Procurement Risk Managementof

Flexible Pipes and Umbilicals

Presented by

Hanh Ha

Kuala Lumpur Convention Centre

9th June 2010

Page 3: Procurement Risk Management - Subsea UK

Content

• Who are BPP-TECH?

• SURF Procurement – What is it about.

• How and where do we control quality?

• Why do we need to control quality?

• Lessons-learnt and how we deal with it...

Page 4: Procurement Risk Management - Subsea UK

Company Overview

BPP-TECH provides specialist engineering, research and product development services to the offshore hydrocarbon and marine industries.

• Company formed in 1981

• Offices in London, Houston and Aberdeen

• Staffed by experienced, highly qualified engineers

• Operating worldwide

Page 5: Procurement Risk Management - Subsea UK

Company Overview

• Analysis & review of subsea architecture:flexible pipes, risers, umbilicals, power cables, flowlines and moorings

• product development & joint industry projects (JIP)

• procurement support, production advice & client representation

• concept and feasibility studies for floating offshore systems

• offshore monitoring and instrumentation

• insured risk and failure analysis

Page 6: Procurement Risk Management - Subsea UK

SURF Procurement

• SURF – Subsea Umbilical, Risers & Flowlines

• The reliability of the subsea production system from the mudline to the sea surface is critical to production in terms of control and flow assurance

• Subsea system components are often safety critical

Page 7: Procurement Risk Management - Subsea UK

SURF Procurement

• There is a history of defects and incorrect designs leading to significant losses

• The majority of field failures relate to manufacturing defects passing through inadequate QA/QC systems

• Ready acceptance of manufacturer’s non-conformance reports in the face of schedule and cost pressures

• FAT - Factory acceptance testing does not ensure long term reliability

• Use of inappropriate procedures and equipment encountered during installation

Page 8: Procurement Risk Management - Subsea UK

Quality Control

• How and where do we control quality?

• Specification

• Design & analysis

• Material procurement

• Manufacturing

• Packing and loading

• Mobilisation & offshore installation

Page 9: Procurement Risk Management - Subsea UK

Design and Analysis

• Prediction of strength, internal strains and service lives

• Global hydro-elastic structural response calculations

• Local nonlinear structural analysis

• Analysis of designed and as-built structures

Finite element meshDeepwater optical fibre cable

Page 10: Procurement Risk Management - Subsea UK

Analysis of Flawed Design

Finite element analysis of the deepwater optical fibre cable

Page 11: Procurement Risk Management - Subsea UK

Qualification Testing

Laborious but often necessary qualification testing– Rotational and Reel Loading Tests

Page 12: Procurement Risk Management - Subsea UK

Qualification Testing

Failure of separators in a deepwater umbilicaldue to crush loads from bending on a reel

Page 13: Procurement Risk Management - Subsea UK

Raw Material Supply

Rejected tensile armouring wires from the sub-suppliers

Page 14: Procurement Risk Management - Subsea UK

Raw Material Supply

Wire defects found on “Approved” wire stockfrom the sub-suppliers

Page 15: Procurement Risk Management - Subsea UK

Umbilical Failure

In-service umbilical thermoplastic hydraulic hose rupture

Page 16: Procurement Risk Management - Subsea UK

Umbilical Failure

Kidney-shaped hose cross-section at failure location

Page 17: Procurement Risk Management - Subsea UK

Umbilical Failure

Damage during production – inadequate setup quality control

Page 18: Procurement Risk Management - Subsea UK

Flexible Pipe Manufacture

Extrusion problem due to inadequate QA/QC procedures

Page 19: Procurement Risk Management - Subsea UK

Flexible Pipe Manufacture

Resulting extrusion defect– irregular sheath thickness

Page 20: Procurement Risk Management - Subsea UK

Remedial Procedure

Permanent change in underlying tape securing procedure

Page 21: Procurement Risk Management - Subsea UK

Inner Surface

Outer Surface

~ 5mm

Crack notch in pressure sheath

Manufacturing Feature

Page 22: Procurement Risk Management - Subsea UK

Close-up of notch

Manufacturing Feature

Page 23: Procurement Risk Management - Subsea UK

In-Service Crack

In-service crack propagation from manufacturing feature

Page 24: Procurement Risk Management - Subsea UK

End Fitting Failure

End fitting dissection to determine root cause of failure

Page 25: Procurement Risk Management - Subsea UK

End Fitting Failure

Incorrect dimensional control on critical components

Page 26: Procurement Risk Management - Subsea UK

Creep under pressure into un-supported sheath location

End Fitting Failure

Page 27: Procurement Risk Management - Subsea UK

Packing & Loadout

Inadequate packing procedure at factory leading to a near-miss offshore

Page 28: Procurement Risk Management - Subsea UK

Mobilisation Issues

Improper weld during sea-fastening operation during mobilisation

Page 29: Procurement Risk Management - Subsea UK

Mobilisation Issues

Inadequate loadout planning – Last-minute welding of deck covers to main deck on the transport vessel during mobilisation!

Page 30: Procurement Risk Management - Subsea UK

Mobilisation Issues

Inadequate mobilisation planning that could have led to over-bending of riser during loadout

Page 31: Procurement Risk Management - Subsea UK

Mobilisation Issues

Requiring “on-the-ground” intervention to rectify problem

Page 32: Procurement Risk Management - Subsea UK

Mobilisation Issues

Panoramic view of “on-the-ground” solution to over-bending problem

Page 33: Procurement Risk Management - Subsea UK

Mobilisation

Detailed planning required for mobilisation of SURF components

Page 34: Procurement Risk Management - Subsea UK

Installation Issues

All set and ready to go...

Page 35: Procurement Risk Management - Subsea UK

Installation Issues

Inappropriate installation planning leading to “on-the-ground”

improvisation to make things work!

Page 36: Procurement Risk Management - Subsea UK

Installation Issues

Pipe alignment issues – Mid-line connection the brute force way...

Page 37: Procurement Risk Management - Subsea UK

Installation Issues

Notice the vessel main crane on the starboard side?

Page 38: Procurement Risk Management - Subsea UK

Installation Issues

... or use the laws of physics to make life simpler!

Page 39: Procurement Risk Management - Subsea UK

Offshore Failures

Inadequate installation planning leading to...

Page 40: Procurement Risk Management - Subsea UK

Offshore Failures

Buckled pipe Kinked cable

Page 41: Procurement Risk Management - Subsea UK

Offshore Failures

Some failure modes are totally unforeseen!

Page 42: Procurement Risk Management - Subsea UK

Lessons-Learnt

• What do we do with all the lessons-learnt?

• Feed lessons-learnt back into new SURF programmes

• Apply lessons-learnt into other forms of procurement processes

New Project

Lessons-LearntFailures/Near-misses Better Procedures

Page 43: Procurement Risk Management - Subsea UK

Lessons-Learnt

• Make use of lessons-learnt to enhance the development of new technologies...

• Cryogenic transfer hoses for the LNG market

• High capacity dynamic power cables for very long and

deepwater offshore applications

Page 44: Procurement Risk Management - Subsea UK

New Technologies

10-year development programme for the Lloyds Type-Approved Dynamic Cryogenic Offshore Transfer Hose

Page 45: Procurement Risk Management - Subsea UK

New Technologies

High capacity dynamic power cable development programme currently undergoing strenuous testing for qualification

Page 46: Procurement Risk Management - Subsea UK

Questions?

Thank You

For

Your Attention!