PROJECT DESIGN DOCUMENT FORM (CDM PDD) - …cdmloanscheme.org/sites/default/files/pdd3_0.pdf ·...
Transcript of PROJECT DESIGN DOCUMENT FORM (CDM PDD) - …cdmloanscheme.org/sites/default/files/pdd3_0.pdf ·...
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 1
CLEAN DEVELOPMENT MECHANISM
PROJECT DESIGN DOCUMENT FORM (CDM-PDD)
Version 03 - in effect as of: 28 July 2006
CONTENTS
A. General description of project activity
B. Application of a baseline and monitoring methodology
C. Duration of the project activity / crediting period
D. Environmental impacts
E. Stakeholders’ comments
Annexes
Annex 1: Contact information on participants in the project activity
Annex 2: Information regarding public funding
Annex 3: Baseline information
Annex 4: Monitoring plan
Annex 5: CER Calculation
Appendix
Appendix A: References
Appendix B: Abbreviations
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 2
SECTION A. General description of project activity
A.1 Title of the project activity:
VKG Steels & Energy Private Limited – 8 MW WHR Based Captive Power Project.
Version: 03
Date : 14/12/2007
A.2. Description of the project activity:
M/s V.K.G. Steel & Energy Pvt. Ltd (herein after referred as VKGSEPL) is operating a Sponge Iron
Plant with an annual capacity of 120, 000 Tons/year. Flue gas with high heat content is generated in the
Rotary kiln in the Sponge iron plant during Sponge iron conversion from iron ore. This flue gas will be
used in a Waste Heat Recovery (WHR) boiler to generate steam which will be fed in to a turbine to
generate electricity.The total power required for the sponge iron unit is 24 MW. Out of this, 8 MW is
generated by the WHR power plant, the balance power requirement will be met by a coal based Fluidised
Bed Combustion (FBC) power plant and TNEB grid. The 8 MW electricity generated by the WHR power
plant displaces electricity that would have otherwise been purchased by the VKGSEPL from the fossil
fuel dominated southern regional grid.
The proposed 8 MW WHR project will be installed in two phases.
Phase I
In the first phase 2 No. of 2 MW Waste Heat recovery Boiler (WHRB) and 1 No. of 4 MW Coal Fired
FBC Boiler are connected to 1 No. of 8MW Steam Turbo Generator (STG). and it was commissioned
on May 2007.
Phase II
In the second phase 2 No. of 2 MW Waste Heat recovery Boiler(WHRB) and another 2 No. of 2 MW
WHRB connected to existing 8MW STG. Existing 4 MW Coal l Fired FBC Boiler & new 4 MW FBC
connected to a new 8 MW STG and it will be expected to commission on Jan 2009.
After accounting for the WHR power plant auxiliary consumption, the net available power from WHR
power plant will be consumed by the Sponge iron plant. The WHR Power Plant will be operated in
parallel with the Tamilnadu Electricity Board (TNEB) grid. Power will be drawn from the grid for the
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 3
start-up purpose as well as during WHR power plant outage. To reduce the water requirement, the plant
will be using an air cooled condenser for cooling of the turbine.
The purpose of the project activity is to generate 8 MW electricity through WHR boiler to partially meet
the in-house requirements of the VKGSEPL which would have been otherwise met by the fossil fuel
dominated southern regional grid.
Project Objective:
The main objectives of this project are listed below:
• Conversion of high heat content waste flue gas in to useful electricity and reduce dependency
on grid based power.
• Reduction of Green House Gas (GHG) emissions by minimizing the usage of its sources like
fossil fuels for power generation.
• To be an energy saving pillar for the nation to overcome energy demand in future.
Sustainable Developments
The project is located in a rural area of Tamilnadu. Thus the project will contribute positively to the
‘Sustainable Development in this Region’ by further strengthening the four pillars of sustainable
development:
Social well being
� The project is located in a backward area and hence it will assist in alleviation of poverty to
certain extent by generating both direct and indirect employment in the area of operation and
maintenance of the power plant.
Economic well being:
� The proposed project activity generates electricity by utilizing waste flue gas from the sponge
iron plant. The implementation of this project activity will displace the purchase of electricity
from TNEB grid which provides economical benefits for VKGSEPL and better management of
waste heat. The project activity will also improve the operating environment of the employees
working in the company to a certain extent.
Environmental well being:
� In India, most of the power generation is based on the fossil fuel like coal, oil and gas but the
proposed project activity generates the electricity from the waste flue gas and there by reducing
the GHG emissions from the fossil fuel based power generation in the regional grid
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 4
� The project activity utilizes the enthalpy of the hot flue gas, which will protect the environment
from thermal pollution.
� Air cooled condenser installed in this project will preserve an enormous amount of water which
is scarce in this region. Further it will reduce sludge generation and water treatment.
Technological well being:
� The Captive Power Plant (CPP) is based on the WHR technology, a clean technology for power
generation from waste hot flue gas, which would otherwise be vented to the atmosphere.
� The unique feature of the project is that it also employs an air cooled condenser instead of the
water cooled condenser. Hence on an overall basis, this project directly contributes in the
reduction of GHG emissions and specific water consumption.
A.3. Project participants:
Name of party involved
((host) indicates a host party)
Private and/or
Public entity(ies) project
participants
Kindly indicate if the Party
involved wishes to be
considered as project
participant
Government of India V.K.G. Steel & Energy Pvt. Ltd No
A.4. Technical description of the project activity:
A.4.1. Location of the project activity:
A.4.1.1. Host Party(ies):
India
A.4.1.2. Region/State/Province etc.:
Tamilnadu State
A.4.1.3. City/Town/Community etc:
District : Kancheepuram
Taluka : Uthiramerur
Village: Melpakkam
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 5
A.4.1.4. Detail of physical location, including information allowing the unique
identification of this project activity (maximum one page):
The proposed project activity of VKG Steel & Energy Private Limited VKGSEPL is located at
Melpakkam village, Uthiramerur Taluka of Kancheepuram District in Tamilnadu state. The project
location is connected by Chengalpattu to Vandhavasi state high way. The nearest railway station is
Chengalpattu, which is at a distance of 25 km from the site. The nearest airport and seaport is Chennai
which is about 120 kms from site.The project site is located within 12º 50’N latitude and 79° 41'E
longitude respectively.
A.4.2. Category (ies) of project activity:
The project activity falls under the following scope and category.
Sectoral Scope: 1 Energy Industries (renewable / non-renewable sources)
A.4.3. Technology to be employed by the project activity:
The proposed 8 MW WHR project will be installed in two phases
In the first phase 2 No. of 2 MW Waste Heat recovery Boiler (WHRB) and 1 No. of 4 MW Coal Fired
FBC Boiler are connected to 1 No. of 8MW Steam Turbo Generator. After implementation of phase 2
would consist of four numbers of 2 MW Waste Heat Recovery Boiler (WHRB) and a single 8 MW steam
turbine arrangement. The steam condenser shall be an air cooled condenser. Power generated from the
generator at 11 kV will be connected to the Sponge Iron plant after the auxiliary power consumption of
WHR power plant. The technology to be used for this project activity is based on a simple Rankine cycle
technology; this is being used for most of the power plants in India.
The VKGSEPL Sponge Iron unit consists of four numbers of rotary kiln. The generation of flue gas from
each kiln is at the flow rate of 27,000 Nm3/hr at 950
0 C. The total flue gas generated from the four kilns
is 108,000 Nm3/hr.The four numbers of rotary kiln is directly connected to the four number of WHR
Boiler, each with a steam generation capacity of 11.5 TPH. The total waste flue gas generated is ducted
to the four WHR boilers to generate steam at 66 Kg/cm2 and 490
oC.The generated steam is then fed in to
the 8 MW bleed cum condensing Turbo Generator for power generation. The power generated from the
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 6
generator at 11 kV will be connected to the Sponge Iron plant after the auxiliary power consumption of
WHR power plant. The technology to be used for this project activity is based on a simple Rankine cycle
technology. After transferring heat the waste flue gas passed through the Electro Static Precipitator (ESP)
then it passed to the atmosphere.
Phase I
Auxiliary
Consumption
FBC Boiler
VKG Sponge
Iron Plant
KILN- I KILN- II
WHR boiler- I WHR boiler-II
TURBO
GENERATOR
TNEB Grid
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 7
During Phase II
Project Boundary
Technical specification of the main equipments in this project activity:
Rotary Kiln
Capacity : 100 Tons per Day
Flue gas generation : 27,000Nm3/hr
No. of units : 4
Waste heat recovery boiler
Type : Vertical, 3 Pass, Natural circulation, Water tube boiler
Auxiliary
Consumption
FBC Captive
power plant
VKG Sponge
Iron Plant
KILN- I KILN- II KILN- III KILN- IV
WHR boiler- I WHR boiler-II WHR boiler-III WHR boiler-IV
TURBO
GENERATOR
TNEB Grid
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 8
Steam output : 11.5 tonnes per hour per unit.
Steam pressure : 64 kg/cm2
Steam temperature : 485°C
No. of units : 4
Steam turbine
Type : Bleed Cum Condensing Type
No. of units : 1
Capacity : 8 MW
Rated speed : 1500 RPM
The other accessories installed in this project activity are air cooled condenser, induced draft fan, air
compressor system, de- aerator, de-mineralisation plant etc.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 9
A.4.4 Estimated amount of emission reductions over the chosen crediting period:
The detailed calculations for the emission reduction are in sections B and Annex 5. The estimated
amount of emission reductions is tabulated below.
A.4.5. Public funding of the project activity:
There is no public funding involved in the project activity.
Years Annual estimation of
emission reduction in
tons of CO2 e
2008 18,799
2009 34,328
2010 39,232
2011 39,232
2012 39,232
2013 39,232
2014 39,232
2015 39,232
2016 39,232
2017 39,232
Total estimated reductions
(Tons of CO2) 3,66,983
Total number of crediting years 10
Annual Average over the
crediting period of estimated
reductions(tons of CO2)
36,698
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 10
SECTION B. Application of a baseline and monitoring methodology
B.1. Title and reference of the approved baseline and monitoring methodology applied to the
project activity:
The approved baseline methodology applied for this project activity is:
Approved consolidated baseline methodology ACM0004 “Consolidated baseline methodology for waste
gas and /or heat and /or pressure for power generation”. Version : 02.
Approved consolidated baseline methodology ACM0002 “Consolidated baseline methodology for grid-
connected electricity generation from renewable sources” – Version 06.
“Tool for the demonstration and assessment of additionality”– Version 03.
B.2 Justification of the choice of the methodology and why it is applicable to the project
activity:
Selection approach:
The heat content of the waste flue gas from sponge iron manufacturing unit has been utilised for power
generation by implementing this project activity. The consolidated baseline methodology referred above
has been chosen for the proposed project activity based on fulfilment of the applicability conditions as
described below.
As per the methodology ACM0004, “This methodology applies to project activities that generate
electricity from waste heat or the combustion of waste gases in industrial facilities”.- This project
activity recovers the heat content of waste gases emitted from the sponge iron Kiln and this heat is
utilized to produce steam which is further used to generate electricity.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 11
The project activity has been undertaken in the new sponge iron plant of VKGSEPL.As per the statement
discussed above the project activity under consideration meets all the applicability conditions of the
baseline methodology ACM0004.
B.3. Description of the sources and gases included in the project boundary
Source
Gas
Included
Justification/Explanation
Baseline Grid electricity
generation
CO2 Yes Main emission source
On-site fossil fuel
consumption due
to the project
activity (stationary
or mobile)
CO2 No This project activity recovers the heat
content of waste gases emitted from the
sponge iron Kiln and this heat is utilized
to produce steam which is further used to
generate electricity Hence there is no
fossil fuel consumption due to the
project activity.
Sr.
No.
Applicability Conditions As per ACM0004
Applicability to this project activity
1 Applicable to project activities that displace
electricity generation with fossil fuels in the
electricity grid or displace captive electricity
generation from fossil fuels.
This project activity displaces the fossil fuel
based electricity generation in the southern
regional grid.
2 Applicable to project activities where no fuel
switch is done in the process ,where the waste
heat or pressure or the waste gas is produced
after the implementation of the project activity
After the implementation of the project activity
there is no fuel switch in the iron making
process from where the waste gases are
generated.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 12
Combustion of
waste gas for
electricity
generation.
CO2
No There is no combustion of waste gas in
this project activity.
B.4. Description of how the baseline scenario is identified and description of the identified
baseline scenario:
As per the approved methodology, ACM0004, all the alternative baseline scenarios involved in the
context of project activity should include all possible options that provide or produce electricity for
captive consumption only and/or sale to grid and/or other consumers.
The project activity shall exclude baseline options that:
• do not comply with legal and regulatory requirements; or
• depend on key resources such as fuels, materials or technology that are not available at the
project site.
The four Alternative baseline scenarios are listed & explained below:
Alternative 1: Proposed project activity without CDM benefit
Alternative 2: Import of electricity from local grid
Alternative 3: Implementation of coal based captive power generation
Alternative4: Implementation of diesel based captive power generation
Alternative 1: Proposed project activity without CDM benefit
The proposed 8 MW WHR based power generation from VKGSEPL will be totally utilised to partially
meet its power demand. The pollution control board norms for the emission of flue gas from the sponge
iron unit can be satisfied by the project even in the absence of the CDM project activity. Implementation
of this WHR project will further reduce the thermal, dust pollution levels from the flue gas and displace
the electricity purchase from southern regional grid, which in turn reduce the CO2 emissions from fossil
fuel based thermal power plants of southern regional grid. In order to implement this project activity
VKGSEPL has to make additional investment in addition to facing the technological barrier, which
makes this alternative, less attractive for the project activity with out CDM benefit. Hence this option can
be eliminated for consideration as a baseline scenario.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 13
Alternative 2: Import of electricity from southern regional grid
In the absence of CDM project activity, VKGSEPL otherwise import electricity from southern regional
grid and this will lead to GHG emissions from fossil fuel based thermal power plants. This alternative is
in compliance with all applicable legal and regulatory requirements and may be a part of the baseline
scenario.
Alternative 3: Implementation of Coal based captive power generation
In the absence of the proposed CDM Project activity, the VKGSEPL will generate electricity by
implementation of coal based CPP to meet their demand. By utilising coal in CPP will lead to the
equivalent amount of CO2 emission to the atmosphere. This alternative is in compliance with all
applicable legal and regulatory requirements and may be a part of the baseline scenario.
Alternative4: Implementation of diesel based captive power generation
In the absence of the proposed CDM Project activity, the VKGSEPL will generate electricity by
implementation of diesel based CPP to meet their power demand. This will lead to the equivalent amount
of CO2 emission to the atmosphere by the diesel based captive power generation. This alternative is in
compliance with all applicable legal and regulatory requirements and may be a part of the baseline
scenario.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board
Evaluation of alternatives for baseline selection:
The alternative-1 eliminated for consideration as a baseline scenario because the additional
investment in addition to facing the technological barrier, which makes this alternative, less
attractive. To evaluate the appropriate baseline scenario for this project activity, the alternatives
2, 3 and 4 are discussed below.
Alternative
baseline
scenario
Capital
Cost
Operation
Costs per
unit
Source Comments
2) Import of
electricity
from local
grid
Initial
investment
is 3.77
lakhs/MW.
Industrial
consumption
Rs 3.50
TNEB.Lr.No.SE/KEDC
/KPM/DEV/JE1/F.HT.
New.03/d.236/06.
H.T Agreement with
TNEB Dated
31/07/2006 & TNEB
bill of VKG
• Initial investment is very less
• Easily available source
• Technical difficulties are
very less.
• Regulatory issues are very
less
3) Imple-
mentation of
Coal based
captive
power
generation
4.0 Crores
/MW
(High)
Rs 2.15-Rs
2.52
Report of the Expert
Committee on fuels for
power generation.CEA
Report Appendix -1.
Lr.No.SE/KEDC/KPM/
DEV/JE1/F.HT.New.03/
D.236/06 dt.21/06/06
• Initial investment is very
high, which results in
financial problems. Getting
loan from banks are very
difficult.
• Technical difficulties are
high.
• Getting Govt Approvals are
difficult.
• Coal supply and its
fluctuating costs are issues.
4) Imple-
mentation of
diesel based
captive
power
generation
3.5 Crores
/MW
Rs 5.96 Report of the Expert
Committee on fuels for
power generation.CEA
Report Appendix -1.
Lr.No.SE/KEDC/KPM/
DEV/JE1/F.HT.New.03/
D.236/06 dt.21/06/06
• Initial investment is High.
Generation cost is high
• Technical difficulties are
high.
• Getting Approvals are
difficult.
• Fluctuating costs is an issue.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 15
From the above discussions it is clear that “Import of electricity from the grid” and “coal based power
generation” be the option for the baseline scenario. VKGSEPL is already connected with southern grid*.
In the absence of the project activity the power will be continuously supplied by the southern regional
grid. There is no technical or financial risk involved in supply from grid. Import of electricity from grid
requires a minimum investment while comparing with other baseline scenario. Among the baseline
scenarios discussed above it should be noted that alternatives 3 and 4 are the most Green House Gas
(GHG) intensive fuel based power generation.
The baseline scenario for this project activity is “Import of electricity from the grid” which is most
economically attractive. The baseline emission factor calculation is based on the combined margin
method of ACM0002.
Baseline emission factor calculation:
As described in ACM0002, the emission factor EFy of the southern grid is represented as a combination
of the Operating Margin and the Build Margin. The emission factor of the associated method is given by:
EFy = wOM . EFOMy + wBM .EFBMy
Where
EFOMy - emission factor of Operating Margin
EFBMy - emission factor of Build Margin
wOM - weight factors of Operating Margin
wBM - weight factors of Build Margin
with respective weight factors wOM and wBM (where wOM + wBM = 1), and by default, are weighted equally
(wOM = wBM = 0.5).
Operating Margin emission factor(s) (EFOM)
In the southern regional the power generation is dominated by fossil fuel based power plants and the
power generation by low cost/must run resources constitute less than 50% of total grid generation, so
simple operating margin method is used for operating margin emission factor calculation. The Operating
Margin emission factor EFOMy is defined as the generation-weighted average emissions per electricity
unit (tCO2 / MWh) of all generating sources serving the system, excluding zero- or low-operating cost
power plants (hydro, geothermal, wind, low-cost biomass, nuclear and solar generation), based on the
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 16
latest three year statistics data (year of 2003-04, 2004-05 and 2005-06) and are derived from the
following equation:
EFOMy = ∑
∑
j yj,
ji,yj,i,
GEN
EF.Fi
CO
Where:
TEMy - Total GHG emissions
TGENy – Total electricity generation supplied to the grid excluding zero- or low-
operating cost sources.
Fi,j,y – the amount of fuel i(mass or volume unit) consumed by the relevant
power sources j in year y
J - Power sources delivering electricity to the grid,not including low-operating cost and must
run power plants and including imports to the grid
COEFi - CO2 emission coefficient of fuel i (tCO2 / mass or volume unit) takking into
account the carbon content of fuels used by the relevant power sources j and
the percent oxidation of the fuel in year y.
GENj,y – The Electricity (MWh) delivered to the grid by source j.
Year
2003-04 2004-05 2005-06 Average
Operating Margin Emission Factor (tCO2 / MWh) 1.00 1.00 1.01 1.01
Source: Central Electricity Authority: CO2 Baseline Database.
Vesion:2,Dated 21st June 2007
http://www.cea.nic.in/planning/c%20and%20e/Government%20of%20India%20website.htm
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 17
Build Margin emission factor (EFBM)
The Build Margin emission factor EFBMy has been calculated based on the generation-weighted average
emission factor (tCO2/MWh) of a sample of power plants m, as follows:
EFBM,y = ∑
∑
m
ym
i
miymi
GEN
COEFF
,
,,, .
where Fi,m,y, COEFi,m and GENm,y are analogous to the variables described for the simple OM method
above for plants m.
Project participants has chosen option 1 to calculate the Build Margin emission factor EFBM,y ex-ante
based on the most recent information available on plants already built for sample group m at the time of
PDD submission. The sample group m consists of either the five power plants that have been built most
recently, or
the power plant capacity additions in the electricity system that comprise 20% of the system generation
(in MWh) and that have been built most recently. Project participants should use from these two options
that sample group that comprises the larger annual generation.
The Build Margin emission factor will be
EFBM =0.71 tCO2/MWh
Source: Central Electricity Authority: CO2 Baseline Database.
Vesion:2,Dated 21st June 2007
http://www.cea.nic.in/planning/c%20and%20e/Government%20of%20India%20website.htm
Calculate the baseline emission factor (EF)
The baseline emission factor EF is calculated as combination of the Operating Margin emission factor
(EFOM) and the Build Margin emission factor (EFBM):
EF = wOM*EFOM + wBM*EFBM
Where
The weight factors wOM and wBM (where wOM + wBM = 1), and by default, are weighted equally
(wOM = wBM = 0.5).
EFOM - 1.01tCO2/MWh
wOM - 0.5
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 18
EFBM - 0.71 tCO2/MWh
wBM - 0.5
EF = 0.5*1.01 + 0.5*0.71
Baseline emission factor will be (EF) = 0.86 tCO2/MWh
Year
2003-04 2004-05 2005-06 Average
Operating Margin Emission Factor
(tCO2 / MWh)
1.00 1.00 1.01 1.01
Build Margin
(tCO2 / MWh)
0.71
0.71
Combined Margin
(tCO2 / MWh)
0.86
0.86
0.86
0.86
Source: Central Electricity Authority: CO2 Baseline Database.
Vesion:2,Dated 21st June 2007
http://www.cea.nic.in/planning/c%20and%20e/Government%20of%20India%20website.htm
B.5. Description of how the anthropogenic emissions of GHG by sources are reduced below
those that would have occurred in the absence of the registered CDM project activity (assessment
and demonstration of additionality):
Additionality of the project activity is demonstrated using the “tool for demonstration and assessment of
additionality” version 03 EB 29, as specified by the approved methodology ACM0004 (version 02) as
described below:
Step 1. Identification of alternatives to the project activity consistent with current laws
and regulations
Sub-step1a- Define alternatives to the project activity
All the possible four alternatives of the project activity has been discussed in the previous section
B4.Among those four alternatives 2, 3, and 4 (2: Import of electricity from local grid, 3: Implementation
of Coal based captive power generation and 4: Implementation of diesel based captive power generation)
are the possible and credible alternatives to the project activity that delivers outputs and services with
comparable quality. These alternatives are in compliance with all applicable legal and regulatory
requirements.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 19
Sub-step1b- Consistency with mandatory laws and regulations
As per the Tamilnadu Pollution Control Board (TNPCB) norms, the presence of Suspended Particulate
Matter (SPM) in the flue gas from the Sponge iron kiln should be maintained in the range of 150 mg/Nm3
and these mandatory limits given by TNPCB were already kept in control even in the absence of the
project. There is no enforcement of mandatory laws and regulations by the Indian government on Sponge
Iron manufacturing units to implement the generation of electricity from waste heat of flue gas in sponge
iron kilns. From the above points it is clear that the implementation of the project activity is decided by
the project proponent on their own and it is not at all implemented by any mandatory law or under any
regulations of the Indian government.
Step 2. Investment analysis
Instead of Step 2, Step 3 (barrier analysis) will be discussed below.
Step –3 Barrier analysis
Sub-step 3.a Identify barriers that would prevent the implementation of the proposed CDM based
project activity.
The barriers that would prevent the implementation of the proposed project activity are as follows :
I. Technological Barriers
II. Barrier due to Prevailing Practice
I Technological Barriers:
The technological barriers faced by the project promoter to implement this project activity are explained
below.
a) Barrier due to operation:
� In Tamilnadu there is no WHR boiler based sponge iron unit before this project activity, hence
skilled and properly trained man power is not available.
� The project promoter felt that it is difficult to overcome the process disturbance due to ring
formation and other requirement in sponge iron kiln. These disturbance increase the Shutdown
days of both sponge iron plant and WHR boiler will lead to the loss of power generation.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 20
� Inconsistency of operation of WHR boiler due to coal quality, Iron quality, equipment fitness,
flue gas temperature and variation in flue gas quantity, hence lower steam generation which
affects the power generation and it will reduce the PLF.
� Temperature variation in the flue gas affects the WHR boiler equipments. The temperature above
950oc will damage the boiler tube
b) Barrier due to Air-cooled Condenser:
The WHR project of the VKGSEPL is located in Uthiramerur taluka of Kancheepuram district in Tamil
nadu. The technology used in this project activity is Rankine cycle technology. The Rankine cycle
technology with the conventional cooling towers requires huge quantity of water. Generally, for power
project capacity of 8 MW with conventional cooling systems, which is a common practice in India, it is
estimated that a very substantial quantity of water (about 35 m3/ hr or 8, 40,000 litres /day) is required.
Due to the water scarcity in the region surrounding the project, implementing the project with
conventional cooling tower is difficult. Hence as an alternative, an air-cooled condenser (ACC) which is
considered as a water conservation equipment (as it reduces use of water only for service applications),
was found essential for the operation of the proposed plant. The cost of the air cooling system is about 3
to 4 times more than conventional water cooling system. Dry cooling systems are the least used systems
as they have a much higher capital cost, higher operating temperatures, and lower efficiency than wet
cooling systems*. Further the ACC results in additional steam requirements at the turbine inlet. This has
a spiralling effect leading to increased auxiliary power consumption. Thus the addition of the air cooling
system increases the capital investment cost and the operational costs of the project.
*Source: http://www.rerc.gov.in/Order/Final%20order_NES_Chairman.pdf
II Barrier due to Prevailing Practice
The Sponge Iron manufacturers release the high temperature flue gas into atmosphere through high
rising stack, which is the prevailing practice in India. There is no existing law prohibiting discharge of
hot flue gases in to atmosphere from the sponge iron plant. Most of the entrepreneurs have preferred to
draw the required power from the grid, as it offers them enormous operating comforts and freedom in the
manufacturing activities. As per prevailing practice not many entrepreneurs have put up the WHR based
power plant. A few of them who have put up the WHR are mainly due to the CDM strength.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 21
In order to generate eco friendly power from the Waste heat of the flue gas from the sponge iron plant
and to displace the power drawn from grid the project promoter has to overcome the above barriers (by
seeking the CDM support).The proposed project activity is not a common practice in India, because only
16 sponge iron plants out of 147 plants have captive power generation as per JPC * (Joint Plant
Committee, a Government of India body) survey on Indian sponge iron industry. Only a few large
capacity sponge iron plants have WHR based CPP and Smaller companies have not been able to install
the WHR power project because of high capital cost and running risk. VKGSEPL is the WHR based
sponge iron unit in Tamilnadu and in the absence of this project activity the power will be drawn from
the TNEB grid. Hence the implementation of WHR boiler in VKGSEPL sponge iron unit will displace
the fossil fuel dominated electricity purchased from the TNEB grid.
* http://cdm.unfccc.int/UserManagement/FileStorage/QVQE67X4FRQB9FSE4SMYXP9J4IVRHP
Sub-step 3b: Show that the identified barriers would not prevent the implementation of at least one of
the alternatives (except the proposed project activity)
The baseline scenario for this project activity is “Import of electricity from the grid”. The technological
barrier for this project activity is operational barrier and barrier due to Air-cooled Condenser. Thèse two
barriers would not prevent the alternative baseline scenario of this project activity.
Step 4: Common Practice analysis:
Based on the information about activities similar to the proposed project activity, the project proponent is
supposed to carry out common practice analysis to complement and reinforce the barrier analysis. The
project proponent is required to identify and discuss the existing common practice through the following
sub steps:
Sub-Step 4a: Analyze other activities similar to the proposed project activity
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 22
Table 1: Indian sponge iron industry summarised table given in JPC report
Indian Sponge Iron Industry : Both Coal & Gas Segments
Data Collected Additional / Total
Industry/ Field
sources^
No of Capacity No. of Capacity# No. of Capacity
Units (Unit :mt) units (unit:mt) units (unit:mt)
Operating
Coal 147 11 56 2 203 13
Gas 3 6 - - 3 6
Total 150 17 56 2 206 19
Under 58 6 167 12* 225 18
commissioning
(Coal)
^=State DI Offices; #=Estimated, *=included units in proposal/ planning stage
Source:http://cdm.unfccc.int/UserManagement/FileStorage/QVQE67X4FRQB9FSE4SMYXP9J4IVRHP
In India 203 sponge iron plants are in operation and 225 plants are under commissioning. Chhattisgarh,
Orissa, Jharkhand and West Bengal are the leading sponge iron producing states in India. In Tamilnadu
only two plants are in operation and two plants are under commissioning stage. This indicates a very low
penetration (Out of 448 plants in India only 4 sponge iron plants are in Tamilnadu) of this technology in
this region. Hence this project activity is not a common practice in this region.
Sub-Step 4b: Discuss any similar options that are occurring
From the above analysis it is clear that the proposed project activity is not a common practice in Tamil
nadu. Other than VKGSEPL, three project activities are under commissioning stage in the state with
waste heat recovery based power generation and are primarily coming up after taking the CDM funding
into consideration .The other three project activities are under PDD Preparation stage and this is a clear
indication that due to the barriers discussed earlier waste heat recovery from the sponge iron unit is not a
common practice in Tamilnadu. Moreover currently the waste heat recovery systems are coming up in
this region only on the basis of CDM funding.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 23
B.6. Emission reductions:
B.6.1. Explanation of methodological choices:
The choice of Methodology is already explained in section B2 and B4.As per the methodology
ACM0004 the emission reduction for this project activity is explained below.
Emission Reduction
As per the methodology the emission reduction ERy by the project activity during a given year y is the
difference between the baseline emissions though substitution of electricity generation with fossil fuels
(BEy) and project emissions (PEy), as follows:
ERY = BEY − PEY ( Equation 5 of methodology ACM0004 in page no 6)
Where,
ERY - are the emissions reductions of the project activity during the year y in tons of CO2,
BEY - are the baseline emissions due to displacement of electricity during the year y in tons of
CO2
PEY - are the project emissions during the year y in tons of CO2,
Baseline emissions :
Baseline emissions are given as:
BEelectricity,y = EGy .EFelectrictyY ( Equation 2 of methodology ACM0004 in page no 4)
where:
EGY Net quantity of electricity supplied to the manufacturing facility by the project during the year y
in MWh, and
EFy CO2 baseline emission factor for the electricity displaced due to the project activity
during the year y (tCO2/MWh).
Leakage
As per the methodology ACM0004 there is no leakage from this project activity
Project emission:
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 24
As per methodology “Project Emissions are applicable only if auxiliary fuels are fired for generation
startup, in emergencies, or to provide additional heat gain before entering the Waste Heat Recovery
Boiler”.
In this project activity there is no auxiliary fuels firing for power generation startup, in emergencies, or to
provide additional heat gain before entering the Waste Heat Recovery Boiler”. Hence there is no project
emission.
PEY = 0
Emission reduction by the project activity
ERY = BEY
B.6.2. Data and parameters that are available at validation:
Data / Parameter: EFOM
Data unit: tCO2eq/MWh
Description: Operating Margin emission factor of the Southern grid
Source of data
used:
Central Electricity Authority (CEA) CO2 Baseline Database values have been used
for calculation. Source:
http://www.cea.nic.in/planning/c%20and%20e/Government%20of%20India%20website.htm
Value applied: 1.01
Justification of the
choice of data or
description of
measurement
methods and
procedures actually
applied :
Calculated by Central Electricity Authority (CEA)
Any comment:
Data / Parameter: EFBM
Data unit: tCO2eq/MWh
Description: Build Margin emission factor of the Southern grid
Source of data
used:
Central Electricity Authority (CEA) CO2 Baseline Database values have been used
for calculation. Source:
http://www.cea.nic.in/planning/c%20and%20e/Government%20of%20India%20website.htm
Value applied: 0.71
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 25
Justification of the
choice of data or
description of
measurement
methods and
procedures actually
applied :
Calculated by Central Electricity Authority (CEA)
Any comment:
Data / Parameter: EFelectricity
Data unit: tCO2eq/MWh
Description: Combined Margin emission factor of the Southern grid
Source of data
used:
Central Electricity Authority (CEA) CO2 Baseline Database values have been used
for calculation. Source:
http://www.cea.nic.in/planning/c%20and%20e/Government%20of%20India%20website.htm
Value applied: 0.86
Justification of the
choice of data or
description of
measurement
methods and
procedures actually
applied :
Calculated by Central Electricity Authority (CEA)
Any comment:
B.6.3 Ex-ante calculation of emission reductions:
Baseline emission calculation:
Baseline emission are calculated by multiplying the net quantity of electricity generated by this project
activity (EGy) with the CO2 baseline emission factor for the electricity displaced due to the project (EF
electricity,y) as follows:
BEelectricity,y = EGy .EFelectrictyY
Where:
EF electricity,y = Baseline emission factor
= 0.86 tCO2/MWh
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 26
Year
2003-04 2004-05 2005-06 Average
Operating Margin Emission Factor
(tCO2 / MWh)
1.00 1.00 1.01 1.01
Build Margin
(tCO2 / MWh)
0.71
0.71
Combined Margin
(tCO2 / MWh)
0.86 0.86 0.86
0.86
Source: http://www.cea.nic.in/planning/c%20and%20e/Government%20of%20India%20website.htm
Year 2010 (during Phase II)
Total Capacity = 8 MW
Operational Days = 330 Days
Plant load factor = 80%
Total Electricity Generation (EGGEN) = 8*24*330*0.8
= 50,688 MWh/year
Auxiliary Consumption (EG AUX) = EG AUX from WHR + EG AUX from GRID
EG AUX from WHR = 10 % of the EG GEN
EG AUX from GRID = 0
EG AUX = 50,688*0.10 + 0
= 5,068
Net Electricity Generation (EGY) = 50,688 -5,068
= 45,620 MWh/year
Baseline emission factor = 0.86 tCO2/MWh
Baseline emission (BEy) = 45,620 * 0.86
= 39,232 tCO2/year
For the first three years (2008, 2009, 2010) detailed calculation are explained in the Annex-5
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 27
B.6.4 Summary of the ex-ante estimation of emission reductions:
Years
Baseline emission
(Tonnes of CO2e)
Project Activity emission
(Tonnes of CO2e)
Emission Reduction
(Tonnes of CO2e)
2008 18,799 0
18,799
2009 34,328 0
34,328
2010 39,232 0
39,232
2011 39,232 0
39,232
2012 39,232 0
39,232
2013 39,232 0
39,232
2014 39,232 0
39,232
2015 39,232 0
39,232
2016 39,232 0
39,232
2017 39,232 0
39,232
Total
(Tonnes of CO2e) 3,66,983 0 3,66,983
B.7 Application of the monitoring methodology and description of the monitoring plan:
B.7.1 Data and parameters monitored:
Phase-I
(Copy this table for each data and parameter)
Data / Parameter: QWHRB
Data unit: Tons/Hr
Description: Flow rate of steam from two numbers of WHR Boilers
Source of data to be
used:
Daily Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
23 TPH
Description of
measurement methods
Flow rate of steam is measured by flow meter.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 28
and procedures to be
applied:
QA/QC procedures to
be applied:
General Manager would be responsible for regular calibration of the meter
Any comment: The flow rate of steam monitored by Distributed Control System(DCS).The data
measured by the flow meter is entered in log book which is maintained regularly.
Data / Parameter: P1
Data unit: kg/cm2
Description: Pressure of WHRB Steam
Source of data to be
used:
Daily Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
66
Description of
measurement methods
and procedures to be
applied:
Pressure of WHRB steam is measured by Pressure gauge.
QA/QC procedures to
be applied:
General Manager would be responsible for regular calibration of the Pressure
gauge
Any comment: The presser of steam monitored by Distributed Control System(DCS).The data
measured by the Pressure gauge is entered in log book which is maintained
regularly
Data / Parameter: T1
Data unit: Deg. C
Description: Temperature of WHRB Steam
Source of data to be
used:
Daily Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
490
Description of
measurement methods
and procedures to be
applied:
Temperature WHRB steam is measured by Thermocouple.
QA/QC procedures to
be applied:
General Manager would be responsible for regular calibration of the
Thermocouple.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 29
Any comment: The Temperature of steam monitored by Distributed Control System(DCS).The
data measured by the thermocouple is entered in log book which is maintained
regularly
Data / Parameter: h 1
Data unit: kcal/kg
Description: Enthalpy of WHRB Steam per kg
Source of data to be
used:
Daily Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
3390.61
Description of
measurement methods
and procedures to be
applied:
Calculated from Average Temperature and Pressure of WHRB Steam
QA/QC procedures to
be applied:
-
Any comment: -
Data / Parameter: H 1
Data unit: Kcal
Description: Total enthalpy of WHRB Steam on daily basis
Source of data to be
used:
Daily Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
1.8716 X109
Description of
measurement methods
and procedures to be
applied:
Calculated from Quantity and Enthalpy of WHRB Steam
QA/QC procedures to
be applied:
-
Any comment: -
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 30
Data / Parameter: QFBC
Data unit: Tons/Hr
Description: Flow rate of steam from FBC Boiler
Source of data to be
used:
Monthly Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
25 TPH
Description of
measurement methods
and procedures to be
applied:
Flow rate of steam is measured by flow meter.
QA/QC procedures to
be applied:
General Manager would be responsible for regular calibration of the meter
Any comment: The flow of steam monitored by Distributed Control System(DCS).The data
measured by the flow meter is entered in log book which is maintained regularly
Data / Parameter: P2
Data unit: kg/cm2
Description: Pressure of FBC Steam
Source of data to be
used:
Daily Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
66
Description of
measurement methods
and procedures to be
applied:
Pressure FBC steam is measured by Pressure gauge.
QA/QC procedures to
be applied:
General Manager would be responsible for regular calibration of the Pressure
gauge
Any comment: The Pressure of steam monitored by Distributed Control System(DCS).The data
measured by the Pressure gauge is entered in log book which is maintained
regularly
Data / Parameter: T2
Data unit: Deg. C
Description: Temperature of FBC Steam
Source of data to be Daily Report
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 31
used:
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
490
Description of
measurement methods
and procedures to be
applied:
Temperature FBC steam is measured by Thermocouple.
QA/QC procedures to
be applied:
General Manager would be responsible for regular calibration of the
Thermocouple.
Any comment: The temperature of steam is monitored by Distributed Control System(DCS).The
data measured by the thermocouple is entered in log book which is maintained
regularly
Data / Parameter: h 2
Data unit: kCal/kg
Description: Enthalpy of FBC Steam per kg
Source of data to be
used:
Daily Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
3390.61
Description of
measurement methods
and procedures to be
applied:
Calculated from Average Temperature and Pressure of FBC Steam
QA/QC procedures to
be applied:
-
Any comment: -
Data / Parameter: H 2
Data unit: kCal /day
Description: Total enthalpy of FBC Steam on daily basis
Source of data to be
used:
Daily Report
Value of data applied
for the purpose of
calculating expected
2.0343x 109
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 32
emission reductions in
section B.5
Description of
measurement methods
and procedures to be
applied:
Calculated from Quantity and Enthalpy of FBC Steam
QA/QC procedures to
be applied:
-
Any comment: -
Data / Parameter: EG Total
Data unit: MWh/year
Description: Total Electricity generated from STG by steam from both WHR and FBC boilers
( Captive Power Plant )
Source of data to be
used:
Daily Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
50,688
Description of
measurement methods
and procedures to be
applied:
Measured by Energy Meter
QA/QC procedures to
be applied:
General Manager would be responsible for regular calibration of the Energy
meter.
Any comment: - The total Electricity generated from STG is monitored by Distributed Control
System(DCS).The data measured by the energy meter is entered in log book
which is maintained regularly
Data / Parameter: EGGEN
Data unit: MWh/year
Description: Total Electricity generated by the project activity ( by steam from WHRB only )
Source of data to be
used:
Daily Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
24,288
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 33
Description of
measurement methods
and procedures to be
applied:
Electricity generated by the WHRB is calculated on the basis of total power
generated from CPP and total enthalpy of steam (Enthalpy per unit steam *
Steam flow) from WHRB as a percentage of total enthalpy of steam fed to the
common header of the CPP.
QA/QC procedures to
be applied:
-
Any comment: -
Data / Parameter: EGAUX –from CPP
Data unit: MWh
Description: Auxiliary consumption of electricity by Captive Power Plant from its own
Generation (Captive power plant.)
Source of data to be
used:
Monthly Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
5069
Description of
measurement methods
and procedures to be
applied:
Measured by Energy Meter
QA/QC procedures to
be applied:
General Manager would be responsible for regular calibration of the Energy
meter.
Any comment: -
Data / Parameter: EGAUX-from GRID
Data unit: MWh
Description: Auxiliary consumption of electricity by the Captive power plant from Grid
Source of data to be
used:
Monthly Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
0
Description of
measurement methods
and procedures to be
applied:
Measured by Energy Meter
QA/QC procedures to General Manager would be responsible for regular calibration of the Energy
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 34
be applied: meter.
Any comment: -
Data / Parameter: EGAUX –TOTAL
Data unit: MWh
Description: Auxiliary consumption of electricity by the Captive power plant from both
Captive power plant and Grid
Source of data to be
used:
Monthly Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
5069
Description of
measurement methods
and procedures to be
applied:
Calculated from the Auxiliary consumption meter reading from Captive Power
Plant and Grid
QA/QC procedures to
be applied:
-
Any comment: -
Data / Parameter: EGAUX
Data unit: MWh
Description: Auxiliary consumption of electricity by the project activity (WHR Power plant )
from both grid and WHR Power Plant
Source of data to be
used:
Monthly Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
2,429
Description of
measurement methods
and procedures to be
applied:
Auxiliary Consumption by the WHR Power Plant is calculated on the basis of
total power consumed by CPP and total enthalpy of steam (Enthalpy per unit
steam * Steam flow) from WHRB as a percentage of total enthalpy of steam fed
to the common header of the CPP.
QA/QC procedures to
be applied:
-
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 35
Any comment: -
Data / Parameter: EGY
Data unit: MWh/Year
Description: Net electricity generated by the project activity
Source of data to be
used:
Calculated from the meter reading of Total electricity generated by the WHR
Power Plant and auxiliary consumption of electricity by project activity.
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
21,859
Description of
measurement methods
and procedures to be
applied:
Calculated from the total electricity generated and auxiliary consumption of
electricity by project activity (WHR Power Plant ).
QA/QC procedures to
be applied:
-
Any comment: -
After Phase- II
Data / Parameter: EGGEN
Data unit: MWh
Description: Total Electricity generated by this project activity
Source of data to be
used:
Daily Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
50,688
Description of
measurement methods
and procedures to be
applied:
Electricity generated is measured by Energy meter
QA/QC procedures to
be applied:
General Manager would be responsible for regular calibration of the Energy
meter.
Any comment: The total Electricity generated from STG is monitored by Distributed Control
System(DCS).The data measured by the energy meter is entered in log book
which is maintained regularly
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 36
Data / Parameter: EGAUX – From WHR
Data unit: MWh
Description: Auxiliary consumption of electricity by the project activity from WHR plant.
Source of data to be
used:
Monthly Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
5,069
Description of
measurement methods
and procedures to be
applied:
Measured by Energy Meter
QA/QC procedures to
be applied:
General Manager would be responsible for regular calibration of the Energy
meter.
Any comment: -
Data / Parameter: EGAUX-From GRID
Data unit: MWh/Year
Description: Auxiliary consumption of electricity by the project activity from Grid
Source of data to be
used:
Monthly Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
0
Description of
measurement methods
and procedures to be
applied:
Measured by Energy Meter
QA/QC procedures to
be applied:
General Manager would be responsible for regular calibration of the Energy
meter.
Any comment: -
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 37
Data / Parameter: EGAUX
Data unit: MWh/Year
Description: Auxiliary consumption of electricity by the project activity from both grid and
WHR Power Plant
Source of data to be
used:
Monthly Report
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
5,068
Description of
measurement methods
and procedures to be
applied:
Calculated from the Auxiliary consumption meter reading from Grid and WHR
Power Plant.
QA/QC procedures to
be applied:
-
Any comment: -
Data / Parameter: EGY
Data unit: MWh/Year
Description: Net electricity generated by the project activity
Source of data to be
used:
Calculated from the meter reading of total electricity generated and auxiliary
consumption of electricity by project activity.
Value of data applied
for the purpose of
calculating expected
emission reductions in
section B.5
45,619
Description of
measurement methods
and procedures to be
applied:
Calculated from the meter reading of total electricity generated and auxiliary
consumption of electricity by project activity.
QA/QC procedures to
be applied:
-
Any comment: -
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 38
B.7.2 Description of the monitoring plan:
To address all O&M issues, though the overall authority and responsibility belongs the management, it
has formed a team of Supervisors and Field Representatives headed by a General Manager to effectively
control and monitor the complete process in the plant area.
The monitoring data of the equipments are recorded by labours/ supervisors and data are submitted to the
shift incharges. The shift incharges report daily to the General Manager. The General manager submits a
monthly report to the management, which will be documented and stored in the project office. By this
operational structure, the management can monitor the project activity and make amendments
immediately, if needed. The monitored parameters have low level of uncertainty. Therefore the possible
monitoring data adjustments are not envisaged for the project. Reported results and data will be
compared with the previous results and data and will be thoroughly checked for any inconsistency.
B.8 Date of completion of the application of the baseline study and monitoring methodology
and the name of the responsible person(s)/entity(ies)
Management
General Manager
Shift in Charge
Supervisor
Labourer
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 39
Organization: V.K.G Steel & Energy Pvt Limited
Street/P.O.Box: Broadway
Building: 163/1, 1st floor, K.Sons Complex
City: Chennai
State/Region: Tamilnadu
Postfix/ZIP: 600 108
Country: India
Telephone: 91-44-2524 9501
FAX: 91-44-4262 7402
E-Mail: [email protected]
URL:
Represented by: Mr.M.Mohamed Abdulla
Title: Director
Salutation: Mr.
Last Name: Abdulla
Middle Name:
First Name: Mohamed
Department: Power Plant
Mobile: +91 93802 22600 / +91 94449 00900
Direct FAX: 91-44-2524 9511
Direct Tel: 91-44-2524 9500
Personal E-Mail: [email protected]
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 40
SECTION C. Duration of the project activity / crediting period
C.1 Duration of the project activity:
C.1.1. Starting date of the project activity:
19/01/2005
C.1.2. Expected operational lifetime of the project activity:
25 years
C.2 Choice of the crediting period and related information:
C.2.1. Renewable crediting period
C.2.1.1. Starting date of the first crediting period:
C.2.1.2. Length of the first crediting period:
C.2.2. Fixed crediting period:
C.2.2.1. Starting date:
The starting date of the crediting period is 01/01/2008 or a date not earlier than the date of registration
of the project activity.
C.2.2.2. Length:
10 years
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 41
SECTION D. Environmental impacts
D.1. Documentation on the analysis of the environmental impacts, including transboundary
impacts:
� ANALYSIS OF ENVIRONMENTAL ASPECTS:
The adversity caused to the environment due to the emission of green house gases can be reduced to
desirable limit by implementing WHR based electricity generation in industries. The support provided by
the CDM activity will further accelerate implementation of the GHG emission reduction projects in the
industrial sectors in India. Due to the implementation of WHR based CPP in the sponge iron unit of
VKGSEPL there is no major impact upon the surrounding environment. Even though the CPP is eco-
friendly in nature, the waste hot flue gas utilised in the CPP consists of pollutants and it must be removed
before vented to the environment. So the project promoter carried out an Environmental Impact
Assessment study to ascertain the impact of the pollutants from various parts of CPP on the environment.
The pollutants monitored in the Environmental Impact Assessment studies are as follows
• DUST AND PARTICULATE MATTER
The waste flue gas generated during the iron ore reduction process in kiln consists of dust, particulate
matter and high heat content. After the utilization of heat content of flue gas in the WHR boiler it
consists of only dust and particulate matter. The dust and suspended particulate matter (SPM) in the flue
gas are trapped by a well designed Electrostatic Precipitator (ESP) in order to achieve concentration level
below the permissible limit as per the Pollution control board norms.
• THERMAL POLLUTION REDUCTION
The reason for thermal pollution is due to liberation of waste hot flue gas directly into the atmosphere
without utilizing the heat content. But in the case of VKGSEPL the heat content of waste flue gas
generated in their sponge iron kiln has been utilized in the WHR boiler for steam generation and thereby
reduces thermal pollution.
• GREEN HOUSE GAS (GHG) EMISSION REDUCTION
In VKG Steel and Energy Pvt.ltd., the waste flue gas generated from sponge iron kiln contains more heat
content and this is utilised in the WHR boiler of the CPP to generate electricity. Thus there is no need for
VKGSEPL to purchase electricity from TNEB grid. By displacing the procurement of electricity from the
state grid, VKGSEPL has reduced the emission of green house gases since the fossil fuel based thermal
power plants are the major power sources for TNEB grid.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 42
• SOx AND NOx EMISSIONS
The chimney of appropriate height has been erected within the boundary of CPP to reduce SOx
emissions and hence controlled within the TNPCB norms. NOx emissions will be controlled by
appropriate firing adjustments in the boiler.
• EFFLUENT FROM WATER TREATMENT PLANT
In order to neutralise (pH 7.0) the water drained from the water treatment plant after regeneration, it is
pumped to a neutralization pit. The neutralization pit will have acid resistant brick lining. Depending on
the quality of water collected in the pit, either an alkaline medium or acidic medium will be pumped into
the pit to neutralize the water.
• BOILER WATER BLOW DOWN
In order to maintain the solids concentration in the boiler water, blow down is employed in the boiler.
The blow down water will be at a temperature of 1000C. The quantity of blow down will be around 1.44
tph. This water can be taken to the effluent pond, where it will get cooled naturally.
• SEWAGE FROM THE POWER PLANT BUILDINGS
The sewage from the power plant building will be taken to a common septic tank through trenches. The
sewage from the septic tank will be disposed off through soak pit/concrete dispersion trenches. As the
sewage is taken in trenches the soil will not get contaminated.
• NOISE POLLUTION
The noise level in the plant has been maintained as per TNPCB standards by installing silencers, sound
proof walls etc.
D.2. If environmental impacts are considered significant by the project participants or the host
Party, please provide conclusions and all references to support documentation of an environmental
impact assessment undertaken in accordance with the procedures as required by the host Party:
CONCLUSION:
From step D.1 it is clear that all the environmental impacts of the CPP analysed in the environmental
impact assessment studies have no remarkable effect in the atmosphere. The assessment studies
undertaken by the VKGSEPL is according to the pollution control board norms. The Green House Gas
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 43
emission, thermal pollution and dust pollution have been reduced by the implementation of WHR based
CPP implemented in the sponge iron unit of VKGSEPL and the project promoter has received valid
approvals from the Tamilnadu Pollution Control Board (TNPCB).
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 44
SECTION E. Stakeholders’ comments
E.1. Brief description how comments by local stakeholders have been invited and compiled:
VKGSEPL has implemented a WHR based power plant at Uthiramerur Taluka of Kancheepuram
District. The project promoter had conducted stakeholders meeting on 18th August 2006 at project site
office in Melappakkam village, with local people, Village administrative officer, Panchayat President and
Government official from the TNEB were the participants in this meeting. The project promoter and
equipment supplier explained the various features and benefits of this project activity. The heat content
of waste hot flue gas has been utilized in a WHR boiler to generate steam and it is passed through a
turbine to generate electricity. In this process only heat energy from the flue gas is used as a thermal
source, so there will be zero GHG emissions by the project activity. They also explained the stakeholders
about the eco-friendly nature of the project. The project proponent has established good relationship with
the local people who ensure cooperation for the successful and continuous operations of the this project
The local people also agreed that their infrastructure facility like road and transportation was improved
due this project activity. A questionnaire had been circulated in order to welcome the comments of the
local people. The local village people agreed that due to this project activity the employment opportunity
has increased. There is no negative comment received from the stakeholders.
E.2. Summary of the comments received:
The project promoter and the equipment supplier explained the scenario about the project. There is no
pollution due to this power genation through the waste heat recovery boiler. The project activity has
contributed to developments in the social, economical and environmental area. Because of this project
activity the local village area and infrastructure facility improved. Further it creates direct employment
for the people in the local region. Hence the administrative leaders of local area like panchayat leader,
people provided positive comments for this project activity.Hence there is no negative comment received
from the stakeholders.
Tamilnadu Pollution Control Board (TNPCB) has issued the consent for establishment & clearance for
this WHR project under section 21 of Air (Prevention and control of Pollution) Act .1981 as amended in
1987, vide letter No.T3/TNPCB/F.NO 3731/KPM/RL/V/2005 dated 03/05/2005.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 45
The Ministry of Commerce & Industry has given an acknowledgement for this project activity. Letter No.
1939/SIA/TMO/2005 dated 25/04/2005.
The project activity has received certificate of registration of captive generating plant fro Department of
Electrical Inspectorate and electricity Tax, Government of Tamilnadu. Letter No. 4289/EI/KPM/2005
dated 25/10/2005
E.3. Report on how due account was taken of any comments received:
There is no negative comments from the local village people. The project activity had provided
employment opportunity for the local village people during the time of construction and operation. The
local people has not faced any problem due to the project activity. There is no negative comment
received from the stakeholders.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 46
Annex 1
CONTACT INFORMATION ON PARTICIPANTS IN THE PROJECT ACTIVITY
Organization: V.K.G Steel & Energy Pvt Limited
Street/P.O.Box: Broadway
Building: 163/1, 1st floor, K.Sons Complex
City: Chennai
State/Region: Tamilnadu
Postfix/ZIP: 600 108
Country: India
Telephone: 91-44-2524 9501
FAX: 91-44-4262 7402
E-Mail: [email protected]
URL:
Represented by: Mr.M.Mohamed Abdulla
Title: Director
Salutation: Mr.
Last Name: Abdulla
Middle Name:
First Name: Mohamed
Department: Power Plant
Mobile: +91 93802 22600 / +91 94449 00900
Direct FAX: 91-44-2524 9501
Direct tel: 91-44-2524 9500
Personal E-Mail: [email protected]
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 47
Annex 2
INFORMATION REGARDING PUBLIC FUNDING
There is no public funding for this project activity.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 48
Annex 3
BASELINE INFORMATION
CENTRAL ELECTRICITY AUTHORITY: CO2 BASELINE DATABASE
VERSION 2.0
DATE 21 June 2007
BASELINE METHODOLOGY ACM0002 / Ver 06
Weighted Average Emission Rate (tCO2/MWh) (incl. Imports)
2000-01 2001-02 2002-03 2003-04 2004-05 2005-06
South 0.74 0.75 0.82 0.84 0.78 0.74
Simple Operating Margin (tCO2/MWh) (incl. Imports)
2000-01 2001-02 2002-03 2003-04 2004-05 2005-06
South 1.03 1.00 1.01 1.00 1.00 1.01
Build Margin (tCO2/MWh) (not adjusted for imports)
2000-01 2001-02 2002-03 2003-04 2004-05 2005-06
South 0.71 0.71
Combined Margin in tCO2/MWh (incl. Imports)
2000-01 2001-02 2002-03 2003-04 2004-05 2005-06
South 0.87 0.85 0.86 0.86 0.85 0.86
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 49
Annex 4
MONITORING INFORMATION
Monitoring plan already discussed in section B.7.The detailed calculation for power generated from
WHRB’s alone and CER Calculation are explained below
Phase I
Calculation of power generated by WHRB’s alone
The power generated from WHRB alone is calculated on the basis of Total Enthalpy (steam enthalpy per
unit x steam flow) of WHRB steam as a percentage of Total Enthalpy of Steam fed to the common
header from both WHRB’s and FBC.
1) Total Enthalpy of Steam from WHR in kCal (H1)
= Enthalpy of Steam generated by WHRB in kcal/Kg * Total steam flow from the
WHRB in Tons
Enthalpy of WHRB steam is calculated based on the average Temperature and pressure of the WHRB
steam.
2) Total Enthalpy of Steam from FBC in kCal (H2)
= Enthalpy of Steam generated by FBC in kcal/Kg * Total steam flow from the
FBC in Tons
Enthalpy of FBC steam is calculated based on the average Temperature and pressure of the FBC steam.
3) Electricity generated by the WHRB alone(EGGEN)
The electricity generated by the WHR alone is calculated by multiplying the Total electricity generated
by both WHRB and FBC with the value of ratio between enthalpy of WHRB steam (H1) and the
enthalpy of total steam generated by WHRB & FBC(H1+H2)
EGGEN = EGTotal * (H1/(H1+H2))------------1
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 50
4) The total Auxiliary power Consumption of the Captive power plant EG AUX-TOTAL is Calculated
from the total auxiliary power consumption by the Captive power plant from both its own generation
(Captive power plant) and Grid
EG AUX-TOTAL = EGAUX –from CPP + EGAUX –from GRID
EGAUX –from CPP - Auxiliary power consumption by the Captive power plant from its (CPP) own
generation
EGAUX –from GRID- Auxiliary power consumption by the Captive power plant from Grid
5) Again, if Auxiliary Consumption for the CPP is EGAUX- EG AUX-TOTAL (in MWh), then WHR
Power Plant Auxiliary Consumption (EGAUX-WHR ) will calculated in the same ratio as
EGAUX = EG AUX –TOTAL x (H1 /(H1 + H2)) --------------2
6) Therefore Net Generation from Waste heat Recovery i.e. project activity (1 – 2)
EGy (MWh) = (EGGEN - EGAUX )
Phase II
In the second phase 2 No. of 2 MW Waste Heat recovery Boiler (WHRB) and existing 2 No. of 2 MW
WHRB connected to existing 8MW STG. So after implementation of Phase II the existing 8 MW STG
will be operating with 100 % Waste Heat Boilers Steam Only. The following monitoring plan will be
followed after Phase II.
1) Electricity generated by the Project activity (EGGEN) is measured by the Energy meter
2) EG AUX is Calculated from the Auxiliary power consumption meter reading from both Grid and
WHR Power Plant
EG AUX = EGAUX –from WHR + EGAUX –from GRID
EGAUX –from WHR- Auxiliary power consumption meter reading from WHR Power Plant
EGAUX –from GRID- Auxiliary power consumption meter reading from Grid
3 ) Therefore Net Generation from Waste heat Recovery i.e. project activity
EGy (MWh) = (EGGEN - EGAUX)
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 51
Annex 5
CER CALCULATION
1. For Year 2008- Phase-I (With 80 % PLF)
WHR Steam Parameter
Pressure of WHRB Steam (P1) = 66 kg/cm2
Temperature of WHRB Steam (T1) = 490O
C
Average temperature (T1) and pressure (P1) of the day is used for enthalpy calculation
Enthalpy of WHRB Steam (h1) = 3,390.61 kcal/kg
Total quantity of steam generated from WHRB (QWHRB) = 23 TPH
Total enthalpy of WHRB steam (H1) = QWHRB * h1
= 23*1,000*24*3,390.61
= 1.8716 *109
kcal/day
FBC Steam Parameter
Pressure of FBC Steam (P2) = 66 kg/cm2
Temperature of FBC Steam (T2) = 490O
C
Average temperature (T2) and pressure (P2) of the day is used for enthalpy calculation
Enthalpy of FBC Steam (h2) = 3,390.61 kcal/kg
Total quantity of steam generated from FBC (QFBC) = 25 TPH
Total enthalpy of FBC steam (H2) = QFBC * h2
= 25*1,000*24*3,390.61
= 2.0343 *109
kcal/day
Enthalpy ratio for WHRB Steam
= H1/ (H1+H2)
= 1.8716/ (1.8716+2.0343)
= 0.4791
Total electricity generated by both FBC and WHRB (EGTotal)
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 52
Total Capacity = 8 MW
Plant load factor = 80%
Operational Days = 330 Days
Total Electricity Generation = 8*24*330*0.8
= 50,688 MWh/year
Total electricity generated by WHRB alone (EGGen)
EGGen = EGTotal * (H1/ (H1+H2)
= 50,688 * 0.4791
= 24,288 MWh/year
Auxiliary electricity consumed by Total captive power plant (EGAUX TOTAL)
= EG AUX –from CPP + EG AUX-from GRID
Electricity consumed from Captive power plant
(EG AUX –from CPP) = 10 % of the EGTotal
Electricity consumed from grid (EG AUX –from GRID) = 0
EGAUX- TOTAL = 50,688 * 0.10 + 0
=5,068 MWh/year
Auxiliary electricity consumed by WHRB alone (EGAUX - WHRB)
= EG AUX - TOTAL * (H1/ (H1+H2)
= 5068 * 0.4791
= 2,429 MWh/year
Net electricity generated by WHRB alone (EGy) = EGGen - EGAUX -WHRB
= 24288 – 2429
= 21,859 MWh/year
Emission Reduction (ER)
Baseline emission factor = 0.86 tCO2/MWh
Baseline emission (BEy) = 21859 * 0.86
= 18,799 tCO2/year
This project activity utilizes the waste heat for power generation. Hence there is no project emission and
leakage from the project activity. There is no GHG emission within the project boundary.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 53
ERY = BEY − PEY
PEY = 0
ERY = B.EY
Emission Reduction (ER) = 18,799 tCO2/year
2. For Year 2009 Phase-II
Power generation from continuation of Phase I Four (4) MW WHR power plant (With 80 % PLF)
Total Capacity = 4 MW
Operational Days = 330Days
Plant load factor = 80%
Total Electricity Generation (EG GEN) = 4*24*330*0.8
= 25,344 MWh/year
Auxiliary Consumption (EG AUX) = EG AUX from CPP + EG AUX from GRID
EG AUX from CPP = 10 % of the EG GEN
EG AUX from GRID = 0
EG AUX = 25,344 *0.10 + 0
= 2,534
Net Electricity Generation = 25,344 -2,534
= 22,810 MWh/year
Phase-II Power generation from new 4 MW WHR power plant (With 60 % PLF)
Total Capacity = 4 MW
Operational Days = 330Days
Plant load factor = 60%
Total Electricity Generation (EG GEN) = 4*24*330*0.6
= 19,008 MWh/year
Auxiliary Consumption (EG AUX) = EG AUX from CPP + EG AUX from GRID
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 54
EG AUX from CPP = 10 % of the EG GEN
EG AUX from GRID = 0
EG AUX = 19,008*0.10 + 0
= 1,900
Net Electricity Generation(EGY) = 19,008 -1,900
= 17,108 MWh/year
Total Net Power generation from Phase-I & Phase-II
Total Net Electricity Generation (EGY) = 39,918 MWh/year
Baseline emission factor = 0.86 tCO2/MWh
Baseline emission (BEy) = 39,918* 0.86
= 34,328 tCO2/year
This project activity utilizes the waste heat for power generation. Hence there is no project
emission and leakage from the project activity. There is no GHG emission within the project
boundary.
ERY = BEY − PEY
PEY = 0
ERY = B.EY
Emission Reduction (ER) = 34,328 tCO2/year
3. For the Year 2010 during Phase II (With 80 % PLF)
Total Capacity = 8 MW
Operational Days = 330 Days
Plant load factor = 80%
Total Electricity Generation (EGGEN) = 8*24*330*0.8
= 50,688 MWh/year
Auxiliary Consumption (EG AUX) = EG AUX from CPP + EG AUX from GRID
EG AUX from CPP = 10 % of the EG GEN
EG AUX from GRID = 0
EG AUX = 50,688*0.10 + 0
= 5,068
Net Electricity Generation (EGY) = 50,688 -5068
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 55
= 45,620 MWh/year
Baseline emission factor = 0.86 tCO2/MWh
Baseline emission (BEy) = 45,620 * 0.86
= 39,232 tCO2/year
This project activity utilizes the waste heat for power generation. Hence there is no project
emission and leakage from the project activity. There is no GHG emission within the project
boundary.
ERY = BEY − PEY
PEY = 0
ERY = B.EY
Emission Reduction (ER) = 39,232 tCO2/year
The basis for 2010 calculation applies for the balance crediting years i.e. 2011 to 2017.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 56
Appendix A REFERENCES
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 57
Appendix B Abbreviations
ACC Air- Cooled Condenser
CASE Commission for Additional Sources of Energy
CCGT Combined Cycle Gas Turbine
1 Kyoto Protocol to the United Nations Framework Convention on Climate Change
(UNFCCC)
2 Website of United Nations Framework Convention on Climate Change,
http://unfccc.int
3 UNFCCC decision 17/CP.7: Modalities and procedures for a clean development
mechanism as defined in article 12 of the Kyoto Protocol
4 UNFCCC, Clean Development Mechanism, Project Design Document (CDM-PDD)
5 UNFCCC document: Approved consolidated baseline methodology
ACM0004“Consolidated baseline methodology for waste gas and /or heat and /or for
pressure for power generation”
6 Detailed project report– VKG Steel and Energy Pvt,Ltd.
7 Baseline for Renewable energy projects under clean development mechanism-TERI
Report No 2000RT64.
8 Website of Central Electric Authority (CEA), Ministry of Power, Govt. of India-
www.cea.nic.in
9 Website of TNERC www.tnerc.tn.nic.in
10 Website of Kerala Electricity Board www.kseboard.com
11 Website of Karnataka Power Transmission Corporation Limited www.kptcl.com
12 Website of Andhrapradesh Power Generation Company www.apgenco.com
13 Website of TamilNadu Electricity Board www.tneb.org
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 58
CDM Clean Development Mechanism
CEA Central Electricity Authority
CER Certified Emission Reductions
cm Centimetre
CO2 Carbon dioxide
CPP Captive Power Plant
DCS Digital Control Systems
DNES Department of Non-conventional Energy Sources
DPR Detailed Project Report
EF Emission Factor
ESP Electro Static Precipitator
FBC Fluidised Bed Combustion
GHG Green House Gas
IPCC Intra governmental Panel for Climate Change
IPP Independent Power Producers
IPP Independent Power Producers
kCal Kilo Calories
kg Kilogram
Km Kilometre
KP Kyoto Protocol
Ksca Kilogram Square Centimetre absolute
kv Kilo voltage
kW Kilowatt
kWh Kilowatt hour
LP Low Pressure
MNES Ministry of Non-Conventional Energy Sources
MT Metric Tons
MU Million Units
MU Million Units
MW Megawatt
NGO Non Government Organizations
NLC Neyveli Lignite Corporation
NHPC National Hydro Power Corporation
NOC No Objection Certificate
NTPC National Thermal Power Corporation
PDD Project Design Document
PFC Power Finance Corporation Ltd.
PIN Project Idea Note
PLF Plant Load Factor
PPA Power Purchase Agreement
QA Quality Assurance
QC Quality Control
RET Renewable Energy Technologies
RLDC Regional Load Dispatch Centres
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03.1.
CDM – Executive Board page 59
SLDC State Load Dispatch Centres
SPM Suspended Particulate Matter
TNEB Tamilnadu Electricity Board
TNERC TamilNadu Electricity Regulatory Commission
TNPCB Tamilnadu Pollution Control Board
TPH Tons Per Hour
VKGSEPL VKG Steel and Energy Pvt,Ltd.
WHR Waste Heat Recovery