Project finance
-
Upload
amit-gaurav -
Category
Economy & Finance
-
view
98 -
download
1
Transcript of Project finance
![Page 1: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/1.jpg)
Project FinanceFeatures
![Page 2: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/2.jpg)
Ideal Venture for Project Finance
Independent economic entities
Completion without undue uncertainty
Generate adequate revenues
Significantly worth more on completion
![Page 3: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/3.jpg)
Characteristics Creation of separate entity
Equity Holding Pattern
Non Recourse Debt
Leverage
Contractual Structure
![Page 4: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/4.jpg)
Project Financing Technique SPV Way Forward
Promoter Equity 15-30% (sponsors contribution)
The Risk Shield› Non recourse› Sans Recourse
![Page 5: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/5.jpg)
Project Financing Technique Viability Gap Funding Mechanism Grant Can’t exceed 40% of project cost) Positive grant Negative grant
› SPV is L&T Vadodara Bharuch Tollways Ltd
› Negative grant of Rs. 471 crore that would be paid to the National Highways Authority of India (NHAI) by L&T.
![Page 6: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/6.jpg)
Project Financing Technique
Contractual Agreements
Lenders Wisdom
Legal advisor responsibility to advise› Appropriate risk allocation› Robust legal and structural framework
![Page 7: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/7.jpg)
Structure Promoters Lenders Borrowers Equipment Providers EPC Contractors Fuel Supplier (Input Supplier) Consultants Product off takers as output buyers Insurance companies providing cover Operations maintenance operators
![Page 8: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/8.jpg)
SPV & Balance Sheet Funding
Type of project Recourse D/E Ratio Equity Funding Project Implementation Risk
![Page 9: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/9.jpg)
SPV & Balance Sheet Funding
Project Size Cost of Funding Third party Investment Separation of Cash Flows Degree of scrutiny
![Page 10: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/10.jpg)
Infrastructure Finance INDIA Public Private Participation
Conceding Authority Concessionaire Concession Period Concession Agreement
![Page 11: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/11.jpg)
PPP Projects BOT
BOOT
DFBOOT
BOO
![Page 12: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/12.jpg)
PPP India
PPP Experience in INDIA
And
Viability Gap Funding (VGF
![Page 13: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/13.jpg)
Disadvantages Huge Third Party Costs
Time Consuming Process
High Cost Project Debt
Stringent Covenants
![Page 14: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/14.jpg)
Project Finance Phases Developmental Phase
Completion Phase
Operation Phase
![Page 15: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/15.jpg)
Project Finance Risks Risk To Lenders
Reallocation of risks
Highest upto Commercial Operations date
![Page 16: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/16.jpg)
Stakeholders Equity investors
Lenders
Input Suppliers
Output Buyers
![Page 17: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/17.jpg)
Managing Risks Identification of risks Assessment of the possibilities Elimination of impact or quantification of risk Determination of level of risks Deciding acceptance level of risks Risk control measures Monitoring through approved process/mechanism
![Page 18: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/18.jpg)
Mitigation of Risks
Avoidance Provision for contingency Prevention Reduction Transference Acceptance
![Page 19: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/19.jpg)
Risk Phases
Development Phase Risk› Borne by promoters› No risk to lenders
Construction Phase Risk
Operational Phase Risk
![Page 20: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/20.jpg)
Development Phase Risk
Joint venture agreement among promoters
Elaborate project development agreement
Environment clearances Equity IPO and strategic investors Loan against future cash flows
![Page 21: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/21.jpg)
Development Phase Risk
Approval of licenses Technology risks Experienced professional Services Turnkey EPC Fuel Supply And Transportation
agreements
![Page 22: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/22.jpg)
Construction Phase Risk Lenders Risk Funding Risk Sponsoring Risk Mitigation through
gearing Pre disbursement Conditions Grievances handling through Mutual
Considerations
![Page 23: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/23.jpg)
Construction Phase Risk
Technology risks mitigation through EPC contractors
Contingency risks Equipment performance risks cover
given by manufacturers
![Page 24: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/24.jpg)
Project Finance Appraisal
Due Diligence Promoters, their capabilities, credit
worthiness, experience Project structure, time taken Technical feasibility Commercial analysis Infra Requirements
![Page 25: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/25.jpg)
Project Finance Appraisal
Legal and regulatory clearance Project cost Financing plan and strategy Risk analysis Risk mitigation proposals Financial Model Credit enhancement mechanism
![Page 26: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/26.jpg)
Process of Appraisal Evaluation of investment decision Free cash Flow for assessing project
› Payback period› NPV› IRR› ENPV› Decision Tree Analysis› TVM
![Page 27: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/27.jpg)
Internal risk management Internal Credit Risk Rating
Differ from bank to bank
Risk validation
Separate risk rating mechanism
![Page 28: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/28.jpg)
Major areas of evaluation Management Analysis
› Past Track Record› Managerial Competence› Financial Strength› Project Team› Financial performance of group,
Promoters(willful default)› CDR Mechanism
![Page 29: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/29.jpg)
Technical Evaluation› Feasibility Study› Outsourcing› TPC
Land Building Equipment Working Capital Provisional Expenses Interest
![Page 30: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/30.jpg)
Financial Viability› Equity, Debt
Pure Rupee debtForeign Currency DebtSubordinate DebtMezzanine Debt
Financing PatternCost of projectMeans of financingStable debt equity gearingFinancial structuring of debt
![Page 31: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/31.jpg)
Market Assessment› Industry Profile
› Demand –Supply Position
› Competition Level
› Absorption Capacity of market
› Promoter’s Track record in marketing
› SWOT
Social Impact› Society
› Employment
› Self Sufficiency
![Page 32: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/32.jpg)
Ecological Analysis› Environment Damage› Corporate Governance
![Page 33: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/33.jpg)
Contractual Framework
Lenders and SPV› Borrower SPV and EPC Contractor› SPV and Fuel/RM Supplier› SPV and Project Management Consultant› SPV and buyer of SPV’s goods/services
![Page 34: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/34.jpg)
![Page 35: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/35.jpg)
Follow up of Project Finance
![Page 36: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/36.jpg)
Cash Flows Trust and Retention Account (TRA)
![Page 37: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/37.jpg)
![Page 38: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/38.jpg)
Project Documentation Concession/License Agreement Shareholders Agreement EPC Contract Operations and maintenance Contract Financing Documents Common Loan Agreement Inter Creditor Agreement
![Page 39: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/39.jpg)
Disbursement and Monitoring
Disbursement of project loans › Drawdown Payments› Ensuring End use
Disbursement for Loan for Tractor Disbursement for power plant
Monitoring in construction phase
![Page 40: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/40.jpg)
Network Technique
Network technique used in project implementation
CPM and PERT
![Page 41: Project finance](https://reader035.fdocuments.net/reader035/viewer/2022081520/58f21e991a28abf7228b458d/html5/thumbnails/41.jpg)
Monitoring, supervision and follow up of project finance loans
LIE Services in operations Phase O&M activity is critical Monitor revenues and TRA Temporary Revenue Maintenance Interest rate dates Consortium Meetings Insurance policies