Project Closing Report
description
Transcript of Project Closing Report
1
AP PROJECTS
PROJECT CLOSING REPORT
ROXTON-GROWELS MALL KANDIWALI
2
GROWELS-KANDIWALI
ROXTON-GROWELS MALL KANDIWALI
3
CONTENTS PAGE NO.
INTRODUCTION 3
PROJECT TEAM 4
STORE LAYOUT 5
BEFORE AND AFTER 6
FINISHED STORE INTERNALLY AND EXTERNALLY 10
PROJECT PLANNING 11
PROJECT DIARY 13
ROXTON-GROWELS MALL KANDIWALI
4
INTRODUCTION
ADDRESSROXTON FIRST FLOORGROWELS MALLAKRUTI ROADWESTERN EXPRESS HIGHWAYKANDIWALI EASTMUMBAI-400101
ROXTON-GROWELS MALL KANDIWALI
ROXTON IS OFFERING CASUAL BRANDS INTO MENS WEAR.ROXTON IS SISTER CONCERN OF RAJHANS EXPORTS WHICH IS THIRD BEST TR IMPORTERS.ROXTON PROMISES HUNDRED PLUS RETAIL OUTLETS ACROSS THE COUNTRY BY 2011.ROXTON HAS ALREADY MADE ITS PRESENCE IN CITIES LIKE DELHI,MUMBAI.CHHATTISGARH,HARIYANA & PUNJABTHE STORE HAS CUSTOMER SERVICE DESK TO HELP CUSTOMER WITH ITS RELATED SERVICES
5
PROJECT HEAD MR. ARVIND PUROHIT
PROJECT MANAGER-SURESH TIWARI
INTERIOR DESIGNER-MR. SHAHZAD
SITE ENGG. MR. JITENDRA PRAJAPATI
MR. AMIT BHHOSLE
& SITE EXECUTION TEAM
PROJECT TEAM
ROXTON-GROWELS MALL KANDIWALI
6
STORE LAYOUT
ROXTON-GROWELS MALL KANDIWALI
7
BEFORE AND AFTER
ROXTON-GROWELS MALL KANDIWALI
8
BEFORE AND AFTER
ROXTON-GROWELS MALL KANDIWALI
9
BEFORE AND AFTER
ROXTON-GROWELS MALL KANDIWALI
10
FINISHED STORE
ROXTON-GROWELS MALL KANDIWALI
11
FINISHED STORE
ROXTON-GROWELS MALL KANDIWALI
12
PROJECT PLANNING
CUSTOMER SATISFACTION
TIME MANAGMENT
PLANING
ROXTON-GROWELS MALL KANDIWALI
13
BAR CHART
ROXTON-GROWELS MALL KANDIWALI
23/8 24/8 25/8 26/8 27/8 28/8 29/8 30/8 31/8 1|9
Material N Tool
Manpower
AP.O.P & CIVIL WORK PLAN
PLASTERING
B.O.Q.
CIVIL1,CIVIL2
TILINGB.O.
CIVIL1,CI
1 ACTUAL
Marking as per dwg, PLAN
Line
P.O.P.(PE1,P
2 ACTUAL
Griding PLAN
B.O.Q.
PE1,PH1,PH2
3 ACTUAL
Fixing of Gypsum sheet as per dwgPLAN
Drill m
PE1,PH1,PH2
4 ACTUAL
T
ADD.-THANE-RAM MARUTI ROAD
Resourc
Delay due to land lord
Delay due to architect
Delay due to Roxton
Planned activiteis
On schedule
Delay due to contractorCOLOUR CODES
14
PROJECT DIARY
ROXTON-GROWELS MALL KANDIWALI
Project Diary Ahead w.r.t. Schedule
GROWELS-KANDIWALI On ScheduleDelay w.r.t. Schedule
Date Count down ACTIVITY DAYS
24-10-10MEETING HELD AND INFORMATION IS PASSED ON AT ROXTON OFFICE TO OPEN THE STORE AT
3.30 PM0
INVENTRY IDENTIFICATION IS STARTED JOINTLY BETWEEN ROXTON AND PMC FROM 9.00 PM
TO 10.30 PM
-30
INVENTRY IDENTIFICATION IS CONTINUED TILL 12.00AM MEAN WHILE THE VENDORE FOR FALL
CEILING & PAINTER IS ARRNAGED ,GYPSUM FALL CEILING WORK IS STARTED AT 2.30
PM,PAINTING WORK IS STARTED,AT 8.00 PM ,MEAN WHILE THE CARPENTOR IS ARRANGED
1
21-10-10 -27 3
FALL CEILING REPAIRING IS CONTINUED ,FIRST COAT OF LAMBI ON THE WALLS ARE DRYED BY
1.00 PM,FURNITURE ARE BOUGHTAT 2.30 PM,ELECTRICAL FITTINGS ARE BOUGHT AND
ELECTRICAL & FURNITURE WORK IS STARTED BY 4.00 PM,PRIMER IS STARTED BY 6.00 PM,FALL
CEILING WORK IS COMPLETED BY 8.00 PM,FIRST COAT PAINTING IS DONE BY 11.30 PM
23-10-10 -29
222-10-10 -28
SECOND COAT PAINTING IS DONE BY 4.00 AM,AND PRIMAR IS DONE ON TRIAL ROOM &
STORE ROOMS BY 70.00 AM,TRIAL ROOM AND STORE ROOMS ARE MADE BY 6.00
AM,ELECTRICALL 75% OF ELECTRICAL WORK IS DONE BY 7.00 AM,VINYL FLOORING IS STARTED
BY 2.30 PM,FACED IS ERECTED BY 5.00 PM,ELECTRICAL WORK IS COMPLETED BY 6.30
PM,FURNITURE IS COMPLETED BY 7.00 PM,PAINTING IS DONE BY 8.30 PM
ROXTON-GROWEL MALL-KANDIWALI
CARPENTARY
ELECTRICAL
POP
PAINTIN
G
NAME BOARD
0%10%20%30%40%50%60%70%80%90%
100%
REWORKEXTRA WORKQTY IN BOQ
COST ANALYSIS