Product Development & Systems Integration Pylon for ... · Gaurangna Tiwari Manufacturing ......
Transcript of Product Development & Systems Integration Pylon for ... · Gaurangna Tiwari Manufacturing ......
0
CAMAQ 2015-2016
Product Development &
Systems Integration
Pylon for installation of the
PW305A engine on the
CRJ-700
Executive Summary
0
ACKNOWLEDGMENTS
Bombardier Aerospace École Polytechnique de Montréal Marco Beaulieu Nour Aimène Warren Hall
Normand Bonhomme Benedict Besner Martin Leclerc
Olivier De Melo Roy Martin Cardonne Grant McSorley
Jean-Marc Leclerc Martine Gagnon
André Montpetit
Alexandre St-Jean
Bell Helicopter Pratt & Whitney Canada
Daniel Carrier François Brophy
Pat Spina Frank Caruso
David Kafshbarghi
CAMAQ Mario Laliberté
Maryse Bélanger Hubert Marcotte
Éric Edstrom François Provencher
Nathalie Paré Michel René
Richard Ullyott
École Nationale d’Aérotechnique Transport Canada Dominique Gonthier Jean-Pierre Francoeur
Louis-Philippe Tousignant José Martin
This project required a huge amount of work, research and dedication. The
successful completion of the project would not have been possible if we did
not have the support of many individuals and organizations. Therefore,
Pyloneers would like to extend its sincere gratitude to all the partners.
1
PROJECT SCOPE The Product Development and Systems Integration (PDSI) Project is a simulation of integrated product
development from the Requirements Review to the Production Readiness Review. A team of 16
aerospace engineering students were tasked with the design, manufacturing, testing and certification
of a pylon to retrofit the P&WC’s PW305A engine on the Bombardier CRJ-700 aircraft.
In order to complete the eight month design process, the team adopted concurrent engineering
methods to deliver a solution fulfilling clients’ requirements as well as certification regulations. The team
completed specific deliverables for the proposed solution within time, budget and resource constraints.
Main activities included designing the pylon structure and systems, testing a critical component and
developing a complete production plan.
Requirements
Review
Advanced
Concept
Review
Preliminary
Design
Review
Critical
Design
Review
Production
Readiness
Review
TABLE OF CONTENTS 1
2-3
4
5
6-7-8
9
10-11
12
13
14-15
16-17
PROJECT SCOPE
TEAM PRESENTATION
FINAL PRODUCT
PROJECT PHASES
DESIGN OVERVIEW
ANALYSES
MANUFACTURING
TESTING
CERTIFICATION
PROJECT MANAGEMENT
LESSONS LEARNED
2
Ma
na
ge
me
nt
Antoine Cadotte Project Manager
Canada
Romain Grard Vice Project Manager
France
Carlos Gajardo Configuration Manager
Structure Specialist
Spain
In charge of leading 16 team members, the project management team's responsibilities include
risk mitigation, budget and time management, cost and weight optimization, as well as the
establishment of a business case to evaluate the company’s profitability.
Configuration management supports the implementation of Integrated Product Development
(IPD). It involves different methodologies to control the evolution of the Bill of Material (BOM) by
defining and tracking engineering changes.
Str
uc
ture
Julien Kuzdzal Team Lead
Communication Manager
France
Renaud Logre Structure Specialist
France
Jérémi Roussel Structure Specialist
Canada
The structure department is responsible for the design of the whole structure of the pylon, which
links the engine to the aircraft and accommodates the embedded systems. The scope of the
design ranges from the primary structure—engine mounts, structural spars—to the secondary
structure—skins, leading edge and trailing edge—to the firewall and the choice of fasteners.
Sy
ste
ms
Sébastien Lortie Team Lead
Canada
Ronak Lakhani Systems Specialist India
Antonio Gajardo Systems Specialist
Certification Specialist
Spain
The main responsibility of the systems department is to design the systems from the fuselage
interface to the engine interface, both defined by Interface Control Drawings. Considering the
large quantity of systems, the primary challenge is to respect minimal clearances and
accessibility requirements in the design.
TEAM PRESENTATION
3
Ma
nu
fac
turi
ng
Karine Gaulin Team Lead
Structure Specialist
Canada
Mohamed Irfan Ali Manufacturing Specialist
India
Gaurangna Tiwari Manufacturing Specialist
India
The main responsibility of the manufacturing department is to ensure that every part in the pylon is
manufacturable and can be produced. Also, the department is in charge of planning all the
activities related to the production of the pylon such as: process plans, assembly plans and a
complete production plan including a 2D layout of the plant and a production schedule.
Test
ing
Anshika Srivastava Team Lead
India
Ramon Montero Testing Specialist
Systems Specialist
Venezuela
Testing department is responsible for tests required to demonstrate compliance with certification
requirements. Major tasks are to develop a test plan and execute a structural test. A prototype of
the front engine mount was tested to validate the analysis methodology used by structure
department. Also, testing must develop Requests for Test (RFT) for systems such as: engine fireX
certification test and bleed air components qualification tests.
Ce
rtific
atio
n
Alexandre Guay Team Lead
Manufacturing Specialist
Canada
Roja Tabar Certification Specialist
Iran
The main responsibility of the certification department is to ensure that the solution complies with
all the certification regulations of Transport Canada, the FAA and EASA. The department is in
charge of developing a complete certification plan, to support the subsequent certification
process of the pylon.
4
Structure Systems
1. Front Mount 6. Bleed air duct 10. Thrust Reversers
2. Rear Mount 7. Fuel lines 11. FADEC
3. Firewall 8. Hydraulic lines 12. PC & Starter-Generator
4. Leading edge 9. FireX system 13. Fire detection
5. Trailing edge
WEIGHT
The final weight of the pylon is 191.1 lbs, respecting
the NTEW requirement of 200 lbs. The weight of
every component was tracked weekly with a level
of uncertatinty that decreased over time,
reaching a level of only 2% at the end of the
project. Targets were set each week to reduce the
overall weight.
FINAL PRODUCT
COST
The cost to produce one shipset is $201,500
including a 17% margin. It was first estimated with
a top-down approach, followed by an estimation
of the manufacturing, assembly and procurement
cost for every part.
Pyloneers’ final product has to respect strict requirements that were provided at the beginning of the
project in the form of a Statement of Work (SOW) and a Technical Requirements Document (TRD). The
present design is the result of many trade-off studies to ensure compliance with all the requirements.
The driving factors taken into consideration were minimizing changes to facilitate retrofit, the rotor-burst
zones and weight reduction.
TOTAL WEIGHT : 191.1 LBS
Structure:
154.7 LBS
Systems:
36.4 LBS
SELLING PRICE : $250,000
5
RR
ACR
PDR
CDR
PRR
Requirements Review Definition of the requirements and
agreement on the scope
Creation of team structure
Development of project schedule
and budget
Creation of the Roadmap
PROJECT PHASES
Advanced Concept Review Exploration of pylon concepts to
address requirements
Risk mitigation strategy
Preliminary test plan
Definition of Certification Basis
Preliminary Design Review Preliminary Digital Mock-Up
Analysis of design elements
Production proposal with schedule
for critical items
Preliminary Certification Plan
Detailed testing proposal
Critical Design Review Detailed pylon design
Cost & Weight analysis
Production Plan proposal
Initial test results
Functional Hazard Analysis and
Systems Safety Assessment
Production Readiness Review Final pylon solution
Complete Production Plan
Final Certification Plan with means
of compliance
Life Cycle Assessment
Final drawing package
6
DESIGN OVERVIEW
PRIMARY STRUCTURE
The primary structure links the engine to the aircraft
fuselage. It is composed of two engine mounts: the
front mount bears 100% of the longitudinal loads
and 80 % of the vertical loads. The rear mount
sustains one third of the inertial loads; but bears no
load in the longitudinal direction, the thrust axis. This
load distribution is ensured by a pivot connection at
the rear mount, using two vertically aligned
spherical bearings. The mounts are titanium 6Al-4V
STA since it is the fireproof material which provides
the best compromise between allowable stress and
weight.
Both mount assemblies present the same general
configuration: the yoke is attached to a
supporting spar, linked to the fuselage, and, on
the other end, two lugs join the pads to support
the engine. The lower lug has a bottom link with a
pivot connection to accommodate for thermal
expansion and movements of the engine. Key
driving elements for the layout were the existing
interfaces with both fuselage and engine, and
minimizing the exposure of critical systems and
mounts to the rotor-burst zones.
SECONDARY STRUCTURE
The secondary structure includes the spars, the skins,
and all the components that are not part of the
primary load path. For retrofit considerations, spars
are designed to minimize any changes from the
existing structure. One spar—at fuselage station
FS1070—is totally redesigned to simplify the design as
it is no longer structural. The other spars are slightly
cut or trimmed to accommodate the firewall. The
skin closing the pylon’s box is permanently attached
to the spars with rivets and hi-lite fasteners, and is
made of ten panels. Those in the fire zone are
titanium, while the others are aluminum. Stress
analyses have been performed to
ensure that the upper skin can support 250 lbs for maintenance purposes. Five access panels allow
easy accessibility and maintainability to the pylon’s systems from below, and one from above. The
leading and trailing edge assemblies of the pylon are removable. The pylon is sealed and is resistant to
bird impact and lightning strikes.
7
FIREX SYSTEM
The purpose of the fireX system is to be able to
extinguish any fires that occur in the engine. The
nozzles are located and designed to maximize
agent dispersion in the nacelle: located towards
the front to favor flow dispersion towards the back
and pointing up and down to favor dispersion
around the engine. A ground test will be made to
confirm that the current configuration is viable.
Space reservation for a third line is provided in
case the test indicates this to be necessary.
FUEL SYSTEM
The fuel system is made of two different lines: the
engine feed line and the motive flow line. Both
CRES 321 pipes are double shrouded to maximize
segregation with potential ignition sources. The
pipes are routed under the bleed air to avoid
flammable fluid leakage on the hot surface of the
bleed air duct. Other parameters are kept from
the previous design, ensuring that certification is
achievable.
BLEED AIR SYSTEM
The purpose of the bleed air system is to bring hot
air to the fuselage, to supply the Environment
Control System of the aircraft. The material selected
is CRES 321, a fireproof material able to sustain air
temperature up to 860°F. To minimize the risk of fire,
a 0.125” thick glass fiber insulation is installed around
the pipe to lower the touch temperature under the
fuel auto ignition point. The final design has a
diameter of 2.00” to respect the various
requirements specified by Bombardier and the
Certification Authorities. A bleed leak detection
system is routed alongside the bleed air to detect
any leakage event that would occur during flight.
8
HYDRAULIC SYSTEM
The purpose of the hydraulic system in the pylon is to connect to
the Engine Driven Pump (EDP) in order to provide primary
hydraulic power to the airplane. All three pipes are made of
titanium to minimize risks of fire in this area. Those lines are also
routed under the bleed air to avoid flammable fluid leakage on
the bleed air pipe.
ELECTRICAL SYSTEM
The electrical system is composed of the FADEC, the thrust
reversers and the starter-generator power cables. The power
cables are AWG 00 to fit the working temperature vs current
requirements in order to be able to start the engine. A voltage
drop analysis was performed to ensure that the correct voltage
would be given to the starter-generator during engine start.
FIREWALL
The firewall’s role is to prevent propagation of
fire between the engine and the fuselage. It is
also the break point for the systems passing
through the pylon. Its position and layout
FIRE DETECTION
The fire protection system is made of two independent loops that are routed on the firewall. The wires
are routed around the potential ignition sources and flammable fluids in order to ensure the detection
of fires. There are also two other loops located in the engine’s
hottest zones since they are the
zones with the highest risk of fire.
have been defined for maintenance and accessibility purposes. It is a non-structural element made of
0.025 inch thick titanium plates, complying with the fireproof requirement, and is attached to the skin
using brackets. Seals around the front mount and nacelle close the fire zone, while the rear mount’s
design accommodates the firewall’s design.
9
SYSTEMS ANALYSES
To justify the design, the team performed key analyses on the
characteristics that were driving the design. For example, the
touch temperature analysis performed on the bleed air
assured that the surface temperature is under the fuel auto
ignition temperature (~400°F). A performance analysis
proved that the minimum pressure at the fuselage interface
is above 20 psi as required per Bombardier. Also, an
expansion analysis is performed to select and position the
bellows that allow for thermal expansion of the duct.
ANALYSES
GLOBAL FINITE ELEMENTS METHOD
A GFEM is carried out to study the general
behavior of the whole pylon’s structure. The
structural geometry is inserted into the model, and
the output is the load distribution at each
element. This is used for the sizing of the
components such as the spars. The GFEM is also
used to study the pylon’s response to vibrations. A
total of 85 limit and ultimate load cases—provided
by the OEM, corresponding to various flight
conditions—have been run through this model.
The extracted loads are used as inputs for further
detailed stress analyses.
ACCESSIBILITY AND MAINTAINABILITY
For the pylon to be a viable design, PY has to
make sure that every part of it can be accessed
and removed quickly by a technician. To facilitate
this, access panels are placed at strategic
locations to provide access to all of the systems
and structural components. To demonstrate the
accessibility, manikins in CATIA V6 are used to
show that there is enough space for a hand and
a tool to fit in the required space, which also
accommodates movement.
DETAILED FINITE ELEMENTS ANALYSES
Critical load cases are identified for each component. Using the GFEM
internal loads as inputs, a finite element analysis is completed on the
two engine mounts, as well as the spars and skins, to verify the stress
levels. This analysis was part of an iterative process used to optimize the
part geometry and save weight. The front mount’s mass was thus
decreased by 18 % (55 lbs to 45 lbs), while the rear mount went from 12
lbs to 6 lbs. Final margins of safety are 3% for the front mount and 15 %
for the rear mount.
10
MANUFACTURING
PRODUCTION PLAN STRATEGY
To satisfy customer requirements, Pyloneers developed a
complete production plan strategy to demonstrate its ability
to produce between 55 and 60 new shipsets and 5 to 20
retrofit shipsets per year. A learning curve was used in order to
model the production schedule. Human factors, a pace
factor and repairs and maintenance were key elements
considered for a realistic schedule. Moreover, parallelism of
tasks allowed Pyloneers to reduce its lead time for one shipset
from 8 days to 3 days in a steady-state production. The plant
is expected to operate 3 shifts per day, 5 days per week.
RETROFIT
Retrofit was considered very early in the design process as one of the main driving factors for the design
and manufacturing. As requested by Bombardier Aerospace, the team proposed a pylon with a
minimum of design changes and no interface changes. For the retrofit pylon, the trailing edge assembly
and selected spars remain the same.
MANUFACTURING AND ASSEMBLY
Pyloneers will manufacture critical components,
such as the front & rear engine mounts and the
spars, in-house. Other elements will be bought
directly from certified suppliers as custom orders
(systems elements) or standard parts (bolts, plates,
rivets, etc…).
The plant will be equipped of two CNC machines
for the manufacturing of titanium and aluminum
components. Anodizing, the application of a
topcoat, and finishing procedures will be
performed on all aluminum parts. Manufacturing
process plans were produced for all components
produced in-house.
Pyloneers developed a layout for its plant, measuring 13,000 ft2. This layout was defined considering
space requirements for machines, jigs, automated forklifts, and tools to produce the components. The
main objective for the layout was to minimize the displacements from one station to another on the
production floor while respecting the process flow defined.
To reduce the lead time for the overall production of the pylon, the assembly process is defined with
multiple sub-assemblies, which enables workers to perform tasks in-parallel. Assembly process plans
were produced for each sub-assembly and contain tool information, operations to perform, time and
human resources required and parts to assemble.
11
FIRST FLIGHT READY PROTOTYPE
The first flight ready prototype is the first pylon which will be produced by Pyloneers and delivered to
Bombardier so that ground and flight testing can be performed to support the certification process.
For the first prototype, the same manufacturing and assembly processes will be used, although they
will take more time to account for workers’ experience. It is scheduled to be manufactured once
Pyloneers’ plant is fully equipped and functional.
First article inspection is also considered for the first prototype. The cost for the production of the first
flight ready prototype (one pylon) is estimated at $297,808, which is approximately three times that of
the steady-state production cost.
PROTOTYPES
As one of the most critical components of the pylon, two
prototypes of the front engine mount were manufactured at École
Nationale d’Aérotechnique. Those prototypes were scaled down
to 40% and made of aluminum alloy. Constant communication with
the manufacturer ensured exchange of valid component
specifications and a common schedule.
The first prototype was representative of the preliminary design and
was used for the structural bench test executed at École
Polytechnique de Montréal. Following the weight optimisation
process and the resizing of key elements during CDR, a second
prototype was produced to present the final design of the front
engine mount.
Step 1
Step 2
Step 3
• Goal and Scope of Analysis • Impact Categories and LCIA
Method • Selection of LCA Tool
• Definition of Product • Definition of Life-cycle Phases • Definition of Processes involved • Build Model in LCA Tool
• Generate results • Analyse relevance of each phase • Interpretation of results • Recommendations
LIFE-CYCLE ASSESSMENT
In order for Pyloneers to propose solutions to its clients
that are respectful of the environment, a life-cycle
methodology is developed. As an example, the
environmental impacts of the manufacturing processes
to produce the aluminum spar at FS1098.2 are
assessed. OpenLCA – a professional LCA and footprint
software – is used to perform the analysis.
Results show that 75% of the total CO2 emitted to the
atmosphere comes from the machining process
selected to produce the spar. Based on this, Pyloneers
recommends that during the first years of production, the company performs further design
optimization to decrease the weight of the component, which will reduce the manufacturing lead
time.
3D printed prototypes were presented to the clients at each design review throughout the project. The
team used a 3D printer – MarkerBot 2X – with fused deposition modeling technology and produced
25% scaled prototypes of the mounts.
12
The aim of the engine fireX discharge test is to demonstrate a proper level of agent concentration in
the fire zone. This is a ground test where critical flight conditions will be simulated by changing the
ventilation regimes. The agent concentration will be recorded by probes positioned at strategic
locations around the nacelle.
STRUCTURAL TEST – FRONT ENGINE MOUNT PROTOTYPE
The aim of the test is to validate the analysis methodology of the
structures department for certification. The prototype is a scaled
down (40%) model of the preliminary design of the front engine mount.
The material used for the prototype is Al 6061-T651 and a coupon test
is performed to obtain material properties.
The test is conducted in Ecole Polytechnique’s Civil Engineering facility
supported by engineers and technicians. The fixture is reused from
previous years to save time and money, where certain new parts are
manufactured to adapt the fixture to the testing machine.
The test is conducted in two configurations. The first
configuration in the forward axis represents the limit
load case in critical thrust during flight. The second
configuration in the downward axis represents the
ultimate load case in critical landing. The loads are
applied in cycles to reach limit and ultimate load.
For data acquisition during the test, strain gauges are
used. Also, Pyloneers uses a digital image correlation
3D data acquisition system to record detailed
deformation and displacement of the prototype during
the test.
The results from the test are analyzed using confidence
levels (CL) which show how close the test
SYSTEMS TEST
Requests for Test (RFT) are developed for systems to
demonstrate compliance with certification requirements.
The RFTs are qualification tests on bleed air components and
an engine fireX discharge test.
For the bleed air system, two components (duct couplings
and bellows) are selected as test articles. Proof of pressure
and burst pressure tests are selected as the qualification
tests.
TESTING
results are to the analyses’ predictions. The confidence level in the elastic domain for both test
configurations is calculated to be between 10 to 20%. Positive confidence levels, like the ones
obtained, verify the conservatism in the design analysis methodology.
13
CERTIFICATION
CERTIFICATION PLAN
The team’s main design consideration is to ensure that the product will be certifiable. Therefore,
Pyloneers followed the typical industrial certification process, starting with the definition of the
certification basis following the changed product rule of Transport Canada. The certification
department then identified relevant official documentation such as advisory circulars, ARP standards,
guidelines and best practices for each requirement. Moreover, Pyloneers implemented a delegation
system to easily communicate certification requirements and official documentation amongst team
members. This led to the elaboration of a complete Certification Plan, which includes the means of
compliance that were defined and accepted by authorities.
Constant communication with transport authorities, as represented by Bell Helicopter Textron, ensured
that the pylon complied with regulations at all times.
FHA & SSA
The Functional Hazard Analysis (FHA) was performed on five
critical systems. All hazards which are classified as major and
above – in terms of severity – were further analyzed in the
Systems Safety Assessment (SSA). Pyloneers has agreed with
authorities to use fault-tree analysis as the method to show
compliance to the requirements. All probabilities of
occurrence for the failure conditions identified meet the
requirements.
GENERAL
CERTIFICATION
PROCESS
INSTRUCTIONS FOR CONTINUED AIRWORTHINESS
Supplemental Instructions for Continued Airworthiness (ICAs)
are provided to Bombardier Aerospace as updates to the
existing maintenance manuals for the bleed air system
passing through the new pylon of the CRJ-700. Supplemental
tasks will guide technicians to implement removal/installation
procedures. Related exploded views of the system,
containing lists of part numbers and assemblies, are also
provided.
14
PROJECT MANAGEMENT
The Management department is in
charge of ensuring the completion of
deliverables fulfilling the client’s
requirements, within the given time,
budget and human resource constraints.
The solution satisfies the company’s
profitability according to the seven year
contract developed with Bombardier.
RESOURCE MANAGEMENT
Earned Value Management has been the main process used to manage resources. The project has
been completed on schedule with a cost of $716,000, 2% over the $700,000 allocated budget.
REQUIREMENTS MANAGEMENT
A list of requirements has been transmitted at the beginning
of the project through a Statement of Work and a Technical
Requirements Document. A total of 209 requirements has
been agreed upon at the Requirements Review and
incorporated into a Compliance Matrix tool. The
requirements management method consisted of the
complete identification of every requirement by the team
at the beginning of the project and the tracking of their
completion and compliance status along the phases.
Throughout the project, Pyloneers Inc. proposed 16
modified compliances that have been formally approved
by all partners.
Structure
Certification
Testing
Manufacturing
Systems
Requirement Management
Business Case
Cost & Weight Human
Resources
Management
Configuration
Management
Communication
Management
In order to complete all the specific deliverables required for a phase, resources have shifted between
departments, particularly from design departments to manufacturing, as the project focus went from
being design-oriented to production-oriented during the PRR phase.
15
CONFIGURATION MANAGEMENT
A configuration management plan is created and
a systems engineering process is implemented to
establish and maintain consistency of the product
while using concurrent engineering methods. This
includes a DMU creation methodology and a
BOM evolution control system using CATIA v6 and
ENOVIA, respectively. To ensure the
communication of technical information among
the team, an engineering change process is also
established. As a result, an Integrated Product Development system is applied to develop the pylon.
COMMUNICATION MANAGEMENT
With the importance of close communication between Pyloneers Inc. and its partners, a
communication management system is developed to ensure that all critical information passes through
one official channel. As such, a Coordination Memorandum process is implemented and their
management, as well as all aspects of meetings with partners, is managed by the Communication
Manager.
RISK MANAGEMENT
One of the key management tools used by
Pyloneers Inc. is the Risk Assessment Cube.
Throughout the project, risks are carefully
monitored on a weekly basis. Critical project risks
are identified and evaluated using this tool. For
each of these risks, mitigation plans are
developed to minimize their consequences and
their probability of occurrence. Examples of high
risks encountered include a delay in the prototype
manufacturing and a cost overrun on the budget.
BUSINESS CASE
A financial analysis is completed on the basis
of a contract negotiated with Bombardier, the
main client. A ceiling price of $250 000 per
shipset is agreed upon. Based on production
costs and initial investments, including the
engineering effort, machinery and equipment,
Pyloneers’s business presents a Net Present
Value of $2.6M at the end of the seven year
contract.
Low
Medium
High
32
9
2
16
TESTIMONIALS
“This project was a challenging experience. We were faced with a real aerospace problem and had to design
a solution as one unified team very quickly. Overall, the project is a great way to learn about integrated product
development, which is central in the industry and not specifically taught in school. This project truly taught me
how to communicate and interact in a multidisciplinary team.” Alexandre Guay “The CAMAQ project gave me a great opportunity to experience engineering challenges in the aerospace
industry. It improved my problem solving skills, and besides the technical knowledge I gained, working in an IPD
team and multicultural environment helped me in all around development as a professional. The experience that
I gained through this project will help me throughout my career.” Anshika Srivastava
“Beyond providing a realistic insight of how the aerospace industry works, this truly unique experience allowed
me to grow into a much better leader, as I faced challenging moments. From giving a direction to the team
when the path was unclear to managing seemingly unsolvable issues, the CAMAQ project showed me what it
truly was to be a manager.” Antoine Cadotte
“Looking forward, it becomes clear how truly valuable this insight into product development is for my career, as
I faced real challenges from the aerospace industry. Through this multidisciplinary project I had the opportunity
to develop integrated solutions in a multidisciplinary environment and to learn lifelong skills related to
teamwork, communications and time management.” Antonio Gajardo Gonzalez
“This simulation is an immersive and challenging experience. In only a few months we have dealt with different
technical problems which arise along all the phases of development of an aerospace product. In addition to
finding a solution for them, we have been placed in several challenging situations, such as time or budget
constraints. In this context we have learnt how to implement IPD, the key to the success for a large project.”
Carlos Gajardo Gonzalez
“The CAMAQ project provided me with the experience of a fast paced and intensive project in the aerospace
industry. I had the opportunity to work with a team of fifteen top notch aerospace engineering students with
multicultural backgrounds. I learnt how to handle difficult situations and always move towards solutions. I learnt
that both engineering and management go hand in hand and a successful aerospace engineer is a good
manager in herself/himself.” Gaurangna Tiwari
“The CAMAQ project is the perfect way to gain experience while being in school. This virtual professional
environment gives you the opportunity to communicate with partners from major aerospace companies and,
above all, to learn from them. This project has already given us some interesting professional opportunities and I
am sure that there are more to come.” Jérémi Roussel
“Working as the communication manager, I became an expert in formal engineering communications
processes. It also showed me how much internal communication is essential in such a project. My experience in
the structure department makes me feel like I gained so much more experience in aerospace design practices
than I could have ever acquired so rapidly at school.” Julien Kuzdzal
“During the project, I improved all my engineering skills (technical, communication, leadership, etc.). I learned
how to be efficient in an IPD team in order to respect schedule and budget constraints. I am now able to
understand both sides of a design as I worked in both the manufacturing and structure departments. I feel that
there is no challenge insurmmountable now.” Karine Gaulin
“This project has been pivotal in my transformation from a student to an engineer. The experience garnered from
working in an IPD environment is incomparable to any that I have had previously. The transformation I have
undergone has been astonishing, and I can vouch that no internship in an organisation would equip one with
such skills, experiences or the confidence that I now possess." Mohamed Irfan Ali
17
“I will strongly recommend for those who are expecting to shift their aerospace careers to get involved in this
project, taught by aerospace experts and driven by the state-of-art of aerospace product development. As a
test engineer and electrical system integrator, I improved my engineering skills, addressing the design
requirements necessary for the delivery of an aerospace product within safety, time, quality and cost
specifications expected by our clients.” Ramon Montero Rodriguez
“CAMAQ project is the perfect opportunity for finishing students to boost their background, and prepare
themselves before a first job. We had to take on responsibilities, and we developed tools to help us make the right
decisions. The goal of this project is to learn what cannot be taught in class, and ensures students leave university
with the relevant skills and knowledge.” Renaud Logre
“This project was a simulated environment of my future job. I learned how to develop deliverables shared
between different departments, and influenced by their specific outputs and inputs. It was an enjoyable
experience. Furthermore, I encountered real aerospace problems, worked with different people from several
countries, and became familiar with their cultures.” Roja Tabar
“The project is a real lesson in team work. It is filled with turnovers and surprises that you must face, and does not
allow you to turn your back on any difficulty you may encounter: each has to be solved carefully, every time. As
a manager, I faced what it was to lead people under pressure and within strict time constraints. A really enriching
experience.” Romain Grard
“The project is very intense and includes aspects that are impossible to learn from any academic course. It taught
me to perform under extreme pressure, while respecting the budget and schedule. I believe any professional
challenge can be tackled if one completes the project successfully. The skills I developed here will definitely be
useful in my entire career. Pyloneers for life!” Ronak Lakhani
“This project really teaches you everything that cannot be learned in school. Aspects like teamwork and time
management are two important dimensions of engineering that I succeeded in developing through this project.
Also, having the chance to get regular feedback on your work is a great opportunity to learn how the aerospace
industry really works.” Sébastien Lortie