Presentation Analysis
Transcript of Presentation Analysis
-
8/10/2019 Presentation Analysis
1/17
-
8/10/2019 Presentation Analysis
2/17
Nor Atikah bintiHusin
117500
Ratna Zuzilianty
binti Zulkifli
117507
Rozita binti Yazit
117508
Kinnakchin a/p All
117490
-
8/10/2019 Presentation Analysis
3/17
Introduction:
What is Penang Undersea Tunnel?
-A new tunnel under purposal in Penang, Malaysia.
-The 6.5 km tunnel connects Butterworth, Seberang Perai in the east to
George Town, Penang Island in the west.
-Will become the first undersea tunnel in Malaysia and the second in
Southeast Asia. The project is undertaken by the State Government of
Penang and a main contractor Consortium Zenith BUCG Sdn Bhd a member
of Zenith Group.
- Construction will start on 2016 and completed on 2025.
-The planned Penang Undersea Tunnel will be the largest privately funded
public works project in Penang. There will be a toll plaza at the undersea
tunnel.
-
8/10/2019 Presentation Analysis
4/17
-
8/10/2019 Presentation Analysis
5/17
-
8/10/2019 Presentation Analysis
6/17
-
8/10/2019 Presentation Analysis
7/17
OBJECTIVES PROJECT
1. Reduce Congestion.
Traffic congestion is a condition on road networks that occurs inslower speeds, longer trip times, and increased vehicular queuing. Ifthe undersea tunnel managed to set up, the customers have threechoices road to use (Penang Bridge, Sultan Abdul Halim Muadzam
Shah Bridge and Penang Undersea Tunnel).
2. Improve equality in society.
Middle of Seberang Perai and South of Seberang Perai alreadygiven two bridges that can help to improve the degree of
accessibility and enhance economic development in Georgetown,Penang. But this equality left out the north of Seberang Peraibehind. So, the third hub routes will also ensure a balanceddevelopment at north of Seberang Perai .
-
8/10/2019 Presentation Analysis
8/17
PROBLEM STATEMENT
Penang Bridge and Sultan Abdul Halim MuadzamShah Bridge, traffic congestion still happenespecially during peak times such as in the morningand evening.
The purpose of this tunnel is to balance out theinequality at north of Seberang Perai.
But, theres also have a lot of issues about the costof the construction and environmental effect if thistunnel build up.
-
8/10/2019 Presentation Analysis
9/17
-
8/10/2019 Presentation Analysis
10/17
1. Construction costThe cost of Penang undersea tunnel is
estimated around RM 6.3 billion about 6.5-
kilometre.
2. Maintenance cost
Maintenance cost is estimated around RM1.6billion
-
8/10/2019 Presentation Analysis
11/17
1. Construction noise
Construction noise has the potential to disturb people athome in their residences, in office building, retailbusinesses or public institutional buildings
May affect peoples quality life
2. Non-human species
affect non-human species such as aquatic life, land andairborne animals in a variety of ways.
3. Social effect
impact on fisheries
the price of seafood hurts ordinary people
-
8/10/2019 Presentation Analysis
12/17
Direct Benefits
1) Time saving
- Enables the traveller to save time
- This can sometimes be of direct monetary benefit as when aquicker journey
- Help to ease traffic congestion dan reduce dwell times
2) Cost saving
- Time saving leads to cost saving
- Peoples daily activity will goes smoothly
3) Reduce congestion
- The number of vehicles on the road can be reduced
-
8/10/2019 Presentation Analysis
13/17
-
8/10/2019 Presentation Analysis
14/17
Estimate Cost:
Construction cost + maintenance cost+ New road construction
cost + Environmental cost + Maritime loss cost + others.
= 6.3 bil + 1.6 bil + 1.2 bil + Environmental cost*+ Maritime
loss cost* + others
= 9.1 bil + Environmental cost*+ Maritim loss cost* + others
Estimate Benefits:
Toll payment x number of vehicles per year + others
= RM 9.4 + 1 mil + others
= RM 9.4 mil + others
After 10 years = (RM 9.4 mil x 10) = 9.4 bil + others
-
8/10/2019 Presentation Analysis
15/17
Because:
1) The costs to make the tunnel is too high andtake a long time to be completed.
- Include a lot of costs like cost of construction,
security, maintenance, and environmental cost.- Can use the money to upgrade the facilities at
north of Seberang Perai.
-
8/10/2019 Presentation Analysis
16/17
2) Not the best way to improve congestion.
- Already have two bridge but still face congestion problem.
- so, must find other alternative: improve public transport
system.
- Campaign: promote usage of public transport.
4) Disturb maritime logistics development .- Fishermen and cargo ships will be interrupt during the
construction.
- decrease income of the maritime.
3) Environmental effect
- Water and soil pollution.
- Marin ecosystem will die.
-
8/10/2019 Presentation Analysis
17/17
Conclusion
Penangs 2ndbridge just completed, and
making another tunnel in 2016 might to
earlier and this rushing decision also might
drag our country to a loss. So, its better for
the Government to think for the second time
and find another alternative to develop the
north of Seberang Perai than take a risky andhigh cost solution.