Process Characteristics Commercial-scale Oxygen Furnace ...Experimental Blast Furnace Equipment...

10
ISIJ International, Vol, 32 (1 992), No. 7, pp. 838-847 Process Furnace Characteristics of Process with Shaft a Gas Commercial-scale Oxygen Blast Injection Yotaro OHN0.1) Masahiro MATSUURA.2) Hiroyuki MITSUFUJ13) and Takeshi FURUKAWA2) Researchand Development Division. N KK Corporation, 1 ) Planning and Coordination Dept.. Maru-no-uchi. Chiyoda-ku, Tokyo, 100 Japan. 2) Steel Research Center, Minamiwatarida-cho. Kawasaki-ku. Kawasaki, Kanagawa-ken, 210 Japan. 3) Steel Division. Fukuyama Works. NKK Corporation, Kokan-cho. Fukuyama. Hiroshima-ken, 721 Japan. (Received on March l7. 1992; accepted in final form on March 19. 7992) A newoxygen blast furnace process, which is characterized by the injection of preheating gas into the shaft, was developed. For the development of the process, operation tests using an experimental blast furnace were carried out, and proved this process to be applicable as an ironmaking process. Mathematical model simulations were also carried out and the process characteristics were clarified on a commercial scale, in comparison with those of a conventional hot blast furnace process, Through the analysis of the experimental blast furnace operation and the mathematical model simulations, this process was found to have the following characteristicsi (1 ) Heating-up and reduction of burden assured throughout the furnace by means of the preheating gas injection. (2) Appropriate preheating gas, in which the low fuel rate is realized, is the range of preheating gas flow rates corresponding to thermal flow ratio in the upper part of 0.74-0.90 and the range of temperatures 600-1 200'C. (3) The preheating gas composition has little influence on the reduction in the lower part. (4) The position of preheating gas injection is adequate in the upper shaft as long as the heat transfer is secured. (5) Operational fuel rate range is wide; 500kg/t(with preheating gas)-1 200 kg/t(without preheating gas). KEYWORDS: ironmaking; blast furnace; oxygen; preheating gas injection; pulverized coal; experimental blast furnace; mathematical model; fuel rate; productivity; Iow shaft furnace, 1. Introduction Recently, greater operational flexibility is required for the blast furnace operation; for example, intensive pulverized coal injection or a higher production rate. However, an advanced improvement in the blast fur- nace process fulfilling these requirements has not yet been developed. Although several attempts have also been madeto d. evelop a new ironmaking process,1'2) there is no process which replaces the blast furnace process at present. Theauthors have proposed the 'Oxygen Blast Furnace Process'.3~7) The process is based on the blast furnace process and characterized by blowing room ternperature oxygen through the tuyeres with a high coal injection rate and by injecting preheating gas into the upper shaft. In the process, the burden is heated up to a temperature above which gaseous reduction proceeds by•injecting preheating gas and high reducing potential of bosh gas generated from the oxygen blast is effectively used. The process was verified through experimental blast furnace operations.3~5) The heating-up and reac- tion characteristics of the process were also studied using a mathematical model.6) In this paper, the outline of the fundamental concept, the advantages of the process and results of the verification of the process through an experimental blast furnace operation are described. The estimated results of the operating conditions for a commercial oxygen blast furnace, that are the appropriate conditions for the preheating gas injection, productivity, the fuel rate range and the lowering of the furnace height, are also reported. 2. Outline of Concept and Advantages of tbe Process Durrer8) noted the advantages of the oxygen blast fur- nace were as follows. The top gas temperature decreas- ed because of the low bosh gas flow rate and therefore thermal efficlency was improved. The reduction rate increased because of the high reducing gas concentra- tion and the furnace height could be lowered. As a result, Iow grade materials could be used. Following that, a test operation with a high oxygen enriched hot blast was carried out using a low shaft experimental blast furnace in Europe.9) However, several operating C 1992 ISIJ 838

Transcript of Process Characteristics Commercial-scale Oxygen Furnace ...Experimental Blast Furnace Equipment...

  • ISIJ International, Vol, 32 (1 992), No. 7, pp. 838-847

    Process

    Furnace

    Characteristics of

    Process with Shafta

    GasCommercial-scale Oxygen BlastInjection

    Yotaro OHN0.1)Masahiro MATSUURA.2)Hiroyuki MITSUFUJ13)and Takeshi FURUKAWA2)

    Researchand DevelopmentDivision. NKKCorporation, 1)Planning and Coordination Dept.. Maru-no-uchi. Chiyoda-ku,Tokyo, 100 Japan. 2) Steel Research Center, Minamiwatarida-cho. Kawasaki-ku. Kawasaki, Kanagawa-ken, 210Japan. 3) Steel Division. FukuyamaWorks. NKKCorporation, Kokan-cho. Fukuyama. Hiroshima-ken, 721 Japan.

    (Received on March l7. 1992; accepted in final form on March 19. 7992)

    Anewoxygen blast furnace process, which is characterized by the injection of preheating gas into theshaft, was developed. For the development of the process, operation tests using an experimental blastfurnace were carried out, and proved this process to be applicable as an ironmaking process. Mathematicalmodel simulations were also carried out and the process characteristics were clarified on a commercialscale, in comparison with those of a conventional hot blast furnace process,

    Through the analysis of the experimental blast furnace operation and the mathematical model simulations,this process wasfound to have the following characteristicsi

    (1 ) Heating-up and reduction of burden assured throughout the furnace by meansof the preheatinggas injection.

    (2) Appropriate preheating gas, in which the low fuel rate is realized, is the range of preheating gasflow rates corresponding to thermal flow ratio in the upper part of 0.74-0.90 and the range of temperatures600-1 200'C.

    (3) The preheating gas composition has little influence on the reduction in the lower part.(4) The position of preheating gas injection is adequate in the upper shaft as long as the heat transfer

    is secured.(5) Operational fuel rate range is wide; 500kg/t(with preheating gas)-1 200kg/t(without preheating

    gas).

    KEYWORDS:ironmaking; blast furnace; oxygen; preheating gas injection; pulverized coal; experimentalblast furnace; mathematical model; fuel rate; productivity; Iow shaft furnace,

    1. Introduction

    Recently, greater operational flexibility is requiredfor the blast furnace operation; for example, intensivepulverized coal injection or a higher production rate.However, an advanced improvement in the blast fur-nace process fulfilling these requirements has not yetbeen developed. Although several attempts have alsobeen madeto d. evelop a new ironmaking process,1'2)there is no process which replaces the blast furnaceprocess at present.

    Theauthors haveproposed the 'Oxygen Blast FurnaceProcess'.3~7) The process is based on the blast furnaceprocess and characterized by blowing roomternperatureoxygen through the tuyeres with a high coal injectionrate and by injecting preheating gas into the uppershaft. In the process, the burden is heated up to atemperature above which gaseous reduction proceedsby•injecting preheating gas and high reducing potentialof bosh gas generated from the oxygenblast is effectivelyused. The process was verified through experimentalblast furnace operations.3~5) The heating-up and reac-tion characteristics of the process were also studied

    using a mathematical model.6)In this paper, the outline of the fundamental concept,

    the advantages of the process and results of theverification of the process through an experimental blastfurnace operation are described. The estimated resultsof the operating conditions for a commercial oxygenblast furnace, that are the appropriate conditions forthe preheating gas injection, productivity, the fuel rate

    range and the lowering of the furnace height, are alsoreported.

    2. Outline of Concept and Advantagesof tbe Process

    Durrer8) noted the advantages of the oxygenblast fur-

    nace were as follows. The top gas temperature decreas-ed because of the low bosh gas flow rate and thereforethermal efficlency was improved. The reduction rateincreased because of the high reducing gas concentra-tion and the furnace height could be lowered. As aresult, Iow grade materials could be used. Followingthat, a test operation with a high oxygen enriched hotblast was carried out using a low shaft experimentalblast furnace in Europe.9) However, several operating

    C 1992 ISIJ 838

  • ISIJ lnternational, Vol.

    problems, such as the insufficient heating-up andreduction of burden, hanging and channeling arose. Asa result, the process could not be sufficiently developed.Whenthe oxygen content is increased in the hot blastoperation, the bosh gas flow rate decreases and thethermal flow ratio increases. Therefore, the heating-upof the burden becomesinsufficient. Miyashita et al.10)made these phenomenaclear using an experimentalbast furnace. Fewtests have been successfully carriedout using oxygen with a concentration of less than50 o/o.1 1~ 13) These test operations were carried out with

    a high fuel rate. Therefore, the thermal flow ratio waslow, and the thermal shortage in the shaft camenotto be a problem. Recently, Wartmann,i4) Lu andKumar,Is) Qin and Yangl6) and Finkl7) have studiedthe oxygen blast operation. In these studies, as acountermeasure for the thermal shortage in the shaftcaused by the high oxygen content blast, the top gasinjection into the tuyere or the reducing gas injection atthe lower shaft or the bosh level were discussed usingmaterial and heat balance models,

    Figure I shows the fundamental concept and advan-tages of the proposed oxygen blast furnace process.The basic constitution of the process is that normaltemperature oxygen is blown into the tuyeres and thepreheating gas is injected into the upper shaft. Hotstoves are not necessary. The intensive pulverized coalinjection is possible and the coke rate can be reduced.With the oxygen blast, the bosh gas flow rate is so lowthat the preheating gas injection into the upper shaftimproves the temperature profile in the furnace. Thethermal reserve zone temperature (TR) is determined bythe coke reactivity in the conventional blast furnace atabout 950-1 OOO'C.In the process, TRcan be controlledby the preheating gas flow rate and temperature, andthe operation over a wide range of fuel rates is possible.As the concentration of reducing gas in the bosh gas ishigh, the gaseous reduction rate is high. Productivity

    can be increased because of the low bosh gas flow rate.As the heating-up of the burden is similar to that inthe hot blast operation by using the preheating gasinjection, the direct reduction rate is decreased and thereducing time is shortened. As a result, the furnaceheight can be lowered and the coke strength can bereduced.

    Tf contral Tf control 9as injectian

    32 (1992), No. 7

    3. FundamentalCharacteristics of the Process

    In order to understand the fundamental character-istics of the process, the operating conditions werestudied using a material and heat balance model, andthe characteristics of the heating-up and of the reactionprogress in the furnace were estimated using a one-dimensional mathematical model. The estimated resultswere partially reported in the previous paper.?)

    In analysis by meansof the material and heat balancemodel,4) the furnace is divided into two parts-aboveand below the preheating gas injection level-and thematerial and heat'balances are calculated in each part.According to the estimated results, a thermal shortagein the shaft is avoided through the preheating gas ,in-jection into the upper shaft.

    The one-dimensional model is similar to the onespresented by Taguchi et a/.18) and Hatano et al.i9)According to results estimated by applying the model tothe process, the burden is heated up to about 700'Cat the preheating gas injection level, an'd once theheating-up of the burden stays below the injection level,and the burden is sufficiently heated before it reachesthe tuyere level. The reduction is faster in' the lowertemperature region comparedto the hot blast operation,so the direct reduction rate is smaller.

    Figure 2 shows the effect of the preheating gastemperature (TH) on the thermal reserve zone tempera-ture (TR) and the direct reduction rate (Yd: the numberof oxygen atoms that combined with carbon in thedirect reduction20)). In the figure, VHis the preheatinggas injection rate, CRthe coke rate and PCRthepulverized coal rate. TR is mainly determined by thereactivity of coke in the conventional hot blast opera-tion, but is controlled by TH in the oxygen blastoperation. Yd is about 0.5 in the hot blast operations,while it is about 0,I~).2 in the oxygen blast operationsbecauseof the large gaseous reduction.

    Fromthe aboveanalysis, realization and fundamentalcharacteristics of this process could be estimated.

    O

    Q:F

    1200

    1ooo

    xygen blast Coal injection rate increase

    LoN, bosh gas fiow rate Productivity increaset

    Thermai shortage in upper shaft

    Preheating gas injection

    Cotrolable TR - Enlarged fuel rate rangeHigh Pco, Iow PN2 Si and N in hot metal decreaset

    High gaseous reduction rate Direct reductiQn rate deoreaset

    Coke degradation decrease

    Low furnace height - Usabi I itY of weak coke

    Fig. 1. Concept and advantages of OXygenblast furnaceprocess.

    800

    600

    YdHot blast

    l- -- - - -TR Hot blast

    Oxygen blastCR 290kg/tPCR300kgltVH 260Nmqlt

    Ti

    Yd

    0.6

    0.4

    o.2

    )~1:

    Fig. 2.

    800 O1OOO 1200TH ('C )

    Effect of preheating gas temperature (TH) on solidtemperature at thermal reserve zone (TR) and directreduction rate (Yd).

    839 C 1992 ISIJ

  • ISIJ International, Vol. 32 (1992), No. 7

    4. Verification of the Realization of the OxygenBlast Table I showstypical examplesofthe operating results.Furnace Process through the Experimental Blast (1) Analysis of Material and Heat BalancesFurnace Operations Table I and Fig. 3show the analytical results of the

    Experimental blast furnace operations were carried test operation. The necessary heat was almost theout and the process realization could be verified. The same in the hot blast operation (Period I) and theoperational and analytical results are described below. oxygen blast operation (Period II). In Period 111, in

    4.1. Experimental Blast Furnace EquipmentWhichpulverized coal was injected at a rate of 320kg/t,the necessary heat decreased greatly and the fuel rate

    An outline of the experimental blast furnace is as also decreased. This is the r~ason why the steam injec-follows; inner volume 3.9m3, hearth diameter O.95mc tion was stopped in order to maintain the theoreticalthroat diameter 0.7mc, distance from throat to tuyere flame temperature (Tf)' In Period IV, in which produc-5.1 mand to the preheating gas injection level I .5m, tion increased to 20 t/d, although Yd increase comparedthree blast tuyeres, and three preheating gas tuyeres. to the Period 111 because the residence time of theThepreheating gas wasprepared by burning LPGwith burden in the furnace decreased, the necessary heat andoxygen and diluting it with N2 or steam. A typical the fuel rate (FR) decreased because of the decreasedcomposition of the preheating gas was CO=2.2"/., heat loss.C02=7,1o/o, H2=0.1o/o, H20=9.60/0 and N2=81 ~/.. Figure 4shows the relationship between Yd and FR.Both the oxygen blast operation and the hot blast In both the hot blast and the oxygenblast operation, Ydoperation were carried out. After the blow-off opera- decreased with the increase in FR. It is considered thattion, which was similar to the period 111 operation in the gaseous reduction rate became larger with theTable 1, the furnace was quenchedwith nitrogen, and increase in the reduction gas flow rate. WhenFRwasore samples were taken from a shaft part. The lower 650kg/t, Yd Wasabout O.45 in the hot blast operation,part of the furnace was fixed with resin for observation but in the oxygen blast operation. Yd Waslow, aboutand analysis. 0.2.4.2. Experimental Operation Results and Analysis (2) preheating GasInjection and Thermal Flow Ratio

    Continuous operations for one and a half months Figure 5shows the relationship between the thermaleach were carried out. The operations were very stable. flow ratio (U) and FR. In calculating U, all specific heat

    Tabte l. operating resuhs of experimental blast turnace.

    I n m rvPeriodHot blast Oxygenblast

    Production (t/d)Cokerate (kg/t)Pulverized coal rate (kg/t)Fuel rate (kglt)

    9.9668

    o668

    l0.7800

    O800

    12.0352320672

    20.0362285647

    Blast Rate (Nm3/t)Temperature ('C)

    l 530885

    o o o

    Oxygenrate (Nm3/t)Steamrate (kg/t)Flame temperature ('C)

    39O

    238 l

    450190

    2705

    383o

    2726

    357o

    2709

    Preheating gas Rate (Nm3/t)Temperature ('C)

    o 670l 019

    530988

    370l 007

    Top gas COIC02(-)Temperature (*C)

    l.38

    2571.41

    187l,lO

    226l.14

    183

    Metal Temperature ('C)C(~/.)Si ('/,)

    Mn('/,)P("/.)S("/.)

    14604.262.35

    O. 240,1210.033

    l 4093.960.960.22O. I150.079

    14184.271,31

    0.21O, 1230.053

    l 4484.37l,150,28O, 1340.049

    Slag Temperature ('C)Rate (kg/t)CaO/Si02()FeO('/,)S('/.)

    l 501324

    l.150.750.931

    l 424362

    1.07l .040.921

    l 481345

    1.120.930.918

    l 478340

    l.16l.300.846

    TR ('C)Shaft efficiency (-)Yd (-)Solution loss carbon (kglt)Heat loss (kcal/t)

    950O.800.50

    lO0.438.9 x 104

    7100.720.06

    13.043.9 x 104

    6500.790.19

    38.838.5 x 104

    7600.8 l0.27

    54.927.7 x 104

    Heat flow ratio (-) in upper partin lower part

    o.80o.80

    0.791.14

    0.74

    l .050.84

    l .09

    C 1992 ISIJ 840

  • ISIJ International. Vol. 32 (1 992), No. 7

    P : Production g : GasCR : Coke rate s : SolidPCR: Pulverized coal rate

    - FR : Fuel rate*\- 250'oo~~ 200e>

    150

    *~:: 100c~::c7

    ~ 50,Uq)

    =:

    - 250*\CD

    o 200~~~oC150>~•- 100~~,~'~ 50,g'D 3000 2000 1OOO O3000 2000 1OOO=:

    Tempera tu re (~) ) Tempera tu re (~) )Fig. 3. Reichardt's diagrams for some typical periods of

    experimental operation.

    I Hot blast ll. OxygenbIasto P =9. 9t/d=668kg/t PCR CR

    =1 O. 7t/d= 800kglt

    o PCR= Okg/t PCR= Okg/tFR =668kg/t FR 800kglto

    g OLO g IIo

    I,Y)UF)

    s :TR:' 950

    s

    o710 I

    o~l. OxygenbIast rv. Oxygenbiast

    o P =12. Ot/d= 352kg/t

    PCR CR

    =20. Ot/d= 362kg/t

    o PCR=320kg/t PCR=672kg/t

    285kg/tFR FR 647kg/t

    o

    o gI,NI- g ls l-

    650 ,S 1~;

    o7601~

    05

    o

    oS~a

    ~~

    ~Q)

    ~

    l.2

    l .o

    A ~~-\Hot blast

    ~~A_~

    0.8

    04

    03I

    ~ 02>

    ol

    o

    A

    e\e

    dbe ee \)!geTID'~~0xygenblast

    e

    \600 700 Boo

    Fuel rate (kg/t)

    Fig. 4. Relation between direct reduction rate (Yd) with fuelrate.

    values were based on values at 500'C. Thecompositionand the flow rate of the solid and the gas were based onvalues at the throat. Only in calculating Uin the lowerpart in the oxygen blast operation, the gas flow rate inthe lower part wasobtained by subtracting VHfrom thegas flow rate at the throat. In the oxygen blast opera-tion, Uis high in the lower part, while it decreases inthe upper part with the injection of the preheating gasto a value simllar to that in the hot blast operation. Inthe oxygen blast operation, whenTf rs lowered and FRis as high as 900kg/t, and as Udecreases to about 0.8,the operation maybe possible without the preheatinggas injection. As in the data of Okamotoet al.12) andthe Bureau of Minesi3) shownin Fig. 5, whenthe ox-ygen content is low, the limit of Uis seen to be lower.(3) Pulverized Coal Injection Rate

    The increase in PCRwas accompanied by thedecrease in the steam rate in order to maintain TrThen FRwas markedly lowered. In Period 111, wherePCRwas 320kglt (PC(kg)/02(Nm3)=0.84). Whenthe

    0.6

    A in upper part : Hot blast}O in lower parte in upper part Oxygen blastPCR(kg/t)

    All coke

    320Calculated

    260

    :lPCR300kg/tJ

    _ 02 100%Tf 27001C~ 2200IC

    \

    \---

    All coke\ 02 40, 600/0

    Tf 2200 'C

    \ \\ Tf\ 2700~C\ \

    A~~__~~--. 2200~C

    .~A 02 600/0 ~+ ++__.400/0 ~3~+A

    cl (AII coke, 02 550/0, Tf22001C)12)(AII coke, 02 37Q/o, Tf22001C)13)

    500 600 700 800 900 Iooo

    F**1 *at* (kg/t)

    Flg. 5. Relation of thermal fiow ratio with fuel rate.

    steam was cut off, FRwas 672kg/t and Tf was about2700'C. After Period 111, in order to investigate thereplacement ratio, PCRwas increased and the coke rate(CR) was gradually reduced, while keeping the oxygenflow rate constant. Tf decreased with the increase of thePC/02 ratio, but the replacement ratio was constantuntil after PCR=363kg/t (PC(kg)/02(Nm3)=0.94).Abovethis value, the replacement ratio worsened.(4) Productivity

    In Period IV, it was possible to continue a stableoperation up to 20.0t/d production (productivity5.1 t/m3/d). It seemedthat the production rate could beincreased further, but this was at a maximumdue totapping work restriction.

    (5) In-furnace ConditionFrom the measured results of the temperature and

    the gas composition in the furnace, the thermal reservezone was observed at about 950'C in the case of thehot blast operation. WhenTH Wasabout IOOO'CandVHWasabout 500Nm3/t, in the case of the oxygenblastoperation (Period 111), the gas temperature at theinjecting level was as low as about 700 'C. This almostagrees with the mathematical modelestimation.7) WhenVHWasincreased, the temperature rose in all sectionsabove the injection level. This showsthe preheating gasinjection has an effect on the whole horizontal section.

    Figure 6shows the temperature distribution and thegas composition in the blow-off operation, and thedistribution of the reduction degree of sinter taken afterblow-off. Eventhough the temperature in the lower partof the shaft was less than 800'C, the reduction degreewasrather high-more than 90 "/o . It wasconfirmed thatthe gaseous reduction rate was higher in the oxygenblast operations. Figure 7 shows in-furnace situationsin the dissected lower part. The ore was completelyreduced before melting, and melted downrapidly abovethe raceway region. A so-called cohesive zone did notexist. It is believed that the softening temperature of the

    841 C 1992 ISIJ

  • ISIJ International, Vol. 32 (1992). No. 7

    TempfoC) C02+H20CO+C02+ H2+H20

    Reduction degreeafter blow-off (Q/o)

    Table 2. Basecondition of simulations.

    l~= - - -

    l*.

    ~'~~~E

    600 700

    ..

    ~"

    ~oo

    700

    0'3

    0,03

    >~'Is~~~~~

    '~"

    1500

    ~1'77~'...

    '"j!~\"

    If'A':t

    9711

    Melting jline l

    Stock level

    c

    tttl

    Preheating gas

    I.

    Ilil

    I I,

    ,..__ d~,

    l

    tLI~~!1~~~;;~:i{~,~f8{O~~~9~~~~O}i7'1l~~\~~)

    \LI I

    /'\:,~;

    Tuyeret v'r!'7 '{~E~Itl Dead"";$ :,l l man :t Il -----.;'- JJ L Tap hole

    Fig. 6.

    Melting

    sta9 Metaj lb~J500 mm

    Distribution of gas temperature' gas composition andreduction degree of sinteri

    Initial Reductionprofile

    Sinter (miXed with Coke) Degreel

    ::iltiLi~:'F~_:~~:'1~~'l'~~u'rJ

    '~~: ~tL ~t'~1'~~:T~:~~~':.~L~~~~\~!r'l~{7T1

    /\4 I(~i\1~~/~b

    {;::~C~iI~P~:~~~;~i,:~:{;r~~i;rig970jo

    L

    ,

    l~ ilLine

    l 1800 J~!"_'1'

    L1 "/ Tuyerel 1900

    :~"I Raceway/I'r)~r:7>~J~'t

    ' I

    Dead Man195AO~ip

    l

    I

    ':'/2;~;:/(/i:

    L~,-

    Eq,>cl,

    (1'

    ,1)

    >=FE:

    o~JJC:~O

    .~;

    I

    Cokerate CR(kg/t)Pulverized coal rate PCR(kg/t)Fuel rate (kg/t)

    Flame temperature Tf ('C)Blast rate (Nm3/t)Oxygenin blast ('/*)Tf control gas species

    rate (Nm3/t)Boshgas rate (Nm3/t)

    temperature ('C)

    CO(~/*)H2 ('/,)N2 ("/.)

    Preheating gas rate VH(Nm3/t)temperature TH('C)oxidation degree nH (-)injection level ZH(m)

    250

    3OO550

    2600292

    99.5

    Topgas46

    865

    210081.717.5

    0.8

    300

    l OOOO.727.5

    Slag

    25

    20

    15

    10

    5

    O

    ~~~e*.'

    \ \ "I\ ' ~,lL,\ \t l,'\".~ ..,,'\L'e!

    \ ..:i,. ..

    d~\"' ~.\~ .

    .~~b

    \\

    ~~~\\~ \a

    ~\

    CR 250kg/tPCR 300kg/tTf 2600=C

    TH IOOO'C~H O, 72

    ~'~.

    VH(Nm3/t)

    a: Ob: 100

    c: 200

    d: 300

    e: 400f: 600

    ~\. f1,,~

    t'

    Reduction

    \ \, :~~\~ "'~.., * e~ ~

    d e~ \ei\ ~\.c :f \ bb: \hSolution'\~\

    : Ioss--- a

    Metal

    500mm

    In-furnace situations and coke temperature distribu-tion in the dissected lower part.

    Fig.

    O 500 1OOO 1500 2000 O 50 1OOSolid temperature ('C) Reaction degree (%)

    8. Effect ofpreheating gas flow rate (VH) on longitudinaldistribution of solid temperature and reaction degree.

    Fig. 7.

    ore rose becauseof the fast reduction rate. The size andthe porosity of coke changed little from the furnace topto the raceway. This corresponds with the low solution10ss rate. Gaspermeability in the dead manmight havebeen good judging from the temperature distributionmeasuredby the graphitization of coke samples.

    5. Estimation of the Operating Conditions of the

    OxygenBlast Furnace on a CommercialScale

    Thesignificant operating conditions to be investigatedfor a commercial oxygen blast furnace are as follows;

    use of preheating gas injection, productivity, fuel rate,and furnace height. These are discussed using one-and two-dimensional mathematical models. The two-dimensional model is similar to the one presented byKuwabaraet al.21) The model is an axially symmetricsteady-state model which considers the simultaneousprocess of the burden fiow, gas fiow, heat transfer, masstransfer and chemical reactions. The applicability of

    these models has been reported in the other papers.6,22)

    Basedon the typical operating condition of the oxygenblast furnace as shown in Table 2,6) someoperatingvariables are estimated. The blast furnace applied is

    NKK's FukuyamaNo. 4 blast furnace (inner volume;4288m3).5.1. Appropriate Conditions for the Preheating Gas

    In jection

    In order to investigate the appropriate conditions for

    the preheating gas injection in the shaft, the injected gasrate (VH), temperature (TH), composition and theposition of injection were varied, and the heating-upand the reduction progress were analyzed.

    (1) Rate and TemperatureFigure 8 shows the calculated results using a one-

    dimensional model with varied VH. As VH increases,

    Uin the upper part decreases, and the solid temperatureraises throughout the furnace. Therefore the reductionis accelerated. As a result, Yd decreases and the solidtemperature at the tuyere level (Tst) increases. Althoughthe rate of heating-up in the shaft increases whenVHis600Nm3/t, the reduction ability of gas decreases at the

    same time because of the decrease in the oxidationdegree of the FeO-Fe equilibrium gas composition.Therefore, the reduction slows down. Yd increases, and

    C 1992 ISIJ 842

  • ISIJ International, Vol. 32 (1 992), No. 7

    25\ VH 300Nm3/t\~ \ nH O, 72E- Ics' 20 l. I Reductlon:

    'dje:~iveecltion aTHjij)

    tll\~

    ,~:

    ~ I_

    >o\~g, \\~ i5 :IIc ~ db: 800 1>::' ' c: 1000 'd L .. :~.\~ l\ b ' ~•t~. d: 1200 ~\ e _E * , *.**. ~\e iO L~ \\\~\ bc~~;$~~~:j \.~'\ e: 1400~~ \~ ~~~ b :e \~_J::'ao~ 5 ~~R ~iijgg://~~tt \\\\\~.

    : ~\a :_Solutlon loss:i

    Tf xOO 500 1OOO 1500 2000 O 50 1OOReactlon degree (%)Solid temperature (C)

    Fig. 9. Effect of preheating gas temperature (TH) on longl-tudinal distribution of solid temperature and reactiondegree.

    preheating gas rate: 300Nm3/t

    .--"" go% reduction degree

    Top gas temperature ('O 195 229 243

    Stock level -- 200 Opreheat ing

    600

    injection *1OOO =

    1400 ~Q,

    ';!)

    i200lOOO800

    oTsh

    o-~- 600o Tgo ="~oh h400

    CR 250kg tPCR 300kg/t 200Tf 2600'C o1800

    f700

    ~ 02 + 11600 ~)

    \ / _\= 1 1500 ~~~0L>

    O 400 800 1200TH ('C)

    Fig. I l. Effect ofpreheating gas temperature (TH) on top gastemperature (Tg"), solid temperature at preheating

    gas injection level (T*h), direct reduction rate (Yd)and solid temperature at tuyere level (T*,).

    Metal temperature ('O 1519 1532 1538

    Preheating gas 800 1000 1200temperature (~O

    Fig, lO. Effect of preheating gas temperature (TH) on solidtemperature and reduction degree distribution in thefurnace,

    Tst becomesalmost constant. Fromthe simulated resultsusing the two-dimensional model, as an example is

    shownin Fig. 13, the preheating gas injected in the shaftflows in the vicinity of the furnace wall. Therefore the

    gas from the lower part flows in the direction of thefurnace center. As a result, the heating-up of burden issecured throughout the upper shaft.

    Figure 9 shows the calculated results using a one-dimensional model with varied TH. Whenthe tempera-ture is below I OOO'C,the heating-up and the reductionare delayed throughout the furance. Conversely, whenTH rises, the temperature near the injection level risesand the reduction is accelerated. However, when THraises to 1400'C, the reduction slows down and Ydincreases because of the restriction in the reductionequilibrium. Since the increase in the heat content ofsolid descending into the lower part counterbalances the

    heat required for the increased direct reduction, there is

    almost no change in the temperature distribution in the10wer part. This tendency is also seen in the changes of

    VH. Figure 10 shows the temperature distribution andthe position of 90 o/, reduction degree in the furnace

    with the two-dimensional model. Whenthe temperatureof injection gas of 300Nm3/t is varied in the range

    843

    of 80(~1 200'C, the heating-up and the reduction ac-celerate in both the upper and lower part, and the hotmetal temperature also rises. However, when TH isvaried from IOOOto 1200'C, there is a small heating-upin the upper shaft, but there is almost no effect on theheating-up at levels above I OOO'C, and there is noacceleration in the reduction rate in the lower part.These simulated results with one- and two-dimensionalmodels showgood agreement. This agreement found inthe simulated results using the different models indicatesthat these estimations are considered to be reliable.

    Figure ll shows the effects of TH on the top gastemperature (Tg"), the solid temperature at the pre-heating gas injection level (T*h), T*t and Yd. AlthoughTg" rises together with a rise in TH, Tg" is constant attemperatures over TH=600'C Changesin T T and. *h, **Yd in Fig. II are similar to the changes in VH.

    As mentioned-above, there is a range of VH andTH in which Yd is minimum. The gaseous reductionadvances at temperatures over about 500'C, and thesolution loss reaction at temperatures over about

    1OOO'C.Onthe other hand, the heating-up of burdensis decided by U and TH. Whenthe residence timeof burden between 500-1000'C is sufficiently longenoughand the reduction of ore is not restricted by thereduction equilibrium, the gaseous reduction advancespreferentially. As a result, the reduction degree issufficient before ore reaches a temperature at which thesolution loss reaction proceeds, so Yd reduces and Tstrises. Theappropriate values of VHand TH, in which YdandFRare low, are in the range corresponding to 0.74-0.90 of U in the upper shaft and at temperatures of600-1 200'C. This wide appropriate range indicates thatthis process can be operated stably at the low fuel rate.

    (2) CompositionFigure 12 shows the calculated results whenthe pre-

    heating gas composition is varied. Whenthe preheating

    C 1992 ISIJ

  • ISIJ International, Vol.

    gas composition is reducible (oxidation degree nn=0),the reduction rate is accelerated in the upper shaft, butthe effect is not so large throughout the whole furnace.In this process, the position of the preheating gasinjection is located in the upper part of the furnace,and the role of the gas injection is to heat the burdenup to not so high a temperature in which only the gase-ous reduction is accelerated and the solution loss reac-tion is not accelerated. Because, in addition to thesesituations, the reducing gas concentration in bosh gasis high, the effect of the preheating gas composition isconsidered to be small.

    (3) Position of InjectionPenetration of the gas injected into blast furnace

    stack is proportional to the ratio of injected gas to thetotal amountof inner gas, and infiuenced by the radialeddy diffusion of the gas and the radial distribution ofburden.23) Several processes which injected the reducinggas into the blast furnace stack were presented in thehot blast furnace process.24,2s) From the viewpoint ofthe penetration and the utilization of the reducing gasfor the reduction of ore in the process, it was reportedthat the gas should contain less C02and H20and hadto be heated above IOOO'Cand should be injected atbelow the thermal reserve zone.26) However, the role ofthe gas injection in the proposed oxygen blast furnaceprocess is to heat up the burden, as mentioned in theprevious section.

    Figure 13 shows the gas stream line and the distribu-

    25~ VH 300Nmslt.

    ~ TH 1000'C t Reduction- 20 \\~;> C02+H20~~ b ~H=C0+c02+H2+H20b \ b

    15~; l> a\ , aa: 0,72=~ .E b: O10 +-),.~_ :a='~; 5 CR 250kg/t ~Solution loss~oI PCR 300kg/t

    Tf 2600'C

    O ~ lO 500 1000 1500 2000 O 50 iOOReaction degree (%)Solid temperature ("C)

    Fig, 12, Effect ofpreheating gas composition on longitudinaldistribution of solid temperature andreaction degree.

    (G)(T)

    32 (1992), No. 7

    Isobalic line

    lOOO

    1400

    (G) (T)

    lOOO

    1400

    E

    (G) (T)

    :Gasstream: Solid temperature ('C):eoo/oReduction

    Stock

    tion of burden temperature and 90~/o-reduction degreewhen the position of the preheating gas injection isvaried from the upper part to the lower part of theshaft. Fromthe aspect of the gas stream line, the lowerthe injection level, the larger the penetration region ofthe injected gas in the furnace. However, from theviewpoint of heating-up, whengas is injected into theshaft at the distance, 3m, from the stock level, since theheat exchanging distance is short, the heat of injected

    gas is not sufficiently transferred to the burden, and Tg"rises. Whengas is injected at 9m, the heat of injectedgas is effectively utilized, and the heating-up of burdenin the upper part adequately promotes the reduction of

    ore in the lower part. Whengas is injected at 16m, itresults in a cooling downof the injected area bec~useof anincrease in the quantity of solution loss comparedto theinjection at 9m. From these estimations, there is anoptimumposition of preheating gas injection, which isconsidered to be the upper part of the shaft as long asthe sufficient heat transfer is secured.

    5.2. Productivity

    In this process, the bosh gas fiow rate is low com-pared to that of a hot blast furnace. Therefore, theflooding in the lower part of the furnace is not thesignificant factor in the restriction of productivity.

    Maximumproductivity in the process maybe deter-minedby the reduction of ore, the heating-up of burdenand the channeling of gas at the stock level. Simulationsof the oxygen blast operation and the hot blast onehave been carried out using a one-dimensional model,and varying the productivity. Figure 14 shows theresults. In the figure, the position is shown, where areduction degree of 90 o/o and a solid ternperature of

    1400'C are achieved. In these cases, the heating-up ofburden and the reduction of ore are almost cornpletedat a distance, 4m, from the tuyere level. From theseresults, the factor which determines the maximumpro-ductivity is the channeling limit. In the case of oxy-gen blast operations, the maximumproductivity is esti-mated at 3.8t/m3/d, which is muchhigher than thevalue of 2.6 in hot blast ones. This is because the gasflow rate is lowered in oxygen blast operatlons. In the

    oxygen blast operation with a maximumproductivityof 3.8t/m3/d, the reduction and the heating-up is thesameas those in hot blast operations with a usual pro-ductivity of 2.0 t/m3/d.

    line

    (G) (T)

    level

    Preheating gasinjection

    --- Tuyere

    Fig. 13.

    Effect of preheating gas injection level on thedistribution of gas flow, solid temperature andreduction.

    C 1992 ISIJ 844

  • ISIJ lnternational, Vol. 32 (1 992), No. 7

    ~

    e,

    (L,

    F:J

    E2G,

    OV1~~

    10Production (103tld )

    15 20

    OxygenB[astCR250, PCR3CO

    kg/t

    f\1~~.+ I~h, R.D.90V.Hot B[ast * l- Ts 1400'CCR510 kg/t :

    25

    10

    5

    o

    Channe[ing ~i mi t$l Reduction

    Degree 90ey.l, So[id TernpI 1400 'C

    2 3 4Productivity ( t!m3!d)

    Comparisonof productivity of oxygen blast furnaceand hot blast furnace estimated for FukuyamaNo. 4BF(4288m3).

    ~~ 20~;>oo 15~;>:~~Eo 10

    ~!:IELO

    q, 5I

    Fig. 14.

    oo

    VH 400Nm3/tTHIOOO'c'\~H0.72

    '\*

    aI \\ FR(kg/t)~\

    a: 650\\\b \b: 550.~

    '~\\'\c: 500

    l*c \\

    1*r~~~~rl \\\:\*

    Tf 2600*C1

    N Reduction, I\LN ,\

    , a \ *\.\a\ \ \1b \ b\

    \

    Ic'l c

    ,i -Soiution loss:

    25 •=~.~~~,~P~. oxygen blast... -~.

    ~' ' ~ -..-FR 950kg/t ,,\ \... "\~ 20t,

    ~\\ Tf 2400'c ~ , \ \-~ ,

    t~>

    'I

    'VHO * + 1~;

    l ---FR 500kg/t ,t \ \t~ Tf 2600'c I 11 '.

    .

    15

    >' ()\

    , VH400Nm3/t }~ ReductlonE

    \\ l .. , IL\ Hot blast I ::10* O ttl~ ~ ---- FR590kg/ l~= ~_, ll"\• Omeasured I '\\~_~ 5~; \~:~ 11 ~FR396kg/ :1\1

    ,I ,\ l solutionl e measured iOo 500 fOOO 1500

    1Ioss

    fOO2000 O 50Temperature ('C) Reaction degree (%)

    Fig. 15. comparison of longitudinal distribution of solid

    temperature and reaction degree at upper and towerhmit of fuel rate betweenoxygen blast operation andhot blast operation.

    5.3. Fuel Rate RangeIn regard to the fuel rate range from the kinematic

    viewpoint, the lower limit is determined by that whichis not able to maintain the hot metal temperature dueto insufficient heating-up and reduction. Theupper limitis determined by that which raises excessively the hotmetal and the top gas temperature. In the reported fuelrates of the hot blast operation in the commercial blastfurnaces, the lowest was 396kglt27) and the highest

    was 590kglt,28) in an ordinary operation, which usedagglomerated ore and produced pig iron for steelmak-ing. The lowest one operated in the high Tf and theliquid fuel injection. The highest one operated in thelow Tf and the all coke operation with the steaminjection. The simulated results of these two limitingoperations using the one-dimensional model are shownin Fig. 15. From these results, in the case of thelowest fuel rate operation 396kg/t, Uis 0.91, the shaftefficiency (R) 0.92, and Yd 0.49. Therefore it can beunderstood that the heating-up and the reduction werein the limiting state. In the case of the highest fuel rateoperation 590kg/t, Tg" is very high, at 280'C.

    In the case of the oxygen blast operations, the fuelrate range was estimated with the constant PCR,300kg/t, using the one-dimensional model. The lowerlimit was analyzed with the preheating gas injection

    845

    Fig. 16.

    500 1000 1500 2000 O 50 fOOSolid temperature ('C) Reaction degree (%)

    Transition of longitudinal distribution of solid tem-perature and reaction degree in decreasing fuel ratewith preheating gas.

    25

    ~~ 20~>~~* f5~>=E- lO

    ~=~D.- 5~I

    Oo 500 1000 f500 2000 O 50 100Solid temperature ('C) Reaction degree (~)

    Fig. 17. Transition of longitudinal distribution of sondtemperature and reaction degree in increasing fuelrate without preheating gas.

    (Series B) and the upper limit without the preheatinggas injection (Series C). The calculated results of SeriesBare shownin Fig. 16. AsCRdecreases, the heating-upand the reduction slow down. Particularly, whenFRis500kg/t, the reduction rate is considerably slower ixl

    the middle level of the furnace and the solution lossincreases. The calculated results of Series Care shownin Fig. 17, whenCRvaries from 350 to 650kg/t. In thecase of FRof 650kg/t, the heating-up and the reductionare insufficient. However, in the case of FR over700kg/t, the heating-up and the reduction rate advancewell. Figure 18 shows Tg", Uand the solid temperature(T~) at a level where the oxidation degree of ore corre-sponds to that of wustite I .05, R, T*t and Yd obtainedfrom the calculated results shown in Figs. 16 and 17.In the case of Series Bwith the preheating gas injection,whenFR is reduced from 550 to 500kg/t, Uchangeslittle from 0.73 to O.75 and the heating-up abovethe injection level is almost same. But in the lowerpart, the heating-up and the gaseous reduction areslowed down. Although T~ is as low as 570'C and theoxidation degree of the FeO-Feequilibrium reducinggas composition is more on the oxidation side, R isclose to unity and the gaseous reduction attains thekinematic limit. Cons~quently, the gaseous reduction is

    PCR300kg/t

    I d VH od

    c~

    Tf ('C)

    N 2600 d c---- 2400

    b c ,FR(kg/t) Reduction1l a: 650 b ~ b~ bl 700l c:t 750

    t~ d: 950 Solution loss

    aa

    a

    C 1992 ISIJ

  • ISIJ International, Vol. 32 (1992), No. 7

    I'2

    600 l Tf ('c)c 2400 1. O

    ~: 400~~~~1P'-~

    ~-~:>::_O-/~-•1::_.~~~Z~~~~~~1:~~]O~:e{T;:oo(~:0'8B-uo ~~~~o QnnH Luu ;i8~: '~ ~B*Tgo 0'6

    O - OPenmark: Tge sohdmark: Uf200 1.O~!E3-R

    1OOO O' 8,,

    c-Tw

    l

    ILk::1(y:L~-O/'/(y'._D_~w

    '-'/~j.

    ...

    "lao c

    600

    B~r/:1~~l~'~'

    :L~~\D_R

    o, 4:; 800 O' 6H

    2000OPenrrlark: TW Solidmark: R 0.4

    c-Tst~

    'O-A/i~::~:__:~;____D-Tst1800 B-Tst 0'3

    ~

    ~~~~P:---jjl~;Y~~1~:!t'~;5;;~~;T~:~'L

    ~~lo ~~~ O' 2~/ 1600 BYd l+' " B: Tf controled wlthu' top gas vH=400Nms/t1400 ~ - O' iH '- c Tf controled Wlthtop gas vH=0

    "- D: Tf controled Withopen mark: Tst I steam vH=01200

    solid mark: Yd --- obiective solld temperature O400 500 600 70O 800 900 1000 f100 i200FUel rate (kg/t)

    Fig' 18. Effect of fuel rate on thermal fiow ratio (U)' top gastemperature (Tgo)' FeO-Feequilibrium temperature(Tlv)' shaft efficiency (R)' direct reduction rate (Yd)

    and solid temperature at tuyere level (Tst)'

    I

    D

    l0::

    O.

    a)

    CQ

    Q)

    ~E 200~~

    coceo)

    ~oH

    1540~)

    a)

    ~Qa)

    1520(~E

    ~+,cQQ)

    ~~

    I;~

    retarded, Yd increases and Tst lowers considerably.Onthe other hand, in the case of Series C, which is

    without the preheating gas injection, Yd has a minimumvalue at about 750kglt fuel rate. Below this fuel rate, Uincreases and the gaseous reduction is slowed downbecauseof the heating-up delay, so Yd increases rapidly.At higher fuel rates, the heating-up is higher than thegaseous reduction progress, so Yd increases and T*t issuperheated comparedto objective temperatures. WhenTf rs lowered from 2600 to 2400'C, the changes inthe upper part are small, as shown in Fig. 17, buttemperatures in the lower part decrease and Tst lowersnear the objective value. As seen from these results, T*tcan be controlled by Tf'

    In-furnace distributions of the calculated results ofthese lower and upper fuel rate llmits of the oxygenblast operation are also shownin Fig. 15as comparedto the hot blast ones. The temperature and the reactiondistributions in the range above 1200'C, in which thesoftening and the cohesiveness of ore begin, are similarto each other. Therefore, the operations in these fuelrate ranges of the oxygen blast furnace are consideredto be possible from the viewpoint of in-furnace con-ditions.

    In regard to Tf' Tf rs controlled in the range of2OO0-2400'C in the conventional hot blast• operations.High Tf can be achieved in the oxygen blast operationcomparedto the hot blast one. However, the upper limitof Tf rs not clear in the blast furnace operation. Oneofthe problems in high Tf operation is the increase of thevaporized substance and the irregular burden descentcaused by the condensation of the vaporized substance.Theamountof the vaporized substance in the proposed

    1500O 10 20Preheating gas injection ievel (m)

    (distance from stock level )Fig. 19. Effect of preheating gas injection level on top gas

    and hot metal temperature.

    oxygen blast furnace process is lower than that of thehot blast one because the bosh gas fiow rate is lower.Therefore, the influence of the condensation of thevaporized substance on the burden decent is consideredsmall comparedto the hot blast operation. Fromtheseconsiderations and on referring to the high Tf' 2533'C,operation,27) Tf of 2600'C is adopted in the basecondition of simulations as shownin Table 2. In the lowTf operation, although it is a problem to maintain thehot metal temperature, this can be controlled by FR.Fromthese considerations, it is considered that there isno problem in the operation in which Tf range of2OO0-2400'C. However,no matter whether Tf rs high orlow, when the mixing of oxygen, pulverized coal andcontrol gas is insufficient, the extreme temperatureincrease takes place locally in the raceway. Therefore,the mixing of oxygen, pulverized coal and control gas isimportant.

    In the oxygen blast furnace operation where PCR=300kg/t, the lower limit of FRis estimated to be about500kglt from the simulation results of Series B. Theupper limit of FR, when the upper limit of Tg" isassumed300'C in the samemanner as the hot blastoperation, is estimated to be about 900kglt in the casewhenTf rs controlled by circulating the top gas fromSeries C, and about 1200kg/t whenit is controlled bythe steam from Series Das in Fig. 18.5.4. Possibility of Lowering the Furnace Height

    In the oxygen blast furnace process, it is thought thatthe furnace height can be lowered comparedto the hotblast one. Figure 19 shows the calculated results of thechanges of top gas and hot metal temperature usingthe two-dimensional model when the preheating gasinjection level is varied. From the figure, when theinjection level is varied in the range of 6-12mfrom thestock level, top gas and hot metal temperature changesare not so large. This indicates that the furnace height

    can be lowered within the range of this height. Figure 20shows the simulation results when the furnace heightand the preheating gas injection condition are varied.In the figure, A is the base condition. Bis the calculatedresult whenthe shaft height is lowered 2.5 mfrom A. Inthe case of B, the region of 120(~l400'C ascends.Whenthe shaft height is decreased more, as in the caseof C, temperature is lowered throughout the furnace. In

    C 1992 ISIJ 846

  • ISIJ International, Vol. 32 (1 992), No. 7

    O

    cQL.

    ~EHa)

    1:,.-

    IS(D

    E]

    c

    75600

    1) 16.5 14.0 11.52) 7,5 75 7.53) 300 300 300

    .--- go•/•-reduction degree

    1) Shaft height (m)2)Prehoating gas injection level (m)

    (distance frcm S.L.)1153)Preheating gas volume (Nm3 /t) g.O300

    Fig. 20. Calculated result of change of solid temperatureand reduction degree distribution with changes offurnace height and condition of preheating gasinjection.

    order to improve temperature decrease, the increase ofVHis not effective (D). CaseE is the calculated resultswhen the injection level was lowered l.5m more thanthat of C. In this case, the temperature distributionimproved remarkably. In the simulation, it is seen thatthe furnace height is able to be reduced by about 5m.From these calculations, if the throat diameter isexpanded, it is possible to increase productivity further,because it is determined from the channeling limitestimated in Fig. 14.

    6. Conclusion

    In regard to the oxygen blast furnace process whichis characterized by the injection of preheating gas intothe shaft, operation tests using an experimental blastfurnace were carried out to verify this process as beingapplicable to an ironmaking process. Mathematicalmodel simulations also were carried out to understandthe process characteristics on a commercial scale,

    The following conclusions were obtained:(1) Fromthe experimental oxygen blast furnace op-

    eration, it was verified as characteristics that the gase-ous reduction proceeded fast in a relatively low tem-perature region and the solution loss reaction rate

    was low comparedto that in the hot blast operation.The pulverized coal was injected up to the ratio of0,94 kg-coal/Nm3-0xygen, and the high productivityof 5.1 t/m3/d wasrealized in the test operation. The testoperation wasso stable that this process was technical-ly verified to be very suitable as an ironmaking process.

    (2) The preheating gas injected into the upper shaftflowed in the vicinity of the furnace wall and the gasfrom the lower part mainly flowed in the furnace center.As a result, the heating-up of burden was securedthroughout the upper shaft, and the reduction progressin the lower part wasalso secured at a high degree.

    (3) Appropriate preheating gas, in which the low

    fuel rate is realized, was estimated to be in the rangecorresponding to the thermal flow ratio of 0.71~0.90 inthe upper shaft and the temperatures of 600-1 200'C.

    (4) The effect of the preheating gas composition onthe reduction in the lower part wassmall.

    (5) The position of preheating gas injection wasadequate in the upper shaft as long as the heat transfer

    was secured.(6) A substantial increase in maximumproductivity

    could be achieved compared to that in the hot blastfurnace process.

    (7) It was estimated that the range of the fuel ratewaswide, and the lower limit and the upper limit of thefuel rate were 500 and 1200kg/t, respectively.

    (8) It was indicated that this process could beoperated with a lower furnace height comparedto thehot blast furnace.

    l)

    2)

    3)

    4)

    5)

    6)

    7)

    8)

    9)

    lO)

    l l)l2)

    13)

    l4)

    l5)l6)l7)

    18)

    19)

    20)

    21)

    22)

    23)

    24)

    25)

    26)

    27)

    28)

    REFERENCESR, B. Smith and M. J. Corbett: Ironmaking Steelmaking, 14(1987), 49.

    K. Shiohara: Proc. Second European lronmaking Cong., TheInst. Met., London, (1991), 310.Y. Ohno. H. Hotta, M. Matsuura, H. Mitsufuji and H. Saito:Process Technology Conf. Proc.. AIME, Penn., (1988), 195.Y. Ohno, H. Hotta, M. Matsuura, H. Mitsufuji and H. Saito:Tetsu-to-Hagan~, 75 (1989), 1278.H. Mitsufuji, M. Matsuura, T. Furukawaand Y. Ohno: Rev.Metall., (1989), Mars, 217.Y. Ohnoand M, Matsuura: Tetsu-to-Hagan~, 76 (1990), 1262.M. Matsuura, H. Mitsufuji. T. Furukawaand Y. Ohno: Proc.The Sixth International lron and Steel Cong., Vol. 2, ISIJ,Tokyo, (1990), 581.R. Durrer: J. Iron Steel Inst., 156 (1947). June, 253.Int. Res. Comm.on LowShaft Furnace: J. Iron Steel Inst., 179(1955), Jan., 36.

    T. Miyashita, H, Nishio, T. Shimotsuma, T. Yamadaand M.Ohtsuki: Trans. Iron Steel Inst. Jpn., 13 (1973), l.

    B. M. Suslov: Iron Age, 134 (1934), No. 4, l.T. Okamoto, T. Tada and S. Sugiura: Tetsu-to-Hagan~, 58(1972), 637.

    P. L. Woolf: Bureau ofMines Report. (1985), OFR,99-85.R. Wartmann:Proc. Fifth Japanand GermanySeminar, VDEh,Dtisseldorf, (1982), 133.

    W-K. Lu and R. V. Kumar: ISS Trans,, 5(1984), 25.Q. Minshengand Y, Naifu: Scan. J. Met., 15 (1986), 138.F, Fink: Proc. Europeanlronmaking Cong., VDEh,Dtisseldorf,(1986). PV-3.S. Taguchi, H. Kubo, N. Tsuchiya, K. Ichifuji and K. Okabe:Tetsu-to-Hagan~, 68 (1982), 2303.

    M. Hatano, K. Kurita, H. Yamaokaand T. Yokoi: Tetsu-to-Hagan~,68 (1982), 2369.A. Rist and N. Meysson: J. Met., (1967), April, 50.

    M. Kuwabara, K, Isobe, K. Mio. K. Nakanishi and I. Muchi:Proc. 2nd Japan-Australia Symp., ISIJ, Tokyo, (1983), 193.

    M. Matsuura, T. Furukawa, Y. Ohnoand Y. Yamaoka:Rev.Metall., (1991), Mai, 453.H. Nishio and T. Miyashita: Tetsu-to-Hagan~, 59 (1973), 1506.T. Yatsuzuka. K. Nakayama,K. Omori, Y. Hara and M. Iguchi:Trans. Iron Steel Inst. Jpn., 13 (1973), I15.T. Miyashita, K. Sano. H. Nishio, S. Ohzeki, T. Nayuki and L.Chaussy: Trans. Iron Steel Inst. Jpn., 14 (1974), 176.

    T, Miyashita, H. Nishio, T. Shimotsuma, T. Yamadaand M.Ohtsuki: Tetsu-to-Hagan~, 58 (1972), 608.S. Kajikawa. R. Yamamoto.R. Nakajima, S. Kishimoto and T.Fukushima: Tetsu-to-Hagan~, 68 (1982), 2361.R. Yamamoto,R. Nakajima, T, Sumigama, A. Maki, K.Wakimoto. Y. Yamadaand K. Tomioka: Tetsu-to-Hagan~, 72(1986), S72.

    847 C 1992 ISIJ