Product Availability

download Product Availability

of 55

Transcript of Product Availability

  • 8/10/2019 Product Availability

    1/55

    Product Availability

  • 8/10/2019 Product Availability

    2/55

    Level of product availability

    Also referred as customer service level.

    Is measured using the cycle service level or fillrate.

    Is high to improve the responsiveness andattract customers.

    But high level requires large inventories. These large inventories tend to raise cost for SC.

    Therefore, SC needs to balance between level ofinventory and cost of inventory.

  • 8/10/2019 Product Availability

    3/55

    Factors affecting optimal level ofproduct availability

    Before understanding factors considerone example of a storekeeper who sells

    jacket.

    He buys the stock for entire seasonssupply of jacket before start of sellingseason.

    High level of product availability requireslarge number of jackets.

    It is likely to satisfy all demands. However, it results in a large number of

    unsold jackets at the end of season.

  • 8/10/2019 Product Availability

    4/55

    Example

    On the other hand, low level of productavailability results in few unsold

    jackets.

    In this scenario, a loss of potentialcustomers has to bear.

    Must balance the loss from having toomany unsold jackets and lost profitfrom turning away customers.

  • 8/10/2019 Product Availability

    5/55

    12-5

    Mattel, Inc. & Toys R Us

    Mattel was hurt last year by inventory cutbacks at Toys RUs, and officials are also eager to avoid a repeat of the 1998Thanksgiving weekend. Mattel had expected to ship a lot ofmerchandise after the weekend, but retailers, wary of

    excess inventory, stopped ordering from Mattel. That led thecompany to report a $500 million sales shortfall in the lastweeks of the year ... For the crucial holiday selling seasonthis year, Mattel said it will require retailers to place their fullorders before Thanksgiving. And, for the first time, the

    company will no longer take reorders in December, Ms.Barad said. This will enable Mattel to tailor production moreclosely to demand and avoid building inventory for ordersthat don't come.

    - Wall Street Journal, Feb. 18, 1999

  • 8/10/2019 Product Availability

    6/55

    12-6

    Key Questions

    How much should Toys R Us ordergiven demand uncertainty?

    How much should Mattel order? Will Mattels action help or hurt

    profitability?

    What actions can improve supply chainprofitability?

  • 8/10/2019 Product Availability

    7/55

    Importance of the Levelof Product Availability

    Product availability measured by cycle service level or fill rate Also referred to as the customer service level Product availability affects supply chain responsiveness Trade-off:

    High levels of product availability increased responsiveness andhigher revenues

    High levels of product availability increased inventory levels andhigher costs

    Product availability is related to profit objectives, and strategicand competitive issues (e.g., Nordstrom, power plants,

    supermarkets, e-commerce retailers) What is the level of fill rate or cycle service level that will result

    in maximum supply chain profits?

  • 8/10/2019 Product Availability

    8/55

    Factors Affecting the OptimalLevel of Product Availability

    Cost of overstocking

    Cost of understocking

    Possible scenarios Seasonal items with a single order in a season

    One-time orders in the presence of quantitydiscounts

    Continuously stocked items Demand during stockout is backlogged

    Demand during stockout is lost

  • 8/10/2019 Product Availability

    9/55

    Cost

    of overstocking = C0 Is the loss incurred by a firm for each unsold

    unit at the end of selling season.

    of understocking = Cu Is the margin lost by a firm for each lost sale

    from current and future sales if customer doesnot return.

    Two factors that affect optimal level of

    product availability. Cost of overstocking

    Cost of understocking

  • 8/10/2019 Product Availability

    10/55

    Optimal level of product

    availability Makes sense in the context of demand

    uncertainty.

    Firms have forecast a consensus estimate ofdemand without any measure of uncertainty.

    Now they have better appreciation foruncertainty.

    Incorporation of uncertainty and optimal levelof product availability can increase profit.

  • 8/10/2019 Product Availability

    11/55

    ExampleDemand distribution for jackets

    Demand Di(*100) Probability Cumulative probability ofdemand being Dior less

    probability of demandbeing greater then Di

    4 0.01 0.01 0.99

    5 0.02 0.03 0.97

    6 0.04 0.07 0.93

    7 0.08 0.15 0.85

    8 0.09 0.24 0.76

    9 0.11 0.35 0.65

    10 0.16 0.51 0.49

    11 0.20 0.71 0.29

    12 0.11 0.82 0.18

    13 0. 10 0.92 0.08

    14 0.04 0.96 0.04

    15 0.02 0.98 0.02

    16 0.01 0.99 0.01

    17 0.01 1.00 0.00

  • 8/10/2019 Product Availability

    12/55

    Example Expected profit from ordering a thousands of jacket

    =$49,900

    Potential outcome to buy 100 more jackets If extra 100 are sold, then profit=$5,500

    If 100 units are send to outlet, then loss=$500

    From table, there is 0.49 probability that demand is 1100 or higherand a 0.51 probability that demand will be 1000 or less.

    Expected profit=$5,500Xprob[Demand1,100]

    -$500Xprob[Demand

  • 8/10/2019 Product Availability

    13/55

    Optimal cycle service levelfor seasonal items

    Focus on seasonal product whereleftover items must be disposed at theend of season.

    Input:C0: cost of overstocking = c-s

    Cu: cost of understocking =p-c

    CSL*=optimal cycle service level

    O*=corresponding optimal order size

    CSL*=probability that demand during seasonwill be at or below O*.

  • 8/10/2019 Product Availability

    14/55

    Optimal cycle service levelfor seasonal items

    Rise in quantity from O* to O*+1 is withprobability 1-CSL* Expected profit of purchasing extra unit= (1-

    CSL*)(p-c) If additional unit remains unsold if demand is

    below O*

    Expected cost of purchasing cost of extra

    unit=CSL*(c-s) Expected marginal contribution of raising the

    order size from O* to O*+1=(1-CSL*)(p-c)-CSL*(c-s)

  • 8/10/2019 Product Availability

    15/55

    Optimal cycle servicelevel for seasonal items

    Expected marginal cost=0 CSL*=probability (demandO*)= (p-c)/(p-s)

    C0/(Cu+C0)=1/{1+(C0/Cu)}

    Optimal CSL* is referred as critical fractile

    If demand during season is normally distributed withmean and standard deviation , optimal orderquantity

    O*=F-1(CSL*, , )

    Expected profit=

    Fs is the standard normal cumulative distribution function andfs is the standard normal density function

    s sO O

    p s F p s f

    O(c s)F(O, , ) O(p c)[1 F(O, , )]

  • 8/10/2019 Product Availability

    16/55

    Desired cycle service level forcontinuously stocked items

    Focus on products such as detergent that areordered repeatedly.

    Organization uses safety inventory to increase thelevel of safety inventory to avoid stocking out.

    Left over detergent can be sold in next cycle.

    However, holding cost is incurred form one cycle tonext cycle.

    Two extreme scenarios All demands that arises when the product is out of stock is

    backlogged and filled later

    All demand arising when product is out of stock is lost.

  • 8/10/2019 Product Availability

    17/55

    When Demand during stockoutis backlogged

    No demand is lost, minimizing costs isequivalent to maximizing profit.

    When store is out of stock, discount of Cu isprovided to each customer.

    Ensures that each customer will return. Increase in safety inventory satisfies more orders

    resulting in less backlogs Cost of holding inventory increases. Level of safety inventory that minimizes backlogs

    and holding cost?? Optimal cycle service level CSL*=1-(HQ/DCu)

  • 8/10/2019 Product Availability

    18/55

    Example

    Input Q=400 gallons, ROP= 300 gallons, D=100

    gallons, D=20, unit cost=$3, holding cost

    as a fraction of cost h=0.2, cost of holdingone unit for one year=0.6 Lead time =2weeks

    Cost of stocking out?? If all unfilled

    demand is backlogged and carried over tonext cycle.

  • 8/10/2019 Product Availability

    19/55

    Solution

    Mean demand over lead time DL=DL=200gallons

    Standard deviation of demand in lead time

    CSL=F(ROP, DL, L) =F(300, 200, 28.3)

    CSL=NORMDIST(300, 200, 28.3, 1)=0.9998

    Imputed cost of stocking out Cu=HQ/(1-

    CSL)Dyear=0.6*400/0.0002*5,200=230.8 pergallon

    L D L 20 2 28.3

  • 8/10/2019 Product Availability

    20/55

    When Demand during stock out is lost

    Optimal cycle service level CSL*

    CSL*=1-HQ/(HQ+DCu)

    Cuis the cost of loosing one unit ofdemand during stockout period.

  • 8/10/2019 Product Availability

    21/55

    Managerial levers to improveSC profitability Focus on actions that can be taken to improvethe SC profitability Two obvious managerial levers

    1. Increasing the salvage value of each unit increases

    profitability.2. Decreasing the margin lost from a stockoutincreases profitability.

    Strategies to1. Increase to salvage value include selling outlet

    stores so that left units are not merely discarded.2. To decrease the margin lost in a stockout include

    arranging the backup sourcing so that customersare not lost forever.

  • 8/10/2019 Product Availability

    22/55

    Importance of the Ratio of cost ofoverstocking and understocking

    If this gets smaller, optimal level ofproduct availability increases.

  • 8/10/2019 Product Availability

    23/55

    Another lever

    Is to reduction of demand uncertainty.

    By this, better supply and demand canbe matched by reducing over and

    understocking. Means to reduce demand uncertainty.

    Improved forecasting

    Quick response Postponement

    Tailored sourcing

  • 8/10/2019 Product Availability

    24/55

    Improving forecast

    Helps the demand planning informationsystems.

    Can help a firm to increase itsprofitability while decreasing excessinventory overstock and sales lost dueto understocking.

  • 8/10/2019 Product Availability

    25/55

    Improved Forecasts

    Improved forecasts result in reduceduncertainty

    Less uncertainty (lower R) results in

    either: Lower levels of safety inventory (and costs) for

    the same level of product availability, or

    Higher product availability for the same levelof safety inventory, or

    Both lower levels of safety inventory andhigher levels of product availabilityAn increase in forecast accuracy decreases both the overstocked

    and understocked quantity and increases a firms profits.

  • 8/10/2019 Product Availability

    26/55

    Impact of Improving Forecasts(Example)

    Demand: Normally distributed with a meanof R= 350 and standard deviation of R=100

    Purchase price = $100Retail price = $250

    Disposal value = $85

    Holding cost for season = $5

    How many units should be ordered as Rchanges?

  • 8/10/2019 Product Availability

    27/55

    Impact of Improving Forecasts

    R O* Expected Overstock

    ExpectedUnderstock

    ExpectedProfit

    150 526 186.7 8.6 $47,469

    120 491 149.3 6.9 $48,476

    90 456 112.0 5.2 $49,482

    60 420 74.7 3.5 $50,488

    30 385 37.3 1.7 $51,494

    0 350 0 0 $52,500

  • 8/10/2019 Product Availability

    28/55

    Quick response

    Is the set of actions a supply chain takes thatleads in the reduction of lead time.

    Decrease in lead time results in increase in

    forecast accuracy. This allows them to better match with the

    demand and increase in profitability.

    Typically, buyers are able to make accurateforecasts once they have observed demandin first or second week in season.

  • 8/10/2019 Product Availability

    29/55

    Quick Response Set of actions taken by managers to reduce lead time

    Reduced lead time results in improved forecasts

    Typical example of quick response is multiple orders in one seasonfor retail items (such as fashion clothing)

    For example, a buyer can usually make very accurate forecasts afterthe first week or two in a season

    Multiple orders are only possible if the lead time is reducedotherwise there wouldnt be enough time to get the later orders beforethe season ends

    Benefits:

    Lower order quantitiesless inventory, same product availability

    Less overstock

    Higher profits

    If quick response allows multiple orders in the season, profitsincrease and the overstock quantity decreases.

  • 8/10/2019 Product Availability

    30/55

    Example

    Selling season is of 14 weeks. Replenishment time is 25 to 30 weeks.

    Difficult for a buyer to make a accurateforecast of demand this far in advance.

    This results in high demand uncertainty,leading the buyer in too many or too less unitseach year.

    Consider a case where replenishment time

    can reduce upto 6 weeks. Its results in entire seasons purchase in two

    orders.

  • 8/10/2019 Product Availability

    31/55

    Variation of profit and inventories with

    forecast accuracy

    Expected understock

    Expected over stock

    Expected profit

    Standard deviation of forecast error

  • 8/10/2019 Product Availability

    32/55

    Quick Response: MultipleOrders Per Season

    Ordering shawls at a department store Selling season = 14 weeks

    Cost per handbag = $40

    Sale price = $150 Disposal price = $30

    Holding cost = $2 per week

    Expected weekly demand = 20 SD of weekly demand = 15

  • 8/10/2019 Product Availability

    33/55

    Comparison of two policies

    1. A single order must arrive at the beginningof the season to cover the entire seasonsdemand.

    2. Two orders are placed in the season, one

    arriving at the beginning of the season andother arriving at the beginning of the eightweek.

    3. Now consider two instances

    One where buyers forecast accuracy does notimprove for the second order and where itimproves and the SD can be reduced.

  • 8/10/2019 Product Availability

    34/55

    Comparison

    Single order: consists of a quantity ordered atthe beginning of season.

    Two orders: consists of initial order quantity forfirst seven weeks followed by an order upto

    level for the second week. Second round quantity should account for sales

    during the first week and inventory remaining.

    The quantity ordered in second round it thedifference between order up-to-level andinventory remaining after first week.

  • 8/10/2019 Product Availability

    35/55

    Consequences of being able toplace a second order

    1. Consequences1. The expected total quantity ordered during the season

    with two orders is less than that with a single order for thesame cycle service level.

    2. The average overstock to be disposed of at the end of thesales season is less if two orders are allowed.

    3. The profits are higher when a second order is allowedduring the sales season.

    Total quantity is broken up intomultiple smaller orders, the buyer isbetter able to match supply anddemand and increase profitability.

  • 8/10/2019 Product Availability

    36/55

    Impact of Quick Response

    Single Order Two Orders in Season ServiceLevel

    OrderSize

    EndingInvent.

    Expect.Profit

    InitialOrder

    OULfor 2nd

    Order

    AverageTotalOrder

    EndingInvent.

    Expect.Profit

    0.96 378 97 $23,624 209 209 349 69 $26,590

    0.94 367 86 $24,034 201 201 342 60 $27,085

    0.91 355 73 $24,617 193 193 332 52 $27,154

    0.87 343 66 $24,386 184 184 319 43 $26,944

    0.81 329 55 $24,609 174 174 313 36 $27,413

    0.75 317 41 $25,205 166 166 302 32 $26,916

  • 8/10/2019 Product Availability

    37/55

    Forecast Improves for SecondOrder (SD=3 Instead of 15)

    Single Order Two Orders in Season

    ServiceLevel

    OrderSize

    EndingInvent.

    Expect.Profit

    InitialOrder

    OULfor 2nd

    Order

    AverageTotalOrder

    EndingInvent.

    Expect.Profit

    0.96 378 96 $23,707 209 153 292 19 $27,007

    0.94 367 84 $24,303 201 152 293 18 $27,371

    0.91 355 76 $24,154 193 150 288 17 $26,946

    0.87 343 63 $24,807 184 148 288 14 $27,583

    0.81 329 52 $24,998 174 146 283 14 $27,162

    0.75 317 44 $24,887 166 145 282 14 $27,268

  • 8/10/2019 Product Availability

    38/55

    Postponement Delay of product differentiation until closer to the time of the sale

    of the product All activities prior to product differentiation require aggregate

    forecasts more accurate than individual product forecasts

    Individual product forecasts are needed close to the time of saledemand is known with better accuracy (lower uncertainty)

    Results in a better match of supply and demand

    Valuable in e-commercetime lag between when an order isplaced and when customer receives the order (this delay isexpected by the customer and can be used for postponement)

    Higher profits, better match of supply and demandPostponement allows a firm to increase profits and better match supply anddemand if the firm produces a large variety of products whose demand is notpositively correlated and is of about the same size.

  • 8/10/2019 Product Availability

    39/55

    Postponement

    Refers to the delay of productdifferentiation until closer to the sale ofproduct.

    Aggregate forecasts are more accuratethen individual product forecasts.

    Individual forecasts are required close to

    the time of sale when demand is knownwith greater accuracy.

    Allows a SC to better match SC demand.

  • 8/10/2019 Product Availability

    40/55

    Postponement

    A powerful managerial tool to increaseprofitability.

    However, while using it production cost

    would be higher than the case wherethere is no postponement.

    Is valuable to for a firm that sells a

    large variety of products with demand.

    Value of Postponement:

  • 8/10/2019 Product Availability

    41/55

    Value of Postponement:Benetton

    For each color

    Mean demand = 1,000; SD = 500 For each garment

    Sale price = $50

    Salvage value = $10

    Production cost using Option 1 (long lead time) =$20

    Production cost using Option 2 (uncoloredthread) = $22

    What is the value of postponement? Expected profit increases from $94,576 to

    $98,092

  • 8/10/2019 Product Availability

    42/55

    Value of Postponementwith Dominant Product

    Color with dominant demand: Mean =3,100, SD = 800

    Other three colors: Mean = 300, SD = 200

    Expected profit without postponement =$102,205

    Expected profit with postponement =$99,872

  • 8/10/2019 Product Availability

    43/55

    Tailored postponement A firm uses production with postponement to satisfy a

    part of demand with the rest being satisfied without it. Produces higher profits then when no postponements

    is used or all are produced using postponement.

    A firm produces a portion of demand which is

    uncertain, postponement significantly improves theforecasts accuracy.

    Thus, allows a firm to increase its profitability by onlypostponing the uncertain part of the demand andproducing the predictable part at a lower cost without

    postponement.

    a ore os ponemen :

  • 8/10/2019 Product Availability

    44/55

    a ore os ponemen :Benetton

    Produce Q1units for each color using Option 1 and QA

    units (aggregate) using Option 2 Results:

    Q1= 800

    QA= 1,550

    Profit = $104,603

    Tailored postponement allows a firm to increase profits bypostponing differentiation only for products with the mostuncertain demand; products with more predictable

    demand are produced at lower cost without postponement

    T il d S i

  • 8/10/2019 Product Availability

    45/55

    Tailored SourcingA firm uses a combination of two supply

    sources One is lower cost but is unable to deal with

    uncertainty well

    The other is more flexible, and can thereforedeal with uncertainty, but is higher cost

    The two sources must focus on differentcapabilities

    Depends on being able to have one sourcethat faces very low uncertainty and cantherefore reduce costs

    Increase profits, better match supply and

    demand

  • 8/10/2019 Product Availability

    46/55

    Tailored sourcing

    Firms uses a combination of two supply sources1. Focusing on cost but unable to handle the uncertainty.

    2. Focusing on flexibility to handle uncertainty but at higher cost.

    But, to be effective, having supply sources where oneserves as the backup to other is not sufficient.

    The first should be required to supply the predictable portionof demand.

    The second should be responsive and be required to supply

    the uncertain portion of demand. Allows to better match supply and demand and increase of

    profit.

  • 8/10/2019 Product Availability

    47/55

    Tailored sourcing

    Value depends on the reduction in costthat can be achieved.

    Small benefitit may not be ideal.

    May be volume based or product based

    depending on source depending on thesource of uncertainty.

  • 8/10/2019 Product Availability

    48/55

    Volume based

    Tailored sourcing, the predictable part of aproducts demand is produced at an efficientfacility.

    Should be considered by firms that havemoved a lot of their production overseas totake advantage of lower costs.

    In this condition source with shorter lead timeis more profitable even if he is moreexpensive.

  • 8/10/2019 Product Availability

    49/55

    Product based

    Low volume product with uncertain demand areobtained from a flexible source while high volumeproduct with less demand uncertainty are obtained forman efficient source.

    New products have a very uncertain demand while wellestablished products have more stable demand.

    May be implemented with a flexible facility focusing onnew products and efficient facilities focusing on wellestablished products.

  • 8/10/2019 Product Availability

    50/55

    Tailored Sourcing

    Sourcing alternatives

    Low cost, long lead time supplier

    Cost = $245, Lead time = 9 weeks

    High cost, short lead time supplier Cost = $250, Lead time = 1 week

  • 8/10/2019 Product Availability

    51/55

    Tailored Sourcing Strategies

    Fraction of demand from

    overseas supplier

    Annual Profi t

    0% $37,250

    50% $51,613

    60% $53,027

    100% $48,875

    T il d S i M lti l

  • 8/10/2019 Product Availability

    52/55

    Tailored Sourcing: MultipleSourcing Sites

    Characteristic Primary Site Secondary Site

    Manufacturing

    Cost

    High Low

    Flexibility(Volume/Mix)

    High Low

    Responsiveness High Low

    EngineeringSupport

    High Low

  • 8/10/2019 Product Availability

    53/55

    Dual Sourcing Strategies

    Strategy Primary Site Secondary Site

    Volume based

    dual sourcing

    Fluctuation Stable demand

    Product baseddual sourcing

    Unpredictableproducts,

    Small batch

    Predictable,large batch

    productsModel baseddual sourcing

    Newerproducts

    Older stableproducts

  • 8/10/2019 Product Availability

    54/55

    Setting Product Availability for MultipleProducts under Capacity Constraints

    Single product order

    Multiple product order

    Decrease the order sizeAllocating the products

    When ordering multiple products under a limited supply capacity,

    the allocation of capacity to products should be based on theirexpected marginal contribution to profits.

    This approach allocates a relatively higher fraction of capacity toproducts that have a high margin relative to their cost of

    overstocking.

    S tti O ti l L l f

  • 8/10/2019 Product Availability

    55/55

    Setting Optimal Levels ofProduct Availability in Practice

    Use an analytical framework to increaseprofits

    Beware of preset levels of availability

    Use approximate costs because profit-maximizing solutions are very robust

    Estimate a range for the cost of stocking

    out Ensure levels of product availability fit with

    the strategy