Lodi, August 10, 2012 Lodi Energy Center - Pioneering Flex-Plant TM Combined Cycle Technology for Seamless Renewable Integration Siemens Energy, Inc., 2012. All Rights Reserved. August 2012 Energy Fossil 2 Northern California Power Agency’s Lodi Energy Center The Nation’s First Fast Start Combined Cycle Siemens Flex-Plant TM 30 Gas Turbine: SGT6-5000F Gas Turbine Generator: SGEN6-1000A Steam Turbine: SST-900 Steam Turbine Generator: SGEN6-100A-2P Control System : SPPA-T3000 Installed Capacity 300 MW Efficiency >57% Fast start capability with 200 MW in 30 Minutes Northern California Power Agency’s Lodi Energy Center Northern California Power Agency’s Lodi Energy Center will be the First Fast Start Combined Cycle Power Plant in the U.S.A. in commercial operation. Based on the Siemens Flex-Plant TM 30 concept Lodi Energy Center is designed to meet the needs of the end user, including efficiency, flexibility and a small environmental footprint. The new plant with an installed capacity of 300 megawatts (MW) will serve the energy needs of 13 different project participants, including Modesto Irrigation District, Power and Water Resources Pooling Authority, Plumas-Sierra Rural Electric, State of California Department of Water Resources, Bay Area Rapid Transit, City of Ukiah, City of Lodi,

Transcript of Presentation: Lodi Energy Center - Pioneering Flex-PlantTM Combined … · Lodi, August 10, 2012 ....

Lodi, August 10, 2012

Lodi Energy Center - Pioneering Flex-PlantTM Combined Cycle

Technology for Seamless Renewable Integration

Siemens Energy, Inc., 2012. All Rights Reserved.August 2012 Energy Fossil 2

Northern California Power Agency’s Lodi Energy Center The Nation’s First Fast Start Combined Cycle

Northern California Power Agency’s Lodi Energy Center The Nation’s First Fast Start Combined Cycle

Siemens Flex-PlantTM 30Gas Turbine: SGT6-5000FGas Turbine Generator: SGEN6-1000ASteam Turbine: SST-900Steam Turbine Generator: SGEN6-100A-2PControl System : SPPA-T3000

Installed Capacity 300 MWEfficiency >57%Fast start capability with 200 MW in 30 Minutes

Northern California Power Agency’s Lodi Energy Center

Northern California Power Agency’s Lodi Energy Center will be the First Fast Start

Combined Cycle Power Plant in the U.S.A. in commercial operation. Based on the

Siemens Flex-PlantTM 30 concept Lodi Energy Center is designed to meet the needs of

the end user, including efficiency, flexibility and a small environmental footprint. The new

plant with an installed capacity of 300 megawatts (MW) will serve the energy needs of

13 different project participants, including Modesto Irrigation District, Power and Water

Resources Pooling Authority, Plumas-Sierra Rural Electric, State of California

Department of Water Resources, Bay Area Rapid Transit, City of Ukiah, City of Lodi,

- 2 -

City of Biggs, City of Azusa, City of Lompoc, City of Santa Clara, City of Healdsburg and

the City of Gridley.

The main components of the Siemens Flex-PlantTM 30 at Lodi Energy Center are:

Gas Turbine: SGT6-5000F

Gas Turbine Generator: SGEN6-1000A

Steam Turbine: SST-900

Steam Turbine Generator: SGEN6-100A-2P

Control System: SPPA-T3000

Major facts and figures:

Installed Capacity: 300 MW

Efficiency: >57%

Siemens Energy, Inc., 2012. All Rights Reserved.August 2012 Energy Fossil 3

Wind energy

Solar thermal

Photovoltaic

Green energy but mostlyintermittent supply

Optimizing the energy mix for clean reliable generation

Siemens is the world’s leading supplier of products, solutions and services for power generation

Coal-fired

Nuclear

Hydro

Traditional combined cycles

Base load with normal load change

Fast Moving Flex-Plant Combined Cycles

fast

clean

Efficient

Enabling a Stable Grid with a Diverse Generation Mix

Compensating Mid/peak load

Optimizing the energy mix for clean reliability generation

Renewable power is becoming a larger and larger part of the energy mix worldwide.

California is a leader in this trend, adding significant amounts of wind and solar capacity

to the grid. These renewable, green resources are environmentally friendly, but are

intermittent due to their dependence on immediate local environmental conditions.

Power today is primarily provided by power plants designed for base load, and lacking

the ability to quickly start up or quickly change load. Fast Moving Flex-Plants are

- 3 -

designed to provide clean, efficient power on demand. Flex-Plants bridge the gap to

enable a stable reliable power generation grid while renewables ramp in and out.

In addition to providing grid stability, the fast start of the gas turbine enabled by the

Siemens Flex-Plant 30 results in a significant reduction in overall plant startup emissions.

Siemens Energy, Inc., 2012. All Rights Reserved.August 2012 Energy Fossil 4

Siemens Energy Solution Portfolio in CaliforniaDesigned to enable diverse resources to operate in concert

Flexible, Efficient, Clean , Solutions for California

Marsh LandingCommercial operation 2013

El SegundoCommercial operation 2013

Lodi Energy CenterCommercial operation 2012

Siemens Flex-PlantTM combined cycles combining the

low cost, clean power generation of a combined cyclewith the

flexible fast load following capability of a gas turbine

Simple cycle Flex-PlantTM 10 Flex-PlantTM 30

Flexible, Efficient and Clean Solutions for California

Siemens Energy Solution Portfolio is designed to enable diverse resources to operate in

concert and is being dispatched here in California. From the fast start simple cycle at

Marsh Landing, to the Flex-Plant 10 at El Segundo to the Flex-Plant 30 at Lodi, Siemens

solutions fit the needs of California with high efficiency for low cost generation, flexibility

for fast dispatch, and low emissions for a clean environment. Siemens has implemented

nine large scale gas turbine projects in California since 1997

- 4 -

Siemens Energy, Inc., 2012. All Rights Reserved.August 2012 Energy Fossil 5

Northern California Power Agency Siemens Power Island 1x1 Flex Plant 30

• BENSON™ Boiler• High-Capacity Attemperators• HRSG / Piping Warm-up

Systems• Steam Turbine Stress Controller• Integration of Boiler Feed Pump,

De-superheaters & Steam Turbine warm up

• 100% Steam By-pass• Condensate Polishing• Auxiliary Boiler Rotor Air Cooler w/ Kettle Boiler

A fast responding, clean, efficient, combined cycle power plantto partner with California’s large non-dispatchable renewable generation

Siemens Energy, Inc., 2012.. All Rights Reserved.

Northern California Power Agency Siemens Power Island 1x1 Flex Plant 30

Lodi Energy Center is a Siemens SCC6-5000F 1x1 Flex-Plant - a fast responding, clean,

efficient combined cycle power plant to partner with California’s large non-dispatchable

renewable generation. It is a highly efficient combined cycle plant with an operating

efficiency of over 57 percent designed for intermediate to continuous duty and capable

of daily cycling. Plant start-up times are reduced by up to 50 percent due to the

integration of fast-start features, including the three-pressure reheat heat recovery steam

generator (HRSG) with Benson® once-through technology, high capacity steam

attemperation, full capacity steam bypass systems, innovative piping warm-up

strategies, and Siemens’ steam turbine stress controller (TSC). Using the Siemens

SGT6-5000F gas turbine as the prime mover, the plant will provide high power density

while requiring a relatively small plant footprint. The Siemens SPPA-T3000 control

system provides an easy-to-use control platform for the entire combined cycle power

plant. Its fast start capability with 200 MW in 30 Minutes or less can result in a carbon

monoxide reduction of over 200 tons per year when compared to traditional F-class

combined cycle plants.

- 5 -

Siemens Energy, Inc., 2012. All Rights Reserved.August 2012 Energy Fossil 6

Siemens Solutions Proven Capabilities & Experiencepartnered with NCPA for a successful project

Core Execution Competencies• Plant Engineering• Procurement• Transportation / Logistics• Construction Management / TFA• Commissioning

Highlights• Over 330 Projects Completed World Wide. • Over 70 HRSG’s procured globally since 2000• Over 105 Turnkey Projects completed in the Americas • Over 20,000 plant operators trained by our Siemens training department since 1990.

Proven, real-world solutions – backed by the power of Siemens

Siemens Solutions Proven Capabilities & Experience

Siemens partnered with NCPA for a successful project by delivering proven solutions

and project execution know-how including core execution competencies in plant

engineering, procurement, transportation / logistics, construction management / TFA,

and commissioning. Siemens has successfully completed over 330 projects worldwide,

and procured over 70 HRSG’s globally since 2000. In the Americas over 105 turnkey

projects were completed.

- 6 -

Siemens Energy, Inc., 2012. All Rights Reserved.August 2012 Energy Fossil 7

Proven, Real World Solutions

Siemens Energy, Inc., 2012.. All Rights Reserved.

Reducing risk by focusing on Safety

IntegrationDeliveryTraining

Implementing the Right Technology To Partner with Renewable Generation

Proven, Real World Solutions

Choosing Siemens for extended power plant scope enables a reduction in overall project

risk. With extended scope, throughout the project Siemens personnel access expertise

in the design offices, in the factories and on the site to minimize technical, personnel,

and financial risks. With an extended scope project, Siemens is a power plant partner,

leveraging the power and expertise of Siemens around the globe. For the Lodi Energy

Center project, the Siemens scope was to deliver the power island. From NTP (notice to

proceed) to PAC (provisional acceptance certificate) and beyond, Siemens uses the best

available tools and processes to manage risk and assure success.

- 7 -

Siemens Energy, Inc., 2012. All Rights Reserved.August 2012 Energy Fossil 8

Safety at Lodi

Zero Lost Time Accidents (LTA) for OEM or subcontractor personnel with over 16,000 man-hours on site

Zero Lost Time Accidents (LTA) for OEM or subcontractor personnel with over 16,000 man-hours on site

Siemens Energy, Inc., 2012.. All Rights Reserved.

Safety at Lodi

At Siemens, safety is considered the most important aspect of every project. In

partnership with NCPA, Siemens followed a detailed safety program for the site.

Siemens Project Manager and Project Engineer independently conducted and

documented a formal site Safety Walk at every site visit. There were also regular site

audits to assure adherence to Siemens and site procedures and prompt action and

resolution for any quality incident reports. This focus on safety resulted in an impressive

Zero Lost Time Accidents (LTA) for OEM or its subcontractor personnel with over 16,000

man-hours on site.

- 8 -

Siemens Energy, Inc., 2012. All Rights Reserved.August 2012 Energy Fossil 9

Having the OEM as an integral part of the Lodi construction management team enhanced the integration of equipment into the site

execution

Having the OEM as an integral part of the Lodi construction management team enhanced the integration of equipment into the site

execution

Siemens Energy, Inc., 2012.. All Rights Reserved.

Integration

Integration

Having the OEM as an integral part of the Lodi construction management team

enhanced the integration of equipment into the site execution. System integration is a

big part of every Siemens project from first concept through construction. Siemens

experts integrate Siemens expertise with local expertise to get the best from both. At

Lodi Siemens provided field engineers to join the construction management team

working directly for the customer. The Siemens experience and expertise contributed to

improving installation by directly working with the craft sharing Siemens experiences to

avoid installation re-work. Siemens integrated the Power Island and BOP controls

including grid connection, water treatment, etc. into an overall integrated Plant Controls

System.

Siemens also provided in house expertise to assist Customer in interfacing and

obtaining design approval of specialty engineering designs including CBO, Fire Marshal,

and authorized ASME Inspector approvals. This team participated in customer, A/E,

constructor partnering workshops to develop open relationships and communication and

to identify potential project risks and mitigations.

- 9 -

Siemens Energy, Inc., 2012. All Rights Reserved.August 2012 Energy Fossil 10

All OEM equipment was delivered ahead of scheduleAll OEM equipment was delivered ahead of schedule

Siemens Energy, Inc., 2012.. All Rights Reserved.

Delivery

Delivery ahead of time

All OEM equipment for Lodi Energy Center was delivered ahead of schedule.

Siemens assigns a factory load planner to monitor the manufacturing of the gas turbine

and steam turbine for all projects to resolve any schedule issues. For Lodi, a project

expediter was dispatched by the Siemens Orlando-Team to Finspong in Sweden

multiple times during the project to monitor and expedite the critical path steam turbine

manufacturing progress.

Siemens also assigned a project specific site services procurement specialist to support

unplanned or emergency needs for parts or services. For Lodi, they developed a

logistics plan for special rail car usage and transit clearance and routing to ensure the

gas turbine and the generator delivery to site without schedule delays.

Steam turbine 74 days early

Gas turbine 13 days early

HRSG 38 days early

Condenser 51 days early

- 10 -

Siemens Energy, Inc., 2012. All Rights Reserved.August 2012 Energy Fossil 11

beside youNCPA personnel were given classroom, hands on operating and maintenance training on site and on the simulator in Orlando

NCPA personnel were given classroom, hands on operating and maintenance training on site and on the simulator in Orlando

Siemens Energy, Inc., 2012.. All Rights Reserved.

Training

Training

Training: NCPA personnel were given classroom, hands on operating and maintenance

training on site and on the simulator in Orlando. Over 20,000 plant operators have been

trained by Siemens since 1990.

Conclusion

Lodi Energy Center innovative fast ramping gas fired plant was specifically designed by

Siemens as a solution to balance fluctuations on diverse power grids managing both

renewable and traditional energy sources. Its clean footprint and versatility makes it an

ideal solution to the growing need for stable and environmentally friendly power sources

in the U.S.A. and around the globe.