also you can also add additionalother predecessorsThe lead time is the amount of time you need to wait after finishing the predecessor task before so youcan start the current task Lead time can be positive or negative

Note

In some programs the is time shift is called ldquolag timerdquo But we think that the term ldquolead timerdquo is moreaccurate and descriptive since itrsquos the amount of time you want to allow before you start a task

See Also

Change Task Details

82

copy Experience In Software Inc 1995 - 2006

-o-

-o-

83

copy Experience In Software Inc 1995 - 2006

Reorganize Tasks in Task Data View

Although your project should be fairly well organized by the time you start the Schedule step you canfine-tune the organization in the Task Data view using the same techniques you use in the Tasks stepTo reorder tasks

Right-click a task and then click Move Task Up or Move Task Down on the shortcut menu Or

Click a task or phase to select it and then click the Up Arrow button or the Down Arrow button on theGantt chart toolbar

To promote and demote tasks

Right-click a task and then click Outdent or Indent on the shortcut menu Or

Click a phase task or subtask to select it and then click the Outdent button or the Indent button onthe Gantt chart toolbar

To add a task1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Task button on the Gantt chart toolbar or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskTo add a subtask1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Subtask button on the Gantt chart toolbar or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtaskTo delete a task

Right-click a task and then click Delete Row on the shortcut menuOr

Click the task you want to delete and then click the Delete button

To delete a row click the Task row number and press the Delete button

See Also

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

-o-

84

copy Experience In Software Inc 1995 - 2006

Change the Timescale of the Schedule

You can display the Gantt chart schedule in the Chart view using days weeks months quarters or yearsas the timescale Changing from days to weeks for example displays a longer period of time but lessdetail

Days timescale Weeks timescale

To change the timescale in the Chart view

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years Youcan also change the timescale by clicking Timescale on the menu bar and then clicking the option youwant

Notes

When you print a Gantt chart your current timescale is used by default However you can change it inthe Print Options dialog For example even though you were viewing your Gantt chart by weeks youcan choose to print the Gantt chart by months

If your mouse comes with a wheel you can adjust Project KickStarts timescale by rolling the wheelforward or backward The Timescale list box must be selected first

-o-

85

copy Experience In Software Inc 1995 - 2006

Specify Working Days

You can select which days are working days and which days are nonworking days for scheduling purposesBy default Monday - Friday are working days and Saturday and Sunday are nonworking days You can addto and change these settings to specify holidays for example

To set working and nonworking days

1 Click the Change Working Schedule button on the Gantt chart toolbar The Change Working Schedule for this Project dialog box opens Nonworking days are shaded in grayWorking days are unshaded

2 To change a single date (from working to nonworking or from nonworking to working) click the date3 To change one day of the week for the entire project such as all Fridays double-click any Friday4 To display schedules for other months click the left and right arrows5 Click OK

Note

Project KickStart maintains separate calendars for each project

If you typically work weekends create a simple template with weekends displayed as Working daysSave as your starter template Use the starter template when you start a new project and then save theproject with a different name Weekends will be displayed as Working days in your projects

-o-

86

copy Experience In Software Inc 1995 - 2006

Change the Color of Taskbars

You can change the color of the taskbars in the Chart view to call attention to particular tasks For exampleyou can change the colors of all tasks in a particular phase resource or deadline to make them stand outin a report

To change the color of a taskbar1 Right-click a taskbar and then click Color on the shortcut menu or click a taskbar and then click the

Color button on the Gantt chart toolbar The Color dialog box opens

2 Click the color you want to assign to the taskbarTips

Avoid changing the taskbar color to black because it obscures the Done progress bar (The Doneprogress bar is a black bar displayed within a taskbar)

Also avoid changing the taskbar color to white because it will not appear in the white rows of the Chartview

-o-

87

copy Experience In Software Inc 1995 - 2006

Make Tasks Overlap

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro the schedule starts in a cascade with each task lasting one day and each tasklinked to the following taskHowever it is very unlikely that your entire schedule matches such a cascade so you can adjust theschedule Start by estimating the duration of tasksmdashthe number of days that each task will take Generallyit is best to estimate how many days will elapse before the task is done You might also want some tasks to occur at the same time To do so you can overlap the tasks To make tasks overlap like this

You can do this in three ways Set the same predecessor for both tasks

Or Set the second task as the successor of the first task and then then move the second task into a

position when it starts on the same day as the first taskOr

Set the second task as the successor of the first task and then assign a lead time of ndash3 days (the number of days scheduled for the task)

To make tasks overlap like this

Set the second task as the predecessor of the first task and then assign a lead time of ndash2 days(one less than the number of days scheduled for the task)

-o-

88

copy Experience In Software Inc 1995 - 2006

Manage Changes in Your Schedule

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro when you schedule with dependencies you can adapt to changes on the fly andcreate what-if scenarios to forecast how one change affects the overall project schedule A commonscenario is dealing with delays You can reschedule an entire project or only selected tasks When you doProject KickStart Pro updates the schedule for you

To delay an entire project Click in the Project Start text box and then edit the date to match your new start date (You can edit

the day month or year)Or

1 Click the Project Start list arrow to display the calendar The calendar highlights the selected date andoutlines todays date

2 Find the date you want using the left and right scroll arrows to view a different month and then click thedate Project KickStart changes the Start and Finish dates for all tasks according to your selection

To delay a task In Task Data view double-click the Days column for the task and then edit the number of days it will

take to complete the taskProject KickStart changes the Finish date of the task adjusts the taskbar in the Chart view andchanges the Start and Finish dates for all tasks linked to this taskOr

In Chart view resize a taskbar by clicking the taskbar and then dragging its left edge to schedule adifferent start date or dragging its right edge to schedule a different finish date Project KickStart updates the summary bar in Chart view the task dates and duration in the Task Dataview and reschedules all tasks linked to this task

To reschedule a task without changing the duration in Chart view drag the taskbar to a different date Project KickStart updates the task dates and duration as necessary in the Task Data view andreschedules all tasks linked to this task

Note

Project KickStart Pro does not include a critical path

-o-

89

copy Experience In Software Inc 1995 - 2006

Managing Libraries

Use a Library

Project KickStart has five libraries that contain lists of useful phases tasks goals people and obstaclesAll libraries expect the People Library contain sample entries that you can use in your projects Yougenerally build your own People Library from the resources that are available to you

To use a library1 In the Phases Tasks Goals People or Obstacles step of the Planning Wizard click the Library button

to open the appropriate library2 Select one or more items in a library and then drag them to your list3 Close the Library window

Tips

Feel free to add (or delete) items to the libraries to make them richer and more pertinent to yourprojects

Keeping libraries small makes them easier to use

Widen the library window to see the full text of long entries

Note

After adding a library entry to a list you can double-click the entry to edit it

See Also

Manage a Library

-o-

90

copy Experience In Software Inc 1995 - 2006

Manage a Library

Customize the libraries by adding and changing entries and reorganizing them so you can use the librariesefficiently The Phases Tasks Goals People and Obstacles Libraries include a single column ofinformation while the People Library provides additional columns (See Manage the People Library)

To edit a library1 Open the library by clicking the appropriate Library button2 To edit an entry double-click it

3 To add an entry to the library press Insert or click the Add a row button You can also select oneor more items in the list and then drag them to the library

4 To delete an entry select the entry and then press Delete or click the Delete a row button 5 To move an item up or down select the item and then click the Up Arrow or the Down Arrow button

6 Click the OK button to save your changes and close the Library windowTips

Widen the Library window to add a long entry

Libraries can serve as ldquoKnowledge Librariesrdquo By including typical company-specific terms in yourLibraries you create a quick reference for yourself and colleagues now and in the future To do so adda new line in the Library enter the name of your company (or department) as a heading in capitalletters and then list your personal terms under the heading

If you use Project KickStart on more than one computer such as at home and work you can transportchanges you make in your Libraries from one computer to another The data in all the Libraries isstored in one file pks5libxdat so you can copy that file on one computer and paste it into the ProjectKickStart 5 folder on the other computer

Keeping Libraries small makes them easier to use Project KickStarts Libraries are fairly rich out of thebox If some of the terms don rsquot apply to your type projects delete them

See Also

Manage the People Library

-o-

91

copy Experience In Software Inc 1995 - 2006

Manage the People Library

The People Library is like the other libraries but with a few important extra features

You can store contact data such as Company Email Phone and Job Title

You can import names from ACT or from Outlook if you use either of those programsTo use the People Library1 In the People step of the Planning Wizard click the People Library button2 Select one or more names in the People Library and then drag them to your list (This adds only the

names of people not their contact data) If the People Library contains company names but not contactnames you can drag the company name to your list

3 Close the Library windowTo organize the People Library

To show or hide a column right-click a column heading to open a shortcut menu and then click acolumn name In the shortcut menu a checkmark appears next to columns that are displayed in thePeople Library

To sort the people in the People Library click a column heading For example click the Name columnheading to sort the people alphabetically by name To reverse the sort click the column heading again

To move a person up or down select the person and then click the Up Arrow or the Down Arrowbutton

Click the OK button to save your changes and close the People LibraryTo edit the People Library

To edit a persons name and contact data double-click the entry

To add a person to the People Library click the first blank row press Insert or click the Add a rowbutton Then type to enter the persons name and contact information You can also select one ormore items in the list and then drag them to the People Library

To delete an entry select the entry and then press Delete or click the Delete a row button

Click the OK button to save your changes and close the People LibraryTips

Use the People Library to store names for people teams (such as Quality control team) departments(such as Manufacturing) companies (such as Acme Widgets Corp) or even equipment (such as wheatthrasher)

Widen the People Library window to add a long entry

Resize the columns by dragging or double-clicking a splitter barNotes

After adding a person or resource to your list you can double-click the name to edit it

You can import contact information stored in an Outlook or ACT (version 6 7 or later) address book toyour People Library

See Also

Import ACT Contacts and Users to the People Library

Import Outlook Contacts to the People Library

-o-

92

copy Experience In Software Inc 1995 - 2006

Import ACT Contacts and Users to the People Library

If you use ACT 7 or later (200520062007) or if you use ACT 6 you can import contacts and users to thePeople Library This speeds up your work by letting you use ACT information in your Project KickStartplans If you export a plan to ACT 7 or later it recognizes the people and other resources you entered inProject KickStart

To import ACT contacts and users1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click ACT 7 or later or ACT 6 Click the Import button3 Click the Select ACT Database button and select the ACT 7 or later database (pad) containing the

people information you want to import The ACT 7 and later databases are usually stored in MyDocumentsACTACT for Win 7Databases (If you use ACT 6 your data is stored in a dbf database) If you select a multi-user ACT database you must enter your user name and password for the ACTdatabase

4 In the Import to People Library dialog box the names of Contacts and Users are listed on the left Clickthe Users tab select one or more users and then click Add to move the user names to the Import listClick the Contacts tab to select contact names the same way Click the Add All button to select allusers or contacts for import Note You can sort the contacts alphabetically by name or by company name by clicking theappropriate column heading

5 Click the Import button to add the names and related information from the selected ACT database tothe People Library

Notes

Importing contacts and users to the People Library does not remove them from the ACT database

If you try to import the same ACT contact or user twice it appears only once in the People Library

-o-

93

copy Experience In Software Inc 1995 - 2006

94

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts to the People Library

If you use Microsoft Outlook to maintain your contacts you can import selected contacts to the PeopleLibrary ThisThis speeds up your work by letting you use Outlook information in your Project KickStartplans If you export a plan to Outlook it recognizes the people and other resources you entered in ProjectKickStart

To import Outlook contacts1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click Outlook Click the Import buttonA dialog box opens informing you that Project KickStart is trying to access your Outlook data

3 Allow access for 1 minute and then click the Yes button4 If Outlook asks you to choose your profile please do so5 The Import to People Library dialog box opens listing Outlook Contacts on the left Select one or more

contacts and then click Add to move the contact names to the Import list Click the Add All button toselect all contacts for import

6 Click the Import button to add the contact names to the People Library

Notes

Importing contacts and users to the People Library does not remove them from Outlook If you try to import the same Outlook contact twice it appears only once in the People Library

95

copy Experience In Software Inc 1995 - 2006

You can import Contacts from the Outlook Business Contact Manager

See Also

Import Outlook Contacts via CSV to the People Library (Pro Users)

-o-

96

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts via CSV to the People Library (ProUsers)

This feature is available only in Project KickStart Professional

If you use Microsoft Outlook to maintain your contacts and many of the people on your project are not inyour personal contacts folder in Outlook you can use our new utility to import these Outlook contacts viaCSV to the People Library

To export Outlook contacts to a CSV file1 In Outlook - Click File Import and Export Export to A File and click Next2 Select Comma Separated Values (Windows) and click Next3 Select the Contacts folder to export and click Next4 Save Exported File As with the default being your My Documents folder5 Click Next

To import Outlook contacts to the People Library

1 Be sure that you exit Project KickStart before running the Import Utility

2 Run ImportCSVToPKSexe which is located in the Project KickStart application folder

3 Browse or type the Contacts CSV file (the path is My DocumentsProject KickStart Projects folder bydefault)

4 Browse or type the pks5libxdat file (default is the Project KickStart application folder)

5 Click on Import

Note

Importing contacts and users to the People Library does not remove them from Outlook

-o-

97

copy Experience In Software Inc 1995 - 2006

Printing Reports

98

copy Experience In Software Inc 1995 - 2006

Printing Dashboards

Print Reports

You can print reports from anywhere in Project KickStart through a new Reports Step

You will see Reports divided into three areas

Dashboard

Task Reports

Gantt Chart Reports

-o-

99

copy Experience In Software Inc 1995 - 2006

Print Dashboard Reports

You can print dashboard reports from anywhere in Project KickStart though it makes the most sense toprint them after you have developed your tasks and arranged them in a sensible order

To print a dashboard report

1 Click File on the menu bar and then click Print Reports and then click Dashboard Reports or clickthe Print Reports button

2 In the left column select one of these dashboard reports Whats Due Today Whats Due NextWeek Whats Due Next Month

3 Change the page setup as necessary or Save As a file (See Page Setup and Save As)

4 Click the Print button

Tip

You can see the number of tasks in each dashboard report from the dashboard menu

-o-

100

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Dashboard Reports

Printer Setup

-o-

101

copy Experience In Software Inc 1995 - 2006

Save as HTML or RTF

You can dashboard reports to a Hypertext Markup Language (HTML) format for viewing with an Internetbrowser such as Microsoft Internet Explorer or Mozilla FireFox or to an RTF format for viewing in MicrosoftWord

To save a dashboard report as an HTML file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save button

To save a report as an RTF file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

102

copy Experience In Software Inc 1995 - 2006

Printing Task Reports

Print Task Reports

You can print task reports from anywhere in Project KickStart though it makes the most sense to print themafter you have developed your tasks and arranged them in a sensible orderBefore you print task reports you might want to widen the Task Name column in the Task List to make sureyou print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a task report

1 Click File on the menu bar and then click Print Task Reports In the Tasks step you can click thePrint Reports button instead

The Create and Print Task Reports dialog box opens

2 Click the list arrow and then click Task Report Individual Assignments or Phases Goals People ampObstacles

3 Select the information you want to include in the report as described below

4 Preview the report and change the page setup as necessary (See Print Preview and Page Setup)

5 Click the Print button

Task Report

The Task report covers the entire project and includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

103

copy Experience In Software Inc 1995 - 2006

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to display in the report

By default the report prints all tasks Click the Incomplete Tasks or Completed Tasks option button tofocus on one type of task

4 Click the Preview button (See Print Preview for details)

Individual Assignments

The Individual Assignments report covers the entire project and lists the tasks assigned to each resourceThe report includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to include in the report

Click the All Tasks Incomplete Tasks or Completed Tasks option button

4 Choose which people to include The report lists tasks assigned to the people you select

Click to insert or remove a checkmark from the box for each person

5 Click the Preview button (See Print Preview for details)

Phases Goals People amp Obstacles

This report includes the phases goals people and obstacles in your project You can include some or all ofthese items in the report

104

copy Experience In Software Inc 1995 - 2006

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Click the Preview button (See Print Preview for details)

Tip

If you have many long notes for the tasks of your project it may be hard to read them if you select everycolumn in the Task Reports You should consider selecting a report with only columns for Tasks andNotes

See Also

Print Gantt Chart Reports

-o-

105

copy Experience In Software Inc 1995 - 2006

Print Preview

Before printing a report preview its pages so you know how the report will look when printed

To preview a task report1 Click the Preview button on the Create and Print Task Reports dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from 79 to 100 or from 100 to 79Zoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25

viewPrint the report

You can also click the Page Setup button to change margins and other settings or click the Closebutton to close the Print Preview window

2 If the report appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintTask Reports dialog box

Note

Print Preview is for viewing only--you cannot edit the contents of a report

See Also

Print Task Reports

Printer Setup

Page Setup

-o-

106

copy Experience In Software Inc 1995 - 2006

Printer Setup

Before you print a report you can change the following printer settings

Printer name (and other properties) Paper size Number of copies

To change the printer setup1 Click the Printer button on the Project KickStart toolbar or the Print Preview toolbar2 In the Print dialog box change the printer settings

See Also

Print Task Reports

Print Preview

Page Setup

-o-

107

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Task Reports

Print Preview

Printer Setup

-o-

108

copy Experience In Software Inc 1995 - 2006

Email Task Reports

After creating and previewing a task report you can distribute it to others via email

To email a task report1 In the Create and Print Task Reports dialog box select a report and then click the Email Report

button Project KickStart creates the report opens a new message in your email software and attaches thereport as an HTML file to the message

2 Insert one or more email addresses include the message text and then send the message the way youusually do

Tip

To send a task report to each person in your project with the appropriate assignments select theIndividual assignments report select one person to receive the report and then click the Email Reportbutton Enter the email address of the recipient and send the message Do this for each person in yourproject

-o-

109

copy Experience In Software Inc 1995 - 2006

Save as HTML

You can export tasks assignments days and notes to a Hypertext Markup Language (HTML) format forviewing with an Internet browser such as Microsoft Internet Explorer or Mozilla FireFox

To save a report as an HTML file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

110

copy Experience In Software Inc 1995 - 2006

Save as RTF

You can export tasks assignments durations and notes to a Rich Text Format (RTF) for editing inMicrosoft Word

To save a report as an RTF file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can open an RTF file in a word processor such as Microsoft Word

To send an RTF document to each person in your project with the appropriate assignments select theIndividual Assignments report select one person to receive the report and then save the report asRTF Do this for each person in your project

See Also

Save as HTML

-o-

111

copy Experience In Software Inc 1995 - 2006

Printing Gantt Chart Reports

Print a Gantt Chart

Once you create your schedule you can print a Gantt chart from anywhere in Project KickStart

Before you print a Gantt chart you might want to widen the Task Name column in the Task pane to makesure you print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a Gantt chart1 Click File on the menu bar and then click Reports and then select Gantt Chart Reports In the

Schedule step you can click the Print Reports button insteadThe Create and Print Gantt Chart Report dialog box opens

2 Click the Format list arrow and then click Wall chart Fit to smallest size or Repeat tasks on everypage (for handouts)

3 Select the information you want to include in the report as described below4 Preview the report and change the page setup as necessary (See Print Preview a Gantt Chart and

Page Setup)5 Click the Print button

Wall Chart The wall chart prints the Gantt chart information spread across many pages which you can tape together tocreate a wall chart On the left side of the report the wall chart includes the task data columns you selectThe right side of the report includes the graphical view shown in the Gantt chart pane on the right

1 Select the task data columns you want to display for the task information on the left side of the wallchartClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the wall chart

112

copy Experience In Software Inc 1995 - 2006

By default the wall chart prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the wall chartBy default the wall chart prints the timescale you were using in the Gantt chart Click the SetTimescale list arrow to change the timescale to Weeks Months Quarters or Years

4 Select the orientation for the wall chartClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Fit to Smallest Size When you select the Fit to smallest size format Project KickStart reduces the size of the entire Gantt chartincluding the information in the Task pane on the left and the graphical view shown in the Gantt chart paneon the right so it fits as well as possible in the smallest number of pages

1 Select the data columns you want to display for the task information on the left side of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 The timescale for the Gantt chart view on the right side of the report is determined by the length of yourproject and may not be changed

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 The number of pages of the report is shown here (The Fit to smallest scale report will print up to 78rows of tasks per page)

6 Click the Preview button (See Print Preview a Gantt Chart for details)

Standard (for Handouts) This report lists the data columns you specify on the left side of the first page and can repeat the tasknumber task name or assignments on every interior page of the report which is especially useful for

113

copy Experience In Software Inc 1995 - 2006

handouts

1 Select the data columns you want to print on the left side of the first page and the data columns youwant to print on every page of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the reportBy default the report prints a daily view of the tasks Click the Set Timescale list arrow to change thetimescale to Weeks Months Quarters or Years

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Tips

Print Preview shows how many pages the Gantt chart will take to print If there are too many pagesconsider changing the timescale or the date range You can also choose to show fewer columns of taskdata

If possible use paper that is larger than 85 x 11 inches You can select the paper size in Print Previewusing the Page Setup dialog box

If you change the timescale from Days to Weeks or Months this can make tasks with short durations (1to 5 days) difficult to see

If you have trouble printing the Gantt chart report try changing the dpi from 600 to 300 (draft mode) Ifyou continue to have problems contact your printer manufacturer and see if it supports PCL (PrinterCommand Language) technology which is included in most printers today

If you have trouble printing the Gantt chart report on a PDF printer you can try to scale the printing tographics setting to 50

114

copy Experience In Software Inc 1995 - 2006

See Also

Save Gantt Chart Images

Print Task Reports

Printer Setup

Page Setup

-o-

115

copy Experience In Software Inc 1995 - 2006

Print Preview a Gantt Chart

Before printing a Gantt chart preview its pages so you know how the report will look when printed

To preview a Gantt chart1 Click the Preview button on the Create and Print Gantt Chart Report dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from the current zoom percentage to 100 or from 100 to the current zoom percentageZoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25 viewChange printer settings and then print the reportYou can also click the Page Setup button to set margins select paper size and enter headers andfooters or click the Close button to close the Print Preview window

2 If the Gantt chart appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintGantt Chart Report dialog box

Notes

Print Preview is for viewing only--you cannot edit the contents of a report

If you want to print a wider task column return to the Gantt chart widen the Tasks Name column andthen print

To change print settings such as the printer selection and number of copies click the Print button to open the Print dialog box You can save the Gantt chart in a PDF file by clicking the Print button andthen clicking the PDF printer selection (such as Adobe PDF or PDF-XChange ) You can then distributethe Gantt chart electronically as a PDF file

See Also

Print a Gantt Chart

Page Setup

-o-

116

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a Gantt chart you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print a Gantt Chart

Print Preview a Gantt Chart

-o-

117

copy Experience In Software Inc 1995 - 2006

Printing to an Adobe PDF file

To print a Gantt chart to an Adobe PDF file you may have to make some adjustments to your settings

To preview a Gantt chart1 Select Adobe PDF as the name of the printer2 Click Properties button3 Click the PaperQuality tab4 Click Advanced button5 In the Graphic Section lower the setting on Print Quality6 Also in the Graphic Section change the Scaling from 100 to 50

-o-

118

copy Experience In Software Inc 1995 - 2006

Save Gantt Chart Images

You can save a Gantt chart as a series of graphic files in the Meta File (emf) format which you can theninsert in a file such as a Microsoft Word document or PowerPoint presentation The number of graphic filescreated depends on the report type and options you choose in the Create and Print Gantt Chart Reportdialog box By default Project KickStart saves the files in a folder named for your project

To save Gantt chart images1 In the Create and Print Gantt Chart Report dialog box click the Save Image button

The Save Image dialog box opens2 Change the location where you want to save the image files or change the part of the file name that

includes the project name and report type if necessary3 Click the Save buttonNotes

Project KickStart saves the image files in the PKSGanttImagesproject name folder stored in the MyDocumentsProject KickStart Projects folder (where project name is the name of your project)

Each graphic file name includes the name of the project report type date you created the report andnumber in the series of images as in CreateaWinningPresentation_Wall chart_09112008_1emf toCreateaWinningPresentation_Wall chart_09112008_20emf

To email the Gantt chart images attach the images in the PKSGanttImagesproject name folder storedin the My DocumentsProject KickStart Projects folder (where project name is the name of your project)If the image files are large zip or compress the files first

If you have installed PDF as a printer selection you can print the Gantt chart to a PDF file and thenattach the PDF file to an e-mail message PDF files are often easier to read than image files See thenotes in Print Preview a Gantt Chart for instructions on printing to a PDF file

-o-

119

copy Experience In Software Inc 1995 - 2006

Export Project Data

120

copy Experience In Software Inc 1995 - 2006

Export to ACT

Export to ACT 7 or Later

If you use ACT 7 or later (20052006200720082009) you can export your plan from Project KickStart toan ACT database with just one click After you export your plan you see your tasks in the ACT Groupview grouped under the name of your project

To export to ACT 7 or later

1 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 7 and later andthen click the Go button You can also click File on the menu bar point to Export to and then clickACT 7 and later

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (pad file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opens

Each time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks

4 Click Start (This works best if ACT is already open )

5 If you are exporting to a multi-user ACT database enter your ACT User Name and Password

To view each project separately in ACT Group Details

1 In ACT click the Group List icon

2 Double-click the Project Name in the Group Name column The Group Detail appears for the projectyou selected

3 Click the Contacts tab to see Contacts and click the Activities tab to see tasks for that project

4 You should press Ctrl-F5 to refresh the view Also you might have to adjust the Filter in ACT so thatDates to show is set to All Dates

Task names are listed in the Regarding column Assignments are listed in the Scheduled With columnPhases are shown in red and tasks and subtasks are shown in blue

To view tasks from multiple projects sorted by date in Task List or Calendar

In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn Project names are in the Associate With column You might have to adjust the Filter in ACT sothat Dates to show is set to All Dates

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar Tasks are set as timeless (Duration of 0 minutes) so the transferred tasks dont fill up thecalendar

121

copy Experience In Software Inc 1995 - 2006

Tips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

The ACT 7 and later export is smart enough to update your existing tasks from the same project If youexport the same Project KickStart project two or more times ACT recognizes the project and asks ifyou want to update the project information in ACT You do not lose your task history or notes in ACT

Tasks that are unassigned in Project KickStart are listed as Scheduled With Unassigned PKS

You can filter by Selected Users in the Task List and in Groups

See Also

Import ACT Contacts and Users to the People Library

-o-

122

copy Experience In Software Inc 1995 - 2006

Export to ACT 6

If you use ACT 6 ACT 2000 or ACT 5 you can transfer a Project KickStart plan into an ACT databasewith just one click After you export your plan you see your tasks in the ACT Group view grouped underthe name of your project

To export to ACT 61 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 6 and then click

the Go button You can also click File on the menu bar point to Export to and then click ACT 6

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (dbf file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opensEach time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks4 Click Start (This works best if ACT is already open )5 If you are exporting to a multi-user ACT database enter your ACT user name and passwordTo view each project separately in ACT1 In ACT click the Groups icon 2 Click the Project Name listed under All Groups on the left3 On the lower-right part of the window click the Activities tab to see tasks for that project

Task names are listed in the Regarding column Assignments are listed in the Scheduled With column 4 You might have to adjust the Filter in ACT so that Dates to show is set to All Dates Also you might

have to press Ctrl-F5 to refresh the view5 To view task details click the button next to the task column on the leftTo view tasks from multiple projects sorted by date1 In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn You might have to adjust the Filter in ACT so that Dates to show is set to All Dates

2 If the Group column is not showing add it by clicking ViewAdd Columns and then double-clickingGroupThe tasks are identified by group (project name)

3 To view task details click the button next to the task column on the leftTips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar as well as in the Task List

You can filter by Selected Users in the Task List and in Groups

After exporting your tasks to ACT you can import them to your Palm Pilot using the ACT Link

See Also

Import ACT Contacts and Users to the People Library

-o-

123

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Outlook

If you use Microsoft Outlook you can export your plan from Project KickStart to Outlook in a click of abutton After you export your plan you see your tasks in the Outlook Tasks view grouped under a categorynamed for your project In Outlook you can track your tasks and email tasks to team members

To export to Microsoft Outlook1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Outlook and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Outlook The Export to Outlook dialog box opens

2 Click an option button to export All tasks Uncompleted tasks or Completed tasks3 If you want to display the tasks you export on your Outlook Calendar click the check box4 Click the Start button A dialog box opens informing you that Project KickStart is trying to access your

Outlook data

5 Allow access for 1 minute and then click the Yes buttonTo view your tasks in Microsoft Outlook1 Click the Outlook Tasks button2 Depending on the version of Outlook you are using set to view the tasks by category In Outlook 2003

click the By Category option button in the Current View list You can also click View on the menu barpoint to Arrange By and then click CategoriesYour project is listed by its project name in the Categories list

3 Click an expand icon to see the complete list of tasks and subtasks

124

copy Experience In Software Inc 1995 - 2006

4 To view task details double-click the task nameTips

The export to Outlook works best if Outlook is already open

In Outlook you can set priorities set reminders and schedule by the hour

If you export to your Outlook Calendar a reminder appears on the due date of each task

After you export tasks to Outlook you can synchronize with your Palm Pilot Windows CE device orother handheld computer

Note

You can export only to Microsoft Office Outlook not Outlook Express

See Also

Import Outlook Contacts to the People Library

-o-

125

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Word

If you use Microsoft Word you can export your plan from Project KickStart to Word in a click of a buttonYour project appears in a Word table in a doc file You can cut and paste change column widths deletecolumns and print from Word

To export to Microsoft Word

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Word andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Word

Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in a Word document in a doc format

2 When youre finished use Save As to save the Word file with a new name such as ltnamegtdoc Forconvenience you can save the file using the same name as your Project KickStart project name

Benefits of using Project KickStart and Word

Communicate projects flexibly After exporting to Word you can communicate your project details ina variety of text formats You can also enhance your document by adding color logos clip art orhyperlinks

Distribute plans to others You can send doc files to other Microsoft Word users via email andrequest comments using Words Send To and Comments features

Tip

Include your strategic plan in documents letters and web pages in a doc or html file

Note

The image of the Gantt chart does not import into Word automatically You can manually import theGantt chart image into a Word document In Word select Insert on the menu bar point to Pictureclick From File and then browse to the folder containing the Gantt chart images you saved By defaultthis is cMy DocumentsProject KickStart ProjectsPKSGanttImages in a folder named for your project

See Also

Export to Word Processors (Other than Word)

Save Gantt Chart Images

126

copy Experience In Software Inc 1995 - 2006

-o-

127

copy Experience In Software Inc 1995 - 2006

Export to Word Processors (Other than Word)

If you are using a word processor other than Microsoft Word you can export your Project KickStart taskreport by first saving it as an HTML or RTF file

To export to word processors other than Microsoft Word

1 Save a Project KickStart task report using HTML or RTF format using the Save As button in the Createand Print Task Reports dialog box

2 Open the file with your word processor

3 Save the file using the Save As command using a different name

See Also

Print Task Reports

Save as HTML

Save as RTF

-o-

128

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Excel

If you use Microsoft Excel you can export your plan from Project KickStart to Excel in a click of a buttonYour project appears in an Excel worksheet in a xls file You can add task details perform calculationsand share your project data with other Excel users

To export to Microsoft Excel1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Excel and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Excel Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in an Excel worksheet in an xls format

2 When youre done select FileSave As to save the Excel file under a new name For convenience youmight want to save it under the same name as your Project KickStart project name

To manually import Gantt chart images into Microsoft Excel1 In Excel click Sheet2 and select ToolsOptions on the menu bar and unclick the box for Gridlines2 Then select Insert on the menu bar point to Picture click From File and then browse to the folder

containing the Gantt chart images you saved By default this is cMy DocumentsProject KickStartProjectsPKSGanttImages in a folder named for your project

3 Select one Gantt chart image at a time to bring it in 4 You can manipulate the size of the image in Excel

Benefits of using Project KickStart and ExcelProject KickStart is very good at scoping out a schedule but there are a few reasons why you might want touse both programs

Data sharing A Project KickStart user might want to share the information with other Excel users whodont have Project KickStart They could change enhance or redistribute their portions of the schedule

129

copy Experience In Software Inc 1995 - 2006

Add more task details Excel users can add new columns of task data that cant be added in ProjectKickStart

Sort task lists For example you could show your projects tasks sorted by each resources namethen see each resources tasks sorted by the tasks start date

Filter tasks Excel can show tasks that meet certain criteria For instance show tasks with the wordtesting in the task name

See Also

Save Gantt Chart Images

-o-

130

copy Experience In Software Inc 1995 - 2006

Export to Microsoft PowerPoint

If you use Microsoft PowerPoint you can export your plan from Project KickStart to PowerPoint in a click ofa button Your project appears as a formatted PowerPoint presentation in a ppt file

To export to Microsoft PowerPoint

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft PowerPointand then click the Go button You can also click File on the menu bar point to Export to and thenclick Microsoft PointPoint

The Export to PowerPoint dialog box opens where you can choose a PowerPoint design template ifyou like

2 Click the Start button

Your tasks days start and finish dates and costs appear in a PowerPoint presentation with an imageof the Gantt chart in one or more slides at the end of your slide show

Once you have created a PowerPoint presentation you can enhance your slides in several ways

Delete slides that are not appropriate for your presentation

131

copy Experience In Software Inc 1995 - 2006

Rearrange the order of the slides

Add colors for emphasis

Add graphics such as company logo clip art and colors

Shorten any long task titles

Benefits of using Project KickStart and PowerPoint

Save time You can dramatically save time in creating a PowerPoint presentation on your project

Present projects to others Present project details in webinars presentations and corporatemeetings Create template presentations or how tos for implementing an installation productintroduction or corporate policy for example

Communicate plans Email project plans in ppt format to colleagues and presentors

Tips

If you use a PowerPoint design template choose one that has a white or light background for maximumlegibility of the Gantt chart in the presentation

The Gantt chart image in the PowerPoint presentation is generated ldquoon the flyrdquo Change the Timescalesettings of the Gantt chart considering how it will be reflected in the number of images of the Ganttchart For example the Day view results in more Gantt chart images than the Months view

-o-

132

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Project

If you use Microsoft Project 98 2000 2002 or 2003 you can export your plan from Project KickStart toProject in a click of a button

To export to Microsoft Project

In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Project andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Project Your tasks assignments days start and finish dates costs done and notes (excluding attachments) appearin a Microsoft Project file

Benefits of using Project KickStart and Microsoft Project

Share data with others Send a project to a colleague or client that expects to see your schedule in anMicrosoft Project format

Schedule tasks with more flexibility Schedule tasks in different durations particularly in less than aday

Track resources Track resource usage and resource leveling and to have greater flexibility in sortingfiltering and reporting project information

Notes

Project KickStart tasks transfer to Microsoft Project as tasks with a Constraint type of Start No EarlierThan This keeps the dates the same as in the Project KickStart schedule

The settings in Project KickStart Working Days Calendar also transfer to Microsoft Project

Exporting to Microsoft Project allows you to take advantage of the advanced tracking and schedulingfeatures that large projects often require

You can also save your Project KickStart projects as an mpx file which you can open in MicrosoftProject and send to other Microsoft Project users Click File on the Project KickStart menu bar clickSave As and then choose mpx as the file type After you save the file click File on the MicrosoftProject menu bar click Open and open your mpx file

-o-

133

copy Experience In Software Inc 1995 - 2006

Export to SureTrak Project Manager

If you use SureTrak Project Manager you can export your plan from Project KickStart to SureTrak ProjectManager

To export to SureTrak Project Manager

1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file

2 In SureTrak click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

SureTrak

You will see your tasks and assignments (but not the notes) appear in a SureTrak file The file is shownin outline view

Benefits of using Project KickStart and SureTrak

Add new information to tasks such as how they are linked

Track progress particularly for comparing plans verses actual results

Have greater flexibility in sorting filtering and reporting project information

Notes

Task notes are not included in the transfer

A version of Project KickStart called the Project KickStart Wizard is included in SureTrak 2 andSureTrak 3 You can use it within SureTrak

See Also

Export MPX Files

-o-

134

copy Experience In Software Inc 1995 - 2006

Export to FastTrack Schedule

If you use FastTrack Schedule you can save your Project KickStart project as an mpx file and import it intoFastTrack ScheduleTo export to FastTrack Schedule1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file2 In FastTrack Schedule click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

FastTrack ScheduleBenefits of using Project KickStart and FastTrack Schedule

Add more task details FastTrack Schedule provides the features and tools needed in many largeprojects

Multiproject reporting Consolidate multiple projects into a master project file

See Also

Export MPX Files

-o-

135

copy Experience In Software Inc 1995 - 2006

Export to Milestones Professional

If you use Milestone Professional you can export your plan from Project KickStart to MilestonesProfessional in a click of a button

To export to Milestone Professional

In the Schedule step click the Export to list arrow below the Gantt chart click MilestonesProfessional and then click the Go button You can also click File on the menu bar point to Export to and then click Milestones Professional

Your tasks assignments start and finish dates and notes (excluding attachments) appear in aMilestones file

Tips

After you export your tasks to Milestones Professional you can create taskbars add titles and performother tasks to produce a presentation-quality schedule You can also use Milestones to track your tasksby showing task durations and percent completions Make scheduling changes by dragging the taskdates

If you have an earlier version of Milestones (eg version 45 or 5) you can save Project KickStart dataas an mpx file and then open the mpx file in Milestones

-o-

136

copy Experience In Software Inc 1995 - 2006

Export to Mindjet MindManager

If you use Mindjet MindManager 7 or later you can export your project plan from Project KickStart in a clickof a button Or you can develop a rough plan in MindManager and export your mind map to ProjectKickStart for enhanced planning It works both ways

To export from Project KickStart to MindManager

In the Schedule step click the Export to list arrow below the Gantt chart click MindManager and thenclick the Go button You can also click File on the menu bar point to Export to and then clickMindManager

Your tasks assignments start and finish dates durations costs Done and notes (excludingattachments) appear in a MindManager file

To export from MindManager to Project KickStart

In MindManager click File on the menu bar point to Send To and then click Project KickStart Thenclick the OK button to start the export

You can also click the Project KickStart icon at the bottom of the MindManager window

Benefits of using Project KickStart and MindManager together

Visualize your plan in two ways Brainstorm plan and communicate your project details in both agraphical and linear style

Develop a graphical plan and then fine-tune the details MindManager uses mindmappingtechniques to develop a high-level plan in a graphical format Export to Project KickStart to enhanceyour plan details by focusing on your projects goals obstacles and resource needs You can alsocreate a Gantt chart schedule

Communicate concepts Project KickStart users can display their plans in a highly graphicalmindmapping format in MindManager The maps make it easier to communicate complex processesand visually identify important tasks issues and relationships

Tip

If you dont already use MindManager you can purchase it in our Thinking Tools Store

-o-

137

copy Experience In Software Inc 1995 - 2006

Export to WBS Chart Pro

If you use WBS Chart Pro you can export your plan from Project KickStart to WBS Chart Pro in a click of abutton

To export to WBS Chart Pro

In the Schedule step click the Export to list arrow below the Gantt chart click WBS Chart Pro andthen click the Go button You can also click File on the menu bar point to Export to and then clickWBS Chart ProYour project is displayed under the project name Each phase in the project is shown in a box with ashadow Each lower level task in a phase is displayed under their respective phase box groupedtogether with the other tasks in that phase

Benefits of using Project KickStart and WBS Chart

Visualize tasks Work with tasks in a tree-style chart called a Work Breakdown Structure (WBS)chart

Communicate your project plan with others WBS Chart uses the outline you create in ProjectKickStart to create a top-down picture of your plan This picture is similar to an Organization chart Butinstead of displaying the structure of your company a WBS chart displays the structure of your projectplan

Notes

WBS Chart refers to the phases in the project as Summary Tasks and the detail for each phase asTasks

The export only works if WBS Chart is not currently running You must close WBS Chart before you cancreate another chart

See Also

Export MPX Files

-o-

138

copy Experience In Software Inc 1995 - 2006

Export MPX Files

The MPX file format is an ASCII format created by Microsoft Project or another program and is used tosend data to and from project management software programs

The following programs can create and open MPX files

FastTrack Schedule

Microsoft Project (95 or 98)

Project KickStart 5

Project KickStart 32

RiskyProject

SureTrak Project Manager

WBS Chart

In these programs you save a project as an MPX file using the Save As command on the File menu Youcan then open an MPX file by using the Open command on the File menu and then specifying the file typeas mpx

For example if you want to move a project from Project KickStart 5 to Project KickStart 32 you can savethe project as an mpx file and then open it in Project KickStart 32

In Microsoft Visio you can create a Visio project time line from Project KickStart To do so you first mustsave your file in Project KickStart as an MPX file Then

1 Start Visio

2 Click File on the menu bar point to New click Business Diagram and then click Project TimelinesWizard

3 Click Next

4 On the second window click Import MPX File to import the Project KickStart mpx file

5 Enter the file location and name or click Browse to locate the file

6 Follow the instructions in the Visio Project Timelines Wizard windows

Tip

If you have difficulty importing the mpx file remove any commas from task names

-o-

139

copy Experience In Software Inc 1995 - 2006

Reference

140

copy Experience In Software Inc 1995 - 2006

Menus

File Menu

Command Keyboard Shortcut Description

New Project Ctrl+N Creates and names a new project fileOpen Project Ctrl+O Opens a previously saved Project KickStart 4 or 5 file

(prx) Project KickStart 3 file (prj) or mpx fileClose Ctrl+W Closes an open Project KickStart fileSave Ctrl+S Saves a project file (prx) in which you made changes Save As Saves a project file with a different file name or different

file format such as MPXPrint Task Reports

Ctrl+T Generates and prints a report letting you preview thecontents

Print Gantt ChartReports

Ctrl+G In the Gantt chart (Schedule step) generates andprints the Gantt chart in the current timescale

Export To Sends the project to another program such asMicrosoft Outlook or ACT 7

Recent file list Lists the last three files opened in Project KickStartExit

Alt+F4 Exits the program

-o-

141

copy Experience In Software Inc 1995 - 2006

Edit Menu

Command Keyboard Shortcut Description

UndoRedo Ctrl+Z Undoes or repeats the last operationCut

Ctrl+X Deletes the currently selected information placing it on theclipboard so you can paste it elsewhere

Copy

Ctrl+C Places a copy of selected information on the Clipboard so youcan paste it elsewhere

Paste

Ctrl+V Places information from the Clipboard to the currently selectedlocation

Select all Ctrl+A Selects all the content in the windowAdd a line Adds a new row where you can enter text

-o-

142

copy Experience In Software Inc 1995 - 2006

View Menu

Command Description

Tool Bar Shows or hides the toolbar (a checkmark indicates thetoolbar is displayed)

Steps Bar Shows or hides the Steps bar (a checkmark indicates the Steps bar is displayed)

Name Go to the Name your project stepPhases Go to Phases stepGoals Go to Goals stepSimilar Projects Go to Similar projects stepPeople Go to People stepObstacles Go to Obstacles stepAssign Go to Assign tasks to people stepTasks Go to Tasks stepSchedule Go to Schedule step

-o-

143

copy Experience In Software Inc 1995 - 2006

Tools Menu

Command Keyboard Shortcut Description

Spelling

F7 Checks spelling of project dataexcept for names of people

Collaboration To access or find out aboutGoToMeeting

Options Select options for running thesoftware

-o-

144

copy Experience In Software Inc 1995 - 2006

Options

-o-

145

copy Experience In Software Inc 1995 - 2006

Data Menu

The Data menu is available in the Tasks and Schedule steps for manipulating tasks and creating ascheduleCommand Description

Move Up Moves the selected task item upMove Down Moves the selected task item downOutdent Moves the selected task item to the leftIndent Moves the selected task item to the rightInsert Task Insert task in row aboveInsert SubTask Insert subtask below current rowDelete Task Delete current taskEdit Task Properties Brings you to an edit screen where you can edit task

name change assignments and edit task notesEdit Notes Brings you to an edit screen for editing task notesColor Taskbars Change the color of selected tasks (in Schedule)Change Working Days Select which days are working and which are

nonworking (in Schedule)Link Tasks Link tasks in Gantt chart (Pro Users)Unlink Tasks Unlink tasks in Gantt chart (Pro Users)

-o-

146

copy Experience In Software Inc 1995 - 2006

Timescale Menu

The Timescale menu is available in the Schedule step so you can change the display of the Gantt chartschedule

Command Description

Days Displays a daily schedule in theGantt chart

Weeks Displays a weekly schedule inthe Gantt chart

Months Displays a monthly schedule inthe Gantt chart

Quarters Displays a quarterly schedule inthe Gantt chart

Years Displays a yearly schedule inthe Gantt chart

-o-

147

copy Experience In Software Inc 1995 - 2006

Help Menu

Command Description

Project KickStart Help Help for Project KickStart including a Table ofContents and index of terms

Online Tutorials View several Getting Started Tutorials to getyou started with Project KickStart whether youare a new or experienced user

Keyboard Shortcuts Shortcuts for programTechnical Support How to obtain Technical Support for Project

KickStart via web form and email[Send Log to Technical Support] If the program detects an error it writes a log

of technical issues Click Send Log toTechnical Support to send the error log to us

ProjectKickStartcom Visit the Project KickStart Web siteGet Latest Version See what the latest published version is and

download it if you need itAbout Project KickStart Shows Project KickStart version number build

date copyright and system information

-o-

148

copy Experience In Software Inc 1995 - 2006

Shortcuts

Use the following keyboard shortcuts to move quickly around in Project KickStart

Navigation

Move forward to the next window Alt+NMove back to the previous window Alt+BSteps

Go to Name step Alt+MGo to Phases step Alt+SGo to Goals step Alt+GGo to Similar step Alt+RGo to People step Alt+PGo to Obstacles step Alt+OGo to Assign step Alt+IGo to Tasks step Alt+KGo to Library (Phases Tasks GoalsPeople Obstacles)

Alt+L

Menus

File menu Alt+FEdit menu Alt+EView menu Alt+VShow menu (Tasks step) Alt+WOutline menu (Tasks step) Alt+UTimescale (Schedule step) Alt+CHelp menu Alt+H F1Other

Edit tasks assignments amp notes (Tasks step)F3Save Ctrl+SPrint Task Report Ctrl+PPrint Gantt Chart (Schedule step) Ctrl+GCut Ctrl+XCopy Ctrl+CPaste Ctrl+VInsert Row InsertDelete Row DeleteInsert Line Break (in Notes in Task List andSchdule steps)

Enter

Spell Check

Ignore Alt+IIgnore All Alt+GChange Alt+CChange All Alt+HHelp

149

copy Experience In Software Inc 1995 - 2006

Contents in Help Alt+CIndex Alt+IBack in Help Alt+BClose Help Alt+LHelp about the current step Alt+H

-o-

150

copy Experience In Software Inc 1995 - 2006

Share Project KickStart Data

Project KickStart makes it easy to share data with other people involved with a project You can share yourProject KickStart data in the following ways

Send a printed report Make a PowerPoint presentation Send a file (prx html rtf mpx) Post an HTML file to a Web site and access it with your web browser Export to other programs such as Microsoft Word or Excel and send data in a format the recipient can

access (such as doc xls or mpx)

Note

You can also collaborate with a colleague by conducting an online meeting using GoToMeeting (Prousers)

-o-

151

copy Experience In Software Inc 1995 - 2006

Open a Project

After you create a project and save it in a prx prj or mpx file using Project KickStart or other softwareyou can open the project in Project KickStartTo open a project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click a file type (prxprj or mpx)

3 Navigate to the folder that contains the file4 Double-click the name of the file

Opening a Project KickStart 3 prj file converts it to a prx file

Generally prj files are stored in cprogram filesProject KickStart 3

The tasks in the converted Project KickStart 5 file will have the same start and finish dates anddurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way To have weekends as non working days open the working days calendar and markweekends as non working

Opening a mpx file converts it to a prx file

The tasks in each project have the same start and finish dates and durations

-o-

152

copy Experience In Software Inc 1995 - 2006

Dedication

I dedicate this software program to my new colleague

Kevin Ahlvin

Roy A Nierenberg President

-o-

153

copy Experience In Software Inc 1995 - 2006

Credits and Trademarks

Credits

Missak Koumoudjian Program Architect and Chief Programmer

Kevin Ahlvin Interface DesignAnn Kawamoto Quality AssuranceAlexander Setzepfandt Quality AssuranceJackie LeungJeffrey Chow

Programming Interns

Kevin Ahlvin Product Supervisor and CoordinatorJoseph Fusco Project Management Consultant and content

providerLisa RuffoloJoseph Fusco

Help System

Roy A Nierenberg President

Trademark

Project KickStart and Project KickStart Wizard are trademarks of Experience In Software Inc in the UnitedStates andor in other countries All rights reserved All other trademarks mentioned herein are the propertyof their respective owners

-o-

154

copy Experience In Software Inc 1995 - 2006

Uninstalling

You can uninstall Project KickStart 5 through the Control Panel AddRemove Programs Select ProjectKickStart 5 This starts the InstallShield Maintenance Program You should then remove all of theprogram files that were installed It will not erase your Project KickStart prx data files

If that does not work you can delete the Project KickStart files manually

Note

If you purchased Project KickStart and you want to return it for a refund follow the instructions forDe-activating the software at httpwwwprojectkickstartcomcontactreturnscfm

-o-

155

copy Experience In Software Inc 1995 - 2006

Using Past Projects

You can use past projects in two ways

If you have projects that are similar you can use a past project as a template for a new project In theWelcome window select Open a Project Open that project and Save As under a different name Nowyou can open up the renamed project and modify it for the current project

You can draw from several projects in the Similar Projects step First select projects that are similarand click Next Then select tasks from those projects and decide where they would fit into your currentproject

See Also

Opening a project Compatibility with earlier versions

-o-

156

copy Experience In Software Inc 1995 - 2006

Index

- - Change Working Schedule 85

- -prj file format 13

- A -About Linking Tasks (Pro Users) 59About Scheduling Tasks 55About the Gantt Chart 57ACT 120 92 122ACT 6 92 122ACT 7 or later 92 120Activate 14Activating Trial Version 14Add a New Person or Resource 39add a subtask 83add a task 83Add a Task or Subtask 47Add or Change Task Assignments 51Add or Change Task Details 52Add Subtask 63Add Task 63Add URL 49Additional Features in Task Data View (Pro Users) 68Additional Tools in Chart View (Pro Users) 71Adobe PDF 117Assignments tab 80Attachments 49Autolink tasks (Pro Users) 58

- B -Back 10borrow tasks 29

- C -Change Details for Linked Tasks (Pro Users) 81Change Project Start 63Change Task Dates 73Change Task Details 80Change the Appearance of the Task List 43Change the Display of the Schedule 61Change Timescale 63Change Working Schedule 63Chart view 57

157

copy Experience In Software Inc 1995 - 2006

Cloning projects 155Color 63 86Compatibility 13Compatibility with earlier versions 13convert projects 13Coordination 12Create and Print Task Reports 102Credits 153Credits and Trademarks 153critical path 88CSV 96Customer support 20Customer Support 20Customizing Project KickStart

- D -Dashboard 99Data Menu 145Dedication 152Delete 63delete a task 83demote 46dependencies 12 76

- E -Edit Menu 141Edit Notes and Attachments 63Edit or Substitute People 40Edit Task Information 63Email Task Reports 108End User License Agreement 16error 21Error Messages 21export from MindManager 136Export MPX Files 138Export to ACT 6 122Export to ACT 7 and Later 120Export to FastTrack Schedule 134Export to Microsoft Excel 128Export to Microsoft Outlook 123Export to Microsoft PowerPoint 130Export to Microsoft Project 132Export to Microsoft Word 125Export to Milestones Professional 135Export to Mindjet MindManager 136Export to SureTrak Project Manager 133Export to WBS Chart Pro 137

- F -FastTrack Schedule 134File Menu 140Fit to page 111Fit to Smallest Size 111

158

copy Experience In Software Inc 1995 - 2006

- G -Gantt chart 55 57General tab 80Goal 26Goal statements 26Goals 26Goals - Step 1 of 3 26Goals - Step 2 of 3 27Goals - Step 3 of 3 28goals library 26 89Goalsadd 26Goalsdelete 26Goalsedit 26Goalstasks for 27GoToMeeting 150 12

- H -Handouts 111Help Menu 147hyperlink 49

- I -Import ACT 92import contacts and users 92import Outlook contacts 94Import Outlook Contacts via CSV to the People Library (Pro Users) 96ImportCSVToPKSexe 96Indent 46Individual Assignments 102Introduction 7Introduction 7

- K -Knowledge Libraries 90

- L -lag time 81lead time 59 81library 89License Key 14link 59Link lines 59Link tasks 12 65linked tasks 59

- M -major activities 24Make Tasks Overlap (Pro Users) 87Manage a Library 90

159

copy Experience In Software Inc 1995 - 2006

Menu 140Microsoft Excel 128Microsoft Outlook 123Microsoft PowerPoint 130Microsoft Project 132Microsoft Project (95 or 98) 138Microsoft Visio 138Microsoft Word 125Milestone 69 79Milestones Professional 135Mindjet MindManager 136MindManager 136

- N -Name 23Name Your Project 23Navigating Project KickStart 10Next 10Notes and Attachments tab 80

- O -Objectives 26Obstacles 34Obstacles - Step 3 of 3 36Obstacles Library 89Open a Project 151Options 144Outdent 46Outdent and Indent arrows 63Outlook Calendar 123Overview

- P -Page Setup 107 116 100PDF 117people 31People - Step 3 of 3 28People Library 91phase 24phase dates 75Phase Dates Cannot Be Edited 75phases 24Phases - Step 1 of 2 24Phases - Step 2 of 2 25Phases Library 89Phases Goals People amp Obstacles 102PowerPoint presentation 130Pred 68Predecessor 68Predecessor tasks 59predecessors 76Print a Gantt Chart 111Print Dashboard Reports 99Print Preview 105Print Preview a Gantt Chart 115Print Reports 98Print Task Reports 102

160

copy Experience In Software Inc 1995 - 2006

Printer Setup 106Printing to an Adobe PDF file 117prj 13Pro 145Pro Edition 145Product support 20Project 23Project KickStart 3 prj file 151Project KickStart for Windows 7project name 23project start date 73project template 155project title 23promote 46promote and demote tasks 83

- Q -Quick Tour of Working with Linked Tasks (Pro Users) 76

- R -Red vertical line 69Redo 11Register Project KickStart 22Registering Project KickStart 22remove people 38Remove People from a Task 38reorder tasks 83Reorganize Tasks in Task Data View 83Repeat tasks on every page (for handouts) 111Reporting Technical Issues 21resource 31resources 31restore 34return 154risks 34RiskyProject 138

- S -Save As 101Save as HTML 109Save as RTF 110Save Gantt Chart Images 118Schedule 55Send Error Report 21similar projects 29spelling 53starter schedule 55Steps 7subtask 47Subtasks 46Succ 68Successor 68Successor tasks 59successors 76Summary bar 69Support 20SureTrak Project Manager 133

161

copy Experience In Software Inc 1995 - 2006

- T -Task Data view 57task dates 73Task Report 102Taskbar 69Taskbar with percent done 69Tasks 25Tasks in Phases 25Tasks Library 89team 31Technical support 20timescale 84Timescale Menu 146Tools Menu 143Trademark 153trademarks 153Trial 14

- U -unassigning 38Understand Chart View 69Understand Task Data View 66Undo 11UndoRedo Buttons 11uninstallUninstalling 154Unlink tasks 12 65Up and Down arrows 63Use Project KickStart to 8Use the Gantt Chart Toolbar 63Use the Planning Wizard 9Uses 8Using Past Projects 29 155

- V -Version View Menu 142Visio 138

- W -Wall chart 111WBS Chart Pro 137Welcome to Project KickStart 7Whats Due Next Month 99Whats Due Next Week 99Whats Due Today 99Whats New in Project KickStart Pro 5 11Windows Vista 20

162

copy Experience In Software Inc 1995 - 2006

copy Experience In Software 2008w w w projectkickstartcom

  • Table of Contents
  • Start Here Welcome to Project KickStart
    • Introduction
      • Welcome to Project KickStart
      • Use Project KickStart to
      • Use the Planning Wizard
      • Navigating Project KickStart
      • Whats New in Project KickStart Pro 5
      • Whats New in Project KickStart Pro 5 (Pro Users)
      • Compatibility with earlier versions
      • Activating Trial Version
        • Licenses and Support
          • End User License Agreement
          • Customer Support
          • Reporting Technical Issues
          • Register Project KickStart
              • Planning Projects
                • Name Your Project
                • Phases - Step 1 of 2
                • Phases - Step 2 of 2
                • Goals - Step 1 of 3
                • Goals - Step 2 of 2
                • Goals - Step 3 of 3
                • Similar Projects - Step 1 of 2
                • Similar Projects - Step 2 of 2
                • People - Step 1 of 3
                • People - Step 2 of 3
                • People - Step 3 of 3
                • Obstacles - Step 1 of 3
                • Obstacles - Step 2 of 3
                • Obstacles - Step 3 of 3
                  • Assigning People
                    • Assign Tasks to People
                    • Remove People from a Task
                    • Add a New Person or Resource
                    • Edit or Substitute People
                      • Organizing the Project Plan
                        • About Organizing Tasks
                        • Change the Appearance of the Task List
                        • Show or Hide Tasks in the Task List
                        • Move Tasks within the Task List
                        • Outdent and Indent Tasks
                        • Add a Task or Subtask
                        • Edit Tasks
                        • Add Task Notes and Attachments
                        • Add or Change Task Assignments
                        • Add or Change Task Details
                        • Check Spelling
                          • Scheduling Tasks in the Gantt Chart
                            • Scheduling Overview
                              • About Scheduling Tasks
                              • About the Gantt Chart
                              • Autolink tasks (Pro Users)
                              • About Linking Tasks (Pro Users)
                              • Change the Display of the Schedule
                              • Use the Gantt Chart Toolbar
                              • Use the Gantt Chart Toolbar (Pro Users)
                              • Understand Task Data View
                              • Additional Features in Task Data View (Pro Users)
                              • Understand Chart View
                              • Additional Tools in Chart View (Pro Users)
                                • Change Task Dates
                                • Phase Dates Cannot Be Edited
                                • Quick Tour of Working with Linked Tasks (Pro Users)
                                • Link and Unlink Tasks (Pro Users)
                                • Create a Milestone
                                • Change Task Details
                                • Change Details for Linked Tasks (Pro Users)
                                • Reorganize Tasks in Task Data View
                                • Change the Timescale of the Schedule
                                • Specify Working Days
                                • Change the Color of Taskbars
                                • Make Tasks Overlap (Pro Users)
                                • Manage Changes in Your Schedule (Pro Users)
                                  • Managing Libraries
                                    • Use a Library
                                    • Manage a Library
                                    • Manage the People Library
                                    • Import ACT Contacts and Users to the People Library
                                    • Import Outlook Contacts to the People Library
                                    • Import Outlook Contacts via CSV to the People Library (Pro Users)
                                      • Printing Reports
                                        • Printing Dashboards
                                          • Print Reports
                                          • Print Dashboard Reports
                                          • Page Setup
                                          • Save As
                                            • Printing Task Reports
                                              • Print Task Reports
                                              • Print Preview
                                              • Printer Setup
                                              • Page Setup
                                              • Email Task Reports
                                              • Save As HTML
                                              • Save As RTF
                                                • Printing Gantt Chart Reports
                                                  • Print a Gantt Chart
                                                  • Print Preview a Gantt Chart
                                                  • Page Setup
                                                  • Printing to an Adobe PDF file
                                                  • Save Gantt Chart Images
                                                      • Export Project Data
                                                        • Export to ACT
                                                          • Export to ACT 7 and Later
                                                          • Export to ACT 6
                                                            • Export to Microsoft Outlook
                                                            • Export to Microsoft Word
                                                            • Export to Word Processors (Other than Word)
                                                            • Export to Microsoft Excel
                                                            • Export to Microsoft PowerPoint
                                                            • Export to Microsoft Project
                                                            • Export to SureTrak Project Manager
                                                            • Export to FastTrack Schedule
                                                            • Export to Milestones Professional
                                                            • Export to Mindjet MindManager
                                                            • Export to WBS Chart Pro
                                                            • Export MPX Files
                                                              • Reference
                                                                • Menus
                                                                  • File Menu
                                                                  • Edit Menu
                                                                  • View Menu
                                                                  • Tools Menu
                                                                  • Options
                                                                  • Data Menu
                                                                  • Timescale Menu
                                                                  • Help Menu
                                                                    • Shortcuts
                                                                    • Share Project KickStart data
                                                                    • Open a Project
                                                                    • Dedication
                                                                    • Credits and Trademarks
                                                                    • Uninstalling the software
                                                                    • Using Past Projects
Page 7: Project KickStart Help File in PDF format

7

copy Experience In Software Inc 1995 - 2006

Introduction

Welcome to Project KickStart

Whether yoursquore a novice or seasoned pro yoursquoll be amazed at how quickly you can create a thoughtfulcomprehensive task list and project schedule Using Project KickStart you can go from raw idea to aproject task list in 30 minutes You do not need any special project management training to use ProjectKickStart

The first thing youll want to do is

Open a project Click to open one of our sample projects

Start a new project Click to begin planning your own project

Open your last project If youve already created a project click this option to open your most recentproject

After that let Project KickStart show you the way Itrsquos easy to navigate Project KickStart with its intuitivegraphical interface--it feels like a coach is guiding you through each step

Next StepsProject KickStart guides you through the process of planning and scheduling your project On the top ofeach Project KickStart window are instructions explaining what to do Read the instructions enter your dataand then click the Next button in the lower-right corner of the window Additional help is always availablefrom the onscreen Advisor and Project KickStart Help

Sample ProjectsThe sample projects are completed projects that let you get a feel for Project KickStart If you find onesimilar to the project you want to create open it save it with a new name and then customize it to meetyour needs

-o-

8

copy Experience In Software Inc 1995 - 2006

Use Project KickStart to

Project KickStart is organized into three sections planning scheduling and exporting to other programs

Plan The Project KickStart graphical interface acts as a Planning Wizard guiding you through eightsteps for planning your project Some planning steps involve brainstorming to identify tasks that youmight otherwise overlook

Schedule The Project KickStart Gantt chart makes scheduling tasks fast and easy You can printtaskbars in color and save Gantt charts reports as images so you can email them to colleagues orinclude them in a report

Export Communicate your projects in a variety of ways by exporting project data to other applicationsincluding Microsoft Outlook With one mouse click you can include Project KickStart plans in aMicrosoft Word document Excel spreadsheet PowerPoint slide presentation and more

People are using Project KickStart to

Create process templates project reports to-do lists and more

Communicate project details to others through reports email and Gantt chart schedules

Ensure project buy-in by including the needs of team members in your plan

Consider project goals and obstacles in the planning process and prevent surprises later

-o-

9

copy Experience In Software Inc 1995 - 2006

Use the Planning Wizard

Project KickStart uses a Planning Wizard that guides you through eight steps for planning your project Tostep through the wizard click each icon on the Steps bar (on the left side of the Project KickStart window) inorder On each window t ips and advice are always available by clicking the Advisor button You click theNext button to continue

Name Each project has a name To start planning your project give it ashort descriptive name

Phases Consider how your project will break down into major activitiesor phases Start by listing your phases and then list the tasks thatbelong in each phase

Goals Goals are what you hope to accomplish in your project Enter orselect the goals for your project Then you can list any new tasks toachieve each goal

Similar Projects often have tasks in common In this step you canborrow tasks from past projects to help you plan this project Then youcan add any new tasks from a similar project to the phases of yourcurrent project

People List the people groups or things that might provide resourcesfor your project including yourself Then identify any new tasks thesepeople might do or suggest for your project

Obstacles Each project has obstacles you can overcome if youanticipate them List the obstacles you will face in your project and thenidentify any new tasks needed to avoid the obstacles

Assign Assign tasks to people and other resources

Tasks Change the order of your tasks add and delete tasks andcreate subtasks You can also edit tasks change assignments and addnotes

Schedule Schedule the tasks in your project To make schedulingeasier new projects open with a starter schedule beginning todaywhich you can customize to fit your project

-o-

10

copy Experience In Software Inc 1995 - 2006

Navigating Project KickStart

When you use the Planning Wizard you work with a step window similar to the following illustration

Steps bar Click a step button to perform a step in the Planning Wizard The selected button shows yourcurrent step

Name of your project Shows the name entered in the Name step

Menu bar Select options from the menu bar to work with your projects

Toolbar Click buttons to perform common tasks such as saving your project

Step instructions Indicate how to perform the current step

Library button Click to open a library for the current step For example click the Goals Library button toopen a library listing typical project goals

Back and Next buttons Click a button to return to the previous step or continue to the next step in thePlanning Wizard

Advisor button Click to see instructions tips and notes for completing the current step

-o-

11

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5

The following table outlines whatrsquos new in Project KickStart Pro 5

If you own a previous version of Project KickStart yoursquoll notice the new Pro version has a new look and feelAs you begin to check it out yoursquoll soon discover Project KickStart Version 5 is a lot more powerful thanprevious versions and comes with some great new features

FEATURE DESCRIPTION IMPROVED

NEW

Dashboard Reporting

Quickly assess what is due TodayNext Week or Next Month

X

Import Contacts Import from a comma separatedvalue (CSV) file

X

Templates Use as is or customize X

Gantt Chart Greater stability and functionality X

User Interface Contemporary look and colorscheme

X

Preferences Customize look and feel andprogram defaults

X

Productivity Pack Project template Word docs fornewbies

X

Exports Improved Outlook MindManager and ACTimproved data exchange

X

-o-

12

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5 (Pro Users)

This feature is available only in Project KickStart Professional

The following table outlines whatrsquos new in Project KickStart Pro 5

FEATURE DESCRIPTION IMPROVED NEW

Gantt Chart Task dependencies in Gantt chart X

Link tasks Show task dependencies X

Unlink tasks Remove task dependencies X

Add predecessors Add task predecessors X

Add successors Add task successors X

Project Coordination Link to GoToMeeting for onlinemeetings on projects

X

Project KickStart Pro now includes dependencies on the Gantt chart This sophisticated scheduling andproject management tool is new to Project KickStart Pro and is designed to make complex projectscheduling easy and straightforward

Use dependencies to handle scheduling demands delays and surprises without modifying every task inyour project Dependencies let you make adjustments as events change giving you a more robust scheduleand the opportunity to conduct what-if analysis

Suppose you are managing a landscaping project involving subcontractors and dozens of tasks One ofyour first tasks is to pave a path with flagstones but the shipment of flagstones is two days late Usingdependencies you can delay the path-paving task in a couple of clicks and Project KickStart Proautomatically updates the schedule for the remaining tasks

Although dependencies meet your advanced scheduling needs the Project KickStart Pro approach todependencies keeps them as simple as possible If you want to link a couple of tasks which are dependenton one another you can simply highlight the tasks and click the link icon

If you select the option of Autolinking tasks then when you display the Gantt chart the first time all tasksare pre-linked allowing you to adjust durations schedules of individual tasks and time between taskswhich is called Lead Time in Project KickStart Pro

Unlike other project management programs such as Microsoft Project Project KickStart Pro does notburden you with complicated error messages and various types of dependencies It provides only one typeof dependency finish-to-start which is the most common type This means you can fine-tune your scheduleas soon as you open the Gantt chartmdashwithout having to learn technical terms or advanced projectmanagement techniques

The Project Coordination functionality that we are providing is through GoToMeeting and is a chargedservice

Note

These features are in addition to those listed on the Whatrsquos New in Project KickStart 5 page

-o-

13

copy Experience In Software Inc 1995 - 2006

Compatibility with earlier versions

Project KickStart 5 can open and save projects in Project KickStart 4 prx file format (Same as ProjectKickStart 5)

Project KickStart 5 can open and convert projects saved in Project KickStart 3 prj file format You need tohave a licensed copy of Project KickStart 3 on your system to make the conversion

To open a prj project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click prj file type3 Navigate to the folder that contains the prj file Generally prj files are stored in cprogram filesProject

KickStart 34 Double-click the name of the file

Tips

The tasks in the converted Project KickStart 5 file will have the same start and finish dates and samedurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way (ie as working days) To have weekends as non working days click the Change WorkingSchedule button on the Gantt chart toolbar and mark weekends as non working

Note

Project KickStart 5 does not open and convert prj files from Project KickStart 1 or 2

-o-

14

copy Experience In Software Inc 1995 - 2006

Activating trial version

You may have obtained a FREE 20-day trial version of Project KickStart 5 from our website or from areseller

To convert your Trial Version to a Full Version youll need to purchase a License Key and to activate thesoftware

To activate Project KickStart 5 trial1 Start the Project KickStart trial

2 If you have not purchased your License Key yet click the Buy button to purchase online3 If you have purchased a License Key click the Activate button and copy and paste the License Key

that you received when you purchased Project KickStart as well as your name and email

15

copy Experience In Software Inc 1995 - 2006

4 You must be connected to the Internet and you must tell your Firewall to allow communication forPKS5Kickstartexe

Tip

Your License Key allows 2 activations per user One is for your primary computer and one is for asecond computer you use such as your laptop or home computer

-o-

16

copy Experience In Software Inc 1995 - 2006

Licenses and Support

End User License Agreement

EXPERIENCE IN SOFTWARE INC END USER LICENSE AGREEMENT AND WARRANTYDISCLAIMER

PROJECT KICKSTARTtrade STANDARD 5 AND PRO 5 EDITIONS

NOTICE This is a legally binding contract between you the end user and EXPERIENCE IN SOFTWAREINC

EXPERIENCE IN SOFTWARE INC (EIS or LICENSOR) LICENSES THE ENCLOSED SOFTWARETO YOU (USER or LICENSEE) ONLY UPON THE CONDITION THAT YOU ACCEPT ALL OF THETERMS CONTAINED IN THIS LICENSE AGREEMENT PLEASE READ THE TERMS CAREFULLY BYOPENING THIS PACKAGE BREAKING THE SEAL CLICKING ON THE ldquoAGREErdquo OR ldquoYESrdquo BUTTONOR OTHERWISE INDICATING ASSENT ELECTRONICALLY OR LOADING THE SOFTWARE YOUAGREE TO THE TERMS AND CONDITIONS OF THIS AGREEMENT IF YOU DO NOT AGREE TOTHESE TERMS AND CONDITIONS CLICK ON THE ldquoI DO NOT AGREErdquo ldquoNOrdquo BUTTON OR MAKE NOFURTHER USE OF THE SOFTWARE IF YOU DO NOT AGREE TO THESE TERMS THEN EIS ISUN-WILLING TO LICENSE THE SOFTWARE TO YOU IN WHICH EVENT YOU SHOULD RETURN THEFULL PURCHASED PRODUCT WITH PROOF OF PURCHASE TO LICENSOR OR THE DEALER FROMWHOM IT WAS ACQUIRED WITHIN 15 DAYS OF PURCHASE AND YOUR MONEY WILL BEREFUNDED

LICENSE AND WARRANTY

The software that accompanies this license (Software) is the property of EIS and is protected by copyrightand other intellectual property law Although EIS at all times owns the Software you will have certain rightsto use the Software after your acceptance of this license Except as may be modified by an addendumwhich may accompany or be added to this license your rights and obligations with respect to the use of thisSoftware are as follows

You may

(i) install and use one copy of the specified edition of Software and documentation on a single computerand only by one user (ldquoPrimary Userrdquo) If you have purchased multiple licenses for the Software asindicated as Quantity or Number of Licenses on the Invoice or electronic confirmation issued by EIS orits Resellers then at any time you may have as many copies of the Software in use as you have licenses The Software is ldquoin userdquo on a computer when it is loaded into the temporary memory (ie RAM) or installedinto the permanent memory (eg hard disk CD-ROM or other storage device) of that computer

(ii) install and use a second copy of the Software on a second computer for the limited and exclusive use ofthe Primary User

(iii) use the Software on a network provided that Licensee has a licensed copy of the Software for eachnamed user that can access the Software over that network

(iv) make one copy of the Software for archival purposes or copy the Software onto the hard disk of yourcomputer and retain the original for archival purposes

(v) after written notice to EIS transfer the Software on a permanent basis to another person or entityprovided that you retain no copies of the Software and the transferee agrees to the terms of this agreement

You may not

(i) rent lease copy distribute license or otherwise transfer the Software or its documentation to any otherparty Licensee may make a reasonable number of back-up copies for archival purposes only TheSoftware contains copyrighted material trade secrets and other proprietary material If Licensee has theright to duplicate the Software for multiple Users then Licensee must reproduce on all such copies of theSoftware the copyright notices and any other proprietary legends that were on the original copy of theSoftware or

(ii) decompile reverse engineer disassemble translate make any attempt to discover the source code ofthe Software or otherwise reduce the Software to a human perceivable form or modify network or create

17

copy Experience In Software Inc 1995 - 2006

derivative works based upon the Software or the documentation in whole or in part nor permit any otherparty to do so

Notwithstanding anything herein if the Software is lawfully acquired outside of the United States within ajurisdiction which is a member of the European Union subject to the EEC Council Directive 91250EEC ofMay 14 1991 Licensee agrees that within that jurisdiction it shall not and shall not allow any party onLicensees behalf to attempt to reverse engineer or decompile the Software into another computerlanguage except as expressly and specifically provided in the EEC Council Directive 91250EEC of May14 1991 Any and all information obtained during such lawful reverse engineering andor decompilingactivities including but not limited to the organization logic algorithms and processes of the Softwareshall be deemed to be the confidential and proprietary information of EIS

Licensee shall not make copies of the copyrighted Software documentation without the prior writtenpermission of EIS provided that for electronic transactions Licensee may make one (1) hard copy of suchdocumentation for each User

Intellectual Property and Duplication of Software

The Software contains copyrighted material trade secrets and other proprietary material If Licensee hasthe right to duplicate the Software for multiple Users then Licensee must reproduce on all such copies ofthe Software the copyright notices and any other proprietary legends that were on the original copy of theSoftware

Upgrades

To use a Product identified as an upgrade you must first be licensed for the product identified by EIS aseligible for the upgrade After upgrading you may no longer transfer the product that formed the basis foryour upgrade eligibility to another person or entity

Technical Support

Licensee must register the Software in order to be eligible for free technical support (including installationand registration of the product) during the first 90 days after purchase

Thirty Day Money Back Guarantee

If you are the original Licensee of this copy of the Software and are dissatisfied with it for any reason youmay return the complete product together with your receipt to EIS or an authorized dealer postageprepaid for a full refund at any time during the thirty-day period following the delivery to you of thePurchased Software

Export Law Assurances

You are responsible for complying with all trade regulations and laws both foreign and domestic Youacknowledge that none of the Software or underlying information or technology may be downloaded orotherwise exported or re-exported (i) into Afghanistan (Taliban-controlled areas) Cuba Iran Iraq LibyaNorth Korea Serbia (except Kosovo) Sudan and Syria or any other country subject to a US embargo or(ii) to anyone on the US Treasury Departments list of Specially Designated Nationals or the USCommerce Departments Denied Parties List or Entity List By using the Software you are agreeing to theforegoing and are representing and warranting that (i) no US federal agency has suspended revoked ordenied you export privileges (ii) you are not located in or under the control of a national or resident of anysuch country or on any such list and (iii) you will not export or re-export the Software to any prohibitedcounty or to any prohibited person entity or end-user as specified by US export controls as defined byEAR 15 CFR Parts 730-774 and BXA (httpwwwbxadocgov)

Data Collection and Privacy Policy

You acknowledge and agree that EIS may collect and retain information about you such as your nameaddress and e-mail address You also understand that EIS may employ other companies to performfunctions on our behalf such as fulfilling orders delivering packages sending postal mail and e-mailproviding marketing assistance and processing credit card payments These companies may have accessto personal information needed to perform their functions and may not use such information for otherpurposes By assenting to this agreement you agree that you have read and understand our Privacy PolicyFor more detailed information httpwwwprojectkickstartcomhtmlprivacy_statementhtm

Termination

This License is effective until terminated Licensee may terminate this License at any time by destroying allcopies of the Software and its documentation This License will terminate immediately without notice from

18

copy Experience In Software Inc 1995 - 2006

EIS if Licensee fails to comply with any provision of this License Upon termination Licensee must destroyall copies of the Software and its documentation and cease and desist from any further use of the Software

Limited Warranty

EIS warrants that the media on which the Software is distributed will be free from defects and that theSoftware shall perform substantially as described in its documentation for a period of sixty (60) days frompurchase Your sole remedy in the event of a breach of this warranty will be that EIS will replace anydefective media returned to EIS within the warranty period EIS does not warrant that the Software willmeet your requirements or that operation of the Software will be uninterrupted or that the Software will beerror-free

THE ABOVE WARRANTY IS EXCLUSIVE AND IN LIEU OF ALL OTHER WARRANTIES WHETHEREXPRESS OR IMPLIED INCLUDING THE IMPLIED WARRANTIES OF MERCHANTABILITY FITNESSFOR A PARTICULAR PURPOSE AND NONINFRINGEMENT OF INTELLECTUAL PROPERTY RIGHTSTHIS WARRANTY GIVES YOU SPECIFIC LEGAL RIGHTS YOU MAY HAVE OTHER RIGHTS WHICHVARY FROM STATE TO STATE AND COUNTRY TO COUNTRY

Disclaimer of Damages

REGARDLESS OF WHETHER ANY REMEDY SET FORTH HEREIN FAILS OF ITS ESSENTIALPURPOSE IN NO EVENT WILL EIS OR ITS RESELLERS BE LIABLE TO YOU FOR ANY SPECIALCONSEQUENTIAL INDIRECT OR SIMILAR DAMAGES INCLUDING BUT NOT LIMITED TO ANY LOSTPROFITS OR LOST DATA ARISING OUT OF THE USE OR INABILITY TO USE THE SOFTWARE EVENIF EIS HAS BEEN ADVISED OF THE POSSIBILTIY OF SUCH DAMAGES SOME STATES DO NOTALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FOR INCIDENTAL OR CONSEQUENTIALDAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAY NOT APPLY TO YOU IN NO CASESHALL EISS ITrsquoS RESELLERrsquoS LIABILITY EXCEED THE PURCHASE PRICE FOR THE SOFTWARE

SOME STATES AND COUNTRIES INCLUDING MEMBER COUNTRIES OF THE EUROPEANECONOMIC AREA DO NOT ALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FORINCIDENTAL OR CONSEQUENTIAL DAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAYNOT APPLY TO YOU

The disclaimers and limitations set forth above will apply regardless of whether you accept the Software

US Government Restricted Rights

DISTRIBUTION TO THE US GOVERNMENT This Software is commercial software developedexclusively at private expense This Software and the documentation are provided with RESTRICTEDRIGHTS applicable to private and public licenses alike Use duplication or disclosure by civilian agenciesof the US Government shall be in accordance with the Commercial Computer Software-Restricted Rightsclause at FAR 52227-19 Use duplication or disclosure by Department of Defense agencies is subjectsolely to the terms of this software licensing agreement pursuant to DFARS 2277202Contractormanufacturer of the Software is EXPERIENCE IN SOFTWARE INC 2029 Durant AveBerkeley CA 94704 USA

General

This Agreement shall be governed by the laws of the State of California without giving effect to principles ofconflict of laws You hereby consent to the exclusive jurisdiction and venue of the state courts sitting in SanFrancisco County California or the federal courts in the Northern District of California to resolve anydisputes arising under this Agreement This Agreement contains the complete understanding between theparties with respect to the subject matter hereof and supersedes all prior or contemporaneous Agreementsor understandings whether oral or written You agree that any varying or additional terms contained in anypurchase order or other written notification or document issued by you in relation to the Software licensedhereunder shall be of no effect No provision hereof shall be deemed waived or modified except in writing No EIS dealer agent or employee is authorized to make any amendment to this Agreement

The intellectual property protections the disclaimers of warranties and the limitation of damages shallsurvive termination The failure or delay of EIS to exercise any of its rights under this Agreement or uponany breach of this Agreement shall not be deemed a waiver of those rights or of the breach If any provisionof this Agreement is held invalid the remainder of this Agreement will remain in full force and effect

Should you have any questions concerning this Agreement or if you desire to contact EIS for any reasonplease write to EXPERIENCE IN SOFTWARE INC 2029 Durant Ave Berkeley CA 94704 USA

-o-

19

copy Experience In Software Inc 1995 - 2006

20

copy Experience In Software Inc 1995 - 2006

Customer Support

When you need help in solving a problem with the software Experience In Software is available to assistyou First check this help file for information on the part of the program you are having a problem withAlso take a look at the Web site for late-breaking technical support information wwwprojectkickstartcomsupporttechnical_supportcfm If you are a regustered user you can obtain support in the following ways

Web httpwwwprojectkickstartcomsupportemail_supportcfm E-mail supportprojectkickstartcom

Hours 900 am to 500 pm Pacific time Monday - Friday

To make the support process more efficient have the following information ready for the support staff

Provide your name phone number and email address

Describe the problem including any error messages

If reporting a potential bug describe what you did immediately before seeing the bug

Provide the Project KickStart version number and Build Date (Click Help on the menu bar and thenclick About Project KickStart)

Identify the version of Windows (Windows Vista etc) you are using

Notes

Our policy is to respond to support email within two business days If you have not received aresponse please double check that spam filters are blocking our messages to you If you maintain anincoming whitelist please allow all messages from the projectkickstartcom domain

Support is available in English only If you purchased a translated version please contact your localreseller for help in other languages

See Also

Reporting Technical Issues

-o-

21

copy Experience In Software Inc 1995 - 2006

Reporting Technical Issues

If Project KickStart 5 detects an error it will write a log of technical issues and then create a temporarymenu to the right of the Help menu which says Send Log to Technical Support You should immediatelyclick the menu and then click Yes to send the error log to us

Please fill in your email address so that we can get back to you with any questions about what caused theerror

Tip

If you have an Internet Security Program such as Norton Internet Security please allowPKS5Kickstartexe to communicate with the Internet to report the error

-o-

22

copy Experience In Software Inc 1995 - 2006

Register Project KickStart

To print this page click the Print button on the Help window toolbar

Register Project KickStart 5 for technical support upgrade information and software discounts You canregister by completing printing and then sending or faxing this form to Experience In Software You canalso register online at httpwwwprojectkickstartcomsupportregiscfm

Name _______________________________________________________

Title _______________________________________________________

Company _______________________________________________________

Address _______________________________________________________

CityStateZip ______________________________________________________

Country _______________________________________________________

Day Phone _______________________________________________________

Fax _______________________________________________________

E-mail _______________________________________________________

Purchased from __ Experience In Software __ Other ____________________

Number of people in company _ 1 to 25 _ 26 to 100 _ 101 to 1000 _ Over 1000

Which industry do you work in ______________________________________

Interested in a project management workshop for your company __ Yes __ No

Comments _______________________________________________________

_________________________________________________________________

_________________________________________________________________

Experience In Software 2029 Durant Ave Berkeley CA 94704

Send or FAX to (510) 644-3823

-o-

23

copy Experience In Software Inc 1995 - 2006

Planning Projects

Name Your Project

Before you start thinking about the tasks in your project yoursquoll want to give your project an appropriate titleIf you open an existing project you might want to edit or change the name of your project

To name your project1 In the Type a name for your project text box enter a name2 Click the Next button

Tips

You can enter up to 58 characters and more than one

Use short descriptive project names such as ldquoCompany Web Siterdquo

Avoid vague project names such as ldquoDatabase Projectrdquo or ldquoCDP-7rdquo especially if you plan to circulatereports to others

Enter your project title using uppercase letters if you want the title to stand out in reports

One way to reuse your projects is to open an existing project and then change its name in this stepAfter saving the project with a different name you can modify details to customize the project

See Also

Use the Planning Wizard

-o-

24

copy Experience In Software Inc 1995 - 2006

Phases - Step 1 of 2

After naming your project the next step in the Planning Wizard is to identify the major activities in yourproject Using phases helps organize tasks so that an obviously early task such as ldquoOrganize materialsrdquoappears before a later task such as ldquoReview final draftrdquo

To enter phases1 Type each phase one per line

OrClick the Phases Library button The Phases Library contains typical phases that many organizationsuse in the early middle and late stages of their projects Drag an entry from the Phases Library to thelist and then click the OK button to close the Phases Library

2 To insert a phase in the middle of the phases list click where you want to insert a new blank line andthen press the Insert keyTo edit the phase text double-click the phase

Tips

Start each phase name with an action verb as in ldquoBuild systemrdquo or ldquoWrite reportrdquo

Use actions that have clearly defined beginnings middles and ends For example you can scheduletasks like ldquoTest prototyperdquo more easily than tasks like ldquoPurchase high-quality partsrdquo

Note

Youll have the opportunity to edit phases later in the Tasks step For now continue planning thephases in your project

See Also

Use the Planning Wizard

Use a Library

Move Tasks within the Task List

-o-

25

copy Experience In Software Inc 1995 - 2006

Phases - Step 2 of 2

For each phase list all of the tasks that could be performed during that phase You can refine and organizethe tasks later in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each phase1 Type the tasks associated with the phase displayed in the Tasks for phase text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next phase in your project click the Next button If you prefer to work out oforder click the Tasks for phase list arrow and then click the phase you want

3 When you are finished entering tasks for the last phase in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

26

copy Experience In Software Inc 1995 - 2006

Goals - Step 1 of 3

Enter the goals for your project the objectives you hope to accomplish Then you can brainstorm anyadditional tasks that will help you meet these goals

To enter goals1 Type each goal one per line

OrThe Goals Library contains typical sample goals that you can customize Drag an entry from the GoalsLibrary to the list and then click the OK button to close the Goals Library

2 To insert a goal in the middle of the goals list click where you want to insert a new blank line and thenpress the Insert keyTo edit the goal text double-click the goal

3 Click the Next button

Tips

List goals that apply to the entire project such as Develop a high-quality system A goal such as Getthe contract signed applies only to an early phase

Write goals as actions you can measure For example Complete the project for $75000 or less ismore concrete and specific than Complete the project within budget Numbers make goal statementsreal

If youre not sure how to measure a goal use a range as in About 15 - 25 people will use the results ofthe project

See Also

Use the Planning Wizard

Use a Library

-o-

27

copy Experience In Software Inc 1995 - 2006

Goals - Step 2 of 3

For each goal list any new tasks needed to accomplish that goal You can refine and organize the taskslater in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each goal1 Type the tasks for accomplishing the goal displayed in the For the goal text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next goal in your project click the Next button If you prefer to work out of orderclick the For the goal list arrow and then click the goal you want

3 When you are finished entering tasks for the last goal in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

28

copy Experience In Software Inc 1995 - 2006

Goals - Step 3 of 3

After you identify new tasks for your project assign each new task to an appropriate phase

To assign new tasks to phases1 Click a task in the New tasks to achieve goals list (on the left)2 Click one or more phases in the Assign them to Phases list (on the right) to which the task belongs A

checkmark appears next to tasks youve assigned

If a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Note

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

29

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 1 of 2

Projects often have tasks in common The Similar Projects step makes it easy for you to borrow tasks fromother projects and add them to your current project

By default this step shows the Project KickStart (PRX) projects stored in the same folder as the currentproject including sample projects and those you already created

To select similar projects1 Review the projects in the list To sort the project names alphabetically click the Project Name header

Click the Project Name header again to sort the names in reverse order2 Click one or more projects in the list that contain tasks you want to use in the current project A

checkmark appears next to the projects you selected3 To list projects stored in a different folder on your system click the Browse button and then navigate to

the folder you want4 Click the Next button

If no projects seem related to your current project skip this step for now

Tips

The Similar Projects step becomes more helpful the more you use Project KickStart Every time yousave a project it becomes available for future use

Many projects share the same phases and tasks such as those for setting up a contract or purchasingequipment You can use Project KickStart to create these mini-projects or templates and then importtheir tasks into a new project during the Similar Projects step

-o-

30

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 2 of 2

After you select one or more projects containing tasks you might want to use assign those borrowed tasksto a phase in this project

To assign borrowed tasks to phases1 Click a task in the list on the left If a task includes subtasks click the plus icon to expand the list Click

the minus icon if you want to hide the subtasks To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more phases in the Assign tasks to phase(s) of your project list (on the right) to whichthe task belongs A checkmark appears next to tasks youve assigned

3 To assign one or more tasks to a new phase select the tasks click ltNew Phasegt in the Assign tasksto Phases of your project list and then type a name for the new phase

4 To select tasks from another project you selected as similar click the Tasks from Similar Projects listarrow click the project you want and then assign the tasks to phases

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also Edit Tasks

-o-

31

copy Experience In Software Inc 1995 - 2006

People - Step 1 of 3

Enter the names or descriptions of the people involved in your project Include key decision makers suchas executives or customers who must approve or consult with you about the project These are yourprojects resources In the next People step youll identify new tasks associated with these resources

To enter people1 Type each name or description one per line

OrIf you have stored information about people and other resources in the People Library click the PeopleLibrary button drag an entry from the library to the list and then click the OK button to close thePeople Library

2 To edit the people text double-click the name or description3 Click the Next button

Tips

Be consistent with the resource names in your projects For instance avoid using Richard in oneproject and Dick in another project when referring to the same person

Include names for people teams (such as Quality control team) departments (such as Manufacturing)companies (such as Acme Widgets Corp) or even equipment (such as wheat thrasher)

Note

Add people and other resource information to the People Library so that you can quickly drag resourcesfrom the library to any project You can even import people from your Outlook and ACT address books

See Also

Manage the People Library

Import ACT Contacts and Users to the People Library

-o-

32

copy Experience In Software Inc 1995 - 2006

People - Step 2 of 3

Now that you have defined the people needed to complete your project list any new tasks that eachresource might suggest or require

To enter new tasks for each person1 Type the new tasks associated with the person displayed in the Tasks For text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next person in your project click the Next button If you prefer to work out oforder click the Tasks For list arrow and then click the person you want

3 When you are finished entering new tasks for the last person in your project click the Next button tocontinue in the Planning Wizard

Tips

This step provides a good opportunity to get input from your resources directly and make sure theproject plan reflects the views of everyone on the team

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo Write the tasks roughly in the order that you will complete them You can reorganize the tasks later in

the Tasks step

Note

You assign people to tasks in the Assign Tasks and Schedule steps

See Also

Use a Library

Move Tasks within the Task List

Assign Tasks to People

-o-

33

copy Experience In Software Inc 1995 - 2006

People - Step 3 of 3

After you identify new tasks associated with the people in your project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by people list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

34

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 1 of 3

Every project has obstacles and risks that can affect its success List the major obstacles you face incompleting your project Then you can brainstorm any additional tasks that can help you overcome orminimize these problems

To enter obstacles1 Type each obstacle one per line

OrThe Obstacles Library contains typical sample obstacles that you can customize Drag an entry fromthe Obstacles Library to the list and then click the OK button to close the Obstacles Library

2 To insert an obstacle in the middle of the obstacles list click where you want to insert a new blank lineand then press the Insert key

3 To edit the obstacle text double-click the obstacle4 Click the Next button

Tips

Be creative when thinking of obstacles Highly imaginative obstacles can suggest realistic tasks Forexample Project manager kidnapped by aliens can lead to Project manager out of town forconference In Obstacles step 2 of 3 you can add the realistic activities as tasks You can delete theunrealistic obstacles later by returning to Obstacles step 1 of 3

Avoid listing too many obstacles even if they are realistic Hard core pessimists find it hard to getanything done

Edit and update the Obstacles Library so that you can quickly drag obstacles from the library to anyproject in your organization

See Also

Use a Library

-o-

35

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 2 of 3

After identifying the obstacles to completing your project determine how you can avoid these stumblingblocks List any new tasks you need to overcome or avoid each obstacle In this way you are developing acontingency plan for your project

To enter new tasks for each obstacle1 Type the new tasks associated with the obstacle displayed in the Obstacle text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next obstacle in your project click the Next button If you prefer to work outof order click the Obstacle list arrow and then click the obstacle you want

3 When you are finished entering new tasks for the last obstacle in your project click the Next button tocontinue in the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

You can reorganize the tasks and add notes later in the Tasks step

See Also

Use a Library

Move Tasks within the Task List

Add Task Notes and Attachments

-o-

36

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 3 of 3

After you identify new tasks for overcoming the obstacles to completing project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by obstacles list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

3 Click the Next button

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

37

copy Experience In Software Inc 1995 - 2006

Assigning People

Assign Tasks to People

After youve identified people working on your project you can assign tasks to each person or otherresource

To assign tasks to people1 Click a phase or task in the For each phase or tasks list (on the left)

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more people in the Assign some people list (on the right) who will perform the task Acheckmark appears next to tasks youve assigned

3 To assign a selected task to all of the people in your project click the All button4 To assign one or more tasks to a new person select the tasks click ltNew Persongt in the Assign

some people list and then type a name for the new person

To unassign a task

To unassign a task click the task and then click the highlighted person from which you want to removethe task You can assign that task to a different person if necessary You can also click the All buttonto remove a task from all of its assignments at the same time

Tip

Some users like to skip to the Tasks step before performing the Assign step That way they can edittheir list of tasks before assigning people and resources This helps them focus the project and givesthem a clearer idea of what must be done before committing resources

Notes

You can also assign tasks to people in the Tasks step and the Schedule step

You can assign tasks to non-personnel resources such as equipment (a CAD system or back hoe)facilities (a classroom or hotel) services (lab work or insurance) or materials (lumber or officesupplies) just as you assign tasks to people Click ltNew Persongt to add a new resource to the list

See Also

Remove People from a Task

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

38

copy Experience In Software Inc 1995 - 2006

Remove People from a Task

After assigning tasks you might need to remove people from a task or unassign them

To remove people from a task (unassigning)1 Click a phase or task in the For each phase or tasks list (on the left)

The people assigned to that phase or task are highlighted in the Assign some people list (on theright)

2 Click a highlighted person to remove or unassign that person from the taskWhen the person is no longer highlighted they are not assigned to the selected task

See Also

Assign Tasks to People

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

39

copy Experience In Software Inc 1995 - 2006

Add a New Person or Resource

If you realize that you want to assign some tasks to a person not included in the Assign some people listyou can add that person and assign tasks in the same step You can also add non-personnel resourcessuch as such as equipment (a CAD system or back hoe) facilities (a classroom or hotel) services (lab workor insurance) or materials (lumber or office supplies)

To add a new person or resource1 Select one or more phases or tasks in the For each phase or tasks list (on the left) 2 Click ltNew Persongt in the Assign some people list and then type a name for the new person or

resourceThis adds the new person or resource to the list and assigns the selected tasks to them

See Also

Assign Tasks to People

Remove People from a Task

Edit or Substitute People

Add or Change Task Assignments

-o-

40

copy Experience In Software Inc 1995 - 2006

Edit or Substitute People

If the people or resources in your project change you can replace them or edit their names anddescriptions

To edit or substitute people1 Click the People icon

You return to People step 1 of 32 In the list of people defined for the project double-click the person you want to edit or replace or click

the name and press F23 Edit the name or description of the person

When you return to the Assign step the name of the person appears as you changed it

See Also

Assign Tasks to People

Remove People from a Task

Add a New Person or Resource

Add or Change Task Assignments

-o-

41

copy Experience In Software Inc 1995 - 2006

Organizing the Project Plan

About Organizing Tasks

In the Tasks step you work with an outline of your project plan Here you can easily edit and reorganizetasks spell check and even add notes and attachmentsClick the following illustration to see tips for using this window

Edit the Task List to Consolidate and delete tasks Add subtasks Add or change task assignments Add follow-up notes to tasks Add or change attachments Review the order of the tasks in each phase and move tasks up or down so that they progress

sequentially Review task descriptions to make sure they are clear and that all the team members will understand

them Convert vague tasks such as reminders and open issues to task notes

Notes

Some users like to revise their Task List before they assign resources You can go to the Task List atany time while you are using Project KickStart

Each project created with Project KickStart can contain up to 1000 tasks

See Also

Change the Appearance of the Task List

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

Add Task Notes and Attachments

Add or Change Task Assignments

Add or Change Task Details

-o-

42

copy Experience In Software Inc 1995 - 2006

43

copy Experience In Software Inc 1995 - 2006

Change the Appearance of the Task List

You can change the appearance of the Task List so you can work with it more effectively

To add a column

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task ListBy default the Task List shows the Task Name Assignments and Notes columns You can also showCost and Done columns

To hide a column

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

To move a column

Drag a column heading to a new position in the Task List

To change the column width

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Show or Hide Tasks in the Task List

-o-

44

copy Experience In Software Inc 1995 - 2006

Show or Hide Tasks in the Task List

To hide tasks or subtasks

To hide the subtasks for a task click the minus icon next to the task

To hide all the tasks in the Task List and show only phases click all the minus icons next to thephases

To show tasks or subtasks

To show the subtasks for a task click the plus icon next to the task

To show the tasks for a phase click the plus icon next to the phase

See Also

Change the Appearance of the Task List

-o-

45

copy Experience In Software Inc 1995 - 2006

Move Tasks within the Task List

In the Tasks step you can reorganize the tasks in your project so that they better represent the work youand your team plan to do In particular you should review the order of the tasks in each phase and move tasks up and down so thattasks follow in a sequential order Use the Up and Down Arrow buttons to move the tasks

To reorder tasks1 Click a task or phase to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youmove must be next to each other

2 Click the Up Arrow button to move a task up one rowOrClick the Down Arrow button to move a task down one row

Note

When you move a bolded phase you move the phase and all of its tasks at the same time

See Also

Outdent and Indent Tasks

-o-

46

copy Experience In Software Inc 1995 - 2006

Outdent and Indent Tasks

Subtasks are smaller parts of tasks Use subtasks when you need to break tasks down into moremanageable parts In the Task List you can turn a task into a subtask by indenting it You can also add anew subtask to the Task ListIf your Task List contains subtasks you can turn a subtask into a task by outdenting itUse the Outdent and Indent buttons to promote (outdent) and demote (indent) tasks

To promote and demote tasks1 Click a phase task or subtask to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youpromote or demote must be next to each other

2 Click the Outdent button to promote the selected tasksOrClick the Indent button to demote the selected tasksYou can also right-click an item in the Task List and then click Outdent or Indent on the shortcut menu

Tips

When you promote (outdent) a task it becomes a phase and its subtasks become tasks When youpromote a subtask it becomes a task

When you demote (indent) a phase it becomes a task and its tasks become subtasks When youdemote a task it becomes a subtask

Notes

You can have up to 10 levels of subtasks in your project

Use Task Notes instead of subtasks for task comments or additions that are not actually work items

See Also

Move Tasks with the Task List

Add a Task or Subtask

-o-

47

copy Experience In Software Inc 1995 - 2006

Add a Task or Subtask

If you realize you want to add another task to the Task List use the Add Task button A subtask is a smaller part of a task Use subtasks when you need to break tasks down into moremanageable partsTo add a subtask use the Add Subtask button

To add a task1 Click a task and then click the Add Task button right-click a task and then click Add Task on the

shortcut menu or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskProject KickStart numbers the new task in the proper sequence

To add a subtask1 Click a task and then click the Add Subtask button right-click a task and then click Add Task on the

shortcut menu or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtask3 Project KickStart numbers the new subtask in the proper sequenceNote

To add a new phase click a phase and then click the Add Task button

See Also

Outdent and Indent Tasks

-o-

48

copy Experience In Software Inc 1995 - 2006

Edit Tasks

Edit tasks in the Task List to fine tune your project You can edit the names of the phases tasks andsubtasks delete tasks and cut copy and paste task information

To edit task names1 Click the phase task or subtask you want to edit and then press the F2 key2 Type to edit the text3 To undo an edit click the Undo button

To delete a task

Click the task you want to delete and then press the Delete key or click the Delete button Or

Right-click a task and then click Delete Row on the shortcut menu

To cut copy and paste tasks1 Select the tasks you want to cut or copy Use Shift-click or Ctrl-click to select more than one task

2 Click the Cut button (Ctrl-X) or click the Copy button (Ctrl-C )

3 Click where you want to insert the tasks and then click the Paste button (Ctrl-V)

Tip

If your project includes some of the same tasks repeated in different phases save time by copying rowsof tasks and pasting them to another phase

Notes

You can also edit task names using the Task Information dialog box To open this dialog boxdouble-click a task or click a task and then click the Edit Task Information button

If you delete a phase you also delete its tasks and subtasks If you delete a task you also delete itssubtasks Project KickStart warns you before deleting tasks or subtasks and gives you a chance tocancel the deletion

See Also

Add Task Notes and Attachments

Add or Change Task Assignments

-o-

49

copy Experience In Software Inc 1995 - 2006

Add Task Notes and Attachments

You might find that some of your tasks are actually more notes than tasks For example Remember tocheck Daves specifications might work better as a note than a task especially if it could take several daysto catch up with Dave but only a few minutes to review his specs By using notes you clarify your projectand increase your chances for success An attachment is a document graphic or any other type of file related to a task For example to a tasksuch as Review proposal you can attach the proposal document Or you can attach a hyperlink to a pageon a web site

To add a note or attachment to a task1 Double-click the Notes column next to the task The Task Information dialog box opens to the Notes

and Attachments tab2 In the Enter a Note box type in or edit the task note (Press Enter to insert line break)3 To attach a file click the Add Files button In the Select File to Attach dialog box navigate to the file

you want and then click the Open button The filename appears in the Add Attachments box with apaperclip icon

4 To insert a hyperlink click the Add URL button In the Insert Hyperlink dialog box type in the URL youwould like to link to The URL appears in the Add Attachments box with a paperclip icon

5 Click the OK button

To open or remove an attachment1 Open the Notes and Attachments tab in the Task Information dialog box2 To open an attachment double-click the filename in the Add Attachments box3 To delete an attachment click the attachment in the Add Attachments box and then click the Remove

button

To change a task into a task note1 Copy (Ctrl-C) the text of the task you want to change into a note2 Double-click the task to which you want to add the note3 In the Task Information dialog box click the Notes and Attachments tab and add paste the text in the

Enter a Note box Close the Task Information dialog box4 In the Task Name column delete the original task that how appears as a note for a different task

Tips

Use notes to keep track of the operational details of a project the little nagging details that are criticalto success

Although the Task List provides plenty of room for notes it is best to keep your notes concise

Some tasks might benefit from instructional notes those that explain what to do in a task or how tosuccessfully complete a task

You can also include a hyperlink in a note by typing httpxxx (where xxx is an e-mail or Web address)In Outlook Word Excel or your browser the hyperlink will be active You can click the link to godirectly to that site or to send an e-mail to that address

Note

You can also open the Notes and Attachments tab in the Task Information dialog box by clicking atask and then clicking the Edit Notes and Attachments button or by double-clicking a task to openthe Task Information dialog box and then clicking the Notes and Attachments tab

See Also

Edit Tasks

Add or Change Task Assignments

Change Task Details in the Gantt chart

50

copy Experience In Software Inc 1995 - 2006

-o-

51

copy Experience In Software Inc 1995 - 2006

Add or Change Task Assignments

The Assignments column in the Task List shows the people and other resources assigned to each task

To add or change a task assignment1 Double-click the Assignments column next to the task The Task Information dialog box opens to the

Assignments tabThe Assignments tab lists all of the people and resources in your project If this task is already assignedto people they are highlighted on the Assignments tab

2 To assign this task to another person or resource click the resource name in the Assignments list3 To remove (unassign) this task from a person or resource click a highlighted name in the Assignments

list4 To add a person and assign the task at the same time click ltNew Persongt in the Assignments list

and then enter the name of the new person5 Click the OK button

Note You can also open the Task Information dialog box by clicking a task and then clicking the Edit Task

Information button to or by double-clicking a task

-o-

52

copy Experience In Software Inc 1995 - 2006

Add or Change Task Details

Besides task names notes and assignments you can include cost and done details about tasks In theSchedule step you can also include start and finish dates and durations

To add task details

1 Click a task and then click the Edit Task Information button or double-click the task you wantThe Task Information dialog box opens

2 Enter Cost or Done informationCost Enter the cost associated with this task For example you could enter $150 as the cost for a tasknamed Purchase photo CD Done Click the list arrow to select 0 25 50 75 or 100 or enter the percentage you want such as33

3 Click the OK button

To show or hide task details

Right-click a column heading to open a shortcut menu and then click Cost or Done In the shortcutmenu a checkmark appears next to columns that are displayed in the Task List

To edit task details

Open the Task Information dialog box (click a task and then click the Edit Task Information button or double-click the task you want)

Or

Double-click the Cost or the Done entry to update these details directly in the Task List

Notes

The Cost amount appears with the currency symbol set for your system (in the Regional and LanguageOptions dialog box of the Windows Control Panel)

Project KickStart calculates the running totals for the tasks within a phase and displays this total in theCost column for the phase When you create and print Task reports the total costs for the entire projectappear at the end of the Cost column

See Also

Edit Tasks

Print Task Reports

-o-

53

copy Experience In Software Inc 1995 - 2006

Check Spelling

Spell check your tasks and notes before you print reports or export to other software

To check the spelling of tasks and notes

Click the Check Spelling button on the Project KickStart toolbarOr

Click Tools on the menu bar and then click Spelling

Notes

Spell checking updates entries on the Task List and the Gantt chart (the Schedule step) It can alsocheck the spelling of intermediate entries such as goals and tasks to accomplish goals if you spellcheck during those steps

Spell checking does not check the names of people on the People List or the contents of the PeopleLibrary

-o-

54

copy Experience In Software Inc 1995 - 2006

Scheduling Tasks in the Gantt Chart

55

copy Experience In Software Inc 1995 - 2006

Scheduling Overview

About Scheduling Tasks

In the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the other

You work with the Gantt chart using the familiar Task Data view in the left pane or the graphical Chart viewin the right pane To adjust the schedule to fit your project set the project start date in the toolbar moveand resize the taskbars in the Chart view or change the start and finish dates or durations of individualtasks in the Task Data view

Click the following illustration to see general tips for using the Gantt chart See About the Gantt Chart formore details

In the Schedule step you can

Change a start date for the project Set start and finish dates or durations for tasks Change the timescale of the schedule Change the working schedule to specify which days are nonworking days such as weekends and

holidays Fine-tune the organization of the phases tasks and subtasks Color-code tasks to identify assignments critical deadlines or other information at a glance Insert milestones to indicate events that mark a moment in time such as the approval of a design Review and edit task details including task name assignments notes and attachments Hide or show task data columns in the left pane Export project data to other software applications

Tip

56

copy Experience In Software Inc 1995 - 2006

To save time you can reuse projects such as one for a trade show and create an updated scheduleby changing the project start date in the Schedule step

See Also

About the Gantt Chart

Understand Task Data View

Understand Chart View

-o-

57

copy Experience In Software Inc 1995 - 2006

About the Gantt Chart

The Gantt chart provides two views of your project schedule The Task Data view in the left pane lists thesame task information as in the Tasks step but now includes durations and start and finish dates TheChart view in the right pane displays taskbars and symbols to represent the same information You canchange the schedule information by working directly in the Task Data view and Chart view or by using theGantt Chart toolbarClick the following illustration to see general tips for using this window

-o-

58

copy Experience In Software Inc 1995 - 2006

Autolink tasks (Pro Users)

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatProject KickStart Pro does not assume that you want to link all of the tasks in a serial manner (one after theother) when you get to the Gantt chart Indeed many users want that behavior and many do notTo accomodate both types of users you can set whether you want the program to Autolink tasks In theTools menu select Autolink tasks Thereafter in all your projects when you get to the Gantt chart for thefirst time the tasks will be linked in a serial mannor

-o-

59

copy Experience In Software Inc 1995 - 2006

About Linking Tasks

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatWhen you link tasks the Gantt chart shows additional information about the tasks Click the followingillustration to see general tips for using linked tasks

Task Data view Chart view Description

Predecessor tasksA predecessor task is onethat you must completebefore you can start thenext task For exampleTask 2 - Prepare soil isthe predecessor to Task3 - Plant shrubs becauseyou need to prepare thesoil before you can plantthe shrubs

Successor tasksWhen you finish onelinked task you can moveonto the next onemdashthesuccessor task Forexample the successorfor Task 2 ndash Prepare soilis Task 3 ndash Plant shrubsand the successor forTask 3 is Task 4 ndash MulchLink linesThe first task isscheduled for one dayand the second one forthe next day In additionthe link line and arrowshow that the first taskmust end before thesecond one can start

These linked tasks arescheduled for the sametime

60

copy Experience In Software Inc 1995 - 2006

These tasks which aredependent on earliertasks and the last twotasks are also scheduledfor the same time

See Also

About the Gantt Chart

Autolink tasks

Make tasks overlap

-o-

-o-

61

copy Experience In Software Inc 1995 - 2006

Change the Display of the Schedule

You can change the onscreen appearance of the schedule so you can work with it more effectively Thefollowing illustration shows the Schedule window with the Steps bar closed and only the task number taskname and duration displayed in the Task Data view This provides more room to display the Gantt chart

To show or hide the Step bar or Project KickStart toolbar

Click View on the menu bar and then click Steps Bar to show or hide the vertical Steps bar on the leftof the Project KickStart window

Click View on the menu bar and then click Tool Bar to show or hide the Project KickStart toolbarwhich appears just below the menu bar In the View menu a checkmark appears next to the items displayed in the Project KickStart window

To display more or less of the Task Data view or Chart view

Drag the splitter bar between the Task Data view and the Chart view

To change the timescale in the chart

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years

To add a column to the Task Data view

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task Data viewBy default the Task Data view shows the Info Task Name Days Start and Finish columns Youcan also show Done Cost and Assignments columns

To hide a column in the Task Data view

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

62

copy Experience In Software Inc 1995 - 2006

To change the column width in the Task Data view

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Understand Task Data View

Understand Chart View

-o-

63

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

-o-

64

copy Experience In Software Inc 1995 - 2006

65

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Some features in this topic are available only in Project KickStart Professional

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view In Project KickStart Professional you also use the Gantt chart toolbar to linkand unlink tasks

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysLink Tasks (Pro Users)Link the selected tasksUnlink Tasks (Pro Users)Unlink the selected tasksChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

See Also

Use the Gantt Chart Toolbar

-o-

66

copy Experience In Software Inc 1995 - 2006

Understand Task Data View

The following illustration shows all the columns of information you can display in Task Data view

The Task data columns are the same as in the Tasks step but also include date information

Row number

Info Shows an icon if a note attachment or both are associated with the task Double-click anicon to view or edit the associated information

Task Name Name of the phases tasks and subtasks Double-click a task name to edit it directly

Days The amount of time it takes to complete the task If you change the number of days for a taskProject KickStart changes the Finish date accordingly

Start Date this task starts Double-click a Start date and then click the list arrow to open a calendar andselect a different date This also changes the Finish date

Finish Date this task ends Double-click a Finish date and then click the list arrow to open a calendar andselect a different date This changes the task duration shown in the Days column

Done Percentage of the phase task or subtask completed Show progress for any task by entering apercent of up to 100

$ Cost Cost for each task summed in the appropriate phase row Reports include total costs for theproject when you select the Cost column in the Create and Print Task Reports dialog box or the Createand Print Gantt Chart Report dialog box The Cost appears with the currency symbol set for your system(in the Regional and Language Options dialog box of the Windows Control Panel)

Assignments People and other resources assigned to the task Double-click an assignment to open theTask Information dialog box to the Assignments tab where you can add and change assignments

Tip

A task with a duration of zero (0) days is a milestone See Create a Milestone for more information

Notes

By default Task Data view displays all the columns the Info Task Name Days Start and Finish Done Cost and Assignments columns Some of these columns might be hidden by the Gantt chartview To hide columns right-click a column heading to open a shortcut menu and then click the columnyou want to hide In the shortcut menu no checkmark appears next to columns that are hidden

To change the width of a column drag a splitter bar in the column heading row or double-click a splitterbar to have the column accommodate its longest entry

As in the Tasks step expand phases and tasks by clicking the plus icon and collapse phases andtasks by clicking the minus icon

See Also

67

copy Experience In Software Inc 1995 - 2006

Understand Chart View

Change Task Dates

-o-

68

copy Experience In Software Inc 1995 - 2006

Additional Features in Task Data View

These features are available only in Project KickStart Professional

In Project KickStart Pro you can view two columns of information in addition to the nine columns availablein the Project KickStart Standard These two additional columns are labeled Pred (for Predecessor) andSucc (for Successor) The following illustration shows a typical Task Data view with these additionalcolumns

Besides the nine columns of information shown in Task Data view in Project KickStart Standard you canalso show the following information in the Professional version

Pred Indicates which task is the predecessor to the current task Double-click a task number in the Predcolumn to change it

Succ Indicates which task is the successor to the current task Double-click a task number in the Succcolumn to change it

Notes

When you link tasks Project KickStart assigns predecessors and successors according to their order inthe Task Data view

When you move a linked task in the Task Data view the predecessor and successor do not changeFor example in the above illustration if you move Task 3 ndash Plan design so it becomes Task 2 itspredecessor remains Land survey and its successor remains Engineering You can change these bydouble-clicking the task number in the Pred or Succ column and then entering a new number

See Also

Understand Task Data View

-o-

69

copy Experience In Software Inc 1995 - 2006

Understand Chart View

The following illustration shows a daily schedule in Chart view Point to the illustration to display text thatdefines the chart elements

Summary bar Summarizes the tasks below it and extends from the earliest start date(where the first triangle in the summary bar appears) to the latest finish date (where the last triangleappears) If a phase has tasks the summary bar appears in the phase row to summarize the tasks If atask has subtasks the summary bar appears in the task row to summarize the subtasks

To reschedule a phase and all of its tasks (or a task and all of its subtasks) click the summary bar and dragit to the left or right until it spans your desired set of dates This changes the earliest start date and latestfinish date in that phase and keeps the same duration And all the tasks move with the change of thephase

Taskbar Shows the length and scheduled dates for a task To change the duration of a taskresize the taskbar click the taskbar and then drag its left edge to schedule a different start date or drag itsright edge to schedule a different finish date

To reschedule a task without changing the duration drag the taskbar to a different date in the chart

Taskbar with percent done If you enter a Done amount in the Task Data view a progress barin the taskbar indicates the amount of the task completed

Red vertical line Indicates todays date

Milestone Indicates a task with a zero duration Milestones mark an event that must be reflected inyour project plan such as the approval of a design or an assembly line startup You can drag the left edgeof a milestone icon to stretch it into a taskbar The milestone becomes a task with a start and finish date

Notes

Because a summary bar summarizes the tasks below it you cannot resize a summary bar

To scroll the schedule use the vertical and horizontal scroll bars or the green drag bar at the top of theChart view

The shaded days in the Chart view indicate nonworking days To set which days are working andnonworking see Specify Working Days

70

copy Experience In Software Inc 1995 - 2006

-o-

71

copy Experience In Software Inc 1995 - 2006

Additional Tools in Chart View

These features are available only in Project KickStart Professional

If you use Project KickStart Pro the Chart view displays lines and arrows to show linked tasks The linklines and arrows show the relationships dependencies between one linked task and another

Besides the summary bar taskbar and other information provided in Project KickStart Standard Chart viewin the Professional version also provides the following information

The first task is scheduled for one day and the second one for the next day In addition the link line andarrow show that the first task must end before the second one can start

These linked tasks are scheduled for the same time However the first task must end before the secondone can start

The first two tasks are scheduled for the same time and must be completed before the third task can start

These linked tasks are scheduled for the same time However the second task must end before the firstone can start

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

Understand Chart View

-o-

72

copy Experience In Software Inc 1995 - 2006

73

copy Experience In Software Inc 1995 - 2006

Change Task Dates

You can revise a project schedule by changing task dates in the Task Data view or the Chart view You canalso reschedule an entire project by changing the projects start date

To change the project start date1 Click the Project Start list arrow to open a calendar

The calendar highlights the selected date and outlines todays date2 Find the date you want using the left and right scroll arrows to view a different month and then click the

date

To change task dates in Task Data view1 Double-click the Start or Finish date for a task

2 Then edit the date (you can edit the day month or year) OrClick the list arrow to open a calendarThe calendar highlights the selected date and outlines todays date

3 Find the date you want using the left and right scroll arrows to view a different month and then click thedateProject KickStart changes the Start and Finish dates according to your selection updates the durationof the task in the Days column and adjusts the taskbar in the Chart view

To change task dates by changing the duration in Task Data view

Double-click the Days column for a task and then enter the number of days it will take to complete thetaskProject KickStart changes the Finish date of the task and adjusts the taskbar in the Chart view

To change task dates in Chart view

Resize a taskbar click the taskbar and then drag its left edge to schedule a different start date or dragits right edge to schedule a different finish dateProject KickStart updates the summary bar in Chart view and the task dates and duration in the TaskData view

To reschedule a task without changing the duration drag the taskbar to a different date You can alsodrag a summary bar to reschedule a phase and all of its tasks (or a task and all of its subtasks) so itspans a different set of datesProject KickStart updates the task dates and duration as necessary in the Task Data view

To change task dates in the Task Information dialog box1 Open the Task Information dialog box (Right-click a task and then click Task Information or click a

task and then click the Edit Task Information button )2 Click the General tab3 In the Dates section change the following information as necessary

Start Click the Start list arrow to open a calendar and then click the appropriate start dateFinish Click the Finish list arrow to open a calendar and then click the appropriate finish dateDays Enter a number or click the spin arrows to set the task durationMilestone Select the Milestone check box if you want this task to be a milestone (A milestone is atask with a zero duration and marks an event such as the approval of a design)

Notes

You cannot delete the Start or Finish date of a task If you want to specify that a task has no durationconvert it to a milestone

When working with a calendar to schedule a start or finish date click the Today date text (where date

74

copy Experience In Software Inc 1995 - 2006

is todays date) to select todays date

See Also

Understand Task Data View

Understand Chart View

Create a Milestone

-o-

75

copy Experience In Software Inc 1995 - 2006

Phase Dates Cannot Be Edited

You cannot change the bold phase dates in the Task Data view of the Gantt chart They are a summary ofthe task dates for a particular phase and are view only You can revise phase dates by changing task dateswithin the phase

To change phase dates in Chart view

You cannot directly resize a summary bar You can extend or move the blue task barswithin a phase on the chart and Project KickStart updates the summary bar

To reschedule a phase on the chart drag the summary bar to a new date and all of its tasks (or a taskand all of its subtasks) will move with it

-o-

76

copy Experience In Software Inc 1995 - 2006

Quick Tour of Working with Linked Tasks

This feature is available only in Project KickStart ProfessionalIn the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the otherIn addition Project KickStart Pro links the tasks for you so when you open the Gantt chart you see a linkedwaterfall similar to the one shown below Besides providing a schedule that starts in a cascade with eachtask lasting one day each task is linked to the next task

You work with the Gantt chart either using the Task Data view in the left pane or the graphical Chart view inthe right pane To adjust the schedule to fit your project set the project start date in the toolbar move andresize the taskbars in the Chart view or change the start and finish dates or durations of individual tasks inthe Task Data view See About Scheduling Tasks for detailsNext fine-tune the dependencies in your project by you can linking and unlinking tasks changing theirpredecessors and successors and setting lead times For example if one task is not dependent onanother you can unlink the tasks If another task canrsquot start until two other tasks are finished you can add apredecessor to that task in which case the two tasks will be linked

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

To fine-tune the linked tasks To change the scheduled start and end dates of linked tasks move and resize taskbars in the Chart

view or change the number of days or the Start date in the Task Data view To display predecessor and successor information in the Task Data view right-click any column

heading and then click Pred or Succ To change the predecessor for a task double-click the number in the Pred column for the task and

then enter the number of a different task To change the successor for a task double-click the number in the Succ column for the task and then

77

copy Experience In Software Inc 1995 - 2006

enter the number of a different task To add another predecessor or successor to a task click in the appropriate column for the task and

then enter the number of another task To change the details of a linked task open its Task Information dialog box To do so right-click the

task and then click Task Information on the shortcut menu or click a task and then click the Edit TaskInformation button See Change Details for Linked Tasks

In the Task Information dialog you can also specify the predecessor(s) of a task and lead time(s) of thetasks

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

About Scheduling Tasks

About Linking Tasks (Pro Users)

Use the Gantt Chart Toolbar (Pro Users)

Manage Changes in Your Schedule (Pro Users)

-o-

-o-

78

copy Experience In Software Inc 1995 - 2006

Link and Unlink Tasks

These features are available only in Project KickStart Professional

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

See Also

About Linking Tasks

Quick Tour of Working with Linked Tasks

-o-

79

copy Experience In Software Inc 1995 - 2006

Create a Milestone

A milestone Indicates a task with a zero duration Milestones mark an event that must be reflected in yourproject plan such as the approval of a design or an assembly line startup

To create a milestone in the Task Data view

Double-click the Days number for a task and then enter 0 (zero)Or

Open the Task Information dialog box click the General tab and then click to insert a checkmark inthe Milestone check box

In the Chart view Project KickStart changes the taskbar to a milestone icon To create a milestone in Chart view

Click a taskbar and then drag to shrink the taskbar to a milestone icon In the Task Data view Project KickStart changes the Days for this task to 0 (zero)

Notes

To change a milestone into a task you change its duration or start and finish dates See Change TaskDates for instructions

To move a milestone in Chart view click the milestone icon on the upper left corner of the milestoneicon With the left mouse down move the icon to another date and release the mouse

To move a milestone in the Task Data view change the start date or the finish date and the milestonewill move

-o-

80

copy Experience In Software Inc 1995 - 2006

Change Task Details

You can use the Task Information dialog box to change the following task details in Task Data view

Task properties including the task name cost for completing the task and the percent completed

Dates including the start and finish dates duration and whether to convert the task to a milestone

Assignments

Notes and attachmentsYou can also edit the task name days dates costs and Done directly by clicking items in the task datacolumns

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button 2 Click the appropriate tab and then change the task details

General tab Change the task name and enter or change the cost associated with the task To changethe amount of the task completed click the Done list arrow and then select a value or type a value inthe Done text box Enter or change date information as described in Change Task Dates Assignments tab People assigned to this task are highlighted in the list To assign this task to anotherperson or resource click the name in the Assignments list To remove (unassign) this task from aperson or resource click a highlighted name in the Assignments list See Add or Change TaskAssignments for more detailsNotes and Attachments tab Type or edit a task note (Press Enter for a line break) To add anattachment click the Add button In the Select File to Attach dialog box navigate to the file you wantand then click the Open button The filename appears with a paper clip icon See Add Task Notes andAttachments for more details

To change task details directly in Task Data view

To modify the task name press F2 or double-click a task and then edit or replace the text

To change date information see Change Task Dates

To change the amount of the task completed double-click in the Done column and then enter a newvalue

To change the cost associated with the task double-click in the Cost column and then enter a newvalue

Notes

When you enter costs for tasks the total appears in the phase row for those tasks Reports include thetotal costs of all tasks in the project when you select the Cost column in the Create and Print TaskReports dialog box or the Create and Print Gantt Chart Report dialog box

You cannot change the cost of a phase because it represents the total costs for the tasks in that phaseInstead change the costs associated with the tasks in the phase

When you enter a Done for a task the corresponding taskbar in the Chart view includes a blackprogress bar

-o-

81

copy Experience In Software Inc 1995 - 2006

Change Details for Linked Tasks

This feature is available only in Project KickStart ProfessionalIf you are using Project KickStart Pro you can use the Task Information dialog box to change the followingtask details

Predecessor for a linked task

Lead time for a linked task

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button

2 Click the Predecessors tab and then change the task details about predecessors and lead timePredecessors tab The Task Properties section shows the name of the selected task which you canchange The Predecessor (Finish-to-Start) section shows the tasks that are predecessors to theselected task A predecessor task must be finished before you start the current task You can change the ID name or lead time of the predecessor task Also you can also add additionalother predecessorsThe lead time is the amount of time you need to wait after finishing the predecessor task before so youcan start the current task Lead time can be positive or negative

Note

In some programs the is time shift is called ldquolag timerdquo But we think that the term ldquolead timerdquo is moreaccurate and descriptive since itrsquos the amount of time you want to allow before you start a task

See Also

Change Task Details

82

copy Experience In Software Inc 1995 - 2006

-o-

-o-

83

copy Experience In Software Inc 1995 - 2006

Reorganize Tasks in Task Data View

Although your project should be fairly well organized by the time you start the Schedule step you canfine-tune the organization in the Task Data view using the same techniques you use in the Tasks stepTo reorder tasks

Right-click a task and then click Move Task Up or Move Task Down on the shortcut menu Or

Click a task or phase to select it and then click the Up Arrow button or the Down Arrow button on theGantt chart toolbar

To promote and demote tasks

Right-click a task and then click Outdent or Indent on the shortcut menu Or

Click a phase task or subtask to select it and then click the Outdent button or the Indent button onthe Gantt chart toolbar

To add a task1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Task button on the Gantt chart toolbar or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskTo add a subtask1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Subtask button on the Gantt chart toolbar or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtaskTo delete a task

Right-click a task and then click Delete Row on the shortcut menuOr

Click the task you want to delete and then click the Delete button

To delete a row click the Task row number and press the Delete button

See Also

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

-o-

84

copy Experience In Software Inc 1995 - 2006

Change the Timescale of the Schedule

You can display the Gantt chart schedule in the Chart view using days weeks months quarters or yearsas the timescale Changing from days to weeks for example displays a longer period of time but lessdetail

Days timescale Weeks timescale

To change the timescale in the Chart view

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years Youcan also change the timescale by clicking Timescale on the menu bar and then clicking the option youwant

Notes

When you print a Gantt chart your current timescale is used by default However you can change it inthe Print Options dialog For example even though you were viewing your Gantt chart by weeks youcan choose to print the Gantt chart by months

If your mouse comes with a wheel you can adjust Project KickStarts timescale by rolling the wheelforward or backward The Timescale list box must be selected first

-o-

85

copy Experience In Software Inc 1995 - 2006

Specify Working Days

You can select which days are working days and which days are nonworking days for scheduling purposesBy default Monday - Friday are working days and Saturday and Sunday are nonworking days You can addto and change these settings to specify holidays for example

To set working and nonworking days

1 Click the Change Working Schedule button on the Gantt chart toolbar The Change Working Schedule for this Project dialog box opens Nonworking days are shaded in grayWorking days are unshaded

2 To change a single date (from working to nonworking or from nonworking to working) click the date3 To change one day of the week for the entire project such as all Fridays double-click any Friday4 To display schedules for other months click the left and right arrows5 Click OK

Note

Project KickStart maintains separate calendars for each project

If you typically work weekends create a simple template with weekends displayed as Working daysSave as your starter template Use the starter template when you start a new project and then save theproject with a different name Weekends will be displayed as Working days in your projects

-o-

86

copy Experience In Software Inc 1995 - 2006

Change the Color of Taskbars

You can change the color of the taskbars in the Chart view to call attention to particular tasks For exampleyou can change the colors of all tasks in a particular phase resource or deadline to make them stand outin a report

To change the color of a taskbar1 Right-click a taskbar and then click Color on the shortcut menu or click a taskbar and then click the

Color button on the Gantt chart toolbar The Color dialog box opens

2 Click the color you want to assign to the taskbarTips

Avoid changing the taskbar color to black because it obscures the Done progress bar (The Doneprogress bar is a black bar displayed within a taskbar)

Also avoid changing the taskbar color to white because it will not appear in the white rows of the Chartview

-o-

87

copy Experience In Software Inc 1995 - 2006

Make Tasks Overlap

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro the schedule starts in a cascade with each task lasting one day and each tasklinked to the following taskHowever it is very unlikely that your entire schedule matches such a cascade so you can adjust theschedule Start by estimating the duration of tasksmdashthe number of days that each task will take Generallyit is best to estimate how many days will elapse before the task is done You might also want some tasks to occur at the same time To do so you can overlap the tasks To make tasks overlap like this

You can do this in three ways Set the same predecessor for both tasks

Or Set the second task as the successor of the first task and then then move the second task into a

position when it starts on the same day as the first taskOr

Set the second task as the successor of the first task and then assign a lead time of ndash3 days (the number of days scheduled for the task)

To make tasks overlap like this

Set the second task as the predecessor of the first task and then assign a lead time of ndash2 days(one less than the number of days scheduled for the task)

-o-

88

copy Experience In Software Inc 1995 - 2006

Manage Changes in Your Schedule

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro when you schedule with dependencies you can adapt to changes on the fly andcreate what-if scenarios to forecast how one change affects the overall project schedule A commonscenario is dealing with delays You can reschedule an entire project or only selected tasks When you doProject KickStart Pro updates the schedule for you

To delay an entire project Click in the Project Start text box and then edit the date to match your new start date (You can edit

the day month or year)Or

1 Click the Project Start list arrow to display the calendar The calendar highlights the selected date andoutlines todays date

2 Find the date you want using the left and right scroll arrows to view a different month and then click thedate Project KickStart changes the Start and Finish dates for all tasks according to your selection

To delay a task In Task Data view double-click the Days column for the task and then edit the number of days it will

take to complete the taskProject KickStart changes the Finish date of the task adjusts the taskbar in the Chart view andchanges the Start and Finish dates for all tasks linked to this taskOr

In Chart view resize a taskbar by clicking the taskbar and then dragging its left edge to schedule adifferent start date or dragging its right edge to schedule a different finish date Project KickStart updates the summary bar in Chart view the task dates and duration in the Task Dataview and reschedules all tasks linked to this task

To reschedule a task without changing the duration in Chart view drag the taskbar to a different date Project KickStart updates the task dates and duration as necessary in the Task Data view andreschedules all tasks linked to this task

Note

Project KickStart Pro does not include a critical path

-o-

89

copy Experience In Software Inc 1995 - 2006

Managing Libraries

Use a Library

Project KickStart has five libraries that contain lists of useful phases tasks goals people and obstaclesAll libraries expect the People Library contain sample entries that you can use in your projects Yougenerally build your own People Library from the resources that are available to you

To use a library1 In the Phases Tasks Goals People or Obstacles step of the Planning Wizard click the Library button

to open the appropriate library2 Select one or more items in a library and then drag them to your list3 Close the Library window

Tips

Feel free to add (or delete) items to the libraries to make them richer and more pertinent to yourprojects

Keeping libraries small makes them easier to use

Widen the library window to see the full text of long entries

Note

After adding a library entry to a list you can double-click the entry to edit it

See Also

Manage a Library

-o-

90

copy Experience In Software Inc 1995 - 2006

Manage a Library

Customize the libraries by adding and changing entries and reorganizing them so you can use the librariesefficiently The Phases Tasks Goals People and Obstacles Libraries include a single column ofinformation while the People Library provides additional columns (See Manage the People Library)

To edit a library1 Open the library by clicking the appropriate Library button2 To edit an entry double-click it

3 To add an entry to the library press Insert or click the Add a row button You can also select oneor more items in the list and then drag them to the library

4 To delete an entry select the entry and then press Delete or click the Delete a row button 5 To move an item up or down select the item and then click the Up Arrow or the Down Arrow button

6 Click the OK button to save your changes and close the Library windowTips

Widen the Library window to add a long entry

Libraries can serve as ldquoKnowledge Librariesrdquo By including typical company-specific terms in yourLibraries you create a quick reference for yourself and colleagues now and in the future To do so adda new line in the Library enter the name of your company (or department) as a heading in capitalletters and then list your personal terms under the heading

If you use Project KickStart on more than one computer such as at home and work you can transportchanges you make in your Libraries from one computer to another The data in all the Libraries isstored in one file pks5libxdat so you can copy that file on one computer and paste it into the ProjectKickStart 5 folder on the other computer

Keeping Libraries small makes them easier to use Project KickStarts Libraries are fairly rich out of thebox If some of the terms don rsquot apply to your type projects delete them

See Also

Manage the People Library

-o-

91

copy Experience In Software Inc 1995 - 2006

Manage the People Library

The People Library is like the other libraries but with a few important extra features

You can store contact data such as Company Email Phone and Job Title

You can import names from ACT or from Outlook if you use either of those programsTo use the People Library1 In the People step of the Planning Wizard click the People Library button2 Select one or more names in the People Library and then drag them to your list (This adds only the

names of people not their contact data) If the People Library contains company names but not contactnames you can drag the company name to your list

3 Close the Library windowTo organize the People Library

To show or hide a column right-click a column heading to open a shortcut menu and then click acolumn name In the shortcut menu a checkmark appears next to columns that are displayed in thePeople Library

To sort the people in the People Library click a column heading For example click the Name columnheading to sort the people alphabetically by name To reverse the sort click the column heading again

To move a person up or down select the person and then click the Up Arrow or the Down Arrowbutton

Click the OK button to save your changes and close the People LibraryTo edit the People Library

To edit a persons name and contact data double-click the entry

To add a person to the People Library click the first blank row press Insert or click the Add a rowbutton Then type to enter the persons name and contact information You can also select one ormore items in the list and then drag them to the People Library

To delete an entry select the entry and then press Delete or click the Delete a row button

Click the OK button to save your changes and close the People LibraryTips

Use the People Library to store names for people teams (such as Quality control team) departments(such as Manufacturing) companies (such as Acme Widgets Corp) or even equipment (such as wheatthrasher)

Widen the People Library window to add a long entry

Resize the columns by dragging or double-clicking a splitter barNotes

After adding a person or resource to your list you can double-click the name to edit it

You can import contact information stored in an Outlook or ACT (version 6 7 or later) address book toyour People Library

See Also

Import ACT Contacts and Users to the People Library

Import Outlook Contacts to the People Library

-o-

92

copy Experience In Software Inc 1995 - 2006

Import ACT Contacts and Users to the People Library

If you use ACT 7 or later (200520062007) or if you use ACT 6 you can import contacts and users to thePeople Library This speeds up your work by letting you use ACT information in your Project KickStartplans If you export a plan to ACT 7 or later it recognizes the people and other resources you entered inProject KickStart

To import ACT contacts and users1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click ACT 7 or later or ACT 6 Click the Import button3 Click the Select ACT Database button and select the ACT 7 or later database (pad) containing the

people information you want to import The ACT 7 and later databases are usually stored in MyDocumentsACTACT for Win 7Databases (If you use ACT 6 your data is stored in a dbf database) If you select a multi-user ACT database you must enter your user name and password for the ACTdatabase

4 In the Import to People Library dialog box the names of Contacts and Users are listed on the left Clickthe Users tab select one or more users and then click Add to move the user names to the Import listClick the Contacts tab to select contact names the same way Click the Add All button to select allusers or contacts for import Note You can sort the contacts alphabetically by name or by company name by clicking theappropriate column heading

5 Click the Import button to add the names and related information from the selected ACT database tothe People Library

Notes

Importing contacts and users to the People Library does not remove them from the ACT database

If you try to import the same ACT contact or user twice it appears only once in the People Library

-o-

93

copy Experience In Software Inc 1995 - 2006

94

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts to the People Library

If you use Microsoft Outlook to maintain your contacts you can import selected contacts to the PeopleLibrary ThisThis speeds up your work by letting you use Outlook information in your Project KickStartplans If you export a plan to Outlook it recognizes the people and other resources you entered in ProjectKickStart

To import Outlook contacts1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click Outlook Click the Import buttonA dialog box opens informing you that Project KickStart is trying to access your Outlook data

3 Allow access for 1 minute and then click the Yes button4 If Outlook asks you to choose your profile please do so5 The Import to People Library dialog box opens listing Outlook Contacts on the left Select one or more

contacts and then click Add to move the contact names to the Import list Click the Add All button toselect all contacts for import

6 Click the Import button to add the contact names to the People Library

Notes

Importing contacts and users to the People Library does not remove them from Outlook If you try to import the same Outlook contact twice it appears only once in the People Library

95

copy Experience In Software Inc 1995 - 2006

You can import Contacts from the Outlook Business Contact Manager

See Also

Import Outlook Contacts via CSV to the People Library (Pro Users)

-o-

96

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts via CSV to the People Library (ProUsers)

This feature is available only in Project KickStart Professional

If you use Microsoft Outlook to maintain your contacts and many of the people on your project are not inyour personal contacts folder in Outlook you can use our new utility to import these Outlook contacts viaCSV to the People Library

To export Outlook contacts to a CSV file1 In Outlook - Click File Import and Export Export to A File and click Next2 Select Comma Separated Values (Windows) and click Next3 Select the Contacts folder to export and click Next4 Save Exported File As with the default being your My Documents folder5 Click Next

To import Outlook contacts to the People Library

1 Be sure that you exit Project KickStart before running the Import Utility

2 Run ImportCSVToPKSexe which is located in the Project KickStart application folder

3 Browse or type the Contacts CSV file (the path is My DocumentsProject KickStart Projects folder bydefault)

4 Browse or type the pks5libxdat file (default is the Project KickStart application folder)

5 Click on Import

Note

Importing contacts and users to the People Library does not remove them from Outlook

-o-

97

copy Experience In Software Inc 1995 - 2006

Printing Reports

98

copy Experience In Software Inc 1995 - 2006

Printing Dashboards

Print Reports

You can print reports from anywhere in Project KickStart through a new Reports Step

You will see Reports divided into three areas

Dashboard

Task Reports

Gantt Chart Reports

-o-

99

copy Experience In Software Inc 1995 - 2006

Print Dashboard Reports

You can print dashboard reports from anywhere in Project KickStart though it makes the most sense toprint them after you have developed your tasks and arranged them in a sensible order

To print a dashboard report

1 Click File on the menu bar and then click Print Reports and then click Dashboard Reports or clickthe Print Reports button

2 In the left column select one of these dashboard reports Whats Due Today Whats Due NextWeek Whats Due Next Month

3 Change the page setup as necessary or Save As a file (See Page Setup and Save As)

4 Click the Print button

Tip

You can see the number of tasks in each dashboard report from the dashboard menu

-o-

100

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Dashboard Reports

Printer Setup

-o-

101

copy Experience In Software Inc 1995 - 2006

Save as HTML or RTF

You can dashboard reports to a Hypertext Markup Language (HTML) format for viewing with an Internetbrowser such as Microsoft Internet Explorer or Mozilla FireFox or to an RTF format for viewing in MicrosoftWord

To save a dashboard report as an HTML file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save button

To save a report as an RTF file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

102

copy Experience In Software Inc 1995 - 2006

Printing Task Reports

Print Task Reports

You can print task reports from anywhere in Project KickStart though it makes the most sense to print themafter you have developed your tasks and arranged them in a sensible orderBefore you print task reports you might want to widen the Task Name column in the Task List to make sureyou print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a task report

1 Click File on the menu bar and then click Print Task Reports In the Tasks step you can click thePrint Reports button instead

The Create and Print Task Reports dialog box opens

2 Click the list arrow and then click Task Report Individual Assignments or Phases Goals People ampObstacles

3 Select the information you want to include in the report as described below

4 Preview the report and change the page setup as necessary (See Print Preview and Page Setup)

5 Click the Print button

Task Report

The Task report covers the entire project and includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

103

copy Experience In Software Inc 1995 - 2006

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to display in the report

By default the report prints all tasks Click the Incomplete Tasks or Completed Tasks option button tofocus on one type of task

4 Click the Preview button (See Print Preview for details)

Individual Assignments

The Individual Assignments report covers the entire project and lists the tasks assigned to each resourceThe report includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to include in the report

Click the All Tasks Incomplete Tasks or Completed Tasks option button

4 Choose which people to include The report lists tasks assigned to the people you select

Click to insert or remove a checkmark from the box for each person

5 Click the Preview button (See Print Preview for details)

Phases Goals People amp Obstacles

This report includes the phases goals people and obstacles in your project You can include some or all ofthese items in the report

104

copy Experience In Software Inc 1995 - 2006

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Click the Preview button (See Print Preview for details)

Tip

If you have many long notes for the tasks of your project it may be hard to read them if you select everycolumn in the Task Reports You should consider selecting a report with only columns for Tasks andNotes

See Also

Print Gantt Chart Reports

-o-

105

copy Experience In Software Inc 1995 - 2006

Print Preview

Before printing a report preview its pages so you know how the report will look when printed

To preview a task report1 Click the Preview button on the Create and Print Task Reports dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from 79 to 100 or from 100 to 79Zoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25

viewPrint the report

You can also click the Page Setup button to change margins and other settings or click the Closebutton to close the Print Preview window

2 If the report appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintTask Reports dialog box

Note

Print Preview is for viewing only--you cannot edit the contents of a report

See Also

Print Task Reports

Printer Setup

Page Setup

-o-

106

copy Experience In Software Inc 1995 - 2006

Printer Setup

Before you print a report you can change the following printer settings

Printer name (and other properties) Paper size Number of copies

To change the printer setup1 Click the Printer button on the Project KickStart toolbar or the Print Preview toolbar2 In the Print dialog box change the printer settings

See Also

Print Task Reports

Print Preview

Page Setup

-o-

107

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Task Reports

Print Preview

Printer Setup

-o-

108

copy Experience In Software Inc 1995 - 2006

Email Task Reports

After creating and previewing a task report you can distribute it to others via email

To email a task report1 In the Create and Print Task Reports dialog box select a report and then click the Email Report

button Project KickStart creates the report opens a new message in your email software and attaches thereport as an HTML file to the message

2 Insert one or more email addresses include the message text and then send the message the way youusually do

Tip

To send a task report to each person in your project with the appropriate assignments select theIndividual assignments report select one person to receive the report and then click the Email Reportbutton Enter the email address of the recipient and send the message Do this for each person in yourproject

-o-

109

copy Experience In Software Inc 1995 - 2006

Save as HTML

You can export tasks assignments days and notes to a Hypertext Markup Language (HTML) format forviewing with an Internet browser such as Microsoft Internet Explorer or Mozilla FireFox

To save a report as an HTML file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

110

copy Experience In Software Inc 1995 - 2006

Save as RTF

You can export tasks assignments durations and notes to a Rich Text Format (RTF) for editing inMicrosoft Word

To save a report as an RTF file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can open an RTF file in a word processor such as Microsoft Word

To send an RTF document to each person in your project with the appropriate assignments select theIndividual Assignments report select one person to receive the report and then save the report asRTF Do this for each person in your project

See Also

Save as HTML

-o-

111

copy Experience In Software Inc 1995 - 2006

Printing Gantt Chart Reports

Print a Gantt Chart

Once you create your schedule you can print a Gantt chart from anywhere in Project KickStart

Before you print a Gantt chart you might want to widen the Task Name column in the Task pane to makesure you print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a Gantt chart1 Click File on the menu bar and then click Reports and then select Gantt Chart Reports In the

Schedule step you can click the Print Reports button insteadThe Create and Print Gantt Chart Report dialog box opens

2 Click the Format list arrow and then click Wall chart Fit to smallest size or Repeat tasks on everypage (for handouts)

3 Select the information you want to include in the report as described below4 Preview the report and change the page setup as necessary (See Print Preview a Gantt Chart and

Page Setup)5 Click the Print button

Wall Chart The wall chart prints the Gantt chart information spread across many pages which you can tape together tocreate a wall chart On the left side of the report the wall chart includes the task data columns you selectThe right side of the report includes the graphical view shown in the Gantt chart pane on the right

1 Select the task data columns you want to display for the task information on the left side of the wallchartClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the wall chart

112

copy Experience In Software Inc 1995 - 2006

By default the wall chart prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the wall chartBy default the wall chart prints the timescale you were using in the Gantt chart Click the SetTimescale list arrow to change the timescale to Weeks Months Quarters or Years

4 Select the orientation for the wall chartClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Fit to Smallest Size When you select the Fit to smallest size format Project KickStart reduces the size of the entire Gantt chartincluding the information in the Task pane on the left and the graphical view shown in the Gantt chart paneon the right so it fits as well as possible in the smallest number of pages

1 Select the data columns you want to display for the task information on the left side of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 The timescale for the Gantt chart view on the right side of the report is determined by the length of yourproject and may not be changed

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 The number of pages of the report is shown here (The Fit to smallest scale report will print up to 78rows of tasks per page)

6 Click the Preview button (See Print Preview a Gantt Chart for details)

Standard (for Handouts) This report lists the data columns you specify on the left side of the first page and can repeat the tasknumber task name or assignments on every interior page of the report which is especially useful for

113

copy Experience In Software Inc 1995 - 2006

handouts

1 Select the data columns you want to print on the left side of the first page and the data columns youwant to print on every page of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the reportBy default the report prints a daily view of the tasks Click the Set Timescale list arrow to change thetimescale to Weeks Months Quarters or Years

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Tips

Print Preview shows how many pages the Gantt chart will take to print If there are too many pagesconsider changing the timescale or the date range You can also choose to show fewer columns of taskdata

If possible use paper that is larger than 85 x 11 inches You can select the paper size in Print Previewusing the Page Setup dialog box

If you change the timescale from Days to Weeks or Months this can make tasks with short durations (1to 5 days) difficult to see

If you have trouble printing the Gantt chart report try changing the dpi from 600 to 300 (draft mode) Ifyou continue to have problems contact your printer manufacturer and see if it supports PCL (PrinterCommand Language) technology which is included in most printers today

If you have trouble printing the Gantt chart report on a PDF printer you can try to scale the printing tographics setting to 50

114

copy Experience In Software Inc 1995 - 2006

See Also

Save Gantt Chart Images

Print Task Reports

Printer Setup

Page Setup

-o-

115

copy Experience In Software Inc 1995 - 2006

Print Preview a Gantt Chart

Before printing a Gantt chart preview its pages so you know how the report will look when printed

To preview a Gantt chart1 Click the Preview button on the Create and Print Gantt Chart Report dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from the current zoom percentage to 100 or from 100 to the current zoom percentageZoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25 viewChange printer settings and then print the reportYou can also click the Page Setup button to set margins select paper size and enter headers andfooters or click the Close button to close the Print Preview window

2 If the Gantt chart appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintGantt Chart Report dialog box

Notes

Print Preview is for viewing only--you cannot edit the contents of a report

If you want to print a wider task column return to the Gantt chart widen the Tasks Name column andthen print

To change print settings such as the printer selection and number of copies click the Print button to open the Print dialog box You can save the Gantt chart in a PDF file by clicking the Print button andthen clicking the PDF printer selection (such as Adobe PDF or PDF-XChange ) You can then distributethe Gantt chart electronically as a PDF file

See Also

Print a Gantt Chart

Page Setup

-o-

116

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a Gantt chart you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print a Gantt Chart

Print Preview a Gantt Chart

-o-

117

copy Experience In Software Inc 1995 - 2006

Printing to an Adobe PDF file

To print a Gantt chart to an Adobe PDF file you may have to make some adjustments to your settings

To preview a Gantt chart1 Select Adobe PDF as the name of the printer2 Click Properties button3 Click the PaperQuality tab4 Click Advanced button5 In the Graphic Section lower the setting on Print Quality6 Also in the Graphic Section change the Scaling from 100 to 50

-o-

118

copy Experience In Software Inc 1995 - 2006

Save Gantt Chart Images

You can save a Gantt chart as a series of graphic files in the Meta File (emf) format which you can theninsert in a file such as a Microsoft Word document or PowerPoint presentation The number of graphic filescreated depends on the report type and options you choose in the Create and Print Gantt Chart Reportdialog box By default Project KickStart saves the files in a folder named for your project

To save Gantt chart images1 In the Create and Print Gantt Chart Report dialog box click the Save Image button

The Save Image dialog box opens2 Change the location where you want to save the image files or change the part of the file name that

includes the project name and report type if necessary3 Click the Save buttonNotes

Project KickStart saves the image files in the PKSGanttImagesproject name folder stored in the MyDocumentsProject KickStart Projects folder (where project name is the name of your project)

Each graphic file name includes the name of the project report type date you created the report andnumber in the series of images as in CreateaWinningPresentation_Wall chart_09112008_1emf toCreateaWinningPresentation_Wall chart_09112008_20emf

To email the Gantt chart images attach the images in the PKSGanttImagesproject name folder storedin the My DocumentsProject KickStart Projects folder (where project name is the name of your project)If the image files are large zip or compress the files first

If you have installed PDF as a printer selection you can print the Gantt chart to a PDF file and thenattach the PDF file to an e-mail message PDF files are often easier to read than image files See thenotes in Print Preview a Gantt Chart for instructions on printing to a PDF file

-o-

119

copy Experience In Software Inc 1995 - 2006

Export Project Data

120

copy Experience In Software Inc 1995 - 2006

Export to ACT

Export to ACT 7 or Later

If you use ACT 7 or later (20052006200720082009) you can export your plan from Project KickStart toan ACT database with just one click After you export your plan you see your tasks in the ACT Groupview grouped under the name of your project

To export to ACT 7 or later

1 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 7 and later andthen click the Go button You can also click File on the menu bar point to Export to and then clickACT 7 and later

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (pad file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opens

Each time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks

4 Click Start (This works best if ACT is already open )

5 If you are exporting to a multi-user ACT database enter your ACT User Name and Password

To view each project separately in ACT Group Details

1 In ACT click the Group List icon

2 Double-click the Project Name in the Group Name column The Group Detail appears for the projectyou selected

3 Click the Contacts tab to see Contacts and click the Activities tab to see tasks for that project

4 You should press Ctrl-F5 to refresh the view Also you might have to adjust the Filter in ACT so thatDates to show is set to All Dates

Task names are listed in the Regarding column Assignments are listed in the Scheduled With columnPhases are shown in red and tasks and subtasks are shown in blue

To view tasks from multiple projects sorted by date in Task List or Calendar

In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn Project names are in the Associate With column You might have to adjust the Filter in ACT sothat Dates to show is set to All Dates

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar Tasks are set as timeless (Duration of 0 minutes) so the transferred tasks dont fill up thecalendar

121

copy Experience In Software Inc 1995 - 2006

Tips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

The ACT 7 and later export is smart enough to update your existing tasks from the same project If youexport the same Project KickStart project two or more times ACT recognizes the project and asks ifyou want to update the project information in ACT You do not lose your task history or notes in ACT

Tasks that are unassigned in Project KickStart are listed as Scheduled With Unassigned PKS

You can filter by Selected Users in the Task List and in Groups

See Also

Import ACT Contacts and Users to the People Library

-o-

122

copy Experience In Software Inc 1995 - 2006

Export to ACT 6

If you use ACT 6 ACT 2000 or ACT 5 you can transfer a Project KickStart plan into an ACT databasewith just one click After you export your plan you see your tasks in the ACT Group view grouped underthe name of your project

To export to ACT 61 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 6 and then click

the Go button You can also click File on the menu bar point to Export to and then click ACT 6

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (dbf file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opensEach time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks4 Click Start (This works best if ACT is already open )5 If you are exporting to a multi-user ACT database enter your ACT user name and passwordTo view each project separately in ACT1 In ACT click the Groups icon 2 Click the Project Name listed under All Groups on the left3 On the lower-right part of the window click the Activities tab to see tasks for that project

Task names are listed in the Regarding column Assignments are listed in the Scheduled With column 4 You might have to adjust the Filter in ACT so that Dates to show is set to All Dates Also you might

have to press Ctrl-F5 to refresh the view5 To view task details click the button next to the task column on the leftTo view tasks from multiple projects sorted by date1 In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn You might have to adjust the Filter in ACT so that Dates to show is set to All Dates

2 If the Group column is not showing add it by clicking ViewAdd Columns and then double-clickingGroupThe tasks are identified by group (project name)

3 To view task details click the button next to the task column on the leftTips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar as well as in the Task List

You can filter by Selected Users in the Task List and in Groups

After exporting your tasks to ACT you can import them to your Palm Pilot using the ACT Link

See Also

Import ACT Contacts and Users to the People Library

-o-

123

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Outlook

If you use Microsoft Outlook you can export your plan from Project KickStart to Outlook in a click of abutton After you export your plan you see your tasks in the Outlook Tasks view grouped under a categorynamed for your project In Outlook you can track your tasks and email tasks to team members

To export to Microsoft Outlook1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Outlook and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Outlook The Export to Outlook dialog box opens

2 Click an option button to export All tasks Uncompleted tasks or Completed tasks3 If you want to display the tasks you export on your Outlook Calendar click the check box4 Click the Start button A dialog box opens informing you that Project KickStart is trying to access your

Outlook data

5 Allow access for 1 minute and then click the Yes buttonTo view your tasks in Microsoft Outlook1 Click the Outlook Tasks button2 Depending on the version of Outlook you are using set to view the tasks by category In Outlook 2003

click the By Category option button in the Current View list You can also click View on the menu barpoint to Arrange By and then click CategoriesYour project is listed by its project name in the Categories list

3 Click an expand icon to see the complete list of tasks and subtasks

124

copy Experience In Software Inc 1995 - 2006

4 To view task details double-click the task nameTips

The export to Outlook works best if Outlook is already open

In Outlook you can set priorities set reminders and schedule by the hour

If you export to your Outlook Calendar a reminder appears on the due date of each task

After you export tasks to Outlook you can synchronize with your Palm Pilot Windows CE device orother handheld computer

Note

You can export only to Microsoft Office Outlook not Outlook Express

See Also

Import Outlook Contacts to the People Library

-o-

125

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Word

If you use Microsoft Word you can export your plan from Project KickStart to Word in a click of a buttonYour project appears in a Word table in a doc file You can cut and paste change column widths deletecolumns and print from Word

To export to Microsoft Word

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Word andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Word

Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in a Word document in a doc format

2 When youre finished use Save As to save the Word file with a new name such as ltnamegtdoc Forconvenience you can save the file using the same name as your Project KickStart project name

Benefits of using Project KickStart and Word

Communicate projects flexibly After exporting to Word you can communicate your project details ina variety of text formats You can also enhance your document by adding color logos clip art orhyperlinks

Distribute plans to others You can send doc files to other Microsoft Word users via email andrequest comments using Words Send To and Comments features

Tip

Include your strategic plan in documents letters and web pages in a doc or html file

Note

The image of the Gantt chart does not import into Word automatically You can manually import theGantt chart image into a Word document In Word select Insert on the menu bar point to Pictureclick From File and then browse to the folder containing the Gantt chart images you saved By defaultthis is cMy DocumentsProject KickStart ProjectsPKSGanttImages in a folder named for your project

See Also

Export to Word Processors (Other than Word)

Save Gantt Chart Images

126

copy Experience In Software Inc 1995 - 2006

-o-

127

copy Experience In Software Inc 1995 - 2006

Export to Word Processors (Other than Word)

If you are using a word processor other than Microsoft Word you can export your Project KickStart taskreport by first saving it as an HTML or RTF file

To export to word processors other than Microsoft Word

1 Save a Project KickStart task report using HTML or RTF format using the Save As button in the Createand Print Task Reports dialog box

2 Open the file with your word processor

3 Save the file using the Save As command using a different name

See Also

Print Task Reports

Save as HTML

Save as RTF

-o-

128

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Excel

If you use Microsoft Excel you can export your plan from Project KickStart to Excel in a click of a buttonYour project appears in an Excel worksheet in a xls file You can add task details perform calculationsand share your project data with other Excel users

To export to Microsoft Excel1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Excel and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Excel Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in an Excel worksheet in an xls format

2 When youre done select FileSave As to save the Excel file under a new name For convenience youmight want to save it under the same name as your Project KickStart project name

To manually import Gantt chart images into Microsoft Excel1 In Excel click Sheet2 and select ToolsOptions on the menu bar and unclick the box for Gridlines2 Then select Insert on the menu bar point to Picture click From File and then browse to the folder

containing the Gantt chart images you saved By default this is cMy DocumentsProject KickStartProjectsPKSGanttImages in a folder named for your project

3 Select one Gantt chart image at a time to bring it in 4 You can manipulate the size of the image in Excel

Benefits of using Project KickStart and ExcelProject KickStart is very good at scoping out a schedule but there are a few reasons why you might want touse both programs

Data sharing A Project KickStart user might want to share the information with other Excel users whodont have Project KickStart They could change enhance or redistribute their portions of the schedule

129

copy Experience In Software Inc 1995 - 2006

Add more task details Excel users can add new columns of task data that cant be added in ProjectKickStart

Sort task lists For example you could show your projects tasks sorted by each resources namethen see each resources tasks sorted by the tasks start date

Filter tasks Excel can show tasks that meet certain criteria For instance show tasks with the wordtesting in the task name

See Also

Save Gantt Chart Images

-o-

130

copy Experience In Software Inc 1995 - 2006

Export to Microsoft PowerPoint

If you use Microsoft PowerPoint you can export your plan from Project KickStart to PowerPoint in a click ofa button Your project appears as a formatted PowerPoint presentation in a ppt file

To export to Microsoft PowerPoint

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft PowerPointand then click the Go button You can also click File on the menu bar point to Export to and thenclick Microsoft PointPoint

The Export to PowerPoint dialog box opens where you can choose a PowerPoint design template ifyou like

2 Click the Start button

Your tasks days start and finish dates and costs appear in a PowerPoint presentation with an imageof the Gantt chart in one or more slides at the end of your slide show

Once you have created a PowerPoint presentation you can enhance your slides in several ways

Delete slides that are not appropriate for your presentation

131

copy Experience In Software Inc 1995 - 2006

Rearrange the order of the slides

Add colors for emphasis

Add graphics such as company logo clip art and colors

Shorten any long task titles

Benefits of using Project KickStart and PowerPoint

Save time You can dramatically save time in creating a PowerPoint presentation on your project

Present projects to others Present project details in webinars presentations and corporatemeetings Create template presentations or how tos for implementing an installation productintroduction or corporate policy for example

Communicate plans Email project plans in ppt format to colleagues and presentors

Tips

If you use a PowerPoint design template choose one that has a white or light background for maximumlegibility of the Gantt chart in the presentation

The Gantt chart image in the PowerPoint presentation is generated ldquoon the flyrdquo Change the Timescalesettings of the Gantt chart considering how it will be reflected in the number of images of the Ganttchart For example the Day view results in more Gantt chart images than the Months view

-o-

132

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Project

If you use Microsoft Project 98 2000 2002 or 2003 you can export your plan from Project KickStart toProject in a click of a button

To export to Microsoft Project

In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Project andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Project Your tasks assignments days start and finish dates costs done and notes (excluding attachments) appearin a Microsoft Project file

Benefits of using Project KickStart and Microsoft Project

Share data with others Send a project to a colleague or client that expects to see your schedule in anMicrosoft Project format

Schedule tasks with more flexibility Schedule tasks in different durations particularly in less than aday

Track resources Track resource usage and resource leveling and to have greater flexibility in sortingfiltering and reporting project information

Notes

Project KickStart tasks transfer to Microsoft Project as tasks with a Constraint type of Start No EarlierThan This keeps the dates the same as in the Project KickStart schedule

The settings in Project KickStart Working Days Calendar also transfer to Microsoft Project

Exporting to Microsoft Project allows you to take advantage of the advanced tracking and schedulingfeatures that large projects often require

You can also save your Project KickStart projects as an mpx file which you can open in MicrosoftProject and send to other Microsoft Project users Click File on the Project KickStart menu bar clickSave As and then choose mpx as the file type After you save the file click File on the MicrosoftProject menu bar click Open and open your mpx file

-o-

133

copy Experience In Software Inc 1995 - 2006

Export to SureTrak Project Manager

If you use SureTrak Project Manager you can export your plan from Project KickStart to SureTrak ProjectManager

To export to SureTrak Project Manager

1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file

2 In SureTrak click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

SureTrak

You will see your tasks and assignments (but not the notes) appear in a SureTrak file The file is shownin outline view

Benefits of using Project KickStart and SureTrak

Add new information to tasks such as how they are linked

Track progress particularly for comparing plans verses actual results

Have greater flexibility in sorting filtering and reporting project information

Notes

Task notes are not included in the transfer

A version of Project KickStart called the Project KickStart Wizard is included in SureTrak 2 andSureTrak 3 You can use it within SureTrak

See Also

Export MPX Files

-o-

134

copy Experience In Software Inc 1995 - 2006

Export to FastTrack Schedule

If you use FastTrack Schedule you can save your Project KickStart project as an mpx file and import it intoFastTrack ScheduleTo export to FastTrack Schedule1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file2 In FastTrack Schedule click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

FastTrack ScheduleBenefits of using Project KickStart and FastTrack Schedule

Add more task details FastTrack Schedule provides the features and tools needed in many largeprojects

Multiproject reporting Consolidate multiple projects into a master project file

See Also

Export MPX Files

-o-

135

copy Experience In Software Inc 1995 - 2006

Export to Milestones Professional

If you use Milestone Professional you can export your plan from Project KickStart to MilestonesProfessional in a click of a button

To export to Milestone Professional

In the Schedule step click the Export to list arrow below the Gantt chart click MilestonesProfessional and then click the Go button You can also click File on the menu bar point to Export to and then click Milestones Professional

Your tasks assignments start and finish dates and notes (excluding attachments) appear in aMilestones file

Tips

After you export your tasks to Milestones Professional you can create taskbars add titles and performother tasks to produce a presentation-quality schedule You can also use Milestones to track your tasksby showing task durations and percent completions Make scheduling changes by dragging the taskdates

If you have an earlier version of Milestones (eg version 45 or 5) you can save Project KickStart dataas an mpx file and then open the mpx file in Milestones

-o-

136

copy Experience In Software Inc 1995 - 2006

Export to Mindjet MindManager

If you use Mindjet MindManager 7 or later you can export your project plan from Project KickStart in a clickof a button Or you can develop a rough plan in MindManager and export your mind map to ProjectKickStart for enhanced planning It works both ways

To export from Project KickStart to MindManager

In the Schedule step click the Export to list arrow below the Gantt chart click MindManager and thenclick the Go button You can also click File on the menu bar point to Export to and then clickMindManager

Your tasks assignments start and finish dates durations costs Done and notes (excludingattachments) appear in a MindManager file

To export from MindManager to Project KickStart

In MindManager click File on the menu bar point to Send To and then click Project KickStart Thenclick the OK button to start the export

You can also click the Project KickStart icon at the bottom of the MindManager window

Benefits of using Project KickStart and MindManager together

Visualize your plan in two ways Brainstorm plan and communicate your project details in both agraphical and linear style

Develop a graphical plan and then fine-tune the details MindManager uses mindmappingtechniques to develop a high-level plan in a graphical format Export to Project KickStart to enhanceyour plan details by focusing on your projects goals obstacles and resource needs You can alsocreate a Gantt chart schedule

Communicate concepts Project KickStart users can display their plans in a highly graphicalmindmapping format in MindManager The maps make it easier to communicate complex processesand visually identify important tasks issues and relationships

Tip

If you dont already use MindManager you can purchase it in our Thinking Tools Store

-o-

137

copy Experience In Software Inc 1995 - 2006

Export to WBS Chart Pro

If you use WBS Chart Pro you can export your plan from Project KickStart to WBS Chart Pro in a click of abutton

To export to WBS Chart Pro

In the Schedule step click the Export to list arrow below the Gantt chart click WBS Chart Pro andthen click the Go button You can also click File on the menu bar point to Export to and then clickWBS Chart ProYour project is displayed under the project name Each phase in the project is shown in a box with ashadow Each lower level task in a phase is displayed under their respective phase box groupedtogether with the other tasks in that phase

Benefits of using Project KickStart and WBS Chart

Visualize tasks Work with tasks in a tree-style chart called a Work Breakdown Structure (WBS)chart

Communicate your project plan with others WBS Chart uses the outline you create in ProjectKickStart to create a top-down picture of your plan This picture is similar to an Organization chart Butinstead of displaying the structure of your company a WBS chart displays the structure of your projectplan

Notes

WBS Chart refers to the phases in the project as Summary Tasks and the detail for each phase asTasks

The export only works if WBS Chart is not currently running You must close WBS Chart before you cancreate another chart

See Also

Export MPX Files

-o-

138

copy Experience In Software Inc 1995 - 2006

Export MPX Files

The MPX file format is an ASCII format created by Microsoft Project or another program and is used tosend data to and from project management software programs

The following programs can create and open MPX files

FastTrack Schedule

Microsoft Project (95 or 98)

Project KickStart 5

Project KickStart 32

RiskyProject

SureTrak Project Manager

WBS Chart

In these programs you save a project as an MPX file using the Save As command on the File menu Youcan then open an MPX file by using the Open command on the File menu and then specifying the file typeas mpx

For example if you want to move a project from Project KickStart 5 to Project KickStart 32 you can savethe project as an mpx file and then open it in Project KickStart 32

In Microsoft Visio you can create a Visio project time line from Project KickStart To do so you first mustsave your file in Project KickStart as an MPX file Then

1 Start Visio

2 Click File on the menu bar point to New click Business Diagram and then click Project TimelinesWizard

3 Click Next

4 On the second window click Import MPX File to import the Project KickStart mpx file

5 Enter the file location and name or click Browse to locate the file

6 Follow the instructions in the Visio Project Timelines Wizard windows

Tip

If you have difficulty importing the mpx file remove any commas from task names

-o-

139

copy Experience In Software Inc 1995 - 2006

Reference

140

copy Experience In Software Inc 1995 - 2006

Menus

File Menu

Command Keyboard Shortcut Description

New Project Ctrl+N Creates and names a new project fileOpen Project Ctrl+O Opens a previously saved Project KickStart 4 or 5 file

(prx) Project KickStart 3 file (prj) or mpx fileClose Ctrl+W Closes an open Project KickStart fileSave Ctrl+S Saves a project file (prx) in which you made changes Save As Saves a project file with a different file name or different

file format such as MPXPrint Task Reports

Ctrl+T Generates and prints a report letting you preview thecontents

Print Gantt ChartReports

Ctrl+G In the Gantt chart (Schedule step) generates andprints the Gantt chart in the current timescale

Export To Sends the project to another program such asMicrosoft Outlook or ACT 7

Recent file list Lists the last three files opened in Project KickStartExit

Alt+F4 Exits the program

-o-

141

copy Experience In Software Inc 1995 - 2006

Edit Menu

Command Keyboard Shortcut Description

UndoRedo Ctrl+Z Undoes or repeats the last operationCut

Ctrl+X Deletes the currently selected information placing it on theclipboard so you can paste it elsewhere

Copy

Ctrl+C Places a copy of selected information on the Clipboard so youcan paste it elsewhere

Paste

Ctrl+V Places information from the Clipboard to the currently selectedlocation

Select all Ctrl+A Selects all the content in the windowAdd a line Adds a new row where you can enter text

-o-

142

copy Experience In Software Inc 1995 - 2006

View Menu

Command Description

Tool Bar Shows or hides the toolbar (a checkmark indicates thetoolbar is displayed)

Steps Bar Shows or hides the Steps bar (a checkmark indicates the Steps bar is displayed)

Name Go to the Name your project stepPhases Go to Phases stepGoals Go to Goals stepSimilar Projects Go to Similar projects stepPeople Go to People stepObstacles Go to Obstacles stepAssign Go to Assign tasks to people stepTasks Go to Tasks stepSchedule Go to Schedule step

-o-

143

copy Experience In Software Inc 1995 - 2006

Tools Menu

Command Keyboard Shortcut Description

Spelling

F7 Checks spelling of project dataexcept for names of people

Collaboration To access or find out aboutGoToMeeting

Options Select options for running thesoftware

-o-

144

copy Experience In Software Inc 1995 - 2006

Options

-o-

145

copy Experience In Software Inc 1995 - 2006

Data Menu

The Data menu is available in the Tasks and Schedule steps for manipulating tasks and creating ascheduleCommand Description

Move Up Moves the selected task item upMove Down Moves the selected task item downOutdent Moves the selected task item to the leftIndent Moves the selected task item to the rightInsert Task Insert task in row aboveInsert SubTask Insert subtask below current rowDelete Task Delete current taskEdit Task Properties Brings you to an edit screen where you can edit task

name change assignments and edit task notesEdit Notes Brings you to an edit screen for editing task notesColor Taskbars Change the color of selected tasks (in Schedule)Change Working Days Select which days are working and which are

nonworking (in Schedule)Link Tasks Link tasks in Gantt chart (Pro Users)Unlink Tasks Unlink tasks in Gantt chart (Pro Users)

-o-

146

copy Experience In Software Inc 1995 - 2006

Timescale Menu

The Timescale menu is available in the Schedule step so you can change the display of the Gantt chartschedule

Command Description

Days Displays a daily schedule in theGantt chart

Weeks Displays a weekly schedule inthe Gantt chart

Months Displays a monthly schedule inthe Gantt chart

Quarters Displays a quarterly schedule inthe Gantt chart

Years Displays a yearly schedule inthe Gantt chart

-o-

147

copy Experience In Software Inc 1995 - 2006

Help Menu

Command Description

Project KickStart Help Help for Project KickStart including a Table ofContents and index of terms

Online Tutorials View several Getting Started Tutorials to getyou started with Project KickStart whether youare a new or experienced user

Keyboard Shortcuts Shortcuts for programTechnical Support How to obtain Technical Support for Project

KickStart via web form and email[Send Log to Technical Support] If the program detects an error it writes a log

of technical issues Click Send Log toTechnical Support to send the error log to us

ProjectKickStartcom Visit the Project KickStart Web siteGet Latest Version See what the latest published version is and

download it if you need itAbout Project KickStart Shows Project KickStart version number build

date copyright and system information

-o-

148

copy Experience In Software Inc 1995 - 2006

Shortcuts

Use the following keyboard shortcuts to move quickly around in Project KickStart

Navigation

Move forward to the next window Alt+NMove back to the previous window Alt+BSteps

Go to Name step Alt+MGo to Phases step Alt+SGo to Goals step Alt+GGo to Similar step Alt+RGo to People step Alt+PGo to Obstacles step Alt+OGo to Assign step Alt+IGo to Tasks step Alt+KGo to Library (Phases Tasks GoalsPeople Obstacles)

Alt+L

Menus

File menu Alt+FEdit menu Alt+EView menu Alt+VShow menu (Tasks step) Alt+WOutline menu (Tasks step) Alt+UTimescale (Schedule step) Alt+CHelp menu Alt+H F1Other

Edit tasks assignments amp notes (Tasks step)F3Save Ctrl+SPrint Task Report Ctrl+PPrint Gantt Chart (Schedule step) Ctrl+GCut Ctrl+XCopy Ctrl+CPaste Ctrl+VInsert Row InsertDelete Row DeleteInsert Line Break (in Notes in Task List andSchdule steps)

Enter

Spell Check

Ignore Alt+IIgnore All Alt+GChange Alt+CChange All Alt+HHelp

149

copy Experience In Software Inc 1995 - 2006

Contents in Help Alt+CIndex Alt+IBack in Help Alt+BClose Help Alt+LHelp about the current step Alt+H

-o-

150

copy Experience In Software Inc 1995 - 2006

Share Project KickStart Data

Project KickStart makes it easy to share data with other people involved with a project You can share yourProject KickStart data in the following ways

Send a printed report Make a PowerPoint presentation Send a file (prx html rtf mpx) Post an HTML file to a Web site and access it with your web browser Export to other programs such as Microsoft Word or Excel and send data in a format the recipient can

access (such as doc xls or mpx)

Note

You can also collaborate with a colleague by conducting an online meeting using GoToMeeting (Prousers)

-o-

151

copy Experience In Software Inc 1995 - 2006

Open a Project

After you create a project and save it in a prx prj or mpx file using Project KickStart or other softwareyou can open the project in Project KickStartTo open a project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click a file type (prxprj or mpx)

3 Navigate to the folder that contains the file4 Double-click the name of the file

Opening a Project KickStart 3 prj file converts it to a prx file

Generally prj files are stored in cprogram filesProject KickStart 3

The tasks in the converted Project KickStart 5 file will have the same start and finish dates anddurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way To have weekends as non working days open the working days calendar and markweekends as non working

Opening a mpx file converts it to a prx file

The tasks in each project have the same start and finish dates and durations

-o-

152

copy Experience In Software Inc 1995 - 2006

Dedication

I dedicate this software program to my new colleague

Kevin Ahlvin

Roy A Nierenberg President

-o-

153

copy Experience In Software Inc 1995 - 2006

Credits and Trademarks

Credits

Missak Koumoudjian Program Architect and Chief Programmer

Kevin Ahlvin Interface DesignAnn Kawamoto Quality AssuranceAlexander Setzepfandt Quality AssuranceJackie LeungJeffrey Chow

Programming Interns

Kevin Ahlvin Product Supervisor and CoordinatorJoseph Fusco Project Management Consultant and content

providerLisa RuffoloJoseph Fusco

Help System

Roy A Nierenberg President

Trademark

Project KickStart and Project KickStart Wizard are trademarks of Experience In Software Inc in the UnitedStates andor in other countries All rights reserved All other trademarks mentioned herein are the propertyof their respective owners

-o-

154

copy Experience In Software Inc 1995 - 2006

Uninstalling

You can uninstall Project KickStart 5 through the Control Panel AddRemove Programs Select ProjectKickStart 5 This starts the InstallShield Maintenance Program You should then remove all of theprogram files that were installed It will not erase your Project KickStart prx data files

If that does not work you can delete the Project KickStart files manually

Note

If you purchased Project KickStart and you want to return it for a refund follow the instructions forDe-activating the software at httpwwwprojectkickstartcomcontactreturnscfm

-o-

155

copy Experience In Software Inc 1995 - 2006

Using Past Projects

You can use past projects in two ways

If you have projects that are similar you can use a past project as a template for a new project In theWelcome window select Open a Project Open that project and Save As under a different name Nowyou can open up the renamed project and modify it for the current project

You can draw from several projects in the Similar Projects step First select projects that are similarand click Next Then select tasks from those projects and decide where they would fit into your currentproject

See Also

Opening a project Compatibility with earlier versions

-o-

156

copy Experience In Software Inc 1995 - 2006

Index

- - Change Working Schedule 85

- -prj file format 13

- A -About Linking Tasks (Pro Users) 59About Scheduling Tasks 55About the Gantt Chart 57ACT 120 92 122ACT 6 92 122ACT 7 or later 92 120Activate 14Activating Trial Version 14Add a New Person or Resource 39add a subtask 83add a task 83Add a Task or Subtask 47Add or Change Task Assignments 51Add or Change Task Details 52Add Subtask 63Add Task 63Add URL 49Additional Features in Task Data View (Pro Users) 68Additional Tools in Chart View (Pro Users) 71Adobe PDF 117Assignments tab 80Attachments 49Autolink tasks (Pro Users) 58

- B -Back 10borrow tasks 29

- C -Change Details for Linked Tasks (Pro Users) 81Change Project Start 63Change Task Dates 73Change Task Details 80Change the Appearance of the Task List 43Change the Display of the Schedule 61Change Timescale 63Change Working Schedule 63Chart view 57

157

copy Experience In Software Inc 1995 - 2006

Cloning projects 155Color 63 86Compatibility 13Compatibility with earlier versions 13convert projects 13Coordination 12Create and Print Task Reports 102Credits 153Credits and Trademarks 153critical path 88CSV 96Customer support 20Customer Support 20Customizing Project KickStart

- D -Dashboard 99Data Menu 145Dedication 152Delete 63delete a task 83demote 46dependencies 12 76

- E -Edit Menu 141Edit Notes and Attachments 63Edit or Substitute People 40Edit Task Information 63Email Task Reports 108End User License Agreement 16error 21Error Messages 21export from MindManager 136Export MPX Files 138Export to ACT 6 122Export to ACT 7 and Later 120Export to FastTrack Schedule 134Export to Microsoft Excel 128Export to Microsoft Outlook 123Export to Microsoft PowerPoint 130Export to Microsoft Project 132Export to Microsoft Word 125Export to Milestones Professional 135Export to Mindjet MindManager 136Export to SureTrak Project Manager 133Export to WBS Chart Pro 137

- F -FastTrack Schedule 134File Menu 140Fit to page 111Fit to Smallest Size 111

158

copy Experience In Software Inc 1995 - 2006

- G -Gantt chart 55 57General tab 80Goal 26Goal statements 26Goals 26Goals - Step 1 of 3 26Goals - Step 2 of 3 27Goals - Step 3 of 3 28goals library 26 89Goalsadd 26Goalsdelete 26Goalsedit 26Goalstasks for 27GoToMeeting 150 12

- H -Handouts 111Help Menu 147hyperlink 49

- I -Import ACT 92import contacts and users 92import Outlook contacts 94Import Outlook Contacts via CSV to the People Library (Pro Users) 96ImportCSVToPKSexe 96Indent 46Individual Assignments 102Introduction 7Introduction 7

- K -Knowledge Libraries 90

- L -lag time 81lead time 59 81library 89License Key 14link 59Link lines 59Link tasks 12 65linked tasks 59

- M -major activities 24Make Tasks Overlap (Pro Users) 87Manage a Library 90

159

copy Experience In Software Inc 1995 - 2006

Menu 140Microsoft Excel 128Microsoft Outlook 123Microsoft PowerPoint 130Microsoft Project 132Microsoft Project (95 or 98) 138Microsoft Visio 138Microsoft Word 125Milestone 69 79Milestones Professional 135Mindjet MindManager 136MindManager 136

- N -Name 23Name Your Project 23Navigating Project KickStart 10Next 10Notes and Attachments tab 80

- O -Objectives 26Obstacles 34Obstacles - Step 3 of 3 36Obstacles Library 89Open a Project 151Options 144Outdent 46Outdent and Indent arrows 63Outlook Calendar 123Overview

- P -Page Setup 107 116 100PDF 117people 31People - Step 3 of 3 28People Library 91phase 24phase dates 75Phase Dates Cannot Be Edited 75phases 24Phases - Step 1 of 2 24Phases - Step 2 of 2 25Phases Library 89Phases Goals People amp Obstacles 102PowerPoint presentation 130Pred 68Predecessor 68Predecessor tasks 59predecessors 76Print a Gantt Chart 111Print Dashboard Reports 99Print Preview 105Print Preview a Gantt Chart 115Print Reports 98Print Task Reports 102

160

copy Experience In Software Inc 1995 - 2006

Printer Setup 106Printing to an Adobe PDF file 117prj 13Pro 145Pro Edition 145Product support 20Project 23Project KickStart 3 prj file 151Project KickStart for Windows 7project name 23project start date 73project template 155project title 23promote 46promote and demote tasks 83

- Q -Quick Tour of Working with Linked Tasks (Pro Users) 76

- R -Red vertical line 69Redo 11Register Project KickStart 22Registering Project KickStart 22remove people 38Remove People from a Task 38reorder tasks 83Reorganize Tasks in Task Data View 83Repeat tasks on every page (for handouts) 111Reporting Technical Issues 21resource 31resources 31restore 34return 154risks 34RiskyProject 138

- S -Save As 101Save as HTML 109Save as RTF 110Save Gantt Chart Images 118Schedule 55Send Error Report 21similar projects 29spelling 53starter schedule 55Steps 7subtask 47Subtasks 46Succ 68Successor 68Successor tasks 59successors 76Summary bar 69Support 20SureTrak Project Manager 133

161

copy Experience In Software Inc 1995 - 2006

- T -Task Data view 57task dates 73Task Report 102Taskbar 69Taskbar with percent done 69Tasks 25Tasks in Phases 25Tasks Library 89team 31Technical support 20timescale 84Timescale Menu 146Tools Menu 143Trademark 153trademarks 153Trial 14

- U -unassigning 38Understand Chart View 69Understand Task Data View 66Undo 11UndoRedo Buttons 11uninstallUninstalling 154Unlink tasks 12 65Up and Down arrows 63Use Project KickStart to 8Use the Gantt Chart Toolbar 63Use the Planning Wizard 9Uses 8Using Past Projects 29 155

- V -Version View Menu 142Visio 138

- W -Wall chart 111WBS Chart Pro 137Welcome to Project KickStart 7Whats Due Next Month 99Whats Due Next Week 99Whats Due Today 99Whats New in Project KickStart Pro 5 11Windows Vista 20

162

copy Experience In Software Inc 1995 - 2006

copy Experience In Software 2008w w w projectkickstartcom

  • Table of Contents
  • Start Here Welcome to Project KickStart
    • Introduction
      • Welcome to Project KickStart
      • Use Project KickStart to
      • Use the Planning Wizard
      • Navigating Project KickStart
      • Whats New in Project KickStart Pro 5
      • Whats New in Project KickStart Pro 5 (Pro Users)
      • Compatibility with earlier versions
      • Activating Trial Version
        • Licenses and Support
          • End User License Agreement
          • Customer Support
          • Reporting Technical Issues
          • Register Project KickStart
              • Planning Projects
                • Name Your Project
                • Phases - Step 1 of 2
                • Phases - Step 2 of 2
                • Goals - Step 1 of 3
                • Goals - Step 2 of 2
                • Goals - Step 3 of 3
                • Similar Projects - Step 1 of 2
                • Similar Projects - Step 2 of 2
                • People - Step 1 of 3
                • People - Step 2 of 3
                • People - Step 3 of 3
                • Obstacles - Step 1 of 3
                • Obstacles - Step 2 of 3
                • Obstacles - Step 3 of 3
                  • Assigning People
                    • Assign Tasks to People
                    • Remove People from a Task
                    • Add a New Person or Resource
                    • Edit or Substitute People
                      • Organizing the Project Plan
                        • About Organizing Tasks
                        • Change the Appearance of the Task List
                        • Show or Hide Tasks in the Task List
                        • Move Tasks within the Task List
                        • Outdent and Indent Tasks
                        • Add a Task or Subtask
                        • Edit Tasks
                        • Add Task Notes and Attachments
                        • Add or Change Task Assignments
                        • Add or Change Task Details
                        • Check Spelling
                          • Scheduling Tasks in the Gantt Chart
                            • Scheduling Overview
                              • About Scheduling Tasks
                              • About the Gantt Chart
                              • Autolink tasks (Pro Users)
                              • About Linking Tasks (Pro Users)
                              • Change the Display of the Schedule
                              • Use the Gantt Chart Toolbar
                              • Use the Gantt Chart Toolbar (Pro Users)
                              • Understand Task Data View
                              • Additional Features in Task Data View (Pro Users)
                              • Understand Chart View
                              • Additional Tools in Chart View (Pro Users)
                                • Change Task Dates
                                • Phase Dates Cannot Be Edited
                                • Quick Tour of Working with Linked Tasks (Pro Users)
                                • Link and Unlink Tasks (Pro Users)
                                • Create a Milestone
                                • Change Task Details
                                • Change Details for Linked Tasks (Pro Users)
                                • Reorganize Tasks in Task Data View
                                • Change the Timescale of the Schedule
                                • Specify Working Days
                                • Change the Color of Taskbars
                                • Make Tasks Overlap (Pro Users)
                                • Manage Changes in Your Schedule (Pro Users)
                                  • Managing Libraries
                                    • Use a Library
                                    • Manage a Library
                                    • Manage the People Library
                                    • Import ACT Contacts and Users to the People Library
                                    • Import Outlook Contacts to the People Library
                                    • Import Outlook Contacts via CSV to the People Library (Pro Users)
                                      • Printing Reports
                                        • Printing Dashboards
                                          • Print Reports
                                          • Print Dashboard Reports
                                          • Page Setup
                                          • Save As
                                            • Printing Task Reports
                                              • Print Task Reports
                                              • Print Preview
                                              • Printer Setup
                                              • Page Setup
                                              • Email Task Reports
                                              • Save As HTML
                                              • Save As RTF
                                                • Printing Gantt Chart Reports
                                                  • Print a Gantt Chart
                                                  • Print Preview a Gantt Chart
                                                  • Page Setup
                                                  • Printing to an Adobe PDF file
                                                  • Save Gantt Chart Images
                                                      • Export Project Data
                                                        • Export to ACT
                                                          • Export to ACT 7 and Later
                                                          • Export to ACT 6
                                                            • Export to Microsoft Outlook
                                                            • Export to Microsoft Word
                                                            • Export to Word Processors (Other than Word)
                                                            • Export to Microsoft Excel
                                                            • Export to Microsoft PowerPoint
                                                            • Export to Microsoft Project
                                                            • Export to SureTrak Project Manager
                                                            • Export to FastTrack Schedule
                                                            • Export to Milestones Professional
                                                            • Export to Mindjet MindManager
                                                            • Export to WBS Chart Pro
                                                            • Export MPX Files
                                                              • Reference
                                                                • Menus
                                                                  • File Menu
                                                                  • Edit Menu
                                                                  • View Menu
                                                                  • Tools Menu
                                                                  • Options
                                                                  • Data Menu
                                                                  • Timescale Menu
                                                                  • Help Menu
                                                                    • Shortcuts
                                                                    • Share Project KickStart data
                                                                    • Open a Project
                                                                    • Dedication
                                                                    • Credits and Trademarks
                                                                    • Uninstalling the software
                                                                    • Using Past Projects
Page 8: Project KickStart Help File in PDF format

8

copy Experience In Software Inc 1995 - 2006

Use Project KickStart to

Project KickStart is organized into three sections planning scheduling and exporting to other programs

Plan The Project KickStart graphical interface acts as a Planning Wizard guiding you through eightsteps for planning your project Some planning steps involve brainstorming to identify tasks that youmight otherwise overlook

Schedule The Project KickStart Gantt chart makes scheduling tasks fast and easy You can printtaskbars in color and save Gantt charts reports as images so you can email them to colleagues orinclude them in a report

Export Communicate your projects in a variety of ways by exporting project data to other applicationsincluding Microsoft Outlook With one mouse click you can include Project KickStart plans in aMicrosoft Word document Excel spreadsheet PowerPoint slide presentation and more

People are using Project KickStart to

Create process templates project reports to-do lists and more

Communicate project details to others through reports email and Gantt chart schedules

Ensure project buy-in by including the needs of team members in your plan

Consider project goals and obstacles in the planning process and prevent surprises later

-o-

9

copy Experience In Software Inc 1995 - 2006

Use the Planning Wizard

Project KickStart uses a Planning Wizard that guides you through eight steps for planning your project Tostep through the wizard click each icon on the Steps bar (on the left side of the Project KickStart window) inorder On each window t ips and advice are always available by clicking the Advisor button You click theNext button to continue

Name Each project has a name To start planning your project give it ashort descriptive name

Phases Consider how your project will break down into major activitiesor phases Start by listing your phases and then list the tasks thatbelong in each phase

Goals Goals are what you hope to accomplish in your project Enter orselect the goals for your project Then you can list any new tasks toachieve each goal

Similar Projects often have tasks in common In this step you canborrow tasks from past projects to help you plan this project Then youcan add any new tasks from a similar project to the phases of yourcurrent project

People List the people groups or things that might provide resourcesfor your project including yourself Then identify any new tasks thesepeople might do or suggest for your project

Obstacles Each project has obstacles you can overcome if youanticipate them List the obstacles you will face in your project and thenidentify any new tasks needed to avoid the obstacles

Assign Assign tasks to people and other resources

Tasks Change the order of your tasks add and delete tasks andcreate subtasks You can also edit tasks change assignments and addnotes

Schedule Schedule the tasks in your project To make schedulingeasier new projects open with a starter schedule beginning todaywhich you can customize to fit your project

-o-

10

copy Experience In Software Inc 1995 - 2006

Navigating Project KickStart

When you use the Planning Wizard you work with a step window similar to the following illustration

Steps bar Click a step button to perform a step in the Planning Wizard The selected button shows yourcurrent step

Name of your project Shows the name entered in the Name step

Menu bar Select options from the menu bar to work with your projects

Toolbar Click buttons to perform common tasks such as saving your project

Step instructions Indicate how to perform the current step

Library button Click to open a library for the current step For example click the Goals Library button toopen a library listing typical project goals

Back and Next buttons Click a button to return to the previous step or continue to the next step in thePlanning Wizard

Advisor button Click to see instructions tips and notes for completing the current step

-o-

11

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5

The following table outlines whatrsquos new in Project KickStart Pro 5

If you own a previous version of Project KickStart yoursquoll notice the new Pro version has a new look and feelAs you begin to check it out yoursquoll soon discover Project KickStart Version 5 is a lot more powerful thanprevious versions and comes with some great new features

FEATURE DESCRIPTION IMPROVED

NEW

Dashboard Reporting

Quickly assess what is due TodayNext Week or Next Month

X

Import Contacts Import from a comma separatedvalue (CSV) file

X

Templates Use as is or customize X

Gantt Chart Greater stability and functionality X

User Interface Contemporary look and colorscheme

X

Preferences Customize look and feel andprogram defaults

X

Productivity Pack Project template Word docs fornewbies

X

Exports Improved Outlook MindManager and ACTimproved data exchange

X

-o-

12

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5 (Pro Users)

This feature is available only in Project KickStart Professional

The following table outlines whatrsquos new in Project KickStart Pro 5

FEATURE DESCRIPTION IMPROVED NEW

Gantt Chart Task dependencies in Gantt chart X

Link tasks Show task dependencies X

Unlink tasks Remove task dependencies X

Add predecessors Add task predecessors X

Add successors Add task successors X

Project Coordination Link to GoToMeeting for onlinemeetings on projects

X

Project KickStart Pro now includes dependencies on the Gantt chart This sophisticated scheduling andproject management tool is new to Project KickStart Pro and is designed to make complex projectscheduling easy and straightforward

Use dependencies to handle scheduling demands delays and surprises without modifying every task inyour project Dependencies let you make adjustments as events change giving you a more robust scheduleand the opportunity to conduct what-if analysis

Suppose you are managing a landscaping project involving subcontractors and dozens of tasks One ofyour first tasks is to pave a path with flagstones but the shipment of flagstones is two days late Usingdependencies you can delay the path-paving task in a couple of clicks and Project KickStart Proautomatically updates the schedule for the remaining tasks

Although dependencies meet your advanced scheduling needs the Project KickStart Pro approach todependencies keeps them as simple as possible If you want to link a couple of tasks which are dependenton one another you can simply highlight the tasks and click the link icon

If you select the option of Autolinking tasks then when you display the Gantt chart the first time all tasksare pre-linked allowing you to adjust durations schedules of individual tasks and time between taskswhich is called Lead Time in Project KickStart Pro

Unlike other project management programs such as Microsoft Project Project KickStart Pro does notburden you with complicated error messages and various types of dependencies It provides only one typeof dependency finish-to-start which is the most common type This means you can fine-tune your scheduleas soon as you open the Gantt chartmdashwithout having to learn technical terms or advanced projectmanagement techniques

The Project Coordination functionality that we are providing is through GoToMeeting and is a chargedservice

Note

These features are in addition to those listed on the Whatrsquos New in Project KickStart 5 page

-o-

13

copy Experience In Software Inc 1995 - 2006

Compatibility with earlier versions

Project KickStart 5 can open and save projects in Project KickStart 4 prx file format (Same as ProjectKickStart 5)

Project KickStart 5 can open and convert projects saved in Project KickStart 3 prj file format You need tohave a licensed copy of Project KickStart 3 on your system to make the conversion

To open a prj project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click prj file type3 Navigate to the folder that contains the prj file Generally prj files are stored in cprogram filesProject

KickStart 34 Double-click the name of the file

Tips

The tasks in the converted Project KickStart 5 file will have the same start and finish dates and samedurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way (ie as working days) To have weekends as non working days click the Change WorkingSchedule button on the Gantt chart toolbar and mark weekends as non working

Note

Project KickStart 5 does not open and convert prj files from Project KickStart 1 or 2

-o-

14

copy Experience In Software Inc 1995 - 2006

Activating trial version

You may have obtained a FREE 20-day trial version of Project KickStart 5 from our website or from areseller

To convert your Trial Version to a Full Version youll need to purchase a License Key and to activate thesoftware

To activate Project KickStart 5 trial1 Start the Project KickStart trial

2 If you have not purchased your License Key yet click the Buy button to purchase online3 If you have purchased a License Key click the Activate button and copy and paste the License Key

that you received when you purchased Project KickStart as well as your name and email

15

copy Experience In Software Inc 1995 - 2006

4 You must be connected to the Internet and you must tell your Firewall to allow communication forPKS5Kickstartexe

Tip

Your License Key allows 2 activations per user One is for your primary computer and one is for asecond computer you use such as your laptop or home computer

-o-

16

copy Experience In Software Inc 1995 - 2006

Licenses and Support

End User License Agreement

EXPERIENCE IN SOFTWARE INC END USER LICENSE AGREEMENT AND WARRANTYDISCLAIMER

PROJECT KICKSTARTtrade STANDARD 5 AND PRO 5 EDITIONS

NOTICE This is a legally binding contract between you the end user and EXPERIENCE IN SOFTWAREINC

EXPERIENCE IN SOFTWARE INC (EIS or LICENSOR) LICENSES THE ENCLOSED SOFTWARETO YOU (USER or LICENSEE) ONLY UPON THE CONDITION THAT YOU ACCEPT ALL OF THETERMS CONTAINED IN THIS LICENSE AGREEMENT PLEASE READ THE TERMS CAREFULLY BYOPENING THIS PACKAGE BREAKING THE SEAL CLICKING ON THE ldquoAGREErdquo OR ldquoYESrdquo BUTTONOR OTHERWISE INDICATING ASSENT ELECTRONICALLY OR LOADING THE SOFTWARE YOUAGREE TO THE TERMS AND CONDITIONS OF THIS AGREEMENT IF YOU DO NOT AGREE TOTHESE TERMS AND CONDITIONS CLICK ON THE ldquoI DO NOT AGREErdquo ldquoNOrdquo BUTTON OR MAKE NOFURTHER USE OF THE SOFTWARE IF YOU DO NOT AGREE TO THESE TERMS THEN EIS ISUN-WILLING TO LICENSE THE SOFTWARE TO YOU IN WHICH EVENT YOU SHOULD RETURN THEFULL PURCHASED PRODUCT WITH PROOF OF PURCHASE TO LICENSOR OR THE DEALER FROMWHOM IT WAS ACQUIRED WITHIN 15 DAYS OF PURCHASE AND YOUR MONEY WILL BEREFUNDED

LICENSE AND WARRANTY

The software that accompanies this license (Software) is the property of EIS and is protected by copyrightand other intellectual property law Although EIS at all times owns the Software you will have certain rightsto use the Software after your acceptance of this license Except as may be modified by an addendumwhich may accompany or be added to this license your rights and obligations with respect to the use of thisSoftware are as follows

You may

(i) install and use one copy of the specified edition of Software and documentation on a single computerand only by one user (ldquoPrimary Userrdquo) If you have purchased multiple licenses for the Software asindicated as Quantity or Number of Licenses on the Invoice or electronic confirmation issued by EIS orits Resellers then at any time you may have as many copies of the Software in use as you have licenses The Software is ldquoin userdquo on a computer when it is loaded into the temporary memory (ie RAM) or installedinto the permanent memory (eg hard disk CD-ROM or other storage device) of that computer

(ii) install and use a second copy of the Software on a second computer for the limited and exclusive use ofthe Primary User

(iii) use the Software on a network provided that Licensee has a licensed copy of the Software for eachnamed user that can access the Software over that network

(iv) make one copy of the Software for archival purposes or copy the Software onto the hard disk of yourcomputer and retain the original for archival purposes

(v) after written notice to EIS transfer the Software on a permanent basis to another person or entityprovided that you retain no copies of the Software and the transferee agrees to the terms of this agreement

You may not

(i) rent lease copy distribute license or otherwise transfer the Software or its documentation to any otherparty Licensee may make a reasonable number of back-up copies for archival purposes only TheSoftware contains copyrighted material trade secrets and other proprietary material If Licensee has theright to duplicate the Software for multiple Users then Licensee must reproduce on all such copies of theSoftware the copyright notices and any other proprietary legends that were on the original copy of theSoftware or

(ii) decompile reverse engineer disassemble translate make any attempt to discover the source code ofthe Software or otherwise reduce the Software to a human perceivable form or modify network or create

17

copy Experience In Software Inc 1995 - 2006

derivative works based upon the Software or the documentation in whole or in part nor permit any otherparty to do so

Notwithstanding anything herein if the Software is lawfully acquired outside of the United States within ajurisdiction which is a member of the European Union subject to the EEC Council Directive 91250EEC ofMay 14 1991 Licensee agrees that within that jurisdiction it shall not and shall not allow any party onLicensees behalf to attempt to reverse engineer or decompile the Software into another computerlanguage except as expressly and specifically provided in the EEC Council Directive 91250EEC of May14 1991 Any and all information obtained during such lawful reverse engineering andor decompilingactivities including but not limited to the organization logic algorithms and processes of the Softwareshall be deemed to be the confidential and proprietary information of EIS

Licensee shall not make copies of the copyrighted Software documentation without the prior writtenpermission of EIS provided that for electronic transactions Licensee may make one (1) hard copy of suchdocumentation for each User

Intellectual Property and Duplication of Software

The Software contains copyrighted material trade secrets and other proprietary material If Licensee hasthe right to duplicate the Software for multiple Users then Licensee must reproduce on all such copies ofthe Software the copyright notices and any other proprietary legends that were on the original copy of theSoftware

Upgrades

To use a Product identified as an upgrade you must first be licensed for the product identified by EIS aseligible for the upgrade After upgrading you may no longer transfer the product that formed the basis foryour upgrade eligibility to another person or entity

Technical Support

Licensee must register the Software in order to be eligible for free technical support (including installationand registration of the product) during the first 90 days after purchase

Thirty Day Money Back Guarantee

If you are the original Licensee of this copy of the Software and are dissatisfied with it for any reason youmay return the complete product together with your receipt to EIS or an authorized dealer postageprepaid for a full refund at any time during the thirty-day period following the delivery to you of thePurchased Software

Export Law Assurances

You are responsible for complying with all trade regulations and laws both foreign and domestic Youacknowledge that none of the Software or underlying information or technology may be downloaded orotherwise exported or re-exported (i) into Afghanistan (Taliban-controlled areas) Cuba Iran Iraq LibyaNorth Korea Serbia (except Kosovo) Sudan and Syria or any other country subject to a US embargo or(ii) to anyone on the US Treasury Departments list of Specially Designated Nationals or the USCommerce Departments Denied Parties List or Entity List By using the Software you are agreeing to theforegoing and are representing and warranting that (i) no US federal agency has suspended revoked ordenied you export privileges (ii) you are not located in or under the control of a national or resident of anysuch country or on any such list and (iii) you will not export or re-export the Software to any prohibitedcounty or to any prohibited person entity or end-user as specified by US export controls as defined byEAR 15 CFR Parts 730-774 and BXA (httpwwwbxadocgov)

Data Collection and Privacy Policy

You acknowledge and agree that EIS may collect and retain information about you such as your nameaddress and e-mail address You also understand that EIS may employ other companies to performfunctions on our behalf such as fulfilling orders delivering packages sending postal mail and e-mailproviding marketing assistance and processing credit card payments These companies may have accessto personal information needed to perform their functions and may not use such information for otherpurposes By assenting to this agreement you agree that you have read and understand our Privacy PolicyFor more detailed information httpwwwprojectkickstartcomhtmlprivacy_statementhtm

Termination

This License is effective until terminated Licensee may terminate this License at any time by destroying allcopies of the Software and its documentation This License will terminate immediately without notice from

18

copy Experience In Software Inc 1995 - 2006

EIS if Licensee fails to comply with any provision of this License Upon termination Licensee must destroyall copies of the Software and its documentation and cease and desist from any further use of the Software

Limited Warranty

EIS warrants that the media on which the Software is distributed will be free from defects and that theSoftware shall perform substantially as described in its documentation for a period of sixty (60) days frompurchase Your sole remedy in the event of a breach of this warranty will be that EIS will replace anydefective media returned to EIS within the warranty period EIS does not warrant that the Software willmeet your requirements or that operation of the Software will be uninterrupted or that the Software will beerror-free

THE ABOVE WARRANTY IS EXCLUSIVE AND IN LIEU OF ALL OTHER WARRANTIES WHETHEREXPRESS OR IMPLIED INCLUDING THE IMPLIED WARRANTIES OF MERCHANTABILITY FITNESSFOR A PARTICULAR PURPOSE AND NONINFRINGEMENT OF INTELLECTUAL PROPERTY RIGHTSTHIS WARRANTY GIVES YOU SPECIFIC LEGAL RIGHTS YOU MAY HAVE OTHER RIGHTS WHICHVARY FROM STATE TO STATE AND COUNTRY TO COUNTRY

Disclaimer of Damages

REGARDLESS OF WHETHER ANY REMEDY SET FORTH HEREIN FAILS OF ITS ESSENTIALPURPOSE IN NO EVENT WILL EIS OR ITS RESELLERS BE LIABLE TO YOU FOR ANY SPECIALCONSEQUENTIAL INDIRECT OR SIMILAR DAMAGES INCLUDING BUT NOT LIMITED TO ANY LOSTPROFITS OR LOST DATA ARISING OUT OF THE USE OR INABILITY TO USE THE SOFTWARE EVENIF EIS HAS BEEN ADVISED OF THE POSSIBILTIY OF SUCH DAMAGES SOME STATES DO NOTALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FOR INCIDENTAL OR CONSEQUENTIALDAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAY NOT APPLY TO YOU IN NO CASESHALL EISS ITrsquoS RESELLERrsquoS LIABILITY EXCEED THE PURCHASE PRICE FOR THE SOFTWARE

SOME STATES AND COUNTRIES INCLUDING MEMBER COUNTRIES OF THE EUROPEANECONOMIC AREA DO NOT ALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FORINCIDENTAL OR CONSEQUENTIAL DAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAYNOT APPLY TO YOU

The disclaimers and limitations set forth above will apply regardless of whether you accept the Software

US Government Restricted Rights

DISTRIBUTION TO THE US GOVERNMENT This Software is commercial software developedexclusively at private expense This Software and the documentation are provided with RESTRICTEDRIGHTS applicable to private and public licenses alike Use duplication or disclosure by civilian agenciesof the US Government shall be in accordance with the Commercial Computer Software-Restricted Rightsclause at FAR 52227-19 Use duplication or disclosure by Department of Defense agencies is subjectsolely to the terms of this software licensing agreement pursuant to DFARS 2277202Contractormanufacturer of the Software is EXPERIENCE IN SOFTWARE INC 2029 Durant AveBerkeley CA 94704 USA

General

This Agreement shall be governed by the laws of the State of California without giving effect to principles ofconflict of laws You hereby consent to the exclusive jurisdiction and venue of the state courts sitting in SanFrancisco County California or the federal courts in the Northern District of California to resolve anydisputes arising under this Agreement This Agreement contains the complete understanding between theparties with respect to the subject matter hereof and supersedes all prior or contemporaneous Agreementsor understandings whether oral or written You agree that any varying or additional terms contained in anypurchase order or other written notification or document issued by you in relation to the Software licensedhereunder shall be of no effect No provision hereof shall be deemed waived or modified except in writing No EIS dealer agent or employee is authorized to make any amendment to this Agreement

The intellectual property protections the disclaimers of warranties and the limitation of damages shallsurvive termination The failure or delay of EIS to exercise any of its rights under this Agreement or uponany breach of this Agreement shall not be deemed a waiver of those rights or of the breach If any provisionof this Agreement is held invalid the remainder of this Agreement will remain in full force and effect

Should you have any questions concerning this Agreement or if you desire to contact EIS for any reasonplease write to EXPERIENCE IN SOFTWARE INC 2029 Durant Ave Berkeley CA 94704 USA

-o-

19

copy Experience In Software Inc 1995 - 2006

20

copy Experience In Software Inc 1995 - 2006

Customer Support

When you need help in solving a problem with the software Experience In Software is available to assistyou First check this help file for information on the part of the program you are having a problem withAlso take a look at the Web site for late-breaking technical support information wwwprojectkickstartcomsupporttechnical_supportcfm If you are a regustered user you can obtain support in the following ways

Web httpwwwprojectkickstartcomsupportemail_supportcfm E-mail supportprojectkickstartcom

Hours 900 am to 500 pm Pacific time Monday - Friday

To make the support process more efficient have the following information ready for the support staff

Provide your name phone number and email address

Describe the problem including any error messages

If reporting a potential bug describe what you did immediately before seeing the bug

Provide the Project KickStart version number and Build Date (Click Help on the menu bar and thenclick About Project KickStart)

Identify the version of Windows (Windows Vista etc) you are using

Notes

Our policy is to respond to support email within two business days If you have not received aresponse please double check that spam filters are blocking our messages to you If you maintain anincoming whitelist please allow all messages from the projectkickstartcom domain

Support is available in English only If you purchased a translated version please contact your localreseller for help in other languages

See Also

Reporting Technical Issues

-o-

21

copy Experience In Software Inc 1995 - 2006

Reporting Technical Issues

If Project KickStart 5 detects an error it will write a log of technical issues and then create a temporarymenu to the right of the Help menu which says Send Log to Technical Support You should immediatelyclick the menu and then click Yes to send the error log to us

Please fill in your email address so that we can get back to you with any questions about what caused theerror

Tip

If you have an Internet Security Program such as Norton Internet Security please allowPKS5Kickstartexe to communicate with the Internet to report the error

-o-

22

copy Experience In Software Inc 1995 - 2006

Register Project KickStart

To print this page click the Print button on the Help window toolbar

Register Project KickStart 5 for technical support upgrade information and software discounts You canregister by completing printing and then sending or faxing this form to Experience In Software You canalso register online at httpwwwprojectkickstartcomsupportregiscfm

Name _______________________________________________________

Title _______________________________________________________

Company _______________________________________________________

Address _______________________________________________________

CityStateZip ______________________________________________________

Country _______________________________________________________

Day Phone _______________________________________________________

Fax _______________________________________________________

E-mail _______________________________________________________

Purchased from __ Experience In Software __ Other ____________________

Number of people in company _ 1 to 25 _ 26 to 100 _ 101 to 1000 _ Over 1000

Which industry do you work in ______________________________________

Interested in a project management workshop for your company __ Yes __ No

Comments _______________________________________________________

_________________________________________________________________

_________________________________________________________________

Experience In Software 2029 Durant Ave Berkeley CA 94704

Send or FAX to (510) 644-3823

-o-

23

copy Experience In Software Inc 1995 - 2006

Planning Projects

Name Your Project

Before you start thinking about the tasks in your project yoursquoll want to give your project an appropriate titleIf you open an existing project you might want to edit or change the name of your project

To name your project1 In the Type a name for your project text box enter a name2 Click the Next button

Tips

You can enter up to 58 characters and more than one

Use short descriptive project names such as ldquoCompany Web Siterdquo

Avoid vague project names such as ldquoDatabase Projectrdquo or ldquoCDP-7rdquo especially if you plan to circulatereports to others

Enter your project title using uppercase letters if you want the title to stand out in reports

One way to reuse your projects is to open an existing project and then change its name in this stepAfter saving the project with a different name you can modify details to customize the project

See Also

Use the Planning Wizard

-o-

24

copy Experience In Software Inc 1995 - 2006

Phases - Step 1 of 2

After naming your project the next step in the Planning Wizard is to identify the major activities in yourproject Using phases helps organize tasks so that an obviously early task such as ldquoOrganize materialsrdquoappears before a later task such as ldquoReview final draftrdquo

To enter phases1 Type each phase one per line

OrClick the Phases Library button The Phases Library contains typical phases that many organizationsuse in the early middle and late stages of their projects Drag an entry from the Phases Library to thelist and then click the OK button to close the Phases Library

2 To insert a phase in the middle of the phases list click where you want to insert a new blank line andthen press the Insert keyTo edit the phase text double-click the phase

Tips

Start each phase name with an action verb as in ldquoBuild systemrdquo or ldquoWrite reportrdquo

Use actions that have clearly defined beginnings middles and ends For example you can scheduletasks like ldquoTest prototyperdquo more easily than tasks like ldquoPurchase high-quality partsrdquo

Note

Youll have the opportunity to edit phases later in the Tasks step For now continue planning thephases in your project

See Also

Use the Planning Wizard

Use a Library

Move Tasks within the Task List

-o-

25

copy Experience In Software Inc 1995 - 2006

Phases - Step 2 of 2

For each phase list all of the tasks that could be performed during that phase You can refine and organizethe tasks later in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each phase1 Type the tasks associated with the phase displayed in the Tasks for phase text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next phase in your project click the Next button If you prefer to work out oforder click the Tasks for phase list arrow and then click the phase you want

3 When you are finished entering tasks for the last phase in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

26

copy Experience In Software Inc 1995 - 2006

Goals - Step 1 of 3

Enter the goals for your project the objectives you hope to accomplish Then you can brainstorm anyadditional tasks that will help you meet these goals

To enter goals1 Type each goal one per line

OrThe Goals Library contains typical sample goals that you can customize Drag an entry from the GoalsLibrary to the list and then click the OK button to close the Goals Library

2 To insert a goal in the middle of the goals list click where you want to insert a new blank line and thenpress the Insert keyTo edit the goal text double-click the goal

3 Click the Next button

Tips

List goals that apply to the entire project such as Develop a high-quality system A goal such as Getthe contract signed applies only to an early phase

Write goals as actions you can measure For example Complete the project for $75000 or less ismore concrete and specific than Complete the project within budget Numbers make goal statementsreal

If youre not sure how to measure a goal use a range as in About 15 - 25 people will use the results ofthe project

See Also

Use the Planning Wizard

Use a Library

-o-

27

copy Experience In Software Inc 1995 - 2006

Goals - Step 2 of 3

For each goal list any new tasks needed to accomplish that goal You can refine and organize the taskslater in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each goal1 Type the tasks for accomplishing the goal displayed in the For the goal text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next goal in your project click the Next button If you prefer to work out of orderclick the For the goal list arrow and then click the goal you want

3 When you are finished entering tasks for the last goal in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

28

copy Experience In Software Inc 1995 - 2006

Goals - Step 3 of 3

After you identify new tasks for your project assign each new task to an appropriate phase

To assign new tasks to phases1 Click a task in the New tasks to achieve goals list (on the left)2 Click one or more phases in the Assign them to Phases list (on the right) to which the task belongs A

checkmark appears next to tasks youve assigned

If a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Note

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

29

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 1 of 2

Projects often have tasks in common The Similar Projects step makes it easy for you to borrow tasks fromother projects and add them to your current project

By default this step shows the Project KickStart (PRX) projects stored in the same folder as the currentproject including sample projects and those you already created

To select similar projects1 Review the projects in the list To sort the project names alphabetically click the Project Name header

Click the Project Name header again to sort the names in reverse order2 Click one or more projects in the list that contain tasks you want to use in the current project A

checkmark appears next to the projects you selected3 To list projects stored in a different folder on your system click the Browse button and then navigate to

the folder you want4 Click the Next button

If no projects seem related to your current project skip this step for now

Tips

The Similar Projects step becomes more helpful the more you use Project KickStart Every time yousave a project it becomes available for future use

Many projects share the same phases and tasks such as those for setting up a contract or purchasingequipment You can use Project KickStart to create these mini-projects or templates and then importtheir tasks into a new project during the Similar Projects step

-o-

30

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 2 of 2

After you select one or more projects containing tasks you might want to use assign those borrowed tasksto a phase in this project

To assign borrowed tasks to phases1 Click a task in the list on the left If a task includes subtasks click the plus icon to expand the list Click

the minus icon if you want to hide the subtasks To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more phases in the Assign tasks to phase(s) of your project list (on the right) to whichthe task belongs A checkmark appears next to tasks youve assigned

3 To assign one or more tasks to a new phase select the tasks click ltNew Phasegt in the Assign tasksto Phases of your project list and then type a name for the new phase

4 To select tasks from another project you selected as similar click the Tasks from Similar Projects listarrow click the project you want and then assign the tasks to phases

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also Edit Tasks

-o-

31

copy Experience In Software Inc 1995 - 2006

People - Step 1 of 3

Enter the names or descriptions of the people involved in your project Include key decision makers suchas executives or customers who must approve or consult with you about the project These are yourprojects resources In the next People step youll identify new tasks associated with these resources

To enter people1 Type each name or description one per line

OrIf you have stored information about people and other resources in the People Library click the PeopleLibrary button drag an entry from the library to the list and then click the OK button to close thePeople Library

2 To edit the people text double-click the name or description3 Click the Next button

Tips

Be consistent with the resource names in your projects For instance avoid using Richard in oneproject and Dick in another project when referring to the same person

Include names for people teams (such as Quality control team) departments (such as Manufacturing)companies (such as Acme Widgets Corp) or even equipment (such as wheat thrasher)

Note

Add people and other resource information to the People Library so that you can quickly drag resourcesfrom the library to any project You can even import people from your Outlook and ACT address books

See Also

Manage the People Library

Import ACT Contacts and Users to the People Library

-o-

32

copy Experience In Software Inc 1995 - 2006

People - Step 2 of 3

Now that you have defined the people needed to complete your project list any new tasks that eachresource might suggest or require

To enter new tasks for each person1 Type the new tasks associated with the person displayed in the Tasks For text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next person in your project click the Next button If you prefer to work out oforder click the Tasks For list arrow and then click the person you want

3 When you are finished entering new tasks for the last person in your project click the Next button tocontinue in the Planning Wizard

Tips

This step provides a good opportunity to get input from your resources directly and make sure theproject plan reflects the views of everyone on the team

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo Write the tasks roughly in the order that you will complete them You can reorganize the tasks later in

the Tasks step

Note

You assign people to tasks in the Assign Tasks and Schedule steps

See Also

Use a Library

Move Tasks within the Task List

Assign Tasks to People

-o-

33

copy Experience In Software Inc 1995 - 2006

People - Step 3 of 3

After you identify new tasks associated with the people in your project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by people list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

34

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 1 of 3

Every project has obstacles and risks that can affect its success List the major obstacles you face incompleting your project Then you can brainstorm any additional tasks that can help you overcome orminimize these problems

To enter obstacles1 Type each obstacle one per line

OrThe Obstacles Library contains typical sample obstacles that you can customize Drag an entry fromthe Obstacles Library to the list and then click the OK button to close the Obstacles Library

2 To insert an obstacle in the middle of the obstacles list click where you want to insert a new blank lineand then press the Insert key

3 To edit the obstacle text double-click the obstacle4 Click the Next button

Tips

Be creative when thinking of obstacles Highly imaginative obstacles can suggest realistic tasks Forexample Project manager kidnapped by aliens can lead to Project manager out of town forconference In Obstacles step 2 of 3 you can add the realistic activities as tasks You can delete theunrealistic obstacles later by returning to Obstacles step 1 of 3

Avoid listing too many obstacles even if they are realistic Hard core pessimists find it hard to getanything done

Edit and update the Obstacles Library so that you can quickly drag obstacles from the library to anyproject in your organization

See Also

Use a Library

-o-

35

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 2 of 3

After identifying the obstacles to completing your project determine how you can avoid these stumblingblocks List any new tasks you need to overcome or avoid each obstacle In this way you are developing acontingency plan for your project

To enter new tasks for each obstacle1 Type the new tasks associated with the obstacle displayed in the Obstacle text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next obstacle in your project click the Next button If you prefer to work outof order click the Obstacle list arrow and then click the obstacle you want

3 When you are finished entering new tasks for the last obstacle in your project click the Next button tocontinue in the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

You can reorganize the tasks and add notes later in the Tasks step

See Also

Use a Library

Move Tasks within the Task List

Add Task Notes and Attachments

-o-

36

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 3 of 3

After you identify new tasks for overcoming the obstacles to completing project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by obstacles list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

3 Click the Next button

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

37

copy Experience In Software Inc 1995 - 2006

Assigning People

Assign Tasks to People

After youve identified people working on your project you can assign tasks to each person or otherresource

To assign tasks to people1 Click a phase or task in the For each phase or tasks list (on the left)

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more people in the Assign some people list (on the right) who will perform the task Acheckmark appears next to tasks youve assigned

3 To assign a selected task to all of the people in your project click the All button4 To assign one or more tasks to a new person select the tasks click ltNew Persongt in the Assign

some people list and then type a name for the new person

To unassign a task

To unassign a task click the task and then click the highlighted person from which you want to removethe task You can assign that task to a different person if necessary You can also click the All buttonto remove a task from all of its assignments at the same time

Tip

Some users like to skip to the Tasks step before performing the Assign step That way they can edittheir list of tasks before assigning people and resources This helps them focus the project and givesthem a clearer idea of what must be done before committing resources

Notes

You can also assign tasks to people in the Tasks step and the Schedule step

You can assign tasks to non-personnel resources such as equipment (a CAD system or back hoe)facilities (a classroom or hotel) services (lab work or insurance) or materials (lumber or officesupplies) just as you assign tasks to people Click ltNew Persongt to add a new resource to the list

See Also

Remove People from a Task

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

38

copy Experience In Software Inc 1995 - 2006

Remove People from a Task

After assigning tasks you might need to remove people from a task or unassign them

To remove people from a task (unassigning)1 Click a phase or task in the For each phase or tasks list (on the left)

The people assigned to that phase or task are highlighted in the Assign some people list (on theright)

2 Click a highlighted person to remove or unassign that person from the taskWhen the person is no longer highlighted they are not assigned to the selected task

See Also

Assign Tasks to People

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

39

copy Experience In Software Inc 1995 - 2006

Add a New Person or Resource

If you realize that you want to assign some tasks to a person not included in the Assign some people listyou can add that person and assign tasks in the same step You can also add non-personnel resourcessuch as such as equipment (a CAD system or back hoe) facilities (a classroom or hotel) services (lab workor insurance) or materials (lumber or office supplies)

To add a new person or resource1 Select one or more phases or tasks in the For each phase or tasks list (on the left) 2 Click ltNew Persongt in the Assign some people list and then type a name for the new person or

resourceThis adds the new person or resource to the list and assigns the selected tasks to them

See Also

Assign Tasks to People

Remove People from a Task

Edit or Substitute People

Add or Change Task Assignments

-o-

40

copy Experience In Software Inc 1995 - 2006

Edit or Substitute People

If the people or resources in your project change you can replace them or edit their names anddescriptions

To edit or substitute people1 Click the People icon

You return to People step 1 of 32 In the list of people defined for the project double-click the person you want to edit or replace or click

the name and press F23 Edit the name or description of the person

When you return to the Assign step the name of the person appears as you changed it

See Also

Assign Tasks to People

Remove People from a Task

Add a New Person or Resource

Add or Change Task Assignments

-o-

41

copy Experience In Software Inc 1995 - 2006

Organizing the Project Plan

About Organizing Tasks

In the Tasks step you work with an outline of your project plan Here you can easily edit and reorganizetasks spell check and even add notes and attachmentsClick the following illustration to see tips for using this window

Edit the Task List to Consolidate and delete tasks Add subtasks Add or change task assignments Add follow-up notes to tasks Add or change attachments Review the order of the tasks in each phase and move tasks up or down so that they progress

sequentially Review task descriptions to make sure they are clear and that all the team members will understand

them Convert vague tasks such as reminders and open issues to task notes

Notes

Some users like to revise their Task List before they assign resources You can go to the Task List atany time while you are using Project KickStart

Each project created with Project KickStart can contain up to 1000 tasks

See Also

Change the Appearance of the Task List

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

Add Task Notes and Attachments

Add or Change Task Assignments

Add or Change Task Details

-o-

42

copy Experience In Software Inc 1995 - 2006

43

copy Experience In Software Inc 1995 - 2006

Change the Appearance of the Task List

You can change the appearance of the Task List so you can work with it more effectively

To add a column

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task ListBy default the Task List shows the Task Name Assignments and Notes columns You can also showCost and Done columns

To hide a column

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

To move a column

Drag a column heading to a new position in the Task List

To change the column width

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Show or Hide Tasks in the Task List

-o-

44

copy Experience In Software Inc 1995 - 2006

Show or Hide Tasks in the Task List

To hide tasks or subtasks

To hide the subtasks for a task click the minus icon next to the task

To hide all the tasks in the Task List and show only phases click all the minus icons next to thephases

To show tasks or subtasks

To show the subtasks for a task click the plus icon next to the task

To show the tasks for a phase click the plus icon next to the phase

See Also

Change the Appearance of the Task List

-o-

45

copy Experience In Software Inc 1995 - 2006

Move Tasks within the Task List

In the Tasks step you can reorganize the tasks in your project so that they better represent the work youand your team plan to do In particular you should review the order of the tasks in each phase and move tasks up and down so thattasks follow in a sequential order Use the Up and Down Arrow buttons to move the tasks

To reorder tasks1 Click a task or phase to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youmove must be next to each other

2 Click the Up Arrow button to move a task up one rowOrClick the Down Arrow button to move a task down one row

Note

When you move a bolded phase you move the phase and all of its tasks at the same time

See Also

Outdent and Indent Tasks

-o-

46

copy Experience In Software Inc 1995 - 2006

Outdent and Indent Tasks

Subtasks are smaller parts of tasks Use subtasks when you need to break tasks down into moremanageable parts In the Task List you can turn a task into a subtask by indenting it You can also add anew subtask to the Task ListIf your Task List contains subtasks you can turn a subtask into a task by outdenting itUse the Outdent and Indent buttons to promote (outdent) and demote (indent) tasks

To promote and demote tasks1 Click a phase task or subtask to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youpromote or demote must be next to each other

2 Click the Outdent button to promote the selected tasksOrClick the Indent button to demote the selected tasksYou can also right-click an item in the Task List and then click Outdent or Indent on the shortcut menu

Tips

When you promote (outdent) a task it becomes a phase and its subtasks become tasks When youpromote a subtask it becomes a task

When you demote (indent) a phase it becomes a task and its tasks become subtasks When youdemote a task it becomes a subtask

Notes

You can have up to 10 levels of subtasks in your project

Use Task Notes instead of subtasks for task comments or additions that are not actually work items

See Also

Move Tasks with the Task List

Add a Task or Subtask

-o-

47

copy Experience In Software Inc 1995 - 2006

Add a Task or Subtask

If you realize you want to add another task to the Task List use the Add Task button A subtask is a smaller part of a task Use subtasks when you need to break tasks down into moremanageable partsTo add a subtask use the Add Subtask button

To add a task1 Click a task and then click the Add Task button right-click a task and then click Add Task on the

shortcut menu or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskProject KickStart numbers the new task in the proper sequence

To add a subtask1 Click a task and then click the Add Subtask button right-click a task and then click Add Task on the

shortcut menu or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtask3 Project KickStart numbers the new subtask in the proper sequenceNote

To add a new phase click a phase and then click the Add Task button

See Also

Outdent and Indent Tasks

-o-

48

copy Experience In Software Inc 1995 - 2006

Edit Tasks

Edit tasks in the Task List to fine tune your project You can edit the names of the phases tasks andsubtasks delete tasks and cut copy and paste task information

To edit task names1 Click the phase task or subtask you want to edit and then press the F2 key2 Type to edit the text3 To undo an edit click the Undo button

To delete a task

Click the task you want to delete and then press the Delete key or click the Delete button Or

Right-click a task and then click Delete Row on the shortcut menu

To cut copy and paste tasks1 Select the tasks you want to cut or copy Use Shift-click or Ctrl-click to select more than one task

2 Click the Cut button (Ctrl-X) or click the Copy button (Ctrl-C )

3 Click where you want to insert the tasks and then click the Paste button (Ctrl-V)

Tip

If your project includes some of the same tasks repeated in different phases save time by copying rowsof tasks and pasting them to another phase

Notes

You can also edit task names using the Task Information dialog box To open this dialog boxdouble-click a task or click a task and then click the Edit Task Information button

If you delete a phase you also delete its tasks and subtasks If you delete a task you also delete itssubtasks Project KickStart warns you before deleting tasks or subtasks and gives you a chance tocancel the deletion

See Also

Add Task Notes and Attachments

Add or Change Task Assignments

-o-

49

copy Experience In Software Inc 1995 - 2006

Add Task Notes and Attachments

You might find that some of your tasks are actually more notes than tasks For example Remember tocheck Daves specifications might work better as a note than a task especially if it could take several daysto catch up with Dave but only a few minutes to review his specs By using notes you clarify your projectand increase your chances for success An attachment is a document graphic or any other type of file related to a task For example to a tasksuch as Review proposal you can attach the proposal document Or you can attach a hyperlink to a pageon a web site

To add a note or attachment to a task1 Double-click the Notes column next to the task The Task Information dialog box opens to the Notes

and Attachments tab2 In the Enter a Note box type in or edit the task note (Press Enter to insert line break)3 To attach a file click the Add Files button In the Select File to Attach dialog box navigate to the file

you want and then click the Open button The filename appears in the Add Attachments box with apaperclip icon

4 To insert a hyperlink click the Add URL button In the Insert Hyperlink dialog box type in the URL youwould like to link to The URL appears in the Add Attachments box with a paperclip icon

5 Click the OK button

To open or remove an attachment1 Open the Notes and Attachments tab in the Task Information dialog box2 To open an attachment double-click the filename in the Add Attachments box3 To delete an attachment click the attachment in the Add Attachments box and then click the Remove

button

To change a task into a task note1 Copy (Ctrl-C) the text of the task you want to change into a note2 Double-click the task to which you want to add the note3 In the Task Information dialog box click the Notes and Attachments tab and add paste the text in the

Enter a Note box Close the Task Information dialog box4 In the Task Name column delete the original task that how appears as a note for a different task

Tips

Use notes to keep track of the operational details of a project the little nagging details that are criticalto success

Although the Task List provides plenty of room for notes it is best to keep your notes concise

Some tasks might benefit from instructional notes those that explain what to do in a task or how tosuccessfully complete a task

You can also include a hyperlink in a note by typing httpxxx (where xxx is an e-mail or Web address)In Outlook Word Excel or your browser the hyperlink will be active You can click the link to godirectly to that site or to send an e-mail to that address

Note

You can also open the Notes and Attachments tab in the Task Information dialog box by clicking atask and then clicking the Edit Notes and Attachments button or by double-clicking a task to openthe Task Information dialog box and then clicking the Notes and Attachments tab

See Also

Edit Tasks

Add or Change Task Assignments

Change Task Details in the Gantt chart

50

copy Experience In Software Inc 1995 - 2006

-o-

51

copy Experience In Software Inc 1995 - 2006

Add or Change Task Assignments

The Assignments column in the Task List shows the people and other resources assigned to each task

To add or change a task assignment1 Double-click the Assignments column next to the task The Task Information dialog box opens to the

Assignments tabThe Assignments tab lists all of the people and resources in your project If this task is already assignedto people they are highlighted on the Assignments tab

2 To assign this task to another person or resource click the resource name in the Assignments list3 To remove (unassign) this task from a person or resource click a highlighted name in the Assignments

list4 To add a person and assign the task at the same time click ltNew Persongt in the Assignments list

and then enter the name of the new person5 Click the OK button

Note You can also open the Task Information dialog box by clicking a task and then clicking the Edit Task

Information button to or by double-clicking a task

-o-

52

copy Experience In Software Inc 1995 - 2006

Add or Change Task Details

Besides task names notes and assignments you can include cost and done details about tasks In theSchedule step you can also include start and finish dates and durations

To add task details

1 Click a task and then click the Edit Task Information button or double-click the task you wantThe Task Information dialog box opens

2 Enter Cost or Done informationCost Enter the cost associated with this task For example you could enter $150 as the cost for a tasknamed Purchase photo CD Done Click the list arrow to select 0 25 50 75 or 100 or enter the percentage you want such as33

3 Click the OK button

To show or hide task details

Right-click a column heading to open a shortcut menu and then click Cost or Done In the shortcutmenu a checkmark appears next to columns that are displayed in the Task List

To edit task details

Open the Task Information dialog box (click a task and then click the Edit Task Information button or double-click the task you want)

Or

Double-click the Cost or the Done entry to update these details directly in the Task List

Notes

The Cost amount appears with the currency symbol set for your system (in the Regional and LanguageOptions dialog box of the Windows Control Panel)

Project KickStart calculates the running totals for the tasks within a phase and displays this total in theCost column for the phase When you create and print Task reports the total costs for the entire projectappear at the end of the Cost column

See Also

Edit Tasks

Print Task Reports

-o-

53

copy Experience In Software Inc 1995 - 2006

Check Spelling

Spell check your tasks and notes before you print reports or export to other software

To check the spelling of tasks and notes

Click the Check Spelling button on the Project KickStart toolbarOr

Click Tools on the menu bar and then click Spelling

Notes

Spell checking updates entries on the Task List and the Gantt chart (the Schedule step) It can alsocheck the spelling of intermediate entries such as goals and tasks to accomplish goals if you spellcheck during those steps

Spell checking does not check the names of people on the People List or the contents of the PeopleLibrary

-o-

54

copy Experience In Software Inc 1995 - 2006

Scheduling Tasks in the Gantt Chart

55

copy Experience In Software Inc 1995 - 2006

Scheduling Overview

About Scheduling Tasks

In the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the other

You work with the Gantt chart using the familiar Task Data view in the left pane or the graphical Chart viewin the right pane To adjust the schedule to fit your project set the project start date in the toolbar moveand resize the taskbars in the Chart view or change the start and finish dates or durations of individualtasks in the Task Data view

Click the following illustration to see general tips for using the Gantt chart See About the Gantt Chart formore details

In the Schedule step you can

Change a start date for the project Set start and finish dates or durations for tasks Change the timescale of the schedule Change the working schedule to specify which days are nonworking days such as weekends and

holidays Fine-tune the organization of the phases tasks and subtasks Color-code tasks to identify assignments critical deadlines or other information at a glance Insert milestones to indicate events that mark a moment in time such as the approval of a design Review and edit task details including task name assignments notes and attachments Hide or show task data columns in the left pane Export project data to other software applications

Tip

56

copy Experience In Software Inc 1995 - 2006

To save time you can reuse projects such as one for a trade show and create an updated scheduleby changing the project start date in the Schedule step

See Also

About the Gantt Chart

Understand Task Data View

Understand Chart View

-o-

57

copy Experience In Software Inc 1995 - 2006

About the Gantt Chart

The Gantt chart provides two views of your project schedule The Task Data view in the left pane lists thesame task information as in the Tasks step but now includes durations and start and finish dates TheChart view in the right pane displays taskbars and symbols to represent the same information You canchange the schedule information by working directly in the Task Data view and Chart view or by using theGantt Chart toolbarClick the following illustration to see general tips for using this window

-o-

58

copy Experience In Software Inc 1995 - 2006

Autolink tasks (Pro Users)

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatProject KickStart Pro does not assume that you want to link all of the tasks in a serial manner (one after theother) when you get to the Gantt chart Indeed many users want that behavior and many do notTo accomodate both types of users you can set whether you want the program to Autolink tasks In theTools menu select Autolink tasks Thereafter in all your projects when you get to the Gantt chart for thefirst time the tasks will be linked in a serial mannor

-o-

59

copy Experience In Software Inc 1995 - 2006

About Linking Tasks

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatWhen you link tasks the Gantt chart shows additional information about the tasks Click the followingillustration to see general tips for using linked tasks

Task Data view Chart view Description

Predecessor tasksA predecessor task is onethat you must completebefore you can start thenext task For exampleTask 2 - Prepare soil isthe predecessor to Task3 - Plant shrubs becauseyou need to prepare thesoil before you can plantthe shrubs

Successor tasksWhen you finish onelinked task you can moveonto the next onemdashthesuccessor task Forexample the successorfor Task 2 ndash Prepare soilis Task 3 ndash Plant shrubsand the successor forTask 3 is Task 4 ndash MulchLink linesThe first task isscheduled for one dayand the second one forthe next day In additionthe link line and arrowshow that the first taskmust end before thesecond one can start

These linked tasks arescheduled for the sametime

60

copy Experience In Software Inc 1995 - 2006

These tasks which aredependent on earliertasks and the last twotasks are also scheduledfor the same time

See Also

About the Gantt Chart

Autolink tasks

Make tasks overlap

-o-

-o-

61

copy Experience In Software Inc 1995 - 2006

Change the Display of the Schedule

You can change the onscreen appearance of the schedule so you can work with it more effectively Thefollowing illustration shows the Schedule window with the Steps bar closed and only the task number taskname and duration displayed in the Task Data view This provides more room to display the Gantt chart

To show or hide the Step bar or Project KickStart toolbar

Click View on the menu bar and then click Steps Bar to show or hide the vertical Steps bar on the leftof the Project KickStart window

Click View on the menu bar and then click Tool Bar to show or hide the Project KickStart toolbarwhich appears just below the menu bar In the View menu a checkmark appears next to the items displayed in the Project KickStart window

To display more or less of the Task Data view or Chart view

Drag the splitter bar between the Task Data view and the Chart view

To change the timescale in the chart

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years

To add a column to the Task Data view

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task Data viewBy default the Task Data view shows the Info Task Name Days Start and Finish columns Youcan also show Done Cost and Assignments columns

To hide a column in the Task Data view

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

62

copy Experience In Software Inc 1995 - 2006

To change the column width in the Task Data view

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Understand Task Data View

Understand Chart View

-o-

63

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

-o-

64

copy Experience In Software Inc 1995 - 2006

65

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Some features in this topic are available only in Project KickStart Professional

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view In Project KickStart Professional you also use the Gantt chart toolbar to linkand unlink tasks

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysLink Tasks (Pro Users)Link the selected tasksUnlink Tasks (Pro Users)Unlink the selected tasksChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

See Also

Use the Gantt Chart Toolbar

-o-

66

copy Experience In Software Inc 1995 - 2006

Understand Task Data View

The following illustration shows all the columns of information you can display in Task Data view

The Task data columns are the same as in the Tasks step but also include date information

Row number

Info Shows an icon if a note attachment or both are associated with the task Double-click anicon to view or edit the associated information

Task Name Name of the phases tasks and subtasks Double-click a task name to edit it directly

Days The amount of time it takes to complete the task If you change the number of days for a taskProject KickStart changes the Finish date accordingly

Start Date this task starts Double-click a Start date and then click the list arrow to open a calendar andselect a different date This also changes the Finish date

Finish Date this task ends Double-click a Finish date and then click the list arrow to open a calendar andselect a different date This changes the task duration shown in the Days column

Done Percentage of the phase task or subtask completed Show progress for any task by entering apercent of up to 100

$ Cost Cost for each task summed in the appropriate phase row Reports include total costs for theproject when you select the Cost column in the Create and Print Task Reports dialog box or the Createand Print Gantt Chart Report dialog box The Cost appears with the currency symbol set for your system(in the Regional and Language Options dialog box of the Windows Control Panel)

Assignments People and other resources assigned to the task Double-click an assignment to open theTask Information dialog box to the Assignments tab where you can add and change assignments

Tip

A task with a duration of zero (0) days is a milestone See Create a Milestone for more information

Notes

By default Task Data view displays all the columns the Info Task Name Days Start and Finish Done Cost and Assignments columns Some of these columns might be hidden by the Gantt chartview To hide columns right-click a column heading to open a shortcut menu and then click the columnyou want to hide In the shortcut menu no checkmark appears next to columns that are hidden

To change the width of a column drag a splitter bar in the column heading row or double-click a splitterbar to have the column accommodate its longest entry

As in the Tasks step expand phases and tasks by clicking the plus icon and collapse phases andtasks by clicking the minus icon

See Also

67

copy Experience In Software Inc 1995 - 2006

Understand Chart View

Change Task Dates

-o-

68

copy Experience In Software Inc 1995 - 2006

Additional Features in Task Data View

These features are available only in Project KickStart Professional

In Project KickStart Pro you can view two columns of information in addition to the nine columns availablein the Project KickStart Standard These two additional columns are labeled Pred (for Predecessor) andSucc (for Successor) The following illustration shows a typical Task Data view with these additionalcolumns

Besides the nine columns of information shown in Task Data view in Project KickStart Standard you canalso show the following information in the Professional version

Pred Indicates which task is the predecessor to the current task Double-click a task number in the Predcolumn to change it

Succ Indicates which task is the successor to the current task Double-click a task number in the Succcolumn to change it

Notes

When you link tasks Project KickStart assigns predecessors and successors according to their order inthe Task Data view

When you move a linked task in the Task Data view the predecessor and successor do not changeFor example in the above illustration if you move Task 3 ndash Plan design so it becomes Task 2 itspredecessor remains Land survey and its successor remains Engineering You can change these bydouble-clicking the task number in the Pred or Succ column and then entering a new number

See Also

Understand Task Data View

-o-

69

copy Experience In Software Inc 1995 - 2006

Understand Chart View

The following illustration shows a daily schedule in Chart view Point to the illustration to display text thatdefines the chart elements

Summary bar Summarizes the tasks below it and extends from the earliest start date(where the first triangle in the summary bar appears) to the latest finish date (where the last triangleappears) If a phase has tasks the summary bar appears in the phase row to summarize the tasks If atask has subtasks the summary bar appears in the task row to summarize the subtasks

To reschedule a phase and all of its tasks (or a task and all of its subtasks) click the summary bar and dragit to the left or right until it spans your desired set of dates This changes the earliest start date and latestfinish date in that phase and keeps the same duration And all the tasks move with the change of thephase

Taskbar Shows the length and scheduled dates for a task To change the duration of a taskresize the taskbar click the taskbar and then drag its left edge to schedule a different start date or drag itsright edge to schedule a different finish date

To reschedule a task without changing the duration drag the taskbar to a different date in the chart

Taskbar with percent done If you enter a Done amount in the Task Data view a progress barin the taskbar indicates the amount of the task completed

Red vertical line Indicates todays date

Milestone Indicates a task with a zero duration Milestones mark an event that must be reflected inyour project plan such as the approval of a design or an assembly line startup You can drag the left edgeof a milestone icon to stretch it into a taskbar The milestone becomes a task with a start and finish date

Notes

Because a summary bar summarizes the tasks below it you cannot resize a summary bar

To scroll the schedule use the vertical and horizontal scroll bars or the green drag bar at the top of theChart view

The shaded days in the Chart view indicate nonworking days To set which days are working andnonworking see Specify Working Days

70

copy Experience In Software Inc 1995 - 2006

-o-

71

copy Experience In Software Inc 1995 - 2006

Additional Tools in Chart View

These features are available only in Project KickStart Professional

If you use Project KickStart Pro the Chart view displays lines and arrows to show linked tasks The linklines and arrows show the relationships dependencies between one linked task and another

Besides the summary bar taskbar and other information provided in Project KickStart Standard Chart viewin the Professional version also provides the following information

The first task is scheduled for one day and the second one for the next day In addition the link line andarrow show that the first task must end before the second one can start

These linked tasks are scheduled for the same time However the first task must end before the secondone can start

The first two tasks are scheduled for the same time and must be completed before the third task can start

These linked tasks are scheduled for the same time However the second task must end before the firstone can start

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

Understand Chart View

-o-

72

copy Experience In Software Inc 1995 - 2006

73

copy Experience In Software Inc 1995 - 2006

Change Task Dates

You can revise a project schedule by changing task dates in the Task Data view or the Chart view You canalso reschedule an entire project by changing the projects start date

To change the project start date1 Click the Project Start list arrow to open a calendar

The calendar highlights the selected date and outlines todays date2 Find the date you want using the left and right scroll arrows to view a different month and then click the

date

To change task dates in Task Data view1 Double-click the Start or Finish date for a task

2 Then edit the date (you can edit the day month or year) OrClick the list arrow to open a calendarThe calendar highlights the selected date and outlines todays date

3 Find the date you want using the left and right scroll arrows to view a different month and then click thedateProject KickStart changes the Start and Finish dates according to your selection updates the durationof the task in the Days column and adjusts the taskbar in the Chart view

To change task dates by changing the duration in Task Data view

Double-click the Days column for a task and then enter the number of days it will take to complete thetaskProject KickStart changes the Finish date of the task and adjusts the taskbar in the Chart view

To change task dates in Chart view

Resize a taskbar click the taskbar and then drag its left edge to schedule a different start date or dragits right edge to schedule a different finish dateProject KickStart updates the summary bar in Chart view and the task dates and duration in the TaskData view

To reschedule a task without changing the duration drag the taskbar to a different date You can alsodrag a summary bar to reschedule a phase and all of its tasks (or a task and all of its subtasks) so itspans a different set of datesProject KickStart updates the task dates and duration as necessary in the Task Data view

To change task dates in the Task Information dialog box1 Open the Task Information dialog box (Right-click a task and then click Task Information or click a

task and then click the Edit Task Information button )2 Click the General tab3 In the Dates section change the following information as necessary

Start Click the Start list arrow to open a calendar and then click the appropriate start dateFinish Click the Finish list arrow to open a calendar and then click the appropriate finish dateDays Enter a number or click the spin arrows to set the task durationMilestone Select the Milestone check box if you want this task to be a milestone (A milestone is atask with a zero duration and marks an event such as the approval of a design)

Notes

You cannot delete the Start or Finish date of a task If you want to specify that a task has no durationconvert it to a milestone

When working with a calendar to schedule a start or finish date click the Today date text (where date

74

copy Experience In Software Inc 1995 - 2006

is todays date) to select todays date

See Also

Understand Task Data View

Understand Chart View

Create a Milestone

-o-

75

copy Experience In Software Inc 1995 - 2006

Phase Dates Cannot Be Edited

You cannot change the bold phase dates in the Task Data view of the Gantt chart They are a summary ofthe task dates for a particular phase and are view only You can revise phase dates by changing task dateswithin the phase

To change phase dates in Chart view

You cannot directly resize a summary bar You can extend or move the blue task barswithin a phase on the chart and Project KickStart updates the summary bar

To reschedule a phase on the chart drag the summary bar to a new date and all of its tasks (or a taskand all of its subtasks) will move with it

-o-

76

copy Experience In Software Inc 1995 - 2006

Quick Tour of Working with Linked Tasks

This feature is available only in Project KickStart ProfessionalIn the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the otherIn addition Project KickStart Pro links the tasks for you so when you open the Gantt chart you see a linkedwaterfall similar to the one shown below Besides providing a schedule that starts in a cascade with eachtask lasting one day each task is linked to the next task

You work with the Gantt chart either using the Task Data view in the left pane or the graphical Chart view inthe right pane To adjust the schedule to fit your project set the project start date in the toolbar move andresize the taskbars in the Chart view or change the start and finish dates or durations of individual tasks inthe Task Data view See About Scheduling Tasks for detailsNext fine-tune the dependencies in your project by you can linking and unlinking tasks changing theirpredecessors and successors and setting lead times For example if one task is not dependent onanother you can unlink the tasks If another task canrsquot start until two other tasks are finished you can add apredecessor to that task in which case the two tasks will be linked

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

To fine-tune the linked tasks To change the scheduled start and end dates of linked tasks move and resize taskbars in the Chart

view or change the number of days or the Start date in the Task Data view To display predecessor and successor information in the Task Data view right-click any column

heading and then click Pred or Succ To change the predecessor for a task double-click the number in the Pred column for the task and

then enter the number of a different task To change the successor for a task double-click the number in the Succ column for the task and then

77

copy Experience In Software Inc 1995 - 2006

enter the number of a different task To add another predecessor or successor to a task click in the appropriate column for the task and

then enter the number of another task To change the details of a linked task open its Task Information dialog box To do so right-click the

task and then click Task Information on the shortcut menu or click a task and then click the Edit TaskInformation button See Change Details for Linked Tasks

In the Task Information dialog you can also specify the predecessor(s) of a task and lead time(s) of thetasks

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

About Scheduling Tasks

About Linking Tasks (Pro Users)

Use the Gantt Chart Toolbar (Pro Users)

Manage Changes in Your Schedule (Pro Users)

-o-

-o-

78

copy Experience In Software Inc 1995 - 2006

Link and Unlink Tasks

These features are available only in Project KickStart Professional

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

See Also

About Linking Tasks

Quick Tour of Working with Linked Tasks

-o-

79

copy Experience In Software Inc 1995 - 2006

Create a Milestone

A milestone Indicates a task with a zero duration Milestones mark an event that must be reflected in yourproject plan such as the approval of a design or an assembly line startup

To create a milestone in the Task Data view

Double-click the Days number for a task and then enter 0 (zero)Or

Open the Task Information dialog box click the General tab and then click to insert a checkmark inthe Milestone check box

In the Chart view Project KickStart changes the taskbar to a milestone icon To create a milestone in Chart view

Click a taskbar and then drag to shrink the taskbar to a milestone icon In the Task Data view Project KickStart changes the Days for this task to 0 (zero)

Notes

To change a milestone into a task you change its duration or start and finish dates See Change TaskDates for instructions

To move a milestone in Chart view click the milestone icon on the upper left corner of the milestoneicon With the left mouse down move the icon to another date and release the mouse

To move a milestone in the Task Data view change the start date or the finish date and the milestonewill move

-o-

80

copy Experience In Software Inc 1995 - 2006

Change Task Details

You can use the Task Information dialog box to change the following task details in Task Data view

Task properties including the task name cost for completing the task and the percent completed

Dates including the start and finish dates duration and whether to convert the task to a milestone

Assignments

Notes and attachmentsYou can also edit the task name days dates costs and Done directly by clicking items in the task datacolumns

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button 2 Click the appropriate tab and then change the task details

General tab Change the task name and enter or change the cost associated with the task To changethe amount of the task completed click the Done list arrow and then select a value or type a value inthe Done text box Enter or change date information as described in Change Task Dates Assignments tab People assigned to this task are highlighted in the list To assign this task to anotherperson or resource click the name in the Assignments list To remove (unassign) this task from aperson or resource click a highlighted name in the Assignments list See Add or Change TaskAssignments for more detailsNotes and Attachments tab Type or edit a task note (Press Enter for a line break) To add anattachment click the Add button In the Select File to Attach dialog box navigate to the file you wantand then click the Open button The filename appears with a paper clip icon See Add Task Notes andAttachments for more details

To change task details directly in Task Data view

To modify the task name press F2 or double-click a task and then edit or replace the text

To change date information see Change Task Dates

To change the amount of the task completed double-click in the Done column and then enter a newvalue

To change the cost associated with the task double-click in the Cost column and then enter a newvalue

Notes

When you enter costs for tasks the total appears in the phase row for those tasks Reports include thetotal costs of all tasks in the project when you select the Cost column in the Create and Print TaskReports dialog box or the Create and Print Gantt Chart Report dialog box

You cannot change the cost of a phase because it represents the total costs for the tasks in that phaseInstead change the costs associated with the tasks in the phase

When you enter a Done for a task the corresponding taskbar in the Chart view includes a blackprogress bar

-o-

81

copy Experience In Software Inc 1995 - 2006

Change Details for Linked Tasks

This feature is available only in Project KickStart ProfessionalIf you are using Project KickStart Pro you can use the Task Information dialog box to change the followingtask details

Predecessor for a linked task

Lead time for a linked task

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button

2 Click the Predecessors tab and then change the task details about predecessors and lead timePredecessors tab The Task Properties section shows the name of the selected task which you canchange The Predecessor (Finish-to-Start) section shows the tasks that are predecessors to theselected task A predecessor task must be finished before you start the current task You can change the ID name or lead time of the predecessor task Also you can also add additionalother predecessorsThe lead time is the amount of time you need to wait after finishing the predecessor task before so youcan start the current task Lead time can be positive or negative

Note

In some programs the is time shift is called ldquolag timerdquo But we think that the term ldquolead timerdquo is moreaccurate and descriptive since itrsquos the amount of time you want to allow before you start a task

See Also

Change Task Details

82

copy Experience In Software Inc 1995 - 2006

-o-

-o-

83

copy Experience In Software Inc 1995 - 2006

Reorganize Tasks in Task Data View

Although your project should be fairly well organized by the time you start the Schedule step you canfine-tune the organization in the Task Data view using the same techniques you use in the Tasks stepTo reorder tasks

Right-click a task and then click Move Task Up or Move Task Down on the shortcut menu Or

Click a task or phase to select it and then click the Up Arrow button or the Down Arrow button on theGantt chart toolbar

To promote and demote tasks

Right-click a task and then click Outdent or Indent on the shortcut menu Or

Click a phase task or subtask to select it and then click the Outdent button or the Indent button onthe Gantt chart toolbar

To add a task1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Task button on the Gantt chart toolbar or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskTo add a subtask1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Subtask button on the Gantt chart toolbar or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtaskTo delete a task

Right-click a task and then click Delete Row on the shortcut menuOr

Click the task you want to delete and then click the Delete button

To delete a row click the Task row number and press the Delete button

See Also

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

-o-

84

copy Experience In Software Inc 1995 - 2006

Change the Timescale of the Schedule

You can display the Gantt chart schedule in the Chart view using days weeks months quarters or yearsas the timescale Changing from days to weeks for example displays a longer period of time but lessdetail

Days timescale Weeks timescale

To change the timescale in the Chart view

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years Youcan also change the timescale by clicking Timescale on the menu bar and then clicking the option youwant

Notes

When you print a Gantt chart your current timescale is used by default However you can change it inthe Print Options dialog For example even though you were viewing your Gantt chart by weeks youcan choose to print the Gantt chart by months

If your mouse comes with a wheel you can adjust Project KickStarts timescale by rolling the wheelforward or backward The Timescale list box must be selected first

-o-

85

copy Experience In Software Inc 1995 - 2006

Specify Working Days

You can select which days are working days and which days are nonworking days for scheduling purposesBy default Monday - Friday are working days and Saturday and Sunday are nonworking days You can addto and change these settings to specify holidays for example

To set working and nonworking days

1 Click the Change Working Schedule button on the Gantt chart toolbar The Change Working Schedule for this Project dialog box opens Nonworking days are shaded in grayWorking days are unshaded

2 To change a single date (from working to nonworking or from nonworking to working) click the date3 To change one day of the week for the entire project such as all Fridays double-click any Friday4 To display schedules for other months click the left and right arrows5 Click OK

Note

Project KickStart maintains separate calendars for each project

If you typically work weekends create a simple template with weekends displayed as Working daysSave as your starter template Use the starter template when you start a new project and then save theproject with a different name Weekends will be displayed as Working days in your projects

-o-

86

copy Experience In Software Inc 1995 - 2006

Change the Color of Taskbars

You can change the color of the taskbars in the Chart view to call attention to particular tasks For exampleyou can change the colors of all tasks in a particular phase resource or deadline to make them stand outin a report

To change the color of a taskbar1 Right-click a taskbar and then click Color on the shortcut menu or click a taskbar and then click the

Color button on the Gantt chart toolbar The Color dialog box opens

2 Click the color you want to assign to the taskbarTips

Avoid changing the taskbar color to black because it obscures the Done progress bar (The Doneprogress bar is a black bar displayed within a taskbar)

Also avoid changing the taskbar color to white because it will not appear in the white rows of the Chartview

-o-

87

copy Experience In Software Inc 1995 - 2006

Make Tasks Overlap

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro the schedule starts in a cascade with each task lasting one day and each tasklinked to the following taskHowever it is very unlikely that your entire schedule matches such a cascade so you can adjust theschedule Start by estimating the duration of tasksmdashthe number of days that each task will take Generallyit is best to estimate how many days will elapse before the task is done You might also want some tasks to occur at the same time To do so you can overlap the tasks To make tasks overlap like this

You can do this in three ways Set the same predecessor for both tasks

Or Set the second task as the successor of the first task and then then move the second task into a

position when it starts on the same day as the first taskOr

Set the second task as the successor of the first task and then assign a lead time of ndash3 days (the number of days scheduled for the task)

To make tasks overlap like this

Set the second task as the predecessor of the first task and then assign a lead time of ndash2 days(one less than the number of days scheduled for the task)

-o-

88

copy Experience In Software Inc 1995 - 2006

Manage Changes in Your Schedule

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro when you schedule with dependencies you can adapt to changes on the fly andcreate what-if scenarios to forecast how one change affects the overall project schedule A commonscenario is dealing with delays You can reschedule an entire project or only selected tasks When you doProject KickStart Pro updates the schedule for you

To delay an entire project Click in the Project Start text box and then edit the date to match your new start date (You can edit

the day month or year)Or

1 Click the Project Start list arrow to display the calendar The calendar highlights the selected date andoutlines todays date

2 Find the date you want using the left and right scroll arrows to view a different month and then click thedate Project KickStart changes the Start and Finish dates for all tasks according to your selection

To delay a task In Task Data view double-click the Days column for the task and then edit the number of days it will

take to complete the taskProject KickStart changes the Finish date of the task adjusts the taskbar in the Chart view andchanges the Start and Finish dates for all tasks linked to this taskOr

In Chart view resize a taskbar by clicking the taskbar and then dragging its left edge to schedule adifferent start date or dragging its right edge to schedule a different finish date Project KickStart updates the summary bar in Chart view the task dates and duration in the Task Dataview and reschedules all tasks linked to this task

To reschedule a task without changing the duration in Chart view drag the taskbar to a different date Project KickStart updates the task dates and duration as necessary in the Task Data view andreschedules all tasks linked to this task

Note

Project KickStart Pro does not include a critical path

-o-

89

copy Experience In Software Inc 1995 - 2006

Managing Libraries

Use a Library

Project KickStart has five libraries that contain lists of useful phases tasks goals people and obstaclesAll libraries expect the People Library contain sample entries that you can use in your projects Yougenerally build your own People Library from the resources that are available to you

To use a library1 In the Phases Tasks Goals People or Obstacles step of the Planning Wizard click the Library button

to open the appropriate library2 Select one or more items in a library and then drag them to your list3 Close the Library window

Tips

Feel free to add (or delete) items to the libraries to make them richer and more pertinent to yourprojects

Keeping libraries small makes them easier to use

Widen the library window to see the full text of long entries

Note

After adding a library entry to a list you can double-click the entry to edit it

See Also

Manage a Library

-o-

90

copy Experience In Software Inc 1995 - 2006

Manage a Library

Customize the libraries by adding and changing entries and reorganizing them so you can use the librariesefficiently The Phases Tasks Goals People and Obstacles Libraries include a single column ofinformation while the People Library provides additional columns (See Manage the People Library)

To edit a library1 Open the library by clicking the appropriate Library button2 To edit an entry double-click it

3 To add an entry to the library press Insert or click the Add a row button You can also select oneor more items in the list and then drag them to the library

4 To delete an entry select the entry and then press Delete or click the Delete a row button 5 To move an item up or down select the item and then click the Up Arrow or the Down Arrow button

6 Click the OK button to save your changes and close the Library windowTips

Widen the Library window to add a long entry

Libraries can serve as ldquoKnowledge Librariesrdquo By including typical company-specific terms in yourLibraries you create a quick reference for yourself and colleagues now and in the future To do so adda new line in the Library enter the name of your company (or department) as a heading in capitalletters and then list your personal terms under the heading

If you use Project KickStart on more than one computer such as at home and work you can transportchanges you make in your Libraries from one computer to another The data in all the Libraries isstored in one file pks5libxdat so you can copy that file on one computer and paste it into the ProjectKickStart 5 folder on the other computer

Keeping Libraries small makes them easier to use Project KickStarts Libraries are fairly rich out of thebox If some of the terms don rsquot apply to your type projects delete them

See Also

Manage the People Library

-o-

91

copy Experience In Software Inc 1995 - 2006

Manage the People Library

The People Library is like the other libraries but with a few important extra features

You can store contact data such as Company Email Phone and Job Title

You can import names from ACT or from Outlook if you use either of those programsTo use the People Library1 In the People step of the Planning Wizard click the People Library button2 Select one or more names in the People Library and then drag them to your list (This adds only the

names of people not their contact data) If the People Library contains company names but not contactnames you can drag the company name to your list

3 Close the Library windowTo organize the People Library

To show or hide a column right-click a column heading to open a shortcut menu and then click acolumn name In the shortcut menu a checkmark appears next to columns that are displayed in thePeople Library

To sort the people in the People Library click a column heading For example click the Name columnheading to sort the people alphabetically by name To reverse the sort click the column heading again

To move a person up or down select the person and then click the Up Arrow or the Down Arrowbutton

Click the OK button to save your changes and close the People LibraryTo edit the People Library

To edit a persons name and contact data double-click the entry

To add a person to the People Library click the first blank row press Insert or click the Add a rowbutton Then type to enter the persons name and contact information You can also select one ormore items in the list and then drag them to the People Library

To delete an entry select the entry and then press Delete or click the Delete a row button

Click the OK button to save your changes and close the People LibraryTips

Use the People Library to store names for people teams (such as Quality control team) departments(such as Manufacturing) companies (such as Acme Widgets Corp) or even equipment (such as wheatthrasher)

Widen the People Library window to add a long entry

Resize the columns by dragging or double-clicking a splitter barNotes

After adding a person or resource to your list you can double-click the name to edit it

You can import contact information stored in an Outlook or ACT (version 6 7 or later) address book toyour People Library

See Also

Import ACT Contacts and Users to the People Library

Import Outlook Contacts to the People Library

-o-

92

copy Experience In Software Inc 1995 - 2006

Import ACT Contacts and Users to the People Library

If you use ACT 7 or later (200520062007) or if you use ACT 6 you can import contacts and users to thePeople Library This speeds up your work by letting you use ACT information in your Project KickStartplans If you export a plan to ACT 7 or later it recognizes the people and other resources you entered inProject KickStart

To import ACT contacts and users1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click ACT 7 or later or ACT 6 Click the Import button3 Click the Select ACT Database button and select the ACT 7 or later database (pad) containing the

people information you want to import The ACT 7 and later databases are usually stored in MyDocumentsACTACT for Win 7Databases (If you use ACT 6 your data is stored in a dbf database) If you select a multi-user ACT database you must enter your user name and password for the ACTdatabase

4 In the Import to People Library dialog box the names of Contacts and Users are listed on the left Clickthe Users tab select one or more users and then click Add to move the user names to the Import listClick the Contacts tab to select contact names the same way Click the Add All button to select allusers or contacts for import Note You can sort the contacts alphabetically by name or by company name by clicking theappropriate column heading

5 Click the Import button to add the names and related information from the selected ACT database tothe People Library

Notes

Importing contacts and users to the People Library does not remove them from the ACT database

If you try to import the same ACT contact or user twice it appears only once in the People Library

-o-

93

copy Experience In Software Inc 1995 - 2006

94

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts to the People Library

If you use Microsoft Outlook to maintain your contacts you can import selected contacts to the PeopleLibrary ThisThis speeds up your work by letting you use Outlook information in your Project KickStartplans If you export a plan to Outlook it recognizes the people and other resources you entered in ProjectKickStart

To import Outlook contacts1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click Outlook Click the Import buttonA dialog box opens informing you that Project KickStart is trying to access your Outlook data

3 Allow access for 1 minute and then click the Yes button4 If Outlook asks you to choose your profile please do so5 The Import to People Library dialog box opens listing Outlook Contacts on the left Select one or more

contacts and then click Add to move the contact names to the Import list Click the Add All button toselect all contacts for import

6 Click the Import button to add the contact names to the People Library

Notes

Importing contacts and users to the People Library does not remove them from Outlook If you try to import the same Outlook contact twice it appears only once in the People Library

95

copy Experience In Software Inc 1995 - 2006

You can import Contacts from the Outlook Business Contact Manager

See Also

Import Outlook Contacts via CSV to the People Library (Pro Users)

-o-

96

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts via CSV to the People Library (ProUsers)

This feature is available only in Project KickStart Professional

If you use Microsoft Outlook to maintain your contacts and many of the people on your project are not inyour personal contacts folder in Outlook you can use our new utility to import these Outlook contacts viaCSV to the People Library

To export Outlook contacts to a CSV file1 In Outlook - Click File Import and Export Export to A File and click Next2 Select Comma Separated Values (Windows) and click Next3 Select the Contacts folder to export and click Next4 Save Exported File As with the default being your My Documents folder5 Click Next

To import Outlook contacts to the People Library

1 Be sure that you exit Project KickStart before running the Import Utility

2 Run ImportCSVToPKSexe which is located in the Project KickStart application folder

3 Browse or type the Contacts CSV file (the path is My DocumentsProject KickStart Projects folder bydefault)

4 Browse or type the pks5libxdat file (default is the Project KickStart application folder)

5 Click on Import

Note

Importing contacts and users to the People Library does not remove them from Outlook

-o-

97

copy Experience In Software Inc 1995 - 2006

Printing Reports

98

copy Experience In Software Inc 1995 - 2006

Printing Dashboards

Print Reports

You can print reports from anywhere in Project KickStart through a new Reports Step

You will see Reports divided into three areas

Dashboard

Task Reports

Gantt Chart Reports

-o-

99

copy Experience In Software Inc 1995 - 2006

Print Dashboard Reports

You can print dashboard reports from anywhere in Project KickStart though it makes the most sense toprint them after you have developed your tasks and arranged them in a sensible order

To print a dashboard report

1 Click File on the menu bar and then click Print Reports and then click Dashboard Reports or clickthe Print Reports button

2 In the left column select one of these dashboard reports Whats Due Today Whats Due NextWeek Whats Due Next Month

3 Change the page setup as necessary or Save As a file (See Page Setup and Save As)

4 Click the Print button

Tip

You can see the number of tasks in each dashboard report from the dashboard menu

-o-

100

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Dashboard Reports

Printer Setup

-o-

101

copy Experience In Software Inc 1995 - 2006

Save as HTML or RTF

You can dashboard reports to a Hypertext Markup Language (HTML) format for viewing with an Internetbrowser such as Microsoft Internet Explorer or Mozilla FireFox or to an RTF format for viewing in MicrosoftWord

To save a dashboard report as an HTML file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save button

To save a report as an RTF file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

102

copy Experience In Software Inc 1995 - 2006

Printing Task Reports

Print Task Reports

You can print task reports from anywhere in Project KickStart though it makes the most sense to print themafter you have developed your tasks and arranged them in a sensible orderBefore you print task reports you might want to widen the Task Name column in the Task List to make sureyou print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a task report

1 Click File on the menu bar and then click Print Task Reports In the Tasks step you can click thePrint Reports button instead

The Create and Print Task Reports dialog box opens

2 Click the list arrow and then click Task Report Individual Assignments or Phases Goals People ampObstacles

3 Select the information you want to include in the report as described below

4 Preview the report and change the page setup as necessary (See Print Preview and Page Setup)

5 Click the Print button

Task Report

The Task report covers the entire project and includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

103

copy Experience In Software Inc 1995 - 2006

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to display in the report

By default the report prints all tasks Click the Incomplete Tasks or Completed Tasks option button tofocus on one type of task

4 Click the Preview button (See Print Preview for details)

Individual Assignments

The Individual Assignments report covers the entire project and lists the tasks assigned to each resourceThe report includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to include in the report

Click the All Tasks Incomplete Tasks or Completed Tasks option button

4 Choose which people to include The report lists tasks assigned to the people you select

Click to insert or remove a checkmark from the box for each person

5 Click the Preview button (See Print Preview for details)

Phases Goals People amp Obstacles

This report includes the phases goals people and obstacles in your project You can include some or all ofthese items in the report

104

copy Experience In Software Inc 1995 - 2006

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Click the Preview button (See Print Preview for details)

Tip

If you have many long notes for the tasks of your project it may be hard to read them if you select everycolumn in the Task Reports You should consider selecting a report with only columns for Tasks andNotes

See Also

Print Gantt Chart Reports

-o-

105

copy Experience In Software Inc 1995 - 2006

Print Preview

Before printing a report preview its pages so you know how the report will look when printed

To preview a task report1 Click the Preview button on the Create and Print Task Reports dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from 79 to 100 or from 100 to 79Zoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25

viewPrint the report

You can also click the Page Setup button to change margins and other settings or click the Closebutton to close the Print Preview window

2 If the report appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintTask Reports dialog box

Note

Print Preview is for viewing only--you cannot edit the contents of a report

See Also

Print Task Reports

Printer Setup

Page Setup

-o-

106

copy Experience In Software Inc 1995 - 2006

Printer Setup

Before you print a report you can change the following printer settings

Printer name (and other properties) Paper size Number of copies

To change the printer setup1 Click the Printer button on the Project KickStart toolbar or the Print Preview toolbar2 In the Print dialog box change the printer settings

See Also

Print Task Reports

Print Preview

Page Setup

-o-

107

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Task Reports

Print Preview

Printer Setup

-o-

108

copy Experience In Software Inc 1995 - 2006

Email Task Reports

After creating and previewing a task report you can distribute it to others via email

To email a task report1 In the Create and Print Task Reports dialog box select a report and then click the Email Report

button Project KickStart creates the report opens a new message in your email software and attaches thereport as an HTML file to the message

2 Insert one or more email addresses include the message text and then send the message the way youusually do

Tip

To send a task report to each person in your project with the appropriate assignments select theIndividual assignments report select one person to receive the report and then click the Email Reportbutton Enter the email address of the recipient and send the message Do this for each person in yourproject

-o-

109

copy Experience In Software Inc 1995 - 2006

Save as HTML

You can export tasks assignments days and notes to a Hypertext Markup Language (HTML) format forviewing with an Internet browser such as Microsoft Internet Explorer or Mozilla FireFox

To save a report as an HTML file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

110

copy Experience In Software Inc 1995 - 2006

Save as RTF

You can export tasks assignments durations and notes to a Rich Text Format (RTF) for editing inMicrosoft Word

To save a report as an RTF file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can open an RTF file in a word processor such as Microsoft Word

To send an RTF document to each person in your project with the appropriate assignments select theIndividual Assignments report select one person to receive the report and then save the report asRTF Do this for each person in your project

See Also

Save as HTML

-o-

111

copy Experience In Software Inc 1995 - 2006

Printing Gantt Chart Reports

Print a Gantt Chart

Once you create your schedule you can print a Gantt chart from anywhere in Project KickStart

Before you print a Gantt chart you might want to widen the Task Name column in the Task pane to makesure you print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a Gantt chart1 Click File on the menu bar and then click Reports and then select Gantt Chart Reports In the

Schedule step you can click the Print Reports button insteadThe Create and Print Gantt Chart Report dialog box opens

2 Click the Format list arrow and then click Wall chart Fit to smallest size or Repeat tasks on everypage (for handouts)

3 Select the information you want to include in the report as described below4 Preview the report and change the page setup as necessary (See Print Preview a Gantt Chart and

Page Setup)5 Click the Print button

Wall Chart The wall chart prints the Gantt chart information spread across many pages which you can tape together tocreate a wall chart On the left side of the report the wall chart includes the task data columns you selectThe right side of the report includes the graphical view shown in the Gantt chart pane on the right

1 Select the task data columns you want to display for the task information on the left side of the wallchartClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the wall chart

112

copy Experience In Software Inc 1995 - 2006

By default the wall chart prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the wall chartBy default the wall chart prints the timescale you were using in the Gantt chart Click the SetTimescale list arrow to change the timescale to Weeks Months Quarters or Years

4 Select the orientation for the wall chartClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Fit to Smallest Size When you select the Fit to smallest size format Project KickStart reduces the size of the entire Gantt chartincluding the information in the Task pane on the left and the graphical view shown in the Gantt chart paneon the right so it fits as well as possible in the smallest number of pages

1 Select the data columns you want to display for the task information on the left side of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 The timescale for the Gantt chart view on the right side of the report is determined by the length of yourproject and may not be changed

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 The number of pages of the report is shown here (The Fit to smallest scale report will print up to 78rows of tasks per page)

6 Click the Preview button (See Print Preview a Gantt Chart for details)

Standard (for Handouts) This report lists the data columns you specify on the left side of the first page and can repeat the tasknumber task name or assignments on every interior page of the report which is especially useful for

113

copy Experience In Software Inc 1995 - 2006

handouts

1 Select the data columns you want to print on the left side of the first page and the data columns youwant to print on every page of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the reportBy default the report prints a daily view of the tasks Click the Set Timescale list arrow to change thetimescale to Weeks Months Quarters or Years

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Tips

Print Preview shows how many pages the Gantt chart will take to print If there are too many pagesconsider changing the timescale or the date range You can also choose to show fewer columns of taskdata

If possible use paper that is larger than 85 x 11 inches You can select the paper size in Print Previewusing the Page Setup dialog box

If you change the timescale from Days to Weeks or Months this can make tasks with short durations (1to 5 days) difficult to see

If you have trouble printing the Gantt chart report try changing the dpi from 600 to 300 (draft mode) Ifyou continue to have problems contact your printer manufacturer and see if it supports PCL (PrinterCommand Language) technology which is included in most printers today

If you have trouble printing the Gantt chart report on a PDF printer you can try to scale the printing tographics setting to 50

114

copy Experience In Software Inc 1995 - 2006

See Also

Save Gantt Chart Images

Print Task Reports

Printer Setup

Page Setup

-o-

115

copy Experience In Software Inc 1995 - 2006

Print Preview a Gantt Chart

Before printing a Gantt chart preview its pages so you know how the report will look when printed

To preview a Gantt chart1 Click the Preview button on the Create and Print Gantt Chart Report dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from the current zoom percentage to 100 or from 100 to the current zoom percentageZoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25 viewChange printer settings and then print the reportYou can also click the Page Setup button to set margins select paper size and enter headers andfooters or click the Close button to close the Print Preview window

2 If the Gantt chart appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintGantt Chart Report dialog box

Notes

Print Preview is for viewing only--you cannot edit the contents of a report

If you want to print a wider task column return to the Gantt chart widen the Tasks Name column andthen print

To change print settings such as the printer selection and number of copies click the Print button to open the Print dialog box You can save the Gantt chart in a PDF file by clicking the Print button andthen clicking the PDF printer selection (such as Adobe PDF or PDF-XChange ) You can then distributethe Gantt chart electronically as a PDF file

See Also

Print a Gantt Chart

Page Setup

-o-

116

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a Gantt chart you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print a Gantt Chart

Print Preview a Gantt Chart

-o-

117

copy Experience In Software Inc 1995 - 2006

Printing to an Adobe PDF file

To print a Gantt chart to an Adobe PDF file you may have to make some adjustments to your settings

To preview a Gantt chart1 Select Adobe PDF as the name of the printer2 Click Properties button3 Click the PaperQuality tab4 Click Advanced button5 In the Graphic Section lower the setting on Print Quality6 Also in the Graphic Section change the Scaling from 100 to 50

-o-

118

copy Experience In Software Inc 1995 - 2006

Save Gantt Chart Images

You can save a Gantt chart as a series of graphic files in the Meta File (emf) format which you can theninsert in a file such as a Microsoft Word document or PowerPoint presentation The number of graphic filescreated depends on the report type and options you choose in the Create and Print Gantt Chart Reportdialog box By default Project KickStart saves the files in a folder named for your project

To save Gantt chart images1 In the Create and Print Gantt Chart Report dialog box click the Save Image button

The Save Image dialog box opens2 Change the location where you want to save the image files or change the part of the file name that

includes the project name and report type if necessary3 Click the Save buttonNotes

Project KickStart saves the image files in the PKSGanttImagesproject name folder stored in the MyDocumentsProject KickStart Projects folder (where project name is the name of your project)

Each graphic file name includes the name of the project report type date you created the report andnumber in the series of images as in CreateaWinningPresentation_Wall chart_09112008_1emf toCreateaWinningPresentation_Wall chart_09112008_20emf

To email the Gantt chart images attach the images in the PKSGanttImagesproject name folder storedin the My DocumentsProject KickStart Projects folder (where project name is the name of your project)If the image files are large zip or compress the files first

If you have installed PDF as a printer selection you can print the Gantt chart to a PDF file and thenattach the PDF file to an e-mail message PDF files are often easier to read than image files See thenotes in Print Preview a Gantt Chart for instructions on printing to a PDF file

-o-

119

copy Experience In Software Inc 1995 - 2006

Export Project Data

120

copy Experience In Software Inc 1995 - 2006

Export to ACT

Export to ACT 7 or Later

If you use ACT 7 or later (20052006200720082009) you can export your plan from Project KickStart toan ACT database with just one click After you export your plan you see your tasks in the ACT Groupview grouped under the name of your project

To export to ACT 7 or later

1 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 7 and later andthen click the Go button You can also click File on the menu bar point to Export to and then clickACT 7 and later

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (pad file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opens

Each time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks

4 Click Start (This works best if ACT is already open )

5 If you are exporting to a multi-user ACT database enter your ACT User Name and Password

To view each project separately in ACT Group Details

1 In ACT click the Group List icon

2 Double-click the Project Name in the Group Name column The Group Detail appears for the projectyou selected

3 Click the Contacts tab to see Contacts and click the Activities tab to see tasks for that project

4 You should press Ctrl-F5 to refresh the view Also you might have to adjust the Filter in ACT so thatDates to show is set to All Dates

Task names are listed in the Regarding column Assignments are listed in the Scheduled With columnPhases are shown in red and tasks and subtasks are shown in blue

To view tasks from multiple projects sorted by date in Task List or Calendar

In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn Project names are in the Associate With column You might have to adjust the Filter in ACT sothat Dates to show is set to All Dates

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar Tasks are set as timeless (Duration of 0 minutes) so the transferred tasks dont fill up thecalendar

121

copy Experience In Software Inc 1995 - 2006

Tips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

The ACT 7 and later export is smart enough to update your existing tasks from the same project If youexport the same Project KickStart project two or more times ACT recognizes the project and asks ifyou want to update the project information in ACT You do not lose your task history or notes in ACT

Tasks that are unassigned in Project KickStart are listed as Scheduled With Unassigned PKS

You can filter by Selected Users in the Task List and in Groups

See Also

Import ACT Contacts and Users to the People Library

-o-

122

copy Experience In Software Inc 1995 - 2006

Export to ACT 6

If you use ACT 6 ACT 2000 or ACT 5 you can transfer a Project KickStart plan into an ACT databasewith just one click After you export your plan you see your tasks in the ACT Group view grouped underthe name of your project

To export to ACT 61 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 6 and then click

the Go button You can also click File on the menu bar point to Export to and then click ACT 6

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (dbf file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opensEach time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks4 Click Start (This works best if ACT is already open )5 If you are exporting to a multi-user ACT database enter your ACT user name and passwordTo view each project separately in ACT1 In ACT click the Groups icon 2 Click the Project Name listed under All Groups on the left3 On the lower-right part of the window click the Activities tab to see tasks for that project

Task names are listed in the Regarding column Assignments are listed in the Scheduled With column 4 You might have to adjust the Filter in ACT so that Dates to show is set to All Dates Also you might

have to press Ctrl-F5 to refresh the view5 To view task details click the button next to the task column on the leftTo view tasks from multiple projects sorted by date1 In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn You might have to adjust the Filter in ACT so that Dates to show is set to All Dates

2 If the Group column is not showing add it by clicking ViewAdd Columns and then double-clickingGroupThe tasks are identified by group (project name)

3 To view task details click the button next to the task column on the leftTips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar as well as in the Task List

You can filter by Selected Users in the Task List and in Groups

After exporting your tasks to ACT you can import them to your Palm Pilot using the ACT Link

See Also

Import ACT Contacts and Users to the People Library

-o-

123

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Outlook

If you use Microsoft Outlook you can export your plan from Project KickStart to Outlook in a click of abutton After you export your plan you see your tasks in the Outlook Tasks view grouped under a categorynamed for your project In Outlook you can track your tasks and email tasks to team members

To export to Microsoft Outlook1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Outlook and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Outlook The Export to Outlook dialog box opens

2 Click an option button to export All tasks Uncompleted tasks or Completed tasks3 If you want to display the tasks you export on your Outlook Calendar click the check box4 Click the Start button A dialog box opens informing you that Project KickStart is trying to access your

Outlook data

5 Allow access for 1 minute and then click the Yes buttonTo view your tasks in Microsoft Outlook1 Click the Outlook Tasks button2 Depending on the version of Outlook you are using set to view the tasks by category In Outlook 2003

click the By Category option button in the Current View list You can also click View on the menu barpoint to Arrange By and then click CategoriesYour project is listed by its project name in the Categories list

3 Click an expand icon to see the complete list of tasks and subtasks

124

copy Experience In Software Inc 1995 - 2006

4 To view task details double-click the task nameTips

The export to Outlook works best if Outlook is already open

In Outlook you can set priorities set reminders and schedule by the hour

If you export to your Outlook Calendar a reminder appears on the due date of each task

After you export tasks to Outlook you can synchronize with your Palm Pilot Windows CE device orother handheld computer

Note

You can export only to Microsoft Office Outlook not Outlook Express

See Also

Import Outlook Contacts to the People Library

-o-

125

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Word

If you use Microsoft Word you can export your plan from Project KickStart to Word in a click of a buttonYour project appears in a Word table in a doc file You can cut and paste change column widths deletecolumns and print from Word

To export to Microsoft Word

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Word andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Word

Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in a Word document in a doc format

2 When youre finished use Save As to save the Word file with a new name such as ltnamegtdoc Forconvenience you can save the file using the same name as your Project KickStart project name

Benefits of using Project KickStart and Word

Communicate projects flexibly After exporting to Word you can communicate your project details ina variety of text formats You can also enhance your document by adding color logos clip art orhyperlinks

Distribute plans to others You can send doc files to other Microsoft Word users via email andrequest comments using Words Send To and Comments features

Tip

Include your strategic plan in documents letters and web pages in a doc or html file

Note

The image of the Gantt chart does not import into Word automatically You can manually import theGantt chart image into a Word document In Word select Insert on the menu bar point to Pictureclick From File and then browse to the folder containing the Gantt chart images you saved By defaultthis is cMy DocumentsProject KickStart ProjectsPKSGanttImages in a folder named for your project

See Also

Export to Word Processors (Other than Word)

Save Gantt Chart Images

126

copy Experience In Software Inc 1995 - 2006

-o-

127

copy Experience In Software Inc 1995 - 2006

Export to Word Processors (Other than Word)

If you are using a word processor other than Microsoft Word you can export your Project KickStart taskreport by first saving it as an HTML or RTF file

To export to word processors other than Microsoft Word

1 Save a Project KickStart task report using HTML or RTF format using the Save As button in the Createand Print Task Reports dialog box

2 Open the file with your word processor

3 Save the file using the Save As command using a different name

See Also

Print Task Reports

Save as HTML

Save as RTF

-o-

128

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Excel

If you use Microsoft Excel you can export your plan from Project KickStart to Excel in a click of a buttonYour project appears in an Excel worksheet in a xls file You can add task details perform calculationsand share your project data with other Excel users

To export to Microsoft Excel1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Excel and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Excel Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in an Excel worksheet in an xls format

2 When youre done select FileSave As to save the Excel file under a new name For convenience youmight want to save it under the same name as your Project KickStart project name

To manually import Gantt chart images into Microsoft Excel1 In Excel click Sheet2 and select ToolsOptions on the menu bar and unclick the box for Gridlines2 Then select Insert on the menu bar point to Picture click From File and then browse to the folder

containing the Gantt chart images you saved By default this is cMy DocumentsProject KickStartProjectsPKSGanttImages in a folder named for your project

3 Select one Gantt chart image at a time to bring it in 4 You can manipulate the size of the image in Excel

Benefits of using Project KickStart and ExcelProject KickStart is very good at scoping out a schedule but there are a few reasons why you might want touse both programs

Data sharing A Project KickStart user might want to share the information with other Excel users whodont have Project KickStart They could change enhance or redistribute their portions of the schedule

129

copy Experience In Software Inc 1995 - 2006

Add more task details Excel users can add new columns of task data that cant be added in ProjectKickStart

Sort task lists For example you could show your projects tasks sorted by each resources namethen see each resources tasks sorted by the tasks start date

Filter tasks Excel can show tasks that meet certain criteria For instance show tasks with the wordtesting in the task name

See Also

Save Gantt Chart Images

-o-

130

copy Experience In Software Inc 1995 - 2006

Export to Microsoft PowerPoint

If you use Microsoft PowerPoint you can export your plan from Project KickStart to PowerPoint in a click ofa button Your project appears as a formatted PowerPoint presentation in a ppt file

To export to Microsoft PowerPoint

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft PowerPointand then click the Go button You can also click File on the menu bar point to Export to and thenclick Microsoft PointPoint

The Export to PowerPoint dialog box opens where you can choose a PowerPoint design template ifyou like

2 Click the Start button

Your tasks days start and finish dates and costs appear in a PowerPoint presentation with an imageof the Gantt chart in one or more slides at the end of your slide show

Once you have created a PowerPoint presentation you can enhance your slides in several ways

Delete slides that are not appropriate for your presentation

131

copy Experience In Software Inc 1995 - 2006

Rearrange the order of the slides

Add colors for emphasis

Add graphics such as company logo clip art and colors

Shorten any long task titles

Benefits of using Project KickStart and PowerPoint

Save time You can dramatically save time in creating a PowerPoint presentation on your project

Present projects to others Present project details in webinars presentations and corporatemeetings Create template presentations or how tos for implementing an installation productintroduction or corporate policy for example

Communicate plans Email project plans in ppt format to colleagues and presentors

Tips

If you use a PowerPoint design template choose one that has a white or light background for maximumlegibility of the Gantt chart in the presentation

The Gantt chart image in the PowerPoint presentation is generated ldquoon the flyrdquo Change the Timescalesettings of the Gantt chart considering how it will be reflected in the number of images of the Ganttchart For example the Day view results in more Gantt chart images than the Months view

-o-

132

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Project

If you use Microsoft Project 98 2000 2002 or 2003 you can export your plan from Project KickStart toProject in a click of a button

To export to Microsoft Project

In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Project andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Project Your tasks assignments days start and finish dates costs done and notes (excluding attachments) appearin a Microsoft Project file

Benefits of using Project KickStart and Microsoft Project

Share data with others Send a project to a colleague or client that expects to see your schedule in anMicrosoft Project format

Schedule tasks with more flexibility Schedule tasks in different durations particularly in less than aday

Track resources Track resource usage and resource leveling and to have greater flexibility in sortingfiltering and reporting project information

Notes

Project KickStart tasks transfer to Microsoft Project as tasks with a Constraint type of Start No EarlierThan This keeps the dates the same as in the Project KickStart schedule

The settings in Project KickStart Working Days Calendar also transfer to Microsoft Project

Exporting to Microsoft Project allows you to take advantage of the advanced tracking and schedulingfeatures that large projects often require

You can also save your Project KickStart projects as an mpx file which you can open in MicrosoftProject and send to other Microsoft Project users Click File on the Project KickStart menu bar clickSave As and then choose mpx as the file type After you save the file click File on the MicrosoftProject menu bar click Open and open your mpx file

-o-

133

copy Experience In Software Inc 1995 - 2006

Export to SureTrak Project Manager

If you use SureTrak Project Manager you can export your plan from Project KickStart to SureTrak ProjectManager

To export to SureTrak Project Manager

1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file

2 In SureTrak click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

SureTrak

You will see your tasks and assignments (but not the notes) appear in a SureTrak file The file is shownin outline view

Benefits of using Project KickStart and SureTrak

Add new information to tasks such as how they are linked

Track progress particularly for comparing plans verses actual results

Have greater flexibility in sorting filtering and reporting project information

Notes

Task notes are not included in the transfer

A version of Project KickStart called the Project KickStart Wizard is included in SureTrak 2 andSureTrak 3 You can use it within SureTrak

See Also

Export MPX Files

-o-

134

copy Experience In Software Inc 1995 - 2006

Export to FastTrack Schedule

If you use FastTrack Schedule you can save your Project KickStart project as an mpx file and import it intoFastTrack ScheduleTo export to FastTrack Schedule1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file2 In FastTrack Schedule click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

FastTrack ScheduleBenefits of using Project KickStart and FastTrack Schedule

Add more task details FastTrack Schedule provides the features and tools needed in many largeprojects

Multiproject reporting Consolidate multiple projects into a master project file

See Also

Export MPX Files

-o-

135

copy Experience In Software Inc 1995 - 2006

Export to Milestones Professional

If you use Milestone Professional you can export your plan from Project KickStart to MilestonesProfessional in a click of a button

To export to Milestone Professional

In the Schedule step click the Export to list arrow below the Gantt chart click MilestonesProfessional and then click the Go button You can also click File on the menu bar point to Export to and then click Milestones Professional

Your tasks assignments start and finish dates and notes (excluding attachments) appear in aMilestones file

Tips

After you export your tasks to Milestones Professional you can create taskbars add titles and performother tasks to produce a presentation-quality schedule You can also use Milestones to track your tasksby showing task durations and percent completions Make scheduling changes by dragging the taskdates

If you have an earlier version of Milestones (eg version 45 or 5) you can save Project KickStart dataas an mpx file and then open the mpx file in Milestones

-o-

136

copy Experience In Software Inc 1995 - 2006

Export to Mindjet MindManager

If you use Mindjet MindManager 7 or later you can export your project plan from Project KickStart in a clickof a button Or you can develop a rough plan in MindManager and export your mind map to ProjectKickStart for enhanced planning It works both ways

To export from Project KickStart to MindManager

In the Schedule step click the Export to list arrow below the Gantt chart click MindManager and thenclick the Go button You can also click File on the menu bar point to Export to and then clickMindManager

Your tasks assignments start and finish dates durations costs Done and notes (excludingattachments) appear in a MindManager file

To export from MindManager to Project KickStart

In MindManager click File on the menu bar point to Send To and then click Project KickStart Thenclick the OK button to start the export

You can also click the Project KickStart icon at the bottom of the MindManager window

Benefits of using Project KickStart and MindManager together

Visualize your plan in two ways Brainstorm plan and communicate your project details in both agraphical and linear style

Develop a graphical plan and then fine-tune the details MindManager uses mindmappingtechniques to develop a high-level plan in a graphical format Export to Project KickStart to enhanceyour plan details by focusing on your projects goals obstacles and resource needs You can alsocreate a Gantt chart schedule

Communicate concepts Project KickStart users can display their plans in a highly graphicalmindmapping format in MindManager The maps make it easier to communicate complex processesand visually identify important tasks issues and relationships

Tip

If you dont already use MindManager you can purchase it in our Thinking Tools Store

-o-

137

copy Experience In Software Inc 1995 - 2006

Export to WBS Chart Pro

If you use WBS Chart Pro you can export your plan from Project KickStart to WBS Chart Pro in a click of abutton

To export to WBS Chart Pro

In the Schedule step click the Export to list arrow below the Gantt chart click WBS Chart Pro andthen click the Go button You can also click File on the menu bar point to Export to and then clickWBS Chart ProYour project is displayed under the project name Each phase in the project is shown in a box with ashadow Each lower level task in a phase is displayed under their respective phase box groupedtogether with the other tasks in that phase

Benefits of using Project KickStart and WBS Chart

Visualize tasks Work with tasks in a tree-style chart called a Work Breakdown Structure (WBS)chart

Communicate your project plan with others WBS Chart uses the outline you create in ProjectKickStart to create a top-down picture of your plan This picture is similar to an Organization chart Butinstead of displaying the structure of your company a WBS chart displays the structure of your projectplan

Notes

WBS Chart refers to the phases in the project as Summary Tasks and the detail for each phase asTasks

The export only works if WBS Chart is not currently running You must close WBS Chart before you cancreate another chart

See Also

Export MPX Files

-o-

138

copy Experience In Software Inc 1995 - 2006

Export MPX Files

The MPX file format is an ASCII format created by Microsoft Project or another program and is used tosend data to and from project management software programs

The following programs can create and open MPX files

FastTrack Schedule

Microsoft Project (95 or 98)

Project KickStart 5

Project KickStart 32

RiskyProject

SureTrak Project Manager

WBS Chart

In these programs you save a project as an MPX file using the Save As command on the File menu Youcan then open an MPX file by using the Open command on the File menu and then specifying the file typeas mpx

For example if you want to move a project from Project KickStart 5 to Project KickStart 32 you can savethe project as an mpx file and then open it in Project KickStart 32

In Microsoft Visio you can create a Visio project time line from Project KickStart To do so you first mustsave your file in Project KickStart as an MPX file Then

1 Start Visio

2 Click File on the menu bar point to New click Business Diagram and then click Project TimelinesWizard

3 Click Next

4 On the second window click Import MPX File to import the Project KickStart mpx file

5 Enter the file location and name or click Browse to locate the file

6 Follow the instructions in the Visio Project Timelines Wizard windows

Tip

If you have difficulty importing the mpx file remove any commas from task names

-o-

139

copy Experience In Software Inc 1995 - 2006

Reference

140

copy Experience In Software Inc 1995 - 2006

Menus

File Menu

Command Keyboard Shortcut Description

New Project Ctrl+N Creates and names a new project fileOpen Project Ctrl+O Opens a previously saved Project KickStart 4 or 5 file

(prx) Project KickStart 3 file (prj) or mpx fileClose Ctrl+W Closes an open Project KickStart fileSave Ctrl+S Saves a project file (prx) in which you made changes Save As Saves a project file with a different file name or different

file format such as MPXPrint Task Reports

Ctrl+T Generates and prints a report letting you preview thecontents

Print Gantt ChartReports

Ctrl+G In the Gantt chart (Schedule step) generates andprints the Gantt chart in the current timescale

Export To Sends the project to another program such asMicrosoft Outlook or ACT 7

Recent file list Lists the last three files opened in Project KickStartExit

Alt+F4 Exits the program

-o-

141

copy Experience In Software Inc 1995 - 2006

Edit Menu

Command Keyboard Shortcut Description

UndoRedo Ctrl+Z Undoes or repeats the last operationCut

Ctrl+X Deletes the currently selected information placing it on theclipboard so you can paste it elsewhere

Copy

Ctrl+C Places a copy of selected information on the Clipboard so youcan paste it elsewhere

Paste

Ctrl+V Places information from the Clipboard to the currently selectedlocation

Select all Ctrl+A Selects all the content in the windowAdd a line Adds a new row where you can enter text

-o-

142

copy Experience In Software Inc 1995 - 2006

View Menu

Command Description

Tool Bar Shows or hides the toolbar (a checkmark indicates thetoolbar is displayed)

Steps Bar Shows or hides the Steps bar (a checkmark indicates the Steps bar is displayed)

Name Go to the Name your project stepPhases Go to Phases stepGoals Go to Goals stepSimilar Projects Go to Similar projects stepPeople Go to People stepObstacles Go to Obstacles stepAssign Go to Assign tasks to people stepTasks Go to Tasks stepSchedule Go to Schedule step

-o-

143

copy Experience In Software Inc 1995 - 2006

Tools Menu

Command Keyboard Shortcut Description

Spelling

F7 Checks spelling of project dataexcept for names of people

Collaboration To access or find out aboutGoToMeeting

Options Select options for running thesoftware

-o-

144

copy Experience In Software Inc 1995 - 2006

Options

-o-

145

copy Experience In Software Inc 1995 - 2006

Data Menu

The Data menu is available in the Tasks and Schedule steps for manipulating tasks and creating ascheduleCommand Description

Move Up Moves the selected task item upMove Down Moves the selected task item downOutdent Moves the selected task item to the leftIndent Moves the selected task item to the rightInsert Task Insert task in row aboveInsert SubTask Insert subtask below current rowDelete Task Delete current taskEdit Task Properties Brings you to an edit screen where you can edit task

name change assignments and edit task notesEdit Notes Brings you to an edit screen for editing task notesColor Taskbars Change the color of selected tasks (in Schedule)Change Working Days Select which days are working and which are

nonworking (in Schedule)Link Tasks Link tasks in Gantt chart (Pro Users)Unlink Tasks Unlink tasks in Gantt chart (Pro Users)

-o-

146

copy Experience In Software Inc 1995 - 2006

Timescale Menu

The Timescale menu is available in the Schedule step so you can change the display of the Gantt chartschedule

Command Description

Days Displays a daily schedule in theGantt chart

Weeks Displays a weekly schedule inthe Gantt chart

Months Displays a monthly schedule inthe Gantt chart

Quarters Displays a quarterly schedule inthe Gantt chart

Years Displays a yearly schedule inthe Gantt chart

-o-

147

copy Experience In Software Inc 1995 - 2006

Help Menu

Command Description

Project KickStart Help Help for Project KickStart including a Table ofContents and index of terms

Online Tutorials View several Getting Started Tutorials to getyou started with Project KickStart whether youare a new or experienced user

Keyboard Shortcuts Shortcuts for programTechnical Support How to obtain Technical Support for Project

KickStart via web form and email[Send Log to Technical Support] If the program detects an error it writes a log

of technical issues Click Send Log toTechnical Support to send the error log to us

ProjectKickStartcom Visit the Project KickStart Web siteGet Latest Version See what the latest published version is and

download it if you need itAbout Project KickStart Shows Project KickStart version number build

date copyright and system information

-o-

148

copy Experience In Software Inc 1995 - 2006

Shortcuts

Use the following keyboard shortcuts to move quickly around in Project KickStart

Navigation

Move forward to the next window Alt+NMove back to the previous window Alt+BSteps

Go to Name step Alt+MGo to Phases step Alt+SGo to Goals step Alt+GGo to Similar step Alt+RGo to People step Alt+PGo to Obstacles step Alt+OGo to Assign step Alt+IGo to Tasks step Alt+KGo to Library (Phases Tasks GoalsPeople Obstacles)

Alt+L

Menus

File menu Alt+FEdit menu Alt+EView menu Alt+VShow menu (Tasks step) Alt+WOutline menu (Tasks step) Alt+UTimescale (Schedule step) Alt+CHelp menu Alt+H F1Other

Edit tasks assignments amp notes (Tasks step)F3Save Ctrl+SPrint Task Report Ctrl+PPrint Gantt Chart (Schedule step) Ctrl+GCut Ctrl+XCopy Ctrl+CPaste Ctrl+VInsert Row InsertDelete Row DeleteInsert Line Break (in Notes in Task List andSchdule steps)

Enter

Spell Check

Ignore Alt+IIgnore All Alt+GChange Alt+CChange All Alt+HHelp

149

copy Experience In Software Inc 1995 - 2006

Contents in Help Alt+CIndex Alt+IBack in Help Alt+BClose Help Alt+LHelp about the current step Alt+H

-o-

150

copy Experience In Software Inc 1995 - 2006

Share Project KickStart Data

Project KickStart makes it easy to share data with other people involved with a project You can share yourProject KickStart data in the following ways

Send a printed report Make a PowerPoint presentation Send a file (prx html rtf mpx) Post an HTML file to a Web site and access it with your web browser Export to other programs such as Microsoft Word or Excel and send data in a format the recipient can

access (such as doc xls or mpx)

Note

You can also collaborate with a colleague by conducting an online meeting using GoToMeeting (Prousers)

-o-

151

copy Experience In Software Inc 1995 - 2006

Open a Project

After you create a project and save it in a prx prj or mpx file using Project KickStart or other softwareyou can open the project in Project KickStartTo open a project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click a file type (prxprj or mpx)

3 Navigate to the folder that contains the file4 Double-click the name of the file

Opening a Project KickStart 3 prj file converts it to a prx file

Generally prj files are stored in cprogram filesProject KickStart 3

The tasks in the converted Project KickStart 5 file will have the same start and finish dates anddurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way To have weekends as non working days open the working days calendar and markweekends as non working

Opening a mpx file converts it to a prx file

The tasks in each project have the same start and finish dates and durations

-o-

152

copy Experience In Software Inc 1995 - 2006

Dedication

I dedicate this software program to my new colleague

Kevin Ahlvin

Roy A Nierenberg President

-o-

153

copy Experience In Software Inc 1995 - 2006

Credits and Trademarks

Credits

Missak Koumoudjian Program Architect and Chief Programmer

Kevin Ahlvin Interface DesignAnn Kawamoto Quality AssuranceAlexander Setzepfandt Quality AssuranceJackie LeungJeffrey Chow

Programming Interns

Kevin Ahlvin Product Supervisor and CoordinatorJoseph Fusco Project Management Consultant and content

providerLisa RuffoloJoseph Fusco

Help System

Roy A Nierenberg President

Trademark

Project KickStart and Project KickStart Wizard are trademarks of Experience In Software Inc in the UnitedStates andor in other countries All rights reserved All other trademarks mentioned herein are the propertyof their respective owners

-o-

154

copy Experience In Software Inc 1995 - 2006

Uninstalling

You can uninstall Project KickStart 5 through the Control Panel AddRemove Programs Select ProjectKickStart 5 This starts the InstallShield Maintenance Program You should then remove all of theprogram files that were installed It will not erase your Project KickStart prx data files

If that does not work you can delete the Project KickStart files manually

Note

If you purchased Project KickStart and you want to return it for a refund follow the instructions forDe-activating the software at httpwwwprojectkickstartcomcontactreturnscfm

-o-

155

copy Experience In Software Inc 1995 - 2006

Using Past Projects

You can use past projects in two ways

If you have projects that are similar you can use a past project as a template for a new project In theWelcome window select Open a Project Open that project and Save As under a different name Nowyou can open up the renamed project and modify it for the current project

You can draw from several projects in the Similar Projects step First select projects that are similarand click Next Then select tasks from those projects and decide where they would fit into your currentproject

See Also

Opening a project Compatibility with earlier versions

-o-

156

copy Experience In Software Inc 1995 - 2006

Index

- - Change Working Schedule 85

- -prj file format 13

- A -About Linking Tasks (Pro Users) 59About Scheduling Tasks 55About the Gantt Chart 57ACT 120 92 122ACT 6 92 122ACT 7 or later 92 120Activate 14Activating Trial Version 14Add a New Person or Resource 39add a subtask 83add a task 83Add a Task or Subtask 47Add or Change Task Assignments 51Add or Change Task Details 52Add Subtask 63Add Task 63Add URL 49Additional Features in Task Data View (Pro Users) 68Additional Tools in Chart View (Pro Users) 71Adobe PDF 117Assignments tab 80Attachments 49Autolink tasks (Pro Users) 58

- B -Back 10borrow tasks 29

- C -Change Details for Linked Tasks (Pro Users) 81Change Project Start 63Change Task Dates 73Change Task Details 80Change the Appearance of the Task List 43Change the Display of the Schedule 61Change Timescale 63Change Working Schedule 63Chart view 57

157

copy Experience In Software Inc 1995 - 2006

Cloning projects 155Color 63 86Compatibility 13Compatibility with earlier versions 13convert projects 13Coordination 12Create and Print Task Reports 102Credits 153Credits and Trademarks 153critical path 88CSV 96Customer support 20Customer Support 20Customizing Project KickStart

- D -Dashboard 99Data Menu 145Dedication 152Delete 63delete a task 83demote 46dependencies 12 76

- E -Edit Menu 141Edit Notes and Attachments 63Edit or Substitute People 40Edit Task Information 63Email Task Reports 108End User License Agreement 16error 21Error Messages 21export from MindManager 136Export MPX Files 138Export to ACT 6 122Export to ACT 7 and Later 120Export to FastTrack Schedule 134Export to Microsoft Excel 128Export to Microsoft Outlook 123Export to Microsoft PowerPoint 130Export to Microsoft Project 132Export to Microsoft Word 125Export to Milestones Professional 135Export to Mindjet MindManager 136Export to SureTrak Project Manager 133Export to WBS Chart Pro 137

- F -FastTrack Schedule 134File Menu 140Fit to page 111Fit to Smallest Size 111

158

copy Experience In Software Inc 1995 - 2006

- G -Gantt chart 55 57General tab 80Goal 26Goal statements 26Goals 26Goals - Step 1 of 3 26Goals - Step 2 of 3 27Goals - Step 3 of 3 28goals library 26 89Goalsadd 26Goalsdelete 26Goalsedit 26Goalstasks for 27GoToMeeting 150 12

- H -Handouts 111Help Menu 147hyperlink 49

- I -Import ACT 92import contacts and users 92import Outlook contacts 94Import Outlook Contacts via CSV to the People Library (Pro Users) 96ImportCSVToPKSexe 96Indent 46Individual Assignments 102Introduction 7Introduction 7

- K -Knowledge Libraries 90

- L -lag time 81lead time 59 81library 89License Key 14link 59Link lines 59Link tasks 12 65linked tasks 59

- M -major activities 24Make Tasks Overlap (Pro Users) 87Manage a Library 90

159

copy Experience In Software Inc 1995 - 2006

Menu 140Microsoft Excel 128Microsoft Outlook 123Microsoft PowerPoint 130Microsoft Project 132Microsoft Project (95 or 98) 138Microsoft Visio 138Microsoft Word 125Milestone 69 79Milestones Professional 135Mindjet MindManager 136MindManager 136

- N -Name 23Name Your Project 23Navigating Project KickStart 10Next 10Notes and Attachments tab 80

- O -Objectives 26Obstacles 34Obstacles - Step 3 of 3 36Obstacles Library 89Open a Project 151Options 144Outdent 46Outdent and Indent arrows 63Outlook Calendar 123Overview

- P -Page Setup 107 116 100PDF 117people 31People - Step 3 of 3 28People Library 91phase 24phase dates 75Phase Dates Cannot Be Edited 75phases 24Phases - Step 1 of 2 24Phases - Step 2 of 2 25Phases Library 89Phases Goals People amp Obstacles 102PowerPoint presentation 130Pred 68Predecessor 68Predecessor tasks 59predecessors 76Print a Gantt Chart 111Print Dashboard Reports 99Print Preview 105Print Preview a Gantt Chart 115Print Reports 98Print Task Reports 102

160

copy Experience In Software Inc 1995 - 2006

Printer Setup 106Printing to an Adobe PDF file 117prj 13Pro 145Pro Edition 145Product support 20Project 23Project KickStart 3 prj file 151Project KickStart for Windows 7project name 23project start date 73project template 155project title 23promote 46promote and demote tasks 83

- Q -Quick Tour of Working with Linked Tasks (Pro Users) 76

- R -Red vertical line 69Redo 11Register Project KickStart 22Registering Project KickStart 22remove people 38Remove People from a Task 38reorder tasks 83Reorganize Tasks in Task Data View 83Repeat tasks on every page (for handouts) 111Reporting Technical Issues 21resource 31resources 31restore 34return 154risks 34RiskyProject 138

- S -Save As 101Save as HTML 109Save as RTF 110Save Gantt Chart Images 118Schedule 55Send Error Report 21similar projects 29spelling 53starter schedule 55Steps 7subtask 47Subtasks 46Succ 68Successor 68Successor tasks 59successors 76Summary bar 69Support 20SureTrak Project Manager 133

161

copy Experience In Software Inc 1995 - 2006

- T -Task Data view 57task dates 73Task Report 102Taskbar 69Taskbar with percent done 69Tasks 25Tasks in Phases 25Tasks Library 89team 31Technical support 20timescale 84Timescale Menu 146Tools Menu 143Trademark 153trademarks 153Trial 14

- U -unassigning 38Understand Chart View 69Understand Task Data View 66Undo 11UndoRedo Buttons 11uninstallUninstalling 154Unlink tasks 12 65Up and Down arrows 63Use Project KickStart to 8Use the Gantt Chart Toolbar 63Use the Planning Wizard 9Uses 8Using Past Projects 29 155

- V -Version View Menu 142Visio 138

- W -Wall chart 111WBS Chart Pro 137Welcome to Project KickStart 7Whats Due Next Month 99Whats Due Next Week 99Whats Due Today 99Whats New in Project KickStart Pro 5 11Windows Vista 20

162

copy Experience In Software Inc 1995 - 2006

copy Experience In Software 2008w w w projectkickstartcom

  • Table of Contents
  • Start Here Welcome to Project KickStart
    • Introduction
      • Welcome to Project KickStart
      • Use Project KickStart to
      • Use the Planning Wizard
      • Navigating Project KickStart
      • Whats New in Project KickStart Pro 5
      • Whats New in Project KickStart Pro 5 (Pro Users)
      • Compatibility with earlier versions
      • Activating Trial Version
        • Licenses and Support
          • End User License Agreement
          • Customer Support
          • Reporting Technical Issues
          • Register Project KickStart
              • Planning Projects
                • Name Your Project
                • Phases - Step 1 of 2
                • Phases - Step 2 of 2
                • Goals - Step 1 of 3
                • Goals - Step 2 of 2
                • Goals - Step 3 of 3
                • Similar Projects - Step 1 of 2
                • Similar Projects - Step 2 of 2
                • People - Step 1 of 3
                • People - Step 2 of 3
                • People - Step 3 of 3
                • Obstacles - Step 1 of 3
                • Obstacles - Step 2 of 3
                • Obstacles - Step 3 of 3
                  • Assigning People
                    • Assign Tasks to People
                    • Remove People from a Task
                    • Add a New Person or Resource
                    • Edit or Substitute People
                      • Organizing the Project Plan
                        • About Organizing Tasks
                        • Change the Appearance of the Task List
                        • Show or Hide Tasks in the Task List
                        • Move Tasks within the Task List
                        • Outdent and Indent Tasks
                        • Add a Task or Subtask
                        • Edit Tasks
                        • Add Task Notes and Attachments
                        • Add or Change Task Assignments
                        • Add or Change Task Details
                        • Check Spelling
                          • Scheduling Tasks in the Gantt Chart
                            • Scheduling Overview
                              • About Scheduling Tasks
                              • About the Gantt Chart
                              • Autolink tasks (Pro Users)
                              • About Linking Tasks (Pro Users)
                              • Change the Display of the Schedule
                              • Use the Gantt Chart Toolbar
                              • Use the Gantt Chart Toolbar (Pro Users)
                              • Understand Task Data View
                              • Additional Features in Task Data View (Pro Users)
                              • Understand Chart View
                              • Additional Tools in Chart View (Pro Users)
                                • Change Task Dates
                                • Phase Dates Cannot Be Edited
                                • Quick Tour of Working with Linked Tasks (Pro Users)
                                • Link and Unlink Tasks (Pro Users)
                                • Create a Milestone
                                • Change Task Details
                                • Change Details for Linked Tasks (Pro Users)
                                • Reorganize Tasks in Task Data View
                                • Change the Timescale of the Schedule
                                • Specify Working Days
                                • Change the Color of Taskbars
                                • Make Tasks Overlap (Pro Users)
                                • Manage Changes in Your Schedule (Pro Users)
                                  • Managing Libraries
                                    • Use a Library
                                    • Manage a Library
                                    • Manage the People Library
                                    • Import ACT Contacts and Users to the People Library
                                    • Import Outlook Contacts to the People Library
                                    • Import Outlook Contacts via CSV to the People Library (Pro Users)
                                      • Printing Reports
                                        • Printing Dashboards
                                          • Print Reports
                                          • Print Dashboard Reports
                                          • Page Setup
                                          • Save As
                                            • Printing Task Reports
                                              • Print Task Reports
                                              • Print Preview
                                              • Printer Setup
                                              • Page Setup
                                              • Email Task Reports
                                              • Save As HTML
                                              • Save As RTF
                                                • Printing Gantt Chart Reports
                                                  • Print a Gantt Chart
                                                  • Print Preview a Gantt Chart
                                                  • Page Setup
                                                  • Printing to an Adobe PDF file
                                                  • Save Gantt Chart Images
                                                      • Export Project Data
                                                        • Export to ACT
                                                          • Export to ACT 7 and Later
                                                          • Export to ACT 6
                                                            • Export to Microsoft Outlook
                                                            • Export to Microsoft Word
                                                            • Export to Word Processors (Other than Word)
                                                            • Export to Microsoft Excel
                                                            • Export to Microsoft PowerPoint
                                                            • Export to Microsoft Project
                                                            • Export to SureTrak Project Manager
                                                            • Export to FastTrack Schedule
                                                            • Export to Milestones Professional
                                                            • Export to Mindjet MindManager
                                                            • Export to WBS Chart Pro
                                                            • Export MPX Files
                                                              • Reference
                                                                • Menus
                                                                  • File Menu
                                                                  • Edit Menu
                                                                  • View Menu
                                                                  • Tools Menu
                                                                  • Options
                                                                  • Data Menu
                                                                  • Timescale Menu
                                                                  • Help Menu
                                                                    • Shortcuts
                                                                    • Share Project KickStart data
                                                                    • Open a Project
                                                                    • Dedication
                                                                    • Credits and Trademarks
                                                                    • Uninstalling the software
                                                                    • Using Past Projects
Page 9: Project KickStart Help File in PDF format

9

copy Experience In Software Inc 1995 - 2006

Use the Planning Wizard

Project KickStart uses a Planning Wizard that guides you through eight steps for planning your project Tostep through the wizard click each icon on the Steps bar (on the left side of the Project KickStart window) inorder On each window t ips and advice are always available by clicking the Advisor button You click theNext button to continue

Name Each project has a name To start planning your project give it ashort descriptive name

Phases Consider how your project will break down into major activitiesor phases Start by listing your phases and then list the tasks thatbelong in each phase

Goals Goals are what you hope to accomplish in your project Enter orselect the goals for your project Then you can list any new tasks toachieve each goal

Similar Projects often have tasks in common In this step you canborrow tasks from past projects to help you plan this project Then youcan add any new tasks from a similar project to the phases of yourcurrent project

People List the people groups or things that might provide resourcesfor your project including yourself Then identify any new tasks thesepeople might do or suggest for your project

Obstacles Each project has obstacles you can overcome if youanticipate them List the obstacles you will face in your project and thenidentify any new tasks needed to avoid the obstacles

Assign Assign tasks to people and other resources

Tasks Change the order of your tasks add and delete tasks andcreate subtasks You can also edit tasks change assignments and addnotes

Schedule Schedule the tasks in your project To make schedulingeasier new projects open with a starter schedule beginning todaywhich you can customize to fit your project

-o-

10

copy Experience In Software Inc 1995 - 2006

Navigating Project KickStart

When you use the Planning Wizard you work with a step window similar to the following illustration

Steps bar Click a step button to perform a step in the Planning Wizard The selected button shows yourcurrent step

Name of your project Shows the name entered in the Name step

Menu bar Select options from the menu bar to work with your projects

Toolbar Click buttons to perform common tasks such as saving your project

Step instructions Indicate how to perform the current step

Library button Click to open a library for the current step For example click the Goals Library button toopen a library listing typical project goals

Back and Next buttons Click a button to return to the previous step or continue to the next step in thePlanning Wizard

Advisor button Click to see instructions tips and notes for completing the current step

-o-

11

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5

The following table outlines whatrsquos new in Project KickStart Pro 5

If you own a previous version of Project KickStart yoursquoll notice the new Pro version has a new look and feelAs you begin to check it out yoursquoll soon discover Project KickStart Version 5 is a lot more powerful thanprevious versions and comes with some great new features

FEATURE DESCRIPTION IMPROVED

NEW

Dashboard Reporting

Quickly assess what is due TodayNext Week or Next Month

X

Import Contacts Import from a comma separatedvalue (CSV) file

X

Templates Use as is or customize X

Gantt Chart Greater stability and functionality X

User Interface Contemporary look and colorscheme

X

Preferences Customize look and feel andprogram defaults

X

Productivity Pack Project template Word docs fornewbies

X

Exports Improved Outlook MindManager and ACTimproved data exchange

X

-o-

12

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5 (Pro Users)

This feature is available only in Project KickStart Professional

The following table outlines whatrsquos new in Project KickStart Pro 5

FEATURE DESCRIPTION IMPROVED NEW

Gantt Chart Task dependencies in Gantt chart X

Link tasks Show task dependencies X

Unlink tasks Remove task dependencies X

Add predecessors Add task predecessors X

Add successors Add task successors X

Project Coordination Link to GoToMeeting for onlinemeetings on projects

X

Project KickStart Pro now includes dependencies on the Gantt chart This sophisticated scheduling andproject management tool is new to Project KickStart Pro and is designed to make complex projectscheduling easy and straightforward

Use dependencies to handle scheduling demands delays and surprises without modifying every task inyour project Dependencies let you make adjustments as events change giving you a more robust scheduleand the opportunity to conduct what-if analysis

Suppose you are managing a landscaping project involving subcontractors and dozens of tasks One ofyour first tasks is to pave a path with flagstones but the shipment of flagstones is two days late Usingdependencies you can delay the path-paving task in a couple of clicks and Project KickStart Proautomatically updates the schedule for the remaining tasks

Although dependencies meet your advanced scheduling needs the Project KickStart Pro approach todependencies keeps them as simple as possible If you want to link a couple of tasks which are dependenton one another you can simply highlight the tasks and click the link icon

If you select the option of Autolinking tasks then when you display the Gantt chart the first time all tasksare pre-linked allowing you to adjust durations schedules of individual tasks and time between taskswhich is called Lead Time in Project KickStart Pro

Unlike other project management programs such as Microsoft Project Project KickStart Pro does notburden you with complicated error messages and various types of dependencies It provides only one typeof dependency finish-to-start which is the most common type This means you can fine-tune your scheduleas soon as you open the Gantt chartmdashwithout having to learn technical terms or advanced projectmanagement techniques

The Project Coordination functionality that we are providing is through GoToMeeting and is a chargedservice

Note

These features are in addition to those listed on the Whatrsquos New in Project KickStart 5 page

-o-

13

copy Experience In Software Inc 1995 - 2006

Compatibility with earlier versions

Project KickStart 5 can open and save projects in Project KickStart 4 prx file format (Same as ProjectKickStart 5)

Project KickStart 5 can open and convert projects saved in Project KickStart 3 prj file format You need tohave a licensed copy of Project KickStart 3 on your system to make the conversion

To open a prj project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click prj file type3 Navigate to the folder that contains the prj file Generally prj files are stored in cprogram filesProject

KickStart 34 Double-click the name of the file

Tips

The tasks in the converted Project KickStart 5 file will have the same start and finish dates and samedurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way (ie as working days) To have weekends as non working days click the Change WorkingSchedule button on the Gantt chart toolbar and mark weekends as non working

Note

Project KickStart 5 does not open and convert prj files from Project KickStart 1 or 2

-o-

14

copy Experience In Software Inc 1995 - 2006

Activating trial version

You may have obtained a FREE 20-day trial version of Project KickStart 5 from our website or from areseller

To convert your Trial Version to a Full Version youll need to purchase a License Key and to activate thesoftware

To activate Project KickStart 5 trial1 Start the Project KickStart trial

2 If you have not purchased your License Key yet click the Buy button to purchase online3 If you have purchased a License Key click the Activate button and copy and paste the License Key

that you received when you purchased Project KickStart as well as your name and email

15

copy Experience In Software Inc 1995 - 2006

4 You must be connected to the Internet and you must tell your Firewall to allow communication forPKS5Kickstartexe

Tip

Your License Key allows 2 activations per user One is for your primary computer and one is for asecond computer you use such as your laptop or home computer

-o-

16

copy Experience In Software Inc 1995 - 2006

Licenses and Support

End User License Agreement

EXPERIENCE IN SOFTWARE INC END USER LICENSE AGREEMENT AND WARRANTYDISCLAIMER

PROJECT KICKSTARTtrade STANDARD 5 AND PRO 5 EDITIONS

NOTICE This is a legally binding contract between you the end user and EXPERIENCE IN SOFTWAREINC

EXPERIENCE IN SOFTWARE INC (EIS or LICENSOR) LICENSES THE ENCLOSED SOFTWARETO YOU (USER or LICENSEE) ONLY UPON THE CONDITION THAT YOU ACCEPT ALL OF THETERMS CONTAINED IN THIS LICENSE AGREEMENT PLEASE READ THE TERMS CAREFULLY BYOPENING THIS PACKAGE BREAKING THE SEAL CLICKING ON THE ldquoAGREErdquo OR ldquoYESrdquo BUTTONOR OTHERWISE INDICATING ASSENT ELECTRONICALLY OR LOADING THE SOFTWARE YOUAGREE TO THE TERMS AND CONDITIONS OF THIS AGREEMENT IF YOU DO NOT AGREE TOTHESE TERMS AND CONDITIONS CLICK ON THE ldquoI DO NOT AGREErdquo ldquoNOrdquo BUTTON OR MAKE NOFURTHER USE OF THE SOFTWARE IF YOU DO NOT AGREE TO THESE TERMS THEN EIS ISUN-WILLING TO LICENSE THE SOFTWARE TO YOU IN WHICH EVENT YOU SHOULD RETURN THEFULL PURCHASED PRODUCT WITH PROOF OF PURCHASE TO LICENSOR OR THE DEALER FROMWHOM IT WAS ACQUIRED WITHIN 15 DAYS OF PURCHASE AND YOUR MONEY WILL BEREFUNDED

LICENSE AND WARRANTY

The software that accompanies this license (Software) is the property of EIS and is protected by copyrightand other intellectual property law Although EIS at all times owns the Software you will have certain rightsto use the Software after your acceptance of this license Except as may be modified by an addendumwhich may accompany or be added to this license your rights and obligations with respect to the use of thisSoftware are as follows

You may

(i) install and use one copy of the specified edition of Software and documentation on a single computerand only by one user (ldquoPrimary Userrdquo) If you have purchased multiple licenses for the Software asindicated as Quantity or Number of Licenses on the Invoice or electronic confirmation issued by EIS orits Resellers then at any time you may have as many copies of the Software in use as you have licenses The Software is ldquoin userdquo on a computer when it is loaded into the temporary memory (ie RAM) or installedinto the permanent memory (eg hard disk CD-ROM or other storage device) of that computer

(ii) install and use a second copy of the Software on a second computer for the limited and exclusive use ofthe Primary User

(iii) use the Software on a network provided that Licensee has a licensed copy of the Software for eachnamed user that can access the Software over that network

(iv) make one copy of the Software for archival purposes or copy the Software onto the hard disk of yourcomputer and retain the original for archival purposes

(v) after written notice to EIS transfer the Software on a permanent basis to another person or entityprovided that you retain no copies of the Software and the transferee agrees to the terms of this agreement

You may not

(i) rent lease copy distribute license or otherwise transfer the Software or its documentation to any otherparty Licensee may make a reasonable number of back-up copies for archival purposes only TheSoftware contains copyrighted material trade secrets and other proprietary material If Licensee has theright to duplicate the Software for multiple Users then Licensee must reproduce on all such copies of theSoftware the copyright notices and any other proprietary legends that were on the original copy of theSoftware or

(ii) decompile reverse engineer disassemble translate make any attempt to discover the source code ofthe Software or otherwise reduce the Software to a human perceivable form or modify network or create

17

copy Experience In Software Inc 1995 - 2006

derivative works based upon the Software or the documentation in whole or in part nor permit any otherparty to do so

Notwithstanding anything herein if the Software is lawfully acquired outside of the United States within ajurisdiction which is a member of the European Union subject to the EEC Council Directive 91250EEC ofMay 14 1991 Licensee agrees that within that jurisdiction it shall not and shall not allow any party onLicensees behalf to attempt to reverse engineer or decompile the Software into another computerlanguage except as expressly and specifically provided in the EEC Council Directive 91250EEC of May14 1991 Any and all information obtained during such lawful reverse engineering andor decompilingactivities including but not limited to the organization logic algorithms and processes of the Softwareshall be deemed to be the confidential and proprietary information of EIS

Licensee shall not make copies of the copyrighted Software documentation without the prior writtenpermission of EIS provided that for electronic transactions Licensee may make one (1) hard copy of suchdocumentation for each User

Intellectual Property and Duplication of Software

The Software contains copyrighted material trade secrets and other proprietary material If Licensee hasthe right to duplicate the Software for multiple Users then Licensee must reproduce on all such copies ofthe Software the copyright notices and any other proprietary legends that were on the original copy of theSoftware

Upgrades

To use a Product identified as an upgrade you must first be licensed for the product identified by EIS aseligible for the upgrade After upgrading you may no longer transfer the product that formed the basis foryour upgrade eligibility to another person or entity

Technical Support

Licensee must register the Software in order to be eligible for free technical support (including installationand registration of the product) during the first 90 days after purchase

Thirty Day Money Back Guarantee

If you are the original Licensee of this copy of the Software and are dissatisfied with it for any reason youmay return the complete product together with your receipt to EIS or an authorized dealer postageprepaid for a full refund at any time during the thirty-day period following the delivery to you of thePurchased Software

Export Law Assurances

You are responsible for complying with all trade regulations and laws both foreign and domestic Youacknowledge that none of the Software or underlying information or technology may be downloaded orotherwise exported or re-exported (i) into Afghanistan (Taliban-controlled areas) Cuba Iran Iraq LibyaNorth Korea Serbia (except Kosovo) Sudan and Syria or any other country subject to a US embargo or(ii) to anyone on the US Treasury Departments list of Specially Designated Nationals or the USCommerce Departments Denied Parties List or Entity List By using the Software you are agreeing to theforegoing and are representing and warranting that (i) no US federal agency has suspended revoked ordenied you export privileges (ii) you are not located in or under the control of a national or resident of anysuch country or on any such list and (iii) you will not export or re-export the Software to any prohibitedcounty or to any prohibited person entity or end-user as specified by US export controls as defined byEAR 15 CFR Parts 730-774 and BXA (httpwwwbxadocgov)

Data Collection and Privacy Policy

You acknowledge and agree that EIS may collect and retain information about you such as your nameaddress and e-mail address You also understand that EIS may employ other companies to performfunctions on our behalf such as fulfilling orders delivering packages sending postal mail and e-mailproviding marketing assistance and processing credit card payments These companies may have accessto personal information needed to perform their functions and may not use such information for otherpurposes By assenting to this agreement you agree that you have read and understand our Privacy PolicyFor more detailed information httpwwwprojectkickstartcomhtmlprivacy_statementhtm

Termination

This License is effective until terminated Licensee may terminate this License at any time by destroying allcopies of the Software and its documentation This License will terminate immediately without notice from

18

copy Experience In Software Inc 1995 - 2006

EIS if Licensee fails to comply with any provision of this License Upon termination Licensee must destroyall copies of the Software and its documentation and cease and desist from any further use of the Software

Limited Warranty

EIS warrants that the media on which the Software is distributed will be free from defects and that theSoftware shall perform substantially as described in its documentation for a period of sixty (60) days frompurchase Your sole remedy in the event of a breach of this warranty will be that EIS will replace anydefective media returned to EIS within the warranty period EIS does not warrant that the Software willmeet your requirements or that operation of the Software will be uninterrupted or that the Software will beerror-free

THE ABOVE WARRANTY IS EXCLUSIVE AND IN LIEU OF ALL OTHER WARRANTIES WHETHEREXPRESS OR IMPLIED INCLUDING THE IMPLIED WARRANTIES OF MERCHANTABILITY FITNESSFOR A PARTICULAR PURPOSE AND NONINFRINGEMENT OF INTELLECTUAL PROPERTY RIGHTSTHIS WARRANTY GIVES YOU SPECIFIC LEGAL RIGHTS YOU MAY HAVE OTHER RIGHTS WHICHVARY FROM STATE TO STATE AND COUNTRY TO COUNTRY

Disclaimer of Damages

REGARDLESS OF WHETHER ANY REMEDY SET FORTH HEREIN FAILS OF ITS ESSENTIALPURPOSE IN NO EVENT WILL EIS OR ITS RESELLERS BE LIABLE TO YOU FOR ANY SPECIALCONSEQUENTIAL INDIRECT OR SIMILAR DAMAGES INCLUDING BUT NOT LIMITED TO ANY LOSTPROFITS OR LOST DATA ARISING OUT OF THE USE OR INABILITY TO USE THE SOFTWARE EVENIF EIS HAS BEEN ADVISED OF THE POSSIBILTIY OF SUCH DAMAGES SOME STATES DO NOTALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FOR INCIDENTAL OR CONSEQUENTIALDAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAY NOT APPLY TO YOU IN NO CASESHALL EISS ITrsquoS RESELLERrsquoS LIABILITY EXCEED THE PURCHASE PRICE FOR THE SOFTWARE

SOME STATES AND COUNTRIES INCLUDING MEMBER COUNTRIES OF THE EUROPEANECONOMIC AREA DO NOT ALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FORINCIDENTAL OR CONSEQUENTIAL DAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAYNOT APPLY TO YOU

The disclaimers and limitations set forth above will apply regardless of whether you accept the Software

US Government Restricted Rights

DISTRIBUTION TO THE US GOVERNMENT This Software is commercial software developedexclusively at private expense This Software and the documentation are provided with RESTRICTEDRIGHTS applicable to private and public licenses alike Use duplication or disclosure by civilian agenciesof the US Government shall be in accordance with the Commercial Computer Software-Restricted Rightsclause at FAR 52227-19 Use duplication or disclosure by Department of Defense agencies is subjectsolely to the terms of this software licensing agreement pursuant to DFARS 2277202Contractormanufacturer of the Software is EXPERIENCE IN SOFTWARE INC 2029 Durant AveBerkeley CA 94704 USA

General

This Agreement shall be governed by the laws of the State of California without giving effect to principles ofconflict of laws You hereby consent to the exclusive jurisdiction and venue of the state courts sitting in SanFrancisco County California or the federal courts in the Northern District of California to resolve anydisputes arising under this Agreement This Agreement contains the complete understanding between theparties with respect to the subject matter hereof and supersedes all prior or contemporaneous Agreementsor understandings whether oral or written You agree that any varying or additional terms contained in anypurchase order or other written notification or document issued by you in relation to the Software licensedhereunder shall be of no effect No provision hereof shall be deemed waived or modified except in writing No EIS dealer agent or employee is authorized to make any amendment to this Agreement

The intellectual property protections the disclaimers of warranties and the limitation of damages shallsurvive termination The failure or delay of EIS to exercise any of its rights under this Agreement or uponany breach of this Agreement shall not be deemed a waiver of those rights or of the breach If any provisionof this Agreement is held invalid the remainder of this Agreement will remain in full force and effect

Should you have any questions concerning this Agreement or if you desire to contact EIS for any reasonplease write to EXPERIENCE IN SOFTWARE INC 2029 Durant Ave Berkeley CA 94704 USA

-o-

19

copy Experience In Software Inc 1995 - 2006

20

copy Experience In Software Inc 1995 - 2006

Customer Support

When you need help in solving a problem with the software Experience In Software is available to assistyou First check this help file for information on the part of the program you are having a problem withAlso take a look at the Web site for late-breaking technical support information wwwprojectkickstartcomsupporttechnical_supportcfm If you are a regustered user you can obtain support in the following ways

Web httpwwwprojectkickstartcomsupportemail_supportcfm E-mail supportprojectkickstartcom

Hours 900 am to 500 pm Pacific time Monday - Friday

To make the support process more efficient have the following information ready for the support staff

Provide your name phone number and email address

Describe the problem including any error messages

If reporting a potential bug describe what you did immediately before seeing the bug

Provide the Project KickStart version number and Build Date (Click Help on the menu bar and thenclick About Project KickStart)

Identify the version of Windows (Windows Vista etc) you are using

Notes

Our policy is to respond to support email within two business days If you have not received aresponse please double check that spam filters are blocking our messages to you If you maintain anincoming whitelist please allow all messages from the projectkickstartcom domain

Support is available in English only If you purchased a translated version please contact your localreseller for help in other languages

See Also

Reporting Technical Issues

-o-

21

copy Experience In Software Inc 1995 - 2006

Reporting Technical Issues

If Project KickStart 5 detects an error it will write a log of technical issues and then create a temporarymenu to the right of the Help menu which says Send Log to Technical Support You should immediatelyclick the menu and then click Yes to send the error log to us

Please fill in your email address so that we can get back to you with any questions about what caused theerror

Tip

If you have an Internet Security Program such as Norton Internet Security please allowPKS5Kickstartexe to communicate with the Internet to report the error

-o-

22

copy Experience In Software Inc 1995 - 2006

Register Project KickStart

To print this page click the Print button on the Help window toolbar

Register Project KickStart 5 for technical support upgrade information and software discounts You canregister by completing printing and then sending or faxing this form to Experience In Software You canalso register online at httpwwwprojectkickstartcomsupportregiscfm

Name _______________________________________________________

Title _______________________________________________________

Company _______________________________________________________

Address _______________________________________________________

CityStateZip ______________________________________________________

Country _______________________________________________________

Day Phone _______________________________________________________

Fax _______________________________________________________

E-mail _______________________________________________________

Purchased from __ Experience In Software __ Other ____________________

Number of people in company _ 1 to 25 _ 26 to 100 _ 101 to 1000 _ Over 1000

Which industry do you work in ______________________________________

Interested in a project management workshop for your company __ Yes __ No

Comments _______________________________________________________

_________________________________________________________________

_________________________________________________________________

Experience In Software 2029 Durant Ave Berkeley CA 94704

Send or FAX to (510) 644-3823

-o-

23

copy Experience In Software Inc 1995 - 2006

Planning Projects

Name Your Project

Before you start thinking about the tasks in your project yoursquoll want to give your project an appropriate titleIf you open an existing project you might want to edit or change the name of your project

To name your project1 In the Type a name for your project text box enter a name2 Click the Next button

Tips

You can enter up to 58 characters and more than one

Use short descriptive project names such as ldquoCompany Web Siterdquo

Avoid vague project names such as ldquoDatabase Projectrdquo or ldquoCDP-7rdquo especially if you plan to circulatereports to others

Enter your project title using uppercase letters if you want the title to stand out in reports

One way to reuse your projects is to open an existing project and then change its name in this stepAfter saving the project with a different name you can modify details to customize the project

See Also

Use the Planning Wizard

-o-

24

copy Experience In Software Inc 1995 - 2006

Phases - Step 1 of 2

After naming your project the next step in the Planning Wizard is to identify the major activities in yourproject Using phases helps organize tasks so that an obviously early task such as ldquoOrganize materialsrdquoappears before a later task such as ldquoReview final draftrdquo

To enter phases1 Type each phase one per line

OrClick the Phases Library button The Phases Library contains typical phases that many organizationsuse in the early middle and late stages of their projects Drag an entry from the Phases Library to thelist and then click the OK button to close the Phases Library

2 To insert a phase in the middle of the phases list click where you want to insert a new blank line andthen press the Insert keyTo edit the phase text double-click the phase

Tips

Start each phase name with an action verb as in ldquoBuild systemrdquo or ldquoWrite reportrdquo

Use actions that have clearly defined beginnings middles and ends For example you can scheduletasks like ldquoTest prototyperdquo more easily than tasks like ldquoPurchase high-quality partsrdquo

Note

Youll have the opportunity to edit phases later in the Tasks step For now continue planning thephases in your project

See Also

Use the Planning Wizard

Use a Library

Move Tasks within the Task List

-o-

25

copy Experience In Software Inc 1995 - 2006

Phases - Step 2 of 2

For each phase list all of the tasks that could be performed during that phase You can refine and organizethe tasks later in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each phase1 Type the tasks associated with the phase displayed in the Tasks for phase text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next phase in your project click the Next button If you prefer to work out oforder click the Tasks for phase list arrow and then click the phase you want

3 When you are finished entering tasks for the last phase in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

26

copy Experience In Software Inc 1995 - 2006

Goals - Step 1 of 3

Enter the goals for your project the objectives you hope to accomplish Then you can brainstorm anyadditional tasks that will help you meet these goals

To enter goals1 Type each goal one per line

OrThe Goals Library contains typical sample goals that you can customize Drag an entry from the GoalsLibrary to the list and then click the OK button to close the Goals Library

2 To insert a goal in the middle of the goals list click where you want to insert a new blank line and thenpress the Insert keyTo edit the goal text double-click the goal

3 Click the Next button

Tips

List goals that apply to the entire project such as Develop a high-quality system A goal such as Getthe contract signed applies only to an early phase

Write goals as actions you can measure For example Complete the project for $75000 or less ismore concrete and specific than Complete the project within budget Numbers make goal statementsreal

If youre not sure how to measure a goal use a range as in About 15 - 25 people will use the results ofthe project

See Also

Use the Planning Wizard

Use a Library

-o-

27

copy Experience In Software Inc 1995 - 2006

Goals - Step 2 of 3

For each goal list any new tasks needed to accomplish that goal You can refine and organize the taskslater in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each goal1 Type the tasks for accomplishing the goal displayed in the For the goal text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next goal in your project click the Next button If you prefer to work out of orderclick the For the goal list arrow and then click the goal you want

3 When you are finished entering tasks for the last goal in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

28

copy Experience In Software Inc 1995 - 2006

Goals - Step 3 of 3

After you identify new tasks for your project assign each new task to an appropriate phase

To assign new tasks to phases1 Click a task in the New tasks to achieve goals list (on the left)2 Click one or more phases in the Assign them to Phases list (on the right) to which the task belongs A

checkmark appears next to tasks youve assigned

If a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Note

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

29

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 1 of 2

Projects often have tasks in common The Similar Projects step makes it easy for you to borrow tasks fromother projects and add them to your current project

By default this step shows the Project KickStart (PRX) projects stored in the same folder as the currentproject including sample projects and those you already created

To select similar projects1 Review the projects in the list To sort the project names alphabetically click the Project Name header

Click the Project Name header again to sort the names in reverse order2 Click one or more projects in the list that contain tasks you want to use in the current project A

checkmark appears next to the projects you selected3 To list projects stored in a different folder on your system click the Browse button and then navigate to

the folder you want4 Click the Next button

If no projects seem related to your current project skip this step for now

Tips

The Similar Projects step becomes more helpful the more you use Project KickStart Every time yousave a project it becomes available for future use

Many projects share the same phases and tasks such as those for setting up a contract or purchasingequipment You can use Project KickStart to create these mini-projects or templates and then importtheir tasks into a new project during the Similar Projects step

-o-

30

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 2 of 2

After you select one or more projects containing tasks you might want to use assign those borrowed tasksto a phase in this project

To assign borrowed tasks to phases1 Click a task in the list on the left If a task includes subtasks click the plus icon to expand the list Click

the minus icon if you want to hide the subtasks To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more phases in the Assign tasks to phase(s) of your project list (on the right) to whichthe task belongs A checkmark appears next to tasks youve assigned

3 To assign one or more tasks to a new phase select the tasks click ltNew Phasegt in the Assign tasksto Phases of your project list and then type a name for the new phase

4 To select tasks from another project you selected as similar click the Tasks from Similar Projects listarrow click the project you want and then assign the tasks to phases

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also Edit Tasks

-o-

31

copy Experience In Software Inc 1995 - 2006

People - Step 1 of 3

Enter the names or descriptions of the people involved in your project Include key decision makers suchas executives or customers who must approve or consult with you about the project These are yourprojects resources In the next People step youll identify new tasks associated with these resources

To enter people1 Type each name or description one per line

OrIf you have stored information about people and other resources in the People Library click the PeopleLibrary button drag an entry from the library to the list and then click the OK button to close thePeople Library

2 To edit the people text double-click the name or description3 Click the Next button

Tips

Be consistent with the resource names in your projects For instance avoid using Richard in oneproject and Dick in another project when referring to the same person

Include names for people teams (such as Quality control team) departments (such as Manufacturing)companies (such as Acme Widgets Corp) or even equipment (such as wheat thrasher)

Note

Add people and other resource information to the People Library so that you can quickly drag resourcesfrom the library to any project You can even import people from your Outlook and ACT address books

See Also

Manage the People Library

Import ACT Contacts and Users to the People Library

-o-

32

copy Experience In Software Inc 1995 - 2006

People - Step 2 of 3

Now that you have defined the people needed to complete your project list any new tasks that eachresource might suggest or require

To enter new tasks for each person1 Type the new tasks associated with the person displayed in the Tasks For text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next person in your project click the Next button If you prefer to work out oforder click the Tasks For list arrow and then click the person you want

3 When you are finished entering new tasks for the last person in your project click the Next button tocontinue in the Planning Wizard

Tips

This step provides a good opportunity to get input from your resources directly and make sure theproject plan reflects the views of everyone on the team

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo Write the tasks roughly in the order that you will complete them You can reorganize the tasks later in

the Tasks step

Note

You assign people to tasks in the Assign Tasks and Schedule steps

See Also

Use a Library

Move Tasks within the Task List

Assign Tasks to People

-o-

33

copy Experience In Software Inc 1995 - 2006

People - Step 3 of 3

After you identify new tasks associated with the people in your project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by people list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

34

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 1 of 3

Every project has obstacles and risks that can affect its success List the major obstacles you face incompleting your project Then you can brainstorm any additional tasks that can help you overcome orminimize these problems

To enter obstacles1 Type each obstacle one per line

OrThe Obstacles Library contains typical sample obstacles that you can customize Drag an entry fromthe Obstacles Library to the list and then click the OK button to close the Obstacles Library

2 To insert an obstacle in the middle of the obstacles list click where you want to insert a new blank lineand then press the Insert key

3 To edit the obstacle text double-click the obstacle4 Click the Next button

Tips

Be creative when thinking of obstacles Highly imaginative obstacles can suggest realistic tasks Forexample Project manager kidnapped by aliens can lead to Project manager out of town forconference In Obstacles step 2 of 3 you can add the realistic activities as tasks You can delete theunrealistic obstacles later by returning to Obstacles step 1 of 3

Avoid listing too many obstacles even if they are realistic Hard core pessimists find it hard to getanything done

Edit and update the Obstacles Library so that you can quickly drag obstacles from the library to anyproject in your organization

See Also

Use a Library

-o-

35

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 2 of 3

After identifying the obstacles to completing your project determine how you can avoid these stumblingblocks List any new tasks you need to overcome or avoid each obstacle In this way you are developing acontingency plan for your project

To enter new tasks for each obstacle1 Type the new tasks associated with the obstacle displayed in the Obstacle text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next obstacle in your project click the Next button If you prefer to work outof order click the Obstacle list arrow and then click the obstacle you want

3 When you are finished entering new tasks for the last obstacle in your project click the Next button tocontinue in the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

You can reorganize the tasks and add notes later in the Tasks step

See Also

Use a Library

Move Tasks within the Task List

Add Task Notes and Attachments

-o-

36

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 3 of 3

After you identify new tasks for overcoming the obstacles to completing project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by obstacles list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

3 Click the Next button

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

37

copy Experience In Software Inc 1995 - 2006

Assigning People

Assign Tasks to People

After youve identified people working on your project you can assign tasks to each person or otherresource

To assign tasks to people1 Click a phase or task in the For each phase or tasks list (on the left)

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more people in the Assign some people list (on the right) who will perform the task Acheckmark appears next to tasks youve assigned

3 To assign a selected task to all of the people in your project click the All button4 To assign one or more tasks to a new person select the tasks click ltNew Persongt in the Assign

some people list and then type a name for the new person

To unassign a task

To unassign a task click the task and then click the highlighted person from which you want to removethe task You can assign that task to a different person if necessary You can also click the All buttonto remove a task from all of its assignments at the same time

Tip

Some users like to skip to the Tasks step before performing the Assign step That way they can edittheir list of tasks before assigning people and resources This helps them focus the project and givesthem a clearer idea of what must be done before committing resources

Notes

You can also assign tasks to people in the Tasks step and the Schedule step

You can assign tasks to non-personnel resources such as equipment (a CAD system or back hoe)facilities (a classroom or hotel) services (lab work or insurance) or materials (lumber or officesupplies) just as you assign tasks to people Click ltNew Persongt to add a new resource to the list

See Also

Remove People from a Task

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

38

copy Experience In Software Inc 1995 - 2006

Remove People from a Task

After assigning tasks you might need to remove people from a task or unassign them

To remove people from a task (unassigning)1 Click a phase or task in the For each phase or tasks list (on the left)

The people assigned to that phase or task are highlighted in the Assign some people list (on theright)

2 Click a highlighted person to remove or unassign that person from the taskWhen the person is no longer highlighted they are not assigned to the selected task

See Also

Assign Tasks to People

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

39

copy Experience In Software Inc 1995 - 2006

Add a New Person or Resource

If you realize that you want to assign some tasks to a person not included in the Assign some people listyou can add that person and assign tasks in the same step You can also add non-personnel resourcessuch as such as equipment (a CAD system or back hoe) facilities (a classroom or hotel) services (lab workor insurance) or materials (lumber or office supplies)

To add a new person or resource1 Select one or more phases or tasks in the For each phase or tasks list (on the left) 2 Click ltNew Persongt in the Assign some people list and then type a name for the new person or

resourceThis adds the new person or resource to the list and assigns the selected tasks to them

See Also

Assign Tasks to People

Remove People from a Task

Edit or Substitute People

Add or Change Task Assignments

-o-

40

copy Experience In Software Inc 1995 - 2006

Edit or Substitute People

If the people or resources in your project change you can replace them or edit their names anddescriptions

To edit or substitute people1 Click the People icon

You return to People step 1 of 32 In the list of people defined for the project double-click the person you want to edit or replace or click

the name and press F23 Edit the name or description of the person

When you return to the Assign step the name of the person appears as you changed it

See Also

Assign Tasks to People

Remove People from a Task

Add a New Person or Resource

Add or Change Task Assignments

-o-

41

copy Experience In Software Inc 1995 - 2006

Organizing the Project Plan

About Organizing Tasks

In the Tasks step you work with an outline of your project plan Here you can easily edit and reorganizetasks spell check and even add notes and attachmentsClick the following illustration to see tips for using this window

Edit the Task List to Consolidate and delete tasks Add subtasks Add or change task assignments Add follow-up notes to tasks Add or change attachments Review the order of the tasks in each phase and move tasks up or down so that they progress

sequentially Review task descriptions to make sure they are clear and that all the team members will understand

them Convert vague tasks such as reminders and open issues to task notes

Notes

Some users like to revise their Task List before they assign resources You can go to the Task List atany time while you are using Project KickStart

Each project created with Project KickStart can contain up to 1000 tasks

See Also

Change the Appearance of the Task List

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

Add Task Notes and Attachments

Add or Change Task Assignments

Add or Change Task Details

-o-

42

copy Experience In Software Inc 1995 - 2006

43

copy Experience In Software Inc 1995 - 2006

Change the Appearance of the Task List

You can change the appearance of the Task List so you can work with it more effectively

To add a column

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task ListBy default the Task List shows the Task Name Assignments and Notes columns You can also showCost and Done columns

To hide a column

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

To move a column

Drag a column heading to a new position in the Task List

To change the column width

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Show or Hide Tasks in the Task List

-o-

44

copy Experience In Software Inc 1995 - 2006

Show or Hide Tasks in the Task List

To hide tasks or subtasks

To hide the subtasks for a task click the minus icon next to the task

To hide all the tasks in the Task List and show only phases click all the minus icons next to thephases

To show tasks or subtasks

To show the subtasks for a task click the plus icon next to the task

To show the tasks for a phase click the plus icon next to the phase

See Also

Change the Appearance of the Task List

-o-

45

copy Experience In Software Inc 1995 - 2006

Move Tasks within the Task List

In the Tasks step you can reorganize the tasks in your project so that they better represent the work youand your team plan to do In particular you should review the order of the tasks in each phase and move tasks up and down so thattasks follow in a sequential order Use the Up and Down Arrow buttons to move the tasks

To reorder tasks1 Click a task or phase to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youmove must be next to each other

2 Click the Up Arrow button to move a task up one rowOrClick the Down Arrow button to move a task down one row

Note

When you move a bolded phase you move the phase and all of its tasks at the same time

See Also

Outdent and Indent Tasks

-o-

46

copy Experience In Software Inc 1995 - 2006

Outdent and Indent Tasks

Subtasks are smaller parts of tasks Use subtasks when you need to break tasks down into moremanageable parts In the Task List you can turn a task into a subtask by indenting it You can also add anew subtask to the Task ListIf your Task List contains subtasks you can turn a subtask into a task by outdenting itUse the Outdent and Indent buttons to promote (outdent) and demote (indent) tasks

To promote and demote tasks1 Click a phase task or subtask to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youpromote or demote must be next to each other

2 Click the Outdent button to promote the selected tasksOrClick the Indent button to demote the selected tasksYou can also right-click an item in the Task List and then click Outdent or Indent on the shortcut menu

Tips

When you promote (outdent) a task it becomes a phase and its subtasks become tasks When youpromote a subtask it becomes a task

When you demote (indent) a phase it becomes a task and its tasks become subtasks When youdemote a task it becomes a subtask

Notes

You can have up to 10 levels of subtasks in your project

Use Task Notes instead of subtasks for task comments or additions that are not actually work items

See Also

Move Tasks with the Task List

Add a Task or Subtask

-o-

47

copy Experience In Software Inc 1995 - 2006

Add a Task or Subtask

If you realize you want to add another task to the Task List use the Add Task button A subtask is a smaller part of a task Use subtasks when you need to break tasks down into moremanageable partsTo add a subtask use the Add Subtask button

To add a task1 Click a task and then click the Add Task button right-click a task and then click Add Task on the

shortcut menu or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskProject KickStart numbers the new task in the proper sequence

To add a subtask1 Click a task and then click the Add Subtask button right-click a task and then click Add Task on the

shortcut menu or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtask3 Project KickStart numbers the new subtask in the proper sequenceNote

To add a new phase click a phase and then click the Add Task button

See Also

Outdent and Indent Tasks

-o-

48

copy Experience In Software Inc 1995 - 2006

Edit Tasks

Edit tasks in the Task List to fine tune your project You can edit the names of the phases tasks andsubtasks delete tasks and cut copy and paste task information

To edit task names1 Click the phase task or subtask you want to edit and then press the F2 key2 Type to edit the text3 To undo an edit click the Undo button

To delete a task

Click the task you want to delete and then press the Delete key or click the Delete button Or

Right-click a task and then click Delete Row on the shortcut menu

To cut copy and paste tasks1 Select the tasks you want to cut or copy Use Shift-click or Ctrl-click to select more than one task

2 Click the Cut button (Ctrl-X) or click the Copy button (Ctrl-C )

3 Click where you want to insert the tasks and then click the Paste button (Ctrl-V)

Tip

If your project includes some of the same tasks repeated in different phases save time by copying rowsof tasks and pasting them to another phase

Notes

You can also edit task names using the Task Information dialog box To open this dialog boxdouble-click a task or click a task and then click the Edit Task Information button

If you delete a phase you also delete its tasks and subtasks If you delete a task you also delete itssubtasks Project KickStart warns you before deleting tasks or subtasks and gives you a chance tocancel the deletion

See Also

Add Task Notes and Attachments

Add or Change Task Assignments

-o-

49

copy Experience In Software Inc 1995 - 2006

Add Task Notes and Attachments

You might find that some of your tasks are actually more notes than tasks For example Remember tocheck Daves specifications might work better as a note than a task especially if it could take several daysto catch up with Dave but only a few minutes to review his specs By using notes you clarify your projectand increase your chances for success An attachment is a document graphic or any other type of file related to a task For example to a tasksuch as Review proposal you can attach the proposal document Or you can attach a hyperlink to a pageon a web site

To add a note or attachment to a task1 Double-click the Notes column next to the task The Task Information dialog box opens to the Notes

and Attachments tab2 In the Enter a Note box type in or edit the task note (Press Enter to insert line break)3 To attach a file click the Add Files button In the Select File to Attach dialog box navigate to the file

you want and then click the Open button The filename appears in the Add Attachments box with apaperclip icon

4 To insert a hyperlink click the Add URL button In the Insert Hyperlink dialog box type in the URL youwould like to link to The URL appears in the Add Attachments box with a paperclip icon

5 Click the OK button

To open or remove an attachment1 Open the Notes and Attachments tab in the Task Information dialog box2 To open an attachment double-click the filename in the Add Attachments box3 To delete an attachment click the attachment in the Add Attachments box and then click the Remove

button

To change a task into a task note1 Copy (Ctrl-C) the text of the task you want to change into a note2 Double-click the task to which you want to add the note3 In the Task Information dialog box click the Notes and Attachments tab and add paste the text in the

Enter a Note box Close the Task Information dialog box4 In the Task Name column delete the original task that how appears as a note for a different task

Tips

Use notes to keep track of the operational details of a project the little nagging details that are criticalto success

Although the Task List provides plenty of room for notes it is best to keep your notes concise

Some tasks might benefit from instructional notes those that explain what to do in a task or how tosuccessfully complete a task

You can also include a hyperlink in a note by typing httpxxx (where xxx is an e-mail or Web address)In Outlook Word Excel or your browser the hyperlink will be active You can click the link to godirectly to that site or to send an e-mail to that address

Note

You can also open the Notes and Attachments tab in the Task Information dialog box by clicking atask and then clicking the Edit Notes and Attachments button or by double-clicking a task to openthe Task Information dialog box and then clicking the Notes and Attachments tab

See Also

Edit Tasks

Add or Change Task Assignments

Change Task Details in the Gantt chart

50

copy Experience In Software Inc 1995 - 2006

-o-

51

copy Experience In Software Inc 1995 - 2006

Add or Change Task Assignments

The Assignments column in the Task List shows the people and other resources assigned to each task

To add or change a task assignment1 Double-click the Assignments column next to the task The Task Information dialog box opens to the

Assignments tabThe Assignments tab lists all of the people and resources in your project If this task is already assignedto people they are highlighted on the Assignments tab

2 To assign this task to another person or resource click the resource name in the Assignments list3 To remove (unassign) this task from a person or resource click a highlighted name in the Assignments

list4 To add a person and assign the task at the same time click ltNew Persongt in the Assignments list

and then enter the name of the new person5 Click the OK button

Note You can also open the Task Information dialog box by clicking a task and then clicking the Edit Task

Information button to or by double-clicking a task

-o-

52

copy Experience In Software Inc 1995 - 2006

Add or Change Task Details

Besides task names notes and assignments you can include cost and done details about tasks In theSchedule step you can also include start and finish dates and durations

To add task details

1 Click a task and then click the Edit Task Information button or double-click the task you wantThe Task Information dialog box opens

2 Enter Cost or Done informationCost Enter the cost associated with this task For example you could enter $150 as the cost for a tasknamed Purchase photo CD Done Click the list arrow to select 0 25 50 75 or 100 or enter the percentage you want such as33

3 Click the OK button

To show or hide task details

Right-click a column heading to open a shortcut menu and then click Cost or Done In the shortcutmenu a checkmark appears next to columns that are displayed in the Task List

To edit task details

Open the Task Information dialog box (click a task and then click the Edit Task Information button or double-click the task you want)

Or

Double-click the Cost or the Done entry to update these details directly in the Task List

Notes

The Cost amount appears with the currency symbol set for your system (in the Regional and LanguageOptions dialog box of the Windows Control Panel)

Project KickStart calculates the running totals for the tasks within a phase and displays this total in theCost column for the phase When you create and print Task reports the total costs for the entire projectappear at the end of the Cost column

See Also

Edit Tasks

Print Task Reports

-o-

53

copy Experience In Software Inc 1995 - 2006

Check Spelling

Spell check your tasks and notes before you print reports or export to other software

To check the spelling of tasks and notes

Click the Check Spelling button on the Project KickStart toolbarOr

Click Tools on the menu bar and then click Spelling

Notes

Spell checking updates entries on the Task List and the Gantt chart (the Schedule step) It can alsocheck the spelling of intermediate entries such as goals and tasks to accomplish goals if you spellcheck during those steps

Spell checking does not check the names of people on the People List or the contents of the PeopleLibrary

-o-

54

copy Experience In Software Inc 1995 - 2006

Scheduling Tasks in the Gantt Chart

55

copy Experience In Software Inc 1995 - 2006

Scheduling Overview

About Scheduling Tasks

In the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the other

You work with the Gantt chart using the familiar Task Data view in the left pane or the graphical Chart viewin the right pane To adjust the schedule to fit your project set the project start date in the toolbar moveand resize the taskbars in the Chart view or change the start and finish dates or durations of individualtasks in the Task Data view

Click the following illustration to see general tips for using the Gantt chart See About the Gantt Chart formore details

In the Schedule step you can

Change a start date for the project Set start and finish dates or durations for tasks Change the timescale of the schedule Change the working schedule to specify which days are nonworking days such as weekends and

holidays Fine-tune the organization of the phases tasks and subtasks Color-code tasks to identify assignments critical deadlines or other information at a glance Insert milestones to indicate events that mark a moment in time such as the approval of a design Review and edit task details including task name assignments notes and attachments Hide or show task data columns in the left pane Export project data to other software applications

Tip

56

copy Experience In Software Inc 1995 - 2006

To save time you can reuse projects such as one for a trade show and create an updated scheduleby changing the project start date in the Schedule step

See Also

About the Gantt Chart

Understand Task Data View

Understand Chart View

-o-

57

copy Experience In Software Inc 1995 - 2006

About the Gantt Chart

The Gantt chart provides two views of your project schedule The Task Data view in the left pane lists thesame task information as in the Tasks step but now includes durations and start and finish dates TheChart view in the right pane displays taskbars and symbols to represent the same information You canchange the schedule information by working directly in the Task Data view and Chart view or by using theGantt Chart toolbarClick the following illustration to see general tips for using this window

-o-

58

copy Experience In Software Inc 1995 - 2006

Autolink tasks (Pro Users)

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatProject KickStart Pro does not assume that you want to link all of the tasks in a serial manner (one after theother) when you get to the Gantt chart Indeed many users want that behavior and many do notTo accomodate both types of users you can set whether you want the program to Autolink tasks In theTools menu select Autolink tasks Thereafter in all your projects when you get to the Gantt chart for thefirst time the tasks will be linked in a serial mannor

-o-

59

copy Experience In Software Inc 1995 - 2006

About Linking Tasks

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatWhen you link tasks the Gantt chart shows additional information about the tasks Click the followingillustration to see general tips for using linked tasks

Task Data view Chart view Description

Predecessor tasksA predecessor task is onethat you must completebefore you can start thenext task For exampleTask 2 - Prepare soil isthe predecessor to Task3 - Plant shrubs becauseyou need to prepare thesoil before you can plantthe shrubs

Successor tasksWhen you finish onelinked task you can moveonto the next onemdashthesuccessor task Forexample the successorfor Task 2 ndash Prepare soilis Task 3 ndash Plant shrubsand the successor forTask 3 is Task 4 ndash MulchLink linesThe first task isscheduled for one dayand the second one forthe next day In additionthe link line and arrowshow that the first taskmust end before thesecond one can start

These linked tasks arescheduled for the sametime

60

copy Experience In Software Inc 1995 - 2006

These tasks which aredependent on earliertasks and the last twotasks are also scheduledfor the same time

See Also

About the Gantt Chart

Autolink tasks

Make tasks overlap

-o-

-o-

61

copy Experience In Software Inc 1995 - 2006

Change the Display of the Schedule

You can change the onscreen appearance of the schedule so you can work with it more effectively Thefollowing illustration shows the Schedule window with the Steps bar closed and only the task number taskname and duration displayed in the Task Data view This provides more room to display the Gantt chart

To show or hide the Step bar or Project KickStart toolbar

Click View on the menu bar and then click Steps Bar to show or hide the vertical Steps bar on the leftof the Project KickStart window

Click View on the menu bar and then click Tool Bar to show or hide the Project KickStart toolbarwhich appears just below the menu bar In the View menu a checkmark appears next to the items displayed in the Project KickStart window

To display more or less of the Task Data view or Chart view

Drag the splitter bar between the Task Data view and the Chart view

To change the timescale in the chart

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years

To add a column to the Task Data view

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task Data viewBy default the Task Data view shows the Info Task Name Days Start and Finish columns Youcan also show Done Cost and Assignments columns

To hide a column in the Task Data view

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

62

copy Experience In Software Inc 1995 - 2006

To change the column width in the Task Data view

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Understand Task Data View

Understand Chart View

-o-

63

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

-o-

64

copy Experience In Software Inc 1995 - 2006

65

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Some features in this topic are available only in Project KickStart Professional

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view In Project KickStart Professional you also use the Gantt chart toolbar to linkand unlink tasks

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysLink Tasks (Pro Users)Link the selected tasksUnlink Tasks (Pro Users)Unlink the selected tasksChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

See Also

Use the Gantt Chart Toolbar

-o-

66

copy Experience In Software Inc 1995 - 2006

Understand Task Data View

The following illustration shows all the columns of information you can display in Task Data view

The Task data columns are the same as in the Tasks step but also include date information

Row number

Info Shows an icon if a note attachment or both are associated with the task Double-click anicon to view or edit the associated information

Task Name Name of the phases tasks and subtasks Double-click a task name to edit it directly

Days The amount of time it takes to complete the task If you change the number of days for a taskProject KickStart changes the Finish date accordingly

Start Date this task starts Double-click a Start date and then click the list arrow to open a calendar andselect a different date This also changes the Finish date

Finish Date this task ends Double-click a Finish date and then click the list arrow to open a calendar andselect a different date This changes the task duration shown in the Days column

Done Percentage of the phase task or subtask completed Show progress for any task by entering apercent of up to 100

$ Cost Cost for each task summed in the appropriate phase row Reports include total costs for theproject when you select the Cost column in the Create and Print Task Reports dialog box or the Createand Print Gantt Chart Report dialog box The Cost appears with the currency symbol set for your system(in the Regional and Language Options dialog box of the Windows Control Panel)

Assignments People and other resources assigned to the task Double-click an assignment to open theTask Information dialog box to the Assignments tab where you can add and change assignments

Tip

A task with a duration of zero (0) days is a milestone See Create a Milestone for more information

Notes

By default Task Data view displays all the columns the Info Task Name Days Start and Finish Done Cost and Assignments columns Some of these columns might be hidden by the Gantt chartview To hide columns right-click a column heading to open a shortcut menu and then click the columnyou want to hide In the shortcut menu no checkmark appears next to columns that are hidden

To change the width of a column drag a splitter bar in the column heading row or double-click a splitterbar to have the column accommodate its longest entry

As in the Tasks step expand phases and tasks by clicking the plus icon and collapse phases andtasks by clicking the minus icon

See Also

67

copy Experience In Software Inc 1995 - 2006

Understand Chart View

Change Task Dates

-o-

68

copy Experience In Software Inc 1995 - 2006

Additional Features in Task Data View

These features are available only in Project KickStart Professional

In Project KickStart Pro you can view two columns of information in addition to the nine columns availablein the Project KickStart Standard These two additional columns are labeled Pred (for Predecessor) andSucc (for Successor) The following illustration shows a typical Task Data view with these additionalcolumns

Besides the nine columns of information shown in Task Data view in Project KickStart Standard you canalso show the following information in the Professional version

Pred Indicates which task is the predecessor to the current task Double-click a task number in the Predcolumn to change it

Succ Indicates which task is the successor to the current task Double-click a task number in the Succcolumn to change it

Notes

When you link tasks Project KickStart assigns predecessors and successors according to their order inthe Task Data view

When you move a linked task in the Task Data view the predecessor and successor do not changeFor example in the above illustration if you move Task 3 ndash Plan design so it becomes Task 2 itspredecessor remains Land survey and its successor remains Engineering You can change these bydouble-clicking the task number in the Pred or Succ column and then entering a new number

See Also

Understand Task Data View

-o-

69

copy Experience In Software Inc 1995 - 2006

Understand Chart View

The following illustration shows a daily schedule in Chart view Point to the illustration to display text thatdefines the chart elements

Summary bar Summarizes the tasks below it and extends from the earliest start date(where the first triangle in the summary bar appears) to the latest finish date (where the last triangleappears) If a phase has tasks the summary bar appears in the phase row to summarize the tasks If atask has subtasks the summary bar appears in the task row to summarize the subtasks

To reschedule a phase and all of its tasks (or a task and all of its subtasks) click the summary bar and dragit to the left or right until it spans your desired set of dates This changes the earliest start date and latestfinish date in that phase and keeps the same duration And all the tasks move with the change of thephase

Taskbar Shows the length and scheduled dates for a task To change the duration of a taskresize the taskbar click the taskbar and then drag its left edge to schedule a different start date or drag itsright edge to schedule a different finish date

To reschedule a task without changing the duration drag the taskbar to a different date in the chart

Taskbar with percent done If you enter a Done amount in the Task Data view a progress barin the taskbar indicates the amount of the task completed

Red vertical line Indicates todays date

Milestone Indicates a task with a zero duration Milestones mark an event that must be reflected inyour project plan such as the approval of a design or an assembly line startup You can drag the left edgeof a milestone icon to stretch it into a taskbar The milestone becomes a task with a start and finish date

Notes

Because a summary bar summarizes the tasks below it you cannot resize a summary bar

To scroll the schedule use the vertical and horizontal scroll bars or the green drag bar at the top of theChart view

The shaded days in the Chart view indicate nonworking days To set which days are working andnonworking see Specify Working Days

70

copy Experience In Software Inc 1995 - 2006

-o-

71

copy Experience In Software Inc 1995 - 2006

Additional Tools in Chart View

These features are available only in Project KickStart Professional

If you use Project KickStart Pro the Chart view displays lines and arrows to show linked tasks The linklines and arrows show the relationships dependencies between one linked task and another

Besides the summary bar taskbar and other information provided in Project KickStart Standard Chart viewin the Professional version also provides the following information

The first task is scheduled for one day and the second one for the next day In addition the link line andarrow show that the first task must end before the second one can start

These linked tasks are scheduled for the same time However the first task must end before the secondone can start

The first two tasks are scheduled for the same time and must be completed before the third task can start

These linked tasks are scheduled for the same time However the second task must end before the firstone can start

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

Understand Chart View

-o-

72

copy Experience In Software Inc 1995 - 2006

73

copy Experience In Software Inc 1995 - 2006

Change Task Dates

You can revise a project schedule by changing task dates in the Task Data view or the Chart view You canalso reschedule an entire project by changing the projects start date

To change the project start date1 Click the Project Start list arrow to open a calendar

The calendar highlights the selected date and outlines todays date2 Find the date you want using the left and right scroll arrows to view a different month and then click the

date

To change task dates in Task Data view1 Double-click the Start or Finish date for a task

2 Then edit the date (you can edit the day month or year) OrClick the list arrow to open a calendarThe calendar highlights the selected date and outlines todays date

3 Find the date you want using the left and right scroll arrows to view a different month and then click thedateProject KickStart changes the Start and Finish dates according to your selection updates the durationof the task in the Days column and adjusts the taskbar in the Chart view

To change task dates by changing the duration in Task Data view

Double-click the Days column for a task and then enter the number of days it will take to complete thetaskProject KickStart changes the Finish date of the task and adjusts the taskbar in the Chart view

To change task dates in Chart view

Resize a taskbar click the taskbar and then drag its left edge to schedule a different start date or dragits right edge to schedule a different finish dateProject KickStart updates the summary bar in Chart view and the task dates and duration in the TaskData view

To reschedule a task without changing the duration drag the taskbar to a different date You can alsodrag a summary bar to reschedule a phase and all of its tasks (or a task and all of its subtasks) so itspans a different set of datesProject KickStart updates the task dates and duration as necessary in the Task Data view

To change task dates in the Task Information dialog box1 Open the Task Information dialog box (Right-click a task and then click Task Information or click a

task and then click the Edit Task Information button )2 Click the General tab3 In the Dates section change the following information as necessary

Start Click the Start list arrow to open a calendar and then click the appropriate start dateFinish Click the Finish list arrow to open a calendar and then click the appropriate finish dateDays Enter a number or click the spin arrows to set the task durationMilestone Select the Milestone check box if you want this task to be a milestone (A milestone is atask with a zero duration and marks an event such as the approval of a design)

Notes

You cannot delete the Start or Finish date of a task If you want to specify that a task has no durationconvert it to a milestone

When working with a calendar to schedule a start or finish date click the Today date text (where date

74

copy Experience In Software Inc 1995 - 2006

is todays date) to select todays date

See Also

Understand Task Data View

Understand Chart View

Create a Milestone

-o-

75

copy Experience In Software Inc 1995 - 2006

Phase Dates Cannot Be Edited

You cannot change the bold phase dates in the Task Data view of the Gantt chart They are a summary ofthe task dates for a particular phase and are view only You can revise phase dates by changing task dateswithin the phase

To change phase dates in Chart view

You cannot directly resize a summary bar You can extend or move the blue task barswithin a phase on the chart and Project KickStart updates the summary bar

To reschedule a phase on the chart drag the summary bar to a new date and all of its tasks (or a taskand all of its subtasks) will move with it

-o-

76

copy Experience In Software Inc 1995 - 2006

Quick Tour of Working with Linked Tasks

This feature is available only in Project KickStart ProfessionalIn the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the otherIn addition Project KickStart Pro links the tasks for you so when you open the Gantt chart you see a linkedwaterfall similar to the one shown below Besides providing a schedule that starts in a cascade with eachtask lasting one day each task is linked to the next task

You work with the Gantt chart either using the Task Data view in the left pane or the graphical Chart view inthe right pane To adjust the schedule to fit your project set the project start date in the toolbar move andresize the taskbars in the Chart view or change the start and finish dates or durations of individual tasks inthe Task Data view See About Scheduling Tasks for detailsNext fine-tune the dependencies in your project by you can linking and unlinking tasks changing theirpredecessors and successors and setting lead times For example if one task is not dependent onanother you can unlink the tasks If another task canrsquot start until two other tasks are finished you can add apredecessor to that task in which case the two tasks will be linked

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

To fine-tune the linked tasks To change the scheduled start and end dates of linked tasks move and resize taskbars in the Chart

view or change the number of days or the Start date in the Task Data view To display predecessor and successor information in the Task Data view right-click any column

heading and then click Pred or Succ To change the predecessor for a task double-click the number in the Pred column for the task and

then enter the number of a different task To change the successor for a task double-click the number in the Succ column for the task and then

77

copy Experience In Software Inc 1995 - 2006

enter the number of a different task To add another predecessor or successor to a task click in the appropriate column for the task and

then enter the number of another task To change the details of a linked task open its Task Information dialog box To do so right-click the

task and then click Task Information on the shortcut menu or click a task and then click the Edit TaskInformation button See Change Details for Linked Tasks

In the Task Information dialog you can also specify the predecessor(s) of a task and lead time(s) of thetasks

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

About Scheduling Tasks

About Linking Tasks (Pro Users)

Use the Gantt Chart Toolbar (Pro Users)

Manage Changes in Your Schedule (Pro Users)

-o-

-o-

78

copy Experience In Software Inc 1995 - 2006

Link and Unlink Tasks

These features are available only in Project KickStart Professional

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

See Also

About Linking Tasks

Quick Tour of Working with Linked Tasks

-o-

79

copy Experience In Software Inc 1995 - 2006

Create a Milestone

A milestone Indicates a task with a zero duration Milestones mark an event that must be reflected in yourproject plan such as the approval of a design or an assembly line startup

To create a milestone in the Task Data view

Double-click the Days number for a task and then enter 0 (zero)Or

Open the Task Information dialog box click the General tab and then click to insert a checkmark inthe Milestone check box

In the Chart view Project KickStart changes the taskbar to a milestone icon To create a milestone in Chart view

Click a taskbar and then drag to shrink the taskbar to a milestone icon In the Task Data view Project KickStart changes the Days for this task to 0 (zero)

Notes

To change a milestone into a task you change its duration or start and finish dates See Change TaskDates for instructions

To move a milestone in Chart view click the milestone icon on the upper left corner of the milestoneicon With the left mouse down move the icon to another date and release the mouse

To move a milestone in the Task Data view change the start date or the finish date and the milestonewill move

-o-

80

copy Experience In Software Inc 1995 - 2006

Change Task Details

You can use the Task Information dialog box to change the following task details in Task Data view

Task properties including the task name cost for completing the task and the percent completed

Dates including the start and finish dates duration and whether to convert the task to a milestone

Assignments

Notes and attachmentsYou can also edit the task name days dates costs and Done directly by clicking items in the task datacolumns

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button 2 Click the appropriate tab and then change the task details

General tab Change the task name and enter or change the cost associated with the task To changethe amount of the task completed click the Done list arrow and then select a value or type a value inthe Done text box Enter or change date information as described in Change Task Dates Assignments tab People assigned to this task are highlighted in the list To assign this task to anotherperson or resource click the name in the Assignments list To remove (unassign) this task from aperson or resource click a highlighted name in the Assignments list See Add or Change TaskAssignments for more detailsNotes and Attachments tab Type or edit a task note (Press Enter for a line break) To add anattachment click the Add button In the Select File to Attach dialog box navigate to the file you wantand then click the Open button The filename appears with a paper clip icon See Add Task Notes andAttachments for more details

To change task details directly in Task Data view

To modify the task name press F2 or double-click a task and then edit or replace the text

To change date information see Change Task Dates

To change the amount of the task completed double-click in the Done column and then enter a newvalue

To change the cost associated with the task double-click in the Cost column and then enter a newvalue

Notes

When you enter costs for tasks the total appears in the phase row for those tasks Reports include thetotal costs of all tasks in the project when you select the Cost column in the Create and Print TaskReports dialog box or the Create and Print Gantt Chart Report dialog box

You cannot change the cost of a phase because it represents the total costs for the tasks in that phaseInstead change the costs associated with the tasks in the phase

When you enter a Done for a task the corresponding taskbar in the Chart view includes a blackprogress bar

-o-

81

copy Experience In Software Inc 1995 - 2006

Change Details for Linked Tasks

This feature is available only in Project KickStart ProfessionalIf you are using Project KickStart Pro you can use the Task Information dialog box to change the followingtask details

Predecessor for a linked task

Lead time for a linked task

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button

2 Click the Predecessors tab and then change the task details about predecessors and lead timePredecessors tab The Task Properties section shows the name of the selected task which you canchange The Predecessor (Finish-to-Start) section shows the tasks that are predecessors to theselected task A predecessor task must be finished before you start the current task You can change the ID name or lead time of the predecessor task Also you can also add additionalother predecessorsThe lead time is the amount of time you need to wait after finishing the predecessor task before so youcan start the current task Lead time can be positive or negative

Note

In some programs the is time shift is called ldquolag timerdquo But we think that the term ldquolead timerdquo is moreaccurate and descriptive since itrsquos the amount of time you want to allow before you start a task

See Also

Change Task Details

82

copy Experience In Software Inc 1995 - 2006

-o-

-o-

83

copy Experience In Software Inc 1995 - 2006

Reorganize Tasks in Task Data View

Although your project should be fairly well organized by the time you start the Schedule step you canfine-tune the organization in the Task Data view using the same techniques you use in the Tasks stepTo reorder tasks

Right-click a task and then click Move Task Up or Move Task Down on the shortcut menu Or

Click a task or phase to select it and then click the Up Arrow button or the Down Arrow button on theGantt chart toolbar

To promote and demote tasks

Right-click a task and then click Outdent or Indent on the shortcut menu Or

Click a phase task or subtask to select it and then click the Outdent button or the Indent button onthe Gantt chart toolbar

To add a task1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Task button on the Gantt chart toolbar or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskTo add a subtask1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Subtask button on the Gantt chart toolbar or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtaskTo delete a task

Right-click a task and then click Delete Row on the shortcut menuOr

Click the task you want to delete and then click the Delete button

To delete a row click the Task row number and press the Delete button

See Also

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

-o-

84

copy Experience In Software Inc 1995 - 2006

Change the Timescale of the Schedule

You can display the Gantt chart schedule in the Chart view using days weeks months quarters or yearsas the timescale Changing from days to weeks for example displays a longer period of time but lessdetail

Days timescale Weeks timescale

To change the timescale in the Chart view

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years Youcan also change the timescale by clicking Timescale on the menu bar and then clicking the option youwant

Notes

When you print a Gantt chart your current timescale is used by default However you can change it inthe Print Options dialog For example even though you were viewing your Gantt chart by weeks youcan choose to print the Gantt chart by months

If your mouse comes with a wheel you can adjust Project KickStarts timescale by rolling the wheelforward or backward The Timescale list box must be selected first

-o-

85

copy Experience In Software Inc 1995 - 2006

Specify Working Days

You can select which days are working days and which days are nonworking days for scheduling purposesBy default Monday - Friday are working days and Saturday and Sunday are nonworking days You can addto and change these settings to specify holidays for example

To set working and nonworking days

1 Click the Change Working Schedule button on the Gantt chart toolbar The Change Working Schedule for this Project dialog box opens Nonworking days are shaded in grayWorking days are unshaded

2 To change a single date (from working to nonworking or from nonworking to working) click the date3 To change one day of the week for the entire project such as all Fridays double-click any Friday4 To display schedules for other months click the left and right arrows5 Click OK

Note

Project KickStart maintains separate calendars for each project

If you typically work weekends create a simple template with weekends displayed as Working daysSave as your starter template Use the starter template when you start a new project and then save theproject with a different name Weekends will be displayed as Working days in your projects

-o-

86

copy Experience In Software Inc 1995 - 2006

Change the Color of Taskbars

You can change the color of the taskbars in the Chart view to call attention to particular tasks For exampleyou can change the colors of all tasks in a particular phase resource or deadline to make them stand outin a report

To change the color of a taskbar1 Right-click a taskbar and then click Color on the shortcut menu or click a taskbar and then click the

Color button on the Gantt chart toolbar The Color dialog box opens

2 Click the color you want to assign to the taskbarTips

Avoid changing the taskbar color to black because it obscures the Done progress bar (The Doneprogress bar is a black bar displayed within a taskbar)

Also avoid changing the taskbar color to white because it will not appear in the white rows of the Chartview

-o-

87

copy Experience In Software Inc 1995 - 2006

Make Tasks Overlap

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro the schedule starts in a cascade with each task lasting one day and each tasklinked to the following taskHowever it is very unlikely that your entire schedule matches such a cascade so you can adjust theschedule Start by estimating the duration of tasksmdashthe number of days that each task will take Generallyit is best to estimate how many days will elapse before the task is done You might also want some tasks to occur at the same time To do so you can overlap the tasks To make tasks overlap like this

You can do this in three ways Set the same predecessor for both tasks

Or Set the second task as the successor of the first task and then then move the second task into a

position when it starts on the same day as the first taskOr

Set the second task as the successor of the first task and then assign a lead time of ndash3 days (the number of days scheduled for the task)

To make tasks overlap like this

Set the second task as the predecessor of the first task and then assign a lead time of ndash2 days(one less than the number of days scheduled for the task)

-o-

88

copy Experience In Software Inc 1995 - 2006

Manage Changes in Your Schedule

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro when you schedule with dependencies you can adapt to changes on the fly andcreate what-if scenarios to forecast how one change affects the overall project schedule A commonscenario is dealing with delays You can reschedule an entire project or only selected tasks When you doProject KickStart Pro updates the schedule for you

To delay an entire project Click in the Project Start text box and then edit the date to match your new start date (You can edit

the day month or year)Or

1 Click the Project Start list arrow to display the calendar The calendar highlights the selected date andoutlines todays date

2 Find the date you want using the left and right scroll arrows to view a different month and then click thedate Project KickStart changes the Start and Finish dates for all tasks according to your selection

To delay a task In Task Data view double-click the Days column for the task and then edit the number of days it will

take to complete the taskProject KickStart changes the Finish date of the task adjusts the taskbar in the Chart view andchanges the Start and Finish dates for all tasks linked to this taskOr

In Chart view resize a taskbar by clicking the taskbar and then dragging its left edge to schedule adifferent start date or dragging its right edge to schedule a different finish date Project KickStart updates the summary bar in Chart view the task dates and duration in the Task Dataview and reschedules all tasks linked to this task

To reschedule a task without changing the duration in Chart view drag the taskbar to a different date Project KickStart updates the task dates and duration as necessary in the Task Data view andreschedules all tasks linked to this task

Note

Project KickStart Pro does not include a critical path

-o-

89

copy Experience In Software Inc 1995 - 2006

Managing Libraries

Use a Library

Project KickStart has five libraries that contain lists of useful phases tasks goals people and obstaclesAll libraries expect the People Library contain sample entries that you can use in your projects Yougenerally build your own People Library from the resources that are available to you

To use a library1 In the Phases Tasks Goals People or Obstacles step of the Planning Wizard click the Library button

to open the appropriate library2 Select one or more items in a library and then drag them to your list3 Close the Library window

Tips

Feel free to add (or delete) items to the libraries to make them richer and more pertinent to yourprojects

Keeping libraries small makes them easier to use

Widen the library window to see the full text of long entries

Note

After adding a library entry to a list you can double-click the entry to edit it

See Also

Manage a Library

-o-

90

copy Experience In Software Inc 1995 - 2006

Manage a Library

Customize the libraries by adding and changing entries and reorganizing them so you can use the librariesefficiently The Phases Tasks Goals People and Obstacles Libraries include a single column ofinformation while the People Library provides additional columns (See Manage the People Library)

To edit a library1 Open the library by clicking the appropriate Library button2 To edit an entry double-click it

3 To add an entry to the library press Insert or click the Add a row button You can also select oneor more items in the list and then drag them to the library

4 To delete an entry select the entry and then press Delete or click the Delete a row button 5 To move an item up or down select the item and then click the Up Arrow or the Down Arrow button

6 Click the OK button to save your changes and close the Library windowTips

Widen the Library window to add a long entry

Libraries can serve as ldquoKnowledge Librariesrdquo By including typical company-specific terms in yourLibraries you create a quick reference for yourself and colleagues now and in the future To do so adda new line in the Library enter the name of your company (or department) as a heading in capitalletters and then list your personal terms under the heading

If you use Project KickStart on more than one computer such as at home and work you can transportchanges you make in your Libraries from one computer to another The data in all the Libraries isstored in one file pks5libxdat so you can copy that file on one computer and paste it into the ProjectKickStart 5 folder on the other computer

Keeping Libraries small makes them easier to use Project KickStarts Libraries are fairly rich out of thebox If some of the terms don rsquot apply to your type projects delete them

See Also

Manage the People Library

-o-

91

copy Experience In Software Inc 1995 - 2006

Manage the People Library

The People Library is like the other libraries but with a few important extra features

You can store contact data such as Company Email Phone and Job Title

You can import names from ACT or from Outlook if you use either of those programsTo use the People Library1 In the People step of the Planning Wizard click the People Library button2 Select one or more names in the People Library and then drag them to your list (This adds only the

names of people not their contact data) If the People Library contains company names but not contactnames you can drag the company name to your list

3 Close the Library windowTo organize the People Library

To show or hide a column right-click a column heading to open a shortcut menu and then click acolumn name In the shortcut menu a checkmark appears next to columns that are displayed in thePeople Library

To sort the people in the People Library click a column heading For example click the Name columnheading to sort the people alphabetically by name To reverse the sort click the column heading again

To move a person up or down select the person and then click the Up Arrow or the Down Arrowbutton

Click the OK button to save your changes and close the People LibraryTo edit the People Library

To edit a persons name and contact data double-click the entry

To add a person to the People Library click the first blank row press Insert or click the Add a rowbutton Then type to enter the persons name and contact information You can also select one ormore items in the list and then drag them to the People Library

To delete an entry select the entry and then press Delete or click the Delete a row button

Click the OK button to save your changes and close the People LibraryTips

Use the People Library to store names for people teams (such as Quality control team) departments(such as Manufacturing) companies (such as Acme Widgets Corp) or even equipment (such as wheatthrasher)

Widen the People Library window to add a long entry

Resize the columns by dragging or double-clicking a splitter barNotes

After adding a person or resource to your list you can double-click the name to edit it

You can import contact information stored in an Outlook or ACT (version 6 7 or later) address book toyour People Library

See Also

Import ACT Contacts and Users to the People Library

Import Outlook Contacts to the People Library

-o-

92

copy Experience In Software Inc 1995 - 2006

Import ACT Contacts and Users to the People Library

If you use ACT 7 or later (200520062007) or if you use ACT 6 you can import contacts and users to thePeople Library This speeds up your work by letting you use ACT information in your Project KickStartplans If you export a plan to ACT 7 or later it recognizes the people and other resources you entered inProject KickStart

To import ACT contacts and users1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click ACT 7 or later or ACT 6 Click the Import button3 Click the Select ACT Database button and select the ACT 7 or later database (pad) containing the

people information you want to import The ACT 7 and later databases are usually stored in MyDocumentsACTACT for Win 7Databases (If you use ACT 6 your data is stored in a dbf database) If you select a multi-user ACT database you must enter your user name and password for the ACTdatabase

4 In the Import to People Library dialog box the names of Contacts and Users are listed on the left Clickthe Users tab select one or more users and then click Add to move the user names to the Import listClick the Contacts tab to select contact names the same way Click the Add All button to select allusers or contacts for import Note You can sort the contacts alphabetically by name or by company name by clicking theappropriate column heading

5 Click the Import button to add the names and related information from the selected ACT database tothe People Library

Notes

Importing contacts and users to the People Library does not remove them from the ACT database

If you try to import the same ACT contact or user twice it appears only once in the People Library

-o-

93

copy Experience In Software Inc 1995 - 2006

94

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts to the People Library

If you use Microsoft Outlook to maintain your contacts you can import selected contacts to the PeopleLibrary ThisThis speeds up your work by letting you use Outlook information in your Project KickStartplans If you export a plan to Outlook it recognizes the people and other resources you entered in ProjectKickStart

To import Outlook contacts1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click Outlook Click the Import buttonA dialog box opens informing you that Project KickStart is trying to access your Outlook data

3 Allow access for 1 minute and then click the Yes button4 If Outlook asks you to choose your profile please do so5 The Import to People Library dialog box opens listing Outlook Contacts on the left Select one or more

contacts and then click Add to move the contact names to the Import list Click the Add All button toselect all contacts for import

6 Click the Import button to add the contact names to the People Library

Notes

Importing contacts and users to the People Library does not remove them from Outlook If you try to import the same Outlook contact twice it appears only once in the People Library

95

copy Experience In Software Inc 1995 - 2006

You can import Contacts from the Outlook Business Contact Manager

See Also

Import Outlook Contacts via CSV to the People Library (Pro Users)

-o-

96

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts via CSV to the People Library (ProUsers)

This feature is available only in Project KickStart Professional

If you use Microsoft Outlook to maintain your contacts and many of the people on your project are not inyour personal contacts folder in Outlook you can use our new utility to import these Outlook contacts viaCSV to the People Library

To export Outlook contacts to a CSV file1 In Outlook - Click File Import and Export Export to A File and click Next2 Select Comma Separated Values (Windows) and click Next3 Select the Contacts folder to export and click Next4 Save Exported File As with the default being your My Documents folder5 Click Next

To import Outlook contacts to the People Library

1 Be sure that you exit Project KickStart before running the Import Utility

2 Run ImportCSVToPKSexe which is located in the Project KickStart application folder

3 Browse or type the Contacts CSV file (the path is My DocumentsProject KickStart Projects folder bydefault)

4 Browse or type the pks5libxdat file (default is the Project KickStart application folder)

5 Click on Import

Note

Importing contacts and users to the People Library does not remove them from Outlook

-o-

97

copy Experience In Software Inc 1995 - 2006

Printing Reports

98

copy Experience In Software Inc 1995 - 2006

Printing Dashboards

Print Reports

You can print reports from anywhere in Project KickStart through a new Reports Step

You will see Reports divided into three areas

Dashboard

Task Reports

Gantt Chart Reports

-o-

99

copy Experience In Software Inc 1995 - 2006

Print Dashboard Reports

You can print dashboard reports from anywhere in Project KickStart though it makes the most sense toprint them after you have developed your tasks and arranged them in a sensible order

To print a dashboard report

1 Click File on the menu bar and then click Print Reports and then click Dashboard Reports or clickthe Print Reports button

2 In the left column select one of these dashboard reports Whats Due Today Whats Due NextWeek Whats Due Next Month

3 Change the page setup as necessary or Save As a file (See Page Setup and Save As)

4 Click the Print button

Tip

You can see the number of tasks in each dashboard report from the dashboard menu

-o-

100

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Dashboard Reports

Printer Setup

-o-

101

copy Experience In Software Inc 1995 - 2006

Save as HTML or RTF

You can dashboard reports to a Hypertext Markup Language (HTML) format for viewing with an Internetbrowser such as Microsoft Internet Explorer or Mozilla FireFox or to an RTF format for viewing in MicrosoftWord

To save a dashboard report as an HTML file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save button

To save a report as an RTF file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

102

copy Experience In Software Inc 1995 - 2006

Printing Task Reports

Print Task Reports

You can print task reports from anywhere in Project KickStart though it makes the most sense to print themafter you have developed your tasks and arranged them in a sensible orderBefore you print task reports you might want to widen the Task Name column in the Task List to make sureyou print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a task report

1 Click File on the menu bar and then click Print Task Reports In the Tasks step you can click thePrint Reports button instead

The Create and Print Task Reports dialog box opens

2 Click the list arrow and then click Task Report Individual Assignments or Phases Goals People ampObstacles

3 Select the information you want to include in the report as described below

4 Preview the report and change the page setup as necessary (See Print Preview and Page Setup)

5 Click the Print button

Task Report

The Task report covers the entire project and includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

103

copy Experience In Software Inc 1995 - 2006

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to display in the report

By default the report prints all tasks Click the Incomplete Tasks or Completed Tasks option button tofocus on one type of task

4 Click the Preview button (See Print Preview for details)

Individual Assignments

The Individual Assignments report covers the entire project and lists the tasks assigned to each resourceThe report includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to include in the report

Click the All Tasks Incomplete Tasks or Completed Tasks option button

4 Choose which people to include The report lists tasks assigned to the people you select

Click to insert or remove a checkmark from the box for each person

5 Click the Preview button (See Print Preview for details)

Phases Goals People amp Obstacles

This report includes the phases goals people and obstacles in your project You can include some or all ofthese items in the report

104

copy Experience In Software Inc 1995 - 2006

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Click the Preview button (See Print Preview for details)

Tip

If you have many long notes for the tasks of your project it may be hard to read them if you select everycolumn in the Task Reports You should consider selecting a report with only columns for Tasks andNotes

See Also

Print Gantt Chart Reports

-o-

105

copy Experience In Software Inc 1995 - 2006

Print Preview

Before printing a report preview its pages so you know how the report will look when printed

To preview a task report1 Click the Preview button on the Create and Print Task Reports dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from 79 to 100 or from 100 to 79Zoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25

viewPrint the report

You can also click the Page Setup button to change margins and other settings or click the Closebutton to close the Print Preview window

2 If the report appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintTask Reports dialog box

Note

Print Preview is for viewing only--you cannot edit the contents of a report

See Also

Print Task Reports

Printer Setup

Page Setup

-o-

106

copy Experience In Software Inc 1995 - 2006

Printer Setup

Before you print a report you can change the following printer settings

Printer name (and other properties) Paper size Number of copies

To change the printer setup1 Click the Printer button on the Project KickStart toolbar or the Print Preview toolbar2 In the Print dialog box change the printer settings

See Also

Print Task Reports

Print Preview

Page Setup

-o-

107

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Task Reports

Print Preview

Printer Setup

-o-

108

copy Experience In Software Inc 1995 - 2006

Email Task Reports

After creating and previewing a task report you can distribute it to others via email

To email a task report1 In the Create and Print Task Reports dialog box select a report and then click the Email Report

button Project KickStart creates the report opens a new message in your email software and attaches thereport as an HTML file to the message

2 Insert one or more email addresses include the message text and then send the message the way youusually do

Tip

To send a task report to each person in your project with the appropriate assignments select theIndividual assignments report select one person to receive the report and then click the Email Reportbutton Enter the email address of the recipient and send the message Do this for each person in yourproject

-o-

109

copy Experience In Software Inc 1995 - 2006

Save as HTML

You can export tasks assignments days and notes to a Hypertext Markup Language (HTML) format forviewing with an Internet browser such as Microsoft Internet Explorer or Mozilla FireFox

To save a report as an HTML file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

110

copy Experience In Software Inc 1995 - 2006

Save as RTF

You can export tasks assignments durations and notes to a Rich Text Format (RTF) for editing inMicrosoft Word

To save a report as an RTF file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can open an RTF file in a word processor such as Microsoft Word

To send an RTF document to each person in your project with the appropriate assignments select theIndividual Assignments report select one person to receive the report and then save the report asRTF Do this for each person in your project

See Also

Save as HTML

-o-

111

copy Experience In Software Inc 1995 - 2006

Printing Gantt Chart Reports

Print a Gantt Chart

Once you create your schedule you can print a Gantt chart from anywhere in Project KickStart

Before you print a Gantt chart you might want to widen the Task Name column in the Task pane to makesure you print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a Gantt chart1 Click File on the menu bar and then click Reports and then select Gantt Chart Reports In the

Schedule step you can click the Print Reports button insteadThe Create and Print Gantt Chart Report dialog box opens

2 Click the Format list arrow and then click Wall chart Fit to smallest size or Repeat tasks on everypage (for handouts)

3 Select the information you want to include in the report as described below4 Preview the report and change the page setup as necessary (See Print Preview a Gantt Chart and

Page Setup)5 Click the Print button

Wall Chart The wall chart prints the Gantt chart information spread across many pages which you can tape together tocreate a wall chart On the left side of the report the wall chart includes the task data columns you selectThe right side of the report includes the graphical view shown in the Gantt chart pane on the right

1 Select the task data columns you want to display for the task information on the left side of the wallchartClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the wall chart

112

copy Experience In Software Inc 1995 - 2006

By default the wall chart prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the wall chartBy default the wall chart prints the timescale you were using in the Gantt chart Click the SetTimescale list arrow to change the timescale to Weeks Months Quarters or Years

4 Select the orientation for the wall chartClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Fit to Smallest Size When you select the Fit to smallest size format Project KickStart reduces the size of the entire Gantt chartincluding the information in the Task pane on the left and the graphical view shown in the Gantt chart paneon the right so it fits as well as possible in the smallest number of pages

1 Select the data columns you want to display for the task information on the left side of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 The timescale for the Gantt chart view on the right side of the report is determined by the length of yourproject and may not be changed

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 The number of pages of the report is shown here (The Fit to smallest scale report will print up to 78rows of tasks per page)

6 Click the Preview button (See Print Preview a Gantt Chart for details)

Standard (for Handouts) This report lists the data columns you specify on the left side of the first page and can repeat the tasknumber task name or assignments on every interior page of the report which is especially useful for

113

copy Experience In Software Inc 1995 - 2006

handouts

1 Select the data columns you want to print on the left side of the first page and the data columns youwant to print on every page of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the reportBy default the report prints a daily view of the tasks Click the Set Timescale list arrow to change thetimescale to Weeks Months Quarters or Years

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Tips

Print Preview shows how many pages the Gantt chart will take to print If there are too many pagesconsider changing the timescale or the date range You can also choose to show fewer columns of taskdata

If possible use paper that is larger than 85 x 11 inches You can select the paper size in Print Previewusing the Page Setup dialog box

If you change the timescale from Days to Weeks or Months this can make tasks with short durations (1to 5 days) difficult to see

If you have trouble printing the Gantt chart report try changing the dpi from 600 to 300 (draft mode) Ifyou continue to have problems contact your printer manufacturer and see if it supports PCL (PrinterCommand Language) technology which is included in most printers today

If you have trouble printing the Gantt chart report on a PDF printer you can try to scale the printing tographics setting to 50

114

copy Experience In Software Inc 1995 - 2006

See Also

Save Gantt Chart Images

Print Task Reports

Printer Setup

Page Setup

-o-

115

copy Experience In Software Inc 1995 - 2006

Print Preview a Gantt Chart

Before printing a Gantt chart preview its pages so you know how the report will look when printed

To preview a Gantt chart1 Click the Preview button on the Create and Print Gantt Chart Report dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from the current zoom percentage to 100 or from 100 to the current zoom percentageZoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25 viewChange printer settings and then print the reportYou can also click the Page Setup button to set margins select paper size and enter headers andfooters or click the Close button to close the Print Preview window

2 If the Gantt chart appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintGantt Chart Report dialog box

Notes

Print Preview is for viewing only--you cannot edit the contents of a report

If you want to print a wider task column return to the Gantt chart widen the Tasks Name column andthen print

To change print settings such as the printer selection and number of copies click the Print button to open the Print dialog box You can save the Gantt chart in a PDF file by clicking the Print button andthen clicking the PDF printer selection (such as Adobe PDF or PDF-XChange ) You can then distributethe Gantt chart electronically as a PDF file

See Also

Print a Gantt Chart

Page Setup

-o-

116

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a Gantt chart you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print a Gantt Chart

Print Preview a Gantt Chart

-o-

117

copy Experience In Software Inc 1995 - 2006

Printing to an Adobe PDF file

To print a Gantt chart to an Adobe PDF file you may have to make some adjustments to your settings

To preview a Gantt chart1 Select Adobe PDF as the name of the printer2 Click Properties button3 Click the PaperQuality tab4 Click Advanced button5 In the Graphic Section lower the setting on Print Quality6 Also in the Graphic Section change the Scaling from 100 to 50

-o-

118

copy Experience In Software Inc 1995 - 2006

Save Gantt Chart Images

You can save a Gantt chart as a series of graphic files in the Meta File (emf) format which you can theninsert in a file such as a Microsoft Word document or PowerPoint presentation The number of graphic filescreated depends on the report type and options you choose in the Create and Print Gantt Chart Reportdialog box By default Project KickStart saves the files in a folder named for your project

To save Gantt chart images1 In the Create and Print Gantt Chart Report dialog box click the Save Image button

The Save Image dialog box opens2 Change the location where you want to save the image files or change the part of the file name that

includes the project name and report type if necessary3 Click the Save buttonNotes

Project KickStart saves the image files in the PKSGanttImagesproject name folder stored in the MyDocumentsProject KickStart Projects folder (where project name is the name of your project)

Each graphic file name includes the name of the project report type date you created the report andnumber in the series of images as in CreateaWinningPresentation_Wall chart_09112008_1emf toCreateaWinningPresentation_Wall chart_09112008_20emf

To email the Gantt chart images attach the images in the PKSGanttImagesproject name folder storedin the My DocumentsProject KickStart Projects folder (where project name is the name of your project)If the image files are large zip or compress the files first

If you have installed PDF as a printer selection you can print the Gantt chart to a PDF file and thenattach the PDF file to an e-mail message PDF files are often easier to read than image files See thenotes in Print Preview a Gantt Chart for instructions on printing to a PDF file

-o-

119

copy Experience In Software Inc 1995 - 2006

Export Project Data

120

copy Experience In Software Inc 1995 - 2006

Export to ACT

Export to ACT 7 or Later

If you use ACT 7 or later (20052006200720082009) you can export your plan from Project KickStart toan ACT database with just one click After you export your plan you see your tasks in the ACT Groupview grouped under the name of your project

To export to ACT 7 or later

1 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 7 and later andthen click the Go button You can also click File on the menu bar point to Export to and then clickACT 7 and later

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (pad file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opens

Each time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks

4 Click Start (This works best if ACT is already open )

5 If you are exporting to a multi-user ACT database enter your ACT User Name and Password

To view each project separately in ACT Group Details

1 In ACT click the Group List icon

2 Double-click the Project Name in the Group Name column The Group Detail appears for the projectyou selected

3 Click the Contacts tab to see Contacts and click the Activities tab to see tasks for that project

4 You should press Ctrl-F5 to refresh the view Also you might have to adjust the Filter in ACT so thatDates to show is set to All Dates

Task names are listed in the Regarding column Assignments are listed in the Scheduled With columnPhases are shown in red and tasks and subtasks are shown in blue

To view tasks from multiple projects sorted by date in Task List or Calendar

In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn Project names are in the Associate With column You might have to adjust the Filter in ACT sothat Dates to show is set to All Dates

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar Tasks are set as timeless (Duration of 0 minutes) so the transferred tasks dont fill up thecalendar

121

copy Experience In Software Inc 1995 - 2006

Tips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

The ACT 7 and later export is smart enough to update your existing tasks from the same project If youexport the same Project KickStart project two or more times ACT recognizes the project and asks ifyou want to update the project information in ACT You do not lose your task history or notes in ACT

Tasks that are unassigned in Project KickStart are listed as Scheduled With Unassigned PKS

You can filter by Selected Users in the Task List and in Groups

See Also

Import ACT Contacts and Users to the People Library

-o-

122

copy Experience In Software Inc 1995 - 2006

Export to ACT 6

If you use ACT 6 ACT 2000 or ACT 5 you can transfer a Project KickStart plan into an ACT databasewith just one click After you export your plan you see your tasks in the ACT Group view grouped underthe name of your project

To export to ACT 61 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 6 and then click

the Go button You can also click File on the menu bar point to Export to and then click ACT 6

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (dbf file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opensEach time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks4 Click Start (This works best if ACT is already open )5 If you are exporting to a multi-user ACT database enter your ACT user name and passwordTo view each project separately in ACT1 In ACT click the Groups icon 2 Click the Project Name listed under All Groups on the left3 On the lower-right part of the window click the Activities tab to see tasks for that project

Task names are listed in the Regarding column Assignments are listed in the Scheduled With column 4 You might have to adjust the Filter in ACT so that Dates to show is set to All Dates Also you might

have to press Ctrl-F5 to refresh the view5 To view task details click the button next to the task column on the leftTo view tasks from multiple projects sorted by date1 In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn You might have to adjust the Filter in ACT so that Dates to show is set to All Dates

2 If the Group column is not showing add it by clicking ViewAdd Columns and then double-clickingGroupThe tasks are identified by group (project name)

3 To view task details click the button next to the task column on the leftTips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar as well as in the Task List

You can filter by Selected Users in the Task List and in Groups

After exporting your tasks to ACT you can import them to your Palm Pilot using the ACT Link

See Also

Import ACT Contacts and Users to the People Library

-o-

123

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Outlook

If you use Microsoft Outlook you can export your plan from Project KickStart to Outlook in a click of abutton After you export your plan you see your tasks in the Outlook Tasks view grouped under a categorynamed for your project In Outlook you can track your tasks and email tasks to team members

To export to Microsoft Outlook1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Outlook and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Outlook The Export to Outlook dialog box opens

2 Click an option button to export All tasks Uncompleted tasks or Completed tasks3 If you want to display the tasks you export on your Outlook Calendar click the check box4 Click the Start button A dialog box opens informing you that Project KickStart is trying to access your

Outlook data

5 Allow access for 1 minute and then click the Yes buttonTo view your tasks in Microsoft Outlook1 Click the Outlook Tasks button2 Depending on the version of Outlook you are using set to view the tasks by category In Outlook 2003

click the By Category option button in the Current View list You can also click View on the menu barpoint to Arrange By and then click CategoriesYour project is listed by its project name in the Categories list

3 Click an expand icon to see the complete list of tasks and subtasks

124

copy Experience In Software Inc 1995 - 2006

4 To view task details double-click the task nameTips

The export to Outlook works best if Outlook is already open

In Outlook you can set priorities set reminders and schedule by the hour

If you export to your Outlook Calendar a reminder appears on the due date of each task

After you export tasks to Outlook you can synchronize with your Palm Pilot Windows CE device orother handheld computer

Note

You can export only to Microsoft Office Outlook not Outlook Express

See Also

Import Outlook Contacts to the People Library

-o-

125

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Word

If you use Microsoft Word you can export your plan from Project KickStart to Word in a click of a buttonYour project appears in a Word table in a doc file You can cut and paste change column widths deletecolumns and print from Word

To export to Microsoft Word

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Word andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Word

Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in a Word document in a doc format

2 When youre finished use Save As to save the Word file with a new name such as ltnamegtdoc Forconvenience you can save the file using the same name as your Project KickStart project name

Benefits of using Project KickStart and Word

Communicate projects flexibly After exporting to Word you can communicate your project details ina variety of text formats You can also enhance your document by adding color logos clip art orhyperlinks

Distribute plans to others You can send doc files to other Microsoft Word users via email andrequest comments using Words Send To and Comments features

Tip

Include your strategic plan in documents letters and web pages in a doc or html file

Note

The image of the Gantt chart does not import into Word automatically You can manually import theGantt chart image into a Word document In Word select Insert on the menu bar point to Pictureclick From File and then browse to the folder containing the Gantt chart images you saved By defaultthis is cMy DocumentsProject KickStart ProjectsPKSGanttImages in a folder named for your project

See Also

Export to Word Processors (Other than Word)

Save Gantt Chart Images

126

copy Experience In Software Inc 1995 - 2006

-o-

127

copy Experience In Software Inc 1995 - 2006

Export to Word Processors (Other than Word)

If you are using a word processor other than Microsoft Word you can export your Project KickStart taskreport by first saving it as an HTML or RTF file

To export to word processors other than Microsoft Word

1 Save a Project KickStart task report using HTML or RTF format using the Save As button in the Createand Print Task Reports dialog box

2 Open the file with your word processor

3 Save the file using the Save As command using a different name

See Also

Print Task Reports

Save as HTML

Save as RTF

-o-

128

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Excel

If you use Microsoft Excel you can export your plan from Project KickStart to Excel in a click of a buttonYour project appears in an Excel worksheet in a xls file You can add task details perform calculationsand share your project data with other Excel users

To export to Microsoft Excel1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Excel and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Excel Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in an Excel worksheet in an xls format

2 When youre done select FileSave As to save the Excel file under a new name For convenience youmight want to save it under the same name as your Project KickStart project name

To manually import Gantt chart images into Microsoft Excel1 In Excel click Sheet2 and select ToolsOptions on the menu bar and unclick the box for Gridlines2 Then select Insert on the menu bar point to Picture click From File and then browse to the folder

containing the Gantt chart images you saved By default this is cMy DocumentsProject KickStartProjectsPKSGanttImages in a folder named for your project

3 Select one Gantt chart image at a time to bring it in 4 You can manipulate the size of the image in Excel

Benefits of using Project KickStart and ExcelProject KickStart is very good at scoping out a schedule but there are a few reasons why you might want touse both programs

Data sharing A Project KickStart user might want to share the information with other Excel users whodont have Project KickStart They could change enhance or redistribute their portions of the schedule

129

copy Experience In Software Inc 1995 - 2006

Add more task details Excel users can add new columns of task data that cant be added in ProjectKickStart

Sort task lists For example you could show your projects tasks sorted by each resources namethen see each resources tasks sorted by the tasks start date

Filter tasks Excel can show tasks that meet certain criteria For instance show tasks with the wordtesting in the task name

See Also

Save Gantt Chart Images

-o-

130

copy Experience In Software Inc 1995 - 2006

Export to Microsoft PowerPoint

If you use Microsoft PowerPoint you can export your plan from Project KickStart to PowerPoint in a click ofa button Your project appears as a formatted PowerPoint presentation in a ppt file

To export to Microsoft PowerPoint

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft PowerPointand then click the Go button You can also click File on the menu bar point to Export to and thenclick Microsoft PointPoint

The Export to PowerPoint dialog box opens where you can choose a PowerPoint design template ifyou like

2 Click the Start button

Your tasks days start and finish dates and costs appear in a PowerPoint presentation with an imageof the Gantt chart in one or more slides at the end of your slide show

Once you have created a PowerPoint presentation you can enhance your slides in several ways

Delete slides that are not appropriate for your presentation

131

copy Experience In Software Inc 1995 - 2006

Rearrange the order of the slides

Add colors for emphasis

Add graphics such as company logo clip art and colors

Shorten any long task titles

Benefits of using Project KickStart and PowerPoint

Save time You can dramatically save time in creating a PowerPoint presentation on your project

Present projects to others Present project details in webinars presentations and corporatemeetings Create template presentations or how tos for implementing an installation productintroduction or corporate policy for example

Communicate plans Email project plans in ppt format to colleagues and presentors

Tips

If you use a PowerPoint design template choose one that has a white or light background for maximumlegibility of the Gantt chart in the presentation

The Gantt chart image in the PowerPoint presentation is generated ldquoon the flyrdquo Change the Timescalesettings of the Gantt chart considering how it will be reflected in the number of images of the Ganttchart For example the Day view results in more Gantt chart images than the Months view

-o-

132

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Project

If you use Microsoft Project 98 2000 2002 or 2003 you can export your plan from Project KickStart toProject in a click of a button

To export to Microsoft Project

In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Project andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Project Your tasks assignments days start and finish dates costs done and notes (excluding attachments) appearin a Microsoft Project file

Benefits of using Project KickStart and Microsoft Project

Share data with others Send a project to a colleague or client that expects to see your schedule in anMicrosoft Project format

Schedule tasks with more flexibility Schedule tasks in different durations particularly in less than aday

Track resources Track resource usage and resource leveling and to have greater flexibility in sortingfiltering and reporting project information

Notes

Project KickStart tasks transfer to Microsoft Project as tasks with a Constraint type of Start No EarlierThan This keeps the dates the same as in the Project KickStart schedule

The settings in Project KickStart Working Days Calendar also transfer to Microsoft Project

Exporting to Microsoft Project allows you to take advantage of the advanced tracking and schedulingfeatures that large projects often require

You can also save your Project KickStart projects as an mpx file which you can open in MicrosoftProject and send to other Microsoft Project users Click File on the Project KickStart menu bar clickSave As and then choose mpx as the file type After you save the file click File on the MicrosoftProject menu bar click Open and open your mpx file

-o-

133

copy Experience In Software Inc 1995 - 2006

Export to SureTrak Project Manager

If you use SureTrak Project Manager you can export your plan from Project KickStart to SureTrak ProjectManager

To export to SureTrak Project Manager

1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file

2 In SureTrak click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

SureTrak

You will see your tasks and assignments (but not the notes) appear in a SureTrak file The file is shownin outline view

Benefits of using Project KickStart and SureTrak

Add new information to tasks such as how they are linked

Track progress particularly for comparing plans verses actual results

Have greater flexibility in sorting filtering and reporting project information

Notes

Task notes are not included in the transfer

A version of Project KickStart called the Project KickStart Wizard is included in SureTrak 2 andSureTrak 3 You can use it within SureTrak

See Also

Export MPX Files

-o-

134

copy Experience In Software Inc 1995 - 2006

Export to FastTrack Schedule

If you use FastTrack Schedule you can save your Project KickStart project as an mpx file and import it intoFastTrack ScheduleTo export to FastTrack Schedule1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file2 In FastTrack Schedule click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

FastTrack ScheduleBenefits of using Project KickStart and FastTrack Schedule

Add more task details FastTrack Schedule provides the features and tools needed in many largeprojects

Multiproject reporting Consolidate multiple projects into a master project file

See Also

Export MPX Files

-o-

135

copy Experience In Software Inc 1995 - 2006

Export to Milestones Professional

If you use Milestone Professional you can export your plan from Project KickStart to MilestonesProfessional in a click of a button

To export to Milestone Professional

In the Schedule step click the Export to list arrow below the Gantt chart click MilestonesProfessional and then click the Go button You can also click File on the menu bar point to Export to and then click Milestones Professional

Your tasks assignments start and finish dates and notes (excluding attachments) appear in aMilestones file

Tips

After you export your tasks to Milestones Professional you can create taskbars add titles and performother tasks to produce a presentation-quality schedule You can also use Milestones to track your tasksby showing task durations and percent completions Make scheduling changes by dragging the taskdates

If you have an earlier version of Milestones (eg version 45 or 5) you can save Project KickStart dataas an mpx file and then open the mpx file in Milestones

-o-

136

copy Experience In Software Inc 1995 - 2006

Export to Mindjet MindManager

If you use Mindjet MindManager 7 or later you can export your project plan from Project KickStart in a clickof a button Or you can develop a rough plan in MindManager and export your mind map to ProjectKickStart for enhanced planning It works both ways

To export from Project KickStart to MindManager

In the Schedule step click the Export to list arrow below the Gantt chart click MindManager and thenclick the Go button You can also click File on the menu bar point to Export to and then clickMindManager

Your tasks assignments start and finish dates durations costs Done and notes (excludingattachments) appear in a MindManager file

To export from MindManager to Project KickStart

In MindManager click File on the menu bar point to Send To and then click Project KickStart Thenclick the OK button to start the export

You can also click the Project KickStart icon at the bottom of the MindManager window

Benefits of using Project KickStart and MindManager together

Visualize your plan in two ways Brainstorm plan and communicate your project details in both agraphical and linear style

Develop a graphical plan and then fine-tune the details MindManager uses mindmappingtechniques to develop a high-level plan in a graphical format Export to Project KickStart to enhanceyour plan details by focusing on your projects goals obstacles and resource needs You can alsocreate a Gantt chart schedule

Communicate concepts Project KickStart users can display their plans in a highly graphicalmindmapping format in MindManager The maps make it easier to communicate complex processesand visually identify important tasks issues and relationships

Tip

If you dont already use MindManager you can purchase it in our Thinking Tools Store

-o-

137

copy Experience In Software Inc 1995 - 2006

Export to WBS Chart Pro

If you use WBS Chart Pro you can export your plan from Project KickStart to WBS Chart Pro in a click of abutton

To export to WBS Chart Pro

In the Schedule step click the Export to list arrow below the Gantt chart click WBS Chart Pro andthen click the Go button You can also click File on the menu bar point to Export to and then clickWBS Chart ProYour project is displayed under the project name Each phase in the project is shown in a box with ashadow Each lower level task in a phase is displayed under their respective phase box groupedtogether with the other tasks in that phase

Benefits of using Project KickStart and WBS Chart

Visualize tasks Work with tasks in a tree-style chart called a Work Breakdown Structure (WBS)chart

Communicate your project plan with others WBS Chart uses the outline you create in ProjectKickStart to create a top-down picture of your plan This picture is similar to an Organization chart Butinstead of displaying the structure of your company a WBS chart displays the structure of your projectplan

Notes

WBS Chart refers to the phases in the project as Summary Tasks and the detail for each phase asTasks

The export only works if WBS Chart is not currently running You must close WBS Chart before you cancreate another chart

See Also

Export MPX Files

-o-

138

copy Experience In Software Inc 1995 - 2006

Export MPX Files

The MPX file format is an ASCII format created by Microsoft Project or another program and is used tosend data to and from project management software programs

The following programs can create and open MPX files

FastTrack Schedule

Microsoft Project (95 or 98)

Project KickStart 5

Project KickStart 32

RiskyProject

SureTrak Project Manager

WBS Chart

In these programs you save a project as an MPX file using the Save As command on the File menu Youcan then open an MPX file by using the Open command on the File menu and then specifying the file typeas mpx

For example if you want to move a project from Project KickStart 5 to Project KickStart 32 you can savethe project as an mpx file and then open it in Project KickStart 32

In Microsoft Visio you can create a Visio project time line from Project KickStart To do so you first mustsave your file in Project KickStart as an MPX file Then

1 Start Visio

2 Click File on the menu bar point to New click Business Diagram and then click Project TimelinesWizard

3 Click Next

4 On the second window click Import MPX File to import the Project KickStart mpx file

5 Enter the file location and name or click Browse to locate the file

6 Follow the instructions in the Visio Project Timelines Wizard windows

Tip

If you have difficulty importing the mpx file remove any commas from task names

-o-

139

copy Experience In Software Inc 1995 - 2006

Reference

140

copy Experience In Software Inc 1995 - 2006

Menus

File Menu

Command Keyboard Shortcut Description

New Project Ctrl+N Creates and names a new project fileOpen Project Ctrl+O Opens a previously saved Project KickStart 4 or 5 file

(prx) Project KickStart 3 file (prj) or mpx fileClose Ctrl+W Closes an open Project KickStart fileSave Ctrl+S Saves a project file (prx) in which you made changes Save As Saves a project file with a different file name or different

file format such as MPXPrint Task Reports

Ctrl+T Generates and prints a report letting you preview thecontents

Print Gantt ChartReports

Ctrl+G In the Gantt chart (Schedule step) generates andprints the Gantt chart in the current timescale

Export To Sends the project to another program such asMicrosoft Outlook or ACT 7

Recent file list Lists the last three files opened in Project KickStartExit

Alt+F4 Exits the program

-o-

141

copy Experience In Software Inc 1995 - 2006

Edit Menu

Command Keyboard Shortcut Description

UndoRedo Ctrl+Z Undoes or repeats the last operationCut

Ctrl+X Deletes the currently selected information placing it on theclipboard so you can paste it elsewhere

Copy

Ctrl+C Places a copy of selected information on the Clipboard so youcan paste it elsewhere

Paste

Ctrl+V Places information from the Clipboard to the currently selectedlocation

Select all Ctrl+A Selects all the content in the windowAdd a line Adds a new row where you can enter text

-o-

142

copy Experience In Software Inc 1995 - 2006

View Menu

Command Description

Tool Bar Shows or hides the toolbar (a checkmark indicates thetoolbar is displayed)

Steps Bar Shows or hides the Steps bar (a checkmark indicates the Steps bar is displayed)

Name Go to the Name your project stepPhases Go to Phases stepGoals Go to Goals stepSimilar Projects Go to Similar projects stepPeople Go to People stepObstacles Go to Obstacles stepAssign Go to Assign tasks to people stepTasks Go to Tasks stepSchedule Go to Schedule step

-o-

143

copy Experience In Software Inc 1995 - 2006

Tools Menu

Command Keyboard Shortcut Description

Spelling

F7 Checks spelling of project dataexcept for names of people

Collaboration To access or find out aboutGoToMeeting

Options Select options for running thesoftware

-o-

144

copy Experience In Software Inc 1995 - 2006

Options

-o-

145

copy Experience In Software Inc 1995 - 2006

Data Menu

The Data menu is available in the Tasks and Schedule steps for manipulating tasks and creating ascheduleCommand Description

Move Up Moves the selected task item upMove Down Moves the selected task item downOutdent Moves the selected task item to the leftIndent Moves the selected task item to the rightInsert Task Insert task in row aboveInsert SubTask Insert subtask below current rowDelete Task Delete current taskEdit Task Properties Brings you to an edit screen where you can edit task

name change assignments and edit task notesEdit Notes Brings you to an edit screen for editing task notesColor Taskbars Change the color of selected tasks (in Schedule)Change Working Days Select which days are working and which are

nonworking (in Schedule)Link Tasks Link tasks in Gantt chart (Pro Users)Unlink Tasks Unlink tasks in Gantt chart (Pro Users)

-o-

146

copy Experience In Software Inc 1995 - 2006

Timescale Menu

The Timescale menu is available in the Schedule step so you can change the display of the Gantt chartschedule

Command Description

Days Displays a daily schedule in theGantt chart

Weeks Displays a weekly schedule inthe Gantt chart

Months Displays a monthly schedule inthe Gantt chart

Quarters Displays a quarterly schedule inthe Gantt chart

Years Displays a yearly schedule inthe Gantt chart

-o-

147

copy Experience In Software Inc 1995 - 2006

Help Menu

Command Description

Project KickStart Help Help for Project KickStart including a Table ofContents and index of terms

Online Tutorials View several Getting Started Tutorials to getyou started with Project KickStart whether youare a new or experienced user

Keyboard Shortcuts Shortcuts for programTechnical Support How to obtain Technical Support for Project

KickStart via web form and email[Send Log to Technical Support] If the program detects an error it writes a log

of technical issues Click Send Log toTechnical Support to send the error log to us

ProjectKickStartcom Visit the Project KickStart Web siteGet Latest Version See what the latest published version is and

download it if you need itAbout Project KickStart Shows Project KickStart version number build

date copyright and system information

-o-

148

copy Experience In Software Inc 1995 - 2006

Shortcuts

Use the following keyboard shortcuts to move quickly around in Project KickStart

Navigation

Move forward to the next window Alt+NMove back to the previous window Alt+BSteps

Go to Name step Alt+MGo to Phases step Alt+SGo to Goals step Alt+GGo to Similar step Alt+RGo to People step Alt+PGo to Obstacles step Alt+OGo to Assign step Alt+IGo to Tasks step Alt+KGo to Library (Phases Tasks GoalsPeople Obstacles)

Alt+L

Menus

File menu Alt+FEdit menu Alt+EView menu Alt+VShow menu (Tasks step) Alt+WOutline menu (Tasks step) Alt+UTimescale (Schedule step) Alt+CHelp menu Alt+H F1Other

Edit tasks assignments amp notes (Tasks step)F3Save Ctrl+SPrint Task Report Ctrl+PPrint Gantt Chart (Schedule step) Ctrl+GCut Ctrl+XCopy Ctrl+CPaste Ctrl+VInsert Row InsertDelete Row DeleteInsert Line Break (in Notes in Task List andSchdule steps)

Enter

Spell Check

Ignore Alt+IIgnore All Alt+GChange Alt+CChange All Alt+HHelp

149

copy Experience In Software Inc 1995 - 2006

Contents in Help Alt+CIndex Alt+IBack in Help Alt+BClose Help Alt+LHelp about the current step Alt+H

-o-

150

copy Experience In Software Inc 1995 - 2006

Share Project KickStart Data

Project KickStart makes it easy to share data with other people involved with a project You can share yourProject KickStart data in the following ways

Send a printed report Make a PowerPoint presentation Send a file (prx html rtf mpx) Post an HTML file to a Web site and access it with your web browser Export to other programs such as Microsoft Word or Excel and send data in a format the recipient can

access (such as doc xls or mpx)

Note

You can also collaborate with a colleague by conducting an online meeting using GoToMeeting (Prousers)

-o-

151

copy Experience In Software Inc 1995 - 2006

Open a Project

After you create a project and save it in a prx prj or mpx file using Project KickStart or other softwareyou can open the project in Project KickStartTo open a project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click a file type (prxprj or mpx)

3 Navigate to the folder that contains the file4 Double-click the name of the file

Opening a Project KickStart 3 prj file converts it to a prx file

Generally prj files are stored in cprogram filesProject KickStart 3

The tasks in the converted Project KickStart 5 file will have the same start and finish dates anddurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way To have weekends as non working days open the working days calendar and markweekends as non working

Opening a mpx file converts it to a prx file

The tasks in each project have the same start and finish dates and durations

-o-

152

copy Experience In Software Inc 1995 - 2006

Dedication

I dedicate this software program to my new colleague

Kevin Ahlvin

Roy A Nierenberg President

-o-

153

copy Experience In Software Inc 1995 - 2006

Credits and Trademarks

Credits

Missak Koumoudjian Program Architect and Chief Programmer

Kevin Ahlvin Interface DesignAnn Kawamoto Quality AssuranceAlexander Setzepfandt Quality AssuranceJackie LeungJeffrey Chow

Programming Interns

Kevin Ahlvin Product Supervisor and CoordinatorJoseph Fusco Project Management Consultant and content

providerLisa RuffoloJoseph Fusco

Help System

Roy A Nierenberg President

Trademark

Project KickStart and Project KickStart Wizard are trademarks of Experience In Software Inc in the UnitedStates andor in other countries All rights reserved All other trademarks mentioned herein are the propertyof their respective owners

-o-

154

copy Experience In Software Inc 1995 - 2006

Uninstalling

You can uninstall Project KickStart 5 through the Control Panel AddRemove Programs Select ProjectKickStart 5 This starts the InstallShield Maintenance Program You should then remove all of theprogram files that were installed It will not erase your Project KickStart prx data files

If that does not work you can delete the Project KickStart files manually

Note

If you purchased Project KickStart and you want to return it for a refund follow the instructions forDe-activating the software at httpwwwprojectkickstartcomcontactreturnscfm

-o-

155

copy Experience In Software Inc 1995 - 2006

Using Past Projects

You can use past projects in two ways

If you have projects that are similar you can use a past project as a template for a new project In theWelcome window select Open a Project Open that project and Save As under a different name Nowyou can open up the renamed project and modify it for the current project

You can draw from several projects in the Similar Projects step First select projects that are similarand click Next Then select tasks from those projects and decide where they would fit into your currentproject

See Also

Opening a project Compatibility with earlier versions

-o-

156

copy Experience In Software Inc 1995 - 2006

Index

- - Change Working Schedule 85

- -prj file format 13

- A -About Linking Tasks (Pro Users) 59About Scheduling Tasks 55About the Gantt Chart 57ACT 120 92 122ACT 6 92 122ACT 7 or later 92 120Activate 14Activating Trial Version 14Add a New Person or Resource 39add a subtask 83add a task 83Add a Task or Subtask 47Add or Change Task Assignments 51Add or Change Task Details 52Add Subtask 63Add Task 63Add URL 49Additional Features in Task Data View (Pro Users) 68Additional Tools in Chart View (Pro Users) 71Adobe PDF 117Assignments tab 80Attachments 49Autolink tasks (Pro Users) 58

- B -Back 10borrow tasks 29

- C -Change Details for Linked Tasks (Pro Users) 81Change Project Start 63Change Task Dates 73Change Task Details 80Change the Appearance of the Task List 43Change the Display of the Schedule 61Change Timescale 63Change Working Schedule 63Chart view 57

157

copy Experience In Software Inc 1995 - 2006

Cloning projects 155Color 63 86Compatibility 13Compatibility with earlier versions 13convert projects 13Coordination 12Create and Print Task Reports 102Credits 153Credits and Trademarks 153critical path 88CSV 96Customer support 20Customer Support 20Customizing Project KickStart

- D -Dashboard 99Data Menu 145Dedication 152Delete 63delete a task 83demote 46dependencies 12 76

- E -Edit Menu 141Edit Notes and Attachments 63Edit or Substitute People 40Edit Task Information 63Email Task Reports 108End User License Agreement 16error 21Error Messages 21export from MindManager 136Export MPX Files 138Export to ACT 6 122Export to ACT 7 and Later 120Export to FastTrack Schedule 134Export to Microsoft Excel 128Export to Microsoft Outlook 123Export to Microsoft PowerPoint 130Export to Microsoft Project 132Export to Microsoft Word 125Export to Milestones Professional 135Export to Mindjet MindManager 136Export to SureTrak Project Manager 133Export to WBS Chart Pro 137

- F -FastTrack Schedule 134File Menu 140Fit to page 111Fit to Smallest Size 111

158

copy Experience In Software Inc 1995 - 2006

- G -Gantt chart 55 57General tab 80Goal 26Goal statements 26Goals 26Goals - Step 1 of 3 26Goals - Step 2 of 3 27Goals - Step 3 of 3 28goals library 26 89Goalsadd 26Goalsdelete 26Goalsedit 26Goalstasks for 27GoToMeeting 150 12

- H -Handouts 111Help Menu 147hyperlink 49

- I -Import ACT 92import contacts and users 92import Outlook contacts 94Import Outlook Contacts via CSV to the People Library (Pro Users) 96ImportCSVToPKSexe 96Indent 46Individual Assignments 102Introduction 7Introduction 7

- K -Knowledge Libraries 90

- L -lag time 81lead time 59 81library 89License Key 14link 59Link lines 59Link tasks 12 65linked tasks 59

- M -major activities 24Make Tasks Overlap (Pro Users) 87Manage a Library 90

159

copy Experience In Software Inc 1995 - 2006

Menu 140Microsoft Excel 128Microsoft Outlook 123Microsoft PowerPoint 130Microsoft Project 132Microsoft Project (95 or 98) 138Microsoft Visio 138Microsoft Word 125Milestone 69 79Milestones Professional 135Mindjet MindManager 136MindManager 136

- N -Name 23Name Your Project 23Navigating Project KickStart 10Next 10Notes and Attachments tab 80

- O -Objectives 26Obstacles 34Obstacles - Step 3 of 3 36Obstacles Library 89Open a Project 151Options 144Outdent 46Outdent and Indent arrows 63Outlook Calendar 123Overview

- P -Page Setup 107 116 100PDF 117people 31People - Step 3 of 3 28People Library 91phase 24phase dates 75Phase Dates Cannot Be Edited 75phases 24Phases - Step 1 of 2 24Phases - Step 2 of 2 25Phases Library 89Phases Goals People amp Obstacles 102PowerPoint presentation 130Pred 68Predecessor 68Predecessor tasks 59predecessors 76Print a Gantt Chart 111Print Dashboard Reports 99Print Preview 105Print Preview a Gantt Chart 115Print Reports 98Print Task Reports 102

160

copy Experience In Software Inc 1995 - 2006

Printer Setup 106Printing to an Adobe PDF file 117prj 13Pro 145Pro Edition 145Product support 20Project 23Project KickStart 3 prj file 151Project KickStart for Windows 7project name 23project start date 73project template 155project title 23promote 46promote and demote tasks 83

- Q -Quick Tour of Working with Linked Tasks (Pro Users) 76

- R -Red vertical line 69Redo 11Register Project KickStart 22Registering Project KickStart 22remove people 38Remove People from a Task 38reorder tasks 83Reorganize Tasks in Task Data View 83Repeat tasks on every page (for handouts) 111Reporting Technical Issues 21resource 31resources 31restore 34return 154risks 34RiskyProject 138

- S -Save As 101Save as HTML 109Save as RTF 110Save Gantt Chart Images 118Schedule 55Send Error Report 21similar projects 29spelling 53starter schedule 55Steps 7subtask 47Subtasks 46Succ 68Successor 68Successor tasks 59successors 76Summary bar 69Support 20SureTrak Project Manager 133

161

copy Experience In Software Inc 1995 - 2006

- T -Task Data view 57task dates 73Task Report 102Taskbar 69Taskbar with percent done 69Tasks 25Tasks in Phases 25Tasks Library 89team 31Technical support 20timescale 84Timescale Menu 146Tools Menu 143Trademark 153trademarks 153Trial 14

- U -unassigning 38Understand Chart View 69Understand Task Data View 66Undo 11UndoRedo Buttons 11uninstallUninstalling 154Unlink tasks 12 65Up and Down arrows 63Use Project KickStart to 8Use the Gantt Chart Toolbar 63Use the Planning Wizard 9Uses 8Using Past Projects 29 155

- V -Version View Menu 142Visio 138

- W -Wall chart 111WBS Chart Pro 137Welcome to Project KickStart 7Whats Due Next Month 99Whats Due Next Week 99Whats Due Today 99Whats New in Project KickStart Pro 5 11Windows Vista 20

162

copy Experience In Software Inc 1995 - 2006

copy Experience In Software 2008w w w projectkickstartcom

  • Table of Contents
  • Start Here Welcome to Project KickStart
    • Introduction
      • Welcome to Project KickStart
      • Use Project KickStart to
      • Use the Planning Wizard
      • Navigating Project KickStart
      • Whats New in Project KickStart Pro 5
      • Whats New in Project KickStart Pro 5 (Pro Users)
      • Compatibility with earlier versions
      • Activating Trial Version
        • Licenses and Support
          • End User License Agreement
          • Customer Support
          • Reporting Technical Issues
          • Register Project KickStart
              • Planning Projects
                • Name Your Project
                • Phases - Step 1 of 2
                • Phases - Step 2 of 2
                • Goals - Step 1 of 3
                • Goals - Step 2 of 2
                • Goals - Step 3 of 3
                • Similar Projects - Step 1 of 2
                • Similar Projects - Step 2 of 2
                • People - Step 1 of 3
                • People - Step 2 of 3
                • People - Step 3 of 3
                • Obstacles - Step 1 of 3
                • Obstacles - Step 2 of 3
                • Obstacles - Step 3 of 3
                  • Assigning People
                    • Assign Tasks to People
                    • Remove People from a Task
                    • Add a New Person or Resource
                    • Edit or Substitute People
                      • Organizing the Project Plan
                        • About Organizing Tasks
                        • Change the Appearance of the Task List
                        • Show or Hide Tasks in the Task List
                        • Move Tasks within the Task List
                        • Outdent and Indent Tasks
                        • Add a Task or Subtask
                        • Edit Tasks
                        • Add Task Notes and Attachments
                        • Add or Change Task Assignments
                        • Add or Change Task Details
                        • Check Spelling
                          • Scheduling Tasks in the Gantt Chart
                            • Scheduling Overview
                              • About Scheduling Tasks
                              • About the Gantt Chart
                              • Autolink tasks (Pro Users)
                              • About Linking Tasks (Pro Users)
                              • Change the Display of the Schedule
                              • Use the Gantt Chart Toolbar
                              • Use the Gantt Chart Toolbar (Pro Users)
                              • Understand Task Data View
                              • Additional Features in Task Data View (Pro Users)
                              • Understand Chart View
                              • Additional Tools in Chart View (Pro Users)
                                • Change Task Dates
                                • Phase Dates Cannot Be Edited
                                • Quick Tour of Working with Linked Tasks (Pro Users)
                                • Link and Unlink Tasks (Pro Users)
                                • Create a Milestone
                                • Change Task Details
                                • Change Details for Linked Tasks (Pro Users)
                                • Reorganize Tasks in Task Data View
                                • Change the Timescale of the Schedule
                                • Specify Working Days
                                • Change the Color of Taskbars
                                • Make Tasks Overlap (Pro Users)
                                • Manage Changes in Your Schedule (Pro Users)
                                  • Managing Libraries
                                    • Use a Library
                                    • Manage a Library
                                    • Manage the People Library
                                    • Import ACT Contacts and Users to the People Library
                                    • Import Outlook Contacts to the People Library
                                    • Import Outlook Contacts via CSV to the People Library (Pro Users)
                                      • Printing Reports
                                        • Printing Dashboards
                                          • Print Reports
                                          • Print Dashboard Reports
                                          • Page Setup
                                          • Save As
                                            • Printing Task Reports
                                              • Print Task Reports
                                              • Print Preview
                                              • Printer Setup
                                              • Page Setup
                                              • Email Task Reports
                                              • Save As HTML
                                              • Save As RTF
                                                • Printing Gantt Chart Reports
                                                  • Print a Gantt Chart
                                                  • Print Preview a Gantt Chart
                                                  • Page Setup
                                                  • Printing to an Adobe PDF file
                                                  • Save Gantt Chart Images
                                                      • Export Project Data
                                                        • Export to ACT
                                                          • Export to ACT 7 and Later
                                                          • Export to ACT 6
                                                            • Export to Microsoft Outlook
                                                            • Export to Microsoft Word
                                                            • Export to Word Processors (Other than Word)
                                                            • Export to Microsoft Excel
                                                            • Export to Microsoft PowerPoint
                                                            • Export to Microsoft Project
                                                            • Export to SureTrak Project Manager
                                                            • Export to FastTrack Schedule
                                                            • Export to Milestones Professional
                                                            • Export to Mindjet MindManager
                                                            • Export to WBS Chart Pro
                                                            • Export MPX Files
                                                              • Reference
                                                                • Menus
                                                                  • File Menu
                                                                  • Edit Menu
                                                                  • View Menu
                                                                  • Tools Menu
                                                                  • Options
                                                                  • Data Menu
                                                                  • Timescale Menu
                                                                  • Help Menu
                                                                    • Shortcuts
                                                                    • Share Project KickStart data
                                                                    • Open a Project
                                                                    • Dedication
                                                                    • Credits and Trademarks
                                                                    • Uninstalling the software
                                                                    • Using Past Projects
Page 10: Project KickStart Help File in PDF format

10

copy Experience In Software Inc 1995 - 2006

Navigating Project KickStart

When you use the Planning Wizard you work with a step window similar to the following illustration

Steps bar Click a step button to perform a step in the Planning Wizard The selected button shows yourcurrent step

Name of your project Shows the name entered in the Name step

Menu bar Select options from the menu bar to work with your projects

Toolbar Click buttons to perform common tasks such as saving your project

Step instructions Indicate how to perform the current step

Library button Click to open a library for the current step For example click the Goals Library button toopen a library listing typical project goals

Back and Next buttons Click a button to return to the previous step or continue to the next step in thePlanning Wizard

Advisor button Click to see instructions tips and notes for completing the current step

-o-

11

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5

The following table outlines whatrsquos new in Project KickStart Pro 5

If you own a previous version of Project KickStart yoursquoll notice the new Pro version has a new look and feelAs you begin to check it out yoursquoll soon discover Project KickStart Version 5 is a lot more powerful thanprevious versions and comes with some great new features

FEATURE DESCRIPTION IMPROVED

NEW

Dashboard Reporting

Quickly assess what is due TodayNext Week or Next Month

X

Import Contacts Import from a comma separatedvalue (CSV) file

X

Templates Use as is or customize X

Gantt Chart Greater stability and functionality X

User Interface Contemporary look and colorscheme

X

Preferences Customize look and feel andprogram defaults

X

Productivity Pack Project template Word docs fornewbies

X

Exports Improved Outlook MindManager and ACTimproved data exchange

X

-o-

12

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5 (Pro Users)

This feature is available only in Project KickStart Professional

The following table outlines whatrsquos new in Project KickStart Pro 5

FEATURE DESCRIPTION IMPROVED NEW

Gantt Chart Task dependencies in Gantt chart X

Link tasks Show task dependencies X

Unlink tasks Remove task dependencies X

Add predecessors Add task predecessors X

Add successors Add task successors X

Project Coordination Link to GoToMeeting for onlinemeetings on projects

X

Project KickStart Pro now includes dependencies on the Gantt chart This sophisticated scheduling andproject management tool is new to Project KickStart Pro and is designed to make complex projectscheduling easy and straightforward

Use dependencies to handle scheduling demands delays and surprises without modifying every task inyour project Dependencies let you make adjustments as events change giving you a more robust scheduleand the opportunity to conduct what-if analysis

Suppose you are managing a landscaping project involving subcontractors and dozens of tasks One ofyour first tasks is to pave a path with flagstones but the shipment of flagstones is two days late Usingdependencies you can delay the path-paving task in a couple of clicks and Project KickStart Proautomatically updates the schedule for the remaining tasks

Although dependencies meet your advanced scheduling needs the Project KickStart Pro approach todependencies keeps them as simple as possible If you want to link a couple of tasks which are dependenton one another you can simply highlight the tasks and click the link icon

If you select the option of Autolinking tasks then when you display the Gantt chart the first time all tasksare pre-linked allowing you to adjust durations schedules of individual tasks and time between taskswhich is called Lead Time in Project KickStart Pro

Unlike other project management programs such as Microsoft Project Project KickStart Pro does notburden you with complicated error messages and various types of dependencies It provides only one typeof dependency finish-to-start which is the most common type This means you can fine-tune your scheduleas soon as you open the Gantt chartmdashwithout having to learn technical terms or advanced projectmanagement techniques

The Project Coordination functionality that we are providing is through GoToMeeting and is a chargedservice

Note

These features are in addition to those listed on the Whatrsquos New in Project KickStart 5 page

-o-

13

copy Experience In Software Inc 1995 - 2006

Compatibility with earlier versions

Project KickStart 5 can open and save projects in Project KickStart 4 prx file format (Same as ProjectKickStart 5)

Project KickStart 5 can open and convert projects saved in Project KickStart 3 prj file format You need tohave a licensed copy of Project KickStart 3 on your system to make the conversion

To open a prj project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click prj file type3 Navigate to the folder that contains the prj file Generally prj files are stored in cprogram filesProject

KickStart 34 Double-click the name of the file

Tips

The tasks in the converted Project KickStart 5 file will have the same start and finish dates and samedurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way (ie as working days) To have weekends as non working days click the Change WorkingSchedule button on the Gantt chart toolbar and mark weekends as non working

Note

Project KickStart 5 does not open and convert prj files from Project KickStart 1 or 2

-o-

14

copy Experience In Software Inc 1995 - 2006

Activating trial version

You may have obtained a FREE 20-day trial version of Project KickStart 5 from our website or from areseller

To convert your Trial Version to a Full Version youll need to purchase a License Key and to activate thesoftware

To activate Project KickStart 5 trial1 Start the Project KickStart trial

2 If you have not purchased your License Key yet click the Buy button to purchase online3 If you have purchased a License Key click the Activate button and copy and paste the License Key

that you received when you purchased Project KickStart as well as your name and email

15

copy Experience In Software Inc 1995 - 2006

4 You must be connected to the Internet and you must tell your Firewall to allow communication forPKS5Kickstartexe

Tip

Your License Key allows 2 activations per user One is for your primary computer and one is for asecond computer you use such as your laptop or home computer

-o-

16

copy Experience In Software Inc 1995 - 2006

Licenses and Support

End User License Agreement

EXPERIENCE IN SOFTWARE INC END USER LICENSE AGREEMENT AND WARRANTYDISCLAIMER

PROJECT KICKSTARTtrade STANDARD 5 AND PRO 5 EDITIONS

NOTICE This is a legally binding contract between you the end user and EXPERIENCE IN SOFTWAREINC

EXPERIENCE IN SOFTWARE INC (EIS or LICENSOR) LICENSES THE ENCLOSED SOFTWARETO YOU (USER or LICENSEE) ONLY UPON THE CONDITION THAT YOU ACCEPT ALL OF THETERMS CONTAINED IN THIS LICENSE AGREEMENT PLEASE READ THE TERMS CAREFULLY BYOPENING THIS PACKAGE BREAKING THE SEAL CLICKING ON THE ldquoAGREErdquo OR ldquoYESrdquo BUTTONOR OTHERWISE INDICATING ASSENT ELECTRONICALLY OR LOADING THE SOFTWARE YOUAGREE TO THE TERMS AND CONDITIONS OF THIS AGREEMENT IF YOU DO NOT AGREE TOTHESE TERMS AND CONDITIONS CLICK ON THE ldquoI DO NOT AGREErdquo ldquoNOrdquo BUTTON OR MAKE NOFURTHER USE OF THE SOFTWARE IF YOU DO NOT AGREE TO THESE TERMS THEN EIS ISUN-WILLING TO LICENSE THE SOFTWARE TO YOU IN WHICH EVENT YOU SHOULD RETURN THEFULL PURCHASED PRODUCT WITH PROOF OF PURCHASE TO LICENSOR OR THE DEALER FROMWHOM IT WAS ACQUIRED WITHIN 15 DAYS OF PURCHASE AND YOUR MONEY WILL BEREFUNDED

LICENSE AND WARRANTY

The software that accompanies this license (Software) is the property of EIS and is protected by copyrightand other intellectual property law Although EIS at all times owns the Software you will have certain rightsto use the Software after your acceptance of this license Except as may be modified by an addendumwhich may accompany or be added to this license your rights and obligations with respect to the use of thisSoftware are as follows

You may

(i) install and use one copy of the specified edition of Software and documentation on a single computerand only by one user (ldquoPrimary Userrdquo) If you have purchased multiple licenses for the Software asindicated as Quantity or Number of Licenses on the Invoice or electronic confirmation issued by EIS orits Resellers then at any time you may have as many copies of the Software in use as you have licenses The Software is ldquoin userdquo on a computer when it is loaded into the temporary memory (ie RAM) or installedinto the permanent memory (eg hard disk CD-ROM or other storage device) of that computer

(ii) install and use a second copy of the Software on a second computer for the limited and exclusive use ofthe Primary User

(iii) use the Software on a network provided that Licensee has a licensed copy of the Software for eachnamed user that can access the Software over that network

(iv) make one copy of the Software for archival purposes or copy the Software onto the hard disk of yourcomputer and retain the original for archival purposes

(v) after written notice to EIS transfer the Software on a permanent basis to another person or entityprovided that you retain no copies of the Software and the transferee agrees to the terms of this agreement

You may not

(i) rent lease copy distribute license or otherwise transfer the Software or its documentation to any otherparty Licensee may make a reasonable number of back-up copies for archival purposes only TheSoftware contains copyrighted material trade secrets and other proprietary material If Licensee has theright to duplicate the Software for multiple Users then Licensee must reproduce on all such copies of theSoftware the copyright notices and any other proprietary legends that were on the original copy of theSoftware or

(ii) decompile reverse engineer disassemble translate make any attempt to discover the source code ofthe Software or otherwise reduce the Software to a human perceivable form or modify network or create

17

copy Experience In Software Inc 1995 - 2006

derivative works based upon the Software or the documentation in whole or in part nor permit any otherparty to do so

Notwithstanding anything herein if the Software is lawfully acquired outside of the United States within ajurisdiction which is a member of the European Union subject to the EEC Council Directive 91250EEC ofMay 14 1991 Licensee agrees that within that jurisdiction it shall not and shall not allow any party onLicensees behalf to attempt to reverse engineer or decompile the Software into another computerlanguage except as expressly and specifically provided in the EEC Council Directive 91250EEC of May14 1991 Any and all information obtained during such lawful reverse engineering andor decompilingactivities including but not limited to the organization logic algorithms and processes of the Softwareshall be deemed to be the confidential and proprietary information of EIS

Licensee shall not make copies of the copyrighted Software documentation without the prior writtenpermission of EIS provided that for electronic transactions Licensee may make one (1) hard copy of suchdocumentation for each User

Intellectual Property and Duplication of Software

The Software contains copyrighted material trade secrets and other proprietary material If Licensee hasthe right to duplicate the Software for multiple Users then Licensee must reproduce on all such copies ofthe Software the copyright notices and any other proprietary legends that were on the original copy of theSoftware

Upgrades

To use a Product identified as an upgrade you must first be licensed for the product identified by EIS aseligible for the upgrade After upgrading you may no longer transfer the product that formed the basis foryour upgrade eligibility to another person or entity

Technical Support

Licensee must register the Software in order to be eligible for free technical support (including installationand registration of the product) during the first 90 days after purchase

Thirty Day Money Back Guarantee

If you are the original Licensee of this copy of the Software and are dissatisfied with it for any reason youmay return the complete product together with your receipt to EIS or an authorized dealer postageprepaid for a full refund at any time during the thirty-day period following the delivery to you of thePurchased Software

Export Law Assurances

You are responsible for complying with all trade regulations and laws both foreign and domestic Youacknowledge that none of the Software or underlying information or technology may be downloaded orotherwise exported or re-exported (i) into Afghanistan (Taliban-controlled areas) Cuba Iran Iraq LibyaNorth Korea Serbia (except Kosovo) Sudan and Syria or any other country subject to a US embargo or(ii) to anyone on the US Treasury Departments list of Specially Designated Nationals or the USCommerce Departments Denied Parties List or Entity List By using the Software you are agreeing to theforegoing and are representing and warranting that (i) no US federal agency has suspended revoked ordenied you export privileges (ii) you are not located in or under the control of a national or resident of anysuch country or on any such list and (iii) you will not export or re-export the Software to any prohibitedcounty or to any prohibited person entity or end-user as specified by US export controls as defined byEAR 15 CFR Parts 730-774 and BXA (httpwwwbxadocgov)

Data Collection and Privacy Policy

You acknowledge and agree that EIS may collect and retain information about you such as your nameaddress and e-mail address You also understand that EIS may employ other companies to performfunctions on our behalf such as fulfilling orders delivering packages sending postal mail and e-mailproviding marketing assistance and processing credit card payments These companies may have accessto personal information needed to perform their functions and may not use such information for otherpurposes By assenting to this agreement you agree that you have read and understand our Privacy PolicyFor more detailed information httpwwwprojectkickstartcomhtmlprivacy_statementhtm

Termination

This License is effective until terminated Licensee may terminate this License at any time by destroying allcopies of the Software and its documentation This License will terminate immediately without notice from

18

copy Experience In Software Inc 1995 - 2006

EIS if Licensee fails to comply with any provision of this License Upon termination Licensee must destroyall copies of the Software and its documentation and cease and desist from any further use of the Software

Limited Warranty

EIS warrants that the media on which the Software is distributed will be free from defects and that theSoftware shall perform substantially as described in its documentation for a period of sixty (60) days frompurchase Your sole remedy in the event of a breach of this warranty will be that EIS will replace anydefective media returned to EIS within the warranty period EIS does not warrant that the Software willmeet your requirements or that operation of the Software will be uninterrupted or that the Software will beerror-free

THE ABOVE WARRANTY IS EXCLUSIVE AND IN LIEU OF ALL OTHER WARRANTIES WHETHEREXPRESS OR IMPLIED INCLUDING THE IMPLIED WARRANTIES OF MERCHANTABILITY FITNESSFOR A PARTICULAR PURPOSE AND NONINFRINGEMENT OF INTELLECTUAL PROPERTY RIGHTSTHIS WARRANTY GIVES YOU SPECIFIC LEGAL RIGHTS YOU MAY HAVE OTHER RIGHTS WHICHVARY FROM STATE TO STATE AND COUNTRY TO COUNTRY

Disclaimer of Damages

REGARDLESS OF WHETHER ANY REMEDY SET FORTH HEREIN FAILS OF ITS ESSENTIALPURPOSE IN NO EVENT WILL EIS OR ITS RESELLERS BE LIABLE TO YOU FOR ANY SPECIALCONSEQUENTIAL INDIRECT OR SIMILAR DAMAGES INCLUDING BUT NOT LIMITED TO ANY LOSTPROFITS OR LOST DATA ARISING OUT OF THE USE OR INABILITY TO USE THE SOFTWARE EVENIF EIS HAS BEEN ADVISED OF THE POSSIBILTIY OF SUCH DAMAGES SOME STATES DO NOTALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FOR INCIDENTAL OR CONSEQUENTIALDAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAY NOT APPLY TO YOU IN NO CASESHALL EISS ITrsquoS RESELLERrsquoS LIABILITY EXCEED THE PURCHASE PRICE FOR THE SOFTWARE

SOME STATES AND COUNTRIES INCLUDING MEMBER COUNTRIES OF THE EUROPEANECONOMIC AREA DO NOT ALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FORINCIDENTAL OR CONSEQUENTIAL DAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAYNOT APPLY TO YOU

The disclaimers and limitations set forth above will apply regardless of whether you accept the Software

US Government Restricted Rights

DISTRIBUTION TO THE US GOVERNMENT This Software is commercial software developedexclusively at private expense This Software and the documentation are provided with RESTRICTEDRIGHTS applicable to private and public licenses alike Use duplication or disclosure by civilian agenciesof the US Government shall be in accordance with the Commercial Computer Software-Restricted Rightsclause at FAR 52227-19 Use duplication or disclosure by Department of Defense agencies is subjectsolely to the terms of this software licensing agreement pursuant to DFARS 2277202Contractormanufacturer of the Software is EXPERIENCE IN SOFTWARE INC 2029 Durant AveBerkeley CA 94704 USA

General

This Agreement shall be governed by the laws of the State of California without giving effect to principles ofconflict of laws You hereby consent to the exclusive jurisdiction and venue of the state courts sitting in SanFrancisco County California or the federal courts in the Northern District of California to resolve anydisputes arising under this Agreement This Agreement contains the complete understanding between theparties with respect to the subject matter hereof and supersedes all prior or contemporaneous Agreementsor understandings whether oral or written You agree that any varying or additional terms contained in anypurchase order or other written notification or document issued by you in relation to the Software licensedhereunder shall be of no effect No provision hereof shall be deemed waived or modified except in writing No EIS dealer agent or employee is authorized to make any amendment to this Agreement

The intellectual property protections the disclaimers of warranties and the limitation of damages shallsurvive termination The failure or delay of EIS to exercise any of its rights under this Agreement or uponany breach of this Agreement shall not be deemed a waiver of those rights or of the breach If any provisionof this Agreement is held invalid the remainder of this Agreement will remain in full force and effect

Should you have any questions concerning this Agreement or if you desire to contact EIS for any reasonplease write to EXPERIENCE IN SOFTWARE INC 2029 Durant Ave Berkeley CA 94704 USA

-o-

19

copy Experience In Software Inc 1995 - 2006

20

copy Experience In Software Inc 1995 - 2006

Customer Support

When you need help in solving a problem with the software Experience In Software is available to assistyou First check this help file for information on the part of the program you are having a problem withAlso take a look at the Web site for late-breaking technical support information wwwprojectkickstartcomsupporttechnical_supportcfm If you are a regustered user you can obtain support in the following ways

Web httpwwwprojectkickstartcomsupportemail_supportcfm E-mail supportprojectkickstartcom

Hours 900 am to 500 pm Pacific time Monday - Friday

To make the support process more efficient have the following information ready for the support staff

Provide your name phone number and email address

Describe the problem including any error messages

If reporting a potential bug describe what you did immediately before seeing the bug

Provide the Project KickStart version number and Build Date (Click Help on the menu bar and thenclick About Project KickStart)

Identify the version of Windows (Windows Vista etc) you are using

Notes

Our policy is to respond to support email within two business days If you have not received aresponse please double check that spam filters are blocking our messages to you If you maintain anincoming whitelist please allow all messages from the projectkickstartcom domain

Support is available in English only If you purchased a translated version please contact your localreseller for help in other languages

See Also

Reporting Technical Issues

-o-

21

copy Experience In Software Inc 1995 - 2006

Reporting Technical Issues

If Project KickStart 5 detects an error it will write a log of technical issues and then create a temporarymenu to the right of the Help menu which says Send Log to Technical Support You should immediatelyclick the menu and then click Yes to send the error log to us

Please fill in your email address so that we can get back to you with any questions about what caused theerror

Tip

If you have an Internet Security Program such as Norton Internet Security please allowPKS5Kickstartexe to communicate with the Internet to report the error

-o-

22

copy Experience In Software Inc 1995 - 2006

Register Project KickStart

To print this page click the Print button on the Help window toolbar

Register Project KickStart 5 for technical support upgrade information and software discounts You canregister by completing printing and then sending or faxing this form to Experience In Software You canalso register online at httpwwwprojectkickstartcomsupportregiscfm

Name _______________________________________________________

Title _______________________________________________________

Company _______________________________________________________

Address _______________________________________________________

CityStateZip ______________________________________________________

Country _______________________________________________________

Day Phone _______________________________________________________

Fax _______________________________________________________

E-mail _______________________________________________________

Purchased from __ Experience In Software __ Other ____________________

Number of people in company _ 1 to 25 _ 26 to 100 _ 101 to 1000 _ Over 1000

Which industry do you work in ______________________________________

Interested in a project management workshop for your company __ Yes __ No

Comments _______________________________________________________

_________________________________________________________________

_________________________________________________________________

Experience In Software 2029 Durant Ave Berkeley CA 94704

Send or FAX to (510) 644-3823

-o-

23

copy Experience In Software Inc 1995 - 2006

Planning Projects

Name Your Project

Before you start thinking about the tasks in your project yoursquoll want to give your project an appropriate titleIf you open an existing project you might want to edit or change the name of your project

To name your project1 In the Type a name for your project text box enter a name2 Click the Next button

Tips

You can enter up to 58 characters and more than one

Use short descriptive project names such as ldquoCompany Web Siterdquo

Avoid vague project names such as ldquoDatabase Projectrdquo or ldquoCDP-7rdquo especially if you plan to circulatereports to others

Enter your project title using uppercase letters if you want the title to stand out in reports

One way to reuse your projects is to open an existing project and then change its name in this stepAfter saving the project with a different name you can modify details to customize the project

See Also

Use the Planning Wizard

-o-

24

copy Experience In Software Inc 1995 - 2006

Phases - Step 1 of 2

After naming your project the next step in the Planning Wizard is to identify the major activities in yourproject Using phases helps organize tasks so that an obviously early task such as ldquoOrganize materialsrdquoappears before a later task such as ldquoReview final draftrdquo

To enter phases1 Type each phase one per line

OrClick the Phases Library button The Phases Library contains typical phases that many organizationsuse in the early middle and late stages of their projects Drag an entry from the Phases Library to thelist and then click the OK button to close the Phases Library

2 To insert a phase in the middle of the phases list click where you want to insert a new blank line andthen press the Insert keyTo edit the phase text double-click the phase

Tips

Start each phase name with an action verb as in ldquoBuild systemrdquo or ldquoWrite reportrdquo

Use actions that have clearly defined beginnings middles and ends For example you can scheduletasks like ldquoTest prototyperdquo more easily than tasks like ldquoPurchase high-quality partsrdquo

Note

Youll have the opportunity to edit phases later in the Tasks step For now continue planning thephases in your project

See Also

Use the Planning Wizard

Use a Library

Move Tasks within the Task List

-o-

25

copy Experience In Software Inc 1995 - 2006

Phases - Step 2 of 2

For each phase list all of the tasks that could be performed during that phase You can refine and organizethe tasks later in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each phase1 Type the tasks associated with the phase displayed in the Tasks for phase text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next phase in your project click the Next button If you prefer to work out oforder click the Tasks for phase list arrow and then click the phase you want

3 When you are finished entering tasks for the last phase in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

26

copy Experience In Software Inc 1995 - 2006

Goals - Step 1 of 3

Enter the goals for your project the objectives you hope to accomplish Then you can brainstorm anyadditional tasks that will help you meet these goals

To enter goals1 Type each goal one per line

OrThe Goals Library contains typical sample goals that you can customize Drag an entry from the GoalsLibrary to the list and then click the OK button to close the Goals Library

2 To insert a goal in the middle of the goals list click where you want to insert a new blank line and thenpress the Insert keyTo edit the goal text double-click the goal

3 Click the Next button

Tips

List goals that apply to the entire project such as Develop a high-quality system A goal such as Getthe contract signed applies only to an early phase

Write goals as actions you can measure For example Complete the project for $75000 or less ismore concrete and specific than Complete the project within budget Numbers make goal statementsreal

If youre not sure how to measure a goal use a range as in About 15 - 25 people will use the results ofthe project

See Also

Use the Planning Wizard

Use a Library

-o-

27

copy Experience In Software Inc 1995 - 2006

Goals - Step 2 of 3

For each goal list any new tasks needed to accomplish that goal You can refine and organize the taskslater in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each goal1 Type the tasks for accomplishing the goal displayed in the For the goal text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next goal in your project click the Next button If you prefer to work out of orderclick the For the goal list arrow and then click the goal you want

3 When you are finished entering tasks for the last goal in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

28

copy Experience In Software Inc 1995 - 2006

Goals - Step 3 of 3

After you identify new tasks for your project assign each new task to an appropriate phase

To assign new tasks to phases1 Click a task in the New tasks to achieve goals list (on the left)2 Click one or more phases in the Assign them to Phases list (on the right) to which the task belongs A

checkmark appears next to tasks youve assigned

If a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Note

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

29

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 1 of 2

Projects often have tasks in common The Similar Projects step makes it easy for you to borrow tasks fromother projects and add them to your current project

By default this step shows the Project KickStart (PRX) projects stored in the same folder as the currentproject including sample projects and those you already created

To select similar projects1 Review the projects in the list To sort the project names alphabetically click the Project Name header

Click the Project Name header again to sort the names in reverse order2 Click one or more projects in the list that contain tasks you want to use in the current project A

checkmark appears next to the projects you selected3 To list projects stored in a different folder on your system click the Browse button and then navigate to

the folder you want4 Click the Next button

If no projects seem related to your current project skip this step for now

Tips

The Similar Projects step becomes more helpful the more you use Project KickStart Every time yousave a project it becomes available for future use

Many projects share the same phases and tasks such as those for setting up a contract or purchasingequipment You can use Project KickStart to create these mini-projects or templates and then importtheir tasks into a new project during the Similar Projects step

-o-

30

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 2 of 2

After you select one or more projects containing tasks you might want to use assign those borrowed tasksto a phase in this project

To assign borrowed tasks to phases1 Click a task in the list on the left If a task includes subtasks click the plus icon to expand the list Click

the minus icon if you want to hide the subtasks To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more phases in the Assign tasks to phase(s) of your project list (on the right) to whichthe task belongs A checkmark appears next to tasks youve assigned

3 To assign one or more tasks to a new phase select the tasks click ltNew Phasegt in the Assign tasksto Phases of your project list and then type a name for the new phase

4 To select tasks from another project you selected as similar click the Tasks from Similar Projects listarrow click the project you want and then assign the tasks to phases

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also Edit Tasks

-o-

31

copy Experience In Software Inc 1995 - 2006

People - Step 1 of 3

Enter the names or descriptions of the people involved in your project Include key decision makers suchas executives or customers who must approve or consult with you about the project These are yourprojects resources In the next People step youll identify new tasks associated with these resources

To enter people1 Type each name or description one per line

OrIf you have stored information about people and other resources in the People Library click the PeopleLibrary button drag an entry from the library to the list and then click the OK button to close thePeople Library

2 To edit the people text double-click the name or description3 Click the Next button

Tips

Be consistent with the resource names in your projects For instance avoid using Richard in oneproject and Dick in another project when referring to the same person

Include names for people teams (such as Quality control team) departments (such as Manufacturing)companies (such as Acme Widgets Corp) or even equipment (such as wheat thrasher)

Note

Add people and other resource information to the People Library so that you can quickly drag resourcesfrom the library to any project You can even import people from your Outlook and ACT address books

See Also

Manage the People Library

Import ACT Contacts and Users to the People Library

-o-

32

copy Experience In Software Inc 1995 - 2006

People - Step 2 of 3

Now that you have defined the people needed to complete your project list any new tasks that eachresource might suggest or require

To enter new tasks for each person1 Type the new tasks associated with the person displayed in the Tasks For text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next person in your project click the Next button If you prefer to work out oforder click the Tasks For list arrow and then click the person you want

3 When you are finished entering new tasks for the last person in your project click the Next button tocontinue in the Planning Wizard

Tips

This step provides a good opportunity to get input from your resources directly and make sure theproject plan reflects the views of everyone on the team

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo Write the tasks roughly in the order that you will complete them You can reorganize the tasks later in

the Tasks step

Note

You assign people to tasks in the Assign Tasks and Schedule steps

See Also

Use a Library

Move Tasks within the Task List

Assign Tasks to People

-o-

33

copy Experience In Software Inc 1995 - 2006

People - Step 3 of 3

After you identify new tasks associated with the people in your project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by people list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

34

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 1 of 3

Every project has obstacles and risks that can affect its success List the major obstacles you face incompleting your project Then you can brainstorm any additional tasks that can help you overcome orminimize these problems

To enter obstacles1 Type each obstacle one per line

OrThe Obstacles Library contains typical sample obstacles that you can customize Drag an entry fromthe Obstacles Library to the list and then click the OK button to close the Obstacles Library

2 To insert an obstacle in the middle of the obstacles list click where you want to insert a new blank lineand then press the Insert key

3 To edit the obstacle text double-click the obstacle4 Click the Next button

Tips

Be creative when thinking of obstacles Highly imaginative obstacles can suggest realistic tasks Forexample Project manager kidnapped by aliens can lead to Project manager out of town forconference In Obstacles step 2 of 3 you can add the realistic activities as tasks You can delete theunrealistic obstacles later by returning to Obstacles step 1 of 3

Avoid listing too many obstacles even if they are realistic Hard core pessimists find it hard to getanything done

Edit and update the Obstacles Library so that you can quickly drag obstacles from the library to anyproject in your organization

See Also

Use a Library

-o-

35

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 2 of 3

After identifying the obstacles to completing your project determine how you can avoid these stumblingblocks List any new tasks you need to overcome or avoid each obstacle In this way you are developing acontingency plan for your project

To enter new tasks for each obstacle1 Type the new tasks associated with the obstacle displayed in the Obstacle text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next obstacle in your project click the Next button If you prefer to work outof order click the Obstacle list arrow and then click the obstacle you want

3 When you are finished entering new tasks for the last obstacle in your project click the Next button tocontinue in the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

You can reorganize the tasks and add notes later in the Tasks step

See Also

Use a Library

Move Tasks within the Task List

Add Task Notes and Attachments

-o-

36

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 3 of 3

After you identify new tasks for overcoming the obstacles to completing project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by obstacles list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

3 Click the Next button

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

37

copy Experience In Software Inc 1995 - 2006

Assigning People

Assign Tasks to People

After youve identified people working on your project you can assign tasks to each person or otherresource

To assign tasks to people1 Click a phase or task in the For each phase or tasks list (on the left)

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more people in the Assign some people list (on the right) who will perform the task Acheckmark appears next to tasks youve assigned

3 To assign a selected task to all of the people in your project click the All button4 To assign one or more tasks to a new person select the tasks click ltNew Persongt in the Assign

some people list and then type a name for the new person

To unassign a task

To unassign a task click the task and then click the highlighted person from which you want to removethe task You can assign that task to a different person if necessary You can also click the All buttonto remove a task from all of its assignments at the same time

Tip

Some users like to skip to the Tasks step before performing the Assign step That way they can edittheir list of tasks before assigning people and resources This helps them focus the project and givesthem a clearer idea of what must be done before committing resources

Notes

You can also assign tasks to people in the Tasks step and the Schedule step

You can assign tasks to non-personnel resources such as equipment (a CAD system or back hoe)facilities (a classroom or hotel) services (lab work or insurance) or materials (lumber or officesupplies) just as you assign tasks to people Click ltNew Persongt to add a new resource to the list

See Also

Remove People from a Task

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

38

copy Experience In Software Inc 1995 - 2006

Remove People from a Task

After assigning tasks you might need to remove people from a task or unassign them

To remove people from a task (unassigning)1 Click a phase or task in the For each phase or tasks list (on the left)

The people assigned to that phase or task are highlighted in the Assign some people list (on theright)

2 Click a highlighted person to remove or unassign that person from the taskWhen the person is no longer highlighted they are not assigned to the selected task

See Also

Assign Tasks to People

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

39

copy Experience In Software Inc 1995 - 2006

Add a New Person or Resource

If you realize that you want to assign some tasks to a person not included in the Assign some people listyou can add that person and assign tasks in the same step You can also add non-personnel resourcessuch as such as equipment (a CAD system or back hoe) facilities (a classroom or hotel) services (lab workor insurance) or materials (lumber or office supplies)

To add a new person or resource1 Select one or more phases or tasks in the For each phase or tasks list (on the left) 2 Click ltNew Persongt in the Assign some people list and then type a name for the new person or

resourceThis adds the new person or resource to the list and assigns the selected tasks to them

See Also

Assign Tasks to People

Remove People from a Task

Edit or Substitute People

Add or Change Task Assignments

-o-

40

copy Experience In Software Inc 1995 - 2006

Edit or Substitute People

If the people or resources in your project change you can replace them or edit their names anddescriptions

To edit or substitute people1 Click the People icon

You return to People step 1 of 32 In the list of people defined for the project double-click the person you want to edit or replace or click

the name and press F23 Edit the name or description of the person

When you return to the Assign step the name of the person appears as you changed it

See Also

Assign Tasks to People

Remove People from a Task

Add a New Person or Resource

Add or Change Task Assignments

-o-

41

copy Experience In Software Inc 1995 - 2006

Organizing the Project Plan

About Organizing Tasks

In the Tasks step you work with an outline of your project plan Here you can easily edit and reorganizetasks spell check and even add notes and attachmentsClick the following illustration to see tips for using this window

Edit the Task List to Consolidate and delete tasks Add subtasks Add or change task assignments Add follow-up notes to tasks Add or change attachments Review the order of the tasks in each phase and move tasks up or down so that they progress

sequentially Review task descriptions to make sure they are clear and that all the team members will understand

them Convert vague tasks such as reminders and open issues to task notes

Notes

Some users like to revise their Task List before they assign resources You can go to the Task List atany time while you are using Project KickStart

Each project created with Project KickStart can contain up to 1000 tasks

See Also

Change the Appearance of the Task List

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

Add Task Notes and Attachments

Add or Change Task Assignments

Add or Change Task Details

-o-

42

copy Experience In Software Inc 1995 - 2006

43

copy Experience In Software Inc 1995 - 2006

Change the Appearance of the Task List

You can change the appearance of the Task List so you can work with it more effectively

To add a column

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task ListBy default the Task List shows the Task Name Assignments and Notes columns You can also showCost and Done columns

To hide a column

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

To move a column

Drag a column heading to a new position in the Task List

To change the column width

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Show or Hide Tasks in the Task List

-o-

44

copy Experience In Software Inc 1995 - 2006

Show or Hide Tasks in the Task List

To hide tasks or subtasks

To hide the subtasks for a task click the minus icon next to the task

To hide all the tasks in the Task List and show only phases click all the minus icons next to thephases

To show tasks or subtasks

To show the subtasks for a task click the plus icon next to the task

To show the tasks for a phase click the plus icon next to the phase

See Also

Change the Appearance of the Task List

-o-

45

copy Experience In Software Inc 1995 - 2006

Move Tasks within the Task List

In the Tasks step you can reorganize the tasks in your project so that they better represent the work youand your team plan to do In particular you should review the order of the tasks in each phase and move tasks up and down so thattasks follow in a sequential order Use the Up and Down Arrow buttons to move the tasks

To reorder tasks1 Click a task or phase to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youmove must be next to each other

2 Click the Up Arrow button to move a task up one rowOrClick the Down Arrow button to move a task down one row

Note

When you move a bolded phase you move the phase and all of its tasks at the same time

See Also

Outdent and Indent Tasks

-o-

46

copy Experience In Software Inc 1995 - 2006

Outdent and Indent Tasks

Subtasks are smaller parts of tasks Use subtasks when you need to break tasks down into moremanageable parts In the Task List you can turn a task into a subtask by indenting it You can also add anew subtask to the Task ListIf your Task List contains subtasks you can turn a subtask into a task by outdenting itUse the Outdent and Indent buttons to promote (outdent) and demote (indent) tasks

To promote and demote tasks1 Click a phase task or subtask to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youpromote or demote must be next to each other

2 Click the Outdent button to promote the selected tasksOrClick the Indent button to demote the selected tasksYou can also right-click an item in the Task List and then click Outdent or Indent on the shortcut menu

Tips

When you promote (outdent) a task it becomes a phase and its subtasks become tasks When youpromote a subtask it becomes a task

When you demote (indent) a phase it becomes a task and its tasks become subtasks When youdemote a task it becomes a subtask

Notes

You can have up to 10 levels of subtasks in your project

Use Task Notes instead of subtasks for task comments or additions that are not actually work items

See Also

Move Tasks with the Task List

Add a Task or Subtask

-o-

47

copy Experience In Software Inc 1995 - 2006

Add a Task or Subtask

If you realize you want to add another task to the Task List use the Add Task button A subtask is a smaller part of a task Use subtasks when you need to break tasks down into moremanageable partsTo add a subtask use the Add Subtask button

To add a task1 Click a task and then click the Add Task button right-click a task and then click Add Task on the

shortcut menu or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskProject KickStart numbers the new task in the proper sequence

To add a subtask1 Click a task and then click the Add Subtask button right-click a task and then click Add Task on the

shortcut menu or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtask3 Project KickStart numbers the new subtask in the proper sequenceNote

To add a new phase click a phase and then click the Add Task button

See Also

Outdent and Indent Tasks

-o-

48

copy Experience In Software Inc 1995 - 2006

Edit Tasks

Edit tasks in the Task List to fine tune your project You can edit the names of the phases tasks andsubtasks delete tasks and cut copy and paste task information

To edit task names1 Click the phase task or subtask you want to edit and then press the F2 key2 Type to edit the text3 To undo an edit click the Undo button

To delete a task

Click the task you want to delete and then press the Delete key or click the Delete button Or

Right-click a task and then click Delete Row on the shortcut menu

To cut copy and paste tasks1 Select the tasks you want to cut or copy Use Shift-click or Ctrl-click to select more than one task

2 Click the Cut button (Ctrl-X) or click the Copy button (Ctrl-C )

3 Click where you want to insert the tasks and then click the Paste button (Ctrl-V)

Tip

If your project includes some of the same tasks repeated in different phases save time by copying rowsof tasks and pasting them to another phase

Notes

You can also edit task names using the Task Information dialog box To open this dialog boxdouble-click a task or click a task and then click the Edit Task Information button

If you delete a phase you also delete its tasks and subtasks If you delete a task you also delete itssubtasks Project KickStart warns you before deleting tasks or subtasks and gives you a chance tocancel the deletion

See Also

Add Task Notes and Attachments

Add or Change Task Assignments

-o-

49

copy Experience In Software Inc 1995 - 2006

Add Task Notes and Attachments

You might find that some of your tasks are actually more notes than tasks For example Remember tocheck Daves specifications might work better as a note than a task especially if it could take several daysto catch up with Dave but only a few minutes to review his specs By using notes you clarify your projectand increase your chances for success An attachment is a document graphic or any other type of file related to a task For example to a tasksuch as Review proposal you can attach the proposal document Or you can attach a hyperlink to a pageon a web site

To add a note or attachment to a task1 Double-click the Notes column next to the task The Task Information dialog box opens to the Notes

and Attachments tab2 In the Enter a Note box type in or edit the task note (Press Enter to insert line break)3 To attach a file click the Add Files button In the Select File to Attach dialog box navigate to the file

you want and then click the Open button The filename appears in the Add Attachments box with apaperclip icon

4 To insert a hyperlink click the Add URL button In the Insert Hyperlink dialog box type in the URL youwould like to link to The URL appears in the Add Attachments box with a paperclip icon

5 Click the OK button

To open or remove an attachment1 Open the Notes and Attachments tab in the Task Information dialog box2 To open an attachment double-click the filename in the Add Attachments box3 To delete an attachment click the attachment in the Add Attachments box and then click the Remove

button

To change a task into a task note1 Copy (Ctrl-C) the text of the task you want to change into a note2 Double-click the task to which you want to add the note3 In the Task Information dialog box click the Notes and Attachments tab and add paste the text in the

Enter a Note box Close the Task Information dialog box4 In the Task Name column delete the original task that how appears as a note for a different task

Tips

Use notes to keep track of the operational details of a project the little nagging details that are criticalto success

Although the Task List provides plenty of room for notes it is best to keep your notes concise

Some tasks might benefit from instructional notes those that explain what to do in a task or how tosuccessfully complete a task

You can also include a hyperlink in a note by typing httpxxx (where xxx is an e-mail or Web address)In Outlook Word Excel or your browser the hyperlink will be active You can click the link to godirectly to that site or to send an e-mail to that address

Note

You can also open the Notes and Attachments tab in the Task Information dialog box by clicking atask and then clicking the Edit Notes and Attachments button or by double-clicking a task to openthe Task Information dialog box and then clicking the Notes and Attachments tab

See Also

Edit Tasks

Add or Change Task Assignments

Change Task Details in the Gantt chart

50

copy Experience In Software Inc 1995 - 2006

-o-

51

copy Experience In Software Inc 1995 - 2006

Add or Change Task Assignments

The Assignments column in the Task List shows the people and other resources assigned to each task

To add or change a task assignment1 Double-click the Assignments column next to the task The Task Information dialog box opens to the

Assignments tabThe Assignments tab lists all of the people and resources in your project If this task is already assignedto people they are highlighted on the Assignments tab

2 To assign this task to another person or resource click the resource name in the Assignments list3 To remove (unassign) this task from a person or resource click a highlighted name in the Assignments

list4 To add a person and assign the task at the same time click ltNew Persongt in the Assignments list

and then enter the name of the new person5 Click the OK button

Note You can also open the Task Information dialog box by clicking a task and then clicking the Edit Task

Information button to or by double-clicking a task

-o-

52

copy Experience In Software Inc 1995 - 2006

Add or Change Task Details

Besides task names notes and assignments you can include cost and done details about tasks In theSchedule step you can also include start and finish dates and durations

To add task details

1 Click a task and then click the Edit Task Information button or double-click the task you wantThe Task Information dialog box opens

2 Enter Cost or Done informationCost Enter the cost associated with this task For example you could enter $150 as the cost for a tasknamed Purchase photo CD Done Click the list arrow to select 0 25 50 75 or 100 or enter the percentage you want such as33

3 Click the OK button

To show or hide task details

Right-click a column heading to open a shortcut menu and then click Cost or Done In the shortcutmenu a checkmark appears next to columns that are displayed in the Task List

To edit task details

Open the Task Information dialog box (click a task and then click the Edit Task Information button or double-click the task you want)

Or

Double-click the Cost or the Done entry to update these details directly in the Task List

Notes

The Cost amount appears with the currency symbol set for your system (in the Regional and LanguageOptions dialog box of the Windows Control Panel)

Project KickStart calculates the running totals for the tasks within a phase and displays this total in theCost column for the phase When you create and print Task reports the total costs for the entire projectappear at the end of the Cost column

See Also

Edit Tasks

Print Task Reports

-o-

53

copy Experience In Software Inc 1995 - 2006

Check Spelling

Spell check your tasks and notes before you print reports or export to other software

To check the spelling of tasks and notes

Click the Check Spelling button on the Project KickStart toolbarOr

Click Tools on the menu bar and then click Spelling

Notes

Spell checking updates entries on the Task List and the Gantt chart (the Schedule step) It can alsocheck the spelling of intermediate entries such as goals and tasks to accomplish goals if you spellcheck during those steps

Spell checking does not check the names of people on the People List or the contents of the PeopleLibrary

-o-

54

copy Experience In Software Inc 1995 - 2006

Scheduling Tasks in the Gantt Chart

55

copy Experience In Software Inc 1995 - 2006

Scheduling Overview

About Scheduling Tasks

In the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the other

You work with the Gantt chart using the familiar Task Data view in the left pane or the graphical Chart viewin the right pane To adjust the schedule to fit your project set the project start date in the toolbar moveand resize the taskbars in the Chart view or change the start and finish dates or durations of individualtasks in the Task Data view

Click the following illustration to see general tips for using the Gantt chart See About the Gantt Chart formore details

In the Schedule step you can

Change a start date for the project Set start and finish dates or durations for tasks Change the timescale of the schedule Change the working schedule to specify which days are nonworking days such as weekends and

holidays Fine-tune the organization of the phases tasks and subtasks Color-code tasks to identify assignments critical deadlines or other information at a glance Insert milestones to indicate events that mark a moment in time such as the approval of a design Review and edit task details including task name assignments notes and attachments Hide or show task data columns in the left pane Export project data to other software applications

Tip

56

copy Experience In Software Inc 1995 - 2006

To save time you can reuse projects such as one for a trade show and create an updated scheduleby changing the project start date in the Schedule step

See Also

About the Gantt Chart

Understand Task Data View

Understand Chart View

-o-

57

copy Experience In Software Inc 1995 - 2006

About the Gantt Chart

The Gantt chart provides two views of your project schedule The Task Data view in the left pane lists thesame task information as in the Tasks step but now includes durations and start and finish dates TheChart view in the right pane displays taskbars and symbols to represent the same information You canchange the schedule information by working directly in the Task Data view and Chart view or by using theGantt Chart toolbarClick the following illustration to see general tips for using this window

-o-

58

copy Experience In Software Inc 1995 - 2006

Autolink tasks (Pro Users)

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatProject KickStart Pro does not assume that you want to link all of the tasks in a serial manner (one after theother) when you get to the Gantt chart Indeed many users want that behavior and many do notTo accomodate both types of users you can set whether you want the program to Autolink tasks In theTools menu select Autolink tasks Thereafter in all your projects when you get to the Gantt chart for thefirst time the tasks will be linked in a serial mannor

-o-

59

copy Experience In Software Inc 1995 - 2006

About Linking Tasks

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatWhen you link tasks the Gantt chart shows additional information about the tasks Click the followingillustration to see general tips for using linked tasks

Task Data view Chart view Description

Predecessor tasksA predecessor task is onethat you must completebefore you can start thenext task For exampleTask 2 - Prepare soil isthe predecessor to Task3 - Plant shrubs becauseyou need to prepare thesoil before you can plantthe shrubs

Successor tasksWhen you finish onelinked task you can moveonto the next onemdashthesuccessor task Forexample the successorfor Task 2 ndash Prepare soilis Task 3 ndash Plant shrubsand the successor forTask 3 is Task 4 ndash MulchLink linesThe first task isscheduled for one dayand the second one forthe next day In additionthe link line and arrowshow that the first taskmust end before thesecond one can start

These linked tasks arescheduled for the sametime

60

copy Experience In Software Inc 1995 - 2006

These tasks which aredependent on earliertasks and the last twotasks are also scheduledfor the same time

See Also

About the Gantt Chart

Autolink tasks

Make tasks overlap

-o-

-o-

61

copy Experience In Software Inc 1995 - 2006

Change the Display of the Schedule

You can change the onscreen appearance of the schedule so you can work with it more effectively Thefollowing illustration shows the Schedule window with the Steps bar closed and only the task number taskname and duration displayed in the Task Data view This provides more room to display the Gantt chart

To show or hide the Step bar or Project KickStart toolbar

Click View on the menu bar and then click Steps Bar to show or hide the vertical Steps bar on the leftof the Project KickStart window

Click View on the menu bar and then click Tool Bar to show or hide the Project KickStart toolbarwhich appears just below the menu bar In the View menu a checkmark appears next to the items displayed in the Project KickStart window

To display more or less of the Task Data view or Chart view

Drag the splitter bar between the Task Data view and the Chart view

To change the timescale in the chart

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years

To add a column to the Task Data view

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task Data viewBy default the Task Data view shows the Info Task Name Days Start and Finish columns Youcan also show Done Cost and Assignments columns

To hide a column in the Task Data view

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

62

copy Experience In Software Inc 1995 - 2006

To change the column width in the Task Data view

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Understand Task Data View

Understand Chart View

-o-

63

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

-o-

64

copy Experience In Software Inc 1995 - 2006

65

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Some features in this topic are available only in Project KickStart Professional

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view In Project KickStart Professional you also use the Gantt chart toolbar to linkand unlink tasks

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysLink Tasks (Pro Users)Link the selected tasksUnlink Tasks (Pro Users)Unlink the selected tasksChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

See Also

Use the Gantt Chart Toolbar

-o-

66

copy Experience In Software Inc 1995 - 2006

Understand Task Data View

The following illustration shows all the columns of information you can display in Task Data view

The Task data columns are the same as in the Tasks step but also include date information

Row number

Info Shows an icon if a note attachment or both are associated with the task Double-click anicon to view or edit the associated information

Task Name Name of the phases tasks and subtasks Double-click a task name to edit it directly

Days The amount of time it takes to complete the task If you change the number of days for a taskProject KickStart changes the Finish date accordingly

Start Date this task starts Double-click a Start date and then click the list arrow to open a calendar andselect a different date This also changes the Finish date

Finish Date this task ends Double-click a Finish date and then click the list arrow to open a calendar andselect a different date This changes the task duration shown in the Days column

Done Percentage of the phase task or subtask completed Show progress for any task by entering apercent of up to 100

$ Cost Cost for each task summed in the appropriate phase row Reports include total costs for theproject when you select the Cost column in the Create and Print Task Reports dialog box or the Createand Print Gantt Chart Report dialog box The Cost appears with the currency symbol set for your system(in the Regional and Language Options dialog box of the Windows Control Panel)

Assignments People and other resources assigned to the task Double-click an assignment to open theTask Information dialog box to the Assignments tab where you can add and change assignments

Tip

A task with a duration of zero (0) days is a milestone See Create a Milestone for more information

Notes

By default Task Data view displays all the columns the Info Task Name Days Start and Finish Done Cost and Assignments columns Some of these columns might be hidden by the Gantt chartview To hide columns right-click a column heading to open a shortcut menu and then click the columnyou want to hide In the shortcut menu no checkmark appears next to columns that are hidden

To change the width of a column drag a splitter bar in the column heading row or double-click a splitterbar to have the column accommodate its longest entry

As in the Tasks step expand phases and tasks by clicking the plus icon and collapse phases andtasks by clicking the minus icon

See Also

67

copy Experience In Software Inc 1995 - 2006

Understand Chart View

Change Task Dates

-o-

68

copy Experience In Software Inc 1995 - 2006

Additional Features in Task Data View

These features are available only in Project KickStart Professional

In Project KickStart Pro you can view two columns of information in addition to the nine columns availablein the Project KickStart Standard These two additional columns are labeled Pred (for Predecessor) andSucc (for Successor) The following illustration shows a typical Task Data view with these additionalcolumns

Besides the nine columns of information shown in Task Data view in Project KickStart Standard you canalso show the following information in the Professional version

Pred Indicates which task is the predecessor to the current task Double-click a task number in the Predcolumn to change it

Succ Indicates which task is the successor to the current task Double-click a task number in the Succcolumn to change it

Notes

When you link tasks Project KickStart assigns predecessors and successors according to their order inthe Task Data view

When you move a linked task in the Task Data view the predecessor and successor do not changeFor example in the above illustration if you move Task 3 ndash Plan design so it becomes Task 2 itspredecessor remains Land survey and its successor remains Engineering You can change these bydouble-clicking the task number in the Pred or Succ column and then entering a new number

See Also

Understand Task Data View

-o-

69

copy Experience In Software Inc 1995 - 2006

Understand Chart View

The following illustration shows a daily schedule in Chart view Point to the illustration to display text thatdefines the chart elements

Summary bar Summarizes the tasks below it and extends from the earliest start date(where the first triangle in the summary bar appears) to the latest finish date (where the last triangleappears) If a phase has tasks the summary bar appears in the phase row to summarize the tasks If atask has subtasks the summary bar appears in the task row to summarize the subtasks

To reschedule a phase and all of its tasks (or a task and all of its subtasks) click the summary bar and dragit to the left or right until it spans your desired set of dates This changes the earliest start date and latestfinish date in that phase and keeps the same duration And all the tasks move with the change of thephase

Taskbar Shows the length and scheduled dates for a task To change the duration of a taskresize the taskbar click the taskbar and then drag its left edge to schedule a different start date or drag itsright edge to schedule a different finish date

To reschedule a task without changing the duration drag the taskbar to a different date in the chart

Taskbar with percent done If you enter a Done amount in the Task Data view a progress barin the taskbar indicates the amount of the task completed

Red vertical line Indicates todays date

Milestone Indicates a task with a zero duration Milestones mark an event that must be reflected inyour project plan such as the approval of a design or an assembly line startup You can drag the left edgeof a milestone icon to stretch it into a taskbar The milestone becomes a task with a start and finish date

Notes

Because a summary bar summarizes the tasks below it you cannot resize a summary bar

To scroll the schedule use the vertical and horizontal scroll bars or the green drag bar at the top of theChart view

The shaded days in the Chart view indicate nonworking days To set which days are working andnonworking see Specify Working Days

70

copy Experience In Software Inc 1995 - 2006

-o-

71

copy Experience In Software Inc 1995 - 2006

Additional Tools in Chart View

These features are available only in Project KickStart Professional

If you use Project KickStart Pro the Chart view displays lines and arrows to show linked tasks The linklines and arrows show the relationships dependencies between one linked task and another

Besides the summary bar taskbar and other information provided in Project KickStart Standard Chart viewin the Professional version also provides the following information

The first task is scheduled for one day and the second one for the next day In addition the link line andarrow show that the first task must end before the second one can start

These linked tasks are scheduled for the same time However the first task must end before the secondone can start

The first two tasks are scheduled for the same time and must be completed before the third task can start

These linked tasks are scheduled for the same time However the second task must end before the firstone can start

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

Understand Chart View

-o-

72

copy Experience In Software Inc 1995 - 2006

73

copy Experience In Software Inc 1995 - 2006

Change Task Dates

You can revise a project schedule by changing task dates in the Task Data view or the Chart view You canalso reschedule an entire project by changing the projects start date

To change the project start date1 Click the Project Start list arrow to open a calendar

The calendar highlights the selected date and outlines todays date2 Find the date you want using the left and right scroll arrows to view a different month and then click the

date

To change task dates in Task Data view1 Double-click the Start or Finish date for a task

2 Then edit the date (you can edit the day month or year) OrClick the list arrow to open a calendarThe calendar highlights the selected date and outlines todays date

3 Find the date you want using the left and right scroll arrows to view a different month and then click thedateProject KickStart changes the Start and Finish dates according to your selection updates the durationof the task in the Days column and adjusts the taskbar in the Chart view

To change task dates by changing the duration in Task Data view

Double-click the Days column for a task and then enter the number of days it will take to complete thetaskProject KickStart changes the Finish date of the task and adjusts the taskbar in the Chart view

To change task dates in Chart view

Resize a taskbar click the taskbar and then drag its left edge to schedule a different start date or dragits right edge to schedule a different finish dateProject KickStart updates the summary bar in Chart view and the task dates and duration in the TaskData view

To reschedule a task without changing the duration drag the taskbar to a different date You can alsodrag a summary bar to reschedule a phase and all of its tasks (or a task and all of its subtasks) so itspans a different set of datesProject KickStart updates the task dates and duration as necessary in the Task Data view

To change task dates in the Task Information dialog box1 Open the Task Information dialog box (Right-click a task and then click Task Information or click a

task and then click the Edit Task Information button )2 Click the General tab3 In the Dates section change the following information as necessary

Start Click the Start list arrow to open a calendar and then click the appropriate start dateFinish Click the Finish list arrow to open a calendar and then click the appropriate finish dateDays Enter a number or click the spin arrows to set the task durationMilestone Select the Milestone check box if you want this task to be a milestone (A milestone is atask with a zero duration and marks an event such as the approval of a design)

Notes

You cannot delete the Start or Finish date of a task If you want to specify that a task has no durationconvert it to a milestone

When working with a calendar to schedule a start or finish date click the Today date text (where date

74

copy Experience In Software Inc 1995 - 2006

is todays date) to select todays date

See Also

Understand Task Data View

Understand Chart View

Create a Milestone

-o-

75

copy Experience In Software Inc 1995 - 2006

Phase Dates Cannot Be Edited

You cannot change the bold phase dates in the Task Data view of the Gantt chart They are a summary ofthe task dates for a particular phase and are view only You can revise phase dates by changing task dateswithin the phase

To change phase dates in Chart view

You cannot directly resize a summary bar You can extend or move the blue task barswithin a phase on the chart and Project KickStart updates the summary bar

To reschedule a phase on the chart drag the summary bar to a new date and all of its tasks (or a taskand all of its subtasks) will move with it

-o-

76

copy Experience In Software Inc 1995 - 2006

Quick Tour of Working with Linked Tasks

This feature is available only in Project KickStart ProfessionalIn the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the otherIn addition Project KickStart Pro links the tasks for you so when you open the Gantt chart you see a linkedwaterfall similar to the one shown below Besides providing a schedule that starts in a cascade with eachtask lasting one day each task is linked to the next task

You work with the Gantt chart either using the Task Data view in the left pane or the graphical Chart view inthe right pane To adjust the schedule to fit your project set the project start date in the toolbar move andresize the taskbars in the Chart view or change the start and finish dates or durations of individual tasks inthe Task Data view See About Scheduling Tasks for detailsNext fine-tune the dependencies in your project by you can linking and unlinking tasks changing theirpredecessors and successors and setting lead times For example if one task is not dependent onanother you can unlink the tasks If another task canrsquot start until two other tasks are finished you can add apredecessor to that task in which case the two tasks will be linked

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

To fine-tune the linked tasks To change the scheduled start and end dates of linked tasks move and resize taskbars in the Chart

view or change the number of days or the Start date in the Task Data view To display predecessor and successor information in the Task Data view right-click any column

heading and then click Pred or Succ To change the predecessor for a task double-click the number in the Pred column for the task and

then enter the number of a different task To change the successor for a task double-click the number in the Succ column for the task and then

77

copy Experience In Software Inc 1995 - 2006

enter the number of a different task To add another predecessor or successor to a task click in the appropriate column for the task and

then enter the number of another task To change the details of a linked task open its Task Information dialog box To do so right-click the

task and then click Task Information on the shortcut menu or click a task and then click the Edit TaskInformation button See Change Details for Linked Tasks

In the Task Information dialog you can also specify the predecessor(s) of a task and lead time(s) of thetasks

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

About Scheduling Tasks

About Linking Tasks (Pro Users)

Use the Gantt Chart Toolbar (Pro Users)

Manage Changes in Your Schedule (Pro Users)

-o-

-o-

78

copy Experience In Software Inc 1995 - 2006

Link and Unlink Tasks

These features are available only in Project KickStart Professional

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

See Also

About Linking Tasks

Quick Tour of Working with Linked Tasks

-o-

79

copy Experience In Software Inc 1995 - 2006

Create a Milestone

A milestone Indicates a task with a zero duration Milestones mark an event that must be reflected in yourproject plan such as the approval of a design or an assembly line startup

To create a milestone in the Task Data view

Double-click the Days number for a task and then enter 0 (zero)Or

Open the Task Information dialog box click the General tab and then click to insert a checkmark inthe Milestone check box

In the Chart view Project KickStart changes the taskbar to a milestone icon To create a milestone in Chart view

Click a taskbar and then drag to shrink the taskbar to a milestone icon In the Task Data view Project KickStart changes the Days for this task to 0 (zero)

Notes

To change a milestone into a task you change its duration or start and finish dates See Change TaskDates for instructions

To move a milestone in Chart view click the milestone icon on the upper left corner of the milestoneicon With the left mouse down move the icon to another date and release the mouse

To move a milestone in the Task Data view change the start date or the finish date and the milestonewill move

-o-

80

copy Experience In Software Inc 1995 - 2006

Change Task Details

You can use the Task Information dialog box to change the following task details in Task Data view

Task properties including the task name cost for completing the task and the percent completed

Dates including the start and finish dates duration and whether to convert the task to a milestone

Assignments

Notes and attachmentsYou can also edit the task name days dates costs and Done directly by clicking items in the task datacolumns

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button 2 Click the appropriate tab and then change the task details

General tab Change the task name and enter or change the cost associated with the task To changethe amount of the task completed click the Done list arrow and then select a value or type a value inthe Done text box Enter or change date information as described in Change Task Dates Assignments tab People assigned to this task are highlighted in the list To assign this task to anotherperson or resource click the name in the Assignments list To remove (unassign) this task from aperson or resource click a highlighted name in the Assignments list See Add or Change TaskAssignments for more detailsNotes and Attachments tab Type or edit a task note (Press Enter for a line break) To add anattachment click the Add button In the Select File to Attach dialog box navigate to the file you wantand then click the Open button The filename appears with a paper clip icon See Add Task Notes andAttachments for more details

To change task details directly in Task Data view

To modify the task name press F2 or double-click a task and then edit or replace the text

To change date information see Change Task Dates

To change the amount of the task completed double-click in the Done column and then enter a newvalue

To change the cost associated with the task double-click in the Cost column and then enter a newvalue

Notes

When you enter costs for tasks the total appears in the phase row for those tasks Reports include thetotal costs of all tasks in the project when you select the Cost column in the Create and Print TaskReports dialog box or the Create and Print Gantt Chart Report dialog box

You cannot change the cost of a phase because it represents the total costs for the tasks in that phaseInstead change the costs associated with the tasks in the phase

When you enter a Done for a task the corresponding taskbar in the Chart view includes a blackprogress bar

-o-

81

copy Experience In Software Inc 1995 - 2006

Change Details for Linked Tasks

This feature is available only in Project KickStart ProfessionalIf you are using Project KickStart Pro you can use the Task Information dialog box to change the followingtask details

Predecessor for a linked task

Lead time for a linked task

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button

2 Click the Predecessors tab and then change the task details about predecessors and lead timePredecessors tab The Task Properties section shows the name of the selected task which you canchange The Predecessor (Finish-to-Start) section shows the tasks that are predecessors to theselected task A predecessor task must be finished before you start the current task You can change the ID name or lead time of the predecessor task Also you can also add additionalother predecessorsThe lead time is the amount of time you need to wait after finishing the predecessor task before so youcan start the current task Lead time can be positive or negative

Note

In some programs the is time shift is called ldquolag timerdquo But we think that the term ldquolead timerdquo is moreaccurate and descriptive since itrsquos the amount of time you want to allow before you start a task

See Also

Change Task Details

82

copy Experience In Software Inc 1995 - 2006

-o-

-o-

83

copy Experience In Software Inc 1995 - 2006

Reorganize Tasks in Task Data View

Although your project should be fairly well organized by the time you start the Schedule step you canfine-tune the organization in the Task Data view using the same techniques you use in the Tasks stepTo reorder tasks

Right-click a task and then click Move Task Up or Move Task Down on the shortcut menu Or

Click a task or phase to select it and then click the Up Arrow button or the Down Arrow button on theGantt chart toolbar

To promote and demote tasks

Right-click a task and then click Outdent or Indent on the shortcut menu Or

Click a phase task or subtask to select it and then click the Outdent button or the Indent button onthe Gantt chart toolbar

To add a task1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Task button on the Gantt chart toolbar or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskTo add a subtask1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Subtask button on the Gantt chart toolbar or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtaskTo delete a task

Right-click a task and then click Delete Row on the shortcut menuOr

Click the task you want to delete and then click the Delete button

To delete a row click the Task row number and press the Delete button

See Also

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

-o-

84

copy Experience In Software Inc 1995 - 2006

Change the Timescale of the Schedule

You can display the Gantt chart schedule in the Chart view using days weeks months quarters or yearsas the timescale Changing from days to weeks for example displays a longer period of time but lessdetail

Days timescale Weeks timescale

To change the timescale in the Chart view

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years Youcan also change the timescale by clicking Timescale on the menu bar and then clicking the option youwant

Notes

When you print a Gantt chart your current timescale is used by default However you can change it inthe Print Options dialog For example even though you were viewing your Gantt chart by weeks youcan choose to print the Gantt chart by months

If your mouse comes with a wheel you can adjust Project KickStarts timescale by rolling the wheelforward or backward The Timescale list box must be selected first

-o-

85

copy Experience In Software Inc 1995 - 2006

Specify Working Days

You can select which days are working days and which days are nonworking days for scheduling purposesBy default Monday - Friday are working days and Saturday and Sunday are nonworking days You can addto and change these settings to specify holidays for example

To set working and nonworking days

1 Click the Change Working Schedule button on the Gantt chart toolbar The Change Working Schedule for this Project dialog box opens Nonworking days are shaded in grayWorking days are unshaded

2 To change a single date (from working to nonworking or from nonworking to working) click the date3 To change one day of the week for the entire project such as all Fridays double-click any Friday4 To display schedules for other months click the left and right arrows5 Click OK

Note

Project KickStart maintains separate calendars for each project

If you typically work weekends create a simple template with weekends displayed as Working daysSave as your starter template Use the starter template when you start a new project and then save theproject with a different name Weekends will be displayed as Working days in your projects

-o-

86

copy Experience In Software Inc 1995 - 2006

Change the Color of Taskbars

You can change the color of the taskbars in the Chart view to call attention to particular tasks For exampleyou can change the colors of all tasks in a particular phase resource or deadline to make them stand outin a report

To change the color of a taskbar1 Right-click a taskbar and then click Color on the shortcut menu or click a taskbar and then click the

Color button on the Gantt chart toolbar The Color dialog box opens

2 Click the color you want to assign to the taskbarTips

Avoid changing the taskbar color to black because it obscures the Done progress bar (The Doneprogress bar is a black bar displayed within a taskbar)

Also avoid changing the taskbar color to white because it will not appear in the white rows of the Chartview

-o-

87

copy Experience In Software Inc 1995 - 2006

Make Tasks Overlap

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro the schedule starts in a cascade with each task lasting one day and each tasklinked to the following taskHowever it is very unlikely that your entire schedule matches such a cascade so you can adjust theschedule Start by estimating the duration of tasksmdashthe number of days that each task will take Generallyit is best to estimate how many days will elapse before the task is done You might also want some tasks to occur at the same time To do so you can overlap the tasks To make tasks overlap like this

You can do this in three ways Set the same predecessor for both tasks

Or Set the second task as the successor of the first task and then then move the second task into a

position when it starts on the same day as the first taskOr

Set the second task as the successor of the first task and then assign a lead time of ndash3 days (the number of days scheduled for the task)

To make tasks overlap like this

Set the second task as the predecessor of the first task and then assign a lead time of ndash2 days(one less than the number of days scheduled for the task)

-o-

88

copy Experience In Software Inc 1995 - 2006

Manage Changes in Your Schedule

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro when you schedule with dependencies you can adapt to changes on the fly andcreate what-if scenarios to forecast how one change affects the overall project schedule A commonscenario is dealing with delays You can reschedule an entire project or only selected tasks When you doProject KickStart Pro updates the schedule for you

To delay an entire project Click in the Project Start text box and then edit the date to match your new start date (You can edit

the day month or year)Or

1 Click the Project Start list arrow to display the calendar The calendar highlights the selected date andoutlines todays date

2 Find the date you want using the left and right scroll arrows to view a different month and then click thedate Project KickStart changes the Start and Finish dates for all tasks according to your selection

To delay a task In Task Data view double-click the Days column for the task and then edit the number of days it will

take to complete the taskProject KickStart changes the Finish date of the task adjusts the taskbar in the Chart view andchanges the Start and Finish dates for all tasks linked to this taskOr

In Chart view resize a taskbar by clicking the taskbar and then dragging its left edge to schedule adifferent start date or dragging its right edge to schedule a different finish date Project KickStart updates the summary bar in Chart view the task dates and duration in the Task Dataview and reschedules all tasks linked to this task

To reschedule a task without changing the duration in Chart view drag the taskbar to a different date Project KickStart updates the task dates and duration as necessary in the Task Data view andreschedules all tasks linked to this task

Note

Project KickStart Pro does not include a critical path

-o-

89

copy Experience In Software Inc 1995 - 2006

Managing Libraries

Use a Library

Project KickStart has five libraries that contain lists of useful phases tasks goals people and obstaclesAll libraries expect the People Library contain sample entries that you can use in your projects Yougenerally build your own People Library from the resources that are available to you

To use a library1 In the Phases Tasks Goals People or Obstacles step of the Planning Wizard click the Library button

to open the appropriate library2 Select one or more items in a library and then drag them to your list3 Close the Library window

Tips

Feel free to add (or delete) items to the libraries to make them richer and more pertinent to yourprojects

Keeping libraries small makes them easier to use

Widen the library window to see the full text of long entries

Note

After adding a library entry to a list you can double-click the entry to edit it

See Also

Manage a Library

-o-

90

copy Experience In Software Inc 1995 - 2006

Manage a Library

Customize the libraries by adding and changing entries and reorganizing them so you can use the librariesefficiently The Phases Tasks Goals People and Obstacles Libraries include a single column ofinformation while the People Library provides additional columns (See Manage the People Library)

To edit a library1 Open the library by clicking the appropriate Library button2 To edit an entry double-click it

3 To add an entry to the library press Insert or click the Add a row button You can also select oneor more items in the list and then drag them to the library

4 To delete an entry select the entry and then press Delete or click the Delete a row button 5 To move an item up or down select the item and then click the Up Arrow or the Down Arrow button

6 Click the OK button to save your changes and close the Library windowTips

Widen the Library window to add a long entry

Libraries can serve as ldquoKnowledge Librariesrdquo By including typical company-specific terms in yourLibraries you create a quick reference for yourself and colleagues now and in the future To do so adda new line in the Library enter the name of your company (or department) as a heading in capitalletters and then list your personal terms under the heading

If you use Project KickStart on more than one computer such as at home and work you can transportchanges you make in your Libraries from one computer to another The data in all the Libraries isstored in one file pks5libxdat so you can copy that file on one computer and paste it into the ProjectKickStart 5 folder on the other computer

Keeping Libraries small makes them easier to use Project KickStarts Libraries are fairly rich out of thebox If some of the terms don rsquot apply to your type projects delete them

See Also

Manage the People Library

-o-

91

copy Experience In Software Inc 1995 - 2006

Manage the People Library

The People Library is like the other libraries but with a few important extra features

You can store contact data such as Company Email Phone and Job Title

You can import names from ACT or from Outlook if you use either of those programsTo use the People Library1 In the People step of the Planning Wizard click the People Library button2 Select one or more names in the People Library and then drag them to your list (This adds only the

names of people not their contact data) If the People Library contains company names but not contactnames you can drag the company name to your list

3 Close the Library windowTo organize the People Library

To show or hide a column right-click a column heading to open a shortcut menu and then click acolumn name In the shortcut menu a checkmark appears next to columns that are displayed in thePeople Library

To sort the people in the People Library click a column heading For example click the Name columnheading to sort the people alphabetically by name To reverse the sort click the column heading again

To move a person up or down select the person and then click the Up Arrow or the Down Arrowbutton

Click the OK button to save your changes and close the People LibraryTo edit the People Library

To edit a persons name and contact data double-click the entry

To add a person to the People Library click the first blank row press Insert or click the Add a rowbutton Then type to enter the persons name and contact information You can also select one ormore items in the list and then drag them to the People Library

To delete an entry select the entry and then press Delete or click the Delete a row button

Click the OK button to save your changes and close the People LibraryTips

Use the People Library to store names for people teams (such as Quality control team) departments(such as Manufacturing) companies (such as Acme Widgets Corp) or even equipment (such as wheatthrasher)

Widen the People Library window to add a long entry

Resize the columns by dragging or double-clicking a splitter barNotes

After adding a person or resource to your list you can double-click the name to edit it

You can import contact information stored in an Outlook or ACT (version 6 7 or later) address book toyour People Library

See Also

Import ACT Contacts and Users to the People Library

Import Outlook Contacts to the People Library

-o-

92

copy Experience In Software Inc 1995 - 2006

Import ACT Contacts and Users to the People Library

If you use ACT 7 or later (200520062007) or if you use ACT 6 you can import contacts and users to thePeople Library This speeds up your work by letting you use ACT information in your Project KickStartplans If you export a plan to ACT 7 or later it recognizes the people and other resources you entered inProject KickStart

To import ACT contacts and users1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click ACT 7 or later or ACT 6 Click the Import button3 Click the Select ACT Database button and select the ACT 7 or later database (pad) containing the

people information you want to import The ACT 7 and later databases are usually stored in MyDocumentsACTACT for Win 7Databases (If you use ACT 6 your data is stored in a dbf database) If you select a multi-user ACT database you must enter your user name and password for the ACTdatabase

4 In the Import to People Library dialog box the names of Contacts and Users are listed on the left Clickthe Users tab select one or more users and then click Add to move the user names to the Import listClick the Contacts tab to select contact names the same way Click the Add All button to select allusers or contacts for import Note You can sort the contacts alphabetically by name or by company name by clicking theappropriate column heading

5 Click the Import button to add the names and related information from the selected ACT database tothe People Library

Notes

Importing contacts and users to the People Library does not remove them from the ACT database

If you try to import the same ACT contact or user twice it appears only once in the People Library

-o-

93

copy Experience In Software Inc 1995 - 2006

94

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts to the People Library

If you use Microsoft Outlook to maintain your contacts you can import selected contacts to the PeopleLibrary ThisThis speeds up your work by letting you use Outlook information in your Project KickStartplans If you export a plan to Outlook it recognizes the people and other resources you entered in ProjectKickStart

To import Outlook contacts1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click Outlook Click the Import buttonA dialog box opens informing you that Project KickStart is trying to access your Outlook data

3 Allow access for 1 minute and then click the Yes button4 If Outlook asks you to choose your profile please do so5 The Import to People Library dialog box opens listing Outlook Contacts on the left Select one or more

contacts and then click Add to move the contact names to the Import list Click the Add All button toselect all contacts for import

6 Click the Import button to add the contact names to the People Library

Notes

Importing contacts and users to the People Library does not remove them from Outlook If you try to import the same Outlook contact twice it appears only once in the People Library

95

copy Experience In Software Inc 1995 - 2006

You can import Contacts from the Outlook Business Contact Manager

See Also

Import Outlook Contacts via CSV to the People Library (Pro Users)

-o-

96

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts via CSV to the People Library (ProUsers)

This feature is available only in Project KickStart Professional

If you use Microsoft Outlook to maintain your contacts and many of the people on your project are not inyour personal contacts folder in Outlook you can use our new utility to import these Outlook contacts viaCSV to the People Library

To export Outlook contacts to a CSV file1 In Outlook - Click File Import and Export Export to A File and click Next2 Select Comma Separated Values (Windows) and click Next3 Select the Contacts folder to export and click Next4 Save Exported File As with the default being your My Documents folder5 Click Next

To import Outlook contacts to the People Library

1 Be sure that you exit Project KickStart before running the Import Utility

2 Run ImportCSVToPKSexe which is located in the Project KickStart application folder

3 Browse or type the Contacts CSV file (the path is My DocumentsProject KickStart Projects folder bydefault)

4 Browse or type the pks5libxdat file (default is the Project KickStart application folder)

5 Click on Import

Note

Importing contacts and users to the People Library does not remove them from Outlook

-o-

97

copy Experience In Software Inc 1995 - 2006

Printing Reports

98

copy Experience In Software Inc 1995 - 2006

Printing Dashboards

Print Reports

You can print reports from anywhere in Project KickStart through a new Reports Step

You will see Reports divided into three areas

Dashboard

Task Reports

Gantt Chart Reports

-o-

99

copy Experience In Software Inc 1995 - 2006

Print Dashboard Reports

You can print dashboard reports from anywhere in Project KickStart though it makes the most sense toprint them after you have developed your tasks and arranged them in a sensible order

To print a dashboard report

1 Click File on the menu bar and then click Print Reports and then click Dashboard Reports or clickthe Print Reports button

2 In the left column select one of these dashboard reports Whats Due Today Whats Due NextWeek Whats Due Next Month

3 Change the page setup as necessary or Save As a file (See Page Setup and Save As)

4 Click the Print button

Tip

You can see the number of tasks in each dashboard report from the dashboard menu

-o-

100

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Dashboard Reports

Printer Setup

-o-

101

copy Experience In Software Inc 1995 - 2006

Save as HTML or RTF

You can dashboard reports to a Hypertext Markup Language (HTML) format for viewing with an Internetbrowser such as Microsoft Internet Explorer or Mozilla FireFox or to an RTF format for viewing in MicrosoftWord

To save a dashboard report as an HTML file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save button

To save a report as an RTF file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

102

copy Experience In Software Inc 1995 - 2006

Printing Task Reports

Print Task Reports

You can print task reports from anywhere in Project KickStart though it makes the most sense to print themafter you have developed your tasks and arranged them in a sensible orderBefore you print task reports you might want to widen the Task Name column in the Task List to make sureyou print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a task report

1 Click File on the menu bar and then click Print Task Reports In the Tasks step you can click thePrint Reports button instead

The Create and Print Task Reports dialog box opens

2 Click the list arrow and then click Task Report Individual Assignments or Phases Goals People ampObstacles

3 Select the information you want to include in the report as described below

4 Preview the report and change the page setup as necessary (See Print Preview and Page Setup)

5 Click the Print button

Task Report

The Task report covers the entire project and includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

103

copy Experience In Software Inc 1995 - 2006

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to display in the report

By default the report prints all tasks Click the Incomplete Tasks or Completed Tasks option button tofocus on one type of task

4 Click the Preview button (See Print Preview for details)

Individual Assignments

The Individual Assignments report covers the entire project and lists the tasks assigned to each resourceThe report includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to include in the report

Click the All Tasks Incomplete Tasks or Completed Tasks option button

4 Choose which people to include The report lists tasks assigned to the people you select

Click to insert or remove a checkmark from the box for each person

5 Click the Preview button (See Print Preview for details)

Phases Goals People amp Obstacles

This report includes the phases goals people and obstacles in your project You can include some or all ofthese items in the report

104

copy Experience In Software Inc 1995 - 2006

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Click the Preview button (See Print Preview for details)

Tip

If you have many long notes for the tasks of your project it may be hard to read them if you select everycolumn in the Task Reports You should consider selecting a report with only columns for Tasks andNotes

See Also

Print Gantt Chart Reports

-o-

105

copy Experience In Software Inc 1995 - 2006

Print Preview

Before printing a report preview its pages so you know how the report will look when printed

To preview a task report1 Click the Preview button on the Create and Print Task Reports dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from 79 to 100 or from 100 to 79Zoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25

viewPrint the report

You can also click the Page Setup button to change margins and other settings or click the Closebutton to close the Print Preview window

2 If the report appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintTask Reports dialog box

Note

Print Preview is for viewing only--you cannot edit the contents of a report

See Also

Print Task Reports

Printer Setup

Page Setup

-o-

106

copy Experience In Software Inc 1995 - 2006

Printer Setup

Before you print a report you can change the following printer settings

Printer name (and other properties) Paper size Number of copies

To change the printer setup1 Click the Printer button on the Project KickStart toolbar or the Print Preview toolbar2 In the Print dialog box change the printer settings

See Also

Print Task Reports

Print Preview

Page Setup

-o-

107

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Task Reports

Print Preview

Printer Setup

-o-

108

copy Experience In Software Inc 1995 - 2006

Email Task Reports

After creating and previewing a task report you can distribute it to others via email

To email a task report1 In the Create and Print Task Reports dialog box select a report and then click the Email Report

button Project KickStart creates the report opens a new message in your email software and attaches thereport as an HTML file to the message

2 Insert one or more email addresses include the message text and then send the message the way youusually do

Tip

To send a task report to each person in your project with the appropriate assignments select theIndividual assignments report select one person to receive the report and then click the Email Reportbutton Enter the email address of the recipient and send the message Do this for each person in yourproject

-o-

109

copy Experience In Software Inc 1995 - 2006

Save as HTML

You can export tasks assignments days and notes to a Hypertext Markup Language (HTML) format forviewing with an Internet browser such as Microsoft Internet Explorer or Mozilla FireFox

To save a report as an HTML file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

110

copy Experience In Software Inc 1995 - 2006

Save as RTF

You can export tasks assignments durations and notes to a Rich Text Format (RTF) for editing inMicrosoft Word

To save a report as an RTF file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can open an RTF file in a word processor such as Microsoft Word

To send an RTF document to each person in your project with the appropriate assignments select theIndividual Assignments report select one person to receive the report and then save the report asRTF Do this for each person in your project

See Also

Save as HTML

-o-

111

copy Experience In Software Inc 1995 - 2006

Printing Gantt Chart Reports

Print a Gantt Chart

Once you create your schedule you can print a Gantt chart from anywhere in Project KickStart

Before you print a Gantt chart you might want to widen the Task Name column in the Task pane to makesure you print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a Gantt chart1 Click File on the menu bar and then click Reports and then select Gantt Chart Reports In the

Schedule step you can click the Print Reports button insteadThe Create and Print Gantt Chart Report dialog box opens

2 Click the Format list arrow and then click Wall chart Fit to smallest size or Repeat tasks on everypage (for handouts)

3 Select the information you want to include in the report as described below4 Preview the report and change the page setup as necessary (See Print Preview a Gantt Chart and

Page Setup)5 Click the Print button

Wall Chart The wall chart prints the Gantt chart information spread across many pages which you can tape together tocreate a wall chart On the left side of the report the wall chart includes the task data columns you selectThe right side of the report includes the graphical view shown in the Gantt chart pane on the right

1 Select the task data columns you want to display for the task information on the left side of the wallchartClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the wall chart

112

copy Experience In Software Inc 1995 - 2006

By default the wall chart prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the wall chartBy default the wall chart prints the timescale you were using in the Gantt chart Click the SetTimescale list arrow to change the timescale to Weeks Months Quarters or Years

4 Select the orientation for the wall chartClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Fit to Smallest Size When you select the Fit to smallest size format Project KickStart reduces the size of the entire Gantt chartincluding the information in the Task pane on the left and the graphical view shown in the Gantt chart paneon the right so it fits as well as possible in the smallest number of pages

1 Select the data columns you want to display for the task information on the left side of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 The timescale for the Gantt chart view on the right side of the report is determined by the length of yourproject and may not be changed

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 The number of pages of the report is shown here (The Fit to smallest scale report will print up to 78rows of tasks per page)

6 Click the Preview button (See Print Preview a Gantt Chart for details)

Standard (for Handouts) This report lists the data columns you specify on the left side of the first page and can repeat the tasknumber task name or assignments on every interior page of the report which is especially useful for

113

copy Experience In Software Inc 1995 - 2006

handouts

1 Select the data columns you want to print on the left side of the first page and the data columns youwant to print on every page of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the reportBy default the report prints a daily view of the tasks Click the Set Timescale list arrow to change thetimescale to Weeks Months Quarters or Years

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Tips

Print Preview shows how many pages the Gantt chart will take to print If there are too many pagesconsider changing the timescale or the date range You can also choose to show fewer columns of taskdata

If possible use paper that is larger than 85 x 11 inches You can select the paper size in Print Previewusing the Page Setup dialog box

If you change the timescale from Days to Weeks or Months this can make tasks with short durations (1to 5 days) difficult to see

If you have trouble printing the Gantt chart report try changing the dpi from 600 to 300 (draft mode) Ifyou continue to have problems contact your printer manufacturer and see if it supports PCL (PrinterCommand Language) technology which is included in most printers today

If you have trouble printing the Gantt chart report on a PDF printer you can try to scale the printing tographics setting to 50

114

copy Experience In Software Inc 1995 - 2006

See Also

Save Gantt Chart Images

Print Task Reports

Printer Setup

Page Setup

-o-

115

copy Experience In Software Inc 1995 - 2006

Print Preview a Gantt Chart

Before printing a Gantt chart preview its pages so you know how the report will look when printed

To preview a Gantt chart1 Click the Preview button on the Create and Print Gantt Chart Report dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from the current zoom percentage to 100 or from 100 to the current zoom percentageZoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25 viewChange printer settings and then print the reportYou can also click the Page Setup button to set margins select paper size and enter headers andfooters or click the Close button to close the Print Preview window

2 If the Gantt chart appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintGantt Chart Report dialog box

Notes

Print Preview is for viewing only--you cannot edit the contents of a report

If you want to print a wider task column return to the Gantt chart widen the Tasks Name column andthen print

To change print settings such as the printer selection and number of copies click the Print button to open the Print dialog box You can save the Gantt chart in a PDF file by clicking the Print button andthen clicking the PDF printer selection (such as Adobe PDF or PDF-XChange ) You can then distributethe Gantt chart electronically as a PDF file

See Also

Print a Gantt Chart

Page Setup

-o-

116

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a Gantt chart you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print a Gantt Chart

Print Preview a Gantt Chart

-o-

117

copy Experience In Software Inc 1995 - 2006

Printing to an Adobe PDF file

To print a Gantt chart to an Adobe PDF file you may have to make some adjustments to your settings

To preview a Gantt chart1 Select Adobe PDF as the name of the printer2 Click Properties button3 Click the PaperQuality tab4 Click Advanced button5 In the Graphic Section lower the setting on Print Quality6 Also in the Graphic Section change the Scaling from 100 to 50

-o-

118

copy Experience In Software Inc 1995 - 2006

Save Gantt Chart Images

You can save a Gantt chart as a series of graphic files in the Meta File (emf) format which you can theninsert in a file such as a Microsoft Word document or PowerPoint presentation The number of graphic filescreated depends on the report type and options you choose in the Create and Print Gantt Chart Reportdialog box By default Project KickStart saves the files in a folder named for your project

To save Gantt chart images1 In the Create and Print Gantt Chart Report dialog box click the Save Image button

The Save Image dialog box opens2 Change the location where you want to save the image files or change the part of the file name that

includes the project name and report type if necessary3 Click the Save buttonNotes

Project KickStart saves the image files in the PKSGanttImagesproject name folder stored in the MyDocumentsProject KickStart Projects folder (where project name is the name of your project)

Each graphic file name includes the name of the project report type date you created the report andnumber in the series of images as in CreateaWinningPresentation_Wall chart_09112008_1emf toCreateaWinningPresentation_Wall chart_09112008_20emf

To email the Gantt chart images attach the images in the PKSGanttImagesproject name folder storedin the My DocumentsProject KickStart Projects folder (where project name is the name of your project)If the image files are large zip or compress the files first

If you have installed PDF as a printer selection you can print the Gantt chart to a PDF file and thenattach the PDF file to an e-mail message PDF files are often easier to read than image files See thenotes in Print Preview a Gantt Chart for instructions on printing to a PDF file

-o-

119

copy Experience In Software Inc 1995 - 2006

Export Project Data

120

copy Experience In Software Inc 1995 - 2006

Export to ACT

Export to ACT 7 or Later

If you use ACT 7 or later (20052006200720082009) you can export your plan from Project KickStart toan ACT database with just one click After you export your plan you see your tasks in the ACT Groupview grouped under the name of your project

To export to ACT 7 or later

1 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 7 and later andthen click the Go button You can also click File on the menu bar point to Export to and then clickACT 7 and later

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (pad file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opens

Each time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks

4 Click Start (This works best if ACT is already open )

5 If you are exporting to a multi-user ACT database enter your ACT User Name and Password

To view each project separately in ACT Group Details

1 In ACT click the Group List icon

2 Double-click the Project Name in the Group Name column The Group Detail appears for the projectyou selected

3 Click the Contacts tab to see Contacts and click the Activities tab to see tasks for that project

4 You should press Ctrl-F5 to refresh the view Also you might have to adjust the Filter in ACT so thatDates to show is set to All Dates

Task names are listed in the Regarding column Assignments are listed in the Scheduled With columnPhases are shown in red and tasks and subtasks are shown in blue

To view tasks from multiple projects sorted by date in Task List or Calendar

In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn Project names are in the Associate With column You might have to adjust the Filter in ACT sothat Dates to show is set to All Dates

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar Tasks are set as timeless (Duration of 0 minutes) so the transferred tasks dont fill up thecalendar

121

copy Experience In Software Inc 1995 - 2006

Tips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

The ACT 7 and later export is smart enough to update your existing tasks from the same project If youexport the same Project KickStart project two or more times ACT recognizes the project and asks ifyou want to update the project information in ACT You do not lose your task history or notes in ACT

Tasks that are unassigned in Project KickStart are listed as Scheduled With Unassigned PKS

You can filter by Selected Users in the Task List and in Groups

See Also

Import ACT Contacts and Users to the People Library

-o-

122

copy Experience In Software Inc 1995 - 2006

Export to ACT 6

If you use ACT 6 ACT 2000 or ACT 5 you can transfer a Project KickStart plan into an ACT databasewith just one click After you export your plan you see your tasks in the ACT Group view grouped underthe name of your project

To export to ACT 61 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 6 and then click

the Go button You can also click File on the menu bar point to Export to and then click ACT 6

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (dbf file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opensEach time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks4 Click Start (This works best if ACT is already open )5 If you are exporting to a multi-user ACT database enter your ACT user name and passwordTo view each project separately in ACT1 In ACT click the Groups icon 2 Click the Project Name listed under All Groups on the left3 On the lower-right part of the window click the Activities tab to see tasks for that project

Task names are listed in the Regarding column Assignments are listed in the Scheduled With column 4 You might have to adjust the Filter in ACT so that Dates to show is set to All Dates Also you might

have to press Ctrl-F5 to refresh the view5 To view task details click the button next to the task column on the leftTo view tasks from multiple projects sorted by date1 In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn You might have to adjust the Filter in ACT so that Dates to show is set to All Dates

2 If the Group column is not showing add it by clicking ViewAdd Columns and then double-clickingGroupThe tasks are identified by group (project name)

3 To view task details click the button next to the task column on the leftTips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar as well as in the Task List

You can filter by Selected Users in the Task List and in Groups

After exporting your tasks to ACT you can import them to your Palm Pilot using the ACT Link

See Also

Import ACT Contacts and Users to the People Library

-o-

123

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Outlook

If you use Microsoft Outlook you can export your plan from Project KickStart to Outlook in a click of abutton After you export your plan you see your tasks in the Outlook Tasks view grouped under a categorynamed for your project In Outlook you can track your tasks and email tasks to team members

To export to Microsoft Outlook1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Outlook and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Outlook The Export to Outlook dialog box opens

2 Click an option button to export All tasks Uncompleted tasks or Completed tasks3 If you want to display the tasks you export on your Outlook Calendar click the check box4 Click the Start button A dialog box opens informing you that Project KickStart is trying to access your

Outlook data

5 Allow access for 1 minute and then click the Yes buttonTo view your tasks in Microsoft Outlook1 Click the Outlook Tasks button2 Depending on the version of Outlook you are using set to view the tasks by category In Outlook 2003

click the By Category option button in the Current View list You can also click View on the menu barpoint to Arrange By and then click CategoriesYour project is listed by its project name in the Categories list

3 Click an expand icon to see the complete list of tasks and subtasks

124

copy Experience In Software Inc 1995 - 2006

4 To view task details double-click the task nameTips

The export to Outlook works best if Outlook is already open

In Outlook you can set priorities set reminders and schedule by the hour

If you export to your Outlook Calendar a reminder appears on the due date of each task

After you export tasks to Outlook you can synchronize with your Palm Pilot Windows CE device orother handheld computer

Note

You can export only to Microsoft Office Outlook not Outlook Express

See Also

Import Outlook Contacts to the People Library

-o-

125

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Word

If you use Microsoft Word you can export your plan from Project KickStart to Word in a click of a buttonYour project appears in a Word table in a doc file You can cut and paste change column widths deletecolumns and print from Word

To export to Microsoft Word

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Word andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Word

Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in a Word document in a doc format

2 When youre finished use Save As to save the Word file with a new name such as ltnamegtdoc Forconvenience you can save the file using the same name as your Project KickStart project name

Benefits of using Project KickStart and Word

Communicate projects flexibly After exporting to Word you can communicate your project details ina variety of text formats You can also enhance your document by adding color logos clip art orhyperlinks

Distribute plans to others You can send doc files to other Microsoft Word users via email andrequest comments using Words Send To and Comments features

Tip

Include your strategic plan in documents letters and web pages in a doc or html file

Note

The image of the Gantt chart does not import into Word automatically You can manually import theGantt chart image into a Word document In Word select Insert on the menu bar point to Pictureclick From File and then browse to the folder containing the Gantt chart images you saved By defaultthis is cMy DocumentsProject KickStart ProjectsPKSGanttImages in a folder named for your project

See Also

Export to Word Processors (Other than Word)

Save Gantt Chart Images

126

copy Experience In Software Inc 1995 - 2006

-o-

127

copy Experience In Software Inc 1995 - 2006

Export to Word Processors (Other than Word)

If you are using a word processor other than Microsoft Word you can export your Project KickStart taskreport by first saving it as an HTML or RTF file

To export to word processors other than Microsoft Word

1 Save a Project KickStart task report using HTML or RTF format using the Save As button in the Createand Print Task Reports dialog box

2 Open the file with your word processor

3 Save the file using the Save As command using a different name

See Also

Print Task Reports

Save as HTML

Save as RTF

-o-

128

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Excel

If you use Microsoft Excel you can export your plan from Project KickStart to Excel in a click of a buttonYour project appears in an Excel worksheet in a xls file You can add task details perform calculationsand share your project data with other Excel users

To export to Microsoft Excel1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Excel and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Excel Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in an Excel worksheet in an xls format

2 When youre done select FileSave As to save the Excel file under a new name For convenience youmight want to save it under the same name as your Project KickStart project name

To manually import Gantt chart images into Microsoft Excel1 In Excel click Sheet2 and select ToolsOptions on the menu bar and unclick the box for Gridlines2 Then select Insert on the menu bar point to Picture click From File and then browse to the folder

containing the Gantt chart images you saved By default this is cMy DocumentsProject KickStartProjectsPKSGanttImages in a folder named for your project

3 Select one Gantt chart image at a time to bring it in 4 You can manipulate the size of the image in Excel

Benefits of using Project KickStart and ExcelProject KickStart is very good at scoping out a schedule but there are a few reasons why you might want touse both programs

Data sharing A Project KickStart user might want to share the information with other Excel users whodont have Project KickStart They could change enhance or redistribute their portions of the schedule

129

copy Experience In Software Inc 1995 - 2006

Add more task details Excel users can add new columns of task data that cant be added in ProjectKickStart

Sort task lists For example you could show your projects tasks sorted by each resources namethen see each resources tasks sorted by the tasks start date

Filter tasks Excel can show tasks that meet certain criteria For instance show tasks with the wordtesting in the task name

See Also

Save Gantt Chart Images

-o-

130

copy Experience In Software Inc 1995 - 2006

Export to Microsoft PowerPoint

If you use Microsoft PowerPoint you can export your plan from Project KickStart to PowerPoint in a click ofa button Your project appears as a formatted PowerPoint presentation in a ppt file

To export to Microsoft PowerPoint

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft PowerPointand then click the Go button You can also click File on the menu bar point to Export to and thenclick Microsoft PointPoint

The Export to PowerPoint dialog box opens where you can choose a PowerPoint design template ifyou like

2 Click the Start button

Your tasks days start and finish dates and costs appear in a PowerPoint presentation with an imageof the Gantt chart in one or more slides at the end of your slide show

Once you have created a PowerPoint presentation you can enhance your slides in several ways

Delete slides that are not appropriate for your presentation

131

copy Experience In Software Inc 1995 - 2006

Rearrange the order of the slides

Add colors for emphasis

Add graphics such as company logo clip art and colors

Shorten any long task titles

Benefits of using Project KickStart and PowerPoint

Save time You can dramatically save time in creating a PowerPoint presentation on your project

Present projects to others Present project details in webinars presentations and corporatemeetings Create template presentations or how tos for implementing an installation productintroduction or corporate policy for example

Communicate plans Email project plans in ppt format to colleagues and presentors

Tips

If you use a PowerPoint design template choose one that has a white or light background for maximumlegibility of the Gantt chart in the presentation

The Gantt chart image in the PowerPoint presentation is generated ldquoon the flyrdquo Change the Timescalesettings of the Gantt chart considering how it will be reflected in the number of images of the Ganttchart For example the Day view results in more Gantt chart images than the Months view

-o-

132

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Project

If you use Microsoft Project 98 2000 2002 or 2003 you can export your plan from Project KickStart toProject in a click of a button

To export to Microsoft Project

In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Project andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Project Your tasks assignments days start and finish dates costs done and notes (excluding attachments) appearin a Microsoft Project file

Benefits of using Project KickStart and Microsoft Project

Share data with others Send a project to a colleague or client that expects to see your schedule in anMicrosoft Project format

Schedule tasks with more flexibility Schedule tasks in different durations particularly in less than aday

Track resources Track resource usage and resource leveling and to have greater flexibility in sortingfiltering and reporting project information

Notes

Project KickStart tasks transfer to Microsoft Project as tasks with a Constraint type of Start No EarlierThan This keeps the dates the same as in the Project KickStart schedule

The settings in Project KickStart Working Days Calendar also transfer to Microsoft Project

Exporting to Microsoft Project allows you to take advantage of the advanced tracking and schedulingfeatures that large projects often require

You can also save your Project KickStart projects as an mpx file which you can open in MicrosoftProject and send to other Microsoft Project users Click File on the Project KickStart menu bar clickSave As and then choose mpx as the file type After you save the file click File on the MicrosoftProject menu bar click Open and open your mpx file

-o-

133

copy Experience In Software Inc 1995 - 2006

Export to SureTrak Project Manager

If you use SureTrak Project Manager you can export your plan from Project KickStart to SureTrak ProjectManager

To export to SureTrak Project Manager

1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file

2 In SureTrak click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

SureTrak

You will see your tasks and assignments (but not the notes) appear in a SureTrak file The file is shownin outline view

Benefits of using Project KickStart and SureTrak

Add new information to tasks such as how they are linked

Track progress particularly for comparing plans verses actual results

Have greater flexibility in sorting filtering and reporting project information

Notes

Task notes are not included in the transfer

A version of Project KickStart called the Project KickStart Wizard is included in SureTrak 2 andSureTrak 3 You can use it within SureTrak

See Also

Export MPX Files

-o-

134

copy Experience In Software Inc 1995 - 2006

Export to FastTrack Schedule

If you use FastTrack Schedule you can save your Project KickStart project as an mpx file and import it intoFastTrack ScheduleTo export to FastTrack Schedule1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file2 In FastTrack Schedule click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

FastTrack ScheduleBenefits of using Project KickStart and FastTrack Schedule

Add more task details FastTrack Schedule provides the features and tools needed in many largeprojects

Multiproject reporting Consolidate multiple projects into a master project file

See Also

Export MPX Files

-o-

135

copy Experience In Software Inc 1995 - 2006

Export to Milestones Professional

If you use Milestone Professional you can export your plan from Project KickStart to MilestonesProfessional in a click of a button

To export to Milestone Professional

In the Schedule step click the Export to list arrow below the Gantt chart click MilestonesProfessional and then click the Go button You can also click File on the menu bar point to Export to and then click Milestones Professional

Your tasks assignments start and finish dates and notes (excluding attachments) appear in aMilestones file

Tips

After you export your tasks to Milestones Professional you can create taskbars add titles and performother tasks to produce a presentation-quality schedule You can also use Milestones to track your tasksby showing task durations and percent completions Make scheduling changes by dragging the taskdates

If you have an earlier version of Milestones (eg version 45 or 5) you can save Project KickStart dataas an mpx file and then open the mpx file in Milestones

-o-

136

copy Experience In Software Inc 1995 - 2006

Export to Mindjet MindManager

If you use Mindjet MindManager 7 or later you can export your project plan from Project KickStart in a clickof a button Or you can develop a rough plan in MindManager and export your mind map to ProjectKickStart for enhanced planning It works both ways

To export from Project KickStart to MindManager

In the Schedule step click the Export to list arrow below the Gantt chart click MindManager and thenclick the Go button You can also click File on the menu bar point to Export to and then clickMindManager

Your tasks assignments start and finish dates durations costs Done and notes (excludingattachments) appear in a MindManager file

To export from MindManager to Project KickStart

In MindManager click File on the menu bar point to Send To and then click Project KickStart Thenclick the OK button to start the export

You can also click the Project KickStart icon at the bottom of the MindManager window

Benefits of using Project KickStart and MindManager together

Visualize your plan in two ways Brainstorm plan and communicate your project details in both agraphical and linear style

Develop a graphical plan and then fine-tune the details MindManager uses mindmappingtechniques to develop a high-level plan in a graphical format Export to Project KickStart to enhanceyour plan details by focusing on your projects goals obstacles and resource needs You can alsocreate a Gantt chart schedule

Communicate concepts Project KickStart users can display their plans in a highly graphicalmindmapping format in MindManager The maps make it easier to communicate complex processesand visually identify important tasks issues and relationships

Tip

If you dont already use MindManager you can purchase it in our Thinking Tools Store

-o-

137

copy Experience In Software Inc 1995 - 2006

Export to WBS Chart Pro

If you use WBS Chart Pro you can export your plan from Project KickStart to WBS Chart Pro in a click of abutton

To export to WBS Chart Pro

In the Schedule step click the Export to list arrow below the Gantt chart click WBS Chart Pro andthen click the Go button You can also click File on the menu bar point to Export to and then clickWBS Chart ProYour project is displayed under the project name Each phase in the project is shown in a box with ashadow Each lower level task in a phase is displayed under their respective phase box groupedtogether with the other tasks in that phase

Benefits of using Project KickStart and WBS Chart

Visualize tasks Work with tasks in a tree-style chart called a Work Breakdown Structure (WBS)chart

Communicate your project plan with others WBS Chart uses the outline you create in ProjectKickStart to create a top-down picture of your plan This picture is similar to an Organization chart Butinstead of displaying the structure of your company a WBS chart displays the structure of your projectplan

Notes

WBS Chart refers to the phases in the project as Summary Tasks and the detail for each phase asTasks

The export only works if WBS Chart is not currently running You must close WBS Chart before you cancreate another chart

See Also

Export MPX Files

-o-

138

copy Experience In Software Inc 1995 - 2006

Export MPX Files

The MPX file format is an ASCII format created by Microsoft Project or another program and is used tosend data to and from project management software programs

The following programs can create and open MPX files

FastTrack Schedule

Microsoft Project (95 or 98)

Project KickStart 5

Project KickStart 32

RiskyProject

SureTrak Project Manager

WBS Chart

In these programs you save a project as an MPX file using the Save As command on the File menu Youcan then open an MPX file by using the Open command on the File menu and then specifying the file typeas mpx

For example if you want to move a project from Project KickStart 5 to Project KickStart 32 you can savethe project as an mpx file and then open it in Project KickStart 32

In Microsoft Visio you can create a Visio project time line from Project KickStart To do so you first mustsave your file in Project KickStart as an MPX file Then

1 Start Visio

2 Click File on the menu bar point to New click Business Diagram and then click Project TimelinesWizard

3 Click Next

4 On the second window click Import MPX File to import the Project KickStart mpx file

5 Enter the file location and name or click Browse to locate the file

6 Follow the instructions in the Visio Project Timelines Wizard windows

Tip

If you have difficulty importing the mpx file remove any commas from task names

-o-

139

copy Experience In Software Inc 1995 - 2006

Reference

140

copy Experience In Software Inc 1995 - 2006

Menus

File Menu

Command Keyboard Shortcut Description

New Project Ctrl+N Creates and names a new project fileOpen Project Ctrl+O Opens a previously saved Project KickStart 4 or 5 file

(prx) Project KickStart 3 file (prj) or mpx fileClose Ctrl+W Closes an open Project KickStart fileSave Ctrl+S Saves a project file (prx) in which you made changes Save As Saves a project file with a different file name or different

file format such as MPXPrint Task Reports

Ctrl+T Generates and prints a report letting you preview thecontents

Print Gantt ChartReports

Ctrl+G In the Gantt chart (Schedule step) generates andprints the Gantt chart in the current timescale

Export To Sends the project to another program such asMicrosoft Outlook or ACT 7

Recent file list Lists the last three files opened in Project KickStartExit

Alt+F4 Exits the program

-o-

141

copy Experience In Software Inc 1995 - 2006

Edit Menu

Command Keyboard Shortcut Description

UndoRedo Ctrl+Z Undoes or repeats the last operationCut

Ctrl+X Deletes the currently selected information placing it on theclipboard so you can paste it elsewhere

Copy

Ctrl+C Places a copy of selected information on the Clipboard so youcan paste it elsewhere

Paste

Ctrl+V Places information from the Clipboard to the currently selectedlocation

Select all Ctrl+A Selects all the content in the windowAdd a line Adds a new row where you can enter text

-o-

142

copy Experience In Software Inc 1995 - 2006

View Menu

Command Description

Tool Bar Shows or hides the toolbar (a checkmark indicates thetoolbar is displayed)

Steps Bar Shows or hides the Steps bar (a checkmark indicates the Steps bar is displayed)

Name Go to the Name your project stepPhases Go to Phases stepGoals Go to Goals stepSimilar Projects Go to Similar projects stepPeople Go to People stepObstacles Go to Obstacles stepAssign Go to Assign tasks to people stepTasks Go to Tasks stepSchedule Go to Schedule step

-o-

143

copy Experience In Software Inc 1995 - 2006

Tools Menu

Command Keyboard Shortcut Description

Spelling

F7 Checks spelling of project dataexcept for names of people

Collaboration To access or find out aboutGoToMeeting

Options Select options for running thesoftware

-o-

144

copy Experience In Software Inc 1995 - 2006

Options

-o-

145

copy Experience In Software Inc 1995 - 2006

Data Menu

The Data menu is available in the Tasks and Schedule steps for manipulating tasks and creating ascheduleCommand Description

Move Up Moves the selected task item upMove Down Moves the selected task item downOutdent Moves the selected task item to the leftIndent Moves the selected task item to the rightInsert Task Insert task in row aboveInsert SubTask Insert subtask below current rowDelete Task Delete current taskEdit Task Properties Brings you to an edit screen where you can edit task

name change assignments and edit task notesEdit Notes Brings you to an edit screen for editing task notesColor Taskbars Change the color of selected tasks (in Schedule)Change Working Days Select which days are working and which are

nonworking (in Schedule)Link Tasks Link tasks in Gantt chart (Pro Users)Unlink Tasks Unlink tasks in Gantt chart (Pro Users)

-o-

146

copy Experience In Software Inc 1995 - 2006

Timescale Menu

The Timescale menu is available in the Schedule step so you can change the display of the Gantt chartschedule

Command Description

Days Displays a daily schedule in theGantt chart

Weeks Displays a weekly schedule inthe Gantt chart

Months Displays a monthly schedule inthe Gantt chart

Quarters Displays a quarterly schedule inthe Gantt chart

Years Displays a yearly schedule inthe Gantt chart

-o-

147

copy Experience In Software Inc 1995 - 2006

Help Menu

Command Description

Project KickStart Help Help for Project KickStart including a Table ofContents and index of terms

Online Tutorials View several Getting Started Tutorials to getyou started with Project KickStart whether youare a new or experienced user

Keyboard Shortcuts Shortcuts for programTechnical Support How to obtain Technical Support for Project

KickStart via web form and email[Send Log to Technical Support] If the program detects an error it writes a log

of technical issues Click Send Log toTechnical Support to send the error log to us

ProjectKickStartcom Visit the Project KickStart Web siteGet Latest Version See what the latest published version is and

download it if you need itAbout Project KickStart Shows Project KickStart version number build

date copyright and system information

-o-

148

copy Experience In Software Inc 1995 - 2006

Shortcuts

Use the following keyboard shortcuts to move quickly around in Project KickStart

Navigation

Move forward to the next window Alt+NMove back to the previous window Alt+BSteps

Go to Name step Alt+MGo to Phases step Alt+SGo to Goals step Alt+GGo to Similar step Alt+RGo to People step Alt+PGo to Obstacles step Alt+OGo to Assign step Alt+IGo to Tasks step Alt+KGo to Library (Phases Tasks GoalsPeople Obstacles)

Alt+L

Menus

File menu Alt+FEdit menu Alt+EView menu Alt+VShow menu (Tasks step) Alt+WOutline menu (Tasks step) Alt+UTimescale (Schedule step) Alt+CHelp menu Alt+H F1Other

Edit tasks assignments amp notes (Tasks step)F3Save Ctrl+SPrint Task Report Ctrl+PPrint Gantt Chart (Schedule step) Ctrl+GCut Ctrl+XCopy Ctrl+CPaste Ctrl+VInsert Row InsertDelete Row DeleteInsert Line Break (in Notes in Task List andSchdule steps)

Enter

Spell Check

Ignore Alt+IIgnore All Alt+GChange Alt+CChange All Alt+HHelp

149

copy Experience In Software Inc 1995 - 2006

Contents in Help Alt+CIndex Alt+IBack in Help Alt+BClose Help Alt+LHelp about the current step Alt+H

-o-

150

copy Experience In Software Inc 1995 - 2006

Share Project KickStart Data

Project KickStart makes it easy to share data with other people involved with a project You can share yourProject KickStart data in the following ways

Send a printed report Make a PowerPoint presentation Send a file (prx html rtf mpx) Post an HTML file to a Web site and access it with your web browser Export to other programs such as Microsoft Word or Excel and send data in a format the recipient can

access (such as doc xls or mpx)

Note

You can also collaborate with a colleague by conducting an online meeting using GoToMeeting (Prousers)

-o-

151

copy Experience In Software Inc 1995 - 2006

Open a Project

After you create a project and save it in a prx prj or mpx file using Project KickStart or other softwareyou can open the project in Project KickStartTo open a project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click a file type (prxprj or mpx)

3 Navigate to the folder that contains the file4 Double-click the name of the file

Opening a Project KickStart 3 prj file converts it to a prx file

Generally prj files are stored in cprogram filesProject KickStart 3

The tasks in the converted Project KickStart 5 file will have the same start and finish dates anddurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way To have weekends as non working days open the working days calendar and markweekends as non working

Opening a mpx file converts it to a prx file

The tasks in each project have the same start and finish dates and durations

-o-

152

copy Experience In Software Inc 1995 - 2006

Dedication

I dedicate this software program to my new colleague

Kevin Ahlvin

Roy A Nierenberg President

-o-

153

copy Experience In Software Inc 1995 - 2006

Credits and Trademarks

Credits

Missak Koumoudjian Program Architect and Chief Programmer

Kevin Ahlvin Interface DesignAnn Kawamoto Quality AssuranceAlexander Setzepfandt Quality AssuranceJackie LeungJeffrey Chow

Programming Interns

Kevin Ahlvin Product Supervisor and CoordinatorJoseph Fusco Project Management Consultant and content

providerLisa RuffoloJoseph Fusco

Help System

Roy A Nierenberg President

Trademark

Project KickStart and Project KickStart Wizard are trademarks of Experience In Software Inc in the UnitedStates andor in other countries All rights reserved All other trademarks mentioned herein are the propertyof their respective owners

-o-

154

copy Experience In Software Inc 1995 - 2006

Uninstalling

You can uninstall Project KickStart 5 through the Control Panel AddRemove Programs Select ProjectKickStart 5 This starts the InstallShield Maintenance Program You should then remove all of theprogram files that were installed It will not erase your Project KickStart prx data files

If that does not work you can delete the Project KickStart files manually

Note

If you purchased Project KickStart and you want to return it for a refund follow the instructions forDe-activating the software at httpwwwprojectkickstartcomcontactreturnscfm

-o-

155

copy Experience In Software Inc 1995 - 2006

Using Past Projects

You can use past projects in two ways

If you have projects that are similar you can use a past project as a template for a new project In theWelcome window select Open a Project Open that project and Save As under a different name Nowyou can open up the renamed project and modify it for the current project

You can draw from several projects in the Similar Projects step First select projects that are similarand click Next Then select tasks from those projects and decide where they would fit into your currentproject

See Also

Opening a project Compatibility with earlier versions

-o-

156

copy Experience In Software Inc 1995 - 2006

Index

- - Change Working Schedule 85

- -prj file format 13

- A -About Linking Tasks (Pro Users) 59About Scheduling Tasks 55About the Gantt Chart 57ACT 120 92 122ACT 6 92 122ACT 7 or later 92 120Activate 14Activating Trial Version 14Add a New Person or Resource 39add a subtask 83add a task 83Add a Task or Subtask 47Add or Change Task Assignments 51Add or Change Task Details 52Add Subtask 63Add Task 63Add URL 49Additional Features in Task Data View (Pro Users) 68Additional Tools in Chart View (Pro Users) 71Adobe PDF 117Assignments tab 80Attachments 49Autolink tasks (Pro Users) 58

- B -Back 10borrow tasks 29

- C -Change Details for Linked Tasks (Pro Users) 81Change Project Start 63Change Task Dates 73Change Task Details 80Change the Appearance of the Task List 43Change the Display of the Schedule 61Change Timescale 63Change Working Schedule 63Chart view 57

157

copy Experience In Software Inc 1995 - 2006

Cloning projects 155Color 63 86Compatibility 13Compatibility with earlier versions 13convert projects 13Coordination 12Create and Print Task Reports 102Credits 153Credits and Trademarks 153critical path 88CSV 96Customer support 20Customer Support 20Customizing Project KickStart

- D -Dashboard 99Data Menu 145Dedication 152Delete 63delete a task 83demote 46dependencies 12 76

- E -Edit Menu 141Edit Notes and Attachments 63Edit or Substitute People 40Edit Task Information 63Email Task Reports 108End User License Agreement 16error 21Error Messages 21export from MindManager 136Export MPX Files 138Export to ACT 6 122Export to ACT 7 and Later 120Export to FastTrack Schedule 134Export to Microsoft Excel 128Export to Microsoft Outlook 123Export to Microsoft PowerPoint 130Export to Microsoft Project 132Export to Microsoft Word 125Export to Milestones Professional 135Export to Mindjet MindManager 136Export to SureTrak Project Manager 133Export to WBS Chart Pro 137

- F -FastTrack Schedule 134File Menu 140Fit to page 111Fit to Smallest Size 111

158

copy Experience In Software Inc 1995 - 2006

- G -Gantt chart 55 57General tab 80Goal 26Goal statements 26Goals 26Goals - Step 1 of 3 26Goals - Step 2 of 3 27Goals - Step 3 of 3 28goals library 26 89Goalsadd 26Goalsdelete 26Goalsedit 26Goalstasks for 27GoToMeeting 150 12

- H -Handouts 111Help Menu 147hyperlink 49

- I -Import ACT 92import contacts and users 92import Outlook contacts 94Import Outlook Contacts via CSV to the People Library (Pro Users) 96ImportCSVToPKSexe 96Indent 46Individual Assignments 102Introduction 7Introduction 7

- K -Knowledge Libraries 90

- L -lag time 81lead time 59 81library 89License Key 14link 59Link lines 59Link tasks 12 65linked tasks 59

- M -major activities 24Make Tasks Overlap (Pro Users) 87Manage a Library 90

159

copy Experience In Software Inc 1995 - 2006

Menu 140Microsoft Excel 128Microsoft Outlook 123Microsoft PowerPoint 130Microsoft Project 132Microsoft Project (95 or 98) 138Microsoft Visio 138Microsoft Word 125Milestone 69 79Milestones Professional 135Mindjet MindManager 136MindManager 136

- N -Name 23Name Your Project 23Navigating Project KickStart 10Next 10Notes and Attachments tab 80

- O -Objectives 26Obstacles 34Obstacles - Step 3 of 3 36Obstacles Library 89Open a Project 151Options 144Outdent 46Outdent and Indent arrows 63Outlook Calendar 123Overview

- P -Page Setup 107 116 100PDF 117people 31People - Step 3 of 3 28People Library 91phase 24phase dates 75Phase Dates Cannot Be Edited 75phases 24Phases - Step 1 of 2 24Phases - Step 2 of 2 25Phases Library 89Phases Goals People amp Obstacles 102PowerPoint presentation 130Pred 68Predecessor 68Predecessor tasks 59predecessors 76Print a Gantt Chart 111Print Dashboard Reports 99Print Preview 105Print Preview a Gantt Chart 115Print Reports 98Print Task Reports 102

160

copy Experience In Software Inc 1995 - 2006

Printer Setup 106Printing to an Adobe PDF file 117prj 13Pro 145Pro Edition 145Product support 20Project 23Project KickStart 3 prj file 151Project KickStart for Windows 7project name 23project start date 73project template 155project title 23promote 46promote and demote tasks 83

- Q -Quick Tour of Working with Linked Tasks (Pro Users) 76

- R -Red vertical line 69Redo 11Register Project KickStart 22Registering Project KickStart 22remove people 38Remove People from a Task 38reorder tasks 83Reorganize Tasks in Task Data View 83Repeat tasks on every page (for handouts) 111Reporting Technical Issues 21resource 31resources 31restore 34return 154risks 34RiskyProject 138

- S -Save As 101Save as HTML 109Save as RTF 110Save Gantt Chart Images 118Schedule 55Send Error Report 21similar projects 29spelling 53starter schedule 55Steps 7subtask 47Subtasks 46Succ 68Successor 68Successor tasks 59successors 76Summary bar 69Support 20SureTrak Project Manager 133

161

copy Experience In Software Inc 1995 - 2006

- T -Task Data view 57task dates 73Task Report 102Taskbar 69Taskbar with percent done 69Tasks 25Tasks in Phases 25Tasks Library 89team 31Technical support 20timescale 84Timescale Menu 146Tools Menu 143Trademark 153trademarks 153Trial 14

- U -unassigning 38Understand Chart View 69Understand Task Data View 66Undo 11UndoRedo Buttons 11uninstallUninstalling 154Unlink tasks 12 65Up and Down arrows 63Use Project KickStart to 8Use the Gantt Chart Toolbar 63Use the Planning Wizard 9Uses 8Using Past Projects 29 155

- V -Version View Menu 142Visio 138

- W -Wall chart 111WBS Chart Pro 137Welcome to Project KickStart 7Whats Due Next Month 99Whats Due Next Week 99Whats Due Today 99Whats New in Project KickStart Pro 5 11Windows Vista 20

162

copy Experience In Software Inc 1995 - 2006

copy Experience In Software 2008w w w projectkickstartcom

  • Table of Contents
  • Start Here Welcome to Project KickStart
    • Introduction
      • Welcome to Project KickStart
      • Use Project KickStart to
      • Use the Planning Wizard
      • Navigating Project KickStart
      • Whats New in Project KickStart Pro 5
      • Whats New in Project KickStart Pro 5 (Pro Users)
      • Compatibility with earlier versions
      • Activating Trial Version
        • Licenses and Support
          • End User License Agreement
          • Customer Support
          • Reporting Technical Issues
          • Register Project KickStart
              • Planning Projects
                • Name Your Project
                • Phases - Step 1 of 2
                • Phases - Step 2 of 2
                • Goals - Step 1 of 3
                • Goals - Step 2 of 2
                • Goals - Step 3 of 3
                • Similar Projects - Step 1 of 2
                • Similar Projects - Step 2 of 2
                • People - Step 1 of 3
                • People - Step 2 of 3
                • People - Step 3 of 3
                • Obstacles - Step 1 of 3
                • Obstacles - Step 2 of 3
                • Obstacles - Step 3 of 3
                  • Assigning People
                    • Assign Tasks to People
                    • Remove People from a Task
                    • Add a New Person or Resource
                    • Edit or Substitute People
                      • Organizing the Project Plan
                        • About Organizing Tasks
                        • Change the Appearance of the Task List
                        • Show or Hide Tasks in the Task List
                        • Move Tasks within the Task List
                        • Outdent and Indent Tasks
                        • Add a Task or Subtask
                        • Edit Tasks
                        • Add Task Notes and Attachments
                        • Add or Change Task Assignments
                        • Add or Change Task Details
                        • Check Spelling
                          • Scheduling Tasks in the Gantt Chart
                            • Scheduling Overview
                              • About Scheduling Tasks
                              • About the Gantt Chart
                              • Autolink tasks (Pro Users)
                              • About Linking Tasks (Pro Users)
                              • Change the Display of the Schedule
                              • Use the Gantt Chart Toolbar
                              • Use the Gantt Chart Toolbar (Pro Users)
                              • Understand Task Data View
                              • Additional Features in Task Data View (Pro Users)
                              • Understand Chart View
                              • Additional Tools in Chart View (Pro Users)
                                • Change Task Dates
                                • Phase Dates Cannot Be Edited
                                • Quick Tour of Working with Linked Tasks (Pro Users)
                                • Link and Unlink Tasks (Pro Users)
                                • Create a Milestone
                                • Change Task Details
                                • Change Details for Linked Tasks (Pro Users)
                                • Reorganize Tasks in Task Data View
                                • Change the Timescale of the Schedule
                                • Specify Working Days
                                • Change the Color of Taskbars
                                • Make Tasks Overlap (Pro Users)
                                • Manage Changes in Your Schedule (Pro Users)
                                  • Managing Libraries
                                    • Use a Library
                                    • Manage a Library
                                    • Manage the People Library
                                    • Import ACT Contacts and Users to the People Library
                                    • Import Outlook Contacts to the People Library
                                    • Import Outlook Contacts via CSV to the People Library (Pro Users)
                                      • Printing Reports
                                        • Printing Dashboards
                                          • Print Reports
                                          • Print Dashboard Reports
                                          • Page Setup
                                          • Save As
                                            • Printing Task Reports
                                              • Print Task Reports
                                              • Print Preview
                                              • Printer Setup
                                              • Page Setup
                                              • Email Task Reports
                                              • Save As HTML
                                              • Save As RTF
                                                • Printing Gantt Chart Reports
                                                  • Print a Gantt Chart
                                                  • Print Preview a Gantt Chart
                                                  • Page Setup
                                                  • Printing to an Adobe PDF file
                                                  • Save Gantt Chart Images
                                                      • Export Project Data
                                                        • Export to ACT
                                                          • Export to ACT 7 and Later
                                                          • Export to ACT 6
                                                            • Export to Microsoft Outlook
                                                            • Export to Microsoft Word
                                                            • Export to Word Processors (Other than Word)
                                                            • Export to Microsoft Excel
                                                            • Export to Microsoft PowerPoint
                                                            • Export to Microsoft Project
                                                            • Export to SureTrak Project Manager
                                                            • Export to FastTrack Schedule
                                                            • Export to Milestones Professional
                                                            • Export to Mindjet MindManager
                                                            • Export to WBS Chart Pro
                                                            • Export MPX Files
                                                              • Reference
                                                                • Menus
                                                                  • File Menu
                                                                  • Edit Menu
                                                                  • View Menu
                                                                  • Tools Menu
                                                                  • Options
                                                                  • Data Menu
                                                                  • Timescale Menu
                                                                  • Help Menu
                                                                    • Shortcuts
                                                                    • Share Project KickStart data
                                                                    • Open a Project
                                                                    • Dedication
                                                                    • Credits and Trademarks
                                                                    • Uninstalling the software
                                                                    • Using Past Projects
Page 11: Project KickStart Help File in PDF format

11

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5

The following table outlines whatrsquos new in Project KickStart Pro 5

If you own a previous version of Project KickStart yoursquoll notice the new Pro version has a new look and feelAs you begin to check it out yoursquoll soon discover Project KickStart Version 5 is a lot more powerful thanprevious versions and comes with some great new features

FEATURE DESCRIPTION IMPROVED

NEW

Dashboard Reporting

Quickly assess what is due TodayNext Week or Next Month

X

Import Contacts Import from a comma separatedvalue (CSV) file

X

Templates Use as is or customize X

Gantt Chart Greater stability and functionality X

User Interface Contemporary look and colorscheme

X

Preferences Customize look and feel andprogram defaults

X

Productivity Pack Project template Word docs fornewbies

X

Exports Improved Outlook MindManager and ACTimproved data exchange

X

-o-

12

copy Experience In Software Inc 1995 - 2006

Whats New in Project KickStart Pro 5 (Pro Users)

This feature is available only in Project KickStart Professional

The following table outlines whatrsquos new in Project KickStart Pro 5

FEATURE DESCRIPTION IMPROVED NEW

Gantt Chart Task dependencies in Gantt chart X

Link tasks Show task dependencies X

Unlink tasks Remove task dependencies X

Add predecessors Add task predecessors X

Add successors Add task successors X

Project Coordination Link to GoToMeeting for onlinemeetings on projects

X

Project KickStart Pro now includes dependencies on the Gantt chart This sophisticated scheduling andproject management tool is new to Project KickStart Pro and is designed to make complex projectscheduling easy and straightforward

Use dependencies to handle scheduling demands delays and surprises without modifying every task inyour project Dependencies let you make adjustments as events change giving you a more robust scheduleand the opportunity to conduct what-if analysis

Suppose you are managing a landscaping project involving subcontractors and dozens of tasks One ofyour first tasks is to pave a path with flagstones but the shipment of flagstones is two days late Usingdependencies you can delay the path-paving task in a couple of clicks and Project KickStart Proautomatically updates the schedule for the remaining tasks

Although dependencies meet your advanced scheduling needs the Project KickStart Pro approach todependencies keeps them as simple as possible If you want to link a couple of tasks which are dependenton one another you can simply highlight the tasks and click the link icon

If you select the option of Autolinking tasks then when you display the Gantt chart the first time all tasksare pre-linked allowing you to adjust durations schedules of individual tasks and time between taskswhich is called Lead Time in Project KickStart Pro

Unlike other project management programs such as Microsoft Project Project KickStart Pro does notburden you with complicated error messages and various types of dependencies It provides only one typeof dependency finish-to-start which is the most common type This means you can fine-tune your scheduleas soon as you open the Gantt chartmdashwithout having to learn technical terms or advanced projectmanagement techniques

The Project Coordination functionality that we are providing is through GoToMeeting and is a chargedservice

Note

These features are in addition to those listed on the Whatrsquos New in Project KickStart 5 page

-o-

13

copy Experience In Software Inc 1995 - 2006

Compatibility with earlier versions

Project KickStart 5 can open and save projects in Project KickStart 4 prx file format (Same as ProjectKickStart 5)

Project KickStart 5 can open and convert projects saved in Project KickStart 3 prj file format You need tohave a licensed copy of Project KickStart 3 on your system to make the conversion

To open a prj project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click prj file type3 Navigate to the folder that contains the prj file Generally prj files are stored in cprogram filesProject

KickStart 34 Double-click the name of the file

Tips

The tasks in the converted Project KickStart 5 file will have the same start and finish dates and samedurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way (ie as working days) To have weekends as non working days click the Change WorkingSchedule button on the Gantt chart toolbar and mark weekends as non working

Note

Project KickStart 5 does not open and convert prj files from Project KickStart 1 or 2

-o-

14

copy Experience In Software Inc 1995 - 2006

Activating trial version

You may have obtained a FREE 20-day trial version of Project KickStart 5 from our website or from areseller

To convert your Trial Version to a Full Version youll need to purchase a License Key and to activate thesoftware

To activate Project KickStart 5 trial1 Start the Project KickStart trial

2 If you have not purchased your License Key yet click the Buy button to purchase online3 If you have purchased a License Key click the Activate button and copy and paste the License Key

that you received when you purchased Project KickStart as well as your name and email

15

copy Experience In Software Inc 1995 - 2006

4 You must be connected to the Internet and you must tell your Firewall to allow communication forPKS5Kickstartexe

Tip

Your License Key allows 2 activations per user One is for your primary computer and one is for asecond computer you use such as your laptop or home computer

-o-

16

copy Experience In Software Inc 1995 - 2006

Licenses and Support

End User License Agreement

EXPERIENCE IN SOFTWARE INC END USER LICENSE AGREEMENT AND WARRANTYDISCLAIMER

PROJECT KICKSTARTtrade STANDARD 5 AND PRO 5 EDITIONS

NOTICE This is a legally binding contract between you the end user and EXPERIENCE IN SOFTWAREINC

EXPERIENCE IN SOFTWARE INC (EIS or LICENSOR) LICENSES THE ENCLOSED SOFTWARETO YOU (USER or LICENSEE) ONLY UPON THE CONDITION THAT YOU ACCEPT ALL OF THETERMS CONTAINED IN THIS LICENSE AGREEMENT PLEASE READ THE TERMS CAREFULLY BYOPENING THIS PACKAGE BREAKING THE SEAL CLICKING ON THE ldquoAGREErdquo OR ldquoYESrdquo BUTTONOR OTHERWISE INDICATING ASSENT ELECTRONICALLY OR LOADING THE SOFTWARE YOUAGREE TO THE TERMS AND CONDITIONS OF THIS AGREEMENT IF YOU DO NOT AGREE TOTHESE TERMS AND CONDITIONS CLICK ON THE ldquoI DO NOT AGREErdquo ldquoNOrdquo BUTTON OR MAKE NOFURTHER USE OF THE SOFTWARE IF YOU DO NOT AGREE TO THESE TERMS THEN EIS ISUN-WILLING TO LICENSE THE SOFTWARE TO YOU IN WHICH EVENT YOU SHOULD RETURN THEFULL PURCHASED PRODUCT WITH PROOF OF PURCHASE TO LICENSOR OR THE DEALER FROMWHOM IT WAS ACQUIRED WITHIN 15 DAYS OF PURCHASE AND YOUR MONEY WILL BEREFUNDED

LICENSE AND WARRANTY

The software that accompanies this license (Software) is the property of EIS and is protected by copyrightand other intellectual property law Although EIS at all times owns the Software you will have certain rightsto use the Software after your acceptance of this license Except as may be modified by an addendumwhich may accompany or be added to this license your rights and obligations with respect to the use of thisSoftware are as follows

You may

(i) install and use one copy of the specified edition of Software and documentation on a single computerand only by one user (ldquoPrimary Userrdquo) If you have purchased multiple licenses for the Software asindicated as Quantity or Number of Licenses on the Invoice or electronic confirmation issued by EIS orits Resellers then at any time you may have as many copies of the Software in use as you have licenses The Software is ldquoin userdquo on a computer when it is loaded into the temporary memory (ie RAM) or installedinto the permanent memory (eg hard disk CD-ROM or other storage device) of that computer

(ii) install and use a second copy of the Software on a second computer for the limited and exclusive use ofthe Primary User

(iii) use the Software on a network provided that Licensee has a licensed copy of the Software for eachnamed user that can access the Software over that network

(iv) make one copy of the Software for archival purposes or copy the Software onto the hard disk of yourcomputer and retain the original for archival purposes

(v) after written notice to EIS transfer the Software on a permanent basis to another person or entityprovided that you retain no copies of the Software and the transferee agrees to the terms of this agreement

You may not

(i) rent lease copy distribute license or otherwise transfer the Software or its documentation to any otherparty Licensee may make a reasonable number of back-up copies for archival purposes only TheSoftware contains copyrighted material trade secrets and other proprietary material If Licensee has theright to duplicate the Software for multiple Users then Licensee must reproduce on all such copies of theSoftware the copyright notices and any other proprietary legends that were on the original copy of theSoftware or

(ii) decompile reverse engineer disassemble translate make any attempt to discover the source code ofthe Software or otherwise reduce the Software to a human perceivable form or modify network or create

17

copy Experience In Software Inc 1995 - 2006

derivative works based upon the Software or the documentation in whole or in part nor permit any otherparty to do so

Notwithstanding anything herein if the Software is lawfully acquired outside of the United States within ajurisdiction which is a member of the European Union subject to the EEC Council Directive 91250EEC ofMay 14 1991 Licensee agrees that within that jurisdiction it shall not and shall not allow any party onLicensees behalf to attempt to reverse engineer or decompile the Software into another computerlanguage except as expressly and specifically provided in the EEC Council Directive 91250EEC of May14 1991 Any and all information obtained during such lawful reverse engineering andor decompilingactivities including but not limited to the organization logic algorithms and processes of the Softwareshall be deemed to be the confidential and proprietary information of EIS

Licensee shall not make copies of the copyrighted Software documentation without the prior writtenpermission of EIS provided that for electronic transactions Licensee may make one (1) hard copy of suchdocumentation for each User

Intellectual Property and Duplication of Software

The Software contains copyrighted material trade secrets and other proprietary material If Licensee hasthe right to duplicate the Software for multiple Users then Licensee must reproduce on all such copies ofthe Software the copyright notices and any other proprietary legends that were on the original copy of theSoftware

Upgrades

To use a Product identified as an upgrade you must first be licensed for the product identified by EIS aseligible for the upgrade After upgrading you may no longer transfer the product that formed the basis foryour upgrade eligibility to another person or entity

Technical Support

Licensee must register the Software in order to be eligible for free technical support (including installationand registration of the product) during the first 90 days after purchase

Thirty Day Money Back Guarantee

If you are the original Licensee of this copy of the Software and are dissatisfied with it for any reason youmay return the complete product together with your receipt to EIS or an authorized dealer postageprepaid for a full refund at any time during the thirty-day period following the delivery to you of thePurchased Software

Export Law Assurances

You are responsible for complying with all trade regulations and laws both foreign and domestic Youacknowledge that none of the Software or underlying information or technology may be downloaded orotherwise exported or re-exported (i) into Afghanistan (Taliban-controlled areas) Cuba Iran Iraq LibyaNorth Korea Serbia (except Kosovo) Sudan and Syria or any other country subject to a US embargo or(ii) to anyone on the US Treasury Departments list of Specially Designated Nationals or the USCommerce Departments Denied Parties List or Entity List By using the Software you are agreeing to theforegoing and are representing and warranting that (i) no US federal agency has suspended revoked ordenied you export privileges (ii) you are not located in or under the control of a national or resident of anysuch country or on any such list and (iii) you will not export or re-export the Software to any prohibitedcounty or to any prohibited person entity or end-user as specified by US export controls as defined byEAR 15 CFR Parts 730-774 and BXA (httpwwwbxadocgov)

Data Collection and Privacy Policy

You acknowledge and agree that EIS may collect and retain information about you such as your nameaddress and e-mail address You also understand that EIS may employ other companies to performfunctions on our behalf such as fulfilling orders delivering packages sending postal mail and e-mailproviding marketing assistance and processing credit card payments These companies may have accessto personal information needed to perform their functions and may not use such information for otherpurposes By assenting to this agreement you agree that you have read and understand our Privacy PolicyFor more detailed information httpwwwprojectkickstartcomhtmlprivacy_statementhtm

Termination

This License is effective until terminated Licensee may terminate this License at any time by destroying allcopies of the Software and its documentation This License will terminate immediately without notice from

18

copy Experience In Software Inc 1995 - 2006

EIS if Licensee fails to comply with any provision of this License Upon termination Licensee must destroyall copies of the Software and its documentation and cease and desist from any further use of the Software

Limited Warranty

EIS warrants that the media on which the Software is distributed will be free from defects and that theSoftware shall perform substantially as described in its documentation for a period of sixty (60) days frompurchase Your sole remedy in the event of a breach of this warranty will be that EIS will replace anydefective media returned to EIS within the warranty period EIS does not warrant that the Software willmeet your requirements or that operation of the Software will be uninterrupted or that the Software will beerror-free

THE ABOVE WARRANTY IS EXCLUSIVE AND IN LIEU OF ALL OTHER WARRANTIES WHETHEREXPRESS OR IMPLIED INCLUDING THE IMPLIED WARRANTIES OF MERCHANTABILITY FITNESSFOR A PARTICULAR PURPOSE AND NONINFRINGEMENT OF INTELLECTUAL PROPERTY RIGHTSTHIS WARRANTY GIVES YOU SPECIFIC LEGAL RIGHTS YOU MAY HAVE OTHER RIGHTS WHICHVARY FROM STATE TO STATE AND COUNTRY TO COUNTRY

Disclaimer of Damages

REGARDLESS OF WHETHER ANY REMEDY SET FORTH HEREIN FAILS OF ITS ESSENTIALPURPOSE IN NO EVENT WILL EIS OR ITS RESELLERS BE LIABLE TO YOU FOR ANY SPECIALCONSEQUENTIAL INDIRECT OR SIMILAR DAMAGES INCLUDING BUT NOT LIMITED TO ANY LOSTPROFITS OR LOST DATA ARISING OUT OF THE USE OR INABILITY TO USE THE SOFTWARE EVENIF EIS HAS BEEN ADVISED OF THE POSSIBILTIY OF SUCH DAMAGES SOME STATES DO NOTALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FOR INCIDENTAL OR CONSEQUENTIALDAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAY NOT APPLY TO YOU IN NO CASESHALL EISS ITrsquoS RESELLERrsquoS LIABILITY EXCEED THE PURCHASE PRICE FOR THE SOFTWARE

SOME STATES AND COUNTRIES INCLUDING MEMBER COUNTRIES OF THE EUROPEANECONOMIC AREA DO NOT ALLOW THE LIMITATION OR EXCLUSION OF LIABILITY FORINCIDENTAL OR CONSEQUENTIAL DAMAGES SO THE ABOVE LIMITATION OR EXCLUSION MAYNOT APPLY TO YOU

The disclaimers and limitations set forth above will apply regardless of whether you accept the Software

US Government Restricted Rights

DISTRIBUTION TO THE US GOVERNMENT This Software is commercial software developedexclusively at private expense This Software and the documentation are provided with RESTRICTEDRIGHTS applicable to private and public licenses alike Use duplication or disclosure by civilian agenciesof the US Government shall be in accordance with the Commercial Computer Software-Restricted Rightsclause at FAR 52227-19 Use duplication or disclosure by Department of Defense agencies is subjectsolely to the terms of this software licensing agreement pursuant to DFARS 2277202Contractormanufacturer of the Software is EXPERIENCE IN SOFTWARE INC 2029 Durant AveBerkeley CA 94704 USA

General

This Agreement shall be governed by the laws of the State of California without giving effect to principles ofconflict of laws You hereby consent to the exclusive jurisdiction and venue of the state courts sitting in SanFrancisco County California or the federal courts in the Northern District of California to resolve anydisputes arising under this Agreement This Agreement contains the complete understanding between theparties with respect to the subject matter hereof and supersedes all prior or contemporaneous Agreementsor understandings whether oral or written You agree that any varying or additional terms contained in anypurchase order or other written notification or document issued by you in relation to the Software licensedhereunder shall be of no effect No provision hereof shall be deemed waived or modified except in writing No EIS dealer agent or employee is authorized to make any amendment to this Agreement

The intellectual property protections the disclaimers of warranties and the limitation of damages shallsurvive termination The failure or delay of EIS to exercise any of its rights under this Agreement or uponany breach of this Agreement shall not be deemed a waiver of those rights or of the breach If any provisionof this Agreement is held invalid the remainder of this Agreement will remain in full force and effect

Should you have any questions concerning this Agreement or if you desire to contact EIS for any reasonplease write to EXPERIENCE IN SOFTWARE INC 2029 Durant Ave Berkeley CA 94704 USA

-o-

19

copy Experience In Software Inc 1995 - 2006

20

copy Experience In Software Inc 1995 - 2006

Customer Support

When you need help in solving a problem with the software Experience In Software is available to assistyou First check this help file for information on the part of the program you are having a problem withAlso take a look at the Web site for late-breaking technical support information wwwprojectkickstartcomsupporttechnical_supportcfm If you are a regustered user you can obtain support in the following ways

Web httpwwwprojectkickstartcomsupportemail_supportcfm E-mail supportprojectkickstartcom

Hours 900 am to 500 pm Pacific time Monday - Friday

To make the support process more efficient have the following information ready for the support staff

Provide your name phone number and email address

Describe the problem including any error messages

If reporting a potential bug describe what you did immediately before seeing the bug

Provide the Project KickStart version number and Build Date (Click Help on the menu bar and thenclick About Project KickStart)

Identify the version of Windows (Windows Vista etc) you are using

Notes

Our policy is to respond to support email within two business days If you have not received aresponse please double check that spam filters are blocking our messages to you If you maintain anincoming whitelist please allow all messages from the projectkickstartcom domain

Support is available in English only If you purchased a translated version please contact your localreseller for help in other languages

See Also

Reporting Technical Issues

-o-

21

copy Experience In Software Inc 1995 - 2006

Reporting Technical Issues

If Project KickStart 5 detects an error it will write a log of technical issues and then create a temporarymenu to the right of the Help menu which says Send Log to Technical Support You should immediatelyclick the menu and then click Yes to send the error log to us

Please fill in your email address so that we can get back to you with any questions about what caused theerror

Tip

If you have an Internet Security Program such as Norton Internet Security please allowPKS5Kickstartexe to communicate with the Internet to report the error

-o-

22

copy Experience In Software Inc 1995 - 2006

Register Project KickStart

To print this page click the Print button on the Help window toolbar

Register Project KickStart 5 for technical support upgrade information and software discounts You canregister by completing printing and then sending or faxing this form to Experience In Software You canalso register online at httpwwwprojectkickstartcomsupportregiscfm

Name _______________________________________________________

Title _______________________________________________________

Company _______________________________________________________

Address _______________________________________________________

CityStateZip ______________________________________________________

Country _______________________________________________________

Day Phone _______________________________________________________

Fax _______________________________________________________

E-mail _______________________________________________________

Purchased from __ Experience In Software __ Other ____________________

Number of people in company _ 1 to 25 _ 26 to 100 _ 101 to 1000 _ Over 1000

Which industry do you work in ______________________________________

Interested in a project management workshop for your company __ Yes __ No

Comments _______________________________________________________

_________________________________________________________________

_________________________________________________________________

Experience In Software 2029 Durant Ave Berkeley CA 94704

Send or FAX to (510) 644-3823

-o-

23

copy Experience In Software Inc 1995 - 2006

Planning Projects

Name Your Project

Before you start thinking about the tasks in your project yoursquoll want to give your project an appropriate titleIf you open an existing project you might want to edit or change the name of your project

To name your project1 In the Type a name for your project text box enter a name2 Click the Next button

Tips

You can enter up to 58 characters and more than one

Use short descriptive project names such as ldquoCompany Web Siterdquo

Avoid vague project names such as ldquoDatabase Projectrdquo or ldquoCDP-7rdquo especially if you plan to circulatereports to others

Enter your project title using uppercase letters if you want the title to stand out in reports

One way to reuse your projects is to open an existing project and then change its name in this stepAfter saving the project with a different name you can modify details to customize the project

See Also

Use the Planning Wizard

-o-

24

copy Experience In Software Inc 1995 - 2006

Phases - Step 1 of 2

After naming your project the next step in the Planning Wizard is to identify the major activities in yourproject Using phases helps organize tasks so that an obviously early task such as ldquoOrganize materialsrdquoappears before a later task such as ldquoReview final draftrdquo

To enter phases1 Type each phase one per line

OrClick the Phases Library button The Phases Library contains typical phases that many organizationsuse in the early middle and late stages of their projects Drag an entry from the Phases Library to thelist and then click the OK button to close the Phases Library

2 To insert a phase in the middle of the phases list click where you want to insert a new blank line andthen press the Insert keyTo edit the phase text double-click the phase

Tips

Start each phase name with an action verb as in ldquoBuild systemrdquo or ldquoWrite reportrdquo

Use actions that have clearly defined beginnings middles and ends For example you can scheduletasks like ldquoTest prototyperdquo more easily than tasks like ldquoPurchase high-quality partsrdquo

Note

Youll have the opportunity to edit phases later in the Tasks step For now continue planning thephases in your project

See Also

Use the Planning Wizard

Use a Library

Move Tasks within the Task List

-o-

25

copy Experience In Software Inc 1995 - 2006

Phases - Step 2 of 2

For each phase list all of the tasks that could be performed during that phase You can refine and organizethe tasks later in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each phase1 Type the tasks associated with the phase displayed in the Tasks for phase text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next phase in your project click the Next button If you prefer to work out oforder click the Tasks for phase list arrow and then click the phase you want

3 When you are finished entering tasks for the last phase in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

26

copy Experience In Software Inc 1995 - 2006

Goals - Step 1 of 3

Enter the goals for your project the objectives you hope to accomplish Then you can brainstorm anyadditional tasks that will help you meet these goals

To enter goals1 Type each goal one per line

OrThe Goals Library contains typical sample goals that you can customize Drag an entry from the GoalsLibrary to the list and then click the OK button to close the Goals Library

2 To insert a goal in the middle of the goals list click where you want to insert a new blank line and thenpress the Insert keyTo edit the goal text double-click the goal

3 Click the Next button

Tips

List goals that apply to the entire project such as Develop a high-quality system A goal such as Getthe contract signed applies only to an early phase

Write goals as actions you can measure For example Complete the project for $75000 or less ismore concrete and specific than Complete the project within budget Numbers make goal statementsreal

If youre not sure how to measure a goal use a range as in About 15 - 25 people will use the results ofthe project

See Also

Use the Planning Wizard

Use a Library

-o-

27

copy Experience In Software Inc 1995 - 2006

Goals - Step 2 of 3

For each goal list any new tasks needed to accomplish that goal You can refine and organize the taskslater in the Tasks stepClick the following illustration to see tips for using this window

To enter the tasks for each goal1 Type the tasks for accomplishing the goal displayed in the For the goal text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter tasks for the next goal in your project click the Next button If you prefer to work out of orderclick the For the goal list arrow and then click the goal you want

3 When you are finished entering tasks for the last goal in your project click the Next button to continuein the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

Write the tasks roughly in the order that you will complete them You can reorganize the tasks later inthe Tasks step

See Also

Use a Library

Move Tasks within the Task List

-o-

28

copy Experience In Software Inc 1995 - 2006

Goals - Step 3 of 3

After you identify new tasks for your project assign each new task to an appropriate phase

To assign new tasks to phases1 Click a task in the New tasks to achieve goals list (on the left)2 Click one or more phases in the Assign them to Phases list (on the right) to which the task belongs A

checkmark appears next to tasks youve assigned

If a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Note

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

29

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 1 of 2

Projects often have tasks in common The Similar Projects step makes it easy for you to borrow tasks fromother projects and add them to your current project

By default this step shows the Project KickStart (PRX) projects stored in the same folder as the currentproject including sample projects and those you already created

To select similar projects1 Review the projects in the list To sort the project names alphabetically click the Project Name header

Click the Project Name header again to sort the names in reverse order2 Click one or more projects in the list that contain tasks you want to use in the current project A

checkmark appears next to the projects you selected3 To list projects stored in a different folder on your system click the Browse button and then navigate to

the folder you want4 Click the Next button

If no projects seem related to your current project skip this step for now

Tips

The Similar Projects step becomes more helpful the more you use Project KickStart Every time yousave a project it becomes available for future use

Many projects share the same phases and tasks such as those for setting up a contract or purchasingequipment You can use Project KickStart to create these mini-projects or templates and then importtheir tasks into a new project during the Similar Projects step

-o-

30

copy Experience In Software Inc 1995 - 2006

Similar Projects - Step 2 of 2

After you select one or more projects containing tasks you might want to use assign those borrowed tasksto a phase in this project

To assign borrowed tasks to phases1 Click a task in the list on the left If a task includes subtasks click the plus icon to expand the list Click

the minus icon if you want to hide the subtasks To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more phases in the Assign tasks to phase(s) of your project list (on the right) to whichthe task belongs A checkmark appears next to tasks youve assigned

3 To assign one or more tasks to a new phase select the tasks click ltNew Phasegt in the Assign tasksto Phases of your project list and then type a name for the new phase

4 To select tasks from another project you selected as similar click the Tasks from Similar Projects listarrow click the project you want and then assign the tasks to phases

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also Edit Tasks

-o-

31

copy Experience In Software Inc 1995 - 2006

People - Step 1 of 3

Enter the names or descriptions of the people involved in your project Include key decision makers suchas executives or customers who must approve or consult with you about the project These are yourprojects resources In the next People step youll identify new tasks associated with these resources

To enter people1 Type each name or description one per line

OrIf you have stored information about people and other resources in the People Library click the PeopleLibrary button drag an entry from the library to the list and then click the OK button to close thePeople Library

2 To edit the people text double-click the name or description3 Click the Next button

Tips

Be consistent with the resource names in your projects For instance avoid using Richard in oneproject and Dick in another project when referring to the same person

Include names for people teams (such as Quality control team) departments (such as Manufacturing)companies (such as Acme Widgets Corp) or even equipment (such as wheat thrasher)

Note

Add people and other resource information to the People Library so that you can quickly drag resourcesfrom the library to any project You can even import people from your Outlook and ACT address books

See Also

Manage the People Library

Import ACT Contacts and Users to the People Library

-o-

32

copy Experience In Software Inc 1995 - 2006

People - Step 2 of 3

Now that you have defined the people needed to complete your project list any new tasks that eachresource might suggest or require

To enter new tasks for each person1 Type the new tasks associated with the person displayed in the Tasks For text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next person in your project click the Next button If you prefer to work out oforder click the Tasks For list arrow and then click the person you want

3 When you are finished entering new tasks for the last person in your project click the Next button tocontinue in the Planning Wizard

Tips

This step provides a good opportunity to get input from your resources directly and make sure theproject plan reflects the views of everyone on the team

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo Write the tasks roughly in the order that you will complete them You can reorganize the tasks later in

the Tasks step

Note

You assign people to tasks in the Assign Tasks and Schedule steps

See Also

Use a Library

Move Tasks within the Task List

Assign Tasks to People

-o-

33

copy Experience In Software Inc 1995 - 2006

People - Step 3 of 3

After you identify new tasks associated with the people in your project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by people list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

34

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 1 of 3

Every project has obstacles and risks that can affect its success List the major obstacles you face incompleting your project Then you can brainstorm any additional tasks that can help you overcome orminimize these problems

To enter obstacles1 Type each obstacle one per line

OrThe Obstacles Library contains typical sample obstacles that you can customize Drag an entry fromthe Obstacles Library to the list and then click the OK button to close the Obstacles Library

2 To insert an obstacle in the middle of the obstacles list click where you want to insert a new blank lineand then press the Insert key

3 To edit the obstacle text double-click the obstacle4 Click the Next button

Tips

Be creative when thinking of obstacles Highly imaginative obstacles can suggest realistic tasks Forexample Project manager kidnapped by aliens can lead to Project manager out of town forconference In Obstacles step 2 of 3 you can add the realistic activities as tasks You can delete theunrealistic obstacles later by returning to Obstacles step 1 of 3

Avoid listing too many obstacles even if they are realistic Hard core pessimists find it hard to getanything done

Edit and update the Obstacles Library so that you can quickly drag obstacles from the library to anyproject in your organization

See Also

Use a Library

-o-

35

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 2 of 3

After identifying the obstacles to completing your project determine how you can avoid these stumblingblocks List any new tasks you need to overcome or avoid each obstacle In this way you are developing acontingency plan for your project

To enter new tasks for each obstacle1 Type the new tasks associated with the obstacle displayed in the Obstacle text box one per line

OrIf you have stored tasks in the Tasks Library click the Tasks Library button and then drag a task fromthe library to the list

2 To enter new tasks for the next obstacle in your project click the Next button If you prefer to work outof order click the Obstacle list arrow and then click the obstacle you want

3 When you are finished entering new tasks for the last obstacle in your project click the Next button tocontinue in the Planning Wizard

Tips

Avoid listing tasks that require too much or too little time Generally break down tasks that take morethan six weeks into shorter tasks so that you can measure progress easily

But donrsquot break down tasks too finely Two-hour tasks are unrealistic because you canrsquot control mostprojects that closely

Use an action verb to begin each task name such as ldquoOutline reportrdquo or ldquoContact three suppliersrdquo

You can reorganize the tasks and add notes later in the Tasks step

See Also

Use a Library

Move Tasks within the Task List

Add Task Notes and Attachments

-o-

36

copy Experience In Software Inc 1995 - 2006

Obstacles - Step 3 of 3

After you identify new tasks for overcoming the obstacles to completing project assign each new task to anappropriate phase

To assign new tasks to phases1 Click a task in the New tasks suggested by obstacles list (on the left)2 Click one or more phases in the Assign them to phase(s) list (on the right) to which the task belongs

A checkmark appears next to tasks youve assignedIf a task does not belong in any phase you can assign the task to a new phase or you can leave itunassigned To assign the selected task to a new phase click ltNew Phasegt and then type a name forthe new phase Project KickStart assigns the selected task to the new phase

3 Click the Next button

To unassign a task

To unassign a task click the task and then click the highlighted phase from which you want to removethe task You can assign that task to a different phase if necessary

Tip

If you want to revise a task assign it to a phase here You can edit the task later in the Tasks step

See Also

Edit Tasks

-o-

37

copy Experience In Software Inc 1995 - 2006

Assigning People

Assign Tasks to People

After youve identified people working on your project you can assign tasks to each person or otherresource

To assign tasks to people1 Click a phase or task in the For each phase or tasks list (on the left)

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click one or more people in the Assign some people list (on the right) who will perform the task Acheckmark appears next to tasks youve assigned

3 To assign a selected task to all of the people in your project click the All button4 To assign one or more tasks to a new person select the tasks click ltNew Persongt in the Assign

some people list and then type a name for the new person

To unassign a task

To unassign a task click the task and then click the highlighted person from which you want to removethe task You can assign that task to a different person if necessary You can also click the All buttonto remove a task from all of its assignments at the same time

Tip

Some users like to skip to the Tasks step before performing the Assign step That way they can edittheir list of tasks before assigning people and resources This helps them focus the project and givesthem a clearer idea of what must be done before committing resources

Notes

You can also assign tasks to people in the Tasks step and the Schedule step

You can assign tasks to non-personnel resources such as equipment (a CAD system or back hoe)facilities (a classroom or hotel) services (lab work or insurance) or materials (lumber or officesupplies) just as you assign tasks to people Click ltNew Persongt to add a new resource to the list

See Also

Remove People from a Task

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

38

copy Experience In Software Inc 1995 - 2006

Remove People from a Task

After assigning tasks you might need to remove people from a task or unassign them

To remove people from a task (unassigning)1 Click a phase or task in the For each phase or tasks list (on the left)

The people assigned to that phase or task are highlighted in the Assign some people list (on theright)

2 Click a highlighted person to remove or unassign that person from the taskWhen the person is no longer highlighted they are not assigned to the selected task

See Also

Assign Tasks to People

Add a New Person or Resource

Edit or Substitute People

Add or Change Task Assignments

-o-

39

copy Experience In Software Inc 1995 - 2006

Add a New Person or Resource

If you realize that you want to assign some tasks to a person not included in the Assign some people listyou can add that person and assign tasks in the same step You can also add non-personnel resourcessuch as such as equipment (a CAD system or back hoe) facilities (a classroom or hotel) services (lab workor insurance) or materials (lumber or office supplies)

To add a new person or resource1 Select one or more phases or tasks in the For each phase or tasks list (on the left) 2 Click ltNew Persongt in the Assign some people list and then type a name for the new person or

resourceThis adds the new person or resource to the list and assigns the selected tasks to them

See Also

Assign Tasks to People

Remove People from a Task

Edit or Substitute People

Add or Change Task Assignments

-o-

40

copy Experience In Software Inc 1995 - 2006

Edit or Substitute People

If the people or resources in your project change you can replace them or edit their names anddescriptions

To edit or substitute people1 Click the People icon

You return to People step 1 of 32 In the list of people defined for the project double-click the person you want to edit or replace or click

the name and press F23 Edit the name or description of the person

When you return to the Assign step the name of the person appears as you changed it

See Also

Assign Tasks to People

Remove People from a Task

Add a New Person or Resource

Add or Change Task Assignments

-o-

41

copy Experience In Software Inc 1995 - 2006

Organizing the Project Plan

About Organizing Tasks

In the Tasks step you work with an outline of your project plan Here you can easily edit and reorganizetasks spell check and even add notes and attachmentsClick the following illustration to see tips for using this window

Edit the Task List to Consolidate and delete tasks Add subtasks Add or change task assignments Add follow-up notes to tasks Add or change attachments Review the order of the tasks in each phase and move tasks up or down so that they progress

sequentially Review task descriptions to make sure they are clear and that all the team members will understand

them Convert vague tasks such as reminders and open issues to task notes

Notes

Some users like to revise their Task List before they assign resources You can go to the Task List atany time while you are using Project KickStart

Each project created with Project KickStart can contain up to 1000 tasks

See Also

Change the Appearance of the Task List

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

Add Task Notes and Attachments

Add or Change Task Assignments

Add or Change Task Details

-o-

42

copy Experience In Software Inc 1995 - 2006

43

copy Experience In Software Inc 1995 - 2006

Change the Appearance of the Task List

You can change the appearance of the Task List so you can work with it more effectively

To add a column

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task ListBy default the Task List shows the Task Name Assignments and Notes columns You can also showCost and Done columns

To hide a column

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

To move a column

Drag a column heading to a new position in the Task List

To change the column width

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Show or Hide Tasks in the Task List

-o-

44

copy Experience In Software Inc 1995 - 2006

Show or Hide Tasks in the Task List

To hide tasks or subtasks

To hide the subtasks for a task click the minus icon next to the task

To hide all the tasks in the Task List and show only phases click all the minus icons next to thephases

To show tasks or subtasks

To show the subtasks for a task click the plus icon next to the task

To show the tasks for a phase click the plus icon next to the phase

See Also

Change the Appearance of the Task List

-o-

45

copy Experience In Software Inc 1995 - 2006

Move Tasks within the Task List

In the Tasks step you can reorganize the tasks in your project so that they better represent the work youand your team plan to do In particular you should review the order of the tasks in each phase and move tasks up and down so thattasks follow in a sequential order Use the Up and Down Arrow buttons to move the tasks

To reorder tasks1 Click a task or phase to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youmove must be next to each other

2 Click the Up Arrow button to move a task up one rowOrClick the Down Arrow button to move a task down one row

Note

When you move a bolded phase you move the phase and all of its tasks at the same time

See Also

Outdent and Indent Tasks

-o-

46

copy Experience In Software Inc 1995 - 2006

Outdent and Indent Tasks

Subtasks are smaller parts of tasks Use subtasks when you need to break tasks down into moremanageable parts In the Task List you can turn a task into a subtask by indenting it You can also add anew subtask to the Task ListIf your Task List contains subtasks you can turn a subtask into a task by outdenting itUse the Outdent and Indent buttons to promote (outdent) and demote (indent) tasks

To promote and demote tasks1 Click a phase task or subtask to select it

To select two or more adjacent tasks hold down the Shift key and then click the tasks The tasks youpromote or demote must be next to each other

2 Click the Outdent button to promote the selected tasksOrClick the Indent button to demote the selected tasksYou can also right-click an item in the Task List and then click Outdent or Indent on the shortcut menu

Tips

When you promote (outdent) a task it becomes a phase and its subtasks become tasks When youpromote a subtask it becomes a task

When you demote (indent) a phase it becomes a task and its tasks become subtasks When youdemote a task it becomes a subtask

Notes

You can have up to 10 levels of subtasks in your project

Use Task Notes instead of subtasks for task comments or additions that are not actually work items

See Also

Move Tasks with the Task List

Add a Task or Subtask

-o-

47

copy Experience In Software Inc 1995 - 2006

Add a Task or Subtask

If you realize you want to add another task to the Task List use the Add Task button A subtask is a smaller part of a task Use subtasks when you need to break tasks down into moremanageable partsTo add a subtask use the Add Subtask button

To add a task1 Click a task and then click the Add Task button right-click a task and then click Add Task on the

shortcut menu or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskProject KickStart numbers the new task in the proper sequence

To add a subtask1 Click a task and then click the Add Subtask button right-click a task and then click Add Task on the

shortcut menu or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtask3 Project KickStart numbers the new subtask in the proper sequenceNote

To add a new phase click a phase and then click the Add Task button

See Also

Outdent and Indent Tasks

-o-

48

copy Experience In Software Inc 1995 - 2006

Edit Tasks

Edit tasks in the Task List to fine tune your project You can edit the names of the phases tasks andsubtasks delete tasks and cut copy and paste task information

To edit task names1 Click the phase task or subtask you want to edit and then press the F2 key2 Type to edit the text3 To undo an edit click the Undo button

To delete a task

Click the task you want to delete and then press the Delete key or click the Delete button Or

Right-click a task and then click Delete Row on the shortcut menu

To cut copy and paste tasks1 Select the tasks you want to cut or copy Use Shift-click or Ctrl-click to select more than one task

2 Click the Cut button (Ctrl-X) or click the Copy button (Ctrl-C )

3 Click where you want to insert the tasks and then click the Paste button (Ctrl-V)

Tip

If your project includes some of the same tasks repeated in different phases save time by copying rowsof tasks and pasting them to another phase

Notes

You can also edit task names using the Task Information dialog box To open this dialog boxdouble-click a task or click a task and then click the Edit Task Information button

If you delete a phase you also delete its tasks and subtasks If you delete a task you also delete itssubtasks Project KickStart warns you before deleting tasks or subtasks and gives you a chance tocancel the deletion

See Also

Add Task Notes and Attachments

Add or Change Task Assignments

-o-

49

copy Experience In Software Inc 1995 - 2006

Add Task Notes and Attachments

You might find that some of your tasks are actually more notes than tasks For example Remember tocheck Daves specifications might work better as a note than a task especially if it could take several daysto catch up with Dave but only a few minutes to review his specs By using notes you clarify your projectand increase your chances for success An attachment is a document graphic or any other type of file related to a task For example to a tasksuch as Review proposal you can attach the proposal document Or you can attach a hyperlink to a pageon a web site

To add a note or attachment to a task1 Double-click the Notes column next to the task The Task Information dialog box opens to the Notes

and Attachments tab2 In the Enter a Note box type in or edit the task note (Press Enter to insert line break)3 To attach a file click the Add Files button In the Select File to Attach dialog box navigate to the file

you want and then click the Open button The filename appears in the Add Attachments box with apaperclip icon

4 To insert a hyperlink click the Add URL button In the Insert Hyperlink dialog box type in the URL youwould like to link to The URL appears in the Add Attachments box with a paperclip icon

5 Click the OK button

To open or remove an attachment1 Open the Notes and Attachments tab in the Task Information dialog box2 To open an attachment double-click the filename in the Add Attachments box3 To delete an attachment click the attachment in the Add Attachments box and then click the Remove

button

To change a task into a task note1 Copy (Ctrl-C) the text of the task you want to change into a note2 Double-click the task to which you want to add the note3 In the Task Information dialog box click the Notes and Attachments tab and add paste the text in the

Enter a Note box Close the Task Information dialog box4 In the Task Name column delete the original task that how appears as a note for a different task

Tips

Use notes to keep track of the operational details of a project the little nagging details that are criticalto success

Although the Task List provides plenty of room for notes it is best to keep your notes concise

Some tasks might benefit from instructional notes those that explain what to do in a task or how tosuccessfully complete a task

You can also include a hyperlink in a note by typing httpxxx (where xxx is an e-mail or Web address)In Outlook Word Excel or your browser the hyperlink will be active You can click the link to godirectly to that site or to send an e-mail to that address

Note

You can also open the Notes and Attachments tab in the Task Information dialog box by clicking atask and then clicking the Edit Notes and Attachments button or by double-clicking a task to openthe Task Information dialog box and then clicking the Notes and Attachments tab

See Also

Edit Tasks

Add or Change Task Assignments

Change Task Details in the Gantt chart

50

copy Experience In Software Inc 1995 - 2006

-o-

51

copy Experience In Software Inc 1995 - 2006

Add or Change Task Assignments

The Assignments column in the Task List shows the people and other resources assigned to each task

To add or change a task assignment1 Double-click the Assignments column next to the task The Task Information dialog box opens to the

Assignments tabThe Assignments tab lists all of the people and resources in your project If this task is already assignedto people they are highlighted on the Assignments tab

2 To assign this task to another person or resource click the resource name in the Assignments list3 To remove (unassign) this task from a person or resource click a highlighted name in the Assignments

list4 To add a person and assign the task at the same time click ltNew Persongt in the Assignments list

and then enter the name of the new person5 Click the OK button

Note You can also open the Task Information dialog box by clicking a task and then clicking the Edit Task

Information button to or by double-clicking a task

-o-

52

copy Experience In Software Inc 1995 - 2006

Add or Change Task Details

Besides task names notes and assignments you can include cost and done details about tasks In theSchedule step you can also include start and finish dates and durations

To add task details

1 Click a task and then click the Edit Task Information button or double-click the task you wantThe Task Information dialog box opens

2 Enter Cost or Done informationCost Enter the cost associated with this task For example you could enter $150 as the cost for a tasknamed Purchase photo CD Done Click the list arrow to select 0 25 50 75 or 100 or enter the percentage you want such as33

3 Click the OK button

To show or hide task details

Right-click a column heading to open a shortcut menu and then click Cost or Done In the shortcutmenu a checkmark appears next to columns that are displayed in the Task List

To edit task details

Open the Task Information dialog box (click a task and then click the Edit Task Information button or double-click the task you want)

Or

Double-click the Cost or the Done entry to update these details directly in the Task List

Notes

The Cost amount appears with the currency symbol set for your system (in the Regional and LanguageOptions dialog box of the Windows Control Panel)

Project KickStart calculates the running totals for the tasks within a phase and displays this total in theCost column for the phase When you create and print Task reports the total costs for the entire projectappear at the end of the Cost column

See Also

Edit Tasks

Print Task Reports

-o-

53

copy Experience In Software Inc 1995 - 2006

Check Spelling

Spell check your tasks and notes before you print reports or export to other software

To check the spelling of tasks and notes

Click the Check Spelling button on the Project KickStart toolbarOr

Click Tools on the menu bar and then click Spelling

Notes

Spell checking updates entries on the Task List and the Gantt chart (the Schedule step) It can alsocheck the spelling of intermediate entries such as goals and tasks to accomplish goals if you spellcheck during those steps

Spell checking does not check the names of people on the People List or the contents of the PeopleLibrary

-o-

54

copy Experience In Software Inc 1995 - 2006

Scheduling Tasks in the Gantt Chart

55

copy Experience In Software Inc 1995 - 2006

Scheduling Overview

About Scheduling Tasks

In the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the other

You work with the Gantt chart using the familiar Task Data view in the left pane or the graphical Chart viewin the right pane To adjust the schedule to fit your project set the project start date in the toolbar moveand resize the taskbars in the Chart view or change the start and finish dates or durations of individualtasks in the Task Data view

Click the following illustration to see general tips for using the Gantt chart See About the Gantt Chart formore details

In the Schedule step you can

Change a start date for the project Set start and finish dates or durations for tasks Change the timescale of the schedule Change the working schedule to specify which days are nonworking days such as weekends and

holidays Fine-tune the organization of the phases tasks and subtasks Color-code tasks to identify assignments critical deadlines or other information at a glance Insert milestones to indicate events that mark a moment in time such as the approval of a design Review and edit task details including task name assignments notes and attachments Hide or show task data columns in the left pane Export project data to other software applications

Tip

56

copy Experience In Software Inc 1995 - 2006

To save time you can reuse projects such as one for a trade show and create an updated scheduleby changing the project start date in the Schedule step

See Also

About the Gantt Chart

Understand Task Data View

Understand Chart View

-o-

57

copy Experience In Software Inc 1995 - 2006

About the Gantt Chart

The Gantt chart provides two views of your project schedule The Task Data view in the left pane lists thesame task information as in the Tasks step but now includes durations and start and finish dates TheChart view in the right pane displays taskbars and symbols to represent the same information You canchange the schedule information by working directly in the Task Data view and Chart view or by using theGantt Chart toolbarClick the following illustration to see general tips for using this window

-o-

58

copy Experience In Software Inc 1995 - 2006

Autolink tasks (Pro Users)

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatProject KickStart Pro does not assume that you want to link all of the tasks in a serial manner (one after theother) when you get to the Gantt chart Indeed many users want that behavior and many do notTo accomodate both types of users you can set whether you want the program to Autolink tasks In theTools menu select Autolink tasks Thereafter in all your projects when you get to the Gantt chart for thefirst time the tasks will be linked in a serial mannor

-o-

59

copy Experience In Software Inc 1995 - 2006

About Linking Tasks

This feature is available only in Project KickStart ProfessionalIn many projects before you can start working on some tasks you need to complete others For examplebefore you can build the second story of a house you need to build the first floor To represent these typesof related tasks you link them in the Gantt chartLinks show which tasks depend on others to start or finish even if you schedule them for the same startingdate You can also set the lead time for linked tasks That means you need to wait a certain amount of timeafter completing one task before you can start the next one For example after applying the first coat ofpaint you might need to wait a few hours before applying the second coatWhen you link tasks the Gantt chart shows additional information about the tasks Click the followingillustration to see general tips for using linked tasks

Task Data view Chart view Description

Predecessor tasksA predecessor task is onethat you must completebefore you can start thenext task For exampleTask 2 - Prepare soil isthe predecessor to Task3 - Plant shrubs becauseyou need to prepare thesoil before you can plantthe shrubs

Successor tasksWhen you finish onelinked task you can moveonto the next onemdashthesuccessor task Forexample the successorfor Task 2 ndash Prepare soilis Task 3 ndash Plant shrubsand the successor forTask 3 is Task 4 ndash MulchLink linesThe first task isscheduled for one dayand the second one forthe next day In additionthe link line and arrowshow that the first taskmust end before thesecond one can start

These linked tasks arescheduled for the sametime

60

copy Experience In Software Inc 1995 - 2006

These tasks which aredependent on earliertasks and the last twotasks are also scheduledfor the same time

See Also

About the Gantt Chart

Autolink tasks

Make tasks overlap

-o-

-o-

61

copy Experience In Software Inc 1995 - 2006

Change the Display of the Schedule

You can change the onscreen appearance of the schedule so you can work with it more effectively Thefollowing illustration shows the Schedule window with the Steps bar closed and only the task number taskname and duration displayed in the Task Data view This provides more room to display the Gantt chart

To show or hide the Step bar or Project KickStart toolbar

Click View on the menu bar and then click Steps Bar to show or hide the vertical Steps bar on the leftof the Project KickStart window

Click View on the menu bar and then click Tool Bar to show or hide the Project KickStart toolbarwhich appears just below the menu bar In the View menu a checkmark appears next to the items displayed in the Project KickStart window

To display more or less of the Task Data view or Chart view

Drag the splitter bar between the Task Data view and the Chart view

To change the timescale in the chart

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years

To add a column to the Task Data view

Right-click a column heading to open a shortcut menu and then click the column you want to add Inthe shortcut menu a checkmark appears next to columns that are displayed in the Task Data viewBy default the Task Data view shows the Info Task Name Days Start and Finish columns Youcan also show Done Cost and Assignments columns

To hide a column in the Task Data view

Right-click a column heading and then click a column name that appears with a checkmark in theshortcut menu

62

copy Experience In Software Inc 1995 - 2006

To change the column width in the Task Data view

Drag a splitter bar in the column heading rowOr

Double-click a splitter bar to change the column width so that it accommodates the longest entry in thecolumn

See Also

Understand Task Data View

Understand Chart View

-o-

63

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

-o-

64

copy Experience In Software Inc 1995 - 2006

65

copy Experience In Software Inc 1995 - 2006

Use the Gantt Chart Toolbar

Some features in this topic are available only in Project KickStart Professional

Use the Gantt chart toolbar to work with the tasks in the Task Data view and adjust the scheduleinformation in the Chart view In Project KickStart Professional you also use the Gantt chart toolbar to linkand unlink tasks

Up and Down arrowsReorder your project tasksOutdent and Indent arrowsDemote tasks to subtasks or phases to tasksPromote subtasks to tasks or tasks to phasesAdd Task Insert a task above the current rowAdd SubtaskInsert a subtask below the current rowDeleteRemove a row of dataEdit Task InformationOpen the Task Information dialog box to changegeneral task information assignments andnotes and attachments In the Schedule stepyou can also change date information includingdurations and start and finish datesEdit Notes and AttachmentsAdd or edit a note or attachmentsColorChange the color of a taskbarChange Working ScheduleSpecify which days are nonworking days suchas weekends and holidaysLink Tasks (Pro Users)Link the selected tasksUnlink Tasks (Pro Users)Unlink the selected tasksChange TimescaleChange the timescale to display the Chart viewin days weeks months quarters or yearsChange Project StartChange the start date for the entire project thischanges dates throughout the scheduleProject FinishView the project finish date (This is calculatedby Project KickStart and cannot be edited)

See Also

Use the Gantt Chart Toolbar

-o-

66

copy Experience In Software Inc 1995 - 2006

Understand Task Data View

The following illustration shows all the columns of information you can display in Task Data view

The Task data columns are the same as in the Tasks step but also include date information

Row number

Info Shows an icon if a note attachment or both are associated with the task Double-click anicon to view or edit the associated information

Task Name Name of the phases tasks and subtasks Double-click a task name to edit it directly

Days The amount of time it takes to complete the task If you change the number of days for a taskProject KickStart changes the Finish date accordingly

Start Date this task starts Double-click a Start date and then click the list arrow to open a calendar andselect a different date This also changes the Finish date

Finish Date this task ends Double-click a Finish date and then click the list arrow to open a calendar andselect a different date This changes the task duration shown in the Days column

Done Percentage of the phase task or subtask completed Show progress for any task by entering apercent of up to 100

$ Cost Cost for each task summed in the appropriate phase row Reports include total costs for theproject when you select the Cost column in the Create and Print Task Reports dialog box or the Createand Print Gantt Chart Report dialog box The Cost appears with the currency symbol set for your system(in the Regional and Language Options dialog box of the Windows Control Panel)

Assignments People and other resources assigned to the task Double-click an assignment to open theTask Information dialog box to the Assignments tab where you can add and change assignments

Tip

A task with a duration of zero (0) days is a milestone See Create a Milestone for more information

Notes

By default Task Data view displays all the columns the Info Task Name Days Start and Finish Done Cost and Assignments columns Some of these columns might be hidden by the Gantt chartview To hide columns right-click a column heading to open a shortcut menu and then click the columnyou want to hide In the shortcut menu no checkmark appears next to columns that are hidden

To change the width of a column drag a splitter bar in the column heading row or double-click a splitterbar to have the column accommodate its longest entry

As in the Tasks step expand phases and tasks by clicking the plus icon and collapse phases andtasks by clicking the minus icon

See Also

67

copy Experience In Software Inc 1995 - 2006

Understand Chart View

Change Task Dates

-o-

68

copy Experience In Software Inc 1995 - 2006

Additional Features in Task Data View

These features are available only in Project KickStart Professional

In Project KickStart Pro you can view two columns of information in addition to the nine columns availablein the Project KickStart Standard These two additional columns are labeled Pred (for Predecessor) andSucc (for Successor) The following illustration shows a typical Task Data view with these additionalcolumns

Besides the nine columns of information shown in Task Data view in Project KickStart Standard you canalso show the following information in the Professional version

Pred Indicates which task is the predecessor to the current task Double-click a task number in the Predcolumn to change it

Succ Indicates which task is the successor to the current task Double-click a task number in the Succcolumn to change it

Notes

When you link tasks Project KickStart assigns predecessors and successors according to their order inthe Task Data view

When you move a linked task in the Task Data view the predecessor and successor do not changeFor example in the above illustration if you move Task 3 ndash Plan design so it becomes Task 2 itspredecessor remains Land survey and its successor remains Engineering You can change these bydouble-clicking the task number in the Pred or Succ column and then entering a new number

See Also

Understand Task Data View

-o-

69

copy Experience In Software Inc 1995 - 2006

Understand Chart View

The following illustration shows a daily schedule in Chart view Point to the illustration to display text thatdefines the chart elements

Summary bar Summarizes the tasks below it and extends from the earliest start date(where the first triangle in the summary bar appears) to the latest finish date (where the last triangleappears) If a phase has tasks the summary bar appears in the phase row to summarize the tasks If atask has subtasks the summary bar appears in the task row to summarize the subtasks

To reschedule a phase and all of its tasks (or a task and all of its subtasks) click the summary bar and dragit to the left or right until it spans your desired set of dates This changes the earliest start date and latestfinish date in that phase and keeps the same duration And all the tasks move with the change of thephase

Taskbar Shows the length and scheduled dates for a task To change the duration of a taskresize the taskbar click the taskbar and then drag its left edge to schedule a different start date or drag itsright edge to schedule a different finish date

To reschedule a task without changing the duration drag the taskbar to a different date in the chart

Taskbar with percent done If you enter a Done amount in the Task Data view a progress barin the taskbar indicates the amount of the task completed

Red vertical line Indicates todays date

Milestone Indicates a task with a zero duration Milestones mark an event that must be reflected inyour project plan such as the approval of a design or an assembly line startup You can drag the left edgeof a milestone icon to stretch it into a taskbar The milestone becomes a task with a start and finish date

Notes

Because a summary bar summarizes the tasks below it you cannot resize a summary bar

To scroll the schedule use the vertical and horizontal scroll bars or the green drag bar at the top of theChart view

The shaded days in the Chart view indicate nonworking days To set which days are working andnonworking see Specify Working Days

70

copy Experience In Software Inc 1995 - 2006

-o-

71

copy Experience In Software Inc 1995 - 2006

Additional Tools in Chart View

These features are available only in Project KickStart Professional

If you use Project KickStart Pro the Chart view displays lines and arrows to show linked tasks The linklines and arrows show the relationships dependencies between one linked task and another

Besides the summary bar taskbar and other information provided in Project KickStart Standard Chart viewin the Professional version also provides the following information

The first task is scheduled for one day and the second one for the next day In addition the link line andarrow show that the first task must end before the second one can start

These linked tasks are scheduled for the same time However the first task must end before the secondone can start

The first two tasks are scheduled for the same time and must be completed before the third task can start

These linked tasks are scheduled for the same time However the second task must end before the firstone can start

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

Understand Chart View

-o-

72

copy Experience In Software Inc 1995 - 2006

73

copy Experience In Software Inc 1995 - 2006

Change Task Dates

You can revise a project schedule by changing task dates in the Task Data view or the Chart view You canalso reschedule an entire project by changing the projects start date

To change the project start date1 Click the Project Start list arrow to open a calendar

The calendar highlights the selected date and outlines todays date2 Find the date you want using the left and right scroll arrows to view a different month and then click the

date

To change task dates in Task Data view1 Double-click the Start or Finish date for a task

2 Then edit the date (you can edit the day month or year) OrClick the list arrow to open a calendarThe calendar highlights the selected date and outlines todays date

3 Find the date you want using the left and right scroll arrows to view a different month and then click thedateProject KickStart changes the Start and Finish dates according to your selection updates the durationof the task in the Days column and adjusts the taskbar in the Chart view

To change task dates by changing the duration in Task Data view

Double-click the Days column for a task and then enter the number of days it will take to complete thetaskProject KickStart changes the Finish date of the task and adjusts the taskbar in the Chart view

To change task dates in Chart view

Resize a taskbar click the taskbar and then drag its left edge to schedule a different start date or dragits right edge to schedule a different finish dateProject KickStart updates the summary bar in Chart view and the task dates and duration in the TaskData view

To reschedule a task without changing the duration drag the taskbar to a different date You can alsodrag a summary bar to reschedule a phase and all of its tasks (or a task and all of its subtasks) so itspans a different set of datesProject KickStart updates the task dates and duration as necessary in the Task Data view

To change task dates in the Task Information dialog box1 Open the Task Information dialog box (Right-click a task and then click Task Information or click a

task and then click the Edit Task Information button )2 Click the General tab3 In the Dates section change the following information as necessary

Start Click the Start list arrow to open a calendar and then click the appropriate start dateFinish Click the Finish list arrow to open a calendar and then click the appropriate finish dateDays Enter a number or click the spin arrows to set the task durationMilestone Select the Milestone check box if you want this task to be a milestone (A milestone is atask with a zero duration and marks an event such as the approval of a design)

Notes

You cannot delete the Start or Finish date of a task If you want to specify that a task has no durationconvert it to a milestone

When working with a calendar to schedule a start or finish date click the Today date text (where date

74

copy Experience In Software Inc 1995 - 2006

is todays date) to select todays date

See Also

Understand Task Data View

Understand Chart View

Create a Milestone

-o-

75

copy Experience In Software Inc 1995 - 2006

Phase Dates Cannot Be Edited

You cannot change the bold phase dates in the Task Data view of the Gantt chart They are a summary ofthe task dates for a particular phase and are view only You can revise phase dates by changing task dateswithin the phase

To change phase dates in Chart view

You cannot directly resize a summary bar You can extend or move the blue task barswithin a phase on the chart and Project KickStart updates the summary bar

To reschedule a phase on the chart drag the summary bar to a new date and all of its tasks (or a taskand all of its subtasks) will move with it

-o-

76

copy Experience In Software Inc 1995 - 2006

Quick Tour of Working with Linked Tasks

This feature is available only in Project KickStart ProfessionalIn the Schedule step you work in the Gantt chart to set start and finish dates for your tasks and refine yourproject plan To make scheduling easy and quick Project KickStart provides a starter schedule for newprojects by setting today as the start date and assigning a one-day duration to each task This creates awaterfall or cascade pattern with one task following the otherIn addition Project KickStart Pro links the tasks for you so when you open the Gantt chart you see a linkedwaterfall similar to the one shown below Besides providing a schedule that starts in a cascade with eachtask lasting one day each task is linked to the next task

You work with the Gantt chart either using the Task Data view in the left pane or the graphical Chart view inthe right pane To adjust the schedule to fit your project set the project start date in the toolbar move andresize the taskbars in the Chart view or change the start and finish dates or durations of individual tasks inthe Task Data view See About Scheduling Tasks for detailsNext fine-tune the dependencies in your project by you can linking and unlinking tasks changing theirpredecessors and successors and setting lead times For example if one task is not dependent onanother you can unlink the tasks If another task canrsquot start until two other tasks are finished you can add apredecessor to that task in which case the two tasks will be linked

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

To fine-tune the linked tasks To change the scheduled start and end dates of linked tasks move and resize taskbars in the Chart

view or change the number of days or the Start date in the Task Data view To display predecessor and successor information in the Task Data view right-click any column

heading and then click Pred or Succ To change the predecessor for a task double-click the number in the Pred column for the task and

then enter the number of a different task To change the successor for a task double-click the number in the Succ column for the task and then

77

copy Experience In Software Inc 1995 - 2006

enter the number of a different task To add another predecessor or successor to a task click in the appropriate column for the task and

then enter the number of another task To change the details of a linked task open its Task Information dialog box To do so right-click the

task and then click Task Information on the shortcut menu or click a task and then click the Edit TaskInformation button See Change Details for Linked Tasks

In the Task Information dialog you can also specify the predecessor(s) of a task and lead time(s) of thetasks

Notes

Changes you make to linked tasks in the Task Data view are reflected in the link lines and otherinformation in the Chart view

As you move and resize taskbars in Chart view the link lines and arrows change accordingly

See Also

About Scheduling Tasks

About Linking Tasks (Pro Users)

Use the Gantt Chart Toolbar (Pro Users)

Manage Changes in Your Schedule (Pro Users)

-o-

-o-

78

copy Experience In Software Inc 1995 - 2006

Link and Unlink Tasks

These features are available only in Project KickStart Professional

To link tasks1 In the Task Data view select the tasks you want to link

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Link button on the Gantt chart toolbarThe tasks are linked so that the first task is the predecessor to the second task the second task is thepredecessor to the third task and so on

To unlink tasks1 In the Task Data view select tasks you want to unlink

To select two or more adjacent tasks hold down the Shift key and then click the tasks To select two ormore nonadjacent tasks hold down the Ctrl key and then click the tasks

2 Click the Unlink button on the Gantt chart toolbarThe tasks are no longer linked

See Also

About Linking Tasks

Quick Tour of Working with Linked Tasks

-o-

79

copy Experience In Software Inc 1995 - 2006

Create a Milestone

A milestone Indicates a task with a zero duration Milestones mark an event that must be reflected in yourproject plan such as the approval of a design or an assembly line startup

To create a milestone in the Task Data view

Double-click the Days number for a task and then enter 0 (zero)Or

Open the Task Information dialog box click the General tab and then click to insert a checkmark inthe Milestone check box

In the Chart view Project KickStart changes the taskbar to a milestone icon To create a milestone in Chart view

Click a taskbar and then drag to shrink the taskbar to a milestone icon In the Task Data view Project KickStart changes the Days for this task to 0 (zero)

Notes

To change a milestone into a task you change its duration or start and finish dates See Change TaskDates for instructions

To move a milestone in Chart view click the milestone icon on the upper left corner of the milestoneicon With the left mouse down move the icon to another date and release the mouse

To move a milestone in the Task Data view change the start date or the finish date and the milestonewill move

-o-

80

copy Experience In Software Inc 1995 - 2006

Change Task Details

You can use the Task Information dialog box to change the following task details in Task Data view

Task properties including the task name cost for completing the task and the percent completed

Dates including the start and finish dates duration and whether to convert the task to a milestone

Assignments

Notes and attachmentsYou can also edit the task name days dates costs and Done directly by clicking items in the task datacolumns

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button 2 Click the appropriate tab and then change the task details

General tab Change the task name and enter or change the cost associated with the task To changethe amount of the task completed click the Done list arrow and then select a value or type a value inthe Done text box Enter or change date information as described in Change Task Dates Assignments tab People assigned to this task are highlighted in the list To assign this task to anotherperson or resource click the name in the Assignments list To remove (unassign) this task from aperson or resource click a highlighted name in the Assignments list See Add or Change TaskAssignments for more detailsNotes and Attachments tab Type or edit a task note (Press Enter for a line break) To add anattachment click the Add button In the Select File to Attach dialog box navigate to the file you wantand then click the Open button The filename appears with a paper clip icon See Add Task Notes andAttachments for more details

To change task details directly in Task Data view

To modify the task name press F2 or double-click a task and then edit or replace the text

To change date information see Change Task Dates

To change the amount of the task completed double-click in the Done column and then enter a newvalue

To change the cost associated with the task double-click in the Cost column and then enter a newvalue

Notes

When you enter costs for tasks the total appears in the phase row for those tasks Reports include thetotal costs of all tasks in the project when you select the Cost column in the Create and Print TaskReports dialog box or the Create and Print Gantt Chart Report dialog box

You cannot change the cost of a phase because it represents the total costs for the tasks in that phaseInstead change the costs associated with the tasks in the phase

When you enter a Done for a task the corresponding taskbar in the Chart view includes a blackprogress bar

-o-

81

copy Experience In Software Inc 1995 - 2006

Change Details for Linked Tasks

This feature is available only in Project KickStart ProfessionalIf you are using Project KickStart Pro you can use the Task Information dialog box to change the followingtask details

Predecessor for a linked task

Lead time for a linked task

To change task details using the Task Information dialog box1 Right-click a task and then click Task Information on the shortcut menu or click a task and then click

the Edit Task Information button

2 Click the Predecessors tab and then change the task details about predecessors and lead timePredecessors tab The Task Properties section shows the name of the selected task which you canchange The Predecessor (Finish-to-Start) section shows the tasks that are predecessors to theselected task A predecessor task must be finished before you start the current task You can change the ID name or lead time of the predecessor task Also you can also add additionalother predecessorsThe lead time is the amount of time you need to wait after finishing the predecessor task before so youcan start the current task Lead time can be positive or negative

Note

In some programs the is time shift is called ldquolag timerdquo But we think that the term ldquolead timerdquo is moreaccurate and descriptive since itrsquos the amount of time you want to allow before you start a task

See Also

Change Task Details

82

copy Experience In Software Inc 1995 - 2006

-o-

-o-

83

copy Experience In Software Inc 1995 - 2006

Reorganize Tasks in Task Data View

Although your project should be fairly well organized by the time you start the Schedule step you canfine-tune the organization in the Task Data view using the same techniques you use in the Tasks stepTo reorder tasks

Right-click a task and then click Move Task Up or Move Task Down on the shortcut menu Or

Click a task or phase to select it and then click the Up Arrow button or the Down Arrow button on theGantt chart toolbar

To promote and demote tasks

Right-click a task and then click Outdent or Indent on the shortcut menu Or

Click a phase task or subtask to select it and then click the Outdent button or the Indent button onthe Gantt chart toolbar

To add a task1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Task button on the Gantt chart toolbar or press the Insert key Project KickStart inserts a new blank row above the task you selected

2 Enter the text of the new taskTo add a subtask1 Right-click a task and then click Add Task on the shortcut menu click a task and then click the Add

Subtask button on the Gantt chart toolbar or press the Insert keyProject KickStart inserts a new blank row below the task you selected and indents the new row toindicate its a subtask

2 Enter the text of the new subtaskTo delete a task

Right-click a task and then click Delete Row on the shortcut menuOr

Click the task you want to delete and then click the Delete button

To delete a row click the Task row number and press the Delete button

See Also

Move Tasks within the Task List

Outdent and Indent Tasks

Add a Task or Subtask

Edit Tasks

-o-

84

copy Experience In Software Inc 1995 - 2006

Change the Timescale of the Schedule

You can display the Gantt chart schedule in the Chart view using days weeks months quarters or yearsas the timescale Changing from days to weeks for example displays a longer period of time but lessdetail

Days timescale Weeks timescale

To change the timescale in the Chart view

Click the Change timescale list arrow and then click Days Weeks Months Quarters or Years Youcan also change the timescale by clicking Timescale on the menu bar and then clicking the option youwant

Notes

When you print a Gantt chart your current timescale is used by default However you can change it inthe Print Options dialog For example even though you were viewing your Gantt chart by weeks youcan choose to print the Gantt chart by months

If your mouse comes with a wheel you can adjust Project KickStarts timescale by rolling the wheelforward or backward The Timescale list box must be selected first

-o-

85

copy Experience In Software Inc 1995 - 2006

Specify Working Days

You can select which days are working days and which days are nonworking days for scheduling purposesBy default Monday - Friday are working days and Saturday and Sunday are nonworking days You can addto and change these settings to specify holidays for example

To set working and nonworking days

1 Click the Change Working Schedule button on the Gantt chart toolbar The Change Working Schedule for this Project dialog box opens Nonworking days are shaded in grayWorking days are unshaded

2 To change a single date (from working to nonworking or from nonworking to working) click the date3 To change one day of the week for the entire project such as all Fridays double-click any Friday4 To display schedules for other months click the left and right arrows5 Click OK

Note

Project KickStart maintains separate calendars for each project

If you typically work weekends create a simple template with weekends displayed as Working daysSave as your starter template Use the starter template when you start a new project and then save theproject with a different name Weekends will be displayed as Working days in your projects

-o-

86

copy Experience In Software Inc 1995 - 2006

Change the Color of Taskbars

You can change the color of the taskbars in the Chart view to call attention to particular tasks For exampleyou can change the colors of all tasks in a particular phase resource or deadline to make them stand outin a report

To change the color of a taskbar1 Right-click a taskbar and then click Color on the shortcut menu or click a taskbar and then click the

Color button on the Gantt chart toolbar The Color dialog box opens

2 Click the color you want to assign to the taskbarTips

Avoid changing the taskbar color to black because it obscures the Done progress bar (The Doneprogress bar is a black bar displayed within a taskbar)

Also avoid changing the taskbar color to white because it will not appear in the white rows of the Chartview

-o-

87

copy Experience In Software Inc 1995 - 2006

Make Tasks Overlap

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro the schedule starts in a cascade with each task lasting one day and each tasklinked to the following taskHowever it is very unlikely that your entire schedule matches such a cascade so you can adjust theschedule Start by estimating the duration of tasksmdashthe number of days that each task will take Generallyit is best to estimate how many days will elapse before the task is done You might also want some tasks to occur at the same time To do so you can overlap the tasks To make tasks overlap like this

You can do this in three ways Set the same predecessor for both tasks

Or Set the second task as the successor of the first task and then then move the second task into a

position when it starts on the same day as the first taskOr

Set the second task as the successor of the first task and then assign a lead time of ndash3 days (the number of days scheduled for the task)

To make tasks overlap like this

Set the second task as the predecessor of the first task and then assign a lead time of ndash2 days(one less than the number of days scheduled for the task)

-o-

88

copy Experience In Software Inc 1995 - 2006

Manage Changes in Your Schedule

This feature is available only in Project KickStart ProfessionalIn Project KickStart Pro when you schedule with dependencies you can adapt to changes on the fly andcreate what-if scenarios to forecast how one change affects the overall project schedule A commonscenario is dealing with delays You can reschedule an entire project or only selected tasks When you doProject KickStart Pro updates the schedule for you

To delay an entire project Click in the Project Start text box and then edit the date to match your new start date (You can edit

the day month or year)Or

1 Click the Project Start list arrow to display the calendar The calendar highlights the selected date andoutlines todays date

2 Find the date you want using the left and right scroll arrows to view a different month and then click thedate Project KickStart changes the Start and Finish dates for all tasks according to your selection

To delay a task In Task Data view double-click the Days column for the task and then edit the number of days it will

take to complete the taskProject KickStart changes the Finish date of the task adjusts the taskbar in the Chart view andchanges the Start and Finish dates for all tasks linked to this taskOr

In Chart view resize a taskbar by clicking the taskbar and then dragging its left edge to schedule adifferent start date or dragging its right edge to schedule a different finish date Project KickStart updates the summary bar in Chart view the task dates and duration in the Task Dataview and reschedules all tasks linked to this task

To reschedule a task without changing the duration in Chart view drag the taskbar to a different date Project KickStart updates the task dates and duration as necessary in the Task Data view andreschedules all tasks linked to this task

Note

Project KickStart Pro does not include a critical path

-o-

89

copy Experience In Software Inc 1995 - 2006

Managing Libraries

Use a Library

Project KickStart has five libraries that contain lists of useful phases tasks goals people and obstaclesAll libraries expect the People Library contain sample entries that you can use in your projects Yougenerally build your own People Library from the resources that are available to you

To use a library1 In the Phases Tasks Goals People or Obstacles step of the Planning Wizard click the Library button

to open the appropriate library2 Select one or more items in a library and then drag them to your list3 Close the Library window

Tips

Feel free to add (or delete) items to the libraries to make them richer and more pertinent to yourprojects

Keeping libraries small makes them easier to use

Widen the library window to see the full text of long entries

Note

After adding a library entry to a list you can double-click the entry to edit it

See Also

Manage a Library

-o-

90

copy Experience In Software Inc 1995 - 2006

Manage a Library

Customize the libraries by adding and changing entries and reorganizing them so you can use the librariesefficiently The Phases Tasks Goals People and Obstacles Libraries include a single column ofinformation while the People Library provides additional columns (See Manage the People Library)

To edit a library1 Open the library by clicking the appropriate Library button2 To edit an entry double-click it

3 To add an entry to the library press Insert or click the Add a row button You can also select oneor more items in the list and then drag them to the library

4 To delete an entry select the entry and then press Delete or click the Delete a row button 5 To move an item up or down select the item and then click the Up Arrow or the Down Arrow button

6 Click the OK button to save your changes and close the Library windowTips

Widen the Library window to add a long entry

Libraries can serve as ldquoKnowledge Librariesrdquo By including typical company-specific terms in yourLibraries you create a quick reference for yourself and colleagues now and in the future To do so adda new line in the Library enter the name of your company (or department) as a heading in capitalletters and then list your personal terms under the heading

If you use Project KickStart on more than one computer such as at home and work you can transportchanges you make in your Libraries from one computer to another The data in all the Libraries isstored in one file pks5libxdat so you can copy that file on one computer and paste it into the ProjectKickStart 5 folder on the other computer

Keeping Libraries small makes them easier to use Project KickStarts Libraries are fairly rich out of thebox If some of the terms don rsquot apply to your type projects delete them

See Also

Manage the People Library

-o-

91

copy Experience In Software Inc 1995 - 2006

Manage the People Library

The People Library is like the other libraries but with a few important extra features

You can store contact data such as Company Email Phone and Job Title

You can import names from ACT or from Outlook if you use either of those programsTo use the People Library1 In the People step of the Planning Wizard click the People Library button2 Select one or more names in the People Library and then drag them to your list (This adds only the

names of people not their contact data) If the People Library contains company names but not contactnames you can drag the company name to your list

3 Close the Library windowTo organize the People Library

To show or hide a column right-click a column heading to open a shortcut menu and then click acolumn name In the shortcut menu a checkmark appears next to columns that are displayed in thePeople Library

To sort the people in the People Library click a column heading For example click the Name columnheading to sort the people alphabetically by name To reverse the sort click the column heading again

To move a person up or down select the person and then click the Up Arrow or the Down Arrowbutton

Click the OK button to save your changes and close the People LibraryTo edit the People Library

To edit a persons name and contact data double-click the entry

To add a person to the People Library click the first blank row press Insert or click the Add a rowbutton Then type to enter the persons name and contact information You can also select one ormore items in the list and then drag them to the People Library

To delete an entry select the entry and then press Delete or click the Delete a row button

Click the OK button to save your changes and close the People LibraryTips

Use the People Library to store names for people teams (such as Quality control team) departments(such as Manufacturing) companies (such as Acme Widgets Corp) or even equipment (such as wheatthrasher)

Widen the People Library window to add a long entry

Resize the columns by dragging or double-clicking a splitter barNotes

After adding a person or resource to your list you can double-click the name to edit it

You can import contact information stored in an Outlook or ACT (version 6 7 or later) address book toyour People Library

See Also

Import ACT Contacts and Users to the People Library

Import Outlook Contacts to the People Library

-o-

92

copy Experience In Software Inc 1995 - 2006

Import ACT Contacts and Users to the People Library

If you use ACT 7 or later (200520062007) or if you use ACT 6 you can import contacts and users to thePeople Library This speeds up your work by letting you use ACT information in your Project KickStartplans If you export a plan to ACT 7 or later it recognizes the people and other resources you entered inProject KickStart

To import ACT contacts and users1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click ACT 7 or later or ACT 6 Click the Import button3 Click the Select ACT Database button and select the ACT 7 or later database (pad) containing the

people information you want to import The ACT 7 and later databases are usually stored in MyDocumentsACTACT for Win 7Databases (If you use ACT 6 your data is stored in a dbf database) If you select a multi-user ACT database you must enter your user name and password for the ACTdatabase

4 In the Import to People Library dialog box the names of Contacts and Users are listed on the left Clickthe Users tab select one or more users and then click Add to move the user names to the Import listClick the Contacts tab to select contact names the same way Click the Add All button to select allusers or contacts for import Note You can sort the contacts alphabetically by name or by company name by clicking theappropriate column heading

5 Click the Import button to add the names and related information from the selected ACT database tothe People Library

Notes

Importing contacts and users to the People Library does not remove them from the ACT database

If you try to import the same ACT contact or user twice it appears only once in the People Library

-o-

93

copy Experience In Software Inc 1995 - 2006

94

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts to the People Library

If you use Microsoft Outlook to maintain your contacts you can import selected contacts to the PeopleLibrary ThisThis speeds up your work by letting you use Outlook information in your Project KickStartplans If you export a plan to Outlook it recognizes the people and other resources you entered in ProjectKickStart

To import Outlook contacts1 In People - Step 1 of 3 click the People Library button to open the People Library2 Click the Import list arrow and then click Outlook Click the Import buttonA dialog box opens informing you that Project KickStart is trying to access your Outlook data

3 Allow access for 1 minute and then click the Yes button4 If Outlook asks you to choose your profile please do so5 The Import to People Library dialog box opens listing Outlook Contacts on the left Select one or more

contacts and then click Add to move the contact names to the Import list Click the Add All button toselect all contacts for import

6 Click the Import button to add the contact names to the People Library

Notes

Importing contacts and users to the People Library does not remove them from Outlook If you try to import the same Outlook contact twice it appears only once in the People Library

95

copy Experience In Software Inc 1995 - 2006

You can import Contacts from the Outlook Business Contact Manager

See Also

Import Outlook Contacts via CSV to the People Library (Pro Users)

-o-

96

copy Experience In Software Inc 1995 - 2006

Import Outlook Contacts via CSV to the People Library (ProUsers)

This feature is available only in Project KickStart Professional

If you use Microsoft Outlook to maintain your contacts and many of the people on your project are not inyour personal contacts folder in Outlook you can use our new utility to import these Outlook contacts viaCSV to the People Library

To export Outlook contacts to a CSV file1 In Outlook - Click File Import and Export Export to A File and click Next2 Select Comma Separated Values (Windows) and click Next3 Select the Contacts folder to export and click Next4 Save Exported File As with the default being your My Documents folder5 Click Next

To import Outlook contacts to the People Library

1 Be sure that you exit Project KickStart before running the Import Utility

2 Run ImportCSVToPKSexe which is located in the Project KickStart application folder

3 Browse or type the Contacts CSV file (the path is My DocumentsProject KickStart Projects folder bydefault)

4 Browse or type the pks5libxdat file (default is the Project KickStart application folder)

5 Click on Import

Note

Importing contacts and users to the People Library does not remove them from Outlook

-o-

97

copy Experience In Software Inc 1995 - 2006

Printing Reports

98

copy Experience In Software Inc 1995 - 2006

Printing Dashboards

Print Reports

You can print reports from anywhere in Project KickStart through a new Reports Step

You will see Reports divided into three areas

Dashboard

Task Reports

Gantt Chart Reports

-o-

99

copy Experience In Software Inc 1995 - 2006

Print Dashboard Reports

You can print dashboard reports from anywhere in Project KickStart though it makes the most sense toprint them after you have developed your tasks and arranged them in a sensible order

To print a dashboard report

1 Click File on the menu bar and then click Print Reports and then click Dashboard Reports or clickthe Print Reports button

2 In the left column select one of these dashboard reports Whats Due Today Whats Due NextWeek Whats Due Next Month

3 Change the page setup as necessary or Save As a file (See Page Setup and Save As)

4 Click the Print button

Tip

You can see the number of tasks in each dashboard report from the dashboard menu

-o-

100

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Dashboard Reports

Printer Setup

-o-

101

copy Experience In Software Inc 1995 - 2006

Save as HTML or RTF

You can dashboard reports to a Hypertext Markup Language (HTML) format for viewing with an Internetbrowser such as Microsoft Internet Explorer or Mozilla FireFox or to an RTF format for viewing in MicrosoftWord

To save a dashboard report as an HTML file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save button

To save a report as an RTF file1 Click the Save As button The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

102

copy Experience In Software Inc 1995 - 2006

Printing Task Reports

Print Task Reports

You can print task reports from anywhere in Project KickStart though it makes the most sense to print themafter you have developed your tasks and arranged them in a sensible orderBefore you print task reports you might want to widen the Task Name column in the Task List to make sureyou print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a task report

1 Click File on the menu bar and then click Print Task Reports In the Tasks step you can click thePrint Reports button instead

The Create and Print Task Reports dialog box opens

2 Click the list arrow and then click Task Report Individual Assignments or Phases Goals People ampObstacles

3 Select the information you want to include in the report as described below

4 Preview the report and change the page setup as necessary (See Print Preview and Page Setup)

5 Click the Print button

Task Report

The Task report covers the entire project and includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

103

copy Experience In Software Inc 1995 - 2006

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to display in the report

By default the report prints all tasks Click the Incomplete Tasks or Completed Tasks option button tofocus on one type of task

4 Click the Preview button (See Print Preview for details)

Individual Assignments

The Individual Assignments report covers the entire project and lists the tasks assigned to each resourceThe report includes the Task Name and other details you select

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Select the date range for the report

By default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose which tasks to include in the report

Click the All Tasks Incomplete Tasks or Completed Tasks option button

4 Choose which people to include The report lists tasks assigned to the people you select

Click to insert or remove a checkmark from the box for each person

5 Click the Preview button (See Print Preview for details)

Phases Goals People amp Obstacles

This report includes the phases goals people and obstacles in your project You can include some or all ofthese items in the report

104

copy Experience In Software Inc 1995 - 2006

1 Select the data columns you want to display in the report

Click to insert or remove a checkmark from the box for each detail

2 Click the Preview button (See Print Preview for details)

Tip

If you have many long notes for the tasks of your project it may be hard to read them if you select everycolumn in the Task Reports You should consider selecting a report with only columns for Tasks andNotes

See Also

Print Gantt Chart Reports

-o-

105

copy Experience In Software Inc 1995 - 2006

Print Preview

Before printing a report preview its pages so you know how the report will look when printed

To preview a task report1 Click the Preview button on the Create and Print Task Reports dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from 79 to 100 or from 100 to 79Zoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25

viewPrint the report

You can also click the Page Setup button to change margins and other settings or click the Closebutton to close the Print Preview window

2 If the report appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintTask Reports dialog box

Note

Print Preview is for viewing only--you cannot edit the contents of a report

See Also

Print Task Reports

Printer Setup

Page Setup

-o-

106

copy Experience In Software Inc 1995 - 2006

Printer Setup

Before you print a report you can change the following printer settings

Printer name (and other properties) Paper size Number of copies

To change the printer setup1 Click the Printer button on the Project KickStart toolbar or the Print Preview toolbar2 In the Print dialog box change the printer settings

See Also

Print Task Reports

Print Preview

Page Setup

-o-

107

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a report you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print Task Reports

Print Preview

Printer Setup

-o-

108

copy Experience In Software Inc 1995 - 2006

Email Task Reports

After creating and previewing a task report you can distribute it to others via email

To email a task report1 In the Create and Print Task Reports dialog box select a report and then click the Email Report

button Project KickStart creates the report opens a new message in your email software and attaches thereport as an HTML file to the message

2 Insert one or more email addresses include the message text and then send the message the way youusually do

Tip

To send a task report to each person in your project with the appropriate assignments select theIndividual assignments report select one person to receive the report and then click the Email Reportbutton Enter the email address of the recipient and send the message Do this for each person in yourproject

-o-

109

copy Experience In Software Inc 1995 - 2006

Save as HTML

You can export tasks assignments days and notes to a Hypertext Markup Language (HTML) format forviewing with an Internet browser such as Microsoft Internet Explorer or Mozilla FireFox

To save a report as an HTML file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the HTML file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Web page (htm html) if necessary5 Click the Save buttonTips

You can transfer the HTML document to the Web (or your intranet) using FTP protocol

In the HTML document indents show the hierarchy of tasks

See Also

Save as RTF

-o-

110

copy Experience In Software Inc 1995 - 2006

Save as RTF

You can export tasks assignments durations and notes to a Rich Text Format (RTF) for editing inMicrosoft Word

To save a report as an RTF file1 In the Create and Print Task Reports dialog box select a report and then click the Save As button

The Save Report dialog box opens2 The default location to save Report files is in the My DocumentsProject KickStart ProjectsReports

folder Click the Save in list arrow if you want to change the folder where you will store the RTF file3 In the File name text box change the name of the file if necessary4 Click the Save as type list arrow and then click Rich Text Form (rtf)5 Click the Save buttonTips

You can open an RTF file in a word processor such as Microsoft Word

To send an RTF document to each person in your project with the appropriate assignments select theIndividual Assignments report select one person to receive the report and then save the report asRTF Do this for each person in your project

See Also

Save as HTML

-o-

111

copy Experience In Software Inc 1995 - 2006

Printing Gantt Chart Reports

Print a Gantt Chart

Once you create your schedule you can print a Gantt chart from anywhere in Project KickStart

Before you print a Gantt chart you might want to widen the Task Name column in the Task pane to makesure you print the complete task information (Drag the splitter bar next to the Task Name column heading)

To print a Gantt chart1 Click File on the menu bar and then click Reports and then select Gantt Chart Reports In the

Schedule step you can click the Print Reports button insteadThe Create and Print Gantt Chart Report dialog box opens

2 Click the Format list arrow and then click Wall chart Fit to smallest size or Repeat tasks on everypage (for handouts)

3 Select the information you want to include in the report as described below4 Preview the report and change the page setup as necessary (See Print Preview a Gantt Chart and

Page Setup)5 Click the Print button

Wall Chart The wall chart prints the Gantt chart information spread across many pages which you can tape together tocreate a wall chart On the left side of the report the wall chart includes the task data columns you selectThe right side of the report includes the graphical view shown in the Gantt chart pane on the right

1 Select the task data columns you want to display for the task information on the left side of the wallchartClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the wall chart

112

copy Experience In Software Inc 1995 - 2006

By default the wall chart prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the wall chartBy default the wall chart prints the timescale you were using in the Gantt chart Click the SetTimescale list arrow to change the timescale to Weeks Months Quarters or Years

4 Select the orientation for the wall chartClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Fit to Smallest Size When you select the Fit to smallest size format Project KickStart reduces the size of the entire Gantt chartincluding the information in the Task pane on the left and the graphical view shown in the Gantt chart paneon the right so it fits as well as possible in the smallest number of pages

1 Select the data columns you want to display for the task information on the left side of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 The timescale for the Gantt chart view on the right side of the report is determined by the length of yourproject and may not be changed

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 The number of pages of the report is shown here (The Fit to smallest scale report will print up to 78rows of tasks per page)

6 Click the Preview button (See Print Preview a Gantt Chart for details)

Standard (for Handouts) This report lists the data columns you specify on the left side of the first page and can repeat the tasknumber task name or assignments on every interior page of the report which is especially useful for

113

copy Experience In Software Inc 1995 - 2006

handouts

1 Select the data columns you want to print on the left side of the first page and the data columns youwant to print on every page of the reportClick to insert or remove a checkmark from the box for each detail

2 Select the date range for the reportBy default the report prints the entire range of tasks Click the Start or Finish list arrow to display acalendar you can use to select a different start or finish date

3 Choose the timescale for the Gantt chart view on the right side of the reportBy default the report prints a daily view of the tasks Click the Set Timescale list arrow to change thetimescale to Weeks Months Quarters or Years

4 Select the orientation for the reportClick the Portrait option button to print the wall chart on a vertical format Click the Landscape buttonto print the wall chart on a horizontal format

5 Click the Preview button (See Print Preview a Gantt Chart for details)

Tips

Print Preview shows how many pages the Gantt chart will take to print If there are too many pagesconsider changing the timescale or the date range You can also choose to show fewer columns of taskdata

If possible use paper that is larger than 85 x 11 inches You can select the paper size in Print Previewusing the Page Setup dialog box

If you change the timescale from Days to Weeks or Months this can make tasks with short durations (1to 5 days) difficult to see

If you have trouble printing the Gantt chart report try changing the dpi from 600 to 300 (draft mode) Ifyou continue to have problems contact your printer manufacturer and see if it supports PCL (PrinterCommand Language) technology which is included in most printers today

If you have trouble printing the Gantt chart report on a PDF printer you can try to scale the printing tographics setting to 50

114

copy Experience In Software Inc 1995 - 2006

See Also

Save Gantt Chart Images

Print Task Reports

Printer Setup

Page Setup

-o-

115

copy Experience In Software Inc 1995 - 2006

Print Preview a Gantt Chart

Before printing a Gantt chart preview its pages so you know how the report will look when printed

To preview a Gantt chart1 Click the Preview button on the Create and Print Gantt Chart Report dialog box

The Print Preview window opens to display your report Point to the following illustration to see tips forusing this window

15 Indicates the current page number and the number of pages in the report

Return to the first page in the reportPreview the previous page in the reportPreview the next page in the reportGo to the last page in the reportZoom from the current zoom percentage to 100 or from 100 to the current zoom percentageZoom to the whole page page width two pages thumbnail or 150 100 75 50 or 25 viewChange printer settings and then print the reportYou can also click the Page Setup button to set margins select paper size and enter headers andfooters or click the Close button to close the Print Preview window

2 If the Gantt chart appears the way you want click the Print button to print the report To change thecontents of the report click the Close button and then change the settings on the Create and PrintGantt Chart Report dialog box

Notes

Print Preview is for viewing only--you cannot edit the contents of a report

If you want to print a wider task column return to the Gantt chart widen the Tasks Name column andthen print

To change print settings such as the printer selection and number of copies click the Print button to open the Print dialog box You can save the Gantt chart in a PDF file by clicking the Print button andthen clicking the PDF printer selection (such as Adobe PDF or PDF-XChange ) You can then distributethe Gantt chart electronically as a PDF file

See Also

Print a Gantt Chart

Page Setup

-o-

116

copy Experience In Software Inc 1995 - 2006

Page Setup

Before you print a Gantt chart you can change the following page settingsPaper sizePrinterOrientation (portrait or landscape)MarginsHeader text and fontFooter text and font

To change the page setup1 Click the Print Preview button and then click the Page Setup button2 In the Page Setup dialog box change the page settingsTips

By default Project KickStart includes the name of the project such as Creating a Presentation in theheader You can change this header by editing the text between angle brackets lt gt

Project KickStart includes the current date on the left and the page number on the right of the footerYou can specify the custom text you want to print in the footer in the center of the page by editing thetext between angle brackets lt gt

See Also

Print a Gantt Chart

Print Preview a Gantt Chart

-o-

117

copy Experience In Software Inc 1995 - 2006

Printing to an Adobe PDF file

To print a Gantt chart to an Adobe PDF file you may have to make some adjustments to your settings

To preview a Gantt chart1 Select Adobe PDF as the name of the printer2 Click Properties button3 Click the PaperQuality tab4 Click Advanced button5 In the Graphic Section lower the setting on Print Quality6 Also in the Graphic Section change the Scaling from 100 to 50

-o-

118

copy Experience In Software Inc 1995 - 2006

Save Gantt Chart Images

You can save a Gantt chart as a series of graphic files in the Meta File (emf) format which you can theninsert in a file such as a Microsoft Word document or PowerPoint presentation The number of graphic filescreated depends on the report type and options you choose in the Create and Print Gantt Chart Reportdialog box By default Project KickStart saves the files in a folder named for your project

To save Gantt chart images1 In the Create and Print Gantt Chart Report dialog box click the Save Image button

The Save Image dialog box opens2 Change the location where you want to save the image files or change the part of the file name that

includes the project name and report type if necessary3 Click the Save buttonNotes

Project KickStart saves the image files in the PKSGanttImagesproject name folder stored in the MyDocumentsProject KickStart Projects folder (where project name is the name of your project)

Each graphic file name includes the name of the project report type date you created the report andnumber in the series of images as in CreateaWinningPresentation_Wall chart_09112008_1emf toCreateaWinningPresentation_Wall chart_09112008_20emf

To email the Gantt chart images attach the images in the PKSGanttImagesproject name folder storedin the My DocumentsProject KickStart Projects folder (where project name is the name of your project)If the image files are large zip or compress the files first

If you have installed PDF as a printer selection you can print the Gantt chart to a PDF file and thenattach the PDF file to an e-mail message PDF files are often easier to read than image files See thenotes in Print Preview a Gantt Chart for instructions on printing to a PDF file

-o-

119

copy Experience In Software Inc 1995 - 2006

Export Project Data

120

copy Experience In Software Inc 1995 - 2006

Export to ACT

Export to ACT 7 or Later

If you use ACT 7 or later (20052006200720082009) you can export your plan from Project KickStart toan ACT database with just one click After you export your plan you see your tasks in the ACT Groupview grouped under the name of your project

To export to ACT 7 or later

1 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 7 and later andthen click the Go button You can also click File on the menu bar point to Export to and then clickACT 7 and later

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (pad file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opens

Each time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks

4 Click Start (This works best if ACT is already open )

5 If you are exporting to a multi-user ACT database enter your ACT User Name and Password

To view each project separately in ACT Group Details

1 In ACT click the Group List icon

2 Double-click the Project Name in the Group Name column The Group Detail appears for the projectyou selected

3 Click the Contacts tab to see Contacts and click the Activities tab to see tasks for that project

4 You should press Ctrl-F5 to refresh the view Also you might have to adjust the Filter in ACT so thatDates to show is set to All Dates

Task names are listed in the Regarding column Assignments are listed in the Scheduled With columnPhases are shown in red and tasks and subtasks are shown in blue

To view tasks from multiple projects sorted by date in Task List or Calendar

In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn Project names are in the Associate With column You might have to adjust the Filter in ACT sothat Dates to show is set to All Dates

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar Tasks are set as timeless (Duration of 0 minutes) so the transferred tasks dont fill up thecalendar

121

copy Experience In Software Inc 1995 - 2006

Tips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

The ACT 7 and later export is smart enough to update your existing tasks from the same project If youexport the same Project KickStart project two or more times ACT recognizes the project and asks ifyou want to update the project information in ACT You do not lose your task history or notes in ACT

Tasks that are unassigned in Project KickStart are listed as Scheduled With Unassigned PKS

You can filter by Selected Users in the Task List and in Groups

See Also

Import ACT Contacts and Users to the People Library

-o-

122

copy Experience In Software Inc 1995 - 2006

Export to ACT 6

If you use ACT 6 ACT 2000 or ACT 5 you can transfer a Project KickStart plan into an ACT databasewith just one click After you export your plan you see your tasks in the ACT Group view grouped underthe name of your project

To export to ACT 61 In the Schedule step click the Export to list arrow below the Gantt chart click ACT 6 and then click

the Go button You can also click File on the menu bar point to Export to and then click ACT 6

2 The first time you export to ACT the Open ACT Database dialog box opens Select the ACTdatabase (dbf file) to which you want to transfer your Project KickStart tasks and then click the Openbutton The Export to ACT dialog box opensEach time you export the Export to ACT dialog box opens so you can select which tasks you want toexport

3 Click an option button to export All Tasks Uncompleted Tasks or Completed Tasks4 Click Start (This works best if ACT is already open )5 If you are exporting to a multi-user ACT database enter your ACT user name and passwordTo view each project separately in ACT1 In ACT click the Groups icon 2 Click the Project Name listed under All Groups on the left3 On the lower-right part of the window click the Activities tab to see tasks for that project

Task names are listed in the Regarding column Assignments are listed in the Scheduled With column 4 You might have to adjust the Filter in ACT so that Dates to show is set to All Dates Also you might

have to press Ctrl-F5 to refresh the view5 To view task details click the button next to the task column on the leftTo view tasks from multiple projects sorted by date1 In ACT click the Task List icon

The Task names are listed in the Regarding Column Assignments are listed in the Scheduled Withcolumn You might have to adjust the Filter in ACT so that Dates to show is set to All Dates

2 If the Group column is not showing add it by clicking ViewAdd Columns and then double-clickingGroupThe tasks are identified by group (project name)

3 To view task details click the button next to the task column on the leftTips

Import ACT Contacts and Users to the Project KickStart People Library first Linking to ACT worksbest if the people in Project KickStart are the same as your Contacts and Users in ACT When youexport tasks to ACT it recognizes your people as Contacts or Users

You can also view tasks from multiple projects in your Monthly Calendar Weekly Calendar or DailyCalendar as well as in the Task List

You can filter by Selected Users in the Task List and in Groups

After exporting your tasks to ACT you can import them to your Palm Pilot using the ACT Link

See Also

Import ACT Contacts and Users to the People Library

-o-

123

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Outlook

If you use Microsoft Outlook you can export your plan from Project KickStart to Outlook in a click of abutton After you export your plan you see your tasks in the Outlook Tasks view grouped under a categorynamed for your project In Outlook you can track your tasks and email tasks to team members

To export to Microsoft Outlook1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Outlook and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Outlook The Export to Outlook dialog box opens

2 Click an option button to export All tasks Uncompleted tasks or Completed tasks3 If you want to display the tasks you export on your Outlook Calendar click the check box4 Click the Start button A dialog box opens informing you that Project KickStart is trying to access your

Outlook data

5 Allow access for 1 minute and then click the Yes buttonTo view your tasks in Microsoft Outlook1 Click the Outlook Tasks button2 Depending on the version of Outlook you are using set to view the tasks by category In Outlook 2003

click the By Category option button in the Current View list You can also click View on the menu barpoint to Arrange By and then click CategoriesYour project is listed by its project name in the Categories list

3 Click an expand icon to see the complete list of tasks and subtasks

124

copy Experience In Software Inc 1995 - 2006

4 To view task details double-click the task nameTips

The export to Outlook works best if Outlook is already open

In Outlook you can set priorities set reminders and schedule by the hour

If you export to your Outlook Calendar a reminder appears on the due date of each task

After you export tasks to Outlook you can synchronize with your Palm Pilot Windows CE device orother handheld computer

Note

You can export only to Microsoft Office Outlook not Outlook Express

See Also

Import Outlook Contacts to the People Library

-o-

125

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Word

If you use Microsoft Word you can export your plan from Project KickStart to Word in a click of a buttonYour project appears in a Word table in a doc file You can cut and paste change column widths deletecolumns and print from Word

To export to Microsoft Word

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Word andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Word

Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in a Word document in a doc format

2 When youre finished use Save As to save the Word file with a new name such as ltnamegtdoc Forconvenience you can save the file using the same name as your Project KickStart project name

Benefits of using Project KickStart and Word

Communicate projects flexibly After exporting to Word you can communicate your project details ina variety of text formats You can also enhance your document by adding color logos clip art orhyperlinks

Distribute plans to others You can send doc files to other Microsoft Word users via email andrequest comments using Words Send To and Comments features

Tip

Include your strategic plan in documents letters and web pages in a doc or html file

Note

The image of the Gantt chart does not import into Word automatically You can manually import theGantt chart image into a Word document In Word select Insert on the menu bar point to Pictureclick From File and then browse to the folder containing the Gantt chart images you saved By defaultthis is cMy DocumentsProject KickStart ProjectsPKSGanttImages in a folder named for your project

See Also

Export to Word Processors (Other than Word)

Save Gantt Chart Images

126

copy Experience In Software Inc 1995 - 2006

-o-

127

copy Experience In Software Inc 1995 - 2006

Export to Word Processors (Other than Word)

If you are using a word processor other than Microsoft Word you can export your Project KickStart taskreport by first saving it as an HTML or RTF file

To export to word processors other than Microsoft Word

1 Save a Project KickStart task report using HTML or RTF format using the Save As button in the Createand Print Task Reports dialog box

2 Open the file with your word processor

3 Save the file using the Save As command using a different name

See Also

Print Task Reports

Save as HTML

Save as RTF

-o-

128

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Excel

If you use Microsoft Excel you can export your plan from Project KickStart to Excel in a click of a buttonYour project appears in an Excel worksheet in a xls file You can add task details perform calculationsand share your project data with other Excel users

To export to Microsoft Excel1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Excel and

then click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Excel Your tasks days start and finish dates done costs assignments and notes (excludingattachments) appear in an Excel worksheet in an xls format

2 When youre done select FileSave As to save the Excel file under a new name For convenience youmight want to save it under the same name as your Project KickStart project name

To manually import Gantt chart images into Microsoft Excel1 In Excel click Sheet2 and select ToolsOptions on the menu bar and unclick the box for Gridlines2 Then select Insert on the menu bar point to Picture click From File and then browse to the folder

containing the Gantt chart images you saved By default this is cMy DocumentsProject KickStartProjectsPKSGanttImages in a folder named for your project

3 Select one Gantt chart image at a time to bring it in 4 You can manipulate the size of the image in Excel

Benefits of using Project KickStart and ExcelProject KickStart is very good at scoping out a schedule but there are a few reasons why you might want touse both programs

Data sharing A Project KickStart user might want to share the information with other Excel users whodont have Project KickStart They could change enhance or redistribute their portions of the schedule

129

copy Experience In Software Inc 1995 - 2006

Add more task details Excel users can add new columns of task data that cant be added in ProjectKickStart

Sort task lists For example you could show your projects tasks sorted by each resources namethen see each resources tasks sorted by the tasks start date

Filter tasks Excel can show tasks that meet certain criteria For instance show tasks with the wordtesting in the task name

See Also

Save Gantt Chart Images

-o-

130

copy Experience In Software Inc 1995 - 2006

Export to Microsoft PowerPoint

If you use Microsoft PowerPoint you can export your plan from Project KickStart to PowerPoint in a click ofa button Your project appears as a formatted PowerPoint presentation in a ppt file

To export to Microsoft PowerPoint

1 In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft PowerPointand then click the Go button You can also click File on the menu bar point to Export to and thenclick Microsoft PointPoint

The Export to PowerPoint dialog box opens where you can choose a PowerPoint design template ifyou like

2 Click the Start button

Your tasks days start and finish dates and costs appear in a PowerPoint presentation with an imageof the Gantt chart in one or more slides at the end of your slide show

Once you have created a PowerPoint presentation you can enhance your slides in several ways

Delete slides that are not appropriate for your presentation

131

copy Experience In Software Inc 1995 - 2006

Rearrange the order of the slides

Add colors for emphasis

Add graphics such as company logo clip art and colors

Shorten any long task titles

Benefits of using Project KickStart and PowerPoint

Save time You can dramatically save time in creating a PowerPoint presentation on your project

Present projects to others Present project details in webinars presentations and corporatemeetings Create template presentations or how tos for implementing an installation productintroduction or corporate policy for example

Communicate plans Email project plans in ppt format to colleagues and presentors

Tips

If you use a PowerPoint design template choose one that has a white or light background for maximumlegibility of the Gantt chart in the presentation

The Gantt chart image in the PowerPoint presentation is generated ldquoon the flyrdquo Change the Timescalesettings of the Gantt chart considering how it will be reflected in the number of images of the Ganttchart For example the Day view results in more Gantt chart images than the Months view

-o-

132

copy Experience In Software Inc 1995 - 2006

Export to Microsoft Project

If you use Microsoft Project 98 2000 2002 or 2003 you can export your plan from Project KickStart toProject in a click of a button

To export to Microsoft Project

In the Schedule step click the Export to list arrow below the Gantt chart click Microsoft Project andthen click the Go button You can also click File on the menu bar point to Export to and then clickMicrosoft Project Your tasks assignments days start and finish dates costs done and notes (excluding attachments) appearin a Microsoft Project file

Benefits of using Project KickStart and Microsoft Project

Share data with others Send a project to a colleague or client that expects to see your schedule in anMicrosoft Project format

Schedule tasks with more flexibility Schedule tasks in different durations particularly in less than aday

Track resources Track resource usage and resource leveling and to have greater flexibility in sortingfiltering and reporting project information

Notes

Project KickStart tasks transfer to Microsoft Project as tasks with a Constraint type of Start No EarlierThan This keeps the dates the same as in the Project KickStart schedule

The settings in Project KickStart Working Days Calendar also transfer to Microsoft Project

Exporting to Microsoft Project allows you to take advantage of the advanced tracking and schedulingfeatures that large projects often require

You can also save your Project KickStart projects as an mpx file which you can open in MicrosoftProject and send to other Microsoft Project users Click File on the Project KickStart menu bar clickSave As and then choose mpx as the file type After you save the file click File on the MicrosoftProject menu bar click Open and open your mpx file

-o-

133

copy Experience In Software Inc 1995 - 2006

Export to SureTrak Project Manager

If you use SureTrak Project Manager you can export your plan from Project KickStart to SureTrak ProjectManager

To export to SureTrak Project Manager

1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file

2 In SureTrak click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

SureTrak

You will see your tasks and assignments (but not the notes) appear in a SureTrak file The file is shownin outline view

Benefits of using Project KickStart and SureTrak

Add new information to tasks such as how they are linked

Track progress particularly for comparing plans verses actual results

Have greater flexibility in sorting filtering and reporting project information

Notes

Task notes are not included in the transfer

A version of Project KickStart called the Project KickStart Wizard is included in SureTrak 2 andSureTrak 3 You can use it within SureTrak

See Also

Export MPX Files

-o-

134

copy Experience In Software Inc 1995 - 2006

Export to FastTrack Schedule

If you use FastTrack Schedule you can save your Project KickStart project as an mpx file and import it intoFastTrack ScheduleTo export to FastTrack Schedule1 Click File on the Project KickStart menu bar click Save As and save your project as an mpx file2 In FastTrack Schedule click File on the menu bar click Import and then select mpx as the file type3 Browse to and then click your Project KickStart mpx file Your Project KickStart data will appear in

FastTrack ScheduleBenefits of using Project KickStart and FastTrack Schedule

Add more task details FastTrack Schedule provides the features and tools needed in many largeprojects

Multiproject reporting Consolidate multiple projects into a master project file

See Also

Export MPX Files

-o-

135

copy Experience In Software Inc 1995 - 2006

Export to Milestones Professional

If you use Milestone Professional you can export your plan from Project KickStart to MilestonesProfessional in a click of a button

To export to Milestone Professional

In the Schedule step click the Export to list arrow below the Gantt chart click MilestonesProfessional and then click the Go button You can also click File on the menu bar point to Export to and then click Milestones Professional

Your tasks assignments start and finish dates and notes (excluding attachments) appear in aMilestones file

Tips

After you export your tasks to Milestones Professional you can create taskbars add titles and performother tasks to produce a presentation-quality schedule You can also use Milestones to track your tasksby showing task durations and percent completions Make scheduling changes by dragging the taskdates

If you have an earlier version of Milestones (eg version 45 or 5) you can save Project KickStart dataas an mpx file and then open the mpx file in Milestones

-o-

136

copy Experience In Software Inc 1995 - 2006

Export to Mindjet MindManager

If you use Mindjet MindManager 7 or later you can export your project plan from Project KickStart in a clickof a button Or you can develop a rough plan in MindManager and export your mind map to ProjectKickStart for enhanced planning It works both ways

To export from Project KickStart to MindManager

In the Schedule step click the Export to list arrow below the Gantt chart click MindManager and thenclick the Go button You can also click File on the menu bar point to Export to and then clickMindManager

Your tasks assignments start and finish dates durations costs Done and notes (excludingattachments) appear in a MindManager file

To export from MindManager to Project KickStart

In MindManager click File on the menu bar point to Send To and then click Project KickStart Thenclick the OK button to start the export

You can also click the Project KickStart icon at the bottom of the MindManager window

Benefits of using Project KickStart and MindManager together

Visualize your plan in two ways Brainstorm plan and communicate your project details in both agraphical and linear style

Develop a graphical plan and then fine-tune the details MindManager uses mindmappingtechniques to develop a high-level plan in a graphical format Export to Project KickStart to enhanceyour plan details by focusing on your projects goals obstacles and resource needs You can alsocreate a Gantt chart schedule

Communicate concepts Project KickStart users can display their plans in a highly graphicalmindmapping format in MindManager The maps make it easier to communicate complex processesand visually identify important tasks issues and relationships

Tip

If you dont already use MindManager you can purchase it in our Thinking Tools Store

-o-

137

copy Experience In Software Inc 1995 - 2006

Export to WBS Chart Pro

If you use WBS Chart Pro you can export your plan from Project KickStart to WBS Chart Pro in a click of abutton

To export to WBS Chart Pro

In the Schedule step click the Export to list arrow below the Gantt chart click WBS Chart Pro andthen click the Go button You can also click File on the menu bar point to Export to and then clickWBS Chart ProYour project is displayed under the project name Each phase in the project is shown in a box with ashadow Each lower level task in a phase is displayed under their respective phase box groupedtogether with the other tasks in that phase

Benefits of using Project KickStart and WBS Chart

Visualize tasks Work with tasks in a tree-style chart called a Work Breakdown Structure (WBS)chart

Communicate your project plan with others WBS Chart uses the outline you create in ProjectKickStart to create a top-down picture of your plan This picture is similar to an Organization chart Butinstead of displaying the structure of your company a WBS chart displays the structure of your projectplan

Notes

WBS Chart refers to the phases in the project as Summary Tasks and the detail for each phase asTasks

The export only works if WBS Chart is not currently running You must close WBS Chart before you cancreate another chart

See Also

Export MPX Files

-o-

138

copy Experience In Software Inc 1995 - 2006

Export MPX Files

The MPX file format is an ASCII format created by Microsoft Project or another program and is used tosend data to and from project management software programs

The following programs can create and open MPX files

FastTrack Schedule

Microsoft Project (95 or 98)

Project KickStart 5

Project KickStart 32

RiskyProject

SureTrak Project Manager

WBS Chart

In these programs you save a project as an MPX file using the Save As command on the File menu Youcan then open an MPX file by using the Open command on the File menu and then specifying the file typeas mpx

For example if you want to move a project from Project KickStart 5 to Project KickStart 32 you can savethe project as an mpx file and then open it in Project KickStart 32

In Microsoft Visio you can create a Visio project time line from Project KickStart To do so you first mustsave your file in Project KickStart as an MPX file Then

1 Start Visio

2 Click File on the menu bar point to New click Business Diagram and then click Project TimelinesWizard

3 Click Next

4 On the second window click Import MPX File to import the Project KickStart mpx file

5 Enter the file location and name or click Browse to locate the file

6 Follow the instructions in the Visio Project Timelines Wizard windows

Tip

If you have difficulty importing the mpx file remove any commas from task names

-o-

139

copy Experience In Software Inc 1995 - 2006

Reference

140

copy Experience In Software Inc 1995 - 2006

Menus

File Menu

Command Keyboard Shortcut Description

New Project Ctrl+N Creates and names a new project fileOpen Project Ctrl+O Opens a previously saved Project KickStart 4 or 5 file

(prx) Project KickStart 3 file (prj) or mpx fileClose Ctrl+W Closes an open Project KickStart fileSave Ctrl+S Saves a project file (prx) in which you made changes Save As Saves a project file with a different file name or different

file format such as MPXPrint Task Reports

Ctrl+T Generates and prints a report letting you preview thecontents

Print Gantt ChartReports

Ctrl+G In the Gantt chart (Schedule step) generates andprints the Gantt chart in the current timescale

Export To Sends the project to another program such asMicrosoft Outlook or ACT 7

Recent file list Lists the last three files opened in Project KickStartExit

Alt+F4 Exits the program

-o-

141

copy Experience In Software Inc 1995 - 2006

Edit Menu

Command Keyboard Shortcut Description

UndoRedo Ctrl+Z Undoes or repeats the last operationCut

Ctrl+X Deletes the currently selected information placing it on theclipboard so you can paste it elsewhere

Copy

Ctrl+C Places a copy of selected information on the Clipboard so youcan paste it elsewhere

Paste

Ctrl+V Places information from the Clipboard to the currently selectedlocation

Select all Ctrl+A Selects all the content in the windowAdd a line Adds a new row where you can enter text

-o-

142

copy Experience In Software Inc 1995 - 2006

View Menu

Command Description

Tool Bar Shows or hides the toolbar (a checkmark indicates thetoolbar is displayed)

Steps Bar Shows or hides the Steps bar (a checkmark indicates the Steps bar is displayed)

Name Go to the Name your project stepPhases Go to Phases stepGoals Go to Goals stepSimilar Projects Go to Similar projects stepPeople Go to People stepObstacles Go to Obstacles stepAssign Go to Assign tasks to people stepTasks Go to Tasks stepSchedule Go to Schedule step

-o-

143

copy Experience In Software Inc 1995 - 2006

Tools Menu

Command Keyboard Shortcut Description

Spelling

F7 Checks spelling of project dataexcept for names of people

Collaboration To access or find out aboutGoToMeeting

Options Select options for running thesoftware

-o-

144

copy Experience In Software Inc 1995 - 2006

Options

-o-

145

copy Experience In Software Inc 1995 - 2006

Data Menu

The Data menu is available in the Tasks and Schedule steps for manipulating tasks and creating ascheduleCommand Description

Move Up Moves the selected task item upMove Down Moves the selected task item downOutdent Moves the selected task item to the leftIndent Moves the selected task item to the rightInsert Task Insert task in row aboveInsert SubTask Insert subtask below current rowDelete Task Delete current taskEdit Task Properties Brings you to an edit screen where you can edit task

name change assignments and edit task notesEdit Notes Brings you to an edit screen for editing task notesColor Taskbars Change the color of selected tasks (in Schedule)Change Working Days Select which days are working and which are

nonworking (in Schedule)Link Tasks Link tasks in Gantt chart (Pro Users)Unlink Tasks Unlink tasks in Gantt chart (Pro Users)

-o-

146

copy Experience In Software Inc 1995 - 2006

Timescale Menu

The Timescale menu is available in the Schedule step so you can change the display of the Gantt chartschedule

Command Description

Days Displays a daily schedule in theGantt chart

Weeks Displays a weekly schedule inthe Gantt chart

Months Displays a monthly schedule inthe Gantt chart

Quarters Displays a quarterly schedule inthe Gantt chart

Years Displays a yearly schedule inthe Gantt chart

-o-

147

copy Experience In Software Inc 1995 - 2006

Help Menu

Command Description

Project KickStart Help Help for Project KickStart including a Table ofContents and index of terms

Online Tutorials View several Getting Started Tutorials to getyou started with Project KickStart whether youare a new or experienced user

Keyboard Shortcuts Shortcuts for programTechnical Support How to obtain Technical Support for Project

KickStart via web form and email[Send Log to Technical Support] If the program detects an error it writes a log

of technical issues Click Send Log toTechnical Support to send the error log to us

ProjectKickStartcom Visit the Project KickStart Web siteGet Latest Version See what the latest published version is and

download it if you need itAbout Project KickStart Shows Project KickStart version number build

date copyright and system information

-o-

148

copy Experience In Software Inc 1995 - 2006

Shortcuts

Use the following keyboard shortcuts to move quickly around in Project KickStart

Navigation

Move forward to the next window Alt+NMove back to the previous window Alt+BSteps

Go to Name step Alt+MGo to Phases step Alt+SGo to Goals step Alt+GGo to Similar step Alt+RGo to People step Alt+PGo to Obstacles step Alt+OGo to Assign step Alt+IGo to Tasks step Alt+KGo to Library (Phases Tasks GoalsPeople Obstacles)

Alt+L

Menus

File menu Alt+FEdit menu Alt+EView menu Alt+VShow menu (Tasks step) Alt+WOutline menu (Tasks step) Alt+UTimescale (Schedule step) Alt+CHelp menu Alt+H F1Other

Edit tasks assignments amp notes (Tasks step)F3Save Ctrl+SPrint Task Report Ctrl+PPrint Gantt Chart (Schedule step) Ctrl+GCut Ctrl+XCopy Ctrl+CPaste Ctrl+VInsert Row InsertDelete Row DeleteInsert Line Break (in Notes in Task List andSchdule steps)

Enter

Spell Check

Ignore Alt+IIgnore All Alt+GChange Alt+CChange All Alt+HHelp

149

copy Experience In Software Inc 1995 - 2006

Contents in Help Alt+CIndex Alt+IBack in Help Alt+BClose Help Alt+LHelp about the current step Alt+H

-o-

150

copy Experience In Software Inc 1995 - 2006

Share Project KickStart Data

Project KickStart makes it easy to share data with other people involved with a project You can share yourProject KickStart data in the following ways

Send a printed report Make a PowerPoint presentation Send a file (prx html rtf mpx) Post an HTML file to a Web site and access it with your web browser Export to other programs such as Microsoft Word or Excel and send data in a format the recipient can

access (such as doc xls or mpx)

Note

You can also collaborate with a colleague by conducting an online meeting using GoToMeeting (Prousers)

-o-

151

copy Experience In Software Inc 1995 - 2006

Open a Project

After you create a project and save it in a prx prj or mpx file using Project KickStart or other softwareyou can open the project in Project KickStartTo open a project in Project KickStart 5

1 Click the Open Project button on the toolbar or click File on the menu bar and then click OpenProject

2 In the Open Project File dialog box click the Files of type list arrow and then click a file type (prxprj or mpx)

3 Navigate to the folder that contains the file4 Double-click the name of the file

Opening a Project KickStart 3 prj file converts it to a prx file

Generally prj files are stored in cprogram filesProject KickStart 3

The tasks in the converted Project KickStart 5 file will have the same start and finish dates anddurations as they had in Project KickStart 3

Summary tasks such as Phases in Project KickStart 5 derive their start finish and duration from thetasks within them and so may be different from in Project KickStart 3

Because Project KickStart 3 has weekends as working days they show up in Project KickStart 5 thesame way To have weekends as non working days open the working days calendar and markweekends as non working

Opening a mpx file converts it to a prx file

The tasks in each project have the same start and finish dates and durations

-o-

152

copy Experience In Software Inc 1995 - 2006

Dedication

I dedicate this software program to my new colleague

Kevin Ahlvin

Roy A Nierenberg President

-o-

153

copy Experience In Software Inc 1995 - 2006

Credits and Trademarks

Credits

Missak Koumoudjian Program Architect and Chief Programmer

Kevin Ahlvin Interface DesignAnn Kawamoto Quality AssuranceAlexander Setzepfandt Quality AssuranceJackie LeungJeffrey Chow

Programming Interns

Kevin Ahlvin Product Supervisor and CoordinatorJoseph Fusco Project Management Consultant and content

providerLisa RuffoloJoseph Fusco

Help System

Roy A Nierenberg President

Trademark

Project KickStart and Project KickStart Wizard are trademarks of Experience In Software Inc in the UnitedStates andor in other countries All rights reserved All other trademarks mentioned herein are the propertyof their respective owners

-o-

154

copy Experience In Software Inc 1995 - 2006

Uninstalling

You can uninstall Project KickStart 5 through the Control Panel AddRemove Programs Select ProjectKickStart 5 This starts the InstallShield Maintenance Program You should then remove all of theprogram files that were installed It will not erase your Project KickStart prx data files

If that does not work you can delete the Project KickStart files manually

Note

If you purchased Project KickStart and you want to return it for a refund follow the instructions forDe-activating the software at httpwwwprojectkickstartcomcontactreturnscfm

-o-

155

copy Experience In Software Inc 1995 - 2006

Using Past Projects

You can use past projects in two ways

If you have projects that are similar you can use a past project as a template for a new project In theWelcome window select Open a Project Open that project and Save As under a different name Nowyou can open up the renamed project and modify it for the current project

You can draw from several projects in the Similar Projects step First select projects that are similarand click Next Then select tasks from those projects and decide where they would fit into your currentproject

See Also

Opening a project Compatibility with earlier versions

-o-

156

copy Experience In Software Inc 1995 - 2006

Index

- - Change Working Schedule 85

- -prj file format 13

- A -About Linking Tasks (Pro Users) 59About Scheduling Tasks 55About the Gantt Chart 57ACT 120 92 122ACT 6 92 122ACT 7 or later 92 120Activate 14Activating Trial Version 14Add a New Person or Resource 39add a subtask 83add a task 83Add a Task or Subtask 47Add or Change Task Assignments 51Add or Change Task Details 52Add Subtask 63Add Task 63Add URL 49Additional Features in Task Data View (Pro Users) 68Additional Tools in Chart View (Pro Users) 71Adobe PDF 117Assignments tab 80Attachments 49Autolink tasks (Pro Users) 58

- B -Back 10borrow tasks 29

- C -Change Details for Linked Tasks (Pro Users) 81Change Project Start 63Change Task Dates 73Change Task Details 80Change the Appearance of the Task List 43Change the Display of the Schedule 61Change Timescale 63Change Working Schedule 63Chart view 57

157

copy Experience In Software Inc 1995 - 2006

Cloning projects 155Color 63 86Compatibility 13Compatibility with earlier versions 13convert projects 13Coordination 12Create and Print Task Reports 102Credits 153Credits and Trademarks 153critical path 88CSV 96Customer support 20Customer Support 20Customizing Project KickStart

- D -Dashboard 99Data Menu 145Dedication 152Delete 63delete a task 83demote 46dependencies 12 76

- E -Edit Menu 141Edit Notes and Attachments 63Edit or Substitute People 40Edit Task Information 63Email Task Reports 108End User License Agreement 16error 21Error Messages 21export from MindManager 136Export MPX Files 138Export to ACT 6 122Export to ACT 7 and Later 120Export to FastTrack Schedule 134Export to Microsoft Excel 128Export to Microsoft Outlook 123Export to Microsoft PowerPoint 130Export to Microsoft Project 132Export to Microsoft Word 125Export to Milestones Professional 135Export to Mindjet MindManager 136Export to SureTrak Project Manager 133Export to WBS Chart Pro 137

- F -FastTrack Schedule 134File Menu 140Fit to page 111Fit to Smallest Size 111

158

copy Experience In Software Inc 1995 - 2006

- G -Gantt chart 55 57General tab 80Goal 26Goal statements 26Goals 26Goals - Step 1 of 3 26Goals - Step 2 of 3 27Goals - Step 3 of 3 28goals library 26 89Goalsadd 26Goalsdelete 26Goalsedit 26Goalstasks for 27GoToMeeting 150 12

- H -Handouts 111Help Menu 147hyperlink 49

- I -Import ACT 92import contacts and users 92import Outlook contacts 94Import Outlook Contacts via CSV to the People Library (Pro Users) 96ImportCSVToPKSexe 96Indent 46Individual Assignments 102Introduction 7Introduction 7

- K -Knowledge Libraries 90

- L -lag time 81lead time 59 81library 89License Key 14link 59Link lines 59Link tasks 12 65linked tasks 59

- M -major activities 24Make Tasks Overlap (Pro Users) 87Manage a Library 90

159

copy Experience In Software Inc 1995 - 2006

Menu 140Microsoft Excel 128Microsoft Outlook 123Microsoft PowerPoint 130Microsoft Project 132Microsoft Project (95 or 98) 138Microsoft Visio 138Microsoft Word 125Milestone 69 79Milestones Professional 135Mindjet MindManager 136MindManager 136

- N -Name 23Name Your Project 23Navigating Project KickStart 10Next 10Notes and Attachments tab 80

- O -Objectives 26Obstacles 34Obstacles - Step 3 of 3 36Obstacles Library 89Open a Project 151Options 144Outdent 46Outdent and Indent arrows 63Outlook Calendar 123Overview

- P -Page Setup 107 116 100PDF 117people 31People - Step 3 of 3 28People Library 91phase 24phase dates 75Phase Dates Cannot Be Edited 75phases 24Phases - Step 1 of 2 24Phases - Step 2 of 2 25Phases Library 89Phases Goals People amp Obstacles 102PowerPoint presentation 130Pred 68Predecessor 68Predecessor tasks 59predecessors 76Print a Gantt Chart 111Print Dashboard Reports 99Print Preview 105Print Preview a Gantt Chart 115Print Reports 98Print Task Reports 102

160

copy Experience In Software Inc 1995 - 2006

Printer Setup 106Printing to an Adobe PDF file 117prj 13Pro 145Pro Edition 145Product support 20Project 23Project KickStart 3 prj file 151Project KickStart for Windows 7project name 23project start date 73project template 155project title 23promote 46promote and demote tasks 83

- Q -Quick Tour of Working with Linked Tasks (Pro Users) 76

- R -Red vertical line 69Redo 11Register Project KickStart 22Registering Project KickStart 22remove people 38Remove People from a Task 38reorder tasks 83Reorganize Tasks in Task Data View 83Repeat tasks on every page (for handouts) 111Reporting Technical Issues 21resource 31resources 31restore 34return 154risks 34RiskyProject 138

- S -Save As 101Save as HTML 109Save as RTF 110Save Gantt Chart Images 118Schedule 55Send Error Report 21similar projects 29spelling 53starter schedule 55Steps 7subtask 47Subtasks 46Succ 68Successor 68Successor tasks 59successors 76Summary bar 69Support 20SureTrak Project Manager 133

161

copy Experience In Software Inc 1995 - 2006

- T -Task Data view 57task dates 73Task Report 102Taskbar 69Taskbar with percent done 69Tasks 25Tasks in Phases 25Tasks Library 89team 31Technical support 20timescale 84Timescale Menu 146Tools Menu 143Trademark 153trademarks 153Trial 14

- U -unassigning 38Understand Chart View 69Understand Task Data View 66Undo 11UndoRedo Buttons 11uninstallUninstalling 154Unlink tasks 12 65Up and Down arrows 63Use Project KickStart to 8Use the Gantt Chart Toolbar 63Use the Planning Wizard 9Uses 8Using Past Projects 29 155

- V -Version View Menu 142Visio 138

- W -Wall chart 111WBS Chart Pro 137Welcome to Project KickStart 7Whats Due Next Month 99Whats Due Next Week 99Whats Due Today 99Whats New in Project KickStart Pro 5 11Windows Vista 20

162

copy Experience In Software Inc 1995 - 2006

copy Experience In Software 2008w w w projectkickstartcom

  • Table of Contents
  • Start Here Welcome to Project KickStart
    • Introduction
      • Welcome to Project KickStart
      • Use Project KickStart to
      • Use the Planning Wizard
      • Navigating Project KickStart
      • Whats New in Project KickStart Pro 5
      • Whats New in Project KickStart Pro 5 (Pro Users)
      • Compatibility with earlier versions
      • Activating Trial Version
        • Licenses and Support
          • End User License Agreement
          • Customer Support
          • Reporting Technical Issues
          • Register Project KickStart
              • Planning Projects
                • Name Your Project
                • Phases - Step 1 of 2
                • Phases - Step 2 of 2
                • Goals - Step 1 of 3
                • Goals - Step 2 of 2
                • Goals - Step 3 of 3
                • Similar Projects - Step 1 of 2
                • Similar Projects - Step 2 of 2
                • People - Step 1 of 3
                • People - Step 2 of 3
                • People - Step 3 of 3
                • Obstacles - Step 1 of 3
                • Obstacles - Step 2 of 3
                • Obstacles - Step 3 of 3
                  • Assigning People
                    • Assign Tasks to People
                    • Remove People from a Task
                    • Add a New Person or Resource
                    • Edit or Substitute People
                      • Organizing the Project Plan
                        • About Organizing Tasks
                        • Change the Appearance of the Task List
                        • Show or Hide Tasks in the Task List
                        • Move Tasks within the Task List
                        • Outdent and Indent Tasks
                        • Add a Task or Subtask
                        • Edit Tasks
                        • Add Task Notes and Attachments
                        • Add or Change Task Assignments
                        • Add or Change Task Details
                        • Check Spelling
                          • Scheduling Tasks in the Gantt Chart
                            • Scheduling Overview
                              • About Scheduling Tasks
                              • About the Gantt Chart
                              • Autolink tasks (Pro Users)
                              • About Linking Tasks (Pro Users)
                              • Change the Display of the Schedule
                              • Use the Gantt Chart Toolbar
                              • Use the Gantt Chart Toolbar (Pro Users)
                              • Understand Task Data View
                              • Additional Features in Task Data View (Pro Users)
                              • Understand Chart View
                              • Additional Tools in Chart View (Pro Users)
                                • Change Task Dates
                                • Phase Dates Cannot Be Edited
                                • Quick Tour of Working with Linked Tasks (Pro Users)
                                • Link and Unlink Tasks (Pro Users)
                                • Create a Milestone
                                • Change Task Details
                                • Change Details for Linked Tasks (Pro Users)
                                • Reorganize Tasks in Task Data View
                                • Change the Timescale of the Schedule
                                • Specify Working Days
                                • Change the Color of Taskbars
                                • Make Tasks Overlap (Pro Users)
                                • Manage Changes in Your Schedule (Pro Users)
                                  • Managing Libraries
                                    • Use a Library
                                    • Manage a Library
                                    • Manage the People Library
                                    • Import ACT Contacts and Users to the People Library
                                    • Import Outlook Contacts to the People Library
                                    • Import Outlook Contacts via CSV to the People Library (Pro Users)
                                      • Printing Reports
                                        • Printing Dashboards
                                          • Print Reports
                                          • Print Dashboard Reports
                                          • Page Setup
                                          • Save As
                                            • Printing Task Reports
                                              • Print Task Reports
                                              • Print Preview
                                              • Printer Setup
                                              • Page Setup
                                              • Email Task Reports
                                              • Save As HTML
                                              • Save As RTF
                                                • Printing Gantt Chart Reports
                                                  • Print a Gantt Chart
                                                  • Print Preview a Gantt Chart
                                                  • Page Setup
                                                  • Printing to an Adobe PDF file
                                                  • Save Gantt Chart Images
                                                      • Export Project Data
                                                        • Export to ACT
                                                          • Export to ACT 7 and Later
                                                          • Export to ACT 6
                                                            • Export to Microsoft Outlook
                                                            • Export to Microsoft Word
                                                            • Export to Word Processors (Other than Word)
                                                            • Export to Microsoft Excel
                                                            • Export to Microsoft PowerPoint
                                                            • Export to Microsoft Project
                                                            • Export to SureTrak Project Manager
                                                            • Export to FastTrack Schedule
                                                            • Export to Milestones Professional
                                                            • Export to Mindjet MindManager
                                                            • Export to WBS Chart Pro
                                                            • Export MPX Files
                                                              • Reference
                                                                • Menus
                                                                  • File Menu
                                                                  • Edit Menu
                                                                  • View Menu
                                                                  • Tools Menu
                                                                  • Options
                                                                  • Data Menu
                                                                  • Timescale Menu
                                                                  • Help Menu
                                                                    • Shortcuts
                                                                    • Share Project KickStart data
                                                                    • Open a Project
                                                                    • Dedication
                                                                    • Credits and Trademarks
                                                                    • Uninstalling the software
                                                                    • Using Past Projects
Page 12: Project KickStart Help File in PDF format
Page 13: Project KickStart Help File in PDF format
Page 14: Project KickStart Help File in PDF format
Page 15: Project KickStart Help File in PDF format
Page 16: Project KickStart Help File in PDF format
Page 17: Project KickStart Help File in PDF format
Page 18: Project KickStart Help File in PDF format
Page 19: Project KickStart Help File in PDF format
Page 20: Project KickStart Help File in PDF format
Page 21: Project KickStart Help File in PDF format
Page 22: Project KickStart Help File in PDF format
Page 23: Project KickStart Help File in PDF format
Page 24: Project KickStart Help File in PDF format
Page 25: Project KickStart Help File in PDF format
Page 26: Project KickStart Help File in PDF format
Page 27: Project KickStart Help File in PDF format
Page 28: Project KickStart Help File in PDF format
Page 29: Project KickStart Help File in PDF format
Page 30: Project KickStart Help File in PDF format
Page 31: Project KickStart Help File in PDF format
Page 32: Project KickStart Help File in PDF format
Page 33: Project KickStart Help File in PDF format
Page 34: Project KickStart Help File in PDF format
Page 35: Project KickStart Help File in PDF format
Page 36: Project KickStart Help File in PDF format
Page 37: Project KickStart Help File in PDF format
Page 38: Project KickStart Help File in PDF format
Page 39: Project KickStart Help File in PDF format
Page 40: Project KickStart Help File in PDF format
Page 41: Project KickStart Help File in PDF format
Page 42: Project KickStart Help File in PDF format
Page 43: Project KickStart Help File in PDF format
Page 44: Project KickStart Help File in PDF format
Page 45: Project KickStart Help File in PDF format
Page 46: Project KickStart Help File in PDF format
Page 47: Project KickStart Help File in PDF format
Page 48: Project KickStart Help File in PDF format
Page 49: Project KickStart Help File in PDF format
Page 50: Project KickStart Help File in PDF format
Page 51: Project KickStart Help File in PDF format
Page 52: Project KickStart Help File in PDF format
Page 53: Project KickStart Help File in PDF format
Page 54: Project KickStart Help File in PDF format
Page 55: Project KickStart Help File in PDF format
Page 56: Project KickStart Help File in PDF format
Page 57: Project KickStart Help File in PDF format
Page 58: Project KickStart Help File in PDF format
Page 59: Project KickStart Help File in PDF format
Page 60: Project KickStart Help File in PDF format
Page 61: Project KickStart Help File in PDF format
Page 62: Project KickStart Help File in PDF format
Page 63: Project KickStart Help File in PDF format
Page 64: Project KickStart Help File in PDF format
Page 65: Project KickStart Help File in PDF format
Page 66: Project KickStart Help File in PDF format
Page 67: Project KickStart Help File in PDF format
Page 68: Project KickStart Help File in PDF format
Page 69: Project KickStart Help File in PDF format
Page 70: Project KickStart Help File in PDF format
Page 71: Project KickStart Help File in PDF format
Page 72: Project KickStart Help File in PDF format
Page 73: Project KickStart Help File in PDF format
Page 74: Project KickStart Help File in PDF format
Page 75: Project KickStart Help File in PDF format
Page 76: Project KickStart Help File in PDF format
Page 77: Project KickStart Help File in PDF format
Page 78: Project KickStart Help File in PDF format
Page 79: Project KickStart Help File in PDF format
Page 80: Project KickStart Help File in PDF format
Page 81: Project KickStart Help File in PDF format
Page 82: Project KickStart Help File in PDF format
Page 83: Project KickStart Help File in PDF format
Page 84: Project KickStart Help File in PDF format
Page 85: Project KickStart Help File in PDF format
Page 86: Project KickStart Help File in PDF format
Page 87: Project KickStart Help File in PDF format
Page 88: Project KickStart Help File in PDF format
Page 89: Project KickStart Help File in PDF format
Page 90: Project KickStart Help File in PDF format
Page 91: Project KickStart Help File in PDF format
Page 92: Project KickStart Help File in PDF format
Page 93: Project KickStart Help File in PDF format
Page 94: Project KickStart Help File in PDF format
Page 95: Project KickStart Help File in PDF format
Page 96: Project KickStart Help File in PDF format
Page 97: Project KickStart Help File in PDF format
Page 98: Project KickStart Help File in PDF format
Page 99: Project KickStart Help File in PDF format
Page 100: Project KickStart Help File in PDF format
Page 101: Project KickStart Help File in PDF format
Page 102: Project KickStart Help File in PDF format
Page 103: Project KickStart Help File in PDF format
Page 104: Project KickStart Help File in PDF format
Page 105: Project KickStart Help File in PDF format
Page 106: Project KickStart Help File in PDF format
Page 107: Project KickStart Help File in PDF format
Page 108: Project KickStart Help File in PDF format
Page 109: Project KickStart Help File in PDF format
Page 110: Project KickStart Help File in PDF format
Page 111: Project KickStart Help File in PDF format
Page 112: Project KickStart Help File in PDF format
Page 113: Project KickStart Help File in PDF format
Page 114: Project KickStart Help File in PDF format
Page 115: Project KickStart Help File in PDF format
Page 116: Project KickStart Help File in PDF format
Page 117: Project KickStart Help File in PDF format
Page 118: Project KickStart Help File in PDF format
Page 119: Project KickStart Help File in PDF format
Page 120: Project KickStart Help File in PDF format
Page 121: Project KickStart Help File in PDF format
Page 122: Project KickStart Help File in PDF format
Page 123: Project KickStart Help File in PDF format
Page 124: Project KickStart Help File in PDF format
Page 125: Project KickStart Help File in PDF format
Page 126: Project KickStart Help File in PDF format
Page 127: Project KickStart Help File in PDF format
Page 128: Project KickStart Help File in PDF format
Page 129: Project KickStart Help File in PDF format
Page 130: Project KickStart Help File in PDF format
Page 131: Project KickStart Help File in PDF format
Page 132: Project KickStart Help File in PDF format
Page 133: Project KickStart Help File in PDF format
Page 134: Project KickStart Help File in PDF format
Page 135: Project KickStart Help File in PDF format
Page 136: Project KickStart Help File in PDF format
Page 137: Project KickStart Help File in PDF format
Page 138: Project KickStart Help File in PDF format
Page 139: Project KickStart Help File in PDF format
Page 140: Project KickStart Help File in PDF format
Page 141: Project KickStart Help File in PDF format
Page 142: Project KickStart Help File in PDF format
Page 143: Project KickStart Help File in PDF format
Page 144: Project KickStart Help File in PDF format
Page 145: Project KickStart Help File in PDF format
Page 146: Project KickStart Help File in PDF format
Page 147: Project KickStart Help File in PDF format
Page 148: Project KickStart Help File in PDF format
Page 149: Project KickStart Help File in PDF format
Page 150: Project KickStart Help File in PDF format
Page 151: Project KickStart Help File in PDF format
Page 152: Project KickStart Help File in PDF format
Page 153: Project KickStart Help File in PDF format
Page 154: Project KickStart Help File in PDF format
Page 155: Project KickStart Help File in PDF format
Page 156: Project KickStart Help File in PDF format
Page 157: Project KickStart Help File in PDF format
Page 158: Project KickStart Help File in PDF format
Page 159: Project KickStart Help File in PDF format
Page 160: Project KickStart Help File in PDF format
Page 161: Project KickStart Help File in PDF format
Page 162: Project KickStart Help File in PDF format