Predictive Maintenance for Improved Grid Performance · Predictive Maintenance for Improved Grid...
Transcript of Predictive Maintenance for Improved Grid Performance · Predictive Maintenance for Improved Grid...
Predictive Maintenance for Improved Grid Performance
Presenter: John Lauletta – Exacter, Inc.
Technical Tutorials 1
Agenda
• Predictive Maintenance Basics
• Creating PdM Business Cases
• Assessing the Grid
• Field Findings
• Case Studies
Technical Tutorials 2
Predictive Maintenance (PdM)
• To use data from an entire process to find any measurable characteristics that may serve to warn that these detrimental situations are approaching.
• PdM techniques are designed to help determine the condition of in-service equipment in order to predict when maintenance should be performed. This approach promises cost savings over routine or time-based preventive maintenance, because tasks are performed only when warranted.
• PdM inspections are performed while equipment is in service, thereby minimizing disruption of normal system operations. Adoption of PdM can result in substantial cost savings and higher system reliability.
Technical Tutorials 4
Predictive Maintenance (PdM)
Visual Inspection
Infrared Detection
Ultrasonic Detection
RF Emission Grid Inspection
Technical Tutorials 5
Impacts of Maintenance Strategies
Technical Tutorials 7
Early FailurePeriod
Constant FailurePeriod
Wear-out FailurePeriod
Failu
re R
ate
Periodic/Preventive Maintenance
Predictive Maintenance
PdM – How?
• To evaluate equipment condition, predictive maintenance utilizes non-destructive testing technologies such as infrared photography, ultrasonic acoustic, radio frequency (RF) emissions, corona detection, vibration analysis, sound level measurements, oil analysis, and other specific online tests.
Technical Tutorials 8
PdM Why? Benefits of PdM Strategies
• Maintenance costs - down by 50%
• Unexpected failures - reduced by 55%
• Repair and overhaul time - down by 60%
• Spare parts inventory - reduced by 30%
• 30% increase in machinery MTBF
• 30% increase in uptime
Technical Tutorials 9
Applying PdM Strategy to the Grid
1. Assess System Condition2. Schedule Maintenance3. Measure Results4. Repeat Process
Technical Tutorials 10
Animals18%
Miscellaneous19%
U.S. Non Weather-Related Outages on the Electric Distribution System
Data Source:
32% of outages are caused by trees
31% of outagesare caused by
failing equipment
Technical Tutorials 11
Animals18%
Miscellaneous19%
Maintenance Techniques
32% of outages are caused by trees
31% of outagesare caused by
failing equipment
Technical Tutorials 12
Data Source:
Detecting Equipment Failure
Device
• Insulator
Failure Mechanism
• Internal Damage
• Contamination
• External Damage
• Dry Band Arcing
• Leakage
• Tracking
Technical Tutorials 13
• RF/USAC Emission
• RF/USAC Emission
• RF/USAC Emission
• RF/USAC Emission
• RF/USAC Emission
• RF/USAC Emission
Failure Detection
Detecting Equipment Failure
Device
• Lightning Arrester
Failure Mechanism
• MOV Damage
• Contamination
• External Damage
• Dry Band Arcing
• Leakage
• Tracking
Technical Tutorials 14
• RF/USAC/IR Emission
• RF/USAC Emission
• RF/USAC Emission
• RF/USAC Emission
• RF/USAC Emission
• RF/USAC Emission
Failure Detection
Detecting Equipment Failure
Device
• Cutout
Failure Mechanism
• Internal Damage
• Contamination
• External Damage
• Dry Band Arcing
• Leakage
• Tracking
Technical Tutorials 15
• RF/USAC Emission
• RF/USAC Emission
• RF/USAC Emission
• RF/USAC Emission
• RF/USAC Emission
• RF/USAC Emission
Failure Detection
Detecting Equipment Failure
Device
• Transformer
Failure Mechanism
• Bushing Damage
• Contamination
• Internal Arcing
• Low Oil
Technical Tutorials 16
• RF/USAC Emission
• RF/USAC Emission
• RF/USAC/IR Emission
• RF/USAC/IR Emission
Failure Detection
Detecting Equipment Failure
• Use Technologies that measure specific failure symptoms
• Apply Technologies in most cost-effective manner
• Manage conditions-based analytics for proactive maintenance action
Technical Tutorials 17
Common Utility Focus Areas• Worst Performing Circuits
• Customer Satisfaction Improvement
• CMI or other related indices
• Circuit Rebuild Priority
• Smart Grid and/or AMI Preparation
• Geography
• Critical Loads
• Equipment Type – i.e. surge arrester only, porcelain cutouts, etc.
Technical Tutorials 19
Elements of Return on Investment (ROI)
• SAIDI Reduction – Value of a SAIDI Minute
• CMI Reduction – Value of a Customer Minute of Interruption (CMI)
• Economic Cost of Outage to Customers
Technical Tutorials 20
Strategic Need
Utility
Director
Grid CMI Data
Exacter
Analyst
Opportunity
Utility
Executive
ReduceSAIDI
Proposal
Technical Tutorials 21
Executive Summary
ProgramObjective
# 3P Miles
# Circuits
Projected Impact
Units/Cost
A. System-Wide SAIDI Reduction StrategyOptimize overall reliability improvementCriteria: Top 613 Circuits: CMin/Mile
7,000 6131.8 to 3.6 SAIDI Min
System-wide
B. Divisional SAIDI Improvement StrategyDivisional targets for reliability improvementCriteria: Bottom 3 Divisions : Divisional SAIDI
9,000 3304.6 to 9.2 SAIDI Min
Targeted Population
C. Focused Customer Experience StrategyTargeted EQ-Related WPCsCriteria: Top 119 Circuits: Circuit SAIDI
5,000 11830 to 60
SAIDI MinTargeted Population
Technical Tutorials 22
A. Holistic/Strategic: System-Wide CMin/SAIDI ReductionBased on Top-Ranked Equipment-Related CMin/MILE CircuitsPresents optimal strategy at 57% of the miles of 1.0
PROJECT SUMMARY PROJECT SCOPE % OF TOTAL
EQ CMin Total 100,058,262 73%
EQ CESO Total 998,040 75%
OH 3P Miles 8,113 7%
Circuit Count 613 20%
# Customers 1,548,757 28%
TARGETED SAIDI 18.12 max system-wide potential
PROJECTED SAIDI SAVINGS 1.8 to 3.6 projected 10%-20% result*
*actual field results showing 20%-40% YoY improvements
PROJECTED SAIDI REDUCTION 2.72 @ 15% improvement
PROJECTED CMin REDUCTION 15,008,739 @ 15% improvement
PROJECT BENEFITS
SYSTEM-WIDE SAIDI IMPROVEMENT - TOP EQ CMin/MILE
Technical Tutorials 23
A. Holistic/Strategic: System-Wide CMin/SAIDI ReductionBased on Top-Ranked Equipment-Related CMin/MILE Circuits
Data
Service Division (if applicable) or Subtation IDCircuit / Feeder NameSum of Equipment CMI Per Mile Sum of OH 3-phase Miles Sum of Feeder Customers Served Count of Circuit / Feeder Name
SAN FRANCISCO 1,134,580 105 137,992 56
PENINSULA 802,670 231 115,426 52
EAST BAY 653,789 243 137,026 58
MISSION 475,089 141 103,005 31
SAN JOSE 385,667 198 138,883 38
DE ANZA 378,159 166 75,350 27
SIERRA 337,912 501 40,366 20
NORTH BAY 298,737 436 90,732 34
DIABLO 258,699 151 88,648 32
KERN 243,368 415 72,640 32
CENTRAL COAST 214,034 794 120,033 35
FRESNO 208,942 681 86,921 42
SACRAMENTO 187,202 668 70,029 34
STOCKTON 172,458 406 47,100 30
YOSEMITE 142,533 912 55,060 24
HUMBOLDT 141,634 488 32,361 16
LOS PADRES 113,246 919 71,959 22
NORTH VALLEY 104,409 439 24,063 18
SONOMA 76,358 218 38,819 14
Grand Total 6,329,487 8,111 1,546,413 615
Technical Tutorials 24
4.0 Tactical: Improved Customer ExperienceFocused on circuit SAIDI WPCsCircuits Experiencing > 200 EQ-Related SAIDI
PROJECT SUMMARY PROJECT SCOPE % OF TOTAL
EQ CMin Total 25,067,758 18%
EQ CESO Total 160,127 12%
OH 3P Miles 5,487 5%
Circuit Count 119 4%
# Customers 83,237 2%
TARGETED SAIDI 301.16 FOR TARGETED POPULATION
PROJECTED SAIDI SAVINGS 30 to 60 projected 10%-20% result*
*actual field results showing 20%-40% YoY improvements
PROJECTED SAIDI REDUCTION 45.17 @ 15% for targeted population
PROJECTED CMin REDUCTION 3,760,164 @ 15% for targeted population
CIRCUITS EXPERIENCING MORE THAN 200 EQ SAIDI
PROJECT BENEFITS
Technical Tutorials 25
4.0 Tactical: Improved Customer ExperienceFocused on circuit SAIDI WPCsCircuits Experiencing > 200 EQ-Related SAIDI
Row Labels Sum of Equipment Circuit SAIDI Sum of Total OH Miles Sum of OH 3-phase Miles Sum of Feeder Customers Served Count of Circuit / Feeder Name
NORTH BAY 19,307 6 0 10 1
SAN FRANCISCO 12,030 22 5 6,432 4
KERN 8,736 1,317 906 6,802 24
FRESNO 6,605 1,564 1,098 8,622 20
CENTRAL COAST 5,343 331 278 2,225 9
NORTH VALLEY 3,660 834 436 5,399 9
SIERRA 2,781 351 235 3,861 6
YOSEMITE 2,704 862 625 7,660 10
SACRAMENTO 2,325 947 728 5,697 8
HUMBOLDT 2,253 620 305 12,647 7
LOS PADRES 2,070 930 467 9,475 6
STOCKTON 1,584 242 177 1,393 5
SONOMA 712 198 71 6,797 2
EAST BAY 672 19 5 1,154 3
MISSION 519 12 3 3,424 2
DE ANZA 344 3 1 979 1
DIABLO 238 - 3 11 1
Grand Total 71,884 8,259 5,343 82,588 118
Technical Tutorials 26
Sustained Outages (SO):• EQ-related rank highest• Unknown issues are 83% of EQ
issues – likely presents another area of focus as we proceed
Technical Tutorials 27
Customer Minutes of Interruption (CMin)• EQ-related ranks highest (again)• Unknown issues are 36% of EQ issues
Technical Tutorials 28
• Based in Columbus, OH
• US / Canada Alliance Partners
• International Alliance Partners
Australia, Mexico
• 5 U.S. Patents, 7 Int’l Patents
• 2 million+ Poles Surveyed
• 3rd Party Validation
• DOE
• NETL
• The Ohio State University
Grid Condition Assessment Priorities for Improved System Resiliency and Reliability
Technical Tutorials 29
Technical Tutorials 30
Exacter Process & Technologies
• Visit identified structure
• Confirm presence of PD/EMI
• Identify specific component(s) responsible for problematic condition
Condition Assessment
Strategic Need
Utility
Director
Grid CMI Data
Exacter
Analyst
Opportunity
Exacter
Survey
Grid Conditions
Contract
Exacter
Field Eng.
Condition Causes
Utility
Operations
New Grid CMI Data
Utility
Executive
ReduceSAIDI
Utility
Operations
Grid Repairs
Exacter
Analyst
PriorityCriteria
GIS CircuitPriority
ProposalField
Report
OptimalMaint.
Plan
Technical Tutorials 31
The 31% Problem
All Studies Agree:
31% of Non-Storm Related Outages in America are due to Deteriorating Equipment
Technical Tutorials 33
Grid Conditions-Based AssessmentWhat is it?
• A strategic and analytic assessment of Overhead circuits that accurately identifies opportunities to improve circuit performance, reliability, and grid resilience
How Does it Work?
• A collaborative process that incorporates utility outage information, technology, and analytics to accurately assess overhead systems
Benefits of PdM on the Grid
• Grid Condition Assessmentsprovides strategic, specific, and actionable information to improvecircuit performance
• Reduce CMI and related indices
• Optimize outage information
• Prioritize maintenance operations
• Reduce costs association with outagerestoration
Example Long Term Trend Analysis
Index2011 2012 2013 2014
SAIDI (minutes)71.18 61.33 63.92 23.38
SAIFI (# of outages)1.52 1.48 1.53 1.03
CAIDI (minutes)46.73 41.32 41.9 22.78
MAIFI (interruptions)5.48 6.13 5.83 4.21
Technical Tutorials 34
Technical Tutorials 39
Regional Deteriorated Equipment Findings
KCP&L Located Equipment
Transmission Posts
2%
Transformers
2%
Dead Ends
12%
Insulators
4%
Lightning Arrestors
7%
Cutouts
3%
Pin Insulators
69%
Misc HW
1%
Lightning Arrestors
Cutouts
Dead Ends
Misc HW
Pin Insulators
Insulators
Transformers
Transmission Posts
Progress Energy Florida — Located Equipment
Non-Utility
2%Trans
Post Insulators
6%
Transformers
6%
Dist
Post Insulators
15%Lightning Arrestors
55%
Ground
2%
Pin Insulators
10%
Dead Ends
4%
Lightning Arrestors
Ground
Transformers
Dead Ends
Pin Insulators
Dist Post Insulators
Trans Post Insulators
Non-Utility
APS Located Equipment
Transmission Posts
10%
Transformers
4%
Dead Ends
16%
Insulators
4%
Lightning Arrestors
13%
Cutouts
10%
Pin Insulators
42%
Misc HW
1%
Lightning Arrestors
Cutouts
Dead Ends
Misc HW
Pin Insulators
Insulators
Transformers
Transmission Posts
Western Located Equipment
Transmission Posts
14%
Transformers
3%
Dead Ends
14%
Insulators
6%
Lightning Arrestors
0% Cutouts
6%
Pin Insulators
57%
Misc HW
0%
Lightning Arrestors
Cutouts
Dead Ends
Misc HW
Pin Insulators
Insulators
Transformers
Transmission Posts
Baltimore
Lightning Arrestors
17%
Cutouts
2%
Deadends
3%
Misc HW
2%
Pin Insulators
74%
Insulators
0%
Transformers
0%
Grounds
2%
Lightning Arrestors
Cutouts
Deadends
Misc HW
Pin Insulators
Insulators
Transformers
Grounds
Baltimore
Lightning Arrestors
4% Cutouts
12%
Deadends
7%
Misc HW
7%
Pin Insulators
55%
Insulators
4%
Transformers
4%
Grounds
7%
Lightning Arrestors
Cutouts
Deadends
Misc HW
Pin Insulators
Insulators
Transformers
Grounds
Transmission Posts
2%
Transformers
2%
Dead Ends
12%
Insulators
4%
Lightning Arrestors
7%
Cutouts
3%
Pin Insulators
69%
Misc HW
1%
Lightning Arrestors
Cutouts
Dead Ends
Misc HW
Pin Insulators
Insulators
Transformers
Transmission Posts
Contamination Flashover
• Largest component of unknown problems
• Difficult to overcome without a PdM strategy
• Creates Fuse Blows, Breaker Operations, and Recloser Operations
Technical Tutorials 40
Laboratory Specimen Test Setup
Arrester Under Test
Antenna Array and Ground Plane
RF Emission Instrumentation
Adjustable HV AC Source
Technical Tutorials 46
Comparing New and
Deteriorated Arresters
• Current Sensing Resistor is 25 ohms
• Resistive voltage divider = 1000/1
• Leading current is typical until cutoff voltage is reached
• 58 Field samples were reviewed
New Specimen
Deteriorated Specimen
Technical Tutorials 47
RF Emission Spectrum
• Linear Frequency scale 0 to 1.5 GHz
• Historical and Instantaneous analysis shown
Deteriorated SpecimenEmission Spectrum
Technical Tutorials 48
Demodulated RF Emission Analysis
Condition Signature Development
Onset of Failure Signature @ 0.67
MCOV
End of RF Signature @ 0.56 MCOV
Sensor correlates demodulated emission characteristics to failure signature
Technical Tutorials 49
Sensor Evaluation
• Results of 170 samples in 10 second intervals for one arrester
• Analysis frequency range from 60 to 3 kHz
• Vertical scale uncalibrated sensor signature correlation statistic Emission Data Evaluation
One Specimen
Technical Tutorials 50
Central Texas Service Territory
• 6 counties
190,000+ customers served
4,600 Distribution Miles
• 2,200 Overhead Miles
• 2,400 Underground Miles
Case Study – South Central U.S.
Technical Tutorials 51
Data Analysis: Historical Interruption Data
The customer provided the most recent 12 months of interruption data
• October 1, 2013 – September 30, 2014
• IEEE Equipment Cause Codes:
• 300 – Material or Equipment Failure
• 400 – Decay/Age of Material or Equipment
• 410 – Corrosion/Abrasion of Material or Equipment
Outage Cause CMI# of
Interruptions% of CMI
Equipment 1,619,925 85 33% (Approx)
** Excludes IEEE days for MEDs // Excludes Momentaries
Technical Tutorials 52
Data Analysis: Exacter Pareto Analysis
• Exacter Analysis normalizes the dataset to allow for meaningful comparison of the circuits
• Divide Total EQ CMI / OH Miles for each circuit
• The new metric used to compare circuits is Equipment CMI / OH Mile
• Exacter ranks each circuit by the Equipment Related CMI / OH Mile
• Circuits with the highest Equipment CMI / OH Mile provide the greatest opportunity to improve performance and reliability
Technical Tutorials 53
Data Analysis: Exacter Pareto Analysis
Feeders that represent greatest opportunity for improvement
Technical Tutorials 54
2015 Pilot Assessment
The pilot covers portions of 67 circuits totaling 180 miles of overhead distribution
- The majority of overhead miles are 3-phase infrastructure- Eastern area of Service territory- High growth area
The option has the opportunity to impact 993,338 equipment related customer minutes of interruption (CMI)
- 29 Equipment related outages
# of
circuits
# of OH
Miles
% of OH
Miles
Equipment
CMI
% of Equipment
CMI
Estimated #
of Repairs
2015 Assessment 67 180 8.5% 993,338 61.3% 20
Circuit Selection: Pareto & Geographic
** Excludes IEEE days for MEDs // Excludes Momentaries
Circuit Selection
Technical Tutorials 55
2015 Pilot Assessment: Equipment Findings
Component # of findings % of findings
Bushing on Capacitor 1 1.5%
Bushing on Transformer 1 1.5%
Lightning Arrester 27 40.3%
Pin Insulator 32 47.8%
Oil Switch 1 1.5%
Switch 1 1.5%
Transformer 2 3.0%
Post Insulator 1 1.5%
Strain Insulator 1 1.5%
Total Component Finds 67
2015 Pilot AssessmentSurvey Results
Technical Tutorials 57
2015 Pilot Assessment: Component Finds
• Exacter assessment identified 1 component every 2.68 miles
– 3-phase overhead // co-located circuits // overbuild
– Density of service territory
– Presence of protective devices on system
• Exacter assessed 6,446 poles
– 180 assessed miles = 6,446 poles
– 67/6,446 = 1.03% of poles with problematic conditions
– 98.97% of assessed infrastructure does not have presence of problematic conditions
Technical Tutorials 58
2015 Pilot Assessment:
Considerations & Conclusions
• May 2015: “Wettest” month on record for Dallas-Ft. Worth area• 4.4 million lightning strikes
• More than 2013 or 2014 total
• Correlate lightning strike data with Exacter assessment
• Maintenance Operations for Identified Components • Further Lightning Arrester investigation
• Identify use for Exacter assessments in future maintenance operations
Technical Tutorials 60
Summary and Remaining Work
• Arresters are a critical component in electric grid equipment reliability
• Arresters are most deteriorated in areas of greatest need: Southeast/Northeast U.S.
• Visual damage is not typically apparent and does not necessarily indicate state of protection element
• RF emissions characterize deterioration that impacts performance
• In 58 samples, 57 showed deterioration of protective ability
• More field samples will be evaluated in laboratory conditions to optimize failure signature discrimination and source location for utility maintenance planning
Technical Tutorials 61