Project control

44
PROJECT CONTROL Case Study – CCS JOE Phatsima Martin Janse van Rensburg [email protected]

Transcript of Project control

Page 1: Project control

PROJECT CONTROL

Case Study – CCS JOE

Phatsima

Martin Janse van Rensburg

[email protected]

Page 2: Project control

PROJECT INFO

• Simple job priced

• Only one end and Joe’s salary in P&G

• 23 Production days per month

• 1000 meter bill quantity (12 months?)

• 100 meters scheduled per month (Cycle Calculation 100 m/month)

• Employment Capital included in Rates – based on machine hours

• Trackless Mining and Engineering Crew

• 20% Mark-up

• More detail, not elaborated on (retention, interest, escalation, cash-flow etc)

Page 3: Project control

BOQ

Page 4: Project control

BOQ – MACRO EXPLODE

Page 5: Project control

PROJECT REVENUE & COST

Page 6: Project control

PROJECT ENVIRONMENT - QS

• Revenue as per certificate (accuracy)

• Accurate Costing – To date Cost and quantities correct (bill, claimed, actual)

• 100% Candy compliance, certification in Candy

• All variations / claims priced (no plug etc. rates)

• Financial accounting and costing compliant

Page 7: Project control

PROJECT ENVIRONMENT - FINANCIAL

• Calendar of Cost roll-over (Buildsmart)

• To date ledger / Chart of account cost codes – mapped to resource codes

• Non-posted costs (Provisions, petty cash etc.)

• Initial budget upload to Buildsmart, revised budget uploads

• Cost rate updates (will show example later)

Page 8: Project control

PROJECT ENVIRONMENT – PLANNING AND PRODUCTION

• Baseline Program (and Revised baseline if applicable)

• Program progress

• Bill and Program linked (QTY forecast)

• Production output analysis

• Tender allowable QTY vs actual QTY

• Tender allowable R vs actual R

Page 9: Project control

VALUATION - 1

Page 10: Project control

VALUATION 1

• Claimed quantity

• Measure Actual Progress QTY

• Progress the Program, synchronise Valuation QTY with Program Progress

Page 11: Project control

COST REPORTING

• Cost import from Buildsmart

(Earned Value not discussed)

SPI – Schedule performance Index (allowable to-date against Baseline)

CPI – Cost Performance Index (allowable to-date against Cost to-date)

Page 12: Project control
Page 13: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 318,000 870,255 1,779,924 390,303 111,412 418,631 754,186

COST 318,000 929,312 2,118,643 389,644 280,402 418,390 313,072

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 14: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 318,000 870,255 1,779,924 390,303 111,412 418,631 754,186

COST 318,000 929,312 2,118,643 389,644 280,402 418,390 313,072

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 15: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 318,000 870,255 1,779,924 390,303 111,412 418,631 754,186

COST 318,000 929,312 2,118,643 389,644 280,402 418,390 313,072

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 16: Project control

REFRESHER

1. Ensure BOQ and Program Conforms

2. Base Forecast

3. Valuation 1

4. Measure ACTUAL QTY progress and re-measure FINAL QTY

5. Progress the Program

6. Synchronise Valuation QTY with Program Progress

7. Update Bill with forecast QTY

8. Import real cost TO DATE

9. UPDATE COST RATE and COST Worksheets

10. Print Reports

11. Next Valuation

Page 17: Project control

VALUATION 2

• COST Rate Update (Point 9 Previous…)

• Rebar support Base rate R69-90 – Estimator got it wrong

• Steel became VERY expensive, say R300 per bolt (escalation not discussed)

• Joe received huge increase from R300,000 per month to R400,000

Page 18: Project control

VALUATION - 2

Page 19: Project control
Page 20: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 448,062 892,881 1,826,203 400,451 114,309 429,516 773,795

COST 703,416 953,474 2,173,728 399,775 1,786,935 429,266 321,212

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 21: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 448,062 892,881 1,826,203 400,451 114,309 429,516 773,795

COST 703,416 953,474 2,173,728 399,775 1,786,935 429,266 321,212

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 22: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 448,062 892,881 1,826,203 400,451 114,309 429,516 773,795

COST 703,416 953,474 2,173,728 399,775 1,786,935 429,266 321,212

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 23: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 448,062 892,881 1,826,203 400,451 114,309 429,516 773,795

COST 703,416 953,474 2,173,728 399,775 1,786,935 429,266 321,212

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 24: Project control

VALUATION 2 - REFRESHER

1. Contractor BLEEDS

2. If he doesn’t run proper project controls, only finds it out in certificate 11

3. If he enforces proper controls, Joe is history (maybe Estimator and Procurement as well)

4. Reduction in Project Margin from 16.67% to 11.55%

Serious Note…

Client should award to contractor that can execute, because

1. The above scenario will erode relationships

2. Contractor will seek remedy (Variations, contract exit etc.)

3. Both contractor and client needs to be “healthy” for successful Project

4. Ensure proper Contract Price adjustment included in longer projects

Page 25: Project control

1. For Valuation 3…

2. Joe’s Cost rate back to R300,000

3. Support element Cost rate back to R69.90

4. This will show reversal on cost…but only done to reset for following examples

5. Forecast cost and duration, with Contract Variation (Not using Cost Worksheets)

…Otherwise changing support density example will become problematic

And that has never ever occurred in executing a mining project…

SOME “RESETS”

Page 26: Project control

VALUATION - 3

Page 27: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 245,814 497,786 1,018,117 223,253 63,728 239,457 431,394

COST -9,540 531,566 1,211,864 222,876 -1,338,854 239,323 179,077

-1,500,000

-1,000,000

-500,000

0

500,000

1,000,000

1,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 28: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 245,814 497,786 1,018,117 223,253 63,728 239,457 431,394

COST -9,540 531,566 1,211,864 222,876 -1,338,854 239,323 179,077

-1,500,000

-1,000,000

-500,000

0

500,000

1,000,000

1,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 29: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 245,814 497,786 1,018,117 223,253 63,728 239,457 431,394

COST -9,540 531,566 1,211,864 222,876 -1,338,854 239,323 179,077

-1,500,000

-1,000,000

-500,000

0

500,000

1,000,000

1,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 30: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 245,814 497,786 1,018,117 223,253 63,728 239,457 431,394

COST -9,540 531,566 1,211,864 222,876 -1,338,854 239,323 179,077

-1,500,000

-1,000,000

-500,000

0

500,000

1,000,000

1,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 31: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 245,814 497,786 1,018,117 223,253 63,728 239,457 431,394

COST -9,540 531,566 1,211,864 222,876 -1,338,854 239,323 179,077

-1,500,000

-1,000,000

-500,000

0

500,000

1,000,000

1,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 32: Project control

1. For Valuation 4…

2. Support density change

3. Thus reduced advance rate from 100m/month to say 80m/month

CHANGE IN SUPPORT

Page 33: Project control

1. Reduced Mining tempo = Longer time

(assume same total quantity / scope)

1. Affects P&G = Duration extended (Program)

2. Increased Drill steel and Bolts usage (Estimate)

3. Increased Equipment Operating cost (OPEX Bolter)

4. Affects Equipment depreciation (CAPEX Bolter)

5. Reduced crew meters – R/m increase

6. Lets first assume only 200 meters of the tunnel scope applies

7. No CPA, shown, but will affect coefficients

CHANGE IN SUPPORT

Page 34: Project control

BOQ – MACRO EXPLODE

Tempo

Support Cost

Page 35: Project control

VALUATION - 4

Page 36: Project control

VALUATION - 5

Page 37: Project control

VALUATION - 12

Page 38: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 303,690 1,453,325 2,972,474 651,807 186,057 699,111 1,810,633

COST 303,690 1,453,325 2,972,474 651,805 186,057 699,114 1,810,633

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

3,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 39: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 303,690 1,453,325 2,972,474 651,807 186,057 699,111 1,810,633

COST 303,690 1,453,325 2,972,474 651,805 186,057 699,114 1,810,633

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

3,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 40: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 303,690 1,453,325 2,972,474 651,807 186,057 699,111 1,810,633

COST 303,690 1,453,325 2,972,474 651,805 186,057 699,114 1,810,633

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

3,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 41: Project control

L-Sup A-Cat A B-Cat B Consumables Materials E-Empl/Cost P-Plant

ALLOWABLE 303,690 1,453,325 2,972,474 651,807 186,057 699,111 1,810,633

COST 303,690 1,453,325 2,972,474 651,805 186,057 699,114 1,810,633

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

3,500,000

CURRENT VALUATION - COST VS ALLOWABLE

Page 42: Project control

VALUATION - FINAL

Page 43: Project control

CLOSING

1. Project Controls – Both Client and Contractor cannot afford not to enforce

2. Above example, Contractor ended on target (Margin)

3. Client didn’t “overpay” but lost 2 months on Program

4. “All In” Bill R/m increased from R60,436/m to R62,871

Page 44: Project control

QUESTIONS