Community Presentation Community Resources August 11, 2010 1 Community Resources Project Status

Transcript of Presentation to the Community on CBE Progress - August 2010

Page 1: Presentation to the Community on CBE Progress - August 2010

Community PresentationCommunity Resources

August 11, 2010

1Community Resources Project Status

Page 2: Presentation to the Community on CBE Progress - August 2010

Purpose of Meeting

Present progress of Center for Business & Education (CBE) developmentLink to Visioning resultsCommunicate with community Opportunity for questions, comments

2Community Resources Project Status

Page 3: Presentation to the Community on CBE Progress - August 2010

Agenda

Introduction to Community ResourcesCenter for Business & Education (CBE)

Public ProcessesCurrent Status Next Steps

Mixed Commerce Zoning UsesQuestions and Comments

3Community Resources Project Status

Page 4: Presentation to the Community on CBE Progress - August 2010

Intro to Community Resources

Mission: Attract, retain, and expand businesses in the Yellow Springs & Miami Township regionFocus on commercial, educational, office, professional,and manufacturingIntroduce members: Lisa Abel, Megan Bachman, David Boyer, Mark Crockett, Matthew Derr, Michael Fishbein, Rick Kristenson, Roi Qualls, Jerry Sutton, Kathryn Van der Heiden, Karl Zalar, Judith Hempfling (ex officio), Sarah Wildman (ex officio)

4Community Resources Project Status

Page 5: Presentation to the Community on CBE Progress - August 2010

Accomplishments

Surveys Cost of livingBusiness retentionHospitality study

Land & funding for CBEAnnexation & zoning for CBERetention of Antioch University MidwestNew website: http://yscommunityresources.wordpress.com/

5Community Resources Project Status

Page 6: Presentation to the Community on CBE Progress - August 2010

Tie to Visioning Results

CR works on planned and intentional economic development Focus is to increase local tax base CBE helps to increase potential business properties Plan to attract entities that provide living wage employment

6Community Resources Project Status

Page 7: Presentation to the Community on CBE Progress - August 2010

CBE: Public ProcessesCooperative Economic Development Agreement (CEDA) approval – for commercial development, not housing or retailEconomic development revolving loan fund & other grantsAnnexation of CBE land to VillageZoning of CBE – mixed commerceFederal grant process & awardVillage authority for infrastructure project

7Community Resources Project Status

Page 8: Presentation to the Community on CBE Progress - August 2010

CBE Funding

Federal grant60%EDRLF

16%

Local grant10%

DDC grant9%

CF grant5%

Page 9: Presentation to the Community on CBE Progress - August 2010

CBE: Current Status

OH DoT Project protocolDesign Phase 1 completed

Design alternativesPreliminary design of roads & utilitiesRough estimate of costs & timing

Design Phase 2 startedEnd result will be detailed engineering drawings for construction bid package

9Community Resources Project Status

Page 10: Presentation to the Community on CBE Progress - August 2010

Phase 1 Design

10Community Resources Project Status

Page 11: Presentation to the Community on CBE Progress - August 2010

CBE: Next Steps & Timeline

Starting Phase 2 designDetailed design plans for roads & utilitiesOutcome: plans for constructionCompletion: estimated end of 2010-early 2011

Construction phase: most of 2011Filling the CBE

Selecting development partner nowMore focused marketing in 2010-11

11Community Resources Project Status

Page 12: Presentation to the Community on CBE Progress - August 2010

Mixed Commerce Zoning Prohibited Uses

(ref zoning chapter 1259)

Activities tending to create direct consumer trafficRetail stores, banks, barber shop, grocery, hardware,clothing, drug store, laundry services, gas station, theatre, auto repair, bowling alley

Living spaces, permanent or temporary:Houses, apartments, nursing homes, motels

12Community Resources Project Status

Page 13: Presentation to the Community on CBE Progress - August 2010

Prohibited Uses

Funeral parlorsTrucking facilitiesWarehousesHeavy manufacturingAgricultureAmusement parks & facilities

13Community Resources Project Status

Page 14: Presentation to the Community on CBE Progress - August 2010

Conditionally Permitted Uses

Limited warehousing or storage of items made onsiteDay care centers primarily serving children of employees working onsiteWireless service facilities (ref chap 1280)Wholesale businesses (ref 1260.04 b or d)Retail only when accessory to primary use (e.g., AUM bookstore)

14Community Resources Project Status

Page 15: Presentation to the Community on CBE Progress - August 2010

Permitted Uses

Data processing, software developmentProfessionals & services (attorneys, accountants, insurance, financial advisors)R & D, engineering, designLight manufacturing (printing, electronics, assembly, food processing)Telemarketing

15Community Resources Project Status

Page 16: Presentation to the Community on CBE Progress - August 2010

Permitted Uses

LibraryMunicipal buildingsFire, ambulance, and police stationsEducational & training institutions (but not K-12 with playgroundsHeadquarters for various institutions

16Community Resources Project Status

Page 17: Presentation to the Community on CBE Progress - August 2010

Questions? Comments?

17Community ResourcesProject Status