Practical legal aspects for implementation of projects under “green” tariff
danevychlaw.com
International Energy Forum in Zaporizhya
11 September 2013Zaporizhia, Ukraine
Legislative incentives for development of renewables in Ukraine
Rates of “green” tariff for electricity from various types of renewables
Rates change/decrease in the future
Local content for “green” tariff projects
Procedure and main requirements/conditions for getting “green” tariff
danevychlaw.com
CONTENT
Strong international focus
Actively involved into green energy legal environment
IFC expert on “green” tariff mapping in Ukraine
Legal expert and partner of Ukrainian Bioenergy Association and Ukrainian Wind Energy Association
We are proud to provide Clients with services which make the environment better and the economy of Ukraine stronger
danevychlaw.com
DANEVYCH law firm
Tax incentives under the Tax Code exemption from import VAT and customs dutiesdecrease of land tax for bioenergy power plants by 75%limits for rental payments for lands lease from state and municipal authorities by 3% of appraisal valueexemption from CPT of
profit from main activity of companies in the energy sphere which produces electricity only from renewable till 2021profit from simultaneous production of electricity and heat and/or heat from biofuels till 2020
Possibility to use JI under Kyoto Protocol for biomass/biogas energy projects
The mechanism of the "green" tariff (GT)
danevychlaw.com
Incentives for development of bioenergy projects
All alternative energy sources, except for blast furnace and coke oven gas, and hydroelectric power plants over 10 MW
However, only certain alternative energy sources have a legally guaranteed level of “green” tariff (tables below)
For all other alternative energy sources NERC sets “green” tariff at its discretion at substantiated level
a relatively low level
danevychlaw.com
The coverage of «green» tariff
GT rate for solar
Categories eligible to GT
Rate of the tariff (€ / kW) depending on commissioning date
till 31.03.2013
inclusively
from 01.04.201
3 till 31.12.201
4
from 01.01.20
15 till 31.12.20
19
from 01.01.20
20 till 31.12.20
24
from 01.01.202
5 till 31.12.202
9
Electricity of solar power plants (SPPs) on lands
0,46526 0,33926 0,30533 0,2714 0,23748
Electricity of SPPs on the roofs of buildings or on facades of constructions with power capacity more than 100 kW
0,44588 0,34895 0,314053 0,27916 0,24426
Electricity of SPPs installed on the roofs of buildings or on facades of constructions with power capacity not more than 100 kW
0,42649 0,35864 0,322777 0,28691 0,25105
Electricity of SPPs on the roofs of buildings or on facades of private households with power capacity not more than 10 kW
- 0,35864 0,322777 0,28691 0,25105
* Expected to take effect on 01.01.2014
GT rate for wind
Categories eligible to GT
Rate of the tariff (€ / kW) depending on commissioning date
till 31.03.2013
inclusively
from 01.04.2013 till
31.12.2014
from 01.01.20
15 till 31.12.20
19
from 01.01.20
20 till 31.12.20
24
from 01.01.20
25 till 31.12.20
29Electricity of
wind farms with turbines* up to
600 kW
0,06462
0,06462
0,058158 0,0517
0,04523
Electricity of wind farms with turbines* from 600 to 2000 kW
0,07539 0,07539 0,067851 0,06031 0,05277
Electricity of wind farms with
turbines* 2000 kW and more
0,11309 0,11309 0,101777 0,09047 0,07916
*GT rates are determined and depends on the power of wind farm till 01.04.2013
GT rate for bioenergy
Categories eligible to
GT
Rate of the tariff (€ / kW) depending on commissioning date
till 31.03.201
3 inclusively
from 01.04.2013
till 31.12.2014
from 01.01.201
5 till 31.12.201
9
from 01.01.202
0 till 31.12.202
4
from 01.01.202
5 till 31.12.202
9
Electricity from
biomass 0,12386 0,12386 0,11147 0,09908 0,0867
Electricity from
biogas - 0,12386 0,11147 0,09908 0,0867
GT for small hydro power plants ( up to 10 MW)
Categories eligible to GT
Rate of the tariff (€ / kW) depending on commissioning date
till31.03.2013
inclusively
from 01.04.201
3 till 31.12.201
4
from 01.01.201
5 till 31.12.201
9
from 01.01.202
0 till 31.12.202
4
from 01.01.202
5 till 31.12.202
9
Micro hydro power plants (up to 200 kW)
0,11632 0,19386 0,174474 0,15509 0,1357
Micro hydro power plants (from 200 kW to 1 mW)
0,11632 0,15509 0,139579 0,12407 0,10856
Small hydro power plants (from 1 mW to 10 mW)
0,11632 0,11632 0,104684 0,09305 0,08142
In the middle of 2009 the core legislation on the current feed-in tariff scheme (GT) was enacted
As of beginning of August 2013 GT is established for 96 companies operating 153 power plants
danevychlaw.com
Current statistics
Why don’t so much as it could be?!
121351 86
Solar power plants with power capacity not more than 10 kW
Not subject to electricity licensing
The procedure of selling and counting such electricity and settlements for it shall be approved by NERC
There is no a project or even understanding how to implement it
Electricity distributors at regulated tariffs are obliged to purchase electricity in the excess of monthly consumption of electricity.
What is “monthly consumption”?
Result: No boom of small SPPs
danevychlaw.com
Expected special rules for households
NERC approves minimal fixed GT rates only for bioenergy power plants (BPPs) using solely biomass/biogas!!!
Combined use of biomass/biogas and conventional energy sources make BPPs ineligible to minimal fixed GT rate for biogas regardless of biogas share
There is no minimal fixed GT rate for electricity plants, commissioned till 1.04.2013!!!
danevychlaw.com
Combined use and GT, biogas and GT
Term «biomas» Silage, energy willow and other energy crops are not covered However, the biomass of any origin is included
Biogas is a gas formed from biomass.
If you are using energy crops, you can’t obtain GT!
danevychlaw.com
Definitions of biomass and biogas
Its rates are not tied to retail rates or average rates for producers of electricity
They are fixed as of January 1, 2009 in EUR and linked to EUR/UAH exchange rate (if more than 10.86 )
The State guarantees GT application to commissioned power plants and purchase of all electricity produced by them
danevychlaw.com
Guarantee of GT application in the future
Wholesale Electricity Market of Ukraine (WEM) represented by State Enterprise “Energorynok”
State guarantee of purchase of all electricity under GT
Direct sales of electricity to consumersLegislative limitations Absence of economic and administrative incentives
Changes of the mechanism of Sales inthe future on the draft law No. 10571
(No. 0916 of 12.12.2012)
danevychlaw.com
Purchase of electricity at GT rates
If a construction began in 2012 or later, the rates of the local component depends on the year of commissioning and shall be:
since 01.04.2013 till 01.07.2013, 15% (old calculation approach)till 07.01.2013 (for biogas in 2014) - 30%till 01.07.2014 (since 2015 for biogas) - 50%
Local component does not affect hydropower plants and installations of households
NERC will itself determine Ukrainian content based on certificates of origin, legal documents, etc.
danevychlaw.com
Ukrainian componentrequirement (from 1.04.2013)
danevychlaw.com
Ukrainian LCR for SPPs (since 1.07.2013)
Elements of local content Operations should be taking in Ukraine Fixed share, %
Polysilicon manufacturing 32
Monocrystals, multicrystals and pseudo-mono-crystals manufacturing 13
Cells from monocrystals or multicrystals manufacturing 7
Photoelectric elements manufacturing 20
Photoelectric modules assembling 23
Construction works manufacturing 5
Total 100
danevychlaw.com
Ukrainian LCR for wind farms (since 1.07.2013)
Elements of local content
Operations should be performed in Ukraine Fixed share, %
Rotor blades manufacturing 15Towers manufacturing 15Nacelle assembling 30Main frame manufacturing 5Main hub manufacturing 5
Rotor hub manufacturing (foundry) 5assembly 5
Construction works performance 20
Total 100
danevychlaw.com
Ukrainian LCR for biomass power plants (since 1.07.2013)
Elements of local content Operations should be taken in Ukraine Fixed share, %
Turbine manufacturing 25
Boiler manufacturing 35
Construction works performance 40
Total 100
The fixed shares since 2014
danevychlaw.com
Ukrainian LCR for biogas power plants (since 1.07.2013)
Elements of local content Operations should be taken in Ukraine Fixed share, %
Bioreactor for hydrolysis manufacturing 35
Cogenerator manufacturing 35
Construction works performance 30
Total 100
According to the order of calculation of the LCR of the NERCIf developer has 100% of one of the element of Ukrainian origin from the table, it can use this element regardless of the value to fulfill the respective share from the table, e.g. in the case of biomass
100 of construction works by a Ukrainian EPC – 40%100% of the turbine production by a Ukrainian manufacturer– 25 %
As a result, 50% of LCR is fulfilled!!?
Practical problem!!!most of the equipment is not produced in Ukraine, or produced not enough and won’t produced enoughunclear the approach of the CCI for an issuance of certificates of originnon-exhaustive list of documents
danevychlaw.com
Ukrainian LCR and fixed shares
Rates of GT shall be approved by NERC for each producer after filing the application and the required package of documents regarding the constructed and commissioned WF
Term for passing a decision by NERC: Consideration of documents package– 30 calendar days Approval by NERC’s meeting– 15 calendar days
GT documentation in the respective NERC’s Resolution
GOOD NEWS! Approval fee is absent
danevychlaw.com
Approval of GT (currently)
Set up of a company Electricity producer licenseConnection to the grid (compensation of expenses related to grid connection) Participation in WEM and signing WEM Agreement Conclusion of agreement for sales of electricity with State Enterprise “Energorynok” Execution of documentation for power plants construction
documents on the use of land plots project documentationcommissioning etc.
danevychlaw.com
Conditions for GT ProjectsImplementation
danevychlaw.com
Conditions for GT ProjectsImplementation
Set up of a company (charter shall provide that
the company produces
electricity) )
Acquisition of rights in land
Construction
Registration of ownership
Registration of leases
Registration of easements and
superficies
Change of designated purpose
License for electricity
production
Receipt of electricity producer’s
license
Receipt of a license for CHP
Joining WEM and Signing WEM Agreement
Conclusion of agreement with
Energorynok
GT approval by NERC
Tax and customs duties breaks
Exemption from import VAT and customs duties
25% of required land tax
Maximal annual lease payments – 3% of appraisal value
Exemption from corporate profit tax till 2021
Receipt of initial data
Receipt of technical
conditions
Development of project
documentation
Examination of PD, if necessary
Registration of declaration re preparatory
works, if necessary
Registration of declaration re beginning of construction
Receipt of permission r e
construction works
Issue of Certificate on readiness for
exploitation
Registration of declaration on
readiness
Registration of ownership
Connection to the grid
Main legislative barriers for development of GT projects
state guarantee
local content requirement
definition of "biomass“
no possibility to combine the use of biomass/biogas and traditional energy sources
uncertainty with GT for SPPs of householders
overall investment climatedanevychlaw.com
Legislative barriers