Privatization and Liberalization of the Electric Power Industry in Taiwan Energy Commission Ministry...
-
Upload
raymond-casey -
Category
Documents
-
view
222 -
download
3
Transcript of Privatization and Liberalization of the Electric Power Industry in Taiwan Energy Commission Ministry...
Privatization and Liberalization of the Electric Power Industry
in Taiwan
Energy Commission
Ministry of Economic Affairs
October 5, 2001
ContentsContents
1. Electricity Supply Industry Structure1. Electricity Supply Industry Structure
2. Privatization of Taipower 2. Privatization of Taipower
3. IPP Programs3. IPP Programs
4. The Envisage of the 4. The Envisage of the Forth Round IPPsForth Round IPPs
5. Basic Structure of Liberalization5. Basic Structure of Liberalization
6. Energy Policy Requirements
7. Revise of Electricity Law7. Revise of Electricity Law
1. Electricity Supply Industry StructureElectricity Supply Industry Structure
IPPs8 projects, 7,220 MW
Transmission
•Power Generation 70 plants, 27,445 MW.
Distribution
Taiwan Power Company
25yrs PPA
Avoided cost
Customers
Supply obligation
self-useusers
Self-generation• co-generation• renewables
For self-
use
• Industry Structure
Thermal (17,818MW: coal 8100; oil 5404; gas 4314 MW)
Extra High Voltage Substation 345 kV Transmission Line
Peak Capacity: 29,124 MW
Peak Load: 25,854 MW
Rserve: 3,270 MW 12.6%
Shenao
1st Nuclear2nd Nuclear
3rd Nuclear
NLinkou
Tunghsiao
Taichung
Takuan Hydro
Mingtan Pumped Storage
Hsinta
Nanpu Talin
Penghu
Mailiao IPP
Hoping IPP
Ever Power IPP
Chiahui IPP
Sunba IPP
Kuokuang IPPHsintao IPP
Nuclear ( 5,144 MW)
Starenergy IPP
• Power System (2000)
Hydro ( 4,422 MW)
IPP ( 2,250 MW)
Hsiehho
Timetable:The deadline for Taipower to finish privatization was set as June 2001 but has failed.
Procedure: Taipower will be privatized by the program of “massive share offering to citizens” with keeping its original integrated business including generation, transmission and distribution.
Preconditions: The Legislature requires that Taipower won’t proceed privatization until the legislation of new Electricity Law is approved.
A tentative plan for Taipower to privatize is made. It suggests that the initial public offering will be completed in one year after the pass of Electricity Law and the government’s shares will be released down to no more than 50% in the next three years for privatization. It is likely that Taipower won’t be privatized by the end of 2005.
2. Privatization of Taipower2. Privatization of Taipower
3. IPP Programs3. IPP ProgramsPolicy Objectives•To meet power demand at reserve margin of 20%
1st & 2nd rounds (1995): 10,260 MW (1997-2002); 3rd round (1999): 2,840 MW (2003-2004)
‧ To balance regional supply and demand
•To prepare for power liberalization1st & 2nd rounds: competitive bidding (base load, medium load)3rd round: fixed price, first come first serve (gas fired, medium load)
•To follow clean energy policy
Areas Peak Demand Peak CapacityNorth 46% 25%
Central 26% 37%South 28% 38%
Fuel Type coal oil gas hydro nuclear renewable
Capacity(year 2020)
35-37% 4-5% 27-29% 9-11% 19-20% 1-3%
Company Location Fuel Type Capacity(MW)
Status
1.Mai LiaoPower
Yunlin Coal 1,800(600*3)
Operating
2.Ever Power Taoyuan Gas 900(450*2)
Operating 450MWTesting 450MW
3.Ho-ping Power Hualilen Coal 1,300(650*2)
Testing
4.Chiahui Power Chia-yi Gas 670(670*1)
Constructing09/00
5.Miao-Li Power Miaoli Orimul-sion
1,200(600*2)
Canceled
6.Hi-doer Power TaichungPort
Coal 990(495*2)
Canceled
7.HuatungPower
Hualien Coal 1,000(500*2)
Canceled
Total 7,860 Operating:2,250 MWConstruct.:2,420 MW
• First Round IPP ProjectsFirst Round IPP Projects
Company Location Fuel Capacity(MW)
Status
1.Hsin Tao Power Hsinchu Gas 600 To be testingDec., 2001
2.Chang-hongPower
Yilan Orimul-sion
1,500 Canceled
3.Full Power Yilan Oil 600 Canceled
4.Fu Bau Power Hualien Coal 550 Canceled
Total 3,250 Construct.: 600 MW
• Second Round IPP ProjectsSecond Round IPP Projects
• Third Round IPP ProjectsThird Round IPP Projects
Company Location Capacity(MW)
OperationDate
Kuokuang Taoyuan 480 2003/6/30
Energystar Changhwa 490 2004/4/30
Sunpa Tainan 980(490*2)
2004/4/30
Ever Light Taoyuan 960(480*2)
Suspended
Total 2,910 1,950MW inprogress
• Status of IPP ProjectsStatus of IPP Projects
Items IPP
CapacityStatus
PolicyAchievement
Capacity(MW)
Preparatory1,950
Constructing 3,020
Operating2,250
ReserveMargin willbe 20% in
2004
FuelTypes
Gas4,120
Coal3,100
Gas Sharewill be 33%
in 2004
Areas
7,220(20% of
Total36,680MW in2004)
North3,280
Central490
South3,450
North will beself-
sufficient in2006
•Rules on applications for a preparatory permit·Required capacity:
1. Year 2007: 1000 MW, gas fired and in the North only
2. Year 2008-2009: 3200 MW ( 1500 MW reserved for TPC)
·Requisitions (Construction planning plus the following 6 documents):
1.Environment Impact Assessment 2.General agreement from local government3.Agreement of fuel supply4.Agreement of power interconnection5.Agreement of land use6.Letter of intent on financing
4. The Envisage of the 4. The Envisage of the Forth Round IPPsForth Round IPPs
•Rules on Power purchase•Purchase prices:
The Price will be decided by bidding process held by Taipower .
•Dispatch rules:1. Year 2007, medium load2. Year 2008-2009, base load
•Transmission constraints: Taipower should announce its transmission constraints in one month since this program is implemented.
Integrated Utility
transmission
Distribution
Generators1st, 2nd round IPPs3rd round IPPs
(Non-utility)
Supply Obligation
GenerationExisted PlantsUnder-constructionApproved ProjectsFuture Projects
Wholesale
5. Basic Structure of Liberalization5. Basic Structure of Liberalization
After PPA terminated
ISO
Bilateral Contract
Generators•IPP's new units•New IPPs
(Non-utility)
Self-generators
Captive Customers
(Unregulated tariff)(regulated tariff)
Contestable Customers
Direct Users
(Unregulated tariff)
Self-useUsers
Direct
Supply
Captive Customers Contestable Customers
Direct Users
Self-useUsers
6. Energy Policy RequirementsIntegrated Utility
Generators1st, 2nd round IPPs3rd round IPPs
(Non-utility)
Supply Obligation
Generation
Bilateral Contract
§Generators are required to have gas-fired and renewable capacity through: 1.installation, 2.purchase by PPA, or 3.pay fund
§required to install hydro and nuclear power.§require to have gas- fired and renewable capacity through: 1.installation, or 2.PPA.
ISO
Generators•IPP's new units•New IPPs
(Non-utility)
Self-generators
§Exempted from the obligation when its capacity less than the assigned
Direct
Supply
Wholesale
– To allow Taipower to be vertically integrated and independent of the privatization process.
– To allow new industries such as generation, transmission, and distribution to enter the market as soon as the law is passed.
– To establish the Independent System Operator(ISO).
– To allow electricity customers to choose their suppliers.
– To require electricity industries to install certain percentage of clean energy capacity.
– To require Integrated utility and distribution company have the obligation of guaranteed supply of electricity.
– To allow generators to supply power directly to nearby users through private power lines.
7. Revise of Electricity Law7. Revise of Electricity Law
THANK YOUTHANK YOU