Precast July 2014
Click here to load reader
-
Upload
isikhova-publishing -
Category
Documents
-
view
231 -
download
2
description
Transcript of Precast July 2014
the cma – QUaLItY caSt IN cONcRete
PRECASTVOLUME EIGHT ISSUE 2 • 2014
co
nc
re
te
m
anufacturers
as
so
cia
tio
n
Quality cast in concrete
• Self-compacting concrete in precast applications
• Precast facades used for load-bearing in Germany
• Poor paving specification costs R-millions
PRECAST VOLUME 8 • ISSUE 2 • 2014
1ConTenTS
neWS2 AFRISAM LAUnCHeS BUSIneSS DeVeLoPMenT CenTRe
2 CIVILWoRKS BeGInS RIB AnD BLoCK MAnUFACTURInG
4 CMA STAnD ATTRACTS SUBSTAnTIAL InTeReST AT ToTALLy ConCReTe
4 CMA STAGeS BoTSWAnA RoADSHoW
5 CARGo CARRIeRS ASSISTS LAFARGe WITH oWneR-DRIVeR PRoGRAMMe
7 neW CMA DIReCTIon MAPPeD oUT AT AGM
CoVeR SToRy8 PeoPLe CoMe FIRST AT SePHAKU CeMenT
ARTICLeS11 SUSPenDeD PAVInG – IT’S In THe BAG
12 HoLLoW-CoRe SLABS FAST-TRACK oFFICe DeVeLoPMenT
14 SeLF-CoMPACTInG ConCReTe BeCKonS LoCAL PReCAST PRoDUCeRS
18 ULTRA-THIn ConCReTe SUPPoRTS HeAVy DUTy LoADS AT n3 WeIGHBRIDGe STATIon
20 HoLLoW-CoRe yIeLDS MoRe SPACe FoR STUDenTS
22 PReCAST FACADeS USeD FoR LoAD-BeARInG In GeRMAny
24 PooR PAVInG SPeCIFICATIon CoSTS R-MILLIonS
26 neW MeMBeRS’ RoLL ConTInUeS To GRoW
APPLICATIonS27 neW RAnGe oF MoULD ReLeASe AGenTS
28 PeRMeABLe PAVInG BLoCK PRoVIDeS eCo- FRIenDLy MoBILITy FoR nATURe ReSeRVe
28 ALFABLoC – RoCLA’S PoRTABLe ReTAInInG WALLInG SySTeM
29 CoST-SAVInG GeoGRID CHoSen FoR ReTAInInG WALL
30 ARCHITeCTS PLUMB FoR PeRMeABLe PAVInG SySTeM
31 PReCAST PAVeRS SPeCIFIeD FoR InAnDA CLUB ReDeVeLoPMenT
31 PUMPInG ConCReTe To ReCoRD HeIGHTS
MeMBeR DeTAILS33 MeMBeRS’ LIST
PReCAST is the official journal of the Concrete Manufacturers Association NPC (CMA)
16 Horn Street, Chloorkop, Kempton Park, 1620
PostNet Suite 8612, Private Bag X32, Kempton Park, 1620
Tel: +27 11 805 6742, Fax: +27 86 524 9216
E-mail: [email protected], Website: www.cma.org.za
Publishers
Isikhova Publishing & Communications
PO Box 651793, Benmore, 2010, South Africa
Tel: +27 11 883 4627, Fax: +27 11 783 2677
Website: www.isikhova.co.za
Publisher: Andrew Meyer
Tel: +27 11 883 4627, Cell 082 456 5175
E-mail: [email protected]
Editor: David Beer
Tel: +27 11 478 0239, Fax: +27 11 678 0254
E-mail: [email protected]
Advertising: Charlene Pillay
Tel: +27 11 883 4627
E-mail: [email protected]
Design, layout and production: Joanne Brook
Tel: +27 11 883 4627 E-mail: [email protected]
The views and statements expressed in this publication are not necessarily those of the editor or the publishers and neither he, the publishers nor the CMA accept responsibility for them. No person connected with the publication of this journal will be liable for any loss or damage sustained as a result of action following any statements or opinions expressed herein.
precast contents
ON THE COVER
Pictured here are the cement si-los at Sephaku Cement’s 155 ton- per-hour cement milling plant in Delmas, Mpumalanga. The plant be- gan producing cement in January and deploys some of the world’s
best high-tech cement-producing equipment. It also incorporates the latest environmentally-friendly technology with particular emphasis on high effi-ciencies and reduced power consumption. See the full story on page eight.
THE CMA – QUALITY CAST IN CONCRETE
PRECASTVOLUME EIGHT ISSUE 2 • 2014
co
nc
re
te
m
anufacturers
as
so
cia
tio
n
Quality cast in concrete
• Self-compacting concrete in precast applications
• Precast facades used for load-bearing in Germany
• Poor paving specification costs R-millions
NEWS
PRECAST VOLUME 8 • ISSUE 2 • 2014
2
aFrIsaM LaUNcHes BUsINess DeVeLOpMeNt ceNtre IN sUppOrt OF sMMe grOwtHCMA member, AfriSam recently opened its
Supplier Development Centre in support
of the company’s Enterprise Development
Programme which has been implemented as
part of a transformation drive, especially in
areas where the company operates.
The aim of the Supplier Development
Programme is to identify black-owned Small,
Medium and Micro Enterprises (SMMEs)
close to the company’s operations and
provide these entrepreneurs with the
necessary support and development for
them to grow their business and ultimately
be included in AfriSam’s database of
registered vendors.
To date, AfriSam’s Enterprise Devel-
opment team has held SMME campaigns
and open days with communities around
the company’s Lichtenburg, Roodekrans,
Roodepoort and Eikenhof operations. More
communities will be included as the pro-
gramme is rolled-out to other provinces
in the future.
Situated on a property adjacent to
AfriSam CEO Dr Stephan Olivier at the launch of the business development centre.
cIVILwOrKs BegINs rIB aND BLOcK MaNUFactUrINgCMA producer member, Civilworks, has
begun manufacturing precast concrete
rib and block flooring material.
A manufacturer of a wide range of
precast concrete products, Civilworks
bought a rib and block production line from
Econoslab in April and re-commissioned
it within two weeks at its Klipriv ier
manufacturing facility in Gauteng.
“While we are pleased with the pur-
chase of the assets, and more so with
the successful and speedy resumption
of production, the biggest gain has been
the transfer of the production and sales
teams. This has ensured a seamless tran-
sition,” says Graham Crooks, Civilworks
managing director.
“We have retained a combined 50 years
of experience within the teams. That
type of transfer is rare, and will ensure
continued quality and service levels.
“Flooring has not formed part of our
traditional civils market, but our strategy
as a precast concrete producer is for
continued growth. We will achieve this both
organically and by acquisition. Rib and block
flooring offers good growth potential and
fits well with our other product lines and
logistic competencies”, he added.
Econoslab was one of the original pro-
ducers of this type of innovative flooring
system, and the product has stood the
test of time over some 18 years. There are
literally thousands of successful installa-
tions spread throughout southern Africa.
“With that reference base and market
footprint, the decision was made a lot
easier, and we are happy to be involved in
this exciting market”.
Civilworks is still an active and growing
producer of miscel laneous v ibrated
products for the civil and structural
industry, and a supplier of manholes to the
sewer, telecoms, and electrical industries.
Other lines include a wide range of municipal
and road products, and a growing list of
bespoke, or special items for individual
clients or applications.
The first blocks produced by Civilworks’ rib and block team at the new facility.
AfriSam’s Roodepoort Cement operation,
the Business Development Centre will also
provide SMMEs with a facility where they
will have access to computers that have
already been set up with an accounting
package that will enable them to manage
their statements and invoices.
The Centre for Supplier Development, a
company focusing on SMME development,
has been appointed to provide entrepre-
neurs with training and development that
will enable them to a level where they can do
business with AfriSam and other companies.
In Lichtenburg, Motswiri Consulting
has been appointed to a similar task of
identifying and developing entrepreneurs
from local communities around the
Dudfield operations, and up-skill them to
a level where they operate efficient and
sustainable businesses.
Some entrepreneurs in Gauteng and
Lichtenburg will be enrolled in an acceler-
ated development programme, with the aim
of ensuring they are ready to do business
with AfriSam.
“This is a wonderful example of how
AfriSam lives its values of People and Planet,
making a sustainable difference to the
communities in which we operate. Well done
to the Enterprise Development team for
making this happen. AfriSam looks forward
to contributing towards the sustainable
growth of these businesses”, says Calie
Ehrke, AfriSam’s supply chain manager.
PRECAST VOLUME 8 • ISSUE 2 • 2014
4 neWS
cMa staND attracts sUBstaNtIaL INterest at tOtaLLY cONcreteThere was huge interest in the CMA stand
at this year’s Totally Concrete exhibition
and conference staged at the Sandton
Convention Centre at the end of May.
Twice the size of last year’s display
at 18m², the CMA stand was manned by
executive director, Wally Armstrong and
Pam Zukor. They were assisted by, Shawn
Sewnath of Brickcast, Silvio Ferarris of
Marcin Nowakowski of Techmatik during his presentation at the CMA.
The Totally Concrete Roads seminar.
Wally Armstrong shares a joke with some visitors to the CMA stand.
The CMA’s Botswana roadshow.
cMa stages BOtswaNa rOaDsHOw May saw the CMA staging a membership
drive in Botswana together with ABCON
(Association of Botswana Building and
Civil Engineering Contractors). Over 60
delegates comprising architects, engi-
neers, contractors, material suppliers,
government employees, students and four
CMA members, Kwena Concrete Products,
Kwena Rocla, Fastdeck and Panda, at-
tended the event.
CMA executive director, Wally Arm-
strong, introduced the CMA and spoke
about its role as the primary representa-
tive of precast concrete in southern Af-
rica and its expanding African footprint.
Subsequent presentations were made by
Lafarge, Chryso, MTS (Chryso’s Botswana
agent), Techmatik and ABCON.
Lafarge showcased its range of cements
and the success it has had with fly ash in
Botswana and Chryso gave a presentation
on the importance of oiling moulds correctly.
CMA member, Techmatik’s Marcin Nowa-
kowski, outlined modern trends in Europe’s
paving and concrete block making industry.
In addition to the CMA, the event was
jointly sponsored by Lafarge, Chryso, MTS
and Techmatik.
ReMaCon, CMA PR consultant, David Beer,
and two overseas members, Marcin Nowa-
kowski (Polish) of Techmatik and Thomas
Schardax (Austrian) of Schlüsselbauer
Technology. The display was sponsored by
nine CMA members; Brickcast; Concrete
Units; Coverland; Echo Group; ReMaCon;
Rocla; Schlüsselbauer Technology; Tech-
matik; and Technicrete.
Wally Armstrong says the interest in
the CMA extended to several requests
for membership. Most came from local
companies but there was foreign interest,
including a block-making machinery company
from China.
A highlight of the CMA’s Totally Concrete
contribution was a seminar on precast con-
crete road construction, Totally Concrete
Roads. It was presented to some 40 con-
ference delegates by independent paving
consultant, John Cairns, who discussed
construction methodologies of precast
concrete roads and the products used to
build them.
Another CMA contribution involved a
panel of experts who answered questions
on precast concrete products and
applications. It comprised: Coenraad
Groenewald of Aveng Manufacturing
Infraset; Graham Crook of Civilworks;
Daniel Petrov of the Echo Group; and Silvio
Ferarris of ReMaCon.
The day after Totally Concrete, Techma-
tik’s Marcin Nowakowski gave a fascinating
two-hour presentation to a select audience
on modern trends in Europe’s paving and
concrete block making industry.
He said that since Poland was trans-
formed into a democracy in the early
1990s, the concrete block and paving
industry had boomed in that country to
the extent that today every major town in
Poland boasts a paving block manufacturer.
He observed that Poland’s current output
was equivalent to that of Germany’s at 85
million paving units a year, and that the two
countries were the world’s biggest paver
producers. Techmatik is one of the world
leaders in manufacturing lines for concrete
paving blocks and decorative products and
sells its equipment worldwide.
5NEWS
Cargo Carriers and Lafarge Cement owner-driver trucks.
Cargo Carriers has assisted Lafarge (one
of its customers) in establishing a B-BBEE
owner-driver scheme. Lafarge saw an
opportunity to develop an owner-driver
scheme based on increased volumes of
its bagged cement products in the Free
State, Northern Cape, and North West
Province and approached Cargo Carriers
for assistance.
Cargo Carriers introduced its own
owner-driver initiative in 2003.
“Owner drivers are contracted directly
to us by means of a service agreement
and we assist them with everything,” says
John Sprenger, Cargo Carriers, owner-
driver manager.
“We source the business opportunity,
provide our own management system,
mentorship and training until the owner-
driver is self-sufficient. This enables us
cargO carrIers assIsts LaFarge wItH OwNer-DrIVer prOgraMMe
business management and communication.
To further increase its B-BBEE rating,
Lafarge owner drivers appointed black
females, either spouses or girlfriends, as
their business partners. This allows Lafarge
to claim at three different B-BBEE levels:
preferential procurement; enterprise devel-
opment; and ownership, with more points
being attained for having black females as
part of the ownership structure.
“We believe our owner-driver scheme is
a win-win initiative. It is about a continuing
partnership in which the drivers are
empowered to determine their own success
and future with the concomitant benefit
of increased productivity and enhanced
service levels,” says Tim Nelson, Lafarge
Cement’s supply chain manager.
“The Lafarge owner-driver initiative
proves that the provision of supply-chain
solutions can go beyond the obvious
areas of application such as performance
and safety. This is what happens when
innovation meets B-BBEE and the results
are truly transformative,” says Sprenger.
to claim for preferential procurement and
enterprise development.”
Cargo Carriers appointed its own drivers
for the Lafarge project as strict selection
criteria are enforced. One of the key condi-
tions for participating in the Lafarge scheme
is compliance with the rigorous Lafarge
South Africa safety standards for driving
and maintenance of the vehicles. Moreo-
ver, drivers underwent intensive training
covering contractual issues, operating pa-
rameters, accounting matters, budgeting,
PReCAST VOLUME 8 • ISSUE 2 • 2014
7neWS
New cMa DIrectION MappeD OUt at agMA new operating structure was announced by CMA executive
director, Wally Armstrong, at the Association’s annual general
meeting which was held at Caesar’s Palace on June 19.
Armstrong advised that the new structure will commence from
March 2015. Other presentations were given by CMA financial
director, John Simpson, and by guest presenters who included:
CMA member, Envirotan’s Business Development manager,
Chantel Maree; CMA member, ASPASA’s director, Nico Pienaar;
and FSC Consulting Engineers consultant, Fred Crofts.
Armstrong said the new executive board would comprise one
executive director and atleast three non-executive directors.
The board is to be supported by several committees and a panel
of experts. Comprising seven individuals, the panel of experts
will provide members with access to a range of consultancy
expertise in the manufacture, application and promotion of
precast concrete. This service is to be delivered at competitive
rates by individual panel members. Details on the panel of
experts and their experience can be viewed on www.cma.org.za.
Armstrong stressed that the success of the CMA essentially
rested on the level of involvement and input from members. He
suggested that members identify ways in which the CMA can
assist them, be this through joint participation in exhibitions
such as Totally Concrete, the publication of technical literature,
or through staging technical seminars, among other avenues.
He also spoke about the Association’s social responsibility
projects. Current projects include the Vrederfort Bridge, the
Rhodes Park Junior Traffic Centre and assisting CMA member,
The Job Club in building precast concrete structures for a
business development initiative. The latter involves establishing
unemployed members of Mamelodi and Moloto communities in
forming commercial ventures.
Wally Armstrong makes his presentation at the CMA’s AGM at Caesar’s Palace.
PRECAST VOLUME 8 • ISSUE 2 • 2014
8 CoVeR SToRy
“Our operation is based on a combination
of non-negotiable quality checkpoints. A
high quality product, which in our industry
means consistency, strength and durability,
is imperative and this demands optimal
performance from every employee. Achieving
this means we must equip ourselves through
ongoing skills acquisition in all aspects of
our business while remaining attuned to the
changing needs of our customers. This, and
state-of-the-art equipment, will enable us
to provide consistent levels of customer
service excellence down the years.
Fourie adds that customer dialogue will
be pivotal to Sephaku Cement’s modus
operandi, so much so, that customers
will have direct access to Fourie and his
executive team.
“Face-to-face customer service without
red tape is invaluable and makes for quick
decision making,” he says. “It remains the
most effective way of listening to custom-
ers and responding to their challenges and
requirements appropriately.”
Commenting on the six-and-a half years
it took to bring Sephaku Cement on stream,
Fourie says he and his team had to over-
come some formidable challenges.
“We were entirely success driven and
never lost faith in why we were coming to
market or in the long-term sustainable
growth prospects of the cement industry.
South Africa may have a relatively good
infrastructure but there is still much to
be developed. Sephaku Cement’s modern
technology, its cost-ef f iciencies and
the commitment of its people, give us a
competitive edge. Looking ahead, we will
remain committed to the people who bring
our products to the market, and to making
South Africa’s cement industry more
people focused.
“Building cement production operations
from the ground up has given us the
With the advent of bag and bulk de-livery by Sephaku Cement, some may wonder what to expect from this new entrant to the South African cement market. Chief executive, Pieter Fourie, observes that the company is primarily people-focused, and values its custom-ers and employees in equal measure.
peOpLe cOMe FIrst At sePHAKU ceMent
Holdings. Sephaku Holdings secured
limestone resources in 2006 when it
invested the initial seed capital. By late
2010, the projects were fully funded, having
attracted South Africa’s largest inward
investment by an African company, Dangote
Cement, one of Africa’s largest cement
producers. Additional debt financing was
provided by Nedbank and Standard Bank.
“We navigated our way through the
global recession by sheer determination
and a belief in our ability to change the face
of the South African cement industry. Ours
is a team passionate about cement-enabled
opportunities. While all of us at Sephaku
have been in the industry for many years,
this project has been a once-in-a-lifetime
experience. Not only has it made us better
cement technologists, but better people,
and we have learnt more than we ever
thought possible. Above all, we discovered,
at first hand, just how incredible the
results can be when teamwork comes into
play,” concluded Fourie.
opportunity to deploy some of the
world’s best high-tech cement-producing
equipment and to establishing new quality
benchmarks across our three cement
grades: Sephaku 32; Sephaku 42; and
Sephaku 52. Moreover, the greenfield
nature of this project has enabled us
to dictate product quality rather than
be dictated to by existing operational
constraints. Both our Delmas plant, which
began producing cement in January and
our Aganang plant in Lichtenburg, which
comes on stream later this year, have
been equipped with the latest-generation
Loesche vertical roller mills.
“We want to ensure that every customer
gets the best value from our product
offering and to this end our Delmas-based
laboratory is providing technical assistance
such as product testing and special mix
design support.”
Sepahku Cement is a 64% owned
subsidiary of Dangote Cement plc and an
associate company of JSE-listed Sephaku
PRECAST VOLUME 8 • ISSUE 2 • 2014
11ARTICLe
Unlike conventional paving or tiling on a con-
crete surface in which the pavers or tiles
are grouted directly onto a concrete base
layer, in suspended paving the pavers are
mounted on small polythene sandbags (see
top picture) without the use of any adhesive
or binding agent. All that is needed to keep
the pavers firmly in place is their weight.
Moreover, they are laid 10-12mm apart
which creates a water permeable surface.
These and other advantages are why
suspended paving is finding increasing
favour among some of the country’s
leading architectural practices. The
process has already been used on some
major construction projects using pavers
supplied by Cape–based CMA member,
Revelstone. Some recent projects include:
Cape Peninsula-based projects such as:
Liberty Life’s headquarter premises in
Century City; Bloemhof in Tyger Valley;
Wembley Square in Gardens; and some
student residences in Stellenbosch.
Suspended paving has also been used
at Dainfern Square in Johannesburg and
Liberty Life’s Umhlanga offices in KwaZulu-
Natal, among other high-profile projects.
According to Johnny Schwartz, a partner
of Louis Karol Architects – one of the
How does one convert a dull bitumen-coated flat roof or terrace into an attractive paved surface without the use of grout or any other form of binding agent? One answer is to be found in suspended paving, a process which uses concrete flagstone pavers without the use of any binding agent.
which is sloped for drainage purposes. Flat
surfaces are achieved by altering the thick-
ness of the supporting sandbags to com-
pensate for the slope. Secondly, because
the paved surface is permeable, there is
no water pooling even during the heaviest
of storms. This means that as soon as the
rain has abated, the surface can be walked
on without any concerns for wet feet.
“Another major advantage is the fact
that the paved surface creates a protec-
tive layer which shields the waterproofing
on the base layer from the sun’s UV rays
and from other forms of possible damage.
However, in the event that the base layer
does require some routine or other main-
tenance work, it is easily effected by simply
lifting the pavers and then re-inserting
them once the job has been completed.
“Contrast this with the expense and
inconvenience of lifting and replacing pavers
which have been grouted to the base layer.
Moreover, no expansion joints are needed
with suspended paving and there is no
chance that the pavers will crack or lift
due to wind or earth induced movement,”
says Schwartz.
Revelstone director, Alex Cyprianos,
says that suspended paving is generally
used in low-traffic areas such as concrete
roofs, balconies and terraces.
“The pavers tend to be large, averaging
600mm² and 55mm thick. We produce a
wet-cast flagstone paver for the purpose
which is steel reinforced, and we can also
make up special shapes to accommodate
curved borders.”
The sandbags used in suspended paving
are filled with a mixture of sand and cement
which hardens once the laying process has
been completed. Over time the polythene
outer casing will deteriorate leaving a hard
and durable concrete core.
Suspended paving is installed at Wembley Square, Cape Town.
The completed suspended paving surface at Wembley Square.
sUspeNDeD paVINg –
suspended-paving pioneers – the process
offers some distinct advantages over
conventional roof-top or terrace paving.
“In the first instance it allows for the
creation of a level paved surface on a base
A balcony at Liberty Life’s head office premises at Century City, Cape Town, where concrete flagstone pavers were used for a suspended paving contract.
It’s In tHe BAG
PRECAST VOLUME 8 • ISSUE 2 • 2014
12 ARTICLe
Built in two phases, the first compromising
a gross lettable area (GLA) of ± 3 100m²
and the second, 3 700m² GLA , the project
was the initiative of local property devel-
oper, Krisp Properties.
“We already had a lease agreement with
Michelin Tyre Company South Africa for
Phase 1 well before the first sod had been
turned, which meant we only had seven
months to erect the building,” said Jordan
Mann, executive director of Krisp Properties.
Francois Marais of Francois Marais Ar-
chitects said the construction of the build-
ings embraced new energy efficiency legis-
lation rather than being restricted by it.
“The design uses overhangs above all
the windows and doors to minimise the
impact of the sun and to reduce heat loss,”
says Marais.
Completed by the end of November
2013, Phase 1 comprises two double
storey buildings, each measuring 1 550m²
(GLA), which are linked by a central
entrance atrium.
“We deployed hollow-core slabs for the
first floors as well as the roofs, and this
assisted us in reducing construction time
by several weeks. Hollow-core slabs were
used for the roofing which would allow the
necessary support for the installation of
Hollow-core concrete slabs – manufactured by CMA member, Echo Prestress – in combination with structural steel frames and raft foundations were used for the fast-track construction of a new office development at Clearwater Estate in Boksburg.
HOLLOw-cOre sLaBs FAst-tRAcK oFFIce DeVeLoPMent
photovoltaic power generation units in
future. Moreover, the roofs have created
ideal catchment areas for harvesting rain-
water which is to be stored in subterranean
tanks,” said Mann.
Echo’s prestressed hollow-core slabs
were specified by PDS Civil and Structural
Engineers and slabs totalling ± 3 100m²
were used for Phase one. Phase two will
make use of ±3 750m² of Echo slabs. Slabs
up to 10m were deployed on the first floor
sections and slabs of between five and seven
metres were installed on the roof. Both the
first floor and roof panels were topped with
steel reinforced screeds and a bitumen
coating was used to waterproof the roofs.
In addition, Echo also supplied nine metre
H-shaped universal steel columns to provide
slab support for the internal cantilevering.
According to structural engineer, Spi-
ros Sdralis, of PDS, Echo’s role involved
Clearwater Phase 1.
A section of Clearwater Phase 2 under construction.
13
PRECAST VOLUME 8 • ISSUE 2 • 2014
ARTICLe
P O Box 124, Sanlamhof, 7532
considerably more than simply supplying
the slabs.
“We provided Echo with a set of draw-
ings and they then prepared a layout which
took all the servicing requirements into ac-
count. Echo’s engineer, Daniel Petrov, was
involved from the outset and he was always
on site when we needed him,” said Sdralis.
“For example, some of the slabs had to
be modified so that the upper-section of
steel skeleton could be anchored to the first
floor on a solid platform. This meant that
the hollow-core end sections of some slabs
had to be packed with concrete to provide
the solid base. Echo filled in the voids with
concrete according to our specifications
and this enabled us to drill out the holes for
the bolt anchor sleeves in the same way as
we had done on the ground floor.
“The builders were able to begin the
assembly of the upper level steel frame
as soon as the slabs had been installed
and this was the prime advantage of
using hollow-core slabs. If in-situ flooring
had been used it would have delayed the
completion dates on both buildings by
several weeks.
“Extensive use was made of cantile-
vering, both internally and for the shade
overhangs, and Daniel assisted with rede-
signing some of the cantilever sections on
Phase 2. He also helped us with changing
the direction of some of the slabs.”
Echo also allowed for service ducts and
suspended ceilings were created 600mm
below the soffits of the roofs and first
floors to accommodate piping and cabling. The upper-level steel framework of Phase 2 which was bolted to solid concrete sections of Echo slabs.
Phase 1 of Clearwater Park Boksburg, where Echo Prestress hollow-core slabs were used to fast track the development.
PRECAST VOLUME 8 • ISSUE 2 • 2014
14 ARTICLe
This explains why so many precast produc-
ers in other parts of the world use SCC
exclusively in place of conventional vibrated
concrete (CVC). Having no slump, SCC can
flow over dense reinforcement and fill voids
under its own weight. And it does this with-
out the need for any post-cast vibration.
As a result moulds can be less robust and
last much longer, noise pollution is greatly
reduced, and the casting process is much
quicker, neater and easier.
Further time savings, long workability
(one hour) and an improved work ing
environment are other benefits. But
arguably its major advantages are high
durability combined with substantially
superior finishes, factors which have
not escaped one of the country’s leading
precast concrete producers. Since the
middle of 2013 Rocla has been using SCC
Self-compacting concrete (SCC) has been used in the developed world for over three decades, yet until recently, it has remained off limits to most South Afri-can precast concrete manufacturers. Complex mixes, increased costs, extreme sensitivity to even the smallest changes in chemical composition and produc-tion processes, and the hands-on attention it demands for achieving consistent results, go some way to clarifying this apparent local reluctance. But for those brave enough to grasp the nettle, the rewards are substantial.
BecKons LocAL PRecAst PRoDUceRsfor a new range of precast products and
for improving the quality of its existing
product line up.
A CMA producer member and part of the
ISG Group, Rocla began experimenting with
SCC in early 2012 shortly after it realised
that some new products such as the
Alfabloc retaining walling system, REBLOC
road barriers, wing walls for stormwater
outlets, and more recently, precast
concrete cabins for photovoltaic plants,
would be better and more easily produced
with SCC. Using European guidelines and
standards (none exist in SA as yet), it took
a year of research and experimentation
before the company was producing SCC
to consistent best-practice standards.
A f ormidab le group o f concrete
technologists was assembled to conduct
Rocla’s SCC research. They included: Rocla
seLF-cOMpactINg cONcrete
15
PRECAST VOLUME 8 • ISSUE 2 • 2014
ARTICLe
BecKons LocAL PRecAst PRoDUceRsA newly cast photovoltaic cabin prior to delivery.
SCC is pumped into a photovoltaic cabin mould.
as we did without the use of SCC. This
achievement led us to introduce SCC at
several other Rocla branches, the ultimate
goal being to produce all our wet-cast
products with SCC. Our Virginia branch
is already using SCC for the manufacture
of culverts and special products such as
Alfablocs and road barriers.
“The requirement for optimal chemical
balances meant we had to prepare specific
SCC designs for each of our branches
across the country, due to chemical
variations in raw materials and the manner
in which they react with each other.
Rocla’s SCC trials began with smaller
products such as manhole cover slabs and
the Alfabloc. Initially several obstacles
were encountered in achieving consistent
levels of repeatability and robustness.
“For instance, we were unable to
achieve robust mixes at first and slight
variations would cause a mix to fail and not
self-compact. Furthermore, when using
precisely the same ingredients in exactly
the same quantities, some of the mixes
would yield variable results and it took time
to work out why,” said Kretzmar.
Commenting on the research work,
Roberts said that he found SCC to be ex-
tremely water sensitive and that anything
above a two percent water variance could
throw out the total mix design in contrast
to about five percent for CVC.
“We made extensive use of fly ash and
condensed silica fume in all the mixes.
Silica fume is a super fine powder, its par-
ticles being about 50-100 times finer than
the average cement or fly ash particles,
and like fly ash, it’s also an eco-friendly
by-product material. We found that fly ash
improved flow and mobility and decreased
water demand whereas silica fume pre-
vented bleeding.”
Roberts added that conveying SCC
from mixer-to-hopper-to-mould presented
additional challenges.
“We observed that even when moving
SCC over a distance of 50-100m, the ensu-
ing vibration, which varied in line with ground
surface conditions, could cause the mix
to separate. The obvious and more costly
alternative involved pumping the concrete
directly from the mixer to the moulds.
However, getting this right meant further
changes to an already successful SCC mix
design and considerable trial and error.
“Initially we encountered frequent
blockages in the pipes which could cause
delays of up to an hour. The pumps were
so powerful that if not properly controlled
and monitored, they would force the
civil technologist, Jason Roberts; Murray
& Roberts group concrete and research
manager, Cyril Attwell, and Warren Mc
Kenzie of the Murray & Roberts Centre
of Concrete Excellence (CCE). Antony
Offenberg of Mapei SA and Rocla head
office personnel added further expertise
to the team. The latter included sales
engineer, Justin Kretzmar and Rocla
technical executive, Gerhard Rossouw.
Commenting on the development work,
Kretzmar said the research team relied
extensively on CCE’s ARC Technology which
focuses on establishing optimal chemical
balances between all the components of
concrete mixes, such as cement, stone,
sand, fly ash, silica fumes, various chemi-
cals and additives.
“We could not have managed our
photovoltaic cabin project as successfully
The photovoltaic cabin mould at Rocla’s Johannesburg premises.
PReCAST VOLUME 8 • ISSUE 2 • 2014
17ARTICLe
An installed photovoltaic cabin which was manufactured under license to Spanish company, Prephor.
cement/water paste inside the pipes past
the aggregates. With the assistance of
Mapei and CCE we examined the aggregate
ratios and other material combinations,
and managed to create a mix suitable for
pumping. Moreover, the pumps had variable
flows and this enabled us to match pump
outputs to the rate of production.
“Besides being much safer than
transporting hoppers with dump trucks,
forklifts or cranes, we found that pumping
made the casting process a lot faster,
by a factor of five at the very least. For
example, we were able to cast a complete
photovoltaic cabin shell (outer walls and
base slab), using approximately eight cubic
metres of SCC in 30 to 40 minutes as
opposed to the 160-210 minutes it would
have taken had we used CVC and more
conventional modes of shifting and then
vibrating the concrete.
“Another challenge was mould stripping,
especially off the cabins and other thin-
walled sections such as the roof and
internal walls, which required exceptionally
smooth finishes and very early strengths.
In order to meet our client’s delivery
schedule, we needed to produce five to
six complete cabins a week using only a
single mould. This meant we had to strip
and recast one cabin a day. Requiring 12m³
of concrete, completed cabins comprised:
outer walls; base floor; suspended floor; a
roof and internal walls; and weighed close
on 28 tons.
“Meeting this production schedule meant
we had to achieve compressive strengths
of 18MPa after 12 to 16 hours and we
relied on a combination of accelerators
and steam heating to do so. To begin with
we used accelerators without the steam
but we found that the former impinged on
the self-compacting properties of the SCC
and affected other quality aspects as well.
By introducing steam heating we were
able to reduce the amount of accelerator
and still realise our early 18MPa strength
requirement. Moreover, after seven days
we were achieving around 60MPa, well in
excess of our 40MPa target.
“Other stripping problems encountered
during the development phase included pull
outs, pin holes and blow holes, blemishes
which could be seen even after painting.
We solved this by changing the releasing
agent and further tweaking the mixes,”
said Roberts.
Kretzmar added that the photovoltaic
cabins are relatively thin-walled, being only
100mm thick at the bottom and tapering
to 75mm at the top.
“Although some sections required dense
reinforcement, we still had to comply
with the required cover. SCC’s flowability
made this very easy for us. Traditional
concrete in a similar application would have
resulted in extensive honeycombing with
the coarse aggregates being visible after
stripping. One very seldom, if ever, finds
honeycombing in SCC.
“One of the reasons SCC is so difficult
to implement in SA is that our aggregates
tend to be flaky, unlike those in America and
Europe, which are more rounded. Needless
to say, we have managed to circumvent
the problem.”
Kretzmar concluded by saying that
although SCC traditionally costs up to
40% more than CVC, the adoption of ARC
technology for mix design, resulted in an
SCC mix at a very similar costing to that
of previous CVC mix designs.
“However, SCC does require a higher
degree of hands-on attention than CVC and
the equipment used to produce it must be
better and more frequently maintained.”
PRECAST VOLUME 8 • ISSUE 2 • 2014
18 ARTICLe
Some 600m of ultra-thin continuously reinforced concrete pavement
(UTRCRCP) has been used in the rehabilitation of the access and egress roads
at the Heidelberg weighbridge stations on the N3 highway, the main corridor
between Johannesburg and Durban. Specified by The South African National
Roads Agency SOC Limited (SANRAL), the 65mm concrete was used to
replace a confalt asphalt surface which had failed in places.
ULtra-tHIN cONcrete sUPPoRts HeAVY-DUtY LoADs At n3 WeIGHBRIDGe stAtIon
premixed off-site. It was important that
we achieved very accurate slumps and to
this end the super plasticisers were added
electronically down to the last millimetre.
What’s more, the amount of water used
in the mix had to be equally accurate,”
Crofford commented.
Before the concrete was placed, the
existing confalt asphalt surface was milled
down to provide a suitable base. Steel
mesh which measured 100 x 75mm was
then fastened to the base prior to placing
the UTCRCP.
Once mixed, the concrete was dis-
charged from the back of the truck off
a metal chute onto the steel mesh. Side
discharging, which would have been prefer-
able, was not possible due to insufficient
space for vehicular access.
‘The concrete had a slump of 90mm and
it only took 15 minutes to set. This meant it
had to be vibrated immediately to eliminate
voids. We attained an average production
rate of 12m³ per day which equates to a
surface area of around 20m², while the
compressive strengths of 65MPa were
achieved after two days rising to 100MPa
after 28 days,” concluded Crofford.
A bag of premixed concrete ingredients is poured into the pan mixer.
King Civil Engineering’s contracts manager, Hugh Crofford.
The concrete is vibrated before setting, which takes 15 minutes.
Concrete with a slump of 90mm, is shovelled down the chute onto the road base.
SANRAL project manager Rajan Padavattan,
said that UTCRCP was specified because of
its superior performance properties as well
as level constraints which are critical for
the screening and prosecution of illegally
loaded vehicles.
The professional team comprised King
Civil Engineering Contractors (main con-
tractor) Aurecon/Blue Quartz, (consulting
engineers) and PC Floors (sub-contractor).
King Civil Engineering’s contracts manag-
er, Hugh Crofford, said that this was the first
time King Civil had used ultra-thin concrete.
“It obviously entailed a considerable
amount of trial and error and we worked
with Allan de Kock of Beton Lab to design
the concrete so that it met SANRAL’s
80MPa specification. Initially the intention
had been to source ready-mix concrete
from an AfriSam depot in Nigel, but a very
short workability time of only 15 minutes
meant that we had no option but to design
our own mixing platform and to do the final
mixing on site.
“Experimenting with concrete is a
lengthy process and it took us three months
to get a suitable mix design approved us-
ing AfriSam’s 50.2 cement. Moreover, the
stringent specifications for all the materials
used in the mix required that all ingredi-
ents had to be tested. We also included
three types of sand which were difficult to
source. Other materials used in the mix in-
cluded steel fibres at 80kg/m³ for additional
strength and 2kg/m³ of polypropylene fibres
to assist against cracking.
“We installed an 800lt generator-
powered pan mixer on the back of the
truck. Apart from the plasticisers, steel
fibres and the water, all the materials were
PRECAST VOLUME 8 • ISSUE 2 • 2014
20 ARTICLe
The use of prestressed hollow-core
slabs, supplied by CMA producer
member, Portland Hollowcore, has
significantly increased floor space
to a student apartment development
currently under construction above
Eikestad Mall, a modern shopping
centre in the heart of Stellenbosch.
HOLLOw-cOre YIeLDs MOre sPAce FoR stUDents
The apartments are being built on the con-
crete roof of the mall by NMC Construction
Group. Given that all roofs have a limited
weight-bearing capacity, the weight of the
building materials used in the construction
of the apartments was a crucial design
consideration.
NMC projects manager, Johan Be-
zuidenhout, said that hollow-core slabs
were an obvious choice for the apart-
ment flooring at Eikestad Mall because
they weigh some 35% less than an in-situ
concrete flooring equivalent.
“Further weight savings were made
through the use of a light clay brick which
weighs 2.5kg. By applying these light-
weight materials we were able to build
116 apartments.
“Speed of construction was another
important design consideration because
the development is taking place on two
main streets in the heart of Stellenbosch’s
CBD and we wanted to minimise disruption
to vehicular and pedestrian traffic as much
as possible. Precast slabs have certainly
assisted in this regard as they only take
hours or at most days to install unlike in-
situ concrete which takes two to three
weeks. Moreover, there is no formwork or
rebar to offload in the streets below.
“Another advantage of hollow-core slabs
is that building operations can resume as
soon they are installed. At Eikestad we
started building the apartment walls before
we laid the structural topping on the slabs
which comprised a 50mm 25MPa concrete
reinforced with 100 rev mesh. The topping
abuts the walls, and in doing so, creates
an automatic joint which allows for wind-
induced movement.
“We also caulked the joints where the
slabs meet end-on-end to prevent the con-
crete topping from seeping into slab hollows
and wasting material’” said Bezuidenhout.
Dirk Thiart, Portland Hollowcore’s site manager, seen here above a hollow-core flooring deck at Eikestad Mall.
A hollow-core slab is lowered into position at Eikestad Mall.
Portland Hollowcore supplied over 950
prestressed hollow-core slabs in lengths
varying between 1.5 and eight metres.
Most of them were 160mm thick, although
some sections required 200mm slabs, es-
pecially where load-bearing walls had been
removed to combine two flats into one.
The apartments are being built on three
levels and a 900mm services void has been
created between the roof of the mall and
the bottom floor of the apartments. Most
of the apartments vary between 35m² and
75m² although 10% comprise duplex units
of ±100m².
In addition to NMC Construction Group
the professional team comprised: DHK,
principal agents and exterior architects;
Macgregor Forsyth, interior architects;
KLS, structural engineers; IQS, quantity sur-
veyors; Eppen Burger & Associates, health
and safety; Arcu Gibb, electrical consultants;
WSP, wet services engineers; Landmark
Studios, landscaping architects; Aurecon,
mechanical engineers; Ecko, fire engineers.
PRECAST VOLUME 8 • ISSUE 2 • 2014
22 ARTICLe
Precast concrete technology has been evolving rapidly in Europe, pav-ing the way for solutions that meet sophisticated architectural and eco-nomic requirements. In this article, which was first published by BFT International, an example of how pre-cast concrete facades can now be used for load-bearing as well as aesthetic purposes is examined.
precast FacaDes UseD FoR LoAD-BeARInG In GeRMAnY
Previously any attempt at using precast
concrete facades for load bearing was sub-
ject to tight constraints. However, recent
developments in precast concrete technol-
ogy have ushered in fresh options. The new
Ohligsmühle building in Wuppertal-Elberfeld,
Germany, is a case in point. A prominent
feature of this six-storey building’s enve-
lope is the use of sculptural architectural
concrete components and windows which
extend from floor to ceiling. Yet its major
achievement lies in its ground-breaking
technical approach to facade design.
The architectural concrete components
used on this project facilitated important
load-bearing functions whilst fully complying
with the legal requirements for thermal
insulation. Various facade elements were
grouped together according to their
technical features and prefabricated as
a unit. Internally, the facade extends over
the entire floor without the use of columns
or supports and the floor is linked to the
beam supports using a thermal barrier. This
approach enlarged the floor space available
for letting and provided greater flexibility
for partitioning because the need for
internal facade supports was completely
eliminated. Furthermore, construction
times were shortened significantly.
The concrete facade was designed and
built within approximately 10 months. This
ambitious project required close cooperation
between architects, structural engineers
and the precast plant. HPP Architects
prepared a design which included beams
and columns arranged as a right-angled tri-
angle. Structural engineers, Schüßler-Plan
Ingenieurgesellschaft discarded the option
of mounting solid cast stone elements on
the facade and suggested an external load-
The new Ohligsmühle building merges aesthetics with functionality.A ground-floor corner column with a match-cast head beam section.
Image courtesy rößner, ed. Züblin ag
Facade view with panoramic windows.
First-floor cantilevered element during assembly.
Image courtesy Franke, ed. Züblin ag
Image courtesy Yasar, ed. Züblin ag
23
PRECAST VOLUME 8 • ISSUE 2 • 2014
ARTICLe
precast FacaDes UseD FoR LoAD-BeARInG In GeRMAnY
Formwork stripping from a cast corner column element.
bearing facade design instead. Precast
concrete manufacturers, Züblin AG added
further details to the proposal.
The design team decided to merge entire
facade components and to make the load-
bearing material out of precast concrete.
Columns were connected to each other
via the beams to facilitate and assemble
large facade elements. Overall, 1 215
columns were merged with 770 elements
using 180 tons of reinforced steel. The
precast elements had a total weight of
about 2,600 tons.
The design of the connecting points
between the beams and the columns posed
a particular challenge. This was where the
lines of the isosceles triangle formed by
the column and the lines of the beam’s
unequal triangle intersection created two
adjacent roof areas with varying pitches.
This challenge was overcome by applying
the precast elements so that the fabrica-
tion of sharp-edged intersections without
joints yielded both aesthetic and functional
benefits. The design team tested the
feasibility of all plans at an early stage
using mock-ups at Züblin’s precast plant
in Gladbeck. These were inspected and
approved by the client, and as a result,
load-bearing facade columns made from
architectural concrete were included in
the general contractor’s brief.
A rapid assembly schedule of one storey
per week per building section necessitated
a very high prefabrication rate. Site
cranes lifted each of the elements from
the trailers to final installation positions.
Socket dowels were inserted in the
precast elements and in the cast-in-situ
floor. The facade elements were then
assembled, aligned and filled in whilst being
held in place by diagonal struts. The next
step entailed the in-situ casting of the
floors. Due to their full-storey height of
about 4.70m, the ground-floor columns
had to be split below floor level to comply
with maximum transport dimensions.
The regular floor grid began on the first
storey. The standard elements were
approximately 3.50m high and 5.40m wide
and each of these elements defined the
height of a storey. They were inserted on
top of each other floor-by-floor.
The pointed internal and external cor-
ners of the envelope formed the special el-
ements of the building. Panoramic window
areas that project from the structure,
starting on the first and second floors,
made it impossible to transfer the loads of
these floors directly via the columns. This
was why cantilevered elements were used.
Non-load bearing columns were split for
the assembly of larger precast elements.
A tailor-made solution was also required
for the facade sections of the attic. The
area designed for connecting the roofing
seal had to be integrated with the precast
elements during prefabrication whilst ad-
hering to the geometrical specifications.
The interdisciplinary collaboration of
architects, structural engineers and the
precast plant resulted in a long-lasting
facade design. Sustainable facade elements
and state-of-the-art precast components
provided a high degree of design freedom.
Image courtesy Yasar, ed. Züblin ag
Image courtesy Franke, ed. Züblin ag
Arrangement of joints in the panoramic window area.
Image courtesy rößner, ed. Züblin ag
PRECAST VOLUME 8 • ISSUE 2 • 2014
24 ARTICLe
The Concrete Manufacturers Association NPC (CMA) warns that R-millions are being wasted on concrete block paving (CBP) roads which fail due to poor specification. In many instances paving is simply specified as being 25MPa without any reference to the SABS mark.
One of the CMA’s technical consultants,
civil engineer and independent paving
consultant, John Cairns, says that many
of the engineers and landscape architects
who design paved roads are not aware of
the most important specification criteria
when using CBP.
“I participate in regular paving seminars
and workshops and am amazed at how
many professionals don’t know that the
new CBP standard, SANS 1058:2012, is
based on tensile strength and abrasion
resistance rather than the old standard
of compression resistance. Some are
not even aware that the standard has
changed. Therefore it is hardly surprising
that so many professionals are still
specifying for CBP projects based on
compression strength,” says Cairns.
“In most instances, pavers fail either
by cracking and then splitting, or through
surface abrasion due to factors such
as partic le distr ibution and b inder
occur in shopping centres, office parks
and housing developments, where paved
surfaces tend to be regarded as simple,
not requiring an engineering design.
“By contrast industrial CBP surfacing
is generally designed correctly, especially
where the paving provides a critical
functional element such as the working
surface of a container yard or steel mill.”
percentages, and these properties are
addressed in SANS 1058:2012. The old
standard, SANS 1058:2006 was based
solely on a single compression test which
measures resistance to crushing.
“Paving blocks never crush under load
which is why the compression test is not a
good performance indicator. In fact pavers
can have a very high compressive strength
but poor abrasion resistance. This is why
the standard was changed.
“This lack of awareness is resulting in
failed CBP installations and unnecessary
remedial expense. For instance, I was
recently asked to submit a report on a new
car park paved with CBP at an East London
shopping mall. Serious abrasion had taken
place even though the paved surface was
barely six months old. The reason for this
was that the pavers were simply specified
on the basis of compressive strength
rather than the SABS standard.”
Cairns says that most paving failures
pOOr paVINg specIFIcatION costs R-MILLIons These pavers are not appropriate for heavy construction traffic.
These pavers do not meet the dimensional tolerances specified in SANS1058:2012 which results in excessive highs and lows in the finished road.
25
PReCAST VOLUME 8 • ISSUE 2 • 2014
ARTICLe
pOOr paVINg specIFIcatION costs R-MILLIons Cairns adds that CBP roads can
also fail when they are not designed for
construction loading.
“This often occurs on housing estates
where roads are designed to handle light
traffic only. What normally happens is
that the roads are built before other
construction takes place. This means that
they must then handle the heavy-duty
trucks and other construction equipment
while the estate is being built and this
obviously causes damage. Further damage
is caused by the spillage of sand and stone,
especially at traffic circles where most of
the braking and turning takes place.
“One way around this problem is to build
road bases to handle the construction and
early resident traffic and only pave them
once the estate is close to completion. Not
only will this save the pavers from unneces-
sary wear but it will also ensure that the
road base has been constructed properly.
“However, in instances where it is
deemed necessary to install complete
roads before the construction of the
estate commences they should be built
with a paver which can handle heavy-duty
traffic. And once built, the contractor
should ensure that the roads are kept free
of sand and stone. Then if damage occurs
responsibility for the repairs will fall to
the contractor.”
CMA director, Wally Armstrong, notes
that most CMA producer members hold
the SABS mark. This means they do
regular batch testing and manufacture
with a recognised quality assurance
system in place.
“Some of our members and other CBP
producers comply with the standard but
don’t actually hold the mark which is also
acceptable. However, holding the mark is
obviously first prize, especially if there
are comebacks due to poor specification.
“Most South African paving producers
manufacture pavers with two layers. The
bottom and thicker layer provides the
required strength and the top layer can
be coloured with pigments for enhanced
aesthetic appeal. And now that the new
standard measures abrasion resistance
this topping layer is also being designed
with excellent surface-wear properties.
Even lower-grade blocks with a good
topping layer can of fer high abrasion
resistance, proving that the topping
layers do more than offer colour variation,”
concludes Armstrong.
Pavers at an intersection in Randfontein which have worn badly due to poor abrasion resistance.
PRECAST VOLUME 8 • ISSUE 2 • 2014
ARTICLe26
New MeMBers’ rOLL contInUes to GRoW
Envirotan
Envirotan is an innovative chemicals
company that specialises in anti-microbial
additives for the cementitous coatings
industry. It has developed and tested
various additives based on customers’
specific needs. These include anti-microbial
additives for tile adhesives and tile grouts,
as well as anti-algae products for marbelite
pools. It also offers a range of products
- all based on cementitious coatings - to
keep floors, walls, counters, kitchen and
bathrooms hygienic.
Envirotan also offers a technical service
to concrete product producers to deter-
mine the origin of stains, be they organic,
in-organic or biological. Once identified,
several solutions are offered which can be
used by manufacturers and their custom-
ers. http://www.envirotan.co.za
Four new members have joined the CMA since April and new member enrolment since November 2012 now stands at 34. The new members are: Envirotan; Schlüsselbauer (Austria); Smartstone and The Job Club. Out-lined below are brief profiles.
Envirotan’s laboratory.
Schlüsselbauer state-of-the-art concrete pipe production.
Some of The Job Club executives: Hester Du Bruyn, CFO (left); Tabea Magodielo, chairlady and corporate governance; and Elise Coetser, CEO.
SmartStone paving at Melrose Arch.
pressure pipes, manhole elements, road-
side channels, and so on.
A newsworthy innovation, PERFECT
PIPE, produces a durable and dense sew-
age pipe with an integrated plastic liner,
distinguished by a high static load-bearing
capacity and a long-lasting resistance to
chemical attack. The pipe is suitable for
both trench construction and pipe jacking/
micro-tunneling.
Furthermore, PERFECT is a wet-cast
system which enables the production of
fully customised dense products as well as
mould-hardened concrete manhole bases,
risers and cones. (www.sbm.at, www.per-
fectsystem.eu).
The Job Club
A registered NPO, The Job Club was es-
tablished in 2010 in association with the
SA Council for Business Women and SA
United Employers to facilitate practical
and sustainable job creation in partnership
with the business community, government
and civil society.
The organisation’s primary objective is
to generate employment by providing people
with the necessary skills to establish and
sustain their own businesses.
Already active in all nine provinces, the
organisation manages a range of innovative
skills training, internship, host employment
and entrepreneurship programmes in as-
sociation with host employers, businesses
and experienced professionals.
Businesses and professionals share
their expertise in programmes aimed at
youth, women and start-up entrepreneurs,
and also assist in identifying host employ-
ment and job opportunities.
The Job Club works in collaboration with
community representatives, as well as local
health, social and education departments.
It also forms social partnerships with gov-
ernment and private sector organisations,
such as the National Youth Development
Agency (NYDA).
SmartStone
SmartStone was founded in 1980. The
original SmartStone concept was to create
concrete products that simulated the look
and feel of natural stone, but the company
quickly evolved into much more. It pioneered
the idea of exterior design systems, which
was achieved by creating products with
natural textures, others which remained
true to concrete and some that could only
be described as authentic SmartStone.
Subsequently, SmartStone became a ge-
neric name and its manufactured product
range expanded to include various paving
shapes, textured pavers, wall cladding, tiles
and landscaping features.
A significant achievement was winning a
premier CMA excellence award for a paving
installation at Melrose arch in 2002 and
then winning the Vintage Award for the
same project at the Association’s Awards
for Excellence competition in 2012.
SmartStone has branches in Bloemfon-
tein, Cape Town, George, Durban, Nelspruit,
Midrand, Port Elizabeth, Potchefstroom and
Pretoria. It also has branches in Namibia,
Zambia and Mozambique.
Schlüsselbauer
Based in Austria, Schlüsselbauer operates
worldwide as a solution provider and sup-
plier of plant equipment for the production
of precast concrete components for sew-
erage and stormwater drainage systems,
as well as water mains.
Schlüsselbauer’s manufacturing tech-
nology for wet and dry cast concrete
products is designed to produce concrete
pipes, concrete pipes with plastic liner,
PReCAST VOLUME 8 • ISSUE 2 • 2014
27APPLICATIonS
Chryso SA has launched a new range of application-driven mould release agents for the concrete industry.
New raNge oF MoULD ReLeAse AGentsCMA member, Chryso South Africa has
launched a new range of application-driven
mould release agents.
Hannes Engelbrecht, Chryso S.A. gen-
eral manager: marketing, says the new
ChrysoDem release agents have been
designed to meet the needs of specific
industries and applications.
“Choosing the appropriate release agent
may be critical to the success of a project,
as it affects both the quality and colour of
the surface finish,” says Engelbrecht .
“The cost of a release agent is low in
proportion to the formwork or mould itself,
so simply choosing the cheapest release
agent available on the market, is false econ-
omy. The top quality release agents in the
ChrysoDem range may cost a little more but
provide greater coverage, are easier to use,
and add consistent quality to the production
line. This is important, particularly in the
precast industry, where high temperature
steam curing forms a formidable challenge
in the production process.
“The new range is a ground-breaking
development for South Africa, long-
awaited by industries which for years
have had to use one-size-fits-all mould
release agents. ChrysoDem, which is
locally manufactured by Chryso S.A. at
our production plants in Gauteng, KZN
and the Western Cape, also includes a
vegetable-based, environmentally-friendly
release agent.”
Mould release agents are primarily
used to assist in the clean, easy release
of moulds or formwork from concrete,
without damaging the concrete, the moulds
or formwork.
“In order to achieve satisfactory
results, it is imperative that the correct
release agent for specific applications
is chosen. The new ChrysoDem range
features dif ferent release agents for
moulds made of metal, wood, plywood, resin
ply, and shutter board as well as for those
made from plastic, polystyrene, rubber,
latex, and fibreglass,” said Engelbrecht.
In addition to the clean and easy release
of the mould or formwork from concrete,
some other advantages of the ChrysoDem
range include:
• Protecting and extending the life of the
formwork/mould
• Reducing the likelihood of imperfections
and surface damage, particularly blow holes,
to create more durable and attractive
concrete surfaces
• Elimination of staining and colour changes
• Plaster, paint and other coatings may be
applied subsequent to the mould removal
as ChrysoDem release agents do not
adversely affect adhesion of finishes and
coatings applied to the concrete
• Water repellent and not affected by rain
• No effect on the hydration of concrete
• Ready-to-use release agents which re-
duce the possibility of errors during mixing
• Two-year storage life for virtually all the
new release agents.
“There has been exceptionally positive
response from the concrete industry
to this new range which Chryso S.A. is
planning to export to the rest of Africa as
well,” added Engelbrecht.
For further information, contact Hannes
Engelbrecht on tel 011 395 9700 or email
[email protected] or visit www.
chryso.com
PRECAST VOLUME 8 • ISSUE 2 • 2014
28 APPLICATIonS
Terracrete paving blocks on track at Geelkrans Nature Reserve.
Rocla’s Alfabloc.
Garden Route Terraforce licensee, CMA
member, Mobicast, is building two-wheel
jeep tracks with Terracrete paving blocks
for Cape Nature at Geelkrans Nature
Reserve in Stillbaai, Western Cape. The
Terracrete block is providing a hard wearing
all-weather surface which is water perme-
able, unlike surfaces such as asphalt or
conventional paving which are impermeable.
Jean du Plessis, conservation manager,
Geelkrans Cluster & Stilbaai Marine
Protected Area (MPA) says:
“We have a network of maintenance jeep
tracks on the reserve and the substrate
comprises mostly deep dune sand unsuited
to normal paving. As an alternative we
sought a hard surface that was water
permeable and allowed the growth of
vegetation. Another proviso was that
it should move with the substrate while
The need to store or partition fertilizer,
coal, sand, stone and other granular or
loose particles in discrete batches is
critical for many sectors of industry.
These requirements are easily facilitated
by the installation of CMA member, Rocla’s
Alfabloc A-framed precast concrete
retaining walling system.
Manu f actured under l i cense to
Poundfield Products Ltd in the UK, Alfabloc
is a naturally stable and robust retaining
wall block which requires little or no ground
fixing while offering limitless configurations
and quick installations.
“Alfabloc is a versatile product that
can be deployed across many applications.
The type of stored material determines
whether the blocks are free-standing
or bolted into place,” says Rocla sales
engineer, Justin Kretzmar.
“The traditional retaining wall concept is
well suited for the separation and storage
of granular materials, however, Alfabloc’s
quick and easy alignment, its even weight
distribution, sturdiness and durability, are
what make it an efficient alternative.
“And the inner cavity formed by the
two A-frame legs can be used for placing
electrical cabling for CCTV alarms or any
other wiring requirements.
Rocla’s Alfabloc is available in three
height options of 1.2m, 2.4m and 3m.
“The mini-Alfabloc, at 1.2m high, has
been very successful at offering a quick,
flexible option for storage requirements
as well as an alternative to the New
Jersey Barrier for many non road-related
applications.
The Port of Durban has used 22 mini-
Alfablocs as a temporary security measure
for crowd control, and a Durban-based
logistics company has used the large 2.4m
Alfablocs for stock piling manganese.
The Alfabloc has also been used at chem-
ical factories, farms and mines as well as
at airports, railways and other transport-
perMeaBLe paVINg BLOcK prOVIDes eco-FRIenDLY MoBILItY FoR nAtURe ReseRVe
aLFaBLOc – rOcLa’s pOrtaBLe RetAInInG WALLInG sYsteM
stability and loose substrate is used to fill
any gaps in and around the blocks.
“The blocks are relatively easy to work
with, compared to other paving methods
which involve more sophisticated machinery
and labour,” says Du Plessis. “We are
finding that approximately two percent of
the blocks are broken during transport and
handling over rough terrain but on the whole
the process is straightforward and causes
very little disturbance in the reserve.”
The tracks are being installed in 250m
stages and 7 000 blocks have already been
laid. Carpobrotus edulis (Sour Fig) is being
planted on the verges of the tracks to
rehabilitate any destabilisation that occurs
during construction. Maintenance of the
tracks is quick and easy, and should blocks
break during the course of their lifetime,
they are easily replaced.
related locations. The mini Alfabloc has
found a home along railway lines keeping
people, wildlife and farm animals safe from
moving trains. And Rocla itself has used the
3m Alfabloc for a river-sand bunker at its
Polokwane manufacturing plant.
Alfablocks interlock with a cast-in
concrete tongue-and-groove joint. Each
block has two sockets cast into the top
surface, which can be used with eye-bolts
to easily lift and move the blocks or to
attach additional items such as roofing,
razor wire or electric fencing.
keeping its shape and integrity. We decided
to use the Terracrete block because of its
permeability, low environmental impact and
cost-effectiveness.”
The blocks are laid after 100-150mm
of substrate is removed. Binding wire is
threaded through them to increase overall
29
PReCAST VOLUME 8 • ISSUE 2 • 2014
APPLICATIonS
Kaytech’s Miragrid GX 80/30 is covered with soil at Olivedale Retirement Village.
Some 14 800m2 of CMA member, Kay-
tech’s Miragrid GX 80/30, has been used
to reinforce 10 open-faced concrete block
retaining (CRB) walls at Olivedale Retire-
ment Village, currently under construction
in Randburg, Johannesburg. Situated on
sloping ground, the site required extensive
terracing and embankment buttressing
to provide level building platforms for the
construction of houses, apartments and
communal buildings.
Completed in April, the retaining walls
were designed and built by Engineered
Interlock Solutions (EIS) in close collabo-
ration with main earthworks contractors,
Lone Rock, and consulting engineers, Pro
North Consultants, to ensure that all
statutory requirements were met.
Building 10 CRB walls reinforced with
Kaytech’s Miragrid GX 80/30 in combination
with Aveng Manufacturing Infraset’s split-
face Terrace Blok® 300 proved to be an
effective and cost saving decision for the
developers.
Miragrid GX geogrids are manufactured
from high tenacity polyester (PET) yarns
with a protective polymeric coating. They
are especially suitable for the reinforcement
of vertical or inclined soil walls with modular
block or panel facings and are available in a
wide variety of strengths and sizes.
Quick and easy to install, Miragrid GX
80/30 was placed at every second block
with tie back lengths of up to 5.4 metres. It
is an economical alternative to conventional
geogrids and provides superior interfacing
with concrete block structures.
The walls were built at a 75° angle
and reached heights of up to 7.5m. To
prevent the possible build-up of hydrostatic
pressure behind the walls, blanket drains
were constructed, consisting of a layer of
bidim A2 covered with a 120mm layer of
19mm stone followed by a second layer of
bidim A2. Outlets were provided at every
three metres.
A layer of PC100/100 was installed on
the second last tier of blocks for erosion
control and reinforcement.
With its performance properties having
been independently verified and tested,
Miragrid GX provides guaranteed long-
term durability (>100 years) and low creep
resistance.
For more information on Kaytech prod-
ucts and systems, visit www.kaytech.co.za.
cOst-saVINg geOgrID cHosen FoR RetAInInG WALL
PRECAST VOLUME 8 • ISSUE 2 • 2014
30 APPLICATIonS
L-shaped Uni-Ecolok permeable pavers, supplied by Aveng Manufacturing Infraset, make attractive visual and important eco statements at Alchemy Architects’ new HQ premises in Edenvale, Johannesburg.
arcHItects pLUMB FOr PeRMeABLe PAVInG sYsteMPermeable interlocking concrete paving
(PICP) is a prominent landscaping feature
at Alchemy Architects’ new office premises
in Edenvale, Johannesburg. Completed
in December 2013, the modern three-
storey building is surrounded by 935m² of
PICP which serves both as driveways and
parking areas.
Alchemy Architects’ permeable paving
system was based on an infiltration-based
PICP design provided by CMA member,
Aveng Manufacturing Infraset, one of
the country’s leading PICP suppliers. The
manufacturer also supplied Uni-Ecolok, its
interlocking paving block system, for the
installation of the paved surface.
Amândio Castanheira, a senior partner
at Alchemy Architects, says that PICP
using Uni-Ecolok made both environmental
and aesthetic sense.
“We were very aware of how widespread
urbanisation, and through it the creation of
impermeable surfaces, is placing mounting
pressure on stormwater drainage. Imper-
meable surfaces increase the risk of flood-
ing, spread pollution and disrupt aquatic
eco systems in rivers, streams and vleis.
“Research has shown that only 30%
of rain water infiltrates surface areas in
urban centres, and in towns and cities
the figure is as low as five percent. This
is why these areas are often flood-prone.
PICP reverses this imbalance allowing up to
95% of rain water to infiltrate the ground,
a figure which largely mirrors what happens
in undeveloped landscapes.
“Minimising pollution, albeit in a small
way, was another motivating factor in
our choice of permeable paving. During
Gauteng’s dry winter months, heavy
metals, hydrocarbons, oil, rubber and other
pollutants are deposited on impermeable
surfaces. When it rains they are washed
into stormwwater systems and are then
discharged into streams and rivers where
they destroy fauna and flora.
“PICP is very effective at removing
pollutants from run-off. The sub-base of
any PICP system is largely comprised of
coarse-graded aggregate and geotextile
sheeting and both materials harbour
natural microbes which devour water-borne
pollutants and prevent them from clogging
PICP systems.
“Moreover, we were also impressed with
the Uni-Ecolok paver’s L-shaped design,
which not only creates a very attractive
paved surface, but offers exceptional load-
bearing capacity, durability and stability
properties,” says Castanheira.
The Alchemy Architects PICP system
was installed by Lushaka Construction.
After excavating to approximately 500mm
below surface, an A4 bidim geofabric was
placed on the sub-grade. This was followed
by a 350mm layer of course-graded aggre-
gate. Uni-Ecolok pavers, 80mm thick, were
then laid on 50mm of bedding grit which
had been placed on top of the aggregate.
Charlene Soupen, Aveng Manufactruring
Infraset’s marketing manager and paving
specifier, says that the PICP installation at
Alchemy Architects is a typical infiltration
PICP system.
“Infiltration is one of two common types
of PICP systems, the other being attenua-
tion. Infiltration allows water to flow through
the crushed stone gradually before ground
infiltration takes place. In attenuation the
water is temporarily stored in the crushed
stone before being slowly released through
outflow pipes into conventional stormwater
drainage systems. This reduces peak flows
during heavy rainfall and reduces water tem-
peratures by 30ºc, both factors minimising
downstream damage considerably.
“There are other PICP options. For in-
stance, some systems store water below
the surface to be used for watering plants,
washing cars and equipment, and for sanita-
tion purposes. And some systems combine
infiltration with attenuation, especially in
instances where ground infiltration rates
are low. However, the final specification of
any permeable paving structure depends on
the hydraulic properties of the sub-grade
and anticipated traffic loading.
“The Uni-Ecolok system covers all these
requirements and its L-shaped concrete
block is ideal for driveways, car parks,
suburban streets and township roads,
light and heavy duty industrial yards,
as well as bus terminals and suburban
arteries. Moreover, the 80mm Uni-Ecolok
block conforms to the new SANS 1058
standard for paving block performance,”
concludes Soupen.
Contact Charlene Soupen on 012 652
000 or via email on [email protected].
31
PRECAST VOLUME 8 • ISSUE 2 • 2014
APPLICATIonS
precast paVers specIFIeD FOr InAnDA cLUB ReDeVeLoPMentCMA member, Colonial Stone, has supplied
4 600m² of concrete block paving (CBP)
for the paving of private roads at the
prestigious Inanda Club redevelopment
project in Sandton, Johannesburg.
Two types of CBP were supplied, a 222
x 222mm and a 222 x 55mm block, the
smaller unit being used for a herringbone
layout. Both pavers have granite finishes
and both have a compressive strength of
over 42MPa.
According to Friedel Weihe, director
Zoomlion’s hydraulically-operated portable concrete pump fitted with Bosch Rexroth’s A4VG axial piston pump.
pUMpINg cONcrete tO RecoRD HeIGHtsBosch Rexroth has supplied its latest
axial piston pump, the A4VG, to Zoomlion
in China for installation in a hydraulically-
operated portable concrete pump capable
of pumping concrete to heights of over
100 metres.
“Pumping concrete to these heights
entails very specific requirements. For
instance, the placing boom must be
robust yet sufficiently flexible for versatile
service,” as Binxing Wu, chief engineer at
Zoomlion, explains.
“Moreover, a limited load-bearing capac-
ity meant that all the main components
had to be highly efficient with the intrinsic
weight as low as possible.”
High operating pressures, large dis-
placement volumes and no critical vibra-
tion in the placement boom were some of
Zoomlion’s requirements for the A4VG.
“The A4VG switches so rapidly and
gently that no such vibration occurs,” says
Christian Frick, project engineer at Bosch
Rexroth in Germany.
As is almost always the case in inter-
national assembly projects, integrating
the different components was a challenge.
The engineers had to make a number of
adjustments to joints and connections for
the axial piston pump to run smoothly in
Chinese machines.
“In cases like this, of course, our re-
gional company in the country concerned
makes our work a lot easier,” explains
Frick. “Working closely with our Chinese
colleagues we were able to grasp all of
Zoomlion’s needs very rapidly.”
Work on the machine began in early-
mid 2012, and was complete by October
that year.
“The use of our axial piston pump in
the concrete pump has had a favourable
effect on the Chinese market and places
products from Zoomlion and Rexroth on
a new level,” says Zhicai Zhang, Bosch
Rexroth’s trade sector manager for
concrete machines in China.
Both Bosch Rexroth and Zoomlion are
of Colonial Stone, both pavers were strip
tested for a period of six months prior to
installation with regular traffic, including
34 ton cement bulk deliveries.
The road was designed by Landmark
Studios and the civil and earthworks were
handled by P&R Construction. R.E.E. Pav-
ing Contracts was responsible for laying
the pavers.
Michael Hartley of R.E.E Paving Con-
tracts said that the paving was begun in
September 2013 and had been completed
in January.
“We laid the pavers on a river sand
base using screed rails. The sub-base
material comprised 150mm layer of G5
aggregate and all the paving was cement
slurry grouted. The paving plated very nicely
and snagging was minimal. We were also
impressed with the fact that Colonial Stone
staggered the off-loading of the pallet loads
which meant we did not have to cart pavers
up to 50-60m using wheelbarrows.”
The Inanda Club’s redevelopment includes
an exclusive residential component, a new
clubhouse which overlooks a polo field, meet-
ing rooms and a large function ballroom.
convinced that even more world records
will soon be broken in China with the aid
of modern hydraulic technology.
A section of road at Inanda Club paved with 222 x 55mm supplied by Colonial Stone.
PRECAST VOLUME 8 • ISSUE 2 • 2014
32 MeMBeRS’ LIST
Producer members
COMPANy NAME TElEPHONE PROVINCE/COuNTRy PIllAR
A Fick Sementwerke Bk 022 913 2370 Western Cape PB
Aveng Manufacturing Infraset
011 876 5500 Gauteng PB/PI
Bass Beams 031 784 1920 Kwa-Zulu Natal PB
Bay Brick 035 792 5218 Kwa-Zulu Natal PB
Beta Tiles 002634 2925303 Zimbabwe PB
Boland Concrete 021 875 5365 Western Cape PB
Bosun Brick Midrand 011 310 1176 Gauteng PB
Brickbuild t/a Panda 00267 244 2107/8 Botswana PB/PI
Brickcast Industries cc 031 507 5525 Kwa-Zulu Natal PI
C.E.L. Paving Products 021 905 5998 Western Cape PI
Cast Industries 011 316 2375 Gauteng PB/PI
Civil Works 011 903 7023 Gauteng PI
Concrete Units016 362 2236021 386 1923
Western Cape/Gauteng PB/PI
Conframat 0861 33 5599 Gauteng PB/PI
Colonial Stone 011 794 9737 Gauteng PB/PI
Corobrik Pty Ltd 031 560 3111 Kwa-Zulu Natal PI
Deranco Precast 041 933 2755 Eastern Cape PB/PI
Eagle Roof Tiles Pty Ltd 044 874 0290 Western Cape PB
Echo Prestress Pty Ltd 011 589 8800/8899 Gauteng PB
Fastdeck Pty Ltd 0026737 71321528 Botswana PB
Inca Masonry Products 043 745 1215 Eastern Cape PB/PI
Keystone Walling 082 850 3512 Gauteng PB/PI
Lategan Cement Works 021 873 1154 Western Cape PB
Mobicast (Pty) Ltd 044 874 2268 Western Cape PB
Monier Roofing South Africa 011 222 7300 Gauteng PB
MVA Bricks 012 386 0050 Gauteng PI
Technicrete 011 674 6900 Gauteng PB/PI
Portland Hollowcore Slabs Pty Ltd
021 972 1111 Western Cape PB
COMPANy NAME TElEPHONE PROVINCE/COuNTRy PIllAR
ReMaCon Products cc 011 393 5504 Gauteng PI
Revelstone (Cape) Pty Ltd 021 761 9734 Western Cape PB
Reya Pele Bricks Ltd 016 363 0340 Gauteng PB
Rocla 011 670 7600 Gauteng PB/PI
Shukuma Flooring 041 372 1933 Eastern Cape PB
Smartstone 011 310 1161 Gauteng PB
Southern Pipeline Contractors
011 914 8500 Gauteng PB/PI
Style Décor Pty Ltd 012 376 2454 Gauteng PB/PI
Swakop Tiles cc t/a Namib Roof Tile Company
00264 6446 3717 Namibia PB
Topfloor Concrete 021 951 7700 Western Cape PB
Vanstone Precast Pty Ltd 012 541 2056/1808 Gauteng PI
West End Cement Bricks Pty Ltd
011 851 1005/1063 Gauteng PI
AssociAte members COMPANy NAME TElEPHONE PROVINCE/
COuNTRy
Aspasa 011 791 3327 Gauteng
ARQ Consulting Engineers Pty Ltd 012 348 6668 Gauteng
British Precast Concrete Federation 044 116 253 6161 United Kingdom
Concrete Society 012 348 5305 Gauteng
ILIFA Africa Engineers Pty Ltd 012 362 1473 Gauteng
JC Paving Consulting 011 431 0727 Gauteng
Sekhukhune & Associates 012 993 4776 Gauteng
SNA Civil & Structural Eng 012 842 000 Gauteng
SARMA 011 791 3327 Gauteng
The Job Club 012 661 1099 Gauteng
Terraforce Pty Ltd 021 465 1907 Western Cape
Tjeka Training Matters 011 665 2777 Gauteng
Young & Satharia Consulting Civil Engineers
031 207 7252 Kwa-Zulu Natal
PI - Precast Infrastructure PB - Precast Building
PReCAST VOLUME 8 • ISSUE 2 • 2014
33MeMBeRS’ LIST
cement membersCOMPANy NAME TElEPHONE PROVINCE/
COuNTRy
AfriSam South Africa 011 670 5500 Gauteng
PPC Ltd 011 386 9000 Gauteng
Sephaku Cement 012 684 6300 Gauteng
contrActor membersCOMPANy NAME TElEPHONE PROVINCE/
COuNTRy
Decorton Retaining Systems 021 875 5155 Western Cape
Friction Retaining Structures Pty Ltd 011 608 4321 Gauteng
Powergate Construction 071 603 5070 Gauteng
PYW Paving 031 903 1736 Kwa-Zulu Natal
Valcal International Export 011 867 2471 Gauteng
non-Producer members
COMPANy NAME TElEPHONE PROVINCE/COuNTRy
Abel Equipment 044 874 1876 Western Cape
Ash Resources (Pty) Ltd 011 657 0230 Gauteng
H Birkenmayer (Pty) Ltd 011 970 3880 Gauteng
Chryso Southern Africa Pty Ltd 011 395 9700 Gauteng
Doubell Brick Machines 041 585 9060 Eastern Cape
Delta Bloc South Africa (Pty) Ltd 011 024-4604 Gauteng
Dick King Lab Supplies 011 499 9400 Gauteng
Envirotan 011 452 7906 Gauteng
HawkeyePedershaab 00 45 9645 4040 Denmark
Kavango Block & Brick cc 00 264 61 213 632 Namibia
Kaytech 031 717 2300 Kwa-Zulu Natal
Kerenos Southern Africa Pty Ltd 011 444 3090 Gauteng
Kobra Moulds B.V. 003111 356 2460 Netherlands
Manitou SA (Pty) Ltd 011 975 7770 Gauteng
Pan Mixers SA Ltd 011 578 8600/8701 Gauteng
SamJung Industries Ltd 0082542607722 Korea
Schlüsselbauer Technology GmbH & Co KG
004377357144 201 Austria
Sika South Africa Pty Ltd 031 792 6500 Kwa-Zulu Natal
Techmatik S.A. 00484 803 690 811 Poland
MaKe sUre YOU secUre
the cma – QUaLItY caSt IN cONcRete
PRECAST
VOLUME EIGHT ISSUE 1 • 2014
co
nc
re
te
manufacturers
as
so
cia
tio
n Q
uality cast in concrete
• Building practice antiquated
• Precast transforms factory into showroom
• Record retaining wall height
YoUR sPot
Contact Charlene for more information:
Tel: 011 883 4627 or E-mail: [email protected]
the cma – QUaLItY caSt IN cONcRete
co
nc
re
te
m
anufacturers
as
so
cia
tio
n
Quality cast in concrete
Don’t miss out! Book your advertising space in the next issue of precast magazine.