Project feasibility report -...
Transcript of Project feasibility report -...
0
PRE FEASIBILITY REPORT
For
PROPOSED SPECIALTY CHEMICALS PLANT IN EXISTING
PREMISES
of
M/s. BROMCHEM LABORATORIES PVT. LTD.
SURVEY No. 295, VILLAGE: LUNEJ, TAL: KHAMBHAT, DIST:
ANAND, GUJARAT
1
CONTENTS
Sr. No. Description Page No.
1. Executive Summary 2
2. Introduction of the Project/Background information 9
3. Project Description 10
4. Site Analysis 14
5. Planning Brief 25
6. Proposed Infrastructure 27
7. Rehabilitation and resettlement (R & R) Plan 28
8. Project Schedule & Cost Estimates 28
9. Analysis of Proposal (Final Recommendations) 29
2
1.0 EXECUTIVE SUMMARY
1.1 Company Profile
M/s. Bromchem Laboratories Pvt. Ltd. have proposed for expansion of Chemicals
manufacturing unit at survey no. 295, Village: Lunej, Tal: Khambhat, Dist: Anand, Gujarat.
Proposed expansion will be carried within the existing unit having land area of 6981 m2.
Total project cost is Rs. 4.5 Crores.
1.2 Project Details
1.2.1 Products along with Production Capacity
Sr. No.
Product Existing Capacity (MT/Month)
Proposed Capacity (MT/Month)
1. Potassium chloride 400 Max. 1 product
400 Max. 1 product
2. Calcium chloride 3. Barium chloride 4. Zinc chloride 5. Potassium bromate 100
Max. 1 product 100 Max. 1 product 6. Sodium bromate
7. Potassium bromide 70 Max. 1 product
70 Max. 1 product
8. Sodium bromide 9. Calcium bromide 10. Ammonium bromide 11. Sodium carbonate 100
Max. 1 product 100 Max. 1 product 12. Potassium carbonate
13. Sodium phosphate 300 Max. 1 product
300 Max. 1 product
14. Potassium phosphate 15. Dicalcium phosphate 16. Tricalcium phosphate 17. Sodium sulphate
200 Max. 1 product
200 Max. 1 product
18. Potassium sulphate 19. Copper sulphate 20. Zinc sulphate 21. Chloroacetyl chloride ‐‐ 80 22. Benzoyl chloride ‐‐ 310 23. Pivaloyl chloride ‐‐ 40 24. Propionyl chloride ‐‐ 80 25. 2‐chloropropionyl chloride ‐‐ 40 26. Butyryl chloride ‐‐ 40
3
By‐Products
27. Isobutyryl chloride ‐‐ 40 28. 4‐Chlorobenzoyl chloride ‐‐ 40 29. 2‐chlorobenzoyl chloride ‐‐ 40 30. Velaryl chloride ‐‐ 40 31. 3‐chloropropionyl chloride ‐‐ 40 32. 4‐chlorobutyryl chloride ‐‐ 40 33. 4‐methoxybenzoyl chloride ‐‐ 25 34. 3‐methoxybenzoyl chloride ‐‐ 25 35. 3‐chlorobenzoyl chloride ‐‐ 25 36. 2,3‐Dichlorobenzoyl chloride ‐‐ 25 37. 2,4‐Dichlorobenzoyl chloride ‐‐ 25 38. 3,4‐Dichlorobenzoyl chloride ‐‐ 25 39. 3,5‐Dichlorobenzoyl chloride ‐‐ 25 40. 4‐methylbenzoyl chloride ‐‐ 25 41. 2‐methylbenzoyl chloride ‐‐ 25 42. Isophthaloyl chloride ‐‐ 20 43. N‐butyl chloride ‐‐ 20 44. Isobutyl chloride ‐‐ 20 45. N‐Hexyl chloride ‐‐ 20 46. Propiophenone ‐‐ 20 47. 3‐chloropropiophenone ‐‐ 20 48. Benzophenone ‐‐ 20 49. 4‐chlorobenzophenone ‐‐ 20 50. 2,4‐dichloroacetophenone ‐‐ 20 51. Valarophenone ‐‐ 20 52. Trityl chloride ‐‐ 50 53. Acetanilide ‐‐ 20 54. Triethylamine hydrochloride ‐‐ 21 55. 2,4,6‐Trichloropyrimidine ‐‐ 20 Total 1170 2536
Sr. No.
Product Existing Capacity (MT/Month)
Proposed Capacity (MT/Month)
1. HCL (30 % ) ‐‐ 872
2. Sodium Bisulfite ‐‐ 1772
3. Aluminum Chloride Solution ‐‐ 396
4
1.3 Raw Material Requirement
Sr. No.
Raw Material Required
Existing Consumption (MT/Month)
Proposed Consumption (MT/Month)
1. Potassium hydroxide 818 818 2. 30% Hydrochloric acid 1570 1570 3. Calcium oxide 222 222 4. Calcium hydroxide 743 743 5. Barium oxide 294 294 6. Zinc oxide 339 339 7. Bromine 202 202 8. Sodium hydroxide 460 460 9. 50% Hydrobromic acid 226 226 10. Ammonium carbonate 25 25 11. 30% Phosphoric acid 2262 2262 12. 50% sulfuric acid 990 990 13. Copper oxide 100 100 14. Monochloroacetic acid (MCA) ‐‐ 84 15. Benzotrichloride ‐‐ 509 16. Pivalic acid ‐‐ 34 17. Thionyl chloride ‐‐ 640 18. Sodium hydroxide ‐‐ 1434 (15%) 19. Propionic acid ‐‐ 64 20. 2‐Chloropropionic acid ‐‐ 34 21. Butyric acid ‐‐ 33 22. Isobutyric acid ‐‐ 33 23. 4‐Chlorobenzoic acid ‐‐ 36 24. 2‐Chlorobenzoic acid ‐‐ 36 25. Valeric acid ‐‐ 34 26. Acrylic acid ‐‐ 23 27. Gamma‐butyrolactone ‐‐ 25 28. 4‐Methoxybenzoic acid ‐‐ 22 29. 2‐Methoxybenzoic acid ‐‐ 22 30. 3‐Chlorobenzoic acid ‐‐ 22 31. 2,3‐Dichlorobenzoic acid ‐‐ 23 32. 2,4‐Dichlorobenzoic acid ‐‐ 23 33. 3,4‐Dichlorobenzoic acid ‐‐ 23 34. 3,5‐Dichlorobenzoic acid ‐‐ 23 35. 4‐Methylbenzoic acid ‐‐ 18 36. 2‐Methylbenzoic acid ‐‐ 18 37. Isophthalic acid ‐‐ 16 38. N‐Butanol ‐‐ 16
5
39. Isobutanol ‐‐ 16 40. N‐Hexanol ‐‐ 17 41 Aluminium chloride ‐‐ 104 42. Benzene ‐‐ 65 43. Propionyl chloride ‐‐ 14 44. 3‐Chloropropionyl chloride ‐‐ 15 45. Benzoyl chloride ‐‐ 28 46. 1,3‐Dichlorobenzene ‐‐ 16 47. Acetyl chloride ‐‐ 21 48. Valeryl chloride ‐‐ 15 49. Aniline ‐‐ 14 50. Triethylamine ‐‐ 15 51. Barbituric acid ‐‐ 14
6
1.4 Water Requirement, Waste Water Generation and Treatment
Total water requirement will be 45 m3/day which will be met through Ground Water. Total
wastewater generation will be 8.8 m3/day. The industrial effluent (6.3 m3/day) will be
treated in proposed ETP consists of primary & tertiary treatment facility & then it will go to
CETP for further treatment.
Domestic Waste water (2.5 m3/day) will be disposed by septic tank & soak pit.
1.5 Air Pollution Source and Control Management
There will be emission from Thermopack & Steam Boiler, D.G. Sets and Process Vents. To
control the emission from process vents, adequate scrubbers will be installed.
Existing: 1. Details of Flue Gas Stack; Stack Attached To Furnace
SOURCES OF GASESOUS EMISSION STACK
Fuel Used Agro Waste/Coal
Type of Emissions SO2 NOx SPM
Permissible Limits 262 mg/Nm3 94 mg/Nm3 150 mg/Nm3
Stack Height 10 meters
Proposed ‐ Flue Gas Emission 2. Details of Flue Gas Stack; Stack Attached To Thermopack Boiler
SOURCES OF GASESOUS EMISSION STACK
Capacity 6 Lack KCal /Hr
Fuel Used Agro Waste/Coal
Type of Emissions SO2 NOx SPM
Permissible Limits 262 mg/Nm3 94 mg/Nm3 150 mg/Nm3
Stack Height 30 meters
Stack Diameter at the Top 600 mm Control Measures Cyclone Separator with dust collector
7
3. Details of Flue Gas Stack; Stack Attached To Steam Boiler
SOURCES OF GASESOUS EMISSION STACK
Capacity 1 TPH
Fuel Used Agro Waste/Coal
Type of Emissions SO2 NOx SPM
Permissible Limits 262 mg/Nm3 94 mg/Nm3 150 mg/Nm3
Stack Height 30 meters
Stack Diameter at the Top 600 mm
Control Measures Cyclone Separator with dust collector
4. Details of Process Vent ; Vent Attached To Process Sr. No. Stack attached to Stack Height Air Pollution
Control System Parameter Permissible Limit
Proposed 1 Process Vent
(Chlorination Plant) 11 m Three Stage
Scrubber HCl SO2
20 mg/Nm3 40 mg/Nm3
2 Process Vent
11 m HCl
20 mg/Nm3
8
1.6 Hazardous Waste
TYPE OF WASTE SCHEDULE
CATEGORY
SOURCE QUANTITY DISPOSAL METHOD
ETP Waste
34.3
ETP 17 MT/ Month Collection, Storage, Transportation & Disposal to TSDF Site
Used Oil
5.1 Plant & Machinery
5 LITERS/ Month Collection, Storage, Transportation & Sale to GPCB Authorized Recycler
Discarded Containers/
Bags/ Carboys
33.3 Process 500 NOS. Decontamination, Storage & Given to GPCB Registered Vendor
Distillation Residue
20.3 Process 12 MT/ Month Collection, Storage, Transportation, Disposal by Incineration at CHWI of NECL OR CO‐Processing in Cement
Industries Fly Ash ‐‐ Boiler 17 MT/ Month Will be sold to Brick Manufacturers
HCL (30 % ) ‐‐ Process 872 MT/Month Captive Consumption
Sodium Bisulfite ‐‐ Process 1772 MT/Month Will be sold to end user.
Aluminum Chloride Solution
‐‐ Process 396 MT/Month Will be sold to end user.
1.7 Green Belt Maximum open land will be provided for green belt development. Total green belt area will be 2303 m2 (approx. 33%) of total land area.
1.8 Power & Fuel Requirements
S. No. Particulars Requirement Power 1 Power Requirement 150 KVA 2 Source of Supply MGVCL Fuel 1 Fuel & IT’S Consumption Agro Waste ‐ 5 MT/Month OR Coal ‐ 4 MT/Month
Diesel ‐ 150 Liter/Day (Emergency) 2 Source of Supply Nearest Supplier
9
2.0 INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION
2.1 Identification of the project and project proponent. In case of mining project, a copy
of mining lease/letter of intent should be given.
Identification of the project Proposed Specialty Chemicals plant in Existing Premises Identification of the project proponent The detail of project proponent is as below: 1. Mr. Raman A. Patel: He is B.Sc. (Chemistry). He has experience of 30 years as analytical
chemist & Production Support. 2. Mr. Mayaben R. Patel
2.2 Brief description of nature of the Project
Proposed Specialty Chemicals plant in Existing Premises 2.3 Need for the project and its importance to the country and or region
There is a good potential for us to fulfill the need of domestic market as well as contribute
in earning foreign Exchange.
2.4 Demands‐Supply Gap
Based on our informal survey of the market with our current customers and various traders,
we have found that there is a big potential for the range of the products we are planning.
2.5 Imports vs. Indigenous production
Based on the current cost of indigenous raw materials and the non availability of some
materials, we will have to import some of the key raw materials as they are not available
indigenously. This will make us very competitive against imported finished products and we
will export our finished products in the international market.
2.6 Export possibility
We shall explore the possibility of export (100%) the products.
10
2.7 Domestic/Export Markets
Our products have good demand in international market. We shall explore the possibility of
export (100%) the products.
2.8 Employment Generation (Direct and Indirect) due to project.
M/s. Bromchem Laboratories Pvt. Ltd. will give direct employment to local people based on
qualification and requirement. In addition to direct employment, indirect employment shall
generate ancillary business to some extent for the local population.
3.0 Project Description
3.1 Type of Project including interlinked and interdependent projects, if any.
No interlinked project has been submitted.
10
3.2 Location (map showing general location, specific location and project boundary & project site layout) with coordinates.
• Map showing general location
12
Plot Layout
N
Parking
D.G. Set
2.5 m
73 m
12 m
100.5 m
13.5 m
37.2 m
78.18 m
40.79 m
Office
Cooling Tower
Tank Farm Area Raw Materials
& Products ‐ Storage Area
Boiler
Coal/Agro Waste Storage
Proposed Manufacturing Unit
Existing Manufacturing Unit
Proposed Manufacturing Unit
ETP
13
3.3 Details of alternate sites considered and the basis of selecting the proposed site,
particularly the environmental considerations gone into should be highlighted.
Major factors involved in the selection of site are listed below:
• Site is very well connected by road
• Proximity to Raw Material suppliers
• Availability of sufficient land free from cultivation
• Availability of power evacuation facilities
• Availability of water for industrial use Modern infrastructure support and amenities at par with industrial estates in other global markets, including: Efficient transport facilities within the industrial estate and to & fro the city area. Environment‐friendly zone. Uninterrupted power supply.
3.4 Size or Magnitude of Operation
Please refer Section‐1.2.1, Page No. 2.
3.5 Project Description with process details (a schematic diagram/flow chart showing the
project layout, components of the project, etc. should be given)
Please refer Please refer Form‐I, Annexure‐2A.
3.6 Raw Material required along with estimated quantity, likely source, marketing area of
final product/s, mode of transport of raw material and Finished product.
For raw material required along with quantity; Please refer Section‐1.3, Page No. 3.
We shall procure the raw material as much as possible from domestic market and if there is
no availability of any raw material we will import. We shall explore the possibility of export
(100%) the finished products.
3.7 Resource optimization/recycling and reuse envisaged in the project, if any, should be
briefly outlined.
It will be incorporated in EIA Study.
3.8 Availability of water its source, energy/power requirement and source should be given. Water Source
Total water requirement shall meet through Ground Water.
14
Power & Fuel Requirement Power required from MGVCL is 150 KVA. Fuel Requirement: Fuel for proposed boiler: Agro Waste ‐ 5 MT/Month or Coal ‐ 4 MT/Month
Diesel ‐ 150 Liter/Day (Emergency)
3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their management/disposal. Please refer Form‐I, Annexure‐IV & V.
3.10 Schematic representations of the feasibility drawing which give information of EIA purpose.
4.0 Site Analysis
4.1 Connectivity
• Site is very well connected by road
• Availability of water, power, etc.
RECONNAISSANCE SURVEY OF EXISTING PLANT ANNUAL REPORT MARKET ASSESSMENT FINANCIAL REPORT PROJECT REPORT
INTRODUCTION
MONITORING OF AIR, WATER & SOIL QUALITY & NOISE LEVELS. DATA ON METEOROLOGY SOCIO‐ECONOMIC STATUS & BASIC AMENITIES. SITE VISITS BY AND INTERVIEWS WITH LOCALS
BASELINE ENVIRONMENTAL
STATUS
ENVIRONMENTAL INFORMATION CENTRE CENTRAL GROUND WATER BOARD GUJARAT POLLUTION CONTROL BOARD (GPCB) PUBLIC HEALTH ENGINEERING DEPT. AGRICULTURE DEPARTMENT FOREST DEPARTMENT IRRIGATION DEPARTMENT EMPLOYMENT EXCHANGE HEALTH CENTER CENSUS DEPT. INDIAN METEOROLOGICAL DEPT.
SOCIOECONOMIC STATUS &
INFRASTRUCTURE
PROPOSED PLANT
FACILITY DESCRIPTION
IMPACTS METHODOLOGY OF
IMPACT ASSESSMENT
IDENTIFICATION & ASSESSMENT OF IMPACTS EVALUATION OF IMPACTS BY MATRIX METHOD
SOURCE OF INFORMATION OVERVIEW OF E. I. A. STUDIES
ACTIVITIES
ENVIRONMENTAL MANAGEMENT PLAN
DESCRIPTION OF EFFLUENT TREATMENT PLAN, AIR POLLUTION CONTROL, HAZARDOUS WASTE MANAGEMENT, GREEN BELT DEVELOPMENT MONITORING PROGRAM
RISK ANALYSIS STUDIES & DISASTER
MANAGEMENT PLAN
SAFETY, HEALTH & ENVIRONMENTAL POLICY, GUIDELINES BY DIRECTOR GENERAL OF FACTORY SAFETY, MINISTRY OF LABOR. CONSEQUENCE ANALYSIS
PREPARATION OF DISASTER MANAGEMENT PLAN
24
4.2 Land Form, Land Use and Land Ownership
It will be incorporated in EIA Study.
4.4 Existing land use pattern (agriculture, non‐agriculture, forest, water bodies (including
area under CRZ)), shortest distances from the periphery of the project to periphery of the
forests, national park, wild life sanctuary, eco sensitive areas, water bodies (distance from
HFL of the river), CRZ. In case of the notified industrial area, a copy of the Gazette
notification should be given.
It will be incorporated in EIA Study.
4.5 Existing Infrastructure
This is proposed project activity in existing premises so now there is only open land.
4.6 Soil Classification
It will be incorporated in EIA Study.
4.7 Climatic data from secondary sources.
Climatic data from primary as well as secondary sources will be incorporated in EIA Study.
4.8 Social infrastructure available.
Various Programs/ Projects related to Social & Economic development of surrounded area
has been planned, which are as follows.
A) Natural Resource Management – The main focus of this program will be to maximize the
yield returns of the farmers through efficient management of existing resources &
extension of new agricultural practices.
1) Integrated Agricultural Growth Project – For improvement and use of the modern
techniques and thereby would certainly contribute to prosperity in the agriculture
sector and reduce the rural poverty by programs like Farmers Training, Nursery
Growing Trainings, Modern agriculture equipment distribution programs etc.
25
2) Animal Husbandry Projects – Various programs like health checkups & treatment,
vaccination program, Anti sterility camps, breed improvement etc. will be carried
out.
B) Income Generation Program ‐
1) Establishment of Self help groups.
2) Rural Entrepreneurship Development Program
3) Handcrafts Development Program
4) Vocational Training
5) Business process outsourcing
C) Health, Education & Infrastructure
1) Aids Awareness Program
2) General Health Camps
3) Innovative Teaching Methods
4) Adult Education
5) Sanitation
6) Infrastructure Development Projects
7)
5.0 Planning Brief
5.1 Planning Concept (type of industries, facilities, transportation etc) Town and Country
planning/Development authority classification.
Type of Industry: Proposed Specialty Chemicals plant in Existing Premises
5.2 Population Projection
It will be incorporated in EIA Study.
26
5.3 Land use planning (breakup along with green belt etc.)
5.4 Assessment of Infrastructure Demand (Physical & Social)
• Employment would be as per prevailing norms of state government for skilled and
unskilled people for the proposed project activity.
• Social Welfare
• Cordial relation with the industry shall be established and representation shall be made
to villagers for help for creation of facilities related to health, education, etc.
Sr. No. Details Dimesion (m x m) Area (m2)
1 Parking 5 x 6 30
2 Office 10 x8 80
3 D.G.Set 5 x 5 25
4 Cooling Tower 10 x 10 100
5 Tank Farm Area 10 x 12 120
6 Raw Materials & Products Storage
Area
18 x 12 216
7 Boiler 5 x 5 25
8 Coal/Agro Waste Storage Area 5 x 5 25
9 Existing Manufacturing Unit 18 x 9 162
10 Proposed Manufacturing Unit‐1 29 x 15 435
11 Proposed Manufacturing Unit‐2 40 x 30 1200
12 Green Belt 45 x 51.17 2303
13 ETP 10 x 10 100
14 Road & Open Area 2160
Total 6981
27
5.5 Amenities/Facilities
It will be incorporated in EIA Study.
6.0 Proposed Infrastructure
6.1 Industrial Area (Processing Area)
Processing Area (Plant facilities, ETP Area and Engineering / Utility Services)
Developed Area: 2047 m2
6.2 Residential Area (Non Processing Area)
Non Processing Area (Green belt, Raw material storage area, finished storage area,
Administration Building, Parking, road and open area)
Area: 4934 m2
6.3 Green Belt
Total 6981 m2 land area is available at site; out of this area about 2303 sq. meter (33 %) area
is covered as greenbelt and other forms of greenery.
6.4 Social Infrastructure
• Power supply by MGVCL
6.5 Connectivity (Traffic and Transportation Road/ Rail/Metro/ Water ways etc)
Major factors involved in the selection of site are listed below:
• Site is very well connected by road
• Proximity to Raw Material suppliers
• Availability of sufficient land free from cultivation and will have single crop pattern
• Availability of power facilities
• Availability of water for industrial use
28
6.6 Drinking water Management (Source & Supply of water)
Total water requirement shall meet through ground water.
6.7 Sewerage System
Sewage pipes would be laid in entire company for the removal and disposal of mainly non‐
harmful liquid wastes from the offices, canteen and domestic waste coming from different
sections of industry. These liquid wastes would be sent to septic tank & soak pit.
6.8 Solid Waste Management
Please refer Form‐I, Annexure‐V. 6.9 Power Requirement & Supply/Source
Please refer Section 1.8, Page No.8 of this report.
7.0 Rehabilitation and Resettlement (R & R) Plan
7.1 Policy to be adopted (central/state) in respect of the project affected including home
oustees, land oustees and landless laborers (a brief outline to be given)
There is no habitation on the proposed project activity area and it is open non‐agricultural
land, so R & R policy is not applicable to this project.
There shall not be displacement of any population in project area. Any major activity that
may lead to resettlement of the people is considered as permanent impact. Hence, there is
no permanent impact on this account. The increasing industrial activity will boost the
commercial and economical status of the locality up to some extent.
8. Project Schedule & Cost Estimates
8.1 Likely date of start of construction and likely date of completion (Time schedule for
the project to be given).
We shall start construction of the project after getting EC & CTE. We shall start
manufacturing after applying for CC&A.
29
8.2 Estimated Project cost along with analysis in terms of economic viability of the
project.
Total Project Cost for proposed project activity is Rs. 4.5 Crores. Capital cost of air & water
pollution control system and environmental monitoring equipments will be Rs. 0.4 Crore.
9. Analysis of Proposal (Final Recommendations)
9.1 Financial and social benefits with special emphasis on the benefit to be local people
including tribal population, if any, in the area.
• Employment would be as per prevailing norms of state government for skilled and
unskilled people for the proposed expansion project.
• Social Welfare shall be done.
• Cordial relation with the industry shall be established and representation shall be made
to villagers for help for creation of facilities related to health, education, etc.