Progress to Date
• In 2006 the University completed its first Carbon
Management Plan
• In January 2011 the University published its second
Carbon Management Plan
• The University commits to reducing direct electricity,
gas & fuel consumption by 48%* by 2020.
* Against a 2005/06 baseline
That’s some big reductions!
Source: Hefce 2010
From here......
....to here!
Progress to Date
• The University has achieved a 20%↓ in its
direct electricity, gas & fuel consumption
already!
• Carbon is now one of the University's key
working themes & will be reviewed annually.
Source: Carbon Trust Alumni Conference 2010
The Carbon Trust believes the University of Sunderland is making
the greatest progress to date of the 120 universities it is engaged
with.
Examples of Some Projects We Have Undertaken
• Energy audits
• Voltage optimisation (8% reduction)
• Boiler replacement
• Ground source heat pump
• Space utilisation
• Reduction in fleet vehicles/improved fuel efficiency
• Reduction in waste to landfill
How Are We Communicating This?
Here are some examples of how we are
telling you what we are doing.
Where Can I Find Out More?