Cash in, Cash out in P6
Dear All,
What is the technique to implement cash in & cash out on the same curve in Primavera.
3 days ago
Like CommentFollow Flag More
5 comments
Follow Azad
Azad Pasha Hvae you soved your first probelm of bars and summary?
:)
1 day ago Like
Follow Hussam
Hussam Hussein it is easy;
you can define 2 Material Resource; call them 1- cash in & 2- cash out.
Assign them on activities that are reflect money from BOQ.
Then, for cash in resource, apply prices from BOQ (selling prices).
And for cash out, apply prices from Project Study, (Prices - profits & overheads)
Finaly, go to resource usage profile, and choose options, disply by CASH, and in curves choose
remaining early and choose those 2 resources from resource list (at left) and you will have Cash in
and Cash OUT.
all the best
1 day ago Like
Follow Mohamed
-
7/28/2019 Primavera Cash in Out
2/3
Mohamed Zaki Khafagi-PMP Dear Mr. Azad,
ya, it's the cause of the difference between the admin preference & the calenders of the activity
1 day ago Like
Follow Mohamed
Mohamed Zaki Khafagi-PMP Mr. Hussam,
But how could I implement the curve of cash out , with the histogram of the cash in with definite
dates as invoices, advance payment.
1 day ago Like
Follow Hussam
Hussam Hussein Hi Mohamed,
the method that I suggested is the used for the baseline, the remaining is equal to the budgeted.
Now;
Usualy, Cash in & Cash out is used internally. It Means, a copy of the schedule is made and loaded
with COST(this cost is Actual estimated cost- budget minus profit and overheads).
So, at the baseline, I should assign 2 costs for each activity, Cash in (the selling cost at BOQ) and cash
out(the palnned cost that the project will spend).
At this stage, you have planned cash in and planned cash out.
During the execution of work, you will have actual cash out, which will replace the planned cash out
and it will be updated monthly.
To show curves,
Go to Resources Profile, right click and choose resource usage profile options.
At the baseline stage, choose commulative- Remaining (click on the cash in and cash out resources
from left screen) and you will have Planned cash in and Planned cash out.
During execution, from option, choose actuals commulative, and you will have the curve for actual
cash out.
-
7/28/2019 Primavera Cash in Out
3/3
I would like to ad a note here, we are using this methodology only when we want to have a loan
from the bank for a particular project.
Belive me, using excel will make you life much more easier.
Best wishes