ACSETPrepared byWISMA ITC, 4th Floor R.401Jln. Abdul Muis No.8, Jakarta PusatTechnical MethodSENOPATI 2 / DISTRICT 8www.acset-indo.com
PROJECT LOCATIONDISTRICT 8 SENOPATI
JAKARTA MAP
PROJECT LOCATIONPROJECT OUTLINE
CONSULTAN:-ARCHITECTURE:PT. AIRMAS ASRI-STRUCTURE:WIRATMAN & ASSOCIATES-M & E:PT. ARNAN PRATAMA CONSULTANT-QUANTITY SURVEYOR:--LANDSCAPE:-DISTRICT 8 SENOPATIPROJECT OUTLINE
LAND AREA 37,956 M2 FLOOR AREABASEMENT AREASemi Basement 27,193 M2 27,193 M2 B1 26,560 M2 26,560 M2 B2 26,560 M2 26,560 M2 B3 26,560 M2 26,560 M2 SUBTOTAL (A) 106,873 M2 106,873 M2 GROUND FLOORSUBTOTAL (B) 27,262 M2 27,262 M2 UPPER STRUCTURE Incl. Tower Exc. Tower PODIUM (8 Stories) SUBTOTAL (C) 37,253 M2 79,922 M2 Incl.Podium Exc. Podium KANTOR 1 TOWER (56 Stories) 156,663 M2 151,619 M2 KANTOR 2 TOWER (41 Stories) 80,369 M2 66,880 M2 APARTMENT 1 TOWER (49 Stories) 58,436 M2 49,952 M2 APARTMENT 2 TOWER (49 Stories) 65,702 M2 56,161 M2 APARTMENT 3 TOWER (36 Stories) 30,711 M2 24,600 M2 SUBTOTAL (D) 391,881 M2 349,212 M2 TOTAL ( A+B+C+D) 563,269 M2 563,269 M2 DISTRICT 8 SENOPATI
EXISTING
KendalaLahan diantara bangunan dan sarana umum yang telah adaLalu lintas yang cukup padat pada jam kerja 08.00~21.00 WIBSedikit lahan tersisa untuk sarana penempatan material dan pabrikasiSaluran air kota yang mengharuskan air keluar tanpa lumpur KemudahanDikelilingi jalan umum sebagai aksesBatasan jelas (pagar) dengan property lainPenggunaan air tanah untuk air kerjaDISTRICT 8 SENOPATISITE ORGANIZATION CHART
DISTRICT 8 SENOPATI
PRELIMINARY CONSTRUCTION SCHEDULE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33PROJECT PERIOD33 MONTHSCommencement of Work 01/04/13DISTRICT 8 SENOPATIMinimum Forcon DWG for Starting (01/04/13) :1. As Built D-Wall Dwg2. Raft Foundation / Foundation Dwg.3. Lift Pit, Sump Pit, Etc.Forcon Dwg. Should be Clearly from beginning1. General RC Structure Dwg2. NSC, SC, etc. AWARD more earlyPreparation Work10/04/13~30/06/13Dewatering PreparationStart 23/04/13FOUNDATION WORKFinish Target Escavation Work Zone 1 - 01/05/13
TC 1 Install - 09/05/13Finish Target Escavation Work Zone 2 - 25/06/13Finish Target Escavation Work Zone 3 - 08/09/13Foundation Zone P5Start - 23/09/13Finish Target Escavation Work Zone 4 - 16/07/14Start Escavation WorkZone 4 - 18/03/14Foundation Kantor 1 Start - 16/05/13Foundation Apartment 2 Start - 10/07/13Foundation Apartment 1 Start - 03/09/13Foundation Kantor 2 Start - 03/09/13Foundation Zone P1Start - 30/07/13Foundation Zone P2Start - 23/09/13Foundation Apartment 3 Start - 22/11/13Foundation Zone P3Start - 02/11/13Foundation P4 Start - 12/12/13Foundation Zone P6Start - 07/11/138BEGINNING ACTIVITIES TO BE CARRIED OUT
DISTRICT 8 SENOPATI9BEGINNING ACTIVITIES TO BE CARRIED
Mobilization of Plant, equipment and staffing Survey and Setting Out WorksJoint Survey for Serah Terima LahanSubmission survey reportEstablishment of security on siteIFC drawings: Structure DrawingArchitectural layoutsPlumbing / DrainageM&E Works Construction of temporary facilities : Employers site officeContractors site office and storeToilet & Washing AreaFormwork fabrication yardRebar fabrication yard7. Construction of Site Access Road8. Construction of truck washing bayArrangement for ASTEK insuranceFoundation for Tower CraneConcrete trial mix and testingRebar testing Preparation of Shop drawingsPreparation & Submission of Method Statement for Raft Foundation/Foundation worksInstallation of Instrumentation - settlement markers & monitoring water standpipe
DISTRICT 8 SENOPATISITE TEMPORARY UTILITIES
DISTRICT 8 SENOPATI11
SITE TEMPORARY UTILITIES TAHAP 1
TEMPORARY FENCESITE OFFICE & STORAGEGATE 2GATE 1GATE 3GENSETHOUSECAR BAYWASHDISTRICT 8 SENOPATIGUARD HOUSEGUARD HOUSEGUARD HOUSELABOURTOILETLABOURTOILETLABOURTOILETLABOURTOILETSTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREASTORAGECAR BAYWASHTC 1ACCESS CONCRETE PAVEMENTZONE K1 & P1TC 2ZONE A2& P2ZONE A1 & P3TC 5TC 6TC 3TC 4ZONE K2 & P4TC 8TC 7ZONE A3, P5 & P6TC 9ACCESS CONCRETE PAVEMENTPROGRESS FOUNDATIONSTART MID OF MONTH 2ndPROGRESS FOUNDATIONSTART BEGINNING OF MONTH 4thPROGRESS FOUNDATIONSTART BEGINING OF MONTH 6thPROGRESS FOUNDATIONSTART MID OF MONTH 7thPROGRESS FOUNDATIONSTART MID OF MONTH 8th
SITE TEMPORARY UTILITIES TAHAP 2
DISTRICT 8 SENOPATIGATE 1GATE 2GATE 3ACCESS CONCRETE PAVEMENTSTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREAZONE K1 & P1ZONE A2& P2ZONE A1 & P3ZONE K2 & P4ZONE A3, P5 & P6GATE 4PROGRESS TOWERUPPER STRPROGRESS ZONE P1UP TO GFPROGRESS TOWERUPPER STRPROGRESS ZONE P4UP TO GFPROGRESS TOWERUPPER STRPROGRESS ZONE P2UP TO GFPROGRESS TOWERUPPER STRPROGRESS ZONE P3UP TO GFPROGRESS TOWERUPPER STRPROGRESS ZONE P5 & P6UP TO GFACCESS CONCRETE PAVEMENTZONEP7ZONEP8PROGRESS ZONE P7UP TO B2START END OFMONTH 9thPROGRESS ZONE P8UP TO FOUNDSTART END OFMONTH 11thPROGRESS ZONE P9 START EXCAVATION ONMID OFMONTH 13thPROGRESS END OF MONTH 12thPH 1&2PH 3&4PH 5&6PH 7&8PH 9&10EXCAVATION WORK (BY OTHERS)WORKING ZONE & SEQUENCE OF WORK
DISTRICT 8 SENOPATI14
EXCAVATION WORKS
DISTRICT 8 SENOPATITARGET FINISH OF EXCAVATION WORK END OF MONTH 1stTARGET FINISH OF EXCAVATION WORK END OF MONTH 3rdTARGET FINISH OF EXCAVATION WORK BEGINNING OF MONTH 6thEXCAVATION WORKSTART MID OF MONTH 12thFINISH MID OFMONTH 16thSTRUCTURE WORKWORKING ZONE
DISTRICT 8 SENOPATI16
DISTRICT 8 SENOPATISUB STRUCTURE WORKING ZONEDIVIDED BYZONE K1MAIN ZONE 16 ZonesZONE K2ZONE A2ZONE A1ZONE A3ZONE P1ZONE P2ZONE P3ZONE P4ZONE P5ZONE P6ZONE P7ZONE P8ZONE P9ZONE P10ZONE P11SUB ZONE 61 Zones17
DISTRICT 8 SENOPATIPODIUM UPPER STRUCTURE WORKING ZONEDIVIDED BYZONE K1MAIN ZONE 11 ZonesZONE K2ZONE A2ZONE A1ZONE A3ZONE P2ZONE P3ZONE P7ZONE P8ZONE P9ZONE P10SUB ZONE 44 Zones18
DISTRICT 8 SENOPATITOWER TYPICAL FLOOR WORKING ZONE
19SUB STRUCTURE
DISTRICT 8 SENOPATI20
DISTRICT 8 SENOPATISEQUENCE OF STRUCTURE WORKSStartFinish30-07-1312-10-13StartFinish12-12-1309-02-14StartFinish16-05-1329-07-13StartFinish13-10-1311-12-13StartFinish23-09-1321-11-13StartFinish03-09-1301-11-13StartFinish10-07-1322-09-13StartFinish02-11-1331-12-13StartFinish22-11-1320-01-14StartFinish23-09-1321-11-13StartFinish07-11-1305-01-14ZONE P1 PROGRESS UP TO GFSTART FOUNDZONE P7StartFinish28-12-1325-02-14StartFinish26-02-1426-04-14ZONE P6 PROGRESS UP TO GFSTART FOUNDZONE P9StartFinish18-03-1416-05-14StartFinish17-05-1415-07-14StartFinish16-07-1428-09-1421
DISTRICT 8 SENOPATISEQUENCE OF FOUNDATION WORKS
CORE AREARAFT FOUNDATIONOUT OF CORE AREASLAB & WALL FOUND.#1 Lean Concrete all area#2 Anti termite #3 Waterproofing work#4 Bottom Rebar all area#5 Top Rebar Bottom Slab Out of Core Area#6 Vertical Rebar for Wall & Column Out of Core Area & For Raft Foundation#7 Pouring Bottom Slab Out of Core Area Rebar work for Raft Found. Continue#8 Setting Horizontal Rebar Wall, Setting Wall Formwork Out of Core Area, Rebar work for Raft Found. Continue#9 Pouring Wall Out of Core Area Rebar work for Raft Found. Continue#10 Remove Wall Formwork Out of Core Area & Install Formwork of Raft Found #11 Pouring Raft Foundation#12 Remove Formwork Raft Foundation#13 Fill in chamber by Sand w/Compaction + Layering Plastic Sheet on top + Lean Concrete#14 Install Rebar Top Slab Out of Core Area#15 Pouring Top Slab (B3 Slab) Out of Core Area22
DISTRICT 8 SENOPATIDURATION OF STRUCTURE WORK Siklus pekerjaan struktur area tower Kantor 1Lantai B3 : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 25~30 hariLantai B2 ~ GF : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 21~25 hariLantai 2 ~ 3 : 10~12 hari/zone/lantai , 1 lantai pekerjaan struktur finish 18~21 hariLantai 4 ~ Atap : 7~8 hari/zone/lantai , 1 lantai pekerjaan struktur finish 13~14 hariLantai Atap ~ LMR : 1 lantai pekerjaan struktur finish 16 hari
Siklus pekerjaan struktur area tower Kantor 2Lantai B3 : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 25~30 hariLantai B2 ~ GF : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 21~25 hariLantai 2 ~ 3 : 10~12 hari/zone/lantai , 1 lantai pekerjaan struktur finish 18~21 hariLantai 4 ~ Atap : 7~8 hari/zone/lantai , 1 lantai pekerjaan struktur finish 13~14 hariLantai Atap ~ LMR : 1 lantai pekerjaan struktur finish 14 hari
Siklus pekerjaan struktur area tower Apartment 1 & 2Lantai B3 : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 25~30 hariLantai B2 ~ GF : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 21~25 hariLantai 2 ~ 3 : 10~12 hari/zone/lantai , 1 lantai pekerjaan struktur finish 18~21 hariLantai 4 ~ Atap : 6~7 hari/zone/lantai , 1 lantai pekerjaan struktur finish 13~14 hariLantai Atap ~ LMR : 1 lantai pekerjaan struktur finish 14 hari
Siklus pekerjaan struktur area tower Service Apartment (A3)Lantai B3 : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 25~30 hariLantai B2 ~ GF : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 21~25 hariLantai 2 ~ 3 : 10~12 hari/zone/lantai , 1 lantai pekerjaan struktur finish 18~21 hariLantai 4 ~ Atap : 7~8 hari/zone/lantai , 1 lantai pekerjaan struktur finish 10~12 hariLantai Atap ~ LMR : 1 lantai pekerjaan struktur finish 12 hari
Siklus pekerjaan struktur area diluar TowerLantai B3 : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 25~30 hariLantai B2 ~ GF : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 21~25 hariLantai 2 ~ 4 : 10~13 hari/zone/lantai , 1 lantai pekerjaan struktur finish 18~21 hariLantai 5 ~ 8/Atap : 7~8 hari/zone/lantai , 1 lantai pekerjaan struktur finish 14~16 hari
23
DISTRICT 8 SENOPATICYCLE OF WORK TYPICAL FLOORKANTOR 1 TOWER
24
DISTRICT 8 SENOPATICYCLE OF WORK TYPICAL FLOORKANTOR 2 TOWER
25
DISTRICT 8 SENOPATICYCLE OF WORK TYPICAL FLOORAPARTMENT 1 TOWER
26
DISTRICT 8 SENOPATICYCLE OF WORK TYPICAL FLOORAPARTMENT 2 TOWER
27
DISTRICT 8 SENOPATICYCLE OF WORK TYPICAL FLOORSERVICE APARTMENT TOWER
28
DISTRICT 8 SENOPATISEQUENCE OF FORMWORK & PROPPINGFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKTEMPORARY SAFETY ASAGOFIXEDTEMPORARY SAFETY ASAGOMOVEABLE29
DISTRICT 8 SENOPATIPROGRESS OF WORKS
End of MONTH 7th
End of MONTH 8th
End of MONTH 9th
End of MONTH 10th
End of MONTH 11th
End of MONTH 12th
End of MONTH 13th
End of MONTH 14th
End of MONTH 15th
End of MONTH 16th
End of MONTH 17th
End of MONTH 18th
End of MONTH 19th
End of MONTH 20th
End of MONTH 21st
End of MONTH 22nd
End of MONTH 23rd
End of MONTH 24th
End of MONTH 25th
End of MONTH 26th30
SATRIO SQUARE OFFICE TOWERFORMWORK SYSTEM
31
SATRIO SQUARE OFFICE TOWERFORMWORK SYSTEM
32
SATRIO SQUARE OFFICE TOWERFORMWORK SYSTEM
33
SATRIO SQUARE OFFICE TOWERUPPER STRUCTURESAFETY34
SATRIO SQUARE OFFICE TOWERORGANISASI K3
35
SATRIO SQUARE OFFICE TOWERPERATURAN DAN TATA TERTIB
36
TEMPORARY FENCEPH 1PH 2SITE OFFICE & STORAGEFORM WORK STOCK & FABRICATION AREAREBAR STOCK & FABRICATION AREALIGHT DUTY WORKINGPLATFORMHEAVY DUTY WORKINGPLATFORMGUARD HOUSEGUARD HOUSEGATE 1GATE 2GATE 3CONCRETE PAVEMENTGENSETHOUSETC
GUARD HOUSE
MPMPP3KP3KP3K
TUTUTUTUMP
P3KTEMPORARY URINOIRMUSTER POINTAPARKOTAK P3KP3KTEMPORARY RAILING
SATRIO SQUARE OFFICE TOWERSAFETY PLAN37
SATRIO SQUARE OFFICE TOWERSAFETY INDUCTION & AKTIFITAS RUTIN K3
38
SATRIO SQUARE OFFICE TOWERTRAINING K3 & SAFETY AWARD
39
SATRIO SQUARE OFFICE TOWERPROTEKSI KESELAMATAN
40
SATRIO SQUARE OFFICE TOWERPROTEKSI KESELAMATAN
41
SATRIO SQUARE OFFICE TOWERRAMBU-RAMBU KESELAMATAN
42
SATRIO SQUARE OFFICE TOWERAPLIKASI RAMBU-RAMBU KESELAMATAN
43
SELESAITERIMA KASIH44