    LONG-HOLE

    MODULE : SUPPORT, DRILLING, BLASTING

    FLOOR

    HoursCLEANING DRILLING INSTALLATION DRILLING REDRILLING BLAST

    1

    2

    3Preparation

    ( 1 hr)

    (section 2.0)

    Preparation

    ( 0.3 hr/shift)

    (section 4.3)

    4

    5

    6

    7

    82 blas

    drop ra

    (section

    18.8 meters/ms 76 m/ms 94.6 meters/ms 31.6 t/

    MOBILIZATION AND CABLES DROP RAISES

    0.13 hr/hole of

    5 meters

    with 2 men(section 4.4)

    3.1 m

    advanc

    /shift w

    2 me

    (section

    Fixed t( 2.48 hr/

    (section

    8 m advanced

    /hour

    with 2 men

    (section 4.1)

    14.9 m/hour

    (section 4.4)

    Productivity 9 manshifts/sub 43 meters/manshift

    DEMOBILIZATION

    3.83 hours/sub-level

    with 2 men

    (section 3.0)

    Fixed time

    ( 2.17 hr/sub-level)

    (section 2.0)

    Preparation

    ( 0.3 hr/shift)

    (section 4.3)

    Fixed activities per shift

    2.13 hours/shift

    (section 1.0)

    8.9 m/hour

    (section 4.3)

    File: 159332107.xls.ms_officeSheet: CompilationPage 1 of 16

    Experimental MineVal-d'Or

  • 7/28/2019 Productivity Long-Hole

    2/16

    UNIT COST DISTRIBUTION PER ACTIVITY

    MODULE: SUPPORT, DRILLING, BLASTING

    FLOOR

    CLEANING DRILLING INSTALLATION DRILLING REDRILLING

    1 - LabourSalary ($/hour) 20.00$ hours hours hours hours hours hoursBonus ($/hour) 8.19$ 237.4 75.9 719.5 612.6 107.1 10.6Fringe benefits 50% $/tonne $/tonne $/tonne $/tonne $/tonne

    Total ($/hour) 42.29$ 0.35$ 1.06$ 0.90$ 0.16$ 0.02$

    Hours/shift 8

    2 - MaterialDrilling (Long-Hole)

    including rods, steel bits, hoses, lubricants and grease

    Explosives and accessories

    Supportmechanical rockboltsrebars and resinSplit-Set

    Swellexscreencables, ciment and drillingshotcrete

    total support :

    Timber

    Track

    Pipes

    Ventilation

    Other supplies

    3 - Equipment maintenancemechanicalelectricaldiesel and lubricants

    Total/tonne 0.35$ 1.06$ 0.90$ 0.16$ 0.02$

    4.45$ $/drilled m (cables) 6.29$ $/drilled m (drop ra

    Labour only

    0.11$

    $/tonne

    0.11$

    DEMOBILIZATION

    MOBILIZATION & CABLES DROP RAIS

    File: 159332107.xls.ms_officeSheet: CostsPage 2 of 16

    Experimental MineVal-d'Or

  • 7/28/2019 Productivity Long-Hole

    3/16

    LONG-HOLE

    STOPE PRODUCTIVITY CALCULATION

    1.0 - DIRECT FIXED ACTIVITIES PER SHIFT (outside the stope)

    Cage (at beginning and end of shift) 2 8 16

    Travelling (shaft - refuge station - shaft) 2 5 10 Three-meterOther travelling delays 0 Two workingBack and forth to stope 4 8 32 Ramp accesSupervision 1 15 15 Three sub-leWork planning 1 10 10

    Complete daily reports 1 15 15

    Lunch 1 30 300

    128 minutes

    2.13 hours/shift

    2.0 - DIRECT FIXED ACTIVITIES PER STEP (inside the stope)

    RELATED TO FLOOR

    CLEANING RELATED TO BLASTIBring and prepare material 1 30 30 Bring and prepare mate

    Store material 1 30 30 Clean the floor followin

    0 Store equipment and e

    0 Check blasting lineminutes/sub-level 60 Connect the blast

    hours/sub-level 1.00 Close access to the stoAccess verification fol lo

    RELATED TO ANCHOR CABLE Extra scalingINSTALLATION Repair and install venti

    Bring and prepare material 1 60 60

    Clean pump and accessories 1 40 40

    Store material 1 30 30

    0

    0

    minutes/sub-level 130

    hours/sub-level 2.17

    Frequency orUnits

    Time(min)/Unit

    Total Time(min)

    Total Time(min)

    Time(min)/Unit

    Frequency orUnits

    Frequency orUnits

    Time(min)/Unit

    Total Time(min)

    File: 159332107.xls.ms_office

    Sheet: Long-HolePage 3 of 16

    Experimental MineVal-d'Or

  • 7/28/2019 Productivity Long-Hole

    4/16

    LONG-HOLE

    STOPE PRODUCTIVITY CALCULATION

    3.0 - DIRECT FIXED ACTIVITIES PER STOPE

    RELATED TO MOBILIZATION OTHER ACTIVITIES

    AND DEMOBILIZATION PER STOPEPrepare the slide and working areas 3 80 240

    Bring and lower drill in the sub-level 3 60 180Assemble the drill 3 20 60

    Install electric services 3 60 180

    Dismantle and bring out drill from sub-level 3 60 180Remove electric services 3 180 540

    0

    0

    01380 minutes

    Required number of men 2 23.00 hours

    4.0 - DIRECT VARIABLE ACTIVITIES PER STEP (inside the stope)

    4.1 - Floor cleaning

    Cleaning time

    Sub-levels (hours) 8

    1 11.632 11.633 11.634 11.63

    5 11.636 11.63

    69.75 hours

    Surveyors

    Geologists

    Productivity (linear meters/hour)

    Frequency orUnits

    Time(min)/Unit

    Total Time(min)

    Repairs in main access

    Mechanics and electricians

    3rd drilling level or UPPER LEVEL

    2nd drilling sub-level

    1st drilling sub-level

    Drop raises

    Typical Long-Hole Stope

    LOWER LEVEL

    File: 159332107.xls.ms_office

    Sheet: Long-HolePage 4 of 16

    Experimental MineVal-d'Or

  • 7/28/2019 Productivity Long-Hole

    5/16

    LONG-HOLE

    STOPE PRODUCTIVITY CALCULATION

    4.2 - Stope parameters

    4.2.1 - Drop raise parameters

    Production Reaming

    Drilling sub-levels Actual length Width Height # of drop raises 54 102

    1 6 2.4 3.0 1 16

    2 6 2.4 3.0 1 163 6 2.4 3.0 1 16

    4 6 2.4 3.0 1 16

    5 6 2.4 3.0 1 16

    6 6 2.4 3.0 1 16

    6

    4.2.2 - Drilling and blasting parameters of production rows

    Length of Spacing between Number Average area Number of tonnes Number of drille

    Drilling sub-levels sub-levels rows of rows /row (m ) /row meters/row

    1 93 1.2 76 18 62 1

    2 93 1.2 76 18 62 1

    3 93 1.2 76 18 62 1

    4 93 1.2 76 18 62 15 93 1.2 76 18 62 1

    6 93 1.2 76 18 62 1369

    Total tonnage from production ro

    Average tonnage per drilled mete

    4.3 - Drilling

    Sub-levels Drop raises Long-Hole % Hours %

    1 10.79 98.42 10% 1.1 1%

    2 10.79 98.42 10% 1.1 1%

    3 10.79 98.42 10% 1.1 1%4 10.79 98.42 10% 1.1 1%

    5 10.79 98.42 10% 1.1 1%

    6 10.79 98.42 10% 1.1 1%64.72 590.50 10% 6.47 1%

    # shifts (incl maintenance) 12 106 # shifts (incl maintenance) 1

    drilling hours (incl maintenance) 68.32 622.30 drilling hours (incl maintenance) 6.77

    NOTE: The average productivity includes: drilling, daily maintenan

    Drop raises -> 43.0 67.3

  • 7/28/2019 Productivity Long-Hole

    6/16

    LONG-HOLE

    STOPE PRODUCTIVITY CALCULATION

    4.4 - Support by anchor cables

    Drilling sub-levels Length of Spacing between Number of Number of Number of cables Number of drilledLong-Hole sub-levels rows rows holes/row /hole meters/row

    1 93 2.4 38 6 1 3

    2 93 2.4 38 6 1 33 93 2.4 38 6 1 3

    4 93 2.4 38 6 1 3

    5 93 2.4 38 6 1 3

    6 93 2.4 38 6 1 3Anchor cables per drift outside the mineralized zone

    0

    0

    00

    Total tonnage from drilling rows (Long-Hole) 28071 tonnes

    Meter of cable/Long-Hole tonne 0.244 meter of cable/tonne

    14.9 meters/hour1

    76.0 meters/shift* The average productivity includes: drilling, daily maintenance, fixed time per shift and contingencies.

    4.5 - Blasting

    4.5.1 - Loading parameters

    Length notSub-levels Drop raises Long-Hole Drop raises loaded/row Long-Hole Drop raises

    1 32 228 96 3 1140 2222 32 228 96 3 1140 222

    3 32 228 96 3 1140 2224 32 228 96 3 1140 222

    5 32 228 96 3 1140 2226 32 228 96 3 1140 222

    192 1368 576 6840 1332

    Number of holes to be loaded

    Number of men (drilling)

    Average productivity (meters/shift) *

    Productivity (meters/hour)

    Number of meters to be loaded

    Kg of

    Long-Hole rows

    See worksheet:

    Cable_Drilling: productivity calculation of ancho

    File: 159332107.xls.ms_office

    Sheet: Long-Hole

    Page 6 of 16

    Experimental Min

    Val-d'Or

  • 7/28/2019 Productivity Long-Hole

    7/16

    LONG-HOLE

    STOPE PRODUCTIVITY CALCULATION

    4.5.2 - Loading time

    Sub-levels Fixed Variable TOTAL Fixed Variable TOTAL

    1 3.39 1.60 5.00 19.00 16.41 35.41

    2 3.39 1.60 5.00 19.00 16.41 35.41

    3 3.39 1.60 5.00 19.00 16.41 35.41

    4 3.39 1.60 5.00 19.00 16.41 35.41

    5 3.39 1.60 5.00 19.00 16.41 35.416 3.39 1.60 5.00 19.00 16.41 35.41

    20.36 29.98 212.45

    NOTE: - fixed time: includes a,b,c,d,e

    - varable time: includes transportation and loading of explosives Loa

    LONG-HOLE NUMBER OF ROWS/SHIFT 4.7 rows/shiftTONNES/SHIFT 289 tonnes/shift

    DROP RAISES NUMBER OF BLASTS/SHIFT 1.03 blasts/shiftMETERS ADVANCED/SHIFT 3.1 meters/shift

    Long-Hole (hours)Drop raises (hours)

    T

    File: 159332107.xls.ms_officeSheet: Long-Hole

    Page 7 of 16

    Experimental Mine

    Val-d'Or

  • 7/28/2019 Productivity Long-Hole

    8/16

    LONG-HOLE

    STOPE PRODUCTIVITY CALCULATION

    5.0 - STOPE COMPILATION

    5.1 - TABLE OF REQUIRED HOURS PER ACTIVITY

    FLOOR

    CLEANING DRILLING REDRILLING

    ref. section 2.0

    1.006

    6.00

    FLOOR

    CLEANING DRILLING REDRILLINGref. section 4.1 ref. section 4.3 ref. section 4.3

    69.75 68.32 6.77

    REFERENCE NUMBER OF MEN 2 One man by default

    PLANNED NUMBER OF MEN 2

    ONLY DIRECT VARIABLE ACTIVITIES ARE INFLUENCED BY THE NUMBER OF MEN.THEREFORE, ACCORDING TO THE NUMBER OF MEN ENTERED, WE OBTAIN:

    69.75 68.32 6.77

    * The planned number of men can be different from the one entered in each section. If the number is different,

    the time required for variable activities will be corrected in proportion to the number of men.

    (inside the stope)

    Number of times

    23.00

    DIRECT VARIABLE (hours) *

    2

    1

    DEMOBILIZATION

    23.00

    ref. section 3.0

    MOBILIZATION AND

    One man per drill

    DROP RAISES

    DIRECT FIXED (hours)

    (inside the stope)

    2

    MOBILIZATION AND DROP RAISES5.1.2 - DIRECT VARIABLE ACTIVITIES

    1

    DEMOBILIZATIONref. section 3.0

    5.1.1 - DIRECT FIXED ACTIVITIES

    DIRECT VARIABLE (hours)

    One man per drill

    File: 159332107.xls.ms_office

    Sheet: Long-HolePage 8 of 16

    Experimental MineVal-d'Or

  • 7/28/2019 Productivity Long-Hole

    9/16

    LONG-HOLE

    STOPE PRODUCTIVITY CALCULATION

    5.2 - STOPE PRODUCTIVITY CALCULATION

    FLOOR

    CLEANING DRILLING REDRILLING

    Hours of fixed activities 6.00 29.

    + + +

    Hours of variable activities 69.75 68.32 6.7727

    Tr= = = 2.9

    TOTAL 75.75 68.32 6.77* * *

    PLANNED NUMBER OF MEN 2 1 1= = =

    TOTAL MANHOURS REQUIRED 151.5 68.3 6.8

    Number of hours per shift (schedule) 8 hours

    with a co

    OUTSIDE STOPE

    PRODUCTIVE CONTINGENCY FIXED

    2863.3 429.5 1194.8 4487.6

    64% 10% 27% 100%

    *23.00

    2=

    DEMOBILIZATION

    INSIDE THE STOPE

    TOTAL (STOPE)TOTAL

    73%

    DROP RAISES

    =

    +

    46.0

    23.00

    MOBILIZATION AND

    MANHOURS

    3292.8

    File: 159332107.xls.ms_officeSheet: Long-HolePage 9 of 16

    Experimental MineVal-d'Or

  • 7/28/2019 Productivity Long-Hole

    10/16

    LONG-HOLE

    STOPE PRODUCTIVITY CALCULATION

    6.0 - STOPE STATISTICS

    Pow

    54 mm 102 mm Tonnes T/drilled m Explosives (kg) (k

    DROP RAISES 576 144 739 1.026 1,332

    LONG-HOLE 8208 28,071 3.42 15,822

    CABLES 6840

    TOTAL 15624 144 28,810 1.83 17,154

    6.1 - STOPE PLANNING FACTORS

    Required number of shifts (including contingencies and fixed time per shift)

    Mobilization and

    Floor cleaning Demobilization DRILLING REDRILLING BLASTING DRILLING REDRILLING BL

    14.8 4.5 13.4 1.3 11.7 121.9 1.2

    with 2 men with 2 men with 1 man with 1 man with 2 men with 1 man with 1 man wit

    Productivity

    Floor Mobilization & Inscleaning Demobilization of

    18.8 meters/ms 9 manshifts/sub 94.6

    Drilling

    (m/shift)

    43.0 63.1 tonnes/shift

    LONG-HOLE 67.3 289.4 tonnes/shift

    CABLES 76.0

    per drill

    DROP RAISES

    DROP RAISES

    LONG-HOLE

    Drilled meters

    Loading

    File: 159332107.xls.ms_officeSheet: Long-HolePage 10 of 16

    Experimental MineVal-d'Or

  • 7/28/2019 Productivity Long-Hole

    11/16

    LONG-HOLEPRODUCTIVITY CALCULATION OF PRODUCTION DRILLING

    1.0 - Calculation of the average drilling time per rod 3.0 - Hole b

    minutes0.41.50.40.5

    1.4

    0.7

    4.0 - Pivotinaverage drilling time per rod 4.9 min/rod

    length of the rod (m) 1.2average time per drilled meter 4.1 min/drilled m

    5.0 - Movingchang

    2.0 - Casingmin

    0.4 average time t1.52.0

    0.8 6.0 - Movingor on t

    minutes/casing 4.7

    Insert the rodDrilling time/rod

    Change of rodHole cleaning/rod

    Loosen the rod

    Store the rod

    Mo

    Insert the rod with steel bit for casing

    DrillingInsert casing

    Remove the rod with steel bit for casing

    A

    Adjust the time in relation to the

    penetration rate and the length

    of the rod

    File: 159332107.xls.ms_officeSheet: Prod_DrillingPage 11 of 16

    Experimental MineVal-d'Or

  • 7/28/2019 Productivity Long-Hole

    12/16

    LONG-HOLEPRODUCTIVITY CALCULATION OF PRODUCTION DRILLING

    7.0 - Typical row 1.254 mm

    Breakthrough Number Hole # Length yes=1, no=0 Setup Casing of rods Drilling Breakthrough Casing Positioning

    15 1 1 12.7 62.1 0.9 0.0 1.1 15 1 1 12.7 62.1 0.9 0.0 1.2 15 1 1 12.7 62.1 0.9 0.0 1.3 0.0 0.0 0.0 0.04 0.0 0.0 0.0 0.05 0.0 0.0 0.0 0.06 0.0 0.0 0.0 0.07 0.0 0.0 0.0 0.08 0.0 0.0 0.0 0.09 0.0 0.0 0.0 0.0

    10 0.0 0.0 0.0 0.011 0.0 0.0 0.0 0.012 0.0 0.0 0.0 0.013 0.0 0.0 0.0 0.014 0.0 0.0 0.0 0.015 0.0 0.0 0.0 0.016 0.0 0.0 0.0 0.017 0.0 0.0 0.0 0.018 0.0 0.0 0.0 0.019 0.0 0.0 0.0 0.020 0.0 0.0 0.0 0.021 0.0 0.0 0.0 0.022 0.0 0.0 0.0 0.023 0.0 0.0 0.0 0.024 0.0 0.0 0.0 0.0

    25 0.0 0.0 0.0 0.0

    45 3 1 186.2 2.7 0.0 4.

    Hole diameter (mm)Length of rods (m)

    0

    Average product

    Number of drill rig displacements on the same row

    Drilling time (min) Disp

    Enter the required number of displacements of the drill rig

    on the same row.

    The displacement time between rows is already included

    in the calculations.

    File: 159332107.xls.ms_officeSheet: Prod_DrillingPage 12 of 16

    Experimental MineVal-d'Or

  • 7/28/2019 Productivity Long-Hole

    13/16

    LONG-HOLEPRODUCTIVITY CALCULATION OF DROP RAISE DRILLING

    1.0 - Calculation of the average drilling time per rodProduction Reaming

    54 102

    0.4 0.41.5 2.4

    0.4 0.8

    0.5 0.5

    1.4 2.0

    0.7 0.8

    average drilling time per rod 4.9 6.9 min/rod

    1.2

    average time per drilled meter 54 mm 4.1 minutes/drilled meter102 mm 5.8 minutes/drilled meter

    2.0 - Casingmin

    0.4

    1.5

    2.0

    0.8

    minutes/casing 4.7

    7.0 - Typical drop raise drilling

    1.26

    Breakthrough # setups Number Casing Number

    # holes Diam (mm) yes=1, no=0 Length /row of rows yes=1, no=0 of rods Drilling Bre

    16 54 1 96 3 5 0 82.7 405.1

    4 102 1 24 2 2 0 20.7 142.6

    120 5 7 547.7

    Insert the rod with steel bit for casing

    length of the rod (m)

    Drilling

    Insert casing

    Remove the rod with steel bit for casing

    Loosen the rod

    DIAMETER (mm)

    Store the rod

    Insert the rod

    Change of rod

    Hole cleaning/rod

    Drilling time/rod

    Length of rods (m)Length of holes (m)

    Drillin

    Average prod

    Total number of additional displacements of the dr

    3

    Only big diameter hole drilling.

    If pilot holes are required before drilling the big diameter,

    these will have to be added to the first line.

    Enter the total number of additional displacements of the drill rig on all the

    rows.

    The displacement time between rows is already included in the

    calculations.

    Adjust the

    penetratio

    of the rod

  • 7/28/2019 Productivity Long-Hole

    14/16

    LONG-HOLEPRODUCTIVITY CALCULATION OF ANCHOR CABLE DRILLING

    1.0 - Calculation of the average drilling time per rod 3.0 - Hole bmin

    0.41.50.40.5

    1.4

    0.7

    4.0 - Pivoti

    average drilling time per rod 4.9 min/rod

    length of the rod (m) 1.2average time per drilled meter 4.1 min/drilled m

    5.0 - Movinchang

    2.0 - Casingmin

    0.4 average time1.52.0

    0.8 6.0 - Movinor on

    minutes/casing 4.7

    DrillingInsert casing

    Remove the rod with steel bit for casing

    M

    Store the rod

    Loosen the rod

    Insert the rod with steel bit for casing

    Drilling time/rodInsert the rod

    Change of rodHole cleaning/rod

    Adjust the time in relation to the

    penetration rate and the length

    of the rod

    File: 159332107.xls.ms_officeSheet: Cable_DrillingPage 14 of 16

    Experimental MineVal-d'Or

  • 7/28/2019 Productivity Long-Hole

    15/16

    LONG-HOLEPRODUCTIVITY CALCULATION OF ANCHOR CABLE DRILLING

    7.0 - Typical row1.2

    54 mm

    Breakthrough Number Hole # Length yes=1, no=0 Setup Casing of rods Drilling Breakthrough Casing Positionin

    1 5 0 1 4.3 21.2 0.0 0.0 12 5 0 1 4.3 21.2 0.0 0.0 13 5 0 1 4.3 21.2 0.0 0.0 14 5 0 2 4.3 21.2 0.0 0.0 15 5 0 2 4.3 21.2 0.0 0.0 16 5 0 2 4.3 21.2 0.0 0.0 17 0.0 0.0 0.0 0.08 0.0 0.0 0.0 0.09 0.0 0.0 0.0 0.0

    10 0.0 0.0 0.0 0.0

    11 0.0 0.0 0.0 0.012 0.0 0.0 0.0 0.013 0.0 0.0 0.0 0.014 0.0 0.0 0.0 0.015 0.0 0.0 0.0 0.016 0.0 0.0 0.0 0.017 0.0 0.0 0.0 0.018 0.0 0.0 0.0 0.019 0.0 0.0 0.0 0.020 0.0 0.0 0.0 0.021 0.0 0.0 0.0 0.022 0.0 0.0 0.0 0.023 0.0 0.0 0.0 0.024 0.0 0.0 0.0 0.0

    25 0.0 0.0 0.0 0.0

    26 0.0 0.0 0.0 0.0

    30 0 2 127.4 0.0 0.0 7

    Dis

    Number of drill rig displacements on the same row

    0

    Average produc

    Length of rods (m)

    Drilling time (min)

    Hole diameter (mm)

    Enter the required number of displacements of the drill rig

    on the same row.

    The displacement time between rows is already included in

    the calculations.

    File: 159332107.xls.ms_officeSheet: Cable_DrillingPage 15 of 16

    Experimental MineVal-d'Or

  • 7/28/2019 Productivity Long-Hole

    16/16

    3rd drillin level or UPPER LEVEL

    2nd drilling sub-level

    1st drilling sub-level

    Drop raises

    Typical Long-Hole Stope

    LOWER LEVEL

    File: 159332107.xls.ms_officeSheet: DrawingPage 16 of 16