Slide 1

ACSETPrepared byWISMA ITC, 4th Floor R.401Jln. Abdul Muis No.8, Jakarta PusatTechnical MethodSENOPATI 2 / DISTRICT 8www.acset-indo.com

PROJECT LOCATIONDISTRICT 8 SENOPATI

JAKARTA MAP

PROJECT LOCATIONPROJECT OUTLINE

CONSULTAN:-ARCHITECTURE:PT. AIRMAS ASRI-STRUCTURE:WIRATMAN & ASSOCIATES-M & E:PT. ARNAN PRATAMA CONSULTANT-QUANTITY SURVEYOR:--LANDSCAPE:-DISTRICT 8 SENOPATIPROJECT OUTLINE

LAND AREA 37,956 M2 FLOOR AREABASEMENT AREASemi Basement 27,193 M2 27,193 M2 B1 26,560 M2 26,560 M2 B2 26,560 M2 26,560 M2 B3 26,560 M2 26,560 M2 SUBTOTAL (A) 106,873 M2 106,873 M2 GROUND FLOORSUBTOTAL (B) 27,262 M2 27,262 M2 UPPER STRUCTURE Incl. Tower Exc. Tower PODIUM (8 Stories) SUBTOTAL (C) 37,253 M2 79,922 M2 Incl.Podium Exc. Podium KANTOR 1 TOWER (56 Stories) 156,663 M2 151,619 M2 KANTOR 2 TOWER (41 Stories) 80,369 M2 66,880 M2 APARTMENT 1 TOWER (49 Stories) 58,436 M2 49,952 M2 APARTMENT 2 TOWER (49 Stories) 65,702 M2 56,161 M2 APARTMENT 3 TOWER (36 Stories) 30,711 M2 24,600 M2 SUBTOTAL (D) 391,881 M2 349,212 M2 TOTAL ( A+B+C+D) 563,269 M2 563,269 M2 DISTRICT 8 SENOPATI

EXISTING

KendalaLahan diantara bangunan dan sarana umum yang telah adaLalu lintas yang cukup padat pada jam kerja 08.00~21.00 WIBSedikit lahan tersisa untuk sarana penempatan material dan pabrikasiSaluran air kota yang mengharuskan air keluar tanpa lumpur KemudahanDikelilingi jalan umum sebagai aksesBatasan jelas (pagar) dengan property lainPenggunaan air tanah untuk air kerjaDISTRICT 8 SENOPATISITE ORGANIZATION CHART

DISTRICT 8 SENOPATI

PRELIMINARY CONSTRUCTION SCHEDULE

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33PROJECT PERIOD33 MONTHSCommencement of Work 01/04/13DISTRICT 8 SENOPATIMinimum Forcon DWG for Starting (01/04/13) :1. As Built D-Wall Dwg2. Raft Foundation / Foundation Dwg.3. Lift Pit, Sump Pit, Etc.Forcon Dwg. Should be Clearly from beginning1. General RC Structure Dwg2. NSC, SC, etc. AWARD more earlyPreparation Work10/04/13~30/06/13Dewatering PreparationStart 23/04/13FOUNDATION WORKFinish Target Escavation Work Zone 1 - 01/05/13

TC 1 Install - 09/05/13Finish Target Escavation Work Zone 2 - 25/06/13Finish Target Escavation Work Zone 3 - 08/09/13Foundation Zone P5Start - 23/09/13Finish Target Escavation Work Zone 4 - 16/07/14Start Escavation WorkZone 4 - 18/03/14Foundation Kantor 1 Start - 16/05/13Foundation Apartment 2 Start - 10/07/13Foundation Apartment 1 Start - 03/09/13Foundation Kantor 2 Start - 03/09/13Foundation Zone P1Start - 30/07/13Foundation Zone P2Start - 23/09/13Foundation Apartment 3 Start - 22/11/13Foundation Zone P3Start - 02/11/13Foundation P4 Start - 12/12/13Foundation Zone P6Start - 07/11/138BEGINNING ACTIVITIES TO BE CARRIED OUT

DISTRICT 8 SENOPATI9BEGINNING ACTIVITIES TO BE CARRIED

Mobilization of Plant, equipment and staffing Survey and Setting Out WorksJoint Survey for Serah Terima LahanSubmission survey reportEstablishment of security on siteIFC drawings: Structure DrawingArchitectural layoutsPlumbing / DrainageM&E Works Construction of temporary facilities : Employers site officeContractors site office and storeToilet & Washing AreaFormwork fabrication yardRebar fabrication yard7. Construction of Site Access Road8. Construction of truck washing bayArrangement for ASTEK insuranceFoundation for Tower CraneConcrete trial mix and testingRebar testing Preparation of Shop drawingsPreparation & Submission of Method Statement for Raft Foundation/Foundation worksInstallation of Instrumentation - settlement markers & monitoring water standpipe

DISTRICT 8 SENOPATISITE TEMPORARY UTILITIES

DISTRICT 8 SENOPATI11

SITE TEMPORARY UTILITIES TAHAP 1

TEMPORARY FENCESITE OFFICE & STORAGEGATE 2GATE 1GATE 3GENSETHOUSECAR BAYWASHDISTRICT 8 SENOPATIGUARD HOUSEGUARD HOUSEGUARD HOUSELABOURTOILETLABOURTOILETLABOURTOILETLABOURTOILETSTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREASTORAGECAR BAYWASHTC 1ACCESS CONCRETE PAVEMENTZONE K1 & P1TC 2ZONE A2& P2ZONE A1 & P3TC 5TC 6TC 3TC 4ZONE K2 & P4TC 8TC 7ZONE A3, P5 & P6TC 9ACCESS CONCRETE PAVEMENTPROGRESS FOUNDATIONSTART MID OF MONTH 2ndPROGRESS FOUNDATIONSTART BEGINNING OF MONTH 4thPROGRESS FOUNDATIONSTART BEGINING OF MONTH 6thPROGRESS FOUNDATIONSTART MID OF MONTH 7thPROGRESS FOUNDATIONSTART MID OF MONTH 8th

SITE TEMPORARY UTILITIES TAHAP 2

DISTRICT 8 SENOPATIGATE 1GATE 2GATE 3ACCESS CONCRETE PAVEMENTSTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREASTOCK & FABRICATION AREAZONE K1 & P1ZONE A2& P2ZONE A1 & P3ZONE K2 & P4ZONE A3, P5 & P6GATE 4PROGRESS TOWERUPPER STRPROGRESS ZONE P1UP TO GFPROGRESS TOWERUPPER STRPROGRESS ZONE P4UP TO GFPROGRESS TOWERUPPER STRPROGRESS ZONE P2UP TO GFPROGRESS TOWERUPPER STRPROGRESS ZONE P3UP TO GFPROGRESS TOWERUPPER STRPROGRESS ZONE P5 & P6UP TO GFACCESS CONCRETE PAVEMENTZONEP7ZONEP8PROGRESS ZONE P7UP TO B2START END OFMONTH 9thPROGRESS ZONE P8UP TO FOUNDSTART END OFMONTH 11thPROGRESS ZONE P9 START EXCAVATION ONMID OFMONTH 13thPROGRESS END OF MONTH 12thPH 1&2PH 3&4PH 5&6PH 7&8PH 9&10EXCAVATION WORK (BY OTHERS)WORKING ZONE & SEQUENCE OF WORK

DISTRICT 8 SENOPATI14

EXCAVATION WORKS

DISTRICT 8 SENOPATITARGET FINISH OF EXCAVATION WORK END OF MONTH 1stTARGET FINISH OF EXCAVATION WORK END OF MONTH 3rdTARGET FINISH OF EXCAVATION WORK BEGINNING OF MONTH 6thEXCAVATION WORKSTART MID OF MONTH 12thFINISH MID OFMONTH 16thSTRUCTURE WORKWORKING ZONE

DISTRICT 8 SENOPATI16

DISTRICT 8 SENOPATISUB STRUCTURE WORKING ZONEDIVIDED BYZONE K1MAIN ZONE 16 ZonesZONE K2ZONE A2ZONE A1ZONE A3ZONE P1ZONE P2ZONE P3ZONE P4ZONE P5ZONE P6ZONE P7ZONE P8ZONE P9ZONE P10ZONE P11SUB ZONE 61 Zones17

DISTRICT 8 SENOPATIPODIUM UPPER STRUCTURE WORKING ZONEDIVIDED BYZONE K1MAIN ZONE 11 ZonesZONE K2ZONE A2ZONE A1ZONE A3ZONE P2ZONE P3ZONE P7ZONE P8ZONE P9ZONE P10SUB ZONE 44 Zones18

DISTRICT 8 SENOPATITOWER TYPICAL FLOOR WORKING ZONE

19SUB STRUCTURE

DISTRICT 8 SENOPATI20

DISTRICT 8 SENOPATISEQUENCE OF STRUCTURE WORKSStartFinish30-07-1312-10-13StartFinish12-12-1309-02-14StartFinish16-05-1329-07-13StartFinish13-10-1311-12-13StartFinish23-09-1321-11-13StartFinish03-09-1301-11-13StartFinish10-07-1322-09-13StartFinish02-11-1331-12-13StartFinish22-11-1320-01-14StartFinish23-09-1321-11-13StartFinish07-11-1305-01-14ZONE P1 PROGRESS UP TO GFSTART FOUNDZONE P7StartFinish28-12-1325-02-14StartFinish26-02-1426-04-14ZONE P6 PROGRESS UP TO GFSTART FOUNDZONE P9StartFinish18-03-1416-05-14StartFinish17-05-1415-07-14StartFinish16-07-1428-09-1421

DISTRICT 8 SENOPATISEQUENCE OF FOUNDATION WORKS

CORE AREARAFT FOUNDATIONOUT OF CORE AREASLAB & WALL FOUND.#1 Lean Concrete all area#2 Anti termite #3 Waterproofing work#4 Bottom Rebar all area#5 Top Rebar Bottom Slab Out of Core Area#6 Vertical Rebar for Wall & Column Out of Core Area & For Raft Foundation#7 Pouring Bottom Slab Out of Core Area Rebar work for Raft Found. Continue#8 Setting Horizontal Rebar Wall, Setting Wall Formwork Out of Core Area, Rebar work for Raft Found. Continue#9 Pouring Wall Out of Core Area Rebar work for Raft Found. Continue#10 Remove Wall Formwork Out of Core Area & Install Formwork of Raft Found #11 Pouring Raft Foundation#12 Remove Formwork Raft Foundation#13 Fill in chamber by Sand w/Compaction + Layering Plastic Sheet on top + Lean Concrete#14 Install Rebar Top Slab Out of Core Area#15 Pouring Top Slab (B3 Slab) Out of Core Area22

DISTRICT 8 SENOPATIDURATION OF STRUCTURE WORK Siklus pekerjaan struktur area tower Kantor 1Lantai B3 : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 25~30 hariLantai B2 ~ GF : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 21~25 hariLantai 2 ~ 3 : 10~12 hari/zone/lantai , 1 lantai pekerjaan struktur finish 18~21 hariLantai 4 ~ Atap : 7~8 hari/zone/lantai , 1 lantai pekerjaan struktur finish 13~14 hariLantai Atap ~ LMR : 1 lantai pekerjaan struktur finish 16 hari

Siklus pekerjaan struktur area tower Kantor 2Lantai B3 : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 25~30 hariLantai B2 ~ GF : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 21~25 hariLantai 2 ~ 3 : 10~12 hari/zone/lantai , 1 lantai pekerjaan struktur finish 18~21 hariLantai 4 ~ Atap : 7~8 hari/zone/lantai , 1 lantai pekerjaan struktur finish 13~14 hariLantai Atap ~ LMR : 1 lantai pekerjaan struktur finish 14 hari

Siklus pekerjaan struktur area tower Apartment 1 & 2Lantai B3 : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 25~30 hariLantai B2 ~ GF : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 21~25 hariLantai 2 ~ 3 : 10~12 hari/zone/lantai , 1 lantai pekerjaan struktur finish 18~21 hariLantai 4 ~ Atap : 6~7 hari/zone/lantai , 1 lantai pekerjaan struktur finish 13~14 hariLantai Atap ~ LMR : 1 lantai pekerjaan struktur finish 14 hari

Siklus pekerjaan struktur area tower Service Apartment (A3)Lantai B3 : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 25~30 hariLantai B2 ~ GF : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 21~25 hariLantai 2 ~ 3 : 10~12 hari/zone/lantai , 1 lantai pekerjaan struktur finish 18~21 hariLantai 4 ~ Atap : 7~8 hari/zone/lantai , 1 lantai pekerjaan struktur finish 10~12 hariLantai Atap ~ LMR : 1 lantai pekerjaan struktur finish 12 hari

Siklus pekerjaan struktur area diluar TowerLantai B3 : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 25~30 hariLantai B2 ~ GF : 13~15 hari/zone/lantai , 1 lantai pekerjaan struktur finish 21~25 hariLantai 2 ~ 4 : 10~13 hari/zone/lantai , 1 lantai pekerjaan struktur finish 18~21 hariLantai 5 ~ 8/Atap : 7~8 hari/zone/lantai , 1 lantai pekerjaan struktur finish 14~16 hari

23

DISTRICT 8 SENOPATICYCLE OF WORK TYPICAL FLOORKANTOR 1 TOWER

24

DISTRICT 8 SENOPATICYCLE OF WORK TYPICAL FLOORKANTOR 2 TOWER

25

DISTRICT 8 SENOPATICYCLE OF WORK TYPICAL FLOORAPARTMENT 1 TOWER

26

DISTRICT 8 SENOPATICYCLE OF WORK TYPICAL FLOORAPARTMENT 2 TOWER

27

DISTRICT 8 SENOPATICYCLE OF WORK TYPICAL FLOORSERVICE APARTMENT TOWER

28

DISTRICT 8 SENOPATISEQUENCE OF FORMWORK & PROPPINGFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGPROPPINGFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKFORMWORKTEMPORARY SAFETY ASAGOFIXEDTEMPORARY SAFETY ASAGOMOVEABLE29

DISTRICT 8 SENOPATIPROGRESS OF WORKS

End of MONTH 7th

End of MONTH 8th

End of MONTH 9th

End of MONTH 10th

End of MONTH 11th

End of MONTH 12th

End of MONTH 13th

End of MONTH 14th

End of MONTH 15th

End of MONTH 16th

End of MONTH 17th

End of MONTH 18th

End of MONTH 19th

End of MONTH 20th

End of MONTH 21st

End of MONTH 22nd

End of MONTH 23rd

End of MONTH 24th

End of MONTH 25th

End of MONTH 26th30

SATRIO SQUARE OFFICE TOWERFORMWORK SYSTEM

31

SATRIO SQUARE OFFICE TOWERFORMWORK SYSTEM

32

SATRIO SQUARE OFFICE TOWERFORMWORK SYSTEM

33

SATRIO SQUARE OFFICE TOWERUPPER STRUCTURESAFETY34

SATRIO SQUARE OFFICE TOWERORGANISASI K3

35

SATRIO SQUARE OFFICE TOWERPERATURAN DAN TATA TERTIB

36

TEMPORARY FENCEPH 1PH 2SITE OFFICE & STORAGEFORM WORK STOCK & FABRICATION AREAREBAR STOCK & FABRICATION AREALIGHT DUTY WORKINGPLATFORMHEAVY DUTY WORKINGPLATFORMGUARD HOUSEGUARD HOUSEGATE 1GATE 2GATE 3CONCRETE PAVEMENTGENSETHOUSETC

GUARD HOUSE

MPMPP3KP3KP3K

TUTUTUTUMP

P3KTEMPORARY URINOIRMUSTER POINTAPARKOTAK P3KP3KTEMPORARY RAILING

SATRIO SQUARE OFFICE TOWERSAFETY PLAN37

SATRIO SQUARE OFFICE TOWERSAFETY INDUCTION & AKTIFITAS RUTIN K3

38

SATRIO SQUARE OFFICE TOWERTRAINING K3 & SAFETY AWARD

39

SATRIO SQUARE OFFICE TOWERPROTEKSI KESELAMATAN

40

SATRIO SQUARE OFFICE TOWERPROTEKSI KESELAMATAN

41

SATRIO SQUARE OFFICE TOWERRAMBU-RAMBU KESELAMATAN

42

SATRIO SQUARE OFFICE TOWERAPLIKASI RAMBU-RAMBU KESELAMATAN

43