![Page 1: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/1.jpg)
C M A
Utilisation de MS Project 2007
![Page 2: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/2.jpg)
2011 - 2012 D. VALLETON - CMA - 07 2
MS Project
COURS N° 7
![Page 3: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/3.jpg)
2011 - 2012 D. VALLETON - CMA - 07 3
MS Project – Cours N° 6 1 – Planification des tâches
• optimisation de la durée du projet• rétro-planning
2 – Entités de base• affichages• tables• filtres• groupes
3 – Planification des ressources• Définitions• Types de tâche• Affectation de ressources
![Page 4: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/4.jpg)
2011 - 2012 D. VALLETON - CMA - 07 4
MS Project – Cours N° 7 1 Entités de base
• affichages• tables• filtres• groupes
2 – Planification des ressources• Définitions• Types de tâche• Affectation de ressources
![Page 5: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/5.jpg)
2011 - 2012 D. VALLETON - CMA - 07 5
MS Project – PlanificationRétro-planning
12
43
Planification par la fin Projet ayant une date de fin impérative Nouveau projet « Conception_usine_06 » Date de fin : le 4 avril 2012 au matin
![Page 6: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/6.jpg)
2011 - 2012 D. VALLETON - CMA - 07 6
MS Project – PlanificationMode de saisie par « Réseau des tâches »
1
2
Zone de saisie du réseau
3
4
![Page 7: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/7.jpg)
2011 - 2012 D. VALLETON - CMA - 07 7
MS Project – PlanificationMode de saisie par « Réseau des tâches »
Zone de saisie du réseau Zone de saisie du réseau
![Page 8: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/8.jpg)
2011 - 2012 D. VALLETON - CMA - 07 8
MS Project – Entités de base
Affichages
Tables
Filtres
Groupes
![Page 9: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/9.jpg)
2011 - 2012 D. VALLETON - CMA - 07 9
MS Project – Entités de baseAffichages
![Page 10: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/10.jpg)
2011 - 2012 D. VALLETON - CMA - 07 10
MS Project – Entités de baseAffichages
Un affichage simple est un « quadruplet »1. Ecran2. Table3. Groupe4. Filtre
Un affichage combiné comporte 2 affichages 1. affichage supérieur2. affichage inférieur
![Page 11: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/11.jpg)
2011 - 2012 D. VALLETON - CMA - 07 11
MS Project – Entités de baseAffichage simple
Choisir :
1. Ecran
2. Table
3. Groupe
4. Filtre
5. Faire « OK »
12
43
5
![Page 12: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/12.jpg)
2011 - 2012 D. VALLETON - CMA - 07 12
MS Project – Entités de baseAffichage combiné
Choisir :
1. Affichage supérieur
2. Affichage inférieur
3. Faire « OK »
12
3
![Page 13: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/13.jpg)
2011 - 2012 D. VALLETON - CMA - 07 13
MS Project – Entités de baseTables
Une table est un ensemble de champs concernant les tâches
Exemples : table des entrées
![Page 14: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/14.jpg)
2011 - 2012 D. VALLETON - CMA - 07 14
MS Project – Entités de baseTables
Exemples : table des prévisions
![Page 15: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/15.jpg)
2011 - 2012 D. VALLETON - CMA - 07 15
MS Project – Entités de baseTables
Exemples : table des prévisions
![Page 16: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/16.jpg)
2011 - 2012 D. VALLETON - CMA - 07 16
MS Project – Entités de baseFiltres
![Page 17: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/17.jpg)
2011 - 2012 D. VALLETON - CMA - 07 17
MS Project – Entités de baseGroupes
![Page 18: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/18.jpg)
2011 - 2012 D. VALLETON - CMA - 07 18
MS Project – Entités de basePratique
Se placer dans le projet « conception_usine_06 » Créer une table « tab-cma » comportant
• N° tâche (centré, 5 caractères)• Nom tâche (gauche, 25 caractères)• Marge libre (droite)• Marge totale (droite)• Prédécesseurs (gauche)
Corriger les largeurs de colonnes Créer affichage « Gantt-marges » avec table « tab-
cma » Ajouter un filtre « devant commencer avant le »
15/03/2012
![Page 19: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/19.jpg)
2011 - 2012 D. VALLETON - CMA - 07 19
MS Project – Entités de basePratique
Se placer dans le projet « conception_usine_06 » Créer un affichage combiné
• Gantt-marges• Formulaire tâche
Créer un affichage comportant• Schéma des dépendances• Diagramme de Gantt
Comment supprimer le double affichage ?
![Page 20: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/20.jpg)
2011 - 2012 D. VALLETON - CMA - 07 20
1. « Affichage » - « Plus d’affichages »
2. « Gantt relatif aux marges »
3. « Appliquer »
MS Project – PlanificationAffichage des marges
12
3
![Page 21: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/21.jpg)
2011 - 2012 D. VALLETON - CMA - 07 21
Marge =
date FPTA – date de fin prévue
MS Project – PlanificationAffichage des marges
![Page 22: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/22.jpg)
2011 - 2012 D. VALLETON - CMA - 07 22
Marge libre : temps pendant lequel on peut retarder une tâche sans influer sur les autres DPTO(successeur le plus proche) - FPTO
MS Project – PlanificationAffichage des marges
Marge totale : temps pendant lequel on peut retarder une tâche sans influer sur la fin du projet DPTA - DPTO
![Page 23: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/23.jpg)
2011 - 2012 D. VALLETON - CMA - 07 23
MS Project – PlanificationAffichage des marges
Marge tot. DPTA (Clôtures) – DPTO (Clôtures) | L 26/03/13 – V 30/11/12
Marge libre DPTO(Alarmes) – FPTO(Bardages) | L 19/11/12 – V 16/11/12
![Page 24: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/24.jpg)
2011 - 2012 D. VALLETON - CMA - 07 24
MS Project – PlanificationAffichage des marges sur le diagramme - Contournement
![Page 25: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/25.jpg)
2011 - 2012 D. VALLETON - CMA - 07 25
MS Project – PlanificationAffichage des marges sur le diagramme - Contournement
1 2 3 4
5 6
![Page 26: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/26.jpg)
2011 - 2012 D. VALLETON - CMA - 07 26
MS Project – PlanificationAffichage des marges sur le diagramme - Contournement
![Page 27: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/27.jpg)
2011 - 2012 D. VALLETON - CMA - 07 27
MS Project – PlanificationAffichage des marges sur le diagramme - Contournement
![Page 28: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/28.jpg)
2011 - 2012 D. VALLETON - CMA - 07 28
MS Project – PlanificationAffichage des marges sur le diagramme - Contournement
![Page 29: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/29.jpg)
2011 - 2012 D. VALLETON - CMA - 07 29
MS Project – PlanificationAffichage des marges sur le diagramme - Contournement
Pratique
Copier le projet « construction_usine_06 » en « construction_usine_07 »
Créer un nouvel affichage « Marge-totale »• comportant une nouvelle barre matérialisant la « marge
totale » (couleur vert clair) de la fin de la tâche, à la valeur de la « marge totale » placer une butée de fin à l’extrémité droite de la barre, une
étoile à l’extrémité gauche Faire afficher, à droite de la barre, le nombre de jours
• avec affichage de la table « Prévisions » Rendre cet affichage utilisable par tout projet
![Page 30: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/30.jpg)
2011 - 2012 D. VALLETON - CMA - 07 30
MS Project – Planification ressources
Planification des tâches• ordre des tâches• durée des tâches
Comment réaliser ces tâches ?• à l’aide de ressources
hommes équipements matières
• les ressources sont affectées aux tâches (1ère étape)
![Page 31: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/31.jpg)
2011 - 2012 D. VALLETON - CMA - 07 31
MS Project – Affectation ressources
Les ressources sont affectées aux tâches
• de manière uniforme (la charge est répartie uniformément pendant la durée de la tâche)
• de manière variable (la charge est variable selon les jours)
![Page 32: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/32.jpg)
2011 - 2012 D. VALLETON - CMA - 07 32
MS Project – Affectation ressources
Affectations uniformes
Les types de tâches • Capacité fixe• Durée fixe• Travail fixe
Tâche pilotée par l’effort
![Page 33: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/33.jpg)
2011 - 2012 D. VALLETON - CMA - 07 33
MS Project – Affectation ressources
Définitions• Durée laps de temps pendant lequel se
déroule la tâche• Unité d’affectation ou capacité nombre de
ressources affectées à une tâche• Travail = Unité d’affectation x durée• Travail ou charge
Exemple : tâche nécessitant 2 personnes pendant 2 jours travail de 28h
![Page 34: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/34.jpg)
2011 - 2012 D. VALLETON - CMA - 07 34
MS Project – Affectation ressources
Prévisions « pilotées par l’effort »• la durée de la tâche varie• la valeur de travail reste constantequelque soit la modification que l’on fait subir au
nombre de ressources (unités)
Prévisions NON « pilotées par l’effort »• le changement d’affectation de ressources ne
modifie pas la durée de la tâche
![Page 35: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/35.jpg)
2011 - 2012 D. VALLETON - CMA - 07 35
MS Project – Affectation ressources
L’équation de base de Project entre 3 variables :
Travail = Unité d’affectation x durée
Travail n’existe que s’il y a eu affectation de ressource !
Que se passe-t-il si une des variables change ?
![Page 36: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/36.jpg)
2011 - 2012 D. VALLETON - CMA - 07 36
MS Project – Affectation ressourcesAffectation d’une ressource (M1)
![Page 37: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/37.jpg)
2011 - 2012 D. VALLETON - CMA - 07 37
Affectation de 5 unités de la ressource « Maçon »
MS Project – Affectation ressourcesAffectation d’une ressource (M1)
25 j x 5 u x 7 h 875 h
875 h x 26 € 22 750 €
![Page 38: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/38.jpg)
2011 - 2012 D. VALLETON - CMA - 07 38
MS Project – Affectation ressourcesAffectation d’une ressource (M1)
Avril 2011 665 h
Mai 2011 210 h
![Page 39: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/39.jpg)
2011 - 2012 D. VALLETON - CMA - 07 39
MS Project – Affectation ressourcesAffectation ressources multiples (M1) – une par une
Affectation de 1 unité des ressources « Maçon », « Menuisier », « Peintre »
![Page 40: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/40.jpg)
2011 - 2012 D. VALLETON - CMA - 07 40
MS Project – Affectation ressourcesAffectation ressources multiples (M1G)
Affectation de 1 unité des ressources « Maçon », « Menuisier », « Peintre »
Ctrl
Uniquement, si même nombre d’unités
Pas de nombre d’unité spécifié 1
![Page 41: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/41.jpg)
2011 - 2012 D. VALLETON - CMA - 07 41
MS Project – Affectation ressourcesAffectation ressources multiples (M1G)
Affectation de 1 unité des ressources « Maçon », « Menuisier », « Peintre »
![Page 42: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/42.jpg)
2011 - 2012 D. VALLETON - CMA - 07 42
MS Project – Affectation ressourcesAffectation ressources multiples (M2)
1
2
![Page 43: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/43.jpg)
2011 - 2012 D. VALLETON - CMA - 07 43
MS Project – Affectation ressourcesAffectation ressources multiples (M2)
1
2
![Page 44: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/44.jpg)
2011 - 2012 D. VALLETON - CMA - 07 44
MS Project – Affectation ressourcesAffectation ressources multiples (M3a)
1
2
2A
B
Affichage combiné – Entrée des tâches :
– Diagramme de Gantt
– Formulaire de tâche
A
B
![Page 45: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/45.jpg)
2011 - 2012 D. VALLETON - CMA - 07 45
MS Project – Affectation ressourcesAffectation ressources multiples (M3b)
1
2
![Page 46: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/46.jpg)
2011 - 2012 D. VALLETON - CMA - 07 46
MS Project – Affectation ressourcesAffectation ressources multiples (M3b)
Si ajout ressource
![Page 47: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/47.jpg)
2011 - 2012 D. VALLETON - CMA - 07 47
MS Project – Affectation ressourcesAffectation ressources multiples (M3b)
++Pratique, présence de tous les paramètres
Entrée des tâchesM3b
++Pratique, présence de tous les paramètres
Entrée des tâchesM3a
+Pratique, mais attention au type de tâche
Informations sur la tâche
M2
-Peu pratique, mais permet affich. graphes
Affecter les ressourcesM1G
-Peu pratique, mais permet affich. graphes
Affecter les ressourcesM1
APPREC.COMMENTAIRESMODE DE SAISIETYPE
![Page 48: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/48.jpg)
2011 - 2012 D. VALLETON - CMA - 07 48
MS Project – Affectation ressources
Utilisation d’un projet « exemple_cma_02 » Calendrier CMA Une tâche « Prototype », durée initiale 2 jours 2 ressources :
• concepteur• assistant
Exemples d’affectation
![Page 49: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/49.jpg)
2011 - 2012 D. VALLETON - CMA - 07 49
MS Project – Affectation ressources
Exemples d’affectation
![Page 50: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/50.jpg)
2011 - 2012 D. VALLETON - CMA - 07 50
MS Project – Affectation ressources
Exemples d’affectation
1 2
3
![Page 51: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/51.jpg)
2011 - 2012 D. VALLETON - CMA - 07 51
MS Project – Affectation ressources
Exemples d’affectation
Passage à la tâche suivante
1. Affichage du nom de la ressource et du nombre d’unités
2. Travail a été calculé : 2 Concepteurs x 2 jours x 7 heures
![Page 52: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/52.jpg)
2011 - 2012 D. VALLETON - CMA - 07 52
MS Project – Affectation ressources
Impact du type de tâche
![Page 53: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/53.jpg)
2011 - 2012 D. VALLETON - CMA - 07 53
MS Project – Affectation ressources
Création d’un projet « exemple_cma_02 » Utiliser le calendrier CMA Création d’une tâche « Prototype », durée
initiale 2 jours 2 ressources (capacité maxi 1) :
• concepteur• assistant
Ajouter dans table entrée colonne « Travail »
Pratique (1)
![Page 54: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/54.jpg)
2011 - 2012 D. VALLETON - CMA - 07 54
MS Project – Affectation ressources
Effectuer l’affectation suivante :• type tâche « capacité fixe »-2 unités « Concepteur »•modifier la durée de 2 jours à 1 jour•noter la modification obtenue
Effectuer l’affectation suivante :• type tâche « durée fixe »-2 unités « Concepteur »•modifier la durée de 2 jours à 1 jour•noter la modification obtenue
Effectuer l’affectation suivante :• type tâche « travail fixe »-2 unités « Concepteur »•modifier la durée de 2 jours à 1 jour•noter la modification obtenue
Pratique (2)
![Page 55: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/55.jpg)
2011 - 2012 D. VALLETON - CMA - 07 55
MS Project – Affectation ressources
Effectuer l’affectation suivante :• type tâche « capacité fixe »-2 unités « Concepteur »•modifier les unités de 2 unités à 1 unité•noter la modification obtenue
Effectuer l’affectation suivante :• type tâche « durée fixe »-2 unités « Concepteur »•modifier les unités de 2 unités à 1 unité•noter la modification obtenue
Effectuer l’affectation suivante :• type tâche « travail fixe »-2 unités « Concepteur »•modifier les unités de 2 unités à 1 unité•noter la modification obtenue
Pratique (3)
![Page 56: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/56.jpg)
2011 - 2012 D. VALLETON - CMA - 07 56
MS Project – Affectation ressources
Effectuer l’affectation suivante :• type tâche « capacité fixe »-2 unités « Concepteur »•modifier le travail de 28h à 14h•noter la modification obtenue
Effectuer l’affectation suivante :• type tâche « durée fixe »-2 unités « Concepteur »•modifier le travail de 28h à 14h•noter la modification obtenue
Effectuer l’affectation suivante :• type tâche « travail fixe »-2 unités « Concepteur »•modifier le travail de 28h à 14h•noter la modification obtenue
Pratique (4)
![Page 57: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/57.jpg)
2011 - 2012 D. VALLETON - CMA - 07 57
MS Project – Affectation ressources
Reconstituer le tableau :Pratique (5)
Travail fixe
Capacité fixe
Durée fixe
TravailUnitésDurée
Modification effectuée sur
Type de tâche
![Page 58: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/58.jpg)
2011 - 2012 D. VALLETON - CMA - 07 58
MS Project – Affectation ressources
Impact du type de tâche : capacité fixe
Modification de la durée : 2 jours 1 jour
Le travail est modifié : 28 heures 14 heures
![Page 59: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/59.jpg)
2011 - 2012 D. VALLETON - CMA - 07 59
MS Project – Affectation ressources
Impact du type de tâche : durée fixe
Modification de la durée : 2 jours 1 jour
Le travail est modifié : 28 heures 14 heures
![Page 60: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/60.jpg)
2011 - 2012 D. VALLETON - CMA - 07 60
MS Project – Affectation ressources
Impact du type de tâche : travail fixe
Modification de la durée : 2 jours 1 jour
Le nombre d’unités affectées : 2 unités 4 unités
![Page 61: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/61.jpg)
2011 - 2012 D. VALLETON - CMA - 07 61
MS Project – Affectation ressources
Impact du type de tâche : capacité fixe
Modification du nombre d’unités : 2 unités 1 unité
La durée est modifiée : 2 jours 4 jours
![Page 62: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/62.jpg)
2011 - 2012 D. VALLETON - CMA - 07 62
MS Project – Affectation ressources
Impact du type de tâche : durée fixe
Modification du nombre d’unités : 2 unités 1 unité
Le travail est modifié : 28 heures 14 heures
![Page 63: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/63.jpg)
2011 - 2012 D. VALLETON - CMA - 07 63
MS Project – Affectation ressources
Impact du type de tâche : travail fixe
Modification du nombre d’unités : 2 unités 1 unité
La durée est modifiée : 2 jours 4 jours
![Page 64: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/64.jpg)
2011 - 2012 D. VALLETON - CMA - 07 64
MS Project – Affectation ressources
Impact du type de tâche : capacité fixe
Modification du travail : 28 heures 14 heures
La durée est modifiée : 2 jours 1 jour
![Page 65: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/65.jpg)
2011 - 2012 D. VALLETON - CMA - 07 65
MS Project – Affectation ressources
Impact du type de tâche : durée fixe
Modification du travail : 28 heures 14 heures
Le nombre d’unités est modifié : 2 unités 1 unité
![Page 66: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/66.jpg)
2011 - 2012 D. VALLETON - CMA - 07 66
MS Project – Affectation ressources
Impact du type de tâche : travail fixe
Modification du travail : 28 heures 14 heures
La durée est modifiée : 2 jours 1 jour
![Page 67: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/67.jpg)
2011 - 2012 D. VALLETON - CMA - 07 67
MS Project – Affectation ressourcesImpact du type de tâche : Synthèse
Durée Durée Travail Capacité fixe
Durée Durée Unités Travail fixe
Unités Travail Travail Durée fixe
Travail Unités Durée
Modification effectuée surType de tâche
![Page 68: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/68.jpg)
2011 - 2012 D. VALLETON - CMA - 07 68
MS Project – Affectation ressourcesImpact du type de tâche : Synthèse
Durée Durée Unités Travail fixe
Durée Durée Travail Capacité fixe
Unités Travail Travail Durée fixe
Travail Unités Durée
Modification effectuée surType de tâche
![Page 69: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/69.jpg)
2011 - 2012 D. VALLETON - CMA - 07 69
MS Project – Affectation ressourcesImpact du type de tâche : Synthèse
si D Usi U D
si T Dsi D T
si T Usi U T
si T D
si C D
si D T
=DxU
=T/D
=T/U
Travail fixe
Capacité fixe
Durée fixe
![Page 70: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/70.jpg)
2011 - 2012 D. VALLETON - CMA - 07 70
MS Project – Affectation ressources
Impact de « tâche pilotée par l’effort » OUI
Ajout de la ressource « Assistant »
La durée est raccourcie : 28 h / 3 unités 9,33 h 1,33 j
« Capacité fixe »
![Page 71: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/71.jpg)
2011 - 2012 D. VALLETON - CMA - 07 71
MS Project – Affectation ressources
Impact de « tâche pilotée par l’effort » NON
La durée est restée fixe : 2 joursLe travail est passé à : 2 jours x 7 heures x 3 unités 42 h
« Capacité fixe »
Ajout de la ressource « Assistant »
![Page 72: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/72.jpg)
2011 - 2012 D. VALLETON - CMA - 07 72
MS Project – Affectation ressources
Impact de « tâche pilotée par l’effort » OUI
La durée est restée fixe : 2 joursLe travail est resté à : 28h – Les unités sont 1,33 et 0,67
Ajout de la ressource « Assistant »
« Durée fixe »
![Page 73: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/73.jpg)
2011 - 2012 D. VALLETON - CMA - 07 73
MS Project – Affectation ressources
Impact de « tâche pilotée par l’effort » NON
La durée est restée fixe : 2 joursLe travail est passé à : 2 jours x 7 heures x 3 unités 42 h
« Durée fixe »
Ajout de la ressource « Assistant »
![Page 74: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/74.jpg)
2011 - 2012 D. VALLETON - CMA - 07 74
MS Project – Affectation ressources
Graphiques associés à l’affectation des ressources
1
1 – Sélection 1 ou plusieurs ressources
2 – Clic sur « Graphiques »
2
![Page 75: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/75.jpg)
2011 - 2012 D. VALLETON - CMA - 07 75
MS Project – Affectation ressources
Graphiques associés à l’affectation des ressources
Graphe « Travail »Ressources sélectionnées
![Page 76: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/76.jpg)
2011 - 2012 D. VALLETON - CMA - 07 76
MS Project – Affectation ressources
Graphiques associés à l’affectation des ressources
Graphe « Affectation »2 ressources sélectionnées1 seule tâche présente
![Page 77: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/77.jpg)
2011 - 2012 D. VALLETON - CMA - 07 77
MS Project – Affectation ressources
Graphiques associés à l’affectation des ressources
Graphe « Affectation »2 ressources sélectionnées2 tâches sélectionnées
![Page 78: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/78.jpg)
2011 - 2012 D. VALLETON - CMA - 07 78
MS Project – Affectation ressources
Graphiques associés à l’affectation des ressources
Graphe « Affectation »2 ressources sélectionnées1 tâche sélectionnée
![Page 79: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/79.jpg)
2011 - 2012 D. VALLETON - CMA - 07 79
MS Project – Affectation ressources
Graphiques associés à l’affectation des ressources
Graphe « Disponibilité »2 ressources sélectionnées (1 assistant)
![Page 80: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/80.jpg)
2011 - 2012 D. VALLETON - CMA - 07 80
MS Project – Affectation ressources
Graphiques associés à l’affectation des ressources
0,5 unité assistantGraphe « Disponibilité »2 ressources sélectionnées (1/2 assistant)
![Page 81: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/81.jpg)
2011 - 2012 D. VALLETON - CMA - 07 81
MS Project – Affectation ressources
Influence de « Tâche pilotée par l’effort » sur la tâche « Prototype »:
•Type de tâche : « Capacité fixe » + « Pilotée par l’effort »•Affecter 1 unité de ressource « Assistant »•Relever la modification survenue (Durée)• Type de tâche : « Capacité fixe » + « Pilotée par l’effort »•Affecter 1 unité de ressource « Assistant »•Relever la modification survenue (Travail)
Examiner les graphiques associés aux affectations Remplacer 1 « Assistant par 0,5 assistant Examiner les graphiques associés aux affectations
Pratique (7)
![Page 82: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/82.jpg)
2011 - 2012 D. VALLETON - CMA - 07 82
MS Project – Affectation ressourcesPratique
Dans le projet « Construction_usine_06 », affecter aux tâches les ressources :• « Terrassement » - 5 « Maçons » – (M1)• « Finition » - 1 « Maçon », 1 « Menuisier » - 1
« Peintre » - (M2)• « Instal. machines » - (M3a)
2 « Electriciens » 1 « Tuyauteur » 1 « Peintre » à mi-temps le « Chef de chantier » à quart-temps
• « Finition » - ajouter 1 « Electricien » - (M3b) Pour chaque tâche, vérifier le « travail Pour chaque ressource, afficher le graphe
M1 – Affecter les ressources M2 – Informations sur la tâcheM3a – Entrée des tâchesM3b – Formulaire tâche
![Page 83: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/83.jpg)
2011 - 2012 D. VALLETON - CMA - 07 83
MS Project – Cours N° 7
1 Entités de base• affichages• tables• filtres• groupes
2 – Planification des ressources• Définitions• Types de tâche• « Pilotée ou non par l’effort »• Affectation de ressources
![Page 84: Project 2007 presentation-07 - dvalleton.free.frdvalleton.free.fr/CMA_MS-Project/pres-07/Project_2007_presentation... · Utilisation de MS Project 2007. 2011 - 2012 D. VALLETON -CMA-07](https://reader033.fdocuments.net/reader033/viewer/2022052516/5b99003809d3f22f0a8cfbcd/html5/thumbnails/84.jpg)
2011 - 2012 D. VALLETON - CMA - 07 84
MS Project – Cours N° 7
FIN DU COURS N° 7