Powering sydneys future workshop

37
Monday 28 November, 2016 Powering Sydney’s Future Workshop 1

Transcript of Powering sydneys future workshop

Page 1: Powering sydneys future workshop

Monday 28 November, 2016

Powering Sydney’s Future Workshop

1

Page 2: Powering sydneys future workshop

Welcome Gerard Reiter

Executive General Manager, Asset Management

TransGrid

2

Page 3: Powering sydneys future workshop

Powering Sydney’s Future - Introduction

Sydney is the most

important load in the

country and it is growing

TransGrid and Ausgrid’s

electricity networks are

critical to support this growth

3

Page 4: Powering sydneys future workshop

High load areas

• CBD

• Inner suburbs

• Transport corridors

Key customers

• Sydney CBD

• Sydney Airport

• Port Botany

• Major rail and road links.

Powering Sydney’s Future - Introduction

Page 5: Powering sydneys future workshop

Powering Sydney’s Future - Introduction

Complex network built in the 60s and 70s

Networks’ abilities to meet growing need is

degrading

Timing is critical. To have a solution in

place to meet the need we have to act

now

TransGrid and Ausgrid are committed to

an open and open-minded process to find a

reliable and efficient solution

5

Page 6: Powering sydneys future workshop

Powering Sydney’s Future – 2014 consultation

• 400 stakeholders representing the public, researchers, industry, government and

regulators participated in a workshop.

• TransGrid and Ausgrid committed to:

o Developing responsive network options – in the PSCR

o Grow demand management using non-network options - in the PSCR and EOI

o Playing active roles in the refinement of standards for a reliable supply at an

efficient cost - engaged with IPART

o Continue to engage and collaborate – we have and continue to do so today

6

Page 7: Powering sydneys future workshop

Powering Sydney’s Future Ausgrid drivers

Matthew Webb

Manager Network Risk and Planning

Ausgrid

Page 8: Powering sydneys future workshop

• Approx. 200MW load

from new large

customers

• Estimated 150 ~250MW

from future large scale

redevelopment

Powering Sydney’s Future – Ausgrid drivers

Sydney – growth and additional loads

Page 9: Powering sydneys future workshop

Powering Sydney’s Future – Ausgrid drivers

Sydney – growth

Forecast demand

growth peak

• Return to demand

forecast growth seen

in 2015 and 2016

• New large customer

loads driving future

growth

• Ausgrid base forecast

is consistent with BIS

Shrapnel forecast

Page 10: Powering sydneys future workshop

Powering Sydney’s Future – Ausgrid drivers

Deteriorating fluid filled cables

• Ausgrid’s 132kV fluid filled

cables mostly installed in

1960’s and 1970’s

• Ausgrid has approx. 350km

• Repairs are complex and

time consuming

• Ausgrid has an MOU with

the EPA for reducing fluid

leaks over time

Page 11: Powering sydneys future workshop

Failure

history Leaks

Test

Results

Predictive unavailability model

- History of cable failures with repair times getting longer

- Consistent leaks and poor test results requiring repairs

- All contributing to poor cable availability

Repair

Times

Powering Sydney’s Future – Ausgrid drivers

Deteriorating fluid filled cables

Page 12: Powering sydneys future workshop

• Total cable unavailability

over past 4 years of

approximately 17%

• Cable fluid loss from leaks

has been significant

• Maintenance

requirements continue to

increase

Powering Sydney’s Future – Ausgrid drivers

Deteriorating fluid filled cables

Page 13: Powering sydneys future workshop

Powering Sydney’s Future – Ausgrid drivers

Planning based on community benefit

• Network energy delivery

capacity is declining

• Customer demand for

energy is increasing

• Shortfall is expected

unserved energy (EUE)

• Trigger point - where

accumulated value of

EUE is greater than cost

of project

Project Trigger Point

Page 14: Powering sydneys future workshop

TransGrid driver, proposed reliability standard and this process Anthony Englund

Group Manager, Investment Strategy and Solutions

TransGrid

14

Page 15: Powering sydneys future workshop

Powering Sydney’s Future – TransGrid driver, proposed standard and process

• Not operating to its full capacity

o Cable 42 CMS showed higher TR (2000s)

o Backfill sampling (to 2009)

o 1st derating - Anders & Orton review (2011)

o Full backfill sampling program (to 2016)

o 2nd derating – Anders (2016)

o Cable and joint sampling (now)

15

Driver 3: Cable 41

• One of two 330kV cables, 20 km long,

built in 1970s, 40 year nominal life

Page 16: Powering sydneys future workshop

Powering Sydney’s Future – TransGrid driver, proposed standard and process

Proposed new reliability standard

• About fine-tuning price/service level balance

• IPART: ‘Modified n-2 + 0.6 minutes EUSE per year at average demand’

• EUSE equivalent of 20MW (UNSW or Kensington) one hour per year

• An important, evolutionary change but…

• Capacity reductions and load growth put us in deficit from 2017

• Challenge to supply energy, major challenge to supply appropriate capacity

• Key message: we need to know what non-network solutions can deliver

16

Page 17: Powering sydneys future workshop

Powering Sydney’s Future – TransGrid driver, proposed standard and process

Project trigger point

Energy shortfall (MWh)

Page 18: Powering sydneys future workshop

Powering Sydney’s Future – TransGrid driver, proposed standard and process

Capacity shortfall (MW)

Page 19: Powering sydneys future workshop

Powering Sydney’s Future – TransGrid driver, proposed standard and process

Process

2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23

RIT-T process

Environmental planning process

Implementation phase

Design phase

19

• PSCR subs due 13 Jan 2017

• PADR Mar/April 2017

• PADR subs due May/June 2017 (6 weeks)

• PACR July/Aug 2017

Page 20: Powering sydneys future workshop

Considering all options Nalin Pahalawaththa

Group Manager, Power System Analysis

TransGrid

20

Page 21: Powering sydneys future workshop

Powering Sydney’s Future – Considering all options

The planning process considers:

Reliability

Cost

Environment

21

Page 22: Powering sydneys future workshop

Powering Sydney’s Future – Considering all options

In situ replacement of cables

330 kV cable replacement:

• Cable Outage – up to 2-5 years

• High costs – similar to new cable

development

• Access issues

• 4 x the capacity of 132 kV cable

132 kV cable replacement:

• Environmental risk – crossing harbour

• High costs – similar to new cable

development

• Limited improvement to network capability

22

Page 23: Powering sydneys future workshop

Powering Sydney’s Future – Considering all options

23

New Cables – 330 kV Vs 132 kV

• Limited Capability enhancement from

132 kV option

load growth

Network Development flexibility

• 132 kV = higher costs ($/MW)

• 132 kV = higher community &

environmental impact

132 kV Option

330 kV Option

Page 24: Powering sydneys future workshop

Powering Sydney’s Future – Considering all options

New cables – 330 kV vs 132 kV

• Limited Capability enhancement from

132 kV option:

o Load growth

o Network development flexibility

• High costs ($/MW)

• Community and environmental impact

24

Page 25: Powering sydneys future workshop

Powering Sydney’s Future – Considering all options

Route selection: Sydney’s East

• 3 out of 6 possible route options were

considered feasible (approx. 26km)

• Environmental impact on national parks

and harbour crossing

• Significant high costs due to the

geography of the area.

• Network limitations: overloading

Sydney’s North to East via 330 kV lines

Sydney

East

Sydney

North

Rookwood

Road

Sydney

West

Sydney

South

Beaconsfield

Haymarket

25

Page 26: Powering sydneys future workshop

Powering Sydney’s Future – Considering all options

Route selection: Sydney’s North

• 4 out of 7 possible route options

were considered feasible (tunnels,

overhead lines, combinations)

• Environmental impact on national

parks and harbour crossing

• Significant costs due to the

geography of the area and the

length of the route

Sydney

East

Sydney

North

Rookwood

Road

Sydney

West

Sydney

South

Beaconsfield

Haymarket

26

Page 27: Powering sydneys future workshop

Powering Sydney’s Future – Considering all options

Route selection: Sydney’s South

• 3 out of 9 possible route options were

considered feasible (tunnels, overhead

lines, combinations)

• Diversity issue:

o Concentrate of 330 kV supply to

CBD from one location

o Part of route is along existing 330kV

cables

• Environmental and community impact on

Georges River National Park and high

density residential area

• Similar costs to Rookwood Road option

Sydney

East

Sydney

North

Rookwood

Road

Sydney

West

Sydney

South

Beaconsfield

Haymarket

27

Page 28: Powering sydneys future workshop

Powering Sydney’s Future – Considering all options

Route selection: Rookwood Road

• 13 possible route options were considered

feasible (tunnels, overhead lines,

combinations)

• Provided diversity to supply CBD area

• Utilised existing 330 kV supply capacity from

Sydney’s West to Rookwood Road

• Low costs compared with the Sydney North

and East options

• Relatively low community and environmental

impact

Sydney

East

Sydney

North

Rookwood

Road

Sydney

West

Sydney

South

Beaconsfield

Haymarket

28

Page 29: Powering sydneys future workshop

Powering Sydney’s Future – Considering all options

Rookwood

Road

Options

Options 2 x 330kV

cables in

stages

2 x 330kV

cables at

once

Remediate

Cable 41

Retire

Cable 41

Operate

Cable 41

at 132kV

Decommission

Ausgrid cables

– 2 stages

Decommission

Ausgrid cables

– 1 stage

1

2

3

4

5

6

29

Page 30: Powering sydneys future workshop

Powering Sydney’s Future – Considering all options

Storage Curtailment of load Embedded

generation

Alternatives to network augmentation which address a potential shortage in electricity supply

Network Solution

Non-Network Solutions

30

Page 31: Powering sydneys future workshop

The possiblity of non-network

David Bones

Service Group Manager – Power Strategy and Economics

GHD

31

Page 32: Powering sydneys future workshop

Powering Sydney’s Future – The possibility of non-network

Non-network comprises of:

• Generation

• Storage

• Demand Management

Non-network components are

1. Unserved energy at risk

2. Project deferral

3. Part of the integrated project solution

32

Page 33: Powering sydneys future workshop

Powering Sydney’s Future – The possibility of non-network

Inner Sydney’s daily

demand profile

33

Page 34: Powering sydneys future workshop

Powering Sydney’s Future – The possibility of non-network

Expected

unserved energy

in 2020-23

without Powering

Sydney’s Future

project

34

Page 35: Powering sydneys future workshop

Powering Sydney’s Future – The possibility of non-network

Examples of

non-network

options

35

Page 36: Powering sydneys future workshop

Powering Sydney’s Future – The possibility of non-network

36

Non-network case study – 60MW, 12 Hr, 8 week options

Existing Standby Generation Central Battery Central Power Station

Page 37: Powering sydneys future workshop

Powering Sydney’s Future Workshop

37