    Progress made Project Team for Development of SEE CAO

    Aleksandar Mijuskovic, PrenosChairman Project Team Steering Committee

    15thAthens Forum, November 25th-26th, 2009

  • 8/10/2019 Progress Made - Project Team for Development of SEE CAO

    2/12

    2

    Content

    I PT SC SEE CAO Meetings

    II Main developments

    III Conclusions

  • 8/10/2019 Progress Made - Project Team for Development of SEE CAO

    3/12

    3

    PT SC SEE CAO Meetings

    1st PT SC CAO Meeting, Athens, May. 11th 2009

    2nd PT SC CAO Meeting, Athens, June. 9th 2009

    3rd PT SC CAO Meeting, Vienna, Sep. 17th - 18th 2009

    4th PT SC CAO Meeting, Brussels, Oct. 28th 2009

  • 8/10/2019 Progress Made - Project Team for Development of SEE CAO

    4/12

    4

    Main developments

    Polit ical Support

    Financing of the Project Team

    Structure of the Project Team

    Setting up Project Company ToR

  • 8/10/2019 Progress Made - Project Team for Development of SEE CAO

    5/12

    5

    Main developments - Polit ical Support

    Conclusions of the Ministerial Council

    Conclusions of the Athens Forum

    Memorandum of Understanding

    Letter of EU Commissioner Piebalgs

  • 8/10/2019 Progress Made - Project Team for Development of SEE CAO

    6/12

    6

    Main developments - Financing of the PT

    70% of the overall project costs will be covered by

    International Financial Institutions IFIs

    30% of the project budget shall be financed by TSOs

    based on equal contributions

  • 8/10/2019 Progress Made - Project Team for Development of SEE CAO

    7/12

    7

    Main developments The structure of the PT

    The Project Company shall be set up for the duration

    of one year There shall be 4 experts (one Legal Expert, one

    Economic Expert, 2 Grid Experts) and a Project Team

    Manager leading the team and reporting to theSteering Committee.

    PT members shall be seconded by TSOs/ISOs from

    the 8th region

    Nomination for Project Team Members Letter

  • 8/10/2019 Progress Made - Project Team for Development of SEE CAO

    8/12

    8

    Main developments Project Company

    The originally planned approach of PRENOS acting as

    beneficiary for the Project Team funds (budget) cannot be followed (difficulties with splitting income in

    the balance sheet/regulated asset base)

    Alternatively a Project Company ( LIMITED LIABILITYCOMPANY ) shall be set up

    PRENOS offered to prepare the setting up

    Legal framework for establishment of ProjectCompany

  • 8/10/2019 Progress Made - Project Team for Development of SEE CAO

    9/12

    9

    Main developments ToR

    On 28 October 2009 the SEE CAO Project Team

    Steering Committee agreed on the final version of theToR for the PT SEE CAO

    After the agreement to go Rules of Association willhave to be finished

  • 8/10/2019 Progress Made - Project Team for Development of SEE CAO

    10/12

    10

    Conclusions

    Setting up a SEE CAO is following the legal

    requirements of the Energy Community Treaty in themost efficient way

    SPECIAL BENEFITS FOR SEE:

    high number of borders and different allocation

    mechanisms aim: implementing procedures that are

    in line with the EU

    integration of markets - one single market is

    considered as the ultimate goal

  • 8/10/2019 Progress Made - Project Team for Development of SEE CAO

    11/12

    11

    Conclusions

    Establishment of a SEE CAO depends on the number

    of the participating TSOs/ISOs and the transmissioncapacities offered at their borders

    Participation of all TSOs would make the project more

    efficient

    The SEE CAO remains open to all TSOs in the Region

    Start with an NTC approach in the first phase andmove to flow based allocations in a second step

  • 8/10/2019 Progress Made - Project Team for Development of SEE CAO

    12/12

    12

    Conclusions

    Message:

    all the conditions were met and that PT can start work

    Governments and ministries play a key role

    Clear political signal on the way forward from theupcoming Ministerial Council (18 Dec 2009)