Project Development And Environment (PD&E) Study
SR 934WELCOME TO THE PROJECT
KICK-OFF MEETING
State Road 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive FINANCIAL MANAGEMENT NUMBER: 410646-4-22-01 EFFICIENT TRANSPORTATION DECISION MAKING (ETDM) NUMBER: 14312
AGENDAPROJECT BACKGROUND AND GOALS
• PROJECT LOCATION
• CORRIDOR HISTORY
• PD&E PROCESS
• ABOUT THE STUDY
• PURPOSE AND NEED
• TRAFFIC AND SAFETY
2PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
PROJECT LOCATIONPD&E Study Limits SR 934 (both 79th and 81st/82nd) from
NW 13th Court to N. Bayshore Drive
Located within: Unincorporated Miami-Dade County
City of Miami
Census Designated Places: Miami
Gladeview
West Little River
Model City
Project also located within the 79th Street Corridor Community Redevelopment Area
3PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
1970 1979 1999 2002 2003 2004 2005 2006 Early 1970s Roadway Converted to Existing Configuration – Emphasis on Mobility March 1979 NW/NE 81st / 82nd St. transferred to FDOT 1999 City of Miami Completes Upper Eastside Master Plan November 2002 FDOT Completes Livable Communities Study August 2003 FDOT Commences PD&E Study
December 2004 PD&E Alternatives Workshop November 2005 Need for Capacity / Transit Project Identified January 2006 City of Miami Requests Capacity / Transit Project from MPO Project placed in abeyance
Three Resurfacing, Rehabilitation, and Restoration (RRR) completed: 2011: Traffic Calming along 82nd St. from N. Bayshore Dr. to Biscayne Blvd. 2012: along 81st / 82nd from NW 13th Court to Biscayne Blvd. 2013: 79th Street from NW 14th Avenue to N. Bayshore Dr.
August 2016: Pavement preservation and safety improvements
CORRIDOR HISTORY
PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
2011 2016
4
WHY IT’S DONE Evaluate project feasibility and potential environmental
impacts (natural, physical, socio-cultural)
Comply with federal and state environmental laws
Required to secure federal regulatory approval
WHAT IT INVOLVES Conducting preliminary engineering
Evaluation options to avoid, minimize, or mitigate potential environmental impacts
Coordinating with federal, state and local agencies
Engaging the public in project development
STEPS TO IMPLEMENTATION
5
PLANNING
PROJECT DEVELOPMENTAND ENVIRONMENT
(PD&E) STUDY
DESIGN
RIGHT OF WAY ACQUISITION
(IF NEEDED)
CONSTRUCTION
MAINTENANCE
1
2
3
4
5
6PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
Project Development and Environment (PD&E) Process
PUBLIC INVOLVEMENT COORDINATION
Unscheduled Public Meetings
Stakeholder Meetings
Alternative Public Meeting
Stakeholder Meetings Public HearingKick-Off
MeetingPublic
Participation
DATA COLLECTION
PRELIMINARY CONCEPT ANALYSIS
ENGINEERING ANALYSIS &
DESIGN
ENVIRONMENTALANALYSIS
VALUE ENGINEERING
EngineeringData Needs Analysis Engineering
Analysis
Environmental Studies
Work Products
Environmental Documents
Environmental Data
Preliminary Concept Screening
Engineering Final Reports
Other Information
Initial Concept Development
Engineering Design
FINALDOCUMENTS
FDOT Review
Location & Design
Concept Acceptance
6PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
ABOUT THE STUDY
• SR 934 – Unbalanced One-way Pairo 3 EB lanes & 1 WB lane on NW 79th Streeto 2 WB lanes on 81st/82nd Street
• Traverses both residential and commercial areas• Provides significant movement from Miami Beach to I-95 and Biscayne Blvd.• Provides opportunity for regional transit accessibility and connectivity
BEGIN PROJECT
END PROJECT
NW
22
AV
E
NW
17
AV
E
NW
7 A
VE
N. M
IAM
I AV
E
BIS
CA
YN
E B
LVD
NW 79 ST
NW 81 STNE 82 ST
Project Corridor
Florida East Coast Railroad
LEGENDUNINCORPORATED
MIAMI-DADE
CITY OF MIAMI
EL PORTAL
7PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
NE 79 ST
PROJECT OBJECTIVES AND GOALS
COMPLETE STREET LIVABILITY GOALS• Promote a choice in transportation
• Traffic calming
• Safe environment for walking and bicycling
• Enhance area's image and aesthetics
• Address on-street parking
• Address loading/delivery issues
• Improve business access
MOBILITY GOALS• Relieve congestion and improve
capacity
• Increase transit accessibility, reliability and capacity
• Improve multimodal safety
• Improve emergency response service and hurricane evacuation times
8PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
Purpose and NeedTo enhance safety, capacity, traffic operations, and multimodal use along SR 934 in order to address existing congestion and future travel demand.
EXISTING TRAFFIC
9PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
END PROJECT
NW
17
AV
E
BIS
CA
YN
E B
LVD
NW 79 ST
NW 81 ST
BEGIN PROJECT
NW
22
AV
E
NW
7 A
VE
N. M
IAM
I AV
E
NE 79 ST
NE 82 ST
Project Corridor
Florida East Coast Railroad
LEGEND
D
C
10,500
WB=8,600EB=15,000
D17,500D13,500
DE
Traffic Observations High pedestrian and bicycle activity Intersection capacity deficiency High vehicular speeds along 82nd Street
Observed pedestrian conflicts (jaywalking) Delays due to stopped buses in single WB lane Parking conflicts with thru lanes
WB=6,700EB=22,000
WB=7,400EB=19,500
SAFETY CONDITIONS – 79TH STREET
10PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
Crash Cluster Locations1. I-95 Ramp Terminals2. N Miami Avenue3. Biscayne Blvd4. NE 10th Avenue
Identified Probable Causes• Congestion at major intersections• Driveway and parking conflicts • Pedestrian jaywalking• Poor intersection lighting
SAFETY CONDITIONS – 82ND STREET
11PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
Crash Cluster Locations1. I-95 Ramp Terminals 2. N Miami Avenue3. Biscayne Blvd.
Identified Probable Causes• Congestion at major intersections• High speeds/aggressive driving • Poor intersection lighting
AGENDAENVIRONMENTAL
• ENVIRONMENTAL EVALUATION
• EFFICIENT TRANSPORTATION DECISION MAKING
12PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
NATURAL RESOURCES
Wetlands and Other Surface Waters
Threatened & Endangered Species
No Essential Fish Habitat
SOCIO-CULTURAL RESOURCES
Support social and economic development
Recreational areas
Archeological / Historic Sites
PHYSICAL ENVIRONMENT
Noise
Air Quality
Contamination
ENVIRONMENTAL EVALUATION
13PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
ETDM SCREENING / POTENTIAL ISSUES• Enables agencies and the public to provide early input regarding the
potential effects of proposed transportation projects• Tentative Class of Action = Categorical Exclusion Type II• Programming Summary Report available at: http://etdmpub.fla-etat.org/
(ETDM # 14312)
EFFICIENT TRANSPORTATION DECISION MAKING (ETDM)
14PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
Degree of Effect
N/A – NOT APPLICABLE
0 – NONE
1 – ENHANCED
2 – MINIMAL
3 – MODERATE
4 – SUBSTANTIAL
AGENDAPUBLIC INVOLVEMENT
• GET INVOLVED
• VISIT OUR WEBSITE
• PROJECT SCHEDULE
• PROJECT CONTACTS
15PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
GET INVOLVEDATTEND PUBLIC MEETINGS Agency and Public Kick-off meetings
Corridor Information Meeting
Alternatives Public Meeting
Public Hearing
Project Advisory Meetings
Additional opportunities will be provided throughout study
PROVIDE YOUR INPUT Complete a comment from today
Drop in comment box or
Mail comments to the address listed on the form
Provide comments on our website: http://www.fdotmiamidade.com/79thstreetpdestudy
Comments appreciated by November 12, 2017
16PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
17PD&E STUDY SR 934/NE/NW 79 STREET FROM WEST OF I-95 (13 CT) TO END OF SR 934/1 WAY PT
VISIT OUR WEBSITE
VISIT OUR WEBSITE:www.fdotmiamidade.com/79thstreetpdestudy
FDOT Website
Project Website
Project Directory
18
PROJECT SCHEDULE
PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
Activity2017 2018 2019
W S S F W S S F W S S F
Data Collection
Kick-off Meetings
Corridor Informational Meeting
Alternatives Public Meeting
Public Hearing
Location and Design Concept Acceptance
Public Involvement
PROJECT CONTACT
Auraliz Benitez, PEProject Manager Florida Department of Transportation, District Six1000 NW 111 AvenueMiami, Florida 33172Tel (305) 470-5471Email: [email protected]
PROJECT CONTACTS19PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive
QUESTIONS?
20PD&E STUDY SR 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive