PROJECT FALCON EUROPEAN UTILITY WEEK - Engerati Utility Week... · Airspan NMS Network management...
Transcript of PROJECT FALCON EUROPEAN UTILITY WEEK - Engerati Utility Week... · Airspan NMS Network management...
PRESENTATION OUTLINE
Western Power Distribution and Project FALCON Overview
Communications Requirements and Design
Initial Results
Lessons Learnt
PROJECT FALCON Presentation Outline
K E Y FA C T S : • Wholly owned by
Pennsylvania Power & Light (PPL - NYSE listed)
• 4 UK Distribution Licences
• 7.7 million customers
• 55,000 sq km area
• Largest length UK network 216,000 kms of overhead lines and underground cables, and 184,000 substations
PROJECT FALCON Overview
LOW CARBON
TECHNOLOGIES
LOW CARBON GENERATION
VOLTAGE RISE/DROP VOLTAGE STABILITY HARMONIC IMPACT THERMAL CAPACITY
BI-DIRECTIONAL ENERGY FLOW EQUIPMENT SUITABILITY POWER FACTOR FAULT LEVEL
PROJECT FALCON Overview
PROJECT FALCON Overview
LCNF provides up to £500m to support DNOs in the development of trials of innovative solutions
The fund allows DNOs to develop solutions to integrate new Low Carbon technologies whilst retaining the security, reliability and value for money of the existing network
“Tier 2” provides funding for larger projects through a competition
FALCON was a successful Tier 2 project in 2011
PROJECT FALCON Overview
Load Reduction
Distributed Generation
1. Control of customer demand to increase capacity on the 11kV network through the use of innovative commercial arrangements
2. Control of distributed generation to increase capacity on the 11kV network using innovative commercial arrangements
COMMERCIAL TECHNIQUES
ENGINEERING TECHNIQUES
Dynamic Asset Ratings Automated Load Transfer Meshed Networks Battery Storage
1. Dynamic calculation and utilisation of 11kV asset ratings to free up unused capacity
2. Automatic load transfer between 11kV feeders within primary substations to increase available capacity
3. Creation of a meshed (interconnected) 11kV network in suburban and rural areas in order to maximise capacity 4. Deployment of new battery technologies
PROJECT FALCON Overview
COMMUNICATION REQUIREMENTS
PROJECT FALCON Communication Requirements
Tx 2 oil temp
Tx 1 oil temp
Ambient air temp
IEC 61850
FALCON comms
Falcon router
P341 Tx. DAR relay
CT
CT
CT
IEC 61850
DNP3; NTP?; C37.118
P341 Tx. DAR relay
CT
CT
CT
Proposed D400 RTU
Marlborough Street
Primary TX. DAR
IEEE C37.118
VT
VT
VT
P847 PMU relay
CT
CT
CT IEEE C37.118
VT
VT
VT
P847 PMU relay
CT
CT
CT
Wind sensor
Spee
d
Dir
ecti
on
Solar sensor
Existing D20 RTU
Ampacity
Ampacity
IEC 61850 DNP3
Check clock sync
signal
DNP3
SSH DNP3
Falcon router
Airspan NMS Network
management
NTP
Tollgrade Super
aggregator
iHost Gridkey
aggregator
Tipton Ocker House
Falcon TDMS
Falcon FEP
Existing PoF
Existing FEP
PMU aggregator
IEEE C37.118
DNP3
COMMUNICATION DECISIONS
Substations to have IEC61850 Ethernet to control plant and monitoring at substation sites
Sites connected together using a “WiMAx” radio system using Internet Protocol
1.4 Ghz and 3.5 Ghz frequencies to be used on a test and development licence from the MoD
Backhaul provided by WPD’s existing microwave and fibre optic trunk network
So what does the solution look like…?
PROJECT FALCON Communication Decisions
PROJECT FALCON Substation Detailed Connectivity
S u b s t a t i o n E t h e r n e t
• Primary Substation has dedicated router and switching using rugged substation devices
• Secondary Substation combines functionality into a single rugged pole mountable device
• All substations devices are Ethernet connected
• Engineering laptops have Secure access for configuration/maintenance
PROJECT FALCON WiMax Radio Network
W i M A X R a d i o N e t w o r k :
• Site to site communications will be primarily wireless
• Proposal to use MoD 1.4GHz spectrum, initially on a T&D licence
• AirSpan AirSynergy pico-cells mounted at 9 locations
• Omni Directional coverage • Pole mounted on WPD sites
- max height 15m • Cisco 1.4Ghz CGR1000
Module
INITIAL RESULTS
PROJECT FALCON Initial Results
Initial performance of the radio solution for FALCON is encouraging as we approach completion of the rollout;
Low rate of initial connection failures due to pre-planning and coverage modelling;
Good system performance with: low rates of packet loss/dropouts; Throughput as expected; Low latency (measured approx 10ms/hop, 20-25ms round trip);
Straightforward, repeatable deployment process, allowing use of suitably trained/qualified contractor staff;
Flexible architecture.
CONCLUSIONS/LESSONS LEARNT
Radio Planning Radio Spectrum allocation is critical There is no substitute for field testing
Physical Network
Understand the substation connectivity requirements Physical network can now be decoupled from the application
logic
PROJECT FALCON Lessons Learnt
CONCLUSIONS/LESSONS LEARNT Protocols & Standards
Understand the protocols especially between devices and control centre
Not all devices will comply to required standards Use Case analysis has been vital in identifying issues
System
FALCON has managed to build a usable WiMAX radio based trials system, gathering a significant number of learning points along the way;
A repeatable “formulaic” approach to system rollout has been perfected;
PROJECT FALCON Lessons Learnt
TIMESCALES
2011 2012 2013 2014 2015
Mobilise Design Build Implement Trials Consolidate &
Share
High level Design approved
Low Level Design
approved
Final Report Produced
Trials Data Analysed
Telecoms installation complete
PROJECT FALCON Timescales
PROJECT FALCON Sharing our learning
www.westernpowerinnovation.co.uk
Sharing our learning: Conferences White papers Via our website