Progress on the RAL Linac Design
description
Transcript of Progress on the RAL Linac Design
Progress on the RAL Linac Design
- HIPPI Yearly Meeting –- CERN, Geneva -
29.10.2008
- C. Plostinar -
Presentation outline
• Upgrades for ISIS
• FETS Overview
– End to end beam dynamics simulations in FETS
• The new RAL linac
• Conclusions
400 MeV LinacCollimating Achromat
(Linac upgrade to 800 MeV)
An upgrade option for ISIS
TS-3
3 GeV 50 Hz Ring
Proposed upgrade (staged approach):
- Isis Now: 800 MeV, Beam Power: 0.16–0.24 MW
- Adding a ~3 GeV RCS -> ~1MW
- Adding a 400 MeV linac will increase the beam power up to 2 MW
- Increasing the linac energy to 800 MeV provides upgrade options to 5 MW
TS-1
TS-2
Linac Layout
Front End
DTL (Drift Tube Linac) SCL (Side Coupled Linac)
324 MHz 972 MHz
3 MeV
180 MeV
90 MeV
180 MeV Linac Layout (old)
800 MeV Linac Layout (new)
Front End DTL CCL ScL 1 ScL 2
3 MeV 75 MeV 193 MeV 409 MeV 800 MeV
324 MHz 648 MHz
H- Ion source
LEBT MEBT RFQ
The Front End Test Stand (FETS)
Front End Overview
Magnetic LEBT
RFQ
MEBT and chopper
H− ion source
Laser profile monitor
Front End Overview
- The beamline support stands and rail system are installed in preparation for ion source and LEBT installation.- View of the HV cage showing the platform and installed equipment - Ion Source vessel in situ
FETS End to End Beam Dynamics Simulations
LEBT MEBT RFQIon
Source
The measured emittance (already improved by a factor of two in the last year) is more than a factor of two larger than the waterbag particle distribution used for the optimization of the individual elements.
Waterbag (Ex=Ey=0.25 Pi.mm.mrad (RMS))
Measured (Ex=0.58, Ey=0.52)
FETS End to End Beam Dynamics Simulations
LEBT MEBT RFQIon
Source
The slight s-shaped aberrations show the influence of non linear magnetic fields on the beam transport but the emittance growth is reasonable.
WaterbagEx=Ey=0.33
MeasuredEx=0.69, Ey=0.64
FETS End to End Beam Dynamics Simulations
LEBT MEBT RFQIon
Source
The large input emittance for the real beam causes large (transversal) particle loss in the RFQ which causes an overall reduction of the emittance.
WaterbagEx=0.28, Ey=0.27
MeasuredEx=0.46, Ey=0.47
FETS End to End Beam Dynamics Simulations
LEBT MEBT RFQIon
Source
Particle losses in the MEBT can be neglected for the ideal case and is < 10% for the real beam distribution.
WaterbagEx=0.30, Ey=0.34
MeasuredEx=0.40, Ey=0.49
FETS End to End Beam Dynamics Simulations
P1 P2 P3 P488%
90%
92%
94%
96%
98%
100%
FETS Transmission (Waterbag Dist.)
Tran
smis
sion
P1 P2 P3 P430%40%50%60%70%80%90%
100%
FETS Transmission (Measured Dist.)
Tran
smis
sion
- Transmission more than 90% for the waterbag distribution (100% - LEBT, 95% - RFQ, 98% - MEBT)
- Much higher losses when using the measured distribution – 46% transmission (100% - LEBT, 52% - RFQ, 89% - MEBT)
FETS End to End Beam Dynamics Simulations
P1 P2 P3 P400.050.1
0.150.2
0.250.3
0.350.4
FETS Emittance Evolution (Waterbag Dist.)
Emit
tanc
e
P1 P2 P3 P400.10.20.30.40.50.60.70.8
FETS Emittance Evolution (Measured Dist.)
Emit
tanc
e- Moderate emittance growth when using the ideal distribution- Emittance reduction when using the real distribution due to high beam
loss- Efforts to reduce the ion source emittance and increase the RFQ
acceptance are under way.
The H- Linac Design
MEBT DTL CCL ScL 1 ScL 2
3 MeV
75 MeV
193 MeV
409 MeV
800 MeV
324 MHz 648 MHz
RFQLEBTIon Source
Key Linac Parameters:- Ion Species: H-- Energy: 3 – 800 MeV- Beam pulse current before MEBT chopping: 43mA- Beam pulse current after MEBT chopping: 30 mA- Beam power 0.5 MW- Repetition Rate: 50 Hz- Sections:
- RFQ- Drift Tube Linac (4 tanks)- Coupled-Cavity Linac (56, 10 cell cavities)- Superconducting Linac (69, 5/6 cell cavities)
~11 m ~280 m
The DTL Section• Input energy: 3 MeV• Output energy: 75 MeV• Operating frequency: 324 MHz
Energy (MeV)
No of cells
Sync. Phase (deg)
Power
Tank 1 3 – 19.6 62 -42 -> -35 1.695
Tank 2 19.6 – 38 39 - 34.5 -> -32
1.699
Tank 3 38 – 56 35 -35 -> - 32.5
1.637
Tank 4 56 – 75 31 -33 -> -30 1.664
• Toshiba Klystrons (2.5 MW)• Compact PMQs (or hybrid
quadrupoles?)• No of tanks: 4 (1 Klystron /Tank)• E field 2.5 MV/m• Maximum E field level: 1.5 Kilpatrick
The H- Linac Design
DTL Simulations for the RAL linac
Beam envelopes in DTL, CCL, ScL1 & ScL2
Phase space plots at CCL output
Phase space plots at ScL2 output
Normalised emittance evolution (RMS)
MEBT MEBT DTL1 DTL2 DTL3 DTL4 CCL ScL1 ScL2Input Output Output Output Output Output Output Output Output
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
Emittance Evolution along the Linac
Nor
mal
ized
RM
S Em
itta
nce
Klystron requirements
Stage Number Freq (MHz) Peak Power
RFQ and DTLs 5 324 2.5CCL (56 cavities)
5 648 5.0
ScL1 (36 cavities)
9 648 1.6
ScL2 (34 cavities)
9/17 648 5.0/1.6
Also needed: amplifiers for four 324 MHz MEBT bunchers, and one 648 MHz buncher between DTL4 and CCL
Studies now required:
1. MEBT optics re-evaluation.
2. Alternatives to DTL & CCL + Shunt Impedance Studies.
3. CCL & ScL 648 & 972 MHz comparisons.
4. Refine designs of various linac stages (matching, etc.).
5. Error effect evaluation for the full linac.
6. Effect of failed superconducting cavities.
7. Design of phase ramping, ring beam line.
Conclusions
• A new ISIS upgrade plan has been identified and it includes a possible 800 MeV linac
• Work on the new linac has started
• Work on the FETS project is progressing well