Probabilistic Risk Assessment (PRA) Mathew Samuel NASA/GSFC/MEI (301) 286-6475...
-
Upload
jeremy-armstrong -
Category
Documents
-
view
217 -
download
0
Transcript of Probabilistic Risk Assessment (PRA) Mathew Samuel NASA/GSFC/MEI (301) 286-6475...
Mission Success Criteria & PRA Activities
Full & Minimum Mission Success Criteria
Reliability Block Diagrams
Master Logic Diagram
Fault Tree Analysis
Failure Modes & Effects Analysis
4 Scientific Objectives
17 Measurements Required
11 Groups of Imagers & Sensors
Reliability Predictions
PRA Activities
Level 1 Science Requirements
DesignFull & Minimum Mission
Success Criteria
- What can go wrong?
- How likely is it?
- What are the consequences?
• For Minimum Mission Success, Both Spacecraft are Required During the First 240 Days and Either Spacecraft is Required From 240 – 820 Days
• For Full Mission Success, Both Spacecraft are Required From 0 – 820 Days
Level 1 Science Requirements
Full Mission (0-820 days)/Minimum Mission (0-240 days) Reliability Block Diagram (RBD)
IMPACT Items in Gray
A – AheadB – Behind
Full Mission (0-820 days)/Minimum Mission (0-240 days)
Measurements F, G
IMPACT Items in Gray
A – AheadB – Behind
Full Mission (0-820 days)/Minimum Mission (0-240 days)
Measurements H, I
IMPACT Items in Gray
A – AheadB – Behind
Full Mission (0-820 days)/Minimum Mission (0-240 days)
Measurement J
IMPACT Items in Gray
A – AheadB – Behind
Full Mission (0-820 days)/Minimum Mission (0-240 days)
Measurement K
IMPACT Items in Gray
A – AheadB – Behind
Minimum Mission RBD (240-820 days)
IMPACT Items in Gray
A – AheadB – Behind
Mission Master Logic Diagram
Gate1
Loss of STEREO Mission
Gate15COR2, HI1 Combination
M:2:4
Gate16COR2, HI2 Combination
M:2:4
Gate17HI1, HI2 Combination
M:2:4
Gate18HI2, SWAVES Combination
M:2:4
Gate19HI1, SWAVES Combination
M:2:4
Gate20HI1, HI2 Combination
M:2:4
Gate21STE-U/D, SEP Combination
M:2:4
Gate22SWAVES Combination
Gate23SWEA, PLASTIC Combination
M:2:4
Gate24SWAVES Combination
Gate27SWAVES Combination
Gate28MAG Combination
Gate25SWEA, PLASTIC Combination
M:2:4
Gate26HI2 Combination
Gate12COR1, EUVI Combination
M:2:4
Gate13COR1, COR2 Combination
M:2:4
Gate14EUVI, COR2 Combination
M:2:4
Gate2
Loss of Mission (0-240 days min/0-820 days full)
Gate4Failure to Obtain Measurement 1A
Gate5Failure to Obtain Measurements 1B, 2C1, 2D1, 2E1
Gate6Failure to Obtain Measurements 2C2, 2D2, 2E2
Gate7Failure to Obtain Measurements 2C3, 2D3, 2E3
Gate8Failure to Obtain Measurements F, G
Gate10Failure to Obtain Measurement J
Gate29COR1 - A
Gate31EUVI - A
Gate33COR2 - A
Gate35HI1 - A
Gate37HI2 - A
Gate39STE-U/D - A
Gate41SEP - A
Gate43SWEA - A
Gate45PLASTIC - A
Gate47SWAVES - A
Gate49MAG - A
Gate51SEB
Can't Exceed 30C
Gate58IDPU Data Controller Board
Gate53STE-U - A
Gate54STE-D - A
Gate55SEP Common Electronics
Gate57SWEA/STE-D I/F Card
+28VSpacecraft
+28VSpacecraft
Gate60LVPS/STE-D Bias
Gate56
LVPS (UCB)
+28V S/C
Gate59IDPU LVPS/STE-U Bias
Gate61IDPU STE-U DIB Card
Gate63IDPU MAG Front-End
Gate62MAG Heater Supply
+28VSpacecraft
Gate68SIT - A
Gate28Antenna Ex
Gate29Antenna Ey
Gate30Antenna Ez
M:2:3
Event59EMC
Ex BrakeEx DADEx SMA ReleaseEx Trap Door
Ey BrakeEy DADEy SMA ReleaseEy Trap Door
Ez BrakeEz DADEz SMA ReleaseEz Trap Door
Gate30COR1 - B
Gate34COR2 - B
Gate36HI1 - B
Gate38HI2 - B
Gate44SWEA - B
Gate46PLASTIC - B
Gate48SWAVES - B
Gate50MAG - B
Event11MEB EUVI Mechanism Card
Event9SCIP CEB COR1 CCD Driver
Event10MEB COR Mechanism Card
Event13SCIP CEB EUVI CCD Driver
Gate52Guide Telescope
Event3
Housekeeping Card
Event4
Spacewire Card
Event5
Power Supply Card
Event7
Backplane
Event14
SCIP CEB Power ConverterEvent12
SCIP CEB COR2 CCD Driver
Event15
SCIP CEB Camera Interface Card
Event17
HI CEB HI-1 CCD Driver
Event16HI Baffle Cover Assembly
Event18
HI CEB HI-2 CCD Driver
Event19
HI CEB Power Converter
Event20HI CEB Camera Interface Card
Event26S/C-IDPU 1553 Bus
Event25BOOM
Event24SSD Bias
Event22
SEP MISC CPU, SRAM,EEPROM Event23
Analog/Post-Regulator
Event21
I/F to IMPACT DPU
Event32
PAC HV Power Supply
Event33
MCP HV Power Supply
Event31S-Channel PS
Event34
Event Selection
Event36
ClassifierEvent37
IDPU Interface
Event35
Instrument Control
Gate76
Gate72TOF SWS Function
Event39
TOF SWS
Event40
SSD HV Power Supply
Event41
TAC PWA 1Gate73
Anode 1 & Anode 2
Gate74TOF WAP Function
Event44
TOF WAP
Gate75Anode 3 & Anode 4
Gate71TOF SWS & TOF WAP Functions
Event29Defl. Sweep PS 1 Defl. Sweep PS 2
Event30
Gate70ESA Sweep PSs
Event27ESA SWEEP PS 1
Event28ESA SWEEP PS 2
Gate77
LVC Box
+28VSpacecraft
Gate40STE-U/D - B
Gate64SEPT-NS - A
Gate65SEPT-E - A
Gate66LET - A Gate67
HET - A
Gate79Sensor
Event604 (+4 redundant) photodiode pramps
Gate80EUVI Assembly
Event61EUVI Door Assembly
Event62EUVI Op. Heaters & Thermistors
Event63EUVI FPS PZTs
Event64EUVI Tel. Mechanisms (3)
Event65EUVI Focal Plane Assembly
Event66
EUVI Decontamination Heater
Gate81COR1 Assembly
Event67COR1 Op. Heaters & Thermistors
Event68COR1 Focal Plane Assembly
Event69COR1 Decontamination Heater
Event70COR1 Tel. Mechanisms (2)
Event71COR1 Door Assembly
Event72COR2 Door Assembly
Event74COR2 Tel. Mechanisms (2)
Event75COR2 Focal Plane Assembly
Event76COR2 Decontamination Heater
Event77HI1 Op. Heaters & Thermistors
Event78HI1 Focal Plane Assembly
Event79HI1 Decontamination Heater
Gate84HI2 Assembly
Gate83HI1 Assembly
Event80HI2 Op. Heaters & Thermistors
Event81HI2 Focal Plane Assembly
Event82HI2 Decontamination Heater
+28VSpacecraft
Gate85
Power Interface Card
Gate82COR2 Assembly
Event73COR2 Op. Heaters & Thermistors
Event84
Door Open During Thruster Firings
Event85
Door Open During Thruster Firings
Gate42SEP - B
Gate3
Loss of Mission (240-820 days min)
Gate86HVPSs
Softwaremay turn onHVPSs atwrong time
FMEA:500.1 -500.4,500.6
Event1
1553 Card
Gate87
Software
Event8
Computer fails to boot;s/w component failure
Reload of Software
IEEE 1553 code stored inmultiple locations (BootSUROM and EEPROM)
permitting reload of software
FMEA:207.1
FMEA:207.2
Interpolation and modelingof time error
FMEA:207.3
Event86
IEEE I/F to S/C intermittent;s/w component failure
Event87
Time error, fails to collect imagedata synchronously with other s/c;
s/w component failure
Event83
Door Open During Thruster Firings
Gate32EUVI - B
Gate69Deflection Sweep PSs
Event2
RAD750 Processor Card
Event50Ez Preamp
Event49Ey Preamp
Event48Ex Preamp
Gate27Antennae Assembly
Highvoltage arc-over due to
part orinsulation
breakdown
Gate11Failure to Obtain Measurement K
Gate9Failure to Obtain Measurements H, I
Anode 1Anode 2
Event45
TAC PWA 2
Anode 3Anode 4
Event51HFR Board
Event58Backplane
Event90LFR
Event92TDS Analog Bay
Event52TDS Board
RAMROMDPU-DSP I/F
Gate92DSP Board
RAMROM
Gate93CPU
Gate78Main Electronics Box
1553Burst RAMDPU-DSP I/F
Gate94I/O Board
+28VSpacecraft
Gate57DC-DC Power Converter
EventSpacecraft - A
EventSpacecraft - B
IMPACT Items in Gray
White Box - Failure PropagationRed Colored Box - Single Point FailureYellow Colored Box - Graceful DegradationGreen Colored Box - Redundancy Failure within InstrumentYellow Outline Box - Ground Contingency ProcedureBlue Outline Box - Onboard Fault Detection & Correction
IMPACT Master Logic Diagram
OR Gate
AND Gate
Basic Event
Undeveloped Event
White Box - Failure PropagationRed Colored Box - Single Point FailureYellow Colored Box - Graceful DegradationGreen Colored Box - Redundancy Failure within InstrumentYellow Outline Box - Ground Contingency ProcedureBlue Outline Box - Onboard Fault Detection & Correction
Gate39STE-U/D - A
Gate41SEP - A
Gate43SWEA - A
Can't Exceed 30C
Gate58IDPU Data Controller Board
Gate53STE-U - A
Gate54STE-D - A
Gate55SEP Common Electronics
Gate57SWEA/STE-D I/F Card
+28VSpacecraft
+28VSpacecraft
Gate60LVPS/STE-D Bias
Gate56
LVPS (UCB)
+28V S/C
Gate59IDPU LVPS/STE-U Bias
Gate61IDPU STE-U DIB Card
Gate63IDPU MAG Front-End
Gate62MAG Heater Supply
+28VSpacecraft
Gate68SIT - A
Event26S/C-IDPU 1553 Bus
Event25BOOM
Event24SSD Bias
Event22
SEP MISC CPU, SRAM,EEPROM Event23
Analog/Post-Regulator
Event21
I/F to IMPACT DPU
Gate64SEPT-NS - A
Gate65SEPT-E - A
Gate66LET - A Gate67
HET - A
Gate86HVPSs
Softwaremay turn onHVPSs atwrong time
FMEA:500.1 -500.4,500.6
Highvoltage arc-over due to
part orinsulation
breakdown
Gate49MAG - A
IMPACT FMEA
Analysis Results (1 of 3)
• Reliability Block Diagrams– IMPACT has backups to obtain measurements for the mission
• SWAVES, PLASTIC, and SECCHI – HI2
– Combination failures of SWAVES and either IDPU DCB or IDPU LVPS will lead to the loss of measurements F, G, H, I and K
– Combination failures of SWAVES and any of the following IMPACT items will lead to the loss of measurement K: MAG, IDPU Front-End Electronics Card, IDPU MAG Heater Supply Card, IDPU DCB, IDPU LVPS, or the BOOM
– Enables the calculation of mission reliability
• Reliability Predictions– Identify reliability drivers based on failure rate calculations
• Reliability drivers to be provided at the Observatory CDR
• Graceful degradation elements turn out to be robust due to backups
– Reliability predictions used in other PRA activities for the mission
Analysis Results (2 of 3)
• Master Logic Diagram (MLD)– Top-down, identification of what causes mission failures and categorized into Single Point
Failures (SPF), graceful degradation failures and redundancy failures. MLD includes non-parts related causes (those not evaluated by RBDs, FTAs and reliability predictions, like operator/software and environment).
• IMPACT provides graceful degradation modes for the mission• BOOM could be a SPF, if partially deployed
– MAG, STE-D, SWEA cannot provide accurate data– Could cause pointing accuracy degradation which affects SECCHI instruments– Analysis being performed with Boom partially deployed
• No operator induced failures identified• Considered time critical contingency procedures and on-board autonomy rules necessary to save
instrument after first failure– Turning instrument off if a “Blabbermouth” condition occurs
• Fault Tree Analysis (FTA)– Minimal cut set analysis identifies and ranks single & combination failures along with
probabilities for loss of mission• Confirm failures identified in RBD and Master Logic Diagram • Confirm likelihood of failures by ranking from the highest contribution to unreliability to the
lowest
Analysis Results (3 of 3)
• Failure Modes and Effects Analysis (FMEA)– Bottom-up analysis of postulated failures and their consequences
• Cross checked MLD and causes of failures with FMEA consequence of lower level failures
• Considered propagation of failures from instrument to spacecraft – Power - Spacecraft fuse blows
– Data - Corrupt 1553 bus, consider protection from “Blabbermouth” on the bus
– Cross-checked spacecraft I/F ICD and FMEA causes
• Summary– Any design changes or recommendations? None
– Be sure that we don’t have a latent design or manufacturing problem
Risk Mitigations
• Moving Surfaces (BOOM, Covers)– Instruments have backups– Design margin, redundancy, peer reviews, testing
• Software and Operations– Software is reloadable, should not result in mission loss– Software and operational plan, peer reviews, testing
• Parts Applications– Parts stress analysis per PPL21/MIL-STD-975, peer reviews, testing
• Understanding of Environment– Analysis with single common environment spec, peer reviews, testing
• Workmanship– Inspection to NASA-STD-8739 or equivalent, material and process control, PCB
coupons, testing
• Random Failures– Grade 2 parts, simplicity, robust design with graceful degradation, redundancy, peer
reviews, testing