6
Press Note th 4 November 2013 Nagole to Meuguda Miyapur to S R Nagar Meuguda to Begumpet Begumpet to Shilparamam SR Nagar to Osmania Medical College Osmania Medical College to LB Nagar Parade Grounds to Narayanguda Unit of Measurement 1
Transcript of Press Note Final - Microsoft€¦ · Press Note 4th November 2013 Nagole to Meuguda Miyapur to S R...
Press Noteth 4 November 2013
Nagole to Me�uguda
Miyapur to S R Nagar
Me�uguda to Begumpet
Begumpet to Shilparamam
SR Nagar to Osmania Medical College
Osmania Medical College to LB Nagar
Parade Grounds to Narayanguda
Unit of Measurement
1
Total No. Spans
As on date
As on date
2
-
-
Highlights1000 founda�ons completed as on date.
st500 days for the first COD - 21 March 2015 - Stage 1 Nagole to Me�uguda