Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra Prepared by: Perfact Envirosolutions (P) Ltd. New Delhi 17PREFEASIBILITY REPORT

Transcript of PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/... · [Indian Minerals...

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Envirosolutions (P) Ltd. New Delhi                                                                                                                  ‐17‐

     

     

       

    PRE‐FEASIBILITY REPORT

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Envirosolutions (P) Ltd. New Delhi                                                                                                                  ‐18‐

    1. EXECUTIVE SUMMARY Jammu & Kashmir along with Odisha, Meghalaya, Uttar Pradesh,  Jharkhand, Kerala, Bihar and Assam contributes  (6%) of the total  Indian deposit. Rajasthan was the  leading producing state accounting for (22%) of the total production of limestone, followed by Madhya Pradesh (12%), Andhra Pradesh (11%), Karnataka  &  Chhattisgarh  (9%  each),  Gujarat  &  Telangana  (8%  each),  Tamil  Nadu  (7%),  Himachal Pradesh & Maharashtra  (4%  each).  Limestone  produced  in  Jammu &  Kashmir  is  suitable  for  cement manufacturing. [Indian Minerals Yearbook 2016, 55th Edition] 

    The total reserves/resources of  limestone of all categories and grades as per NMI data based on UNFC system as on 1.4.2015 have been estimated at 203,224 Million Tons, of which 16,336 Million Tons (8%) are  placed  under  reserves  category  and  1,86,889 Million  Tons  (92%)  are  under  remaining  resources category. [Indian Minerals Yearbook 2016, 55th Edition]  

    Project Description 

    The proposal is for semi‐mechanized collection of limestone mineral from Pulwama District of J&K. The lease of lime stone was granted in favor of Mr. Riaz Ahmad Panjra in an area of 29.4151 ha falling under Khasra  No.  3450‐Min,  3498‐Min  and  3499‐Min  by  the  Government  of  Jammu  and  Kashmir  on 28.03.2002 and lease agreement was executed on 09.09.2002. The lease will be valid for 50 years from the date of grant i.e. up to 08.09.2052 as per MMDR Act 2015. It is a captive mine to the lessee’s own cement plant M/s Cemtac Cement Pvt. Ltd adjoing  lease area. The Cement Plant  is  located at Sulnar, Satur Marg, Khrew, Pulwama Jammu and Kashmir. (Lease deed Annexure‐1)  

    First Mining Plan was approved vide letter no. 614(2)/MP‐B‐135‐2001‐DDN dated 17.05.2000.  The latest review & updation of mining plan in respect of limestone mine was approved vide File 

    no.‐614(2)/MP‐B‐135/2000‐DDN  Dated  26/10/2016.  (Copy  of  mining  plan  approval  letter enclosed as Annexure II). 

    Maximum annual proposed production from the limestone mine is 0.12 Million Tons.  

    M/s Cemtac Cement Pvt. Ltd had applied for grant of EC to MoEF & CC for both Cement Plant expansion and extraction of limestone for the cement plant in an area 29.4151 ha. The ToR was granted by MoEF & CC vide  letter no. J‐11011 /226/2012‐IA.II (I) dated 11th February 2013 for expansion of cement plant. The Public hearing was conducted on 2nd may, 2013 at Khrew, Tehsil‐ Pampore, District‐ Pulwama under the  chairmanship of Additional District Magistrate  Pulwama.  The proposal was  considered by  Expert Appraisal Committee in its 43rd EAC meeting held during 2nd ‐3rd July,2015 and 47th meeting held on 3rd ‐4th September, 2015. 

    In  the  43rd  EAC meeting  the  committee  desired  additional  information  on  the  following  for  further consideration of the proposal: 

    i. EC for mine to be obtained. 

    ii. 1 month baseline data should be collected and submitted. 

    In  the  47th  meeting  of  EAC  the  PP  vide  letter  dated  13th  August,  2015  submitted  the  additional information as desired by the Committee. It was mentioned that they had yet to apply for environment clearance for the mining project. However, they had conducted PH for both mine and cement project. As per minutes of aforementioned 47th meeting, PH conducted will remain valid for both cement plant 

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐19‐ 

    and  mines.  Further,  the  Ministry  of  Environment,  Forest  and  Climate  Change  had  considered  the application based on  the recommendations of the Expert Appraisal Committee  (Industry) and  thereby decided to grant Environmental Clearance to the proposal of Expansion of Cement Plant. 

    As mentioned earlier,  the existing mining  lease was accorded  to  the PP  in  the year 2002,  the mining activity started in the year 2003 over 29.4151 ha of land without EC, considering mining project to be a minor mineral project. However, since the mining activity is carried out for use in the cement plant, the mining comes under the major mineral project and attracts EIA Notification. Hence, the case falls under violation category.  No litigation/court case is pending pertaining to the project. 

    A ToR Vide  letter No J‐11015/25/2016‐IA.II  (M) Dated 08.02.2016 was  issued to Project Proponent for extraction of limestone from the lease area 29.4151 ha. The EIA was under preparation and in the mean time  notification  vide  S.O.  804(E)  dated  14.03.2017  was  published.  Accordingly,  a  fresh  ToR  under villation category is being submitted herewith. 

    It has been observed that the PP has not taken EC  for mining project and started mining  in 2003 and continued up  to 2017 on  lease area. The circular of MoEF&CC vide No.  J‐20012/11/98‐  IA.II(M) dated 28.10.2004, quoted below: 

    The EIA Notification, 1994 as amended from time to time shall include: (i) Mining projects of major mineral with more than 5ha  lease area, which have started production or increased their production and/or lease area on or after 27.01.1994. 

    (ii) In addition, all mining projects of major minerals of more than 5 ha  lease area which have so far not obtained an environmental clearance under the EIA Notification, 1994 shall do so at the time of renewal of  their  lease  in  the context of  the SC  Judgment dated 18.03.2004  in W.P. 4677/1985– M.C. Mehta vs UOI & Ors. 

    Since lease was granted in 2002 and mining activity started in 2003 without obtaining EC as per circular as mentioned above, therefore it comes under violation category. Damage Assessment & Remediation plan on account of Violation: Under the aegis of EPA Act 1986, EIA Notification 2006 and amendments thereafter, Violation Notification vide S.O. 804(E) dated 14.3.2017 and based on  the specific  Terms of Reference prescribed by  Expert Appraisal Committee,  a  separate chapter will be included in the EIA report wherein, assessment of ecological damage done by the project will be discussed. Subsequently, a remediation plan and natural and community resource augmentation plan will be given in the said chapter. As per the notification, the data collection and analysis of data for assessment of ecological damage, preparation of remediation plan and natural and community resource augmentation plan will be done by Environmental laboratory duly accredited by National Accreditation Board for Testing and Calibration Laboratories. Here it may be worthwhile to mention that subsequent to aforementioned notification dated 14th March 2017, honorable Supreme Court passed an order for violation cases of mining for depositing the penalty based on the quantum of production done during the period of violation. The status of mining projects under violation appears to be in a flux for the time being.   The proposal  is  considered under Category  “A”  as  the mining  lease area of 29.4151 ha  situated at a distance of 4.85 km  from Dachigam National Park,  in addition  it  falls under  the category of  ‘Violation Cases’. 

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐20‐ 

    The  lease area falls  in Khasra No. 3450 Min, 3498 Min and 3499 Min Village Sulnar Satur Marg Khrew, Tehsil‐ Pampore & District‐ Pulwama (J&K) between the latitude is 34o02'07.11"N to 34o02'30.34" N, and longitude 75o01'51.83"E  to 75o02'41.20"E. The area  falls  in  the Survey of  India Topo‐sheet no.43 N/4 (OSM sheet no. I43J4). The  leasehold area displays an undulating  topography. The maximum and minimum elevations  in  the lease are 2101.50 m RL and 1881.20m R respectively. The lease area is non‐forest government land. The lease was granted to the company for an area of 29.4151 ha on 09.09.2002 and validity of lease is for 50 years as per MMDR Act 2015 The Approved review and updation of Mining Plan from IBM for the production of 0.12 Million Tons per annum of Limestone was  issued vide  letter no. 614(2)/MP‐B‐135/2000‐DDN, Dated: 26 October 2016. The PP exploited 0.16 Million Tons limestone from 01‐10‐2003 to 30‐09‐2017. 

    During next five years, mining shall be carried out in two pits. The mining shall be carried out from top to downward through the formation of benches. No soil shall be generated due to advancement of mining faces.  Small  quantities  of waste  shall  be  generated &  it  shall  be  spread  over  the  haul  roads  for  its maintenance. The mineable reserve estimated at about 45.73 Million Tons. The life of mine is about 365 years. Method adopted will be semi‐mechanized open cast mining with small scale drilling and blasting as  per  need  for  breaking  the  harder  rock.  Drilling  equipment  which  may  use  are  jack  hammer, compressor, excavator, and tippers. During mining there will be about 15 KLD water required per day at peak demand. The maximum strength of direct workers will be 174 majority will be hired locally. Besides there will be indirect employment on account of transportation, canteen, repair shop, security etc. The project cost is about Rs. 2.0 cr.  

     

     

     

     

     

     

     

     

     

     

     

     

     

     

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐21‐ 

    2. PREFEASIBILITY REPORT Introduction of Project—Background information 

    Jammu & Kashmir along with Odisha, Meghalaya, Uttar Pradesh,  Jharkhand, Kerala, Bihar and Assam contributes  (6%)  of  the  total  Indian  limestone  deposits.  Rajasthan was  the  leading  producing  state accounting for (22%) of the total production of limestone, followed by Madhya Pradesh (12%), Andhra Pradesh (11%), Karnataka & Chhattisgarh (9% each), Gujarat & Telangana (8% each), Tamil Nadu (7%), Himachal Pradesh & Maharashtra  (4% each). Limestone produced  in  Jammu & Kashmir  is suitable  for cement manufacturing. [Indian Minerals Yearbook 2016, 55th Edition] 

    The total reserves/resources of  limestone of all categories and grades as per NMI data based on UNFC system as on 1.4.2015 have been estimated at 203,224 Million Tons, of which 16,336 Million Tons (8%) are  placed  under  reserves  category  and  1,86,889 Million  Tons  (92%)  are  under  remaining  resources category. [Indian Minerals Yearbook 2016, 55th Edition]  

    Project Description 

    The proposal is for semi‐mechanized collection of limestone mineral from Pulwama District of J&K. The lease of lime stone was granted in favor of Mr. Riaz Ahmad Panjra in an area of 29.4151 ha falling under Khasra  No.  3450‐Min,  3498‐Min  and  3499‐Min  by  the  Government  of  Jammu  and  Kashmir  on 28.03.2002 and lease agreement was executed on 09.09.2002. The lease will be valid for 50 years from the date of grant i.e. up to 08.09.2052 as per MMDR Act 2015. It is a captive mine to the lessee’s own cement plant M/s Cemtac Cement Pvt. Ltd adjoing  lease area. The Cement Plant  is  located at Sulnar, Satur Marg, Khrew, Pulwama Jammu and Kashmir. (Lease deed Annexure‐1)  

    First Mining Plan was approved vide letter no. 614(2)/MP‐B‐135‐2001‐DDN dated 17.05.2000.  The latest review & updation of mining plan in respect of limestone mine was approved vide File 

    no.‐614(2)/MP‐B‐135/2000‐DDN  Dated  26/10/2016.  (copy  of  mining  plan  approval  letter enclosed as Annexure II). 

    Maximum annual proposed production from the limestone mine is 0.12 Million Tons.  

    M/s Cemtac Cement Pvt. Ltd had applied for grant of EC to MoEF & CC for both Cement Plant expansion and extraction of limestone for the cement plant in an area 29.4151 ha. The ToR was granted by MoEF & CC vide  letter no. J‐11011 /226/2012‐IA.II (I) dated 11th February 2013 for expansion of cement plant. The Public hearing was conducted on 2nd may, 2013 at Khrew, Tehsil‐ Pampore, District‐ Pulwama under the  chairmanship of Additional District Magistrate  Pulwama.  The proposal was  considered by  Expert Appraisal Committee in its 43rd EAC meeting held during 2nd ‐3rd July,2015 and 47th meeting held on 3rd ‐4th September, 2015. 

    In  the  43rd  EAC meeting  the  committee  desired  additional  information  on  the  following  for  further consideration of the proposal: 

    i. EC for mine to be obtained. 

    ii. 1 month baseline data should be collected and submitted. 

    In  the  47th  meeting  of  EAC  the  PP  vide  letter  dated  13th  August,  2015  submitted  the  additional information as desired by the Committee. It was mentioned that they had yet to apply for environment 

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐22‐ 

    clearance for the mining project. However, they had conducted PH for both mine and cement project. As per minutes of aforementioned 47th meeting, PH conducted will remain valid for both cement plant and  mines.  Further,  the  Ministry  of  Environment,  Forest  and  Climate  Change  had  considered  the application based on  the recommendations of the Expert Appraisal Committee  (Industry) and  thereby decided to grant Environmental Clearance to the proposal of Expansion of Cement Plant. 

    As mentioned earlier,  the existing mining  lease was accorded  to  the PP  in  the year 2002,  the mining activity started in the year 2003 over 29.4151 ha of land without EC, considering mining project to be a minor mineral project. However, since the mining activity is carried out for use in the cement plant, the mining comes under the major mineral project and attracts EIA Notification. Hence, the case falls under violation category.  No litigation/court case is pending pertaining to the project. 

    A ToR Vide  letter No J‐11015/25/2016‐IA.II  (M) Dated 08.02.2016 was  issued to Project Proponent for extraction of limestone from the lease area 29.4151 ha. The EIA was under preparation and in the mean time  notification  vide  S.O.  804(E)  dated  14.03.2017  was  published.  Accordingly,  a  fresh  ToR  under villation category is being submitted herewith. It has been observed that the PP has not taken EC  for mining project and started mining  in 2003 and continued up  to 2017 on  lease area. The circular of MoEF&CC vide No.  J‐20012/11/98‐  IA.II(M) dated 28.10.2004, quoted below: The EIA Notification, 1994 as amended from time to time shall include: (i) Mining projects of major mineral with more than 5ha  lease area, which have started production or increased their production and/or lease area on or after 27.01.1994. 

    (ii) In addition, all mining projects of major minerals of more than 5 ha  lease area which have so far not obtained an environmental clearance under the EIA Notification, 1994 shall do so at the time of renewal of  their  lease  in  the context of  the SC  Judgment dated 18.03.2004  in W.P. 4677/1985– M.C. Mehta vs UOI & Ors. 

    Since lease was granted in 2002 and mining activity started in 2003 without obtaining EC as per circular as mentioned above, therefore it comes under violation category. 

    Damage Assessment & Remediation plan on account of Violation: Under the aegis of EPA Act 1986, EIA Notification 2006 and amendments thereafter, Violation Notification vide S.O. 804(E) dated 14.3.2017 and based on  the specific  Terms of Reference prescribed by  Expert Appraisal Committee,  a  separate chapter will be included in the EIA report wherein, assessment of ecological damage done by the project will be discussed. Subsequently, a remediation plan and natural and community resource augmentation plan will be given in the said chapter. As per the notification, the data collection and analysis of data for assessment of ecological damage, preparation of remediation plan and natural and community resource augmentation plan will be done by Environmental laboratory duly accredited by National Accreditation Board for Testing and Calibration Laboratories. Here it may be worthwhile to mention that subsequent to aforementioned notification dated 14th March 2017, honorable Supreme Court passed an order for violation cases of mining for depositing the penalty based on the quantum of production done during the period of violation. The status of mining projects under violation appears to be in a flux for the time being.   

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐23‐ 

    The proposal  is  considered under Category  “A”  as  the mining  lease area of 29.4151 ha  situated at a distance of 4.85 km  from Dachigam National Park,  in addition  it  falls under  the category of  ‘Violation Cases’. The lease area falls in Khasra No. 3450 Min, 3498 Min and 3499 Min Village Sulnar, Satur Marg, Khrew Tehsil‐ Pampore, District‐ Pulwama (J&K) between the latitude is 34o02'07.11"N to 34o02'30.34" N, and longitude 75o01'51.83"E  to 75o02'41.20"E. The area  falls  in  the Survey of  India Topo‐sheet no.43 N/4 (OSM sheet no. I43J4).  The  leasehold area displays an undulating  topography. The maximum and minimum elevations  in  the lease are 2101.50 m RL and 1881.20m R respectively. The lease area is non‐forest government land. The lease was granted to the company for an area of 29.4151 ha on 09.09.2002 and validity of lease is for 50 years as per MMDR Act 2015. The Approved review and updation of Mining Plan from IBM for the production of 0.12 Million Tons per annum of Limestone was  issued vide  letter no. 614(2)/MP‐B‐135/2000‐DDN, Dated: 26 October 2016. The PP exploited 0.16 Million Tons limestone from 01‐10‐2003 to 30‐09‐2017.  During next five years, mining will be carried out in two pits. The mining will be carried out from top to downward through the formation of benches. No soil will be generated due to advancement of mining faces.  Small  quantities  of  waste  will  be  generated  &  it  will  be  spread  over  the  haul  roads  for  its maintenance. The mineable reserve estimated at about 45.73 Million Tons. The life of mine is about 365 years. Method adopted will be semi‐mechanized open cast mining with small scale drilling and blasting as per need for breaking the harder rock. Drilling will be done by jack hammer, other equipments which will  be  used  include  compressor,  excavator,  and  tippers. During mining,  about  15  KLD water will  be required per day during peak demand periods. Need of the Project: There  is a growing demand of Cement  in the country. Production from the mine, will  be  used  in  their  own  plant M/s  Cemtac  Cements  Pvt.  Ltd.  The  project will  generate  direct  and indirect  employment which will  help  in  escalating  socio‐economic  growth  in  the  area.  The  strategic importance of cement plant increases in view of the fluid situation in J&K. 

    Demand‐Supply Gap: 

    Growth  in consumption of mineral  in cement plant  is taking place  in the country; therefore, there will always be demand of limestone in the country. The mined out mineral shall be used as a raw material in their own cement plant. At present the cement industry is experiencing a sort of boom due to thrust in infrastructure sector. 

    Imports vs. Indigenous production 

    There will be no import of limestone produced from the mine. Entire limestone will be consumed in the PP’s own cement plant. 

    Export Possibility 

    Since entire limestone will consumed in their cement plant hence there is no export possibility. 

    Domestic/ export Markets 

    Entire  limestone  from  the mine will  be  consumed  domestically  in  their  cement  plant.  No  export  is proposed. 

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐24‐ 

    Employment Generation:  The maximum strength of direct workers will be 174. Majority of them will be hired locally. Besides direct employment, substantial amount of indirect employment will be generated in the form of dhabas, transporters, repair shops etc. which will improve the economic conditions of the area. 

    3. PROJECT DESCRIPTION Type of Project: Present proposal pertains to mining of Limestone mineral  in 29.4151 ha  in vill Sulnar, district  Pulwama,  J&K.    The  project  is  located  at  4.85  Km  S  from  Dachigam  National  park  hence categorized  as  category  A  for  obtaining  the  environmental  clearance  as  per  EIA  notification  2006. Location of mine is given ahead. This is an opencast semi‐mechanized mine with small scale drilling and blasting. Maximum annual proposed production is 0.12 Million Tons. (Location Plan is at Annexure V) 

    Interlinked Projects: 

    It is a captive mine of limestone mineral for a cement plant. 

       

       

     

    Lease Details: 

    Name of the company    : M/s. Cemtac Cements Pvt. Ltd. 

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐25‐ 

    Name of Authorized person  : Mr. Riaz Ahmad Panjra 

    Designation      : Owner 

    Status of lessee          : Private Company 

    Address                : vill Sulnar Satur Marg  Khrew, Tehsil‐ Pampore, District‐ Pulwama, J&K 

    Lease Area              : 29.4151 Hectares 

    Date of Grant           : 09.09.2002 

    Location             :  Latitude    34o02'07.11"N to 34o02'30.34"N 

               Longitude 75o01'51.83"E to 75o02'41.20"E 

    The area falls in the Survey of India Topo‐sheet no.43 N/4 (OSM sheet no. I43J4). 

    Village‐ Sulnar Satur Marg Khrew, Tehsil‐Pampore, District‐ Pulwama, J&K 

     

      

    Details of Alternate Sites  

    The mining of limestone for the cement plant is site specific and is dependent on availability of mineral and grant of mining lease by the State Government. In the present case PP has been granted the lease of 

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐26‐ 

    limestone  having  area  29.4151  ha  at  village  Sulnar  Satur  Marg  Khrew  Tehsil‐  Pampore,  District‐ Pulwama, Jammu & Kashmir. Therefore, no alternative site has been considered. 

    Magnitude of operation: 

    The  mining  lease  has  been  granted  over  an  area  of  29.4151  ha.  It  has  been  proposed  to  extract limestone to the tune of 0.12 Million Tons Per Annum. The average number of working days in the year would be 250. 

    Project description with process details 

    Past  Production:    There  has  been  past  production  during  2003‐2017.  As  per  details  of  dispatch  of limestone from Government of Jammu and Kashmir Department of Geology and Mining, Srinagar vide letter no. MJM/DGM/Sgr/F‐28/498 Dated 08‐02‐2018. The letter is enclosed as Annexure IV 

    S. No.  Period  Dispatches (Tons) 

    01  2003 to 2004  120 

    02  2004 to 2005  32 

    03  2005 to 2006  220 

    04  2006 to 2007  1670 

    05  2007 to 2008  2680 

    06  2008 to 2009  6872 

    07  2009 to 2010  4525 

    08  2010 to 2011  6321 

    09  2011 to 2012  11940 

    10  2012 to 2013  12000 

    11  2013 to 2014  33519.89 

    12  2014 to 2015  21958 

    13  2015 to 2016  25054 

    14  2016 to 2017  35295 

      G. Total  162206.89 

    PP has taken consent from SPCB on 18.02.2017. The consent letter is enclosed as Annexure III 

     

    Proposed Production: This is a new mine. The Proposed production of limestone mine will be 0.12 Million Tons. 

    Year  Soil (Cum)  Exploitation of Limestone 

    (Million Tons) 

    Total Exploitation of 

    Sub grade 

    (Million 

    Inter‐burden 

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐27‐ 

    Pit‐1  Pit‐2  Limestone 

    (Million Tons) 

    Tons)  (Cum) 

    1st year  Nil  0.023940  0.057855  0.081795  ‐  Nil 

    2nd year  Nil  0.033345  0.068713  0.102058  ‐  Nil 

    3rd year  Nil  0.038760  0.078375  0.117135  ‐  Nil 

    4th year  Nil  0.041610  0.079002  0.120612  ‐  Nil 

    5th year  Nil  0.052012  0.073388  0.125400  ‐  Nil 

    Total    0.189667  0.357333  0.547     

     

    The Surface & Geological Plan and the conceptual plan are shown as Annexure‐VII, VIII & IX. 

    Equipment: The mine will be worked by opencast semi mechanized method. Mineral shall be exploited with  the  adoption  of  drilling  and  blasting  as  per  need  for  breaking  the  harder  rock.  ROM  will  be transported  by  trucks/tippers  to  their  own  cement  plant  and  consumer.  List  of  equipments  is  given below — 

    Type  Make & Model  Capacity  Fleet 

    i) Excavator  Tata Hitachi & Ex 200  150 HP  1 No. 

    ii) Compressor  Atlas CApco, XA175 450cfm  125 HP  1 Nos. 

    iii) Tippers  Tata, 112 HP  10 tons  10 Nos. 

    iv) Jack Hammer  Atlas Cipco  300 cfm  4 Nos. 

     

    Salient Features of the proposed Working:   Semi‐mechanized open cast mining with jack hammer drilling & blasting   The area is rocky having no soil cover, therefore, generation of top soil will be negligible.    Mining is proposed from upper level to lower levels. The height & width of benches will be kept 

    6.0m & 5.0 to 6.0m respectively. Approach road having width 6.0m & gradient 1:16 will be provided to join the mining faces. 

    No. of working day will be 250.  Total no. of direct employment is about 174(skilled, semi‐skilled and unskilled.)  During mining water table is not likely to get intersected.  ROM will be excavated by manual method or by excavator and sent to consumer by trucks/tippers.  

    Raw Materials: 

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐28‐ 

    The important inputs required for mining of desired quantity of ore are given below.  

    Inputs  Approx Quantity required  

    Water for Drinking & Domestic  8KLD 

    Water for Sprinkling and allied activities & Plantation  7 KLD 

     

    Market and Mode of Transport: The ore produced from this mine will be used  in their own plant as a raw material and sent to their own cement plant by trucks/tippers. 

    Resource Optimization/Recycling: The entire lease area is rocky terrain having no soil cover, therefore, generation of  top  soil  shall be negligible. Small quantities of waste  shall be generated & used  in  the backfilling of the pit or maintenance of haul road.   

    Requirement  of  Water,  Energy/Power:  The  water  will  be  used  for  drinking  purpose,  wet  drilling, sprinkling and plantation. Domestic water requirement will be 8 KLD approx.  Water for sprinkling, dust suppression in the lease and green belt development in the areas will be about 7 KLD. Thus, there will be total  requirement of 15 KLD water  (at peak demand). Water will be  sourced  from  their own  cement plant. Electricity shall not be required as this is a semi‐mechanized mine and work will be carried out in day time. All equipments are diesel driven. 

    Waste Generation and Disposal: The area is stony topography having no soil cover therefore generation of top soil shall be nil. Small quantities of waste shall be generated due to advancement of mining faces & it shall be used for maintenance of haul roads therefore no such proposal has been envisaged for its separate dumping. 

    4. SITE ANALYSIS:  Location and Connectivity of the lease is given as under: 

    Location and Connectivity: The area falls  in the Survey of  India Topo‐sheet no.43 N/4 (OSM sheet no. I43J4). The  lease area  is non‐forest government  land. The  latitude  is 34o02'07.11"N to 34o02'30.34" N, and  longitude 75o01'51.83"E  to 75o02'41.20"E marks  the  lease area. There  is one eco‐sensitive  areas namely; Dachigam National park at a distance of 4.85 km N. NH 1A is 10.67 km SSW from the mine  lease. The nearest railway station is  in Pampur about 13.40 Km SWW and Kakapore railway station about 14.46 km SW from the lease area. The location plan is shown in Annexure V and 10 Km buffer zone area at Annexure VI  Land use and Land ownership:    It  is a government  land,  involving 29.4151 ha. Land  is mainly rocky and barren with a few patches of grazing area. The details of existing and proposed land use are given below —  

    S.NO.  Activities  As on date (in ha) 

    At the review of M.P. (in ha) 

    At conceptual stage (in ha) 

    1  Pits and Quarries  

    1.34 1.50 

    21.85 (4 ha plantation including dump) 

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐29‐ 

    2  Waste dumps  Nil  Nil  Nil 3  Approach Road  0.294  Nil  Nil 4  Reclamation/rehabilitation  by 

    plantation  including  dump and 7.5m boundary 

    Nil  Nil  7. 5651 

    5  Infrastructure  such  as  office building etc. 

    Nil  Nil  Nil 

      Total  1.634  1.50  29.4151 

      

     

      

    Topography  of  the  area:  The  topography  is  rough  and  rugged  representing  the  typical  scenario  of mountainous region. The maximum and minimum elevations in the lease are 2101.50 mRL and 1881.20 mRL respectively. The lease area is non‐forest government land. The leasehold towards western side is 

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐30‐ 

    occupied by a prominently marked  ridge  trending  from east  to west whereas on eastern  side  shows uniform distribution of ridges and valleys trending between south‐west and north‐east. 

    Drainage: Ephemeral nala exists outside  the  lease area  in village‐Sulnar  is about 300m away  towards south west direction of proposed mining area. 

    Geology of the area: Regional and Local Geology of the area is briefly described as under: Regional Geology: The geological formation of the area in order of their natural sequence from top to bottom area as follows: Sl. No.  Formation  Age 

    1.  Recent deposits, scree, talus and clay  Recent 2.  Karewas (clay, silt, and sand)  Pleistocene 3.  Triassic formations 

    a) Upper (predominantly calcareous) b) Middle (calcareous & Argillaceous) c) Lower (siliceous & calcareous) 

    Triassic 

    4.  Zewan series‐ Bottom argillaceous top calcareous  Permian 5.  Panjal traps  Permocarboniferous  Local  Geology:  The  limestone  of  the  area may  be  correlated  with  the  upper  Triassic  formation  of regional geology. Limestone: The limestone shows some minor gradational changes from argillaceous to siliceous to calcareous, due to nearness of Panjal traps. The beds have undergone minor folding puckering put the general behavior of the bedding plane is normal. The limestone deposit belongs to upper Triassic formation. The main rocks in the area and surroundings are limestone, siliceous limestone and quartzites. The limestone shows colour variation both along and across  the strike. The general strike of  the  rock  formation varies  from 290 deg.  to 295 deg. with dips ranging from 59 deg. – 62 deg. and direction of dip is varies from 20deg N to 25 deg N. 

    i) Upper Limestone: The limestone occurs towards northern flank of lease area. The limestone  is fine to medium grained, grey to dark grey  in colour, massive & well  jointed. Three sets of joints are seen within high grade  limestone. The cement of CaO varies 50.02% to 51.80%, SiO2 varies 1.98% to 2.02%, MgO Varies 1.36% to 1.70%. 

    ii) Middle  Limestone:  Fine  Grained  dark  grey  colour  limestone  bed  underlying  high  grade limestone. The hanging wall  contact of  limestone  is high grade  limestone while  foot wall contact  is  siliceous grade  limestone. The CaO varies 48%  to 49.70%,  SiO2 varies 2.40%  to 2.52% & MgO varies 1.46% to 1.82%. 

    iii) Lower  Limestone: The band of  limestone occurs below middle  limestone band. Hanging wall contact  is middle grade  limestone while foot wall contact  is not exposed. The Cao content varies 46.70% to 48.58%, SiO2 varies 3.08% TO 4.08%, & MgO varies 1.58% to 1.68%. 

      

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐31‐ 

    Structure: Limestone band forms the western limb of the plunging anticline. The corresponding eastern limb of the anticline  is  represented  by  the  hillocks  covering Hingpora Dudawagan  to  Punzoo  Batapora  belt  and Sandram nala  is flowing almost through the axis of the anticline. Moderate to steep dips (in slope) on either side of sandram valley.  Exploration:    In the past area is exposed by mining pits & depth of pits from 6m to 20m & limestone bearing strata is exposed in the pit. Apart from this exploration by means channels have been carried out & occurrence of  limestone has been established  in the  lease area. However, four trial pits having dimension of 5m x 5m x 5m will be dug  towards southern  flank & western  flank. Apart  from  this,  two DTH holes will be drilled to ascertain grade, strike continuity & depth persistence of mineral.   Quality & Grade  of Mineral:  The  CaO  content  up  to  46.70% &  SiO2  content  up  to  4.08%  has  been considered as cut off grade & called as Cement Grade. 

    Reserves: The mineable reserve estimated at about 45.73 Million Tons as on date which will  increase after further exploration carried out after obtaining Environmental Clearance. Life  of Mine:  It  is  about  365  years,  Considering Maximum  production @0.12 Million  Tons/  annum. Further  exploration will  be  carried  out  in  future  depending  upon  the  cement  requirement  trend  in future.  

    Sensitivity of Location: 

    The nearest water body  is tributary of  Jhelum river about 2.20 km E and Jhelum river  is 10.81 Km SWW from the mining lease. 

    There is Dachigam National Park at 4.85 Km N to the lease boundary.  The lease area lies in the seismic zone V. 

    The nearest settlement is Khrew at 3.56 km SW.  

     

    Existing Infrastructure:  The  area  is  connected with  all  season motor  roads.  The  nearby  villages  are electrified.  

    Soil classification: The area proposed for mining is rocky terrain having almost devoid of soil cover. Climatic Data from Secondary sources:  The  South‐West monsoon  changes  its direction  to North‐East along  the  lesser Himalayas due  to E‐W trending  syn‐axial  bend  of  the  north‐eastern  Himalayas.  As  the  Pirpanjal  ranges  run  parallel  to  the direction of rain bearing monsoon, there is relatively less rainfall as compared to the eastern India, due to the obstruction of hill. The maximum temperatures in the buffer zone vary from 32O C to 35o C in the month of June and the minimum temperature vary between ‐1o C to 8o C in January. Humidity during the year varies between 40.0%  to 85% avg. Months of  January, February, March and  July  to October are comparatively more humid than other months. 

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐32‐ 

    Social  Infrastructure Available: Nearest Public Health Centre  is  located  in Wuyan at  about 5 Km  SW from  this mining  lease area. All other  community  facilities  like Post office, ATM, are also available  in Wuyan. Police Station and other few facilities are available in Khrew in SW direction from the lease area. 

    5. PLANNING BRIEF Planning Concept 

    Proposed project  is an open cast semi‐mechanized mining with small scale drilling and blasting as per need using jack hammer, excavator, compressor and tippers etc. 

    Population Projection 

    There will be employment to about 174 persons in the mine (skilled, semi‐skilled and unskilled). Most of the  labor will be employed from nearby villages hence there will be  insignificant  impact  in  increase of population.  

    Land use planning 

    Mined out area shall be backfilled with interburden & sub soil shall be carpeted over it to bring back its maximum original topography. There will be plantation in the statutory 7.5 m barrier along with benches of the pit 

    Assessment of Infrastructure Demand 

    The proposed mining activity will produce cement. There will be construction of temporary structures such as mine office, rest shelters, store etc. as per approved mine plan. 

    6. PROPOSED INFRASTRUCTURE Industrial Area: It is a captive mining project of a cement plant. The limestone excavated will be directly supplied to cement plant, no industrial area is proposed within leasehold.  

    Residential Area: As most of workers are employed from nearby villages, no residential area/ housing is proposed. 

    Physical Infrastructure: The proposed mining activity will produce limestone for PPs own cement plant. There will be construction of temporary structures such as mine office, rest shelters, store etc. as per approved mine plan. Green Belt/Afforestation: 

     

    Proposed Plantation: Plantation shall be undertaken with  in 7.5m barrier zone. The plantation  raised earlier should be carefully maintained & mortalities should be replaced by fresh planting. 

    Year  Over 7.5m strip  Plantation 

    1st year  0.05  50 

    2nd year  0.05  50 

    3rd year  0.05  50 

    4th year  0.05  50 

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐33‐ 

    5th year  0.05  50 

    Total  0.25  250 

     

    Besides above, Benches after rehabilitation will be reclaimed through plantation, in addition, plantation will be undertaken in surrounding area in consultation with community. 

    Social Infrastructure: Due to  initiation of mining project there will be an overall development  in social infrastructure as a result of indirect employment. 

    Drinking Water Management (Source & Supply of Water): 

    Domestic water requirement will be approx 8 KLD, Water for sprinkling & dust suppression and green belt development about 7 KLD. Thus, there will be total requirement of 15 KLD water (at peak demand). Water will be sourced from their own cement plant.  

    Solid  Waste  Management:  The  top  soil  is  very  less  in  the  area.  Mining  shall  be  carried  out  in homogeneous grade of  limestone having small quantities of waste. All quantities shall be spread over the  haul  roads  for  its maintenance  and  used  in  Plant  as  subgrade.  Remaining waste will  be  used  in reclamation of mined out area.  

    Power Requirement: No electricity is required for limestone mine. Work will be carried out in day time. All equipments are diesel driven. 

    Supply/Source of Energy: Overall average diesel consumption will be 800 L/day. 

    7. REHABILITATION AND RESETTLEMENT (R &R) PLAN:  The mining lease encompasses about 29.4151 ha area which consists of limestone. Entire lease area falls in Government  land  for which  land will be  acquired by  giving mutually  agreed  compensation  to  the Government. No rehabilitation and resettlement will be needed. 

    8. ENVIRONMENT MANAGEMENT PLAN  Mining  operations mainly  contribute  to  generation  of  dust  for  which  sprinkling  of  water  is 

    proposed.  Vegetative barrier is proposed for dust suppression.  All the equipment’s will be of highest standard of reputed make and adhered to  international 

    standards.   Groundwater table is not going to be intersected throughout the future mining.  Maintenance of approach road will be done regularly.  Benches  shall be  rehabilitated by planting  local  species  in place of  existing  rocky  and barren 

    land.  As  the  lease  area  fall  in  the  seismic  zone V which  is high  risk  area,  therefore, precautionary 

    measures will  be  adopted.  Light  structured houses will  be  constructed  in place  of  cemented houses  in and around  the area,  fast growing  soil binding  species will be planted & cemented bunds will be made at the lower side to minimize damage. 

    Labors will be made aware of the ways of clean and green environment. 

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐34‐ 

    9. ASSESSMENT OF ECOLOGICAL DAMAGE, REMEDIATION PLAN AND NATURAL AND COMMUNITY RESOURCE AUGMENTATION PLAN 

    The proposal  is being submitted to MoEF&CC under violation Notification S.O. 804(E) dated 14.3.2017. Therefore, a separate chapter will be added for assessment of Damage/Compensation.  

    Mining  is an activity, which produces a definite  impact on environment. Fortunately, one of the major activity. Proposed project is an open cast semi‐mechanized mining with small scale drilling and blasting as per need. However, during the excavation and transportation dust and noise is likely to be generated. The water  table  in  the  lease area  is about 1116 mRL and  the ultimate depth of pit will be 1874mRL. Hence  it  is not going  to be  intersect  throughout  the  future mining. Though  the nature of  impact will remain temporary in this mining activity as the excavated area shall be backfilled with interburden and sub soil/soil shall be carpeted over it to bring back its maximum original topography. The overall impact on air, water, noise, soil and  land environment will be assessed. In addition,  it will be weighed against the  positive  impact  created  on  the  socioeconomic  scenario.  To  estimate  the  impact  produced  a framework  has  been  designed.  The  framework  or methodology  to  be  used  for  the  purpose  is  given ahead — 

    Methodology for Estimation of Impact of Activity created during Violation Period:  The first part of the damage assessment will include — 

    The  place  of  activity  is  permissible  for  the  purpose  (like  it  should  fall  in  sensitive  zones  like Aravali notified area, etc.) 

    Environmental Sensitivity to be clearly defined  Status  of  activities  (in  quantitative  terms)  undertaken  during  violation  period  and  extent  of 

    damage o Criteria to be used (given in the table ahead) 

    Status of deterioration of environmental parameters  o Criteria to be used o Impact on Air Quality 

    To be compared by a nearby control area as well as anticipated pollution  load during activity/construction, if any. 

    o Impact on Water Quality  To be compared by a nearby control area as well as anticipated pollution  load 

    during activity/construction, if any. o Impact on Noise Quality 

    To be compared by a nearby control area as well as anticipated pollution  load during activity/construction 

    o Impact on Land Environment  Extent of land excavation  Estimated loss of top soil in cum  No.  of  trees  cut with  details  of  their  sizes  like  girth  length  and  approximate 

    weight, etc. o Impact on Socio Economic Scenario 

    Negative  impact  like  increase  pollution  load,  vibration  and  public inconveniences  

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐35‐ 

    Positive  impact  in  terms  of  increased  income  due  to  employment,  or  other ancillary activities. Also benefits generated due  to activities undertaken under corporate social responsibility   

    The subsequent part of the report will include — 

    Remediation Plan including following: o Control measures for preventing deterioration of air quality along with approximate cost o Control measures for preventing deterioration of noise quality along with approximate 

    cost o Control measures for preventing deterioration of water quality along with approximate 

    cost o Remediation of loss of top soil, loss of vegetation including trees and their  approximate 

    cost o Control  measures  for  keeping  community  safe  from  adverse  affects  of  activity  

    approximate cost  Natural and Community Resource Augmentation Plan will include 

    o Various activities  to be  taken  for augmentation of Natural Resources  like water,  land vegetative cover in a time bound manner and estimation of financial implication 

    o Activities  to be  taken  for augmentation of  community  resources. The  key  community resources include —  A physical  structure or place  ‐‐ a school, hospital,  library,  recreation center.  It 

    might  also  be  an  unused  building  that  could  house  a  community  centre,  a community  owned  forest,  a  park,  a  pond,  or  other  pasture  and  open  space belonging to community.  

    A community service that makes life better for majority of community members ‐ public transportation, early childhood education center, community recycling facilities, cultural organization.  

    An activity that provides jobs and supports the local economy.  Quantitative Assessment: Attempt will  also be made  to  assess  the  impact quantitatively.  The  format  of  assessment of impact by mining activity  is given ahead. Scores will be given based on  the extent of activity undertaken during violation period. An overall score will be estimated as per table and criteria given ahead — 

    Assessment of Extent of Damage 

    Sl. No. 

    Activities  Status % Score 

     ‐ve   +ve 

    1  Excavation 

    2.  Blasting       

    3.  Mining of mineral       

    4.  Loading/Unloading 

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐36‐ 

    5.  Ground extraction or dewatering 

    6.  Dumping 

    7.  Plantation/ Reclamation 

    8.  Surface drainage 

    9.  Transportation 

    10.  Mineral processing 

    11.  Road construction 

    12.  Rain Water Harvesting 

    13  Check dams/building 

    14  Any other Environment Improving Activity 

    15  Any Community Development Activity 

    Total 

    Final Score after adjusting difference between ‐ve and +ve    

     

    Criteria for Scoring 

    Particular Status of Construction as of now 

    1 to 20%  21 to 40%  41 to 60%  61 to 80%  81% to 100% 

    Impact Score  1  2  3  4  5 

     

    Damage Scale 

    Particulars  Score Range 

    Extremely Damaging   ‐46 to‐60 

    Damaging   ‐31 to‐45 

    Minutely damaging    ‐16 to30 

    Not damaging significantly   

  • Limestone Mine (29.4151 ha) of Mr. Riaz Ahmad Panjra 

    Prepared by: Perfact Enviro Solutions (P) Ltd. New Delhi                                                                                                                 ‐37‐ 

    10. PROJECT SCHEDULE & COST ESTIMATES. Likely date of start of Mining and likely date of completion: 

    After grant of EC for extraction of limestone, mining from lease area will be started after 3‐4 months.  

    Project Cost along with analysis in terms of Economic Viability of the Project. The project cost is about Rs. 2.0 cr. It is a captive mine of PPs own cement plant the mine will always have economic viability as the market/enduse is already assured. 

    11. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS) The project is proposed to mine limestone in an area of 29.4151 ha. It will provide direct employment to about  174 workers.  Besides,  there will  be  indirect  employment  from  transportation,  canteen,  repair shop, security etc. Most of the employment will be given to locals from the nearby village. Further, the share of  indirect employment  like  increased purchasing power, dhabas and  retail shops etc.  is  largely shared by local residents.  The Company M/s. Cemtac Cements Pvt. Ltd. Mining Industries is committed to fulfill its responsibilities towards CSR.