PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING … · 2017. 5. 28. · 4.4 Size or...

13
1 (B) PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING PROJECT OF Ashokbhai Khushalbhai Ode AT VILLAGE:- Sayar, TALUKA:- Karjan, DIST.:-VADODARA CONTENTS

Transcript of PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING … · 2017. 5. 28. · 4.4 Size or...

Page 1: PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING … · 2017. 5. 28. · 4.4 Size or magnitude of operation : B category manual. The existing capacity N.A. / year 6000 TPM.

1

(B)

PREFEASIBILITY REPORT

OF

EXISTING ordinary sand

MINING PROJECT

OF

Ashokbhai Khushalbhai Ode

AT VILLAGE:- Sayar,

TALUKA:- Karjan,

DIST.:-VADODARA

CONTENTS

Page 2: PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING … · 2017. 5. 28. · 4.4 Size or magnitude of operation : B category manual. The existing capacity N.A. / year 6000 TPM.

2

1.0 INTRODUCTION

1.1 PREAMBLE

2.0 EXECUTIVE SUMMARY

3.0 INTRODUCTION OF THE PROJECT /BACKGROUND

INFORMATION

4.0 PROJECT DESCRIPTION

4.0 AVAILABLITY OF RAW MATERIAL

5.0 SELECTION OF SITE & LOCATION OF STONE MINE

6.0 PLANNING BRIEF

7.0 EXISTING INFRASTRUCTURE

8.0 REHABILITATION AND RESETTLEMENT (R & R) PLAN

9.0 PROJECT SCHEDULE & COST ESTIMATES

10.0 ANALYSIS OF PROPSAL (FINAL RECOMMENDATION)

Page 3: PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING … · 2017. 5. 28. · 4.4 Size or magnitude of operation : B category manual. The existing capacity N.A. / year 6000 TPM.

3

1.0 INTRODUCTION

1.1 Preamble

ordinary sand is base of all types of Building works, Construction of Road,

Construction of Cement Concrete road and infrastructure. The need of ordinary sand

is in all fields are very essential as it is a compulsory material for all types of

construction, and Industries fields, ordinary sand Mines are providing employments to

the local Labour in Rural area, as the labour of rural area have no any work for labour,

They are Unemployed, Thus this Existing mine is providing work to many labours and

it is a good employment.

2.0 Executive Summary

ASHOKBHAI KHUSHALBHAI ODE is an existing mine, as the demand of

construction material in all sectors are highly necessary, and this project will provide

and try to fulfill major demands of ordinary sand in complete around area. About

01.00.00 hectare of land is under possession of ASHOKBHAI KHUSHALBHAI

ODE At, Village : KARJAN, Taluka : SAYAR, Dist : VADODRA. As per the statuary

obligation this project needs environmental clearance from department of Environment

and forest dept.(GPCB) Gujarat. It is Existing lease and to start quarrying

operations (production) Accordingly project proponent has submitted form 1, pre-

feasibility report and copy of Approval letter from department of mines and geology

Gujarat, to the state level environmental assessment authority of Gujarat constituted

by MOEF, GOI for issuing environmental clearance, as per EIA, September 14.2006

notification but the term of S.E.A.C. and S.E.I.A.A. of Gujarat is expired in July - 2013.

3.0 Introduction of the Project/Background information :

1 Name of the Existing unit ASHOKBHAI KHUSHALBHAI ODE

2 Registered Office AT-KARJAN, TA-SAYAR, DIST-VADODRA

3 Location of Existing unit Village : KARJAN,SR NO. 424 OPP. / NARMADA

RIVER - 01.00.00 HA,Taluka : SAYAR Dist : VADODRA.

(Gujarat)

4 Name of Owner ASHOKBHAI KHUSHALBHAI ODE

Page 4: PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING … · 2017. 5. 28. · 4.4 Size or magnitude of operation : B category manual. The existing capacity N.A. / year 6000 TPM.

4

3.2 Brief description of nature of the project :

It is an existing plan of ordinary sand Quarrying, it will contains ordinary sand

which will be used in construction of infrastructures and road, railways and building

construction etc.

3.3 Demand - Supply Gap :

As sand is used as raw material in construction of building and infrastructure

projects, the demand of sand is increasing day by day. In past, demand was not too

much but now a days due to rapid industrialization and urbanization its demand

increasing with pace of time. At present, demand of sand is more than the supply.

3.4 Imports vs. Indigenous Production :

In VADODRA of Gujarat, a number of sand mines are there. There is abundance of

sand in the area; it had become a major source of economy in the area/region.

3.5 Export Possibility :

There is ban on sand export to other states in the Gujarat by Private so export

possibility of river sand from this area is nil.

Major consumers of sand located almost in nearby areas in the district.

3.6 Domestic / Export Markets :

Sand produced is used locally as well as circulated in nearby area. So clearly there is

a huge market of sand in the area.

3.7 Employment Generation (Direct and Indirect) due to the project :

By this mining project of river sand in the area, peoples get employment, The

project directly generates the employment for the local people and indirectly for

the others. Also the marketing of the product generates the employment for

peoples. By this project, approximately Skilled labours-3 and Unskillled 10 to 15

labours on project site.

4.0 Project Description

4.1 type of project including interlinked and interdepended project if any :

No other material is interliked with this mining work.

4.2 Location (map showing general location, specific location and project

boundary & project site layout) with co-ordinates :

Page 5: PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING … · 2017. 5. 28. · 4.4 Size or magnitude of operation : B category manual. The existing capacity N.A. / year 6000 TPM.

5

The area has been marked on Google map including the mining lease location. This

comprises the mining lease area near village : KARJAN, taluka: SAYAR, Dist :

VADODRA of Gujarat location of the mining lease is as under.

Location map

The geographical location of

the project is as follows :

Page 6: PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING … · 2017. 5. 28. · 4.4 Size or magnitude of operation : B category manual. The existing capacity N.A. / year 6000 TPM.

6

SR.NO Latitude (N) Longitude (E)

A- 21°52'0.36"N 73°14'21.45"E

B- 21°51'56.90"N 73°14'22.57"E

C- 21°51'57.86"N 73°14'25.56"E

D- 21°52'1.15"N 73°14'24.36"E

4.3 Detail of alternate site, considered and the basis of selecting the existing

site, particularly the environment considerations gone into should be

highlighted :

No other site is considered for the existing project. The land has been allocated by

government for the mining only. As sand in the river is replenished every year by river

so, site is adequate for sand mining.

4.4 Size or magnitude of operation : B category manual.

The existing capacity N.A. / year 6000 TPM. Total area of mining lease is 01.00.00

Ha.The mining operation will be @ 6000 Tonne Production of River sand per annum.

4.5 Project description with process details ( a schematic diagram/flow chart

showing the project layout, components of the project etc. is given below:

Open cast mining

Fencing

Page 7: PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING … · 2017. 5. 28. · 4.4 Size or magnitude of operation : B category manual. The existing capacity N.A. / year 6000 TPM.

7

4.6 Raw material required along with estimated quantity, likely source,

marketing area of final products. Mode of transport of raw materials And

finished products :

No raw material is required during the mining process.

4.7 Resource optimization / recycling and reuse envisaged in the project. If any,

should be briefly outlined :

As a result of extraction of mineral, the rate of recharging of ground water is likely to

be increased considerably.

4.8 Availability of water its source, Energy/power requirement and source

should be given :

Total water requirement in the mine will be about 3.0 KLD for drinking & domestic use,

dust suppression and plantation. Drinking water will be available by water tanker from

nearby village KARJAN. Diesel will be used in dumpers and tractors.

Nearly village KARJAN is well electrified.

4.9 Quantity of wastes to generated (liquid and solid) and scheme for their

Management/disposal :

No waste will be generated. All the material is saleable.

4.10 Schematic representations of the feasibility drawing which give

information of EIA purpose :

According to MOEF mining project containing area ≤5 Ha. Are considered in

category B2. Schematic representations of the feasibility is as under.

OB removal

Loading

Transportation to end use

Page 8: PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING … · 2017. 5. 28. · 4.4 Size or magnitude of operation : B category manual. The existing capacity N.A. / year 6000 TPM.

8

5.0 site Analysis

5.1 Connectivity

Mine site is well connected with road transport. Nearest railway station is at

CHANDOD RAILWAY STATION (5 km) of mine site. State Highway No. GJ SH 160

(2.93 km). VADODRA is the District centre and all the primary facilities like education,

health centres including hospitals govt. as well as private, religious places are

vailable. District centre VADODRA is connected by GJ SH 160 is 2.93 km. away

from lease area.

Project Concept and Site selection

From 1 pre - feasibility project report wi th

existing TOR to MOEF (EAC)

Scoping by SEAC (site visit by sub group of

SEAC, if necessary

Ategory B2 – EIA not required

Appraisal and recommended by SEAC

Appraisal by SEAC

Display on the SPCB/UTPCC website &

project proponent website

Page 9: PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING … · 2017. 5. 28. · 4.4 Size or magnitude of operation : B category manual. The existing capacity N.A. / year 6000 TPM.

9

5.2 Land Form - Land use and land Ownership :

The area of lease is 01.00.00 Ha. (SR NO. 424 OPP. / NARMADA RIVER - 01.00.00

HA). The lease areaforms part of No forest land is involved in leased area. Details are

given in below table.

S.NO Type Land Of Area

in (Ha.)

Near

Village

Tatuka District State

1 On River bed

SR.NO- 424 opp.

NARMADA

RIVER - 01.00.00

HA

01.00.00 KARJAN SAYAR VADODRA Gujarat

5.3 Topography (Google image):

The lease area is situated nearby village Sayar. Topographically, the area is almost flat &

river bed area.

5.4 Existing land use pattern (agriculture, non-agriculture, forest, water bodies

including area under CRZ), shortest distances from the periphery of the

project to periphery of the forests, national park, wild life sanctuary,

eco sensitive areas, water bodies(distance from the HFL of the river),

CRZ. In case of notified industrial area, a copy of the Gazette notification

should be given:

Page 10: PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING … · 2017. 5. 28. · 4.4 Size or magnitude of operation : B category manual. The existing capacity N.A. / year 6000 TPM.

1

0

Nearest

Sensitive Area

Name Distance from

the Project

within 10 kms

a)Reserve Forest N.A.

There is no

reserve or

protected forest

within 10.0 kms

of lease area.

b) National

Park

c) Wild life

Sanctuary

N.A.

There is no

national park or

wild life

sanctuary within

10.0 km of lease

area.

d) Eco sensitive

areas

N.A.

There is no eco

sensitive area

within 10.0 km

of lease area

e) Water source

(a)Ground water

map

N.A.

No big water

reservoir is

within 10.0 km

of lease area

The grounder

water level is 10

to 15 mt. deep

The project is

located in

seismic zone-3

There is no

flood.

Cloudburst and

and landslide

reported so far.

Page 11: PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING … · 2017. 5. 28. · 4.4 Size or magnitude of operation : B category manual. The existing capacity N.A. / year 6000 TPM.

1

1

f) CRZ

There is no

C.Z.R. within

10.0 km

periphery of

lease area

5.5 Existing infrastructure:

Mine office is existing in lease area. A well equipped first aid facility is existing to be

available at there. Temporary rest shelter urinal and latrine are established. Water

will be purchased from nearby tube well from nearby villages. A small water tank also

exists in mine office premises. This can be used for supply of water to drinking

purposes.

5.6 Soil classification:

Soil of the region falls within Average rain fall zone of 850-900 mm. The soils are

sandy loam, shallow depth reddish-black soils.

5.7 Climatic data from secondary sources :

The climate here is considered to be a local steppe climate. There is not much rainfall

in VADODRA all year long. According to Köppen and Geiger, this climate is classified

as BSh. The temperature here averages 27.4 °C. The average annual rainfall is 827

mm.

5.8 Social Infrastructure available : N.A.

6.0 Planning Brief:

6.1 Planning Concept (type of industries, facilities, transportation etc.)

Town and country planning development authority classification:

No industries and town planning programmers in the existing area.

6.2 Population Projection:

No Human settlements near project area.

6.3 Land Use planning (breakup along with green belt etc):

Page 12: PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING … · 2017. 5. 28. · 4.4 Size or magnitude of operation : B category manual. The existing capacity N.A. / year 6000 TPM.

1

2

Details will be given in land use pattern of quarry plan.

6.4 Assessment of Infrastructure Demand (Physical & Social):

There is no large infrastructure demand near to existing area.

6.5 Amenities / Facilities:

Not applicable as it is a small project.

7.0 Existing Infrastructure:

7.1 Industrial Area (processing Area): N.A. 7.2

Residential Area (Non Processing Area): N.A.

7.3 Green Belt:

The plant will follow the norms and will in process to develop 33% green belt in lease

area

7.4 Social Infrastructure: N.A.

7.5 Connectivity (Traffic and Transportation Road/Rail/Metro/Water ways etc):

Well connected with Road/Rail No metro and water ways.

7.6 Drinking Water Management (Source & Supply of water):

Drinking water will be procured from tube well Existing nearby.

7.7 Sewage system:

The domestic wastewater will be treated in the septic tank followed by soak pit.

7.8 Industrial waste management: N.A. 7.9

Solid waste management: N.A.

7.10 Power Requirement & Supply / Source: N.A.

8.0 Rehabilitation and Resettlement (R&R) Plan:

Page 13: PREFEASIBILITY REPORT OF EXISTING ordinary sand MINING … · 2017. 5. 28. · 4.4 Size or magnitude of operation : B category manual. The existing capacity N.A. / year 6000 TPM.

1

3

Policy to be adopted (Central / State) in respect of the project affected persons

including home outs tees, land outs tees and landless laborers (a brief outline to be

given): N.A.

9.0 Project Schedule & Cost Estimates:

9.1 Likely date of start of construction and likely date of completion (Time

schedule for the project to be given):

It is an existing project and applied for renewal.

9.2 Estimated project cost along with analysis in terms of economic viability of

the project:

No. Particulars

Amounts (Rs.)

1 Mining equipments

40,000/-

2 Trolley based water tanker

1,50,000/-

Total 1,90,000/-

The existing cost of the project is Rs. 2, 00,000/- and it is economically

10.0 Analysis of proposal (Final Recommendation):

Financial and social benefits with special emphasis on the benefit to the project will

create employment potential for approximately about 10 to 15 local people.

THANKS