Processing Major Repair Application from DSS School REO’s Perspective 1.

12
Processing Major Repair Application from DSS School REO’s Perspective 1

Transcript of Processing Major Repair Application from DSS School REO’s Perspective 1.

Page 1: Processing Major Repair Application from DSS School REO’s Perspective 1.

Processing Major Repair Application from DSS School

REO’s Perspective

1

Page 2: Processing Major Repair Application from DSS School REO’s Perspective 1.

Underlying Principles

Provision for minor repairs costing $2M or below is included in the existing DSS subsidy.

To ensure students and staff’s safety, schools should take prompt action to carry out minor repairs.

2

Page 3: Processing Major Repair Application from DSS School REO’s Perspective 1.

Don’ts in MR Application

Not to include the non-school portion / F&E items in the application such as boarding annex, curtains of special rooms, etc.

Not to include repair / alteration items for above standard facilities built by the school using own fund such as auditorium

Not to include the duplicated items of the previously approved projects

3

Page 4: Processing Major Repair Application from DSS School REO’s Perspective 1.

Don’ts in MR Application

Not to apply for above-standard repair / alteration items such as CCTV system, air-conditioning system/units in assembly hall, etc.

Not to include routine maintenance work to existing slopes such as clearing of slope’s surface, channel and tree management.

4

Page 5: Processing Major Repair Application from DSS School REO’s Perspective 1.

Checklist for Application

Up-dated drawings for each application item attached

Cost breakdown of the estimated costs of the proposed work with full justification and description

Warranty of re-roofing to the premises is required if works involve re-roofing to the premises

5

Page 6: Processing Major Repair Application from DSS School REO’s Perspective 1.

Checklist for Application

Prior approval / approval in principle from relevant departments is required for works involving structural alterations

Inspection, load and insulation test report is required for works involving complete rewiring works

6

Page 7: Processing Major Repair Application from DSS School REO’s Perspective 1.

Justifications / Informationto be provided by schools

External-redecoration (including painting work to external wall, replacement work of external wall tiles) – to provide the year of last approval and the conditions involving safety, material of wall paint to be used, etc.

Replacement of air-conditioners – to provide supporting documents that the air-conditioners have been provided by EDB, e.g. under noise abatement programme.

The school’s representative attending the site inspection conducted by ASD & EDB should be familiar with the details of application items and be able to answer the queries raised in the site inspection.

7

Page 8: Processing Major Repair Application from DSS School REO’s Perspective 1.

School’s Actions after Approval for MR Application

Prepare tender documents for appointing architectural / QS consultants

Submit the tenderer list and draft tender documents to EDB with copy to ASD for comments / advice

8

Page 9: Processing Major Repair Application from DSS School REO’s Perspective 1.

School’s Actions after Approval for MR Application

Incorporate the comments from ASD on the tenderer list / draft tender documents and issue tenders to those tenderers who have expressed interest

Propose appointment of architectural / QS consultants with recommended fees to EDB for approval

9

Page 10: Processing Major Repair Application from DSS School REO’s Perspective 1.

School / AP’s Actions on Appointment of Contractor

Prepare tender documents Submit the tenderer list and draft tender

documents to EDB with copy to ASD for comments / advice

Incorporate the comments from ASD in the tender

Propose the contractor with recommended fees to school / EDB / ASD for comments / approval

10

Page 11: Processing Major Repair Application from DSS School REO’s Perspective 1.

School’s Roles after Approval Closely monitor the work progress of AP /

contractor to ensure prompt completion of approved works

Inform EDB of the cashflow requirement for the approved MR work in subsequent financial years

Provide justifications for the unspent cashflow of the financial year(s) where necessary

11

Page 12: Processing Major Repair Application from DSS School REO’s Perspective 1.

Reimbursement of Claims

Subsidy approved will be reimbursed upon school’s submission of claims with receipts / presentation of school’s certificate / AP’s certificate

12