Presentation outline
description
Transcript of Presentation outline
Presentation outline
1-Confidential-
Solar Water Heating Programme
Progress Report
28 February 2011
04/22/23
Presentation outline
2-Confidential-04/22/23
Strategic Plan - Intermediate Outcome 1 of 2: Demand side, efficiency and diversified energy mix programmes implemented
– In her 2009 budget vote speech, the Minister of Energy, Ms Dipuo Peters announced a target of 1 million Solar Water Heaters installed by 2014 /2015.
– The overall programme focused on both tariff and fiscal funded programmes in residential and commercial sectors.
– Initially, the SWH programme took off very slowly till mid 2010.
– The fiscal funded were are rolled out through both Schedule 6 (i.e. Direct transfer to the municipalities) and through Schedule 7 – (i.e. Transfer to Eskom as an implementing agent) of the Division of Revenue Act (DoRA) .
Presentation outline
3-Confidential-04/22/23
Strategic Plan - Intermediate Outcome 1 of 2: Demand side, efficiency and diversified energy mix programmes implemented
– In 2011/2012 financial year, the SWH programme started on a baseline of 55,000 units installed, with target of 250, 041 units.
– There was an overlap on implementation from 2010/2011 for completion of a roll out with: Tshwane, Naledi and Sol Plaatjie.
– In all the municipalities implementation was through Schedule 7 of the Division of Revenue Act (DoRA).
Presentation outline
4-Confidential-04/22/23
Implementation overlap from 2010/2011 to 2011/2012
Municipality Approved project value (m)
Planned Units
MW GWh Status Actual Units Installed
Naledi (i.e. Stella and Vryburg)
R54,450 7 837 2.2 5.9 Incomplete 1 362
Sol Plaatjie R54, 450 7 837 2.2 5.9 Installationcompleted
7837
Tshwane R74 15 094 4.2 11.9 Installationcompleted
15094
Total R182,900 30 868 8.6 22.7
Jobs created per municipality: Sol Plaatjie – 156 persons appointed; Naledi: 9 persons; Tshwane: 130 persons
Presentation outline
5-Confidential-04/22/23
Implementation challenges in Naledi Municipality
– In July 2011, water quality challenges experienced in Naledi Municipality:
• Some beneficiaries had no water connected directly to the house
which is one of the fundamental requirements to SWH installation –
this challenge was resolved by providing the required funds for water
reticulation (connection and maintenance);
• Bad roof structures and old pipes that cannot be tapped into;
• Hard water – the prevalence of hard water could have a severe
impact on the direct functionality of SWH and its lifespan;
• Naledi Municipality later confirmed the hard water condition for the
entire area;
Presentation outline
6-Confidential-04/22/23
Implementation challenges in Naledi Municipality Cont’
• Two solutions were presented:
• Solution 1: Removing calcium and iron mass;
• Solution 2: Chemically treat the water through reverse Osmosis;
• Cost breakdown for solution 1: the budget cost per SWH was R1 195
and the cost of 7 837 was R 9 365 215. 00
• Maintenance for solution 1: the filter needs to be changed as soon
as it is visibly blocked and the replacement depends on the solids
present in the raw feed to the geyser (i.e. at most within six months);
• Cost breakdown for Solution 1: Cost for filter at R25.00 and Cost of
NanoPhos at R125.80 per kg = R7 837 every six months, or to R 1 2m
• After analysing all the project challenges, it was clear that the cost
associated with water quality would make the project unviable and
that systems would need to be replaced on a regular basis.
Presentation outline
7-Confidential-04/22/23
Implementation challenges in Naledi Municipality Cont’
• Cost breakdown for solution 2: Reverse Osmosis (operates at high pressure and removes all ions, bacteria, viruses, etc).
• Solution 2 excludes maintenance and running costs.
Areas Daily Consumption Remedial Costs
Stella 6 M l R15, 000, 000.00
Huhudi 9 Ml R18, 600,000.00
Vryburg & Coldridge
18 Ml R45, 000,000.00
Dithakwaneng 2 Ml R6, 200, 000.00
Devondale 1 Ml R3, 100,000.00
Total R88, 400,000.00
Presentation outline
8-Confidential-04/22/23
Recommendations to resolve water quality problem
• Based on an analysis of all the costs presented above, projects are moved
to a new and more suitable area. All SWH Units for Naledi had already
been procured when the project was terminated.
• Selection of a new area: Relocation form Naledi to Maluti-a-Phofung.
• Free State Province had already engaged the DoE on a Business Plan to
roll out SWH Units.
• Maluti-a-Phofung was then approved to take over the roll out from Naledi
Municipality .
• Eskom has submitted a report confirming that a feasibility study is
underway prior to the start of the actual installations.
Presentation outline
9-Confidential-04/22/23
2011/2012 SWH Fiscal update
• Emfuleni , Musina and Umsobomvu approved for the current financial
year. An allocation of R54,400m each was approved for the current
financial year under schedule 7 of DoRA, whilst
• R60 million was allocated to Umsobomvu municipality, under schedule 6.
• 1st and 2nd Quarters of the financial year focused on the finalisation of the
business plans and contracts.
• A feasibility study is necessarily undertaken in each municipality to allow
clear remedial actions prior to the start of the roll out.
• Musina Municipality has appointed Roschcon to undertake the feasibility
study and Umsobomvu has issued an advertisement in January 2012 and
currently finalising the procurement process. The actual installations
planned to start in March/April 2012.
Presentation outline
10-Confidential-04/22/23
SWH Rebate Level Revision
• In June 2011, Eskom revised the claim rates due a threat on diminishing rebate funds. The above constraint prompted Eskom to review the Rebate Progamme as follows:– On 11 April 2011 Eskom announced the downward revision of the rebate
levels as shown on the table below and later approved R500 million to continue.
– :
Presentation outline
11-Confidential-04/22/23
Installations per Region
Above graph represents total installations to date, including installations received but not yet processed. This includes Eskom funded (rebate and contracts) and DoE funded (Tshwane, Sol Plaatjie and Naledi).
Presentation outline
12-Confidential-04/22/23
No. SWH MW GWhHP 42,207 21 110 LP 168,830 17 89
211,037 38 199
SWH installation inception to date - Dec 2011
Installations to date
Presentation outline
13-Confidential-04/22/23
Standard Offer Model Update
• Concept of the Standard Offer Model has been finalised;
• A one year Business Plan for SWH Pilot phase has been completed and
ready for approval and implementation as of 1 April 2012;
• The SO implementation will start with the roll out of about 250 000
units within the allocated R1 billion.
Presentation outline
14-Confidential-04/22/23
Standard Offer Model Recap
• The Standard Offer Concept is based on the energy savings to be derived from an initiative, irrespective of the technology applied to achieve such savings. It is an intervention that is outcome based with the incentive flowing after delivery of the intervention, and subject to verification of the savings. The solar water heating system will have a deemed savings value. It is envisaged that the rebate will be attractive initially, in order to kick-start the market. Over time, it is predicted that costs will be reduced through economies of scale.
Pool of funding required to service
debt
Funding requirements
Fiscal
Carbon Credit
MYPD
Grants
Owner /user
Source of immediate
funding
Commercial Debt
Concessionary Debt
To be obtained
from
Total funding required for Solar
Water Heating units
Cost of installed
units (making allowance for reduced cost
due to volume)
Interest on debt
To be serviced
by
15
Presentation outline
16-Confidential-04/22/23
Cost Benefit Analysis
Residential market targets Total Potential %
Reducing electricity
demand MW
Universal access
Offset rising electricity cost
Accelerated service delivery
Renewable energy targets
GWh/annum
Climate change
'000 tons
Upper income geyser replacement560,000 1,200,000 47% 347
Completely equitable across the markets. Plus
frees grid capacity
<60% of water heating costs
672 679
Mid/low income geyser replacement1,750,000 3,000,000 58% 1,085
<70% of water heating costs
Major impact
2,100 2121
Non Geyser delivery2,690,000 6,600,000 41% 1,668
<80% of water heating costs
Major impact
3,228 3260Insurance geyser replacement 55,000 0 34 66 67New build 110,000 0 68 132 133
5,165,000 10,800,000 48% 3,202 6,000 6,060
Residential market targets Total Potential %
Reducing electricity
demand MW
Access across all markets
Offset rising electricity cost
Accelerated service delivery
Renewable energy targets
GWh/annum
Climate change
'000 tons
Upper income geyser replacement236,500 1,380,000 17% 142
Completely equitable across the markets. Grid
capacity freed
<60% of water heating costs
284 358
Mid/low income geyser replacement440,259 3,550,000 12% 264
<70% of water heating costs
Major impact
528 1248
Non Geyser delivery383,389 6,320,000 6% 115
<80% of water heating costs
Major impact
460 842Insurance geyser replacement 31,343 19 38 91New build - SWH over geyser 123,631 74 148 182New build -non geyser delivery 142,000 43 1,458 2,721
1,357,122 11,250,000 12% 657
Presentation outline
17-Confidential-04/22/23
Cost Benefit AnalysisProgramme MYPD Subsidy Needs
Residential market targets 2010 2011 2012 2013 2014 2015
Upper income geyser 92,089,800 143,250,800 255,805,000 270,130,080 252,735,340 212,829,760
150 litre SWH System 10,788,525 16,782,150 29,968,125 31,646,340 29,608,508 24,933,480
200 litre SWH System 49,838,085 77,525,910 138,439,125 146,191,716 136,777,856 115,181,352
250 litre SWH System 9,468,360 14,728,560 26,301,000 27,773,856 25,985,388 21,882,432
300 litre SWH System 21,994,830 34,214,180 61,096,750 64,518,168 60,363,589 50,832,496
Mid/low income geyser 76,708,800 150,409,412 270,736,941 391,064,471 451,228,235 752,047,059
Closed coupled 61,367,040 120,327,529 216,589,553 312,851,576 360,982,588 601,637,647
Split unit 15,341,760 30,081,882 54,147,388 78,212,894 90,245,647 150,409,412
Non Geyser delivery 14,016,324 60,834,740 134,761,117 225,407,313 363,159,065 730,016,883
100lt Roof mounted 8,806,068 38,220,779 84,666,670 141,617,160 228,162,764 458,649,351
100lt Pole mounted 4,403,034 19,110,390 42,333,335 70,808,580 114,081,382 229,324,675
55lt Pole with hand pump 807,223 3,503,571 7,761,111 12,981,573 20,914,920 42,042,857
Insurance replacement 11,475,403 26,775,940 33,469,925 33,661,182 29,071,021 24,480,860
Totals 194,290,327 381,270,892 694,772,983 920,263,046 1,096,193,662 1,719,374,562
Programme MYPD CDM Needs
Residential market targets 2010 2011 2012 2013 2014 2015
Upper income subsidy 0 0 0 0 0 0
150 litre SWH System 0 0 0 0 0 0
200 litre SWH System 0 0 0 0 0 0
250 litre SWH System 0 0 0 0 0 0
300 litre SWH System 0 0 0 0 0 0
Mid/low income geyser 77,333,357 151,634,033 272,941,259 394,248,486 454,902,099 758,170,165
Closed coupled 61,866,685 121,307,226 218,353,007 315,398,789 363,921,679 606,536,132
Split unit 15,466,671 30,326,807 54,588,252 78,849,697 90,980,420 151,634,033
Non Geyser delivery 10,502,649 45,584,416 100,978,597 168,901,200 272,120,727 547,012,987
100lt Roof mounted 6,301,590 27,350,649 60,587,158 101,340,720 163,272,436 328,207,792
100lt Pole mounted 3,150,795 13,675,325 30,293,579 50,670,360 81,636,218 164,103,896
55lt Pole with hand pump 1,050,265 4,558,442 10,097,860 16,890,120 27,212,073 54,701,299
Insurance replacement 0 0 0 0 0 0
Totals 87,836,006 197,218,449 373,919,857 563,149,686 727,022,826 1,305,183,152
Presentation outline
18-Confidential-04/22/23
SWH: Localisation
• Government and our social partners signed a Green Economy Accord on 17
November 2011, as an outcome of social dialogue on the New Growth Path.
• The Accord has been signed on behalf Organised Labour, Business, Community
and Government.
• The Green Economy Accord recognise that the installation of SWH systems can
help with climate-change goals and increase the number of South Africans who have
access to hot water while creating jobs in manufacturing and installation.
• Business committed to working with Government to develop, establish and then
publicise a sustainable funding plan to support the installation of 1 million SWH
systems.
• It should be noted that the success of localisation within the Green Economy Accord
depends on its implementation together with other Accords such as Local
Procurement Accord, National Skills Development Accord and Basic Education
Accord because of cross cutting elements
Presentation outline
19-Confidential-04/22/23
SWH: Localisation
• The following localisation issues are addressed under Commitment One (Green
Economy Accord):
• Increase the rollout to one million units: In order to achieve the targets for
SWH installations, it will require financing, enterprise development, training and
policy coordinated across all stakeholders. Business committed to working with
Government to develop, establish and then publicise a sustainable funding
plan to support the installation of 1 million SWH systems
• Improve localisation of the components: All parties commit to the drive to
increased localisation of the components of the SWH systems. Government
committed to ensure that incentives and regulatory measures are in place to
promote greater local manufacturing of components of the SWH systems.
Specific opportunities for localisation to be identified and support localisation
accordingly
• Secure support from the industry for replaced units: Approximately 200
000 electric geysers are replaced annually by householders through payments
via the insurance industry, to promote the use of locally-manufactured SWH for
replacement of a damaged electric hot-water geyser
Presentation outline
20-Confidential-04/22/23
SWH: Localisation...
• Secure support from the industry for replaced units : Business will work
with the insurance industry to approve a manageable selection of suitable
systems to be used by insurers. Business will implement a pilot by 2012
followed by a wider SWH roll-out by the insurance industry in 2013.
• Secure guarantees on installed units: The parties identified a potential risk
with the guarantees on the SWH units, particularly i.r.o start up companies who
may no longer be in business when warranties needed to be honoured.
Business, government and various funding institutions including Eskom are
engaging to develop proposals on warranty systems, standards and funding
mechanisms to address this risk.
• Promote the marketing of SWH systems: The parties recognise that it is
imperative that consumers embrace the technological shift to SWH. Business
therefore committed to develop with Government as well as organised labour
and community organisations, national communication campaign, linked to
local community initiatives and campaigns like Lead SA, Proudly SA and 49m,
to educate South Africans about SWH and its benefits
Presentation outline
21-Confidential-04/22/23
SWH: Localisation...
• The following localisation issues are addressed under Commitment One of the
Green Economy Accord:
• Promote uniform technical and performance standards for SWH: The
parties recognised that given South Africa’s unique climate conditions, the
need to develop local standards for the different component parts of SWH, in
order to not only support local technological development, but to also ensure
that we can facilitate the introduction of imported technologies for local
manufacturers. Government committed to develop the standards for the
different components that make SWH units, through SABS. Business
undertook to support the development of local standards for SHW at
component level.
Presentation outline
22-Confidential-04/22/23
SWH Allocation for 2012/13 – 2014/2015
• An amount of R 4.7 billion has been allocated to achieve 1 million SWH units by
2014/2015
Financial Year Amount (R)
2012/2013 1 billion
2013/2014 1.7 billion
2014/2015 2 billion
Presentation outline
23-Confidential-04/22/23
Conclusion
• Progress made to date on the Solar Water Heating programme,
challenges encountered and they are being resolved;
• That from the above figures, it is evident that the cumulative target of
250, 041 installations for the current financial year is still in sight
given that about 82% of the targeted units have been installed.
• Budget allocated to achieve 1 million SWH units by 2014/2015.
• Commitments already made with respect to the Green Economy
Accord to address the localisation issues to create more jobs.
• That work is in progress with all stakeholders to intensify the
operationalisation of all identified key factors to localisation.
• Energy savings will only be improved through penetration of high end
market, through the Standard Offer Concept