Project Fact Sheet 14633J – NB & SB Mainline from Exit 1 to Exit 5 RebuildingI93.com Project Overview Project 14633J addressed the I-93 northbound (NB) and southbound (SB) mainline construction elements to implement the full four lane facility from Exit 1 in Salem to just north of Exit 3 in Windham (approximately 4.8 miles of southbound and 6.1 miles of northbound). This work involved shoulder reconstruction on the median side, establishing the supporting pavement structure, drainage modifications, guardrail, paving, overlay, pavement marking, and signing elements. This project also completed the corridor wide Intelligent Transportation Systems (ITS) implementation from Exit 1 to just north of Exit 5, including integration into the statewide ITS network. Finally, the project also installed Motor Vehicle Detection Systems (MVDS) permanent traffic counting equipment between Exits 1 and 2, and between Exits 2 and 3. The overall project covered approximately 14.4 miles. Construction was completed in the Fall of 2020. Updated January 2021 Project Facts Project 14633J Advertised Date October 1, 2019 Award Date January 22, 2020 Start Construction Date Spring 2020 Completion Date Fall 2020 Bid Price $6.84 M Total Construction Cost 1 $7.43 M Construction Funding $200 M TIFIA Loan and Federal Funding Contractor Pike Industries, Inc. 1 Includes bid plus inspection, testing, oversight, and environmental mitigation N Contract 14633J Contract 14633J (ITS and MVDS (ITS and MVDS Elements) Elements) Exit 1 Exit 2 Exit 4 Exit 3 Exit 5 I-93 NB Median Shoulder I-93 NB Median Shoulder Reconstruction Reconstruction I-93 SB Median I-93 SB Median Shoulder Reconstruction Shoulder Reconstruction New Hampshire Massachusetts Salem Windham Pelham Londonderry Derry Manchester Project Schedule % Complete: 100% Recent Activities: The project was completed in the Fall of 2020 with all work items complete. This included installation of the Intelligent Transportation Systems (ITS) fiber optic network, installation of mile marker signs, and site clean up.

Transcript of Project Fact Sheet - nh.gov

Page 1: Project Fact Sheet - nh.gov

Project Fact Sheet 14633J – NB & SB Mainline from Exit 1 to Exit 5

RebuildingI93.com

Project Overview

Project 14633J addressed the I-93 northbound (NB) and southbound (SB) mainline construction elements to implement the full four lane facility from Exit 1 in Salem to just north of Exit 3 in Windham (approximately 4.8 miles of southbound and 6.1 miles of northbound). This work involved shoulder reconstruction on the median side, establishing the supporting pavement structure, drainage modifications, guardrail, paving, overlay, pavement marking, and signing elements. This project also completed the corridor wide Intelligent Transportation Systems (ITS) implementation from Exit 1 to just north of Exit 5, including integration into the statewide ITS network. Finally, the project also installed Motor Vehicle Detection Systems (MVDS) permanent traffic counting equipment between Exits 1 and 2, and between Exits 2 and 3. The overall project covered approximately 14.4 miles. Construction was completed in the Fall of 2020.

Updated January 2021

Project Facts Project 14633J

Advertised Date October 1, 2019

Award Date January 22, 2020

Start Construction Date Spring 2020

Completion Date Fall 2020

Bid Price $6.84 M

Total Construction Cost 1 $7.43 M

Construction Funding $200 M TIFIA Loan and Federal Funding

Contractor Pike Industries, Inc. 1 Includes bid plus inspection, testing, oversight, and environmental mitigation

N

Contract 14633J Contract 14633J (ITS and MVDS (ITS and MVDS Elements)Elements)

Exit 1

Exit 2

Exit 4

Exit 3

Exit 5

I-93 NB Median Shoulder I-93 NB Median Shoulder Reconstruction Reconstruction

I-93 SB Median I-93 SB Median Shoulder ReconstructionShoulder Reconstruction

New Hampshire

Massachusetts

Salem

Windham

Pelham

Londonderry

Derry

Manchester

Project Schedule

% Complete: 100%

Recent Activities: The project was completed in the Fall of 2020 with all work items complete. This included installation of the Intelligent Transportation Systems (ITS) fiber optic network, installation of mile marker signs, and site clean up.

Page 2: Project Fact Sheet - nh.gov

Project Fact Sheet 13933A: I-93 NB & SB Mainline, State Line to Exit 1

RebuildingI93.com

Completed 4th Lane Construction