Precast Concrete Barriers

download Precast Concrete Barriers

of 142

Transcript of Precast Concrete Barriers

  • 7/28/2019 Precast Concrete Barriers

    1/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page i of 142

    Developing and Testing of Precast Concrete

    Bridge Barrier Anchorages to meet the

    Requirements for PL-2 Barrier Systems of

    the Canadian Highway Bridge Design Codeat

    University of British Columbia, UBC

    Prepared by K. Bleitgen

    Edited by S. F. Stiemer

  • 7/28/2019 Precast Concrete Barriers

    2/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page ii of 142

    Conceptual formulation

    The objectives of the research and testing will be as follows:

    Research and testing of the precast concrete bridge barriers shall result in developingand testing anchorages that meet the requirements for PL2 barrier systems as given by

    the Canadian Highway Bridge Design Code (CHBDC).

    The scope of the research and testing for the precast concrete bridge barriers will include thefollowing:

    1. Review Canadian Highway Bridge Design Code (CHBDC) requirements for bridgebarriers

    2. Literature review of background to CHBDC requirements of bridge barriers and otherbackground regarding bridge barriers and bridge testing

    3. Review the effect of having inter-connection between adjacent precast concrete barriers

    4. Compare British Columbia Ministry of Transportation (BC MoT) anchorage details forprecast concrete bridge barriers to details by other jurisdictions / suppliers

    5. Review the effect of type of bridge on the anchorage capacity:- Barrier anchored to concrete slab- Barrier anchored to box girder flange

    6. Carry out site visits to existing bridges to see the existing BC MoT precast concrete boltdown barrier system in service

    7. Carry out visits to the fabrication plants where the precast concrete barriers are fabricatedand liaise with the fabricators regarding fabrication issues

  • 7/28/2019 Precast Concrete Barriers

    3/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page iii of 142

    Abstract

    In this report, an introduction into precast concrete bridge barriers which are used in the

    Province of British Columbia in Canada is given with an emphasis on bolt-down barriers.

    Concrete barriers appear to be simple and uncomplicated, but in reality, they are sophisticated

    safety devices.

    Barriers are developed to delineate the superstructures edge to reduce the consequences of

    vehicles leaving the roadway or humans leaving the sidewalk. The shape of a barrier as well asthe type of anchorage are the most important features in the design of a barrier. The design can

    be done either with a crash test or an analysis method, i.e. the yield line analysis and strengthdesign method or finite element analysis.

    Due to constantly updated design provisions established in Codes in order to improve theperformance of barriers, considerable amounts of research and development of new design

    methods have been carried out. The basics of the design requirements of barriers have changed

    dramatically in the last twenty years. Since most nowadays used precast concrete bridge barriersare developed based on the 1988 Code, the need of an up-to-date design became necessary.

    Therefore, the Ministry of Transportation of British Columbia started a series of research

    projects to satisfy that need.

    This report is the first research report which will be followed soon by further projects and

    gives an introduction into bolt-down precast concrete bridge barriers. It gives an overview on

    applicable Codes, their precursor as well as relevant literature of other jurisdictions. Finally themost common barriers and their superstructures as well as comparable ones from other

    jurisdictions are presented.

  • 7/28/2019 Precast Concrete Barriers

    4/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page iv of 142

    List of Contents

    Conceptual formulation ii

    Abstract iii

    List of Contents ivList of Tables v

    List of Figures vi1. Introduction 1

    2. The hierarchy and application area of applicable Codes 32.1 In Canada 3

    2.2 In the United States of America 3

    3. Review of the Canadian Highway Bridge Design Code (CHBDC) requirements forbridge barriers 5

    3.1 Traffic barrier 5

    3.1.1 Performance Level 6

    3.1.2 Crash test requirements 73.1.3 Anchorages 8

    3.2 Pedestrian barrier 9

    3.3 Bicycle barrier 103.4 Combination barrier 11

    4. Literature review of background to CHBDC requirements of bridge barriers and other

    background regarding bridge barriers and barrier testing 124.1 The precursor of the Canadian Highway Bridge Design Code 12

    4.1.1 Review of CAN/CSA-S6-88 requirements of bridge barriers 12

    4.1.2 Comments on changes between CAN/CSA-S6-88 and CAN/CSA-S6-00 13

    4.1.3 Review of OHBDC-91-01 requirements of bridge barriers 13

    4.1.4 Comments on changes between OHBDC-91-01 and CAN/CSA-S6-00 154.1.5 General comment on the changes of the CHBDC to the precursor 16

    4.2 Other background literature regarding the CHBDC 164.2.1 AASHTO LRFD Bridge Design Specifications, Section 13, Railings, from 1997 17

    4.2.2 AASHTO LRFD Bridge Design Specifications, Section 13, Railings, 2004:

    Important changes from the 2nd

    to the 3rd

    Edition 194.2.3 Appendix A of AASHTO LRFD Bridge Design Specifications, 1997 21

    4.2.4 Appendix A of AASHTO LRFD Bridge Design Specifications, 2004: Important

    changes from the 2nd

    to the 3rd

    Edition 29

    4.2.5 NCHRP Report 350: Recommended Procedures for the Safety PerformanceEvaluation of Highway Features 29

    4.3 Other literature regarding bridge barriers and barrier testing 304.3.1 Basics of Concrete Barriers 304.3.2 Review of the Washington State Bridge Design Manual 31

    4.3.3 Comment on the Washington State Bridge Design Manual 34

    5. Literature review of BC MoT's design literature regarding requirements of precastconcrete bridge barriers 35

    6. Review the effect of having inter-connection between adjacent precast concrete barriers 37

    6.1 The hook and eye connection 37

  • 7/28/2019 Precast Concrete Barriers

    5/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page v of 142

    6.2 The pin and loop connection 39

    6.3 The inter-connection effect between adjacent precast barriers 417. Compare British Columbia Ministry of Transportation (BC MoT) anchorage details for

    precast concrete bridge barriers to details by other jurisdictions 42

    7.1 Anchor details of the MoT of British Columbia 42

    7.1.1 The 810 mm high precast concrete bridge parapet 427.1.2 The 865 mm high precast concrete bridge parapet 45

    7.1.3 The 875 mm high precast concrete bridge parapet 47

    7.2 Anchorage details of precast concrete bridge barriers of other Canadian Provinces andTerritories than British Columbia 50

    7.2.1 Anchorage details McKenzie Creek Hwy 6, used by the Ministry of

    Transportation Ontario (MTO) 1991 507.3 United States of America anchorage details 54

    7.4 Comparison of the anchorage details 57

    7.4.1 Comparison of the BC MoT bolt-down precast concrete bridge barriers with theMcKenzie precast bridge barrier 58

    7.4.2 Comparison of the BC MoT bolt-down precast concrete bridge barriers with theL.B. Foster NJ-Shape precast bridge railing 58

    8. Review the effect of type of bridge (concrete slab vs. box girder) on the anchorage capacity 608.1 The anchor capacity of barriers anchored to concrete slabs 62

    8.1.1 The Misinchinka Bridge, # 6819 62

    8.1.2 The Hudgens Bridge, # 7476 648.1.3 The Twan Creek Bridge, # 8023 66

    8.2 The anchor capacity of barriers anchored to box girder flange 67

    8.2.1 The Standard Precast Concrete Bridge, # 2965 678.2.2 The Elkins Bridge Precast Concrete Parapets, #7780 69

    9. Carry out site visits to existing bridges to see the existing BC MoT precast concrete boltdown barrier system in service 71

    9.1 Detailed information of the construction of the Birkenhead Causeway Bridge No. 8024 71

    9.2 Site visit: Birkenhead Causeway Bridge No. 8024 7310. Precast concrete barrier fabrication plants in British Columbia 76

    Conclusions 80

    References 81

    Appendix 83

    List of TablesTable 1 Traffic barrier loads, from Figure 3.8.8.1, CAN/CSA-S6-00 .......................................... 9Table 2 Bridge railing Performance Levels and crash test criteria from Table 13.7.2.1,

    AASHTO LRFD Bridge Design Specifications, 1997 .............................................. 18Table 3 Bridge railing Testing Levels and crash test criteria, from Figure 13.7.2-1, AASHTO

    LRFD Bridge Design Specifications 2004................................................................. 20

    Table 4 Design forces for traffic railings, from Table A13.2-1, AASHTO LRFD Bridge Design

    Specifications, 2004 ................................................................................................... 29Table 5 Vehicle impact loading on traffic barrier by WSDOT, WSBDM, Section 10.2.4,

    Design Criteria ........................................................................................................... 33

  • 7/28/2019 Precast Concrete Barriers

    6/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page vi of 142

    Table 6 List of precast concrete bridge barriers from Section 941, Standard Specifications for

    Highway Construction, BC MoT ............................................................................... 36Table 7 Standard precast concrete bolt-down systems used by the BC MoT............................ 60

    Table 8 Precast concrete bolt-down system used by the MoT Ontario ..................................... 60

    Table 9 Precast concrete bolt-down systems used by the US. DoT, FHWA............................. 60

    Table 10 List of fabricators of precast concrete bridge barriers within British Columbia ........ 76

    List of FiguresFigure 1 Sketch of the hierarchy of the Codes concerning traffic barriers in the USA............... 4Figure 2 Application of traffic design loads to traffic barriers, from Figure 12.5.2.4, CAN/CSA-

    S6-00 ............................................................................................................................ 9

    Figure 3 The application of pedestrian and bicycle design loads to barriers, from Figure12.5.3.2, CAN/CSA-S6-00 .......................................................................................... 10

    Figure 4 Application of pedestrian loads for pedestrian railings, from Figure 5-4.5.2.3,

    OHBDC-91-01 ........................................................................................................... 14

    Figure 5 Application of pedestrian loads for bicycle railings and combination barriers, fromFigure 5-4.5.2.3, OHBDC-91-01................................................................................ 15

    Figure 6 Pedestrian railing loads, from Figure 13.8.2.1, AASHTO LRFD Bridge Design

    Specifications ............................................................................................................. 18Figure 7 Bicycle Railing Loads, from Figure 13.9.3.1, AASHTO LRFD Bridge Design

    Specifications ............................................................................................................. 19

    Figure 8 Geometrical definitions of two typical traffic railings, from Figure A13.1.1-1,AASHTO LRFD Bridge Design Specifications ........................................................ 21

    Figure 9 Post setback criteria, from Figure A13.1.1-3, AASHTO LRFD Bridge Design

    Specifications ............................................................................................................. 22

    Figure 10 Nomenclature for traffic railing equations, from Figure CA13.2.1, AASHTO LRFD

    Bridge Design Specifications, 1997........................................................................... 23Figure 11 Design forces for traffic railings, from Table A13.2-1, AASHTO LRFD Bridge

    Design Specifications, 1997....................................................................................... 24Figure 12 Railing design forces, from Figure A13.2-1, AASHTO LRFD Bridge Design

    Specifications ............................................................................................................. 24

    Figure 13 Yield Line Analysis of concrete parapet walls for impact within wall segment andnear end of wall segment, part 1 of Table A13.3.1-1/2, AASHTO LRFD Bridge

    Design Specifications................................................................................................. 25

    Figure 14 Yield Line Analysis of concrete parapet walls for impact within wall segment, part 2

    of Table A13.3.1-1, AASHTO LRFD Bridge Design Specifications........................ 26Figure 15 Possible failure modes for post-and-beam railings, from Table A13.3.2-1, AASHTO

    LRFD Bridge Design Specifications.......................................................................... 26Figure 16 Combination concrete wall and metal rail evaluation-impact at (1) mid-span of rail

    and (2) at a post, from Table A13.3.3-1/ 2, AASHTO LRFD Bridge Design

    Specifications ............................................................................................................. 28

    Figure 17 Detail drawing of the F-shape and Single Slope barrier, WSDoT, Figure 10.2.3-2 . 32Figure 18 Hooks and eyes, from Standard Specifications for Highway Construction 2006,

    SP941-04.01.01 .......................................................................................................... 37

    Figure 19 Eye of the BC MoT's precast concrete bridge barrier, from drawing 7780-5........... 38

  • 7/28/2019 Precast Concrete Barriers

    7/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page vii of 142

    Figure 20 Hook and eye end section of a barrier in 3D, standard median barrier 810 mm, from

    drawing SP941-02.01.08 and 09, BC MoT................................................................ 38Figure 21 Plan view on the end of a hook and eye unit, standard median barrier 810 mm, from

    drawing SP941-02.01.03 and 04, BC MoT................................................................ 38

    Figure 22 Connection detail (plan view) of the hook (left) and eye (right) system, standard

    median barrier 810 mm, drawing SP941-02.01.03, BC MoT.................................... 39Figure 23 Plan view of the pin and loop system, from drawing C-8d, Standard Drawings,

    WSDoT ...................................................................................................................... 39

    Figure 24 The pin in detail, from drawing C-8d, Standard Drawings, WSDoT........................ 40Figure 25 Top and side view of the whole barrier, showing the anchors for the pin and loop

    system, from drawing C-8d, Standard Drawings, WSDoT........................................ 40

    Figure 26 View on the end of the barrier, from drawing C-8d, Standard Drawings, WSDoT.. 41Figure 27 810 mm high precast concrete bridge barrier, from drawing 8023-22, BC MoT ..... 42

    Figure 28 Typical section through the 810 mm high precast concrete bridge barrier, from

    drawing 8023-22, BC MoT ........................................................................................ 43Figure 29 Bolt sleeve detail of the 810 mm high precast concrete bridge barrier, from drawing

    8023-22, BC MoT ...................................................................................................... 44Figure 30 Bolt detail of the 810 mm high precast concrete bridge barrier, from drawing 8023-

    22, BC MoT ............................................................................................................... 44Figure 31 865 mm high precast concrete bridge barrier, from drawing 8023-22, BC MoT ..... 45

    Figure 32 Typical section through the 865 mm precast parapet, from drawing 2965-4, BC MoT45

    Figure 33 Blockout and bolt sleeve detail of the 865 mm high barrier, from drawing 2965-4,BC MoT ..................................................................................................................... 46

    Figure 34 Bolt sleeve detail of the 865 mm high barrier, from drawing 2965-4, BC MoT....... 46

    Figure 35 One possible anchor bolt of the 865 mm high precast concrete bridge parapet, fromdrawing 2965-23, BC MoT ........................................................................................ 47

    Figure 36 875 mm high precast concrete bridge barrier, from drawing 8023-22, BC MoT ..... 47Figure 37 Typical section through the 875 mm high precast concrete bridge barrier, from

    drawing 7476-12, BC MoT ........................................................................................ 48

    Figure 38 Bolt sleeve detail of the 875 mm high precast concrete bridge barrier, from drawing7476-12, BC MoT ...................................................................................................... 49

    Figure 39 Blockout and bolt sleeve detail of the 875 mm high barrier, from drawing 7476-12,

    BC MoT ..................................................................................................................... 49

    Figure 40 Cut through barrier, anchor type 1, used by the Ministry of Transportation, Ontario51Figure 41 Cut through barrier, anchor type 2, used by the Ministry of Transportation, Ontario51

    Figure 42 Anchor details: type 1 and type 2, used by the Ministry of Transportation, Ontario 52

    Figure 43 Step I to III of the construction sequence of the McKenzie Creek Barrier, used by theMinistry of Transportation, Ontario........................................................................... 53

    Figure 44 Step IV and VII of the construction sequence of the McKenzie Creek Barrier, used

    by the Ministry of Transportation, Ontario................................................................ 54Figure 45 Section through L.B. Foster NJ-Shape barrier, from Bridge Rail Guide 2005, FHWA55

    Figure 46 Bolt detail of the L.B. Foster NJ-Shape barrier, from Bridge Rail Guide 2005,

    FHWA........................................................................................................................ 56Figure 47 Barrier end detail of the L.B. Foster NJ-Shape barrier, from Bridge Rail Guide 2005,

    FHWA........................................................................................................................ 57

  • 7/28/2019 Precast Concrete Barriers

    8/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page viii of 142

    Figure 48 Failure modes for anchors under tension and shear load, from CSA A23.3-04, Figure

    D.1 and D.2 ................................................................................................................ 61Figure 49 Plan and elevation view of the Misinchinka Bridge, from drawing 6819-9, BC MoT62

    Figure 50 Parapet anchor insert of the Misinchinka Bridge, from drawing 6819-8, BC MoT.. 63

    Figure 51 Misinchinka Bridge after the installation of the anchor bolt, from drawing 6819-10,

    BC MoT ..................................................................................................................... 63Figure 52 Plan and elevation view of the Hudgens bridge, from drawing 7476-12, BC MoT.. 65

    Figure 53 Section through exterior bridge deck, from drawing 7476-12, BC MoT.................. 65

    Figure 54 Detail drawing of the nut in the panel deck, from drawing 7476-12, BC MoT........ 65Figure 55 The Hudgens precast concrete bridge barrier # 7476 after the installation of the

    anchor bolt, from drawing 7476-12, BC MoT ........................................................... 66

    Figure 56 Detail of the precast concrete deck bridge, from drawing 8023-21, BC MoT.......... 66Figure 57 Parapet connection to deck at Twin Creek bridge, from drawing 8023-22, BC MoT67

    Figure 58 Plan and elevation view of the standard precast parapet MK P1, from drawing 2965-

    4, BC MoT ................................................................................................................. 68Figure 59 Section through exterior stringer MK 700/16/E, from drawing 2965-23, BC MoT . 68

    Figure 60 Standard precast concrete bridge after installation of the anchor bolt, from dwg.2965-6, BC MoT ........................................................................................................ 69

    Figure 61 Elkins bridge after the installation of the anchor bolt, from drawing 7780-6, BC MoT70Figure 62 Section through the Birkenhead Causeway Bridge barrier, from dwg. 8024-9, BC

    MoT............................................................................................................................ 71

    Figure 63 Plan and elevation view of the Birkenhead Causeway Bridge barrier, from dwg.8024-9, BC MoT ........................................................................................................ 72

    Figure 64 Cut through box stringer of the Birkenhead Causeway Bridge, from dwg. 8024-9,

    BC MoT ..................................................................................................................... 72Figure 65 After placing the Birkenhead Causeway Bridge barrier, from dwg. 8024-9, BC MoT73

    Figure 66 Filled precast concrete barrier forms at the plant of Eagle West Truck & Crane ..... 77Figure 67 Hook bars used for the connection of adjacent barriers at the plant of Eagle West

    Truck & Crane............................................................................................................ 77

    Figure 68 Eye bar(s) used for the connection of adjacent barriers at the plant of Eagle WestTruck & Crane............................................................................................................ 78

    Figure 69 Precast concrete barriers after 3 days at the plant of Eagle West Truck & Crane .... 78

    Figure 70 Side and end view of a precast concrete bridge barrier at the plant of Eagle West

    Truck & Crane............................................................................................................ 79Figure 71 Side and end view of the precast concrete bridge barrier anchor at Eagle West Truck

    & Crane ...................................................................................................................... 79

  • 7/28/2019 Precast Concrete Barriers

    9/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 1 of 142

    1. Introduction

    The objective of this report is to give an introduction into precast concrete reinforced

    bridge barriers and in particular into bolt-down precast barriers used in British Columbia in

    Canada.

    Barrier design provisions established in codes are constantly updated in order to improve the

    performance of barriers to help to restrain errant vehicles from leaving the roadway or humans

    from leaving the sidewalk. Considerable amounts of research and development of new structuralsystems is being carried out. However, there are still many barrier design requirements that

    remain challenging.

    The 2000 edition of the Canadian Highway Bridge Design Code (CHBDC), as well as the

    third edition of the American Association of State Highway and Transportation Officials

    (AASHTO), Load and Resistance Factor Design (LRFD), Barrier Design Specifications and

    National Cooperative Highway Research Program (NCHRP), Report 350: RecommendedProcedures for the Safety Performance Evaluation of Highway Features, contain significant

    changes compared to previous editions regarding barrier design requirements. The main feature

    of these standards is the requirement for crash-testing in order to establish a specified level towhich a traffic barrier will perform (Performance Level, Testing Level).

    Due to the fact that many Codes and Guidelines which deal with barriers are conflictedbetween the each other, the second chapter gives a short introduction into relevant Codes

    showing their hierarchy and application area. In the third chapter, a summary of the section that

    deals with barriers in the Canadian Highway Bridge Design Code (CHBDC) is presented.

    Many of the nowadays used precast concrete bridge barriers are designed before 2000, based onthe Canadian Highway Bridge Design Code (CHBDC) from 1988. Due to this high importance,

    the precursor of the Canadian Highway Bridge Design Code (CHBDC) published in 2000 as wellas their background, are introduced in Chapter 4.1. Afterwards a general introduction into

    concrete barriers is given. It explains the reason for the shape of a barrier and gives some

    historical background concerning the development of barriers (Chapter 4.2). Then, the mainrelated literatures to the Canadian Highway Bridge Design Code (CHBDC) as the AASHTO

    LRFD Bridge Design Specifications and theNCHRP Report 350: Recommended Procedures for

    the Safety Performance Evaluation of Highway Features are presented.To make a comparison of the applicable Codes regarding barriers used in British Columbia, the

    state Washington in the United States is chosen due to similar conditions. Therefore a summary

    of the Washington State Bridge Design Manual as well as a comment on the differences is given.

    Then, in Chapter 5, the design and production requirements of precast concrete barriers in British

    Columbia which are given by the Ministry of Transportation of BC are explained. These design

    provisions give all necessary information for the production of barriers and are therefore relevantfor fabrication plants. One visit to a fabrication plant was done and is presented in Chapter 10.

  • 7/28/2019 Precast Concrete Barriers

    10/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 2 of 142

    Since precast concrete reinforced barriers have to be delivered to the bridge site, they can only be

    produced in small pieces. Thus, the connection between two adjacent barriers produces an inter-connection effect which can influence the design and is therefore analysed in Chapter 6.

    The main purpose of the research series is to get a proof for used precast concrete bridge barrier

    how they perform and in which level (Performance Level or Testing Level) they can becategorized. Therefore, the three main precast concrete bridge barriers which are used in British

    Columbia are analysed in the beginning of Chapter 7. Since crash tests are really expensive and

    time intensive, the Ministry of Transportation wants to design the barriers either with showingthere are similar to proofed barriers and thus crashworthy or with analysis methods. Due to that

    comparable precast concrete bridge barriers of other jurisdictions are presented. Finally, acomparison between the barriers used in British Columbia and the barriers of other jurisdictions

    is done.

    The Ministry of Transportation of British Columbia uses the aforementioned three barrier types

    in combination with different superstructures which results in five different models. Precast

    concrete bridge barriers are combined either with a twin box stringer or a concrete panel decksuperstructure. Since different bolt systems are used for different superstructure types, anchorage

    capacities are determined when the necessary information was present.

    Finally, in Chapter 9, the results of a site visit to an existing bridge which is built with the bolt-down precast concrete bridge barriers are presented after the bridge itself is explained.

  • 7/28/2019 Precast Concrete Barriers

    11/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 3 of 142

    2. The hierarchy and application area of applicableCodes

    This short introduction is supposed to give an overview of existing Codes and explains the

    hierarchy of the Codes as well as its area of application. Since the first part of this research report

    consists of a literature review of existing Codes dealing with traffic barriers this overview ofapplicable Codes should help to understand the coherences between the different Codes and its

    countries. It is important to understand the Code's hierarchy and its appropriate application

    because there occur conflicts between the structural design literatures. In general the nationalcode provides a general design method whereas the state code deals with specifications.

    2.1 In Canada

    In Canada the National Code which deals with bridge barriers is the Canadian Highway

    Bridge Design Code published by the Canadian Standards Association (CSA) for highway bridge

    design. As a subdivision, each state of Canada is having additional specifications and standards

    establishing detailed requirements, consistent with current nationwide practices, which apply tocommon highway bridges. For example in British Columbia, the British Columbia Ministry of

    Transportation (BC MoT) published the Standard Specifications for Highway Construction 2006

    as well as the Design Standards, Bridge Standards and Procedures, which have to be applied inBritish Columbia.

    But nevertheless the system is not as clear as it seems, because some Codes give

    references to relevant literature of other jurisdictions. For example, concerning crash testrequirements, the Canadian Highway Bridge Design Code refers to theAmerican Association of

    State Highway and Transportation Officials (AASHTO), Guide Specifications of Bridge Railings.

    And in addition, the AASHTO Guide Specifications of Bridge Railings refers further to the

    National Cooperative Highway Research Program (NCHRP), Report 350: RecommendedProcedures for the Safety Performance Evaluation of Highway Features.

    2.2 In the United States of America

    Since most comparisons are done with the United States of America, the hierarchy and the

    application areas of the Codes of the United States of America concerning bridge barriers are

    explained as well. The American Association of State Highway and Transportation Officials(AASHTO) Load and Resistant Factor Design (LRFD) Bridge Design Specifications is intended

    to serve as the National Standard for use in the development of the Department's own structural

    specifications.

    Since the United States of America are quite big and consists of many states, the next

    lower level consists of three subdivisions which are (1) the Western Federal Lands HighwayDivision, (2) the Central Federal Lands Highway Division, and (3) the Eastern Federal Lands

    Highway Division. Each division has a different Project Development and Design Manual.

  • 7/28/2019 Precast Concrete Barriers

    12/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 4 of 142

    The next level under these three subdivisions are the states itself. A sketch of the

    hierarchy of the Codes in the United States of America is given in the beneath figure.

    AASHTO LRFD BridgeDesign Specifications

    USA

    -COUNTRY

    Western Federal Central Federal Eastern Federal

    Lands Highway Lands Highway Lands Highway

    Division (WFLHD) Division (CFLHD) Division (EFLHD)

    FEDERAL

    SUBDIVISION

    Alaska California Maryland

    Washington Nevada Kentucky

    Oregon Utah Virginia

    Idaho Arizona Mississippi

    Montana Wyoming TennesseeWyoming Colorado Virginia

    ... ...

    STA

    TE-

    LEVEL

    Figure 1 Sketch of the hierarchy of the Codes concerning traffic barriers in the United States of America

  • 7/28/2019 Precast Concrete Barriers

    13/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 5 of 142

    3. Review of the Canadian Highway Bridge DesignCode (CHBDC) requirements for bridge barriers

    The Canadian Highway Bridge Design Code CAN/CSA-S6-00 is prepared by the Canadian

    Standards Association (CSA) for highway bridge design in Canada and was published in

    December 2000. The requirements for the design of barriers are specified in section 12. Barrierson bridges receiving salt are exposed to a highly corrosive environment. To ensure long-term

    performance, these barriers must either be made from materials that can withstand this

    environment or be protected by an adequate protective coating.

    The barriers are divided into four different types of barriers according to their function:

    Traffic barrier; Pedestrian barrier; Bicycle barrier; and

    Combination barrier.

    In the appraisal of a barrier the specific regulations, which will be mentioned in the following

    subsections, are not the only factors to consider. There also exist some general factors which

    should not be underestimated. These factors are durability, ease of repair, snow accumulation on

    and snow removal from deck, visibility through or over barrier, deck drainage, future wearingsurfaces, and aesthetics. Damaged barriers need to be repaired quickly with minimal disruption to

    traffic. Traffic barriers should be designed with features such as anchorages that are unlikely to

    be damaged or cause damage to the bridge deck during an accident and modular constructionusing prefabricated sections that allow damaged sections to be repaired quickly.

    3.1 Traffic barr ier

    Traffic barriers should be provided on both sides of highway bridges to delineate the

    superstructure edge and therefore to reduce the consequences of vehicles leaving the roadway

    upon the occurrence of an accident. Crash tests are used to determine barrier adequacy in

    reducing the consequences of vehicles leaving the roadway. If a barrier has the same details asthose of an existing traffic barrier the adequacy can be determined from an evaluation of the

    existing barrier's performance when struck by vehicles.

    The adequacy of a traffic barrier in reducing the consequences of a vehicle leaving the roadway is

    based on the level of protection provided to the occupants of the vehicle, to other vehicles on theroadway and to people and property beneath the bridge. This protection is provided by retainingthe vehicle and its cargo on the bridge, by smoothly redirecting the vehicle away from the barrier

    and by limiting the rebound of the vehicle back into traffic.

  • 7/28/2019 Precast Concrete Barriers

    14/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 6 of 142

    3.1.1 Performance Level

    Traffic barrier requirements vary from bridge site to bridge site and are based on the expected

    frequency and consequences of vehicle accidents at a bridge site. This procedure assumes that thefrequencies and consequences of vehicle accidents at bridge sites are a function of many

    variables. The ranking system, used in CAN/CSA S6-00 to determine the site conditions of abridge site, are named Performance Level (PL) and are defined as the following (CAN/CSA-S6-00, Section 12.2 Definitions):

    Performance Level 1 (PL-1): The performance level for traffic barriers on bridges wherethe expected frequency and consequences of vehicles leaving the roadway are similar tothat expected on low traffic volume roads. Crash test requirements require crash testing

    with a small automobile and a pickup truck in accordance with the AASHTO (American

    Association of State Highway and Transportation Officials) Guide Specifications for

    Bridge Railings.

    Performance Level 2 (PL-2): The performance level for traffic barriers on bridges wherethe expected frequency and consequences of vehicles leaving the roadway are similar tothat expected on high to moderate traffic volume highways. Crash test requirements

    require crash testing with a small automobile, a pickup truck, and a single unit truck in

    accordance with theAASHTO Guide Specifications for Bridge Railings.

    Performance Level 3 (PL-3): The performance level for traffic barriers on bridges wherethe expected frequency and consequences of vehicles leaving the roadway are similar to

    that expected on high traffic volume highways with high percentage of trucks. Crash test

    requirements require crash testing with a small automobile, a pickup truck, and a tractor-trailer truck in accordance with theAASHTO Guide Specifications for Bridge Railings.

    Alternative Performance Levels, as mentioned in Section 12.5.2.1.1 in CAN/CSA-S6-00, have tobe approved by the Regularity Authority for the bridge and defined by specifying their crash test

    requirements. These levels shall be considered along with Performance Level 1, 2, or 3 when

    determining the optimum performance level which is the one with the least costs.

    The optimal level of traffic barrier performance at a bridge site is assumed to be the level giving

    the least costs where costs includes the costs of supplying and maintaining a traffic barrier as wellas the costs of the accidents expected with the use of the traffic barrier. The assumed accident

    rates, accident severities and traffic barrier costs used by a computer-based Benefit-Cost Analysis

    Program (BCAP) in determine optimal levels of traffic barrier performance as well as the

    engineering judgement used to adjust these optimal levels for use in the Codes are given inAASHTO (1989).

    The Performance Levels are determined with the barrier exposure index (Be) which isbased on the estimated average annual daily traffic for the first year after construction (AADT1).

    Other influencing parameters, as the type of the highway, the curvature of the highway, the grade

    of the highway and the height of the superstructure as well as the type of substructure, areconsidered in the barrier exposure index.

  • 7/28/2019 Precast Concrete Barriers

    15/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 7 of 142

    The barrier exposure index is defined as:1 h c g s

    e

    (AADT ) K K K K B =

    1000

    Where:

    AADT1 10,000 vehicles per day per traffic lane per vehicle speeds 80km/h or greater

    Kh = highway type factor, see CAN/CSA-S6-00, Table 12.5.2.1.2 (a)

    Kc = highway curvature factor, see CAN/CSA-S6-00, Table 12.5.2.1.2 (b)

    Kg = highway grade factor, see CAN/CSA-S6-00, Table 12.5.2.1.2 (c)

    Ks = superstructure height factor, see CAN/CSA-S6-00, Table 12.5.2.1.2 (d)

    With the design speed and the percentage of trucks as well as the barrier exposure index thePerformance Level can be determined with tables given under CAN/CSA-S6-00 Section

    12.5.2.1.3. There exist three different tables for three different barrier clearances in the CanadianHighway bridge design Code:

    Table 12.5.2.1.3 (a) for Barrier Clearance 2.25m

    Table 12.5.2.1.3 (b) for 2.25m < Barrier Clearance 3.75m

    Table 12.5.2.1.3 (c) for Barrier Clearance > 3.75m

    Due to the Performance Level a minimum barrier height can be determined with Table 12.5.2.2

    from CAN/CSA-S6-00. The minimum barrier heights for PL 1, 2, and 3 traffic barriers are 0.68 m,

    0.80 m, and 1.05 m respectively. Traffic barrier height requirements are intended to prevent

    impacting vehicles from vaulting or rolling over a barrier. The higher the center of gravity of the

    impacting vehicle, the greater the required traffic barrier height needed to contain it.

    And the geometry of the roadway face of a traffic barrier as well as the transition into theroadway face of the approach roadway traffic barrier shall have a smooth and continuous

    alignment, as laid out in Section 12.5.2.2 in CAN/CSA-S6-00. Where a traffic barrier is located

    between the roadway and a sidewalk or bikeway, the sidewalk or bikeway face of the barriershould have a minimum height of 0.60 m measured from the surface of the sidewalk or bikeway.

    3.1.2 Crash test requirements

    With the defined Performance Level the crash test requirements which should be inaccordance with the crash test requirements ofAASHTO Guide Specifications for Bridge Railingsare defined, as mentioned in Section 12.5.2.3 in CAN/CSA-S6-00. Those crash test requirements

    shall be satisfied along the entire length of a traffic barrier, including at any changes in barrier

    type, shape, alignment, or strength that may affect the barrier performance. Alternative

    Performance Levels shall meet the crash test requirements of the optimum Performance Level orof a more severe Performance Level as considered.

  • 7/28/2019 Precast Concrete Barriers

    16/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 8 of 142

    Under Section 12.5.2.3.2 CAN/CSA-S6-00, the crash test requirements for traffic barrier

    transitions are defined. They should meet the crash test requirements used for appraising theapproach roadway traffic barrier, provided that it has been crash tested to requirements that test

    its geometry, strength, and behaviour to an equivalent or more severe level. These requirements

    are normally in accordance with Test Designation 30 ofNCHRP 230: Recommended Procedures

    for the Safety Performance Evaluation of Highway Appurtenances (Michie 1981) which requirescrash testing with a 2040 kg automobile travelling 96 km/h and striking the transition at an

    impact angle pf 25.

    The crash test requirements for longitudinal barrier Test Levels 2, 4, and 5 of National

    Cooperative Highway Research Program (NCHRP) Report 350:Recommended Procedures forthe Safety Performance Evaluation of Highway Features shall be taken as meeting the crash test

    requirements for Performance Level 1, 2, and 3 respectively.

    According to Section 12.5.2.3.4 in CAN/CSA-S6-00, any changes in details effecting the

    geometry, strength, or behaviour of the traffic barrier or traffic barrier transition that meets the

    aforementioned requirements can be demonstrated to not adversely affect barrier-vehicleinteraction.

    3.1.3 Anchorages

    The performance of the traffic barrier anchorage during crash testing is the basis for its

    capability. In case no significant damage occurs in the anchorage or deck during crash testing, the

    anchorage is considered to be acceptable.

    If there are no crash testing results for the anchorage available, the anchorage and deck shall be

    designed to resist the maximum bending, shear and punching loads that can be transmitted tothem by the traffic barrier. The loads should be applied as the following:

  • 7/28/2019 Precast Concrete Barriers

    17/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 9 of 142

    Figure 2 Application of traffic design loads to traffic barriers, from Figure 12.5.2.4, CAN/CSA-S6-00

    But the loads have to be greater than those resulting from the loads defined in Section 3.8.8,Barrier Loads, in CAN/CSA-S6-00. The transverse, longitudinal, and vertical loads should be

    applied simultaneously and are specified as the following:

    Table 1 Traffic barrier loads, from Figure 3.8.8.1, CAN/CSA-S6-00

    3.2 Pedestr ian barr ier

    Pedestrian barriers should be provided on both sides of pedestrian bridges and on the

    outside edges of highway bridge sidewalks separated from the roadway by a traffic barrier.Pedestrian barriers should be in accordance with the minimum height requirements which are

    given in Table 12.5.2.2 in CAN/CSA-S6-00, as aforementioned in chapter 3.1 Traffic barrier.

    Openings in pedestrian barriers should not exceed 150 mm in the least direction, or be coveredwith chain link mesh with a minimum wire diameter of 3.5 mm and openings smaller than 50 mm

    by 50 mm.

  • 7/28/2019 Precast Concrete Barriers

    18/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 10 of 142

    The design loading for pedestrian barrier are given in Section 3.8.8,Barrier Loads, in CAN/CSA-

    S6-00 (see Table 1 Traffic barrier loads, from Figure 3.8.8.1, CAN/CSA-S6-00). These loadsshould be applied as shown in the beneath figure (the design load application for pedestrians and

    bicycle are the same). When designing posts of post and railing barriers only one railing should

    be loaded at a time.

    Figure 3 The application of pedestrian and bicycle design loads to barriers, from Figure 12.5.3.2,CAN/CSA-S6-00

    3.3 Bicycle barrier

    Bicycle barriers should be provided on both sides of bicycle bridges and on the outside

    edges of highway bridge bikeways where the bikeway is separated from the roadway by a traffic

    barrier. Bicycle barriers should also conform the minimum height requirements which are given

    in Table 12.5.2.2 in CAN/CSA-S6-00, as aforementioned in chapter 3.1 Traffic barrier. Openingsin bicycle barriers for the lower 1050 mm should be smaller than 150 mm in the least direction,

    or be covered with chain link mesh with a minimum wire diameter of 3.5 mm and openings

    smaller than 50 mm by 50 mm.

    The design loading for bicycle barrier are given in Section 3.8.8 in CAN/CSA-S6-00, BarrierLoads. Since the design load application for pedestrians and bicycle are the same, the loadsshould be applied as shown in Figure 3 The application of pedestrian and bicycle design loads

    to barriers, from Figure 12.5.3.2,

    CAN/CSA-S6-00. When designing posts of post and railing barriers only one railing should beloaded at a time.

  • 7/28/2019 Precast Concrete Barriers

    19/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 11 of 142

    3.4 Combination barrier

    Combination barriers shall be provided on the outside edges of bridge sidewalks and

    bikeways not separated from the traffic lanes by traffic barrier. They should meet the

    requirements mentioned in chapter 3.1 Traffic barrier, 3.2 Pedestrian barrier, and 3.3 Bicycle

    barrier except in respect of geometry and the openings. In combination barriers opening shall besmaller than 150 mm in the least direction for the lower 600 mm of the barrier and 380 mm in the

    least direction above the lower 600 mm of the barrier.

  • 7/28/2019 Precast Concrete Barriers

    20/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 12 of 142

    4. Literature review of background to CHBDCrequirements of bridge barriers and other backgroundregarding bridge barriers and barrier testing

    4.1 The precursor of the Canadian Highway Bridge Design Code

    The CAN/CSA-S6-00 Canadian Highway Bridge Design Code amalgamates andsupersedes both, CAN/CSA-S6-88Design of Highway Bridges and the OHBDC-91-01 Ontario

    Highway Bridge Design Code, third edition, becoming the standard National Code used in

    Canada. CAN/CSA-S6-88Design of Highway Bridges is prepared by the Canadian Standards

    Association (CSA) for highway bridge design in Canada and the OHBDC-91-01 Ontario

    Highway Bridge Design Code was published by the Ontario Ministry of Transportation,

    Downsview, Ontario.

    Therefore, reviews of the CAN/CSA-S6-88Design of Highway Bridges as well as the

    OHBDC-91-01 Ontario Highway Bridge Design Code are presented and in addition the main

    changes of the precursor compared to the CAN/CSA-S6-00 Canadian Highway Bridge DesignCode are outlined.

    4.1.1 Review of CAN/CSA-S6-88 requirements of bridge barriers

    In Section 4.4 of the CAN/CSA-S6-88 Design of Highway Bridges barriers named

    roadway railings are defined. The type of barrier is due to its function defined as traffic railing,

    sidewalk railing, bicycle railing, and combination railing. The different types of railings whichshould be illustrative only are shown in Figure 3, CAN/CSA-S6-88, with its dimensions and

    design loads. All bridges should have a railing on each side.

    Roadway railings are covered in Section 4.4.2. The first subsection, Section 4.4.2.1, deals

    with the geometry and defines that the rail on the traffic side should have a smooth and

    continuous face of rail. The next section deals with joints and says that provisions should bemade where expansion joints interrupt the continuous railings to transfer the loads. The endings

    of railings should be treated with caution and are covered in Section 4.4.2.3.

    Concerning the design of traffic railings, Section 4.4.2.4 outlines a height of minimum 700 mm,

    except that parapets with sloping traffic faces are used which demands a minimum height of800 mm. The height is measured from the top of the roadway, the top of future overlay, or the top

    of the curb to the top of the upper rail members.

    The lower element of a roadway or combination railing should consists of a parapet projecting atleast 600 mm above the reference surface, or a participating curb (Section 4.4.2.5). The next

    section defines the maximum opening below the lower rail, or between succeeding rails to a

    maximum of 380 mm.

  • 7/28/2019 Precast Concrete Barriers

    21/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 13 of 142

    The height of sidewalk and bicycle railings should be as indicated in Figure 3, CAN/CSA-

    S6-88. Beside that, sidewalk railings should have a maximum opening of 150 mm in leastdimension (Section 4.4.3, CAN/CSA-S6-88). Concerning combination railings, governed in

    Section 4.4.4 ofCAN/CSA-S6-88, the minimum height of combination railings is 1000 mm.

    The design of the roadway railings, parapets, and posts, as laid out in Section 5.2.10.4 inCAN/CSA-S6-88, should be done with transverse loads given for some railing types (see Figure 3,

    CAN/CSA-S6-88). Sidewalk, bicycle, and combination railings should be designed for transverse

    and vertical loads on each longitudinal member, simultaneously (see Section 5.2.10.4.2 to5.2.10.4.4, CAN/CSA-S6-88).

    4.1.2 Comments on changes between CAN/CSA-S6-88 and CAN/CSA-S6-00

    The requirements on the geometry of the barriers has only little changes. But the

    definition of the height of a barrier as well as the design requirements underlie many changes.

    Traffic railings are not differentiated due to different site conditions of a bridge site whichis done with the Performance Level in the new Code, CAN/CSA-S6-00. Under Section 4.4.2.4 ofCAN/CSA-S6-88 a minimum height of the roadway railing is defined by 700 mm which is

    comparable with the height of PL-1 given in CAN/CSA-S6-00. But on the other side, CAN/CSA-

    S6-88gives a minimum opening of 380 mm for traffic barriers which does not exists any more inCAN/CSA-S6-00.

    Another point which is new in CAN/CSA-S6-00 are the anchorages of the roadway railings

    and their design. Since the aspect of failure became a bigger role in the design, because of thechanges of the power of cars, traffic barriers and their design changed. They should nowadays

    also provide a reduction of the consequences of a vehicle leaving the roadway due to the

    occurrence of an accident.

    The requirements on the geometry of pedestrian, bicycle, and combination barriers has

    changed only little too. CAN/CSA-S6-00 describes the requirements on the geometry moredetailed and more separated due to its function. The requirements on the design of pedestrian,

    bicycle, and combination barriers are no more as detailed as they were before, but therefore crash

    test requirements are defined.

    In the end it can be said that CAN/CSA-S6-88 gives a great flexibility in the design of

    roadway railings. For some cases the design loads are given but it is mentioned that they are only

    illustrative. Therefore a definition of the design of other types of railings is missing. Crash teststo determine the effectiveness in reducing the consequences of vehicles leaving the roadway upon

    the occurrence of an accident are not considered at all.

    4.1.3 Review of OHBDC-91-01 requirements of bridge barriers

    In Section 5 of the OHBDC-91-01, third edition, barriers and highway appurtenances are

    defined. In general, barriers are design at superstructure sides or edges and are supposed to helpto restrain errant vehicles from leaving the roadway as mentioned in Section 5-4.1,

    OHBDC-91-01. Barriers are differentiated due to their location and function in traffic,

  • 7/28/2019 Precast Concrete Barriers

    22/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 14 of 142

    combination, pedestrian, and bicycle barriers. The barrier alignment, as defined in Section

    5-4.1.3, OHBDC-91-01,Barrier Geometry, should be continuous and smoothly transitioned. Theexpansion joints that allow for bridge flexure and thermal movements should be designed in

    detail for all barrier types. The minimum barrier heights are defined in Table 5-4.1.3.2, OHBDC-

    91-01 and come up to 0.70 m, 0.80 m, and 1.05 m for PL 1, 2, and 3 traffic barriers respectively.

    In Section 5-4.2, OHBDC-91-01, superstructure side barriers are defined. Within that section it is

    mentioned that traffic barriers should conform to the relevant Performance Levels PL-1, PL-2, or

    PL-3 in accordance with the crash testing procedures of the AASHTO Guide Specifications for

    Bridge Railings, 1989.

    The Performance Level selection, defined in Section 5-4.3, OHBDC-91-01, is based on the

    barrier exposure index, BI. And the barrier exposure index is based on the first year annual daily

    traffic (ADTi) and corrected by factors concerning the highway type, curvature, grade, and theheight of superstructure. With a calculated barrier exposure index the Performance Level can be

    determined together with the design speed, percentage of trucks using the highway, and the

    barrier clearance (see Tables 5-4.3.2.2(a) to (c), OHBDC-91-01).

    The barrier appraisal due to traffic barrier acceptance and selection are defined in Section

    5-4.4.2, OHBDC-91-01. Traffic and combination barriers which conform the geometry and

    strength of the prototypes that have been tested and appraised in accordance with AASHTO Guide

    Specification for Bridge Railings, 1989, are accepted directly. Barrier transitions should be crash

    tested and approved in accordance with NCHRP Report 230:Recommended Procedures for theSafety Performance Evaluation of Highway Appurtenances, to be accepted. Barriers and barriertransitions, which do not meet the conditions as defined in the aforementioned paragraph, but

    have similar geometry to that of a specific barrier that has been crash tested, may be used if three

    conditions which are mentioned in Section 5-4.4.2.2 (a) to (c), OHBDC-91-01, are met.

    Pedestrian and bicycle barriers have more detailed definitions about spacing between

    barriers and openings of the barriers themselves in the sections 5-4.5.2, and 5-4.5.3, OHBDC-91-01, respectively. The design loads should be applied as shown in the following figure:

    Figure 4 Application of pedestrian loads for pedestrian railings, from Figure 5-4.5.2.3, OHBDC-91-01

  • 7/28/2019 Precast Concrete Barriers

    23/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 15 of 142

    Figure 5 Application of pedestrian loads for bicycle railings and combination barriers,

    from Figure 5-4.5.2.3, OHBDC-91-01

    4.1.4 Comments on changes between OHBDC-91-01 and CAN/CSA-S6-00

    The OHBDC-91-01 was definitely the basis for the development of CAN/CSA-S6-00.There are only little changes in the contents as well as in the sequence.

    The requirements on the geometry have almost no changes. The minimum heights of the

    barriers are approximately the same in the OHBDC-91-01 and CAN/CSA-S6-00. But there aresome changes in the values which are used in the determination of the Performance Level. The

    correcting factors, to calculate the Performance Level, are in average higher in OHBDC-91-01,

    but the range is still the same. But besides that, the tables which result to the Performance Levelare based on higher values of the barrier exposure index (BI). And, in the end, it can be said that

    the Performance Level results in both Codes, the OHBDC-91-01 and CAN/CSA-S6-00, in average

    in the same Levels, although the values used for the determination are different.

    Another point that is different in CAN/CSA-S6-00 is that it accepts alternative

    Performance Levels whereas the OHBDC-91-01 only accepts the Performance Levels PL-1, PL-

    2, and PL-3.

    The design of the traffic barriers is based on some prototypes and there geometry inOHBDC-91-01. Crash testing can be waived for barriers that have a successful in-serviceperformance record which makes the design very fast. But nevertheless OHBDC-91-01 does not

  • 7/28/2019 Precast Concrete Barriers

    24/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 16 of 142

    mention any requirements for the traffic barrier anchorages which are the basis in helping to

    restrain errant vehicles from leaving the roadway.

    The design of pedestrian and bicycle barriers, as well as combination barriers is very

    similar in the OHBDC-91-01and the CAN/CSA-S6-00.

    4.1.5 General comment on the changes of the CHBDC to the precursor

    Finally, it can be said that Section 12 of CAN/CSA-S6-00 Canadian Highway Bridge

    Design Code, Barriers and Highway Accessory Supports, is based on OHBDC-91-01 Ontario

    Highway Bridge Design Code, third edition. The composition of the twelfths Section ofCAN/CSA-S6-00 is more or less the same than in the OHBDC-91-01. But Section 12 ofCAN/CSA-S6-00 carriers forward the crash testing requirements for barriers that appeared in

    OHBDC-91-01. And crash testing may be waived for barriers that have a successful in-service

    performance record. Section 12 ofCAN/CSA-S6-00 also propels forward the aspect of alternative

    Performance Levels.

    4.2 Other background literature regarding the CHBDC

    Concerning the design of the barriers the CAN/CSA-S6-00 Canadian Highway Bridge

    Design Code as well as the precursor refer several times to theAASHTO (American Association

    of State Highway Transportation Officials) Guide Specifications for Bridge Railings.

    In 1989AASHTO published Guide Specifications for Bridge Railings, which contains the

    recommendations and procedures to evaluate bridge railings by full-scale vehicle crash testing. In

    2004, the 3rd

    Edition and therefore the newest AASHTO LRFD (Load and Resistant FactorDesign) Bridge Design Specifications was published and deals in section 13 with bridge railings.

    This section describes three bridge-railing Performance Levels and associated crash tests and

    performance requirements plus guidance for determining the appropriate railing Performance

    Level for a given bridge site.

    Concerning full-size crash tests the CHBDCas well as theAASHTO refers toReport 350:Recommended Procedures for the Safety Performance Evaluation of Highway Features. Thisreport was published by the NCHRP (National Cooperative Highway Research Program) in 1993.

    It presents a uniform guideline for crash testing of both, permanent and temporarily highwaysafety features and recommended evaluation criteria to assess test results.

    Due to the importance ofAASHTO LRFD Bridge Design Specifications and NCHRP

    Report 350: Recommended Procedures for the Safety Performance Evaluation of Highway

    Features even in Canada, the guides itself as well as their backgrounds are presented.

  • 7/28/2019 Precast Concrete Barriers

    25/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 17 of 142

    4.2.1 AASHTO LRFD Bridge Design Specifications, Section 13, Railings,from 1997

    In section 13 ofAASHTO LRFD Bridge Design Specifications railings which should be

    provided along the edges of structures for protection of traffic and pedestrians are defined. The

    guideline indicates the application of four types of rails including which are: (1) traffic railing,(2) pedestrian railing, (3) bicycle railing and (4) combination railing. A traffic railing is used

    when a bridge is for the exclusive use of highway traffic whereas a combination barrier is used on

    low-speed highways in conjunction with a raised curb and sidewalk and on high-speed highwayswhere the pedestrian or bicycle path should have both, an outboard pedestrian or bicycle railing,

    respectively, and an inboard combination railing.

    4.2.1.1 Traffic railings

    In general, the primary purpose of traffic railings is to contain and redirect vehicles using

    the structure and that means that they should be crashworthy, which means a system is

    successfully crash-tested). When choosing traffic railings the following aspects should beconsidered:

    Protection of the occupants of a vehicle in collision with the railing; Protection of other vehicles near the collision; Protection of persons and property on roadways and other areas underneath the structure; Possible future rail upgrading; Railing cost-effectiveness; and Appearance and freedom of view from passing vehicles.

    An approach guardrail system, including a transition from the guardrail system to the rigid bridge

    railing system, should be provided at the beginning and end of all bridge railings in high speedrural areas.

    Depending on the chosen performance level the corresponding testing criteria as theweight of the vehicles, speed, and angle of impact are defined and can be found in the following

    table:

  • 7/28/2019 Precast Concrete Barriers

    26/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 18 of 142

    Table 2 Bridge railing Performance Levels and crash test criteria from Table 13.7.2.1,

    AASHTO LRFD Bridge Design Specifications, 1997

    Concerning the design, a crashworthy railing system, which is a system that is crashtested and afterwards accepted, may be used without further analysis provided that the proposed

    installation features are the same. New railing systems may be used, provided that acceptable

    performance is demonstrated through full-scale crash tests which can be tested with the NCHRPReport 350: Recommended Procedures for the Safety Performance Evaluation of HighwayFeatures) or that crash test specimens for a railing system is designed to resist the applied loads

    in accordance with Appendix A of AASHTO LRFD Bridge Design Specifications (see chapter4.2.3 Appendix A of AASHTO LRFD Bridge Design Specifications). The minimum edge

    thickness for concrete deck overhangs should be 8 inches for concrete deck overhangs, either

    supporting a deck-mounted post system or supporting concrete parapets or barriers, and 12 inches

    for a side-mounted post system.

    The height of concrete railings should be at least 32 inches for PL-2 and 42 inches for

    PL-3. For future overlay considerations the bottom 3-inches lip of the safety shape should not be

    increased. The minimum height for a concrete parapet with a vertical face is 27 inches whichapplies also to combined concrete and metal railings. The geometry of the railing should provide

    a smooth and continuous face of rail on the traffic side.

    4.2.1.2 Pedestrian railings

    The pedestrian railing should be at least 42 inches high measured from the top of the

    walkway. And the clear opening applied to the lower 27 inches should be less than 6 inchesbetween rail elements and above the 27 inches less than 15 inches between rail elements.

    The design live loading for pedestrian railing should be w = 0.05 KLF, both transverselyand vertically, acting simultaneously on each longitudinal element. The application of the loads is

    shown in the beneath picture.

    Figure 6 Pedestrian railing loads, from Figure 13.8.2.1, AASHTO LRFD Bridge Design Specifications

  • 7/28/2019 Precast Concrete Barriers

    27/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 19 of 142

    4.2.1.3 Bicycle railings

    The bicycle railing should be at least 54 inches high, measured from the top of the riding

    surface. The height of the upper and lower zones of bicycle railing should be at least 27 inches.

    The design live loading for bicycle railing should be w = 0.05 KLF, both transversely andvertically, acting simultaneously on each longitudinal element for rail heights under 54 inches. If

    the rail is higher than 54 inches, the designer has to determine the design loads himself. The

    application of the loads is shown in the beneath picture.

    Figure 7 Bicycle Railing Loads, from Figure 13.9.3.1, AASHTO LRFD Bridge Design Specifications

    4.2.1.4 Combination railings

    The requirements of either the pedestrian or the bicycle railings, whichever is applicable,

    should be used for the design of the combination railing.

    4.2.2 AASHTO LRFD Bridge Design Specifications, Section 13, Railings,2004: Important changes from the 2nd to the 3rd Edition

    The important changes from the second to the third edition ofAASHTO LRFD BridgeDesign Specifications are mainly in the traffic railing chapter.

  • 7/28/2019 Precast Concrete Barriers

    28/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 20 of 142

    The testing criteria are no more chosen due to a selected Performance Level, they are

    chosen due to a selected Testing Level. It is the responsibility of the user agency to determinewhich of the test levels is the most appropriate for the bridge site. The Testing Levels are defined

    as the following:

    Testing Level 1 (TL-1) taken to be generally acceptable for work zones with low postedspeeds and very low volume, low speed local streets:

    Testing Level 2 (TL-2) taken to be generally acceptable for work zones and most localand collector roads with favourable site conditions as well as where a small number ofheavy vehicles is expected and posted speeds are reduced;

    Testing Level 3 (TL-3) taken to be generally acceptable for a wide range of high-speedarterial highways with very low mixtures of heavy vehicles and with favourable siteconditions

    Testing Level 4 (TL-4) taken to be generally acceptable for the majority of applicationson high speed highways, freeways, expressways, and Interstate highways with a mixtureof trucks and heavy vehicles;

    Testing Level 5 (TL-5) taken to be generally acceptable for the same applications as TL-4 and where large trucks make up a significant portion of the average daily traffic or when

    unfavourable site conditions justify a higher level of rail resistance; and

    Testing Level 6 (TL-6) taken to be generally acceptable for applications where tanker-type trucks or similar high center of gravity vehicles are anticipated, particularly along

    with unfavourable site conditions.

    The testing criteria such as vehicle weights, vehicle speeds, and angles of impact are given in the

    following table for a chosen Testing Level:

    Table 3 Bridge railing Testing Levels and crash test criteria, from Figure 13.7.2-1, AASHTO LRFD Bridge

    Design Specifications 2004

  • 7/28/2019 Precast Concrete Barriers

    29/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 21 of 142

    The height of concrete railings should be at least 27 inches for TL-3, 32 inches for

    TL-4, 42 inches for TL-5, and 90 inches for TL-6. For future overlay considerations the bottom3-inches lip of the safety shape should not be increased. The minimum height for a concrete

    parapet with a vertical face is 27 inches which applies also to combined concrete and metal

    railings. The geometry of the railing should provide a smooth and continuous face of rail on the

    traffic side.

    4.2.3 Appendix A of AASHTO LRFD Bridge Design Specifications, 1997

    In Appendix A the design of barriers and the specimens are explained in detail. The

    geometry and anchorages are explained first in chapter A13.1. Then, in chapter A13.2 traffic

    railing design forces and in chapter A13.3 design procedures for railing test specimens, dividedinto concrete railings, post-and-beam railings, combination concrete parapet and metal rail, and

    wood barriers, are defined. The last chapter in the appendix, A13.4, deals with deck overhang

    design.

    4.2.3.1 Geometry and Anchorages

    Traffic railings have a defined setback distance S which recognizes the tendency for

    various shape posts to snag wheels. The implication of the various definitions of the setback

    distance S is that all other things being equal the space between a rail and the face of arectangular post will be greater than the distance between a rail and the face of a circular post.

    Figure 8 Geometrical definitions of two typical traffic railings, from Figure A13.1.1-1,

    AASHTO LRFD Bridge Design Specifications

    For post railings, the combination of ratio of rail contact width to height (A/H) and the post

    setback distance S, should be within or above the shaded area of the following figure:

  • 7/28/2019 Precast Concrete Barriers

    30/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 22 of 142

    Figure 9 Post setback criteria, from Figure A13.1.1-3, AASHTO LRFD Bridge Design Specifications

    The reinforcing steel for concrete barriers should have a sufficient embedment length

    which is defined in Section 5 in AASHTO LRFD Bridge Design Specifications to develop thenecessary yield strength.

    4.2.3.2 Traffic Railing Design Forces

    The railing design forces and geometric criteria that are used for developing test

    specimens for a crash test program are defined in this chapter.

    The effective height of the vehicle rollover force, He, should be taken as: et

    WBH = G -

    2F

    Where:

    G = Height of vehicle center of gravity above bridge deck (FT)

    W = Weight of vehicle corresponding to the required Performance Level (KIP)

    B = Out-to-out wheel spacing on an axle (FT)

    Ft = Transverse force corresponding to the required Performance Level (KIP)

  • 7/28/2019 Precast Concrete Barriers

    31/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 23 of 142

    Figure 10 Nomenclature for traffic railing equations, from Figure CA13.2.1,AASHTO LRFD Bridge Design Specifications, 1997

    And the railings should be proportioned so that:

    tR F , for which iR= R

    eY H , for which

    i i(R Y )Y=

    R

    Where:

    Ri = Resistance of the rail (KIP)

    Yi = Distance from bridge deck to the ith

    rail (FT)

    The transverse and longitudinal loads have to be applied in conjunction with vertical loads

    as given in the figure below. All the forces should be applied to the longitudinal rail elements.

    The distribution of longitudinal loads to posts should be consistent with the continuity of railelements and the transverse loads with the assumed failure mechanism of the railing system.

  • 7/28/2019 Precast Concrete Barriers

    32/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 24 of 142

    Figure 11 Design forces for traffic railings, from Table A13.2-1,

    AASHTO LRFD Bridge Design Specifications, 1997

    To understand the application of the design loads better they are presented, for example, on a

    metal bridge railing which can be seen in the beneath figure.

    Figure 12 Railing design forces, from Figure A13.2-1,

    AASHTO LRFD Bridge Design Specifications

    4.2.3.3 Design Procedures for Railing Test Specimens

    A design procedure for reinforced concrete and prestressed concrete railing or parapet testspecimens is the yield line analysis and strength design. The yield line analysis includes the

    ultimate flexural capacity of the concrete component. Stirrups or ties should be able to resist the

    shear and the diagonal forces if present. In the yield line analysis it is assumed that the yield line

    failure occurs only in the parapet and does not extend to the deck. That means that the decks needa sufficient resistance to force the yield line failure pattern to remain within the parapet.

  • 7/28/2019 Precast Concrete Barriers

    33/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 25 of 142

    The nominal railing resistance to transverse load, RW, can be determined using the yield

    line approach as the following:

    For impacts within a wall segment:2

    c cW b w

    c t

    M L2R = 8M +8M H+

    2L -L H

    where the critical wall length is:

    2

    t t b wC

    c

    L L 8H(M +M H)L = +

    2 2 M

    For impacts at the end of wall or joint:2

    c cW b w

    c t

    M L2R = M +M H+

    2L -L H

    where the critical wall length is:

    2

    t t b wC

    c

    L L M +M HL = + H2 2 M

    Where:

    Rw = Total transverse resistance of the railing (KIP)

    Lt = Longitudinal length of distribution of impact force Ft (FT)

    Mb = Additional flexural resistance of beam in addition to Mw, if any, at top of wall (KFT)

    Mw = Flexural resistance of the wall (KFT/FT)

    H = Height of the barrier (FT)

    Mc = Flexural resistance of cantilevered wall (KFT/FT)

    The yield line analysis is explained in the following figures. The first figure shows the

    explanation of the lengths for a wall segment and for a near the end of wall segment. The secondfigure shows the where and in which direction the moments occur.

    Figure 13 Yield Line Analysis of concrete parapet walls for impact within wall segment and near end of wall

    segment, part 1 of Table A13.3.1-1/2, AASHTO LRFD Bridge Design Specifications

  • 7/28/2019 Precast Concrete Barriers

    34/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 26 of 142

    Figure 14 Yield Line Analysis of concrete parapet walls for impact within wall segment,

    part 2 of Table A13.3.1-1, AASHTO LRFD Bridge Design Specifications

    For a combination concrete parapet with metal rail, the resistance of each part has to be

    determined first, separately. The resistance of the concrete parapet should be determined as

    explained in the paragraph before with the yield line analysis. The nominal resistance R of themetal railing is the result of possible yield failure modes for post-and-beam railings. The basis of

    the failure modes are shown in the figures on the next page.

    Figure 15 Possible failure modes for post-and-beam railings, from Table A13.3.2-1,

    AASHTO LRFD Bridge Design Specifications

  • 7/28/2019 Precast Concrete Barriers

    35/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 27 of 142

    The critical wall nominal resistance, R, for the metal railing should be the least value determined

    by the following two equations for various numbers of railing spans N:

    For failure modes involving an odd number of railing spans N:

    p p

    t

    16M + (N-1)(N+1)P LR =2NL-L

    For failure modes involving an even number of railing spans N:

    2

    p p

    t

    16M + N P LR =

    2NL-L

    Where:

    R = Total ultimate resistance, i.e. nominal resistance, of the railing (KIP)

    Mp = Inelastic or yield line resistance of all of the rails contributing to a plastic hinge (KFT)

    N = Number of railing spans (-)

    Pp = Ultimate transverse load resistance of a single post located Y above the deck (KIP)

    L = Post spacing or single-span (FT)

    Lt = Longitudinal length of distribution of impact force Ft (FT)

    The flexural strength of the combination rail, R , should be determined over one span, RR,

    and over two spans, R'R. The resistance of the post on the wall, PP, shall be determined includingthe resistance of the anchor bolts or post.

    The resistance of the combination parapet with rail is the lesser resistance determined for

    the two failure modes, impact at mid-span and impact at post, respectively. The failure modes are

    shown in a figure after the equations on the next page.

    Where the impact is at mid-span:

    The combined resultant strength is: R WR = R + R

    and the effective height is: R R W WR H + R H

    Y =R

    Where the impact is at a post:

    The combined resultant strength is: P R WR = P + R' + R'

  • 7/28/2019 Precast Concrete Barriers

    36/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 28 of 142

    and the effective height is: P R R R W WP H + R' H + R' H

    Y =R

    for which W W P R WW

    R H - P HR' =

    H

    Where:

    R = Flexural strength of the combination rail (KIP)

    RR = Ultimate capacity of rail over one span (KIP)

    RW = Ultimate capacity of wall (KIP)

    Y = The effective height (FT)

    HR = Height of wall (FT)

    HW = Height of rail (FT)

    PP = Resistance of the post on the wall (KIP)

    R'R = Ultimate transverse resistance of rail over two spans (KIP)

    R'W = Capacity of wall, reduced to resist post load (KIP)

    Figure 16 Combination concrete wall and metal rail evaluation-impact at (1) mid-span of rail and (2) at a

    post, from Table A13.3.3-1/ 2, AASHTO LRFD Bridge Design Specifications

  • 7/28/2019 Precast Concrete Barriers

    37/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 29 of 142

    4.2.4 Appendix A of AASHTO LRFD Bridge Design Specifications, 2004:Important changes from the 2nd to the 3rd Edition

    The important changes from the second to the third edition ofAASHTO LRFD Bridge

    Design Specifications are only in the chapter Traffic Railing Design Forces. The table giving the

    design forces for traffic railings changed due to the change from performance Levels to TestingLevels. The new table is the following:

    Table 4 Design forces for traffic railings, from Table A13.2-1,

    AASHTO LRFD Bridge Design Specifications, 2004

    4.2.5 NCHRP Report 350: Recommended Procedures for the SafetyPerformance Evaluation of Highway Features

    Report 350: Recommended Procedures for the Safety Performance Evaluation of

    Highway Features was published by the National Cooperative Highway Research Program

    (NCHRP) in 1993 and is an all-metric document. This report replaced NCHRPReport 230:Recommended Procedures for the Safety Performance Evaluation of Highway Appurtenances,

    which was published in 1981.

    In Report 350: Recommended Procedures for the Safety Performance Evaluation of

    Highway Features recommended procedures for evaluating the safety performance of various

    highway safety features are contained. The features covered by these procedures include (1)longitudinal barriers such as bridge rails, guardrails, median barriers, transitions, and terminals;

    (2) crash cushions; (3) breakaway or yielding supports for signs and luminaries; (4) breakaway

    utility poles; (5) truck-mounted attenuators; and (6) work zone traffic control devices.

    The approach of the report was to normalize test conditions. And therefore the testparameters as the testing facility, the test article, and the test vehicle are defined. Report 350

    includes six different Test Levels (TL-1 through TL-6) for various classes of roadside safetyfeatures, and a number of optional test levels to provide the basis for safety evaluations to support

    more or less stringent performance criteria. Although this document does not include objective

    criteria for relating a test level to a specific roadway type, the lower test levels generally areintended for use on roadways with lower service levels and certain types of work zones, whereas

    the higher test levels are intended for use on higher-service-level roadways.

  • 7/28/2019 Precast Concrete Barriers

    38/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 30 of 142

    For vehicle crash tests, specific impact conditions such as vehicle mass, speed, approach

    angle, and point on safety feature to be hit are presented. The test matrices including standardtests as well as the standard test vehicle types are described. To evaluate the crash test

    performance, three primary appraisal factors as structural adequacy, occupant risk, and after-

    collision vehicle trajectory are presented. Depending on the safety feature's function, it should

    contain, redirect, and permit controlled penetration of the impacting vehicle, or permit acontrolled stop in a predictable manner to satisfy structural adequacy requirements.

    In addition the report reflects a critical review of methods and technologies for safety-

    performance evaluation, such as surrogate test vehicles and computer simulations, andincorporates state-of-the-art methods in the procedures. In-service evaluation of extensively

    modified roadside safety features are used with the purpose of appraising actual performance

    during a broad range of collision, environmental, operational, and maintenance situations fortypical site and traffic conditions.

    4.3 Other literature regarding bridge barriers and barrier testing

    There exist many literatures dealing with bridge barriers and their testing. A summary of

    the paper "Basics of Concrete Barriers" published by Charles F. McDevitt is given to get ageneral introduction to barriers and their shapes.

    And to get a comparison to the Codes used in the Province of British Columbia to another

    country, the state of Washington in the United States of America has been chosen. Washingtonstate is the neighbour state of British Columbia which means that they deal with the same climate

    conditions. And in addition, many of the barriers and anchors used in British Columbia are

    compared to the United States of America. Hence, the Washington State Bridge Design Manual

    which is the bridge design code of the state Washington in the United States of America, ispresented and a comment on the Manual is given.

    4.3.1 Basics of Concrete Barriers

    The basic principles of concrete barriers are not generally known and easy to understandand therefore this chapter gives a short introduction explaining the reasons for the shape of a

    barrier. Concrete barriers appear to be simple and uncomplicated, but in reality they aresophisticated safety devices. This chapter represents a summary of the paper "Basics of Concrete

    Barriers" published by Charles F. McDevitt who is a structural engineer in the Federal Highway

    Administration's Office of Safety Research and Development at the Turner-Fairbank HighwayResearch Center in McLean.

    The most well-known barrier in the United States of America is the New Jersey Concrete

    Safety Shape Barrier, also called NJ-shape or Jersey barrier. Since some problems occurred in the1970's, a parametric study with systematically varying the parameters of various configurations

    that were labelled A through F was done. The result was that configuration F performed distinctly

    better than the NJ-shape. The results of these computer simulations were confirmed by a series offull-scale crash tests and configuration F became known as the F-shape barrier. The slope of the

  • 7/28/2019 Precast Concrete Barriers

    39/142

    MOT / UBC Testing of Bridge Barrier Anchorages

    precast concrete barriers in British Columbia.doc page 31 of 142

    F-shape and the NJ-shape barrier are the same, but the major difference is the distance from the

    ground to the slope break point. This distance is 255 mm for the F-shape barrier which is 75 mmlower than the NJ-shape one. The lower slope break point significantly reduced the lifting of the

    vehicle and greatly improved the performance of the concrete barrier.

    The key design parameter for a safety shape profile is the distance from the ground to theslope break point because this determines how much the suspension will be compressed. For

    example for the NJ-shape barrier, this distance is 330 mm (13 inches). The front bumper impactsthe upper sloped face and slides upwards. This interaction initiates lifting of the vehicle. When a

    concrete safety shape lifts a vehicle, some of the kinetic energy of the vehicle is converted topotential energy. This potential energy is turned back into kinetic energy as the vehicle returns to

    the ground. If the bumper is relatively weak, the front end starts to crush before any uplift occurs.

    Then, as the vehicle becomes more nearly parallel with the barrier, the wheel contacts the lowerslope face. Most of the additional lift of the vehicle is caused by the lower sloped face

    compressing the front suspension. However, wheel side-scrubbing forces provide some additional

    lift, particularly if the barrier face is rough. Therefore, exposed aggregate and other rough surface

    finishes should be avoided. Drainage openings in the face of the reveal do not have a significanteffect on an impacting vehicle.

    Vertical concrete parapets do not have the energy management feature as described in theparagraph before. But crash tests have demonstrated that they can perform acceptable as traffic

    barriers. All of the energy absorption in an impact with a rigid vertical parapet is due to crushing

    of the vehicle. Bumpers usually do not slide up vertical concrete parapets and lift the vehicle, soall four wheels tend to stay on the ground. This minimizes the potential for vehicle rollover.

    Finally, it can be said that each of these barrier types fills a niche and helps meet the needsof highway agencies that select, design, and locate traffic barriers. In terms of safety

    performance, the 1070 mm (42 inches) high F-shape is currently the best technology in the

    United States of America. The F-shape profile is clearly superior to the NJ-shape and is gradually

    being used by more jurisdictions for both portable concrete barriers and permanent barriers.

    4.3.2 Review of the Washington State Bridge Design Manual

    The Washington State Bridge Design Manual (WSBDM) M 23-50 was published by the

    Was