Presentation on Visakhapatnam PCPIR · Source: Paradip 284.15 sq.km Visakhapatnam - Kakinada 640...
Transcript of Presentation on Visakhapatnam PCPIR · Source: Paradip 284.15 sq.km Visakhapatnam - Kakinada 640...
ANDHRA PRADESH – OVERVIEW
GSDPCurrent price (2017-18)
USD 125.6 billion
GSDP Growth Rate YoY (2017-18)
16%
Population(Census 2011)
49.4 million
Population in Working Age Group
70%
Literacy Rate
67.4%
Coastline length
974 km
No. of SEZs
19
EODB Rank(2017)
1
Source: www.indiachem.in
Paradip
284.15 sq.km
Visakhapatnam - Kakinada640 sq.km
Cuddalore and Nagapattinam
256.83 sq.km
Dahej
453 sq.km
VISAKHAPATNAM PCPIR – ANDHRA PRADESH
❑ Largest Petrochemical Hub of India,
covering 640 sq.km with total population
of 3.23 lakhs (2011 census)
❑ Well connected with all possible modes of
transport (Air, Rail, Road and Sea). Also
lies on the “Golden Quadrilateral”
❑ Currently under the management of
Special Development Authority (SDA),
formed under G.O. Ms. No, 373 in 2008,
which is chaired by the Managing Director
APIIC (Nodal Agency)
VISAKHAPATNAM PCPIR – SIGNIFICANCE
VK – PCPIR Boundary
National Highway
Railway line
Urban Centers
Visakhaptnam
Anakapalle
ParawadaYellamanchili
Tuni
Pithapuram
SamalkotKakinada
❑ Strategically connected with
✓ Airport – Visakhapatnam International Airport
✓ Rail – Chennai – Howrah main line
✓ Road – NH 16 & NH 216
✓ Sea – Visakhapatnam port, Gangavaram port, Kakinada Anchorage port and Kakinada Deep water port
❑ Special significance – proximity to urban centers including Visakhapatnam, Kakinada and other major towns
Gangavaram Port
Visakhapatnam Port
Kakinada Port
VISION FOR VK - PCPIR
VKIC PCPIR should project Andhra Pradesh as largest Petro Chemical hub of India by
➢ Conserving and Protecting Eco sensitive areas
➢ Guided Development for Industries
➢ Promoting green technologies and energy efficient mechanisms
➢ Ensure better transport connectivity
➢ Planned urban development for Non processing area
PROPOSED VK-PCPIR MASTER PLAN 2031 - PARAMETERS
❑ Residential Townships
❑ Industrial Clusters
❑ Expressway and Major Transport Network
❑ Knowledge Hubs
PROPOSED MASTER PLAN
Knowledge Hubs
Visakhapatnam Zone
Total Area : 33,450 Ha
Total processing Area : 16,618 Ha
Occupied Area: 4990 Ha
Area Under Expansion to be Developed:
4173 Ha
Unoccupied Area: 2280 Ha
Others (Circulation area , Open spaces,
etc.): 5173 Ha
Nakkapalli Zone
Total Area : 15,820 Ha
Total processing Area : 5280 Ha
Occupied Area: 60 Ha
Area Under Expansion to be
Developed: 5055 Ha
Unoccupied Area: 141 Ha
Others (Circulation area , Open
spaces, etc.): 23 Ha
Kakinada Zone
Total Area : 14,730 Ha
Total processing Area : 5667 Ha
Occupied Area: 436 Ha
Area Under Expansion to be
Developed: 4684 Ha
Unoccupied Area: 331 Ha
Others (Circulation area, Open
spaces, etc.): 230 Ha
ZONES OF VK-PIPIR
Area : 147.3 sq.km. (23% ) Area : 158.2 sq.km. (25% ) Area : 334.5 sq.km. (52% )
Total Area : 640 sq.km.
PROJECT COMPOSITION – INDUSTRIAL MIXS. No. Industrial Cluster
Ownership and IndustrialArea Status
Existing Product Mix Proposed Industrial Mix
Visakhapatnam PCPIR Zone
1 RINL RINL Steel and Downstream Industries Steel and Downstream Industries
2 NTPC and HNPCL NTPC & HNPCL Power Generation Power Generation
3 JNPCRAMKEY SEZ
Pharmaceuticals Pharmaceuticals
4 AP SEZAPIDC, GoAPSEZ
Petrochemical, Chemicals, Textiles, Engineering, Metal and Non-Metallic, Mixed Industries etc.
Petrochemical, Chemicals, Metal and Engineering, Textiles, Petroleum Refinery, Metal and Non Metallic, Mixed Industries etc.
5AP SEZ Expansion Area, Pudi IC, Krishnapalem IC
GoAPSEZ
-Mixed Industries, Metal and Engineering Industries, Chemical Industries
Nakkapalli PCPIR Zone
5 Nakkapalli APIDC, GoAPPetrochemicals (HETERO SEZ)
Petrochemical, Chemicals, Textiles, Metals andLight Engineering, Food Processing, MixedIndustries.
6 Payakaraopeta APIDC, GoAP -Food Processing, Light Engineering, Mixed and Non- Polluting Industries.
Kakinada PCPIR Zone
7 Kakinada SEZKakinada SEZ Pvt. LtdSEZ
-Petrochemical, Chemicals, Petroleum Refinery, Downstream Industries, Power Generation, Mixed Industries etc.
8 Other Industrial ClustersSPCL, APIDC,Coromandel InternationalLimited Pvt. Ltd.,
Chemicals, Food Processing, Fisheries
Chemicals, Food Processing, Fisheries, otherNon-polluting industries.
Kakinada- Potential for development of petrochemical hub
KAKINADA ZONE
❑ Land availability: About 6,750 Ha of land remains available for allotment for industrial operations in the KSEZ with total of 9,120 Ha of allottable land available in the Kakinada region for establishment of petrochemical downstream industries.
❑ Anchor unit: Haldia Petro Chemicals and HPCL in JV with GAIL with proposed investment in Kakinada would serve as the anchor unit with supply of required feedstock
❑ Dedicated Infrastructure: Development of PCPIR expressway would connect the Kakinada to markets in and outside the PCPIR region. Development of VCIC would further improve the connectivity of the region and thereby boost the industrial development in Kakinada
❑ Port availability: The proposed GMR Port in the region, dedicated liquid cargo handling facility would provide the proposed petrochemical units/ industries with required access to global markets
❑ Water supply: 40 MGD of assured water supply from the Godavari perennial river
❑ Power supply: The proposed GMR power plants would be providing uninterrupted 40 MGD supply for supporting industrial operations in the region
❑ Feed Availability: Discovery of K.G. Basin in the region can serve as a dedicated source of feed for petrochemical industries in the region, eliminating the import dependency
ROAD CONNECTIVITY OF VK-PCPIR
Proposed Major Roads
PCPIR Expressway
National Highway
State Highway
National Highway – 16 Golden Quadrilateral
State Highway – 16 Connector to Vizag City
National Highway – 214
ADB RoadConnector from Port to NH - 16
Proposed VK-PCPIR Expressway
RAIL CONNECTIVITY OF VK-PCPIR
Proposed HNPCL – SCR Trunk Line
Proposed KSEZ – SCR Trunk Line
Chennai – Howrah Trunk Line – SCR
AIR CONNECTIVITY OF VK-PCPIR
Visakhapatnam International Airport
Rajahmundry Airport(Upgradation Plans)
Proposed BhogapuramInternational Airport
PORT CONNECTIVITY OF VK-PCPIR
Visakhapatnam Port
Gangavaram Port
Proposed Mutyalammapalem Port
Proposed Dedicated Port for Kakinada SEZ
Kakinada Deep Water Port
Kakinada Anchorage Port
UTILITY - WATER SOURCE
Polavaram Canal Capacity 1124 mld
Nakkapalli Zone
Demand – 224 mld
Kakinada Zone
Demand – 484 mld
Visakhapatnam Zone
Demand – 1106 mld
Godavari Tapping Point
Samalkota Canal
10
16
mld
10
8 m
ld
11
6 m
ld
13
9 m
ld34
5 m
ld
Polavaram Canal (Proposed)
90 mldGVMC Recycled
Sewage Water
Godavari River (Direct tapping 255 mld from River)
Samalkota Canal, Capacity 345 mld
UTILITY – POWER & SOCIAL INFRASTRUCTURE
❑ NTPC, NHPCL and SPGL are the major power projects. Existing power facilities for supporting industrial operations across various industrial clusters/SEZs include:
➢ 220/132 KV substation for APSEZ
➢ 220/132 KV substation for Brandix SEZ
➢ 220/132 KV substation for Pharma SEZ
➢ 33/11 KV supply in KSEZ with 220/132 KV substation proposed under VCIC scheme
❑ Various power projects proposed to meet the future power requirement include:
➢ 220/132 KV substation for Nakkapally Cluster under VCIC scheme
➢ 132 KV substation proposed in Rambilli Cluster under VCIC scheme
❑ At present, about 3,472 Ha of land is
under development of residential
estate, which is further proposed to
extend as per the master plan with
proposed land already identified for
residential township in all three zones
❑ Infrastructure for public utilities and
facilities is being implemented in the
region
❑ Development of knowledge hubs
across all zones is proposed for skill
development
Power: Social Infrastructure:
FEEDSTOCK
Anchor tenant: HPCL/ GAIL
Feedstock availability:
❑ HPCL refinery in Visakhapatnam has installed capacity of 8.33 MMTPA. The refinery is one of the first major industries of Visakhapatnam and first oil refinery on the East Coast
❑ The tenant is dedicated to processing of a wide range of petroleum products, viz. LPG, MS, SKO, ATF, HSD, Bitumen etc. and various grades of lubricants, specialties and greases as per BIS standard.
❑ Expansion as proposed by the tenant include:➢ Refinery capacity: Expansion from 8.33 to15 MMTPA➢ Hydrocracker unit (FCHCU) with a capacity of 3.053 MMTPA-as
a part of the Visakha Refinery Modernization Project (VRMP)➢ Olefins and Aromatics Complex proposed at APSEZ
Visakhapatnam
HPCL/ GAIL
HPCL in JV with GAIL has plansfor a greenfield refinery project(1.5 MMTPA petrochemicalcomplex) in Kakinada at aninvestment of US$ 4.29 bn
Haldia Petro-Chemicals
Proposes to setup a refinery inKakinada SEZ at an investment ofUS$ 11.43 bn.
Upcoming Anchor Projects: