![Page 1: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/1.jpg)
Project Execution Plan (PEP)
for the SKA Pre-construction Phase
Aus-NZ Power Workshop
Perth, 25 Nov 2011
Phil Crosby, CSIRO Astronomy and Space Science / SPDO
![Page 2: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/2.jpg)
From today ...
ASKAP = one SKA Precursor
36 dish array; 6km extent
On-site data processing
Signal transport to BBN
$150M Build (2010)
![Page 3: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/3.jpg)
From today ... to the SKA
SKA
1000’s dish array; plus multiple receiver
technologies & receptors.
Mega-scale computing
1000’s of kms extent
EUR 1.5B start build 2016
ASKAP = one SKA Precursor
36 dish array; 6km extent
On-site data processing
Signal transport to BBN
$150M Build (2010)
![Page 4: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/4.jpg)
Project
Milestones
SKA1
Baseline
DesignSite decision
Costed
system
design
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Baseline
Design for
SKA2
Phase 1 Construction, Verification, Commissioning,
Acceptance, Integration & First SciencePhase 1 Pre-Construction Phase SKA Preparatory Phase
Start of SKA1
Construction
ConceptSKA1 System Testing
SRRCoDR
SKA1 Systems integration
PDR CDR
Detailed
Design
REV REV
Science
SKA2DRM
Development
REV
REV REV
Science / Engineering tradeoffs
Continuous Performance Evaluation
SKA1
construction
approval
Preliminary DesignDefinition*ConceptSKA1
SKA2
Sys Eng
& Change management
dCoDR
Preliminary Design
PDR
Demonstration
& testingAIP definition, development and fabricationAIP
AIP Decision
REV
Science
SKA1
DRM
Development
(Ph 1 part)
REV
Refinement of
Early Science
Shared
Risk
Science
REV
Science / Engineering
TradeoffsEarly Science Proposals
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
SKA1 User
Tech.
Requirements
Initial SKA2
User Tech.
Requirements
Early Preliminary
DesignSystem Definition (includes non-science requirements)
System
Rev K
2010-08-18* Includes definition of non-science requirements.
Extraction of detailed SKA2 requirements
REV
SKA2
construction
approval
Context of Pre-Construction Phase
![Page 5: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/5.jpg)
The big picture
Between now and January 2012:
• The SPDO will become the (legal) SKA Project Office (SPO)
• Interim Director-General (Michiel van Haarlem ex-ASTRON)
• Will hold management & system authority for the whole project
• Will oversee the global effort – largely via Work Package
Consortia (i.e. Participating Organisations + Industry)
• The baseline plan for the Pre-construction phase is the PEP
• Funding for the PEP is essentially ‘national’ – with some
contracts possibly emanating from the SPO
![Page 6: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/6.jpg)
SKA Ltd
![Page 7: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/7.jpg)
SKA Pre-construction Phase
Pre-Construction PEP
2012-2015
CSIRO Confidential
SKA R&D
foundation
Studies ->
Concept
Designs
& SKA
Precursors
SKA build
Phase I
SKA build
Phase 2 NOW
2011
To end
2015
To end
2018
![Page 8: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/8.jpg)
SKA Pre-construction Phase
Pre-Construction PEP
2012-2015
PEP Stage 1
work delivery
PEP WP Stage 2
work delivery
CSIRO Confidential
SKA R&D
foundation
Studies ->
Concept
designs &
SKA
Precursors
Plan for
PEP
Stage 1
SKA build
Phase I
SKA build
Phase 2
Jun 12 – Mar 13
Mar 13 - Dec 15
2016
2018
NOW
2011
![Page 9: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/9.jpg)
SKA Pre-construction Phase
Pre-Construction PEP
2012-2015
CSIRO Confidential
SKA R&D
foundation
Studies ->
CoDRs
..................
SKA
Precursors
Plan for
PEP
Stage 1
SKA build
Phase I
SKA build
Phase 2
2016
2018
SPDO-led working groups
all SKA-interested parties
Institutes, industry... can
be involved; Nov 2011 – Mar 2012
PEP Stage 1
work delivery
Jun 12 – June 13
NOW
2011
![Page 10: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/10.jpg)
SKA Pre-construction Phase
Pre-Construction PEP
2012-2015
CSIRO Confidential
SKA R&D
foundation
Studies ->
CoDRs
..................
SKA
Precursors
Plan for
PEP
Stage 1
SKA build
Phase I
SKA build
Phase 2
2016
2018
SPDO-led working groups
all SKA-interested parties
Institutes, industry... can
be involved; Nov 11 – Mar 12
PEP Stage 1
work delivery
Stage 1 work packages will
be awarded via ‘bids’ from
Consortia (bid process ~May
2012, award of Stage 1 work
~July 2012)
Aus-NZ partners
form consortia ready
for Stage 1 bidding
Jun 12 – June 13
NOW
2011
![Page 11: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/11.jpg)
SKA Pre-construction Phase
Pre-Construction PEP
2012-2015
CSIRO Confidential
SKA R&D
foundation
Studies ->
CoDRs
..................
SKA
Precursors
Plan for
PEP
Stage 1
SKA build
Phase I
SKA build
Phase 2
2016
2018
Stage 1 PEP work includes
planning for Stage 2 (the major
prototyping work phase).
Deliverables = SRR, and input for
WBS
PEP Stage 1
work delivery
Jun 13 - Dec 15
PEP WP Stage 2
delivery
Contracts
Stage 2 PEP work contracts. RfP
issued ~March 2013. Contracts
awarded August 2013
NOW
2011
Jun 12 – June 13
Q4 2013 – PDR
Q4 2014 – CDR
Q1 2015 – PRR
![Page 12: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/12.jpg)
SKA Pre-construction Phase
Pre-Construction PEP
2012-2015
CSIRO Confidential
SKA R&D
foundation
Studies ->
CoDRs
..................
SKA
Precursors
Plan for
PEP
Stage 1
SKA build
Phase I
SKA build
Phase 2
2016
2018
End of Stage 2
Deliverables = data-
packs (document sets
for construction
contracts.
PEP Stage 1
work delivery
Jun 13 - Dec 15
PEP WP Stage 2
delivery
Contracts
NOW
2011
![Page 13: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/13.jpg)
Run by SKA Project Office (SPO)
• Management
• Science
• System Design
• Maint / support
• Site Engineering
11 Work Packages
User System (PM, PE, Scientists)Level 7
User System
AA- low Infrastructure
SPO
WPC1 WPC2 WPC3
System (PM, PE, SE)
Dish Array (PM, SE, Eng’s)
Areas of strong collaboration
and interaction(WPC into system
and SPO into subsystem)
(PM, SE, Eng’s) (PM, SE, Eng’s)
Dis
h
Re
ce
ive
r
WB
SP
F
PA
F
Re
ce
pto
r
Da
ta L
ink
Sta
tio
n
Pro
ce
sso
r
Ro
ad
s
Bu
ildin
gs
Tre
nch
ing
SPO
Level 6System
Level 4
Level 5Subsystem
Via Work Package Agreements
• Dish Array
• Aperture array
• Signal Transport, and networks
• Central Signal Processing
• Software and Computing
• Power
![Page 14: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/14.jpg)
CSIRO Confidential
Work Package Allocation
![Page 15: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/15.jpg)
Work Package 10 - Power
WP10.1 – Engineering and Management
The overall management of the work package as well as interfaces with other
WPs.
WP10.2 – Intra-System Power Design
Review the system design for SKA1 (and the top-level design for SKA2) from
the perspective of power minimization and optimization of intra-system power
distribution.
WP10.3 – Power System Design
Produce a complete, costed power solution for SKA1, and a detailed plan for
the extension of the solution to SKA2. Includes areas such as EMC/RFI,
monitoring and control, and protection and test.
WP10.4 – Power Systems Operation Plan
WP10.5 – Strategic Power Planning
Assessment of the applicability of emerging power solutions to the SKA
![Page 16: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/16.jpg)
Work Package 10 - Scope
In:
• Power transmission, conditioning, and
distribution into the site ‘core’ facility (MRO),
and the MRO Support Facility (MSF).
• Uninterruptable (local) power supply to
critical components at the MRO.
• Power distribution around the ‘core’ facility
to the local arrays – up to 50? kms.
• Independent power generation (up to 8
MW) for remote ‘off-grid’ SKA stations
• A ‘green’ energy component seen as
favourable
Out:
• Design / development of large
scale (say, > 10MW) power
generation / storage.
![Page 17: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/17.jpg)
CSIRO Confidential
Goals of Today...
1. A good understanding of the content and scope of the Power
Work Package, context for power in WA, and engagement
options for industry.
2. What technology options are ‘in’, or ‘out’?
3. What does the power work package consortia need to know for
(a) the Pre-construction PEP planning phase (pre-June 2012),
and (b) the Pre-construction PEP design delivery phase (post-
July 2012).
4. Confirm a list of participants interested in investment in the Work
Package bidding phase over the coming six months, and
preparedness for later contractual involvement.
![Page 18: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/18.jpg)
Contact Us
Phone: 1300 363 400 or +61 3 9545 2176
Email: [email protected] Web: www.csiro.au
Thank you
CSIRO Astronomy & Space Science
Web: www.atnf.csiro.au
www.csiro.au/org/CASS.html
![Page 19: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/19.jpg)
Spare stuff follows – from RTS talk, Manchester
![Page 20: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/20.jpg)
Pre-construction Phase
Stage 1: Schedule 2011 - 2013
Period Activity Deliverable SPO resources
required
WPC resources
required
Nov 2011 –
Mar 2012
Pre-Stage 1 Planning Development of
Statements of Work for
sub-system work
packages
5 SPDO/SPO
staff at 30%
(8 person
months)
3 people per
sub-system
(75-120 person
months)
Nov 2011 –
Mar 2012
Assemble Work
Package Consortia
Draft Consortium
Agreements
TBD TBD
Nov 2011 –
Mar 2012
Develop Terms and
Conditions for SPO
Agreements and
Contracts
Terms and Conditions for
SPO Agreements and
Contracts
TBD + legal
consultancy
0
Nov 2011 –
Oct 2012
System
Requirements
Development
Documentation for
Systems Requirements
Review, system level
WBS
System
Engineers (56
person months)
TBD assistance
![Page 21: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/21.jpg)
Period Activity Deliverable SPO Res WPC Res
Mar 2012 Prepare Request for
Proposals for Work Pkg
RfP issued by Board of Directors 1 person
month
0
Apr 2012 WP Consortia prepare
responses to RfP
Responses to Board (Consortium
Agreement, deliverables, resources,
schedule, IP)
0 TBD
May 2012 SPO to evaluate
responses
Report to Board of Directors 3 person
months
0
June 2012 Board of Directors to
assign Work Packages
and approve
agreements or
contracts
Memoranda of Agreement with
Consortia; contracts with industry
TBD TBD
Jul 2012 –
Jun 2013
Technical requirements
development for each
element of the system
Documentation for Systems
Requirements Reviews for each
element: detailed WBS for each
element
6 person
years (PEP
estimate)
91 person
years (PEP
estimate)
Pre-construction Phase
Stage 1: Schedule 2011 - 2013
![Page 22: Project Execution Plan (PEP) for the SKA Pre-construction ... · R isk S cie nce R EV Scie nce / E ngine e ring T ra de offs E a rly S cie nce P roposa ls ... SKA Project Office (SPO)](https://reader034.fdocuments.net/reader034/viewer/2022050715/5d3f1d9a88c993860c8ca2fa/html5/thumbnails/22.jpg)
Period Activity Deliverable SPO res WPC res
Jan 2013 – Jul
2013
Prepare Requests for
Proposals for Stage 2
Work Packages
RfPs issued by Board of Directors TBD 0
Feb 2013 –
Aug 2013
WPC Consortia
prepare responses to
RfP
Responses delivered to SPO 0 TBD
Mar 2013 –
Sept 2013
SPO to evaluate
responses
Reports to Board of Directors TBD 0
Apr 2013 – Oct
2013
Board of Directors to
assign Work Packages
and approve
agreements
Agreements and Contracts TBD TBD
Nov 2012 –
Dec 2015
Prepare for system
level PDR, CDR, PRR
Documentation for Preliminary
Design Review, Critical Design
Review, Production Readiness
Review
149 person
years (PEP
estimate)
TBD
Jan 2013 –
Dec 2015
Other Stage 2 Work
Packages (PDR, CDR,
PRR, TBD)
Defined in the PEP, but subject to
revision as part of Stage 1 WBS
development
38 person years
(PEP estimate)
353 person
years (PEP
estimate)
Pre-construction Phase
Stage 2: Schedule 2013 - 2015