  • S10 Pgina 1

    PresupuestoMEJORAMIENTO DE LA CARRETERA JULIACA - COATA - CAPACHICA - PUSI - TARACO, EMP.R.3S ( ILLPA ) - HUATA -COATA

    0403003Presupuesto

    TRAMO II : COATA - CAPACHICA001SubpresupuestoGOBIERNO REGIONAL PUNO 28/07/2009Costo alCliente

    Lugar PUNO - PUNO - CAPACHICA

    Precio S/. Parcial S/.Item Descripcin Und. Metrado

    01 41,010.67OBRAS PRELIMINARES1.00MOVILIZACION DE EQUIPO Y HERRAMIENTAS glb01.01 19,225.43 19,225.431.00CARTEL DE IDENTIFICACION DE LA OBRA u01.02 957.94 957.94

    01.03 12,360.91DESVIOS PROVISIONALES2.00DESVIOS PROVISIONALES PARA ALCANTARILLAS km01.03.01 1,867.56 3,735.124.10DESVIOS PROVISIONALES PARA EXTRACCION DE MATERIAL BLANDO km01.03.02 2,103.85 8,625.79

    01.04 VARIOS1.00SEALIZACIONES, FLECHAS DE DESVIO Y TRANQUERAS glb01.05 3,466.39 3,466.391.00CAMPAMENTO PROVISIONAL DE OBRA PAV y MOVIMIENTO DE TIERRAS glb01.06 5,000.00 5,000.00

    02 21,837.11TRABAJOS PRELIMINARES18.84TRAZO Y REPLANTEO km02.01 165.06 3,109.73

    18.84TRAZO Y REPLANTEO DURANTE EL PROCESO km02.02 62.66 1,180.5152.70ACONDICIONAMIENTO DE ACCESO A CANTERAS km02.03 174.30 9,185.61

    3.05ACONDICIONAMIENTO DE ACCESO A FUENTES DE AGUA km02.04 871.45 2,657.929.42DESBROCE Y LIMPIEZA ha02.05 605.45 5,703.34

    03 1,994,105.12MOVIMIENTO DE TIERRAS03.01 13,701.65EXPLANACIONES

    1,519.03CORTE DE MATERIAL SUELTO CON MAQUINARIA m303.01.01 9.02 13,701.65

    03.02 116,471.52PEDRAPLENES3,762.00EXTRACCION Y APILAMIENTO DE ROCA PARA PEDRAPLEN m303.02.01 8.58 32,277.963,762.00CARGUIO DE ROCA m303.02.02 5.29 19,900.98

    3,762.00TRANSPORTE DE ROCA m303.02.03 8.42 31,676.043,762.00ENROCADO Y CIMENTACION EN PEDRAPLEN m303.02.04 8.67 32,616.54

    03.03 31,487.94RELLENO ANTICONTAMINANTE682.00EXTRACCION Y APILAMIENTO DE MATERIAL HORMIGON m303.03.01 14.20 9,684.40

    682.00CARGUIO DE MATERIAL HORMIGON m303.03.02 3.65 2,489.30682.00TRANSPORTE DE MATERIAL HORMIGON ANTICONTAMINANTE m303.03.03 10.52 7,174.64682.00RELLENO CON MATERIAL ANTICONTAMINANTE m303.03.04 17.80 12,139.60

    03.04 1,045,731.91CONFORMACION DE TERRAPLEN112,942.21EXTRACCION Y APILAMIENTO (MATERIAL - CANTERA) m303.04.01 1.54 173,931.00

    112,942.21ZARANDEO DE MATERIAL EN CANTERA m303.04.02 1.49 168,283.89112,942.21CARGUIO DE MATERIAL DE CANTERA m303.04.03 1.43 161,507.36112,942.21TRANSPORTE DE MATERIAL DE PRESTAMO m303.04.04 1.61 181,836.96

    112,942.21CONFORMACION DE TERRAPLENES CON MATERIAL DE PRESTAMO m303.04.05 2.37 267,673.0411,294.22RIEGO PARA RELLENO m303.04.06 8.19 92,499.66

    03.05 786,712.10MEJORAMIENTO SUB RASANTE C/MAT. CANTERA172,169.27PERFILADO Y COMPACTADO DE SUB-RASANTE m303.05.01 1.43 246,202.06

    58,376.72EXTRACCION Y APILAMIENTO (MATERIAL - CANTERA) m303.05.02 1.54 89,900.1558,376.72ZARANDEO DE MATERIAL EN CANTERA m303.05.03 1.49 86,981.3158,376.72TRANSPORTE DE MATERIAL DE PRESTAMO m303.05.04 1.61 93,986.52

    58,376.72CARGUIO DE MATERIAL DE CANTERA m303.05.05 1.43 83,478.7158,376.72CONFORMACION DE TERRAPLENES CON MATERIAL DE PRESTAMO m303.05.06 2.37 138,352.83

    5,837.67RIEGO PARA RELLENO m303.05.07 8.19 47,810.52

    04 3,542,591.41PAVIMENTOS04.01 457,673.27SUB BASE GRANULAR

    18.84TRAZO Y REPLANTEO PARA SUB BASE km04.01.01 105.53 1,988.19165,735.79PERFILADO Y COMPACTADO DE SUB-BASE m304.01.02 1.08 178,994.65

    27,028.46EXTRACCION Y APILAMIENTO (MATERIAL - CANTERA) m304.01.03 1.54 41,623.8327,028.46ZARANDEO DE MATERIAL EN CANTERA m304.01.04 1.49 40,272.41

    27,028.46CARGUIO DE MATERIAL DE CANTERA m304.01.05 1.43 38,650.7027,028.46TRANSPORTE DE MATERIAL DE PRESTAMO m304.01.06 1.61 43,515.8227,028.46CONFORMACION DE SUB BASE m304.01.07 2.09 56,489.48

    2,702.85RIEGO PARA SUB BASE m304.01.08 20.77 56,138.19

    04.02 314,577.75BASE GRANULAR18.84TRAZO Y REPLANTEO PARA BASE km04.02.01 105.53 1,988.19

    19/10/2009 04:04:49p.m.Fecha :

  • S10 Pgina 2

    PresupuestoMEJORAMIENTO DE LA CARRETERA JULIACA - COATA - CAPACHICA - PUSI - TARACO, EMP.R.3S ( ILLPA ) - HUATA -COATA

    0403003Presupuesto

    TRAMO II : COATA - CAPACHICA001SubpresupuestoGOBIERNO REGIONAL PUNO 28/07/2009Costo alCliente

    Lugar PUNO - PUNO - CAPACHICA

    Precio S/. Parcial S/.Item Descripcin Und. Metrado

    146,380.82PERFILADO Y COMPACTADO DE BASE m304.02.02 0.68 99,538.96

    20,091.54EXTRACCION Y APILAMIENTO (MATERIAL - CANTERA) m304.02.03 1.54 30,940.9720,091.54CARGUIO DE MATERIAL DE CANTERA m304.02.04 1.43 28,730.9020,091.54ZARANDEO DE MATERIAL EN CANTERA m304.02.05 1.49 29,936.39

    20,091.54TRANSPORTE DE MATERIAL DE PRESTAMO m304.02.06 1.61 32,347.3820,091.54CONFORMACION DE BASE m304.02.07 2.41 48,420.61

    2,009.15RIEGO PARA BASE m304.02.08 21.24 42,674.3504.03 720,356.59IMPRIMADO

    18.84TRAZO Y REPLANTEO DE IMPRIMADO km04.03.01 62.66 1,180.51

    1,148.00EXTRAC. C/EQUIPO DE ARENA PARA IMPRIMADO m304.03.02 5.25 6,027.001,148.00CARGUIO DE ARENA PARA IMPRIMADO m304.03.03 3.59 4,121.32

    1,148.00TRANSPORTE DE ARENA PARA IMPRIMADO m304.03.04 8.62 9,895.76114,800.00IMPRIMADO RIEGO ASFALTICO RC-250 m204.03.05 6.09 699,132.00

    04.04 740,514.58PRIMERA CAPA 3/4"18.84TRAZO Y REPLANTEO 1RA CAPA 3/4" km04.04.01 105.53 1,988.19

    5,014.97CARGUIO PIEDRA CHANCADA DE 3/4" m304.04.02 3.59 18,003.74

    5,014.97TRANSPORTE DE PIEDRA CHANCADA DE 3/4" m304.04.03 6.54 32,797.90124,870.02TRATAMIENTO SUPERFICIAL 1RA CAPA DE 3/4" m204.04.04 5.50 686,785.11

    18.91CONTROL DE TRAFICO Y EXUDACION km04.04.05 49.69 939.6404.05 759,453.39SEGUNDA CAPA 3/8"

    18.84TRAZO Y REPLANTEO 2DA CAPA 3/8" km04.05.01 105.53 1,988.19

    5,064.86CARGUIO PIEDRA CHANCADA DE 3/8" m304.05.02 3.59 18,182.855,064.86TRANSPORTE DE PIEDRA CHANCADA DE 3/8" m304.05.03 8.54 43,253.90

    126,150.42TRATAMIENTO SUPERFICIAL 2DA CAPA m204.05.04 5.51 695,088.8118.91CONTROL DE TRAFICO Y EXUDACION km04.05.05 49.69 939.64

    04.06 550,015.83SELLO ASFALTICO126,150.42SELLO ASFALTICO m204.06.01 4.36 550,015.83

    05 21,793.88TRANSPORTE5,922.25TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE m305.01 3.68 21,793.88

    06 996,650.78OBRAS DE ARTE Y DRENAJE06.01 31,278.22CUNETAS

    540.89EXCAVACION PARA CUNETA m306.01.01 14.19 7,675.23951.35ENCOFRADO CON SERCHAS PARA CUNETAS m206.01.02 24.81 23,602.99

    06.02 965,372.56ALCANTARILLAS TIPO TMC518.34CONCRETO F'C=175 KG/CM2 CUNETA REVESTIDA m06.02.01 127.87 66,280.14

    3,455.60PERFILADO Y COMPACTADO PARA CUNETAS m206.02.02 1.27 4,388.614,756.73JUNTAS DE CONSTRUCCION Y DILATACION DE CUNETAS m06.02.03 11.29 53,703.48

    06.02.04 146,220.02TRABAJOS PRELIMINARES2,390.00DSVIO PARA ALCANTARILLAS km06.02.04.01 16.88 40,343.20

    437.46DEMOLICION DE ALCANTARILLA EXISTENTE m306.02.04.02 48.68 21,295.55

    591.83ELIMINACION DE MATERIAL EXCEDENTE m306.02.04.03 71.32 42,209.321,988.36TRAZO, NIVEL Y REPLANTEO CON INSTRUMENTOS km06.02.04.04 21.31 42,371.95

    06.02.05 133,947.39MOVIMIENTO DE TIERRAS1,959.10EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m306.02.05.01 16.56 32,442.701,647.45RELLENO DE ESTRUCTURAS CON MATERIAL DE PRESTAMO m306.02.05.02 14.93 24,596.43

    2,448.88ELIMINACION MATERIAL EXCEDENTE m306.02.05.03 30.88 75,621.41841.08CAMA DE APOYO m306.02.05.04 1.53 1,286.85

    06.02.06 280,620.64OBRAS DE CONCRETO SIMPLE3,080.76ENCOFRADO Y DESENCOFRADO EN ALCANTARILLAS m206.02.06.01 54.97 169,349.38

    5,276.20ACERO DE FY=4200 KG/CM2 kg06.02.06.02 4.20 22,160.04493.09CONCRETO F'C=175 KG/CM2, EN ALCANTARILLAS m306.02.06.03 180.72 89,111.22

    06.02.07 280,212.28VARIOS217.06PINTADO m206.02.07.01 4.99 1,083.13245.00SUMINISTRO E INSTALACION ALCANTARILLA TMC 36" m06.02.07.02 551.11 135,021.95

    78.75SUMINISTRO E INSTALACION ALCANTARILLA TMC 48" m06.02.07.03 661.91 52,125.41

    19/10/2009 04:04:49p.m.Fecha :

  • S10 Pgina 3

    PresupuestoMEJORAMIENTO DE LA CARRETERA JULIACA - COATA - CAPACHICA - PUSI - TARACO, EMP.R.3S ( ILLPA ) - HUATA -COATA

    0403003Presupuesto

    TRAMO II : COATA - CAPACHICA001SubpresupuestoGOBIERNO REGIONAL PUNO 28/07/2009Costo alCliente

    Lugar PUNO - PUNO - CAPACHICA

    Precio S/. Parcial S/.Item Descripcin Und. Metrado

    105.00SUMINISTRO E INSTALACION ALCANTARILLA TMC 72" m06.02.07.04 824.11 86,531.55

    50.84EMBOQUILLADO DE PIEDRA m306.02.07.05 12.79 650.241.00PREPAR. Y ROTURA DE BRIQUETAS glb06.02.07.06 2,800.00 2,800.001.00PRUEBA CONTROL DE COMPACTACION glb06.02.07.07 2,000.00 2,000.00

    07 76,901.46SEALIZACION19.00HITOS KILOMETRICOS u07.01 96.66 1,836.54

    2.00SEALES INFORMATIVAS u07.02 320.14 640.2811.00SEALES PREVENTIVAS u07.03 53.62 589.825.00SEALES REGLAMENTARIAS u07.04 320.14 1,600.70

    83.00POSTES DELINEADORES u07.05 46.95 3,896.854,588.89MARCAS EN EL PAVIMENTO m207.06 10.70 49,101.12

    135.00GUARDAVIAS m07.07 142.49 19,236.15

    08 12,723.93IMPACTO AMBIENTAL08.01 5,875.00TRABAJOS DE CONSERVACION EN BOTADEROS Y CANTERAS

    2,500.00RECOMPOSICION DE CANTERAS m208.01.01 2.35 5,875.00

    08.02 778.56PROGRAMA PREVENTIVO CORRECTIVO3.00SEALIZACIONES AMBIENTALES u08.02.01 259.52 778.56

    08.03 6,070.37TRABAJOS DE RESTAURACION2,300.00RESTAURACION DE AREA AFECTADA POR CAMPAMENTO m208.03.01 2.57 5,911.00

    1.00SELLANDO DE LETRINAS u08.03.02 159.37 159.37

    09 24,916.61FLETE1.00FLETE DE MATERIALES VARIOS glb09.01 24,916.61 24,916.61

    COSTO DIRECTO 6,732,530.97

    ================================================ ===================GASTOS GENERALES ( 5.64 % ) 379,554.60

    UTILIDAD ( 9 % ) 605,927.79================================================ ===================SUB TOTAL 7,718,013.36

    I.G.V. ( 19 % ) 1,466,422.54================================================== ===================PRESUPUESTO PARCIAL DE LA OBRA 9,184,435.90

    SON : NUEVE MILLONES CIENTO OCHENTICUATRO MIL CUATROCIENTOS TRENTICINCO Y 90/100 NUEVOS SOLES

    19/10/2009 04:04:49p.m.Fecha :