Pre-Submittal Meeting...info, email, signature of contact person, vendor number, project title &...
Transcript of Pre-Submittal Meeting...info, email, signature of contact person, vendor number, project title &...
1
CITY OF PHOENIX
REQUEST FOR QUALIFICATIONS
AVIATION DEPARTMENT
TERMINAL 2 CONCOURSE DEMOLITION
AND APRON RECONSTRUCTION
CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES
PROJECT NOs. AV08000082 FAA & AV02000033
PROCUREPHX PRODUCT CATEGORY CODE 912000000
RFx 6000000601
August 23, 2018
Pre-Submittal Meeting
2
Debra Russell, Contracts Specialist – Team Lead
Point of Contact for Submittals and RFQ Questions
Office of the City Engineer
[email protected] (602) 681-5713
Rubben Lolly, Civil Engineer III, Project Manager
Aviation Department
Gloria Hucher, Compliance Assistant
Equal Opportunity Department
[email protected] (602)-262-7716
Welcome and Introductions
3
Meeting Overview
Vendor Registration
EOD Overview and DBE Program Requirements
Project Description and Scope of Work
Statement of Qualifications Evaluation Criteria
Statement of Qualifications Submittal Requirements
ProcurePHX and RFx Electronic Submittal
Important Dates: Selection Schedule
Questions?
Agenda
4
Sign-in please
Sign-in sheet and PowerPoint will be posted City of Phoenix’s
ProcurePHX system (RFx: 6000000XXX):
https://eprocurement.phoenix.gov/irj/portal
And on Procurement’s website:
https://www.phoenix.gov/streets/procurement-opportunities
Click on respective project, then click on:
■ Planholder List ■ RFQ ■ Notification (if applicable)
Bidders Handbook – Step-by-step Guide to RFx Submittals
It is your responsibility as an RFQ holder to determine, prior to
submittal, if any Notifications have been issued
Please hold questions until Q&A period
This is the ONLY opportunity to discuss this project with City staff
Meeting Overview
5
All Firms MUST Be Registered in the Vendor
Management System PRIOR TO SUBMITTING A
PROPOSAL
New Firms – After registering, the City will send an
e-mail with a vendor number approx. 2 days
NEW: NEW: Information on how to register with the
City is available at:
https://www.phoenix.gov/finance/vendorsreg
Vendor Registration
6
Gloria Hucher, Compliance Assistant
Equal Opportunity Department
(602) 262-7716
Equal Opportunity Department
Equal Opportunity Department (EOD) is responsible
for ensuring contractors and consultants achieve full
compliance with all applicable federal regulations
during all phases of this project/contract:
EOD Overview
• Solicitation
• Bid/Submittal Verification
• Subcontract Approval
• Compliance Monitoring
• Prompt Payment
• Release of Retention
• Sanctions and Penalties
8
49 CFR Part 26 mandates
recipient (City) administers a
Disadvantaged Business
Enterprise (DBE) Program
DBE Program
U.S. Department of Transportation (USDOT) assists in
the funding for this project, which is subject to the
requirements of the Federal Aviation Administration
(FAA) and 49 CFR Part 26.
Phoenix DBE Program has annual Overall DBE Goal
of 4.48% [to be achieved entirely with race- and
gender-neutral (RGN) means]
9
Four Elements of Small Business Outreach
(demonstration of Good Faith Efforts):
1. Identify Opportunities
2. Communicate Broadly
3. Evaluate Proposals
4. Constructive Feedback
Small Business Outreach
Phoenix imposes Small Business Outreach
requirements in lieu of DBE Goals (RGN measure)
Submittal Requirements
(Due at time of submittal)
DBE Program
FORM EO1: Statement of Small
Business Outreach Commitment
Failure to submit = Non-Responsive
1 Form
Post-Award Submittal Requirements
(DUE prior to each GMP)
DBE Program
1. FORM EO2: Small Business
Outreach Efforts
2. Supporting documentation for
FORM EO2
3. FORM EO3: Proposed Statement
of Small Business Participation
* Good Faith Effort Documentation
Submit to EOD for review and approval prior to
execution of GMP
For more information, please contact:
Equal Opportunity Department
Gloria Hucher
Compliance Assistant
(602) 262-7716
Email:
Project LocationPhoenix Sky Harbor International Airport
14
Proposed Project AreaTerminal 2 (T2)
15
Preconstruction and Construction services for the T2
Demolition and Apron reconstruction Project.
T2 Concourse, Apron, Terminal Processor and Parking
Garage are located at Terminal 2, west of Terminal 3 at
PSHIA
Design and Construction will be completed in two distinctly
separate Phases.
Phase 1 – AV08000082-FAA will Demolish T2 Concourse
building and existing Apron and reconstruct Apron to
accommodate new Taxilane east of Terminal 3 South
Concourse and RON Apron.
Phase 2 – AV02000033 will relocate art mural from T2
processor to the RCC and demolish theT2 processor and
garage after T2 is decommissioned.
Project Description
16
Phase 1- AV08000082 FAA
Funded by Federal Aviation Administration (FAA)
Estimated construction cost $20.5 million
Disadvantage Business Enterprise (DBE) Market availability
has been established for this project
Project may be constructed in phases based on funding
availability and/or operational needs
Phase 2 - AV02000033
No Federal Funds utilized
Detail Scope and estimate to be defined at a later date
Mural relocation feasibility study completed by PHX to be
incorporated into the design and phasing of Phase 2
Project Description (Cont.)
Project Description (Cont.)
T2 Art Mural to be relocated from the processor to RCC
Scope of WorkIncludes but not limited to:
I - Pre-construction Services
Coordinate efforts with project Engineer, designer,
various City of Phoenix Departments, Aviation Divisions
and other stakeholders
Address all Federal, State and Local requirements
Provide project planning, scheduling and estimating for
the various phases of the project - minimizing impacts to
airport operations
Investigate utility conflicts
Arrange/manage procurement of materials and long-lead
items, as needed
Scope of Work (Cont.)
I - Pre-construction Services (cont.)
Provide detailed cost estimating, Guaranteed Maximum
Price(s) (GMP) schedules and knowledge of market place
conditions for the various phases of the project
Assist in the permitting processes
Advise the city on ways to gain efficiencies in project
execution and delivery
Perform constructability reviews of the plans and
specifications
Participate with the City in the DBE participation and
implementation process
I- Pre-construction Services (cont.)
Select subcontractors/suppliers for this project
Coordinate with the Labor Compliance Office to obtain the
appropriate Davis-Bacon wage schedule required for
construction services
Advise the City on choosing green building materials,
processes, and utilize the DCS Green Guide for sustainable
project implementation
Utilize the City’s web based project management system,
Unifier
Scope of Work (Cont.)
21
II - Construction Services
Phase1: Demolish the T2 Concourse and reconstruct the
T2 Apron
Phase 2: Relocate the T2 art mural, demolish the T2
Processor and T2 Parking Garage and furnish proposed
design solution for remaining area.
Manage all construction related contracts while meeting
city bid requirements including DBE program requirements
Arrange for procurement of materials and equipment
Bid, award, and manage all construction related contracts
while meeting City bid requirements including Davis Bacon
Act compliance and DBE participation
Scope of Work (Cont.)
22
II - Construction Services (cont.)
Coordinate with various City of Phoenix departments,
other agencies, utility companies, etc.
Provide quality control
Bond and insure the construction
Address all federal, state and local permitting
requirements
Maintain a safe & secure work site for all project
participants
Schedule and manage site operations
Scope of Work (Cont.)
23
The CMAR shall have comprehensive and
extensive Aviation experience
Flexibility
Availability
Promptness
Thorough design review
Time is of the essence … Entire Project
package including GMP needed by End of May
2019.
Project Expectations
24
QUESTIONS?
25
A. General Information (150 points)
B. Experience and Qualifications of the Firm (200 points)
C. Experience of Key Personnel to be Assigned (250 points)
D. Understanding of the Project and Approach to
Performing the Required Services (300 points)
E. Overall Evaluation of the Firm and its Perceived Ability to
Provide the Required Services (100 points)
F. Reference Check (75 points*)
Provide responses in the order listed in the RFQ
Be complete, be concise
Statement of Qualifications Criteria
26
All Firms MUST be registered in the Vendor Management
System to SUBMIT a Proposal
If your firm is already registered with the City of Phoenix’s
ProcurePHX system, to login and access the electronic
solicitation visit:
https://eprocurement.phoenix.gov/irj/portal
Product Category Code is: 912000000
RFx Number is: 6000000601
The VENDOR NUMBER is to be included on the cover of
the Statement Of Qualifications
Statement of Qualifications Submittal
27
Information Sheet (firm name, address, phone, contact
info, email, signature of contact person, vendor number,
project title & number, RFx number). Firm logo is optional.
Category code not required on the Information Sheet. Do
not include any additional information.
MAXIMUM pages permitted is 10 pages:
+ Evaluation Criteria (including organizational chart)
+ Additional Content = resumes or other information,
photos, charts / graphs or other evaluation content
= 10 MAXIMUM pages permitted
Statement of Qualifications Submittal (Cont.)
28
Each page side with criteria information will be counted.
Pages that have photos, charts, and graphs will be counted toward maximum number of pages.
Information Sheet, front and back covers, Table of Contents and tab dividers will NOT be counted toward the maximum page limit, UNLESS they include information that may be considered by the selection panel.
Statement of Qualifications Submittal (cont.)
29
Submit Electronically via ProcurePHX System:
https://eprocurement.phoenix.gov/irj/portal
SOQ and Form EO1 due:
12:00pm Noon – Arizona local time
Friday, September 7, 2018
Statement of Qualifications Submittal (cont.)
30
Each SOQ will be evaluated according to the evaluation
criteria in the RFQ
One contractor will be selected
A contract will be executed upon completion of
negotiations of contract terms and City Council approval
Selection Process
31
Failure to submit electronically through the
ProcurePHX online portal by the due date and time.
Violating “Contact with City Employees” policy.
Missing DBE Form EO1 and/or supporting
documentation (Exhibit C). Note: Please submit as a
separate electronic PDF.
Grounds for Disqualification
RFx Electronic Submittals
Log in to ProcurePHX portal:
https://eprocurement.phoenix.gov/irj/portal
Select RFx and Auctions tab on the Ribbon
You will be taken to the RFx (Event) Landing Page
RFx Electronic Submittals
Click the Refresh Button on the RFx (Event) Landing Page to see the most current information
Find the solicitation you’d like to view from the list, by RFx (Event) Number.
For this solicitation, your RFx (Event) Number is: 6000000XXX
RFx Electronic Submittals
The RFx (Event) Landing Page is also where you can find your saved RFx response.
Locate the desired RFx (Event) Number, and scroll to the right. You will see your RFx
response number shown as a hyperlink.
Click on the hyperlink, a new window will pop up to allow you to edit your RFx response.
RFx Electronic Submittals
Click the gray box next to the RFx (Event) Number you’d like to view. Then,
Click Display Event
This will open a new window to view the selected RFx
If you don’t see the new window, check your pop-up blocker
RFx Electronic Submittals
Update your Participation Status accordingly
Clicking Participate will allow you to get email notifications regarding your RFx Event, i.e. Notifications, New attachments.
Review RFx Information Tab for Start/Due dates/ Title of Solicitation
RFx Electronic Submittals
Click Create Response
Review Items Tab for
RFQ Evaluation Category
Yes/No questions
Review Notes and
Attachments Tab for
RFQ and Notifications
RFx Electronic Submittals
Click Create Response
Review Notes and
Attachments Tab for the
RFQ, Pre-Submittal
Presentation, Attendance
Sheet, and Notifications
RFx Electronic Submittals
Attach SOQ by clicking Add
Attachment
Click Browse in the pop up
window to navigate to the desired
attachment document
RFx Electronic Submittals
Once you’ve
selected your
document, add a
Description and
then click OK
The Summary Tab
provides a high-
level overview of
your RFx
Response
RFx Electronic Submittals
Click the CHECK button to ensure no system errors
Click the SUBMIT button to submit your RFx response
RFx Electronic Submittals
You will see a confirmation message that your response was
submitted
Click Close, and return to the RFx (Event) Landing Page
RFx Electronic Submittals
Click Refresh on the RFx (Event) Landing Page.
Locate the desired RFx (Event) Number, and scroll to the right.
Your Response Status should display as Submitted.
A Response Status of In Process, or Saved indicates you are still in edit mode,
and need to complete a step(s) before the system will update your RFxresponse to Submitted.
44
SOQ’s Due September 7, 2018
Scope Meeting November 2018
Selection Schedule
45
https://www.phoenix.gov/streets/procurement-opportunities
Current Opportunities – Project Specific RFQs / CFBs
Addenda / Notifications (if any)
Pre-Submittal Sign-in Sheet and Power Point Presentation
Project Interview Announcements
Awards / Results
Planholder List
Sign up for Procurement’s Weekly e-Newsletter
Bidders Handbook – Step-by-step Guide to RFx Submittals
The ProcurePHX online portal will be used for Professional
Services Solicitations
https://eprocurement.phoenix.gov/irj/portal
Procurement WEBPAGE
46
E-mail your questions to:
PROJECT TITLE:
AVIATION DEPARTMENT
T-2 CONCOURSE DEMOLITION AND APRON RECONSTRUCTION
CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES
PROJECT NOs. AV08000082 FAA & AV02000033
PROCUREPHX PRODUCT CATEGORY CODE 912000000
RFx 6000000601
Debra Russell, Contract Specialist – Team Lead
(602) 681-5317
OPEN FOR QUESTIONS&
Thank you for your interest in this project!!!
Questions After Today