PROJECT IMPLEMENTATION MANUAL - OGM · viii NRDP National Rural Development Plan ... vii v)...
Transcript of PROJECT IMPLEMENTATION MANUAL - OGM · viii NRDP National Rural Development Plan ... vii v)...
ii
PAGE
CURRENCY EQUIVALENT vi
WEIGHTS AND MEASURE vi
ABBREVIATIONS AND ACRONYMS
vii
PART A: PLANNING 1
I. Introduction 2
II. Project Framework 4
a. Components 4
b. Project Target Group 5
III. Implementing Parties Duties and Responsibilities 5
a. Enablers and Financiers 5
b. Implementing and Cooperating Parties 6
PART B: IMPLEMENTATION GUIDELINES AND PROCEDURES 7
I. Implementation Arrangements for the Project 8
a. Central Operations Unit 9
b. Field Operations Unit 9
c. Provincial Project Teams 10
d. Project Steering Committee 11
II. Financing Project Expenditures 11
a. Project Costs and Financing 11
b. Special Account 13
c. Flow of Funds 14
d. IFAD Disbursement Procedures 15
e. Withdrawal Applications 15
TABLE OF CONTENTS
iii
f. Audit Procedures 16
g. Financial Monitoring Report (FMRs) 16
h. Financial Management Supervision 17
i. Project Completion 17
III. Annual Work Plan and Budgets 19
IV. Detailed Activities and Implementation Procedures by Component 19
Component 1. Natural Resources and Environmental Management 20
a. Introduction 21
b. Awareness Raising 22
c. MC Selection Process 23
d. MC Plan Concept 25
e. Participatory Tool and the Process 26
f. Implementation Arrangements and Procurement 27
Component 2. Investments in Natural Resources and Environmental Assets 31
a. Introduction 32
b. Investment Menu 33
Soil Conservation 33
Rehabilitation of Degraded Forests 34
Rehabilitation of Degraded Grazing Land 36
Investments in Rangeland Infrastructure 36
c. Implementation Arrangements and Procurement 39
Component 3. Investment in Livelihood Improvement 41
a. Introduction 42
b. Impacts and Linkages 42
c. Investment Menu 43
Improving wheat and barley productivity 43
Expanding area under forage crops 44
Improving of livestock stable conditions 44
iv
Establishing modern orchards 45
Improving vegetable production 45
Water storage ponds 46
Rehabilitation of existing irrigation infrastructure 47
On-farm low pressure drip irrigation 47
Contracted seedling production 48
Promoting energy saving technologies 49
d. Knowledge and Skill Development 49
e. Implementation and Procurement Arrangements 55
PART C: REPORTING, MONITORING, SUPERVISION and EVALUATION 57
I. Introduction 58
II. Progress Reporting 58
III. Monitoring and Evaluation 59
VI. Inception Review 62
V: Assessment of Project Impact 62
PART D: IFAD SUPERVISION 65
I. Introduction 65
II. Field Visit 66
III. Mission Report (Aide Memoire) 70
VI: References for Additional Information 71
TABLES
Table 1. Composition of Central Operations Unit (COU) 9
Table 2. Composition of Field Operations Unit (FOU) 10
Table 3. Schedule II of Loan Agreement 12
Table 4. Financing Plan by Component 12
Table 5. Financing Plan by Expenditure Accounts
13
FIGURES
v
Figure 1. Organizational Chart 8
Figure 2. Flow of Funds
14
Figure 3. Measuring Results and Impacts
60
BOXES
Box 1. Criteria for MC Selection
24
Box 2. MC Plan Preparation Steps
26
ANNEXES
Annex 1. Terms of Reference for Secretary/Translator
72
Annex 2. Terms of Reference for Deputy Project Manager (DPM) 73
Annex 3. Terms of Reference for Provincial Project teams (PPTs) 75
Annex 4. Letter to Borrower 78
Annex 5. Disbursement Semester and Government Cash Flow
79
Annex 6. Checklist for Withdrawal Applications 80
Annex 7. Format for Financial Statements
82
Annex 8. Terms of Reference for Auditors
83
Annex 9. Format for AWPB 88
Annex 10. Guidelines for Participatory Integrated MC Plans 89
Annex 11. BCPSBS Process 96
Annex 12. Term of Reference for Micro Catchment Planning Teams (MCTP) 100
Annex 13. Guidelines for Successful Demonstrations 103
Annex 12. Logical Framework 110
CURRENCY EQUIVALENT (March, 2013)
vi
Monetary Unit = Turkish Lira TL
1 USD = TL 1.8
1 TL = USD 0.56
1 kilogram (kg) = 2.204 pounds
1 000 kg = 1 metric ton (mt)
1 kilometer (km) = 0.62 miles
1 meter (m) = 1.09 yards
1 square meter (m2) = 10.76 square feet
1 decare (da) = 0.1 hectare (ha)
1 hectare (ha) = 2.47 acres
WEIGHTS and MEASURES
vii
AGM General Directorate of Afforestation and Erosion Control (former)
AWPB Annual Work Plan and Budget
BCPCPS Beneficiary Centered Problem Census Problem Solving
CEM General Directorate of Combatting Desertification and Erosion
Control (Turkish acronym)
COU Central Operations Unit
FMR Financial Monitoring Report
FOU Field Operations Unit
HBS Household budget survey
HH Household
IC Individual Consultants (procurement method)
ICB International Competitive Bidding
IY Implementation year
GIS Geographic Information System
IPSAS International Public Sector Accounting Standards
M&E monitoring and evaluation
MAPs Medicinal and Aromatic Plants
MFAL Ministry of Food, Agriculture and Livestock
MC micro-catchment
MCP Micro-catchment Plan
MCPT Micro-catchment Planning Team
MFWA Ministry of Forestry and Water Affairs
MoU Memorandum of Understanding
MRWRP Murat River Watershed Rehabilitation Project
MTR Mid-term Review
NCB National Competitive Bidding
NGO non-governmental organization
ABBREVIATION AND ACRONYMS
viii
NRDP National Rural Development Plan
NRDS National Rural Development Strategy
NRM natural resource management
NWFP non-wood forest product
O&M operation and maintenance
OBM Regional General Directorate of Forestry (Turkish acronym)
OGM General Directorate of Forestry (Turkish acronym)
OIM Provincial General Directorate of Forestry (Turkish acronym)
ORKOY General Directorate of Forest Village Relations of MOFWA (Turkish
Acronym)
PCE/IA Project Completion Evaluation/Impact Assessment
PDA Provincial Directorate of Agriculture
PDO Provincial Directorate of OGM
PIM Project Implementation Manual
PPL Public Procurement Law
PPP public-private partnership
PPT Provincial Project Team
PY project year
RIMS Results and Impact Management System
SBD Standard Bidding Document
SOE Statement of Expenditure
TA Technical assistance
WS Watershed
2
1. The present Murat River Watershed Development Project (MRWDP) design is aligned
with the objectives set out in the Results-based Country Strategic Opportunities Program
(COSOP) of 2006 and its 2011-12 Addendum, in particular the emphatic statement that
sustainable natural resource management is a necessary condition for rural poverty
reduction. The 2006 COSOP notes that the support from IFAD should aim to combine
targeted interventions, geared towards quality of life improvements in poorer villages, with
primarily self-targeting measures to stimulate, where feasible, broader-based growth in
economic activity that can generate jobs and increase income for poorer rural people. The
Addendum 2011-2012 served mainly to provide updated information and analysis with
regard to the 2006 COSOP, and to steer the focus of the IFAD country program towards
improved natural resource management with pronounced emphasis on the participatory
rehabilitation of degraded forests and agricultural lands together with creating income-
generating opportunities for poor forest dwellers.
2. The MRWDP Loan Agreement was signed on 5 November 2012. The Project
Completion Date is …….. 2018 and the Financing Closing Date is on ………. 2016.
3. The overall goal of the Project is to reduce poverty among the upland communities of
the Murat river watershed. The objective is to support Government‟s efforts to check further
degradation of watersheds and to improve the natural resource base as a means to raise
income and livelihood in upland villages. The Project will specifically focus on village dwellers‟
involvement in the decision making and implementation processes relating to the
rehabilitation of the existing natural resources while facilitating the creation of a strong sense
of ownership among the upland communities and thereby ensuring sustainability of
investments.
4. Considerations that have shaped the design of the MRWDP include: (i) compliance
with Government strategies and policies, in particular, the Government‟s Long-term
Strategy (2001-2023), Ninth Development Plan (2007-2013), National Rural
Development Strategy (2010-2013), National Forest Program (2004-2023); National
Action Program on Combating Desertification and National Climate Change
Strategy (2010-2020), (ii) compliance with IFAD‟s strategies and policies including:
Strategic Framework 2011-15; Targeting Policy – Reaching the Poor; Gender Strategy;
Engagement with Middle-Income Countries; Climate Change Strategy; Environment and
Natural Resource Management Policy; Policy on Supervision and Implementation Support;
and Environmental and Social Assessment Procedures; iii) IFAD‟s 2006 Country Strategic
Opportunities Paper (COSOP) for Turkey and the Addendum for 2011-2012; (iii) the urgent
and well-recognized need to break the vicious cycle between natural resource degradation
and rural poverty in the Murat river watershed characterized by a high degree of
environmental deterioration and widespread poverty in the upland villages; iv) the
communities‟ expressed needs as well as the physical and economic feasibility of the
I. INTRODUCTION
3
selected activities; vi) criteria-based targeting of project interventions; vii v) mitigation and
perhaps reversal of outmigration;) complementarities with and lessons learned from the two
ongoing IFAD-financed projects in Turkey, the Sivas-Erzincan Development Project (SEDP)
and the Diyarbakir, Batman and Siirt Development Project (DBSDP).
4. This Project Implementation Manual (PIM) for MRWDP sets out the project
strategy, operational activities, steps and procedures, and responsibilities of key
stakeholders. PIM also includes a Monitoring and Evaluation (M&E) operational plan.
5. IFAD has supported eight projects in Turkey since 1982. The overall record of
implementation was mixed. Difficulties arose from the highly centralized and bureaucratic
nature of government administration and a supply-driven attitude towards development. In
the past, these problems were compounded by unstable and adverse macroeconomic
conditions but recent stabilization and rapid growth of the economy accompanied by fiscal
and structural reforms has improved markedly the overall climate for investment and
development. Nevertheless, bureaucratic procedures continue to act as a constraint on the
smooth and successful implementation of projects. However, in the last six years these
difficulties have been addressed through a series of measures including: Collaboration with
UNDP for assistance in procurement and flow of funds; direct supervision and
implementation support by IFAD; a more focused design of investments; and clearly defined
modalities and institutional responsibility for Project implementation. These initiatives have
resulted in a decrease in the time required for declaration of effectiveness and an
accelerated disbursement for the three projects currently under implementation. Specific
problems have included delays in declaring projects effective, slow rates of disbursement,
and difficulties in managing the flow of funds. In some cases, portfolio restructuring, partial
loan cancellation or resource reallocation has been necessary, resulting in adjustments to
loan agreements and Project administration arrangements.
6. In Turkey, some constraints to implementing IFAD projects in the past have arisen
from required bureaucratic procedures and an historical tendency to supply-driven
development, which was not based on technical, financial feasibility, or concerns for
marketability of produce. Specific difficulties, experienced not only by IFAD that support
eight projects in Turkey since 1982 but also by other agencies such as the World Bank,
include: (i) long delays in declaring projects effective; (ii) slow rates of disbursement; and
(iii) difficulties in maintaining the flow of funds. There are also some lessons learned that
need to be applied to new projects to mitigate the constraints to successful implementation.
The following lessons learned were taken into consideration in defining the implementation
steps and procedures and responsibilities of key stakeholders in the PIM: i) institutional
responsibility for implementation should be streamlined with clear assignment to one arm of
the administration for overseeing project execution thus minimizing the need for
coordination within the state apparatus; ii) project management needs to be decentralized
to the province level with a certain amount of authority for decision making related to
implementation, and iii) projects financed by the Fund in Turkey require frequent follow-up
and assistance to implementing parties.
II. PROJECT FRAMEWORK
4
7. The MRWDP would comprise three components: (i) Natural Resources and
Environmental Management; (ii) Investments in Natural Resources and Environmental
Assets; and (iii) Investments in Improved Livelihoods.
8. Component 1: Natural Resources and Environmental Management (about
USD 3.18 million) this component seeks to promote the establishment of environmentally
conscious communities capable of planning and management of natural resources. The
component focuses on assisting Government institutions‟ efforts to make planning and
management more people oriented, and to built ownership and sustainability into its
programs for investments in the upper watersheds of Eastern Turkey. The centerpiece of
the Project is the generation, negotiation, preparation, and implementation of around 25
viable and replicable micro-catchment plans. The Project will seek to promote participatory
co-management modalities under which the village communities‟ livelihood strategies are
aligned with the sustainable use and improvement of public/shared natural resources.
Contracted Micro-Catchment Planning Teams (MCPT) will assist villagers from selected MCs
to make informed decisions about committing themselves to work with OGM to rehabilitate
their degraded natural resources (in the short term) and manage them sustainably (in the
medium and long term). The participatory planning will result in the preparation of village
plans addressing both NRM management and improved livelihood. The village plans
constitutes the building blocks of an integrated Micro-Catchment Plan comprising sub-plans
for forestry land, pastureland, agricultural land, water and energy.
9. Component 2: Investments in Natural Resources and Environmental Assets
(about USD 15.6 million). The component will make investments through activities as
identified in the MCPs for rehabilitation and protection of degraded areas in public land
(gazetted forest land including rangelands). Reversing degradation and checking of erosion
will establish the base for a sustainable economic development and poverty reduction in the
upland communities. Natural resources rehabilitative measures will be implemented under
the direction of the General Directorate for Forestry (OGM) with assistance from village
communities. The investments for the management of land, vegetation and water will
include: (i) soil conservation investments; (ii) rehabilitation of degraded forests;
(iii) rehabilitation and sustainable management of degraded grazing land/rangelands; and
(iv) livestock watering structures.
10. Component 3: Investments in Improved Livelihood (about USD 18.5million).
This component‟s outcome is improved living conditions through supporting small-scale crop
and livestock production on private land. The Project will provide opportunities on a cost-
sharing basis to raise the income of MC communities reinforcing the adoption of
rehabilitation activities. Contracted multidisciplinary Project Provincial Teams (PPTs) will
assist villagers in the implementation of activities. A forester from the provincial Forest
a. Components
5
Directorate (OIM) will be seconded to each PTT as a focal point for the liaison between OIM,
PPT and local communities. The Governors‟ Offices in the Project provinces will provide
necessary coordination and linkages between the Project and the resources of Provincial
Directorates of Agriculture (PDAs) for extension and training support. The investments in
livelihood improvements will target: (i) improved grain production; (ii) forage crop
production; (iii) improved livestock stables; (iv) orchard establishment; (v) improved
vegetable production; (vi) small-scale irrigation; and (vii) contracted seedling production;
and viii) promotion of energy saving technologies. The selected areas of investments will be
based on the agro-ecological and socio-economic conditions in each village as well as
farmers‟ resources and needs and wishes as expressed in the village plan for the MC plan.
11. The MRWRP‟s primary target group would be poor women and men smallholders,
living in upland villages in the selected MCs within Elaziğ, Bingöl and Muş provinces. A
secondary target group would be other non-farming stakeholders in the locality who would
benefit from improvements of the physical environment and living standards in the micro-
catchment. Together, these groups total an estimated 80 000 very poor potential direct
beneficiaries (12 500 households) usually resident in the targeted MCs. The majority lack
the means to escape poverty either by earning sufficient incremental income locally, or by
migrating permanently within Turkey or beyond. Tertiary indirect beneficiaries are the
general population living downstream.
12. Within the objective selection of whole village communities by virtue of their
location, the state of their local natural resource base and degree of household poverty, all
subsequent Project interventions would be demand driven and self-targeting. Whilst all
upland villagers would benefit from the substantial investments in public goods, and some
from the provision of energy-saving technologies for individual households, participation in
the promotion of small-scale agriculture would be entirely individual voluntary basis.
13. The major enablers/financers of MRWDP are: i) IFAD, and ii) the Government of
Turkey (also the borrower). These parties developed the project concept collaboratively
through consultation with the local beneficiaries. Then, the detailed project design was
undertaken. Focus Group Meetings in the villages and individual interviews with local
III. Implementing Parties and Responsibilities
b. Project Target Group
a. Enablers and Financers
6
stakeholders provided information on the prospects and bottlenecks in rural livelihood from
their perspective.
14. The Project is to be financed not only by IFAD and the Government of Turkey but
Project beneficiaries as well. IFAD provided a loan and a grant to the Republic of Turkey in
the amount of approximately USD27.2 million and US$ 410.000 respectively. The
Government of Turkey‟s contribution as counterpart financing is approximately equivalent to
USD 1.5 million in cash contribution and approximately USD 6.4million to cover taxes and
duties on all Project inputs that involve funding from the IFAD loan.
15. The ratio of MRWDP support to beneficiary contribution varies according to
components and component activities. It could be in cash or in-kind (labor or land) and
varies between 5% and 30% depending on the activities.
16. The details of financing are presented under the heading II. Financing Project
Expenditures below.
17. The implementing parties of MRWDP are: i) Government of Turkey through Ministry
of Forestry and Water Affairs (MFWA) at the central and provincial levels, and ii)
beneficiaries. In the MFWA, two general directorates is responsible for implementation:
o General Directorate of Forestry (OGM) through the following 6 departments: i)
Afforestation; ii) Soil Conservation and Watershed Rehabilitation; iii) Forest-
Village Relationship; iv) Strategy Development; v) Data Processing and vi)
Nursery and Seed Affairs.
o General Directorate of Combating Desertification and Erosion Control (ÇEM)
through its Department of Watershed Planning and Land Rehabilitation.
18. The details regarding role and responsibilities of MFWA and the Central (COU) and
Field Operational Unit (FOU) are presented under Part B.
19. During implementation of the Project by the Ministry and beneficiaries, IFAD will
administer the loan, supervise the project and provide support in project implementation.
20. Supervision: The Project will be supervised directly by IFAD. IFAD supervision
missions (a team of experts) will be undertaken at least once a year or more frequently if
considered desirable. The details are given in Part D of this Manual.
b. Implementing and Cooperating Parties
8
21. Overall responsibility for the management and implementation of WRWDP would rest
with MFWA through OGM (Figure 1). Under WRWDP leadership the following management
structure would be established: i) Central Operations Unit; ii) Field Operations Unit; and iii)
Project Steering Committee.
Figure1. Organizational chart for the Project
I. IMPLEMENTATION ARRANGEMENTS FOR
THE PROJECT
9
22. The unit will be established within OGM in Ankara. It will be responsible for assisting
in the overall and day-to-day management and implementation of the Project.
23. Principal functions of the COU: i) to provide broad based management support
including planning, programming, budgeting, monitoring and documenting progress;
ii) elevating experiences and lessons learned through the steering committee to the policy
level; and iii) to report to the Ministerial level and general directorate level and IFAD.
24. Composition of the COU: it comprises a Project Manager, a Central Focal Point (CFP),
a technical team, and a secretary/translator (Table 1).
Table 1: Composition of Central Operation Unit (COU) in Ankara
Position in Project Position in OGM Type of recruitment
Project Manager (PM) Deputy General Director Seconded
Central Focal Point (CFP) Head, Department of Afforestation
Seconded
Technical Staff
Senior Forestry Engineer Procurement Specialist
M&E Specialist Procurement Officer Finance Officer
All OGM forest engineers and
administrative staff
Seconded
Secretary / Translator - Contracted
25. The technical staff (seconded) will use approximately 20% of their time (yearly
average) on COU related work. Appropriate office premises and infrastructure for the COU
will be provided by the OGM. The TOR for the secretary/translator is provided as Annex 1.
26. The COU will receive technical support through the Afforestation and Soil
Conservation and Watershed Department (Components 1 and 2) and the Forest-Village
Relations Department (ORKÖY) (Component 3). Both departments are integral parts of OGM
reporting to the General Director.
27. This will be established at the Regional Directorate of Forestry (OBM) in Elazığ, with
seconded staff from OBM and supported by a Deputy Project Manager hired through a
national competitive recruitment process and based on prior review by IFAD.
a. Central Operations Unit (COU)
b. Field Operations Unit (FOU)
10
28. Principal functions of the FOU: (i) to provide management support at the field level;
(ii) to coordinate the planning and reporting between Provincial Directorates of Forestry
(OIMs), the OBM and OGM in Ankara; and (iii) to handle day-to-day management and
implementation of the Project. The FOU will take the lead in the procurement of all civil
works, goods and services, and technical assistance that relate to the field activities.
29. Composition of the FOU: It comprises a Field Project Manager (FPM), Deputy Project
Manager (DPM), and Focal Points for each province and an administrative team (Table 2).
Table 2: Composition of FOU/Elazığ
Position in Project Position in OBM/Elazığ Type of recruitment
Field Project Manager (FPM) Deputy Regional Director Seconded
Deputy Project Manager (DPM) Assistance to FOU and COU Contracted
Provincial Focal Points (PFPs) OIM forest engineers Seconded
Administrative Staff Senior Forestry Engineer M&E Officer Finance Officer Procurement Officer
All OBM forest engineers and administrative staff
Seconded
30. Field Project Manager (FPM): The Deputy Regional Director of OBM in Elazığ assumes
the position as FPM. He is supported by the DPM who is contracted.
31. Deputy Project Manager (DPM): He will be stationed in Elazığ and support The FPM
but will have frequent assignments with the COU in Ankara. He reports to the FPM as the
immediate supervisor and the PM of the COU in Ankara. The TOR for the DPM is provided as
Annex 2. He will be employed by using CQ procurement method.
32. Provincial Focal Points (PFPs): in each OIM, one forest engineer will be seconded as
PFP and remain stationed at their respective OIMs. Their task is to ensure coordination
between: i) their respective OIMs, and DPM in Elazığ and ii) OIM, Provincial Project Teams
(PPT) and local communities for the implementation of Component 3.
33. The administrative staff (seconded) will use approximately 20% of their time (yearly
average) on COU related work.
34. The teams will be based in Elazığ, Bingöl and Muş OIMs with regular visits to
Regional Forestry Directorate (OBM) in Elazığ as required to provide requisite support to OIM
according to the approved MC plans.
c. Provincial Project Teams (PPTs)
11
35. Team composition: each team will comprise a forest engineer, a crop production
specialist (agronomist with capacity in the fields of land and water management), and a
livestock production specialist (zoo technician or veterinarian).
36. Major tasks : as indicated in the TOR Annex 3, these include: i) ensuring that the
Project is implemented in accordance with the design and agreement with Turkish
Government (MFWA/OGM) and IFAD; ii) collecting relevant data and information to be used
as input to the Project M&E System; iii) initiating the awareness raising campaign before the
MC planning process is started ; iv) providing technical and logistical support to MCPT during
participatory process; v) developing action plans for each village, based on the MC plans for
efficient and effective implementation of Component 3, to a certain extent to Component 2
(rehabilitation of degraded grazing land) and Component 3 (farmer exchange visits), and vi)
implementing Project activities included in the MC plans through a multi-sectoral, client-
focused, coordinated, demand-driven and participatory advisory services.
37. This will be established within MFWA will be chaired by the Deputy Undersecretary
for Forestry.
38. Composition of the SC: Membership comprises the Director General of OGM and the
Heads of the following departments: (i) Afforestation; (ii) Soil Conservation and Watershed;
(iii) Forest-Village Relations; (iv) Strategy Planning; v) Data Processing; and (vi) Nursery and
Seed Activities. The DPM will act as secretary and be responsible for the dissemination of the
decisions and follow-up.
39. The role of the SC: i) to provide overall policy guidance and oversight, ii) to approve
the Annual Work Plans and Budgets and the Program Implementation Plan, and, iii) to ensure
that overall Project operations are within the legal and technical framework agreed between
the Government and IFAD.
40. Detailed implementation arrangements for the three components are given in
Chapter IV of this document under the following heading: Detailed Activities and
Implementation Procedures by Component.
d. Project Steering Committee (SC)
II. FINANCING PROJECT EXPENDITURES
a. Project Costs and Financing
12
41. The Project is to be financed by IFAD, the Government and Project beneficiaries.
Table 3 sets forth the Categories of Eligible Expenditures to be financed by the IFAD Loan
and IFAD Grant and the allocation of the amounts of the IFAD Loan and the IFAD Grant to
each Category and the ratios of expenditures for items to be financed in each Category.
Table3. Schedule II of Loan Agreement (SDR)
Category
IFAD Loan Amount
Allocated (in SDR)
IFAD Grant Amount
Allocated (in SDR)
% of Expenditures to be Financed (net of taxes)
1. Civil Works 10 194 162 100% net of taxes, beneficiary and Government contribution
2. Vehicles, Equipment, Goods 4 261 000 100% net of taxes and Beneficiary Contribution
3.Technical Assistance, Training, Studies and Workshops
2 991 000 280 000 100% net of taxes and Government Contribution
3. Recurrent Costs
a. salaries
257 000
100% net of taxes, and net beneficiary contribution
b. Recurrent costs b. other operating expenditures
252 000 100% net of taxes and Government Contribution
TOTAL 17 955 162 280 000
42. Tables 4 and 5 gives the financing plan by components and expenditure accounts
respectively.
43. IFAD Contribution: the IFAD loan in the amount of USD 27.2 would be used to
finance 75% of the costs of Component 1, Natural Resources and Environmental
Management, 74.8 of the costs of Component 2, Investments in Natural Resources and
Environmental Assets and 68.2% of the costs of Component 3, Investments in Improved
Livelihood. On the other hand, the Loan would finance 81.4% of the expenditures related to
the Operations Unit. IFAD Grant that is approximately USD 410.000 is allocated for technical
assistance, studies and workshops.
Table 4. Financing Plan by Components (thousand USD)
13
Table 5. Financing Plan by Expenditures Accounts (thousand USD)
44. Government contribution is estimated at approximately USD1.5 million in the
form of foregone taxes and duties. In conformity with the principle that no taxes or duties
would be financed out of the proceeds of the IFAD loan, any future changes in the rates and
or structures of taxes and duties would apply, thus affecting the amount of foregone
revenues. About 7% (USD1.5 million) of the Component 1 would be financed by
Government. This ratio is 0.7% for Component 2. For the expenditures of the Operations
Units, the contribution of Government is 9.5%.
45. Primary beneficiary contribution: beneficiaries would provide approximately
USD3.0 million. It could be in cash or in-kind (labor or land) and varies according to
components and component activities:
Component 1: no contribution by the beneficiaries
Component 2: for rehabilitation of degraded grazing lands that includes
temporary closure, livestock drinking structures and simple shelters for
communal use, the ratio is 5 %,
Component 3: i) for water storage ponds and rehabilitation of earth canals
the ratio is 5%, ii) for the remaining investments, the ratio is 30%.
46. A Special Account in US Dollars (USD) will be established by the Government
(Undersecretariat of Treasury) in the Central Bank for the exclusive purposes of receiving
advance liquidity in support of Project implementation from the Loan Account. The Strategy
Department (SDD) of the OGM will be authorized to operate this account. The SDD will
b. Special Account (SA)
14
channel the funds through its OGM corporate account based on approved Annual Work Plan
and Budgets (AWPB) and track the funds through specially assigned codes.
47. After the SA has been opened, upon the borrower‟s request, IFAD shall make one or
more withdrawals in aggregate from a „Loan Account‟. The SA will be administered in
accordance with Section 4.08 of the General Conditions (Special Account) and will be
replenished from time to time upon request, in such minimum amounts as IFAD may specify
by notice to the Borrower.
48. The flow of funds arrangements is presented in Figure 2.
Figure2. Flow of funds
c. Flow of Funds
15
49. The IFAD Loan of Special Drawing Right (SDR) 17.955.162 (approximately USD
27.2million) will be disbursed over 7 years. The Loan Closing Date is the 7th anniversary of
the date when the project was declared effective. No disbursement from the loan can be
made in respect of goods or services or other expenditures incurred after the project closing
date.
50. All Operations Units (COU and FOU) related expenditures would be financed jointly
from the IFAD Loan Proceeds and Government contributions including the incremental
operating costs required for the operations of the COU and FOU. It is important to remember
that the IFAD loan cannot be used to pay for land purchase and custom duties or taxes.
51. According to Schedule 2 of the Loan Agreement, the loan proceeds will be disbursed
as shown in Chapter I, paragraph 1. The attached Letter to Borrower (Annex 4) sent by
IFAD explains the action to be taken by the Borrower in order to start withdrawing funds and
spells out the methods and procedures for withdrawal of funds, procurement of goods, works
and consulting services as well as the financial and audit reporting requirements.
52. The IFAD loan will be disbursed over a seven-year period. The disbursements by
semesters and government cash flow are given in Annex 5. Disbursement by IFAD for
expenditures of less than USD …………. and for incremental credit will be made against
certified statements of expenditure. The PMU will retain the relevant documents and make
them readily available for inspection and review by supervision missions and auditors.
Contracts over USD ………will require full documentation. No taxes and duties will be financed
out of the proceeds of the IFAD loan. Funds from the Special Account may finance all IFAD
disbursement categories.
53. For costs incurred at the Central level, the Operations Unit (OU) at OGM will be
responsible for approving and releasing the payments. Payments for works, goods and
services procured at provincial level would be executed by the Regional Directorate of
Forestry (OBM), who is responsible for field implementation. Payments made at provincial
level (OIMs) would be authorized by the Governor‟s Office, in line with the practice for
Government-financed projects, against approved work plans and associated budgets.
54. Four standard disbursement procedures may be used for withdrawal of financing: i)
advance withdrawal; ii) direct payment; iii) special commitment and iv) reimbursement.
55. Regardless of the procedure applied, disbursement will be based on a withdrawal
application submitted by the Borrower. Each withdrawal application is made up of two
d. IFAD Disbursement Procedures
e. Withdrawal Applications
16
integral parts. The first part is the withdrawal application itself, in letter form, which
mentions the total amount to be withdrawn and contains requisite statements and agreement
as well as the signature of the Borrower. The second part consists of one or more summary
sheets with supporting documentation as appropriate. The checklist for withdrawal
application is provided in Annex 6.
56. IFAD will accept withdrawal applications for reimbursement, direct payments and
special commitments. Replenishment of the Special Account from the loan account at IFAD
will be by way of withdrawal applications, supported by appropriate documentation or
certified statements of expenditure prepared by the COU endorsed by the Ministry of Finance
and submitted to IFAD for approval and payment.
57. Financial statements would be prepared on an accrual basis of accounting in
accordance with International Standards on Auditing (ISA) that reflect receipts, payments
(by disbursement category) and fund balance for the current reporting period and the
cumulative period from the commencement of the Project. Format for Financial Statements is
provided in Annex 7.
58. Annual financial statements for the Project will be audited by the Undersecretariat of
Treasury in accordance with International Standards on Auditing and under Terms of
Reference (TOR) agreed upon with the IFAD. Audits will also cover expenditures made by the
Project provinces and include specific opinions on the financial management arrangements of
each province.
59. The auditors would issue separate opinions covering the financial statements, FMRs,
and the management of the designated account, including accounts in provinces. IFAD‟s
generic template for Auditors TORs that is given in Annex 8 included for guidance.
60. The audited financial statements and audit reports would be submitted to IFAD and
the Government. For IFAD, audit reports would be submitted within six months after the end
of each fiscal year and after the financing closing date. In addition, management letters
outlining any internal control weaknesses shall be issued by the auditor.
61. The FMRs will be prepared on a semi-annual basis by the COU using the accrual basis
of accounting. As the FMRs will be used as a monitoring tool, they will summarize: i) the
Project progress and provide budget versus actual variance analysis; ii) financial statements
on sources and uses of funds; iii) Project financial position; iv) expenditures and physical
progress compared with plans; v) procurement and contract monitoring reports. Such reports
will be prepared on a timely basis and be submitted to IFAD by the COU within 45 days after
the end of each 6 months starting from when the first disbursement is made.
f. Audit Procedures
g. Financial Monitoring Reports (FMRs)
17
62. Annual financial statements will be prepared individually by the FOUs and
consolidated by the COU. The annual financial statements for the Project are subject to
annual audit by an external auditor.
63. The Financial Management Manual prepared under the World Bank financed Anatolia
Watershed Rehabilitation Project will be utilized for MRWDP. This manual includes formats for
Financial Monitoring Reports (FMRs) that would be included in Project semi-annual reports to
IFAD. Relevant guidance will be provided in the form of start-up training but also provided in
detail in the Letter to the Borrower.
64. Full documentation in support of FMRs would be retained by the OGM for at least ten
years after the Financing Closing Date. This information would be made available for review
during supervision by IFAD staff and for annual audits which would be required to comment
specifically on the propriety of FMR disbursements and the quality of the associated record-
keeping.
65. This will be aligned with risk-based supervision for financial management
arrangements. At least one “on-site fiduciary-focused visit” would be carried out each year,
and more, if deemed necessary.
66. In the final year of implementation, as part of the preparation of the IFAD-required
Project Completion Report (PCR), M&E data collected during implementation will form the
basis for an overall assessment of Project achievements, particularly in terms of documented
improvements to the natural resource base as well as changes in the livelihoods of villagers
living in the targeted MC areas.
67. Stakeholder Workshop: The PCR process will include a workshop in each Project
province to provide an opportunity for stakeholders themselves to evaluate performance, to
promote accountability, to identify and elaborate upon factors that will improve sustainability,
and to lay out key successes and shortcomings. Equal representation of different interest
groups should be promoted and female representation in the stakeholder workshop is a
must. If required, female stakeholders may have a distinct evaluation process.
68. Assessment of the Project‟s impact: This will be based on monitoring data including
in annual reporting. Monitoring data will be compared with data contained in the micro-
catchment plans on pre-program erosion level and living conditions. An impact study in
selected villages from previous years‟ implementation will be carried out at the last year of
the Project to allow for a post-Project comparison. Only villages where Project activities had
commenced by the fourth implementation year will be used for comparative purposes. As
h. Financial Management Supervision
i. Project Completion
18
proxy, the post-Project impact review will cover at least one micro-catchment (MC) not
supported by the Project in each of the three provinces.
69. The main categories of information to be collected during the planning phase and
used to assess Project impact are detailed in the MC Plan guidelines. These include but are
not be limited to:
(a) Socio-economic characteristics: number of households in the village,
composition of the households, employment and migration data, household income
and expenditure patterns (in particular for food and energy);
(b) Physical characteristics: location of village (longitude and latitude), distance
from and access to provincial center, housing and roofing material, sanitation and
drinking water;
(c) Agriculture and livestock: Number of livestock owned by villagers (type and
average per household), size of grazing/rangeland, number of functioning livestock
drinking points and shade structures, livestock productivity, rainfed area (by crop),
irrigated area (by crop), size of household plots (irrigated and rainfed), crop yields;
and
(d) Natural resources: state of forested area, eroded land, grazing/rangeland.
GIS maps will be prepared at completion for the selected MC and compared to
those prepared during the planning phase. These provide evidence of
improvements to natural resources. As a complimentary modality, photos with
marked with date/time and GPS coordinates should be taken at specified time
intervals to accompany written information and linked into the GIS system.
70. Provisions are made for the use of innovative monitoring measures such as cameras
with integrated GPS function possible combined with aerial photos, which can be used to
detect physical changes in the MC, landslides, gully formation and vegetative cover. Photos
should be taken in few locations with characteristics typical for the MC. Photos should as far
as possible be taken at the same time of the year. 64. GDAPD, acting on behalf of the
PMU that may then be closed, will submit to the IFAD, the Project Completion Report/Impact
Assessment (PCR/IA) no later than six months after the Project Completion Date that is 30
September 2015. This report examines the implementation process and the final results of
the project. It therefore serves to make a formal identification of both those aspects of the
project that succeeded and those that failed. IFAD uses the project completion report,
together with its own internal project evaluation process, to evaluate the success of its
lending operations and applies the lessons learned to new lending activities. It should be
noted that at a minimum, the PCR would address the following: i) i) the costs and benefits of
the Project; ii) achievements of its objectives; iii) the performance of TUGEM and P/DDAs, iv)
lessons learned.
71. M&E data collected over the period of project implementation would be fed into an
overall assessment of Project achievements, particular, in terms of changes in the income
and livelihood status of beneficiaries targeted by the respective components and in terms of
sharing lessons learned and knowledge of development. The PCR/IA process would include
19
stakeholder workshops to provide an opportunity for stakeholders themselves to evaluate
Project performance, to promote accountability, to identify and elaborate upon factors that
would increase the likelihood of sustainability and to lay out key successes and shortcomings.
72. If an assessment of country level impact is required then countrywide information
from a variety of sources will have to be traced once at Project start and again at closure.
73. The Micro-Catchment Plans (MCPs) developed for each targeted MC and the Project
Implementations Plan (PIP) forms the basis for all further planning. OGM supported by the
Coordination Units (FOU/COU) prepares the Annual Work Plan and Budgets (AWPBs) in
accordance with procedures agreed with IFAD and detailed in the PIM. The AWPB format is
given in Annex 9. The inputs for the AWPBs will be provided by OBM and the Deputy Project
Manager (DPM), in line with the Micro-Catchment Plans (MCP). The FOU/COU will assist in
generating the AWPBs that would be submitted to OGM for review and formal approval in the
Steering Committee and presented to IFAD for no objection.
74. These AWPBs will clearly describe which activities will be carried out the coming
year. The AWPBs will link the proposed budgetary envelope with physical results to be
achieved, taking into account previous years‟ achievements. The FOU will review and approve
provincial AWPBs and send a consolidated version to the COU in Ankara. The COU inserts its
contributions and complete the AWBP. The Deputy Project Manager supports the AWPB
preparation process at both the FOU and the COU level. Finally the Project Steering
Committee reviews and approves the AWPB in time for Project activities to be included in the
normal government budgeting process, and submits the AWPB to IFAD at least sixty days
prior to the commencement of the fiscal year.
75. Starting from the next chapter, the details of project activities, implementation
processes and procedures, and beneficiary targeting are elaborated by components.
III. ANNUAL WORK PLANS AND BUDGET (AWPBs)
IV. DETAILED DESCRIPTION OF ACTIVITIES
AND IMPLEMENTATION PROCEDURES BY COMPONENTS
21
76. The component concentrated on both the management and modalities of
Government‟s ambitious investment program of environmental remedial works in the upper
watersheds in the east of the country. Inadequate arrangements in the past for the
sustainable economic use of fragile forests and rangelands have contributed to the depleted
and deteriorating state of the landscape, both close to human settlements and at higher
altitudes.
77. The experience gained in identifying, planning, implementing and then maintaining
productive natural resources in the project area is expected to contribute to the realization of
national environmental goals. A gradual change in the effectiveness of land use management
is a necessary condition for reversing the deterioration of the natural resource base and the
related livelihood in the upper watersheds. Expensive rehabilitation works will not be
sustainable in terms of physical conditions or poverty reduction without far greater
involvement of the local communities.
a. Introduction
22
78. MC Concept: The project adopts a participatory, demand driven approach based on a
micro-catchment (MC) area as the smallest unit of intervention. A MC is a small hydrological
unit in a watershed that supplies water by surface or subsurface flow to a given drainage
system (stream, river or lake).
79. Number of MCs for the Project: The project aims at working in a fourth
(approximately 25 MCs) from the estimated 100 MCs of the Murat Watershed. The
interventions will be selected and implemented based on site-specific participatory
rehabilitation and investment plans prepared for each.
80. The component finances awareness-raising activities for the target beneficiaries
(men, women, and youth) and other stakeholders (including local administrations, provincial
agencies, OGM field staff and school children) regarding the project‟s approach and terms of
participation in MC development.
b. Awareness Raising
23
81. Before starting MC planning, it is particularly important for the MC communities to
make educated decisions about committing themselves to work with OGM to rehabilitate their
degraded natural resources (in the short term) and manage them sustainably (in the medium
and long term). To achieve this they will benefit from the awareness campaign and also
village-to-village visits. These visits will be organized to challenge their pre-conceived notions
and predispositions regarding mainly forestry activities by exposing them to MCs in the region
that were rehabilitated earlier by other projects thus enabling interaction with the villagers in
those MCs. Such activities will help to increase transparency in project implementation and
encourage beneficiaries to participate and articulate demands for project services. It will also
complement and improve the effectiveness and ownership of the investments undertaken
under Components 2 and 3.
82. Following awareness raising, the Project staff will select the MCs in their respective
provinces and the “integrated MC plans” will be prepared in a participatory manner for
implementation by the Micro-catchment Planning Teams (MCPTs).
83. The selection is a three-step process and criteria based (Box 1). It is important to
ensure that this process is objective and transparent.
84. First step: A map indicating the existing MCs in the Project area is available and
statistical data from the Governor‟s office. The OIMs in each of the three provinces make an
initial screening of the 100 MCs (estimated total number of MCs in the Project area) and
produce a long list of possible candidate MCs for their respective provinces. The long list will
form the basis for a further scrutiny of the MCs.
85. Second step: The MCs in the three long lists will be discussed at OBM. Then these
will be visited by a team comprising representatives from OIMs of each province and the OBM
to make observation and collect ground truth data.
86. Third step: The available information and field observations for the long listed MCs in
each province will be used by the same team at OBM to evaluate and rank the MCs on a 1-5
scale to come up with a short list for each of the provinces. For screening, a set of criteria will
c. MC Selection Process
24
be used (Box 1). Considering the benefit of synergy between communities, preference will be
given the selection of neighboring MCs as much as possible.
Box 1. CRITERIA FOR MC SELECTION
Severity of natural resource degradation: has to be rated as severe, a well identified cause of poverty and the area already subject to flooding and land slides, high levels of sedimentation effecting downstream investments for irrigation and drainage,
Reversibility of degradation: Possibility of reversing the natural resource degradation in a sustainable and economic way; investments should lead to sustainable rehabilitation of degraded natural resources,
Risk of natural disasters: through flood, land slides and rock falls,
Accessibility of the MC: adequate degree of access is needed for project staff and contractors/transporters. It is also important for demonstration purposes; if a MC is too remote there will be almost no chance to be seen by other communities
Level of potential for introducing income raising activities: availability of sufficient resource base (pastures, agricultural land, water) for crops and livestock where incomes may be increased to be used as leverage for better natural
resource management
Level of rural poverty: as demonstrated by rural out migration and measured through estimated annual incomes
Willingness of rural communities to participate in the project: prepared to make in kind and/or cash contributions and take responsibility for specific activities (e.g. small infrastructure investments, pasture management, conservation of new
plantations and use of irrigation water), and prepared to change the way they use natural resources
Social harmony in and between MC villages: conflicts (i.e. over water and pastures) will hamper the success of the project,
25
Short listing for the 1st and 2nd year: For each province, the short list of MCs will
be comprised of those ranking in the top 25% that may be treated by the
Project. For planning in the 1st and 2nd year, the top 3 will be selected from its
respective pool for each province (a total of 9). The final selection will be done
jointly by OIM and the Regional Forest Directorate (OBM) based on physical as
well as socio-economic criteria.
Demo MCs: One of the three MCs that will be planned in the first year will have a
demonstration effect in the Project provinces. Therefore, the proximity of the
MCs is important considering the initial difficulties in implementing such a
participatory and, integrated project that will need frequent visits and close
supervision/monitoring. It should be taken into consideration that potential for
success is also important since it will pave the way for the other MCs and
communities. The experience gained in these first MCs will shed light on
potential issues and risks and will allow both the central and field managers to
take necessary actions for more efficient and effective implementation in
succeeding MCs and years.
87. For each selected MC, an integrated plan will be prepared for each of the villages
located in the MC in a participatory manner with the resident communities for the
rehabilitation and subsequent care of the natural resources and the improvement of
livelihoods of the resident households. The plan is “participatory” because it is prepared
based on communication, collaboration and agreements of the resident communities and
“integrated” because it includes sub-plans for several sectors; forestry land, grazing land,
agricultural land, water and energy. These sub-plans are interlinked where each of the
activities included have dual impact upon both natural resources and rural livelihood. For
each MC, plans will be prepared for each of the villages located in the MC.
88. Each plan will include an MC activity map and associated maps to include soil,
erosion, topography and vegetation, and ten pre-determined chapters: i) overview of the MC;
ii) current status of the natural resources, land-use, crop and livestock production; reasons
for selection of the MC; iii) participatory process and priority problems as identified by the
communities; iv) forestry sub plan; v) grazing land sub plan; vi) agricultural sub plan; vii)
water sub plan; viii) energy sub plan, ix) costs, and x) agreements and arrangements. In
preparing the sub-plans, the main principle is to keep a ratio between rehabilitation and
income-generating interventions by taking the nature of the project into consideration.
89. In any MC, implementation interventions may be carried out only in some parts of a
MC and in some villages of the MC based on clearly established priorities agreed with the
communities. The main principle to stop the erosion, starting from the upper MCs and move
downward.
d. MC Plan Concept
26
Forestry sub-plan: is prepared for forest land and includes rehabilitation of
eroded areas and improvements in degraded forest land.
Rangeland sub-plan: includes investments for rangelands/livestock and
interventions regarding sustainable management.
Agricultural sub-plan: is prepared for agricultural land and includes crop
(grain, forage and horticultural crops, and greenhouse production) and
livestock interventions. It will also include training and demonstration
program.
Water/irrigation sub-plan: is prepared for the investments for: i) the
development of small water sources for small-scale irrigation purposes and
rehabilitation the existing irrigation infrastructure; ii) livestock drinking water,
and iii) village sanitation.
Energy use sub-plan: is prepared for the investments regarding energy
saving and renewable technologies.
90. The MC planning process comprises 14 steps (Box 2). MCPs will be prepared by the
MC Planning Teams (MCPTs) that will be multi-disciplinary service providers. The guidelines
for preparing MC plans are given in Annex 10.
91. The MC planning, implementation and monitoring will be participatory. To achieve
this, the participatory tool called “Beneficiary Centered - Problem Census - Problem Solving
(BCPCPS)” modality will be used (Annex 11). The appropriate tools of IFAD methodology will
Box 2. MC Plan Preparation Steps
Step Action 1 Awareness raising
2 First field trip to the MC
3 Informing local communities about the project
4 Compilation of data and information
5 Problem identification
6 Analysis of the problems
7 Solution of identification
8 Preparation of the first Draft MC Plan
9 Preparation of the draft Map of Activities
10 Display of the first Draft MC Plan in MC villages
11 Preparation and approval of the final draft at the local level
12 Signing of the Final MC Plan
13 Display of the signed plan at the local level
14 Budget allocation for the MC Plan
e. Participatory Tool and Process
27
fill the gaps in the BCPCPS process when relevant. During planning process, focus group
discussions and community consultation will also be undertaken, when needed.
92. Approach: The BCPCPS provides the setting in which all members of the community
have equal voice irrespective of gender, age and social status. Particular efforts are made to
encourage women‟s participation, so as to assure that gender issues are mainstreamed into
MC development planning and implementation. In villages where local culture does not allow
undertaking the process with mixed groups, separate meetings will be held with women.
93. Management responsibility for the Component: it belongs to the OBM in Elazığ
through the FOU. Main responsibilities of the OBM are: i) procurement of all service
providers in the field; ii) planning and execution of the workshops, study tours and exchange
visits under the component and iii) organizing and delivering the sensitization and awareness
raising programs.
94. Service providers to be recruited: For the component, 2 contracted teams will carry
out the envisaged activities: i) MC Planning Teams (MCPTs), and ii) Provincial Project Teams
(PPTs). Procurement of the teams will be handled by the Procurement Specialist (seconded)
of the FOU. The Deputy Project Manager (DPM) in Elazığ, oversee the recruitment of the
MCPTs and PPTs under the oversight of COU. One of the following methods will be used in
procurement: i) National Competitive Bidding (NCB) or ii) Direct Contracting (DC) in the case
of Universities.
MCPTs: Teams will be responsible for preparing integrated MC Plans in a
participatory manner as detailed in TOR (Annex 12) for the pre-identified areas
where the Murat River Watershed Rehabilitation Project is being implemented. While
the composition of MCPT is flexible in terms of the size and would be decided by the
Consultancy Contractor as a minimum, the following specialists will be made
available as MCPT members: forester, crop production specialist (agronomist),
livestock production specialist, rural sociologist, rural infrastructure engineer, and
economist. MCPTs will be supported by: i) respective OIMs in Elazığ, Bingöl and
Muş, and ii) Provincial Project Teams (PPTs) in terms of technical and logistical
support in the BCPCPS process and in the preparation of the MC plans. Provisions
are made for preparation of 25 MC plans (USD75.000/MC plan including cost of
consultants, 6-7 visits/MC by the team, soil surveys and detailed physical planning.
PPTs: Three teams will be recruited for each of the Project provinces based on the
TOR (Annex 3). The teams will be based in Elazığ, Bingöl and Muş with regular
visits to Regional Forestry Directorate (OBM) in Elazığ as required reporting and
coordination and monitoring. Each team will comprise a forest engineer, a crop
Implementation Arrangements for the Component
28
production specialist (agronomist with capacity in the fields of land and water
management), a livestock production specialist (zoo technician or veterinarian).
Their TOR includes various tasks for the Project. However, for the component, each
team will spearhead the awareness-raising campaign before the MC Planning
process is started and working closely with the MCPTs to develop the village visit
plans, arrange venues through the village administrations, and ensure the
participation of women and the elderly. The teams also assist the MC Planning
teams by providing technical and logistical support in conducting the BCPCPS
process and preparation of the MC plans to ensure congruity with the norms and
approaches outlined in this PIM. The Teams will assist the PFPs who are seconded
foresters in each of the OIMs responsible for ensuring coordination between their
respective OIMs and the DPM in Elazığ.
95. Phasing: One MC will be selected for each province (3 MCs for the Project/year).
Every MC plan will be implemented in 3 years, successively. To be able to complete the
implementation of the all MC plans during the life of the Project, 4th year will be the last year
for planning (Table 6). Most of the physical works can be undertaken in the first year (or 1.5
years) and maintenance will be carried out in the following two.
Table 6. Phasing of planning and implementation of 25 MCs
Project Year
1 2 3 4 5 6 7
PY* IY**-1 IY-2 IY-3
PY IY-1 IY-2 IY-3
PY IY-1 IY-2 IY-3
PY IY-1 IY-2 IY-3
No. of MCs
in the work
program
3 6 8 8 3 2 1
* Planning Year (PY) ** Implementation Year (IY)
96. Training /Technical Assistance and Workshops: this Category covers the capacity
building activities for both technical staff (OGM) and MC communities:
Technical assistance: funds are made available for: i) a GIS/data management
specialist to layer information from the MC plans onto GIS maps; ii) upgrade of
existing monitoring system of physical interventions including soil erosion and
linking to the GIS system. IFAD Procurement thresholds and guidelines would
apply for the procurement of consultants. Selection based on Consultants‟
Qualifications (CQ) will be employed in hiring the specialists.
Workshops: i) natural resource economics for OGM and PPTs; ii) planning and
technical subjects identified, for PPT, OGM and Regional OGM staff, annually,
29
and iii) carbon sequestration. Local shopping (LS) would be used for the
expenses related to workshops, the venue, office supply etc.
Training courses: funds are made available for courses on :i) preparation of
multi-functional forest management plans for sustainable management of forest
ecosystem services including environment for recreation and education, nature
conservation, timber and fuel wood production, and ii) project approaches and
implementation guidelines for PPTs. The funds allocated are for training related
expenses including the venue and training material that will be procured through
LS.
Studies: Several studies that deemed to be useful for the Project and MFWA will
be funded under the Component. These are: i) natural resource economics; ii)
assessment of opportunities for carbon sequestration; iii) assessment of
opportunities for non-wood forest products; iv) assessment of alternatives for
energy sources including wind, and v) private/public nursery feasibility study.
For hiring the individual specialists who will carry out these studies, CQ
procurement method will be used.
Awareness raising: PFPs and PTTs under the supervision of the DPM will be
responsible for the awareness raising activities in the Project area. PPTs will start
the awareness-raising campaign before the MC Planning process is started and
later working closely with the MCPTs develop the village visit plans, arrange
venues through the village administrations, and ensure wide participation with a
special emphasis of women, youth and the elderly. Funds are allocated for 25
visits during 4 first years of the Project covering various expenses. Procurement
method is LC.
Farmer Exposure Visits: These will be organized for the MC villages to expose
them to the OGM and General Directorate of Combatting Desertification and
Erosion Control (ÇEM, former AGM) work, previous project sites (e.g. Eastern
Anatolia Watershed Rehabilitation Project), and challenge their preconceived
ideas and predispositions about interventions foreseen under the Project. These
visits will also help the participating villagers to: i) interact with other villagers
who have experience regarding natural resource and watershed rehabilitation
activities, ii) open up themselves to explore different ideas and broaden their
understanding, and iii) develop a vision for their village and surrounding. Funds
are allocated for 50 visits over the life of the Project covering various expenses.
Procurement method is LC.
97. Vehicles/Equipment and Goods: All items in this Category will be will be procured
through LS:
Vehicle rental: Provisions are made to rent vehicles for: i) PPT‟s (4x4): for
each of the teams 200 days/year including driver, maintenance, fuel and
insurance, and ii) villagers‟ exposure visits (minibus): for groups of villagers
to make around 50 visits to various sites,
30
Office equipment: Provisions are made for office equipment for three PPTs,
OBM and OIMs: 3 computers for each PPT, one printer/province and one
photocopier/province and 3 handheld GPS/PPT.
Software: GIS software and GIS maps
98. Cost Sharing: There is no cost sharing foreseen for the Component, all will be
financed 100% by IFAD Loan and IFAD Grant (technical assistance, studies and planning and
technical subjects identified, for PPT, OGM and Regional OGM staff, annually). The others will
be financed 100% by the IFAD Loan.
99. Bidding documents: All bidding documents for the procurement of goods, works and
services shall be prepared by the procuring entity (relevant Procurement Officers) with the
participation of the OBM and/or OU/FOU specialist(s) as required. At the provincial level, the
responsible team of the line agencies would prepare the procurement documents under the
supervision of central management of the relevant agencies and OU. All the procurement
documents would be cleared by the OU before any action is taken.
32
100. The primary objective of the Component 2 is to invest in activities as identified in the
MCPs to protect and rehabilitate degraded areas in gazetted forest land including rangelands
to stem further degradation and erosion.
101. It should be noted that: i) this Component comprises interventions on public land
while interventions under Component 3 are for private land and ii) Component 2 and 3 are
interlinked. Interventions under Component 2 have impact on the activities under
Component 3 by protecting agricultural land from flooding and landslides, improving water
supply and quality for irrigation, contributing to livestock productivity by improving
vegetative cover and providing small but useful structures in grazing lands thus increasing
drinking water availability. Component 2 also effects livelihood of the villages by providing
temporary employment, reducing flood and land slide risks, and allowing communities to
benefit from fruit bearing trees and plant material obtained from oak coppice rehabilitation
and support beekeeping by improving the flora.
102. The component includes investments for land, soil, vegetation and water:
i) soil conservation investments,
ii) rehabilitation of degraded forests,
iii) rehabilitation and sustainable management of degraded grazing land/rangelands,
103. To protect the areas where the above investments are made, protection of these is
important. It was estimated that about 10% of the total area rehabilitated fencing will be
needed. Provisions are made to finance fencing under the Component.
a. Introduction
33
104. Soil conservation investments: The purpose of the investment is to put in place
measures to conserve soils and vegetation in micro-catchments and to introduce mechanical
and biological approaches toward catchment conservation, management and rehabilitation of
forestry land.
105. The investment will include the following interventions: i) erosion control and
slope stabilization measures such as gully rehabilitation; ii) shallow/manual terracing for
improved moisture retention; iii) plantations of forest and fruit-bearing tree species as
agreed with communities; and iv) closure of specific and agreed areas to grazing
investments for land, soil, vegetation and water. MC, one or more of these interventions
could be selected based on the: i) magnitude of the erosion; ii) soil type; iii) percentage of
slope; iv) type of vegetation cover; v) rainfall characteristics, vi) land use, and foremost,
vii) the agreement of the resident communities.
b. Investment Menu
34
106. Rehabilitation of the degraded forests: this will include: i) oak coppice
rehabilitation, and ii) tree planting (afforestation) on the degraded forestland. The
rehabilitated areas will be closed off to grazing by fencing for a period of time (2 3 years) to
35
enable the seedlings to grow to above a height that could be damaged/eaten by the small
ruminants.
Oak coppice rehabilitation: In the mountains of the Project are, particularly in
Bingöl there are oak coppices/forests. The prominent oak species are: i) Quercus
infectoria Olivier, ii) Q. ithaburensis Decne. subsp. macrolepis (Kotschy) Hedge,
iii) Q. brantii Lindley, Q. libani A. Rich., iv) Q. robur subsp. pedunculiflora (K.
Koch) Menitsky and v)Q. petraea Lieble. However, many parts of these oak
forests are degraded and unproductive due to illegal grazing, illegal using of
leaves and branches for livestock feeding (mainly for goats) and illegal cutting for
firewood. These degraded forests can be transformed to productive forests by
rehabilitation. By taking the actual condition of the stands into consideration one
or more of the improvement techniques will be applied including i) throat cutting
of the stem to enable the tree to regenerate, ii) supplemental seeding with
acorns, and iii) supplemental planting with oak seedlings.
36
Tree planting on degraded forestland: forest degradation in the Project area is
the result of overutilization, unsustainable forest management, the socio-
economic problems of local forest dwellers, ownership and land tenure problems,
converting forest land to agriculture. To restore these areas, afforestation will be
undertaken and the species will be selected based on various factors including: i)
soil type and depth; ii) type of bedrock; iii) climatic conditions; degree of
erosion; and v) local preferences.
107. Rehabilitation of degraded grazing land: will be undertaken to reduce grazing
pressure on forest rangelands/ grazing land and improve the carrying capacity of the
degraded rangelands. This will be achieved by: i) closing the area, and ii) promoting
rotational grazing.
closure of the area: this will be achieved by fencing the area to grazing for a
period of time in order to increase the carrying capacity in terms of both
biomass and botanical composition. Forage crop seeds will be provided to
livestock owners on cost sharing basis to be used in the agricultural land
(under Component 3) to compensate temporary closure of the rangelands.
helping the users to adopt rotational grazing as a routine practice through
providing training and demonstration for shepherds and livestock owners.
108. Investments in rangeland infrastructure: The Component will also finance
investments in rangeland infrastructure to ensure the participation of the livestock owners
and also to increase the livestock productivity per animal. These investments will include: i)
livestock drinking water structures; ii) shades and scratch posts, and iii) simple shelters in
the grazing land.
Scratch posts: One or two will be installed in the grazing land per 50 ha.
37
Simple shelters/pens: Provisions are made to construct simple
shelters/pens in the rangeland for protection of shepherds and the
livestock against theft, negative weather conditions and wild animals.
There will be one shelter per 50ha. These structures will be open to
communal use in the MC.
109. Livestock drinking water structures will provide access to water in grazing lands and
so reduce animal travelling distances for drinking. The benefits derived are two-fold: i)
reduction in the risk of spreading animal diseases, and ii) increased productivity per animal.
38
The structures will be: i) water troughs and ii) watering ponds. It should be noted emphasis
will be on the water troughs. Only a few watering ponds will be constructed
Water troughs: these will be poured-in-place concrete (mostly) or prefabricated
sheet metal with dimensions of about 10 x 1 x 0.6 meters and will be installed
strategically over the rangeland as one per 300 ha.
The construction of livestock watering ponds in rangelands for direct use during
the summer grazing period will be supported in villages where livestock
production is the main activity and where water sources are scarce but site
conditions are favorable to collect surface runoff.
Typical ponds will be of the watershed (or embankment) type with a maximum
total embankment height of five meters and riprap protection on the upstream
slope. Ponds should be fenced and include a control structure with a drainpipe
through the embankment used to supply water to a set of troughs in order to
avoid direct livestock access. Investments in ponds should include formal
arrangements for communal use of the facility. The detailed design may also
include catchment afforestation measures to reduce siltation. A geologic note, an
environmental impact assessment note and a brief hydrological study assessing
the recharge regime will also be part of the feasibility analysis. All investments in
livestock watering facilities should include a basic financial analysis relating
investment cost to the expected increase in production and revenues.
39
110. Sediment measurement stations: Erosion will be measured in all 25 MCs through in
situ erosion measurement and sediment capture and will be combined with GPS marked
photos in predestined locations of the catchment area. This will serve the dual purpose of a)
obtaining data, which can document impact of NR rehabilitating activities directly in the MC
areas and b) create awareness by involving communities in the installation, management and
data collection. The stations will be installed at each MC during the MC planning phase.
111. The OIMs in Elazığ, Bingöl and Muş will be responsible for the implementation of the
component and will report to the OBM. The forestry-related activities, including those that
relate to the rangeland investments under this component will be implemented according to
the MC plans that have been finalized under Component 1.
112. Civil works: The works to be financed under the Component include: i) forestry work,
and ii) livestock drinking water structures.
Forestry work: this includes but not limited to the following: afforestation of
degraded forests (including terracing, planting trees, pocket terraces around
the trees planted), protection and improvement of degraded soils, coppice
rehabilitation (including regeneration cutting, supplemental seeding,
supplemental planting. These contracts would be procured through NCB/LS in
accordance with the procedures acceptable to IFAD. The OIM will hire the
service providers, e.g. the village administrations or local contractors, for the
rehabilitation and afforestation activities or other small civil works. All work
related to rehabilitation, afforestation and the maintenance and guarding of
same is expected to be undertaken by the resident villagers (hired under the
village administration or individually) in the respective MCs. In case sufficient
labor is not available, the OIM will contract the work to eligible service
providers that will be competitively recruited as described in the PIM.
Livestock drinking water structures: The civil works for livestock drinking
water and ancillary facilities will be competitively contracted (LS) at the
provincial level by the OIMs. Provincial Project Teams (PPTs) will be
responsible for the monitoring of these works and the reporting to the
Provincial Focal Points (PFPs). The OIM/OBM will make arrangements with the
relevant Governors‟ office and Government agencies in the provinces, e.g.
Agricultural Department (PDA) to receive technical support on an “as-needed-
and as-agreed” basis.
113. Vehicles/Equipment/Materials/Goods: for the component there are 2 items in this
category: i) seeds and seedlings, and sediment measurement equipment.
c. Implementation Arrangements and Procurement
40
Seeds and seedlings: As standard OGM practice to ensure steady and risk-
free supply, the required seedlings will be bought from nurseries that are
capable of producing such at prices that are annually determined by OGM.
The suppliers include state owned nurseries in Elazığ and Muş. Other public
nurseries and private producers that are capable of supplying the desired
seedlings may be contracted in accordance with the needs determined in the
MC plans with respect to timing, quantity and quality,
Sediment measurement equipment: Provisions are made under Equipment
and Goods category for the procurement of 25 equipment kit through LS.
114. Bidding documents: All bidding documents for the procurement of goods, works and
services shall be prepared by the procuring entity (relevant procurement officer) with the
participation of the OBM and/or OU/FOU specialist(s) as required. At the provincial level, the
responsible team of the line agencies would prepare the procurement documents under the
supervision of central management of the relevant agencies and OU. All the procurement
documents would be cleared by the OU before any action is taken.
115. Cost sharing: the following investments will be financed 95% by IFAD and 5% by the
Government: i) soil conservation investments and ii) rehabilitation of degraded forests. The
investments for the rehabilitation of degraded grazing lands, livestock drinking water
structures and simple shelters will be financed 95% by IFAD and 5% by the beneficiaries. If
and when needed, guard could be hired per MC. The cost will be cover totally, by the
Government. The equipment for sediment measurement will be financed 100% by the Loan.
42
116. The primary objective of the Component 3 is to improve livelihood in MC villages
through support to small-scale crop and livestock production on private land and improve
living conditions in settlement areas.
117. It should be noted that Component 2 and 3 are interlinked. Interventions under
Component 2 have impact on the activities under Component 3 by protecting agricultural land
from flooding and landslides, improving water supply and quality for irrigation, contributing to
livestock productivity by improving vegetative cover and providing small but useful structures
in grazing lands thus increasing drinking water availability. Component 2 also effects
livelihood of the villages by providing temporary employment, reducing flood and land slide
risks, and allowing communities to benefit from fruit bearing trees and plant material
obtained from oak coppice rehabilitation and support beekeeping by improving the flora.
118. Investments under Component 3 address both poverty (directly) and natural
resource degradation (both directly and indirectly).
119. Impact on poverty: some activities reduce poverty directly by increasing the
household income and others by decreasing the expenditures:
Activities increasing income: Crop production: wheat/barley and forage crop
production with some degree of mechanization on relatively larger plots will have
direct effect on income as a result of improvements in crop yields and total
production. Vegetable and fruit production will also provide income but from
smaller plots by utilizing family labor where income per unit of cultivated area will
be higher. Investments for small-scale irrigation (water storage ponds,
rehabilitation of earth canals and on-farm drip irrigation) will directly improve
earning capacity of the households. All of these will also have positive impact on
the nutritional status of families. Contracted seedling production will not only
generate income but may create models/opportunities for future small-scale
businesses. Livestock production: forage crop production on agricultural land that
integrates crop and livestock production, improvement of livestock stables will
improve the livestock productivity and contribute to the household income.
Activities decreasing expenditures: Investments regarding alternative energy
resources comprising solar water heaters, energy efficient stoves and house
insulation, the effects of which are compounded when used in combination.
a. Introduction
b. Impacts /Linkages
43
120. Impact on natural resource degradation: the impact is both direct and indirect:
Direct impacts are derived form: i) improvements of wheat and barley yield
(correcting land use by freeing slopes from annual production that cause surface
runoff and loss of top soil and fertility, moving away from monoculture that
continuously depletes soil moisture and nutrients from the same depth, results in
building up of certain weeds, insects and diseases), ii) fallow reduction
(protecting land from wind and water erosion for about 12 months by creating
vegetation cover), iii) expanding forage crop production with nitrogen fixating
leguminous crops (increasing soil organic matter content, improving soil strength
by increased aggregate stability and increasing water retention capacity); iv)
establishment of fruit orchards, if done particularly on slopes replacing annual
cropping mainly wheat (stabilizing slopes and reducing surface runoff), v)
improving small-scale irrigation (improving water use efficiency through reducing
conveyance losses, adopting water efficient methods like drip irrigation), vi)
contracted seedling production (establishing good ground cover reducing erosion,
and by steady supply of seedlings enabling successful afforestation), vii)
alternative energy sources (reducing fuel wood consumption resulting in
improved land cover). For all crop production, soil tillage parallel to contours will
be encouraged. This will stop creation of small furrows on the slopes that cause
significant topsoil, soil fertility loss and lead to gullying.
Indirect impacts are created by: i) expanding forage crop production (reducing
pressure on forest land and grazing land); ii) leguminous forage production
(increasing water supply by increasing water retention in soil, improving soil
fertility); iii) establishing good ground cover with cereals, forage crops,
vegetables and fruit trees (improving water quality by reducing sedimentation).
121. The investment menu for private land will include: i) improvement of the
productivity of wheat and barley; ii) forage crop production; iii) improvement of livestock
stables; iv) orchard establishment; v) improving vegetable production; vi) small-scale
irrigation; vii) contracted seedling production; and viii) promoting energy saving
technologies.
122. The menu offered will vary with agro-ecological and socioeconomic conditions in each
village as well as farmers‟ resources and needs. The approach will be flexible and the scale,
scope, timing/phasing and associated costs for all activities will be detailed in the agricultural
sub plans made in the negotiated MCPs.
123. Improving wheat and barley productivity: Poor crop productivity and low profitability
will be addressed by assisting smallholders to adopt better agronomic practices under
prevailing agro-ecological conditions to match cropping patterns to the productive and
c. Investment Menu
44
physical limitations of agricultural lands. This will help to reduce soil erosion and associated
soil fertility loss in fragile land where annual cropping has been practiced for years. The
agronomic practices will include improved soil cultivation and seedbed preparation (on
contour for erosion prevention), improved timing of planting, and quality seeds (certified) of
higher yielding varieties resulting in production of satisfactory grain yields, and quality hay
and feed grains. Yield improvement will reduce the need for additional land and/or number of
plots to be dedicated to wheat and barley enabling farmers to allocate more land for forage
crops. The component will introduce nitrogen fixating annual forage crop (Hungarian vetch)
into the existing crop rotation (fallow-wheat rotation or wheat monoculture) that use the
same piece of land and available rainfall more efficiently and effectively that support livestock
production but also increase grain yields due to improved soil fertility.
124. Expanding area under forage crops: forage production will be encouraged in the MC
villages under both rainfed and irrigated conditions will be supported. For rainfed conditions,
winter vetch (Hungarian vetch) or spring vetch by replacing fallow that leaves land idle and
unprotected (exposed to water and wind erosion) for about 12 months. Sainfoin (a perennial
forage crop, korunga) will be introduced to the plots on slopes with effective erosion control
measures to avoid the annual disturbance (soil tillage for annual grain production) of the
earth that increases soil and land degradation. In areas of higher annual precipitation (about
750-800 mm), silage maize will be promoted. For irrigated conditions, alfalfa and silage
maize will be priority crops particularly for villages where dairy cattle production is gradually
developing.
125. Improving of livestock stable conditions: this will address one of the major issues in
livestock production (sheep and cattle) by financing materials and equipment to upgrade
traditional stables. Measures will include ventilation and chimney windbreak, window opening,
lighting, improved feed and watering units, paint/whitewash, and disinfectant and spraying
on a cost-sharing basis. All these will decrease the parasite and disease incidence in the
stables and improve stable/barn hygiene.
45
126. Establishing modern orchards: although the agro-ecological conditions are
appropriate for fruit production in a number of upland villages, there is no orchard
established with appropriate geometry and technique. Individual trees of outdated varieties
are scattered on the farmers‟ fields and backyards and kept poorly. The component will
support investment in small modern orchards for production of soft and stone fruits (e.g.
apple, pear, plum) and nuts (e.g. almond, walnut or chestnut) by providing seedlings.
127. Improving vegetable production: there is a proven demand for fruits and vegetables
in the region. However, poverty, lack of technical information and skills, finance issues, and
outdated varieties and practices limit production. Therefore, production under plastic tunnels
and open fields will be supported in MC villages where climatic conditions are favorable, good
agricultural land is limited and household labor is available. Provisions are made for 500 m2
plastic tunnels, plastic sheets, iron frames, and drip irrigation (drip tube accessories) with
initial skills transfer and advice.
46
128. Small-scale irrigation: Support will be provided for off-farm and on-farm irrigation.
Small-scale off-farm irrigation investments will ensure a reliable supply of water for irrigation
and expand the irrigated area available to a village, if any, by improving irrigation efficiency.
Given the sloped nature of the irrigated areas, drainage is not expected to be an issue
requiring additional investment or to create any negative environmental impact.
129. The investments will include: i) small water storage ponds (off-farm) for multiple
users with established water use rights, and ii) improvement and rehabilitation in the water
conveyance systems (off-farm) by conversion to concrete canals or where feasible to PVC
pipe, and iii) on-farm drip irrigation.
Water storage ponds: these will enable farmers to: i) store water from small
springs/streams (with a discharge less than 15 liters/second) to be used in
periods of water shortage, and ii) engage in production of more profitable
crops. The ponds will be concrete and about 400 m3 in size with requisite
inlet and outlet structures and fittings. In selecting the water source to be
developed, the main criterion in addition to technical feasibility will be the
number of households that will benefit. In the case of civil works for
irrigation, arrangements for in-kind contributions by the beneficiaries will be
negotiated during the preparation of each MC Plan. The remote location of
these investments predicates civil works designs that require minimal use of
heavy machinery. Further guidance regarding the design parameters will be
provided in the PIM.
47
Rehabilitation of the existing irrigation infrastructure will be undertaken by: i)
replacing damaged and poorly functioning parts of existing open canals with
pipes (PVC or glass fiber) and ii) concrete lining of earth canals to reduce
water conveyance losses and modification of the canal profile (trapezoidal
instead of rectangular).
On-farm low pressure drip irrigation: provisions under the Component are
made to support for on-farm low-pressure drip emitters for horticultural and
forage crops complementing and benefitting from off-farm project
investments in water harvesting. A typical installation will include the
rehabilitation of the intake, the construction of a reinforced concrete tank and
the installation of an underground LD/HDPE pipeline (including valve boxes
for air valves, washouts and hydrants). The valve boxes will be made of
steam-cured pre cast units. Due to the harsh weather conditions in the
project area, specific minimum pipe laying depths are required.
48
130. Contracted seedling production. The project will support the establishment of tree
nurseries in the MC villages. The objective is to ensure a steady supply of quality industrial
tree and nutty fruit tree seedlings that are of local provenance for the need of OIMs. There
will be a buy back guarantee by the OGM. For the surplus could be sold to individual farmers,
communal entities (such as village administrations) and commercial entities.
49
131. Promoting energy saving technologies: The activity is designed to reduce the overall
demand for fuel and excessive reliance on fuel wood and to promote the use of affordable
renewable energy sources in the upland villages. The Component will introduce new and
scale-up on existing modalities of energy conservation in order to reduce pressure on the
forests and to improve living conditions of the rural communities. The interventions comprise
mainly solar water heaters, energy efficient stoves, and alternative small-scale energy-saving
technologies including house insulation.
132. Knowledge and skills required for these investments will be provided through: i)
farmer training courses, ii) on-farm demonstrations and iii) farmer exposure visits. Timing of
these is important. Ideally, these should be conducted before the start of the investments.
This will enable the beneficiaries to utilize the investments efficiently and effectively.
d. Knowledge and Skill Development
50
Farmer training courses: these will be conducted to: improve knowledge and
skills of farmers in order to reduce the technology and farm management
gap; ii) to enable them to interact with peers and specialists; iii) stimulate
their thinking, reflecting and connecting ideas, exploring knowledge and
enjoying learning, and iv) challenging their preconceived ideas and
predispositions.
Training courses will be structured to cover both classroom and hands-on
training (in the field). About 300 training courses could be conducted for the
life of the Project. Major topics include livestock husbandry and waste
management, forage and cereal crop production, greenhouse and open field
vegetable production, small scale irrigation and seedling production. Unit cost
(300 USD/course) includes course material and beverages and simple food for
25 participants.
Separate training courses will be provided to women farmers systematically
throughout project implementation. Youth will be given priority in all training
programs. Women will also benefit from farmer exposure visits that will be
organized for couples and youth. Depending on the activities included in the
MC plans, the PPTs analyze the capacity building needs for the implementing
community members and technical assistance.
51
On-farm demonstrations: these will be conducted to: i) kindle interest and
create awareness about behavioral change, ii) enable farmers to observe new
practices in crop and livestock production to reduce the differential between
potential and actual yields by accelerating technology transfer (i.e., to reduce
the technology gap) and helping farmers become better farm managers (i.e.,
to reduce the management gap), iii) actively engage them in the learning
process, iii) motivate them for trying for what they have observed.
Provisions are made to conduct about 300 demonstrations in 25 MCs (3
provinces) in 7 years. Major topics include livestock husbandry and waste
management, forage and cereal crop production, greenhouse and open field
vegetable production, small scale irrigation and seedling production.
Depending on the objective of the demonstration, it is recommended to plan
and design them to: i) show before-and-after, control-versus-test, side-by-
side comparisons; ii) expose farmers to only one or two treatment/practice,
or to whole package of practices, and iii) conduct one-year (e.g. wheat
cultivars, seedbed preparation) or multi-year (e.g. crop rotations, tree crops,
livestock feeding).
52
The number of demonstrations per MC varies from 1 to 3. For example one
concrete manure storage demonstration should be sufficient for one of the
villages in each MC (in total 25) or orchard demonstrations could be 15 in
total (in 15 MCs where the agro-ecological conditions are suitable). Forage
demonstration should be 3/MC while 3 irrigation demonstrations could be
conducted in each MC. Unit cost (500 USD) for each demonstration includes
inputs and cost for agricultural operations.
53
It should be noted that if a demonstration:
o does not reflect technical expertize and discipline,
o is not significantly different from an average farmer field and practice
and is not easily visible among local/traditional practices,
o does not attract the attention of those who pass by the demonstration
field and make them stop and look,
it should be cancelled and the sign has to be removed. There is nothing
harmful for a project than a “bad/failed demonstration”. Guidelines for
successful demonstrations are given in Annex 13.
Farmer exposure visits: these will be organized to help the participating
farmers to: i) interact with better farmers, successful companies; ii) open up
themselves to explore different ideas and broaden their understanding; iv)
develop a vision for their holding and v) sharpen their interest in the Project.
on the average, 3 couples or sister/brother or father/daughter from each MC
village would benefit from these visits. It is important to ensure the
participation of women. Each tour using Project minibus can include 25
couples. It is envisaged that during the life of the Project about 30 tours could
be organized on about 7 different topics (livestock husbandry and waste
management, forage and cereal crop production, greenhouse and open field
vegetable production, small scale irrigation and seedling production). Visits
should target private companies, large farms, leader farmers, other project
activities and interventions. Field days organized by government agencies
and local or regional fairs are good opportunities for the MC communities.
55
• The main principles in preparing and implementing the program will be: i)
spouses or brothers/sisters will participate, ii) the majority of the visits will be daily;
every year only one visit for 2 days will be planned; iii) upon their return to their
villages, the participants will share their experiences in one of the training programs
or in a meeting organized by the VH.
133. The Component will provide opportunities on a cost-sharing basis to raise income of
MC communities reinforcing the adoption of rehabilitation activities undertaken Component 2.
It will be implemented by OGM through contracted multi-disciplinary Provincial Project Teams
(PPTs) comprising a forest engineer, an agronomist and a livestock specialist. OIM will second
a forester to each PTT to be a focal point for the liaison between OIM, PPT and local
communities. The governors‟ offices in the Project provinces will provide necessary
coordination and linkages between the Project and the resources of Provincial Directorates of
Agriculture (PDAs) for extension and training support.
134. Provisions are made for training of the three PPTs on technical topics as well as in
poverty targeting and gender issues at the beginning of their work and for refresher training
in third and fifth year of implementation. Both PPTs and OGM staff will participate in training
in participatory methods and gender/poverty sensitization.
135. Civil works: this Category includes all small scale irrigation investments.
Procurement method is LS.
136. Training/ Technical Assistance/Workshops: demonstration, farmer training and
farmer exposure visits are under this Category. Provisions are made to finance the related
expenditures: agricultural operations and inputs for demonstrations, organizational expenses,
audio-visual and printed material for farmer training and exposure visits, vehicle rental, and
meals. Procurement method is LS.
137. Vehicle/Equipment/Materials/Goods: Livestock shelter rehabilitation, and energy
saving technologies are under this category and the procurement method is Community
Procurement (CP). Seeds and seedlings needed for productivity and profitability improvement
for wheat, barley, rainfed and irrigated forages, vegetable and fruit production is covered
under this category and these inputs will be procured through LS.
138. Bidding documents: All bidding documents for the procurement of goods, works and
services shall be prepared by the procuring entity (relevant procurement officer) with the
participation of the OBM and/or COU/FOU specialist(s) as required. At the provincial level, the
responsible team of the line agencies would prepare the procurement documents under the
Implementation and Procurement Arrangements
56
supervision of central management of the relevant agencies and OU. All the procurement
documents would be cleared by the OU before any action is taken.
139. Cost sharing: All farmer demonstrations, training and exposure visits will be financed
100% by IFAD Loan. Irrigation ponds and rehabilitation of existing irrigation infrastructure
will be financed 95% by IFAD and 5% by the beneficiaries. The following investments
(including provision of seeds and seedlings) that will be made for: i) improvement of wheat
and barley production; ii) improvement of livestock production; iii) improvement of
horticultural production and iv) on-farm drip irrigation will be financed 70% by IFAD and 30%
by the Government.
58
140. As part of its responsibility for implementing the project, the MARA/TUGEM is
required to report periodically on project progress in order to satisfy IFAD that the project is
being carried out properly and is likely to achieve the objectives of the loan. Two types of
reporting are required: i) Semi-annual Progress Reports, and ii) Annual Performance Reports.
These reports will be in English with Turkish translations if and when required by
OGM/CEM/MFWA. The PMU will maintain a website where all project related reports are
disclosed for interested readers.
141. The purposes of the Progress Reports are: i) to provide essential information on the
physical and financial progress of Project activities, and ii) regular assessment of Project
impact. Such reports would be prepared semi-annually and annually. These reports provide
information on the progress in implementation, spending and achievements. A brief summary
of activities undertaken and results achieved in each MC will also be provided. The progress
reports include regular information on Project outputs broken down by province and to the
extent possible, outcomes, and where appropriate reference to the baseline situation.
142. Semi-annual Progress Reports: Twice a year (every six months), the COU will submit
a progress report to OGM and IFAD, no later than three months after the end of each six-
month period during the project implementation period. The exact dates for submission of the
progress reports will be announced during the Project Start-up Workshop. The COU will
develop quarterly financial and physical progress reporting formats for service providers and
such conditions will be incorporated into the contracts to be engaged with these service
providers. Based on these reports prepared by service providers, COU will issue a
consolidated report on all service providers and include these in the Semi-annual Reports.
143. Annual Progress Report: One of the semi-annual reports will be the Annual
Performance Report that will have broader coverage and sent to IFAD. It will contain
summarized information on all aspects of the Project implementation by province. The report
will allow supervision missions and evaluators to be fully informed of Project activities,
achievements and constraints, clearly indicating planned and actual targets for key indicators
agreed between the Government, IFAD and the OGM. Paper copies will be also sent to the
Treasury, Ministry of Development (MOD) and Provincial Governorates.
144. The format is provided in Annex 15. However, it should be noted that these reports
should address the following at a minimum:
Introduction
Progress Reporting
59
quantitative and qualitative progress made in implementing and achieving
project objectives, including detailed financial and procurement data as well
as staffing,
analysis regarding community participation, transparency in selecting
districts, villages, smallholders and infrastructure investments,
sustainability of the investments,
effect of interventions on rural environment
problems encountered during the reporting period,
gender mainstreaming and bottlenecks experienced,
steps/actions taken or proposed to mitigate or solve these problems,
the status of problems that have been raised in IFAD Supervision reports,
the proposed program of activities and the progress expected during the
following reporting period
145. The monitoring and evaluation (M&E) function will be guided by the Project‟s logical
framework and integrated in the Project‟s reporting to assess impact of implemented
activities. Information from a variety of sources including the socio-economic and physical
baselines as derived from the MCPs, will form the basis for an integrated management
information system (MIS) focusing on continued analysis of, rather than generation of,
information. The analysis of Project results will be used to manage Project activities so as to
be more responsive to the beneficiaries‟ needs and priorities vis-à-vis the Project‟s objectives,
which in turn will lead to enhanced achievement of impact.
146. The Project M&E system will be based on existing structures for reporting of primary
or 1st level results (e.g. ha of land afforested, ha of land rehabilitated, grazing land
rehabilitated, livestock drinking water points established) and on activities directly targeting
improved livelihoods in the villages (farmers trained in improved livestock production
practices, crop and vegetable production, etc.). To that end, the Project M&E function will
focus on analyzing key results indicators, rather than on the collection of data, although data
collection will serve as an input to the M&E. All Project stakeholders, (including national,
regional and provincial OGM staff and communities) have a role in monitoring and/or
assessing Project implementation. Provision has been made in the Project design both to
assess the impact on villagers‟ livelihoods and to measure efficiency and impact of erosion
mitigation investments. The Project area will be visited regularly by OBM and Ankara based
OGM staff in order to provide them with first hand opportunities to interact with villagers and
assess progress.
Monitoring and Evaluation
60
147. Staff responsibility for M&E: The Project Manager (PM) and the Field Project
Manager (FPM) will be responsible for ensuring that a responsive M&E system is established
and regular monitoring and progress reporting is in place for Project activities. The M&E
Specialist of the COU together with the M&E officer of the FOU will have day-to-day
responsibility for collecting and analyzing data and preparing, as required but at minimum
quarterly reports, on progress and results achieved and implementation issues arising from
monitoring activities. These reports will be directed at Project management, but may be
shared with the Project Steering Committee. Within the COU, provision for supplementary
studies has been made, the findings of which will feed into M&E arrangements over the
course of implementation. Provision has also made for computer training of staff to enhance
their skills in using computer application to support analysis.
148. The relationships among program entities are set out in Figure 3, which depicts the
linkages within the proposed information system.
Figure 3: Measuring Results and Impact - Information and Feedback Flows
149. The M&E system comprises both performance and impact monitoring. All M&E data
will be disaggregated by gender and province. The Logical Framework indicators combined
with a selection of indicators from the MCPs form the basis of the monitoring system. During
the start-up workshops, one in Ankara and one in each of the three provinces, further
recommendations will be made on specific indicators and Means of Verification (MoVs). The
61
methodology that will used to analyze such indicators and MoVs will also include information
regarding their source, baseline values and periodicity of reporting. In large part, baseline
values for each MC will be defined in the MCPs. The existing GIS system at OGM will be
utilized as a mainframe for visualizing baseline and monitoring data, which will detail the
extent of environmental degradation at baseline. OGM has in-house capacity to measure
erosion following internationally recognized methods and this experience will be made
operational in the erosion control monitoring.
150. Micro-catchment communities will participate in the monitoring of surface and
rill/gully erosion through the set-up of simple field trials consisting of rectangular erosion
plots on level land, and using metal sticks to measure the development of rill and gullies.
Forestry Research Institute in Elazığ can provide assistance for this. Participatory monitoring
will also be applied in the collection of data from sediment traps at the waterways draining
run-off areas within and at the border of the micro catchment. Participatory monitoring can
be very cost effective and at the same time raise community awareness.
151. The participatory monitoring may be supplemented by data collected at larger
watershed area, possible at provincial level, and at the macro watershed/basin level. The
macro level data is routinely collected by the hydro electrical dam authorities, and will serve
as a reference to measure the data collected at micro-catchment and possible watershed
level.
152. At the annual Planning Workshops, findings from M&E, various studies, and field
trials will guide decisions on the future scope and course of the Project. The workshops will be
a forum for revising elements of the Project‟s logical framework such as indicators and MoVs,
and to discuss implications of the results achieved in the previous year(s) with respect to set
milestones and the Project‟s objective and long-term goal. This analysis will provide the basis
to: (i) Review the overall implementation progress and poverty focus; (ii) identify successes
and means for replication; and (iii) analyze problems encountered in the course of
implementation and agree on corrective actions.
153. OGM already possesses a robust, computerized system for tracking progress in terms
of physical works. Data on expenditures and activities carried out are entered into this
system at provincial level. These data form the backbone of the M&E system, and to the
extent possible be supplemented with existing government data as well as data from erosion
monitoring and social surveys carried out during the Project‟s implementation. An early task
of the M&E specialist will be to identify data sources and periodicity of reporting for the
agreed indicators.
154. Contracts with service providers will clearly stipulate the results to be achieved,
whether in terms of land and water improvements, agricultural production or with respect to
people trained. Final payment to service providers should be contingent both on acceptance
of the works or services rendered and on receipt of a report quantifying the results achieved.
Such reports will be made public in the villages and certified by the village headmen. Data on
training will be disaggregated by gender, age group and type of training provided. If
information from service providers cannot be accommodated in the existing computer
system, the data will be stored in Excel or similar commercial computer application.
62
155. This review will take place after the first 18 months of implementation to assess the
(i) effectiveness of institutional modalities; (ii) planning and implementation interactions; and
(iii) monitoring system. A Mid-Term Review is planned to be conducted at the end of three
years of implementation. It will cover: (i) an assessment of achievement of Project outcomes,
physical and financial progress as measured against design and the AWPBs; (ii) performance
and management of contracted implementing partners and an assessment of the efficacy of
technical assistance and training programs; and (iii) institutional implications, in particular
related to sustainability of the Project achievements and potential for scaling up or replicating
the Project approach. These Reviews‟ findings will inform decision-making on possible
adjustments to the content, targeting and financing of the Program components.
156. In the final year of implementation, as part of the preparation of the IFAD-required
Project Completion Report (PCR), M&E data collected during implementation will form the
basis for an overall assessment of Project achievements, particularly in terms of documented
improvements to the natural resource base as well as changes in the livelihoods of villagers
living in the targeted MC areas. The PCR process will include a stakeholder workshop in each
province to provide an opportunity for stakeholders themselves to evaluate performance, to
promote accountability, to identify and elaborate upon factors that will improve sustainability,
and to lay out key successes and shortcomings. Equal representation of different interest
groups should be promoted and female representation in the stakeholder workshop is a must.
If required, female stakeholders may have a distinct evaluation process.
157. The assessment will be based on monitoring data including in annual reporting.
Monitoring data will be compared with data contained in the MTPs on “before project”
erosion level and living conditions. An impact study in selected villages from previous years‟
implementation will be carried out at the last year of the Project to allow for a “after
project” comparison. Only villages where Project activities had commenced by PY 4 will be
used for comparative purposes. As proxy, the “after project impact review” will cover at least
one MC not supported by the Project in each of the three provinces.
158. The main categories of information to be collected during the planning phase and
used to assess Project impact are detailed in the MC Plan guidelines. These include but are
not be limited to:
a. Socio-economic characteristics: number of households in the village,
composition of the households, employment and migration data, household
income and expenditure patterns (in particular for food and energy);
Inception Review
Assessment of Project’s Impact
63
b. Physical characteristics: location of village (longitude and latitude), distance
from and access to provincial center, housing and roofing material, sanitation
and drinking water
c. Agriculture and livestock: Number of livestock owned by villagers (type and
average per household), size of grazing/rangeland, number of functioning
livestock drinking points and shade structures, livestock productivity, rainfed
area (by crop), irrigated area (by crop), size of household plots (irrigated and
rainfed), crop yields; and
d. Natural resources: state of forested area, eroded land, grazing/rangeland.
GIS maps will be prepared at completion for the selected MC and compared to
those prepared during the planning phase. These provide evidence of
improvements to natural resources. As a complimentary modality, photos
with marked with date/time and GPS coordinates should be taken at specified
time intervals to accompany written information and linked into the GIS
system.
19. Provisions are made for the use of innovative monitoring measures such as cameras
with integrated GPS function possible combined with aerial photos, which can be used to
detect physical changes in the MC, landslides, gully formation and vegetative cover. Photos
should be taken in few locations with characteristics typical for the MC. Photos should as far
as possible be taken at the same time of the year.
65
159. Although the Borrower is responsible for project and program implementation,
ensuring an efficient implementation, resolving implementation problems and obstacles as
they arise and enhancing the achievement of development objectives, impact and
sustainability is the shared concern of all stakeholders. Supervision and implementation
support is IFAD‟s contribution to this effort, with the explicit objective of building the capacity
of national implementation partners and policy makers. Supervision during project
implementation, despite its importance, is only one of many factors that determine project
performance. These factors include: (i) quality of the project design and preparation; (ii)
quality of project management; (iii) the political and economic environment; (iv) commitment
and ownership by government, co-financiers and implementation agencies; and, (v) quality
and timing of supervision inputs.
160. Objective of the Supervision Mission: IFAD puts together a team of experts
(Supervision Mission) and send them to the borrowing country at least once a year or more
frequently- if considered desirable in order to: i) ascertain whether satisfactory progress is
being made, ii) ensure the early identification of problems requiring remedial action, and iii)
find out whether the project is implemented with the interests and concerns of its target
groups as a primary focus of attention. Mission staffing takes into account the nature of the
project and any special expertise that may be needed to address specific problems.
161. Supervision Mission Terms of Reference (TOR): Before the departure of the
mission from Rome where the IFAD Headquarters is, the management sends a Supervision
Mission TOR to the implementing agency (MFWA). The TOR reflects the principal objective of
the mission i.e. to ensure that the project‟s development objectives are being met, and to
satisfy IFAD‟s fiduciary responsibilities. The timing of the missions are planned and agreed in
advance with the implementing agencies.
162. A typical TOR includes the following:
• Introduction: a summary of the Project to be supervised (effectiveness
and closing date, loan size, project components, major developments,
issues)
• Aspects of the project implementation that will be supervised:
1. overall performance
2. financial management and procurement
3. management and coordination
4. activities and output under each component
5. component‟s compliance with the AWPB in terms of targeting
6. project‟s performance with respect to gender mainstreaming
7. actions taken on the recommendations of the previous
Supervision Mission
66
• Mission composition: a list of members and their area of expertise and
their individual responsibilities for the supervision
• Itinerary and program
163. Field program: As indicated in the TOR, the supervision missions travel to the project
provinces at the dates agreed with main implementation agency (OGM) to undertake field
visits to the project area to spot check and verify reported physical progress, interact with
the beneficiaries (men and women) local technical staff, and local administrators (if
necessary) to ascertain whether the implementation progresses as planned and whether
there are bottlenecks and issues that require remedial action. The COU in coordination with
FOU is expected to prepare a detailed visit program (with timing) for the mission. A sample
program is presented in Table 6.
Table 6. An Example for a Supervision Mission Itinerary and Program
MISSION ITINENARY and PROGRAM
164. As indicated in the sample program in Table 7, the provincial visit program should
include but not limited to the following:
• Visiting Director of the OBM
• Briefing by the Project Staff
• Visiting project office of the FOU
• Visiting Provincial Forestry Directorates (selected ones or all) in Project
provinces
• Visiting project villages/sites to see the implementation on the ground
165. Visit to Director and Deputy Director of OBM: The Mission visits the Regional
Director and his deputy (Field Project Manager) and DPM at OBM in Elazığ to gets views about
IFAD MISSION PROGRAM
15 May, Mon Mission‟s arrival in Elazığ
16 May, Tue Meetings at OBM with the relevant project staff
16-24 May Field work in Project Provinces A, B, and C
24 May, Thu Travel from Project Province C to Ankara
28 May, Mon Wrap-up Meeting at TÜGEM
29 May, Tue Departure for Rome
b. Field Visit
67
the project, implementation progress, and the issues. The Regional Director may not
accompany the mission to the project sites due his workload and/or earlier commitments;
therefore this visit is an opportunity for him to convey his views directly to the mission and
respond to their questions.
166. Briefing by the Project Staff: The purpose is to give an overall picture to the
Mission about the implementation of the project by the field agencies. A Power Point
Presentation should be prepared with pictures and figures indicating the progress made.
Therefore, it is important to develop a photo archive by taking pictures in the project sites to
indicate the situation before, during and after implementation including physical work and
beneficiaries. All the Project staff should attend the meeting and be introduced to the
mission. This will not only help the mission to understand who is who but also help to develop
the team sprit among the project staff.
167. It should be noted that the duration of the meeting should not be longer than an
hour including the translation of the presentation by the translator accompanying the mission
and a short question/answer session. More information (figures, charts, pictures etc.) could
be presented to the mission members through proving briefing files prepared in advance.
Table7. Sample provincial visit program for IFAD Supervision Mission
Presentation to the Mission
168. A suggested outline for the presentation includes the following:
• Present a map indicating the areas (districts, MC boundaries and MC
villages) where the project components are being implemented.
• For each component indicate the work done by providing pictures,
tables/charts about the scope, size and cost, and resource allocation.
Progress should indicate the number of beneficiaries and the level of their
participation by emphasizing gender equity/gender mainstreaming. Each
Date Time Activity/program
Oct 17, 2013
9:00-10:00 Visit to OBM
10:00-11:00 Meeting at the FOU Office (Presentation)
12:00-13:00 Lunch break
13:00-17:00 Visit to a project site, to see activities and
meeting with beneficiaries
Oct 17, 2013
8:00-14:00 Drive to project sites to see activities, have a
coffee shop meeting with the villagers
14:00-15:00 Drive back to the provincial center
15:00-16:00 Evaluation meeting at the PDA
16:00 Departure for the second project province
68
data should be presented as disaggregated by gender as much as
possible,
• Highlight actual and potential/emerging problems and constraints and
suggest solutions to improve project progress and impact
• List next implementation steps
169. In the FOU Meeting, after the presentation, the mission should be given information
about the planned field visit program in that province. A short presentation should be made
on a map where the stops are marked in the MCs and the purpose of that particular visit
should be explained. The program should be finalized by incorporating the topics/sites that
the mission members want to include or excluding those that are not in the priority of the
mission.
170. FOU Office: The purpose of the visit is to see the office setting, working facilities
and if desirable, to spot check filing and archiving and interact with the staff.
171. MC and Village visits: the FOU together with the PPTs should organize a meeting
with the Project staff before the arrival of the mission and to make plans for village and site
visits to ensure that the mission members use their time in the field efficiently and effectively
to measure the progress. The planners should avoid repetition of the project activities in the
program unless there is a special reason to visit the same intervention in a different site.
69
172. The field program should be prepared in a such a way that missions should be given
opportunity to interact with individual beneficiaries (interviews) and/or with groups of
villagers (focus group meetings) and see physical progress such as forests, rangelands,
agricultural fields, barns, equipment, irrigation infrastructure etc. It should be noted that
although information is given by the technical staff, the mission need to discuss directly with
project beneficiaries (sometimes also with non-beneficiaries) their perception of the Project,
the level of their participation and fairness in benefit/resource allocation, actively seek their
opinion on improving project performance. For this purpose, the beneficiaries should be
encouraged to speak freely.
173. IFAD‟s Targeting Policy identifies women as a major cross-cutting target group, and
attention to gender differences as a key requirement. The supervision reports that would be
prepared after the country visit are required to provide information on gender-differentiated
participation in and benefits from the project. Therefore, the missions have to review project
performance in terms of gender-equality/gender mainstreaming and collect sex-
disaggregated information on project participants, beneficiaries and staff. In preparing the
field visit programs these requirements should be taken into consideration by allocating
adequate time to meet with women beneficiaries. Logistical arrangements (separate meeting
places with women groups or household visits) should also be completed in advance.
70
174. The distances between stops and meeting durations should be calculated in advance
to ensure that adequate time is allocated in the program to meet the mission‟s information
needs are met satisfactorily. Informing the relevant stakeholders for each stop/site in
advance and make them ready to meet with the mission, ensuring the availability of the
vehicles and drivers, and other logistical arrangements contribute to the success of the field
visit.
175. It should be noted that it is important for the missions to leave the provinces with
actual/correct/unbiased information about the implementation. Only showing
positive/successful examples mislead the missions and give distorted impression. Discussing
actual and potential/emerging problems and constraints and suggest solutions will create
opportunity to improve project progress and impact, and make the life easier for the
implementers and contribute to their successful performance.
176. The Supervision Missions allocate some of their time to meet with implementing
Ministry and Treasury officials in Ankara. Based on their TOR, at the Ministry they discuss
implementation progress and issues and agree on actions to be taken, review documents and
collect necessary information for their Aide-Memoire (Mission Supervision Note) and
Supervision Report. The supervision missions begin and end with joint meetings between the
mission and the senior government officials of the department or agency charged with overall
responsibility for project implementation, at which the mission objectives and findings
(respectively) are discussed. The mission will have a “wrap-up meeting” with OGM and AGM
at MOFWA and review/discuss the Mission‟s Aide Memoire.
2. Aide-Memoire: The mission prepares an Aide-Memoire summarizing the findings of
the mission and discusses this in the wrap-up meeting. It itemizes those issues on
which agreement was reached and those that remain to be resolved. Mission
recommendations clearly headed as “Recommendations” in the Aide-Memoire. The
c. Mission Report (Aide Memoire)
71
Government staff needs to be allowed sufficient time to read, analyze and digest the
contents of the Aide-Memoire. Therefore, the Mission distributes the draft to
implementing agencies and where appropriate to other partners for their comments,
which is incorporated to the extent possible. Any agreed changes, additions and
omissions could then be accommodated by the mission. The Aide-Memoire is
circulated at least 24 hours ahead of a „wrap-up‟ meeting (or any other mutually
agreed timeframe). Any agreed changes should be made following the wrap-up
meeting and the final version submitted to the lead ministry and others concerned.
On their immediate return to IFAD, supervision missions submit the Aide-Memoire as
part of their Back-to- Office report to IFAD management.
3. Management Letter: Within 10 days after the supervision mission, a Management
Letter is sent to the implementing agency (MFWA) by IFAD requesting resolution or
intervention with regard to issues that have to be addressed by implementing
agencies at higher levels. It highlights positive and negative trends in
implementation and concerns relevant to IFAD‟s strategic thrusts.
4. Supervision Report: After Returning to IFAD Headquarters, the Mission Leader
prepares a Supervision Report. The report is primarily a tool to be used by
implementing agencies, IFAD, and other stakeholders to judge progress over time,
and the vehicle to ensure that project objectives are being met and the expected
impact achieved. The focus of the report is on action, undertaken or envisaged, to
improve project progress and impact. The Aide- Memoire submitted before the
mission‟s departure from the country is an important source of information for the
report. Data obtained from the project regarding physical and financial progress and
impact are also key ingredients.
5. For additional information about IFAD‟s operational manuals, tools and guidelines
(i.e. M&E Guide, Loan and Grant Administration Operational Manual, Procurement
Guidelines, Tools and Guidelines on Gender, Guidelines on Project Auditing) visit the
website: www.ıfad.org (In English).
d. References for Additional Information
72
ANNEX 1
Duration of Assignment: Following successful completion of six-month probationary
period; renewable one-year contracts up to a total of seven years, if performance is
satisfactory.
Duty Station: Based in Ankara, travel to Elazığ, Bingöl, Muş when necessary,
Qualifications and Experience
1. University degree in English language (proven interpretation and translation),
administration or related fields,
2. Good command of both written and spoken English and at least three (03) years of
working experience in the positions of secretary or interpreter/ translator for foreign
funded projects
3. Good secretarial, organizational and communication skills
4. Good computer skills in common word processing (MS Word), spreadsheet (MS Excel),
5. Some knowledge in administrative procedures of the Government is preferable,
Job Description
Provide assistance to project implementation and daily tasks,
Make minutes of project meetings and make requested distribution,
Maintain communication with the project field offices and respond promptly to requests
for information and assistance,
Provide supports in preparing project events, including workshops, meetings, study
tours, trainings, etc.
Be responsible for project filing
Take care of project telephone, fax and e-mail system
Translation of project documents, materials, letter, papers
Interpretation during mission meetings, small-scale workshops, and relevant events
Arranging trips (air tickets, hotels etc.)
TERMS OF REFERENCE
Secretary/Translator
73
ANNEX 2
Duration of Assignment: Following successful completion of six-month probationary
period; renewable one-year contracts up to a total of seven years, if performance is
satisfactory.
Duty Station: Based in Elazığ, with regular travel to Ankara and within the Project area
(Elazığ, Bingöl, Muş) as required for co ordination, monitoring, reporting and oversight.
Qualifications and Experience
1. A higher degree in Agricultural Economics, Economics, Business Administration,
Forestry, Agriculture, Public Administration or related discipline relevant to the Murat
River Watershed Rehabilitation Project (MRWRP) with sound knowledge of contemporary
issues in the rural economy of Turkey and natural resource management. A minimum of
five years at a senior technical or management level in a relevant public institution,
private sector or an international organization, with proven skills in the management
and co-ordination of internationally financed development programs.
2. The candidate would be expected to have a creative, energetic and pragmatic approach
to problem solving and an appreciation of the respective roles of the public and private
sectors in rural economic development and natural resource management. Computer
literacy would be requisite and good command of spoken and written English would be
an advantage.
Job Description
3. The Deputy Project Manager will report to the Field Project Manager of the Field
Operations Unit (FOU) as the immediate supervisor and to the Project Manager of the
Central Operations Unit (COU) in Ankara and would be responsible to:
Provide support to COU;
Provide oversight and guidance to the Regional Directorate of OGM (OBM) in
Elazığ and Provincial Forestry Offices (OIMs) in Elazığ, Bingöl and Muş on all
matters pertaining to the smooth implementation of the Project, in
accordance with procedures and obligations specified in the IFAD Financing
Agreement and implementation arrangements detailed in the Project
Operations Manual;
Act as secretary for the Project Steering Committee (SC) and arrange for
dissemination of the decisions taken and follow-up;
TERMS OF REFERENCE
Deputy Project Manager (DPM)
74
Oversee the recruitment and activities of Project staff, consultants, and
consulting service providers (Micro catchment planning teams (MCPTs),
provincial Project teams (PPTs) those for special studies and surveys, and
similar) in accordance with the conditions of the IFAD Loan Agreement; the
related Terms of Reference; and the requirements of Annual Work Programs
and Budgets (AWPBs);
Provide guidance to the Provincial Focal Points (PFPs);
Oversee the preparation of the participatory micro catchment (MC) plans;
Ensure timely review and approval of the MC plans and sending then to OGM
for final endorsement and required budget allocation;
Ensure timely and effective implementation of the endorsed MC plans;
Oversee the work of the PPTs;
In close collaboration with the OBM and the PPTs in Elazığ, Bingöl and Muş,
and IFAD, prepare the Annual Work Plan and Budget (AWPB) in relation to the
Project design and available financing, and oversee the implementation of the
activities as per the approved AWPB;
Oversee the preparation, introduction and utilization of a Results-oriented
Management Information System for the Project, and ensure timely
collection, analysis and utilization of monitoring information;
In addition to the internal documentation (including technical reports,
financial documentation and accounts, and procurement requests) prepared
at the provincial level, co-ordinate the submission of other internal
documentation (payments, background documents, financial reports,
replenishment requests) as per the requirements of OGM Ankara, and/or IFAD
as appropriate and in accordance with the Loan Agreement and the
arrangements specified in the Operations Manual;
Ensure implementation of the participatory, iterative, multi-faceted
approaches of the Project that are crucial to maintaining its focus on poverty
reduction and natural resource rehabilitation; and
Receive and arrange for the reproduction and circulation of reports, studies
and other Project documentation from consultants as appropriate
75
ANNEX 3
Duration of Assignment: Following successful completion of six-month probationary
period; renewable one-year contracts up to a total of seven years, if performance is
satisfactory.
Duty Station: Three teams based in Elazığ, Bingöl and Muş with regular visits to Regional
Forestry Directorate (OBM) in Elazığ as required reporting and coordination and monitoring.
Composition of the Team
1. Each team will comprise a forest engineer, a crop production specialist (agronomist
with capacity in the fields of land and water management), a livestock production specialist
(zoo technician or veterinarian).
Qualifications and Experience
2. Every member will be expected to have as a minimum a Bachelors degree in his or
her relevant field(s). The Team Leader and will be expected to have proven 5-10 year field
experience. Experience in community forestry projects (participation/gender issues) will be
an advantage. Computer literacy will be required.
3. The candidate PPT members will be expected to have at least 5 years of proven
experience in their respective fields, and capable of adopting creative but pragmatic
approach to problem-solving and an appreciation of the participatory approaches in natural
resource management and livelihood improvement. Computer literacy will be required.
Job Description
4. Each team will provide requisite support to Provincial Directorate of Forestry (OIM)
according to the approved MC plans.
5. Each Team Leader will ensure that the Project is implemented in accordance with the
design and agreement with Turkish Government (MFWA/OGM) and IFAD; and provide
guidance in interacting with the OIM and the MC communities and while maintaining
responsibility for collection of relevant data and information to be used as input to the
Project M&E System.
TERMS OF REFERENCE
Provincial Project Teams (PPTs)
76
6. Each team will spearhead the awareness-raising campaign before the MC Planning
process is started and working closely with the service provider(s) develop the village visit
plans, arrange venues through the village administrations, and ensure the participation of
women and the elderly.
7. Each team will assist the MC Planning teams by providing technical and logistical
support in conducting the BCPCPS process and preparation of the MC plans to ensure
congruity with the norms and approaches outlined in the PIM.
8. Each team will develop action plans for each village based on the agreed MC plans
for efficient and effective implementation of Component 3 and to a certain extent
Component 1 (regarding farmer exchange visits) and Component 2 (regarding rehabilitation
of degraded grazing lands). If needed, OIMs will contract service providers as needed to
implement action plan.
9. Each team is responsible for implementing the Project activities included in the MC
plans through multi-sectoral, client-focused, coordinated, demand-driven and participatory
advisory services. Within this framework each team is expected to:
• Conduct a situation analysis in each of the villages included in an MC:
altitude, length of growing period, annual precipitation and
distribution, no. of days of snow cover, soil depth, texture, land
capability class;
production patterns: agronomic practices and related calendar in crop
production, livestock husbandry practices, yields, total production;
if relevant, marketing opportunities and channels;
farmers‟ resources: Total land/hh, no. of plots/hh, type of livestock
owned, no. of livestock/household, mechanization;
natural resources: available water, forest, rangelands and their
traditional uses by the community or outsiders (nomadic livestock
production); and
Labor: availability of household labor, seasonal migration patterns;
identify yield limiting factors (environmental factors, input availability and
provision, required knowledge and skills etc.) jointly with the farmers;
identify marketing problems jointly with the community, if relevant;
identify production practices causing natural resource degradation jointly with
the community;
improve irrigation efficiency;
erosion control and fertility management in agricultural fields:
identify potential solutions and opportunities jointly with the community;
77
to address problems, provide and facilitate advice, build partnerships with
provincial directorate of agriculture and research institutes of Ministry of
Food, Agriculture and Livestock and other relevant government agencies,
universities, local input dealers, private sector, local municipalities, farmer
organizations, markets (inputs and outputs) and credit institutions;
identify farmers‟ training needs;
design, provide and facilitate training programs (formal, informal and hands-
on);
design, provide and facilitate training programs (formal, informal and hands-
on) for women and youth systematically throughout Project implementation
and not just on a “demand driven basis”;
design, provide and facilitate on-farm demonstration programs and follow-up
on-farm advice;
design and implement a series of farmer exposure visits in collaboration with
public and private agencies and lead farmers; and follow-up dissemination of
information; and
provide technical and business information on new business opportunities and
diversification alternatives to raise incomes and broaden the rural economic
base, if relevant.
10. The Team will assist the Provincial Focal Points (PFP) in compiling data for
monitoring. Such data will be sent to the Deputy Project manager at the Regional
Directorate of Forestry (OBM) in Elazığ for evaluation and dissemination.
11. The Team will be responsible also for organizing the delivery and distribution of the
various inputs to the beneficiaries and monitor their use to ensure the planned outputs of
the component.
12. The nature and scope of the PPTs role may be expected to change in terms of detail
as the Project evolves and new/adjusted functions become necessary following 18-month
and Mid-term Reviews.
80
ANNEX 6
Form 100- APPLICATION WITHDRAWAL
1. Sequential numbering of withdrawal application
YES
or NO
2. Withdrawal application amount tallies with sequentially numbered
summary sheets
3. Categories/subcategories charged according to Schedule 2 of Financing
Agreement
4. Percentage of financing applicable for each category or subcategory
5. Availability of funds in categories and overall financing amount
6. Currency of payment
7. Completeness and accuracy of banking instructions
8. Complete name and address of correspondent bank
9. WA is signed by Authorized Representative
STATEMENT OF EXPENDITURE
1. Eligibility of expenditures claimed
(a) Within SOE financial ceiling
(b) Expenditures under specific category (……….) eligibility
2. Form 102 signed by designated Project Accountant, Project Director,
Authorized Representative
3. Form 102 supported by signed Form 101 (for items reported in 2, but
over the financial ceiling
DESIGNATED ACCOUNT-REPLENISHMENT REQUESTS
1. Amount within ceiling figure agreed as a reasonable limit (….USD or ……);
or per AWPB period
2. Amount at least equal to 20% of the agreed limit; or per AWPB project
requirements
3. Amount agreed sufficient to cover a specific reporting period (revolving
fund option)
4. Exchange rate used
5. Completeness of designated account banking and account details
6. Enclosed designated account reconciliation and bank statements
SUPPORTING DOCUMENTATION (attached when/if required)
1. Copy of the contract
2. Copy of invoice, certified by Project Director
3. Copy of bank guarantee and performance guarantee
4. Copy of delivery receipt
5. Copy of evidence of payment
6. Completed Form 101
CHECKLIST FOR WITHDRAWAL
APPLICATION
81
PROCUREMENT
1. Copy of “no objection(s)” provided by IFAD (attached)
2. 2. Copy of Contract Payment Monitoring Form(s) (attached)
COMPLIANCE WITH CONDITION(S) FOR DISBURSEMENT
1. In accordance with terms in Section E of the Financing Agreement
2. In accordance with terms in the Letter to the Borrower/Recipient1.
EXPENDITURE INCURRED/COMMITTED BEFORE PROJECT
COMPLETION DATE
1. Expenditure verified as eligible:
a. Contract signed before completion date
b. Goods delivered before project completion date
c. Services completed and/or rendered before project completion date
Remarks:
(b) Expenditures under specific category (……….) eligibility
2. Form 102 signed by designated Project Accountant, Project Director,
Authorized Representative
3. Form 102 supported by signed Form 101 (for items reported in 2, but
over the financial ceiling
DESIGNATED ACCOUNT-REPLENISHMENT REQUESTS
1. Amount within ceiling figure agreed as a reasonable limit (….USD or ……);
or per AWPB period
2. Amount at least equal to 20% of the agreed limit; or per AWPB project
requirements
3. Amount agreed sufficient to cover a specific reporting period (revolving
fund option)
ANNEX 7.
Prepared by: Project Accountant
Dated:
Certified by: Project Director
Dated:
83
ANNEX 8.
Background [OPTIONAL]
The TOR should provide appropriate background information of the project, including:
(a)a brief description of the project including information on project sources of funding;
(b)a general description of implementation arrangements, including the organizational
structure of all implementing entities (if more than one);
(c) list the source and total amount of funds for the period subject to audit under this TOR
(Bank‟s loan/credit, trust funds, counterpart funds, etc.); and
(d) total disbursements / expenditures for the period subject to audit
Objective
The objective of the audit is to enable the auditor to express an opinion on the project
financial statements (PFS) of the [NAME OF PROJECT] (the Project) as of [MONTH
DATE, YEAR] and for the fiscal year then ending.
The Project‟s accounting system (books and records) provides the basis for the
preparation of the PFS, was established to record the financial transactions of the
Project, and is maintained by the Project‟s implementing agency, [NAME OF PROJECT
IMPLEMENTING AGENCY].
Scope
The audit will be conducted in accordance with International Standards on Auditing
(ISA) as published by the International Auditing and Assurance Standards Board of the
International Federation of Accountants (IFAC), with special reference to ISA 800
(Auditor‟s Report on Special Purpose Audit Engagements) and to relevant World Bank
guidelines. In conducting the project audit, special attention should be paid to the
following:
a. External funds have been used in accordance with the conditions of the
relevant financing agreements, with due attention to economy and
efficiency, and only for the purposes for which the financing was
TERMS OF REFERENCE
FOR THE AUDIT OF THE [NAME OF PROJECT] FOR
THE YEAR (PERIOD) ENDED [MONTH DATE, YEAR]
84
provided. Relevant financing agreements are [CITE RELEVANT
FINANCING AGREEMENTS];
b. Counterpart funds have been provided and used in accordance with
the relevant financing agreements, and only for the purposes for which
they were provided;
c. Goods and services financed have been procured in accordance with
the relevant financing agreements;
d. Necessary supporting documents, records, and accounts have been
kept in respect of all Project ventures including expenditures reported
via Statement of Expenditures (SOEs) (or Financial Monitoring Reports
(FMRs) if used as the basis of disbursement), or Special Accounts
(SAs). Clear linkages should exist between the accounting records and
the financial reports presented to the Bank.
e. Where Special Accounts have been used, they have been maintained
in accordance with the provisions of the relevant financing
agreements.
f. The PFS have been prepared in accordance with generally accepted
accounting principles and practices and relevant World Bank
guidelines, and give a true and fair view of the financial position of the
Project as of [MONTH DATE, YEAR] and of the resources and
expenditures for the fiscal year then ending.
g. Review the compliance on each of the financial covenants in the
(STATE SPECIFIC SECTION OF LOAN/CREDIT AGREEMENT and list, as
necessary).
Project Financial Statements
The Project Financial Statements should include
a. a Summary of Funds received, showing the World Bank, Project funds
from other donors, and counterpart funds separately.
b. a Summary of Expenditures shown under the main project headings
and by main categories of expenditures, both for the current fiscal year
and accumulated to-date;
c. a Summary of SOEs used as the basis for the submission of withdrawal
applications;
d. A Statement of Special Account; and
e. a Balance Sheet showing Accumulated Funds of the Project, bank
balances, other assets of the Project, and liabilities, if any.
85
OR
The Project Financial Statements have been prepared in accordance with International
Public Sector Accounting Standards issued by the Public Sector Committee of the
International Federation of Accountants. The Project Financial Statements should
include:
a. the cash receipts and payments of the project during the year [or
period] ended [MONTH DATE, YEAR], showing the World Bank, project
funds from other donors, and counterpart funds separately,
b. a Summary of SOEs used as the basis for the submission of withdrawal
applications in the notes, as appropriate;
c. A Statement of Special Account in the notes, as appropriate; and
d. a Balance Sheet showing Accumulated Funds of the Project, bank
balances other assets of the Project, and liabilities, if any.
Statements of Expenditures
(or Financial Monitoring Reports if used as the basis of disbursement)
As part of the audit of the PFS, the auditor is required to audit all SOEs and FMRs used
as the basis for the submission of withdrawal applications.
These SOEs (or FMRs) should be compared for project eligibility with the relevant
financing agreements, and with reference to the Project Appraisal Document for
guidance when considered necessary. Where ineligible expenditures are identified as
having been included in withdrawal applications and reimbursed against, these should
be separately noted in separate note disclosures and also in the management letter, by
the auditor. The Project Financial Statements (or included within the notes to the
project financial statements) should be a schedule listing individual SOEs (or FMRs if
used as the basis of disbursement) withdrawal applications by specific reference
number and amount.
The auditor should pay particular attention as to whether:
a. the SOEs (or FMRs) have been prepared in accordance with the
provisions of the relevant financing agreement.
b. expenditures have been made wholly and necessarily for the
realization of project objectives.
c. information and explanation necessary for the purpose of the audit
have been obtained;
d. supporting records and documents necessary for the purpose of the
audit have been retained, and
86
e. the SOEs (or FMRs) can be relied upon to support the related
withdrawal applications.
Special Accounts
In conjunction with the audit of the Project Financial Statements, the auditor is also
required to audit the activities of the Special Accounts associated with the Project. The
Special Accounts usually comprise
a. deposits and replenishments received from the Bank;
b. payments substantiated by withdrawal applications;
c. interest that may be earned from the balances and which belong to the
borrower; and
d. the remaining balances at the end of each fiscal year.
The auditor should pay particular attention as to the compliance with the Bank's
procedures and the balances of the Special Accounts at the end of the fiscal year (or
period). The auditor should examine the eligibility of financial transactions during the
period under examination and fund balances at the end of such a period, the operation
and use of the SAs in accordance with the financing agreements, and the adequacy of
internal controls for this type of disbursement mechanism.
For this Project, the Special Accounts are referred to in [CITE RELEVANT CLAUSES]
of the relevant financing agreements.
Audit Reports
The auditors will issue an audit opinion on the [NAME OF PROJECT] Project Financial
Statements (refer to the “Project Financial Statements” paragraph above for a definition
of the statements included therein).
Attachment 3 of the Audit Guidelines: Annual Financial Reporting and Auditing for World
Bank-Financed Activities provide specimen auditor‟s opinion on the project financial
statements.
In addition to the audit opinion, the auditor will prepare a "management letter," in
which the auditor will:
a. give comments and observations on the accounting records, systems,
and controls that were examined during the course of the audit;
b. identify specific deficiencies and areas of weakness in systems and
controls and make recommendation for their improvement;
c. report on the lack of compliance of each financial covenant in the
relevant financing agreement;
87
d. communicate matters that have come to their attention during the
audit which might have a significant impact on the implementation of
the project;
e. bring to the borrower's attention any other matters that the auditor
considers pertinent; and
f. include management's comments in the final management letter .
The financial statements, including the audit opinion, and management letter should be
received by the Project‟s implementing agency, [NAME OF PROJECT IMPLEMENTING
AGENCY], no later than six months after the end of the audited fiscal year. The Project‟s
implementing agency should then promptly forward two copies of the audited project
financial statements (including audit opinion) and management letter to the Bank.
General
The responsibility for the preparation of financial statements including adequate
disclosure is that of the management of the [NAME OF PROJECT IMPLEMENTING
AGENCY]. This includes the maintenance of adequate accounting records and internal
controls, the selection and application of accounting policies, and the safeguarding of
the assets of the entity. As part of the audit process, the auditor will request from
management written confirmation concerning representations made to the auditor in
connection with the audit.
The [NAME OF PROJECT IMPLEMENTING AGENCY] will co-operate fully with the auditor
and will make available to the auditor whatever records, documentation and other
information is requested by the auditor in connection with the audit. The auditor should
be given access to all legal documents, correspondence, and any other information
associated with the project and deemed necessary by the auditor. Confirmation should
also be obtained of amounts disbursed and outstanding at the Bank and of amounts
disbursed under [SPECIFY OTHER DONORS, LOANS OR GRANTS, IF ANY].
88
ANNEX 9.
FORMAT FOR AWPB
EXECUTIVE SUMMARY
CONTENTS
ABBREVIATIONS
INTRODUCTION
I. ANNUAL WORK PLAN AND BUDGET FOR …..
I.1 Component I: Definition (expectations from each activity and reasonable
explanations of the key questions: What? When? Why? By Whom? How? The Cost of
Activity?)
Objective
Activities Proposed for…..
Summary of planned Component Expenditure
I.2 Component I: Definition (expectations from each activity and reasonable
explanations of the key questions: What? When? Why? By Whom? How? The Cost of
Activity?)
Objective
Activities Proposed for…..
Summary of planned Component Expenditure
I.3 Component 3: Definition (expectations from each activity and reasonable
explanations of the key questions: What? When? Why? By Whom? How? The Cost of
Activity?)
II. ATTACHMENTS
ATTACHMENT 1. IMPLEMENTATION SCHEDULE OF PROJECT ACTIVITIES
ACCORDING TO …..AWPB
ATTACHMENT 2. ESTIMATED COST AND FINANCE PLAN
Table 1: Withdrawal Applications
Table 2: Summary of Expenditures by Components
Table 3: Summary of Expenditures by Loan Categories and Financiers
Table 4: Summary of Expenditures by Loan Categories and
ATTACHMENT 3. PROCUREMENT PLAN FOR ….
If any, related attachments will be added
FORMAT FOR AWBP
89
ANNEX 10
Preparation of the Sub-Plans
1. In preparing the sub-plans, the main principle is to keep a ratio between rehabilitation
and income-generating interventions by taking the nature of the project into
consideration.
2. In any MC, implementation interventions may be carried out only in some parts of a
MC and in some villages of the MC based on clearly established priorities agreed with
the communities. The main principle to stop the erosion, starting from the upper MCs
and move downward.
3. Forestry sub-plan: is prepared for forest land and includes rehabilitation of eroded
areas and improvements in degraded forest land.
4. Rangeland sub-plan: includes investments for rangelands/livestock and interventions
regarding sustainable management.
5. Agricultural sub-plan: is prepared for agricultural land and includes crop (grain, forage
and horticultural crops, and greenhouse production) and livestock interventions. It
will also include training and demonstration program.
6. Water/irrigation sub-plan: is prepared for the investments for: i) the development of
small water sources for small-scale irrigation purposes and rehabilitation the existing
irrigation infrastructure; ii) livestock drinking water, and iii) village sanitation.
7. Energy use sub-plan: is prepared for the investments regarding energy saving and
renewable technologies.
8. The MC planning process comprises 14 steps (Box 1) listed below and each step is
elaborated in the following paragraphs.
STEP 1: Awareness raising
9. The component finances awareness-raising activities as explained in paragraphs 75-77
above.
STEP 2: First field trip to the MC
GUIDELINES FOR PREPARING
PARTICIPATORY INTEGRATED MC PLANS
90
10. After the selection of the Project MCs by the OBM and OIMs, MCPT will visit those that
they will prepare the plans for to get an overall idea about the natural resources,
location, topography, distances, elevation etc. This is just a technical visit to get
familiar with the setting and does not require contact with the communities.
Observation sharing within the team is important to start the synergy.
STEP 3: Informing the Local Communities about NRDP
11. The PPT visits the local agencies in the district to brief them about the Project and
introduce the MCPT(s) and explain what type of assistance will be needed from the
agencies during planning period.
12. The PPT also visits MC villages to introduce the MCPT(s) to the MC communities. For this
purpose an “introductory meeting” is organized for each MC village. It is very important
to inform all the stakeholders about the meeting in advance to ensure good attendance
and create interest in the community for the succeeding steps. The MCPT records the
names of the participants. This information will go to the table under Chapter III:
Participatory Process of the MC Plan.
STEP 4: Compilation of data and information
13. To fully understand the physical and socio-economic conditions of the MC, the MCPT(s)
should have access to updated data. This step includes collection of information (data
and maps), data verification and updating, and/or supplementing available information
by some further simple surveys and interviews and/or focus group meetings. It is
important to start this step as early as possible.
Box 1. MC Plan Preparation Steps
Step Action 1 Awareness raising
2 First field trip to the MC
3 Informing local communities about the project
4 Compilation of data and information
5 Problem identification
6 Analysis of the problems
7 Solution of identification
8 Preparation of the first Draft MC Plan
9 Preparation of the draft Map of Activities
10 Display of the first Draft MC Plan in MC villages
11 Preparation and approval of the final draft at the local level
12 Signing of the Final MC Plan
13 Display of the signed plan at the local level
14 Budget allocation for the MC Plan
91
14. It should be noted that if some data are not available, in order to prepare realistic plans,
best estimates should be developed based on local knowledge and professional
judgment, instead of leaving information gaps in the Plan.
15. The data collected at this step are recorded in the tables in Chapter II: Current Status
in MC Villages of the MC Plan.
STEP 5: Problem identification
16. It should be underlined that identification of problems and solutions is not putting
together a wish/demand list. Without identifying the underlying issues, one should not
jump into the tools that can be used for the solution of that particular problem (Box 2).
17. The MC planning, implementation and monitoring will be participatory as explained in
paragraphs 81-90. To achieve this participatory tool called ”Beneficiary Centered -
Problem Census - Problem Solving (BCPCPS)” modality will be used. The appropriate
tools of IFAD methodology will fill the gaps in the BCPCPS process when relevant. During
planning process, focus group discussions and community consultation will also be
undertaken, when needed. In order to conduct such an exercise, the MCPT/PPT contacts
the village headman at least 2 weeks in advance and sets an appropriate date. Then, the
purpose of meeting, date, time and the venue is publicly displayed (at several points in
a village) and announced. Efforts should be made to gather the majority of the village
population. MCPT have to ensure that women and children are not marginalized in the
process. If necessary, separate meetings can be held with males and females.
BOX 2. Cause and Effect and Solution Relationship
Symptom Poor vegetation (in terms of quantity of the biomass and botanical composition) in the rangeland and erosion
Problem
1st layer over grazing
2nd layer grazing starting to early in the spring and ending too late in the fall
Underlying issues
insufficient feed for winter period
limited on-farm forage crop production lack of knowledge on crop rotations where forages can be rotated
with wheat and barley under dryland conditions
Solution increase forage crop production on agricultural land (one of the solutions)
Tool
making the farmers/livestock owners aware of various options to increase on-farm forage production options through on-farm demonstrations, training and farmers exposure visits, providing high yielding forage crop seeds, small-scale irrigation
92
18. Contact Groups. After the problem identification session, several contact groups could
be identified in the meeting above or in the next meeting that is conducted for problem
solution.
19. During the MC planning process, the MCPT usually work under time pressure when they
visit the villages. To be able to see the right people at the planned time, to visit a
particular site in the forest, or water sources or to contact some livestock owners, the
team should use assistance from the village to use the available time efficiently and to
contact the right people and visit the right site. Villagers can identify 3-4
individuals/group as counterparts to assist the sectoral experts on a sectoral basis
(forestry, crop production, irrigation and livestock/pasture management). Individuals
(man or woman) with in-depth knowledge about the village, resources and the sub-
sector and good interpersonal skills, could be designated to make themselves available
and work closely with the experts. Team should be careful in dealing with these groups
not to create concerns on the community side regarding getting benefits from the
Project. It should be made clear to the communities that that these groups have no
decision making role or any other privilege. Their assistance is limited to the logistical
support and some consultation. In case of poor performance and/or misconduct, the
MCPC should immediately replace the contact groups or its individual members.
20. Record the name of the contact groups and their cell phone numbers in the related table
under Chapter III: Participation Process of the MC Plan.
STEP 6: Analysis of the problems
21. The problems are analyzed first by the individual specialists of the MCPT and then by the
MCPT as a whole. It is important to develop a thorough understanding of the links
between the users and the ways they use these resources and the links between the
types of uses. At this stage, it would be helpful to make an assessment of the data
(whatever is available at this stage) and find out whether the data and the problems
identified are matching. It would also be useful to have additional field trips to the MC to
ensure the outcome of the analysis reflects the situation on the ground. If all these are
not enough to come to a conclusion, additional data should be collected through simple
surveys and/or focus group meetings.
22. Based on work at this step, RWPTs fill the remaining relevant tables in Chapter II:
Current Status in MC Villages of the MC Plan.
STEP 7: Solution Identification
23. It is recommended that the solution identification process is undertaken as a part of the
problem identification meeting. Once the villagers are focused on the topic, it will be
easier to move to the solution phase. If the identification session is conducted according
to the rules, it will take maximum 2 hours. Here, it is important to maintain the interest
and the attention of the participants for the solution identification session. Therefore, the
93
MCPC should observe the participants carefully and decide whether to continue or to
organize another meeting later.
24. In the solution identification session, the participants are allowed to suggest solutions to
the prioritized problems. All solutions are considered and recorded. Then a Menu of
Activities is shared with the communities.
25. Menu of activities: A menu comprising activities for improving natural resources and
livelihood will be available for the communities to choose from. The activities selected
depending on the technical feasibilities and agreements reached with the MC
communities will be included in the MC plans and the associated scale, scope, labor
needs, co-financing arrangements, timing/phasing and costs will be detailed. The menu
will be flexible and during implementation it could be revised based on the agro-
ecological and socio-economic conditions of the MC villages.
26. The Menu has to be presented together with the cost sharing arrangements and each
activity need to be explained to ensure that the community makes educated decisions. If
some of the suggested solutions cannot be accommodated by the Project, these are
openly explained to the communities. Before closing the meeting, MCPT explains to the
community that the solutions will be studied and draft plans will be prepared accordingly
and to be discussed and shared with them.
27. Later, MCPT discusses the solutions in a team meeting, and screens those based on the
following criteria: i) whether solutions are corresponding with the problems, ii) whether
the selected solutions have multiple effects (positive effect on both natural resources
and rural livelihood); iii) number of households to be benefiting; iv) cost of activity, v)
possibility of completing the implementation within maximum 3 years.
Step 8: Preparation of the first Draft MC Plan
28. The MCPT should be ready for a shower of demands from the community side
particularly for income generation. It should be made clear to the villagers that the
resources- in-terms of money and time- available under the project are limited and the
project will support those activities that bring the most benefits at the MC level that are
cost- effective and that can be replicated in other parts of the country. Selection of these
depends on professional judgment, thorough understanding of problems and local
conditions.
29. 126. Planning process incorporates expected behavioral changes on the community
side. It will be explained to the villagers that, from now on, “business will not be as
usual”, and they have to change the way they use the natural resources. It should be
underlined that there is a link between poverty and natural resource degradation, when
the local communities get poorer they put more pressure on natural resources and when
the natural resources get more degraded, the communities get poorer.
30. There are 3 areas (forest, pasture and agricultural land) where people‟s participation in
Component 2 will be sought. The community would be told that the scope of
participation would also be different in each case: afforestation and forest management,
94
for example require the agreement of the livestock owners for implementation of the
forest rehabilitation and conservation measures; in pastures, closure, rotational grazing
and other management practices will require early participation for implementation and
conservation measures on agricultural land, will require participation of individual
farmers.
31. The communities should be clearly informed about the cost sharing between the Project
and the beneficiaries. For Component 3, a list of beneficiaries is attached to the MC plan
with their signatures indicating that they understand and accept the cost sharing
arrangements. The MC Plan includes a format for such arrangements Under Chapter
VIII: Agreements and Arrangements.
32. For activities on areas where the investment will benefit a number of families,
arrangements for cost sharing during investment and profit sharing at harvest time need
to be agreed between the beneficiaries in writing. This document must be endorsed by
the village administration and be a part of the Plan. The MC Plan includes a format for
such arrangements Under Chapter VIII: Agreements and Arrangements.
33. The MCPT must explain to the communities that all soil cultivation and planting/seeding
should be on contour (perpendicular to the slope). This is an absolute requirement at
least for the direct beneficiaries (receiving inputs from the Project).
34. For some of the activities planned, detailed plans are needed for implementation e.g.
construction of small irrigation systems, forest and rangeland structures.
35. The Project envisages achieving behavioral change on the MC communities‟ way of using
natural resources. In order to achieve this particularly on agricultural and pastureland
and water resources, effective extension support is needed. This would be achieved by
the PPTs who address problems, provide and facilitate advice, and build partnerships
with provincial directorate of agriculture and research institutes of Ministry of Food,
Agriculture and Livestock, and other relevant government agencies, universities, local
input dealers, private sector, local municipalities, farmer organizations, markets (inputs
and outputs) and credit institutions.
Step 9: Preparation of the draft Map of Activities
36. Once the draft MC plan is ready, activities have to be marked on the MC Map with
different colors/patterns corresponding to activities on forest land, pasture land,
agricultural land (if possible by type of activity i.e. horticulture, forage crops, agro-
forestry and field crops) and small scale irrigation. The map has to include a clear
legend. While giving information or briefing to any individual or group or agency, the
map has to be ready and used.
Step 10: Display of the Draft MC Plan in MC villages
37. The draft MC plan and the map are displayed publicly (in village school, commune office,
mosque, health center, coffee shop in the MC villages) for about a week. Community
members are expected to review the plan and the map, request clarification, raise
95
objections or make comments. All these are collected/recorded by the village headmen
with the assistance of contact groups
Step 11: Preparation and approval of the final draft at the local level
38. The MCPT review the comments/objections and make necessary amendments in the first
draft. If needed, they make additional observations in the field, consult with additional
people or collect and analyze new data and based on all these prepares the final draft.
MCPC may see a need for a third community meeting before finalizing the draft. It
should be noted that until the signing and the approval of the plan by the envisaged
bodies, the plan is considered as “draft”.
Step 12: Signing of the final draft
39. The village headmen of the participating villages, the MCPT and the OBM will sign the
final draft. The signed MC Plan is necessary to secure Project financing for
implementation. Therefore, a signed copy will be sent to Central Operations Unit (COU)
in Ankara. If any changes are requested by OGM, the plan will be returned for further
consultation with the MC communities. Once negotiated and signed, the MCP will
become binding on the parties and implementation will proceed.
Step 13: Display of the final MC Plan in MC villages
40. The final MC plan and the map are displayed publicly (in village school, mosque, health
center, coffee shop in the MC villages) for about 2 weeks to inform the community. At
the end of this period, the MC plan is kept by village administration and made available
for the community members in case of an inquiry.
Step 13: Budget allocation for the MC Plan
41. The COU undertakes a rapid review of the document to ensure that the MC Plan is
prepared: i) according to the Guidelines, ii) in line with the principles of the Project, iii)
based on the agreed ratios between investments and v) based on the established unit
costs, and vi) by taking the agreed implementation period into consideration. If the Plan
is found satisfactory, the budget allocation is approved.
96
ANNEX 11
1. ”Beneficiary Centered - Problem Census - Problem Solving (BCPCPS) is a non-
threatening, focused discussion that uses small group dynamics to elicit: i)
perception of the causes of natural resource degradation; ii) a complete and ranked
census of the real and perceived problems of individual households, villages and
locality as a whole, and iii) the communities‟ proposed solutions to these problems.
No problem is rejected and all solutions are considered. The final ranking of problems
and preferred solutions are theirs. The project‟s contribution is limited to facilitating
the BCPCPS approach. Project staff only explains the process, and neither takes part
in the discussion nor makes promises. In the “solutions” sessions, the participants‟
proposed solutions will be collected, evaluated and decided according to technical
and financial viability criteria.
2. The output of the group far exceeds the sum of information experiences and
options contributed by individuals. Each group member gains from the shared
experience, both in receiving new knowledge and in increased social awareness. For
example, a farmer or village may initially consider a particular problem of paramount
importance, but this view may change in favor of problems raised by other village
members. This compromise is made by many villagers and is the first step toward
group consensus. Consistent with small group theory, once the group agrees to take
specific action arising from the problem census, the majority of the members are
committed and social mechanisms that normally operate in the village situation
ensure that all villagers (males and females) attending the discussion group are
committed to the action.
3. The planning process incorporates expected behavioral changes on the
community side. It will be explained to the village members that, from now on,
“business will not be as usual”, and they have to change the way they use the
natural resources. It would also be underlined that the project is not a “rural
development project” but it is a project where the local people‟s participation is
found necessary in the conservation of specific natural resources that are essential to
their well being.
4. There are 3 areas (forest, rangelands and agricultural land) where people‟s
participation in the definition and endorsement of project components will be sought.
The community would be told that the scope of participation would also be different
in each case:
Beneficiary Centered - Problem Census - Problem Solving (BCPCPS)
97
i. afforestation and forest management, for example require the agreement of
the livestock owners for implementation of the forest rehabilitation and conservation
measures;
ii. in rangelands, closure, rotational grazing and other management practices
will require early participation for implementation as well as the agreement of the
livestock owners for implementation of the pasture rehabilitation and conservation
measures;
iii. on agricultural land, selected farmers (because of their potentially highly
erodible soils and erosion prone cultural practices
5. Also the project will try to ensure that women and children are not
marginalized in the BCPCPS process. Gender issues will be mainstreamed into the
project implementation.
The Process
6. When the exercise is started in a village, a facilitator should follow the steps
below. First, he should explain to the group how they would do the exercise. Note
that the facilitator does not make any selection, suggestion or interpretation. He only
assures that no single group and/or individuals dominate the discussions and
decision-making.
Announcement to the participants
• We will start the exercise in 15 minutes. We need each and every one of you
in this exercise. However, it depends on your own will to participate. If you do not
participate, later you should not criticize and/or complain about the project activities.
If you want to improve the things in your village, you should allocate time, provide
input, make effort and collaborate with others.
• We will adhere to the following ground rules: i) listen to the others, do not
talk at the same time; ii) respect others‟ views; iii) act within the time limits given
• We will do the same exercise in each of the MC villages.
• Today we will learn from you why and how the natural resources around your
village occurred, how you see the problems in your own village or community. We
are here only to set up a democratic environment to hear your voice. Everybody‟s
voice is equal and equally important for the project.
• First as a group you will tell us: i) whether there is natural resource
degradation around you, ii) if yes, why/how the degradation occurred, what are the
reasons? You will tell and I will write down and make a list.
• Then you will work individually and write down the problems, which you
perceive in your village on a piece of paper that we gave you. Then you will form
small groups of five to present your list to the group members. You are the ones to
98
decide in which group you want to be. You will be given 20 -30 minutes to write
down the problems. Based on the problems you have written, each group will jointly
come up with a list in the order of importance. This means that the problem on top
of the list is the most important problem for your group. Each small group will select
a spokesperson.
• All the groups in this room will do the same thing. When every group informs
us that they have finished their work, the groups will come together to do the second
part of the exercise.
• Second part will take about 1.5 hours. Every spokesperson will introduce the
list of the problems identified by his/her group to all participants. These will be
recorded on the flip chart by us. After completion of the individual group
presentations, the whole group has to come up with one list of problems. This joint
list will be prioritized by all of you. You will decide how to do that; either by voting or
interacting to convince each other. If no consensus is reached than the group may
choose to vote and discuss the prioritization. We will also record the prioritized list on
the flip chart. When the final list is formed, note that the problem that is ranked first
by most groups is regarded as the most important problem in the community and so
on. The priority problems will be recorded in the table under Chapter III:
Participatory Process of the MC Plan.
The process:
• Record the names of the participants. This information will go to the table
under Chapter III: Participatory Process of the MC Plan.
• Distribute pieces of paper and pen to the villagers and let them start the
process as individuals. When they finish their work, help them to organize the chairs
for small groups of about 5 individuals. Do not interfere with the grouping. Let them
decide themselves. Let each group also choose a spokes-person.
• While groups are making presentations, record those on the wall with letters
large enough to be seen from every distance. Then, read each of the lists loudly to
the group.
• When the group comes together to come up with the joint list also help them
to write down these on the wall.
• When the list is put on a wall, go through the items together with them to
point out the ones that are not within the mandate of the project such as village
roads, telephone, health center etc.
• Make a new list (Final List of Priority Problems) that includes only the
problems that can be addressed by the project by making references to the
objectives of the project. The list on the wall will stay with the village. Do not forget
to make copy the final list for your records.
99
• Thank to the group for their good work, participation and patience. Before the
closure of the meeting, inform them about the next steps (problem solution and
planning).
100
ANNEX 12
Duration of Assignment: Approximately 4 months field work and 2 months report
writing. Maximum 6 months.
Location: The boundaries of the micro-catchment (MC) are provided in the attached
1/25,000 map.
Composition of the Micro Catchment Planning Team (MCPT)
1. While the composition of the Micro Catchment (MC) Planning Team (MCPT) is
flexible in terms of the size and would be decided by the Consultancy Contractor
(CC) as a minimum the following specialists would be made available as MCPT
members: forester, crop production specialist (agronomist), livestock production
specialist, rural sociologist, rural infrastructure engineer, and economist. The forestry
specialist would lead the team.
Qualifications and Experience
2. Every member would be expected to have as a minimum a BA or BS in his or
her relevant field(s). The forestry specialist would be the Team Leader and would be
expected to have 5-10 year field experience in forest and/or natural resource
management planning and investment implementation including beneficiary
participation and gender issues. The candidate MCPT‟s members would be expected
to have proven (CV-based) experience, and capable of adopting creative but
pragmatic approach to problem-solving and an appreciation of the respective roles of
the private and public sectors in natural resource management and rural income
generation.
Job Description
3. The team would be responsible to prepare integrated (MC) Plan(s) in a
participatory manner as detailed in subsequent sections of this TOR for the pre-
identified areas where the Murat River Watershed Rehabilitation project is being
implemented. The MCs are the units of implementation, that being the smallest
hydrological unit for the project. Information regarding the components and the
overall availability of funds for these would be provided to the Contactor.
TERMS OF REFERENCE
MC PLANNING TEAM (MCPT)
101
4. The MC(s) has been identified by Regional Directorate of General Directorate
of Forestry (OBM) in Elazığ, and preliminary demographic natural resource-related
data are available. The MCPT would work closely with the Provincial Project Teams
(PPTs) and would be provided with background information related to the project,
area, and the MC(s) where they would be responsible for planning.
5. The modality of Beneficiary Centered– Problem Census – Problem
Solving (BCPCPS (SOR-SAP-COZ; in Turkish) would be used and a handbook on
BCPCPS would be provided to the contactor together with the IFAD methodology
(participatory mapping).
6. MCPT will be supported by Provincial Project Teams (PPTs) in terms of
technical and logistical support in the BCPCPS process and in the preparation of the
MC plans.
7. Respective OIMs in Elazığ, Bingöl and Muş will monitor and provide support to
the MCPT in preparing the MC plans. The plans will be reviewed and approved by
OBM and sent to OGM for final endorsement and serve as the basis for all
investments in an MC(s) and detailed in the AWPB(s).
Expected Output
8. A fully-costed time-bound MC Plan for (TBD……) in the Province(s) of
(TBD……) in accordance with the Guidelines. The plans for the activities would cover
a maximum of 36 months implementation period for the investments.
Preparation of MC Plans
9. Annex 11 of the PIM gives the guidelines for the MC planning activities. It
would be provided to the Contracted MCPT.
10. The scale, scope, labor needs, cost sharing arrangements, timing, phasing,
and associated activities would be detailed in the plans.
11. The overarching principle of the planning is to maintain a ratio of
approximately 70% - 30% between natural resource rehabilitation and livelihood
improvements. The allocation of funds would be broadly distributed where
rehabilitation activities would comprise a minimum of 60% and maximum of
maximum 80% of the total funds to be allocated for an MC. The remaining amount
would be used for livelihood improvement activities (crop and livestock interventions
and irrigation, social infrastructure and energy-related investments, etc.). In any MC,
project investments may be carried out only in some parts and in some villages on
clearly established priorities agreed with the communities.
102
12. Each plan must include the below 10 mandatory chapters with each related
maps and an MC activity map summary tables:
• Chapter I. Overview of the MC
• Chapter II. Current status in the MC (regarding natural resources and
socio-economic structure) and justification for selection of the MCs
• Chapter III. Participatory process and priority problems as identified
by the community and their perception of reasons of degradation
Sub-plans:
• Chapter IV. Forest land
• Chapter V. Grazing land
• Chapter VI. Agricultural land
• Chapter VII. Water
• Chapter VIII. Energy
• Chapter IX. Costs
• Chapter X. Agreements and Arrangements
Sub-Plans: (Chapters IV-VIII)
13. Each MC plan would include sub-plans for forestry land, pasture land,
agricultural land, water and energy, hence the ”integrated” nomenclature.
a. Forestry sub-plan: covers the gazetted forestland and includes
rehabilitation of eroded areas and improvements in degraded forest, including
oak coppice.
b. Grazing land sub-plan: covers investments for communal grazing lands
interventions including infrastructure for livestock and regarding sustainable
management.
c. Agricultural sub-plan: covers private agricultural land and includes
crop (grain, forage and horticultural crops, and greenhouse production, etc.)
and livestock interventions.
d. Water/irrigation sub-plan: covers: i) water storage ponds ii)
rehabilitation of earth canals and iii) on-farm drip irrigation
e. Energy use sub-plan: covers energy saving and renewable
technologies for home use.
103
ANNEX 13.
1. The PPTs would identify and agree on the MC villages where demonstrations would be
carried out. After the identification of the villages, the PPTs together with the mother
should identify the demonstrator farmers. The PPTs would be responsible for all extension
programming and activities including but not limited to the initiation of demonstrations,
provision of technical advice, planning and conducting field days to disseminate the
results. They could be supported with advice and staff from the Provincial Directorate of
Food, Agriculture and Livestock, as required.
2. The major equipment (tractor, plough, cultivator etc.) required to set up/implement the
demonstration program would be provided from the MC villages, these can also be rented
from the villagers. The inputs will be provided by the Project and provisions are already
made for these.
3. It should be noted that in addition to the demonstration that would be established by the
technical staff, there would be opportunities also in the farmers‟ fields, orchards and
barns where the farmers‟ current practices could be used as demonstrations e.g. wheat
field suffering from insufficient nitrogen, fields tilled at wrong time and/or with wrong
implements, vegetable crops damaged by soil-borne diseases, degraded village rangeland
due to overgrazing by the livestock owners, poorly aerated barns where ammonia
concentration is significantly high or well preserved and stored hay, good forage crop
stand with good yield potential, clean, well lighted and aerated barn, drip irrigation used
in vegetable production in plastic tunnels, orchards with modern fruit varieties. These
demonstrations are readily available and needs no expenditures and effort. The important
thing is to agree with the owner farmers to share his experience with the others.
4. The on-farm demonstrations need to be implemented and closely monitored and recorded
from the beginning to the end in order to ensure that the intended technical practices are
demonstrated appropriately. After each demonstration is over (both established and/or
readily available ones), the PTTs should monitor the behavioral change in the villages. In
order to measure the change, a rapid assessment will be conducted in the villages where
demonstrations will be conducted to determine the current practices, and after the
demonstration (after several days/weeks or months) review the practices in the same
village and measure the change. For example it is expected that the PPT should be able to
say that in Village A, before the demonstration program only 11% of the farmers were
producing Hungarian vetch in rotation with wheat but after the demonstrations, the ratio
increased to 15%.
GUIDELINES FOR SUCCESSFUL DEMONSTRATIONS
104
5. New demonstrations should be planned and conducted based on the observations in the
villages. Those farmers who changed their practices and benefited from the advice should
be interviewed and their experience needs to be recorded to be used in the new
programs.
CONDUCTING SUCCESSFUL DEMONSTRATIONS
6. It is important to conduct successful on-farm demonstrations where every operation is
implemented according to the technical norms. A demonstration that reflects technical
knowledge and practice gives vision to the farmers and motivates them to perform better
in order to achieve similar good results in their environment with their resources. There
is nothing worse than an unsuccessful demonstration for a project. The negative impact
left on the farmer requires much repeated effort by the project staff to convince them to
take up the recommended practices later. It should always be kept in mind that the
quality of a demonstration is more important then the quantity, i.e. number of
demonstrations. Therefore, unless the PPTs ensure high quality in all demonstrations with
the available resources (inputs, staff, machinery, etc.), the number of demonstration
plots should be reduced. For crop demonstrations, the plots should be fenced, all
agricultural operations should be carried out at the right time, with the right machinery
and equipment and inputs should be used at the technically recommended rates.
7. It should be noted that demonstrations work best when the cooperating farmer is
representative of the farmers that are targeted. Despite all the positive developments, the
planned and expected results may still not be achieved without a good cooperator farmer.
Selection of the demonstration site is as important as selecting the cooperating farmer.
The fields, orchards, greenhouses, barns/sheds of the candidate cooperating farmers need
to be visited and assessed as regards whether these are appropriate for holding a
demonstration. Following aspects should be considered in selecting the appropriate
cooperating farmer:
• Interest: A farmer showing interest in a demonstration is a good starting
point and being a volunteer may indicate more serious interest. Nevertheless, when
the project staff explain what are expected from him/her during the process, despite
the interest, he/she may not be willing to commit him/herself due to a number of
reasons including the interest shown and/or articulated being limited only to one
aspect of the demonstration such as free seed, free soil preparation, or even the
larger share of the harvested crop; such limited interest may not be sufficient to
carry the full responsibilities of being the cooperating farmer.
• Collaborative attitude: While a major part of the physical work to establish
the demonstration will be undertaken by the project staff, a number of things still
remain that need to be handled by the farmer who owns the field, orchard or barn
that is used in the demonstration. The staff needs to be sure if potential cooperating
farmers have previously demonstrated collaborative attitudes. Although they may be
well known in the village, the staff must still assess them individually as to whether
he/she is willing to take on the responsibilities that are expected of a cooperator. At
least one house visit should be made to explain: i) purpose of the demonstration
program; ii) the purpose of the specific demonstration to be conducted, and iii)
105
distribution of labor/responsibilities i.e. those that will be undertaken by the project
staff and those expected from the farmer. These would include but not be limited to:
i) allowing the use of field/orchard/barn/greenhouse for a specified period specified;
ii) allocating time and labor when needed; iii) informing the project staff promptly
about the agreed key stages of progress and/or unexpected developments; iv)
protecting the demonstration site particularly from livestock or other intruders; v)
some basic but systematic record keeping as required by the staff, and vi) allowing
others to visit the demonstration site and provide basic information if/when asked.
• Credibility: It is important to select cooperators who are dependable and
honest that should be discreetly ascertained through contacts in the community by
the project staff. Otherwise, there could be a good demonstration that nobody
believes. Selecting an opinion leader is advantageous. However, if there are several
demonstrations in a village, chances are reduced to find an opinion leader for every
demonstration.
• Basic communication skills: The farmers selected for demonstrations have an
important role in farmer-to-farmer extension. Throughout the demonstration period
and in the absence of the project staff, when other farmers stop at the
demonstration site and ask questions, the cooperating farmers should be able to
express/explain what best practices were used in establishing the demonstration.
Therefore, as the cooperator, he/she must be prepared for and be willing to engage
in such continuous communication. Technical staff responsible for the demonstration
would be expected to provide such basic training to the farmer. His/her role will not
be limited to the field days where the results explained to the audience by the
project staff.
• Age: It is important in three aspects: i) attitude towards change, ii) the
energy and effort needed to expend the extra effort required by the demonstrations
iii) communication barriers. Elderly farmers: In traditional rural communities, the
elderly are generally respected as experienced farmers. They also tend to perceive
themselves as “masters” and dislike their ideas and practices being challenged. They
may feel that tradition is threatened: “We have always done it this way” is a
common attitude, implying there is only one way. Trying to change such
predispositions will be difficult and time-consuming bringing with it the risk of giving
them the responsibility of collaborating on a demonstration. Furthermore and due to
age, their energy may not be enough to handle the work including continuous
interaction with technical staff or other inquisitive farmers. Additionally, young
farmers may be reluctant to entering into discussions with the “masters” thus
preventing the new ideas/practices from reaching the younger groups through
demonstrations. Consequently it is advisable to avoid selecting those above the age
of 50. Young farmers: Working with them is an advantage because they have the
energy to handle the additional work and although there may be differences in
attitude and openness to change, in general they are more open and, more
importantly, they recognize the need for change faster. However, in the eyes of the
older farmers, credibility of the very young farmers is low in terms of being
recognized as a “real” farmer. Asking questions to them may deflate the ego of the
106
older farmers thus reducing the outreach potential of the demonstration. So in this
case, the project staff should refrain from working with those very young farmers
below the age of 25. Medium-age individuals between 25 and 45 and is the least
risky group to work with due to the above-mentioned demerits of the older and
younger.
• Gender: Depending on the traditional division of labor in the production of
different crops or in agricultural activities in the Project area, the team will need to
work with both women and men farmers. In crop production for example, men
generally prune the fruit trees or cultivate the soil for wheat or alfalfa; therefore the
collaborators have to be male. For any demonstration designed for vegetable
production, women have to be selected as the cooperating farmers. There are also
activities where women and men work together such as greenhouse (plastic tunnel)
production, so the team may select either as counterpart. For livestock-related
demonstrations, those on barn/milk hygiene, feeding/watering could be conducted
with women and on grazing practices, with men.
• Agreements: A “demonstration agreement” should be prepared by the project
staff that clearly includes the objective and the duration of the demonstration, an
action plan, and clear indication of the responsibilities for the variety of tasks, and
how the harvest will be used. This is necessary in order to: i) achieve timely and
effective application on the ground; ii) avoid loss of resources allocated for the
demonstration; iii) prevent an unsuccessful demonstration resulting in
embarrassment, and more importantly, loss of confidence in the whole program, and
iv) prevent friction or dispute with the collaborating farmer. The team will prepare a
standard format in advance to be used for all demonstrations. All involved parties i.e.
the project staff, cooperator farmer and muhtar will sign it and each will be given a
copy. While perhaps not a legally binding document, it will indicate the seriousness
of intent to the community/village where the demonstration is carried out.
• Inputs: The inputs (seeds/seedlings, pesticides, veterinary drugs and
chemicals, fertilizers, artificial insemination, material, plastic cover for plastic
tunnels, drip irrigation pipes and hose, fencing material, etc.) and the agricultural
machinery and equipment for the demonstration must be provided by the project
staff. Provisions for these have been made in the Project. It should be noted that the
inputs are provided for the purpose of demonstration not as a donation to the poor
farmers; the economic status of a farmer shall not be a criteria for their selection as
a cooperating farmer. Therefore, the amounts of the inputs need to be calculated
based only on the size/scale of the demonstration. For crop demonstration 1-2 da
will be sufficient. The cooperating farmer would be required to provide labor as
needed as well as be expected to provide a tractor and small
tools/equipment/implements that would be commonly available on a farm. In some
cases (e.g. orchard establishment, installing drip irrigation), there may be a need for
a guard for a certain period and if the host farmer cannot provide this, an outsider
could be hired as guard from the demonstration budget until the demonstration
becomes self-sustaining.
107
8. For crop demonstrations, the plot must represent a typical farm plot in the area in terms
of soil type and depth, land capability class and water availability etc. This will convince
the farmers targeted that if best practices are followed, similar results could be achieved
on other similar plots. The conditions must not be superior to that of other farms in the
area and for the success of the demonstration problematic areas/land has to be
eliminated. Farmers are generally good at judging if the results on the demonstration plot
will work on their farms. For livestock demonstrations similar principles should be applied.
9. It is essential that the farm and/or demonstration plots be located in reasonably close
proximity to a road or a public facility where large numbers of farmers regularly pass by.
Legible signs must be posted to ensure that neighboring farmers understand what is
being demonstrated so they can observe the change throughout the growing season. The
plots should also be located so that it is easy to transport farmers, local administrators,
input dealers and other influential groups during field days that must be held at all critical
stages of any demonstration, i.e. soil preparation, sowing, fertilizer/chemical application,
barn disinfection, animal hygiene practice, etc.
10. New/additional demonstrations in any village should be planned and conducted based on
earlier results. Those farmers who changed their practices and benefited from the advice
should be interviewed and their experience recorded that may be used as case study
material in the extension programs.
11. Depending on the objective of the demonstration, it is recommended to plan and design
them to: i) show before-and-after, control-versus-test, side-by-side comparisons; ii)
expose farmers to only one or two treatment/practice, or to whole package of practices,
and iii) conduct one-year (e.g. wheat cultivars, seedbed preparation) or multi-year (e.g.
crop rotations, tree crops, livestock feeding).
12. It is important to keep a “Demonstration Record Book (DRB)” for each demonstration
that also includes a sequenced photographic record of the activities (Box 1, 2 and 3). The
Book has to include a hand drawn site sketch and also a field plan indicating the
treatments. All this information should not be kept only by one staff member. It has to be
available the all project stakeholders. Anyone who wants to visit the demonstration can
use this information without the necessary presence of the PPTs. DRB is also useful in: i)
giving information to the public; and ii) evaluating the results. In case of staff turnover,
these records would ensure continuity.
108
Box 1. DEMONSTRATION RECORD BOOK
1) Name of the demonstration: Winter wheat fertilizer demonstration under
rainfed conditions
2) Cooperator farmer: Ali Bayrak (age 42)
3) District and the village: Selim, Aşağıdamlapınar
4) Size of the demonstration: 40x50 m=2000 m2
5) Soil type: sandy loam
6) Irrigation: no
7) Implementation:
Production operations Explanation/Comment
Soil tillage (equipment, date, no of tillage, tillage depth)
Seedbed preparation (preparation date, machinery and
equipment used)
Seeding (source of seed, rate as kg/ha)
Wheat Variety
Fertilizer applied at seeding (type, rate as kg N/ha and kg
P2O5/ha, date)
Pesticides used for diseases and pests (application rate and
date, and application method)
Spring fertilizer application (type, rate as kg/ha, application
date)
Weed control (herbicide used, application rate and date)
Harvest
8) Yield/ha (as grain and straw)
9) No. of field days organized and dates:
10) No. of farmers visiting the demonstration:
11) No. of farmers applying the same technique in the village (succeeding year)
110
LOGICAL FRAMEWORK
Results Hierarchy Verifiable Indicators Means of Verification Assumptions
Goal Reduced poverty among the upland communities
of the Murat river watershed. Number of village HHs living below the poverty line reduced (10%). Official statistics, Baseline (MCP)
and impact assessment studies. Government maintains and pursues pro-poor
policies. No extreme economic, seismic, or climatic
shocks. Development Objective
Improved livelihood and natural resources
management in the upper catchment areas in the Murat watershed.
30% increase in vegetative cover in treated micro-catchments, three
years after project completion (include tree survival rate).
80% of participating families have improved livelihood (nutrition, income, reduced workload).
10% reduction in government expenditures on rehabilitation of public works damaged due to floods and landslides.
GIS –based data collection including
photos.
Vegetation plot/afforestation data Social survey.
Improved livelihood measured by
nutritional diet, income and women workload.
Provincial records.
Existing forestry and natural resource policies
are improved & enforced.
Infrequent staff turnover.
Components/Outcomes 1. Natural resources and environmental management 1.1 Environmental awareness enhanced in
MC communities. ▪ 50% of villagers in targeted micro catchment areas have agreed to
MC management plans. ▪ OGM records.
▪ Baseline survey.
▪ Impact assessment. ▪ Meeting attendance and minutes.
Awareness raising effective.
1.2 Modalities for participatory &
sustainable natural resource management operational.
▪ Consensus in planning and management decision-making is reached through participatory processes with equal gender representation
and inclusion of vulnerable groups.
Existing village and OIM structures for
decision making allows for the establishing effective modalities for NRM co-
management.
2 Investments in natural resources and environmental assets
2.1 Rehabilitation of soil and vegetation.
2.1.1. Soil erosion reduced. 10% reduction in sediment load from selected micro catchments. ▪ Sediment traps.
▪ Erosion field plots. ▪ Vegetation field plots. ▪ OGM records.
Physical conditions (soil, rainfall) and
management practices (fire wood collection, livestock rearing) adequate for soil and
vegetation rehabilitation. 2.1.2. Vegetative/forest cover increased. 20% reduction in erosion from treated areas.
2.1.3. Improvements in grazing/rangeland. 30% increase in vegetation cover in rangelands.
2.2. Improved livestock productivity due to
improved access to clean water. 75% of livestock in rangeland benefit from water points (possible proxy:
livestock mortality). ▪ OGM/PPT records
▪ Social surveys Improved water access translates into better
livestock management.
111
LOGICAL FRAMEWORK (CONT’D)
3 Investments in improved livelihood
3.1. Diversified and more efficient use of energy.
3.1.1. Fuel wood consumption reduced. 30% reduction in annual HH fuel wood use. ▪ OGM/PPT records. Improved energy efficiency leads to reduced
use of fuel wood. 3.1.2. Energy saving technologies adopted. 25% increase in number of HH using renewable technologies.
3.2. Improved agricultural productivity.
3.2.1. Improved stables and livestock
management. 20% productivity increase per livestock head ▪ HH and focus group interviews.
▪ PPT records.
▪ HH and focus group interviews.
Villagers demonstrate an interest and are
willing to invest in new management practices
Sufficient water availability. Possible to provide sufficient no. of villagers
without irrigation access to irrigation.
3.2.2. Output from horticulture, orchards,
forage and field crops increased. 10% increase in rain fed crop production and yields/ha.
30% increase in overall value for irrigated crop. 3.2.3 Increased access to irrigation for
horticulture/agriculture, forage and
orchards).
20 % increase of number of households with access to irrigation.
Outputs 1 Natural Resources and Environmental
Management
▪ NRM awareness raised in MC communities.
▪ 25 MC plans produced with operational modalities for
participation.
▪ Staff trained in NR and environmental management
including: Multifunctional
participatory planning; participatory monitoring & data management;
poverty and gender sensitization ▪ Studies and workshops in: NR
economics; carbon sequestration;
energy efficiency and alternative energy sources
▪ Percentage of villagers in MC area taking part in preparing MC plans.
▪ Selected elements in the MC plans are NRM oriented.
▪ Numbers of plans produced (pro-poor/gender sensitive/ participatory).
▪ Number of TA contracts, workshops and training.
▪ OGM, OBM, OIM staff and PPT attendance and results.
▪ Supervision reports.
▪ OGM records.
▪ Audits.
▪ OGM records. ▪ Post training test/evaluation
charts.
▪ Procurement systems in place and functioning.
▪ Sufficient Government counterpart funds available in a timely manner.
▪ No community segment excluded from participating.
▪ Beneficiaries accept terms of cost
sharing.
2 Investments in Natural Resources
Soil conservation works (9 000 ha).
Forest and rangeland rehabilitation
and afforestation (22 160 ha).
Two public nurseries completed in
Elazığ and Muş.
Erosion measurement field trials
installed (25).
Sediment measurement stations
Soil conservation investments effective.
Forests rehabilitated (% increase vegetation cover), afforestation
(number of trees/survival rate).
Rangelands rehabilitated (ha. and % increase in vegetation cover):
o No. of livestock drinking facilities operational; and
o No. of shelters for communal use operational.
Public nursery that includes cold storage for seedlings developed
(production increase).
Erosion/sediment measurement.
MFWR records/photo (time and
GPS marked).
Audits.
Data collected for erosion/water
run-off/sediment yield.
OGM pursue best practices for NRM and erosion control
OGM and village collaboration in operation and data handling
OGM and village collaboration in
operation and data handling
112
installed (25).
Erosion field plots and gully erosion (stick measurement) operational
and participatory.
Sediment measurement stations operational.
113
LOGICAL FRAMEWORK (CONT’D)
3 Investments in Improved Livelihood
Demonstrations and farmer training events (308).
Farmer exposure visits (292).
Improved wheat and barley production (1 381 ha).
Improved forage crops (1 230 ha).
Improved horticultural production
(247 ha) including 180 ha of new orchards.
Water storage ponds built and connecting earth canals rehabilitated
(250).
Drip irrigation installed (127 ha).
New contracted seedlings producers
operational and selling (4).
New solar panels installed and in use
(1 250 hh’s).
Insulation (625hh’s).
Energy saving stoves installed (1 250 hh’s).
Improved stables (100).
Demonstration and farmer training program conducted (number of participants).
Farmer exposure visits carried out (number of participants).
Sustained increase in grain yields (%).
Sustained increase in forage crop production (%).
Sustained increase in horticultural production (%).
Small scale irrigation developed: o Water storage ponds functioning (increase in water collection);
and
o Increase in water supply from rehabilitated earth canals (%).
Increase in crop yield and value from irrigated land (%).
Contracted seedling production introduced as a profitable business model.
Energy saving technologies (solar, insulation and stoves) has led to
reduced fuel consumption. Increases revenues from increased yield o meat and milk and savings
from less disease.
Supervision reports.
OGM records. PPT records.
Audits.
Number of trees in orchards and survival rate (OGM records).
PPT records.
Number of seedlings produced/ revenues.
(Sale Record.)
Fuel consumption (PPT record/ survey).
PPT records.
Village communities interested in participating in training/exposure.
Sufficient land available and farmers
interested in applying new technologies.
(Improved crop production, crop rotations
and soil conservation measures.)
Interest to engage in seedling production.
Possible to produce seedlings at competitive prices sufficient demand for
seedlings.
Improved efficiency translates into less use of fuel.
Existing stables have negative impact on livestock production and health.
Inputs USD million
Civil Works 23 901.4
Vehicles, Equipment, and Goods 13 109.8
Technical Assistance, Training, Studies
and Workshop 6 164.8
Operational Expenses and Salaries 1 608.2
Total 44 784.2