PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated...

25
SAKTHI MINES & MINERALS PRE FEASIBILITY REPORT 1 JANUARY 2018 PRE – FEASIBILITY REPORT 1. INTRODUCTION M/s. Sakthi Mines & Minerals, 15/26, Sannathi Street, Shiruthuraipoondi Taluk, Thiruvarur District – 614 713, Tamil Nadu. Mr. G. Kumaran, Managing Partner of M/s. Sakthi Mines & Minerals has 15 years of experience in Mining. The Project Proponent has mine lease area for the production of Silica Sand in an area of 1.62.0 Ha at S.F. No. 205/1B of Vanduvancheri Village, Vedaraniyam Taluk, Nagapattinam District, Tamil Nadu. The applicant Mr. G. Kumaran Managing Partner of M/s. Sakthi Mines & Minerals, has already obtained for grant of Mining lease to Silica Sand Mine over an extent of 1.62.0 Ha in S.F. No. 205/1B in Vanduvancheri Village, Vedaraniyam Taluk, Nagapattinam District, Tamil Nadu for 20 years. The mining lease was granted in favor of M/s. Sakthi Mines and Minerals, vide G.O (3D), No.59 dated 16.03.1996 for a period of 8 years. The lease was expired on 26.07.2004. The State Government have renewed the lease for the further period of 20 years in the proceeding of commissioner of geology and mining vide Rc. No. 24/MM3/2004 dated 08.04.2004. The lease deed was executed on 07.08.2004. Mining operation commenced on 07.08.2004. The lease will expire on 06.08.2024. The Silica Sand Mine grant lease over an extent of 1.62.0 Ha in S.F. No. 205/1B in Vanduvancheri Village, Vedaraniyam Taluk, Nagapattinam District, Tamil Nadu and requested to M/s. Sakthi Mines & Minerals, to submit the approved Scheme of Mining through the Indian Bureau of Mines, Chennai and also obtain Environmental Clearance from SEIAA. The Scheme of Mining was approved by Indian Bureau of Mines in letter No.TN/NPM/S.SAND/MS-1144.MDS dated 17.12.2014. The Scheme of Mining over an extent of 1.62.0 Ha at S.F.No. 205/1B of Vanduvancheri Village, Vedaraniyam Taluk, Nagapattinam District, Tamil Nadu(Copy of Scheme of Mining approval letter enclosed). M/s. Sakthi Mines & Minerals, propose to Mine Average Silica Sand for 1439 Tonnes per year up to (2018 - 19) from this existing mine lease area by open cast mining technique. This feasibility report is prepared towards obtaining the Environmental Clearance. As per MOEF O.M. No. L - 11011/ 47/ 2011–A.II (M) dated 18 th May 2012, leases of minor minerals also require environmental clearance. For getting environmental clearance, depending on the nature magnitude and capacity, the projects are categorized as “A” Category & “B” Category. “A” Category projects have to be cleared by MOEF

Transcript of PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated...

Page 1: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

1 JANUARY 2018

PRE – FEASIBILITY REPORT

1. INTRODUCTION

M/s. Sakthi Mines & Minerals, 15/26, Sannathi Street, Shiruthuraipoondi Taluk,

Thiruvarur District – 614 713, Tamil Nadu. Mr. G. Kumaran, Managing Partner of

M/s. Sakthi Mines & Minerals has 15 years of experience in Mining. The Project

Proponent has mine lease area for the production of Silica Sand in an area of 1.62.0 Ha

at S.F. No. 205/1B of Vanduvancheri Village, Vedaraniyam Taluk, Nagapattinam District,

Tamil Nadu.

The applicant Mr. G. Kumaran Managing Partner of M/s. Sakthi Mines & Minerals,

has already obtained for grant of Mining lease to Silica Sand Mine over an extent of

1.62.0 Ha in S.F. No. 205/1B in Vanduvancheri Village, Vedaraniyam Taluk,

Nagapattinam District, Tamil Nadu for 20 years.

The mining lease was granted in favor of M/s. Sakthi Mines and Minerals, vide

G.O (3D), No.59 dated 16.03.1996 for a period of 8 years. The lease was expired on

26.07.2004. The State Government have renewed the lease for the further period of 20

years in the proceeding of commissioner of geology and mining vide Rc. No.

24/MM3/2004 dated 08.04.2004. The lease deed was executed on 07.08.2004. Mining

operation commenced on 07.08.2004. The lease will expire on 06.08.2024.

The Silica Sand Mine grant lease over an extent of 1.62.0 Ha in S.F. No. 205/1B

in Vanduvancheri Village, Vedaraniyam Taluk, Nagapattinam District, Tamil Nadu and

requested to M/s. Sakthi Mines & Minerals, to submit the approved Scheme of Mining

through the Indian Bureau of Mines, Chennai and also obtain Environmental Clearance

from SEIAA.

The Scheme of Mining was approved by Indian Bureau of Mines in letter

No.TN/NPM/S.SAND/MS-1144.MDS dated 17.12.2014. The Scheme of Mining over an

extent of 1.62.0 Ha at S.F.No. 205/1B of Vanduvancheri Village, Vedaraniyam Taluk,

Nagapattinam District, Tamil Nadu(Copy of Scheme of Mining approval letter enclosed).

M/s. Sakthi Mines & Minerals, propose to Mine Average Silica Sand for 1439

Tonnes per year up to (2018 - 19) from this existing mine lease area by open cast

mining technique. This feasibility report is prepared towards obtaining the Environmental

Clearance.

As per MOEF O.M. No. L - 11011/ 47/ 2011–A.II (M) dated 18th May 2012, leases

of minor minerals also require environmental clearance. For getting environmental

clearance, depending on the nature magnitude and capacity, the projects are categorized

as “A” Category & “B” Category. “A” Category projects have to be cleared by MOEF

Page 2: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

2 JANUARY 2018

while “B” Category by the State Environmental Impact Assessment Agency (SEIAA). This

being a small mine of just 1.62.0 Ha (< 25 Ha) it can be treated as B-2 category.

TABLE 1 – LEASE PARTICULARS

Rc. No Extent (Ha)

Date of Grant

Date of Execution

Period of lease

Date of Expiry

24/MM3/2004 1.62.0 08.04.2004 07.08.2004 20 Years 06.08.2024

As per MoEFCC Notification S.O.804 (E) dated 14.3.2017, our project is considered as

violation since we are operating mine without obtaining prior EC. In order to obtain EC

we are applying to EAC, MoEFCC to get EC as per the procedure prescribed in

Notification dated 12.03.2017.

Accordingly the lessee has to evaluate the possible environmental aspects and their

associated impacts that will be raised due to the production of Silica Sand and to

delineate the management plan to prevent, control, mitigate or minimize the adverse

environmental impacts envisaged. In this regard, the applicant has appointed M/s. ABC

Techno Labs India Private Limited, Chennai, who is accredited by National

Accreditation Board for Education and Training (NABET), Quality Council of India (QCI),

New Delhi to prepare Environmental Impact Assessment (EIA) report including

Environmental Management Plan to mitigate any adverse impacts to the Environment.

2. DETAILS ABOUT THE MINE

Mr. G. Kumaran, Managing Partner of M/s. Sakthi Mines & Minerals mine lease (1.62.0

ha) is a Patta Land at S.F. No. 205/1B, of Vanduvancheri Village, Vedaraniyam Taluk,

Nagapattinam District, Tamil Nadu. Vanduvancheri Silica Sand mining method is open

cast mine. The silica sand is loose and free flowing. There is no need of any blasting or

drilling in the projected operations.

The applied area is about 1.2 km, away from Vanduvancheri Village. Mine lease area is

well connected with roadways, the nearest roadway is Vanduvancheri – Thakkattur

road, 0.8 km west. Nearest Railway station is Thiruthuraipoondi which is located about

12.0 km N, from the mine lease area. Nearest Air Port is Tricharapalli International

Airport of about 125.0 km NW from the mine lease area. Nearest Port is Nagapattinam at

a distance of 45 km NE. The applied area is easily accessible by means of roadways

(Lorries and trucks). The lease area comes in SOI, Toposheet No. 58 N/11.

The detailed Google Image of the project site is show below.

Page 3: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

3 JANUARY 2018

TABLE 2 - LOCATION OF THE PROJECT SITE

District and State

Village and Taluk

S. F. No Extent of area Hectares

Ownership

Nagapattinam, Tamil Nadu

Vanduvancheri Village, Vedaraniyam Taluk

205/1B 1.62.0 Patta Land

TABLE 3 - SALIENT FEATURE OF THE PROJECT SITE

Description Details

Project Name Vanduvancheri Silica Sand Mine

Mining Lease Area 1.62.0 ha

Location of Mine Vanduvancheri Village, Vedaraniyam Taluk,

Nagapattinam District, Tamil Nadu

Topo sheet number 58 N/11

Production capacity 1439 tonnes/Year for Silica Sand (5755 T for four year)

Method of mining Open Cast manual method

Drilling/Blasting The silica sand is loose and free flowing. There is no need

of any blasting or drilling in the projected operations.

No. of working days 250 days

Water demand 2.5 KLD

Sources of water Water will be supplied from bore wells of the nearby area

Man power 18 Nos

Nearest railway station Thiruthuraipoondi Railway station – 12.0 km (N)

Nearest airport Tricharapalli International Airport – 125.0 km (NW)

Page 4: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

4 JANUARY 2018

FIGURE 1 – LOCATION MAP OF THE PROJECT SITE

3. NEED FOR THE PROJECT AND ITS IMPORTANCE

Silica sand forms the major ingredient among natural raw materials required for

glass making and it is also used in foundry, ferro-silica alloy and cement industries

besides being used in many other industries like ceramic, fertilizer, abrasives, chemical,

coal washery, electrode, paint, rubber, textile, water filtration, construction etc. The

natural silica sand is preferred in glass industries, but in cases when silica deposits are

located far away, crushed quartz is used. The proposed Silica Sand mine for mining high

grade glass industry suitable sand. The general mining method in is by manual cum

opencast Manual method.

There is a growing demand of quality silica sand mineral in the foundry as well as

glass industries. Availability of good quality silica sand is limited. Therefore marginal and

Page 5: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

5 JANUARY 2018

low grade silica sand needs to be beneficiated for making it useable in the industries.

The lessee has network for supply of the silica sand to the foundry persons. Therefore

the purpose of the project is to excavate and trade silica sand to the customers, mainly

comprising of glass industries, while taking care for safety of persons and machines

deployed, and care for the environment. The Mines in the present area are supplying the

material to glass industries.

As per EIA notification 2006 project proponent is submitting the proposal to get

Environmental Clearance for Silica Sand mining with production capacity of 1439

Tonnes/Year from Environmental Appraisal Committee constituted by MoEFCC, GOI for

the purpose of grant of Environmental clearance.

4. LAND USE SPLIT UP

Vanduvancheri mine lease area is a Patta Land with total land area of 1.62.0 ha. The

land use pattern of the mine lease area is shown below.

TABLE 4 - LAND USE SPLIT UP

Description Present Area (Ha.)

Area in use during the quarrying period (Hect)

Mining (Quarry) 0.78.0 0.82.0

Waste Dump - -

Office Infrastructure - -

Mineral Stack / Processing Yard - 0.04.0

Sub Grade Mineral Stacks - -

Mines Roads - 0.05.0

Area Under Plantation - 0.10.0

Township Area - -

Others (Way to Explosive Magazine) -

Unutilized Area 0.84.0 0.61.0

Total 1.62.0 1.62.0

Page 6: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

6 JANUARY 2018

FIGURE 2 - KEY PLAN OF VANDUVANCHERI Mine Lease Area

The Silica Sand extracted with the help of machineries for digging, excavation, Alluvial

sand and mine reject. All operations of mining, including excavation, loading &

transportation on single shift basis shall form the complete mining operation. The silica

sand is loose and free flowing. There is no need of any blasting or drilling in the

projected operations.

NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND OR

REGION.

The production of silica sand at 2,283 thousand tonnes in 2009 – 10 decreased by

about 19% over that of the previous year due to lack of demand from cement plants and

labour problems. Andhra Pradesh the major producing state reported decrease of about

28% in comparison with the previous year due to of request labour problems. During the

year under review, there were 133 reporting mines as against 138 in the preceding year.

Besides, the production of silica sand was also reported as an associated mineral by four

mines during the year. Ten principal producers accounted for about 54% of the total

Page 7: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

7 JANUARY 2018

production. The share of public sector in the total production was 5% in 2009-10 as

against 1% in the preceding year. Andhra Pradesh, the leading producing state

accounted for 39% of the total production during the year followed by Gujarat (17%),

Rajasthan (14%), Maharashtra (13%), Uttar Pradesh (7%), Jharkhand and Karnataka

(4%each). The remaining two percent productions was the contribution of Kerala, Odisha

and Tamil Nadu. About 62% of the total production of silica sand was contributed by 15

silica sand mine sand two associated mines, each mine producing more than 50

thousand tonnes annually and about 33% by 56 silica sand mines and one associated

mine, each producing five thousand to fifty thous and tonnes. The remaining 5% of the

output was contributed by 62 silica sand mine sand one associated mine, each producing

less than 5000 tonnes annually. Mine-head stocks of silica sand at the end of 2009-10

were 3,260 thousand tonnes as against of 1,280 thousand tonnes in the beginning of the

year. The average daily employment of labourers in 2009-10 was 2,401 as against 2,257

in the previous year. Domestic prices of silica sand are furnished in the General Review

on Prices. (Source: Indian Minerals Yearbook 2011 (Part- II) by Indian Bureau of Mines.)

5. DEMAND SUPPLY GAP

There is a demand of Silica Sand and is ever growing with the growth of industrial

sector in the country. The requirement of the mineral is always found high in adjoining

areas. Geological processes have occasionally deposited sands that are composed of

almost 100% quartz grains. These deposits have been identified and produced as

sources of high purity silica sand. These sands are used in the glassmaking industry

projects.

6. INDIGENOUS PRODUCTION

Presently there are no imports of this sand. The indigenous production is sufficient for

the Indian market. There is established export market for this material. Most of the

material is exported from Mundra port and Mumbai port. There are possibilities of export

to China, Bangladesh, and Korea etc.

7. EXPORT POSSIBILITY

Most of the material is exported from Mundra port and Mumbai port. There are

possibilities of export to China, Bangladesh, and Korea etc.

Page 8: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

8 JANUARY 2018

8. DOMESTIC/EXPORT MARKETS

Nagapattinam District is bestowed with abundance of Silica Sand deposits as such the

state has enriched in production of Silica Sand. Silica sand mined by the Lessee will be

used in the own captive plant M/s. Sakthi Mines & Minerals for manufacturing Sodium

Silicate. The grade is been already approved and fit for Suitable for Glass making and

the proposed site is easily accessible through roadways to the various places and Silica

Sand marketing will not be a problem.

9. EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE

PROJECT

The mine will have a potential of direct employment comprising of managerial, skilled,

semiskilled and unskilled staff. Due to proximity of villages near the mine lease area

there is not much problem about the labor forces for mining operation such as loading

and other associated jobs. The existing employment potential status is given below.

As the Silica Sand mining operations in the proposed mine will employ about 18 persons

directly and on indirect employment several workers in the nearby area for loading silica

sand in to trucks , tractors and tippers, etc, which will provide a great fillip for raising

income levels and standards of living in the area.

PROJECT DESCRIPTION

i) Type of project including Interlinked and Interdependent project, if any.

The project is Silica Sand mining by opencast method in the lease hold area of 1.62.0

Ha. The project meeting the Silica Sand requirement for production of Suitable for Glass

Making etc, for various applications at Vanduvancheri Village, Vedaraniyam Taluk,

Nagapattinam District, Tamil Nadu.

ii) Location (map showing general location, specific location, and project

boundary & project site layout) with coordinates.

The mining lease area is located at S.F. No. 205/1B of Vanduvancheri Village,

Vedaraniyam Taluk, Nagapattinam District, Tamil Nadu and the entire mining lease area

falls in Patta Land with Plain terrain. The mine lease area is covered in parts of Survey of

India Topo sheet No. 58 N/11 and having elevation of 3 m AMSL and located at Latitude

of N 10° 25’ 44.41” & Longitude of E 79° 39’ 50.34” Detailed Topo map & Site Layout is

enclosed.

Page 9: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

9 JANUARY 2018

FIGURE 3 - SATELLITE IMAGERY SHOWING THE PROJECT SITE AND ITS BOUNDARIES

Page 10: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

10 JANUARY 2018

FIGURE 4 - SOCIAL INFRASTRUCTURE AROUND THE 5 KM RADIUS OF THE PROJECT SITE

Page 11: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

11 JANUARY 2018

iii) Details of alternate sites considered and the basis of selecting the proposed

site, particularly the environmental consideration gone into should be

highlighted.

The occurrence of mineral is site specific and the mining/exploitation is to be taken up to

that particular location only therefore no alternative sites were required to be explored.

iv) Size or magnitude of operation.

The mining of Silica Sand will be carried out from the leasehold area of 1.62.0 Ha. It has

been observed from the Geological Plan that the topography of the area is flat

topography.

a. GEOLOGY OF THE AREA :

This area is made up sediments of Holocene age (10,000 Years Old) covered by

the Alluvial sands. The formations are rarely exposed, excepting along the

embankments of tanks, in which the silica sand abounds. The geological succession in

the region may be summaried as follows :

Recent Alluvial Sands

Holocene Silica Sand

-----------------Unconformity ------------------------------------------------------------------

-----

Mic-Pliocene Cuddalore Sandstone

----------------- Unconformity -----------------------------------------------------------------

-----

Archaean Granites and gneisses

The archaean granites and gneisses which form the crystalline basement have

been met with at a depth of about 900 m below the sediments in some of the bore holes

put down by the oil and natural gas commission drilled for oil in the surrounding area.

The Holocene sequence of Silica Sands over lie the Vanduvancheri sandstones which

seem to have formed their provenance.

The Silica Sands form a persistent horizon and are overlain by light brown

coloured, fine grained windblown sands simulating the teri-sands along the Tamilnadu

Coast. They are about a metre in thickness and form an extensive cover. The silica

sand are generally of greyish white colour. They made also carry at places shells of

gastropods and oysters, suggestive of its margine origin. The sands are underlain by a

black clay, which is sticky in nature. The following is a generalized section of the

different horizons observed in the area.

Alluvial Sand : 0.5m (average)

White Silica Sand : 4.5m

Page 12: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

12 JANUARY 2018

b. RESERVES

The area is an existing Silica Sand mine. The geological and mineable reserves are

estimated by cross sectional method. The geological reserve is estimated as 35932

tonnes by area cross sectional method.

The mineable reserves and the recoverable reserves are 35932 tonnes and

20340 tonnes respectively, The reserves details are as follows:

Page 13: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

JANUARY 2018

PRE FEASIBILITY REPORT

12 JANUARY 2018

TABLE 5 - ESTIMATION OF GEOLOGICAL RESERVES AS PER CROSS SECTIONAL METHOD

Section

Classification

Section

L

(m)

W

(m)

D

(m)

Volume

CUM

BD Reserves

(111) 90%(t)

Reserves

(111) 10%(t)

Resources in Benches &

Safety Distances in

Tonnes in S.D

PQ&WX

Locked up Bench & Safety

Distance P & Q Side

2 Sides W Side

8.0 (4x2) 8.0

58

53

3

3

1392

1272

2.0

2.0

2784

2544

ST & XY S.Sand II Bench

Locked up bench & Safety

Distance T Side Y Side

41

9.0 9.0

76

76 63

3

3 3

9348

2052 1701

2.0

2.0 2.0

16826 1870

4104 3402

RS & UV S.Sand II Bench

Locked up bench & Safety

Distance R Side U Side U Side

58

3.0 6.0 5.0

61

61 135 135

3

3 3 3

10614

549 2430 2025

2.0

2.0 2.0 2.0

19105 2123

1098 4860 4050

TOTAL 35932 3992 20340

Page 14: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

19 JANUARY 2018

SITE SELECTION OF MINE BOUNDARY:

The mine boundary is demarcated in line with the conditions / stipulations laid down by

the Scheme of Mining was also approved the Indian Bureau of Mines vide letter No.

TN/NPM/S.SAND/MS-1144.MDS dated 17.12.2014 (Copy of Scheme of Mining approval

letter enclosed). Now we prepared and submitted to Environment Clearance MOEFCC.

Proposed rate of Production and expected life of the Mine:

The mineable reserves is estimated by cross-sectional method having considered the

recovery factor, depth of mining, safety barriers etc., The mineable reserves is estimated

35932 tonnes and the recoverable reserves is 20340 tonnes.

The life of the mine is computed as Four Years at a production rate of 1439 Tonnes per

annum. The wastes (10%) are generated during the mining period is 639 tonnes shall be

proposed to Dumping to the North and South side of the 7.5m boundary barrier of the

lease area.

v) Project description with process details (a schematic diagram/ flow chart

showing the project layout, components of the project etc. should be given).

a. Physiography

The Mining Lease area is approximately at N 10° 25’ 44.41” latitude and at E 79°

39’ 50.34” longitude and is represented by Topo Sheet No.58 N/11 of Survey of India.

b. Regional Geology

Water table is noticed at a depth of 10m from the surface in the adjacent open wells of

the area.

This area is made up sediments of Holocene age (10,000 Years Old) covered by

the Alluvial sands. The formations are rarely exposed, excepting along the

embankments of tanks, in which the silica sand abounds.

The geological succession in the region may be summaried as follows :

Recent Alluvial Sands

Holocene Silica Sand

-----------------Unconformity --------------------------------------------------------------

Mic-Pliocene Cuddalore Sandstone

----------------- Unconformity -----------------------------------------------------------------

Archaean Granites and gneisses

The archaean granites and gneisses which form the crystalline basement have

been met with at a depth of about 900 m below the sediments in some of the bore holes

put down by the oil and natural gas commission drilled for oil in the surrounding area.

Page 15: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

20 JANUARY 2018

The Holocene sequence of Silica Sands over lie the Vanduvancheri sandstones which

seem to have formed their provenance.

The Silica Sands form a persistent horizon and are overlain by light brown

coloured, fine grained windblown sands simulating the teri-sands along the Tamilnadu

Coast. They are about a metre in thickness and form an extensive cover. The silica

sand are generally of greyish white colour. They made also carry at places shells of

gastropods and oystars, suggestive of its margined origin. The sands are underlain by

black clay, which is sticky in nature. The following is a generalized section of the

different horizons observed in the area.

Alluvial Sand : 0.5m (average)

White Silica Sand : 4.5m

Alluvial Sand:

It forms an extensive blanket of thickness with light brownish colour and grain

size. The sandy surface is of adulatory nature and appears to represent a fill of the

uneven surface by Alluvial sand from the shore and may represent sand dunes of

migratory and recent origin. The well rounded nature of the sand grains is due to

continual wave action during formation as coastal sand beds and transported under

Aeolian influences.

Silica Sand:

The Silica Sand, with an average thickness of 5.0m is of light grey colour and

yellow at the base in some sections. It is of medium to coarse grain size forming a good

aquifer. Presumably storing the rain water and to some extent of the water from the

Cauvery Canal System passing through the area. The greyish colour of the sand may be

due to moisture since it becomes white on drying.

The upper 0.5m zone of the 3.0m thick sand is of medium grain size, while the

lower zone is of coarse size of 2 to 3 mm indicative of some type of graded bedding

during is deposition. The coarse particles are colourless and somewhat angular quartz,

suggestive of their immature nature due to limited transportation from their source. The

yellow colour observed is about 0.3m thickness of the basal section of the sand could be

due to infiltration of ferruginous material. Shells of gastropods and oyster are

conspicuous at the base of the sands in some places.

Black Clay :

The Black Clays underlying the sand are somewhat semi-plastic and form a good

impervious zone and prevents loss of ground water. This is a very extensive horizon and

seems to have been formed under reducing conditions in a deep seated depositional

environment during the evolution of the (Holocene) sedimentary sequence. The nodules

of canker dispersed in the clays are presumably due to capillary action before the

deposition of the sands.

Page 16: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

21 JANUARY 2018

i. Method of Mining

Open Cast manual method of mining is adopted for exploitation of Silica Sand

from this area. The mine worked manually and “B” category mines. The silica sand is

loose and free flowing. There is no need of any blasting or drilling in the projected

operations. Thus the use of explosives and calculation of powder factor does not arise.

Only tippers will be used. Loading will be done manually by hand shovels.

BENCH DESIGN PARAMETERS:

Silica Sand benches will be formed to a height of 2.5m and width not less than

2.5m for movement of machineries and slope shall not be more than 60º for waste

bench and therefore the working face is designed to a height of 2.5m and the width not

less than 2.0 - 2.5m and the working slope will be vertical, however the final slope will

be 45º while abutting the ultimate pit limit.. Construction of parapet as a fencing around

such ultimate pit limit on top of opencast workings will be arranged to safeguard the

mine from inadvertent entry and hazards.

TABLE 10 - YEARWISE DEVELOPMENT AND PRODUCTION SCHEDULE

Year

Section

L

(m)

W

(m)

D

(m)

Volume

CUM

Bulk Density

Production 90%/ Waste 10% (t)

2013-2014 Lapsed - - - - - 1000

2014-2015 RS&CD 23 23 1.5 794 2 1429/159

2015-2016 PQ&AB 22 24 1.5 792 2 1426/158

2016-2017 PQ&CD 23 23 1.5 794 2 1429/159

2017-2018 TU&CD 49.5 11 1.5 817 2 1471/163

TOTAL 5755/639

ii. Chemical and Physical Specification

Chemical Specifications:

The average grade of the Silica Sand Grade is Suitable for Glass Making

Industries.

Since the entire mined out mineral is been utilized by the Ceramic and Glass

manufacturing industries and pulverizing unit in Nagapattinam. The grade is been

already approved and fit for Suitable for Glass Making Industries.

Page 17: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

22 JANUARY 2018

Physical specifications:

Colour of Silica Sand is light grey and yellow color massive in form, hardness-2, specific

gravity 2.0, and streak is white.

vi) Raw material along with estimated quantity, likely source marketing area of

final products, mode of transport of raw material and Finished product.

No raw material will be required in the proposed project. The operation involves

the extraction of sand in its existing form and it will be transported to the Non Local

market through Lorries. The existing roads will be utilized for the transport of silica sand

from mine site to market.

vii) Resource optimization / recycling and reuse envisaged in the project, if

any, should be briefly outlined.

No optimization / recycling and reuse envisaged in the mine lease area.

viii) Availability of water its source, Energy / power requirement and source

should be given.

The quantity of water required for the mine lease area of 1.62.0 ha is estimated to be

2.5 m3/day. Drinking water is available from well & tube well near the project site which

is portable and will fulfill the requirement of drinking water at site.

TABLE 12 - WATER CONSUMPTION DETAILS

S. No. Description Water in KLD 1 Domestic Water use (For Labors) 0.750 2 Dust Suppression (Material

Transportation) 1.5

3 Greenbelt Development 0.250 Total 2.5 KLD

Power Requirement - As already mentioned the simple methods adopted and the

limited scale of activities involved in Silica Sand dimensional stone mining does not

require high- tension electric power. The mining work is restricted to one general shift

during daytime only. No electricity is needed for Mine operations etc as mainly diesel

operated mining machinery are used for Mining However, the power requirement of the

administrative buildings, roads etc can be met from state grid. The silica sand is loose

and free flowing. There is no need of any blasting or drilling in the projected operations.

Thus the use of explosives and calculation of powder factor does not arise.

Page 18: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

23 JANUARY 2018

ix) Quantity of waste to be generated (liquid and solid) and scheme for their

Management /disposal.

The wastes (10%) are generated during the mining period is 639 tonnes shall be

proposed to Dumping to the North and South side of the 7.5m boundary barrier of the

lease area.

TABLE 13 – Total Waste Management

Year Mineral Reject 10% (t)

Total waste (t)

2014-2015 159 159 2015-2016 158 158 2016-2017 159 159 2017-2018 163 163

TOTAL 639 639

Waste water:

There will not be any process effluent generation from the mine lease area. Domestic

effluent from the mine office is discharged in septic tank and soak pit. There is no toxic

effluent expected to generate in the form of solid liquid and gases and the no

requirement of treatment of waste.

x) Schematic representation of the feasibility drawing which give information

of EIA purpose

Form - 1 Along with Pre Feasibility Report

& Scheme of Mining with Annexure

To Submit MOEFCC

Final EC Presentation

Page 19: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

24 JANUARY 2018

10. SITE ANALYSIS

i) Connectivity.

The area is approachable by well-developed road network. The road connectivity map for

the mine lease area is given below.

FIGURE 4 – SITE CONNECTIVITY MAP

ii) Land use and Land ownership.

Vanduvancheri Silica Sand mine deposit nearly measuring an area of 1.62.0 Ha of patta

Land. The mine lease area is Patta Land.

iii) Topography (along with map).

The Silica Sand deposit in Vanduvancheri Silica Sand made up sediments of Holocene

age (10,000 years old) covered by the windblown sands. The formations are rarely

exposed, excepting along the embankments of tanks, in which the silica sand abounds.

The Silica Sand is overlain by 0.5 m thickness of windblown soil. The depth of Silica

Sand is ranging from 0.5 m to 5.0 m. Except some thorny bushes, no trees or thick

vegetation is found. Outcrops of Silica Sand are visible in some areas. The detailed topo

map of the site is enclosed.

Page 20: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

25 JANUARY 2018

iv) Existing land use pattern (agriculture, non-agriculture, forest, water bodies

(including area under CRZ), shortest distances from the periphery of the

project to periphery of the forest, national park, wild life sanctuary, eco

sensitive areas, water bodies (distance from the HFL of the river), CRZ. In case

of notified industrial area, a copy of the Gazette notification should be given.

The mining lease of 1.62.0 Ha is categorized as Patta Land has been used for extraction

of the Silica Sand. The detailed site surrounding features are given in Topo map which is

enclosed. Significant features in 10 Km radius (aerial distance) of the project are tabular

below.

TABLE 1.3. ENVIRONMENTAL SETTING OF THE PROJECT SITE

S. No. Description Details

1. Site Location Proposed Silica Sand Excavation to an extent of

1.62.0 Ha in S.F. Nos.205/1B of Vanduvancheri

Village, Vedaraniyam Taluk, Nagapattinam District

2. Latitude and Longitude Lease Boundary

(A)- N 10o 25’ 44.41” E 79o 39’ 50.34” (B)- N 10o 25’ 44.33” E 79o 39’ 44.47” (C)- N 10o 25’ 46.60” E 79o 39’ 44.44” (D)- N 10o 25’ 48.98” E 79o 39’ 51.48”

3. Topography Flat terrain

4. SOI Toposheet 58 N/11

5. Above Mean Sea Level in m 3m AMSL

6. Nearest City/ Town District Headquarters NAGAPATTINAM – 45.0 km (NE)

Taluk Headquarters VEDARANIYAM – 22.0 km (E)

7. Nearest Roadways Vanduvancheri - Thakkattur Road - 0.8 km (W)

8. Nearest Air port Tricharapalli Airport – 125.0 km (NW)

9. Nearest Railway Station Nagapattinam –45.0 km (NE)

10. Hills/ valleys Nil within 10 km radius

11. National parks / Wildlife

Sanctuaries

Nil within 10 km radius

12. Reservoir / Lake/River/Sea Alli Kulam – 2.8 km SW

Thiruvasaga Kulam – 3.23 km W

Valvan Aaru – 3.3 km W

Pappan Kulam – 3.5 km W

Thulasiyapatinam – 3.21 km W

Pallivasal Kulam – 3.81 km W

13. Reserved/ Protected Nil within 10 km radius

Page 21: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

26 JANUARY 2018

Forests

14. Archaeological Important

Places

Nil within 10 km radius

15. Seismicity Seismic Zone II as per IS 1893 (Part-1): 2002

16. Defence Installations Nil within 10 km radius

17. Nearest Port Nagapattinam Port – 45.0 km (NE)

18. Nearby mines Nil

v) Existing Infrastructure

Approach road is available from the village road up to the mining Lease Area. Office

Shed containing basic facilities such as Office, store room, First Aid Station, Rest Shed,

Toilet etc. as per Mines Rules, 1960 are available within the lease hold area.

vi) Soil classification

The Alluvial sand is in red colour and thickness of the soil is 554 Tonnes and followed by

weathered pediments. The Silica Sand is overlain by Weathered Formation.

vii) Climatic data from secondary sources.

The area receives rain during NE monsoon. Wind direction is NE to SW and vice-versa.

The temperature in summer rises above 40°C and fall down to 25°C in winter months.

The average amount of rainfall is about 400 mm per annum. There are no national

monuments, places of worship or archaeological interest, public buildings, permanent

structures near the area. There is no river, tank or reservoir, sanctuary or forest near

the area. There is no reserve forest or places of Archaeological interest or national

monument within a radius of five km. from this area.

11. PLANNING BRIEF

i) Planning Concept (type of Industries, facilities, transportation etc) Town and

country planning/Development authority Classification.

Open Cast manual method of mining is adopted for exploitation of Silica Sand from this

area. Transportation and commodities infrastructure facilities are locally available near

the project site. The mining of Silica Sand is transported from mine head to processing

plant by tippers.

Page 22: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

27 JANUARY 2018

Transportation

The mining of Silica Sand is transported from mine head to processing by tippers. The

entire mine out mineral is being sold in domestic market and to industries nearby the

lease area.

ii) Population Projection

There are few villages located in the 5 km radius of mining site and approximate

distance and population are given below.

TABLE 14 Total Populations

Basic human welfare needs such as schools, communications facilities and commercial

centers etc are available at Thiruthuraipoondi located at a distance of 12.0 km from the

North side of the mining area.

iii) Land use planning (breakup along with green belt etc.)

Green belt will be developed in the safety zone area etc, and at all possible places. Local

trees like Coconut, Casuarinas, Eucalyptus, Neem, acacia, Tamarind etc will be planted

along the 7.5m boundary barrier of the lease area and avenues as well as over Non-

active dumps at a rate of 10 trees per annum with interval 5m in between. The rate of

survival expected to be 80% in this area.

iv). Assessment of Infrastructure Demand (physical & social).

The existing roads facilities are already available which shall be used and maintained.

The labors requires to operate the mine is drawn from the nearest villages.

V) Amenities/Facilities.

Associated buildings like mine office, store, First Aid Station, rest shelter, Toilets, etc. as

per Mine Rules 1960 are available within the leasehold area.

Direction Village Distance

in Kms

Population

North Melamarathur 3.0km 250

East Thanikottagam 2.0km 150

South Annapettai 2.0km 300

West Vanduvancherri 1.3km 200

Page 23: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

28 JANUARY 2018

12. PROPOSED INFRASTRUCTURE

i) Industrial area (processing area).

Mineral Processing operation only hand sorting of ore is involved

ii) Residential Area (Non processing Area).

No Residential area are envisaged

iii) Green Belt.

7.5 m safety distance on the southern side is selected for green belt development by

planting and maintaining native species of Coconut, Casuarinas, Eucalyptus, Neem,

acacia, Tamarind etc will be planted along the 7.5m boundary barrier of the lease area

and avenues as well as over Non- active dumps at a rate of 10 trees per annum with

interval 5m.

iv) Social Infrastructure.

Social infrastructure like primary school at Vanduvancheri secondary schools, banks and

hospitals are located at nearest town Thiruthuraipoondi. Since the mine site is located

near to Nagapattinam City and it has all the essential facilities like school, hospitals and

medical facilities etc and also well connected with roadways.

v) Connectivity (Traffic and Transportation Road/Rail/Metro/Water ways etc.)

Adequate road facility is available from the mine lease area.

vi) Drinking Water management (Source & Supply of water)

Drinking water is available from well & tube well near the proposed site which is potable

and will fulfill the requirement of drinking water at site. Source – Borewell.

vii) Sewerage System

The sewage generated in the mine lease area is treated through septic tank followed by

soak pit.

viii) Industrial Waste Management.

No industrial waste will be generated from the project.

Page 24: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

29 JANUARY 2018

ix) Solid Waste Management.

The proposed Silica Sand mine anticipated waste during the present scheme period is

about 639 Tonnes (Total waste).

x) Power Requirement & Supply / Source.

As already mentioned the simple methods adopted and the limited scale of activities

involved in Silica Sand dimensional stone mining does not require high- tension electric

power. The mining work is restricted to one general shift during daytime only. No

electricity is needed for Mine operations etc as mainly diesel operated mining machinery

are used for Mining However, the power requirement of the administrative buildings,

roads etc can be met from state grid. The silica sand is loose and free flowing. There is

no need of any blasting or drilling in the projected operations. Thus the use of explosives

and calculation of powder factor does not arise.

13. REHABILITATION AND RESETTLEMENT (R & R) PLAN

i) Policy to be adopted (central/state) in respect of the project affected person

including home oustees, land oustees and landless laborers (a brief outline to

be given.)

There is no rehabilitation and resettlement is involved. The deployed labors will be

insured as per government norms.

14. PROJECT SCHEDULE & COST ESTIMATES

The total project cost is Rs. 13,50,000/- for deployment of machinery and creation of

infrastructural facilities like approach road, Mine office / Workers Shed, First Aid Room

etc.., including electrifications and water supply.

15. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)

i) Financial and social benefits with special emphasis on the benefit to the local

people including tribal population, if any, in the area.

The project is been giving direct and indirect benefits to the peoples in around the

project site, beside the government. As the Silica Sand mining operations in the

proposed mine will employ about 18 persons directly and on indirect employment several

workers in the nearby area for loading silica sand in to trucks , tractors and tippers, etc,

which will provide a great fillip for raising income levels and standards of living in the

area.

Page 25: PRE – FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...24/MM3/2004 dated 08.04.2004 The lease deed was executed on . 07.08.2004. Mining operation commenced on

SAKTHI MINES & MINERALS

PRE FEASIBILITY REPORT

30 JANUARY 2018

The socio- Economic conditions of the village and distance has enhanced due to the

project, hence, the project should be allowed after considering all the parameters. The

detail furnished in this scheme of mining is based on information provided by the State

Government and the lessee.