Prof Eivind GROV

download Prof Eivind GROV

of 13

Transcript of Prof Eivind GROV

  • 1SINTEF Building and Infrastructure 1

    General Review on Geotechnical Aspeects

    of Cavern Engineering

    Presented by Professor/Chief scientist Eivind Grv

    NTNU/SINTEF

    The importance of understanding and utilizing in-

    situ rock stress

    SINTEF Building and Infrastructure 2

    Introduction

    Annual tunnelling production in Norway since 1973, statistics

    prepared by the Norwegain Tunnelling Society

  • 2SINTEF Building and Infrastructure 3

    Introduction

    The Scandinavian host rock: igneous & metamorphic, poor to

    extremely good rock.

    Folding, faulting and high tectonic stresses influence the

    quality of the rock

    Weakness zones can exhibit great variation in quality:

    extremely poor to good

    The width of zones may be a few centimeters to tens of meters

    Hard rock not necessarily good rock

    Frequently changing rock mass conditions to be negotiated

    The same conditions can be

    found a lot of places and is

    certainly not limited to Norway or

    Scandinavia

    It is maybe more a matter of

    philosophy and courage to utilize

    the rock mass properties

    SINTEF Building and Infrastructure 4

    Large rock caverns: in Norway mainly used for: Hydro electric power stations number of 200++

    Oil and gas storage, appr. 50 caverns

    Combined sports halls and civil defense facilities

    Sewage treatment plants, potable water storage

    Railway stations

    Underground parking, ice cream storage, waste repository

    By the Way: What is a large underground rock cavern?

    No clear definition found, assume something larger than a normal road and railroad tunnel, eg. greater than 12m width

    But TBM's today are up to 18m diameter! Caverns?

    What about height? Height can be an unfavourable parameter too which may need to be considered

    Introduction

  • 3SINTEF Building and Infrastructure 5

    Development of large underground caverns

    The hydropower development: started in the 1950es in Norway

    Lack of steel then the penstock was deleted

    Underground caverns became compatible in price and the technology

    level evolved

    Unlined head race tunnels forced its way into the design, with a maximum

    water pressure to appr. 1100m

    Cavern design: width 12 to 25m, straigth walls, up to 35m height,

    unlined, complicated geometry

    SINTEF Building and Infrastructure 6

    Development of large underground caverns Flexible design and

    construction approach!

    Layout is pre-designed on the baseline geology knowledge

    But subject to modifications based on encountered conditions:

    Rock type and mechanical properties (mapping and testing)

    Characteristics of discontinuities (continuous mapping in tunnels)

    In-situ rock stress (measured at various locations during constr.)

    Groundwater conditions (monitored under ground)

  • 4SINTEF Building and Infrastructure 7

    Development of large underground caverns

    Flexible design and construction approach!

    Layout is subject to modifications based on

    encountered conditions

    Here: stress measurements in a number of locations to fix;

    The location and layout of power house caverns

    Air cushion chamber

    Length of steel lined penstock

    SINTEF Building and Infrastructure 8

    Development of large underground caverns

    The mining industry: learned us numerous cases with large

    span:

    Were 60-80 meters wide

    Were Stable

    With no rock support at all

    WHY? The rock mass has certain

    excellent properties:

    Its stress induced confinement

    Its selfstanding capacity

    Its impermeable nature

    Its thermal capacity

    Stable mining rooms

    Length 70m, width 30m andheight 400 m

    Feasible by:

    understanding rock mechanics performing stress measurement numerical and analyticalmodeling

    Stjerny

    underground mine

  • 5SINTEF Building and Infrastructure 9

    Measuring in-situ stress

    A diamond drill hole (76 mm outer diameter) is drilled to the desired

    depth. Usually, this depth is 1,5 times the span of tunnel/ cavern.

    The hole bottom is flattened with a special drill bit, and a concentric

    hole with smaller diameter (36 mm o.d) is drilled approximately 30

    cm further.

    A measuring cell with strain gauges and data log unit is installed

    with a special installing tool containing orienting device.

    Compressed air is used to expand the cell in the hole, and the strain

    gauges are fixed to the walls in the hole.

    The cell is now ready to start measuring, and continously logging of

    strain data is stored in the measuring cell. The installing tool is

    removed and the cell is ready for overcoring.

    The small hole is over cored by the larger diameter bit, thus stress

    relieving the core. The corresponding strains are recorded by the

    strain gauge rosettes. The core is recovered from the hole with a

    special core catcher, and immediately after removal from for the

    hole the recorded data is transferred to the computer. When the

    elastic parameters are determined from biaxial- and laboratory test,

    the stresses may be calculated.

    SINTEF Building and Infrastructure 10

    Arch effect in roof

    Pillar capacity

    Water curtain

    pressure

    Optimized geometry!

    Area for 3D

    Pilar stress

    horizontallyPilar stress vertically

    Measuring in-situ stress

    In a virgin rock body

  • 6SINTEF Building and Infrastructure 11

    Measuring in-situ stress

    Increase the pressure at a speed of 0,1-0,5 MPa/sek

    At critical pressure a crack is initiated and water flows into the rock mass

    Water supply is cut off

    Re-pressurize

    SINTEF Building and Infrastructure 12

    Measuring in-situ stress

    Measuring hydraulic

    fracturing and

    jacking existing

    cracks

    Shut-in pressure sets

    equal to 3

  • 7SINTEF Building and Infrastructure 13

    Tunnel Engineering Handbook

    By Bickel & Kuesel:

    Knowledge of the in-situ

    stresses is essential to the

    sound, logical design of

    rock reinforcement systems,

    excavation procedures and

    opening layouts, and to the

    interpretation of expected

    rock strength and

    deformational properties.

    How did this happen??

    Lack of knowledge of the in-situ

    stress?!

    SINTEF Building and Infrastructure 14

    Development of large underground caverns

    Some guidelines on design: Geotechnical mapping focusing joints

    and weak zones, geomechanical tests

    In-situ stress measurements are required (often from surface/adjacent UG opening)

    Work in the 3-D picture, pillars are subject to high stresses, corners & bends are released

    Locate and align the cavern

    Empirical and analytical design

    Numerical modeling and analytical models to verify layout

    Observation/monitoring in excavation

  • 8SINTEF Building and Infrastructure 15

    A particular functional requirement of certain

    facilities!

    To reduce the length of access tunnels

    Lead to:

    Shallow locations, such as

    Holmlia: width 25m, rock cover is only 15m

    Gjvik: width 61m, rock cover between 25 and 50m

    Confinement, OR in-situ rock stress

    How??

    Knowledge of the in-situ

    stress situation is crucial

    SINTEF Building and Infrastructure 16

    Construction of large underground caverns

    Normally excavation is split into various sections:

    Top heading

    Benching

    Each level must be mapped and sup--ported prior to going to lower level

    Benching can be by vertical blast holes

    Logistic is a challenge and do not believe that work is going on as smooth as on the figure

    Knowing the stress conditions may allow a different sequence leaving a horisontal pilar to be done lastly

    Observe the water

    curtain holes above the

    caverns, typical oil and

    gas caverns to work in

    saturated rock mass

  • 9SINTEF Building and Infrastructure

    Construction of large underground caverns

    Stability of caverns:

    Visual inspections of exposed rock, shotcrete and bolts

    Measuring bolts

    Extensometers (rod & tape), convergence pins

    The Gjvik hall

    was a complicated excavation

    procedure with pilots and a

    number of side stopping,

    slashing, headings and

    benches

    SINTEF Building and Infrastructure 18

    Construction of large underground caverns

    Unlined Tunnelling! Permanent rock support

    consists of rock bolts and

    shotcrete

    Primary support is approved as permanent on the condition that

    it meets the material standard

    Active design of support to fit the encountered geological

    conditions

    Water control by groutingHydrocarbon storage at

    Sture

  • 10

    SINTEF Building and Infrastructure 19

    A cargo terminal in rock cavern?

    A cargo terminal; is being planned in

    Trondheim covering a huge surface area replacing the existing one.

    Is there any other option?

    We were looking at the possibility of locating the shunting area underground.

    In large underground caverns! Of course.

    SINTEF Building and Infrastructure 20

    A cargo terminal in rock cavern?

    Underground solutions: One single cavern with a width of 42m

    and length of 700m

    Two parallel caverns, each 28m wide and with a pillar of 25m width

    EXIT

    ENTRANCE

    2 CAVERNS

    SOLUTOION FOR

    SHUNTING AREA

    1 TUNNEL TRACK THROUGH THE SYSTEM 2500 M

  • 11

    SINTEF Building and Infrastructure 21

    A cargo terminal in rock cavern?

    Design input: Rock cover 125m

    K-value of 1

    Vertical and horizontal stress components 3,5 to 4 MPa

    One major joint set

    Rock bolts in a 2x2m pattern, 5m long, no other support

    modelled

    Notice the model ran with 42m width in 2 caverns and

    25m pilar

    An existing railway tunnel

    through the area provided

    excellent possibilities for data

    acquisition

    SINTEF Building and Infrastructure 22

    A cargo terminal in rock cavern?

    Results from the numerical analysis:

    No particular indications of over-stressing in the pillar, its stable

    Positive redistribution of the stresses above the cavern

    roof establishing a stabilizing

    arch

    Some minor tensional areas in the roof

  • 12

    SINTEF Building and Infrastructure 23

    The worlds largest public rock cavernWhat made the Gjvik hall

    feasible?? Results from earlier projects

    indicate presence of sufficient high horizontal stress

    In situ stress measurements were done; h=3-5MPa at a depth of 25-50m which is far more than the theoretical gravity approach (

  • 13

    SINTEF Building and Infrastructure 25

    Some pros and cons of in-situ stressType of facility 1 3 K = hor/vert

    Rock caverns Moderate to high level can

    enable an optimised geometry,

    too high may lead to stability

    problems

    Low level may produce a too

    small arch building in the

    roof/lack of confinement thus

    instability.

    K= 1-2 is OK.

    K> 3 is not OK.

    K< 0,5 is not OK.

    Pressurised

    tunnels/caverns

    Minor influence, high level may

    give stability problems.

    Minor principal stress

    component must be higher

    than the water pressure (or

    the pressure from any other

    confined material) as an

    ultimate requirement.

    No particular

    requirement.

    Facilities with

    particular

    requirements to

    tightness

    Moderate to high level can

    provide good confinement and

    stability and improved

    tightness.

    Critical low level gives

    poor safety against leakage.

    Grout design press. < 3Storage pressure < 3

    No particular

    requirement.

    Transport-tunnels Moderate to high level is good

    for the confinement and

    stability. Too high stresses may

    give stability-problems,

    spalling.

    No particular requirements,

    but low stress might lead to

    lack of confinement and

    instability.

    K appr. 1 is OK.

    SINTEF Building and Infrastructure 26

    Conclusions

    Large underground caverns have been used in Norway

    for several purposes

    Majority have typical dimensions 15-25m width

    Unlined caverns, supported by rock bolts and sprayed

    concrete

    In-situ stresses are utilized to obtain confinement

    Field testing is needed

    Underground, presence of

    in-situ rock stresses would

    normally be an asset